15
Ref: NR/SP/OHS/00102 Issue: 03 Date: June 2005 Page 1 of 15 Network Rail Work Activity Risk Assessment Work Activity Assessed: Generic Track Risks Ref. No. NR/MTC/WARA/TRK/000 Function: Maintenance Discipline or Department: Track (inc Off Track) Location/site of work activity: Sites of Work in all Maintenance Areas Date Assessment carried out: 22/11/07 Groups at risk: Track staff Previous assessments superseded: All generic risk assessments contained in NRSOP’s Name: Positions: Persons carrying out assessment: J McCormick AMWSAEA Reviewed and Approved by: Robert Staughton Ron Cameron Safety Procedures Engineer Head of Maintenance Workforce Safety Date of acceptance and publication: 31/01/2008 Planned review date: 31/01/2010

WARATK000-Generic Track Risks

Embed Size (px)

DESCRIPTION

Generic Track Risks

Citation preview

  • Ref: NR/SP/OHS/00102 Issue: 03

    Date: June 2005

    Page 1 of 15

    Network Rail Work Activity Risk Assessment

    Work Activity Assessed:

    Generic Track Risks

    Ref. No. NR/MTC/WARA/TRK/000

    Function:

    Maintenance Discipline or Department:

    Track (inc Off Track)

    Location/site of work activity:

    Sites of Work in all Maintenance Areas Date Assessment carried out:

    22/11/07

    Groups at risk:

    Track staff Previous assessments superseded:

    All generic risk assessments contained in NRSOPs

    Name: Positions: Persons carrying out assessment:

    J McCormick AMWSAEA

    Reviewed and Approved by:

    Robert Staughton Ron Cameron

    Safety Procedures Engineer Head of Maintenance Workforce Safety

    Date of acceptance and publication:

    31/01/2008 Planned review date:

    31/01/2010

  • Ref: NR/SP/OHS/00102 Issue: 03

    Date: June 2005

    Page 2 of 15

    Network Rail Work Activity Risk Assessment

    Ref. No. TK000 1 2 3 4 5 6 7 8 9 10 11 12

    Component of Activity

    Hazards Consequences Existing Controls S L R Additional Controls

    S L R Specialised Risk Assessment

    Trains

    Fatality Major Injury

    See GH1, GA1 and GA2 Rule Book Modules G1,

    G2, T3, T2, T4, OTP

    5-

    1

    6

    - - -

    All tasks Fatality Major Injury

    Suitable supervision arrangements must be put in place for all activities

    A COSS must be appointed when on or near the line

    All staff must receive and understand a COSS brief prior to start of work

    4-

    1

    - 5

    - - -

    Electrocution AC

    Fatality Major Injury

    See GH6 Make sure you and any tools

    or equipment you are carrying/using, are at least 2.75m from the OLE unless an isolation has been arranged and a form C has been issued and available on site with the nominated competent COSS

    5

    1

    5

  • Ref: NR/SP/OHS/00102 Issue: 03

    Date: June 2005

    Page 3 of 15

    1 2 3 4 5 6 7 8 9 10 11 12 Component of Activity

    Hazards Consequences Existing Controls S L R Additional Controls

    S L R Specialised Risk Assessment

    Electrocution DC

    Fatality Major Injury

    See GA 20 A,B,C,D,E for DC Lines

    insulated tools must be used shields must be used where required See GA 20A-E

    5

    1

    6

    Fuelling of Plant

    Injury See GA64 Ensure equipment has

    been switched off and allowed to cool prior to re-fuelling

    Hand/eye protection to be worn

    Refuel a minimum of 10m from naked flames/hot work

    Funnel/spout to be used to aid refuelling

    AFFF Fire extinguishers to be available on site

    3

    1

    4

    Working in Darkness

    See GH3 Access to and from site,

    head/hand torches to be provided as a minimum

    Suitable site lighting to be provided within the work area

    2

    3

    5

  • Ref: NR/SP/OHS/00102 Issue: 03

    Date: June 2005

    Page 4 of 15

    1 2 3 4 5 6 7 8 9 10 11 12 Component of Activity

    Hazards Consequences Existing Controls S L R Additional Controls

    S L R Specialised Risk Assessment

    Use of Hand tools

    Minor injury See GA 27 All tools to be checked and

    inspected to ensure good condition prior to use

    All staff to be trained in the use of hand tools

    Ensure the tool being used is correct for the task

    3

    1

    4

    Lack of Welfare facilities

    Welfare facilities to be considered in the work planning stage and provided as and when required

