Upload
others
View
2
Download
0
Embed Size (px)
Citation preview
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 1
Report Control
Document: Environmental Statement Vol. 1 – Main Text
Project: Forest Green Rovers Football Club Stadium, Stroud
Client: Ecotricity
Job No: 15_149
File storage: Client files\15-112 to 15-189\15-149_Eco Park, Stroud_Ecotricity\7.
Stadium Only Submission\4. ES\Vol 1 Main Text
Document Checking
Primary Author: Daniel Hughes Initialled: DH
Contributor: Initialled:
Reviewer: Initialled:
Revision Status
Issue Date Status Checked for issue
1 06.11.17 Draft DH
2 15.11.17 Final Draft DH
3
4
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 2
FOREWORD
INSPECTION OF THE AMENDED PLANNING APPLICATION,
ENVIRONMENTAL STATEMENT AND
SUPPORTING DOCUMENTS
Copies of the ES documentation are available for viewing at Stroud District Council during their normal
office hours. The ES may also be viewed at Ecotricity's Offices at Unicorn House, 7 Russell St, Stroud,
Gloucestershire, GL5 3AX. Copies of the Non-Technical Summary (NTS) are also freely available from this
address.
Hard copies of the ES may be purchased from the above Ecotricity address at a cost of up to £500 for the
entire documentation (lower charges may apply for specific documents). The complete ES documentation
may also be obtained on a CD free of charge (limited to one per person).
Printed on FSC
paper from
responsible sources
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 3
VOLUME 1 MAIN TEXT – CONTENTS
1 INTRODUCTION 8
2 APPROACH TO EIA 18
3 DESCRIPTION OF THE SITE AND SURROUNDING AREA 31
4 CONSIDERATION OF ALTERNATIVES 34
5 DESCRIPTION OF THE REVISED SCHEME 39
6 PLANNING POLICY CONTEXT 50
7 ARCHAEOLOGY AND CULTURAL HERITAGE 53
8 ECOLOGY AND NATURE CONSERVATION 74
9 FLOOD RISK, HYDROLOGY AND DRAINAGE 123
10 LANDSCAPE AND VISUAL 164
11 SOCIO-ECONOMICS 238
12 TRANSPORT AND ACCESS 256
13 AIR QUALITY AND DUST 292
14 LIGHTING 320
15 NOISE AND VIBRATION 342
16 CLIMATE CHANGE 366
17 MAJOR ACCIDENTS AND DISASTERS 385
18 CUMULATIVE EFFECTS 414
19 SUMMARY OF EFFECTS AND MITIGATION 424
20 GLOSSARY 431
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 4
RS FIGURES (VOLUME 2)
Chapter 1 - Introduction
RS Figure 1.1 Concept Plan
RS Figure 1.2 Local Context Plan
RS Figure 1.3 Site Context Plan
Chapter 4 – Consideration of Alternatives
RS Figure 4.1 Site search area for the Revised Scheme
Chapter 5 – Description of the Revised Scheme
RS Figure 5.1. Building Height Parameter Plan
RS Figure 5.2 Land Use Parameter Plan
RS Figure 5.3 Indicative Green Infrastructure Parameter Plan
RS Figure 5.4 Indicative Construction Compound Locations
RS Figure 5.5 Site Plan and Sections
RS Figure 5.6 Cross section at Grove Lane
Chapter 7 – Archaeology and Cultural Heritage
RS Figure 7.1 Designated Heritage Assets
RS Figure 7.2 Non-designated heritage assets
Chapter 8 – Ecology and Nature Conservation
RS Figure 8.1 Arboricultural Survey
RS Figure 8.2 Trees and Hedgerows Balance
RS Figure 8.3 Ecological Survey Area
RS Figure 8.4 Potential Zones of Influence
RS Figure 8.5 Bat Survey Static Locations 2015-16
RS Figure 8.6 Ecological Designations (Statutory and non-Statutory)
RS Figure 8.7 Protected Species Records Mammals (other than bats), Amphibians and Reptiles
RS Figure 8.8 Confidential Protected Species Records- Badgers - NOT FOR PUBLIC RELEASE
RS Figure 8.9 Protected Species Records Birds Directive Annex I
RS Figure 8.10 Protected Species Records WACA Schedule 1 - Birds
RS Figure 8.11 Protected Species Records BOCC Red List - Birds
RS Figure 8.12 Protected Species Records Bats
RS Figure 8.13 Protected Species Records Bat Roosts
RS Figure 8.14 Baseline Survey
RS Figure 8.15 National Vegetation Classification
RS Figure 8.16 Reptile and Amphibian Survey
RS Figure 8.17 Tree Endoscope Survey for Bats
RS Figure 8.18 Bat Survey Tree Emergence and Dawn Re-entry Locations
RS Figure 8.19 Bat Survey Transect Routes 2015-16
RS Figure 8.20 Visual Summary of Bat Passes 2015-2016
RS Figure 8.21 Static Bat Passes Common Pipistrelle
RS Figure 8.22 Static Bat Passes Soprano Pipistrelle
RS Figure 8.23 Static Bat Passes Myotis
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 5
RS Figure 8.24 Static Bat Passes Noctule
RS Figure 8.25 Static Bat Passes Lesser Horseshoe
RS Figure 8.26 Static Bat Passes Greater Horseshoe
RS Figure 8.27 Breeding Bird Territory Locations 2015
RS Figure 8.28 Breeding Bird Territory Locations 2016
RS Figure 8.29 Confidential Badger Setts - NOT FOR PUBLIC RELEASE
RS Figure 8.30 Confidential Badger Survey 2016 - NOT FOR PUBLIC RELEASE
Chapter 9 – Flood Risk, Hydrology and Drainage
RS Figure 9.1 Watercourses within the vicinity of the Revised Scheme
Chapter 10 – Landscape and Visual
RS Figure 10.1 Site Location, Study Area and Viewpoint Location
RS Figure 10.2 Aerial Photograph and Site Layout with PRoW
RS Figure 10.3 Topography Plan and Cross-Section
RS Figure 10.4 Zone of Theoretical Visibility (ZTV) and Viewpoint Locations
RS Figure 10.5a Landscape Character with ZTV (SDC and National) (Study Area)
RS Figure 10.5b Landscape Character with ZTV (Gloucestershire and Cotswolds AONB) (Study Area)
RS Figure 10.5c Industrial Heritage Conservation Area (IHCA) Character Areas (Study Area)
RS Figure 10.5d Relationship between Landscape Character Types and Areas in Study Area
RS Figure 10.6 Landscape Designations and Public Access / Recreational Resources with ZTV (Study Area)
RS Figure 10.7a Key Landscape and Visual Receptors with ZTV
RS Figure 10.7b Key Landscape and Visual Receptors with ZTV including PRoW and Residential (Detail)
RS Figure 10.8a SALA Assessment of Onsite Landscape Sensitivity with Project Components (SDC)
RS Figure 10.8b Landscape Sensitivity of Stroud District Landscape Character Types (Ecotricity)
RS Figure 10.9a 1st Edition OS Map 1842-1852
RS Figure 10.9b 1st Edition OS Map 1842-1852 with Project Components
RS Figure 10.10a Cotswolds AONB Light Pollution Map
RS Figure 10.10b Night-time Baseline / Existing Light Sources / Lighting Levels (Study Area)
RS Figure 10.10c Night-time Baseline / Existing Light Sources / Lighting Levels (Detailed Area)
RS Figure 10.11a Off Site Constraints and Opportunities Plan
RS Figure 10.11b On Site Constraints and Opportunities Plan
RS Figure 10.11c Landscape Strategy
RS Figure 10.11d Landscape Mitigation
RS Figure 10.12a Cumulative Schemes and Landscape Character (SDC and National)
RS Figure 10.12b Cumulative Schemes and Landscape Character (Gloucestershire and Cotswolds AONB)
RS Figure 10.13 Baseline Photographs (including Night-time)
RS Figure 10.14 Enhanced Wireframe Visualisations
RS Figure 10.15 Additional Residential Visual Amenity Assessment Visualisations
Chapter 11 – Socio-Economics
RS Figure 11.1 Stroud District Context Plan
RS Figure 11.2 Index of Multiple Deprivation Plan
Chapter 12 – Transport and Access
RS Figure 12.1 Two-Way Link Flows Saturday Matchday Arrival Period (14:00 - 15:00)
RS Figure 12.2 Two-Way Link Flows Saturday Matchday Departure Period (17:00 - 18:00)
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 6
RS Figure 12.3 Two-Way Link Flows Weekday Matchday Arrival Period (18:00 - 19:00)
RS Figure 12.4 A419 Junctions Assessed for Capacity
RS Figure 12.5 Percentage difference between Two-Way Link Flows Saturday Matchday
RS Figure 12.6 Percentage difference between Two-Way Link Flows Weekday Matchday
Chapter 13 – Air Quality and Dust
RS Figure 13.1 Air Roads and Receptors
RS Figure 13.2 Air Construction Activities
RS Figure 13.3 Air Trackout Activities
RS Figure 13.4 Air N02 Concentrations
RS Figure 13.5 Air PM10 Concentrations
RS Figure 13.6 Air PM25 Concentrations
Chapter 14 - Lighting
RS Figure 14.1 Baseline
RS Figure 14.2 Provisional Task Area
RS Figure 14.3 Lighting with Mitigation
RS Figure 14.4 Road Lighting
RS Figure 14.5 Entire Site and Road Lighting
RS Figure 14.6 Worst Case Light Spill
RS Figure 14.7 Worst Case Light Spill with Enhancement
RS Figure 14.8 Intrusive Lighting on Dwellings
RS Figure 14.9 Intrusive Lighting on Dwellings with Enhancements
Chapter 15 – Noise and Vibration
RS Figure 15.1 Survey Locations
RS Figure 15.2 Stadium LAeq30secs First Floor
RS Figure 15.3 Stadium Lmax First Floor
RS Figure 15.4 Training Pitches LAeq2h First Floor
RS Figure 15.5 Training Pitches Lmax First Floor
RS Figure 15.6 Car Park LAeq30min First Floor
RS Figure 15.7 Traffic Noise 2017 - Baseline
RS Figure 15.8 Traffic Noise 2036 - Difference between with and without development scenario
Chapter 18 – Cumulative Effects
RS Figure 18.1 Cumulative Schemes
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 7
RS APPENDICES (VOLUME 3)
RS Appendix 1.1 Competent Expert CVs
RS Appendix 1.2 Scoping Opinion
RS Appendix 1.3 Scoping Report
RS Appendix 2.1 Schedule 4 of 2017 EIA Regulations
RS Appendix 6.1 Relevant Planning Policy
RS Appendix 6.2 Draft Planning Conditions
RS Appendix 7.1 Heritage Assessment
RS Appendix 7.2 Geophysics Report
RS Appendix 7.3 Evaluation
RS Appendix 7.4 Written Scheme of Investigation for Evaluation
RS Appendix 7.5 Consultation
RS Appendix 8.1 Baseline Survey
RS Appendix 8 2 Fauna Surveys
RS Appendix 8.3 Arboricultural Survey
RS Appendix 8.4 Confidential Badger Report - NOT FOR PUBLIC RELEASE
RS Appendix 8.5 Green Infrastructure Plan
RS Appendix 8.6 Principles of Environmental Enhancements
RS Appendix 8.7 Consultation responses
RS Appendix 8.8 Further Consultation J13_M5 Eco Park EPR
RS Appendix 8.9 Planning Policy and Guidance
RS Appendix 9.1 Flood Risk Assessment
RS Appendix 9.2 Water Framework Directive Watercourses
RS Appendix 9.3 Assessment of Non-Significant Effects
RS Appendix 10.1 Landscape and Visual Impact Assessment Methodology
RS Appendix 10.2 Baseline Assessment
RS Appendix 10.3 Landscape Assessment Schedules
RS Appendix 10.4 Visual assessment schedules
RS Appendix 10.5 Cumulative Landscape and Visual assessment Schedules
RS Appendix 10.6 Cotswolds AONB Position Statements
RS Appendix 10.7 Landscape Strategy
RS Appendix 10.8 Non-Significant Landscape and Visual Effects
RS Appendix 10.9 Planning Policy
RS Appendix 10.10 Bareground ZTV out to 25km to include Wye Valley AONB
RS Appendix 12.1 Transport Assessment
RS Appendix 12.2 S-Paramics Traffic Model – Forecasting Report
RS Appendix 12.3 Outline Travel Plan
RS Appendix 13.1 Detailed Air Quality Assessment Report
RS Appendix 14.1 Calibration Certificate
RS Appendix 14.2 Schedule of Luminaries
RS Appendix 15.1 Glossary
RS Appendix 15.2 Survey Equipment Details
RS Appendix 15.3 Noise Survey Data
RS Appendix 15.4 Assessment of Non-Significant Effects
RS Appendix 15.5 Assumed Construction Plant
RS Appendix 15.6 Arup Stadium Internal Noise Survey
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 8
1 INTRODUCTION
Introduction
1.1 PWA Planning is retained by Ecotricity Group Limited (‘the Applicant’) to assist with the
preparation of an Environmental Statement (ES) in respect of Land at M5 Junction 13 West of
Stonehouse (‘the Site’), which is within the ownership of the Applicant, for a sports complex that
will provide replacement sports facilities for Forest Green Rovers (FGR) Football Club (FC). The
complex will include a centrepiece stadium and additional training pitches to serve FGR (the
‘Revised Scheme’). The Revised Scheme represents an amendment to planning application ref.
S.16/0043/OUT, which sought permission for an ‘Eco Park’ that included some of the sports
facilities proposed as part of the Revised Scheme, a Green Technology Hub (B1/B2/B8 uses),
additional indoor and outdoor pitches, transport hub and nature conservation area.
1.2 As this is an amendment to the previously submitted and larger Eco Park application, the Redline
Boundary remains unchanged. It includes the area south of the A419 and east of the M5
(formerly the Sports Complex), the area north of the A419 and east of the M5 (formerly the
Green Technology Hub) and the area south of the A419 and west of the M5 (formerly the Nature
Conservation Area). However, only the area north of the A419 and east of the M5 is being
proposed for development (‘Development Footprint’) as part of this Revised Scheme.
1.3 The ES supports an outline planning application with all matters reserved save for access, with
detailed permission being sought for:
• Signalised site access off the A419 (as previously) with full dualling of the A419 from the
M5 Junction 13 to Chipmans Platt.
• A signal controlled pedestrian and cycle crossing of the A419, with a combined footway/
cycleway on the south side of the A419 which will link to National Cycle Route 45 (NCN45)
at Grove Lane.
1.4 Planning permission for internal access is not sought by the application. This will be finalised
through Reserved Matters as determined by the final site layout. However, an indicative internal
access has been illustrated as part of RS Figure 1.1 Indicative Concept Plan.
1.5 This Chapter outlines the background to the Applicant, development and the project team, along
with the legal framework and structure of the ES.
About the Applicant
1.6 Ecotricity was founded in 1995 as the world’s first green energy company and now supplies over
200,000 customers across the UK from a growing fleet of wind and sun parks. More recently
Ecotricity has introduced green gas to Britain and built and run Britain’s first national network of
electric vehicle charge points, the Electric Highway.
About Forest Green Rovers
1.7 FGRFC was founded in 1889. The club is currently the joint-highest ranked football side from
Gloucestershire in the football pyramid. Attendances at FGR games has grown 73% over the last
four seasons. The urgency of the amended Revised Scheme has been increased as a result of
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 9
FGRs promotion into the Football League (League 2), for the first time in its history at the end of
the 2016/ 17 Season, and consequently a further increase in attendances.
About the Development
1.8 The Revised Scheme seeks to provide replacement sports facilities for FGR. In order to meet the
club’s requirements moving forward, a sports complex is proposed which includes an innovative
centrepiece 5,000 capacity stadium designed by world-renowned architects Zaha Hadid, as well
as two additional full-size training pitches and goalkeeping training area to serve FGR. The pitches
will be grass and none will be flood lit. The Revised Scheme is illustrated on RS Figure 1.1
Indicative Concept Plan.
1.9 The training pitches will be used primarily by the FGR first team who currently train at Stanley
Park, Chippenham, which is approximately 24 miles from the New Lawn. The proposals will allow
FGR to centralise its operations and will provide a ‘hub’ of activity.
1.10 The Redline Boundary remains the same as for the previous application submitted. However, all
development will now take place on land north of A419 and east of the M5 within the
Development Footprint only (on land previously allocated for the Green Technology Hub in the
initial submission). No development will take place to the south of the A419, however,
translocation of a hedge will occur on this land (as a result of road widening) as discussed in both
Chapter 5 and Chapter 8.
1.11 The Redline Boundary is approximately 39.5ha. The area that will form the new FGR site is
approximately 18.9ha with the highways improvement works 2.5ha. The Site is approximately
centred on National Grid Reference SO 77965 206584. RS Figure 1.2 shows the Site’s local
context and RS Figure 1.3 shows the Site’s context. The key components of the Revised Scheme
are listed in Table 1.1 (final amounts to be determined at Reserved Matters based on the
parameters set out in RS Figures 5.1, 5.2 and 5.3).
Table 1.1: Key Components of the Revised Scheme
Use Use
Class
Indicative Amount Based on Indicative
Concept Plan (RS Figure 1.3)
Sports Complex 18.9ha
Stadium including ancillary facilities
designed for a capacity of 5,000
D2 To be determined at Reserved Matters. Form
and design of stadium is set out in the Design
and Access Statement.
Two full-sized grass pitches and a goal
practice area
D2 To be determined at Reserved Matters.
Car parking and associated infrastructure N/A To be determined at Reserved Matters.
Parking will be provided for 1,700 vehicles (lit
to previous arrangements, LED luminaries
complete with street optics and including
sensors).
Access Works 2.5ha
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 10
Use Use
Class
Indicative Amount Based on Indicative
Concept Plan (RS Figure 1.3)
Including: signalised site access off the A419;
full dualling of the A419 from M5 J13 to
Chipmans Platt; a signal controlled
pedestrian and cycle crossing of the A419
with a combined footway/ cycleway on the
south side of the A419 (which will link to
National Cycle Route 45 at Grove Lane).
N/A 2.5ha
1.12 FGR are currently based at The New Lawn in Nailsworth, Gloucestershire. The New Lawn was
built in 2006 and has a capacity for a crowd of just under 5,000. The ability of FGR to operate
sustainably is hindered by the location of The New Lawn, which is not readily accessible.
Nailsworth has no railway station (Stroud is the nearest) and is some nine miles from the Stroud
junction of the motorway. There is also a chronic lack of parking and facilities for fans.
1.13 As part of identifying the need for FGR to relocate, an automatic traffic survey took place on
Nympsfield Road, Nailsworth (ST 84159 99977) from 22nd September 2015 to 6th October 2015
whilst the FGR were still playing in the National League. This period was selected for a survey as
it covered two FGR homes matches, Cheltenham on Tuesday 22nd September 2015 and
Gateshead on 26th September 2015, therefore covering a Tuesday and Saturday home match but
also a Tuesday and Saturday where no match took place. On the day of a match there can be a
significant increase in traffic within the residential areas in the vicinity of the existing New Lawn
ground, in some cases, the increase in traffic was over 150%.
1.14 As such, it is clear that as the club progresses, and attendances increase, the number of vehicles
in association with FGR, particularly in relation to the limited transport options in proximity of
The New Lawn, are also anticipated to increase. Therefore, the relocation of FGR to a more
accessible site would be of significant benefit.
1.15 In this respect, the average attendance for FGR during the 2016/ 2017 season prior to attaining
promotion to the League 2 was 1,753. Since attaining promotion, up to 25 November 2017,
attendances at home games at the New Lawn this season have been substantially higher (as
obtained from the FGRFC website) averaging at 2,234 per game (an increase of approximately
27% when compared to the 2016/2017 season) (see Table 12.9)
1.16 Additionally, car parking at The New Lawn is limited – there are just 228 spaces onsite and the
Club regularly uses overflow car parking at Nailsworth Primary School and operates a Park and
Ride from local company Renishaw’s for bigger games. In any event, fans invariably park
in adjacent residential areas, causing significant congestion. This has led to parking restrictions
being implemented on match days. A more accessible location, with more on-site car parking
and better public transport links will enable the club to grow its support to sustainable levels for
the league it plays in now, and for those above.
1.17 The existing FGR stadium (The New Lawn, Nailsworth) was subject to recent planning application
(S.17/0850/OUT), for the demolition of the stadium and re-development to provide the erection
of up to 95 dwellings, up to 0.11 hectares of community uses (which may include D1/D2/A3/B1
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 11
uses), landscaping, open space, associated access, parking and infrastructure. Whilst this
application has been withdrawn, a resubmission is due imminently, and this will be dependent
(and conditioned) upon the replacement sporting facilities being provided as part of the Revised
Scheme.
The Project Team
1.18 PWA Planning has been commissioned by the Applicant to assist with an Environmental Impact
Assessment (EIA) in support of the outline planning application for the Revised Scheme. This has
incorporated technical input from a number of consultants, as outlined in Table 1.2 below. A
copy of the relevant CVs for each competent expert is included within RS Appendix 1.1, and
within each chapter a brief overview of the author’s experience has been provided.
Table 1.2: Project Team
Project Team Contribution
PWA Planning Ltd. and Ecotricity
Group Ltd.
EIA Co-ordination and other project management inputs
Zaha Hadid Ltd. Project Architects and Concept Design
Cotswold Archaeology Ltd. Archaeology and Cultural Heritage
Gavin David CMLI
Chartered Landscape Architect
(lead input) and Ecotricity Group
Ltd.
Landscape and Visual Impact Assessment
Ecotricity Group Ltd. Ecology and Nature Conservation (Biodiversity)
RSK Environment Ltd. Flood Risk, Hydrology and Drainage & Air Quality and Dust
Hopkin Coats Associates Lighting
Hoare Lea LLP. Noise and Vibration
Regeneris Consulting Ltd. Socio-Economics
PFA Consulting Ltd. Transport and Access
Hunter Page Planning Ltd. Planning Statement
Consult QRD Ltd. Sports and Pitches Statement
LUC Ltd. Major Accidents and Disasters & Climate Change
The Environmental Statement (ES)
1.19 This Environmental Statement (ES) on the Revised Scheme is the output of the EIA process which
has been undertaken in accordance with the Town and Country Planning (Environmental Impact
Assessment) Regulations 20111, as amended in 20152 (hereafter referred to as the ‘2011 EIA
Regulations’).
1.20 Since the submission of the original scheme in January 2016, the Town and Country Planning
(Environmental Impact Assessment Regulations 20173 came into force on 16th May 2017
(hereafter referred to as the ‘EIA Regulations 2017’). Regulation 76 of the EIA Regulations 2017
contains provisions for the revocation of the 2011 EIA Regulations and transitional
arrangements. Relevant parts of Regulation 76 are as follows;
1 Town and Country Planning (Environmental Impact Assessment) Regulations 2011 available from
http://www.legislation.gov.uk/uksi/2011/1824/contents/made accessed on 8th December 2015. 2 Town and Country Planning (Environmental Impact Assessment) Amendments 2015 available from
http://www.legislation.gov.uk/uksi/2015/660/contents/made accessed on 8th December 2015. 3 Town and Country Planning (Environmental Impact Assessment) Amendments 2017 available from
http://www.legislation.gov.uk/uksi/2017/571/contents/made accessed on 22nd November 2017.
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 12
’76. – Revocation and transitional provisions
(1) Subjection to paragraphs (2) to (4), the 2011 Regulations are revoked.
(2) Notwithstanding the revocation in paragraph (1), the 2011 Regulations continue to apply
where before the commencement of these Regulations –
(a) An applicant, appellant or qualifying body, as the case may be, has submitted an
environmental statement or requested a scoping opinion; or
(b) In respect of local development orders, the local planning authority has in connection with
that order prepared an environmental statement or a scoping opinion or requested a scoping
direction’
1.21 Accordingly, the 2011 EIA Regulations will continue to govern the determination of extant
planning applications where an Environmental Statement has been submitted before 16th May
2017, or alternatively, where a request for a scoping opinion had been made before that date,
both of which are relevant in this instance.
1.22 Therefore, this EIA has been carried out in accordance with the 2011 EIA Regulations. However,
it should be noted that the 2017 Regulations now contain additional matters which were not
required to be assessed in the 2011 Regulations. As these matters are clearly important, whilst
this ES will be determined in line with the 2011 Regulations, the additional matters which would
have been required under the 2017 Regulations have also been assessed, and the scope of this
work is explained in more detail within Chapter 2.
Legal Framework for the ES
1.23 The EIA Regulations require that prior to consent being granted for certain types of development,
an EIA must be undertaken. The 2011 EIA Regulations set out the type of development which
must always be subject to an EIA (Schedule 1 development) and other developments which may
require an assessment if they are likely to have a significant effect on the environment by virtue
of factors such as its nature, size or location (Schedule 2 developments).
1.24 The Revised Scheme falls under Paragraph 10(b) of Schedule 2 of the EIA Regulations which
relates to Infrastructure Projects. Specifically, Paragraph 10(b) relates to Urban development
projects, including the construction of shopping centres and car parks, sports stadiums, leisure
centres and multiplex cinemas and sets the following thresholds for when a development should
be screened (Table 1.3 below).
Table 1.3: Extract of Paragraph 10(b) of Schedule 2 of the 2011 EIA Regulations (as amended in
2015)
10. Infrastructure projects Threshold
(b) Urban development projects,
including the construction of
shopping centres and car parks,
sports stadiums, leisure centres and
multiplex cinemas;
(i) The development includes more than 1 hectare of urban
development which is not development; or
(ii) the development includes more than 150 dwellings; or
(iii) the overall area of the development exceeds 5 hectares.
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 13
1.25 In this instance, the Revised Scheme exceeds the thresholds set by both parts (i) and (iii). It has
been agreed in consultation with Stroud District Council (SDC) that the Revised Scheme may have
‘significant’ environmental effects, and as such a voluntary ES should be submitted.
1.26 The EIA process identifies likely ‘significant’ environmental effects of proposed developments,
by comparing the existing situation, that which pertains before development is carried out
(baseline) with the situation once the proposals (including any embedded mitigation) are in
place. Likely significant effects during construction are also considered.
1.27 The first stage of the EIA process is to identify the issues which should be addressed in the ES;
this is termed ‘scoping’ and the results are presented as a Scoping Report. This Scoping Report
sets out the views of the Applicant, as to the proposed scope of the environmental issues to be
considered in the EIA and as to the method by which assessment will be undertaken. A Scoping
Report (RS Appendix 1.3) was submitted to accompany a request for a Scoping Opinion in
relation to the original Eco Park scheme from SDC under Regulation 13 of the EIA Regulations in
2015. The Scoping Opinion from SDC identified all issues to be addressed in the ES and is included
in RS Appendix 1.2. As discussed, this new ES accompanies an amendment to the existing
planning application, the Revised Scheme. A further Scoping Opinion has not been sought,
rather, further on-going discussions with statutory and non-statutory consultees from before
and during the planning process have been engaged in order to ensure environmental effects
associated with the Revised Scheme can be fully taken into account within this new ES.
Structure of the ES and Documentation submitted with this Revised Scheme
1.28 The ES is provided in four parts:
• Non-Technical Summary – contains, in non-technical language, a summary of the main
text as a separate self-contained document.
• Volume 1: Main Text – contains a detailed description of the proposal. It evaluates the
existing environmental baseline conditions and identifies and addresses the predicted
environmental effects that could occur as a result of the development. It provides detailed
analysis of the design procedure and how mitigation measures have been embedded into
the design, where possible, to prevent, reduce or offset any environmental effects
identified. Where this is not possible, mitigation has been proposed to ameliorate those
effects which cannot be dealt with through embedded mitigation.
• Volume 2: RS Figures – contains all the illustrative material referred to in the Main Text
(Volume 1). RS refers to the Revised Scheme.
• Volume 3: RS Appendices – contains details of assessment methodologies, assessment
data, technical details and background information.
1.29 Table 1.4 below outlines the structure and content of this document, Volume 1: Main Text.
Table 1.4: Structure of Volume 1: Main Text
Chapter
Number
Chapter Title Content
1 Introduction This Chapter outlines the Project Team, along with the legal
framework and structure of the ES.
2 Approach to the
EIA
This Chapter outlines the approach to the Environmental Impact
Assessment (EIA) in order to meet the information required in an ES
under the EIA Regulations
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 14
Chapter
Number
Chapter Title Content
3 Description of
the Site and its
surround area
This Chapter provides a description of both the Site location, defined
by the Redline Boundary, and the surrounding area.
4 Consideration of
Alternatives
This Chapter outlines the description of the alternatives to the
Revised Scheme in terms of both alternative site locations and
alternative site layouts during the evolution of the Concept Design.
5 Description of
the Revised
Scheme
This Chapter provides a description of the Revised Scheme in
accordance with the amended application for planning permission.
6 Planning and
Environment
Context
This Chapter summarises the land-use planning policy framework
against which the Revised Scheme has been considered.
7 – 17 Technical
Chapters
These Chapters provide a description of the existing baseline
environment, the specific methods used to assess the potential
effects of the Revised Scheme, an assessment of these effects and
mitigation measures proposed to remove/reduce adverse effects for
each receptor on a chapter-by-chapter basis.
18 Cumulative
Effects
This Chapter assesses the potential for significant cumulative
environmental effects associated with the Revised Scheme.
19 Summary of
Effects and
Mitigation
This Chapter provides a summary of effects table for each of the
technical assessment chapters of the ES. A summary of all proposed
mitigation measures is also included.
1.30 Table 1.5 below provides a breakdown of the information required in an ES under the 2011 EIA
Regulations, and where this information can be located in this ES. As discussed, this ES is
submitted in accordance with the 2011 EIA Regulations. Additional matters identified within the
2017 EIA Regulations have also been included within this new ES. These additional matters are
discussed within Chapter 2.
Table 1.5: Location of Required Information within the ES
Schedule
No 1.
Required Information Location within ES
1 Description of the development, including in particular
a) Description of the physical characteristics of the whole
development and land-use requirements during the
construction and operation phases.
Chapter 5 –
Description of the
Revised Scheme
b) Description of the production processes, for instance, the
nature and quantity of materials used.
Chapter 5 –
Description of the
Revised Scheme
c) An estimate, by type and quantity, of expected residues and
emissions (water, air and soil pollution, noise, vibration, light,
heat, radiation etc.) resulting from the operation of the Revised
Scheme.
Technical Chapters 7 -
17
2 An outline of the main alternatives studies by an applicant or
appellant and an indication of the main reasons for this choice,
taking into account the environmental effects.
Chapter 4 –
Consideration of
Alternatives
3 A description of the aspects of the environment likely to be
significantly affected by the development, including in
particular, population, fauna, flora, soil, water, air, climate
factors, material assets including architectural and
archaeological heritage, landscape and the interrelationship
between the above factors.
Technical Chapters 7-
17
4 A description of the likely significant effects of the development
on the environment, which should cover the direct effects and
any indirect, secondary, cumulative, short, medium and long
Technical Chapters 7-
17
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 15
Schedule
No 1.
Required Information Location within ES
term, permanent and temporary, positive and negative effects
of the development, resulting from:
• The existence of the development;
• The use of natural resources; and
• The emissions of pollutants, the creation of nuisances,
and the elimination of waste
5 A description of the measures envisaged to prevent, reduce
and where possible, offset any significant adverse effects on
the environment.
Technical Chapters 7-
17
6 A non-technical summary of the information provided. Non-Technical
Summary
7 An indication of any difficulties (technical deficiencies of lack-
of-know-how) encountered by the applicant in compiling the
required information.
Chapter 2 – Approach
to the EIA and the
relevant Technical
Chapters 7-17.
1.31 The purpose of this ES is to provide a description of the Revised Scheme, to identify and assess
potential significant environmental effects and, where necessary, propose mitigation to offset
those affects. Enhancement measures are also proposed in addition to mitigation where
appropriate.
1.32 The ES is one of the supporting documents submitted to the determining planning authority, SDC
in support of the amended planning application. Volume 3 of the ES contains the Arboricultural
Report (RS Appendix 8.3), Flood Risk Assessment (including Drainage Strategy) (RS Appendix 9.1)
and Transport Assessment (RS Appendix 12.1) which are required as part of SDC’s planning
application local validation requirements. The ES should also be read in conjunction with the
other documents submitted as part of the amended planning application, comprising:
• Design and Access Statement
• Desk Based Utility Report
• Environmental Statement (Volumes 1 to 3) and Non-Technical Summary
• Planning Drawings (Location Plan, Existing Site Plan)
• Planning Statement
• Preliminary Risk Assessment
• Statement of Community Involvement
1.33 It should be noted that the suit of documents submitted as part of this amended planning
application (the Revised Scheme), including the ES and associated documents, replaces all
previous submissions for this Site in their entirety. This includes the original planning application
and ES (submitted January 2016), Further Environmental Information (FEI) 1 (submitted
September 2016), FEI 2 (submitted February 2017), and FEI 3 (submitted August 2017).
Definition of Key Terms
1.34 The following provides the definition of some of the key terms included within the Environmental
Statement. A full glossary is included at the end of this document.
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 16
Table 1.6: Definition of Key Terms
Key Term Definition
Assessment Process by which information about effects of the Revised Scheme is collected,
assessed and used to inform decision making.
Baseline
Conditions
Environment as it appears (or would appear) immediately prior to the
implementation of the project together with any known or foreseeable future
changes that will take place before completion of the project.
Cumulative
Effect
Effects that result from incremental changes caused by other past, present or
reasonably foreseeable actions together with the project.
A cumulative effect may arise as the result of (a) the combined effect of a number of
different environmental topic-specific effects from a single environmental impact
assessment project on a single receptor/ resource or (b) the combined effect of a
number of different projects within the vicinity (in combination with the
environmental impact assessment project) on a single receptor/resource.
Development
Footprint
Development on land north of A419 and east of the motorway subject of the
amended application.
Effect Term used to express the consequence of an impact (expressed as the ‘significance
of effect’), which is determined by correlating the magnitude of the impact with the
importance (or sensitivity) of the receptor or resource in accordance with defined
significance criteria. For example, land clearing during construction results in
habitat loss, the effect of which is the significance of the habitat loss on the
ecological resource.
Embedded
Mitigation
Mitigation that has been embedded into the design of the Revised Scheme.
Environmental
Impact
Assessment
(EIA)
Statutory process by which certain planned projects must be assessed before a
formal decision to proceed can be made. Involves the collection and consideration
of environmental information, which fulfils the assessment requirements of the EIA
Directive, including the publication of an environmental statement.
Environmental
Statement
Document produced in accordance with the EIA Directive (as transposed into UK
law by the EIA Regulations) that reports the outcomes of the EIA process.
Mitigation Measures that are necessary to avoid, minimise, or offset anticipated adverse
impacts and, where appropriate, to incorporate these into an environmental
management plan or system.
Receptor Defined individual environmental feature usually associated with population, fauna
and flora with the potential to be affected by a project.
Redline
Boundary
Application area as indicated on RS Figure 1.2 Local Context Plan. This includes the
area south of the A419 and east of the M5 (formerly the Sports Complex), the area
north of the A419 and east of the M5 (formerly the Green Technology Hub) and the
area south of the A419 and west of the M5 (formerly the Nature Conservation
Area).
Revised
Scheme
Development on land north of A419 and east of the motorway subject of the
amended application (the Development Footprint)
Scoping Process of identifying the issues to be addressed by the environmental impact
assessment process. It is a method of ensuring that an assessment focuses on the
important issues and avoids those that are considered not significant.
Scoping
Opinion
Opinion provided by a competent authority that indicates the issues an
environmental impact assessment of a proposed development should consider.
Screening Formal process undertaken to determine whether it is necessary to carry out a
statutory environmental impact assessment and publish an Environmental
Statement in accordance with the EIA Regulations.
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 17
Significant
Effect
Environmental effect considered material to the decision-making process.
Significance of
Effect
Measure of the importance or gravity of the environmental effect, defined by either
generic significance criteria or criteria specific to the environmental topic
Site Land at M5 Junction 13 West of Stonehouse.
Study Area Spatial area within which a particular environmental effect has been assessed.
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 18
2 APPROACH TO EIA
Introduction
2.1 This Chapter outlines the approach to the Environmental Impact Assessment (EIA) in order to
meet the information required in an ES under the 2011 EIA Regulations as outlined in Table 1.5.
A request for a Scoping Opinion for the previous Eco Park application was made in 2015 and SDC
confirmed the scope for the ES. The Scoping Opinion is provided in RS Appendix 1.2. For the
Revised Scheme consultation has continued with stakeholders engaged both within and outside
the planning process for the previous Eco Park application. The details of these discussions have
been included within the technical chapters that form part of the ES.
2.2 Since the submission of the original scheme, the Town and Country Planning (Environmental
Impact Assessment Regulations 20174 came into force on 16th May 2017. Regulation 76 of the
2017 contains provisions for the revocation of the 2011 EIA Regulations. Relevant parts of
Regulation 76 are as follows;
’76. – Revocation and transitional provisions
(3) Subjection to paragraphs (2) to (4), the 2011 Regulations are revoked.
(4) Notwithstanding the revocation in paragraph (1), the 2011 Regulations continue to apply
where before the commencement of these Regulations –
(c) An applicant, appellant or qualifying body, as the case may be, has submitted an
environmental statement or requested a scoping opinion; or
(d) In respect of local development orders, the local planning authority has in connection with
that order prepared an environmental statement or a scoping opinion or requested a scoping
direction’
2.3 Accordingly, the 2011 EIA Regulations will continue to govern the determination of extant
planning applications where an Environmental Statement has been submitted before 16th May
2017, or alternatively, where a request for a scoping opinion had been made before that date,
both of which are relevant in this instance.
2.4 Therefore, this EIA has been carried out in accordance with the 2011 EIA Regulations. However,
it should be noted that the 2017 Regulations now contain additional matters which were not
required to be assessed in the 2011 Regulations. As these matters are clearly important, whilst
this ES will be determined in line with the 2011 Regulations, the additional matters which would
have been required under the 2017 Regulations have also been assessed.
2.5 The key objectives of the EIA are as follows:
• Set the legal framework;
• Consider the main alternatives to the Revised Scheme;
• Identify potentially significant effects during the design process so that some effects can
be prevented or reduced through design changes and embedded mitigation prior to the
4 Town and Country Planning (Environmental Impact Assessment) Amendments 2017 available from
http://www.legislation.gov.uk/uksi/2017/571/contents/made accessed on 22nd November 2017.
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 19
assessments within the Environmental Statement (ES), i.e. demonstrating an iterative
approach to EIA;
• Identify, predict and assess the significance of environmental effects associated with the
Revised Scheme: positive and negative; permanent and temporary; direct and indirect and
short/medium/long term. These include environmental effects associated with the
following topic areas: archaeology and cultural heritage; ecology and nature conservation;
flood risk, hydrology and drainage; landscape and visual; socio-economics; transport and
access; air quality and dust; noise and vibration; lighting; major accidents and disasters;
climate change and any interactions between these;
• Identify, predict and qualitatively assess the cumulative effects of the Revised Scheme,
including those associated with other developments in the vicinity (cumulative effects);
• Identify suitable mitigation and monitoring measures to prevent, reduce or remedy
significant negative environmental effects and identify the residual effects following the
implementation of these measures.
EIA Strategy
2.6 The ES will clearly outline that the assessment of effects is based on the Revised Scheme
description and supporting plans outlined within Chapter 5 – Description of the Revised Scheme.
These will be based on the worst-case scenario to ensure all potential effects are considered in
the ES.
Approach to Baseline Conditions
2.7 The baseline conditions for the purpose of the ES will be as at the time of the surveys for each
individual topic as noted in the Technical Chapters 7-17. These were initially conducted between
approximately July to December 2015 for all technical topics. However, many chapters have
benefitted from update work during both 2016 and 2017. There are slight variances across the
ES depending on the use of existing data obtained through other external sources as well as more
recent surveys. A summary of the baseline environment is also provided in Chapter 3 –
Description of the Site and Surroundings.
2.8 Table 2.5 details the developments that have been taken into account as part of the cumulative
assessment for the technical assessments. For certain chapters, including Chapter 12 – Transport
and Access, Land West of Stonehouse (planning application S.14/0810/OUT) has formed part of
the baseline (rather than being assessed cumulatively). This is because of Land West of
Stonehouse’s existing allocation within SDC’s Local Plan5, the recent approval of Reserved
Matters and commencement of development on site in summer 2017. As such, given Chapter
13 – Air Quality and Dust and Chapter 15 – Noise and Vibration utilise the data from the traffic
assessment, these topics have also included Land West of Stonehouse as part of the baseline to
their assessments.
Design Parameters
5 Stroud District Council’s Local Plan available from
http://www.stroud.gov.uk/info/plan_strat/newlocalplan/PLAIN_TEXT_Local%20Plan_Adopted_November_2015.pd
f accessed on 8th December 2015.
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 20
2.9 The Revised Scheme is assessed against parameter plans as detailed in Chapter 5 – Description
of the Revised Scheme. There will be a degree of flexibility within some of the parameter plans
to allow the Revised Scheme to evolve through the detailed design stages and Reserved Matters
Applications, however the finalised design will be within the identified parameters, as set out in
the following parameter plans:
• Building Height Parameter Plan (RS Figure 5.1)
• Lane Use Parameter Plan (RS Figure 5.2)
• Indicative Green Infrastructure Parameter Plan (RS Figure 5.3)
• Indicative Construction Compound Locations (RS Figure 5.4)
• Site Plan and Sections (RS Figure 5.5)
• Cross section at Grove Lane (RS Figure 5.6)
2.10 The assessments undertaken have led to design changes, but also now utilise these parameter
plans in combination with RS Figure 1.1 Indicative Concept Plan and the details provided in
Chapter 5 – Description of the Revised Scheme.
Design Iterations
2.11 Details of the design iterations are provided in Chapter 4 – Consideration of Alternatives and
Design and Access Statement, with design evolution specific to the various disciplines described
in Technical Chapters 7 – 17. The assessment of pre-mitigation effects of the Revised Scheme
has been based on the information contained within Chapter 5 – Description of Revised Scheme.
2.12 As a result of embedded mitigation via design iterations, a number of potentially significant
effects have been reduced in severity. Consequently, the number of specific mitigation measures
proposed to reduce potential significant effects is also reduced.
Screening (Regulation 5)
2.13 The EIA Regulations require that prior to consent being granted for certain types of development,
there must be consideration, by the relevant planning authority, of environmental information.
The EIA Regulations set out the type of development which must always be subject to an EIA
(Schedule 1 development) and other developments which may require an assessment if they are
likely to have significant effects on the environment (Schedule 2 development). In this instance,
as described in Chapter 1, the Revised Scheme is a Schedule 2 development and should be
screened. It has been agreed in consultation with SDC that the Revised Scheme may have
‘significant’ environmental effects, and as such a voluntary ES is submitted.
Scoping (Regulation 13)
2.14 An EIA Scoping Report for the original Eco Park scheme was submitted to SDC on 17th July 2015
alongside a request for a formal Scoping Opinion in accordance with Regulation 13 of the EA
Regulations. The Scoping Report identifies likely ‘significant’ environmental effects of the
Scheme, by comparing the existing situation (that which pertains before development is carried
out (baseline)), with the situation once the proposals are in place. The report also took into
account significance of effects during construction. The Scoping Report is provided in RS
Appendix 1.3 and the Scoping Opinion in RS Appendix 1.2. The effects outlined in the Scoping
Opinion have been taken forward and assessed within this ES as presented in Chapters 7 – 17.
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 21
2.15 The scoping exercise identified that the original Eco Park scheme would not give rise to significant
environmental effects on either a temporary (construction) and / or permanent (constructed)
basis to some of the environmental disciplines discussed. Consequently, some of the
environmental disciplines were scoped out of any further assessment. Table 2.1 below provides
a summary of what was scoped in and out of the original ES, full details are in the Scoping Opinion
(RS Appendix 1.2).
Table 2.1: Environmental Disciplines Scoped In and Out of the ES
Discipline Scoped
In / Out
Summary of Scoping Opinion
Agriculture Out The Site is Grade 3 and as such its loss is not considered to be significant
in EIA terms.
Air Quality and
Emissions
(Chapter 13)
In The proposal could generate substantial traffic unless alternative
sustainable transport is established. There is the potential for an
increase in car borne pollutants and bearing in mind the surrounding
residents it is considered that this should be included in the scope. This
may affect on ecology and the aquatic environment.
Archaeology
and Cultural
Heritage
(Chapter 7)
In There are numerous heritage assets within the area, the development
may have a significant effect on them. Archaeology should be included.
There is high potential for significance which may be masked by the
agricultural soils.
Ecology and
Nature
Conservations
(Chapter 8)
In Given the ecological activity on site, there is potential for significant
environmental effects. Ecology will be interrelated to other sections of
the ES, which should use clear cross-referencing. The ecological
strategy must aim for ecological enhancement.
Flood Risk,
Hydrology and
Drainage
(Chapter 9)
In The Site partially falls within Flood Zone 3, therefore there is potential
for a significant effect. Existing local surface water flow paths should be
identified and there should be an assessment of how these flow paths
will be affected by the development. The SUDS water/run off
implications must be considered. Water quality and the need to filter
run off could be important and impinge on ecology.
Ground
Conditions,
Contamination
Out There is no history of land instability in this vicinity. The topography
does not suggest much re-engineering would be required. The Site is
not likely to have any significant land contamination. The proposal
should not cause contamination.
Landscape and
Visual
(Chapter 10)
In Given the scale of the development and proximity of receptors, it is
considered that there is a potential for significant effects. The Site is
very prominent from public viewpoints including the M5, A38, A419, as
well as various roads. These views are close by and short range, which
are therefore likely to be affected considerably by the proposal.
Lighting
(Chapter 14)
In Lighting should be included in the scope due to its relationship with
other factors. A lighting strategy will be required. The lighting need of
the development must be assessed and the height; direction; intensity;
hooding; orientation and position within the development will have to
be assessed. Guidance from the Institute of Lighting Engineers should
be referenced and the Bat Conservation Trust guidance on lighting
should be used where relevant.
Noise and
Vibration
(Chapter 15)
In The noise implications may compound other issues. They should be
included in the scope of the ES. The methodology set out in the scoping
report is broadly acceptable.
Socio-
Economics
In The development is anticipated to create numerous jobs in the area, as
such there is the potential for a significant effect. Health benefits of the
proposal should be explained. As the proposal involves the relocation
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 22
Discipline Scoped
In / Out
Summary of Scoping Opinion
(Chapter 11) of FGR, the effect of this relocation must be considered, both on the
effect of the new development on the surrounding area, and the loss
of the use on the Site in Nailsworth. The effect of the development on
the redevelopment of other sites within the area must be undertaken.
Transport and
Access
(Chapter 12)
In The Site is located adjacent to the Junction 13 of the M5, therefore
there is the potential for significant effects. The Site is adjacent to the
M5, and its junction with the A419. The A38 major road is close by.
Effectively these roads form major arteries north-south but also
eastwards. The capacity of the roads and junctions in particular at peak
time needs to be considered as well as the safety of all users of the
highway.
2.16 The Revised Scheme now proposed is much reduced from the proposals which were scoped
above. Therefore, it is considered that following the Scoping Opinion outlined above will ensure
the worst case is now assessed as part of this Revised Scheme. In addition, further matters raised
since this Scoping Opinion of 2015 have been taken on board. Where relevant, responses to pre-
and post- application discussions and details of further technical consultations with respective
consultees have been included within the respective technical chapters of the ES.
2017 EIA Regulations
2.17 Additionally, to respond to the 2017 EIA Regulations, although not required for this ES under the
2011 Regulations, two additional chapters have now been produced. These two new chapters
are; Climate Change (Chapter 16); and Major Accidents and Disasters (Chapter 17). In this
respect, Regulation 18(3) of the 2017 EIA Regulations sets out the requirements for
environmental statements in the following terms;
‘(3) An environmental statement is a statement which includes at least—
(a) a description of the proposed development comprising information on the site, design, size
and other relevant features of the development;
(b) a description of the likely significant effects of the proposed development on the environment;
(c) a description of any features of the proposed development, or measures envisaged in order to
avoid, prevent or reduce and, if possible, offset likely significant adverse effects on the
environment;
(d) a description of the reasonable alternatives studied by the developer, which are relevant to
the proposed development and its specific characteristics, and an indication of the main reasons
for the option chosen, taking into account the effects of the development on the environment;
(e) a non-technical summary of the information referred to in sub-paragraphs (a) to (d); and
(f) any additional information specified in Schedule 4 relevant to the specific characteristics of the
particular development or type of development and to the environmental features likely to be
significantly affected.’
2.18 Accordingly, insofar as the requirements of Regulation 18(3)(a) to (e) are concerned, there has
not been any fundamental change in requirements of the EIA Regulations when compared with
the requirements of Part 2, of Schedule 4 to the 2011 EIA Regulations. Those requirements were
directed at:
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 23
• a description of the development (comprising information on the site, design and size of
development),
• a description of measures to avoid, reduce and, if possible, remedy significant adverse
effects,
• data required to identify and assess the main effects on the environment,
• an outline of the main alternatives studied and indication of the reasons for the choice
made (taking into account environmental effects), and,
• a non-technical summary.
2.19 Given that the previously prepared Environmental Statement adequately addressed those
requirements, there would not be any substantive changes to any subsequent Environmental
Statement in order to address the demands of Regulation 18(3)(a) to (e) of the 2017 EIA
Regulations.
2.20 However, as set out above in by Regulation 18(3)(f) of the 2017 EIA Regulations, there is a
requirement for an Environmental Statement to include, ‘any additional information specified in
Schedule 4 relevant to the specific characteristics of the particular development or type of
development and to the environmental features likely to be significantly affected’.
2.21 Schedule 4 of the 2017 EIA Regulations contains some different requirements when compared
with Part 1 of Schedule 4 to the 2011 EIA Regulations. The list of requirements has become more
detailed. Amongst other things, Schedule 4 of the 2017 EIA Regulations contains specific
reference to:
• energy demand and use for a development’s operational phase (paragraph 1),
• ‘reasonable alternatives’ as opposed to ‘main alternatives’ in the 2011 EIA Regulations
(paragraph 2),
• the evolution of the baseline scenario in the event that the proposed development does
not occur (paragraph 3),
• human health as a potential factor for consideration (paragraphs 4 and 5, and Regulation
4(2) of the 2017 EIA Regulations),
• ‘the impact of the project on climate (for example the nature and magnitude of
greenhouse gas emissions) and the vulnerability of the project to climate change’
(paragraph 5),
• ‘A description of the forecasting methods or evidence, used to identify and assess the
significant effects on the environment, including details of difficulties (for example
technical deficiencies or lack of knowledge) encountered compiling the required
information and the main uncertainties involved’ (paragraph 6).
2.22 A copy of Schedule 4 of the 2017 EIA Regulations has been included in RS Appendix 2.1. However,
it is considered these additional matters have either already been addressed within the scope of
the ES, or through the additional chapters included as part of this new ES. For the avoidance of
doubt, although this ES is prepared to be compliant with the 2017 Regulations, it is submitted
under the 2011 Regulations.
Public Consultation
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 24
2.23 As part of the planning process for the original Eco Park scheme, the Applicant made every effort
to engage with a range of stakeholders in advance of the submission of the planning application.
This allowed concerns raised through consultation to be addressed. Consultation was
undertaken with both the public and the various stakeholders potentially affected, this is
detailed fully within the Statement of Community Involvement submitted as part of the planning
application.
2.24 In total five public exhibitions took place prior to the submission of the original Eco Park
application, a summary of these are provided in Table 2.2 below. At the exhibitions information
displayed included site location and concept plans with a newsletter, comments form, survey
postcards and FGR advantages sheets also available for completion or taking away.
Table 2.2: Summary of Public Exhibitions
Public Exhibition Summary
31st August 2015:
The New Lawn,
Forest Green
Rovers,
Nailsworth, 12 to
2.45pm (pre-
match).
Attended by 235
people.
The response was broadly positive with regards to employment and recreational
benefits.
The general points of interest discussed revolved around: parking charges and
costs associated with season and match day tickets; footpath links from
Whitminster; the use of the stadium as a concert venue; a family fun park on
match days and disability access.
Concerns raised about the Proposed Development were in relation to: the all
seater ruining the match day atmosphere (with strong support for an all standing
stand); the traffic effects associated with the development; that public transport
is not an option in rural Gloucestershire and further to travel for local (Nailsworth
based) fans.
2nd September
2015: The New
Lawn, Forest
Green Rovers
Football Club,
Nailsworth, 12 to
7.30pm.
Attended by 24
people.
The response was broadly positive.
The general points of interest discussed revolved around: will the community be
able to access the facilities; the local community having a say on the future use of
The New Lawn; sustainable transport needs to be considered within the proposal
and The New Lawn to accommodate conference facilities or after school club.
Concerns raised about the Proposed Development were in relation to: the traffic
effect of the proposal; the loss of gym/facilities from FGR and the potential for
increased traffic if housing is delivered on The New Lawn site and that young
supporters will find the new location hard to get to.
3rd September
2015: Village Hall,
Eastington, 12 to
7.30pm.
Attended 115
people.
The response was a mixture of positive and negative feedback, with the greatest
concern being the traffic along the A419 and through Eastington.
The general points of interest discussed revolved around: the proposed use being
better than for housing; too much emphasis on ball games and not enough on
racquet sports; the athletic facility should be indoors; the effect on existing public
rights of ways; runoff and sewerage needs attention as houses on Grove Lane have
no main sewerage; facilities on canal need to attract boat owners; survey should
be undertaken to see how FGR would access the new stadium and that high speed
internet would be needed for the area.
