Upload
andre-mendes
View
212
Download
0
Embed Size (px)
DESCRIPTION
Generic Track Risks
Citation preview
Ref: NR/SP/OHS/00102 Issue: 03
Date: June 2005
Page 1 of 15
Network Rail Work Activity Risk Assessment
Work Activity Assessed:
Generic Track Risks
Ref. No. NR/MTC/WARA/TRK/000
Function:
Maintenance Discipline or Department:
Track (inc Off Track)
Location/site of work activity:
Sites of Work in all Maintenance Areas Date Assessment carried out:
22/11/07
Groups at risk:
Track staff Previous assessments superseded:
All generic risk assessments contained in NRSOPs
Name: Positions: Persons carrying out assessment:
J McCormick AMWSAEA
Reviewed and Approved by:
Robert Staughton Ron Cameron
Safety Procedures Engineer Head of Maintenance Workforce Safety
Date of acceptance and publication:
31/01/2008 Planned review date:
31/01/2010
Ref: NR/SP/OHS/00102 Issue: 03
Date: June 2005
Page 2 of 15
Network Rail Work Activity Risk Assessment
Ref. No. TK000 1 2 3 4 5 6 7 8 9 10 11 12
Component of Activity
Hazards Consequences Existing Controls S L R Additional Controls
S L R Specialised Risk Assessment
Trains
Fatality Major Injury
See GH1, GA1 and GA2 Rule Book Modules G1,
G2, T3, T2, T4, OTP
5-
1
6
- - -
All tasks Fatality Major Injury
Suitable supervision arrangements must be put in place for all activities
A COSS must be appointed when on or near the line
All staff must receive and understand a COSS brief prior to start of work
4-
1
- 5
- - -
Electrocution AC
Fatality Major Injury
See GH6 Make sure you and any tools
or equipment you are carrying/using, are at least 2.75m from the OLE unless an isolation has been arranged and a form C has been issued and available on site with the nominated competent COSS
5
1
5
Ref: NR/SP/OHS/00102 Issue: 03
Date: June 2005
Page 3 of 15
1 2 3 4 5 6 7 8 9 10 11 12 Component of Activity
Hazards Consequences Existing Controls S L R Additional Controls
S L R Specialised Risk Assessment
Electrocution DC
Fatality Major Injury
See GA 20 A,B,C,D,E for DC Lines
insulated tools must be used shields must be used where required See GA 20A-E
5
1
6
Fuelling of Plant
Injury See GA64 Ensure equipment has
been switched off and allowed to cool prior to re-fuelling
Hand/eye protection to be worn
Refuel a minimum of 10m from naked flames/hot work
Funnel/spout to be used to aid refuelling
AFFF Fire extinguishers to be available on site
3
1
4
Working in Darkness
See GH3 Access to and from site,
head/hand torches to be provided as a minimum
Suitable site lighting to be provided within the work area
2
3
5
Ref: NR/SP/OHS/00102 Issue: 03
Date: June 2005
Page 4 of 15
1 2 3 4 5 6 7 8 9 10 11 12 Component of Activity
Hazards Consequences Existing Controls S L R Additional Controls
S L R Specialised Risk Assessment
Use of Hand tools
Minor injury See GA 27 All tools to be checked and
inspected to ensure good condition prior to use
All staff to be trained in the use of hand tools
Ensure the tool being used is correct for the task
3
1
4
Lack of Welfare facilities
Welfare facilities to be considered in the work planning stage and provided as and when required
2
2
4
Dust, Silicates,Oil,Effluence,Bio hazards including sharps
See GH 7 and GH 8 COSHH Assessments and
controls Wash hands before eating,
drinking or smoking Cover all cuts and broken
skin with waterproof plasters
1
3
4
Ref: NR/SP/OHS/00102 Issue: 03
Date: June 2005
Page 5 of 15
1 2 3 4 5 6 7 8 9 10 11 12 Component of Activity
Hazards Consequences Existing Controls S L R Additional Controls
S L R Specialised Risk Assessment
Use of OTP
Fatality Major Injury
See MP 01 And Refer to relevant OTP
Risk Control Sheet Competent operator and
Machine Controller to be appointed
Ensure the necessary pre-use checks have been carried out
All machine movements must be authorised by the Machine Controller (for traveling see OTP07and OTP08)