    2

    2

    4

    Dust, Silicates,Oil,Effluence,Bio hazards including sharps

    See GH 7 and GH 8 COSHH Assessments and

    controls Wash hands before eating,

    drinking or smoking Cover all cuts and broken

    skin with waterproof plasters

    1

    3

    4

  • Ref: NR/SP/OHS/00102 Issue: 03

    Date: June 2005

    Page 5 of 15

    1 2 3 4 5 6 7 8 9 10 11 12 Component of Activity

    Hazards Consequences Existing Controls S L R Additional Controls

    S L R Specialised Risk Assessment

    Use of OTP

    Fatality Major Injury

    See MP 01 And Refer to relevant OTP

    Risk Control Sheet Competent operator and

    Machine Controller to be appointed

    Ensure the necessary pre-use checks have been carried out

    All machine movements must be authorised by the Machine Controller (for traveling see OTP07and OTP08)

    Prior to any movement of a OTP the horn must be sounded

    All lifts must be planned, controlled, a Crane Controller must be appointed

    1

    4

    5

  • Ref: NR/SP/OHS/00102 Issue: 03

    Date: June 2005

    Page 6 of 15

    1 2 3 4 5 6 7 8 9 10 11 12 Component of Activity

    Hazards Consequences Existing Controls S L R Additional Controls

    S L R Specialised Risk Assessment

    Use of Hand trolley

    to GA17 Ensure trolley is within its

    service date Ensure the necessary pre-

    use checks and brake test has been carried out

    Not to be used on gradients greater than 1:50

    Operated by competent persons and must have at least two people with it when being moved with one in control of the brake

    Hand trolleys must not be overloaded, load secured and not foul of open lines

    3

    1

    4

    Hand Arm Vibration from powered plant

    Ensure plant is within its service date

    Competent operator Rotation of staff / regular

    breaks from all vibratory equipment

    Control time on machine Planned Preventive

    Maintenance Hands to be kept warm to

    increase blood flow to extremities

    3

    1

    4

  • Ref: NR/SP/OHS/00102 Issue: 03

    Date: June 2005

    Page 7 of 15

    1 2 3 4 5 6 7 8 9 10 11 12 Component of Activity

    Hazards Consequences Existing Controls S L R Additional Controls

    S L R Specialised Risk Assessment

    Manual Handling

    See GH4 Lifting operations to be

    mechanized wherever possible

    All staff to be trained in manual handling techniques

    A person must be appointed to control the movement and must brief all staff prior to the movement on how the load is to be moved and where it is to be moved to

    Gloves to be worn

    - 1

    3

    4

    Slips trips and falls

    See GH2 Site to be regularly checked

    for slip, trips and falls hazards

    Site to be kept tidy Protective footwear to be

    worn and in good condition Consider underfoot

    conditions when on or about the infrastructure at all times and in all weather conditions

    1

    3

    4

  • Ref: NR/SP/OHS/00102 Issue: 03

    Date: June 2005

    Page 8 of 15

    1 2 3 4 5 6 7 8 9 10 11 12 Component of Activity

    Hazards Consequences Existing Controls S L R Additional Controls

    S L R Specialised Risk Assessment

    Load/unload vehicles

    See GA36 Sufficient staff required to

    carry out the lift Load to be evenly

    distributed and secured The load must not exceed

    the SWL of the vehicle Staff must access and

    egress the vehicle in a controlled manner

    Competent person to operate vehicle lifting devices

    Load / unload the vehicle in a methodical manner avoiding trapping hazards (body parts and clothing)

    Ensure firm foot position when in loading / unloading area

    Ensure vehicle is parked in a suitable position for the lifting operations and the hand brake is applied.

    3

    1

    4

  • Ref: NR/SP/OHS/00102 Issue: 03

    Date: June 2005

    Page 9 of 15

    1 2 3 4 5 6 7 8 9 10 11 12 Component of Activity

    Hazards Consequences Existing Controls S L R Additional Controls

    S L R Specialised Risk Assessment

    Buried Services

    Fatality Major Injury

    See SP05 All ground disturbance to

    be planned Area to be Cat Scanned by

    a competent person prior to the work and hazards identified and marked

    Permit to dig to be issued and available on site

    Safe digging practice to be adopted

    3

    1

    4

    Noise Ear defenders to be worn within the hearing protection zone

    Plant to be maintained and inside maintenance date

    Where possible site noisy equipment away from worksite

    Warning Protection (Touch Lookout )

    Use Audible Warning Devices where fitted to plant

    3

    1

    4

    Communication and form filling s

    All form filling and communication must be carried out in a position of safety

    2

    1

    3

  • Ref: NR/SP/OHS/00102 Issue: 03

    Date: June 2005

    Page 10 of 15

    1 2 3 4 5 6 7 8 9 10 11 12 Component of Activity

    Hazards Consequences Existing Controls S L R Additional Controls

    S L R Specialised Risk Assessment

    Environment All waste to be removed fromsite in a controlled manner

    All spillages / leaks of fuels / contaminants to be cleaned up using spill kits

    Control to be contacted if water courses / SSSI Sites are at risk or a large spillage of contaminants occurs