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 25
Public Exhibition Summary
Concerns raised about the Proposed Development were in relation to: traffic
effect relating to congestion of A419 and knock-on use of Spring Hill / Eastington
Road; the nature reserve would not be accessible; the proposal is in contradiction
to Ecotricity’s green ethos and that the cumulative effect of the development
would lead to conjoining of Stroud with Stonehouse.
8th September
2015: Unicorn
House, Stroud, 12
to 7.30pm.
Attended by 26
people.
The majority of the responses were broadly positive.
The general point of interest discussed revolved around: requests for a swimming
pool and other sports to be considered; the canal trust being interested in office
space; the towpath being wide enough for pedestrians and cyclists and that the
use of the Site for the proposal is better than as a housing development.
Concerns raised about the Proposed Development were in relation to; traffic
concerns; not good to lose farmland and the loss of community facilities at The
New Lawn.
30th September
2015: Town Hall,
Stonehouse, 3 to
8.30pm
Attended by 44
people.
The response was a mixture of positive and negative feedback, with the greatest
concern being the traffic along the A419 and the use of green land.
The general points of interest discussed revolved around: the benefit of high
quality sporting facilities and improved transport links.
There also much discussion on how the proposal may assist with the reopening of
the Bristol Road Station in Stonehouse, along the Birmingham to Bristol railway
line.
2.25 A summary of the further consultations which took place after the original submission in January
2016 is summarised in Table 2.3 below.
Table 2.3: Summary of Public Exhibitions and Consultation following submission of the Eco Park
Planning Application in January 2016
Public Exhibition Summary
Saturday 30 January 2016
Before and after match at
Forest Green Rovers FC, The
New Lawn, Nailsworth
Public Exhibition. Very well attended with overwhelmingly positive
support for the proposals. A few fans were concerned about the loss
of the ground in Nailsworth to which they could currently walk.
Thursday 4 February 2016
Eastington Village Hall,
Eastington
Public Exhibition. Well attended exhibition where a wide range of
questions and comments were raised by members of the public, the
majority of which were subsequently stated in consultation responses
on the application. Main issues were traffic and parking, through-
traffic in Eastington, lighting and noise, as well as clarification on what
kind of community access/ facilities would be available.
Saturday 6 February 2016
Stonehouse Town Hall,
Stonehouse
Very poor weather was likely to be a factor in a lower than expected
turnout. Again, from those that attended a wide range of issues were
raised.
Saturday 13 February 2016
The Ale House, 9 John Street,
Stroud, GL5 2HA
Well attended and generally positive response to Eco Park.
Saturday 16th April 2016
SGS College, Berkeley Green,
Berkeley
Berkeley Green Open Day was for companies and organisations that
have expressed an interest in the development of the former nuclear
site at Berkeley.
Wednesday 29th June 2016
Growing Gloucestershire
Conference, University of
Gloucestershire, Longlevens,
GL2 9HW
The Growing Gloucestershire Conference is an annual event which
brings together delegates from the business community to discuss
interesting developments in the county. Eco Park was the subject of
the Keynote Address on ‘Delivering the Eco Park and a new home for
Forest Green Rovers at Junction 13’. Over 200 delegates attended
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 26
Public Exhibition Summary
the Conference from across the Gloucestershire Business
Community.
Thursday 17th November
2016
Eastington Village Hall,
Eastington
As previously, a well-attended exhibition. Main issues were again
traffic and parking, through-traffic in Eastington, lighting and noise, as
well as clarification on what kind of community access/ facilities would
be available.
Saturday 17 December 2017
Before and after match at
Forest Green Rovers FC, The
New Lawn, Nailsworth
Public Exhibition. Again, well attended with overwhelmingly positive
support for the proposals, including the new ZHA Stadium design.
Wednesday 5th April 2017
Eco Park Business Breakfast
Event
Over one hundred businesses attended a Business Breakfast Event,
which featured ZHAs design for FGR’s new stadium, and opportunities
presented in the proposed new Green Technology Hub.
2.26 In addition to public consultation, numerous meetings with stakeholders have continued
throughout the process, and included stakeholder engagement and meetings with Eastington
Parish Council and an exhibition/ open day, William Morris College, Stagecoach, FGR, Hitchens
(related to overlapping issues with West of Stonehouse), the Cotswold Conservation Board, and
discussions over the feasibility of re-opening Stonehouse Bristol Road Train Station.
2.27 The technical chapters also provide further detail with regards to the consultation that has been
undertaken with both statutory and non-statutory consultees. Discussions with stakeholders are
ongoing and the Applicant will continue these throughout the application and consultation
process.
Approach to the Assessment of the Revised Scheme
2.28 The assessment of potential effects resulting from the Revised Scheme has taken into account
the construction and operational phases. The significance level attributed to each effect
identified has been assessed on the magnitude of change due to the Revised Scheme and the
sensitivity of the affected receptor/ receiving environment to change/ effect as well as a number
of other factors that are outlined below in more detail. The determination of the significance of
residual effects has been assessed with regard to the extent to which mitigation measures will
reduce or reverse significant negative effects. Whether these residual effects are significant or
not is also stated.
Assessment Criteria
2.29 The assessment of potential effects for each of the technical topic areas are presented in
Technical Chapters 7 – 17 and have taken into account a number of criteria to determine
whether or not the potential effects are ‘significant’. Wherever possible and appropriate, the
effects will be assessed quantitatively. The following criteria have been taken into account when
determining the significance of potential effects.
• Relevant legislation and planning policy;
• International, national, regional and local standards;
• Geographical extent;
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 27
• Magnitude and complexity of effect;
• Sensitivity / value of affected receptor or receiving environment;
• Duration (short, medium or long-term), frequency and reversibility of effect;
• Inter-relationship between different effects (both cumulatively and in terms of potential
effect interactions);
• The outcomes of consultations.
2.30 Unless specified in the Technical Chapters 7 – 17 the following criteria will be used to determine
the magnitude of change and the sensitivity of the receptor/ receiving environment.
Magnitude of Change
2.31 The magnitude (scale) of change for each effect has been identified and predicted as a deviation
from the established baseline conditions, for the construction and operational phases of the
Revised Scheme. The scale used (high, medium, low, and negligible) is shown in Table 2.4 below.
Sensitivity of Receptors
2.32 The sensitivity of receptors/ receiving environments considered within the ES are defined within
Chapters 7 – 17. The sensitivity/ value of receptors/ receiving environments to change have been
determined by quantifiable data (where applicable), the consideration of existing and proposed
designations and professional judgement. The scale used (high, medium, low, and negligible) is
also shown in Table 2.4.
Assessment Effect Significance
2.33 The level of effects has been assessed using appropriate national and international standards or
limits (WHO Limits, EU Quality Standards etc.). Where no such standards exist, the assessments
in each individual subject area describe the professional judgements (assumptions and value
systems) that underpin the attribution of significance.
2.34 Each effect has been assessed against the change of magnitude and the sensitivity of the receptor
as shown in Table 2.4.
Table 2.4: Matrix for determining the level of effects
Sensitivity of receptor/ Receiving Environment to Change/ Effect
High Medium Low Negligible
Ma
gn
itu
de
of
Ch
an
ge
/ e
ffe
ct Substantial Major Moderate Minor Negligible
Medium Moderate Moderate Minor Negligible
Minor Minor Minor Minor Negligible
Negligible Negligible Negligible Negligible Negligible
2.35 While effects are considered to fall into one of four effect categories ranging from ‘negligible’,
‘minor’, ‘moderate’, ‘major’ in the effects matrix presented in Table 2.4, it is only those effects
that fall into the ‘moderate’ or ‘major’ category (as shaded above) that are considered to be the
significant environmental effects arising from the construction and operation of the Revised
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 28
Scheme. It should however be noted that different specialist topics within the ES may use a
different approach to identify which level of effects are significant. A summary of effects table is
contained within each technical assessment chapter clearly stating for each effect identified
whether it has been found to be ‘significant’ or ‘not significant’.
2.36 Whilst the ES provides a full factual description of the development, as emphasised by Schedule
4 of the 2011 EIA Regulations 6, and clearly stated in Planning Practice Guidance (PPG)7, the ES
needs to be proportionate and not any longer than is necessary to assess properly those effects
which are considered significant. In this instance, effects considered significant have been
assessed within the main technical chapters, with supporting appendices clearly identified in
these chapters providing details of the assessments undertaken on the effects considered not
significant.
2.37 The terms as used within the table have been defined below:
• Major positive or negative effect: where the development would cause significant
improvement (or deterioration) to the existing environment.
• Moderate positive or negative effect: where the development would cause noticeable
improvement (or deterioration) to the existing environment.
• Minor positive or negative effect: where the development would cause perceptible
improvement (or deterioration) to the existing environment.
• Negligible: no discernible improvement or deterioration to the existing environment.
2.38 In addition to the assessment structure set out above, specific criteria have been developed for
certain technical studies and are detailed in the respective chapters of the ES. The inter-
relationship between environmental effects and residual effects following implementation of
mitigation measures has also been discussed.
2.39 In terms of the duration of an effect, short-term has been considered as 1 year (or below), a
medium-term effect has been considered to be between 1 and 10 years in duration and a long-
term effect has been considered to be greater than 10 years in duration. If variation on these
timeframes is necessary, this is stated and explained in Technical Chapters 7 to 17.
Cumulative Effects
2.40 Schedule 4 of the EIA Regulations requires that cumulative effects of a development are
considered within an EIA. There is no widely accepted methodology or best practice for the
assessment of cumulative effects, although various guidance documents exist. The following
approach has been adopted for the assessment of cumulative effects, based on previous
experience, the types of receptors being assessed, the nature of the Revised Scheme, the
committed developments under consideration and the information available to inform the
assessment.
6 Schedule 4 of the EIA Regulations available from http://www.legislation.gov.uk/uksi/2011/1824/schedule/4/made
accessed on 8th December 2015. 7 Planning Practice Guidance, Paragraph: 035 Reference ID: 4-035-20140306 available from
http://planningguidance.communities.gov.uk/blog/guidance/environmental-impact-assessment/preparing-an-
environmental-statement/ accessed on 8th December 2015.
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 29
2.41 With regards to cumulative effects, they have been considered within the technical assessments
as both cumulative effects from different committed developments and cumulative effects from
different environmental features. Table 2.5 lists the committed developments that have been
identified as part of this assessment. RS Figure 18.1 illustrates the locations of these sites. As
such, each consultant has reviewed the respective planning submission (and ES chapters where
these exist) to ensure any cumulative effect has been fully assessed within the respective
technical chapters.
2.42 As detailed above and within Chapter 12 – Transport and Access, Land West of Stonehouse has
formed part of the baseline for the assessment undertaken as opposed to the cumulative
assessment. This is because all the traffic modelling has included West of Stonehouse (and
associated A419 junction improvements) as part of the baseline traffic flows in order to assess
worst case. Given Chapter 13 – Air Quality and Dust and Chapter 15 – Noise and Vibration rely
on data from the traffic assessment, these have also included Land West of Stonehouse and the
A419 junction improvements as part of the baseline to their assessments.
2.43 Further details regarding the scope of the assessment of cumulative effects are provided within
Chapter 18 – Cumulative Effects.
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 30
Table 2.5: List of committed developments that have been identified for cumulative assessment
Reference Address Development Status Co-ordinates Distance from site
(km)
S.14/0810/OUT Land West of
Stonehouse, Nastend
Lane, Nastend,
Stonehouse,
Gloucestershire
A mixed-use development comprising up to 1,350 dwellings and 9.3 hectares of employment land
for use classes B1, B2 and B8; a mixed use local centre comprising use classes A1, A2, A3, A4, A5,
D1, D2 and B1; primary school, open space and landscaping, parking and supporting infrastructure
and utilities; and the creation of new vehicular accesses from Grove Lane, Oldends Lane and Brunel
Way. Reserved Matters now approved under S.17/0095/REM.
Application
Permitted
379312,
206558
0.1
S.12/0763/FUL Bonds Mill, Unit 27,
Bristol Road, Stonehouse
Demolition of part of an existing warehouse including a hoist on the adjacent building, renovation
of the remainder as office space and erection of a two-storey extension.
Application
Permitted
379344,
205327
1.51
S.15/1088/FUL Westend Courtyard,
Grove Lane, Westend,
Stonehouse,
Gloucestershire
Proposed extension to Westend courtyard to provide 10 additional offices (B1 use). Application
Permitted
378312,
207018
0.1
N/A Infilled canal to the south
of the Site
Canal restoration and realignment scheme subject to successful Lottery bid funding from Cotswold
Canals Trust
No planning history. Directly to the
south of
Redline
Boundary.
Directly to the south
of Redline Boundary.
13/0001/INQUIR Land at Javelin Park Proposed Development of an Energy from Waste (EfW) facility for the combustion of non-
hazardous waste and the generation of energy
Appeal Allowed 380040,
210430
3.92
S.15/2089/OUT Land Adjacent To
Eastington Trading Estate
Churchend, Eastington,
Gloucestershire.
Erection of three industrial employment buildings with associated access, car parking and service
yards (Outline application - Access, Layout and Scale included).
Application
Permitted
378000,
206050
0.1
S.17/0563/OUT Land Off School Lane,
Whitminster,
Gloucestershire
Residential development for up to 60 dwellings including infrastructure, ancillary facilities, open
space and landscaping. Construction of a new vehicular access from School Lane.
Application Refused 377106,
208403
1.5
S.17/1133/FUL Former Standish Hospital
and Former Westridge
Hospital Standish,
Stonehouse,
Gloucestershire
Conversion and refurbishment of the former Standish Hospital complex, including Standish House
(Building A), Stable Block (Building B), Ward Blocks (Buildings C & G), Standish Lodge (Building L),
Building I, and demolition and works to associated out-buildings and gatehouse to form 50
dwellings; demolition of Westridge Hospital and associated building. Development of 98 new build
homes within the grounds; conversion; associated surface vehicle and cycle car parking, pedestrian
and vehicular access and associated ancillary development, landscaping, ancillary storage and plant
and ecological bat housing; and all associated engineering works and operations
Pending
Consideration
381646,
206566
3.0
S.16/0922/REM Land Adjoining Station
Road Bristol Road,
Stonehouse,
Gloucestershire, GL10
3RB
Approval of Reserved Matters Appearance and Landscaping from appeal
APP/C1625/A/13/2195656 (S.12/2538/OUT) - residential development for 49 units, new access
way and associated works.
Application
Permitted
379900,
205480
1.8
S.17/2331/OUT
Land Adjoining Oldbury
Lodge Pike Lock Lane
Eastington
Gloucestershire
Erection of new buildings for uses within use class C1 (Hotel) up to 1,908 Sqm (56 Beds), and use
classes A3 / A4 Pub (Pub/Restaurant) up to 711 Sqm (Including ancillary manager's apartment) and
associated access, servicing, parking, drainage and landscaping (outline application: all matters
reserved except for access and scale)
Awaiting Decision 378500,
206100
0.3
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 31
3 DESCRIPTION OF THE SITE AND SURROUNDING AREA
Introduction
3.1 This Chapter provides a description of both the Site location, defined by the Redline Boundary
(RS Figure 1.3), and the surrounding area. Further detailed site descriptions along with the Study
Areas in relation to the technical assessments undertaken are provided within Chapters 7 – 17.
Site Location and Surrounding Area
3.2 The Site is approximately centred on National Grid Reference SO 77965 206584. RS Figure 1.2
shows the Site’s local context and RS Figure 1.3 shows the Site context. As noted under scoping
in Chapter 2 above, the Site is Grade 3 agricultural land. It consists of relatively species poor
agricultural land throughout with fields currently used for cattle grazing and cutting of hay. The
Site is bisected by the A419, running in a north-west, south-east direction, and the M5 in a north-
east to south-west direction. The Site is fairly flat with a slight fall south across the Site from 20m
AOD to 15m AOD.
3.3 The southern land parcel of the Site (formerly the Sports Complex) is approximately 13.5ha in
size and is bounded to the south-east by residential properties and warehouses, and to the south
by the flood plain of the River Frome which lies in Flood Zone 3 of the Environment Agency Flood
Map. It is comprised of mixed agricultural fields.
3.4 The south-western land parcel of the Site (formerly the Nature Conservation Area) is
approximately 4.6ha and is bounded to the east by the M5, River Frome to the south, mature
hedgerow and trees to the west and the Eastington Maintenance Compound associated with the
motorway to the north. It comprises two agricultural fields with belts of trees and mature
hedgerow with a line of scrub bordering the river to the south. It is located within Flood Zone 3.
3.5 The area where the Revised Scheme is located is approximately 18.9ha in size and is bounded by
properties and Grove Lane to the north, a tree lined agricultural track to the east, the A419 to
the south and the M5 to the west. It is comprised of mixed agricultural fields with belts of trees
and hedgerows.
3.6 As the land use at the Site is predominantly agricultural (grazing land), it is understood that
potable water supply and foul drainage services are not currently present on-site. However, the
nearest foul water drainage and water supply are within close proximity to the Site at properties
directly to the east of the southern parcel of land at Chipmans Platt, and properties located off
Grove Lane adjacent to the Revised Scheme. The existing landscape context is a combination of
built development and major infrastructure and rural land use – a dynamic rural landscape with
urban fringe qualities including the hustle and bustle (both aural and visual) of an urban
environment.
3.7 The highways improvement works covers an area approximately 2.5ha in size. It comprises the
A419 which forms the main road corridor into Stonehouse and Stroud from the west. To the
west the A419 has a grade separated roundabout junction with the M5 (Junction 13) and, beyond
the M5, a roundabout junction with the A38 south of Whitminster. The section of the A419
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 32
located to the south of the area subject of the Revised Scheme, between the M5 and Chipmans
Platt Roundabout is a single carriageway road subject to the national speed limit. There is no
street lighting and no footway along this section.
3.8 Chipmans Platt roundabout to the south east of the Site forms the junction between the A419,
Spring Hill to the south and Grove Lane to the north, and is street lit. A service area is located at
this junction, and includes a filling station, a coffee shop and a hotel. Entrance is from the
roundabout, with exit on to Grove Lane to the north. It should be noted that this service area
junction onto Grove Lane is currently the subject of works associated with the West of
Stonehouse development. Construction commenced in summer 2017, and works to the site
access are now well underway.
3.9 North of Chipmans Platt, Grove Lane leads north and west to join the A38 at Whitminster. The
southern section is a two-lane single carriageway, with a footway on the eastern side, and subject
to a 50mph speed limit (and currently the subject to West of Stonehouse access works as
described above). The footway stops to the north of the service area exit, and a 40mph speed
limit commences on the approach to the settlement of Westend, returning to 50mph to the
south east of the bridge over the M5. South of Chipmans Platt, Spring Hill / Alkerton Road leads
south west to the village of Eastington where it has a roundabout junction with Bath Road.
3.10 There is currently no footway or cycleway along the A419 bisecting the Site and no formal
pedestrian crossing of the A419 is provided, even though a Public Right of Way crosses from the
southern parcel of land into the northern parcel of land where the Revised Scheme is located.
There is an underpass approximately 100m long which could be made suitable for use on foot
(subject to some refurbishment) under the M5 south of Junction 13. The local public rights of
way network through the Site includes a footpath running south-west to north-east through the
southern parcel of land, and a footpath that runs south-west to north-east and then splits into
two separate footpaths through the Revised Scheme. These two footpaths in the southern parcel
of land and the Revised Scheme to the north are linked across the A419 (but without a pedestrian
crossing as noted above). Evidence on the ground indicates generally infrequent use near the
A419 crossing, with slightly greater levels or use near Grove Lane and William Morris College.
3.11 National Route 45 of the NCN, which links Chester with Salisbury via Gloucester, Cirencester and
Swindon, runs along Grove Lane to the north of the Revised Scheme, and then south along Spring
Hill south of Chipmans Platt for a short distance.
3.12 The noise environment at the Site is dominated by road traffic noise from both the M5 and A419.
Other noise sources include agricultural plant, livestock and potentially the operation of the
Highways Agency Maintenance Compound. The baseline air quality estimated at the Revised
Scheme site does not exceed the relevant air quality objectives for NOx, NO2, PM10 and PM2.5.
3.13 No Scheduled Monuments, Registered Parks and Gardens or Registered Battlefields are present
within or in the vicinity of the Site. The southern part of the Site lies partially within the Stroud
Industrial Heritage Conservation Area. No Listed buildings are present within the Redline
Boundary.
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 33
3.14 There are no ecological designations within the Site. However, the land holding adjacent to the
southern parcel of land adjoins, and is partly included in, the River Frome Key Wildlife Site (KWS)
and the River Frome mainstream and Tributaries KWS. A desk study within 5km of the Site
identified two internationally important sites, four nationally important sites, and 18 Key Wildlife
Sites. Fourteen species of bats have been recorded within 10km of the Site centre. Otter, badger,
hare, water vole, reptiles and amphibians were recorded within 5km of the Site centre. A large
number of bird records were returned due to the proximity of the Site to the Severn Estuary
Special Protection Area.
3.15 The Site is currently unlit with no existing sources of artificial lighting within the Redline
Boundary. Existing light emissions are associated with the M5, A419 and the junction which
connects these two roads. While the sections of these roads immediately adjacent to the Site are
unlit, there are light emissions associated with traffic traversing these roads at night, the
Highways Agency maintenance compound, the service station to the southeast of the Revised
Scheme, and residential dwellings along Grove Lane and associated with Chipmans Platt. Light
intrusion is also observed from the Eastington Trading Estate which adjoins the Redline Boundary
of the southern parcel.
3.16 Committed development in the surrounding area is illustrated in RS Figure 18.1 and listed in
Table 2.5. Directly to the south west of the Redline Boundary is the proposed canal realignment
scheme by the CCT. To the east of the Revised Scheme is Land West of Stonehouse. This is a
strategic site allocation within the recently adopted Local Plan, has outline planning permission,
and has recently been granted Reserved Matter approvals with work now commencing on the
site access from Grove Lane as noted above. It is a mixed-use development with permission for
up to 1,350 dwellings and 9.3 hectares of employment land.
3.17 Another committed development to the north of the Revised Scheme, located on the north side
of Grove Lane, is Westend Courtyard. This is an approved permission for 10 additional offices.
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 34
4 CONSIDERATION OF ALTERNATIVES
Introduction
4.1 This Chapter outlines the description of the main alternatives to the Revised Scheme which have
been considered by the Applicant and the principal reasons for proceeding with the current
planning application. It firstly looks at alternative sites and then discusses alternative site layouts.
Requirement of the Consideration of Alternatives
4.2 Schedule 4, Part 1 of the 2011 EIA Regulations states that an ES should include ‘an outline of the
main alternatives studied by the applicant or appellant and an indication of the main reasons for
the choice made, taking into account the environmental effects’.
Alternative Sites
4.3 A number of options have been considered in relation to the future location of the FGR, but also
the concept of Eco Park that formed part of the original planning submission. In the initial stage
of the project appraisal the Site options were considered against FGR’s requirements and
aspirations for relocation. These were (as per Chapter 1):
• Provide a location easily accessed by supporters being well served by public transport and
with adequate onsite parking provision;
• Remove parking congestion on match days from Nailsworth;
• Provide adequate facilities in one location for the youth, academy, first and ladies teams,
helping to ensure sustainability in sport by supporting and encouraging local talent;
• Be an educational resource for local further education establishments, enabling more
sports related courses to be run and an increase in student numbers;
• Deliver an all-weather pitch together with training pitches, gym, state of the art sports
science and medical facilities;
• Create a centre of excellence for sports medicine, rehabilitation, fitness and health,
working with local health and education providers.
• Be of benefit to the residents and Sports Clubs of Stroud District and beyond who will have
access to the FGR facilities for a range of sports;
• Provide additional sports facilities which will be developed and could include, for example,
an athletics track and a rugby pitch;
• Be the focal point of Eco Park, which offers FGR the prospect of a long-term home, set
within a traffic free parkland and designed to show case sustainable construction
practices.
4.4 In order to identify an area of search for the Revised Scheme, a GIS mapping exercise was carried
out to identify potential available land for Eco Park. The methodology used for the area of search
was as follows:
1. Land located within the AONB, existing built up areas and land already allocated for
housing was removed from the area of search.
2. Land located within the Flood Zones 2 and 3 according to the Environment Agency
mapping was then subsequently removed from the area of the search.
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 35
3. From the existing stadium development an area of search of 10km was identified. Given
FGR’s location within Nailsworth, it was important when looking for a new location that
the club did not relocate too far and lose its local association.
4. The proposed Stonehouse Cluster (strategic site SA2 from the Local Plan) was then
subsequently removed from the area of search.
5. Further constraints such as common land, National Trust land and both national and
international designated ecological sites were identified on the plan.
6. Finally, an area of search from the junctions of the M5 motorway were added to the plan.
4.5 The output from was RS Figure 4.1 Site search area for the Revised Scheme. From these
requirements, a number of available sites within Stroud District were considered. The search was
limited to the District given FGR’s association with the area, current fan base and the need to
avoid this fan base from travelling longer distances in order to maintain their support for the
club. The following alternative options have been considered:
• Option 1: The ‘Do Nothing’ Scenario: FGR stays at The New Lawn and the Site remains as
agricultural land
• Option 2: Redevelopment of The New Lawn
• Option 3: Relocation Alternative Sites
• Option 4: Relocation to Land at Junction 13 M5 ‘Eco-Park’, West of Stonehouse
• Option 5: Relocation to Land at Junction 13 M5 ‘Revised Scheme’, West of Stonehouse
Option 1 - Do Nothing
4.6 The ‘do nothing’ scenario would mean that the Site would continue to remain Greenfield
agricultural land. A number of important effects would derive from this ‘do nothing’ scenario and
largely relate to lost opportunities for improvement / enhancement. These include:
• The loss of opportunity for significant investment in Stroud District in a difficult economic
climate;
• The loss of provision of employment opportunities on-site during construction and
operation and in the surrounding area through supply chain services;
• The loss of improved traffic and transportation implications associated with match days at
The New Lawn;
• The missed opportunity of a landmark building providing a gateway into Stroud District;
• The missed opportunity to deliver the dualling of the A419 between the Junction 13 of the
M5 and Chipmans Platt roundabout which will deliver traffic flow improvements towards
Stroud.
• The missed opportunity to deliver the biodiversity enhancements sought by the Revised
Scheme.
4.7 There are, however, a number of positive effects resulting from the ‘do nothing’ scenario,
including the following:
• The increased noise, dust and visual intrusion associated with the construction phase
would be avoided;
• The increased traffic, noise, lighting and air quality effects associated with the operational
phase would be avoided;
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 36
• Existing ecology (species and habitats, albeit limited) and agricultural land would not be
disturbed and would remain unaffected;
• Preservation of the existing landscape character and existing views from the surrounding
features and properties.
Option 2: Redevelopment of The New Lawn
4.8 One option considered was to redevelop the stadium on The New Lawn site. This was ruled out
fairly early in the process due to the technical difficulties that would be encountered
redeveloping the current stadium. Issues such as the size of the pitch, the orientation logistics of
working around the current buildings and the current and future access to the Site were all
constraints that were considered and caused this option to be discounted. Furthermore, part of
the reason for the relocation is to allow future expansion of the stadium as the ambition is to
progress up the Football League, and therefore the alleviation of traffic effect on the local
community associated with higher attendances – which are already being experienced since
FGR’s promotion to League 2 this season.
Option 3 - Relocation Alternative Sites
4.9 As part of an initial search for sites, three alternative sites to land at M5 Junction 13 were
considered, these were Aston Down Industrial Estate, Javelin Park, Oldends Lane Industrial Estate
and the Stonehouse Area. These sites have been assessed below.
4.10 Oldends Lane Industrial Estate and the Stonehouse Area: The Site allocations at the Stroudwater
Business Park previously comprise of 18.6ha of land within three allocations (EA9, EA10 and EA11
of Saved Policy EM5). However, the residual allocations of these have now been reallocated to
form part of Policy SA2 of the adopted Local Plan. The Site is one of the primary employment
allocations within the District having good access to the A419 and M5. The location is within the
M5 growth corridor. The previous allocation EA9 has been partially developed with new
applications coming forward on behalf of Schlumberger in the form of “buildings A and F”.
Allocation EA10 also benefits from a recent planning permission (S.14/0353/FUL) for Stroud
Metals. In addition to the Site allocations, a further development of 1.83ha by Ashville
Developments Finance Limited was permitted in July 2015 adding a further 1.83ha to the
employment land supply here. The remaining area of land available at this site is 10.4ha in the
residual allocation from EA9 and EA11, which like EA10 are now formally revoked. The Stroud
Local Plan reallocates the residual part of allocation EA9 from the previous Local Plan and
accordingly there is no increase of employment land at this location from the previous local plan
despite it being in the optimum location for business growth. However, as is clear from scale and
need of the Revised Scheme, a site of 10.5 ha will not be sufficient to deliver the Revised Scheme
which covers some 18.9ha.
4.11 Aston Down Industrial Estate: The Site is identified as a key employment site within the Local
Plan (Policy El1 site EK21). It is located within the AONB and this, coupled with the distance from
the motorway, would make it unacceptable in the scale and form of the Revised Scheme and also
unlikely to be found acceptable in planning terms.
4.12 Javelin Park: The Site is identified a Key Employment Site and is a Waste Core Strategy Allocation
within the Local Plan, it has also recently been subject to a successful appeal for an Energy from
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 37
Waste Plant. As such, through the implementation of that development it would not allow the
form and scale of the Revised Scheme that would be required. Furthermore, the Site falls outside
the area of search in terms of distance from the area of search.
4.13 All four sites following an assessment were not considered to be suitable for the Revised Scheme
in its current scale and form.
Options 4 and 5: Relocation to Land at M5 Junction 13, West of Stonehouse
4.14 A further option discussed (and which formed the Eco Park Application), was the relocation to
Land at M5 Junction 13 West of Stonehouse. The original planning application was larger, and
included the area south of the A419 and east of the M5 (the Sports Complex), the area north of
the A419 and east of the M5 (the Green Technology Hub) and the area south of the A419 and
west of the M5 (the Nature Conservation Area). Since submission of this application in January
2016, the Applicant and their advisors have been in on-going discussions with both SDC and
statutory consultees, and this has given rise to this Revised Scheme. Only the area north of the
A419 and east of the M5 is being proposed for development (the ‘Development Footprint’) as
part of this Revised Scheme, to provide a stadium and ancillary facilities, together with training
pitches for FGRFC.
4.15 A full description of the Revised Scheme is included in Chapter 5 – Description of the Revised
Scheme.
Alternative Site Layouts
4.16 Following the selection of the Site, environmental constraints have been identified and
subsequently addressed through alteration of the concept design to minimise or avoid adverse
significant environmental effects. As a result of embedded mitigation via design iterations, a
number of potentially significant effects have been reduced in severity. Consequently, the
number of specific mitigation measures proposed to reduce potential significant effects is also
reduced.
4.17 The Design and Access Statement submitted as part of the planning submission also provides
further details of the design evolution of the Revised Scheme. These are provided in more detail
within that statement, however the key design iteration changes can be summarised in Table
4.1.
Table 4.1: Design Iterations
Iteration Changes
1 • Concept Design: was prepared to assess the preliminary viability of the Site and to
establish whether the development could be accommodated within the Site.
• Environmental Constraints: were taken into account in order to build embedded
mitigation into the Revised Scheme.
• William Morris College: was identified as key receptor at the outset and ways to reduce
the effect upon them were considered.
• Access: a new access point was built in due to both proximity of the M5 and existing
congestion issues along the A419.
2 • Concept Plan: was broadly translated to the submitted outline parameter plans
submitted as part of this ES (RS Figures 5.1, 5.2 ad 5.3). The layout in the Indicative
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 38
Iteration Changes
Concept Plan was developed as feedback became available from members of the
consultant team as their assessments were carried out.
• Access: the Concept Design was adjusted to accommodate the introduction of a signalised
junction as opposed to a roundabout, along with a separate access off Grove Lane for
busses to utilise on matchdays via the Stonehouse development.
• Pedestrian Access: various options were considered, including the location of footways.
The signalised junction was considered the most appropriate means of accessing the Site
from the A419.
• Footpath / Cycle Link: was built in to be delivered on the A419 between the new junction
and Chipmans Platt roundabout improving the Site’s sustainability credentials and
reducing the potential traffic effect.
4 • Topographic Data: was overlaid to further inform the detailed positioning of the new and
maintained green infrastructure. This included incorporating the Arboricultural Report
(RS Appendix 8.4) ensuring certain hedgerows and trees identified for retaining were
incorporated.
• Access: the most notable change was the relocation of the junction slightly further east
along the A419 to reduce the effect on surrounding trees. As part of this two hedgerows
to the south of the A419 will be affected by the widening of the A419. Prior to the
carriageway widening, the hedgerows will be translocated 40m to the south of the original
alignment.
6 • Concept Design: the design was altered so the pitches to be delivered by the Revised
Scheme would be located solely for the use of FGR. This avoids the need for flood lighting,
and potential for effects on surrounding receptors such as residential properties and the
identified bat corridors (see RS Figure 5.3).
• Landscape Bund: a bund was introduced as illustrated on RS Figure 5.3 to reduce
potential effects in relation to noise, lighting and visual intrusion on neighbouring
properties but also ecological receptors. In particular this will allow for a bat commuting
corridor to provide commuting and foraging opportunities for bats while preventing light
spill.
• Parking: an increase of car parking spaces to 1,700 was made to comply with
Gloucestershire County Council Highways requirements. Capacity for 100 cycle spaces
will also be provided.
4.18 Through the key design iterations discussed in Table 4.1, RS Figure 1.1 the Indicative Concept
Plan has been developed. It includes the embedded mitigation within the design required to
reduce potential significant effects. However, the Concept Plan is still draft, and the final Revised
Scheme may still be subject to change at the Reserved Matters stage (within the parameters that
have been applied for).
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 39
5 DESCRIPTION OF THE REVISED SCHEME
Introduction
5.1 This Chapter provides a description of the Revised Scheme. An indicative description of how the
Revised Scheme will be constructed and construction principles has also been provided. It is upon
this description, information and the supporting spatial plans that the technical assessments in
Chapter 7 – 17 are based.
Revised Scheme
5.2 The Revised Scheme seeks to provide replacement sports facilities for FGR. In order to meet the
club’s requirements moving forward, a sports complex is proposed which includes an innovative
centrepiece 5,000 capacity stadium designed by world-renowned architects Zaha Hadid, as well
as two additional full-size training pitches and goalkeeping training area to serve FGR. The pitches
will be grass, and none will be flood lit. The Revised Scheme is illustrated on RS Figure 1.1
Indicative Concept Plan.
5.3 The training pitches will be used primarily by the FGR first team who currently train at Stanley
Park, Chippenham, which is approximately 24 miles from the New Lawn. The proposals will allow
FGR to centralise its operations and will provide a ‘hub’ of activity.
5.4 The Redline Boundary remains the same as for the previous application submitted. However, all
development will now take place on land north of A419 and east of the M5 within the
Development Footprint only (on land previously allocated for the Green Technology Hub in the
initial submission). No development will take place to the south of the A419, however,
translocation of a hedge will occur on this land (as a result of road widening).
5.5 The Redline Boundary is approximately 39.5ha. The area that will form the new FGR site is
approximately 18.9ha with the highways improvement works 2.5ha. The Site is approximately
centred on National Grid Reference SO 77965 206584. RS Figure 1.2 shows the Site’s local
context and RS Figure 1.3 shows the Site’s context. The key components of the Revised Scheme
are listed in Table 5.1 (final amounts to be determined at Reserved Matters based on the
parameters set out in RS Figures 5.1, 5.2 and 5.3).
Table 5.1: Key Components of the Revised Scheme
Use Use
Class
Indicative Amount Based on Indicative
Concept Plan (RS Figure 1.3)
Sports Complex 18.9ha
Stadium including ancillary facilities
designed for a capacity of 5,000
D2 To be determined at Reserved Matters. Form
and design of stadium is set out in the Design
and Access Statement.
Two full-sized grass pitches and a goal
practice area
D2 To be determined at Reserved Matters.
Car parking and associated infrastructure N/A To be determined at Reserved Matters.
Parking will be provided for 1,700 vehicles (lit
to previous arrangements, LED luminaries
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 40
Use Use
Class
Indicative Amount Based on Indicative
Concept Plan (RS Figure 1.3)
complete with street optics and including
sensors).
Access Works 2.5ha
Including: signalised site access off the A419;
full dualling of the A419 from M5 J13 to
Chipmans Platt; a signal controlled
pedestrian and cycle crossing of the A419
with a combined footway/ cycleway on the
south side of the A419 (which will link to
National Cycle Route 45 at Grove Lane).
N/A 2.5ha
5.6 FGR are currently based at The New Lawn in Nailsworth, Gloucestershire. The New Lawn was
built in 2006 and has a capacity for a crowd of just under 5,000. The ability of FGR to operate
sustainably is hindered by the location of The New Lawn, which is not readily accessible.
Nailsworth has no railway station (Stroud is the nearest) and is some nine miles from the Stroud
junction of the motorway. There is also a chronic lack of parking and facilities for fans.
Design Principles
5.7 The Revised Scheme aspires to be a green low carbon development, employing the very best,
innovative and most recent practices in;
• Sustainable construction;
• Innovative sustainable building design, orientation and landscape works, which have
excellent thermal performance, exceptional air-tightness with mechanical ventilation to
minimise heating/ energy demand, and unadopted highways to be constructed of KWS
Infra sustainable plastic roads;
• Sustainable operation through, for example, a site layout which creates a parkland
setting around the stadium itself.
• Creating a sustainable development by providing facilities for accessing the Site by public
transport, walking, cycling and the use of electric vehicles.
• Use of Green Infrastructure within the Revised Scheme and the retention and ecological
enhancements of woodlands and mature hedgerows wherever possible;
• Integration of species rich grassland into non-sporting areas throughout the site;
• Use of SuDs where practicable throughout the development;
• The adoption of best practice ecological management and enhancement for green
corridors.
5.8 Specific detailed design proposals will emerge from the evolution of the outline planning Concept
Design, and will be subject to Reserved Matters. The principal considerations for the Revised
Scheme design are outlined below. The principal benchmark used for the Revised Scheme will
be BREEAM with the aspiration for achieving the ‘outstanding’ standard. “BREEAM sets the
standard for best practice in sustainable building design, construction and operation and has
become one of the most comprehensive and widely recognised measures of a building's
environmental performance. It encourages designers, clients and others to think about low
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 41
carbon and low effect design, minimising the energy demands created by a building before
considering energy efficiency and low carbon technologies.”8
5.9 It is anticipated that the finalised Revised Scheme will incorporate the following principal design
considerations (Table 5.2) set out through any subsequent Reserved Matters Applications.
Considerations are set out in relation to sustainable construction; sustainable building design
and landscape works; green travel plan (see Outline Travel Plan, RS Appendix 12.3); sustainable
operation; and best practice ecological creation, management and enhancement.
Table 5.2: Principal Design Considerations
Principal Design Considerations
Sustainable Construction
• Monitoring, recording and reporting energy, water and transport consumption data resulting from
all construction processes;
• The use of responsible sourcing for construction materials with a low environmental impact
(including embodied carbon) over the full life cycle of the building (e.g. source materials such as
timber from sustainable/ certified sources);
• The provision of a Site Waste Management Plans to design out waste, reduce waste generated on
site and implement procedures to sort and reuse/recycle construction waste on and off site;
• The use of re-used materials where possible, such as the use of recycled and secondary aggregates,
and the construction of unadopted roads with sustainable waste plastic;
• The use of thermal insulation which has a low embodied environmental impact relative to its
thermal properties and has been responsibly sourced;
• Sustainable procurement and the use local contractors where possible;
• Construction site operative awareness and training in sustainable practices;
• A detailed Construction Management Plan including a Pollution Prevention Plan, and the use of an
Environmental and /or Ecological Clerk of Works to maintain best practice procedures;
• Measures to protect ecological habitats including all important hedgerows and trees, and
establishment of a suitable buffer around identified protected species (such as the main badger
sett);
Sustainable Building Design and Landscape Works
• The Revised Scheme aspires be carbon neutral or carbon negative, by including measures such as
the provision of on-site renewable energy generation;
• Design of buildings to minimise operational energy demand, consumption and CO2 emissions (such
as use of appropriate insulation and meeting Passivhaus standards);
• Building design to ensure maximum use of natural daylight, limited use of artificial lighting (both
internal and external), utilise energy efficient lighting technology (such as the use of LEDs) and
sustainable occupant controls to minimise energy consumption;
• External lighting will be controlled through a combination of movement sensors, time switches
and daylight sensors to prevent operation during daylight hours. It will be concentrated in the
appropriate areas, and upward lighting will be minimised, reducing unnecessary light pollution,
energy consumption and nuisance to neighbouring properties. In addition, external lighting will: -
o Be designed to minimise horizontal spill of light to hedgerows and areas of restored
species-rich grassland;
o Avoid use of white- and ultra-violet light;
o Implement a dark period, when there is no lighting.
• Design buildings for robustness, recognising and encouraging adequate protection of exposed
elements of the building and landscape, therefore minimising the frequency of replacement and
maximising materials optimisation;
• Enhancement of areas around the buildings for ecological mitigation and enhancement (see
separate section below);
8 BREEAM’s on line resource available at http://www.breeam.org/about.jsp?id=66. Accessed on 30/09/15.
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 42
Principal Design Considerations
• The proper integration, design and maintenance of SUDs throughout, which could include a
combination of: -
o Attenuation features and infiltration devices;
o Swales to store and/or convey runoff and remove pollutants;
o Infiltration basins/ vegetated depressions;
o Modular storage such as soakaways beneath communal parking areas and footpaths;
o Permeable paving for all parking areas and footpaths;
o Other inlets, outlets and control structures, including landscaped pipes, perforated pipes,
weirs, orifices, vortex control devices and spillways.
Green Travel Plan (see Outline Travel Plan, RS Appendix 12.3)
• The provision and compliance with a Green Travel Plan which will have examined all options for
sustainable travel to and from the Site. These might include: -
o Information and promotion of alternative green travel choices;
o Dedicated bus services;
o Minimisation of vehicular movements within the Site, and the incorporation of
pedestrian priority throughout the development (as noted on the Concept Design);
o Provision of electric charging points for electric vehicles including electric motorbikes and
bicycles;
o Safe dedicated priority cycle lanes, and plentiful, safe, sheltered, secure storage for
bicycles in proximity to destination, with supporting facilities such as lockers, changing
and showering;
o Footpaths to provide direct access to the stadium throughout, connect to PROW off site,
and link to local transport and other off-site amenities.
Sustainable Operation
• Life-cycle costing and service life planning in order to improve design, specification and through-
life maintenance and operation;
• Source energy from renewable energy sources, including the provision of on-site renewable
energy production (see above);
• Reduce the consumption of potable water for sanitary use in the stadium from all sources
through the use of water efficient components and water recycling systems, and ensure water
consumption can be monitored and managed. Leak detection systems will also be installed;
• Encourage procurement of energy-efficient equipment;
• Utilise the supply of heat from a system that minimises NOx emissions, and therefore reduces
pollution of the local environment;
• Provision of dedicated operational-related recyclable waste streams, so that this waste is
diverted from landfill or incineration;
• Encourage utilisation and participation in the EMAS (Eco-Management and Audit Scheme), a
voluntary initiative designed to improve companies’ environmental performance. The scheme
recognises organisations that go beyond minimum legal compliance and continuously strive to
improve their environmental performance, with requirement to produce publicly available
statements.
Best Practice Ecological Creation, Management and Enhancement – including integral Green
Infrastructure
• Development of a full Biodiversity Management Plan including avoiding clearance/works at key
times of the year (e.g. breeding seasons)
• Minimisation of the loss of ecological habitats (hedgerows, trees etc.);
• Ecological enhancement of existing habitat;
• Protection and enhancement for bats including bat friendly lighting throughout the Site, and the
creation of bat corridors;
• The creation of species rich parkland grassland using seed of local provenance;
• Planting of new native hedgerow and native trees throughout;
• Creation of linear orchards with local apple, pear and perry pear trees;
• Creation of flower-rich verges from locally sourced seed;
• Enhancement of the Site for invertebrates, particularly butterflies and bees;
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 43
Principal Design Considerations
• Potential creation of new artificial badger sett (with cameras);
• Use of sustainable drainage throughout (see above);
• Creation of new ponds throughout the Site for birds, bats and invertebrates;
• Stock-proof fencing adjacent to A419 and cattle grids on the Site entrances to minimise deer
movement onto A419;
• On-going programme of monitoring and management, which will include conservation
management;
• The adoption of horticultural good practice (e.g. no, or low, use of residual pesticides);
• The installation of insect boxes at appropriate locations;
• Installation of nest boxes for Little Owl, Barn Owl and Swifts, and artificial Sand Martin nesting
towers;
• Installation of bat boxes and other bird nesting boxes on suitable trees throughout;
• Suitable interpretation throughout the Site.
Access
5.10 The principal vehicle access will be from a new traffic signal junction on the A419 east of the M5
Junction 13. The proposed layout for the access junction is shown in RS Figure 12.6 (Drawing
No. E191/04 Rev A). This includes the dualling of the A419 between the M5 J13 and Chipmans
Platt roundabout.
5.11 The provision of the access will result in the loss of the existing laybys on this section of the A419.
However, it has been agreed with Gloucestershire County Council that the laybys can be re-
provided on the A419 to the west of the M5 – on land under the ownership of the Highways
Authority.
5.12 The existing public footpath (Eastington Footpath 37) which crosses the A419 to the east of the
proposed access will be incorporated into a signalised pedestrian crossing, as part of the
signalised Site access, as indicated in RS Figure 12.6.
5.13 The proposed improvements also include a footway on the south side of the A419 from the
proposed Site access to Chipmans Platt, providing a link to Stonehouse, and on to Stroud via the
canal towpath.
5.14 A second vehicular access for buses/ coaches and emergency vehicles only is proposed from
Grove Lane, as indicated on the Concept Plan (RS Figure 1.1). This entrance will be gated when
not in use. It will enable buses serving the west of Stonehouse development to divert through
the Site on match days, without joining the main flow of traffic entering via the main entrance.
Coach parking will be provided on site for away coaches. Bus shelters will be provided within the
Site as required.
5.15 A pedestrian and cycle access will be provided adjacent to the bus access from Grove Lane, and
will be kept open to allow continued use of Eastington Footpath 38 as well as access to the
Stadium from the West of Stonehouse development. A footway will be continued along Grove
Lane to connect with the West of Stonehouse proposals. Crossing points will be located to the
north of the proposed entrance on Grove Lane, and at Nupend.
5.16 Within the Site, the area around the Stadium will be vehicle free during matches, as indicated on
the Concept Plan (RS Figure 1.1).
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 44
5.17 Following discussions with Gloucestershire County Council regarding the Revised Scheme, a total
of 1,700 parking spaces are included to cater for the 5,000 capacity Stadium. Electric vehicle
charging points will be provided within the parking area.
5.18 Up to 100 cycle parking spaces will be available initially, with scope to increase this number if
demand requires.
Parameter Plans
5.19 RS Figures 5.1 to 5.3 provide details of the elements in Table 5.1 for which outline planning
permission is sought. Specifically, RS Figure 5.1 Building Height Parameter Plan takes into
account the varying needs of the surrounding local environment and has been largely governed
by the assessments undertaken from both the cultural heritage and landscape and visual
chapters of the EIA submitted with the application.
5.20 With regards to the Revised Scheme, the RS Figure 5.1 indicates that the maximum height of any
built development in the area will be up to 19.5m. This is largely a result of the scale of the
stadium, although given that the application is currently in outline form, the actual location is
not yet finalised. However, within the ES, the assessments have been undertaken based on RS
Figure 1.1 Indicative Concept Plan, and the parameters set within RS Figure 5.1.
5.21 RS Figure 5.2 Land Use Parameter Plan illustrates the information presented in Table 5.1, whilst
RS Figure 5.3 Indicative Green Infrastructure Parameter Plan illustrates the proposed Green
Infrastructure strategy for the Site. Further details are also provided in RS Appendix 8.5.
Indicative cross sections of the Site are provided in RS Figure 5.5.
Construction
5.22 The planning application is in outline form with all matters reserved save for access. The
necessary access works for the Revised Scheme as discussed at the beginning of this chapter are
being applied for in full. As such, the future development of the Site will be dependent on
subsequent Reserved Matters Applications. It is anticipated that should planning permission be
granted, Reserved Matters Applications would be submitted within two years and construction
starting within a year following approval. For the purpose of the ES the following sequence has
been assumed.
• Phase A: Highways improvements.
• Phase B: Stadium, outdoor training pitches, landscape works
Pre-construction Phase
5.23 Prior to the main construction contract commencing, a number of enabling works will be
undertaken, including geotechnical investigations of the Site, sufficient to facilitate the
development of detailed designs, and the production of a detailed Construction Environmental
Management Plan. There are further details in relation to construction that will require pre-
construction work, and these are outlined within the Technical Chapters 7-17 as they are
considered important mitigation for reducing the residual effect of the Revised Scheme.
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 45
Construction Phase
5.24 A series of assumptions have been made to the construction proposals including the following:
• Anticipated construction activities;
• Haulage routes;
• Construction traffic timings and frequency;
• Traffic management requirements (including the sourcing of local construction materials);
• Construction compound location;
• Temporary drainage solution;
• Foundation solutions;
• Site working hours and days;
• Construction employment (including the sourcing of local labour);
• Site Management Plan;
• Trees within the Redline Boundary.
Anticipated construction activities
5.25 The following provides an outline timetable of the expected aspects of construction and when
they will be completed in relation to the Revised Scheme.
Table 5.3 Anticipated Construction Activities
Sequence Activities
1 - Site activities; site set up fencing and gates; site compound set up; start on site; dualling
to commence.
- Plant anticipated; minimal plant anticipated.
2 - Substructure; Site Strip; Top soil strip and store; Drainage Works; Form site
infrastructure, roads and services; Piling / Vibro compaction Operations; Excavate,
Concrete Bases / footings; Services Ducts and drainage.
- Plant anticipated; Large Rotary Bored Piling Rig; Dumpers, Earth Moving Plant;
Compressor Generators; Tracked Excavators; Dozer; Dump Truck; Tracked Mobile Crane;
Water Pump.
3 - Superstructure works; Structural Steel installation; In situ concrete; Roof/ Wall Cladding;
Brick / Block walling; Rainwater Goods; Internal Services installation; Secondary
Steelwork; PCC Installation and Barriers; Spectator Seating; Roof Sheeting / Cladding;
Internal Walls; Windows / Curtain Walling / Doors; Rainwater goods / Signage; dualling
anticipated to be completed.
- Plant anticipated; Tracked Mobile Crane; Dumpers, Earth Moving Plant; Compressor
Generators; Cement Mixers; Concrete Mixer Truck; Lifting Platforms; Mobile Telescopic
Crane.
4 - Superstructure works; Structural Steel installation; In situ concrete; Roof/ Wall Cladding;
Brick / Block walling; Rainwater Goods; Internal Services installation; Secondary
Steelwork; PCC Installation and Barriers; Spectator Seating; Roof Sheeting / Cladding; -
the main super structure is proposed to be in Glue – laminated timber. There will be
minimal steel at the superstructure level probably in terms of secondary steel work and
joints. The roof is stretched fabric. Minimal block work. Currently no brickwork
anticipated. Internal Walls; Windows / Curtain Walling / Doors; Rainwater goods /
Signage. Plant anticipated; Lifting Platforms; Mobile Telescopic Crane; Compressor
Generators.
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 46
Sequence Activities
5 - External works; Drainage; Service Trenches; Car Parks and Access Roads; Landscaping.
External fittings & fixtures in terms of bollards / lights.
- Plant anticipated; Dumpers Earth Moving Plant; Tracked Excavators; Compressor
Generators; Tarmac Machinery.
5.26 Indicative construction activities are anticipated to be as per Table 5.3. Final timescales and
construction activities are likely to be agreed pending Reserved Matters Applications.
Haulage routes
5.27 The majority of construction traffic is expected to be routed via the A419, M5 and A38 to the
west of the Site, identified for HGV traffic on the Gloucestershire Advisory Freight Route Map
(See Appendix O within the TA which forms RS Appendix 12.1 of this ES).
Construction traffic timings and frequency
5.28 The selection of construction vehicles and the numbers of vehicular trips which are required will
depend on the size and number of vehicles operated by the contractor. Appropriate controls will
be implemented to ensure the safety of other road users and to protect the environment.
5.29 When considering possible size restrictions for vehicles which would be in daily use, the key
vehicles would be the tipper trucks used for moving materials arising from preparation of the
Site and, in the later stages of construction, the delivery of bulky items by articulated lorry.
Specialised items such as low-loaders to deliver construction plant and other machinery would
need to be considered on an individual basis and would be dependent on both the form of
construction to be adopted and the programme.
5.30 It has been assumed that the majority of construction deliveries and collections to the Site will
occur outside the prevailing traffic peak periods on a weekday and weekend. However, for the
purpose of assessing a worst-case scenario, the following traffic flows have been assumed for
peak periods:
• 260 car movements daily (i.e. 130 in, 130 out).
• 100 HGV movements daily (i.e. 50 in, 50 out). This equals 4.5 HGV’s in and out per hour
into the Site assuming an 11-hour day or 1 every 15 minutes.
