Warm House Haworth Estates: Waverley Design Development & Building for Life SKPPRA Warm House Public meeting No.2 23rd February 2012

Warmhouse 02

  • Upload
    skppra

  • View
    278

  • Download
    1

Embed Size (px)

Citation preview

Warm House

Haworth Estates: Waverley Design Development & Building for Life

SKPPRA – Warm HousePublic meeting No.2

23rd February 2012

Warm House

Agenda

Energy Saving in The Home

Elliot Bushay – Energy Solutions (North West London)

Energy Performance Certificates

Sagar Patal - RS Designs Ltd.

The SKPPRA Warm House Project

Michael Rushe – ICE Architects Ltd.

Pawel Ptak - Renderline Ltd.

Questions & Draw for Demonstration House

Warm House

Approved Funding (LEAF)DECC (Department of Energy & Climate Change)assess energy consumption/needs in their area

Demonstration projects for the Green Deal.

ICE Architects bid on behalf of SKPPRA – early December 2011

Grant Awarded – 19th January 2012Work to be complete – 24th March 2012

Warm House

Project TeamRenderline - (Montpelier Rise) - contractors

ICE Architects - (Carlton Avenue East) - architectsRS Designs (Carlton Avenue East) - EPC Assessors

Energy Solutions (North West London) - energy adviceBerrymans Lace Mawer LLP - legal advisors

Warm House

1930s 3 Bed Semi-detached House

Warm House

1930s 3 Bed Semi-detached House

Warm House

External Insulation

Warm House

External Insulation

Warm House

External Insulation

Warm House

External Insulation

Warm House

External Insulation

Warm House

External Insulation

Warm House

Terraced

Warm House

Extensions

Warm House

Extensions

Warm House

Rear Single Storey Extension (3m)

Warm House

Rear Single Storey Extension (3m)

Warm House

Rear & Side Single Storey Extension

Warm House

Rear & Side Single Storey Extension

Warm House

Rear Single & Side Two Storey Extension

Warm House

Loft Conversion

Warm House

Loft Conversion

Warm House

External Appearance

Warm House

External Appearance

Warm House

External Appearance

Warm House

External Appearance

3%

Warm House

Gas Costs £/annum

Warm House

Gas Costs £/annum & kWh/annum

Warm House

Gas Costs £/annum & kWh/annum

Warm House

Gas Costs £/annum & kWh/annum

Warm House

Gas Costs £/annum & kWh/annum

Warm House

ProgrammeDraw House - at end of meeting

24-25th February 2012 - notification & inspection of house

-- meeting with residents-- issue of legal documents

-- agreement to proceed by 27th February 2012

- No agreement by 27th - another house will be selected.

Warm House

LegalsAccess for the workAccess for demonstration from streetA sign in the garden referring to the projectUse of house in publicityAny contribution requiredLegal liabilityThe building contractPlanning and Building RegulationsObstructions

Warm House

ProgrammeLegal agreements by 1st March 2012

Start on site 2nd March 2012Completion - 23rd March 2012

Utility bills to be provided until March 2013