Prior to any movement of a OTP the horn must be sounded
All lifts must be planned, controlled, a Crane Controller must be appointed
1
4
5
Ref: NR/SP/OHS/00102 Issue: 03
Date: June 2005
Page 6 of 15
1 2 3 4 5 6 7 8 9 10 11 12 Component of Activity
Hazards Consequences Existing Controls S L R Additional Controls
S L R Specialised Risk Assessment
Use of Hand trolley
to GA17 Ensure trolley is within its
service date Ensure the necessary pre-
use checks and brake test has been carried out
Not to be used on gradients greater than 1:50
Operated by competent persons and must have at least two people with it when being moved with one in control of the brake
Hand trolleys must not be overloaded, load secured and not foul of open lines
3
1
4
Hand Arm Vibration from powered plant
Ensure plant is within its service date
Competent operator Rotation of staff / regular
breaks from all vibratory equipment
Control time on machine Planned Preventive
Maintenance Hands to be kept warm to
increase blood flow to extremities
3
1
4
Ref: NR/SP/OHS/00102 Issue: 03
Date: June 2005
Page 7 of 15
1 2 3 4 5 6 7 8 9 10 11 12 Component of Activity
Hazards Consequences Existing Controls S L R Additional Controls
S L R Specialised Risk Assessment
Manual Handling
See GH4 Lifting operations to be
mechanized wherever possible
All staff to be trained in manual handling techniques
A person must be appointed to control the movement and must brief all staff prior to the movement on how the load is to be moved and where it is to be moved to
Gloves to be worn
- 1
3
4
Slips trips and falls
See GH2 Site to be regularly checked
for slip, trips and falls hazards
Site to be kept tidy Protective footwear to be
worn and in good condition Consider underfoot
conditions when on or about the infrastructure at all times and in all weather conditions
1
3
4
Ref: NR/SP/OHS/00102 Issue: 03
Date: June 2005
Page 8 of 15
1 2 3 4 5 6 7 8 9 10 11 12 Component of Activity
Hazards Consequences Existing Controls S L R Additional Controls
S L R Specialised Risk Assessment
Load/unload vehicles
See GA36 Sufficient staff required to
carry out the lift Load to be evenly
distributed and secured The load must not exceed
the SWL of the vehicle Staff must access and
egress the vehicle in a controlled manner
Competent person to operate vehicle lifting devices
Load / unload the vehicle in a methodical manner avoiding trapping hazards (body parts and clothing)
Ensure firm foot position when in loading / unloading area
Ensure vehicle is parked in a suitable position for the lifting operations and the hand brake is applied.
3
1
4
Ref: NR/SP/OHS/00102 Issue: 03
Date: June 2005
Page 9 of 15
1 2 3 4 5 6 7 8 9 10 11 12 Component of Activity
Hazards Consequences Existing Controls S L R Additional Controls
S L R Specialised Risk Assessment
Buried Services
Fatality Major Injury
See SP05 All ground disturbance to
be planned Area to be Cat Scanned by
a competent person prior to the work and hazards identified and marked
Permit to dig to be issued and available on site
Safe digging practice to be adopted
3
1
4
Noise Ear defenders to be worn within the hearing protection zone
Plant to be maintained and inside maintenance date
Where possible site noisy equipment away from worksite
Warning Protection (Touch Lookout )
Use Audible Warning Devices where fitted to plant
3
1
4
Communication and form filling s
All form filling and communication must be carried out in a position of safety
2
1
3
Ref: NR/SP/OHS/00102 Issue: 03
Date: June 2005
Page 10 of 15
1 2 3 4 5 6 7 8 9 10 11 12 Component of Activity
Hazards Consequences Existing Controls S L R Additional Controls
S L R Specialised Risk Assessment
Environment All waste to be removed fromsite in a controlled manner
All spillages / leaks of fuels / contaminants to be cleaned up using spill kits
Control to be contacted if water courses / SSSI Sites are at risk or a large spillage of contaminants occurs