Traffic management requirements
5.31 Mitigation of the effects of construction will be achieved through controls imposed by planning
conditions, health and safety requirements and good construction site practices. The mitigation
measures to address the transport effects associated with the construction of the Revised
Scheme will be co-ordinated and implemented by means of a Construction Traffic Management
Plan which can be secured by a planning condition. Measures are likely to include:
• Appropriate signing of the delivery route to ensure vehicles use the approved route to and
from the Site
• Warning signs for vehicles and pedestrians as appropriate
• Co-ordination of delivery times to ensure that as far as possible deliveries take place
outside peak periods
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 47
• Layout of site to allow adequate space for goods vehicle manoeuvring and ensure that
vehicles are not required to wait on the public highway
• Temporary traffic management for short periods if delivery of oversized loads may cause
obstruction to the public highway
• Design of the Site access to ensure that vehicles have appropriate visibility upon leaving
the Site
• Wheel washing facilities for vehicles leaving the Site, and road sweeping when necessary
5.32 During construction, particular restrictions in relation to Public Rights of Ways may be required
for pedestrians in the vicinity of the Site in order to ensure their safety. When such restrictions
are needed the correct legal process will be followed as necessary.
5.33 In relation to on-site access, a traffic system will be designed and detailed in a Traffic
Management Plan (within the Construction Environmental Management Plan). It will also detail
the maximum size of vehicles, appropriate routes, and appropriate delivery timings in line with
the text above. Appropriate controls will be implemented to ensure the safety of other road
users and to protect the environment.
5.34 It is anticipated that where required, material will be attempted to be sourced locally. No
material will be moved off site as it will be used as part of the landscape works.
Construction Compound location
5.35 During the construction period, a temporary construction compound will be required. At this
point in time, it is not known exactly where the compound will be located on site given the outline
nature of this application. Prior to construction starting a plan will be provided to the Local
Planning Authority (LPA) as to where the compound will be located for their approval. This can
be secured via a planning condition and the Construction Environmental Management Plan.
However, RS Figure 5.4 Indicative Construction Compound Locations indicates areas of the Site
where a construction compound could be located. This plan has been taken into account within
each of the technical assessments in relation to potential construction effects.
5.36 The compound will be surrounded by hoarding to reduce any potential visual effects and security
lighting will be designed in accordance with a lighting design strategy in conjunction with the
ecologists to ensure suitable bat mitigation is incorporated. It will be in use for the duration of
the works and will require an area of approximately 0.3 ha. This will be confirmed when a plan
of the location of the construction compound is submitted for LPA approval.
5.37 It is anticipated that the compound will comprise of a hardstanding area and will provide space
for:
• Temporary porta cabins/ parking for site offices and welfare facilities for contractors;
• Containers used for tool and equipment storage;
• Storage of construction vehicles when not in use;
• Storage of components and material including fuels, lubricants and oils.
Temporary drainage solution
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 48
5.38 Surface water management during the Site preparation, earthworks and construction phase will
include measures to remove silt, sediment and debris and to attenuate surface water runoff prior
to controlled discharge to the drain network. This is discussed further within both Chapter 8 and
Chapter 9 of the ES. As part of the construction phase, mitigation is proposed to ensure no
significant effect.
Foundation solutions
5.39 For the purposes of the ES it has been assumed that surcharge may be required across the Site.
This is the temporary process by which additional material is added to the Site and existing
moisture levels are reduced. A piling foundation solution has been assumed across the Site within
the area of built development. The piles will be driven to the required depth using conventional
pile driving equipment.
Site working hours and days
5.40 It has been assumed for the purposes of this ES that working hours for site construction activities
will be as follows:
• 07:00 and 18:00hrs Monday to Friday;
• 08:00 and 13:00 on Saturdays;
• Other hours by exception and with the prior agreement of the LPA.
Construction employment
5.41 It is estimated that the Revised Scheme will result in approximately 120 full time equivalent jobs
within the construction sector during a 12-month construction period (see Chapter 11 for further
information). Where possible, labour will be sourced locally.
Site Management Plan
5.42 Detailed Site Management Plans will be prepared as part of the Construction Environmental
Management Plan (CEMP) by the Contractor in advance of construction. Task specific risk
assessment will be carried out for each work activity and detailed method statements prepared
to control the operation and to ensure that all concerned are aware of safety and environmental
hazards associated with the work and the precautions to be taken. These will refer to:
• Details on working boundaries for the work activity;
• Details on the order and method of construction for the work activity with reference to
work procedures;
• The planned measures to reduce the risk identified;
• Information on material being used, plant, labour and any temporary works requirements;
• Site constraints that affect the works activity and how they will be dealt with e.g. pollution
prevention methods, noise, by-pass channels, over pumping etc.;
• The quality requirements for the item of work;
• Focus on protected species: otters, water vole, great crested newt, etc.
• Compliance with all legal frameworks in force at the time.
Trees within Redline Boundary
5.43 An Arboricultural Report has been undertaken as part of the planning application submission,
showing tree locations, canopy sizes and classification with an accompanying tree schedule
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 49
within the Redline Boundary. A Tree Constraints Plan has also been included as part of the
planning submission and this ES (see RS Appendix 8.3).
Post-construction Phase
5.44 All reinstatement works, landscape mitigation and enhancement measures including grass
seeding, native tree planting and shrub planting will be carried out upon completion of
construction. The Principal Contractor will be responsible for the reinstatement works arising
from construction operations.
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 50
6 PLANNING POLICY CONTEXT
Introduction
6.1 Section 38(6) of the Planning and Compulsory Purchase Act 2004 places a requirement upon
Authorities when determining planning applications to do so in accordance with the adopted
Development Plan unless material considerations indicate otherwise.
6.2 The Development Plan relevant to the Site comprises the Stroud District Local Plan9 (adopted
November 2015) and the Eastington Neighbourhood Development Plan 2015-203110 (made in
October 2016). Material considerations include the National Planning Policy Framework (NPPF)11
and the associated National Planning Practice Guidance (PPG)12, as well as the Stroud Local Plan
Review13.
6.3 This chapter considers the planning policies from the Development Plan, along with any material
considerations relevant to the determination of the application, before summarising the
planning balance as set out within the Planning Statement (submitted as part of the suite of
documentation supporting the Revised Scheme). RS Appendix 6.1 provides full details of the
relevant planning policies to the Revised Scheme, whilst RS Appendix 6.2 provides a list of
proposed draft planning conditions for the Revised Scheme.
Development Plan
Stroud District Local Plan
6.4 The Local Plan relates to the whole District and provides a strategy for delivering growth for
Stroud District up to 2031. The document provides the vision, objectives and strategic policies
for delivering new homes, jobs, services, facilities and infrastructure. Section 1 of RS Appendix
6.1 provides the policies of the Local Plan considered most relevant to the determination of the
Revised Scheme.
Eastington Neighbourhood Development Plan
6.5 The Neighbourhood Plan has been designed to closely follow and be in conformity with the
Stroud District Local Plan. The settlement boundaries in the Neighbourhood Plan are closely
aligned to those defined in the Local Plan. These reflect the strategic growth options in the Local
Plan. Section 2 of RS Appendix 6.1 provides the policies of the Neighbourhood Plan considered
most relevant to the determination of the Revised Scheme.
9 The Stroud District Local Plan available from https://www.stroud.gov.uk/media/1455/stroud-district-local-
plan_november-2015_low-res_for-web.pdf accessed on 27th November 2017. 10 Eastington Neighbourhood Development Plan available from http://eastington-pc.gov.uk/wp-
content/uploads/2016/08/Eastington-NDP-Adopted-Version-Oct-2016.pdf accessed on 27th November 2017. 11 National Planning Policy Framework (2012) available from
http://www.stroud.gov.uk/info/plan_strat/newlocalplan/PLAIN_TEXT_Local%20Plan_Adopted_November_2015.pd
f accessed on 12th December 2015. 12 Planning Practice Guidance (2014) available from http://planningguidance.communities.gov.uk/blog/guidance/
accessed on 12th December 2015. 13 Stroud Local Plan Review available from https://www.stroud.gov.uk/environment/planning-and-building-
control/planning-strategy/stroud-district-local-plan-review accessed on 27th November 2017.
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 51
Planning policy documents that comprise ‘material considerations’
National Planning Policy Framework (NPPF)
6.6 The NPPF sets out Government planning policies for England and how these are expected to be
applied. Paragraph 14 of the NPPF states that the purpose of the planning system is to contribute
to the achievement of sustainable development and that a presumption in favour of sustainable
development is at the heart of the NPPF. For decision taking this means:
• Approving development proposals that accord with the development plan without delay;
and
• Where the development plan is absent, silent or relevant policies are out of date, grant
planning permission unless:
o Any adverse effects of doing so would be significant and demonstrably outweigh
the benefits, when assessed against the policies in the framework as a whole; or
o Specific policies in the framework indicate development should be restricted.
6.7 Furthermore, Paragraph 7 of the NPPF sets out the three dimensions to sustainable
development; economic, social and environmental. With regards to the economic dimension it
states that the planning system is required to ‘contribute to building a strong, responsive and
competitive economy, by ensuring that sufficient land of the right type is available in the right
places at the right time to support growth and innovation’.
6.8 It is considered that the Revised Scheme will meet the dimensions of sustainable development
as set out by the NPPF. Section 3 of RS Appendix 6.1 provides a summary of the sections and
paragraphs considered most relevant to the determination of the Revised Scheme.
National Planning Practice Guidance (PPG)
6.9 PPG acknowledges that open space, which includes all open space of public value, can take many
forms, from formal sports pitches to open areas within a development, linear corridors and
country parks. It can provide health and recreation benefits to people living and working nearby;
have an ecological value and contribute to green infrastructure, as well as being an important
part of the landscape and setting of built development, and an important component in the
achievement of sustainable development (Paragraph: 001 Reference ID: 37-001-20140306).
Stroud Local Plan Review
6.10 The District Council is now starting the process of reviewing the current Stroud District Local Plan.
The first stage is the Issues and Options, which is currently going through consultation. Given
the early stage of the review, very limited weight can be given to the Issues and Options at this
stage; however, it indicates possible directions of travel for the Local Plan.
6.11 The site, as well as land to the south of the A419, has been identified as a potential ‘broad
location for future growth’ (reference STO D) for employment, open space and community
uses.
Planning Balance
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 52
6.12 The key policies relating to the principle of development within the adopted Development Plan
are Core Policy 15 and Delivery Policy EI11. There are no policies relating to sports provision
within the Neighbourhood Plan.
6.13 Core Policy CP15 generally seeks to restrict all new developments outside of identified
settlement boundaries. It is considered that the application proposal is consistent with the two
criteria and all other qualifying criteria of the policy. Therefore, whilst the Revised Scheme falls
outside of an identified settlement boundary, it is considered to be consistent with the policy
when read as a whole. The Revised Scheme does not conflict with the purposes of the policy
which is designed at protecting the separate identity of settlements, avoiding coalescence and
ensuring that new development is located sustainably.
6.14 Despite this minor conflict (being outside of a settlement boundary), there is a need for Forest
Green Rovers (FGR) to improve its facilities to enable it to continue to develop. There are no
alternative sites available within the District where this can be achieved; Chapter 4 of this ES,
along with the supporting Planning Statement provide further information over the search for
alternative sites. Policy EI11 supports the provision of sports facilities and it is clear from the
Planning Statement that the proposal is fully compliant with all aspects this policy.
6.15 Overall, the proposals will provide facilities for FGR which will allow the club to continue to
develop, an urgent matter as a result of its promotion into League 2. The existing stadium is
constrained, and the proposals reflect FGR aspirations for long-term, sustainable growth to
provide a hub, combining the new stadium with a range of training facilities for the first team.
The site is in an accessible and sustainable location for both players and fans of FGR and the
proposal is essential for FGR’s continued development. This is a material consideration which
should be given significant weight in the determination of the application.
6.16 It has also considered that the Revised Scheme constitutes sustainable development, providing
net gains across all three dimensions set out within the NPPF. At the heart of the NPPF is a
presumption in favour of sustainable development. For decision-taking this means approving
development proposals that accord with the development plan without delay. Whilst there is
some minor conflict with CP15, the proposal is consistent with the purpose of this policy and is
supported by the Local Plan objectives in general and particularly Policy EI11.
6.17 It is considered that the proposal is consistent with the Development Plan when read as a whole.
Furthermore, the proposal is fully consistent with the NPPF and Sport England’s guidance, and
as such is acceptable in planning policy terms.
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 53
7 ARCHAEOLOGY AND CULTURAL HERITAGE
Summary
7.1 Several phases of survey and assessment have been carried out to fully inform the following
chapter on ‘Archaeology and Cultural Heritage’. This has included historical research, inspection
of the Site and wider landscape, geophysical survey and archaeological trial trenches. This
approach has allowed a proportionate level of information to be collected on the heritage assets
of the Site and its locale, and enabled an informed assessment to be made on any effects that
the development may have. This approach is in accordance with Paragraph 128 of the NPPF14,
regarding levels of information accompanying an application.
7.2 The proposals align with the Council’s Strategic Assessment of Land Availability report15 for area
EAS 007 (which comprises the present Redline Boundary) which states that “land to the north of
the A419 has no significant heritage constraints.”
7.3 No development will take place within the Stroud Industrial Heritage Conservation Area (IHCA),
or in its immediate vicinity. The Revised Scheme will not harm the significance of the IHCA, and
adheres to the Five Priorities and accompanying Management Proposals of the IHCA
Supplementary Planning Document (SPD)16. The only archaeological remains of significance
within the Redline Boundary comprise those of the Roman ‘Whitminster’ villa. The Revised
Scheme has ensured that these remains are removed from the areas of built development, and
that no built development is near them. It has been agreed in consultation with the
Gloucestershire County Council (GCC) archaeology officer that mitigation works may suitably
form a condition of any planning application.
7.4 The Revised Scheme will not lead to any significant harm to any other designated heritage assets
through changes to their setting. A very small degree of harm (the lower end of ‘less than
substantial harm’) would be occasioned to the heritage significance of the Grade II listed
Westend Farmhouse and Mulgrove, both on Grove Lane. No other designated heritage assets
will be harmed.
7.5 It is concluded that the Revised Scheme will lead to no significant heritage harm in
Environmental Impact Assessment (EIA) terms.
Introduction
7.6 This chapter of the Environmental Statement considers the likely significant effects of the
Revised Scheme on heritage assets. The chapter describes the assessment methodology; the
baseline conditions within the Site and its environs; the likely significant environmental effects
upon identified and potential heritage assets; the mitigation measures required to prevent,
reduce, or offset any significant adverse effects; potential enhancement measures; and the likely
residual effects after these measures have been employed.
7.7 The chapter assesses both potential physical effects and non-physical effects upon heritage
assets.
14 Department for Communities and Local Government (2012) National Planning Policy Framework 15 Stroud District Council 2017 Strategic Assessment of Land Availibility 16 Stroud District Council 2008 The Industrial Heritage Conservation Area Management Proposals
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 54
7.8 The chapter is informed by a range of archaeological and heritage work which is held in the
following Technical Appendices: -
• RS Appendix 7.1: Heritage Assessment
• RS Appendix 7.2: Geophysical Survey
• RS Appendix 7.3: Evaluation Trial Trenches
• RS Appendix 7.4: Written Schemes of Investigation
• RS Appendix 7.5: Key Consultation Responses (from original application)
7.9 The survey work has been designed to fulfil the requirements set out in Paragraph 128 of the
National Planning Policy Framework (the NPPF), which states that “In determining applications,
local planning authorities should require an applicant to describe the significance of any heritage
assets affected, including any contribution made by their setting. The level of detail should be
proportionate to the assets’ importance and no more than is sufficient to understand the
potential impact of the proposal on their significance”.
7.10 This chapter addresses an area of land defined on RS Figures 7.1 and 7.2 and referred to as the
‘Redline Boundary’. This includes land which will be developed, and land which will not (as
described in Chapters 3 and 5). The land to the north of the A419 where development will take
place is referred to as the ‘Development Footprint’. Assessment work has specifically addressed
this proposal. Reference is also made to the original application and development proposal that
was made in January 2016, referred to as the ‘original application’. These include advice from
the Gloucestershire County Council (GCC) archaeology officer; the Stroud District Council (SDC)
Conservation Officer; and Historic England. Key communications from these consultees are
provided in RS Appendix 7.5 for convenience.
Legislation, Policy and Guidance
Heritage Statute
7.11 This chapter has been prepared within the following key heritage statutes: -
• Ancient Monuments and Archaeological Areas Act 197917;
• Planning (Listed Buildings and Conservation Areas) Act 199018;
• National Heritage Act 198319.
7.12 The Ancient Monuments and Archaeological Areas Act 1979 pertains to the protection of
Scheduled Monuments. It refers explicitly to the monument itself, and does not, for example,
refer to the ‘setting’ of Scheduled Monuments.
7.13 Section 66(1) of the Planning (Listed Buildings and Conservation Areas) Act 1990 notes (regarding
Listed Buildings) that a decision maker “shall have special regard to the desirability of preserving
the building or its setting or any features of special architectural or historic interest which it
possesses”.
17 Ancient Monuments and Archaeological Areas Act, 1979 18 Planning (Listed Buildings and Conservation Areas) Act, 1990 19 National Heritage Act, 1983
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 55
7.14 Section 72 of the same Act notes that “with respect to any building or other land in a conservation
area…(2), special attention shall be paid to the desirability of preserving or enhancing the
character or appearance of that area”. It should be noted that this requirement of the Act refers
explicitly to buildings or land ‘in’ a Conservation Area, not outside.
National Heritage Policy
7.15 Regarding National heritage policy this chapter has been compiled within the context of the
NPPF. Relevant policies regarding heritage are set out in Paragraphs 126 – 141 of the NPPF.
7.16 The NPPF defines heritage assets as “a building, monument, site, place, area or landscape
identified as having a degree of significance meriting consideration in planning decisions, because
of its heritage interest. Heritage asset includes designated heritage assets and assets identified
by the local planning authority (including local listing)”.
7.17 Designated heritage assets comprise World Heritage Sites, Scheduled Monuments, Listed
Buildings, Protected Wreck Sites, Registered Parks and Gardens, Registered Battlefields, and
Conservation Areas. Within this category, the NPPF (Paragraph 132) identifies designated
heritage assets ‘of the highest significance’, which comprise Scheduled Monuments, Protected
Wreck Sites, Battlefields, Grade I and II* Listed Buildings, Grade I and II* Registered Parks and
Gardens, and World Heritage Sites. Non-designated heritage assets comprise all other heritage
assets which have a degree of significance meriting consideration in planning decisions.
Development Plan Policy
7.18 The Development Plan for the district comprises the Stroud District Local Plan November 201520.
The Local Plan sets out the Council’s policies for the historic environment. Policy ES10 references
‘Valuing our Historic Environment and Assets’.
7.19 Part 1 of the Policy essentially addresses the requirement of Paragraph 128 of the NPPF (see
above), and requires the significance of heritage assets affected to be described, as well as the
impact of the development. This may include desk-assessment, field evaluation, and should
utilise the Historic Environment Record. These provisions have been addressed in the present
application.
7.20 Part 2 of the Policy notes that “Proposals and initiatives will be supported which conserve and,
where appropriate, enhance the heritage significance and setting of the District’s heritage
assets”. Parts 3 and 4 similarly note that proposals which preserve/ enhance local heritage assets,
and key views, will be supported. Part 5 notes that “any harm or loss would require clear and
convincing justification to the relevant decision-maker as to why the heritage interest should be
overridden.” This requirement is aligned, broadly, to Paragraph 134 of the NPPF which states that
harm which is less than substantial “should be weighed against the public benefits of the
proposal”.
Assessment Methodology and Significance Criteria
7.21 The detailed methodologies of the different elements of heritage work are set out in the relevant
RS appendices. A brief summary of the key elements is provided here.
20 Stroud District Council 2015 Stroud District Local Plan
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 56
7.22 The EIA heritage work has been carried out by Cotswold Archaeology, a Registered Organisation
with the Chartered Institute for Archaeologists (CIfA). The work has been managed for Cotswold
Archaeology by Richard Morton, Principal Heritage Consultant, and a Member of CIfA. Mr
Morton is highly experienced in managing and carrying out EIA heritage assessment both in
Gloucestershire and across the country, with particular expertise in archaeological remains,
historic buildings and the historic landscape. He has been a professional archaeologist and
heritage consultant for 26 years.
Consultation
7.23 A consultation response for the Revised Scheme has been provided by the archaeological officer
at Gloucestershire County Council (provided in RS Appendix 7.5, dated 26 October 2017). In
summary, the officer has confirmed that “there would be no objection in principle to development
affecting those remains, with the proviso that a programme of archaeological investigation and
recording is undertaken, secured as a condition of any planning permission granted for this
scheme.” An appropriate programme of mitigation is set out in this chapter (‘Mitigation and
Enhancement Measures’, below). An appropriate draft Planning Condition has also been
provided at RS Appendix 6.2.
7.24 Historic England and the Council’s Conservation Officer provided consultation responses with
regard to the previous scheme (key ones of which are provided in RS Appendix 7.5).
Heritage Assessment: (RS Appendix 7.1)
7.25 The heritage assessment is informed by all of the heritage and archaeological works undertaken.
It includes detailed desk-based assessment, carried out in accordance with the Standard and
Guidance for Historic Environment Desk-Based Assessment provided by the Chartered Institute
for Archaeologists21. The documentary research included the key sources set out in Table 7.1
below.
Table 7.1: Heritage Assessment Data Sources
Source Data
Gloucestershire Historic
Environment Record
- Heritage sites and events records, Historic Landscape
Characterisation (HLC) data, and other spatial data supplied in
digital format (shapefiles) and hardcopy.
Historic England Archives - Additional sites and events records, supplied in digital and hardcopy
formats.
Gloucestershire Records
Office
- Historic mapping, historic documentation, and relevant published
and grey literature.
Historic England’s Aerial
Photograph Research Unit
- Vertical and oblique aerial photography ranging in date from the
1940s to present.
A History of the County of
Gloucester, Volume 10
- The Victoria County History (Westbury and Whitstone Hundreds)
Stroud District Council - The Industrial Heritage Conservation Area: Conservation Area
Statement, Part 1: Conservation Area Appraisal
- The Industrial Heritage Conservation Area Management Proposals:
Supplementary Planning Document
21 Chartered Institute for Archaeologists 2014 Standard and Guidance for Historic Environment Desk-Based
Assessment
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 57
Source Data
LiDAR data - LiDAR imagery and point cloud data, available from the Environment
Agency website.
British Geological Survey
data
- UK geological mapping (bedrock & superficial deposits) & borehole
data.
Cranfield University’s LandIS
Soil Portal
- UK soil mapping.
7.26 The heritage assessment assessed the contribution that the Redline Boundary makes to heritage
assets beyond its boundaries, and any effects that the development may have on their
significance.
7.27 ‘Setting’ is not a heritage asset: it may, however, contribute to the value of a heritage asset. The
‘setting’ of a heritage asset is defined by the NPPF as “the surroundings in which a heritage asset
is experienced. Its extent is not fixed and may change as the asset and its surroundings evolve.
Elements of a setting may make a positive or negative contribution to the significance of an asset,
may affect the ability to appreciate that significance or may be neutral.”
7.28 Guidance on assessing the effects of change upon setting and significance is provided in the
Historic England publication ‘The Setting of Heritage Assets: Historic Environment Good Practice
Advice in Planning: 3’22 (hereon referred to as GPA3), which was used in the heritage assessment.
The landscape around the Redline Boundary was examined in the field, and a photographic
record and written notes taken.
Study Area
7.29 The heritage assessment was informed by a suitable ‘Study Area’. With regard to ‘archaeological
remains’ the above sources were examined for both the Redline Boundary itself, and also land
beyond to provide context. A fixed ‘Study Area’ was not used. Rather, appropriate context was
examined for different elements of the historic environment. The CIfA Standard and Guidance
does not stipulate a particular size of ‘Study Area’ that should be utilised: rather, the ‘significance
and character’ of the Study Area should be examined, to inform the nature of potential change.
Data from sources including the Historic Environment Record and Historic England Archives was
gathered for at least a 1km area around the Redline Boundary.
7.30 It is with regard to potential non-physical effects of development that a ‘Study Area’ is of
particular relevance. The appropriate guidance on this is provided in ‘GPA3. GPA3 does not
advise a particular size of ‘Study Area’ that should be utilised. Rather, heritage assets which may
be affected by development should be identified (as part of Step 1) and their settings, and
potential development effects, assessed accordingly. This has been carried out in the RS
Appendix 7.1 Heritage Assessment. All designated heritage assets within 2km distance of the
Redline Boundary were assessed in order to identify if their significance might be affected by
development.
Geophysical Survey (RS Appendix 7.2)
22 Historic England 2015 The Setting of Heritage Assets: Historic Environment Good Practice Advice in Planning 3
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 58
7.31 The geophysical survey was carried out with a Bartington Grad 601-2 instrument. This is a high-
resolution fluxgate gradiometer, used for measuring small variations in the magnetic field caused
by hidden features underground. Traverse Intervals of 1m and Sample Intervals of 0.25m were
used. Data processing was carried out using GeoSuB software, with Zero Mean Traverse step
correction and interpolation. These are industry-standard methods of processing the raw survey
data, to allow interpretation of potential archaeological features. The survey was carried out by
Sumo GSB Prospection Ltd., a specialist geophysical surveyor. The survey was carried out 24-28
August and 28-29 September 2015.
7.32 The survey was carried out in accordance with the Historic England guidance ‘Geophysical Survey
in Archaeological Field Evaluation’23.
Evaluation Trial Trenches (RS Appendix 7.3)
7.33 The archaeological evaluation comprised the excavation of some 82 trial trenches, each
measuring 1.8m in width and 50m in length. The evaluation was carried out in accordance with
a Written Scheme of Investigation (RS Appendix 7.4) approved by the archaeology officer at GCC.
The evaluation was carried out in accordance with the ‘Standard and Guidance: Archaeological
Field Evaluation’ issued by the Chartered Institute for Archaeologists24.
Heritage Asset Significance (EIA Sensitivity of Receptor)
7.34 Significance (for heritage policy) is defined in the NPPF (Annex 2) as “the value of a heritage asset
to this and future generations because of its heritage interest. That interest may be
archaeological, architectural, artistic or historic. Significance derives not only from a heritage
asset’s physical presence, but also from its setting”.
7.35 The NPPF identifies designated heritage assets ‘of the highest significance’, namely Scheduled
Monuments, Protected Wreck Sites, Battlefields, Grade I and II* Listed Buildings, Grade I and II*
Registered Parks and Gardens, and World Heritage Sites.
7.36 Current national guidance for the assessment of the significance of heritage assets is based on
criteria provided by Historic England (formerly English Heritage) in ‘Conservation Principles,
Policies and Guidance for the Sustainable Management of the Historic Environment’25.
Significance is weighed by consideration of four forms of value: historic; evidential; aesthetic;
and communal.
7.37 Table 7.2 below sets out the criteria for assessing heritage asset significance. This table is guided
by the criteria included in HA 208/07. The NPPF also identifies designated heritage assets of ‘the
highest significance’, notably Scheduled Monuments, Registered Battlefields, Grade I and II*
Listed Buildings, Grade I and II* Registered Parks and Gardens and World Heritage Sites.
Table 7.2: Heritage Asset Significance
Heritage Asset Value
Description
23 Historic England 2008 Geophysical Survey in Archaeological Field Evaluation 24 Chartered Institute for Archaeologists 2014 Standard and Guidance: Archaeological Field Evaluation 25 English Heritage 2008 Conservation Principles Policies and Guidance for the Sustainable Management of the Historic
Environment
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 59
High
Designated heritage assets of ‘the highest significance’ as described
in NPPF Paragraph 132. Includes Scheduled Monuments, Protected
Wreck Sites, Battlefields, Grade I and II* Listed Buildings, Grade I
and II* Registered Parks and Gardens, and World Heritage Sites.
Also, non-designated heritage assets of demonstrably equivalent
significance
Medium
Designated heritage assets not defined by the NPPF as ‘of the
highest significance’. Includes Grade II Listed Buildings and
Conservation Areas
Also, non-designated heritage assets of demonstrably equivalent
significance
Low
Non-designated heritage assets
Negligible
Elements of the historic environment that have insufficient
heritage value to comprise ‘heritage assets’
The scale of harm or benefit (EIA magnitude of effect)
7.38 The heritage works undertaken in support of this chapter have looked closely at the particular
values of heritage assets, and in particular the concept of ‘what matters and why’ set out in GPA3.
The magnitude of effect of development upon designated heritage assets is expressed with
reference to heritage planning policy, and ‘harm’ and ‘benefit’, set out in the NPPF, as
summarised in Table 7.3 below.
Table 7.3: Assessment of Magnitude of Effect on Designated Heritage Assets
Heritage
Magnitude of
Effect
Description
Note regarding statute and policy
Benefit The proposals would better
enhance or reveal the heritage
significance of the designated
heritage asset.
Enhancing or better revealing the significance of a
designated heritage asset is a desirable
development outcome in respect of heritage. It is
consistent with key policy and guidance, including
the NPPF (2012) Paragraphs 126 and 137
No effect The proposals would preserve
the significance of the
designated heritage asset
Preserving a Listed Building and its setting is
consistent with s66 of the Planning (Listed
Buildings and Conservation Areas) Act (1990).
Preserving or enhancing the character or
appearance of a Conservation Area is consistent
with s72 of the Act.
Sustaining the significance of a designated
heritage asset is consistent with Paragraph 126 of
the NPPF, and should be at the core of any material
local planning policies in respect of heritage.
Less than
substantial
The proposals would be
anticipated to result in a
restricted level of harm to the
In determining an application, this level of harm
should be weighed against the public benefits of
the proposals, as per Paragraph 134 of the NPPF
(2012).
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 60
Heritage
Magnitude of
Effect
Description
Note regarding statute and policy
harm – lower
half
significance of the designated
heritage asset, such that the
asset’s contributing heritage
values would be largely
preserved
Proposals involving change to a Listed Building or
its setting, or any features of special architectural
or historic interest which it possesses, or change
to the character or appearance of Conservation
Areas, must also be considered within the
context of Sections 7, 66(1) and 72(2) of the 1990
Act. The provisions of the Act do not apply to the
setting of Conservation Areas.
Proposals with the potential to physically affect a
Scheduled Monument (including the ground
beneath that monument) will be subject to the
provisions of the Ancient Monuments and
Archaeological Areas Act (1979); these provisions
do not apply to proposals involving changes to the
setting of Scheduled Monuments.
Less than
substantial
harm – upper
half
The proposals would lead to a
notable level of harm to the
significance of the designated
heritage asset. A reduced, but
appreciable, degree of its
heritage significance would
remain
Substantial
harm
The effect is so serious that the
significance of the heritage
asset is removed altogether or
very much reduced
Paragraphs 132 and 133 of the NPPF (2012) would
apply. Sections 7, 66(1) and 72(2) of the Planning
Act (1990), and the Ancient Monuments and
Archaeological Areas Act (1979), may also apply
7.39 The NPPF (Paragraph 135) requires the magnitude of effect of an application on a non-
designated heritage asset to be defined as ‘the scale of any harm or loss’.
7.40 Combining the magnitude of effect on the heritage significance of the heritage asset provides
the significance of effect of development.
7.41 The NPPF (Paragraph 132) identifies ‘substantial harm’ as a key consideration in the effects of
development, and it is clear that effects leading to this level of harm are ‘significant’. Effects of
less than substantial harm may also be ‘significant’ if they lead to a notable level of harm, such
as would impair future appreciation or understanding of a heritage asset. Thus, for the purposes
of this ES, effects which lead to ‘substantial harm’ or ‘the upper half of less than substantial harm’
are considered EIA ‘significant effects’.
7.42 The NPPF (Paragraph 135) requires the effect of an application on a non-designated heritage
asset to be considered and expressed in terms of:
• The scale of any harm or loss (EIA magnitude of effect)
• The significance of the heritage asset (EIA sensitivity of the receptor)
Baseline Conditions
Designated heritage assets
7.43 Designated heritage assets assessed as part of the heritage works are summarised in Table 7.4
below, and illustrated on RS Figure 7.1.
Table 7.4: Designated heritage assets
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 61
Reference Heritage asset Designation Heritage
Significance
D1 Stroud Industrial Heritage
Conservation Area
Conservation Area Medium
D2 Grove Farmhouse Grade II listed Medium
D3 Westend Farmhouse Grade II listed Medium
D4 Mulgrove Grade II listed Medium
D5 Milestone Grade II listed Medium
D6 Nupend Court Grade II listed Medium
D7 The Nestings and Sundial Grade II listed Medium
D8 Rose Tree Cottage Grade II listed Medium
D9 Nupend House Grade II listed Medium
D10 Oldbury House Grade II listed Medium
D11 Nastend House and barn Grade II* listed
(house)
Grade II listed (barn)
High and Medium
D12 Somerlea Grade II listed Medium
D13 Nastend Green Farmhouse and
stables and barn
Grade II listed Medium
D14 Nastend Farmhouse Grade II listed Medium
D15 Oldend Farmhouse Grade II listed Medium
D16 Blunder Lock, Spill Weir and
Boundary Markers
Grade II listed Medium
D17 Newtown Lock, Spill Weir And
Boundary Markers
Grade II listed Medium
D18 The Gatehouse at Bonds Mill Grade II listed Medium
D19 Little Court and The Coach House,
including coach house and cart
shed
Grade II listed Medium
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 62
Reference Heritage asset Designation Heritage
Significance
D20 Splash Cottage; mill workshops;
Leonard Stanley House; and
associated stable and cartsheds
Grade II listed Medium
D21 Eastington Park, and stables and
coach house
Grade II listed Medium
D22 3, 4 and 5 Churchend Grade II listed Medium
D23 Weir between the River Frome
and the Kemmett Canal
Grade II listed Medium
D24 Church of St Michael and All
Angels
Grade II* and Grade
II listed churchyard
monuments
High and Medium
D25 Elm Beams And Manor Cottage Grade II listed Medium
D26 Millend Mill Grade II listed Medium
D27 Brookhill House and Meadow
Cottage
Grade II listed Medium
D28 Eastington House and stable Grade II listed Medium
D29 Springhill Cottages Grade II listed Medium
D30 Former Stable And Coach House
To Springhill House
Grade II listed Medium
D31 Alkerton Farmhouse and barn Grade II* and Grade
II listed barn
High and Medium
D32 The Kings Head Grade II listed Medium
D33 Alkerton Cross House Including
Front And Rear Walls And
Outbuilding To Rear
Grade II listed Medium
D34 Direction Post Grade II listed Medium
D35 Green Farmhouse Grade II listed Medium
D36 1 2 And The Cross Grade II listed Medium
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 63
Reference Heritage asset Designation Heritage
Significance
D37 Alkerton Grange Grade II and Grade
II* listed
summerhouse
High and Medium
D38 Alkerton Court and barn Grade II listed Medium
D39 Claypits Farmhouse Grade II listed Medium
D40 Milestone Grade II listed Medium
D41 The Hawthornes Grade II listed Medium
D42 Nethermills Farmhouse Grade II listed Medium
D43 Fromebridge Mill Grade II listed Medium
D44 Millowner's House, Also Known
As Fromebridge Mill
Grade II listed Medium
D45 Nastfield Farmhouse Grade II listed Medium
D46 Milestone Grade II listed Medium
D47 The Old Forge Grade II listed Medium
D48 Parklands Grade II listed Medium
D49 Parkland Farmhouse Grade II listed Medium
D50 Yew Tree Cottage (North End) Grade II listed Medium
D51 Oak Cottage Grade II listed Medium
D52 Jaxons Farmhouse Grade II listed Medium
D53 King's Orchard Grade II listed Medium
D54 Manor Farmhouse Grade II listed Medium
The Stroud Industrial Heritage Conservation Area (D1)
7.44 The southernmost part of the Redline Boundary lies within the Stroud Industrial Heritage
Conservation Area (IHCA). No development will take part within the Conservation Area, as the
Development Footprint lies entirely to the north of the A419.
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 64
7.45 The IHCA (No. 29) was designated by Stroud District Council in September 1987. The IHCA has
been extended in several places since that date, including at Eastington in January 1989. In
November 2008 a Conservation Area Statement for the IHCA was adopted by the Council.
7.46 The IHCA divides the Conservation Area into numerous ‘Character Parts’. The southernmost part
of the main Site area lies within the IHCA, within Character Part 4.4 ‘Fromebridge to Chipman’s
Plat’. A small part of the south-eastern corner of the Redline Boundary also lies within Character
Part 1.2 ‘Newtown and Chipman’s Plat’. Character Part 7.1 ‘Meadow Mill, Eastington’ lies
immediately adjacent to the southernmost part of the Redline Boundary. The smaller part of the
Redline Boundary on the western side of the M5 lies wholly within the IHCA, within Character
Part 4.4 ‘Fromebridge to Chipman’s Plat’.
Listed Buildings
7.47 A total of 77 Listed buildings have been considered as part of step 1 of the settings assessment.
These comprise:
• Three Grade II* Listed Buildings (designated heritage assets of ‘the highest significance’)
• Seventy-four Grade II Listed Buildings (designated heritage assets not of ‘the highest
significance’)
7.48 The locations of the Listed Buildings are illustrated on RS Figure 7.1, and comprise D2 – D54 in
Table 7.4 above. Several of the ‘D’ references include more than one Listed Building (for example
churches, with associated listed tomb chests). Reference D1 is the IHCA, which has been
discussed above.
Non-designated heritage assets
7.49 The phased archaeological works carried out within the Redline Boundary have characterised the
archaeological resource in detail. Non-designated heritage assets are summarised on RS Figure
7.2, and itemised in Table 7. 5 below.
Table 7.5: Non-designated heritage assets
Heritage asset Description Heritage Significance
Whitminster Roman
villa
The below-ground remains of a Roman villa. Not
of the highest quality and significance, but may
contribute to the understanding of the Roman
period in the region
Medium to High
Roman field system Boundary ditches of the field system of the villa Low
Ridge and furrow
earthworks
Eroded ridge and furrow earthworks of medieval
date
Low
‘Important’
hedgerows
Hedgerows which qualify as ‘important’
hedgerows under the criteria for ‘archaeology
and history’ of the Hedgerow Regulations 1997
Low
7.50 The Cotswold Archaeology evaluation confirmed that the Roman villa (known as the
‘Whitminster Villa’) was occupied between the 2nd to 4th centuries AD, and possibly even in the
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 65
first century. Roman villas are relatively numerous in the Cotswolds, with over 50 probable sites
recorded in Gloucestershire. Stone wall foundations and floor layers with mosaic and opus
signinum were recorded, and also a potential T-shaped kiln, set within a rectangular ditched
enclosure. The remains are not well-preserved, as walls had been subject to later robbing and
there has also been significant plough damage.
7.51 The villa is situated in the area south of the A419 and will not be impacted upon by the
Development Footprint. The GCC archaeology officer confirmed in his consultation advice that
the villa “is not of the highest quality and significance”, but nonetheless may contribute to the
understanding of the Roman period in the region.
7.52 Boundary ditches of the associated Roman field system were also recorded, largely, again, to the
south of the road near the villa (see also RS Appendix 7.2). Some evidence was found for these
to also extend into at least part of the Development Footprint to the north of the A419. Such
remains are of sufficient interest to comprise ‘heritage assets’, but of low heritage significance.
7.53 Earthworks of ridge and furrow cultivation survive within parts of the Redline Boundary (RS
Figure 7.2). These comprise heritage assets of low heritage significance.
7.54 The hedgerows that survive in the Redline Boundary (RS Figure 7.2) qualify as ‘important’
hedgerows under the criteria for ‘archaeology and history’ of the Hedgerow Regulations 1997.
The Regulations require appropriate notice to be provided to the Council prior to their removal.
The hedgerows comprise ‘heritage assets’ of low heritage significance, and are situated along
the boundaries of fields created in the post-medieval period. Any below-ground ditches of
removed field boundaries will not comprise heritage assets. There has been significant boundary
loss in the Redline Boundary and adjacent areas, and it is not one of high historic landscape value.
Design Evolution
7.55 Step 4 of GPA3 is directed towards ‘maximising enhancement and minimising harm’. This best-
practice guidance is specifically tailored to effects on the setting of heritage assets, through non-
physical change.
7.56 GPA3 states that” options for reducing the harm arising from development may include the
relocation of a development or its elements, changes to its design, the creation of effective long-
term visual or acoustic screening.” Furthermore,” good design may reduce or remove the harm,
or provide enhancement, and design quality may be the main consideration in determining the
balance of harm and benefit.”
7.57 Following the original submission, a very much smaller scheme is now proposed. No
development will be carried out in the fields to the south of the A419. The following elements
have been removed from the proposals: -
• The Green Technology Hub;
• The sporting facilities south of the A419;
• The leisure facilities south of the A419;
• The indoor training pitch;
• Two outdoor training pitches;
• The proposed Ecotricity B1 building.
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 66
7.58 The design has included measures to minimise any harm to the heritage significance of the listed
buildings on Grove lane, namely; Grove Farmhouse, Westend Farmhouse, and Mulgrove.
Measures include landscape structures such as earthed bunds. The bunds are designed to limit
noise, visual and light intrusion. Where appropriate tiered seating will be incorporated into the
bunds surrounding sports pitches. Gaps through the hedge on Grove Lane are limited, but where
views into the Redline Boundary are possible (such as opposite Mulgrove) the earthed bunds
(which will be grassed) will screen the car parking areas. A landscape buffer area along the
northern boundary with Westend Farmhouse has also been provided, including a provision for
orchard planting (reflecting a former landuse). Soft landscaping measures have also been
proposed, including extensive planting, including ‘parkland’ trees between car park bays. Existing
hedgerows and trees are retained as far as possible. It is also noted that the stadium itself has
been designed with measures such as non-reflective surfaces, and recessive colours and textures.
Potential Effects
Construction Effects
7.59 The assessment of construction effects includes consideration of all groundworks required for
the stadium, pitches, car parking, infrastructure (including drainage/ services) and also the
construction compound, which will be located immediately to the north of the A419 (RS Figure
5.4). Construction effects are summarised in Table 7.7 below.
7.60 The Roman villa, a heritage asset of Medium-High heritage value, will not be impacted upon as
it is outside the Development Footprint.
7.61 As non-designated heritage assets, the low heritage significance of the boundary ditches should
be taken into account in determining the application (in accordance with Paragraph 135 of the
NPPF). The scale of impact is likely to be limited (to the stadium, landscaping for the practice
pitches, and below-ground works such as drainage and services), and the majority of any such
buried ditches would be preserved.
7.62 Eroded earthworks of ridge and furrow cultivation survive within parts of the Redline Boundary
(RS Figure 7.2). Although not within the area of the new stadium, it is likely that the car park
creation and landscaping will require levelling of these earthworks, and surfacing with hard core/
rough stone (for the car-parks). This will comprise removal of a heritage asset of low heritage
significance. Such earthworks are reasonably well-represented in the parish.
7.63 Several post-medieval hedgerows which qualify as ‘important’ under the Hedgerow Regulations
1997 lie within the Redline Boundary, as illustrated on RS Figure 7.2. The hedgerows mark field
boundaries created in the post-medieval period, a form of enclosure very well-represented in
the parish and wider region. They are non-designated heritage assets of low heritage
significance. The hedgerows are retained where possible, although the Revised Scheme will
require the translocation of several of the hedgerows. This represents a very small loss of this
form of heritage asset (see also Chapter 8, Ecology, as well as RS Figure 8.2 and 8.14.
7.64 The hedgerow translocation that is required, and the Revised Scheme itself, will not lead to harm
to an area of historic landscape value. The proposals would not lead to any significant heritage
effects in EIA terms.
Operational Effects
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 67
7.65 A detailed analysis of the potential effects of the Revised Scheme on the setting of heritage assets
(those set out in Table 7.3, above) is provided in the RS Appendix 7.1 heritage assessment.
7.66 The Revised Scheme would not lead to any substantial harm to any designated heritage assets
through changes to their setting. The proposals would not lead to any significant heritage effects
in EIA terms.
7.67 The significance of the Industrial Heritage Conservation Area will not be harmed.
7.68 A very small degree of harm (the lower half of ‘less than substantial harm’) will be occasioned to
the heritage significance of:
• the Grade II listed Westend Farmhouse;
• the Grade II listed Mulgrove.
7.69 This level of harm is not a significant environmental effect in EIA terms.
7.70 No other designated heritage assets will be affected.
Mitigation and Enhancement Measures
7.71 In an email of 26th October 2017 (RS Appendix 7.5), the GCC archaeology officer confirmed that
the mitigation works may suitably form a condition of any planning application, and that “there
would be no objection in principle to development affecting those remains”. It is recommended
that this mitigation would comprise archaeological observation and recording, the detailed
methodology for which should be agreed in a Written Scheme of Investigation to be approved
before construction with the archaeology officer.
Residual Effects
7.72 The NPPF guides (Paragraph 141) that LPAs “should also require developers to record and
advance understanding of the significance of any heritage assets to be lost (wholly or in part) in
a manner proportionate to their importance and the impact, and to make this evidence (and any
archive generated) publicly accessible”. However, the ability to record evidence of our past
should not be a factor in deciding whether such loss should be permitted.
7.73 The mitigation measures agreed with the archaeology officer are appropriate, and are in line
with the requirements of the NPPF. They do not, however, reduce the limited, and EIA not-
significant, harm to the non-designated heritage assets which has been identified above, and
would as such constitute enhancement measures.
Cumulative Effects
7.74 The following section considers potential effects from other development schemes in the area,
and whether additional heritage effects may occur in-combination with the present proposals.
The section considers both construction and operation effects. RS Figure 18.1 may be consulted
for locations of the relevant schemes, and Table 2.5 for further descriptive detail.
Land West of Stonehouse, Stroud (Ref. S.14/0810/OUT) and S.17/0095/REM
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 68
7.75 Land to the West of Stonehouse is a permitted mixed-use development of up to 1,350 dwellings
and 9.3ha of employment land. The development will stretch from Grove Lane to the railway line
east of Oldends.
7.76 Development is now proceeding in areas H1, H6 and H7 as identified in the Reserved Matters
Application. This comprises 103 new dwellings, with associated infrastructure, open space and
landscaping. The new development includes a new vehicular access off the lower part of Grove
Lane (opposite the Travelodge and Service Station) which is now under construction.
7.77 Under ‘landscape’ the Statement of Common Ground for Land to the West of Stonehouse notes
that” The Landscape Appraisal Study confirms that the site has a medium-low landscape
sensitivity to change. The SA Addendum Report notes that the site is relatively unconstrained in
landscape and heritage terms and there is good potential to address landscape and heritage
issues through the Concept Design / planning application process”. That situation is in fact closely
correlated to the Revised Scheme, where no significant effects have been identified upon
designated heritage assets including Listed Buildings and the Conservation Area.
7.78 It is therefore not anticipated that the development of that site will lead to effects upon any
heritage assets over and above those identified within this ES chapter. The Listed Buildings of
greatest proximity to the current site have been assessed in detail in the heritage assessment
comprising RS Appendix 7.1. Mulgrove is the building in greatest proximity to the West of
Stonehouse site but, as clarified in RS Appendix 7.1, it faces the opposite way, to the west, and
there is little inter-visibility with that land due to intervening hedges and tree cover. Westend
Farmhouse and Grove Farmhouse lie a good deal further north on Grove Lane, and inter-visibility
is highly restricted.
7.79 It is concluded that there will be no greater ‘in-combination’ effects from development of the
current and future development West of Stonehouse, and the present application.
Westend Courtyard, Grove Lane, Westend, Stonehouse (Ref. S.15/1088/FUL)
7.80 The proposals for Westend Courtyard are for extension to provide additional offices. This site lies
around 100m to the north-east of the present site, and a detailed analysis of the setting of the
farmhouse has again been provided in RS Appendix 7.1. The proposed works are relatively
limited, comprising an extension to allow 10 additional offices. The current proposals will lead to
a very small level of harm to its significance as a historic farmhouse. This effect will not be
increased in conjunction with the planned Courtyard extension.
Comment regarding potential restoration of the Stroudwater Navigation canal
7.81 Delivery Policy ES11 of the Local Plan regards ‘maintaining, restoring and regenerating the
District’s canals’. The Council will “encourage the restoration of, and other necessary functional
improvements to, the District’s canals. It will seek to improve access to, and along, the canals to
encourage use for transport and leisure/ recreational purposes. Development on the route of, or
adjacent to, the Stroudwater Navigation, the Thames and Severn canal or the Gloucester and
Sharpness Canal must not prevent the improvement, reconstruction, restoration or continued use
of the canals or towpaths.” The current proposals are in accordance with these requirements,
and will not affect any future restoration plans for the canal – including restoration of the now
in-filled element which passes within the Redline Boundary.
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 69
7.82 The same policy notes that all developments must respect the character and setting of the canals.
Again, the present proposals do this (as set out in RS Appendix 7.1).
7.83 If the canal were to be restored in the future, including the part below-ground within the Redline
Boundary, it seems very likely that it would present a ‘heritage benefit’. It would be consistent
with the guidance of Paragraph 137 of the NPPF which states that “Local Planning Authorities
should look for opportunities for new development within Conservation Areas and World Heritage
Sites and within the setting of heritage assets to enhance or better reveal their significance.”
Restoration of the canal is likely to better reveal the significance of the canal, given that it is
completely in-filled in this section.
7.84 RS Appendix 7.1 provides a detailed analysis of the heritage significance of the canal-route and
the IHCA in which it lies. The Revised Scheme will not hinder future restoration. Neither will they
harm the significance of the canal due to any change to its setting. It is concluded that if this
Revised Scheme north of the A419 is permitted and constructed, then this will not affect future
heritage benefits (or harms) that restoration of the canal might bring.
Other schemes
7.85 Table 7.6 below lists further schemes which have been considered in terms of any further ‘in-
combination’ effects which may take place. Following review, it is concluded that none of these
schemes will, or would, lead to additional effects.
Table 7.6: Other developments considered in the assessment of cumulative effects
Application
Reference
Description Comment
S.12/0763/FUL Unit 27 Bonds Mill, Bristol Road,
Stonehouse, Gloucestershire, GL10
3RF. Permitted
No additional in-combination effect.
The proposals are limited to alterations
to an existing warehouse, in a specific
urban character area
13/0001/INQUIR Land at Javelin Park proposed
development of Energy from Waste
(EfW) facility for the combustion of
non-hazardous waste and the
generation of energy. Permitted
No additional in-combination effect.
The facility is some 3.5km north-east of
the Redline Boundary, and is not
anticipated to lead to harm to any
heritage assets in the vicinity of the
Development Footprint. The Secretary
of State (APP/T1600/A/13/2200210)
considered that the ‘heritage assets
most affected’ by the Javelin Park
scheme would be St Peter’s Church,
Haresfield and Hiltmead Farmhouse:
neither of these buildings would be
affected by the current Revised
Scheme.
S.17/0337/FUL Land Adjoining Bristol Road,
Stonehouse, Gloucestershire, GL10
3RW Change of use to low key open
No additional in-combination effect.
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 70
Application
Reference
Description Comment
storage/employment base (use class
B8) restricted to use in association
with contractor for gardening/tree
surgery/landscaping services and siting
of associated steel storage container
unit (green). Appeal in progress
The proposals are of insufficient scale
to lead to any harm to heritage assets
in the vicinity of the Revised Scheme.
S.16/0607/FUL John Stayte Services Ltd Puddlesworth
Lane, Eastington, Stonehouse,
Gloucestershire, GL10 3AH Erection of
four commercial units. Permitted
No additional in-combination effect.
The development is in a specific
context of existing development on the
west side of the M5. The proposals
would lead to no harm to heritage
assets in the vicinity of the Revised
Scheme.
S.17/1133/FUL
and
S.17/1134/LBC
Former Standish Hospital and Former
Westridge Hospital Standish,
Stonehouse, Gloucestershire
Conversion and refurbishment of the
former Standish Hospital complex.
Under consideration
No additional in-combination effect.
The proposals are in a specific built
environment on the east side of
Stonehouse, and would lead to no
harm to heritage assets in the vicinity
of the Revised Scheme.
S.16/2155/FUL Lake Cottage Lake Lane, Frampton On
Severn, Gloucester, Gloucestershire,
GL2 7HG Erection of 6 dwellings with
associated vehicular access and
parking. Permitted
No additional in-combination effect.
The proposals are in the urban area of
the village, and will lead to no harm to
heritage assets in the vicinity of the
Revised Scheme.
S.16/0922/REM Land Adjoining Station Road Bristol
Road, Stonehouse, Gloucestershire,
GL10 3RB. Permitted
No additional in-combination effect.
The proposals are on the east side of
the significant built-up industrial area
at Oldends.
S.15/2089/OUT Land adjacent to Eastington Trading
Estate
No additional in-combination effect.
The heritage assessment accompanying
the proposals found that there would
be no adverse effects upon the setting
of heritage assets.
S.17/2331/OUT Land adjoining Oldbury Lodge Pike,
Lock Lane, Eastington. Erection of new
buildings for uses within use class C1
(Hotel) and use classes A3 / A4 Pub
(Pub/Restaurant)
No additional in-combination effect.
The heritage report accompanying the
application found that the proposals
would not harm the significance of any
heritage assets.
Conclusions
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 71
7.86 The only archaeological remains of significance within the Redline Boundary comprise those of
the Roman ‘Whitminster’ villa. There is no built development near them.
7.87 It has been agreed in consultation with the GCC archaeology officer that mitigation works may
suitably form a condition of any planning application. This measure would suitably manage the
remains of low significance which do lie within the area north of the A419 where development
will take place. It is recommended that this will comprise archaeological observation and
recording, the detailed methodology for which will be agreed in a Written Scheme of
Investigation with the archaeology officer to be approved before construction.