    General public to be advised of noise and light nuisance in advance of work being undertaken (e.g.letter drop)

    2-

    1-

    3-

    - - -

    Lone Workers

    See GA 10 Ensure means of

    communication is available at all times

    -2

    1

    - 3

    - - -

    Adverse Weather

    See GH05 -3

    1

    -4

    - - -

    Sun

    Protect skin from suns rays, lightweight clothing, sun blocker

    Carry water to prevent dehydration

    3 1 4

  • Ref: NR/SP/OHS/00102 Issue: 03

    Date: June 2005

    Page 11 of 15

    1 2 3 4 5 6 7 8 9 10 11 12 Component of Activity

    Hazards Consequences Existing Controls S L R Additional Controls

    S L R Specialised Risk Assessment

    Visibility

    Do not start work if visibility is poor prior to leaving depot (site could be a long way from depot and it may be necessary to have other protection arrangements for incidents)

    Fog/Mist leave worksite in a safe condition, go to a position of safety

    3 1 4

    Cold

    Warm clothing underneath High Visibility PPE

    Drink warm/hot drinks on breaks whenever possible

    Slips See GH2 and 13 above

    3 1 4

    Wet

    Wet weather High Vis clothing

    Suitable protective footwear Slips See GH 2 and 13

    above

    3 1 4

  • Ref: NR/SP/OHS/00102 Issue: 03

    Date: June 2005

    Page 12 of 15

    Network Rail Work Activity Risk Assessment

    Ref. No. TK000 Additional local condition factors that should be considered

  • Ref: NR/SP/OHS/00102 Issue: 03

    Date: June 2005

    Page 13 of 15

    Manual Handling Operations Risk Assessment Filter

    Work Activity Risk Assessment Reference No. ..

    Activity Assessed Assessed by .. Component of Activity

    WARA risk classification

    1 2 3 4

    Y/N

    Further controls identified (carry back to WARA)

    Specialist MHO risk assessment required Y/N

    Lifting and Lowering Weight outside guidelines according to body zone?

    Y/N Y/N

    Repetitive lifting/lowering -more than twice per minute?

    Y/N Y/N

    Twisting motion - more than 45 degrees?

    Y/N Y/N

    Carrying

    Load supported some distance away from the body?

    Y/N Y/N

    Load carried more than 10m distance?

    Y/N Y/N

    Hands below knuckle height or above elbow height when carrying/lifting.?

    Y/N Y/N

    Pushing and Pulling Excessive force required to move load?

    Y/N Y/N

    Excessive force required to keep load in motion?

    Y/N Y/N

    Refer to Appendix D of NR/SP/OHS/00102 for guidance on completing this form

  • Ref: NR/SP/OHS/00102 Issue: 03

    Date: June 2005

    Page 14 of 15

    Noise Risk Assessment Filter

    Work Activity Risk Assessment Reference No. ..

    Activity Assessed . Assessed by ..

    1 Component(s) of Activity

    2 WARA risk classification

    Manufacturers/Measurement Data (where available)

    3 Name of Tool/Equipment/Noise source

    4 Suppliers/Manufacturers/ Measurement Information available Y/N

    Y/N Y/N Y/N Y/N

    5 Continuous Noise Level dBA.

    6 Impact Noise Level dB(C) (if applicable)

    Listening Checks (where manufacturers/measurement data is not available)

    7 Difficulty being heard at 2m (85dB(A))

    8 Difficulty being heard at 1m (90dB(A))

    Estimation of Noise Exposure

    9 Estimated usage time (hrs.)

    10 Noise exposure points (from Table 1)

    11 Total noise exposure points

    12 Estimated Noise Exposure (dB) (from Table 2)

    Refer to Appendix D of NR/SP/OHS/00102 for guidance on completing this form

  • Ref: NR/SP/OHS/00102 Issue: 03

    Date: June 2005

    Page 15 of 15

    Hand-Arm Vibration Risk Assessment Filter

    Work Activity Risk Assessment Reference No. ..

    Activity Assessed . Assessed by ..

    1 Component(s) of Activity

    2 WARA risk classification

    Manufacturers/Measurement Data (where available)

    3 Name of Tool/Equipment/Vibration source

    4 Suppliers/Manufacturers/ Field Measurement Information available Y/N

    Y/N Y/N Y/N Y/N

    5 Vibration Level (m/s2) from available information

    6 Source of information

    Estimation of Hand-Arm Vibration Exposure

    7 Estimated usage time (hrs.)

    8 HAV exposure points (from Table 1)

    9 Total HAV exposure points

    10 Estimated HAV Exposure (m/s2 A(8)) (from Table 2)

    Refer to Appendix D of NR/SP/OHS/00102 for guidance on completing this form