General public to be advised of noise and light nuisance in advance of work being undertaken (e.g.letter drop)
2-
1-
3-
- - -
Lone Workers
See GA 10 Ensure means of
communication is available at all times
-2
1
- 3
- - -
Adverse Weather
See GH05 -3
1
-4
- - -
Sun
Protect skin from suns rays, lightweight clothing, sun blocker
Carry water to prevent dehydration
3 1 4
Ref: NR/SP/OHS/00102 Issue: 03
Date: June 2005
Page 11 of 15
1 2 3 4 5 6 7 8 9 10 11 12 Component of Activity
Hazards Consequences Existing Controls S L R Additional Controls
S L R Specialised Risk Assessment
Visibility
Do not start work if visibility is poor prior to leaving depot (site could be a long way from depot and it may be necessary to have other protection arrangements for incidents)
Fog/Mist leave worksite in a safe condition, go to a position of safety
3 1 4
Cold
Warm clothing underneath High Visibility PPE
Drink warm/hot drinks on breaks whenever possible
Slips See GH2 and 13 above
3 1 4
Wet
Wet weather High Vis clothing
Suitable protective footwear Slips See GH 2 and 13
above
3 1 4
Ref: NR/SP/OHS/00102 Issue: 03
Date: June 2005
Page 12 of 15
Network Rail Work Activity Risk Assessment
Ref. No. TK000 Additional local condition factors that should be considered
Ref: NR/SP/OHS/00102 Issue: 03
Date: June 2005
Page 13 of 15
Manual Handling Operations Risk Assessment Filter
Work Activity Risk Assessment Reference No. ..
Activity Assessed Assessed by .. Component of Activity
WARA risk classification
1 2 3 4
Y/N
Further controls identified (carry back to WARA)
Specialist MHO risk assessment required Y/N
Lifting and Lowering Weight outside guidelines according to body zone?
Y/N Y/N
Repetitive lifting/lowering -more than twice per minute?
Y/N Y/N
Twisting motion - more than 45 degrees?
Y/N Y/N
Carrying
Load supported some distance away from the body?
Y/N Y/N
Load carried more than 10m distance?
Y/N Y/N
Hands below knuckle height or above elbow height when carrying/lifting.?
Y/N Y/N
Pushing and Pulling Excessive force required to move load?
Y/N Y/N
Excessive force required to keep load in motion?
Y/N Y/N
Refer to Appendix D of NR/SP/OHS/00102 for guidance on completing this form
Ref: NR/SP/OHS/00102 Issue: 03
Date: June 2005
Page 14 of 15
Noise Risk Assessment Filter
Work Activity Risk Assessment Reference No. ..
Activity Assessed . Assessed by ..
1 Component(s) of Activity
2 WARA risk classification
Manufacturers/Measurement Data (where available)
3 Name of Tool/Equipment/Noise source
4 Suppliers/Manufacturers/ Measurement Information available Y/N
Y/N Y/N Y/N Y/N
5 Continuous Noise Level dBA.
6 Impact Noise Level dB(C) (if applicable)
Listening Checks (where manufacturers/measurement data is not available)
7 Difficulty being heard at 2m (85dB(A))
8 Difficulty being heard at 1m (90dB(A))
Estimation of Noise Exposure
9 Estimated usage time (hrs.)
10 Noise exposure points (from Table 1)
11 Total noise exposure points
12 Estimated Noise Exposure (dB) (from Table 2)
Refer to Appendix D of NR/SP/OHS/00102 for guidance on completing this form
Ref: NR/SP/OHS/00102 Issue: 03
Date: June 2005
Page 15 of 15
Hand-Arm Vibration Risk Assessment Filter
Work Activity Risk Assessment Reference No. ..
Activity Assessed . Assessed by ..
1 Component(s) of Activity
2 WARA risk classification
Manufacturers/Measurement Data (where available)
3 Name of Tool/Equipment/Vibration source
4 Suppliers/Manufacturers/ Field Measurement Information available Y/N
Y/N Y/N Y/N Y/N
5 Vibration Level (m/s2) from available information
6 Source of information
Estimation of Hand-Arm Vibration Exposure
7 Estimated usage time (hrs.)
8 HAV exposure points (from Table 1)
9 Total HAV exposure points
10 Estimated HAV Exposure (m/s2 A(8)) (from Table 2)
Refer to Appendix D of NR/SP/OHS/00102 for guidance on completing this form