7.88 This assessment has found that the Revised Scheme will not lead to any significant harm (no
significant heritage effects in EIA terms) to any designated heritage assets through changes to
their setting. The IHCA will not be harmed. A very small degree of harm (the lower end of ‘less
than substantial harm’) will be occasioned to the heritage significance of the Grade II listed
Westend Farmhouse and Mulgrove, both on Grove Lane. This will not comprise a significant
heritage effect in EIA terms. No other designated heritage assets will be harmed.
7.89 No development will take place within the IHCA, or in its immediate vicinity. All development is
north of the modern tree-lined A419. This road is identified in the Council’s SALA report as a
defining boundary: the report for EAS 007 notes that” land to the north of the A419 has no
significant heritage constraints.” The Revised Scheme will not harm the significance of the IHCA,
and adheres to the Five Priorities and accompanying Management Proposals of the IHCA SPD
(see RS Appendix 7.1, Table 7.1). In particular, it will not harm the transition from built
development at Chipmans Platt and Meadow Mill, to the post-medieval field system comprising
the Green Corridor of the Rural Frome Vale.
7.90 It is concluded that the Revised Scheme will lead to no significant heritage harm, and no
significant heritage effects in EIA terms.
7.91 The amended scheme has considered appropriate methods to minimise heritage harm, in
accordance with heritage best-practice. The Revised Scheme can successfully be implemented
and avoid significant heritage harm. This conclusion is consistent with the Council’s SALA, which
found that the land to the north of the A419 has no significant heritage constraints.
7.92 It is recommended that a planning condition is attached to any planning permission for the
Revised Scheme which provides for archaeological mitigation in the form of archaeological
observation and recording during construction phase (an archaeological ‘watching brief’). An
appropriately worded draft condition is supplied in RS Appendix 6.2.
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 72
Table 7.7: Summary of Archaeology and Cultural Heritage Effects and Mitigation
Receptor Effect Phase
(Construction /
Operation)
Embedded
Mitigation
Sensitivity of
Receptor
Magnitude
of Change
Level of Effect and
Significance Prior to
Mitigation
Mitigation Enhancement Level of
Effect (and
EIA
Significance)
after
Mitigation
Nature of effect (short
term / medium term /
long term, permanent /
temporary, direct /
indirect)
Roman field
boundary
ditches
Disturbance of
in-filled former
ditches
Construction
phase
Non-designated
heritage asset –
low heritage
value
Lower end
of less than
substantial
harm
(adverse)
Not
Significant
Archaeological
monitoring and
recording by
Condition
Design has
been amended
to remove any
impact to
remains of
more than low
heritage
significance
Possible on-
site
interpretati
on
None Permanent Adverse
Ridge and
furrow
earthworks
Disturbance/
removal
Disturbance/r
emoval of
remains
during
construction
Non-designated
heritage asset
Lower end
of less than
substantial
harm
(adverse)
Not
significant
N/A N/A Recording
of remains
that will be
disturbed/
removed
and
publication
None Permanent Adverse
The in-filled
Stroudwater
Navigation
No change No change Non-designated
heritage asset
No change Not
significant
N/A No built
development
N/A N/A N/A
‘Important’
hedgerows
Partial
translocation
Partial
translocation
during
construction
works
Non-designated
heritage asset
Lower end
of less than
substantial
harm
(adverse)
Not
significant
N/A N/A None N/A
Stroud
Industrial
Heritage
Conservation
Area
No change No change Designated
Heritage Asset
of the Highest
Level of
Significance
No change
to
significance
Not
significant
N/A No built
development
N/A None N/A
Grove
Farmhouse
Grade II
Change to
landuse in
wider vicinity
Change to
landuse in
wider vicinity
Designated
Heritage Asset
of less than the
No change
to
significance
Not
significant
N/A Use of
planting and
green space
N/A None N/A
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 73
Listed
Building
Highest Level of
Significance
Westend
Farmhouse
Grade II
Listed
Building
Change to
landuse in
wider vicinity
Change to
landuse in
wider vicinity
Designated
Heritage Asset
of less than the
Highest Level of
Significance
Lower end
of less than
substantial
harm
(adverse)
Not
significant
N/A Use of
planting and
green space
N/A Not
significant
Permanent Adverse
Mulgrove
Grade II
Listed
Building
Change to
landuse in
wider vicinity
Change to
landuse in
wider vicinity
Designated
Heritage Asset
of less than the
Highest Level of
Significance
Lower end
of less than
substantial
harm
(adverse)
Not
significant
N/A Use of
planting and
green space
N/A Not
significant
Permanent Adverse
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 74
8 ECOLOGY AND NATURE CONSERVATION
Summary
8.1 This chapter of the Environmental Statement addresses the significant ecological effects of the
Revised Scheme of a 5,000 capacity football stadium, associated training pitches, access
arrangements from the A419 and car parking for Forest Green Rovers Football Club (FGRFC). It
suggests a number of avoidance and mitigation measures to maintain ecological coherence,
habitat connectivity and conservation of protected species present. It is concluded that after
mitigation there will be no significant ecological effects. It also outlines a number of
enhancements to increase the biodiversity value of the Development Footprint to north of the
A419. The Development Footprint currently consists of improved and semi-improved pasture cut
for silage and some cattle grazing, divided by mature hedgerows and associated ditches.
8.2 This is a revision to original Eco park application (S.16/0043/OUT). This differs in that the Revised
Scheme now only includes the Football Stadium, two practice pitches, a goal keeping practice
area, associated access and car parking all located to the north of the A419 (See Chapter 5
Description of Revised Scheme for full details).
8.3 The original surveys submitted as part of S.16/0043/OUT were accepted as being suitable to
allow an assessment of the original outline application. Throughout this chapter the Term ‘Site’
refers to the land at M5 Junction 13 West of Stonehouse. ’Survey Area’ refers to the area covered
by the 2015 and 2016 surveys. The term ‘Development Footprint’ or ’Revised Scheme’ is used
throughout this chapter to refer to the area subject to works, largely to the north of the A419.
However, for this chapter, it is also taken to encompass the section of hedgerow to the south of
the A419, which will require translocating to allow for the dualling of A419 and creation of the
new access.
8.4 The detailed ecological surveys are provided as appendices to this chapter (RS Appendix 8.1, RS
Appendix 8.2, RS Appendix 8.3, RS Appendix 8.4. and have been used to assess the potential
effects of the Revised Scheme. Further information on potential ecological enhancements that
will be brought forward as part of Reserved Matters Applications are documented in RS
Appendix 8.5 and RS Appendix 8.6.
8.5 Receptors considered unlikely to be significantly affected by the development have been scoped
out of the assessment. These are listed in Table 8.9, along with the reason for their removal.
Those receptors considered in this chapter are those where a potential significant effect has been
identified or where a precautionary approach had been taken and mitigation or enhancements
are proposed.
8.6 A desk study within 5km of the Survey Area identified two internationally important sites, four
nationally important sites, 18 Key Wildlife Sites, two of which are adjacent to, and partly within,
the southern Survey Area boundary, and a Conservation Road Verge along the A419. The
Gloucestershire Centre for Environmental Records (GCER) has provided protected species
records for otter, badger, hare, water vole, reptiles and amphibians within 5km of the centre of
the Development Footprint and records of fourteen species of bats within 10km. A total of 232
species of birds have been recorded within 5km. This is largely due to the proximity of the Site
to the Severn Estuary SPA, where large numbers of wetland species overwinter on the Estuary.
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 75
8.7 Zones of Influence were considered for a range of species present on or near the Survey Area.
For most habitats and species, the Zones of Influence applied to an area within or immediately
adjacent to the Survey Area. However, for the River Frome the Zone of Influence includes the
flood plain and habitats downstream of the Development Footprint, which extend to the Severn
Estuary 4.5km away. For most bats it was considered the Zone of Influence was unlikely to extend
beyond 1-5km, although potentially up to 10km for larger strong-flying species.
8.8 An extended Baseline Survey was conducted in 2015 to identify habitats and the potential for
the presence of protected species. Potential habitat suitable for otter, water vole, badger,
reptiles, bats and farmland birds were identified. Subsequent surveys in 2015 and 2016 were
carried out to verify the presence of these protected species. A National Vegetation Classification
(NVC) survey was also carried out in 2016 to further elucidate grassland community structure.
The main habitats present are improved and semi-improved grassland, hedgerows, and small
patches of woodland and mature trees. There are two permanent streams present on the
boundary of the Survey Area and a number of internal ephemeral ditches which had dried out
by late spring in both 2015 and 2016. This was confirmed by site walkovers in 2017.
8.9 The surveys showed that grasslands both to the north and south of A419 are mostly agriculturally
improved species poor with small areas of semi-improved grassland whilst those to west of the
A419 are mostly semi-improved grassland.
8.10 The boundary hedgerows are mostly intact, whilst a number of the internal hedgerows are
becoming gappy due to lack of management and damage by cattle. The Arboricultural Survey
(carried out only on land to the east of the M5) identified 101 individual trees, 32 hedgerows and
16 tree groups (RS Figure 8.1). Two active badger setts were identified to the north of the A419
in 2015. In 2016 and 2017 only one was active. During the otter survey in 2015 and 2016, otter
spraints were found just outside the Survey Area on the River Frome.
8.11 Bat surveys consisted of:
• Transects monthly from May to September 2015 (five surveys), and April to July 2016 (five
surveys) including a dawn survey in 2016;
• Endoscope surveys on 47 of trees for evidence of roosting bats in 2016, of these, 20 trees
were within the Development Footprint;
• Emergence surveys were conducted on 52 trees (19 within the Development Footprint)
and re-entry surveys on 27 trees (6 within the Development Footprint) identified as having
bat roost potential;
• An assessment of the potential for roosting bats was made on the derelict farm buildings
to the north of the survey area followed by two emergence surveys and one re-entry
survey;
• Static monitoring from August to October in 2015 and April to July in 2016 (this included
533 nights from 34 locations within the Development Footprint);
• Targeted surveys of bats using the M5 Pedestrian Underpass and River Frome Underpass
in 2016;
• Targeted surveys of bats crossing the A419 in 2016.
8.12 A low level of bat activity was recorded over most of the Survey Area but with a concentration
of activity close to suitable foraging areas. Common pipistrelle Pipistrellus pipistrellus and
soprano pipistrelle Pipistrellus pygmaeus were the most frequently recorded species across most
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 76
of the Survey Area. However, there was a very high level of Myotis (Daubenton’s bat Myotis
daubentonii) activity adjacent to the River Frome particularly over the river under the M5 River
Frome Underpass. There were smaller numbers of noctule Nyctalus noctula bat passes and
evidence of small numbers of greater horseshoe Rhinolophus ferrumequinum and lesser
horseshoe Rhinolophus hipposideros, serotine Eptesicus serotinus, brown long-eared bat
Plecotus auritus, and occasional records of a Nathusius pipistrelle Pipistrellus nathusii and
Leisler’s bat Nyctalus leisleri. Endoscope investigations of 47 trees found no evidence of bat
roosts. Emergence surveys (on 52 trees, and dawn re-entry on 27 of these) located just one
individual Myotis sp. roosting in an old Field Maple in hedgerow SH10 south of the A419.
8.13 Bird surveys were conducted from May to July 2015 and March to July 2016. Fifty-two species of
birds were recorded in 2015 and 54 in 2016, of which 31 were breeding in 2015 and 30 in 2016.
Five UK red listed species (herring gull, skylark, song thrush, house sparrow, and starling) were
recorded during the surveys but only one (song thrush) was recorded breeding within the Survey
Area. Three species (skylark, house sparrow and starling) were recorded breeding outside the
boundary of the Survey Area and herring gull was recorded foraging during the breeding season.
8.14 Reptile surveys were conducted in 2016 with small numbers of grass snake and slow worm being
recorded adjacent to the A419, and to the west of the M5.
8.15 Water Samples for eDNA were collected from two water bodies (ditches) in 2016. The test results
from Agricultural Development and Advisory Service (ADAS) proved negative for great crested
newt DNA.
8.16 The effect of the development on habitats and species within the Development Footprint was
significantly reduced during the design evolution by avoidance and suitable mitigation measures.
8.17 With regards to bats, the detailed design of the Revised Scheme (avoidance) will include the
retention of the majority of mature trees and the translocation or replacement of hedgerows.
Further mitigation through the creation of bat commuting corridors, bat-friendly lighting
throughout the Development Footprint and the creation of enhanced foraging areas (orchards
and pond) will reduce the potential negative effects to ‘not significant’. Habitat creation to
enhance the Development Footprint for bats is outlined in the Green Infrastructure Plan (RS
Figure 5.3 Indicative Green Infrastructure Parameter Plan).
8.18 With regards to birds, construction and operation effects are perceived to be minimal after
mitigation, and therefore not significant. Reptiles will be trapped and translocated to suitable
areas west of the M5, so after mitigation, there will be no residual significance.
8.19 Cumulative effects of six consented developments, one pre-planning and two pending
consideration within a 5km radius of the Development Footprint were assessed. It was concluded
that there will be no significant cumulative effects, singly or in concert, on the Revised Scheme.
8.20 A Green Infrastructure Plan (RS Appendix 8.5) outlines the enhancements for biodiversity,
mitigation for climate change, ecosystem services, landscape improvements and social benefits
for well-being. Implementation of the Green Infrastructure Parameter Plan will result in a net
gain in biodiversity.
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 77
8.21 Therefore, the development will contribute to the delivery of the NPPF objective of net
biodiversity gains, the objectives of Stroud District Local Plan policies ES6 and ES8 and the
recently approved Eastington Neighbourhood Plan Policies EP2, EP4 and EP9.
Introduction
8.22 This Chapter concerns the potential effects of the construction and operation of a new Forest
Green Rovers Football Club (FGRFC) Stadium, associated training pitches, access arrangements
from the A419 and car parking adjacent to Junction 13 of the M5 in Gloucestershire on
biodiversity. The assessment of the nature conservation value of the Survey Area is based on
detailed surveys conducted in 2015 and 2016, as set out in the summary statement of EIA
significance. Further walk over surveys were conducted in 2017 to assess whether there has been
any significant changes in habitats within the survey area. This chapter explains the ways in which
habitats and species may be affected by the Revised Scheme and the significance of any potential
effects identified. It sets out any avoidance or mitigation measures required to reduce significant
negative effects to negligible and non-significant. It also describes biodiversity enhancements
that will be implemented as part of this development.
8.23 The ecological assessment follows the approach set out in the Chartered Institute of Ecology and
Environmental Management (CIEEM) Guidelines for Ecological Impact Assessment in the UK and
Ireland (2016)26. The guidelines are based upon the baseline description of the ecological
characteristics of the survey area, the evaluation of the habitats and species present (ecological
receptors), the identification of ecological effects, the assessment of the significance of the
identified ecological effects, the identification of mitigation to avoid or offset significant effects,
and other enhancement measures to address any other identified effects.
8.24 The technical reports, which comprise detailed raw data sets and other information prepared
following the surveys in both 2015 and 2016, can be found in RS Appendix 8.1 Baseline Survey,
in RS Appendix 8.2 Fauna surveys, RS Appendix 8.3 Arboricultural Survey, RS Appendix 8.4
Confidential Badger Report (not for public release) and RS Appendix 8.5 Green Infrastructure
Plan, describing proposed enhancements to encourage wildlife, improve landscape elements and
promote health and well-being. RS Appendix 8.6 Principles of Environmental Enhancements
provides further indicative information on the types of environmental enhancements proposed.
RS Appendix 8.7 Consultation Responses contains pre and post submission consultation
responses to the original Eco Park application (S.16/0043/OUT). RS Appendix 8.8 includes
further consultation from EPR and the responses which were the basis of the agreement that the
level of ecological survey and assessment was sufficient for the original outline application. RS
Appendix 8.9 contains the Planning Policy and Guidance. It should be noted that all European
Legislation still applies to the UK. The ecological Survey Area is shown on RS Figure 8.3.
8.25 The scope of this Ecological Impact Assessment covers the potential direct and indirect effects to
selected ecological receptors found within the Survey Area due to the construction and/or
operation of the football stadium, associated training pitches and car parking.
8.26 This is an outline planning application for a new Stadium for FGRFC, associated training pitches
and car parking to the north of the A419. The total area of the Development Footprint is
26 CIEEM (2016) Guidelines for Ecological Impact Assessment in the UK and Ireland: Terrestrial, Freshwater and
Coastal; 2nd Edition, Chartered Institute of Ecology and Environmental Management, Winchester
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 78
approximately 19ha. The stadium and pedestrian area will cover 5.17 ha, the training pitches
1.73 ha and the car park and roads covers 5.7 ha. There will be 5.16 ha of enhanced wildlife
habitats including grasslands, orchards, ponds and park woodland. The remaining areas will be
either retained woodland, grassland and hedgerow (0.69ha) or site maintenance/ farm area
(0.44 ha). Full project description details are provided in Chapter 5: Description of the Revised
Scheme.
Legislation, Policy and Guidance
8.27 The ecology chapter considers how all levels of planning policy relating to ecology and relevant
to this application are addressed and how the Revised Scheme will contribute to their delivery.
8.28 International legislation includes the European Directive on the Conservation of Natural Habitats
and of Wild Fauna and Flora (92/43/EEC) and the Bern Convention, whilst national legislation
considers the Wildlife and Countryside Act, The Conservation of Habitat and Species Regulations
(2010) and the Natural Environment and Rural Communities Act 2006 (NERC), as well as the
National Planning Policy Framework (NPPF). Also, relevant national legislation and guidance are
the Hedgerow Regulations (1997), Tree Preservation Orders made under the Town and Country
Planning act 1990, the town and Country Planning (Tree Preservation) (England) Regulations
2012, the UK Biodiversity Action Plan and England’s Biodiversity Strategy 2020.
8.29 On a local level, policies of the Stroud District Council Local Plan Policies ES6 and ES8 and the
Eastington Neighbourhood Plan Policies EP2, EP4 and EP9 are considered in RS Appendix 8.9
Planning Policy and Guidance.
Assessment Methodology and Significance Criteria
Professional Competence
8.30 Dr. Simon Pickering and Dr. Grace O’Donovan, who carried out the Assessment, are both
experienced ecologists and consultants. Dr. Simon Pickering has a Bachelor of Science with
Honours degree in Biological Sciences from Hatfield Polytechnic and a degree of Doctor of
Philosophy in Zoology from the University of Durham. He has worked as a professional ecologist
for over 30 years and has been the Principal Ecologist at Ecotricity since 2008. He is responsible
for overseeing the ecological assessment process for renewable energy as well as other
development projects for the company and has experience of writing over 25 Ecological Impact
Assessments (EcIA), the most recent ones being for wind farms at Dulater, Scottish Borders and
Upper Sonachan, Argyll and Bute
8.31 Grace O’Donovan is a professional botanist with 30 years’ experience in the environmental
sector, of which 13 years’ experience is in environmental consultancy. She has written over 10
EcIAs, the most recent ones being Fiddington, Gloucestershire, New Lawn, Gloucestershire and
Berkeley Green Energy Storage, Gloucestershire. She is a full member of the Chartered Institute
of Ecology and Environmental Management (CIEEM) and holds protected species licences for
bats, barn owl and great crested newt.
Potential Zone of Influence
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 79
8.32 The Zone of Influence is the area over which the ecological feature identified may be subject to
significant effects as a result of the Revised Scheme. These will vary between ecological
receptors26..
8.33 The key receptors are considered to be:
• The River Frome, its flood plain and designated sites downstream of the Survey Area;
• The grassland habitats within the Survey Area;
• The hedgerows, woodland relics and historic ecological features;
• The functional ecology of the population of protected species using the Survey Area or
influenced within the Development Footprint. This would include: breeding birds, reptiles,
bats, badgers and potentially otter.
River Frome
8.34 Sources of water pollution on building sites include: diesel and oil; paint, solvents, cleaners and
other harmful chemicals; and construction debris and dirt. When land is cleared, it causes soil
erosion that leads to silt-bearing run-off and sediment pollution. Silt and soil that runs into
natural waterways turns them turbid, which restricts sunlight filtration and destroys aquatic life.
8.35 Surface water run-off also carries other pollutants from the site such as diesel and oil, toxic
chemicals, and building materials like cement. When these substances get into waterways they
poison water life and any animal that drinks from them.
8.36 The River Frome is over 400 m from the Development Footprint to the south of the A419.
Therefore, the potential risk of silt run-off and pollution entering the River Frome during
construction is considered to be very low. It is therefore considered highly unlikely that any silt
or pollution from the Revised Scheme, could reach the confluence with the Severn Estuary
approximately 4.5km downstream to the west of the Survey Area.
Grassland Habitats
8.37 The effects on grasslands, hedgerows, trees and breeding birds through construction are likely
to be largely restricted to within the Development Footprint or the immediate vicinity. Semi-
improved grasslands are not well mapped in Gloucestershire, but the CEH Land Cover Map (2007)
in RS Figure 8.4 shows the distribution of ‘semi-improved grassland’ (a combination of
calcareous-, acid-, neutral- and rough grassland) in a 5km radius. From this it can be seen that
there are a number of isolated patches scattered throughout the area and they are not a rare
feature locally.
8.38 Semi-improved grassland is interpreted and mapped variously depending on the requirement.
As grasslands are often not a permanent feature, their mapping is not very reliable at the
National scale. The semi-improved grasslands within the Survey Area may be a significant seed
source for adjacent habitats available for habitat restoration at the landscape scale, as part of
the Green Infrastructure Framework for Gloucestershire. Grass seed can be dispersed by wind
tens of metres, but rarely over 50m, and herbaceous and grass seed may also be dispersed by
animals too such as birds, deer, badger and hare (epizoochory) observed within the Survey Area.
As most of the grassland affected by the development is improved, the loss of this grassland to
the development will not have a large zone of influence as the majority of grasslands in the
surrounding area are also improved and not of conservation interest.
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 80
Hedgerows and Woodlands
8.39 Hedgerows act as important corridors for movement of species such as birds, bats and
invertebrates. The Zone of Influence for hedgerows is the Survey Area, however this zone of
influence would link in to the 10km zone of influence for bats. Loss of hedgerow continuity could
have a significant influence on bat movements because the majority of bat species (with the
exception of high flying species such as noctule, and Daubenton’s - which tend to follow water
courses) tend to forage and commute along hedgerows. It has been suggested that gaps as small
as 10-15m wide may present a deterrent to some species of bats to cross27, although recent
research has shown that pipistrelle spp. will cross gaps up to 80m even in a lit urban
environment28 . It should be noted that the Survey Area is already dissected by the M5 and the
A419. Hedgerow loss within the Development Footprint may affect the wider area with regard
to connectivity with other hedgerow networks, but as hedgerow loss will be compensated with
a net gain in hedgerow length, the zone of influence is confined to the Development Footprint.
Protected Species
8.40 Although temporary disturbance or loss of breeding habitat could result in temporal
displacement of breeding birds to the surrounding area, this is unlikely to extend more than a
few hundred metres.
8.41 The effect on reptiles is likely to be restricted to the Development Footprint, as slow worms have
very poor dispersal rates - 4m within a lifetime (Smith 1970)29 and reptiles in general have limited
dispersal rates30. Habitat where reptiles are present may be removed, but reptiles will be
translocated to the area within the Redline Boundary west of M5, so the Zone of Influence is
within the Development Footprint.
8.42 Otter territories can extend up to 20km and although the River Frome is 400m from the
Development Footprint, there is no potential risk of silt run-off and pollution that, if it entered
the River Frome during construction, could reach the Severn Estuary approximately 4.5km
downstream of the Survey Area, so the Zone of Influence is considered to be 20km.
8.43 Badger territories can extend up to several kilometres although the effects are likely only to
extend to the sett territory and the surrounding badger territories.
8.44 The majority of bats typically forage with 1-5km of their roost although some species may travel
further to suitable feeding sites, such as noctule, which travels up to 9km, Daubenton’s bats up
to 10km, Serotine up to 6km, lesser horseshoe up to 6km and greater horseshoe, when habitat
is restricted, up to 12km. There are large areas of high quality bat foraging habitat within the
Stroud Valleys and it is highly unlikely greater horseshoe bats would travel such a distance to the
lower quality habitat within this Survey Area to forage. However, it is known that greater- and
lesser horseshoes breeding at Woodchester Mansion migrate to hibernacula in old mines within
27 JNCC 2001 Habitat management for bats: A guide for land managers, land owners and their advisors.
http://jncc.defra.gov.uk/pdf/Habitat_Management_for_bats.pdf. 28 Hale, J.D, Fairbrass, A.J., Matthews, T.J., Davies, G. and Sadler, P. 2015. The ecological impact of city lighting
scenarios: exploring gap crossing thresholds for urban bats. Global Change Biology 21, 2476-2478. 29 Smith N.D. (1990) The ecology of the slow-worm (Anguis fragilis L.) in southern England. M.Phil. University of
Southampton. 30 Reptile Management Handbook 2010. ARC. Bournemouth.
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 81
the Forest of Dean, and therefore may cross the Survey Area during autumn migration. Potential
Zones of Influence for particular receptors are shown in Table 8.1.
Table 8.1: Potential Zones of Influence
Ecological receptor Potential zone of influence
River Frome Up to 4.5km downstream to confluence with River Severn
Grasslands Within Survey Area
Hedgerows Within Survey Area
Trees Within Survey Area
Breeding birds Within or adjacent to Survey Area
Reptiles Within Survey Area
Otter Up to 20km
Badger Within Survey Area and neighboring territories
Common & Soprano Pipistrelle, and
Myotis species
Up to 1.5km
Serotine Up to 6km
Noctule Up to 9km
Daubenton’s Up to 10km
Lesser Horseshoe Up to 6km
Greater Horseshoe Up to 12km
Consultation
8.45 There has been very extensive consultation for the planning application of Eco Park
(s.16/0043/OUT), which included the Sports Park south of the A419 (no longer to be developed
as part of this Revised Scheme), and a Green Business park north of the A419 (now the location
of the Revised Scheme). Details of all these consultations are provided RS Appendix 8.7 and RS
Appendix 8.8. A further consultation letter has been sent to Stroud District Council on 23rd
October 2017, though no response has been received to this.
Methodology - Desk Study
8.46 The desk-based study methodology involved consulting both statutory and non-statutory bodies’
pre-application in order to identify protected sites and species (both confirmed and potential)
within a 5km radius of the Survey Area. Gloucestershire Environmental Records Centre (GCER)
and the Gloucestershire Bat Group provided records of protected sites and species present
within 5km, and within 10km for bats. A review of the ecological survey information from the
adjacent West of Stonehouse ES was also undertaken to ensure the data search was as
comprehensive as possible.
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 82
8.47 This approach follows guidelines on ecological assessments that have been produced by CIEEM
in 201531 and 201626.
8.48 Features of nature conservation interest are considered to be the ecological receptors. These are
populations, species, communities, habitats and sites selected as likely to be affected (in a
positive or negative way) by the environmental changes created by a development.
8.49 The important ecological receptors define the nature conservation interest of the Survey Area
and must be valued to provide a basis for assessing the effects of a development. Valuation
usually seeks to assign a geographical frame of reference for the importance of an ecological
receptor. Those used are as follows in Table 8.2:
Table 8.2: Determining Factors for Nature Conservation Importance
Designation Importance
International Sites of international importance on the basis of their habitats or species are
designated under the EU Habitats Directive and include Special Areas of
Conservation (SACs). Candidate or potential sites for these designations are also
considered to be of international importance. Species protected under Annex II
of the Habitats Directive and given UK protected status by Schedule 2 of the
Conservation of Habitats and Species Regulation 2010.
National (i.e.
England, Wales,
Scotland or
Northern Ireland)
Sites of Special Scientific Interest (SSSIs) are of national importance and are
designated under the Wildlife and Countryside Act 1981 using guidelines on their
selection (JNCC, 1998), as well as the presence of species listed in Schedule 5 of
the Act. National Nature Reserves (NNRs) were established to protect some of
our most important habitats, species and geology, and to provide ‘outdoor
laboratories’ for research.
Regional Local authorities and County Wildlife Trusts may have designated sites of regional
importance, designation criteria being published locally. This may include areas,
habitats or species identified in regional BAPs.
County (or
Metropolitan)
Local authorities and County Wildlife Trusts may have designated sites at
regional, county or district levels (e.g. Sites of (Local) Importance for Nature
Conservation – S (L) INCs, Key Wildlife Sites (KWS) and the designation criteria
may be published locally.
District (or Unitary
Authority, City or
Borough)
Local Nature Reserve (or LNR) is a statutory designation made under Section 21
of the National Parks and Access to the Countryside Act 1949 by principal local
authorities, Parish and Town Councils
Local or Parish Habitats within a parish of local importance which may be designated as Local
Nature Reserves or local designations such as pocket parks, village greens, or
Conservation Road Verges.
Within zone of
influence only
(site or Study
Area).
Evaluation of features or resources likely to be affected. Areas or resources
affected by the biophysical changes caused by the project. Features of sufficient
value to be included and are vulnerable to significant impacts arising from the
project.
8.50 Sites worthy of designation with habitat and/or species interest at any level must have a 'viable
area' of habitat. Viability means that the area should be sufficient to maintain the habitat interest
in adequate condition through appropriate management (which might involve some form of
rotational manipulation of vegetation), as well as providing sufficient territory and suitable
habitat for the breeding and wintering populations of species of interest.
31 CIEEM (February 2015). Guidelines for Ecological Report Writing CIEEM.
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 83
8.51 It is more difficult to judge a level of importance for Study Areas/ sites with no designation.
Ecological resources contributing to the biodiversity or nature conservation importance of a
Study Area may include:
• Internationally, nationally or locally rare or uncommon species, subspecies or varieties;
• Ecosystems or their parts supplying the requirements of populations of the above species;
• Habitat rarity, diversity and connectivity;
• Communities typical of valued natural or semi-natural vegetation types;
• Large populations of uncommon or threatened species;
• Species-rich assemblages;
• Species on the edge of their range;
• Typical faunal assemblages of homogenous habitats.
8.52 Establishment of the level of importance relating to the ecological features found by the baseline
surveys firstly involves applying the criteria for designation of international, national and sub-
national (where available) sites to the feature set. The approach should be to consider the
ecologically coherent unit(s) of the Study Area and to establish as well as possible the extent of
equivalent ecologically coherent units at the local, regional, national and international scales in
order that the Study Area can be placed in context.
8.53 Reference to national and local BAPs is necessary, although the biodiversity importance of a
particular species must be judged in relation to its rarity, distribution (national and international,
including consideration of its mobility), population size, status (e.g. population stable or
declining) and priority according to BAPs.
8.54 Other aspects that may be important in the valuation of habitats and species include potential
value (e.g. the potential for habitat enhancement or creation), social value (e.g. the value of the
Study Area to local people for recreation and the enjoyment of wildlife), economic value (e.g.
hunting and fishing interests or the value of the ecological interest as a tourist attraction), and
secondary ecological value (e.g. buffer zones to areas of greater importance or areas that are
important in ecological networks or corridors).
8.55 Legal protection must be considered and may apply to habitats and species that are rare and
declining and are covered by statutory instruments such as the Conservation of Habitats and
Species Regulations 2010, the Countryside and Rights of Way Act (CRoW Act) 2000 and the
Wildlife and Countryside Act 1981 (as amended). Species may be protected under legislation (e.g.
parts of the Wildlife and Countryside Act 1981, the Protection of Badgers Act 1992 and the Wild
Mammals (Protection) Act 1996) for reasons other than rarity. In these cases, the ecological
importance of the species concerned must be judged in their local context.
Predicting and characterising effects
8.56 Following the identification of the activities likely to cause significant effects, it is necessary to
predict and characterise the resultant changes (effects) and to assess the effect on the valued
ecological resource.
8.57 In order to do this, it is necessary to take into account the effects the following parameters will
have on the ecological structure and function of the relevant feature.
Likelihood
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 84
8.58 A level of likelihood should be attached to both the occurrence of a predicted effect and the
assessment of its ecological effect (Table 8.3):
Table 8.3: Likelihood of Occurrence
Likelihood Definition
Certain/near-Certain: Probability estimated at 95% chance or higher.
Probable Probability estimated above 50% but below 95%.
Unlikely Probability estimated above 5% but less than 50%.
Extremely Unlikely Probability estimated at less than 5%.
Positive or Negative effect
8.59 In addition, a description of any potential effect also needs to address whether that effect will
have a positive or negative effect on the population level of a particular species or habitat.
Magnitude
8.60 This is the size or amount of an effect (e.g. a small increase in the proportion of the population
of a rare species is displaced, or a total loss of the structure and function of semi-natural
grassland). Broad categories of spatial magnitude can be defined as below (Table 8.4):
Table 8.4: Spatial Magnitude Criteria
Magnitude Definition
Very High Total loss or very major alteration to key elements/features of the baseline (pre-
development) conditions such that the post-development attributes will be
fundamentally changed and may be lost altogether.
Guide: >80% of population lost (or gained).
High Major loss or major alteration to key elements/features of the baseline conditions such
that the post development attributes will be fundamentally changed.
Guide: 21-80% of population lost (or gained).
Moderate Loss or alteration to one or more key elements/features of the baseline conditions
such that post development attributes will be partially changed.
Guide: 6-20% of population lost (or gained).
Minor Shift away from baseline conditions. Change arising from the loss/alteration will be
discernible, but the underlying attributes will be similar to pre-development
circumstances/patterns.
Guide: 1-5% of population lost (or gained).
Negligible Very slight change from baseline conditions. Change barely distinguishable,
approximating to the ‘no change’ situation.
Guide: < 1% population lost (or gained).
Duration and Reversibility
8.61 The period over which the effect is expected to last prior to recovery and replacement of the
feature is considered. An irreversible (permanent) effect is one from which recovery is not
possible. A reversible (temporary) effect is one from which recovery is possible (see Table 8.5).
Note these timeframes differ from the general assumed timeframes set out in the introductory
chapters of this ES.
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 85
Table 8.5: Temporal magnitude criteria
Magnitude Definition
Permanent Effects continuing indefinitely beyond the span of one human generation (taken as
approximately 25 years), except where there is likely to be substantial improvement
after this period (e.g. the replacement of mature trees by young trees which need >25
years to reach maturity, or restoration of ground after removal of a development.
Such exceptions can be termed very long-term effects).
Temporary Long term (15 - 25 years or longer)
Medium term (5 – 15 years).
Short term (up to 5 years).
Timing and frequency
8.62 Some changes may only cause an effect if they happen to coincide with critical life stages or
seasons, such as the breeding season. The frequency of an activity should also be considered.
Significance of Effects
8.63 The effects identified are then attributed a level of significance (based on the sensitivity of the
receptor and the magnitude of the effect) and their beneficial or harmful character identified. In
order to provide a consistent approach and ensure different environmental effects are assessed
in a comparable manner; receptor value, magnitude of change and level of effect for each
environmental topic are described consistently throughout the ES as set out in ES Chapter 2:
Approach to EIA.
8.64 Where sufficient information exists to ascribe a value to a receptor and to understand the
magnitude of change, EIA often uses a matrix to determine the level of effect. An example of a
common matrix used to assess the significance of ecological effects is presented in Table 8.6. In
this approach, the level of effect matrix combines the sensitivity or importance of the receptor
being affected with the magnitude of change resulting from the development.
Table 8.6: Level of Effect Matrix with boxes highlighted considered as having significant effects
requiring mitigation
Magnitude of
Change
Importance or Sensitivity of Receptor
High Medium Low Negligible
Very High / High Very Substantial /
Substantial
Substantial /
Moderate
Moderate /
Slight Negligible
Moderate Substantial /
Moderate Moderate Slight Negligible
Minor Moderate / Slight Slight Slight /
Negligible Negligible
Negligible Negligible Negligible Negligible Negligible
8.65 While effects are considered to fall into one of five effect categories ranging from ‘negligible’,
‘slight ‘, ‘moderate’, ‘substantial’ to ‘very substantial’, it is only those effects that fall into the
‘moderate’, ‘substantial’ or ‘very substantial’ categories that are considered to be the significant
environmental effects within the meaning of the EIA Regulations arising from the construction
and operation of the development.
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 86
8.66 However, CIEEM guidance moved away from the use of this matrix in 2006. Instead, a
transparent approach is promoted, whereby an effect is determined to be significant or not on
the basis of an evaluation of the factors that categorise it. In this chapter, the matrix set out
above is only used as a broad guide to assess whether an identified activity will have a significant
effect on ecological receptors.
Designated/defined sites and ecosystems
8.67 Significant effects encompass effects on structure and function of defined sites and ecosystems.
8.68 For designated sites it needs to be determined whether the project and associated activities are
likely to:
• Undermine the site’s conservation objectives or affect the conservation status of species
or habitats for which the site is designated either positively or negatively; or,
• Whether it may have positive or negative effects on the condition of the site or its
interest/qualifying features.
8.69 For ecosystems it needs to be determined if the project is likely to result in a change in ecosystem
structure and function. Consideration should be given to whether any processes or key
characteristics will be removed or changed; whether there will be an effect on the nature, extent,
structure and function of component habitats; or whether there is an effect on the average
population size and viability of component species.
8.70 Consideration of functions and processes acting outside the formal boundary of a designated site
is required, particularly where a site falls within a wider ecosystem e.g. wetland sites. Predictions
should always consider wider ecosystem processes.
8.71 Many ecosystems have a degree of resilience to perturbation that allows them to tolerate some
biophysical change. Ecological effects should be considered in the light of any information
available or reasonably obtainable about the capacity of ecosystems to accommodate change.
Habitats and species
8.72 Consideration of conservation status is important for evaluating the effects of impacts on
individual habitats and species and assessing their significance.
8.73 For habitats, the conservation status is determined by the sum of the influences acting on the
habitat that may affect its extent, structure and functions, as well as its distribution and its typical
species within a given geographical area.
8.74 For species, the conservation status is determined by the sum of influences acting on the species
concerned that may affect its abundance and distribution within a given geographical area.
8.75 In many cases (e.g. for species and habitats of principal importance for biodiversity), there may
be an existing statement of the conservation status of a feature and objectives and targets
against which the effect can be judged. However, not all species or habitats will be described in
this way. The conservation status of a habitat or species will vary depending on the geographical
frame of reference.
8.76 When assessing potential effects on conservation status, the known or likely background trends
and variations in status should be taken into account. The level of ecological resilience or likely
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 87
level of ecological conditions that would allow the population of a species or area of habitat to
continue to exist at a given level, or continue to increase along an existing trend, or reduce a
decreasing trend, should also be estimated.
Limitations of Assessment
8.77 It is neither possible nor intended to cover the entire ecology of a site during a survey for an
outline application such as this.
8.78 This report is based upon the results obtained from ecological surveys conducted in 2015 and
2016 plus a walkover survey in 2017. There is only a limited time- lag between the detail surveys
and the date when activities are likely to take place, therefore surveys still provide a reliable
indication of the baseline conditions and a robust basis to assess any potential effects. Walkover
surveys conducted during 2017 noted no changes the distribution or management of habitats
recorded on site and no change in badger sett use from 2016.
8.79 Best practice was followed for the faunal field surveys, the species in question are secretive
animals and it is possible that some field signs may have been overlooked. In addition, usage of
the Survey Area by many mammal species for foraging, shelter and as a transit route varies with
season, and the surveys carried out therefore represent only ‘snapshots’ of activity within the
Survey Area at the time of the survey. In order to overcome this limitation in relation to bats, an
intensive static bat detectors survey was conducted to record bat activity throughout the Survey
Area over the survey period. (See RS Figure 8.5). It should also be noted that absence of recorded
field signs is not necessarily evidence that a particular species is not utilising an area. However,
this report will identify the probable value of the Survey Area for the pertinent species, based
upon the survey data gathered.
Baseline Conditions
8.80 The area surveyed (Survey Area) for the baseline habitat, NVC and protected species surveys is
shown in RS Figure 8.3. It encompasses land to north of A419 (18.9ha), south of A419 (13.5ha)
west of the M5 (4.6ha), as well as an area between the Redline Boundary and the river Frome.
The full details of the survey methods and results for the vegetation surveys and protected
species are presented in RS Appendix 8.1 Baseline Survey and RS Appendix 8.2 Fauna Surveys
respectively. The surveys were carried out by experienced professional ecologists following the
appropriate survey guidance.
Site description
8.81 The Site is situated in the Severn and Avon Vale Natural Area, an area that is a low-lying
undulating plain through which the rivers Severn and Avon and their many tributaries flow. It
comprises of agricultural land with fields cut for silage and hay and some limited cattle grazing.
The Development Footprint is bounded by the M5 on the west and the A419 to the south. Grove
Lane, residential housing and agricultural land bound the site to the north and agricultural land
and a service station adjoin it on the eastern boundary. The Development Footprint is bounded
by hedgerows. The external hedgerows are largely intact, although a number of the internal
hedgerows are becoming gappy and defunct due to damage by cattle and lack of management.
A number of hedgerows have standard trees present. There is one small water course on the
north-western boundary of the Survey Area (the Selbrook). This flows under the M5 and flows
parallel to the River Frome before entering the Frome at Wheatenhurst 3 km to the west of the
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 88
site. Construction has started on the West of Stonehouse (WOS) housing development (1,350
houses) on the opposite side of Grove Lane, the boundary of which is less than 50m from the
boundary of the site.
8.82 The Survey Area south of the A419, which is not to be developed as part of the Revised Scheme,
is surrounded by scattered industrial development, residential housing, the M5, and agricultural
land. William Morris College and Eastington Business Park are directly to the east and south-east
of the Redline Boundary south of the A419. Stonewater Business Park is 1.5 km to the east. The
south is bounded by the River Frome flood plain. The original route of the Stroudwater Canal
runs through the land to the south of the Redline Boundary from east to west. The former line
of the Canal was infilled, and the route blocked during the construction of the M5.
Statutory designated sites - International and nationally important sites
8.83 Statutory Designated Sites within 10km of the Development Footprint are shown on RS Figure
8.6.
8.84 The Severn Estuary SPA/SAC/Ramsar Site (designated for overwintering wetland birds and for
presence of mudflats, Atlantic salt meadows, sea lamprey, river lamprey and Twaite shad) is
located 3.8km directly to the west of the Survey Area in a straight line (4.5km downstream
following the Frome to its confluence with the Severn).
8.85 Rodborough Common SAC/SSSI, internationally important for calcareous grasslands, is 6km to
the east of the Survey Area and the Cotswold Beech Wood SAC is just over 10km from the Survey
Area.
8.86 Frampton Pools SSSI (wetland) is 1.6km from the Survey Area to the west of the M5 and A38.
The Upper Severn Estuary SSSI (estuarine habitat including salt marsh, pasture and over
wintering wetland birds) is 3.8km to the west of the Survey Area in straight line and Haresfield
Beacon SSSI (limestone grassland) is 4.2km to the east of the Survey Area. Woodchester Park
SSSI is designated for a breeding colony of greater horseshoe bats within the Mansion (deciduous
woodland and semi-improved grassland and associated species) and is just over 5km from the
Development Footprint, but within 5km of the of proposed cycle track improvements.
8.87 Selsley Common SSSI, just over 5km from the Survey Area, is designed principally for the herb
rich calcareous grassland and associated species but also includes Leigh’s Quarry which is notified
for its geological interest.
8.88 Minchinhampton Common SSSI is just over 8km from the Survey Area. Whilst principally
designated for herb-rich limestone grassland and associated species, the citation also mentions
the disused stone mines on the Nailsworth side of the Common, which are used as winter roost
sites by the greater horseshoe bat.
8.89 There are three principal geological SSSIs within 10km: Edge Common 6.5km to the north east,
Garden Cliff 5.6km to the west on the bank of the River Severn and Coaley Wood Quarries 7.2km
to the south.
Non-statutory designated sites and Strategic Nature Area
8.90 Non-Statutory sites within 5km are shown on (RS Figure 8.6). There are 18 Key Wildlife Sites
(KWS), six conservation road verges and a further 22 Potential Key Wildlife Sites (PKWS) within
5km of the Survey Area.
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 89
8.91 The Frome Valley Strategic Nature Area (SNA) (No. 55) encompasses the two KWSs (River Frome
(SO70) and River Frome (SO80) and is part of the larger Severn Vale Priority Landscape. The main
body of the SNA and associated floodplains extends for 5km on either side of the Survey Area
(RS Figure 8.6) linking the River Frome with the River Severn to the North.
Historic management
8.92 The land has traditionally been farmed. There is evidence within the Survey Area of ridge and
furrow dating from the Middle Ages and more recent ridge furrow probably dating from the
Napoleonic Wars period. The hedgerow network and field boundaries appear to have changed
little, although the construction of the canal, M5 and A419 has dissected the landscape through
the Survey Area (see Figure 10.6a 1st edition OS Map).
Desk Study Protected Species
Flora
8.93 Native Bluebell Hyacinthoides non-scripta is the only protected plant species recorded within the
Survey Area.
Amphibians and reptiles
8.94 There are no records of reptiles or amphibians from within the Survey Area. However, there are
records of common toad Bufo bufo, common frog Rana temporaria, great crested newt Triturus
cristatus, common lizard Lacerta zootoca, grass snake Natrix natrix and slow-worm Anguis fragilis
within 5km (as supplied by GCER). The nearest record of great crested newt is at 2.2km north-
east of the Survey Area. Further details are provided in RS Appendix 8.2 Fauna Surveys and the
location of these records is shown on RS Figure 8.7.
Invertebrates
8.95 There are no records for White-clawed crayfish Austropotamobius pallipes within 5km of the
centre of the Survey Area. In addition, a detailed evaluation was procured from GCER for the
adjacent Key Wildlife Sites, and white-clawed crayfish were only reported in the upper reaches
of the Frome and tributaries.
Mammals other than bats
8.96 Water vole Arvicola amphibius, badger Meles meles, and otter Lutra lutra have been recorded
within a 5km radius of the Survey Area and the location of these records is shown on RS Figure
8.7 and on RS Figure 8.8 Confidential Protected Species Records-Badgers (not for general
release to the public). There are records of otter signs from the River Frome.
8.97 There are no records for Hazel dormouse Muscardinus avellanarius within 5km of the Survey
Area. There has been no evidence of hazel dormouse present within the Survey Area, and surveys
conducted as part of the WOS application did not find this species.
Birds
8.98 Protected bird species were identified as being on the Red List for Britain (Birds of Conservation
Concern, Schedule 1 of the Wildlife and Countryside Act and Annex I of the Birds Directive). Due
to the close proximity of the Severn Estuary SPA, a large number of protected bird species records
(2,356) fitting these criteria occur in the area. The species are shown on RS Figure 8.9, RS Figure
8.10 and Figure 8.11, where they are mapped according to their level of protection.
Bats
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 90
8.99 There are records of fourteen species of bat within 10km of the Survey Area: greater horseshoe,
lesser horseshoe, common pipistrelle, soprano pipistrelle, whiskered bat Myotis mystacinus,
Brandt’s bat Myotis brandtii, Natterer’s Myotis nattereri, Daubenton’s bat, Bechstein’s Myotis
bechsteinii, barbastelle Barbastella barbastellus, brown long eared Plecotus auritus, serotine
Eptesicus serotinus, Leisler’s Nyctalus leisleri and noctule Nyctalus noctula (RS Figure 8.12 and
RS Figure 8.13). RS Figure 8.13 distinguishes between the different types of roost recorded on
the GCER database.
Baseline Ecological Conditions - Habitats
8.100 Full details of the habitat and species surveys are provided in RS Appendix 8.1 and RS Appendix
8.2 and these are summarised below.
8.101 The majority of the habitat within the Development Footprint is lowland neutral agriculturally
improved and semi-improved grassland divided by mature hedgerows (RS Figure 8.14).
Hedgerows within the Survey Area contain a number of mature trees. The Survey Area is drained
by a small number of ditches - the internal ditches are seasonally dry. There is a permanently
flowing water course (the Selbrook) in the north west corner which flows into the River Frome
3km west of the Survey Area (it is culverted under the M5 – see also RS Figure 9.1). On the
northern boundary adjacent to Grove Lane there is a modern barn used for hay storage
surrounded by several abandoned and partially derelict farm buildings.
Hedgerows
8.102 Hedgerows surround all the fields within the Development Footprint. Whilst most of the
boundary hedgerows are intact, a number of the internal hedgerows have become gappy and
defunct due to lack of maintenance and cattle damage. Analysis of the hedgerow flora to the
north of the A419 showed that three hedgerows (NH12, NH13 and NH15, RS Figure 8.14) showed
evidence of being woodland remnants due the presence of woodland ground flora. This indicates
that one of the fields (Field 5, RS Figure 8.14) may have been woodland in the past that was
cleared prior to 1846. This would have incorporated the existing two small blocks of woodland
to the north of the A419 and connected directly to the double hedgerow (Hedgerows NH5 and
NH6, RS Figure 8.14). The rest of the hedgerows in the Development Footprint fell into three
compartments: hedgerows of low species diversity (18-21 spp.), of medium species diversity (25-
34 spp.) and of high species diversity (36-45 spp.). The number of woody species in all hedgerows
ranges from three-nine, and nine of the 16 hedgerows meet the criteria for ‘Important
Hedgerows’ under the Hedgerow Regulations (Defra 199732). With the exception of the
hedgerows either side of the A419, all the hedgerows were present on the 1846-1899 Ordnance
Survey Map (RS Figure 10.6a). The hedgerows either side of the A419, or adjacent to the M5,
were planted in the late 1960’s/early 1970’s when these roads were constructed. Full details of
hedgerows present are provided in RS Appendix 8.1.
Woodland
8.103 There are two small areas of broad-leaved woodland within the Development Footprint. The first
woodland to the north of A419 occurs between Field 2 and Field 5 (Woodland (RS Figure 8.14)).
Tree species present include Goat Willow Salix caprea, Pedunculate oak Quercus robur, Field
maple Acer campestre and saplings of Hawthorn Crataegus monogyna. The Field Maples have
32 The Hedgerow Regulations (1997) A guide to the law and good practice. DEFRA.
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 91
rot holes suitable for roosting in by bats. The ground flora is rank with abundant grass species,
bramble and some Rose Rosa species with very few woodland species present. The second area
of woodland to north of A419 has been truncated by the A419. There are several mature trees
present e.g. Pedunculate Oak, Ash Fraxinus excelsior, Field Maple, Poplar Populus spp. and Elder
Sambucus nigra. The ground here is in a dip, is muddy in places and has some species indicating
wetness e.g. Small Sweet Grass Glyceria declinata and Hairy Sedge Carex hirta. The ground flora
is overgrown with brambles and rank grassland but some remnants of a woodland flora are
present e.g. Violets Viola spp., Bluebell Hyascinthoides non-scripta, Lords and Ladies Arum
maculatum and Creeping Jenny Lysimachia nummularia. The full species list can be found in RS
Appendix 8.1; Annex 1D (Woodland (ii)).
8.104 There are two further areas of woodland on the boundary of the Development Footprint. These
areas are part of an embankment adjacent to the M5 roundabout, which extends beyond the
Survey Area boundary and are of recent origin (1977). A mixture of early mature broadleaved
species were found here including Field Maple, Hawthorn, Elm Ulmus spp., Ash, Poplar and Crack
Willow. The two areas form a broad shelter belt providing good screening (see RS Appendix 8.3
Arboricultural Report and RS Figure 8.1).
Trees
8.105 The small blocks of mature woodland within the Development Footprint contain mature Ash,
Pedunculate Oak, Field Maple and Hawthorn. These are marked on the 1845 1st Edition
Ordnance survey map (RS Figure 10.6a). The southern block of woodland was divided into two
parts with the construction of the A419 which opened in 1970-71.
8.106 There are also standard mature trees in a number of the hedgerows throughout the Survey Area
e.g. Ash, Field maple, Elm, Wild Pear Pyrus communis and Hawthorn.
8.107 An Arboricultural Survey was carried out in 2016 (RS Appendix 8.3). This identified eight Category
A1 trees (trees of high quality), 21 Category B (moderate quality) and 25 Category C trees (low
quality) or tree groups (RS Figure 8.1). Of note is the well-formed and broad roadside Oak, tree
T21 and other Oak trees T14 and T26 to T28 within the Development Footprint, which collectively
form a significant and large feature.
8.108 There is one large and old Ash tree which are classed as of high conservation value (T4), due to
size, age and features such as internal decay and cracks that provide valuable habitat for many
species of flora and fauna. These trees have been pollarded over many years and this has helped
them remain standing as well as increasing the number of potential wildlife-friendly features.
Pollarded Ash are also of significance through the County of Gloucestershire. Similarly, tree T3,
an ancient Oak in decline, provides numerous habitat features although it has been classed as
the lowest retention category (Category U; Trees with serious defects, or dead) within the British
Standard.
Grassland
8.109 The majority of the grasslands within the Development Footprint are improved, with some semi-
improved grassland present (MG7, MG7b, MG7d; Lolium perenne leys and related grasslands)
(RS Figure 8.15). A strip of grassland forming roughly a 30m margin along the western boundary
of Field 3 adjacent to the M5 was classified as MG6a, b (Lolium perenne-Cynosurus cristatus
grassland), which is less improved and characterised by Sweet Vernal Grass Anthoxanthum
odoratum (RS Figure 8.15). Fields 1, 2, 4 and 5 are predominantly MG7, but more disturbed areas
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 92
within 4 and 5 reflected OV 23 (Lolium perenne - Dactylis glomerata community) and OV 26
(Epilobium hirsutum community), due to heavy tractor movements within those fields (RS Figure
8.15).
8.110 There are ridge and furrow formations within the fields present, particularly in Fields 1, 2 and 5
(RS Figure 8.15). There are a mixture of wide medieval and narrow post-medieval (Napoleonic)
furrows, with both types present in Field 5 to the north of the A419. However, the botanical
survey did not identify any flora typical of ridge and furrow indicating that these have been
improved with fertilizers or possibly re-seeding.
8.111 The two verges along the A419 belong to Conservation Road Verge CRV009, designated by
Gloucestershire County Council in association with the Gloucestershire Wildlife Trust (GWT) and
GCER. This includes the roundabout on Chipmans Platt and beyond the M5 roundabout to the
A38 junction. The verges were surveyed in June 2016 and results showed that the verge north of
the A419 has a greater species diversity than the southern side, with 70 species recorded and
four indicator species. More hedgerow ground flora and wetland species are also present in the
northern verge. This corresponded with the most recent surveys carried out by the GWT in 2015.
Water courses
8.112 There is a water course (Selbrook, RS Figure 9.1) in the northwest corner of the Development
Footprint which flows south and the under the M5 and A38 and flows parallel to the River Frome
before entering the Frome at Wheatenhurst 3 km to the west of the site. This flows throughout
the year in a deep cut channel approximately 1.5m deep. It is heavily shaded by the adjacent
hedgerow with very limited flora. (RS Figure 8.15).
Baseline Ecological Conditions - Species
Flora
8.113 Bluebell Hyacinthoides non-scripta was the only protected plant species recorded during the
surveys on several hedgerows and woodland remnants to north and south of A419 (RS Appendix
8.1).
Amphibians
8.114 No ponds or standing waters holding water beyond early May 2015 were found within the Survey
Area. Water Samples for eDNA were collected from two water bodies in 2016; one from the west
of the M5 and one from the south of the A419. The test results from ADAS proved negative for
great crested newt DNA.
Reptiles
8.115 There is limited suitable habitat for reptiles within the Survey Area. Reptile surveys were
conducted in spring and summer 2016 and recorded very low numbers of grass snake and slow
worm adjacent to the A419 and west of the M5 (see RS Figure 8.16).
Water voles
8.116 Whilst the habitat along the River Frome is suitable, there was no evidence of water voles on this
section of the Frome. American mink, a major predator of water vole are still present in the
Severn Vale. However, with an increasing otter population in the Stroud Valleys there may be
future potential for re-colonisation of water vole in the local area. There is insufficient flow and
riparian habitat in the Selbrook adjacent to the Development Footprint site to support water
vole.
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 93
Hazel dormouse
8.117 There is very limited suitable habitat for use by hazel dormice within the Survey Area and no
ecological connections to suitable habitat or woodland where dormice are known to be present.
Badgers
8.118 Badger setts were found within the Development Footprint. A Confidential Badger Report is
provided with regard to this in the Confidential RS Appendix 8.4 and RS Figure 8.8, RS Figure
8.29 and RS Figure 8.30. The report and the figures are not publicly available.
Otters
8.119 Fresh otter footprints and spraints were recorded on rocks and wet mud adjacent to the River
Frome under the M5 River Frome Underpass and under the road bridge over the Frome on Spring
Hill during 2015 and 2016. The flow in the Selbrook is insufficient to provide suitable foraging
habitat for otter where it flows adjacent to the Development Footprint.
Bats
Endoscope surveys
8.120 A preliminary bat roost feature assessment of trees and buildings within the Survey Area was
carried out from ground level in 2016 with the aid of binoculars. This included looking for
woodpecker holes, rot holes, cracks, crevices, cavities, gaps between overlapping branches and
extensive areas of ivy on larger trees, signs of bats, such as staining or bat droppings below a
PRF, scent of bats or audible squeaking in suitable conditions. A total of 80 trees in the Survey
Area were surveyed for potential roost features (PRFs) of which 34 of these were within the
Development Footprint. Endoscope surveys were carried out on 20 trees with identifiable PRFs
(RS Figure 8.17) within Development Footprint. Inspections of PRFs were carried out up to 4m
above ground level with a telescopic ladder (Annex VI in RS Appendix 8.2). No bats or signs of
bats were found during the endoscope surveys. Emergence surveys were conducted on trees
with PRFs features above 4m. A visual assessment of the derelict farm buildings was carried from
safe locations. Limited suitable potential roost location were identified. Although no feeding
signs (moth wings or beetle carapaces) of horseshoe bats were found it was considered that
three of these barns could potentially provide suitable night roosts.
Emergence surveys on buildings and trees
8.121 Two emergence surveys and one re-entry survey was carried out on the derelict farm buildings
north of the Survey Area in June 2016. Emergence surveys were conducted on 52 trees (19 within
Development Footprint) and re-entry surveys conducted on 27 trees (6 within the Development
Footprint) (RS Figure 8.18 and Annex VI in RS Appendix 8.2).
8.122 No roosts were identified within the Development Footprint during the emergence, re-entry and
endoscope surveys. A single bat (Myotis sp. probably a whiskered/ Brandt’s bat based on the
echolocation), was recorded emerging from a group of old Field Maple (Hedgerow SH10, T81-
T89; south of the A419 (RS Figure 8.18) on one occasion. This tree is over 150m from the
Development Footprint. Evidence from emergence- and re-entry surveys indicate the bats using
the Development Footprint are from off-site roosts. During transect surveys and emergence
surveys bats were observed coming onto the Survey Area after sunset or leaving the Survey Area
just before dawn.
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 94
Transect activity surveys
8.123 Five bat activity transect surveys were conducted in 2015 and a further five activity transect
surveys were carried out in 2016, including a dawn re-entry survey (RS Figure 8.19).
8.124 At least ten bat species were recorded during the transects: common pipistrelle, soprano
pipistrelle, Myotis spp. (mainly Daubenton’s, but also Natterer’s Myotis natterer and
Whiskered/Brandt’s Myotis mystacinus/Myotis brandtii), noctule, lesser horseshoe, brown long-
eared and Leisler’s.
8.125 A low level of bat activity was recorded over most of the Revised Scheme area with
concentrations of activity close to suitable foraging areas such as woodlands, mature trees and
green lanes (double hedgerows with a track or footpath between the two hedgerows). Common
and soprano pipistrelle were the most frequently recorded species within the Survey Area.
However, there was a high level of Myotis spp. (Daubenton’s bat) activity adjacent to the River
Frome, particularly adjacent to the River Frome Underpass. This is, however, over 400m from
the Development Footprint. There were smaller numbers of noctule bat passes and several
Leisler’s passes. One lesser horseshoe pass and one long- eared bat pass was recorded during
the transect surveys. A visual summary of bat passes on activity transects in 2015-2016 is shown
in RS Figure 8.19.
Static surveys
8.126 Static detector surveys (2015 and 2016) obtained a total of 935 nights recording from detectors
placed at 62 different locations across the Survey Area as well as two locations on and adjacent
to Chipmans Platt roundabout (RS Figure 8.5). Paired static detectors were deployed at four
locations along the A419 in order to detect evidence of bats crossing the A419. Paired detectors
were also placed in the M5 Pedestrian Underpass and the River Frome Underpass under the M5
to discover if bats were using these. A total of 533 night’s recording from 34 locations were made
within or directly adjacent to the Development Footprint.
8.127 A total of 147,979 passes were recorded from all static locations in the Survey Area. The number
of bat passes ranged from zero to over 2,900 Myotis spp. passes per night (mainly Daubenton’s
at the River Frome Underpass). Overall Myotis spp. (mainly Daubenton’s) were the most
frequently recorded species although this was largely due to the high level of bat activity
recorded from locations adjacent to the River Frome (RS Figures 8.21 to 8.26 and Annex IV A in
RS Appendix 8.2.). A total 46,839 passes were recorded within the Development Footprint over
the two seasons of intensive static monitoring. (Annex VI in RS Appendix 8.2).
8.128 Within the Development Footprint, common pipistrelle are the most frequent species recorded
accounting for 74% of passes, soprano pipistrelle 10%, Myotis spp. 8%, noctule 5%, lesser
horseshoe 1.2 %, greater horseshoe 0.9%, serotine 0.01%, brown long-eared 0.2% and Nathusius
pipistrelle 0.04%( Annex IV f in RS Appendix 8.2).
8.129 There appear to be several Myotis species using the Survey Area. Daubenton‘s were recorded
foraging over the Frome, particularly at the River Frome Underpass. Based on calls only, it
appears that there are probably also Natterer’s and Brandt’s/Whiskered using the Survey Area
(RS Figure 8.23 and RS Appendix 8.2 Annex IV f).
8.130 Greater horseshoe was recorded along the northern boundary of the Survey Area, occasionally
along other hedgerows, adjacent to the open disused farm buildings on the northern boundary
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 95
of the site, as well as along the alignment of the disused Stroudwater Canal and under the
Pedestrian Underpass of the M5 (see RS Figure 8.26). Within the Development Footprint greater
horseshoe were recorded mainly along the northern boundary and within derelict farm buildings.
8.131 Lesser horseshoe were recorded in the open partially dilapidated farm buildings. They were also
recorded throughout the Survey Area along the old route of the canal, adjacent to the River
Frome, on the River Frome under the River Frome Underpass, and in the M5 Pedestrian
Underpass (see RS 8.21). Within the Development Footprint Lesser Horseshoe bats were
recorded along the northern boundary, within the derelict farm building and along the double
hedgerow.
8.132 A small number of serotine and brown long- eared bats were recorded, along with several
Nathusius pipistrelle.
8.133 Evidence from static and transect surveys indicates a generally low level of bats commuting along
hedgerows around the Survey Area. However, there was a concentration of activity when one or
two bats were feeding around mature trees, tall hedgerows, farm buildings, in the lee of the
small blocks of woodlands, over orchards north of the Survey Area or over the River Frome (RS
Figures 8.21 to 8.26 and RS Appendix 8.2 Annex IV f).
Bat use of the M5 Pedestrian Underpass
8.134 Paired bat detectors were placed within the M5 Pedestrian Underpass in June, July 2016 and
August, September 2016. These recorded a small number of greater horseshoe and lesser
horseshoe passes each night and provided evidence that a small number of these may have been
passing through the M5 Pedestrian Underpass (RS Appendix 8.2 Annex II location 16 location
46; RS Appendix 8.2, Table 8.2.8 - 8.2.10.). However, without radio-tracking, it is not possible to
categorically prove an individual bat is passing through the tunnel at a particular time. However,
the data collected provides evidence that the M5 Pedestrian Underpass is used by a small
number of lesser and great horseshoe bats to get from one side of the M5 to the other.
Assessment of bats crossing the A419
8.135 Paired bat detectors at four locations along the A419 recorded a relatively high level of bat
activity in some locations (common pipistrelle and Myotis spp.), close to the small block of
woodland either side of the A419 and by more recent woodland adjacent to the M5 junction.
There was evidence of a number of common pipistrelle crossing the A419 within the range of the
bat detectors (RS Appendix 8.2; Table 8.2.7a). A visual survey confirmed several common
pipistrelle and Myotis spp. crossing at locations 54-55 by the green lane on the eastern boundary
of the Survey Area and three bat species crossing at locations 52/53 between the blocks of
woodland adjacent to Junction 13 on the M5 (RS Appendix 8.2, Table 8.2.7b; RS Figure 8.5).
Noctule bats were regularly seen and heard flying high over the A419 during transect and
emergence surveys. There was no evidence of greater or lesser horseshoe bats crossing the A419.
Birds
8.136 A total of 52 species were recorded during the 2015 breeding bird survey of which 31 species
showed evidence of breeding (RS Appendix 8.2 Table 8.2.2; RS Figure 8.27 and RS Figure 8.28).
In 2016, 54 species were recorded of which 30 were recorded breeding. Most of the species
recorded breeding were common farmland or garden birds.
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 96
8.137 Five UK Red Listed species (herring gull, skylark, song thrush, house sparrow and starling) were
recording during the surveys but only song thrush was recorded breeding within the Survey Area.
House sparrow and starling were recorded breeding in dwellings just outside the Survey Area
boundary. A single skylark was recorded defending a territory outside the Survey Area south of
the River Frome in 2015 and 2016. Herring gull were recorded foraging after hay/silage was cut,
these were most likely from the breeding population on the factory roofs in Stonehouse
Industrial Estate. One reed bunting (Local BAP species) was recorded defending a territory south
of the River Frome to the south-west of the Survey Area.
8.138 Kingfisher, listed on Schedule 1 of the Wildlife and Countryside Act (1981) and Annex 1 of the
Birds Directive (1979), was recorded on the River Frome although the nest site was not recorded.
A pair made a successful breeding attempt along the river close to the Survey Area in 2015 as
young were observed. Little egret, which is listed on Schedule 1, was recorded foraging adjacent
to the River Frome in 2015 and 2016.
8.139 Within or directly adjacent to the Development Footprint 15 species of common farmland birds
were recorded breeding in both 2015 and 2016, including Song Thrush.
Design Evolution
8.140 Several aspects of the design evolution were modified to avoid significant negative effects on
habitats and species identified within the Development Footprint (embedded mitigation/
avoidance). Further account was also taken of the location of the ecological features described
above in order to ensure that effects on ecology were minimised and avoided through further
embedded changes to design. These included, for example, adjustment of the location of the
entrance to avoid a group of trees and adjustment to the stadium location and car park
arrangement to minimise hedgerow loss. The construction effects are defined in Table 8.7 in
this document.
8.141 The majority of mature trees will be retained both for their ecological and landscape value within
the Development Footprint. The placement of the road entrances from the A419 (Transport and
Access, Chapter 12) was designed to avoid the small woodland blocks along the A419 identified
during the Phase I Habitat Survey (RS Appendix 8.1).
8.142 Hedgerows SH1 and SH4 to the south of the A419 (RS Figure 8.14) and two Class A mature oak
trees (T59 and T60 RS Figure 8.1) and a further seven younger trees will be affected by the
widening of the A419. Prior to the carriageway widening, the hedgerows will be translocated
40m to the south of the original alignment. The translocation of this hedgerow rather than re-
planting will ensure rapid re-growth and retention of the ground flora (3-5 years). The road verge
will also be re-established from locally sourced seed banks e.g. from the Conservation Road
Verge CRV009. The majority of hedgerow NH6 and NH5 will be affected by the construction of
the stadium. The affected parts of these hedgerows will be translocated to a line parallel with
NH3 to re-create a new double hedgerow to retain ecological connectivity.
8.143 A bat commuting corridor will be created to provide commuting and foraging opportunities for
bats while preventing light spill. The bat corridor will incorporate a 2m bund on which the inner
hedgerows (the hedgerows closest to the built development) will be planted to prevent light spill
and act as a buffer against noise (enhancement).
Potential Effects
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 97
Potential construction effects to be assessed
8.144 A range of construction activities will be required for the various elements of the project (Chapter
5; Description of the Revised Scheme). These include temporary construction compound(s),
storage of construction materials, temporary access routes on and within the Development
Footprint, vegetation clearance, soil removal, ground and excavation work, establishment of
built structures, roads and car parking.
Table 8.7: Construction effects to be assessed
Construction Activity Effect Potential Effects on Receptors
General (Temporary) Noise, vibration,
movement and physical
disturbance of vegetation
Loss or disturbance of habitat and
fauna, runoff of silt and fine
sediment into water courses.
Foundations (Temporary) Noise, vibration,
removal or alteration of
habitat
Disturbance or loss of habitat
Built development
(including roads and car
parks)
Removal / overlaying of
vegetation
Loss of habitat runoff of silt and
fine sediment into water courses.
Construction Lighting Increasing lighting of dark
areas
Creation of ecological traps for
insects attracted to lighting,
disruption of foraging and
commuting routes due to
avoidance of light by certain bat
species.
Construction Compound Removal / overlaying of
vegetation
Loss of habitat
Potential operational effects to be assessed
8.145 Operational effects are defined in Table 8.8 as habitat- or species loss due to development
infrastructure.
Table 8.8: Operational effects to be assessed
Operating Effects Effect Potential Effects on
Receptors
Use of Stadium and Car
parking
Increased movement of cars and
people, noise and lighting
Disturbance to species
Service and Maintenance Vehicle movements / personnel on Site Disturbance to species
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 98
Operating Effects Effect Potential Effects on
Receptors
Lighting Increased lighting of dark areas Creation of ecological traps
for insects attracted to
lighting. Disruption of
roosting, foraging and
commuting routes by
certain bat species due to
avoidance of light.
Water run-off from
buildings and hard standing
Increased flow in the drainage ditches
within the Survey Area and River
Frome.
Increased silt, carried along
ditches and potential
damage to habitat
Ecological receptors to be considered
8.146 The ecological receptors (habitats and species) found on or adjacent to the Survey Area are
considered in this section. Receptors considered unlikely to be significantly affected by the
development have been scoped out of the assessment. These are listed in Table 8.9, along with
the reason for their removal.
Table 8.9: Ecological receptors scoped out of the Assessment
Ecological Receptor Nature
Conservation
Value/
sensitivity
Rationale for Scoping out of Detailed Assessment
Rodborough
Common SAC
High -
Internationally
important
calcareous
grassland
The development is over 6km from the SAC. There will be
no residential development and therefore no increase in
recreation pressure on Rodborough Common.
Cotswold Beech
Woods SAC
High-
Internationally
Important Beech
Woods
The development is over 10km from the SAC. There will be
no residential development and therefore no increase in
recreational pressure on the Cotswold Beech Woods SAC.
There will be no heavy industrial processes, producing
increased levels of air pollution and will therefore not add
to the cumulative air pollution effect on the SAC (See
Chapter 13 Air Quality).
Severn Estuary
SPA/Ramsar
High
International
Importance for
wintering water
fowl
There will be no direct loss of habitat within the SPA
boundary. During construction there is potential for noise
and disturbance, however the Development Footprint is to
the east of the A38 and M5 from the estuary and over
3.8km away (straight line distance), therefore there will be
no noise or visual disturbance to wintering waterfowl.
There is a hydrological connection between the Revised
Scheme and the SPA, but as the Key Wildlife Site is acting as
a buffer and, providing no pollution is allowed to enter the
watercourse, it is probable that likely significant effects can
be screened out).
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 99
Ecological Receptor Nature
Conservation
Value/
sensitivity
Rationale for Scoping out of Detailed Assessment
The football stadium will attract an increase in numbers of
people to the area, but any increase in road traffic will be
sufficiently distant from the estuary to have no effect on
wintering waterfowl. The new football stadium will be lit at
certain times; however, the level of lighting will not reach
the estuary. Therefore, it is considered the development
will have no effect on the Severn Estuary SPA.
Frampton Pools SSSI High: National
importance for
wetland plants
and wetland
birds.
There is no hydrological connection between Development
Footprint and Frampton Pools SSSI; therefore, the Revised
Scheme will have no effect on the water quality of the SSSI.
Frampton Pools is separated from the site by an area of
woodland, an old gravel working currently being used for
inert landfill, a very active lorry depot, a mineral extraction
site as well as the A38 and M5. Therefore, it is considered
that there will be no disturbance to wetland birds from
either the construction or operation of a stadium.
Haresfield Beacon
SSSI
High There will be no development in or adjacent to SSSI and
there is no hydrological connection.
Rodborough
Common SSSI
High There will be no development in or adjacent to SSSI and
there is no hydrological connection.
Edge Common SSSI High There will be no development in or adjacent to SSSI and
there is no hydrological connection.
Minchinhampton
Common SSSI
(botanical interest)
High There will be no development in or adjacent to SSSI and
there is no hydrological connection.
Coaley wood
Quarries SSSI
High There will be no development in or adjacent to SSSI and
there is no hydrological connection.
Garden Cliff SSSI High There will be no development in or adjacent to SSSI and
there is no hydrological connection.
Selsley Common
SSSI
High There will be no development in or adjacent to SSSI and
there is no hydrological connection.
Otter High Present but there will be no development within a distance
of c. 400m of River Frome.
Water Vole High Not currently present on this section of River Frome.
Hazel Dormouse High No records close to Survey Area and very limited suitable
habitat. Non-recorded on surveys on the adjacent WOS site
Amphibians Local Some ephemeral ditches were found within the Survey
Area although these had dried up before the main breeding
period.
Great crested newt High No suitable ponds within the Survey Area, no evidence of
great crest newt DNA from suboptimal water bodies.
Identified construction effects
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 100
Statutory Designated Sites of International Importance: Severn Estuary SAC
Evaluation and assessment of potential effects and significance
8.147 The SAC is over 3km from the Development Footprint, therefore there will be no direct
disturbance or habitat loss during construction. There will be no construction within 400m of the
River Frome. Therefore, during construction, there is very limited potential for increased run-off
of sediment, fine silts or contaminated water via the streams or as run-off into the River Frome,
and ultimately the SAC during construction. The Selbrook flows along the northwest corner of
the Development Footprint which flows south under the M5 and A38 and flows parallel to the
River Frome before entering the Frome at Wheatenhurst 3 km to the west of the site. There will
be no built development within 150 m of the Selbrook, however the northern practice pitch will
be constructed within 10m of this water course. Therefore, there is a very low potential risk for
silt run- off. It is considered highly unlikely that any fine silts, sediments or chemical
contamination will enter these water courses or reach the River Severn SAC 3km downstream.
Given the massive volume of silt moving up and down the estuary on each tide the volumes
involved would be insignificant.
8.148 Therefore, there will be no potential negative effect on Sea Lamprey, River Lamprey and Twaite
shad and therefore the effect is not significant. However, a precautionary approach has been
taken.
Mitigation
8.149 Despite the effects being considered not significant, a precautionary approach will be adopted.
A detailed Construction Environment Management Plan (CEMP), including a Pollution Prevention
Plan will be developed and agreed with the LPA and the Environment Agency prior to
commencement of development and secured by condition as part of any permission granted. An
Ecological Clerk of Works (ECoW) will be employed to ensure this is fully implemented.
8.150 Suitable Sustainable Drainage Systems (SuDS) will be installed throughout the Revised Scheme.
Where necessary, this will include silt and oil traps (see Chapter 9, Flood Risk, Hydrology and
Drainage). Therefore, it is certain there will be no significant effects of the Severn Estuary SAC.
Residual significance
8.151 There is no residual significance.
Statutory Designated Sites of National Importance: Woodchester Park SSSI
Evaluation and assessment of potential effects and significance
8.152 Woodchester Park SSSI is designated principally for a breeding colony of greater horseshoe bats
within the Mansion, deciduous woodland and semi-improved grassland and associated species.
The Mansion building also supports a large breeding colony of lesser horseshoe bats although
these are not included in the citation. This SSSI is just over 5km from the Development Footprint,
although within 5km of the proposed cycle path improvements. There will be no direct loss of
habitat to this SSSI. Greater horseshoe bats tend to forage within 2-3km of maternity roosts33.
The habitat close to the breeding roost at Woodchester Mansion within the SSSI is specifically
managed for bats and highly suitable for greater- and lesser horseshoe bats. Therefore, it is highly
33 Duvergé, L. & Jones, G. 1994. Greater Horseshoe Bats – Activity, foraging behaviour and habitat use. British
Wildlife,6,69-77.
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 101
unlikely that individuals from Woodchester Park SSSI will forage as far as the Development
Footprint during the breeding season. However, individual greater horseshoe bats including
young regularly use hibernacula sites in the Forest of Dean. It is unknown where these bats cross
the M5. The greater width of motorways may make them more effective barriers than a road for
bats (Berthinussen & Altringham 201234). The River Frome Underpass and the Pedestrian
Underpass under the M5 therefore may provide safe crossing points for bats.
8.153 There is no development within 400m of the River Frome and no development within 250m of
the M5 Pedestrian Underpass, therefore it is considered highly unlikely that there will be any
negative effects from construction on the potential use of the River Frome Underpass or the M5
Pedestrian Underpass by bats.
8.154 Therefore, prior to mitigation it is considered that there will be no significant negative effect on
bats from Woodchester Park SSSI. However, a precautionary approach will be taken and secured
by condition as part of any permission granted. Any lighting required for safe working will be of
low intensity and only be used within or directed into the construction area.
Residual significance
8.155 There is no residual significance.
Statutory Designated Sites of National Importance: Minchinhampton Common SSSI
Evaluation and assessment of potential effects and significance
8.156 Minchinhampton Common SSSI is designated principally for its unimproved, herb-rich limestone
grassland and geological importance of disused quarry workings. Potential effects on the
grassland or geological interest has been scoped out of this assessment. The citation, however,
does also mention the disused stone mines on the Nailsworth side of the Common are used as
winter roost sites by greater horseshoe bat. Minchinhampton Common is over 8km from the
Survey Area and there is no hydrological connection to this, therefore the Revised Scheme will
have no effect on the botanical or geological interest of the SSSI. Whilst greater horseshoe bats
may travel up to 10km in winter in search of roosts with the correct temperature and feeding
opportunities35, there are no suitable roosting caves within the Development Footprint and there
are large tracts of high quality bat foraging habitat between Minchinhampton Common and the
Development Footprint. Therefore, it is considered there will be no negative effect on this SSSI
during construction and the effect is therefore not significant. However, as noted for
Woodchester Park SSSI, a precautionary approach will be taken. Any lighting required for safe
working will be of low intensity and only be used within or directed into the construction area to
avoid any disruption if these bat species are crossing the site and secured by condition as part of
any permission granted.
Residual significance
8.157 There is no residual significance.
34 Berthinussen A, Altringham J. 2012a. The effect of a major road on bat activity and diversity. Journal
of Applied Ecology 49, 82-89.
35 Ransome, R. D. 1991. Greater horseshoe bat. In: The Handbook of British Mammals (G. B. Corbet & S. Harris
eds.), pp. 88-94. Oxford: Blackwell.
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 102
Non-Statutory Designated Sites (County Importance) - Evaluation and assessment of potential
effects and significance
River Frome and River Frome Mainstream Tributaries KWS
8.158 The development will be approximately 270m from the designated KWS River Frome and River
Frome Mainstream and Tributaries (RS Figure 8.6). Whilst there is potential for increased
sediment run-off, fine silts or contaminated water during construction, there will be no built
development within 400m of River Frome and no direct drainage ditches from the development
to the River Frome. Therefore, it is considered highly unlikely that any run –off will reach the
River Frome. Whilst this is considered not significant, a precautionary approach has been
adopted.
Precautionary mitigation
8.159 A detailed Construction Environmental Management Plan (CEMP), including a Pollution
Prevention Plan will be developed and agreed with the LPA and the Environment Agency prior to
commencement of development and secured by condition as part of any permission granted. An
Ecological Clerk of Works (ECoW) will be employed to ensure this is fully implemented.
8.160 Suitable SuDS will be installed throughout the Development Footprint. Where necessary, this will
include silt and oil traps (see Chapter 9, Flood Risk, Hydrology and Drainage). Therefore, it is
certain there will be no significant effects on the KWSs River Frome and River Frome Mainstream
and Tributaries.
Residual significance
8.161 There is no residual significance.
Habitats – Hedgerows - Evaluation and assessment of potential effects and significance
8.162 Whilst most of the boundary hedgerows are intact, some of the internal hedgerows have become
gappy and defunct due to lack of maintenance and cattle damage. The hedgerows are important
for ecological connectivity within the Survey Area and the surrounding area and are considered
to be of local importance. Embedded mitigation (avoidance) as part of the Revised Scheme
retains 1,900m of internal hedgerows (RS Figure 8.2). However internal hedgerow NH1, NH3
NH5, NH6, NH10, NH11, NH 12 and NH15 will be affected by the Revised Scheme (see RS Figure
1.4 and RS Figure 8.2). In addition, SH4 and SH1 directly to south of A419 will be affected by the
creation of an access junction with the A419. Construction works close to hedgerows present a
risk of damage to both hedgerows and associated ground flora. Whilst there is potential loss of
internal hedgerows, they are considered to be only of local importance. However, it is still
moderate and therefore significant at a local level.
Mitigation
8.163 While the exact layout of the development will be subject to a Reserved Matters Application the
approach to hedgerows will be to ensure that those hedgerows affected will be translocated and
where appropriate enhanced with additional planting to improve species diversity. Based on the
current layout of 3,200m of existing hedgerows 1,900m will be retained. A total length of
approximate 1,300 m of hedgerows (including woody species and ground flora) will be
translocated to new locations. These hedgerows will be supplemented by woody hedgerow
species of local provenance to ensure each hedgerow provides pollen and nectar throughout the
spring, summer and autumn.
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 103
8.164 Translocating the hedgerow rather than planting a new hedgerow will mean quicker re-growth
(3-5 years) and ensure any negative effects from this are short term rather than medium term.
8.165 In addition, part of the mitigation for bats will involve creating a commuting route for bats across
the site which will involve planting of approximately 1,800 m of new hedgerow. Consequently,
there will be approximately 5,000m of hedgerow post development an overall net gain of 56% %
in the length of hedgerows within the Development Footprint over the medium term (up to
seven years. All retained hedgerows, translocated and new hedgerows will be taken into
conservation management to enhance their ecological value and connectivity throughout the
Development Footprint. The management will be hedgerow-specific but will include planting up
gaps with native broadleaved species, together with cutting and potentially laying on a 4-7 year
rotation. The aim will be to create tall (4m), thick hedgerows.
8.166 To avoid damage to hedgerows and associate ground flora, all hedgerows to be retained will be
fenced off prior to the commencement of construction at least 2m from the boundary of the
hedgerow. This will also protect ground flora and grassland margins to the hedgerows.
Residual significance
8.167 There is no residual significance
Habitats – Grassland
Evaluation and assessment of potential effects and significance
8.168 The majority of the grassland within the Development Footprint is agriculturally improved
(species- poor) with some semi-improved grassland. This is considered as important within the
site. The grassland to south of the A419 adjacent to river Frome and west of M5 may be
considered of local importance. The exact layout of the development will be subject to reserve
matter applications, however with the current layout there will be a permanent loss of
approximately 12.6ha of mostly improved and some semi improved grassland for the Stadium
training pitches car parking and access to the Stadium Complex. The remaining area of the
grassland south of A419 (13.4ha) will be unaffected by construction. Approximately 5.4ha of
grassland to north of A419 will be enhanced and restored to species rich grassland.
8.169 Given the low nature conservation value of the grassland affected by the development, the
effects are not considered to be significant. However, a precautionary approach will be
implemented, and a number of measures will be taken to avoid damage, restore and re-create
species- rich grassland with the Development Footprint secured by condition as part of any
permission granted.
8.170 The hierarchy of grassland conservation is set out below:
• Areas of grassland unaffected by development will be fenced to protect from
construction work.
• Where semi-improved grasslands are to be removed for development, it is proposed that
the turfs of the semi-improved grassland will be cut and set aside to re-turf disturbed
areas after construction.
• Where this method of grassland re-establishment is not possible, it is proposed to re-
seed disturbed areas with species-rich seed mixes and/ or green hay from local sources.
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 104
Potential sources would include the species-rich embankments on Junction 13 or the
Chipmans Platt roundabout.
Residual significance
8.171 There is no residual significance.
Woodland and Trees
Evaluation and assessment of potential effects and significance
8.172 There are a number of mature trees within the three small woodland blocks within the
Development Footprint; two on the north of the A419 (Woodland I and Woodland II,) and one to
the south of the A419 (Woodland III, RS Figure 8.14). There are also a number of mature Ash,
Oak and Field Maple within hedgerows throughout the Survey Area (RS Appendix 8.3). The
woodland and hedgerow trees within the Survey Area are considered to be of local importance.
The embedded design principle of the Revised Scheme is one of avoidance to reduce the loss of
woodlands and mature trees during development. The main access point to the Development
Footprint has been relocated and the small blocks of woodland are to be retained. The layout of
the stadium and of the concourse ensure minimal loss and retention of mature trees within the
design.
8.173 The construction of the Stadium will result in the loss of one mature Ash tree T32. The proposed
dualling of the A419 and the provision suitable visual splays for the access will potentially affect
nine trees adjacent to the A419. Of these T59, T60, and T67 are classed as Category A (trees of
high quality). The Category A trees have been assessed for conservation value and T59 (A) and
T60 (A) were considered to be of conservation value to the Survey Area as these are mature Oak
trees which were present on the OS Ordnance Survey maps dated 1842-1852 (RS Figure 10.6a).
The Category B and Category C trees are not of high conservation value. Trees within the Survey
Area have been assessed for bat roost potential with a follow up endoscope survey (RS Figure
8.17 and RS Appendix 8.2 Annex VI). Trees T59, T60 and T61, likely to be affected by the creation
of visual splays, do not have features of bat roost potential. Trees T2 Oak and T2 Hawthorn are
likely to be affected by the construction of the car park although the exact layout of the car park
will be subject to a reserved matter application
Mitigation
8.174 The two mature Oak trees of conservation interest (T59, T60) that will potentially be affected by
the widening of the A419 will be translocated to a suitable position along the translocated
Hedgerow HN4.
8.175 The loss of the seven younger trees in Hedgerow adjacent to A419 will be compensated by
further planting. There will be extensive tree planting of approximately 400 native deciduous
trees throughout the development plus approximately 100 native fruit trees of local provenance
to ensure a net significant gain of in biodiversity of over 500% in term of the number of native
deciduous trees.
8.176 Fencing off all important trees and groups of trees of nature conservation interest will be carried
out observing Root Protection Areas (RPA) (as per the Arboricultural Survey RS Appendix 8.3)
before construction.
Significance of residual effects
8.177 There will be no residual significance.
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 105
Rivers and water courses
Evaluation and assessment of potential effects and significance
8.178 The River Frome corridor is considered of county importance by virtue of its designation as a Key
Wildlife Site. However, this is 400m from the Development Footprint and therefore it is
considered highly unlikely (RS Figure 8.14 and RS Figure 9.1) that during construction there will
be run-off of sediment, fine silts or contaminated water directly into the Frome. There is one
small water course (the Selbrook) on the north-western boundary of the Development Footprint.
This flows under the M4 and flows parallel to the River Frome before entering the Frome at
Wheatenhurst 3 km to the west of the site. The Selbrook is considered to be of local importance
although any fine silts or contaminated water could enter the River Frome and therefore
eventually the Severn Estuary SAC. The Selbrook is of local importance, although it has
hydrological connection to an internationally important site.
8.179 There will be no built development within c. 150m of the Selbrook, however the northern
practice pitch will be constructed within 10m of this water course. Therefore, there is a potential,
but very low risk, for silt run- off. This risk will be considerably lower than run-off from the normal
arable cultivation of the field which will be to within 1-2m of the water course boundary. It is
considered highly unlikely that any fine silts, sediments or chemical contamination will enter
these water courses or reach the River Frome. Whilst any risks are considered extremely unlikely,
and therefore not significant, a precautionary approach has been taken.
Mitigation
8.180 A detailed Construction Environmental Management Plan (CEMP) including a Pollution
Prevention Plan will be developed and agreed with the LPA and the Environment Agency prior to
commencement of development (secured by condition as part of any permission granted) and
an ECoW will be employed to ensure this is fully implemented. SuDS will be employed throughout
the Development Footprint (see Chapter 9 Hydrology).
Residual significance
8.181 There is no residual significance.
Protected Species – Bats
Evaluation and assessment of potential effects and significance
8.182 At least ten species of bat were identified during the activity transects and at least twelve species
during static surveys. The transect survey recorded low numbers of bats commuting along
hedgerows with the Development Footprint with a concentration of activity when one or two
individual bats where found foraging. These concentrations in activity were at suitable foraging
locations close to woodlands, mature trees, green lanes and around farm buildings. The static
surveys found a similar pattern of activity to transect surveys. There was a relatively low level of
activity throughout most of the Survey Area but with a higher level of activity adjacent to higher
quality bat habitat such as mature trees, the River Frome and tall hedgerows. A very low level of
activity of both greater horseshoe and lesser horseshoe bats was recorded (See RS Appendix 8.2
for full details). There was no evidence of active roosts within the Development Footprint. The
area is therefore considered to be of local importance of foraging bats.
8.183 The removal of mature trees during construction could pose a direct threat to potential roosts
and breeding behaviour, and a risk of injury or death to any bats in a roost. There is no evidence
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 106
of roosts within the Development Footprint. Therefore, there will be no direct effect on breeding
bats, risk of death or injury from the removal of trees within the Development Footprint.
However, the loss of trees and hedgerows could potentially reduce foraging habitat and possibly
commuting routes.
8.184 The use of lighting during construction could interfere with commuting patterns of bats and
disrupt breeding behaviour, particularly those species sensitive to light, which are all Myotis
species and greater- and lesser horseshoe bats. However, the number of greater- and lesser
horseshoe bats using the Development Footprint is very low and therefore the effects on this
species are likely to be very limited. There is no evidence of breeding roosts on the area of the
Development Footprint, and therefore there will be no direct effects on breeding success from
lighting.
8.185 Therefore, prior to mitigation lighting during construction could have a moderate negative effect
on bats using the Development Footprint, which would be considered as significant.
Avoidance and Mitigation
8.186 The embedded mitigation (avoidance) as part of the Revised Scheme retains the majority of the
mature trees.
8.187 The embedded mitigation also includes the translocation of hedgerow lengths. Whilst there will
a temporary loss of these commuting features, translocation rather than re-planting will ensure
rapid re-growth of these hedgerows which should provide a suitable commuting feature within
3-5 years. Hedgerow lost will be replaced with a great length of hedgerow of similar species and
new hedgerow will be planted as part of the bat commuting corridor. There will be a 56% net
gain in the length of hedgerow.
8.188 Hedgerows to be retained will be fenced during construction to prevent accidental damage. The
positive management of retained hedgerows and planting of new hedgerows throughout the
Development Footprint, combined with retention, enhancement and creation of species-rich
grassland, will minimise any losses of foraging habitat and enhance the quality of the retained
habitat. The creation of linear orchards and parkland habitat throughout, combined with the
creation of ponds in dark unlit areas, will provide new foraging habitats within the Development
Footprint.
8.189 A commuting corridor for bats will be created along the northern boundary of the site to create
an unlit commuting route through the site. This is close to an existing orchard outside the
northern boundary adjacent to the proposed new orchards.
8.190 New roost sites including potential maternity roosts suitable for pipistrelle, Myotis and noctule
bat species will be provided in suitable unlit locations (typically on large mature trees) using
woodcrete bat boxes.
8.191 Any lighting required for safe working will be limited to winter use when bats are hibernating. If
construction lighting is required during the summer months, this will be of low intensity and only
be used within the construction area.
Residual Significance
8.192 There will be no residual significance.
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 107
Protected Species - Badgers
Evaluation and assessment of potential effects and significance
8.193 Precise locations of badger setts within the Survey Area are to be found in the confidential
document RS Appendix 8.4. The main sett was occupied in 2015, 2016 and 2017 whilst the
outlying sett was unoccupied in 2016 and 2017. The Severn Vale and the Stroud Valleys support
a very high density of badgers. The value of the Development Footprint in terms of badgers is
considered to be at the local level.
8.194 The potential effects of the development will be (a) disturbance of the active main sett and
possibly the outlier sett if it becomes re-occupied and (b) removal of foraging habitat. Surveys
during 2016 indicated that there were several preferred foraging areas outside the Survey Area.
8.195 The main sett will not be directly affected by construction. Surveys will be conducted in the
appropriate season prior to construction. If there are new active entrances within 20m of any
proposed works a precautionary approach will be taken and appropriate mitigation implemented
to ensure there will be no disturbance during development to the main sett.
8.196 The removal of 12.6ha of improved or semi-improved grassland during construction could
potentially result in the loss of foraging habitat for badgers within the Development Footprint.
However, this will leave over 30 ha within Ecotricity’s land holding unaffected. It is therefore
considered that any effects on badger will be negligible and not significant. However, a
precautionary approach will be adopted, and badger surveys will be conducted in the
appropriate season prior to construction.
Residual Significance
8.197 There is no residual significance.
Protected Species - Birds
Evaluation and assessment of potential effects and significance
8.198 The number and composition of the breeding birds recorded is very typical of this type of habitat
over large parts of lowland England and is therefore considered of local importance. The
distribution of nesting birds varied between 2015 and 2016.
8.199 The removal of sections of internal hedgerow will result in a loss of potential breeding habitat
for a number of common farmland birds. There was one red listed species (song thrush) recorded
breeding within the Development Footprint. This was within a mature Oak which will be retained
as part of the development
8.200 The removal of sections of hedgerows whilst birds are nesting (1st March-31st August)) would
be a contravention of the Wildlife and Countryside act 1981 and therefore considered significant.
8.201 There will be no built development within c.400m of the River Frome and therefore there will be
no effect on breeding kingfisher (Schedule 1 species).
8.202 The house sparrow and starling are both tolerant of human disturbance and were breeding
within domestic properties outside the Survey Area boundary and therefore will not be disturbed
by construction works.
Mitigation
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 108
8.203 Careful design of the development has ensured no net loss of hedgerows and trees. Any
hedgerow removal and translocation will be completed outside the bird breeding season (March
to August inclusive). If for unforeseen reasons works on hedgerows are required during the bird
breeding season, detailed breeding bird surveys will be conducted prior to commencement. If
active nests are located, works will be delayed until the young have fledged or the breeding
attempt has failed.
Residual significance
8.204 There is no residual significance.
Protected Species - Reptiles
Evaluation and assessment of potential effects and significance
8.205 No reptiles were recorded to the north of the A419, however a small population of grass snake
and slow worm was identified using the hedgerow to the south of the A419. Slow worm and
grass snake are relatively common in suitable habitat within the Severn Vale. This population is
considered to be of local importance. The translocation of the hedgerow and the Conservation
Road Verge directly to the south of the A419 will pose a direct risk of disturbance, injury or death
to both grass snake and slow worm and loss of habitat. Therefore, prior to mitigation that there
will be a significant negative effect on reptiles.
Mitigation
8.206 It is proposed that any reptiles using the hedgerow and the road verge to the south the A419 will
be trapped and translocated following appropriate guidance to a suitable nearby location, such
as the land to west of M5 within the Redline boundary or the banks of the river Frome.
Significance of residual effects
8.207 There is no residual significance.
Operational effects
Non-Statutory Designated Sites
Evaluation and assessment of potential effects and significance
8.208 The River Frome is considered of county importance by virtue of designation as a Key Wildlife
Site. There will be no development works within c. 250m of boundary of the Key Wildlife Site.
There is one water course (the Selbrook) which flows from the northwest boundary of the
Development Footprint flows under the M5 and then parallel to the river Frome before entering
the Frome at Wheatenhurst 3 km to the west of the site into the Frome. There is no built
development proposed within 150m of the Selbrook although the closest training pitch is within
10m from this water course. All training pitches will include internal watering and drainage
systems and therefore there will be no run-off from these into the Selbrook or into the River
Frome Key Wildlife Site. Therefore, will be no significant effect on the River Frome Key Wildlife
Site. Whilst any risks are considered extremely unlikely, and therefore not significant, a
precautionary approach has been taken.
Mitigation
8.209 A Pollution Prevention Plan will be developed and agreed with the LPA and the Environment
Agency prior to commencement of development and an ECoW will be employed to ensure this
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 109
is fully implemented. SuDS will be employed throughout the Development Footprint (see ES
Chapter 9 Hydrology) secured by condition as part of any permission granted.
Protected Species – Bats
Evaluation and assessment of potential effects and significance
8.210 No bat roosts were identified within the Development Footprint, which has been identified as of
local importance for foraging and commuting bats. Bats can be affected by light while commuting
and foraging. There will be no lighting required for the training pitches, however there will be
external lighting required for the Stadium, car parking and access routes within the site. The use
of external lighting will be greatest during the winter months when bats are hibernating and
there are no bats using the Development Footprint. However, lighting during the shorter spring
and autumn nights may have a negative effect on the use of the Development Footprint by bats
sensitive to white light (Stone 201336).
8.211 A Baseline survey on lighting found that there is low background level lighting within the
Development Footprint at present. Expected levels of lighting within the Development Footprint
for the stadium, public car park, general roads, private roads and footpaths are given in Table
14.1 (Guidance Illumination Levels of each Task areas) vary between an average of 5 lux in
footpath and amenity areas to 25 lux in car parks and 500 lux within the stadium
8.212 Whilst most bats tend to avoid brightly lit areas, almost certainly to avoid predators, some bats
such as Pipistrelle sp. and noctule frequently feed on insects attracted to lights and may benefit
from the introduction of lighting. However certain bat species particularly of the genera
Rhinolophus (horseshoe bats,), Plecotus (e.g. Brown long-eared bat) and Myotis species avoid
areas with light levels likely to found within part of Development Footprint (Stone 2013).
Therefore, there may be a moderate negative effect on commuting or foraging Myotis and
Horseshoe species during matches in early spring or late autumn which would be considered as
significant.
8.213 There will be no development south of the A419 and therefore there will be no effect on the
River Frome Underpass or the M5 Pedestrian Underpass which were identified as potential
routes for Horseshoe bats to cross the M5. Therefore, it is considered that there will be no risk
to Greater and Lesser horseshoe bats potentially crossing the Survey Area to hibernation roosts
in the Forest of Dean.
8.214 The loss of internal hedgerows could reduce the length of suitable foraging habitat or disrupt
commuting routes. The area of the Development Footprint is considered as being of local
importance for foraging bats and therefore the negative effects of the removal of a number of
internal hedgerows is likely to be substantial to moderate and therefore significant.
Mitigation
8.215 Embedded mitigation (avoidance) in the design will ensure retention of the majority of mature
trees within the Development Footprint. The hedgerows affected by the Revised Scheme will
either be translocated where appropriate, or replaced with hedgerows of equal length and
36 Stone E. L. (2013) Bats and lighting. Current evidence and mitigation guidance. University of Bristol.
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 110
similar species composition. The creation of species- rich grassland, water bodies and parkland
woodland around the stadium will provide new habitat for foraging bats.
8.216 Embedded mitigation through the creation of a commuting corridor for bats in the north of the
Development Footprint (RS Figure 5.3, RS Figure 5.6 and RS Figure 8.2) will allow bat species that
avoid light to commute across the area of the Development Footprint. These will take the form
of a bund planted with dense hedgerow species on the side of the corridor closest the
development. It will also incorporate a narrow open path 1-2m wide and second hedgerow on
the outside (see RS Figure 5.6). Lighting throughout the Revised Scheme will be designed and
used to minimise effects on bats, and enhancements will include:
• Lighting of the junction on A419 will be directed onto the carriageway through the
inclusion of back plates and directional lighting to minimise spill.
• There is a provisional curfew for the Development Footprint of 21.00 (likely to be a
condition at Reserved Matters)
• Lighting throughout the Development Footprint will be designed to minimise horizontal
spill of light by use of back shields and louvers to direct light spill way from hedgerows,
woodlands, new ponds and areas of species-rich grassland.
• The use of bright white and ultra-violet light will be avoided where appropriate.
• Dimmed and reactive lighting and variable lighting regimes will be used where
appropriate.
• The roads within the Development Footprint will be private and therefore lighting will be
under control of the Facilities Manager and will be switched off when not required.
During the bat activity period April-October, this can be managed automatically or be
reactive by use of road loops.
• Car parking areas will only be lit when required.
8.217 The implementation of the mitigation and enhancement measures will reduce the significant
effect to negligible and not significant.
Residual Significance
8.218 There is no residual significance.
Major Accidents and Disasters
8.219 An assessment has been undertaken of any potentially significant adverse effects on the
environment deriving from the vulnerability of the development to risks of major accidents and/
or disasters in Chapter 17.
8.220 Given a number of proposed design and operational measures, which are all considered and
reported in the assessment, it is not anticipated that the Revised Scheme is vulnerable to any
major accidents and/ or disasters which could result in significant effects on the environment.
8.221 In relation to biodiversity large spillage of materials, particularly liquids, could in theory result in
significant adverse effects on environmental receptors such as the river Frome Key wildlife site
or the River Severn SAC. However, given the distance from the stadium and associated
infrastructure to the river Frome and the Severn Estuary SAC any risks are considered extremely
unlikely, and therefore not significant. However, a precautionary approach has been taken and
Pollution Prevention Plan will be developed and agreed with the LPA and the Environment
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 111
Agency prior to commencement of development secured by condition as part of any permission
granted.
Climate Change
8.222 A detailed assessment has been undertaken of the potential effects of the Revised Scheme on
climate change (‘climate change mitigation’) and of the vulnerability of the Revised Scheme to
climate change (‘climate change adaptation’) in Chapter 16.
8.223 Natural England published its ‘climate change risk assessment and adaptation plan’ report in
2015, part of the statutory requirement on Government Agencies to provide such advice, arising
from the Climate Change Act 2008. In the report Natural England sets out the risks and threats
posed by current climate change predictions and how the agency proposes to respond to them.
As part of its strategy Natural England recognises that climate change offers opportunities as well
as threats. For instance:
“There is an opportunity to facilitate landscape change in ways that create valuable new
landscapes that are more resilient to climate change and deliver improved benefits for society
(sense of place, biodiversity and other ecosystem services).”
8.224 Increased rainfall and flooding events, coupled with rising temperatures, are likely to modify UK
flora and fauna over time. Habitat management measures can be introduced to cope with and
adapt to the anticipated change. Such measures form part of the SUDS proposals (embedded
mitigation) for the Revised Scheme, which will be the subject of detailed design at the Reserved
Matters Application stage. This will include details of climate change adaption measures at this
particular location, for example by specifying suitably resilient plant species or pollinator species
suitable for invertebrates shifting their range northward, so as to exploit the opportunity climate
change presents to create ‘valuable new habitat’.
8.225 Other climate change adaption measures relating to green infrastructure / ecosystem services,
which form part of the embedded mitigation and promote a quality and healthy environment,
are set out in the landscape strategy at RS Appendix 8.7 and Green Infrastructure Plan RS
Appendix 8.5. These measures include extensive tree planting to establish a ‘parkland’
landscape, species rich meadows, wildlife corridors and orchards. Ponds will create shade for
cooling effects and sequestrate carbon.
Statement of residual significance
8.226 The potential residual significance of the Revised Scheme is detailed in Table 8.10 in this chapter.
Proposed additional monitoring
8.227 There will be a programme of ongoing ecological monitoring to assess delivery of biodiversity
targets for the Revised Scheme. Habitat management programmes will be modified as required.
Biodiversity enhancements
8.228 There will be a wide range of potential biodiversity enhancements, as outlined in the Green
Infrastructure Plan (RS Appendix 8.5) and bulleted below. These will be developed subject to
detailed design and assessment as part of Reserved Matters Applications.
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 112
• 1,800m of new hedgerow planting.
• Enhancement/positive management of existing hedgerows.
• Planting of native hedgerow ground flora.
• Creation of new night roosts to maintain and extend foraging area of greater horseshoe
and lesser horseshoe bats.
• Sowing of species-rich grassland using seed of local provenance.
• Planting of native broadleaved trees throughout.
• Creation of orchards to the north of the stadium, training pitches and car parking
• Installing bat boxes and bird nesting boxes on suitable trees throughout the Development
Footprint.
• Creation of flower-rich verges throughout from locally sourced seed.
• Enhancement of the Development Footprint for invertebrates, particularly butterflies and
bees through native wild flower and shrub planting.
• Creation of hibernacula for reptiles.
• Use of Sustainable Drainage (SuDS) throughout the Development Footprint.
• Ongoing monitoring and maintenance programme.
8.229 An Environmental Enhancement Plan has been written to give indicative illustrations of how
some of these habitat mitigation, management and enhancement will be carried out at. This is
detailed in RS Appendix 8.6 Principles of Environmental Enhancements.
Summary and statement of significance
8.230 Detailed baseline Surveys, NVC and protected species surveys have been carried out on the
Survey Area and an assessment of potential effects on designated sites and protected species
has been undertaken. Much of the Survey Area is currently of low biodiversity value. This
assessment concludes that without mitigation there is a low potential risk to hedgerows, mature
trees, and bat species sensitive to excessive light pollution, breeding birds and reptiles.
8.231 Embedded mitigation (avoidance) will ensure the design of the development, combined with a
detailed Construction Environmental Management Plan, will minimise effects on breeding birds,
bats, hedgerows and trees. In addition, a bat-friendly lighting strategy will be implemented
across the Development Footprint and reptiles will be trapped and translocated to a suitable
receptor site. Therefore, these potentially significant effects can be avoided, to ensure there are
no significant residual effects on these habitats and species.
8.232 Comprehensive ecological enhancements throughout the Revised Scheme will ensure that
ecological value, ecosystem service value and benefit to human health and wellbeing is
enhanced.
Cumulative effects
8.233 Cumulative effects, both individually and in combination, on ecological receptors may arise from
multiple developments within the range of sensitivity of each receptor. Effects may be direct
(such as habitat loss) or indirect (such as sediment run-off degrading the quality of water in a
catchment).
Scope of Cumulative Assessment
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 113
8.234 The cumulative assessment considers relevant planned developments (i.e. validated planning
applications and schemes at appeal) within 5km of the developable area (RS Figure 18.1).
Relevant proposals at the pre-planning stage (‘in scoping’) are also considered including the
SDC/CCT partnership for restoration proposals of the Stroudwater Canal. The Cumulative
Assessment Schemes (CAS) which have the potential to cause cumulative ecological effects are
listed in Table 2.5, and illustrated on RS Figure 18.1.
Cumulative Ecological Effects
Consented developments
8.235 There are six consented developments within a 5km radius of the Development Footprint; WOS
development (c. 50m); the incinerator at Javelin Park (nearly 4.0km); land at Bond’s Mill on the
Bristol Road, Stonehouse (c.1.5km); Westend Courtyard, Grove Lane (100m); land adjacent to
Eastington Trading Estate and land adjoining Station road, Stonehouse (development of 49
residential units) (RS Figure 18.1 Cumulative Schemes).
8.236 WOS is the closest cumulative development, at approximately 50m away at its closest point. It is
a mixed use development for 1,350 dwellings and 9.3ha of employment land. The area for
development is mostly of low ecological value and WOS is considered to be in an area of generally
low sensitivity in terms of the water environment.
8.237 The creation of areas of species-rich grassland along the stream to the south, and along the green
corridors through the WOS development, will retain and enhance foraging opportunities for bats
and birds. The planting of new hedgerows and trees will provide new and enhanced foraging and
nesting opportunities for birds. This approach resonates with the Green Infrastructure proposed
for the Revised Scheme and should provide combined greater connectivity for bats and birds in
the immediate area.
8.238 The Environment Agency has identified potential problems with the River Frome downstream
which is currently failing to meet the Water Framework Directive objective of a ‘Good’ status by
2027. The WOS development will not result in any deterioration of the status of the River Frome.
The use of SuDS, together with ecological enhancements to the existing watercourses, will help
improve the quality of the existing watercourses and is considered to have a minor beneficial
effect.
8.239 Severn Trent Water has confirmed that the foul sewage from the development can be
accommodated within the existing sewerage infrastructure without modification and without
causing any additional flooding. The effect of WOS on the existing foul sewerage infrastructure
is therefore considered to be negligible. WOS will be mitigated against flooding, and flood risk
will not be increased downstream. Overall flood risk in the area will be reduced. As WOS is
upstream of Revised Scheme, the development will have a negligible effect on flood risk and will
not pollute the waterway.
8.240 With the mitigation proposed, WOS will not result in any adverse residual effect on habitats or
species of any significance, and there will be no net loss of features of ecological importance.
Therefore, despite the scale and proximity of this development to the Development Footprint,
the cumulative effect is considered not significant.
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 114
8.241 Westend Courtyard involved the extension to provide additional office space. No ecological
receptors were identified with this development, and therefore the cumulative effect is not
significant.
8.242 The development of land adjacent to Eastington Trading Estate includes the delivery of three
employment buildings comprising a total floor space of up to 2,695sqm with associated access,
car parking and service yards. This permitted development is within an improvement grassland
field entirely within the River Frome Key Wildlife Site. Conditions attached to this permission
require the implementation of a number of ecological mitigation measures and enhancements.
There is however no compensation offered for the loss of the land within the Key Wildlife Site.
The Revised Scheme north of A419 does not impact on the river Frome Key Wildlife Site. The
cumulative effect is therefore considered not significant.
8.243 The development at Bond’s Mill involves the demolition of a warehouse, renovation of office
space and erection of a two storey extension. No ecological factors were identified in the
planning application, and given the nature of the development and the distance from the
Development Footprint; it will have no effect on the Revised Scheme in ecological terms. The
cumulative effect is therefore considered not significant.
8.244 Land at Javelin Park is to be developed as an Energy from Waste (EfW) facility for the combustion
of non-hazardous waste and the generation of energy. It is nearly 4km away to the Development
Footprint, adjacent to Junction 12 of the M5. Javelin Park is already poor in ecological receptors
and is a brownfield site, being formerly an airfield. There is limited connectivity in terms of
habitat for bats, and no hydrological connection as the stream to the southern boundary of the
Javelin site is not currently connected to the River Frome.
8.245 There are plans for substantial ecosystem reconstruction on Javelin Park. The wildlife corridor
along the existing watercourse on the site boundary will be protected for the duration of
construction activities and on completion will be supplemented with additional native planting
to optimise biodiversity potential. In addition to the woodland and tree planting, all areas of land
not required for operational activities will be used for local ecosystem reinstatement and
enhancement. Extensive conservation grassland areas will be sown, which will ultimately support
diverse insect communities. Within the sustainable site drainage system (SuDS), new wetland
habitats (both permanent ponds and seasonally damp grassland) will be introduced. A long term
Management Plan will be prepared for the site.
8.246 The large volumes of water that can be generated by buildings of this scale will be managed on
Javelin Park within an appropriately scaled surface water drainage system to prevent adverse
effects on local water courses including erosion and flooding. The proposed design includes
swales and attenuation ponds to collect excess run-off during storm events and store it within
the site before gradually releasing the water after the storm has passed.
8.247 The design of the lighting scheme for Javelin Park will also take into account the need to avoid
unnecessary light pollution so as to limit any adverse effects upon local residents, flora and fauna.
With all these safeguards in place, and given the site is sufficiently far away from Revised Scheme
to have no direct effect, the cumulative effect of this proposed development is considered to be
not significant.
Developments in planning
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 115
8.248 There are two submitted planning applications pending a decision: one for the conversion and
refurbishment of the former Standish Hospital and the second for a Hotel on land at Pike Lock.
8.249 The conversion and refurbishment of the former Standish Hospital complex, will include
refurbishment of Standish House and associated building to form 50 dwellings. The development
will also include the demolition of Westridge Hospital and associated building and the
development of 98 new build homes within the grounds with associated vehicle and cycle car
parking, pedestrian and vehicular access and associated landscaping, ancillary storage and plant
and ecological bat housing; and all associated engineering works and operations. The Standish
site has been identified as being important for bats and although 3.5km from the Development
Footprint it is possible that bats from this site could occasionally visit the area of the
Development Footprint. It is proposed that the development at Standish Hospital will include
significant ecological mitigation and enhancements including new bats roosts. With all these
safeguards in place, and given the site is sufficiently far away from the Revised Scheme to have
no direct effect, the cumulative effect of this proposed development is considered to be not
significant.
8.250 The outline planning application at Pike lock is for a new pub/ restaurant 56 bed hotel and
associated access, parking, drainage and landscaping. This site is approximately 240m to south
and east of the Development Footprint adjacent to Chipmans Platt roundabout. This site is
currently an abandoned agricultural field with rough grassland/tall ruderal vegetation of limited
ecological value. Although only at outline stage, the applicant has suggested ecological
enhancements to improve the floristic value of the habitats, to provide foraging habitat for birds
and pollinators species and to ensure bat friendly lighting throughout the scheme. This is
complementary to the proposed enhancement for the Revised Scheme. With all these
safeguards in place, and given the site is sufficiently far away from Revised Scheme to have no
direct effect, the cumulative effect of this proposed development is considered to be not
significant.
Pre-planning
8.251 There is a proposal for restoration of the Stroudwater Canal by Cotswold Canal Trust (CCT)
directly to the south of the Development Footprint, within the wider Survey Area (RS Figure
18.1). This is a planned restoration of the canal between the Ocean at Stonehouse and the
Gloucester/ Sharpness canal at Saul Junction. This will recreate the missing length of the canal
between Westfield Bridge and the A38 which had been previously in filled during the
construction of the M5. The previous application to the Heritage Lottery was unsuccessful.
Stroud District Council in partnership CCT are continuing to seek funding and resubmitted a bid
in November 2017. As part of this process an outline planning application for restoration of the
section between Westfield Bridge and the A38 is imminent.
8.252 It is understood that this will include a full ecological assessment of the effects of the restoration
and a detailed biodiversity offsetting programme to ensure an overall net gain in priority
habitats, in line with national and local conservation priorities throughout the length of the canal.
Therefore, there is likely to be a positive cumulative net biodiversity gain.
Conclusion
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 116
8.253 The Revised Scheme Footprint consists of agricultural land, with mixed pasture/hay meadow and
interconnecting hedgerows throughout. There is one boundary stream which ultimately flows
into the River Frome 3km to the west.
8.254 The Survey Area is generally of low biodiversity interest in terms of habitats – although the
interconnecting hedgerow network provides good connectivity for bats and nesting
opportunities for birds. Embedded mitigation (avoidance) and translocation has minimised loss
of mature trees that the effect of the development on trees is deemed to be not significant.
8.255 Whilst there is potential loss of internal hedgerows, they are considered to be only of local
importance. However, this is still moderate and therefore will result in significant effects.
Mitigation will involve translocation and replacement of hedgerow of the same length and
species composition, as well as creation of a commuting corridor for bats. Overall there will be
significant net gain in hedgerow length
8.256 Approximately 12.6 ha of agriculturally improved and semi-improved grassland of low ecological
value will be lost due to the footprint of the development.
8.257 Due to the ephemeral nature of the water bodies within the Survey Area, it was not considered
suitable for great crested newts. New ponds will be created throughout the Revised Scheme as
part of the SuDS and the Green Infrastructure to encourage amphibians to colonize and breed.
8.258 A total of 15 common farmland birds were recorded breeding within or adjacent the
Development Footprint in 2015 and 2016 including one red –listed species (Song Thrush)
breeding within the Development Footprint. The removal of any potential bird nesting habitat
will be carried out outside the bird breeding season. Other construction effects on birds are
perceived to be minimal and not significant. As part of the Green Infrastructure proposals, there
will be extensive planting of new hedgerows, which will enhance and extend foraging and nesting
opportunities.
8.259 The main sett will not be affected by the stadium construction and is sufficiently distant from
training pitches to ensure no disturbance and therefore the effects are not considered to be
significant.
8.260 Extensive bat surveys over two seasons recorded up to twelve bat species using the Survey Area.
Common pipistrelle were the most frequently recorded species within the Development
Footprint. Lesser horseshoe and greater horseshoe bats were also recorded in low numbers, each
accounting for approximately 1% of total bat activity. Detailed design of the Revised Scheme,
creation of ponds, orchards, bat commuting corridors, bat friendly lighting and the minimal loss
of mature trees and tall hedgerows will reduce negative effects on bats to negligible.
8.261 Cumulative effects of nearby developments were considered and it was concluded that there will
be no ecological cumulative effects, singly or in concert, with the Revised Scheme.
8.262 The Green Infrastructure Parameter Plan outlines the enhancements for biodiversity, ecosystem
services, climate mitigation, landscape improvements and social benefits for well-being.
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 117
Table 8.10: Summary of Ecology and Nature Conservation Effects, Mitigation and Enhancement assessed
Receptor and
indicative
importance
Effect Developmen
t phase
Potential
unmitigated
effect on the
feature
Magnitude
change
Likely
occurrence
Level of
effect (and
significance
) prior to
mitigation
Mitigation/Embedd
ed mitigation
Enhancement Residual significance
Severn Estuary
SAC/
International
During
construction
there is
potential for
increased run-
off of sediment,
fine silts or
contaminated
water into the
River Frome and
therefore the
SAC during
construction
Construction
/ Operation
Potential
negative
effect on Sea
Lamprey,
River
Lamprey and
Twaite shad.
Negligible Temporary
and
extremely
unlikely
Negligible
and not
significant
A precautionary
approach will be
adopted which will
involve
development and
implementation of a
Pollution Prevention
Plan and installation
of suitable drainage
systems
incorporating Suds
drainage.
N/A Any potential risks of
significant effects will be
removed to ensure no residual
significant effect
Woodchester
Park SSSI
National
Disruption of
Commuting
behaviour of
bats
Construction
/ Operation
Removal or
alteration of
habitat, and
potential
effects of
lighting on
foraging and
migrating
patterns
Moderate Extremely
unlikely
Negligible
and not
significant
A precautionary
approach will be
taken.
Retention and
appropriate
management of
existing hedgerows.
Creation of dark
corridors and
orchards. A bat-
friendly lighting
scheme throughout
the Revised Scheme
Planting of new
hedgerows and
creation of ponds
and species-rich
grassland.
No residual significance
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 118
Receptor and
indicative
importance
Effect Developmen
t phase
Potential
unmitigated
effect on the
feature
Magnitude
change
Likely
occurrence
Level of
effect (and
significance
) prior to
mitigation
Mitigation/Embedd
ed mitigation
Enhancement Residual significance
Minchinhampton
Common SSSI
National
Disruption of
Commuting
behavior of bats
Construction
/ Operation
Removal or
alteration of
habitat, and
potential
effects of
lighting on
foraging and
migrating
patterns
Negligible Certain Negligible
and not
significant
A precautionary
approach will be
taken. Retention
and appropriate
management of
existing hedgerows.
Creation of dark
corridors and
orchards. A bat-
friendly lighting
scheme throughout
the Revised Scheme
Planting of new
hedgerows.
No residual significance
River Frome and
River Frome
mainstream
tributaries KWSs
County
During
construction
there is
potential for
increased run-
off of sediment,
fine silts or
contaminated
water into the
River Frome and
therefore the
KWSs during
construction.
Construction
/ Operation
Contaminatio
n of the River
Frome and its
tributaries,
and animals
associated
with it, due to
run-off from
the
development.
Temporary
moderate
negative
effects
Highly
unlikely
that any silt
or chemical
contaminat
ion will
reach the
River
Frome.
Negligible
and not
significant
A precautionary
approach will be
adopted which will
involve
development and
implementation of a
Pollution Prevention
Plan and installation
suitable drainage
systems
incorporating SuDS
drainage
N/A No residual significant effect
Hedgerows
Local
Removal or
alteration of
habitat.
Construction Loss of
habitat
Slight/
negative
Certain Moderate
and
significant
Design of the
Revised Scheme
ensures retention of
hedgerows.
Mitigation will
include
translocation and
new planting of
hedgerows and
Enhancement of
retained hedgerows
and ground flora.
Any risks of significant effects
will be removed to ensure no
significant residual effect
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 119
Receptor and
indicative
importance
Effect Developmen
t phase
Potential
unmitigated
effect on the
feature
Magnitude
change
Likely
occurrence
Level of
effect (and
significance
) prior to
mitigation
Mitigation/Embedd
ed mitigation
Enhancement Residual significance
result in a net
increase in
hedgerow length by
planting of new
hedgerows to
beyond original
extent...
Grasslands
Local
Removal Construction Loss of
species-rich
grassland
Slight /
Negative
Certain Negligible
and not
significant
Not required
However retained
grassland will be
managed
appropriately to
increase species
diversity.
Sow species-rich
grassland verges
around footpaths
and car parks using
local seed from the
adjacent
Conservation Road
Verge.
No residual significance.
Trees
Local
Removal or
alteration of
habitat.
Construction Loss of
habitat
Slight/
negative
Certain Moderate
and
significant
Avoidance will
ensure retention of
the majority of
trees, translocation
of two mature oaks
(T59, T60) as a
result of the
widening of the
A419.
Any risks of significant effects
will be removed to ensure no
significant residual effect.
Grasslands
Local
Removal of
grassland verge
south of the
A419
Construction Loss of
feature
Negative Certain Moderate
and
significant
Re-establishment of
the grass verge as
part of hedgerow
translocation.
Species of local
provenance will be
used to re-establish
the road verge e.g.
grass seed from
Chipmans Platt
Roundabout and M5
roundabout.
No residual significance.
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 120
Receptor and
indicative
importance
Effect Developmen
t phase
Potential
unmitigated
effect on the
feature
Magnitude
change
Likely
occurrence
Level of
effect (and
significance
) prior to
mitigation
Mitigation/Embedd
ed mitigation
Enhancement Residual significance
Bats Greater and
Lesser Horseshoe
International
although in
survey area only
of local
importance
Disruption of
foraging
behavior
Construction
/ Operation
Removal or
alteration of
habitat,
effects of
lighting on
foraging and
roosting
patterns
Moderate Moderate
and
significant
Retention and
appropriate
management of
hedgerows and
mature trees.
Replacement of an
equal length of
hedgerow lost.
Creation of dark
corridors and
orchards. A bat-
friendly lighting
scheme throughout
the Revised Scheme
will reduce negative
effects to a
negligible effect.
Creation of ponds
and species-rich
grassland beneath
parkland. Creation
of orchards.
No residual significance
Myotis bat
species
International
although
development site
only of local
importance
Disruption of
foraging
behavior
Construction
/ Operation
Removal or
alteration of
habitat,
effects of
lighting on
foraging and
roosting
patterns
High Certain Moderate
and
significant
Retention and
appropriate
management of
hedgerows, and
mature trees.
Replacements of an
equal length of
hedgerow lost.
Creation of dark
corridors and
orchards. A bat-
friendly lighting
scheme throughout
the Revised Scheme
will reduce negative
effects to a
negligible effect.
Planting of new
hedgerows and
creations of ponds
and species-rich
grassland. Provision
of bat boxes.
No residual significance
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 121
Receptor and
indicative
importance
Effect Developmen
t phase
Potential
unmitigated
effect on the
feature
Magnitude
change
Likely
occurrence
Level of
effect (and
significance
) prior to
mitigation
Mitigation/Embedd
ed mitigation
Enhancement Residual significance
Common and
Soprano
Pipistrelle bats
International
although
development site
only of local
importance
Disruption of
foraging
behavior
Construction
/ Operation
Removal or
alteration of
habitat,
effects of
lighting on
foraging and
roosting
patterns
High Certain
Moderate
and
significant
Retention,
replacements and
appropriate
management of
existing hedgerows.
Creation of dark
corridors and
orchards will reduce
negative effects to a
negligible effect.
Planting of new
hedgerows and
creations of ponds
and species-rich
grassland. Provision
of bat boxes.
No residual significance
Badger
Local
Disruption of
main breeding
sett
Construction Removal or
alteration of
habitat
Moderate Unlikely Negligible
and not
significant
A buffer of 20m will
be established
around the main
sett. If the outlying
set is occupied an
alternative sett will
be created and the
badgers temporarily
excluded under
licence to prevent
disturbance during
construction.
No residual significance
Birds
Local
Disruption of
breeding habitat
Construction Removal or
alteration of
habitat.
Temporary
lights, noise,
vibration,
foundation
construction,
movement
and physical
Minor/
Negligible
Certain Moderate
and
significant
Any in hedgerow
removed or
hedgerow
translocated will be
completed outside
the bird breeding
season
The design process
will include
retention and
enhancement of
hedgerows and
planting of new
hedgerows.
No residual significance
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 122
Receptor and
indicative
importance
Effect Developmen
t phase
Potential
unmitigated
effect on the
feature
Magnitude
change
Likely
occurrence
Level of
effect (and
significance
) prior to
mitigation
Mitigation/Embedd
ed mitigation
Enhancement Residual significance
disturbance
of vegetation
Reptiles; Slow
worm and Grass
snake
National
Risk of
disturbance,
injury or death
and removal of
habitat.
Construction Removal or
alteration of
habitat.
High Certain High and
significant
Capture and
translocation of
slow worm and
grass snake from
hedgerow and road
verge south of A419
and trans-location
to suitable habitat.
Creation of
hibernacula in
suitable locations.
No residual significance
Eco Park, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol.1 Main Text
December 2015
Page | 123
9 HYDROLOGY, FLOOD RISK AND DRAINAGE
Summary
9.1 The location of the Revised Scheme is currently a Greenfield site located to the north of the A419.
In terms of hydrology and flood risk, the closest watercourse to the Site is known as the Selbrook,
which flows for a section adjacent to the western boundary of the Revised Scheme. Further
hydrological receptors are present in the wider area, including the River Frome which is located
approximately 500m to the south of the Revised Scheme.
9.2 A Flood Risk Assessment has been completed for the Revised Scheme and is included in RS
Appendix 9.1 and outlines that the Revised Scheme is predominantly at a very low risk of flooding
from all sources, with only a small section of pluvial flood risk on site.
9.3 The nature and the scale of the Revised Scheme have the potential to affect different receptors
during the construction of the development and operational phase, though due to the nature of
the works this is predominantly the Selbrook and the River Frome.
9.4 During the construction period adverse effects may arise from the development resulting from
the siting of the stadium and associated infrastructure.
9.5 The primary adverse effects generally arise from the potential for uncontrolled sediment runoff
created during the construction of the site or spillages of chemical pollutants (oils, cements,
paints etc.) entering the surface water network. These effects are more prevalent in relation to
the stadium development, where longer-term, more invasive construction works are
undertaken.
9.6 During the operation phase, adverse effects may arise from uncontrolled spills and leaks of
vehicular fluids entering the surface water network or surface water flooding caused by heavy
rainfall falling on the new road and areas of hardstanding. These effects are limited to the area
surrounding the stadium and the associated parking areas. Embedded mitigation incorporated
through the use of SuDS within the drainage design may give rise to positive biodiversity and
water quality effects during the operation of the site.
9.7 The incorporation of the SuDS schemes for Revised Scheme could deliver positive significant
effects, whilst all other effects have been assessed as not significant following the incorporation
of the appropriate mitigation.
Introduction
9.8 This chapter presents the assessment of the likely effects on flood risk, hydrology and surface
water drainage as a direct or indirect result of the Revised Scheme as outlined in Chapter 5 -
Description of the Revised Scheme. The chapter sets out the legislative and policy context
associated with flood risk, hydrology and drainage for the Revised Scheme, the scope of the
assessment and the methodology which has been followed throughout the assessment, along
with the baseline conditions. The assessment identifies the potential effects occurring through
the construction and operation phases of the development and outlines any mitigation measures
required to offset significant environmental effects, as well as any in-combination effects
Eco Park, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol.1 Main Text
December 2015
Page | 124
between the Revised Scheme and other planning applications in the surrounding area. Residual
effects are determined following assessment and the incorporation of mitigation.
9.9 This chapter has been produced in line with the EIA Regulations (2011). However, it should be
noted that the 2017 Regulations now contain additional matters which were not required to be
assessed in the 2011 Regulations. As these matters are clearly important, whilst this ES will be
determined in line with the 2011 Regulations, the additional matters which would have been
required under the 2017 Regulations have also been assessed, and the scope of this work is
explained in more detail within Chapter 1 and Chapter 2.
Legislation, Policy and Guidance
Water Framework Directive (WFD) 2000/60/EC37
9.10 This was established in 2000 to preserve, restore and improve the water environment, and is
transposed into law in England and Wales through the Water Environment (Water Framework
Directive) (England and Wales) in 2003 with the data recorded in the River Basin Management
Plans.
9.11 The Environmental Objectives of the WFD for surface waters include:
• Prevent deterioration in status of all water bodies;
• Protect, enhance and restore all bodies of surface water with the aim of achieving good
surface water status by 2015 [or in some cases 2027];
• Comply with the standards and objective for Protected Areas;
• Aim to cease or phase out discharges, emissions and losses of priority hazardous
substances.
Directive on Environmental Quality Standards (EQSD) 2008/105/EC38
• Sets out the environmental quality standards (EQS) for the substances in surface waters
(river, lake, transitional and coastal) and confirm their designation as priority or priority
hazardous substances.
• With reference to the WFD, good chemical status is achieved when a water body complies
with the EQS for all the priority substances and other pollutants listed in Annex I of the
EQSD.
Water Act 200339 and Water Resources Act 199140
• Governs the control of water abstraction, discharge to water bodies, water impoundment,
conservation and drought provision.
37European Commission (2000),’Directive 2000/60/EC - Water Framework Directive’ 38 European Commission (2008), Directive on Environmental Quality Standards (EQSD) 2008/105/EC 39 Water Act 2003 40 Water Resources Act 1991
Eco Park, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol.1 Main Text
December 2015
Page | 125
• The 2003 Act has changed six key areas of the 1991 Act and relevant to the components
of the Revised Scheme is the need to obtain a license for any dewatering for engineering
works, which was previously exempt.
• The Water Resources Act sets out the relevant statutory regulatory controls that provide
protection of water bodies and water resources.
Flood and Water Management Act 201041
• Provides for better, more comprehensive management of flood risk for people, homes
and businesses, helps safeguard community groups from unaffordable rises in surface
water drainage charges, and protects water supplies to the consumer.
• The activities required under this act aim to reduce the flood risk associated with extreme
weather.
Environmental Protection Act 199042
• Establishes the legislative framework for identifying and dealing with contaminated land
and water.
The Land Drainage Act, 199143
• Underpins ordinary watercourse regulation undertaken by Local Authorities.
• Requires that a watercourse be maintained by its owner in such a condition that the free
flow of water is not impeded.
• The riparian owner must accept the natural flow from upstream but need not carry out
work to cater for increased flows resulting from some types of works carried out
upstream.
Groundwater Regulations 199844
• Outlines the requirement for the prevention of risks to groundwater from certain
substances.
Environmental Permitting Regulations 2010 (as amended)45
• Includes the discharge of water and groundwater activates.
Environmental Protection (Duty of Care) Regulations 1991 (as amended)46
• Ensures that waste is properly stored while on the premised and that it is adequately
packaged for transportation.
41 Flood and Water Management Act 2010 42 Environmental Protection Act 1990 43 The Land Drainage Act, 1991 44 Groundwater Regulations 1998 45 The Environmental Permitting (England and Wales) Regulations 2010 46 The Environmental Protection (Duty of Care) Regulations 1991
Eco Park, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol.1 Main Text
December 2015
Page | 126
Environmental Damage (Prevention and Remediation) Regulations 200947
• Aim to prevent and remedy damage to land, water and biodiversity.
The Water Environment (Water Framework Directive) Regulations 200348
• Transposes 2000/63/EC into law in England.
National Planning Policy
National Planning Policy Framework (NPPF) 201249
• The aims of planning policy on development and flood risk are to ensure that flood risk is
taken into account at all stages in the planning process to avoid inappropriate
development in areas at risk of flooding, and to direct development away from areas at
the highest risk.
• Where new development is, exceptionally, necessary in such areas, policy aims to make it
safe without increasing flood risk elsewhere and where possible, reducing flood risk
overall. It also emphasises the need to adopt proactive mitigation to protect development
against Climate Change in the long term.
Planning Practice Guidance (PPG) - 201450
• Provides additional guidance to ensure the effective implementation of the planning
policy set out in the NPPF on development in areas of flood risk.
• Provides more detail on the Sequential and Exception Test, producing Flood Risk
Assessments, with the inclusion of climate change and managing residual flood risk.
Local Policy
Gloucestershire County Council Local Flood Risk Management Strategy51
9.12 Under the Flood and Water Management Act 2010, Gloucestershire County Council was
designated a Lead Local Flood Authority (LLFA), with a key requirement of the Act requiring
Gloucestershire County Council to produce and maintain a Local Flood Risk Management
Strategy. The Local Strategy is an important tool to help individuals, communities, businesses
and authorities understand and manage flood risk within the county.
Stroud District Council Adopted Local Plan (adopted November 2015)52
9.13 SDC Local Plan has been adopted and Policy ES4 (Water resources, quality and flood risk) will be
the key development policy with respect to the development and flood risk and drainage. The
policy emphasises the reduction of flood risk, the incorporation of SuDS and mitigation measures
to reduce flood risk and surface water runoff.
47 Environmental Damage (Prevention and Remediation) Regulations 2009 48 The Water Environment (Water Framework Directive) Regulations 2003 49 Communities and Local Government (2012), ‘National Planning Policy Framework’ 50Communities and Local Government (2014), ‘Planning Practice Guidance - Flood Risk and Coastal Change, ID 7’,
March 2014. http://planningguidance.planningportal.gov.uk/blog/guidance/flood-risk-and-coastal-change/ 51 Gloucestershire County Council (2014) Local Flood Risk Management Strategy, Main Document 52 The Stroud District Local Plan available from https://www.stroud.gov.uk/media/1455/stroud-district-local-
plan_november-2015_low-res_for-web.pdf accessed on 27th November 2017.
Eco Park, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol.1 Main Text
December 2015
Page | 127
Eastington Neighbourhood Development (adopted October 2016)53
9.14 The NDP was made in October 2016, and now forms part of the Development Plan. Policy EP2
sets a criteria based test. It requires that where appropriate, development proposal should
incorporate SuDS. It also confirms that development will not be supported within 8m of all
watercourses in the parish and within Flood Zone 3.
9.15 Further information in relation to planning policy is provided in Chapter 6 – Planning Policy
Context.
Assessment Methodology and Significance Criteria
9.16 This assessment has been prepared by a suitably competent person. Kristian Jackson BA (hons)
MCD is a Senior Hydrologist and Member of Chartered Institute of Water and Environmental
Management (MCIWEM) and an affiliate member of the Institute of Environmental Management
and Assessment.
9.17 Kristian has over six years of consultancy experience within the hydrology and flood risk sector
and has worked on a number of EIA projects throughout the UK including residential and
commercial developments, cable routes, solar farms, rail projects and windfarms. Kristian is also
a Technical Specialist ES reviewer for hydrology and flood risk for a London Borough.
9.18 This section of the chapter presents the following:
• Identification of the information sources that have been consulted throughout the
preparation of this chapter;
• Details of the consultation undertaken with respect to hydrology, drainage and flood risk;
• The methodology behind the assessment of hydrological effects, including the criteria for
the determination of sensitivity of a receptor and magnitude of change from the existing
(baseline) condition;
• An explanation as to how the identification and assessment of potential hydrological
effects has been reached;
• The significance criteria and terminology for the assessment of the residual effects to flood
risk, hydrology and drainage.
Data Sources
9.19 Initial baseline information on the physical environment was gathered from the following
sources:
• Environment Agency flood maps and data54;
• Severn River Basin District River Basin Management Plan55;
• Scheme proposals and design parameters;
• OS Mapping;
53 Eastington Neighbourhood Development Plan available from http://eastington-pc.gov.uk/wp-
content/uploads/2016/08/Eastington-NDP-Adopted-Version-Oct-2016.pdf accessed on 27th November 2017. 54 Environment Agency online mapping, available at http://watermaps.environment-
agency.gov.uk/wiyby/wiyby.aspx?lang=_e&topic=floodmap&layer=default&scale=2&x=357683&y=355134#x=3576
83&y=355134&scale=2 55 Environment Agency (2009), River Basin Management Plan, Severn River Basin District
Eco Park, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol.1 Main Text
December 2015
Page | 128
• Aerial mapping;
• British Geological Survey geology maps and borehole records56;
• Soilscapes soil classification data57;
• Borehole data provided by Cotswolds Canals Trust58
• Stroud Strategic Flood Risk Assessment59;
• Gloucestershire Preliminary Flood Risk Assessment60;
• Gloucestershire Local Flood Risk Management Strategy;
• Private Water Supply data;
• Abstraction and Discharge license data.
9.20 This chapter of the ES has been accompanied by a Flood Risk Assessment for the Site produced
by RSK (660670 R3 (01)) and included as RS Appendix 9.1.
Data Limitations
9.21 Reliance has been placed on factual and anecdotal data obtained from the sources identified
above. New information, revised practices or changes in legislation during the assessment or
development stages may necessitate the reinterpretation of the report, in whole or in part.
9.22 There are no significant areas of uncertainty with regard to the assessment of hydrological
environmental effects and mitigation measures. However, further hydrological/ geotechnical
assessment may be undertaken at the detailed design stage during Reserved Matters
Applications for construction and engineering purposes.
9.23 Overall, despite the potential uncertainties, it is considered that the available data is sufficient
to provide a robust basis for the assessment undertaken.
Study Area
9.24 The Study Area (see RS Figure 9.1) covered by this chapter includes the assessment of the
hydrological environment within the Redline Boundary, with a range extending to approximately
250m downstream for direct effects (ensuring the survey encompasses the River Frome). Direct
effects have been assessed on watercourses within the 250m search boundary. Under the
direction of the Water Framework Directive, it is required that recorded watercourses
downstream of the Site have been considered within the assessment process to ensure that no
deterioration of downstream watercourse status occurs. Therefore, indirect effects upon the
downstream recorded watercourses have been included in the assessment process.
Consultation and Scoping Overview
9.25 As part of the scoping phase of the Environmental Impact Assessment (EIA), a Scoping Report
was prepared in July 2015 (RS Appendix 1.3), setting out the proposed approach to the
56 British Geological Survey online mapping, available at
http://mapapps.bgs.ac.uk/geologyofbritain/home.html?location=&gobBtn=go 57 Cranfield Soil and Agrifood Institute – Soilscapes, available at
http://mapapps.bgs.ac.uk/geologyofbritain/home.html?location=&gobBtn=go 58 Cotswolds Canal Trust, Borehole Data 59Stroud District Council (2008) Strategic Flood Risk Assessment for Volume 1 – FINAL September 2008 60Environment Agency (2011) Gloucestershire County Council Preliminary Flood Risk Assessment
Eco Park, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol.1 Main Text
December 2015
Page | 129
assessment in respect to the previous scheme. The Scoping Report outlined the identification of
methods utilised for the assessment on flood risk, hydrology and drainage.
9.26 A summary of the Scoping Opinion for the previous scheme (RS Appendix 1.2) is outlined below.
Due to the nature of the Revised Scheme, the scoping responses gained through the previous
submission will still hold relevance for the Revised Scheme and have been included below for
completeness:
Table 9.1: Scoping Responses
Consultee Issue Raised Location in chapter
where addressed
Environment
Agency Scoping
Response dated
17/08/15
The Flood Risk to the proposed development Site has been
correctly identified within section 3.63 of the report, in
accordance with our Flood Map for Planning (Rivers and
Seas). The floodplain at this location is from the River
Frome, which is classified as a ‘main river’. As highlighted
the Site benefits from the presence of defences in the area,
and is therefore offered some protection from flooding,
however for planning purposes it is important to consider
the floodplain without the presence of such defences. This
is because the defences may not always be present, and
therefore cannot be relied upon, or they may not be
maintained to their current standard for the lifetime of the
development. In addition, any defence can be subject to
breach, failure or overtopping.
Flood Risk
Assessment (RS
Appendix 9.1)
Environment
Agency Scoping
Response dated
17/08/15
In addition, there are some smaller watercourse and ditches
crossing the southern boundary of the Site, which are
classed as ‘ordinary watercourses’. Please note our Flood
Maps primarily show flooding from main rivers, not
ordinary watercourses with a catchment of less than 3km2.
Therefore, an assessment of flood risk associated with these
unmodelled watercourses may also be necessary.
Flood Risk
Assessment (RS
Appendix 9.1)
Environment
Agency Scoping
Response dated
17/08/15
The need for a Flood Risk Assessment as required by the
National Planning Policy Framework (NPPF) has been
correctly highlighted in paragraphs 3.72 of the report.
Flood Risk
Assessment (RS
Appendix 9.1)
Environment
Agency Scoping
Response dated
17/08/15
The FRA should define the exact extent of all flood zones
upon the Site to define the appropriate developable area
and appropriately locate development uses in a sequential
manner following the guidance set out within the Flood and
Coastal Change section of the National Planning Practice
Guidance (NPPG).
Flood Risk
Assessment (RS
Appendix 9.1)
Environment
Agency Scoping
Response dated
17/08/15
The assessment should include the effect of climate change
based on the 1% modelled extent of the floodplain that
forms the basis of the outlines shown on our Flood Map.
Flood Risk
Assessment (RS
Appendix 9.1)
Environment
Agency Scoping
Response dated
17/08/15
A Level 2 Strategic Flood Risk Assessment (SFRA) has also
been produced as an evidence base in support of SDC’s
Emerging Local Plan, which we note has been referenced as
a useful source of information on surface water, flood risk
and ground conditions.
Flood Risk
Assessment (RS
Appendix 9.1)
Environment
Agency Scoping
Response dated
17/08/15
For Sites greater than 1 hectare in size, a surface water
strategy should be carried out as part of a Flood Risk
Assessment (FRA) to demonstrate that the proposals will
not create an increased risk of flooding from surface water.
Flood Risk
Assessment (RS
Appendix 9.1)
Eco Park, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol.1 Main Text
December 2015
Page | 130
Consultee Issue Raised Location in chapter
where addressed
We note paragraph 3.74 indicates a drainage strategy is to
be developed to address this issue and detailed further in
paragraph 3.80.
Environment
Agency Scoping
Response dated
17/08/15
We [the EA] would expect the subsequent planning
application to detail any effects on the water environment
in the context of the WFD. This would include any effects
on the watercourses close to the Site, the groundwater
below and any water features in hydraulic continuity.
Potential Effects
section
Environment
Agency Scoping
Response dated
17/08/15
This work should identify existing pressures on the water
body; measures to ensure there is no deterioration in
ecological status and measures to ensure the achievement
of this is not precluded in the future.
Potential Effects
section
Environment
Agency Scoping
Response dated
17/08/15
Measures to improve the ecological status of the water
bodies should also be identified as part of any assessment.
This might include the positive contribution that
Sustainable Urban Drainage (SuDS) can play to water
quality.
Flood Risk
Assessment (RS
Appendix 9.1)
Significance Criteria
9.27 The assessment includes a qualitative assessment of potential effects on flood risk, hydrology
and drainage from construction works and operational activities on Site.
9.28 Potential effects of the Revised Scheme on flood risk, hydrology and drainage have been
identified and assessed using criteria from the Institute of Environmental Management and
Assessment (IEMA 2011).
9.29 The content of this assessment has been identified through a combination of project experience,
available documentation, consultation and professional judgement.
9.30 The assessment of effects has taken into account the sensitivity / importance of the receptor and
the magnitude of the effect on that receptor as set out below.
Table 9.2: Definition and description of sensitivity
Receptor
Sensitivity/
Importance
Receptor
Type
Description / Notes
High Hydrology
and Water
Resources
• Low lying land and local drainage network;
• Areas at high risk of flooding;
• Human receptor – public and visitors;
• Highly and more vulnerable developments, including landfill and Sites
used for waste management facilities for hazardous waste; and
• Principal aquifers.
High Water
Quality
• High and good water quality (as defined by the WFD) with pristine or near
pristine water quality; and
• Areas of known/ confirmed contaminated land/ groundwater.
High Desig-
nated
Sites
• Protected or designated areas e.g. Sites of Special Scientific Interest
(SSSI), Ramsar Sites, Special Protected Areas (SPAs), Special Areas of
Conservation (SACs), which are highly sensitive to disruption.
Eco Park, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol.1 Main Text
December 2015
Page | 131
Receptor
Sensitivity/
Importance
Receptor
Type
Description / Notes
Medium Hydrology
and Water
Resources
• Areas with intermediate groundwater vulnerability;
• Surface water (flow patterns);
• Secondary (A, B and undifferentiated aquifers);
• Areas at a medium risk of flooding;
• Human receptor – construction crew and operators, locals and occupants
with prior knowledge of Site conditions or the local area;
• Less vulnerable developments, including industrial properties and waste
treatment (except landfill and hazardous waste facilities); and
• Surface water drainage networks including drainage ditches and drains
(flow patterns and capacity).
Medium Water
Quality
• Moderate water quality (as defined by the WFD) with a measurable
degradation in its water quality.
Low Hydrology
and Water
Resources
• Areas with low groundwater vulnerability;
• Non-aquifers;
• Areas at a low risk of flooding;
• Water compatible developments, including water transmission
infrastructure and pumping stations, and sand and gravel workings; and
• Local drainage network including drainage ditches and drains, and private
Site drainage.
Low Water
Quality
• Poor or bad water quality (as defined by the WFD) resulting from
anthropogenic factors.
Negligible Hydrology
and Water
Resources
• Features not designated under the WFD, assessed in terms of water
quality or hold any designated affiliation which may be effected upon.
Negligible Water
Quality
• Features not designated under the WFD, assessed in terms of water
quality or hold any designated affiliation which may be effected upon.
9.31 The magnitude of the potential effects resulting from the environmental effects of the
development (adverse or beneficial) on flood risk, hydrology and drainage is outlined in Table
9.3. The allocation of the level of magnitude has been identified through the consideration of
and the application of professional judgement and the assessment of supporting evidence.
Table 9.3: Definition and description of magnitude
Magnitude Receptor Type Description / Notes
Substantial Large scale change to key
hydrological elements
Major or permanent change in
the quality of surface water
resources
Moderate to severe
temporary effect on aquatic
flora and fauna
Moderate increase in peak flood level
Deterioration of a water body leading to a failure to meet
Good Ecological Status (WFD) and reduction in class
Loss of a protected area
Medium Noticeable change to key
hydrological elements
Moderate increase in peak flood level
Eco Park, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol.1 Main Text
December 2015
Page | 132
Magnitude Receptor Type Description / Notes
Moderate or temporary
reduction in the quality of
surface water resources
Moderate to severe
temporary effect on aquatic
flora and fauna
Discharge of polluting substances to water body but
insufficient to change water quality status in the long
term
Loss in production of fisheries.
Minor Slight changes to key
hydrological elements
Slight reduction in surface
water quality, reversible
within a short period of time
Minor or reversible
detrimental effects on aquatic
flora and fauna
Small increase in peak flood level
Measurable discharge of pollutant to water body which
does not lead to reduction in water quality or failure to
improve status.
Negligible Minute to none identifiable
change to key hydrological
elements
No discernible effects on hydrological elements (neither
beneficial nor adverse)
9.32 The effect is the term used to express the consequence of an impact (expressed as the
significance of effect), which is determined by correlating the magnitude of the effect to the
sensitivity of the receptor. This is achieved using the matrix presented in Table 9.4.
Table 9.4: Significance of effect assessment matrix
Sensitivity of receptor/ Receiving Environment to Change/ Effect
High Medium Low Negligible
Ma
gn
itu
de
of
Ch
an
ge
/ e
ffe
ct Substantial Major Moderate Minor Negligible
Medium Moderate Moderate Minor Negligible
Minor Minor Minor Minor Negligible
Negligible Negligible Negligible Negligible Negligible
9.33 The terms as used within the table have been defined below:
• Major positive or negative effect: where the development will cause significant
improvement (or deterioration) to the existing environment (significant in EIA terms).
• Moderate positive or negative effect: where the development will cause noticeable
improvement (or deterioration) to the existing environment (significant in EIA terms).
• Minor positive or negative effect: where the development will cause perceptible
improvement (or deterioration) to the existing environment (not significant within the
meaning of the EIA Regulations).
Eco Park, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol.1 Main Text
December 2015
Page | 133
• Negligible: no discernible improvement or deterioration to the existing environment (not
significant within the meaning of the EIA Regulations).
9.34 Effects requiring mitigation measures would be those of significance (which is generally
considered to be a moderate significant effect or higher). An assessment has also been made of
the significance of the residual effects, i.e. those which will remain after application of embedded
and additional mitigation.
9.35 Where the certainty of the effect could be variable, professional judgement and understanding
of the hydrological conditions and knowledge of the Revised Scheme and area has been used in
assessing the consequence of the effect.
9.36 The likelihood of the potential consequence of the effect occurring is then explicitly taken into
account to derive the overall consequence of the effect on hydrology. In terms of the duration
of an effect (as outlined in Chapter 2), short-term has been considered as 1 year (or below), a
medium term effect has been considered to be between 1 and 10 years in duration and a long-
term effect has been considered to be greater than 10 years in duration.
9.37 The levels of likelihood that have been considered are shown in Table 9.5 and the method for
assessing the likelihood of an effect is adapted from the IEMA Quality Mark Article61 .
Table 9.5: Likelihood of effects
Likelihood Definition
Highly
Likely
The event appears very likely in the short term and almost inevitable over the long term
or there is evidence at the receptor of harm or pollution.
Likely It is probable that an event will occur or circumstances are such that the event is not
inevitable, but possible in the short term and likely over the long term.
Unlikely Circumstances are possible under which an event could occur, but it is not certain in the
long term that an event would occur and it is less likely in the short term.
Highly
Unlikely
Circumstances are such that it is improbable the event would occur, even in the long term.
Baseline Conditions
General Site Description
9.38 The Site is located approximately 3.2km to the west of Stonehouse and approximately 7.2km to
the west of Stroud in Gloucestershire. The Site is located around the roundabout at J13 of the
M5, with the development of the Stadium area situated to the north of the A419. The
development proposals are listed in Table 1.1 and shown in RS Figure 1.1.
9.39 The overall Redline Boundary is currently open Greenfield / agricultural land totalling
approximately 39.5ha.
61 Derek Duckett, Xodus, unknown date
Eco Park, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol.1 Main Text
December 2015
Page | 134
Hydrological Features
9.40 Several significant hydrological features are located in close proximity to the Site (see also RS
Figure 9.1). The closest Main River to the Site is the River Frome, which is located adjacent to
the southern Redline Boundary and approximately 500m to the south of the Revised Scheme.
The River Frome rises from springs in the region of Birdlip and Brimpsfield (approximately 16km
to the north-east of the Site). The Frome flows south from its source towards Sapperton where
it turns to the west, flowing past Stroud and the Site before passing beneath the Gloucester and
Sharpness Canal, eventually discharging to the River Severn at Upper Framiload (approximately
4.32km to the north west of the Site).
9.41 An ordinary watercourse (not classed as a Main River by the Environment Agency and therefore
under the LLFA’s jurisdiction) surfaces at Grove Farm to the north of the Site, flows to the north
before turning to the south west and flowing adjacent to the western boundary of the Site. The
drain is then culverted beneath the M5 and appears to re-surface to the west of the Eastington
Maintenance Compound and follow the Redline Boundary before discharging to the River Frome.
9.42 To the east of the Site, the River Frome splits into two branches to the south west of Ebley. The
branches of the Frome converge approximately 800m to the south.
9.43 Sections of the now abandoned Stroudwater Navigation (canal) area are present to the south
and west of the Redline Boundary. When operational, the Stroudwater Navigation linked Stroud
(and the Thames and Severn Canal) to the River Severn. The Stroudwater Navigation was severed
in the vicinity of the Site by the construction of the M5 and the A38. The Stroudwater Navigation
running from the east terminates at William Morris College (approximately 350m from the
Revised Scheme). The former channel of the canal runs adjacent to the south of the Redline
Boundary, this has been confirmed as infilled. A small stretch of the channel exists to the west
of Whitminster. The WFD status of the canal sections has been detailed in RS Appendix 9.2.
9.44 Ordinance Survey mapping shows several small drains, ditches and watercourses, however there
is potential that these may be ephemeral ditches remaining along the line of the former canal
corridor.
9.45 The River Severn is located approximately 3.7km to the west of the Site.
9.46 The watercourses and water bodies within the Site and the surrounding environs (as defined by
the Study Area) are outlined in Table 9.6 and detailed further within the Flood Risk Assessment
(RS Appendix 9.1) and RS Figure 9.1.
Table 9.6: Watercourses in the vicinity of the Site
Watercourse
/Water body
Description Distance from Site
River Frome Main River running to the south of the Site and A419 and
adjacent to the southern Redline Boundary (west of the
M5). Approximately 15m in width at top of bank.
Designated a Main River and recorded under the WFD
(GB209054032450). To the south of Ebley, the River
Frome splits into several branches, which converge again
to the south east of the Proposed Development Site.
500m south of Site (at
closest point)
Eco Park, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol.1 Main Text
December 2015
Page | 135
Watercourse
/Water body
Description Distance from Site
Stroudwater
Navigation
(canal)
Truncated canal terminates south of William Morris
College. Approximately 15m width of channel prior to
the terminus. Small drain potential connects into
tributary of the River Frome. The Stroudwater
Navigation to the east of the Site is classified by the
Inland Waterways Association as an isolated section, ‘a
canal in water and used for limited navigation but
isolated from other parts of the waterway’. The section
of ‘watered’ canal closest to the Site is classified as a
Disused Canal, where, ‘the line of the waterway is clearly
evident and retaining some water although it may be
heavily silted or overgrown’. The Stroudwater Navigation
to the south of the Site is classified by the Inland
Waterways Association as an Historic Line of Canal, the
‘line of waterway largely obliterated; built over or filled
in, with little or no visible evidence of canal remaining’.
To the west of the Site (beyond the A38 to the River
Severn) the Stroudwater Navigation is classed as either a
derelict canal or disused canal. The Cotswold Canals
Partnership has bid to the Heritage Lottery Fund towards
the cost of the restoration of the 6.4km stretch of the
Stroudwater navigation from Stonehouse to Saul. A
Scoping Request has also been submitted ahead of
making a planning application.
350m to the south of the
Revised Scheme
The Selbrook Small drain (assumed 1-2m width at top of bank), tree
lined channel. Surfaces at Grove Farm to the north of the
Site, flows to the north before turning to the south west
and flowing adjacent to the western boundary of the
Site. The drain is then culverted beneath the M5 and
appears to re-surface to the west of the Eastington
Maintenance Compound and follow the line of the Site
boundary before discharging to the River Frome.
Flowing adjacent to the
western boundaries of the
Site.
Former line
of
Stroudwater
Navigation
(infilled)
Small depression may remain where former Stroudwater
Canal is infilled (potentially ephemeral), with no ability
to convey surface water flows
Located to the south of the
Redline Boundary
Unnamed
Drain
Small watercourse shown on OS mapping flowing from
the east, beneath the roundabout on the A419, then to
the south of William Morris College, towards a
confluence with the River Frome near the Eastington
Trading Estate. The watercourse emerges from several
spring locations to the north and east of Stonehouse and
flows via Stonehouse, Oldends and Nastend towards
Chipmans Platt. Approximately 1 – 2m in width at top of
bank.
Located to the south of the
Redline Boundary for
highway works.
Unnamed
Drain
Small watercourse runs to the south of the River Frome,
roughly parallel to the line of the river. The origin of the
ditch is unclear, though appears to form as part of a field
drain before running to the west and beneath the M5
and discharges to the River Frome at Fromebridge Mill.
Approximately 650m to
the southeast of the Site.
Lakes at
Frampton On
Severn
Former gravel pits now utilised for sailing and course
fishing. Northern lake recorded under the WFD
(GB30940946).
Designated a SSSI (Frampton Pools SSSI)
Approximately 1.8km to
the west of the Site
Eco Park, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol.1 Main Text
December 2015
Page | 136
Watercourse
/Water body
Description Distance from Site
Pond located
in grounds of
Eastington
Court
Small pond located within the grounds of Eastington
Court
Approximately 435m to
the south of the Site
River Severn Main river – Estuarine nature. Designated under the
WFD GB530905415403 – Severn Upper, (where the
Frome discharges to the Severn) and GB530905415402 –
Severn Middle, (closest section to the Site).
Designated SSSI, SPA, SAC and RAMSAR Site
Approximately 3.7km to
the west of the Site.
Flood Defences
9.47 Flood Defences are shown to be in the area along the Frome according to the Environment
Agency Detailed Flood Map for Planning. Further details are included within the Flood Risk
Assessment (RS Appendix 9.1). The Environment Agency did not supply any more information
with regard to the defences in their response to the Product 4 data request.
Geology
Bedrock
9.48 Blue Lias Formation and Charmouth Mudstone Formation (undifferentiated) – Lithological
Description: Thinly interbedded limestone (laminated, nodular, or massive and persistent) and
calcareous mudstone or siltstone (locally laminated). Individual limestones are typically 0.10 –
0.30m thick. In some areas, intervening mudstone units with relatively few limestone beds.
Superficial
9.49 River Terrace Deposits, 3 (Frome, Glos) – Lithological Description: Sand and gravel, locally with
lenses of silt, clay or peat.
9.50 Alluvium – Lithological Description: Normally soft to firm, consolidated, compressibly silty clay,
but can contain layers of silt, sand, peat and basal gravel. A stronger, desiccated surface zone
may be present.
BGS Borehole Records
9.51 Numerous borehole records are present in the surrounding areas of the Site (predominantly
associated with J13 of the M5 – central to the Redline Boundary location). Of the J13 boreholes,
five extend beyond 10m below ground level (mBGL); SO70NE107, SO70NE15, SO70NE109,
SO70NE110, and SO70NE111. The borehole records present similar results with Made Ground
to approximately 6.5mbgl - 8mbgl, with stiff grey thinly laminated clays extending beyond this
depth.
Stroudwater Canal – Preliminary Site Investigation Interpretive Report62
9.52 Preliminary investigation works were undertaken for a stretch of the Stroudwater Canal between
the Ocean (a minor waterways place on the Cotswold Canal to the east of the Site) and Saul
Junction including the infilled section of the canal. In summary, the borehole / geological
sequence was recorded for the area of the Site as;
62 White Young Green (2007) Preliminary Site Investigation Interpretative Report – Stroudwater Canal
Eco Park, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol.1 Main Text
December 2015
Page | 137
• Topsoil – present at up to 1.0m thickness.
• Alluvium – thickness varied between 0.4m and 3.5m. Greater thicknesses of alluvium
were present closer to the River Frome, indicating that the deposit is closely related to the
course of the river. The alluvium was typically a soft-grey – brown slightly gravelly clay.
• River Terrace Gravels – thickness varied between 0.4m and 2.2m and was found at depths
up to 4.8mbgl. The river terrace gravels were typically a yellow brown slightly clayey
gravel of angular to subangular fine to coarse limestone, although in places graded to a
gravelly clay.
• Weathered Lower Lias – thickness extended beyond 8.8m and was encountered at depths
of between 1.8mbgl and 4.8mbgl. Typically described as firm (becoming stiff with depth)
silty clay within the upper 2 – 3m, becoming a stiff grey silty clay with weak mudstone
bands at depth.
• Lower Lias – only encountered in one borehole comprising of grey weathered mudstone
with silty clay bands.
Designations
9.53 International, national and locally designated Sites within a 5km buffer zone of the Site are
illustrated within RS Figure 8.6.
Water Quality
9.54 The WFD requires that environmental objectives be set for all surface and groundwaters in
England and Wales to enable them to achieve Good Status (Or Good Ecological Potential for
Heavily Modified and Artificial Water Bodies) by a defined date.
9.55 The assessment of sensitivity is based on the current status of the waterbody. If the aquatic
environment is of existing poor quality, it is likely to be less sensitive to changes that occur as a
result of construction works (e.g. from an increase in silt content from construction Site
discharge). Therefore, the sensitivity is considered to decline with poorer water quality.
9.56 The WFD classification is not available for all surface waters in the vicinity of the Site. Those
recorded under the WFD are outlined in RS Appendix 9.2.
WFD Screening
9.57 A Water Framework Directive screening exercise has been undertaken with respect to the
watercourses and waterbodies are detailed in RS Appendix 9.2. Due to the nature of the
development, there will be no in-channel works within any of the watercourses listed above, and
current proposals are for discharge via infiltration and as such no off-Site connection to a
watercourse is being sought. Therefore, the potential effects on the watercourses would be
negligible and as there will be no development in, or around the watercourse, the potential to
improve the geomorphology would be very limited. As such this assessment has considered the
objectives of the WFD and ensured that the objectives are not compromised. Therefore, a full
WFD assessment has been scoped out of this EIA.
Flood Risk
Fluvial
Eco Park, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol.1 Main Text
December 2015
Page | 138
9.58 The Revised Scheme is located outside the flood zone for all return periods up to the 1,000-year
event, indicating a low risk of flooding from fluvial sources.
Tidal
9.59 The Site is not outlined to be a risk of tidal flooding. The River Frome has a flapped outfall
structure to prevent tidal inundation. An extreme fluvial flood event may be exacerbated when
outfalls are tide-locked. The impact of tidal flooding to the development has therefore been
scoped out of the following assessment. However, details regarding this form of flooding have
been considered with the Flood Risk Assessment for the Site, (included in RS Appendix 9.1).
Pluvial
9.60 Surface water flood risk has been a major cause of flooding in more recent times and is a result
of inundation of an area subject to excessive runoff or served by inadequate drainage
infrastructure. Surface water flooding is a potential issue in areas to the north of the A419. It
has been noted by the ecologist that, following a Site walkover, a culvert was located flowing
under the A419. This culvert was heavily silted and therefore the road embankment is acting as
a dam for overland flow routes, contributing to the pluvial flood risk at the site.
Groundwater
9.61 The Revised Scheme is located outside a Source Protection Zone, however they overlie a
Secondary A and Secondary B aquifer (Superficial Deposits) and a Secondary (undifferentiated)
aquifer (bedrock). The Secondary A and to a lesser extent the Secondary B aquifers may have
permeable layers capable of supporting water supplies at a local scale. With the Blue Lias
bedrock beneath the Site, it is possible that areas of perched groundwater may be encountered.
Groundwater flooding however is sporadic and groundwater records are generally limited. It has
been indicated that Groundwater Emergence Maps do not cover the Stroud District and there
are no records of groundwater flooding incidents in the area. Groundwater flooding has
therefore been scoped out of the following assessment, however details regarding this form of
flooding have been considered with the Flood Risk Assessment for the Site, (included in RS
Appendix 9.1).
Sewer
9.62 With the predominantly Greenfield nature of the Site, it is believed that any sewer flood risk to
the Site would be low, and in all likelihood contained within the arterial road network
surrounding the Site areas. Residual effects from non-functioning / over flowing septic tanks
could lead to isolated incidents of ‘sewer flooding’ on Site. Sewer flooding has therefore been
scoped out of the following assessment.
Reservoirs
9.63 The Revised Scheme is not indicated to be at risk of flooding from reservoirs according to the EA
reservoir flood maps.
9.64 Small sections of the area within the Redline Boundary west of the M5 are classed as being at
risk of reservoir flooding with the potential source reservoirs being Parkmill Pond, Kennel Pond
and Middle Pond in Woodchester, according to the EA reservoir flood maps.
9.65 The risk of reservoir flooding is extremely unlikely. There has been no loss of life in the UK from
reservoir flooding since 1925. Since then safety legislation has been introduced to ensure
Eco Park, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol.1 Main Text
December 2015
Page | 139
reservoirs are maintained. The EA reservoir flood map shows the largest area that might be
flooded if a reservoir were to fail and release the water it holds. Since this is a prediction of a
worst case scenario, it is unlikely that any actual flood would be this large. This is therefore
scoped out for the purposes of this assessment, however details regarding this form of flooding
have been considered with the Flood Risk Assessment for the Site, (included in RS Appendix 9.1).
Artificial Structures (Canals)
9.66 The truncated Stroudwater Navigation is in close proximity of the Site; however, the section of
the canal up to its terminus to the south east of the Site is not classed as providing a residual
flood risk to the surrounding area and is therefore scoped out of this assessment. As such the
risk of flooding to the Site is considered low, with further details provided within the Flood Risk
Assessment for the Site, (included in RS Appendix 9.1).
Historic Flood Records
9.67 Historic flood events have been recorded in the vicinity of the Site. Two isolated records are
located within the vicinity of the Northern and Southern Site areas (an unknown flood event
within the Development Footprint to the north of the A419, and a flood event from artificial
drainage on the A419). By contrast, a total of 18 flood events are mapped by SDC within the area
west of the M5 or at the neighbouring Eastington Maintenance Compound (2 surface water
records, 5 artificial drainage records, 1 fluvial record and 11 unknown records).
Climate Change
9.68 Climate Change can affect local flood risk in several ways. Effects will depend on local conditions
and vulnerability. In terms of the wider effects of the climate change these are detailed in RS
Chapter 16. Climate Change influences specific to hydrology and flood risk for the Revised
Scheme are outline below.
9.69 In accordance with the recently published Flood Risk Assessments: Climate Change allowances
applicable to this Site are predictions of anticipated change for peak river flow (by river basin
district) and peak rainfall intensity.
Peak River Flow
9.70 The Guidance provides a range of peak river flow allowances against an Allowance Category. The
Allowance Categories are based on percentiles (a measure used in statistics to describe the
proportion of possible scenarios that fall below an allowance level), with:
• The central allowance based on the 50th percentile
• The higher central based on the 70th percentile
• The upper end based on the 90th percentile.
9.71 The determination of the Allowance Category applicable to the Site is ascertained through the
confirmation of the River Basin District in which the Site lies, the flood risk vulnerability of the
development and the flood zone designation of the Site.
9.72 With the location of the Revised Scheme in Flood Zone 1 the Guidance does not provide
information of peak river flow allowances for this scenario.
Eco Park, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol.1 Main Text
December 2015
Page | 140
Peak Rainfall
9.73 In the Severn River Basin District, wetter winters and more rain falling in wet periods may
increase river flooding for rivers and tributaries. More intense rainfall causes more surface
runoff, increasing localised flooding and erosion. In turn, this may increase pressure on drains,
sewers and water quality. Storm intensity in summer could increase even in drier summers.
Rising sea or river levels may increase local flood risk inland or away from major rivers because
of interactions with drains, sewers and smaller watercourses.
9.74 In accordance with the recently published Flood Risk Assessments: Climate Change Allowances,
for the surface water runoff assessment of a mixed use (sports and associated infrastructure)
development (60-year lifetime), the Flood Risk Assessment is required to assess both the central
and upper end allowances to understand the range of impacts at the Site.
9.75 As such an allowance of a 40% increase in the rainfall intensity values for the period 2060 to 2115
will be included in the detailed design of the drainage. This allows for the impact of climate
change on the design of the development with respect to the Central (20%) and Upper End (40%)
allowance. Such events have been considered to ensure that there is no flooding to properties
during these events. These increases will apply towards the end of design lifetime of the
development.
Design Evolution
9.76 The concept design for Eco Park, and the amendments now incorporated within the Revised
Scheme, has evolved such that the Stadium has been located in Flood Zone 1.
9.77 The Revised Scheme will increase the impermeable area from the pre-development state, and
as such will result in an increase in surface water runoff across the Site. It will therefore be
necessary to manage surface water on Site in order to limit the discharge of surface water off
Site at an agreed rate, to provide sufficient on Site attenuation up to the 1 in 100-year climate
change rainfall event and to provide improvements to water quality through appropriate source
treatment.
9.78 The embedded mitigation for the Site will take the form of the proposed SuDS which could
include a combination of soakaways, swales, infiltration basins and permeable paving which
should be located depending on the relative groundwater depths, underlying soil type and
locality of proposed buildings. Subject to infiltration test results, discharge from the Site may be
via infiltration or direct connection to watercourse.
9.79 In terms of Site drainage, most adopted surface water drainage networks are designed to the
criteria set out in the SuDS Manual. One of the design parameters is that sewer systems be
designed such that no flooding of any part of the Site occurs in a 1 in 30-year rainfall event.
9.80 To ensure that sewer and surface water flooding is not exacerbated; surface water must be
considered within the design of the Site. This ensures that any additional surface water and
overland flows are managed correctly, to minimise flood risk to the Site and the surrounding
area. The proposed surface water network on the Site has been designed to ensure exceedance
of the network has been considered and that there is no flooding of properties during a 1 in 100-
year rainfall event.
Eco Park, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol.1 Main Text
December 2015
Page | 141
9.81 A SuDS system will be utilised on Site, and a new attenuation pond designed as part of the
drainage strategy for the Site.
9.82 The development of the Site will be designed to ensure that any excess surface water during
storm events is contained within the road network and away from properties and released to
the sewer network as capacity dictates.
9.83 Due to the nature of the Site (and in line with the Flood Risk Assessment), surface water will be
discharged from the Site via infiltration (subject to test results).
9.84 Further information on the provisional surface water drainage strategy for the Site is included as
part of the associated Flood Risk Assessment (RS Appendix 9.1) and in the Scheme Specific
Mitigation sections of this Chapter.
Potential Effects
Construction Effects
9.85 The construction assessment stage is based on the designs with design evolution (embedded
mitigation - outlined above) during the construction phase. During the construction phase, there
is the potential for the construction of the Revised Scheme to result in the following effects on
the water environment:
• Water pollution from silt laden runoff if allowed to drain to surrounding watercourses
untreated;
• Chemical / fuel spillages and leaks from plant and machinery;
• Cements and concrete spillages from building works;
• Inappropriate disposal of foul waste from the Site;
• Debris from construction Sites blocking culverts, increasing risk of flooding;
• Impermeable areas constructed on Site increasing surface water runoff;
• Changing overland flow routes, increasing flood risk.
9.86 During the construction phase, following embedded mitigation, but prior to mitigation measures
being implemented, there is the potential significant effects anticipated from spillages of fuels,
oils, paints or solvents from the Revised Scheme into watercourses affecting water quality. The
assessment of these is discussed below, however the full detailed assessments for non-
significant effects during the construction phase are included in RS Appendix 9.3
9.87 The closest watercourse to the Revised Scheme is the small watercourse/ drain, which for a short
distance, runs adjacent to the western boundary (the Selbrook). The watercourse is small and
not recorded under the WFD; however, the watercourse does discharge to the River Frome to
the north of the western parcel of the Redline Boundary.
9.88 Due to the proximity of the proposed works to the watercourse, and the relatively short distance
to its discharge point into the River Frome, the watercourse is classed as having a medium
sensitivity. Small watercourses and ditches predominantly have low flows and as such will
reduce the likelihood of any potential contaminants entering the River Frome for the
development location.
Eco Park, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol.1 Main Text
December 2015
Page | 142
Chemical and Fuel Spillages
9.89 During the construction phase there will be a notable presence and frequency of use of plant and
vehicles on Site. As such fuels, oils, paints, solvents and other chemical contaminants will be
stored and used on Site. The presence and utilisation of these contaminants increases the
potential for spillages and the likelihood of the contaminants reaching a watercourse.
9.90 Where fuels, oils and other chemicals enter a watercourse, they can have a number of effects on
water quality and can be particularly harmful to the local aquatic fauna.
9.91 The sensitivity of the Selbrook adjacent to the western boundary is considered medium due to
the connectivity with the River Frome (medium sensitivity).
9.92 Accidental spillages of chemical pollutants which could migrate towards the watercourse
adjacent to the Revised Scheme would have a substantial magnitude of impact on the
watercourse, with the potential to cause significant, long term changes to the watercourse.
9.93 In line with the assessment of significance matrix (Table 9.4), the overall significance of
accidental spillages of oils, fuels, or other chemicals during construction activities entering the
Selbrook adjacent to the western boundary of the Revised Scheme degrading water quality is
considered a moderate negative significance of effect, and therefore significant in EIA terms. Any
effect on the watercourse will be considered short term (i.e. duration of construction works in
proximity to the watercourse), and with the low-level sensitivity of the watercourse, non-
permanent and restricted to the local scale.
9.94 Due to the hydrological connectivity of the watercourse to the River Frome (medium sensitivity
in accordance with the WFD status), the magnitude of the impact due to a reduction in water
quality following accidental chemical spillages into the small watercourse discharging to the
Frome is considered medium. The flow of the River Frome and the distance from the Revised
Scheme to the confluence of the adjacent watercourse and the Frome is such that itallows for
potential remediation actions prior to reaching the Frome).
9.95 In line with the assessment of significance matrix (Table 9.4), the overall significance of
accidental spillages of oils, fuels, or other chemicals from the Revised Scheme degrading water
quality within the River Frome is considered a moderate negative significance of effect, and
therefore significant in EIA terms. Any effect on the watercourse will be considered short term
(i.e. duration of construction works in proximity to the watercourse), with the flow of the River
Frome and the distance from the Revised Scheme to the confluence of the adjacent watercourse
and the Frome limiting some of the impact. Both effects will therefore be viewed as significant
in EIA terms.
Cements and Concrete Spillages
9.96 During the construction phase there will be an increased presence and frequency of use of
cements and concretes. This use will necessitate the storage on Site and the transport to the
Site of the mixtures. The presence and utilisation of these mixtures increases the potential for
spillages and the likelihood of the contaminants reaching a watercourse.
9.97 Concretes and cements, when entering a watercourse, can have a number of effects on water
quality. Concretes and cements are highly alkaline and corrosive and can cause serious pollution
Eco Park, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol.1 Main Text
December 2015
Page | 143
to watercourse. Invertebrates and fish are particularly sensitive to changes in pH levels. Unlike
oil spillages, changes to pH levels in watercourses are not immediately apparent and can occur
for some time before the extent is realised.
9.98 Concretes and cements could potentially reach surface water receptors following accidental
spillages during the construction of the commercial units, via concrete wastewater or via
dispersal of concrete dust.
9.99 The sensitivity of the unnamed watercourse adjacent to the western boundary is considered
medium due to the connectivity with the River Frome (medium sensitivity).
9.100 Ingress of concretes and cements via spillages, wastewater or dust dispersal would have a
substantial magnitude impact on the watercourse adjacent to the Revised Scheme, with the
potential to cause significant, long term and potentially unseen changes to the watercourse.
9.101 In line with the assessment of significance matrix (Table 9.4), the overall significance of cements
and concretes activities entering the watercourse adjacent to the western boundary of the
Revised Scheme (The Selbrook) degrading water quality is considered a moderate negative
significance of effect, and therefore significant in EIA terms. Any effect on the watercourse will
be considered short term (i.e. duration of construction works in proximity to the watercourse),
and with the low-level sensitivity of the watercourse, non-permanent and restricted to the local
scale.
9.102 Due to the hydrological connectivity of the watercourse to the River Frome (medium sensitivity
in accordance with the WFD status), the magnitude of the impact due to a reduction in water
quality following ingress of concretes or cements into the small watercourse discharging to the
Frome is considered medium. The flow of the River Frome and the distance from the Revised
Scheme to the confluence of the adjacent watercourse and the Frome is such that it allows for
potential remediation actions prior to reaching the Frome).
9.103 In line with the assessment of significance matrix (Table 9.4), the overall significance of cements
and concretes from the Revised Scheme degrading water quality within the River Frome is
considered a moderate negative significance of effect and therefore significant in EIA terms. Any
effect on the watercourse would be considered short term (i.e. duration of construction works
in proximity to the watercourse), with the flow of the River Frome and the distance from the
Revised Scheme to the confluence of the adjacent watercourse and the Frome limiting some of
the impact. Both effects will therefore constitute significant effects in terms of the EIA
Regulations.
Operational Effects
9.104 The operational assessment stage is based on the completed designs with design evolution
(embedded mitigation - outlined above) and assumed design standards during the operational
phase.
9.105 During the operational phase, there is the potential for the utilisation of the Revised Scheme to
result in the following impacts on the water environment:
• Oil / fuel spillages and leaks from vehicles;
Eco Park, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol.1 Main Text
December 2015
Page | 144
• Potential flooding from surface water drainage network exceedance;
• New impermeable areas altering surface water runoff rates, impacting upon downstream
flood risk;
• New impermeable areas increasing risk on Site surface water flooding;
• Potential risk of increased flooding caused by climatic changes;
• Biodiversity and conservation effects.
9.106 Other than biodiversity and conservation effects, there are no significant effects anticipated by
the Revised Scheme. The full detailed assessments for non-significant effect during the
operational phase are included in RS Appendix 9.3.
9.107 The incorporation of the SuDS infiltration features into the surface water drainage network will
provide beneficial ecological and conservation effects. The SuDS features will introduce
attractive planting features, and increased biodiversity whilst helping to ensure adaptation to
climate change. Due to the desired nature of the development, demonstrating the best in
sustainability principles, the magnitude of the impact of the increased biodiversity following
SuDS development is considered medium.
9.108 In line with the assessment of significance matrix (Table 9.4), the overall significance of the
increased biodiversity following the incorporation of SuDS techniques into the drainage design
is considered moderate positive and therefore significant within the meaning of the EIA
Regulations.
Mitigation and Enhancement Measures
9.109 This sub-section details all of the mitigation and enhancement measures that will be
implemented during the construction and operational phases of the Revised Scheme.
9.110 Such measures will be secured through the production of a Construction Environmental
Management Plan (CEMP) for the development. A standalone Surface Water Management Plan
(SWMP) will be prepared in response to a condition on any planning permission that is granted.
These documents will be secured through planning conditions.
Best Practice
9.111 Mitigation and enhancement will include the use of appropriate measures as outlined on the
Environment Agency’s website and in the now revoked Environment Agency’s Pollution
Prevention Guidelines (PPGs) including guidance on storing and handling materials and products,
Site drainage and dealing with trade effluents, and good environmental practice. Specific details
are provided below:
• PPG 1: General guide to the prevention of water pollution;
• PPG 2: Above ground oil storage tanks;
• PPG 3: Use and design of oil separators in surface water drainage systems;
• PPG 4: Treatment and disposal of sewage where no foul sewer is available;
• PPG 5: Works and maintenance in or near watercourses;
• PPG 6: Working at construction and demolition Sites;
• PPG 7: Safe storage – The safe operation of refueling facilities;
• PPG 8: Safe storage and disposal of used oils;
Eco Park, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol.1 Main Text
December 2015
Page | 145
• PPG 13: Vehicle washing and cleaning;
• PPG 20: Dewatering of underground ducts and chambers;
• PPG 21: Pollution incident response planning;
• PPG 22: Incident response – dealing with spills;
• PPG 26: Safe storage - drums and intermediate bulk containers.
9.112 In line with the Pollution Prevention Guidelines (in particular PPG5) and best practice to reduce
the instance of silt laden and or contaminated runoff from the Site during the construction
period, the following measures will be implemented.
9.113 With respect to stockpiles, exposed ground and sediment:
• Minimise the amount of exposed ground and soil stockpiles from which water drains and
the period of time such water drains (any surplus excavated materials will be disposed of
offsite as early as possible);
• Gaps will be provided at intervals in the stockpiles to act as water pathways to ensure that
floodwater movement is not hindered and surface water flooding is not exacerbated;
• Only remove vegetation from the area that needs to be exposed in the near future (ensure
a vegetated strip will be left adjacent to any watercourses);
• Seed or cover stockpiles;
• All soils will be stored away from watercourses and any potentially contaminated soil will
be stored on an impermeable surface and covered to reduce leachate generation and
potential migration to surface waters;
• Use of silt fences at the toe of the slopes, made from semi-permeable geotextile fabric,
vertically held on timber post, to reduce sediment transportation;
• Use of silt traps on the inlet or outlets side of culverts to reduce sediment transportation;
• Provided lagoons / ponds that allow suspended solids to settle out before disposal;
• Use of straw bales to filter out sediment from normal flows in drainage ditches, pinned
into position to avoid being washed away. Silt laden bales should be discarded in line with
relevant waste regulations.
9.114 With respect to on-Site working:
• Ensure that any vehicle or plant washing is carried out on designated areas of hard
standing at least 10m from any watercourse or surface water body;
• Collect run-off from hard standing area in a sump;
• Ensure settled solids are removed regularly.
9.115 For the disposal of contaminated water treatment and disposal methods include:
• Tanker off Site by registered waste carrier;
• Discharge to foul sewer (subject to agreements);
• Use of Sustainable Drainage Systems (SuDS);
• Settlement lagoons to allow contaminants to settle out;
• Filtration through use of straw bales or geotextiles.
9.116 With respect to safe storage and use of concrete and cement, concrete and cement mixing and
washing areas should:
Eco Park, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol.1 Main Text
December 2015
Page | 146
• Be sited 10m from any watercourse or surface water drain to minimise the risk of runoff
entering a watercourse;
• Have settlement and re-circulation systems for water re-use, to minimise the risk of
pollution and reduce water usage;
• Dispose of contained water to either foul sewer if possible, or tanker off Site.
9.117 With respect to safe storage and use of oils and chemicals:
• Fuel, oil and chemical storage should be on an impervious base within a secondary
containment system such as a bund. The base and bund walls should be impermeable to
the solution stored and be able to contain at least 110% of the volume stored;
• The storage facility should be sited at least 10m from any watercourse and 50m away from
any well, borehole or spring;
• Appropriate spill kits should be stored in the immediate vicinity of the storage facility and
trained staff to utilise in case of incident.
9.118 When refuelling (risk of spillage is greatest when refuelling plant):
• Refuel mobile plant in designated areas, or on impermeable base away from drain,
watercourses or abstraction locations;
• Use a bunded bowser;
• Supervise all refuelling and bulk deliveries;
• Check the available capacity in the tank before refuelling;
• Don’t jam open a delivery valve;
• Check hoses and valves regularly for signs of wear;
• Turn off valves after refuelling and lock them when not in use;
• Position drip trays under pumps to catch minor spills;
• Keep a spill kit with sand, earth or commercial products for containment of spillages;
• Provide incident response training to staff and contractors.
9.119 With respect to vehicle and wheel washing on Site:
• Vehicle washing and cleaning should be carried out in areas that are clearly marked and
isolated from surface water drainage systems, unmade ground and porous surfaces
(designated washing bays);
• A designated washing bay should be designed so that runoff is isolated using channels,
gullies, gradients, directed to a silt trap or sediment tank to remove larger particles, and
either collected in a sealed system for reuse or authorised disposal or discharged to public
foul sewer (subject to approval).
9.120 With respect to oils and trade materials on Site:
• If possible, use biodegradable hydraulic oil in plant when working in or near watercourses;
• If possible, use water based or low solvent products;
• Avoid products containing lead as a drying agent and those containing hazardous solvents
(toluene or chlorinated hydrocarbons);
• Provide safe and secure storage (biodegradable oils to same standards as synthetic oils).
Eco Park, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol.1 Main Text
December 2015
Page | 147
9.121 With respect to any uncontrolled (and particulate) runoff from construction areas and access
tracks:
• Any compounds should, where possible, utilise a wide strip of geotextile laid on the
ground covered by a nominal layer of stone to form the compound. Areas of the
construction compound such as porta cabins, storage systems etc., will result in the
potential increase in surface water runoff;
• Generally, the compounds will maintain a permeable nature, however as there will be an
increase in hard standing, a form of attenuation will be required on Site to maintain flow
rates at the pre-development level;
• Any flows in excess of the infiltration rates will be stored in the attenuation facility and
will not have an effect on land outside the Site. The specifications of the attenuation
facility will be determined at the detailed design stage;
• Where stone is used as a capping layer, the content of the stone should not include a high
percentage of fines so as not to increase the risk of sediment contamination of the
adjacent area and watercourses.
Residual Effects
9.122 An assessment of the significance of the effects likely to arise as a result of the Revised Scheme
after embedded mitigation and further mitigation and enhancement measures have been
employed is included at the end of the chapter in Table 9.8 (Construction) and Table 9.9
(Operational).
9.123 The assessment of significance in terms of each receptor is included (in full) for both significant
and non-significant effects in RS Appendix 9.3.
9.124 A detailed Flood Risk Assessment has been carried out on this Site and an assessment of potential
effects on potential receptive watercourses and other hydrological elements has been carried
out. Several of the watercourses in the vicinity of the Site have been assessed to be of moderate
sensitivity. This assessment concludes that without mitigation there is potential for significant
negative effects on the River Frome and associated tributaries, primarily from spillages of
chemicals and cements potentially degrading water quality of the watercourses.
9.125 Suitable mitigation in the form of an appropriately detailed CEMP (including a Pollution
Prevention Plan), will be developed and agreed with the Local Planning Authority (LPA) and the
Environment Agency during the evolution of Reserved Matters Applications prior to
commencement on Site. Therefore, these potentially significant effects can be removed, to
ensure there are no significant negative effects on these watercourses.
9.126 Comprehensive biodiversity enhancements throughout the Site through the development of the
SuDS drainage network will ensure that water quality is not diminished, and in turn, the
development does not compromise the objectives of the Water Framework Directive. The
development will also ensure that ecological value, ecosystem service value and benefit to
human health and wellbeing is increased and represents a residual positive effect resulting from
the biodiversity enhancements.
Eco Park, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol.1 Main Text
December 2015
Page | 148
9.127 The majority of the effects following the Design Evolution and any further mitigation (as secured
through the CEMP) are not considered significant.
Cumulative Effects
9.128 Cumulative effects, both individually and in combination, on hydrological receptors may arise
from multiple developments within the range of sensitivity of each receptor. Effects may be
direct (such as water pollution) or indirect (such as habitat loss).
Scope of Cumulative Assessment
9.129 The cumulative assessment considers major planned development (i.e. validated planning
applications and schemes at appeal) within 5km of the developable area. Relevant proposals at
the pre-planning stage (‘in scoping’) are also considered including the Cotswolds Canals
Partnership Phase1b Proposals for restoration of the Stroudwater Canal. The cumulative
assessment schemes (CAS) which have the potential to cause cumulative ecological effects are
listed in Table 9.7.
Effect interactions
9.130 The potential for interaction between effects on the hydrology, drainage and flood risk and other
aspects of the environment are identified in other technical chapters and also described here.
Biodiversity and Hydrology
9.131 Possible inter-relationships can occur between the water environment and aquatic ecology and
biodiversity.
9.132 Mobilised materials (suspended solids) can potentially produce adverse effects on aquatic
ecology. In particular, suspended solids may have an effect on:
• the survival of fish eggs in gravel beds or spawning grounds as a result of deoxygenation
caused by silt deposition;
• the survival of plants and algae by smothering;
• the survival of young fish and aquatic invertebrates such as dragonflies through gill
damage from sediment particles;
• the success of angling owing to increased turbidity;
• amenity value through impaired visual appearance.
Ground Environment and Hydrology
9.133 Inter-relationships will occur between the hydrological and ground environment. The ground
environment interacts with the hydrology principally through groundwater and the
hydrogeological environment. The hydrology can also be affected through changes in soil
drainage parameters, which has implications on flooding patterns; via sediment ingress or
migration of contamination to surface watercourses. Groundwater within permeable superficial
and bedrock strata provides base flow of water to surface water courses and rivers on a local and
regional scale. Contamination within groundwater has the potential to migrate to surface water.
Similarly, possible inter-relationships will also be present between surface water hydrology and
hydrogeology.
Eco Park, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol.1 Main Text
December 2015
Page | 149
Climate Change and Major Accidents and Disasters
9.134 Inter-relationships will occur between the hydrological and changing climatic influences. In
terms of Climate Change, in line with the current guidelines the Revised Scheme has been
considered in line with the allowances for peak river flow increases and rainfall increases. Due
to the location of the Revised Scheme in Flood Zone 1, the flow increase attributed to climate
change in the Frome are not applicable to the Revised Scheme. Climate Change allowances in
terms of increased rainfall will be included as part of the drainage strategy for the Revised
Scheme.
Cumulative Inter-Relationships
9.135 There are 9 applications at varying stages of planning as outlined by SDC that have been
identified as having as either having effect interactions or in-combination effects. The details of
the proposals are provided in Table 2.5 and illustrated in RS Figure 18.1 (other than the Junction
13 Highways Drainage Works).
9.136 The following committed developments (Table 9.7), as set out on the following page, have been
cumulatively assessed with respect to hydrology and flood risk and scoped in or out of the
assessment accordingly.
Eco Park, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol.1 Main Text
December 2015
Page | 150
Table 9.7: Cumulative Effects
Planning application
/ allocation ref no. Application Cumulative Assessment
Cumulative Effects
S.14/0810/OUT
Land West of
Stonehouse
Nastend Lane,
Nastend,
Stonehouse,
Gloucestershire
Application
Permitted
S.17/0095/REM
Land West of
Stonehouse Nastend
Lane, Nastend,
Stonehouse,
Gloucestershire,
S.14/0810/OUT
A mixed-use development
comprising up to 1,350
dwellings and 9.3 hectares
of employment land for
use classes B1, B2 and B8;
a mixed use local centre
comprising use classes A1,
A2, A3, A4, A5, D1, D2 and
B1; primary school, open
space and landscaping,
parking and supporting
infrastructure and utilities;
and the creation of new
vehicular accesses from
Grove Lane, Oldends Lane
and Brunel Way.
S.17/0095/REM
Development of areas H1
H6 and H7 as identified in
S.14/0810/OUT for 103
new dwellings comprising
73 open market units and
30 affordable units with
associated infrastructure,
open space and
landscaping.
Summary of Project Detail
Land West of Stonehouse
The construction of the Land West of Stonehouse on land to the north east of Redline Boundary is outlined for a mixed-use
development comprising up to 1,350 dwellings and areas of employment and non-residential uses off Nastend Lane Stonehouse.
Description of Potential Effects
The aspects of the Revised Scheme and the proposed Land West of Stonehouse Site that will result in potential effects on
hydrology are identified below and include;
• The introduction of the stadium and associated infrastructure
• The introduction of the residential and non-residential components of the Land West of Stonehouse scheme
Assessment of Potential Cumulative Effects – During Construction
Revised Scheme.
As discussed in this Chapter, the Revised Scheme will have a moderate negative significance of effect on the tributary of the River
Frome and the River Frome, which both attain a medium sensitivity in line with the direction of the WFD in terms of water quality
following chemical or cement spillages.
The Land West of Stonehouse development
The construction the development is underway, therefore there is potential that there will be an overlap between the
construction phases of the two developments. If developed unmitigated it is assumed that similar effects would occur during the
construction phase and it is therefore inferred that the effect on hydrology will be considered a moderate negative significance
of effect.
Cumulative Effects
Flood Risk
The sensitivity of the land outlined for development (land undeveloped at the Site until 2017) will be classified as low significance
in terms of flood risk. Should the developments occur simultaneously (unmitigated), the magnitude of the cumulative effects will
be considered medium. Therefore, the overall significance of the cumulative increase in surface water runoff and pluvial flooding
potential is considered slight negative, and as such will not be considered significant in EIA terms. If the development timescales
were staggered, the significance of effect will be reduced to negligible
Water Quality
Generally, due to the ‘upstream’ location of the development of ‘West of Stonehouse Site’ the construction works can affect the
Revised Scheme (i.e. increase in silt laden runoff / spillages). As there is potential that both Sites be constructed simultaneously,
Pre-mitigation – minor negative
to moderate negative
significant effects, therefore if
left unmitigated will be
considered significant in EIA
terms.
Following mitigation if both
developments are constructed
simultaneously - negligible
cumulative effects expected
and therefore not significant in
EIA terms.
Eco Park, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol.1 Main Text
December 2015
Page | 151
Planning application
/ allocation ref no. Application Cumulative Assessment
Cumulative Effects
there will be an elevated potential for cumulative effects stemming from silt laden runoff or pollutant spillages. The significance
of the receptor unnamed tributary of the River Frome will be medium (draining to the River Frome) and in turn the River Frome
will be considered medium (moderate water quality under the WFD).
Should the developments occur simultaneously (unmitigated), the magnitude of the silt laden runoff cumulative effects will be
considered medium. Therefore, the overall significance of the unmitigated cumulative increase in silt laden runoff from both
developments will be considered moderate negative if the development timescales overlap. If the development timescales were
staggered, the significance of effect will be reduced to minor.
Should the developments occur simultaneously (unmitigated), the magnitude of the chemical spillages cumulative effects will be
considered substantial. Therefore, the overall significance of the unmitigated cumulative increase in chemical spillages both
developments will be considered moderate negative if the development timescales overlap. If the development timescales were
staggered, the significance of effect will remain moderate negative.
Mitigation / Design Evolution
It is anticipated that West of Stonehouse will be developed in line with the planning policy guidance at the time (NPPF)
It was confirmed that for the Land West of Stonehouse Site, the FRA demonstrated that the Site is suitable for development
without increasing flood risk elsewhere. The development will also ensure that SuDS will be used to manage surface water from
the development and to ensure that water quality is not adversely affected.
The proposed surface water outfall from Revised Scheme is via soakaway and there will be negligible effects on water quality if
both developments are constructed simultaneously.
No mitigation is proposed above and beyond what has already been outlined for the Revised Scheme as this has been developed
to satisfy local and national policies.
Residual Cumulative Effects (following mitigation)
The residual cumulative effects on flood risk following the implementation of the specified mitigation and best if both
developments are constructed simultaneously will be seen as negligible.
The residual cumulative effects on water quality following the implementation of the specified mitigation and best if both
developments are constructed simultaneously will be seen as negligible.
If development timescales for the two developments are staggered, the significance of the residual cumulative effects will remain
negligible.
Cumulative Effects between the Revised Scheme, Land West of Stonehouse Site and Canal Restoration.
There are no cumulative effects anticipated between the West of Stonehouse Site, the Revised Scheme and the proposed canal
works. This is due to the A419 and the tributary of the River Frome separating the West of Stonehouse Site and the proposed
canal works. The tributary of the River Frome and the A419 will create a hydraulic separation between the West of Stonehouse
Site and the canal.
Eco Park, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol.1 Main Text
December 2015
Page | 152
Planning application
/ allocation ref no. Application Cumulative Assessment
Cumulative Effects
The cumulative effects of the Revised Scheme and the proposals for the canal are outlined within this table.
S.12/0763/FUL
Unit 27, Bonds Mill,
Bristol Road,
Stonehouse
Permitted
Demolition of part of an
existing warehouse
including a hoist on the
adjacent building,
renovation of the
remainder as office space
and erection of a two
storey extension.
Overview
Approximately 1.65km from the northernmost Site boundary and separated by the Grove Lane and Grove Farm.
As a permitted development it is assumed that the demolition and construction works will have commenced if not completed
within 3 years (from 2102 determination date for S.12/0763/FUL) and unlikely to be in conjunction with the Revised Scheme.
The development is outlined to drain to soakaway / River Frome. There will be no cumulative hydrological effects as a result of
the Revised Scheme.
No cumulative effects
anticipated
S.15/1088/FUL
Westend Courtyard
Grove Lane,
Westend,
Stonehouse,
Gloucestershire
Permitted
Proposed extension to
Westend courtyard to
provide 10 additional
offices (B1 use).
Overview
Approximately 150m from the northernmost Redline Boundary and separated by the Grove Lane and Grove Farm.
The development is outlined to drain to soakaway, and as such there will be no direct hydraulic linkages between the two
developments. There will be no cumulative hydrological effects as a result of the Revised Scheme.
No cumulative effects
anticipated
S,15/2089/OUT
Land adjacent to
Eastington Trading
Estate, Churchend,
Eastington,
Gloucester
Permitted
Erection of three
industrial employment
buildings with associated
access, car parking and
service yards (Outline
application - Access,
Layout and Scale
included).
Summary of Project Detail
The Site to the east of the Redline Boundary is outlined for industrial employment uses.
Description of Potential Effects
The aspects of the Revised Scheme and the proposed Former Land adjacent to Eastington Trading Estate site that will result in
potential effects on hydrology are identified below and include;
• The introduction of the stadium and associated infrastructure and the introduction of the new industrial uses
Assessment of Potential Cumulative Effects – During Construction
The Revised Scheme
As discussed in this Chapter, the Revised Scheme will have a moderate negative significance of effect on the River Frome, which
attains a medium sensitivity in line with the direction of the WFD in terms of water quality following chemical or cement
spillages.
Land at adjacent to Eastington Trading Estate
No cumulative effects
anticipated
Eco Park, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol.1 Main Text
December 2015
Page | 153
Planning application
/ allocation ref no. Application Cumulative Assessment
Cumulative Effects
The construction timeframe for the development is as yet unconfirmed, the application has been permitted, therefore there is
potential that there could be an overlap between the construction phases of the two developments. If developed unmitigated
it will be assumed that similar effects will occur during the construction phase and it is therefore inferred that the effect on
hydrology will be considered a moderate negative significance of effect.
Cumulative Effects
Water Quality
Generally, due to the ‘upstream’ location of the development of ‘Eastington Trading Estate site’ the construction works can
affect the Revised Scheme (i.e. increase in silt laden runoff / spillages). As there is potential that both Sites be constructed
simultaneously, there will be an elevated potential for cumulative effects stemming from silt laden runoff or pollutant spillages.
The significance of the receptor, the River Frome will be medium (moderate water quality under the WFD).
Should the developments occur simultaneously and unmitigated, the magnitude of the cumulative silt laden runoff cumulative
effects will be considered minor, as a hydraulic connection is maintained through River Frome. Therefore, the overall
significance of the unmitigated cumulative increase in silt laden runoff from both developments will be considered minor
negative if the development timescales overlap. If the development timescales were staggered, the significance of effect will
be reduced to minor.
Should the developments occur simultaneously and unmitigated, the magnitude of the cumulative chemical spillages will be
considered medium, as a hydraulic connection is maintained through the Stroudwater Navigation / River Frome. Therefore, the
overall significance of the unmitigated cumulative increase in chemical spillages both developments would be considered
moderate negative if the development timescales overlap. If the development timescales were staggered, the significance of
effect would remain moderate negative.
Mitigation / Design Evolution
It is anticipated that development at the Eastington Trading Estate, will be developed in line with the planning policy guidance
at the time (NPPF)
It is assumed that the development will also ensure that SuDS will be used to manage surface water from the development and
to ensure that water quality is not adversely affected as has been outlined in the Flood Risk Assessment for the development.
The proposed surface water outfall from the Revised Scheme is via soakaway and there will be negligible effects on water
quality if both developments are constructed simultaneously.
No mitigation is proposed above and beyond what has already been outlined for the development of the Revised Scheme as
this has been developed to satisfy local and national policies.
Residual Cumulative Effects (following mitigation)
The residual cumulative effects on flood risk following the implementation of the specified mitigation and if both developments
are constructed simultaneously will be seen as negligible.
Eco Park, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol.1 Main Text
December 2015
Page | 154
Planning application
/ allocation ref no. Application Cumulative Assessment
Cumulative Effects
The residual cumulative effects on water quality following the implementation of the specified mitigation and if both
developments are constructed simultaneously will be seen as negligible.
If development timescales for the two developments are staggered, the significance of the residual cumulative effects will
remain negligible.
Canal to the south
of the Site
(reinstatement of
Stroudwater Canal)
Canal realignment scheme
subject to successful bid
funding from Canal and
River Trust.
Summary of Project Detail
Stroudwater Canal reinstatement
The reinstatement of the Stroudwater Canal in land adjacent to the southern Redline Boundary.
Description of Potential Effects
The aspects of the Revised Scheme and the proposed Land West of Stonehouse Site that will result in potential effects on
hydrology are identified below and include;
• The introduction of the stadium and associated infrastructure
• The reinstatement of the Stroudwater Canal and any new features added.
Assessment of Potential Cumulative Effects – During Construction
The Revised Scheme
As discussed in this Chapter, the Revised Scheme will have a moderate negative significance of effect on the tributary of the River
Frome and the River Frome, which both attain a medium sensitivity in line with the direction of the WFD in terms of water quality
following chemical or cement spillages.
Stroudwater Canal
The construction timeframe for the development is as yet unconfirmed, the application is currently being submitted for funding,
therefore there is potential that there could be an overlap between the construction phases of the two developments. If
developed unmitigated it will be assumed that similar effects will occur during the construction phase and it is therefore inferred
that the effect on hydrology will be considered a moderate negative significance of effect.
Cumulative Effects
Water Quality
Generally, due to the ‘downstream’ / adjacent location of the reinstatement works the construction works can affect the Revised
Scheme and on the canal, works (i.e. increase in silt laden runoff / spillages). As there is potential that both Sites be constructed
simultaneously, there will be an elevated potential for cumulative effects stemming from silt laden runoff or pollutant spillages.
The significance of the receptor (The Selbrook) y of the River Frome will be medium (draining to the River Frome) and in turn the
River Frome will be considered medium (moderate water quality under the WFD).
Following mitigation if both
developments are constructed
simultaneously - negligible
cumulative effects expected.
Eco Park, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol.1 Main Text
December 2015
Page | 155
Planning application
/ allocation ref no. Application Cumulative Assessment
Cumulative Effects
Should the developments occur simultaneously and unmitigated, the magnitude of the cumulative silt laden runoff will be
considered medium. This is due to the potentially large volume of excavated soils to construct the canal in close proximity to
assessed watercourses that maintain a hydraulic connection between the Sites. Therefore, the overall significance of the
unmitigated cumulative increase in silt laden runoff from both developments will be considered moderate negative if the
development timescales overlap. If the development timescales were staggered, the significance of effect will be reduced to
minor.
Should the developments occur simultaneously and unmitigated, the magnitude of the cumulative chemical spillages will be
considered medium. Therefore, the overall significance of the unmitigated cumulative increase in chemical spillages both
developments will be considered moderate negative if the development timescales overlap. If the development timescales were
staggered, the significance of effect will remain moderate negative.
Mitigation / Design Evolution
It is anticipated that canal restoration will be developed in line with the planning policy guidance (NPPF) / design standards at the
time.
The proposed surface water outfall from the Revised Scheme is via soakaway and there will be negligible effects on water quality
if both developments are constructed simultaneously.
No mitigation is proposed above and beyond what has already been outlined for the development of the Revised Scheme as this
has been developed to satisfy local and national policies.
Residual Cumulative Effects (following mitigation)
The residual cumulative effects on flood risk following the implementation of the specified mitigation and best if both
developments are constructed simultaneously will be seen as negligible.
The residual cumulative effects on water quality following the implementation of the specified mitigation and best if both
developments are constructed simultaneously will be seen as negligible.
If development timescales for the two developments are staggered, the significance of the residual cumulative effects will remain
negligible.
13/0001/INQUIR
Land at Javelin Park
Planning Appeal
Proposed development of
an Energy from Waste
(EfW) facility for the
combustion of non-
hazardous waste and the
generation of energy
Overview
The application at Javelin Park is approximately 5km from the Redline Boundary and separated by various built infrastructure.
With no hydraulic connectivity between the Sites there will be no cumulative effects anticipated through the development of
both applications.
No cumulative effects
anticipated
17/0563/OUT
Land off School
Lane, Whitminster,
Gloucestershire
Residential development
for up to 60 dwellings
including infrastructure,
ancillary facilities, open
Overview
No cumulative effects
anticipated
Eco Park, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol.1 Main Text
December 2015
Page | 156
Planning application
/ allocation ref no. Application Cumulative Assessment
Cumulative Effects
Application Refused
space and landscaping.
Construction of a new
vehicular access from
School Lane.
The application is approximately 3km from the Redline Boundary and separated by various built infrastructure. With no hydraulic
connectivity between the Sites there will be no cumulative effects anticipated through the development of both applications.
S.17/1133/FUL
S.17/1134/LBC
Former Standish
Hospital and Former
Westridge Hospital
Standish,
Stonehouse,
Gloucestershire
Pending
Consideration
Conversion and
refurbishment of the
former Standish Hospital
complex, including
Standish House (Building
A), Stable Block (Building
B), Ward Blocks (Buildings
C & G), Standish Lodge
(Building L), Building I, and
demolition and works to
associated out-buildings
and gatehouse to form 50
dwellings; demolition of
Westridge Hospital and
associated building.
Development of 98 new
build homes within the
grounds; conversion;
associated surface vehicle
and cycle car parking,
pedestrian and vehicular
access and associated
ancillary development,
landscaping, ancillary
storage and plant and
ecological bat housing;
and all associated
engineering works and
operations
Summary of Project Detail
Former Standish Hospital and Former Westridge Hospital Standish, the site to the east of the Revised Scheme is outlined for a
residential development comprising up to 148 dwellings and areas of ancillary facilities and landscaping.
Description of Potential Effects
The aspects of the Revised Scheme and the proposed Former Standish Hospital and Former Westridge Hospital Standish Site
that will result in potential effects on hydrology are identified below and include;
• The introduction of the stadium and associated infrastructure
• The introduction of the residential and non-residential components of the Former Standish Hospital and Former
Westridge Hospital Standish, scheme
Assessment of Potential Cumulative Effects – During Construction
The Revised Scheme
As discussed in this Chapter, the Revised Scheme will have a moderate negative significance of effect on the River Frome, which
attains a medium sensitivity in line with the direction of the WFD in terms of water quality following chemical or cement
spillages.
Former Standish Hospital and Former Westridge Hospital Standish,
The construction timeframe for the development is as yet unconfirmed, the application is currently at appeal, therefore there is
potential that there could be an overlap between the construction phases of the two developments. If developed unmitigated
it will be assumed that similar effects will occur during the construction phase and it is therefore inferred that the effect on
hydrology will be considered a moderate negative significance of effect.
Cumulative Effects
Water Quality
Generally, due to the ‘upstream’ location of the development of ‘Former Standish Hospital and Former Westridge Hospital
Standish Site’ the construction works can affect the Revised Scheme (i.e. increase in silt laden runoff / spillages). As there is
potential that both Sites be constructed simultaneously, there will be an elevated potential for cumulative effects stemming
from silt laden runoff or pollutant spillages. The significance of the receptor, the River Frome will be medium (moderate water
quality under the WFD).
Following mitigation if both
developments are constructed
simultaneously - negligible
cumulative effects expected.
Eco Park, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol.1 Main Text
December 2015
Page | 157
Planning application
/ allocation ref no. Application Cumulative Assessment
Cumulative Effects
Should the developments occur simultaneously and unmitigated, the magnitude of the cumulative silt laden runoff cumulative
effects will be considered minor. This is due to the 4km separating the Site, yet a hydraulic connection being maintained
through the River Frome. Therefore, the overall significance of the unmitigated cumulative increase in silt laden runoff from
both developments will be considered minor negative if the development timescales overlap. If the development timescales
were staggered, the significance of effect will be reduced to minor.
Should the developments occur simultaneously and unmitigated, the magnitude of the cumulative chemical spillages will be
considered medium. This is due to the 4km separating the Site, yet a hydraulic connection being maintained through the River
Frome. Therefore, the overall significance of the unmitigated cumulative increase in chemical spillages both developments
would be considered moderate negative if the development timescales overlap. If the development timescales were staggered,
the significance of effect would remain moderate negative.
Mitigation / Design Evolution
It is anticipated that Former Standish Hospital and Former Westridge Hospital Standish, will be developed in line with the
planning policy guidance at the time (NPPF)
It is assumed that the development will also ensure that SuDS will be used to manage surface water from the development and
to ensure that water quality is not adversely affected.
The proposed surface water outfall from the Revised Scheme is via soakaway and there will be negligible effects on water
quality if both developments are constructed simultaneously.
No mitigation is proposed above and beyond what has already been outlined for the development of the Revised Scheme as
this has been developed to satisfy local and national policies.
Residual Cumulative Effects (following mitigation)
The residual cumulative effects on flood risk following the implementation of the specified mitigation and best if both
developments are constructed simultaneously will be seen as negligible.
The residual cumulative effects on water quality following the implementation of the specified mitigation and best if both
developments are constructed simultaneously will be seen as negligible.
If development timescales for the two developments are staggered, the significance of the residual cumulative effects will
remain negligible.
S.16/0922/REM
Land Adjoining
Station Road Bristol
Road, Stonehouse,
Gloucestershire,
GL10 3RB
Approval of reserved
matters Appearance and
Landscaping from appeal
APP/C1625/A/13/2195656
(S.12/2538/OUT) -
residential development
Overview
The application is a reserved matters application (Appearance and Landscaping) and in excess of 2km from the Site there will be
no cumulative effects anticipated through the development of both applications.
No cumulative effects
anticipated
Eco Park, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol.1 Main Text
December 2015
Page | 158
Planning application
/ allocation ref no. Application Cumulative Assessment
Cumulative Effects
Application
Approved
for 49 units, new access
way and associated works.
S.17/2331/OUT
Land Adjoining
Oldbury Lodge Pike
Lock Lane
Eastington
Gloucestershire
Awaiting Decision
Erection of new buildings
for uses within use class
C1 (Hotel) up to 1,908
Sqm (56 Beds), and use
classes A3 / A4 Pub
(Pub/Restaurant) up to
711 Sqm (Including
ancillary manager's
apartment) and associated
access, servicing, parking,
drainage and landscaping
(outline application: all
matters reserved except
for access and scale)
Summary of Project Detail
The Site to the east of the Redline Boundary is outlined for hotel and pub development comprising up to 56 beds and areas of
ancillary facilities and landscaping.
Description of Potential Effects
The aspects of the Revised Scheme and the proposed Former Land at Oldbury Lodge, site that will result in potential effects on
hydrology are identified below and include;
• The introduction of the stadium and associated infrastructure The introduction of the hotel and pub
Assessment of Potential Cumulative Effects – During Construction
The Revised Scheme
As discussed in this Chapter, the Revised Scheme will have a moderate negative significance of effect on the River Frome, which
attains a medium sensitivity in line with the direction of the WFD in terms of water quality following chemical or cement
spillages.
Land at Oldbury Lodge
The construction timeframe for the development is as yet unconfirmed, the application is currently awaiting decision, therefore
there is potential that there could be an overlap between the construction phases of the two developments. If developed
unmitigated it will be assumed that similar effects will occur during the construction phase and it is therefore inferred that the
effect on hydrology will be considered a moderate negative significance of effect.
Cumulative Effects
Water Quality
Generally, due to the ‘upstream’ location of the development of ‘Former Land at Oldbury Lodge, Site’ the construction works
can affect the Revised Scheme (i.e. increase in silt laden runoff / spillages). As there is potential that both Sites be constructed
simultaneously, there will be an elevated potential for cumulative effects stemming from silt laden runoff or pollutant spillages.
The significance of the receptor, the River Frome will be medium (moderate water quality under the WFD).
Should the developments occur simultaneously and unmitigated, the magnitude of the cumulative silt laden runoff cumulative
effects will be considered minor, as a hydraulic connections maintained through the Stroudwater Navigation / River Frome.
Therefore, the overall significance of the unmitigated cumulative increase in silt laden runoff from both developments will be
considered minor negative if the development timescales overlap. If the development timescales were staggered, the
significance of effect will be reduced to minor.
Following mitigation if both
developments are constructed
simultaneously - negligible
cumulative effects expected.
Eco Park, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol.1 Main Text
December 2015
Page | 159
Planning application
/ allocation ref no. Application Cumulative Assessment
Cumulative Effects
Should the developments occur simultaneously and unmitigated, the magnitude of the cumulative chemical spillages will be
considered medium, as a hydraulic connections maintained through the Stroudwater Navigation / River Frome. Therefore, the
overall significance of the unmitigated cumulative increase in chemical spillages both developments would be considered
moderate negative if the development timescales overlap. If the development timescales were staggered, the significance of
effect would remain moderate negative.
Mitigation / Design Evolution
It is anticipated that development at the Land adjoining Oldbury Lodge, will be developed in line with the planning policy
guidance at the time (NPPF)
It is assumed that the development will also ensure that SuDS will be used to manage surface water from the development and
to ensure that water quality is not adversely affected.
The proposed surface water outfall from the Revised Scheme is via soakaway and there will be negligible effects on water
quality if both developments are constructed simultaneously.
No mitigation is proposed above and beyond what has already been outlined for the development of the Revised Scheme as
this has been developed to satisfy local and national policies.
Residual Cumulative Effects (following mitigation)
The residual cumulative effects on flood risk following the implementation of the specified mitigation and best if both
developments are constructed simultaneously will be seen as negligible.
The residual cumulative effects on water quality following the implementation of the specified mitigation and best if both
developments are constructed simultaneously will be seen as negligible.
If development timescales for the two developments are staggered, the significance of the residual cumulative effects will
remain negligible.
Eco Park, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol.1 Main Text
December 2015
Page | 160
Conclusions
9.137 The development has the potential to effect upon different receptors during the construction of
the development and operational phase.
9.138 During the construction period significant adverse effects may arise from the development of
the Revised Scheme from uncontrolled sediment runoff created during the construction of the
Site or spillages of chemical pollutants (oils, cements, paints etc.) entering the surface water
network. Upon operation significant adverse effects may arise from uncontrolled spills and leaks
of vehicular fluids entering the surface water network or surface water flooding caused by heavy
rainfall falling on the new road and areas of hardstanding. The incorporation of the SuDS within
the drainage design may give rise to positive biodiversity and water quality effects during the
operation of the Site.
9.139 The risks to the water environment and development during the construction phase and
operational phase has been assessed in line with current policy and legislation. Mitigation has
been outlined to ensure that in line with good construction practices, the surface water and
groundwater networks will be sufficiently protected against pollution and occupiers of the Site
and the adjacent areas will not experience any residual adverse significant effects in EIA terms.
The detailed summary of the specific effects is outlined in Table 9.8 and Table 9.9.
9.140 Due to the inclusion of the surface water drainage plan and associated landscape / biodiversity
works, there will be a residual positive significant effect in EIA terms through the biodiversity
enhancements.
Eco Park, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol.1 Main Text
December 2015
Page | 161
Table 9.8: Summary of Flood Risk, Hydrology and Drainage Construction Effects and Mitigation
Receptor Effect Development
Phase
Sensitivity
/
importance
of receptor
Magnitude
Change
Level of Effect
(and
Significance)
prior to
mitigation
Mitigation Enhancement Level of Effect
(and
Significance)
after mitigation
Nature
of
effect
Watercourse
adjacent to western
Redline Boundary
boundary
Sedimentation of
watercourses effecting upon
water quality
Construction Medium Minor to
Negligible
Minor
negative / not
significant
PPG 5 N/A Negligible / not
significant
N/A
River Frome Sedimentation of
watercourses effecting upon
water quality
Construction Medium
Minor to
Negligible
Minor
negative / not
significant
PPG 5 N/A Negligible / not
significant
N/A
Culvert beneath M5 /
land upstream of
culvert
Siltation of M5 culvert
reducing capacity
Construction Low
N/A Minor
negative / not
significant
PPG 5 Unblocking of
culvert
maintaining /
improving flow
Minor positive /
not significant
Positive
The Selbrook Spillages of fuels, oils, paints
or solvents into watercourse
effecting upon water quality
Construction Medium
Substantial
to
Negligible
Moderate
negative /
significant
PPGs Prevention of
pollutants
entering
watercourse
Negligible / not
significant
N/A
River Frome Spillages of fuels, oils, paints
or solvents into watercourse
effecting upon water quality
Construction Medium
Medium to
Negligible
Moderate
negative /
significant
PPGs Prevention of
pollutants
entering
watercourse
Negligible / not
significant
N/A
The Selbrook Spillages of cements and
concretes into watercourse
increasing alkalinity of water
Construction Medium Substantial
to
Negligible
Moderate
negative /
significant
PPGs Prevention of
pollutants
entering
watercourse
Negligible / not
significant
N/A
River Frome Spillages of cements and
concretes into watercourse
increasing alkalinity of water
Construction Medium Medium to
Negligible
Moderate
negative /
significant
PPGs Prevention of
pollutants
entering
watercourse
Negligible / not
significant
N/A
Open watercourse Inappropriate disposal of
foul waste to watercourse
Construction N/A N/A No effect / not
significant
Industrial waste will be
stored on Site,
N/A No effect / not
significant
N/A
Eco Park, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol.1 Main Text
December 2015
Page | 162
transported off Site by
registered carrier.
Culvert beneath M5 Debris blocking culverts
resulting in upstream
flooding
Construction Low Minor to
Negligible
Minor
negative / not
significant
PPGs and ensuring no
large materials enter the
watercourse. If
blockages are detected,
remove blockage
immediately
Unblocking of
culvert
maintaining /
improving flow
Negligible / not
significant
N/A
Stadium Location New impermeable areas
increase surface water
runoff and flood risk
Construction Low Medium to
Negligible
Minor
negative / not
significant
PPGs and development
of surface water
drainage network
Enhancement
through formal
drainage network
Negligible / not
significant
N/A
Stadium Location Changing overland flow
paths
Construction Low N/A Minor positive
/ not
significant
Incorporation of a
formal drainage
network.
Enhancement
through formal
drainage network
Minor / not
significant
Positive
Eco Park, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol.1 Main Text
December 2015
Page | 163
Table 9.9: Summary of Flood Risk, Hydrology and Drainage Operation Effects and Mitigation
Receptor Effect Development
Phase
Sensitivity
/
importance
of receptor
Magnitude
Change
Level of Effect
(and
Significance)
prior to
mitigation
Mitigation Enhancement Level of Effect
(and
Significance)
after
mitigation
Nature
of
effect
The Selbrook Spillages of fuels, oils, and
other chemicals from
stationary vehicles
Operation Medium N/A Negligible
negative / not
significant
SuDS drainage network
design
Surface water
drainage through
treatment train
Negligible / not
significant
N/A
River Frome Spillages of fuels, oils, and
other chemicals from
stationary vehicles
Operation Medium
N/A Negligible
negative / not
significant
SuDS drainage network
design
Surface water
drainage through
treatment train
Negligible
negative / not
significant
N/A
Groundwater Spillages of fuels, oils, and
other chemicals from
stationary vehicles
Operation Low
N/A Negligible
negative / not
significant
SuDS drainage network
design
Surface water
drainage through
treatment train
Negligible
negative / not
significant
N/A
The Selbrook Diffuse highways pollution
from moving vehicles
Operation Medium
Minor to
Negligible
Minor negative /
not significant
SuDS drainage network
design
Surface water
drainage through
treatment train
Negligible
negative / not
significant
N/A
River Frome Diffuse highways pollution
from moving vehicles
Operation Medium
Minor to
Negligible
Minor negative /
not significant
SuDS drainage network
design
Surface water
drainage through
treatment train
Negligible
negative / not
significant
N/A
Groundwater Diffuse highways pollution
from moving vehicles
Operation Low N/A Negligible
negative / not
significant
SuDS drainage network
design
Surface water
drainage through
treatment train
Negligible
negative / not
significant
N/A
Stadium Location Flood risk from surface
water runoff
Operation High Medium to
Negligible
Negligible
positive / not
significant
SuDS drainage network
design
Surface water
drainage through
treatment train
Negligible
negative / not
significant
N/A
Stadium Location Climate Change Operation High N/A Negligible
negative / not
significant
SuDS drainage network
design
N/A Negligible
negative / not
significant
N/A
Stadium Location Biodiversity enhancements Operation Medium N/A Minor positive /
not significant
SuDS drainage network
design
Moderate
positive /
significant
Positive
Eco Park, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol.1 Main Text
December 2015
Page | 164
10 LANDSCAPE AND VISUAL
Summary
10.1 The Eco Park Revised Scheme (RS) will be designed and constructed to the highest architectural
and sustainability standards. The overall design of the Revised Scheme has been informed by an
integrated landscape strategy which seeks to create an attractive ‘parkland’ setting for Zaha
Hadid Associates’ (ZHA) landmark stadium, one which will both enhance the landscape and visual
amenity of the Site itself and preserve the character of the surrounding area. The Site layout,
stadium design and choice of materials have been informed by the character of the locality as
reflected in the landscape strategy which includes generous setbacks and landscape buffers
adjacent to neighbouring settlements and properties. Of particular importance is the use of
natural materials (timber) in the stadium building, with non-reflective, recessive and muted
colours and textures, resulting in a striking landmark structure. This exciting new landscape
feature, whilst sensitively responding to its rural surroundings in both form and appearance, will
create a memorable sense of arrival at this ‘gateway’ to Stroud location, enlivening the western
approach to the town.
10.2 Mitigation and enhancement measures are proposed to avoid or minimise potential adverse
landscape and visual effects on local residents and visitors to the Site and surrounding area.
These measures are embedded in the Eco Park Revised Scheme as illustrated in RS Figure 1.1
Indicative Concept Plan and outlined in the RS Figure 5.3 Indicative Green Infrastructure
Parameter Plan both contained in Volume 2.
Landscape effects
10.3 The proposal will have a significant adverse effect on the landscape fabric of the Site and will
significantly change the character of both the Site itself and the immediate surrounding area of
Stroud District up to a distance of approximately 250m from the Development Footprint where
uninterrupted visibility of the proposal exists. These changes to the local landscape, although
transformative and significant in the EIA context, will involve an innovative and sensitively
designed landmark building, together with sports pitches and informal open space, set within a
framework of existing hedgerows, mature trees / woodland and appropriate new planting,
including orchard trees. The remainder of Stroud District’s landscape will not be affected to any
significant degree character wise. No significant landscape effects are predicted to arise beyond
250m, including on the character and special qualities of the Cotswolds AONB and its prominent
escarpment, or Registered Parks and Gardens in the vicinity.
Visual effects
10.4 Significant residual visual effects are predicted for users of Eastington Footpath Nos 37 and 38
crossing the Development Footprint and short stretches of public highway adjacent to the Site
including the M5 motorway, the A419 and Grove Lane. The visual amenity of three dwellings
adjacent to the Site, namely Mole Cottage, Ivy Cottage and Westend House is likely to experience
significant adverse change in the short term due to relatively unrestricted visibility of the Revised
Scheme (or part of) at close range. However, these initially significant visual effects will reduce
as the embedded mitigation establishes and matures over time to become not significant
adverse residual effects in the longer term.
Eco Park, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol.1 Main Text
December 2015
Page | 165
10.5 Other visual receptors, including residential properties / settlements at Westend, Nupend and
Chipmans Platt (including West of Stonehouse), Eastington and Claypits, and recreational
resources and publicly accessible routes and land in the vicinity, will not experience significant
visual effects. No significant adverse visual effects are predicted to arise on the Cotswold Way
or the Thames and Severn Way, or any publicly accessible land such as commons, National Trust
property, access land, country park and village green.
Cumulative effects
10.6 Implementation of the Revised Scheme will have a significant adverse cumulative landscape and
visual effect in combination with the proposed Land West of Stonehouse and Pike Lock in the
vicinity of Westend and Chipmans Platt up to a distance of approximately 500m from the
Development Footprint. The significant cumulative effect will be residual in the case of
landscape character, but not in respect of visual effects. Apart from that no other significant
cumulative effects attributable to the Revised Scheme are predicted in conjunction with the
assessed cumulative schemes.
Conclusion
10.7 The Revised Scheme will significantly alter the landscape character and visual amenity of the
Development Footprint and its immediate surroundings up to approximately 250 metres from
the Development Footprint (up to approximately 500m in the cumulative context). The change
will be adverse during construction, but effects will reduce as the embedded landscape
mitigation matures and provides landscape and visual benefit. Some people are likely to perceive
the localised change as negative (as assumed in this LVIA), whilst others will see it as neutral or
positive. This difference in landscape perception will be due to the potential for the stadium,
should it be consented, to become a much admired, landmark feature and a symbol of Stroud’s
forward thinking, ‘green’ credentials63.
Introduction
The Assessment
10.8 This Chapter contains a Landscape and Visual Impact Assessment (LVIA) of the Eco Park Amended
Application (the Revised Scheme) located adjacent to the M5 Junction 13 (the Site), which is the
subject of an outline planning application to Stroud District Council (SDC) with all matters
reserved except access. The LVIA assesses the potential impact of the Revised Scheme on the
landscape and visual environment and comprises a suite of descriptive text, methodology and
assessment tables / schedules (all provided in Volume 3 – RS Appendices 10.1 – 10.10) and
graphic information (all provided in Volume 2 – RS Figures 10.1 – 10.15) which are intended to
be read in conjunction with this chapter. Other information of particular importance to the LVIA
includes the Indicative Concept Plan (RS Figure 1.1), the Building Height Parameter Plan (RS
Figure 5.1), the Land Use Parameter Plan (RS Figure 5.2) and the Indicative Green Infrastructure
Parameter Plan (RS Figure 5.3). Cumulative schemes considered in the LVIA are listed in Chapter
2, Table 2.5 and shown on RS Figure 18.1 Cumulative Schemes.
63 The European Landscape Convention defines landscape as: “an area, as perceived by people, whose character is
the result of the action and interaction of natural and/or human factors.” (para. 2.2)
Eco Park, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol.1 Main Text
December 2015
Page | 166
Scope
10.9 This LVIA considers the potential for significant effects (negative and / or positive) to arise on the
landscape and visual resource of the Site and surrounding area within a 10km radius of the
Redline Boundary – the Study Area (refer RS Figure 10.1 Site Location, Study Area and Viewpoint
Location (Study Area)). Having due regard to emphasis on proportionality of assessment urged
in best practice guidance contained in the Landscape Institute’s ‘Guidelines for Landscape and
Visual Impact Assessment – Third Edition’ (2015) (GLVIA3), and taking account of the type and
scale of the Revised Scheme and the landscape context, a 10km study area is considered
appropriate and sufficient to identify likely significant landscape and visual effects arising. The
assessment scope has been refined and agreed through extensive consultations dating back to
2015.
Authorship
10.10 The principle LVIA author was Gavin David with supporting contributions from Fiona Sharman
and Kara Davies. Kara has a PhD in Strategic Environmental Assessment and MSc in
Environmental Impact Assessment with over eight years’ experience lecturing in these subjects.
She has been working in a landscape role at Ecotricity for the past three years on a range of
renewable energy and built development projects and is an Affiliate Member of the Landscape
Institute (AMLI). Fiona is a freelance Chartered Landscape Architect and Member of the
Landscape Institute (CMLI) until recently formerly in the employ of Ecotricity; she was previously
a Landscape Planner at Bristol City Council where she gained considerable experience in the
assessment of planning applications for a range of development projects. Gavin is also a
freelance Chartered Landscape Architect and CMLI with over twenty years’ experience, including
as expert witness at planning inquiries and appeals. In addition to serving with Ecotricity for the
past eight years as Lead Landscape Architect and team manager (up to January 2017), he was
formerly technical director at WSP Parsons Brinckerhoff (London), and previously employed by
RPS Planning and Development (Oxford) and Land Use Consultants (London and Bristol), involved
in a wide range of urban design, landscape architecture and environmental planning work on a
day to day basis.
The Site
10.11 The Revised Scheme is proposed on agricultural land situated adjacent to the A419 and M5
motorway Junction 13 (the Site) near Stonehouse in Gloucestershire, as delineated by the
Redline Boundary on RS Figure 10.1 described in this ES as ‘the Site’. The Site comprises three
separate parcels of land the majority of which lies to the east of the M5 J13. The built
development proposed will take place on the land parcel lying immediately north of the A419
and east of the M5, described in this ES as the ‘Development Footprint’ (also termed the ‘Revised
Scheme’); the remaining parcels located south of the A419 either side of the M5 adjacent to the
River Frome will remain as they are. Save certain mitigation and enhancement works proposed
in Chapter 8 Ecology and Nature Conservation (in relation to the required highways works) no
development is proposed in these areas in this application. More details of the Site and its
landscape are provided in the Baseline Conditions section below, and a general description of
the Site is contained in Chapter 3.
Terminology
Eco Park, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol.1 Main Text
December 2015
Page | 167
10.12 The following terms are used in this chapter (and across the ES as a whole) in relation to the
Revised Scheme (see also Chapter 1):
• The "Site" = land at M5 Junction 13 West of Stonehouse (see RS Figure 1.1 Indicative
Concept Plan).
• The "Redline Boundary" = the redline boundary of the Site as shown on RS Figure 1.1 and
RS Figures 10.1 – 10.15.
• The "Study Area" = area surrounding the Site within which landscape and visual effects are
assessed (see RS Figure 10.1 Site Location, Study Area and Viewpoint Location).
• The "Development Footprint" = the area of the Site subject to works (north of A419 and
east of M5 motorway) in this Revised Scheme (see RS Figure 5.2 Land Use Parameter
Plan).
The Revised Scheme
10.13 The Eco Park RS proposal is as described in Chapter 5 Description of the Revised Scheme and
shown on RS Figure 1.1. For the purposes of the LVIA the main components of the Revised
Scheme are summarised as follows:
• a 5,000 capacity football stadium and other ancillary uses (Use Class D2);
• two full-sized grass pitches and a goal practice area;
• a car parking area for 1,700 vehicles with signalised access and dualling of A419 from the
M5 to Chipmans Platt roundabout;
• a signal controlled pedestrian / cycle crossing at the A419 access point and a combined
bus route and footway / cycleway linking with Grove Lane (National Cycle Route 45) via
the Development Footprint;
• soft and hard landscape works relating to the stadium and the car parking area (hard core
surface) including formal and informal open space provision incorporating a landscape
‘buffer’ with planted bund adjacent to Westend;
• stadium lighting elements integrated into roof structure with controlled illumination
direction and levels to fulfil different requirements.
Legislation, Policy and Guidance
Legislative Context
European Landscape Convention
10.14 The European Landscape Convention was signed and ratified by the UK government in 2006, and
became binding in the UK in 2007. The Convention seeks to promote landscape protection,
management and planning across Europe, and to organise European-wide co-operation on
landscape issues. It states that:
”Landscape’ means an area, as perceived by people, whose character is the result of the action
and interaction of natural and / or human factors”
Planning Policy Context
10.15 The Site is located in Gloucestershire in the jurisdiction of SDC.
Eco Park, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol.1 Main Text
December 2015
Page | 168
10.16 A review of relevant national and local planning policy and guidance relating to landscape and
visual resources is provided at RS Appendix 10.9 (a-d). Planning policy generally is dealt with in
Chapter 6 and RS Appendix 6.1.
10.17 A summary of relevant landscape related policy and guidance is presented below.
Planning Policy and Guidance
National Planning Policy Framework (NPPF)
10.18 The NPPF published on the 27thof March 2012. Aspects of the NPPF with particular relevance to
landscape include Section 7 (Requiring Good Quality Design) and Section 11 (Conserving and
Enhancing the Natural Environment) which support the core planning principles set out in
Paragraph 17. NPPF paragraphs considered particularly relevant to the Revised Scheme are listed
in Table 10.9.2 of RS Appendix 10.9b. Also of importance is the Planning Practice Guidance
(PPG)64 in particular with respect to LVIA the Natural Environment: Landscape section.
10.19 The ethos of the Revised Scheme aims to support key themes of the NPPF and PPG, particularly
in relation to planning positively for good quality design and respecting local character, identity
and sense of place (refer NPPF Paragraphs 60-63).
Local Planning Policy
10.20 Chapter 6 / RS Appendix 6.1 Planning Policy Context provides a detailed description of all
relevant policies contained in the Stroud District Local Plan (2015) adopted on the 19th November
2015. Strategic and overarching policies are also covered in more detail in Chapter 6. The 2015
Plan replaces the 2005 Local Plan entirely and provides a planning policy framework for Stroud
District up to 2031.
10.21 RS Appendix 10.9b, Table 10.9.1 provides an overview of policies with particular relevance to
landscape and visual resources, acknowledging that there will also be an interrelationship with
policies than span across a number of other disciplines (e.g. ecology, cultural heritage). Relevant
(adopted) planning guidance is also referred to in Table 10.9.1 of RS Appendix 10.9b. Local
policies with particular relevance to landscape and cultural heritage can be summarised as:
Stroud District Local Plan (Adopted November 2015)65
• Strategic objective SO6 (Our District’s distinctive qualities, based on landscape, townscape
and biodiversity);
• Strategic policies: CP4 (Place Making), CP14 (High Quality Sustainable Development);
• Delivery Policies: ES7 (Landscape Character), ES8 (Trees, hedgerows and woodland). EI11
(Promoting sport, leisure and recreation), ES12 (Better Design of Places), ES3 (Maintaining
Quality of Life within our Environmental Limits);
• Cross cutting policies with other topics: E6 (Biodiversity and Geodiversity), ES10 (Valuing
our Historic Environment and Assets).
64 Planning Practice Guidance available from http://planningguidance.communities.gov.uk/ accessed on 16th
December 2015. 65 Stroud District Local Plan available from
http://www.stroud.gov.uk/docs/planning/planning_strategy.asp#s=sectioncontent2&p=lp accessed on 16th
December 2015.
Eco Park, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol.1 Main Text
December 2015
Page | 169
Eastington Parish Council Neighbourhood Development Plan (Adopted October 2016)66
• Policy EP2: Protect and enhance biodiversity and the natural environment;
• Policy EP4: Siting and design of new development and conservation;
• Policy EP9: Public rights of way and wildlife corridors.
10.22 It is important to note here regarding Eastington NDP Policy EP9 that the Revised Scheme makes
provision for improvements to both wildlife corridors and public rights of way which are
described in this LVIA below in the Landscape Fabric section.
Industrial Heritage Conservation Area Supplementary Planning Document (Adopted Nov 2008)67
• Five Overarching Policy and Design Priorities (1-5);
• Management Proposals: IHCA-MP 5: Policy and design priorities, IHCA-MP 6: Policy and
design guidance;
• Policy and Design Guidance: IHCA-G 1 (Building in Context). Relevant Landscape Policy and
Design Guidance (PDG1 – PDG42) are also referenced where appropriate.
Sustainable Construction Supplementary Planning Document (Adopted February 2017)
10.23 The Design and Access Statement and Chapter 5 describes how the proposal has been designed
to promote a high standard of sustainable construction and design. The LVIA has had regard to
this SPD in respect to the approach to the design and hard and soft landscape works as outlined
in RS Figure 5.3 and RS Figure 10.11c Landscape Strategy and 10.11d Landscape Mitigation and
RS Appendix 10.7 Landscape Strategy.
Stroud District Landscape Sensitivity Assessment (December 2016)68 – Part of Strategic
Assessment of Land Availability (SALA)
• The Council has produced, and published on its website, a range of environmental
evidence to support the preparation of the Local Plan69. This information will be a material
planning matter for the determination of planning applications;
• As part of this, SDC appointed White Consultants to undertake a Landscape Sensitivity
Assessment of land parcels in Stroud District. This study forms part of the Council’s
Strategic Assessment of Land Availability (SALA) process, which in turn will inform
subsequent reviews of the local plan. A full report of findings on the SALA process
(covering multiple topics) was published by SDC in May 201770 ;
• Information relating to the December 2016 Landscape Sensitivity Assessment, which was
utilised in the SALA process, is summarised in Landscape Resource section below with
66 Eastington Neighbourhood Development Plan available from http://eastington-pc.gov.uk/neighbourhood-
development-plan/ accessed on 24/10/2017. 67 Industrial Heritage Conservation Areas Supplementary Planning Document available from
https://www.stroud.gov.uk/environment/planning-and-building-control/conservation-listed-buildings-trees-and-
hedgerows/conservation-areas/conservation-area-no29-stroud-industrial-heritage/the-ihca-conservation-area-
management-proposals-spd accessed on 24/10/2017. 68 Stroud District Landscape Sensitivity Assessment (December 2016) available from
https://www.stroud.gov.uk/environment/planning-and-building-control/planning-strategy/evidence-
base/environmental-evidence/landscape-sensitivity-assessment-2016 accessed on 24/10/2017. 69 Stroud District Environmental Evidence available from https://www.stroud.gov.uk/environment/planning-and-
building-control/planning-strategy/evidence-base/environmental-evidence accessed on 24/10/2017 70 Stroud District Strategic Assessment of Land Availability (SALA, May 2017). Available from
https://www.stroud.gov.uk/media/355585/final-report-of-findings.pdf accessed on 24/10/2017.
Eco Park, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol.1 Main Text
December 2015
Page | 170
further details provided in RS Figure 10.8a SALA Assessment of Onsite Landscape
Sensitivity with Project Components (SDC), RS Appendix 10.2 and RS Appendix 10.9c and
10.9d (full extract).
Cotswold Area of Outstanding Natural Beauty Management Plan (2013-18)71
• Landscape Policies LP1 & LP2.
Cotswold Area of Outstanding Natural Beauty Position Statements72
• Cotswold Conservation Board Position Statements, in particular ‘Development in the
Setting of the Cotswolds AONB’ (as amended in June 2016) and Tranquility and Dark Skies
(with Appendices) (2010).
Assessment Methodology and Significance Criteria
Introduction
10.24 As described in the main Introduction section above this LVIA has been undertaken by qualified
landscape architects with the relevant expertise and experience of similar types of development,
and carried out in line with current best practice guidelines, according to the stated methodology
summarised below and set out in more detail at RS Appendix 10.1 LVIA Methodology.
10.25 The Site (defined by the Redline Boundary) and the Revised Scheme are described, and an outline
description of the local landscape and visual amenity provided drawing on desk study / published
documents and fieldwork. The terms Revised Scheme and Development Footprint both refer to
the area of built development within the Site as distinct from the other areas within the Redline
Boundary left undeveloped (i.e. land to the south of the A419, and land west of the M5
Motorway).
10.26 Potential landscape, visual and cumulative effects arising from the Revised Scheme are identified
and the significance of the residual effects on the landscape fabric, landscape character, views
and visual amenity assessed. The likely effects are identified and described for three stages of
development: A) during construction; B) at commencement of operation (Year 1); and C) upon
establishment / maturing of proposed landscape mitigation (Year 15).
10.27 A range of mitigation and enhancement measures are considered and the potential benefits
factored into the statement of residual effects.
Basis of Assessment
10.28 The LVIA is based on the Revised Scheme Parameter Plans (RS Figures 5.1-5.5) which comprise
the following information submitted as part of the planning application:
• Building Height Parameter Plan (RS Figure 5.1);
• Land Use Parameter Plan (RS Figure 5.2);
71 Cotswold Area of Outstanding Natural Beauty Management Plan available from
http://www.cotswoldsaonb.org.uk/management_plan/index.html accessed on 24/10/2017. 72 Cotswold Area of Outstanding Natural Beauty Position Statements
http://www.cotswoldsaonb.org.uk/conservation-board/position/ accessed on 24/10/2017.
Eco Park, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol.1 Main Text
December 2015
Page | 171
• Indicative Green Infrastructure Parameter Plan (RS Figure 5.3);
• Indicative Construction Compound Locations (RS Figure 5.4);
• Site Plan and Sections (RS Figure 5.5);
• Cross Section at Grove Lane (RS Figure 5.6).
10.29 The LVIA is also informed, inter alia, by the:
• Indicative Concept Plan (RS Figure 1.1)
• Design and Access Statement (seperate document submitted as part of the Revised
Scheme).
Consultations
10.30 The following pre-application consultations relating to the Revised Scheme were carried in order
to agree the scope and approach of the LVIA.
Table 10.1: Pre-Application Consultations
Consultee Date Note Summary Comment
Stroud
District
Council
(David
Lowin)
23/10/17 Pre-application consultation letter
setting out the approach, method
and scope of the LVIA together
with plans showing the site
location, study area, preliminary
ZTV and viewpoint locations.
No formal consultation response
received to date, but relevant
comments and advice received at
the meeting with SDC / David Lowin
on 2nd November 2017 have been
incorporated into this LVIA.
Natural
England
23/10/17 Copy of the above pre-application
consultation letter forwarded to
statutory consultee.
No consultation response or
comments received to date.
Cotswolds
AONB
23/10/17 Copy of the above pre-application
consultation letter forwarded to
statutory consultee.
No consultation response or
comments received to date.
Assessment Assumptions and Limitations
10.31 The landscape and visual environment is understood to be a public resource. In this LVIA private
interests such as views from private property (residential visual amenity) are considered only in
so far as they relate to the public interest73.
10.32 LVIA concerns the landscape and visual environment considered as a public resource as
experienced and / or perceived by the dispassionate observer. This position is reflected in the
European Landscape Convention definition of landscape. It should be kept in mind that some
people will perceive changes to the landscape and visual resource as negative, and others
positive or neutral (neither positive nor negative). This is likely to be case with the Revised
73 The ‘public interest test’ (the Lavender test) holds that when developments “… represent an unpleasantly
overwhelming and unavoidable presence in main views from a house or garden, there is every likelihood that the
property concerned would come to be widely regarded as an unattractive and thus unsatisfactory (but not necessarily
uninhabitable) place in which to live. It is not in the public interest to create such living conditions where they did not
exist before.”
Eco Park, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol.1 Main Text
December 2015
Page | 172
Scheme due to the innovative nature and high standard of the stadium’s architecture combined
with its ‘parkland’ setting. Notwithstanding this predicted landscape and visual effects arising
from the Revised Scheme are assumed to be negative unless stated otherwise in order to
assess worst case scenario in line with EIA good practice.
10.33 A significant landscape and visual effect is one which is ‘significant’ in the context of the relevant
EIA Regulations. However, EIA significance does not mean the effect is unacceptable in planning
terms, but rather that the assessor considers it likely to be material to the determination of the
planning application. As such certain parts of the proposal will come into operation whilst
construction is proceeding on others. Thus, although assessed separately, construction and
operational effects will in fact be a continuum of landscape change starting with site clearance
and proceeding through site works (construction phase) to completion of the Revised Scheme
and the landscape mitigation works (operation phase Year 1), culminating in the establishment
and maturing of the ‘parkland’ landscape (operation phase Year 15); the residual effects in other
words.
10.34 The LVIA assesses the Revised Scheme as described by the Parameter Plans and relevant
supporting information including the Indicative Concept Plan.
10.35 In line with the NPPF and the PPG the proposed built development will be of the highest
architectural quality and of the highest standards in sustainable design that responds sensitively
to the local landscape context. Further details on this are provided in the separate Design and
Access Statement and RS Appendix 10.7. Furthermore, it is assumed that built form so designed
will be perceived by dispassionate observers as logical and appropriate development at this
particular location.
10.36 The LVIA was carried out in the summer and autumn of 2017 (drawing on work undertaken in
2015 and 2016) and reviewed and finalised in November and December 2017. The assessment
of likely significant effects is that predicted to arise during the winter months when deciduous
vegetation is devoid of foliage – the ‘worst case scenario’. Photographs of the baseline situation
in summer and winter are provided at RS Figure 10.13 Baseline Photographs (including Night-
time) for each of the agreed representative viewpoints. Variations in magnitude of likely effect
in summer compared with winter are described in the assessment narrative as appropriate. The
LVIA has regard to scheme variations due to design evolution and proposed mitigation and
enhancement measures, embedded or otherwise (e.g. landscape works), within the range of
defined parameters, so as to assess the likely maximum effect or worst case scenario.
10.37 It is assumed that the proposed tree planting on top of the 2m tall earth bund would reach a
height of approximately 5m by Year 15, as shown on RS Figure 5.6 Cross Section at Grove Lane.
This assumption takes into account variations in growth rates dependent on growing conditions
and choice of species, details of which will be provided at the Reserved Matters Stage.
10.38 The LVIA has regard to the night time environment baseline and the effect of the Revised Scheme
lighting on it. The lighting design described in Chapter 14 will provide required illumination for
sporting events whilst minimising light obtrusion through the careful positioning and aiming of
lighting elements as well as integrating lighting elements into the architectural roof structure.
The sports lighting control system will allow switching for different illumination levels to fulfil
different requirements such as maintenance, training and league matches with all controls
accessible via a graphical user interface. The proposed training pitches will be unlit.
Eco Park, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol.1 Main Text
December 2015
Page | 173
10.39 Further details on the Assumptions and Limitations of the LVIA are provided in RS Appendix 10.1.
Method Statement
10.40 The approach used in carrying out this LVIA is summarised below. More information on the LVIA
methodology is provided in RS Appendix 10.1.
Best Practice Guidance
10.41 The assessment was undertaken in accordance with current best practice outlined in published
guidance, in particular:
• Guidelines for Landscape and Visual Effect Assessment (GLVIA), 3rd Edition (2013)
Landscape Institute and the Institute for Environmental Management and Assessment
(referred to below as GLVIA3);
• An Approach to Landscape Character Assessment, Natural England (2014);
• Landscape Institute Advice Note 01/11 photography and photomontage.
10.42 Other documents consulted when undertaking the LVIA include, inter alia, best practice
guidelines contained in the following adopted supplementary planning guidance / advice and
publicly available, landscape related publications:
• Stroud District Landscape Assessment (2000);
• The Cotswolds AONB Landscape Assessment (2004);
• Cotswold Area of Outstanding Natural Beauty Management Plan (2013-18);
• The Industrial Heritage Conservation Areas Statement (2008);
• The Industrial Heritage Conservation Area Design Guide (2008): Scope of Assessment.
Identification and Description of Landscape and Visual Effects
10.43 The landscape and visual effects potentially occurring during the construction and operational
phases of the development are described under the following headings:
• Physical effects on the landscape fabric e.g. vegetation removal and / or new planting;
• Effect on the character of the landscape;
• Effect on designated (valued) landscapes;
• Effect on views and visual amenity having regard to sensitive receptors e.g. people at/
using public rights of way and residential properties.
Study Area
10.44 The Study Area is defined by a 10km radius from the Revised Scheme Redline Boundary – see RS
Figure 10.1. The LVIA considers the potential effect on landscape character and visual amenity
across the 10km study area. However, having due regard to GLVIA3’s emphasis on
proportionality, as explained below, the focus of the assessment of visual amenity and character
effects is a 5km radius from the Redline Boundary. The reason for this is that, taking account of
the type and scale of the Revised Scheme and the landscape context, significant adverse effects
on landscape character and views / visual amenity are considered highly unlikely in excess of 5km
Eco Park, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol.1 Main Text
December 2015
Page | 174
from the Site. The Study Extent was previously agreed with consultees in relation to the original
submission74.
Assessment Approach
10.45 The approach to the LVIA involved:
• Recording and analysis of the existing landscape elements (physical features) landscape
character and visual amenity associated with the Site and surrounding area through desk
based study and field appraisal;
• Appreciation of the nature, form and scale of the Revised Scheme having regard to the
landscape and visual context;
• Evaluation of the ‘sensitivity’ of the existing landscape and visual receptors likely to be
affected by the Revised Scheme. Sensitivity is a product of the ‘value’ of the receptor and
its ‘susceptibility’ to the type of development proposed. More detail on the evaluation of
landscape and visual sensitivity is provided in RS Appendix 10.1.
• An assessment of the ‘level’ of effect likely to result from implementation of the Revised
Scheme, having regard to the landscape and visual context and potential cumulative
effects. The level of effect is derived from combining an assessment of the magnitude of
effect (from the baseline situation) and the sensitivity of the receptor. More details on the
assessment approach are provided in RS Appendix 10.1.
• Assessment of whether the predicted effects will be ‘significant’ or ‘not significant’ in the
context of the relevant EIA Regulations75;
• Identification of mitigation and enhancement measures appropriate to the Revised
Scheme and its effects and to the receiving landscape;
• Assessment of the residual effects on the landscape and visual environment including
cumulative;
• Provision of appropriate supporting graphics including baseline photographs for
assessment purposes;
• Consideration of other cumulative schemes in the Study Area, the approach for which is
outlined in the subsequent sections. In this instance the cumulative schemes considered
as part of this application were informed by advice provided by the Council in a meeting
on 03/08/2015 and its Scoping Response (RS Appendix 1.2)) along with the approach set
out in Chapter 2 (Approach to EIA) and Chapter 18 (Cumulative Effects).
10.46 More detail on the assessment approach is provided in RS Appendix 10.1.
10.47 The baseline assessment includes collation of relevant published information relating to
landscape character and designations (national and local). Preliminary Zone of Theoretical
Visibility (ZTV) plans were prepared based on the parameter dimensions of the Revised Scheme
to assist in the identification of viewpoints and sensitive receptors. Key features, components,
characteristics and views contributing to the character and quality of the landscape and visual
amenity it provides were identified and evaluated.
74 Previously agreed with Natural England, the Cotswolds AONB Conservation Board and SDC during pre-application
and post-application consultations relating to the original submission. 75 The Town and Country Planning (Environmental Impact Assessment) Regulations 2011
Eco Park, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol.1 Main Text
December 2015
Page | 175
10.48 The potential effects of the Revised Scheme on the existing landscape and views / visual amenity
were assessed having regard to the potential harm or benefit to the receiving environment and
sensitive receptors. The process relies on a combination of quantitative and qualitative
assessment using professional judgement including as to whether landscape and/ or visual
effects are ‘significant’ or not in the context of the EIA Regulations.
10.49 The LVIA process and identification of likely significant adverse effects formed part of an iterative
process which has informed the design and layout of the Revised Scheme. As part of this process
mitigation measures have been identified which are incorporated into the design as ‘embedded
mitigation’.
10.50 The assessment concludes with a statement that identifies the significant, adverse residual
landscape and visual effects that are likely to result from the Revised Scheme and will potentially
remain, post mitigation.
Identifying Significant Effects
10.51 The purpose of EIA is to identify significant environmental effects (negative and / or positive)
likely to arise from the Revised Scheme. GLVIA states that:
“The EIA Directive and UK Regulations refer to projects likely to have significant effects on the
environment. This means that identifying and describing the effects of a project is not enough in
itself. They must also be assessed for their significance. This is a key part of the LVIA process and
is an evidence-based process combined with professional judgement (Para 3.23) ... LVIA, in
common with other topics in EIA tends to rely on linking judgements about the sensitivity of the
receptor and about the magnitude of the effects to arrive at the conclusions about the
significance of the effects ... (GLVIA3, para 3.24, p37).”76
10.52 GLVIA3 emphasises the importance of ‘proportionality’ in carrying out the assessment stating
that:
“Identifying significant effects stresses the need for an approach that is in proportion to the scale
of the project that is being assessed and the nature of its likely effects. Judgement needs to be
exercised at all stages in terms of the scale of investigation that is appropriate and proportional.”
(GLVIA3, para 1.17, page 9)
10.53 The principle of proportionality has guided the content of the LVIA, the scope of which is the
result of various consultations with the Council, Natural England and the Cotswolds AONB.
10.54 The likely landscape and visual effects resulting from the Revised Scheme are assessed in
accordance with the approach set out in GLVIA3. This establishes the magnitude of landscape
and/ or visual change, weighing it against the sensitivity of the landscape and/ or visual receptor,
to arrive at the level of landscape and/ or visual effect and whether that level of change is
significant within the meaning of the EIA Regulations. The process uses a combination of
objective and subjective analysis and assessment informed by professional judgement.
Table 10.2: Level and Significance Matrix
Sensitivity of Receptor
M a g High Medium Low
76 Guidelines for Landscape and Visual Effect Assessment 3rd Edition (2013). Landscape Institute and IEMA
Eco Park, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol.1 Main Text
December 2015
Page | 176
High Major Major/Moderate Moderate/Major
Major/Moderate Moderate/Major Moderate
Medium Moderate/Major Moderate Moderate/Minor
Moderate Moderate/Minor Minor/Moderate
Low Moderate/Minor Minor/Moderate Minor
Minor/Moderate Minor Minor/Negligible
Negligible Minor Minor/Negligible Negligible
10.55 The above matrix provides a framework and guide for establishing the ‘level of effect’. The
shaded area indicates where the landscape or visual effect will normally be judged to as
‘significant’ within the spirit of the EIA Regulations.
Presentation of Findings
10.56 In accordance with the recommendations contained in GLVIA3 the assessment findings are
presented as narrative in the main body of the text supported by the tabular results in the
appendices and graphic information in the figures as set out in the introductory section above.
In accordance with good practice, only significant EIA effects are discussed in this chapter; non-
significant effects are mentioned, but it should be noted that the reasoning explaining why they
are not significant is contained in RS Appendix 10.8 Potential Non-Significant Landscape and
Visual Effects.
Graphic Presentation
10.57 The LVIA is supported by a set of annotated plans – RS Figures 10.1 to 10.15 (Volume 2), including
Baseline Photographs looking towards the Site from the surrounding area taken from 22
representative Viewpoints. The methodology for photography and graphics production is
described in RS Appendix 10.1.
Baseline Conditions
General Site Description and Context
10.58 This section contains an outline baseline assessment of the landscape and visual resource; a full
baseline assessment for a wide range of landscape and visual receptors is provided at RS
Appendix 10.2. Both these elements should be read in conjunction with RS Figures 10.1 to 10.15.
The likely effects of the Revised Scheme against the baseline situation are assessed below in the
following sections.
10.59 An evaluation of the sensitivity of landscape and visual receptors is also provided here having
regard to the type and scale of development proposed. The sensitivity of each individual receptor
is recorded in RS Appendix 10.3 Landscape Assessment Schedules and RS Appendix 10.4 Visual
Assessment Schedules.
Site Landscape
10.60 The Site (Redline Boundary) is a 39.5ha tract of farmland and adjacent public highway, located
adjacent to the M5 Motorway at Junction 13, divided into three separate parcels by the
motorway and the A419 main road heading east towards Stroud and the Cotswolds. The
Development Footprint parcel comprises 18.9ha to the east of the M5 / J13 and north of the
A419; the area to the south of the A419 and east the M5 / J13 measures 13.5ha, and the parcel
to the southwest of J13, west of the M5 is 4.6ha.
Eco Park, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol.1 Main Text
December 2015
Page | 177
10.61 The Site is relatively flat, lying at an elevation of around 20m AOD, sloping slightly to the south
towards the River Frome to 15m AOD. RS Figure 5.5 Site Plan and Sections is helpful in
understanding the onsite topography. The M5, the A419, Grove Lane and their associated
boundary vegetation and fencing delineate the various parts of the Site. A remnant track
(without public access) formerly linking Westend with Chipmans Platt marks the south-eastern
boundary of the Site north of the A419. The entire site is currently used for agricultural purposes
for the grazing of cattle and cutting of hay. Onsite there is currently a modern barn in the
southern land parcel used for hay storage and a small cluster of five disused barns in the northern
parcel (within the Development Footprint) which are a mix of concrete / corrugated structures
(larger barns) and red brick barns (smaller structures).
10.62 Regarding the immediate environs of the Site, there are several low ridges and hills within 2km,
principally at Whtiminster (30m AOD approx) to the west, Nupend (40m AOD approx) in the east
and Eastington / Claypits (30m AOD approx) to the south. These are partly wooded and contain
the Site visually, partially restricting views towards and from the wider surrounding lowland.
Beyond 2km to the east, the topography becomes more varied and contrasting. At approximately
3km from the Site the Cotswolds footslopes and escarpment rise steeply towards the High Wolds
of the prominent Cotswold upland with its deep incised valleys, one of which the nearby town of
Stroud is located in. The combination of local topography, vegetation cover and settlement
pattern underlies the restricted ZTV with Screening of the Revised Scheme as depicted on the
figures (for example RS Figure 10.4 Bareground and With Screening ZTV and Viewpoint Location
(Study Area) and RS Figure 10.7a Key Landscape and Visual Receptors with ZTV.
10.63 With respect to the wider context, the landscape of the Study Area is composed of the relatively
flat flood plain of the River Severn with occasional gentle undulations and isolated low hills and
ridges across the Severn Vale. There is an abrupt change in topography from the broadly level
Vale to the Cotswolds escarpment in the east (300+mAOD) and the Forest of Dean upland area
to the West (300+mAOD) as shown on RS Figure 10.3 Topography Plan and Cross-Section (Study
Area). The elevated landforms of the Cotswolds and Forest of Dean run broadly parallel to the
each other, separated by the meandering course of the River Severn.
10.64 The majority of the Site is improved and semi-improved grassland divided by hedgerows (see RS
Figure 8.14 Baseline Survey. Sixteen hedgerows occupy the north part of the Site (within the
Development Footprint) and there are 21 hedgerow lengths on the southern part of the Site.
Hedgerows on site contain a number of mature trees, particularly Crack Willows (Salix fragilis),
close to the River Frome, Mature Ash (Fraxinus excelsior), Sessile Oak (Quercus petraea),
Hawthorn (Crataegus monogyna) and Blackthorn (Prunus spinosa), along with some very old field
maples (Acer campestre). Whilst most of the boundary hedgerows are intact, a number of the
internal hedgerows have become gappy and defunct due to lack of maintenance and cattle
damage.
10.65 Tree diversity within hedgerow lengths on the land east of the M5 and north of the A419 (within
the Development Footprint) is between 1 and 6 and tree species present were Ash (Fraxinus
excelsior), Blackthorn (Prunus spinosa), Crack Willow (Salix fragilis), Elder (Sambucus nigra),
English Elm (Ulmus procera), Field maple (Acer campestre), Goat Willow (Salix caprea), Hawthorn
(Crataegus monogyna), Sessile Oak (Quercus petraea), Wild Cherry (Prunus avium), Dogwood
(Cornus sanguineum) and Spindle (Eunonymus europaeus).
Eco Park, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol.1 Main Text
December 2015
Page | 178
Tree diversity within hedgerow lengths on the land east of the M5 and south of the A419 is
between 2 and 7, with all of the species found on the north side of the Site except for Sessile
Oak, Dogwood and Spindle, and with the addition of Sycamore (Acer pseudoplatanus) and Wild
Pear (Pyrus communis). Full details of hedgerows and species present is provided in RS Appendix
8.1 Baseline Survey.
10.66 There are three very small blocks of woodland onsite; two on the north side of the A419 (within
the Development Footprint) and one on the southern side which contain mature Ash (Fraxinus
excelsior), Sessile Oak (Quercus petraea), Field Maple (Acer campestre) and Hawthorn (Crataegus
monogyna). There are occasional standard mature trees in many of the hedgerows throughout
the Site, and in the south area close to the River Frome a number of very large Crack Willow (Salix
fragilis), and Goat Willow (Salix caprea). Further details are provided in RS Figure 8.1
Arboricultural Survey and RS Appendix 8.3 Arboricultural Survey. For more information on
vegetation and wildlife generally refer to Chapter 8 Ecology.
10.67 There are two Public Rights of Way (PRoW) which cross the Site: Eastington Footpath No.37
(EEA37) and Eastington Footpath No. 38 (EEA 38). EEA37 runs north east across the Site / Redline
Boundary from its junction with Eastington Footpath No.41 (EEA41) near to Westfield Bridge and
then crosses the A419 at grade, splitting into two paths (EEA37 & EEA38) across the Development
Footprint. EEA37 continues north to Westend Farm and Grove Lane; EEA38 runs north east
towards Westend Cross and Nupend beyond Grove Lane (see RS Figure 10.7b Key Landscape
and Visual Receptors with ZTV (Detail). PRoW are also shown on RS Figure 10.2 Aerial
Photograph and Indicative Site Layout and PRoW.
Landscape and Visual Context
10.68 Beyond its immediate context of the A419 and the M5 motorway / Junction 13 the Site is
surrounded by agricultural land with some settlement and employment development around the
perimeter and in the immediate environs. Thus, the existing landscape context is a combination
of built development and major infrastructure and rural land use – a dynamic landscape with
rural and peri-urban qualities influenced by the hustle and bustle (both aural and visual) of a
lively, settled environment.
10.69 The hamlets of Nupend and Nastend are situated within 0.5km and 1km to the north east of the
Site respectively, both of which are experiencing change due to the urban expansion nearby at
Land West of Stonehouse (WOS). The villages of Eastington and Whitminster are located
between 0.7km and 1km to the south and northwest of the Site respectively. Eastington Trading
Estate lies approximately 100m to the south of the Redline Boundary and Stroudwater and
Stonehouse Business Parks are located about 1-1.5km to the east and southeast, marking the
edge of Stonehouse.
10.70 The two PRoW crossing the Site described above link into a network of footpaths and trails in the
surrounding area including the Thames & Severn Way which follows the course of the
Stroudwater Canal Tow Path and River Frome and located immediately to the south of the Site,
the latter flowing in a north westerly direction towards the River Severn. The intervening fields
and grassland immediately south of the Site contain a currently infilled part of the Stroudwater
Canal route, known locally as the ‘missing mile’. This part of the former canal route is considered
in the Cumulative Effects section of this chapter under the title of Indicative Canal Realignment
as shown in RS Figure 18.1 Cumulative Schemes.
Eco Park, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol.1 Main Text
December 2015
Page | 179
10.71 The Severn Estuary with its associated Severn Way long distance trail is located approximately
3.5km to the west of the Site near Frampton-on-Severn. The Cotswolds AONB and Cotswold Way
National Trail are situated about 2km and 3km respectively at their nearest point in the vicinity
of Stonehouse. The Cotswolds is a nationally important upland landscape which together with
the Forest of Dean to the west (outside the Study Area) frames the Severn Vale and affords broad
views across the Severn Vale as well as providing a backdrop to views from the lowland. RS
Figures 10.1, 10.2, 10.3 and 10.6 Landscape Designations and Public Access / Recreational
Resources with ZTV (Study Area) are helpful in understanding the Site’s landscape and visual
context.
Landscape Resource
10.72 For the purposes of this assessment the landscape resource is described and its sensitivity to the
Revised Scheme assessed according to the following broad categories:
• Landscape Fabric (within the Development Footprint);
• Landscape Character (within the Study Area);
• Valued / Designated Landscape (within the Study Area).
10.73 An outline description of the landscape resource has been provided above; more detail on the
baseline landscape is included at RS Appendix 10.2 and RS Appendix 10.9(a-d).
Landscape Fabric and its Sensitivity
10.74 The following landscape fabric receptor groups, described in more detail above, have been
identified and assessed:
• Landform / Topography;
• Vegetation and Boundary Features;
• Other Site Elements including PRoW.
10.75 The Site lies adjacent to the River Frome corridor, located within the Severn Vale, approximately
4km to the east of the River Severn. The Development Footprint is situated to the north of the
A419 and sits at an elevation of around 20-24m AOD; the southern part of the Site lies adjacent
to the River Frome floodplain at around 13m AOD. The Frome valley drains west / south west
towards the River Severn. Generally speaking, the Site landform / topography is relatively flat
and uniform and plays a minor role in terms of its contribution to local landscape character (see
RS Figure 10.3 Topography Plan and Cross-Section (Study Area) and RS Figure 10.5a Landscape
Character with ZTV (SDC and National) (Study Area)). The onsite topography is judged to be of
low landscape value and have a medium susceptibility to the type of change proposed giving it a
low to medium landscape sensitivity.
10.76 The vegetation on the Site (described in more detail above) is typical of the locality and varies in
its landscape value and susceptibility to change. Regarding the Development Footprint, on
balance and taking into account the proposed embedded mitigation and careful design of the
Revised Scheme, the mature native trees and boundary hedgerows are considered to be medium
landscape sensitivity, and the improved / semi-improved grassland low landscape sensitivity.
Eco Park, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol.1 Main Text
December 2015
Page | 180
10.77 Other elements on the Site comprise agricultural fencing and several agricultural buildings which
are judged to be low sensitivity. PRoW are considered to be of high value and high susceptibility
to change and therefore are assigned high landscape sensitivity.
10.78 See RS Appendix 10.1 Methodology for more information on the evaluation of landscape
sensitivity.
Landscape Character and Sensitivity
10.79 This section considers the character of the local landscape and considers its sensitivity to and
capacity for the Revised Scheme. The sensitivity of individual landscape units as classified in the
various Landscape Character Assessments is evaluated further in the Potential Effects section
below.
10.80 Landscape character is a description and identification of:
“The overall character of the landscape in the study area, including any distinctive Landscape
Character Types or areas that can be identified, and the particular combinations of elements and
aesthetic and perceptual aspects that make each distinctive, usually by identification as key
characteristics of the landscape.”77
10.81 The landscape character of the Study Area has been assessed at various levels (i.e. degrees of
detail) over the past two decades. The following Landscape Character Assessments are
considered relevant to this LVIA:
• Natural England Landscape Character Assessment 2014 – National Character Area (NCA)
profiles78;
• Stroud District Landscape Assessment 2000;
• The Cotswolds AONB Landscape Assessment 200479;
• Gloucestershire Landscape Character Assessment 2006.
10.82 The various levels of assessment and their geographic extent are shown graphically as follows:
• RS Figure 10.5a Landscape Character with ZTV (SDC and National) (Study Area)
• RS Figure 10.5b Landscape Character with ZTV (Gloucestershire and Cotswolds AONB)
(Study Area)
• RS Figure 10.5c Industrial Heritage Conservation Area (IHCA) Character Areas (Study
Area)
• RS Figure 10.5d Relationship between Landscape Character Types and Areas in Study
Area
10.83 In the interest of proportionality of assessment, as referred to above, the focus of the LVIA with
respect to character is the potential effect on the host landscape within 5km of the Site. The
reason for this is that, taking account of the type and scale of the Revised Scheme and the
landscape context, significant adverse effects on landscape character are considered highly
77GLVIA 3rd Edition, 2013 (page 74, para 4) 78https://www.gov.uk/government/publications/national-character-area-profiles-data-for-local-decision-
making/national-character-area-profiles#ncas-in-south-west-england 79http://www.cotswold.gov.uk/residents/planning-building/landscape/landscape-character/
Eco Park, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol.1 Main Text
December 2015
Page | 181
unlikely in excess of 5km from the Site. That said, erring on the side of caution, the character of
the AONB within 10km of the Site is included within the assessment due to the high sensitivity
of the nationally important designated landscape.
10.84 In terms of national landscape character classification the Site is located within the Severn and
Avon Vales National Character Area (NCA 106), to the west of The Cotswolds (NCA 107) (see RS
Figure 10.5a). Full descriptions of these areas are provided by Natural England in the character
area profiles on its website. The NCA are assessed further at RS Appendix 10.2 and RS Appendix
10.3 Landscape Assessment Schedules.
10.85 At the intermediate level (Gloucestershire Landscape Character Assessment 2006) the Site lies
within the Settled Unwooded Vale Landscape Character Type (LCT SV6) and Vale of Berkeley
landscape character area (LCA SV6A) (see RS Figure 10.5b). At the local level (SDLA) the Site is
located in Lowland Plain landscape character type (LCT5) (see RS Figure 10.5a)
10.86 An assessment of the likely effect on the relevant landscape character units (LCTs and LCAs)
described in these landscape character assessments is provided in RS Appendix 10.3. For the
relationship between the various different levels on LCTs and LCAs see RS Figure 10.5d.
Stroud District Landscape Assessment 2000
10.87 Stroud District Landscape Assessment (SDLA) provides a relatively fine grain and appropriate
level of assessment for the purposes of this LVIA. The Site is situated within SDC’s Rolling
Agricultural Plain LCT 5 and occupies parts of sub types Escarpment Foot slopes (5A), Lowland
Plain (5B) and Frome River Valley (5C). The wider Study Area is characterised by LCT 4 Escarpment
situated approximately 2.5km to the east, and LCT 7 Severn Vale Hillocks located approximately
5km to the northwest, transitioning into LCT 8 Severn Vale Grazing Marshland towards the River
Severn.
10.88 The Council’s SDLA describes the host landscape (LCT 5 Rolling Agricultural Plain) as having the
following key unifying characteristics:
• “Varied landscape of open flat plain to more undulating landform towards limestone
escarpment.
• Established old, rich, rural lowland, with some woodlands and mature hedgerow trees and
occasional fruit trees
• Land dissected by River Cam and Frome.
• Traversed from north to south by M5, railway, Gloucester-Sharpness Canal and the A38
• Semi-enclosed landscape with some distant views and more restrained views from Frome
Valley.
• Churches act as strong foci and landmarks.
• Dispersed pattern of isolated villages.
• Land use is a mix of arable and pasture.
• Strong field pattern medium to small in scale.”
10.89 Regarding the Development Footprint north of the A419, the north-eastern part adjacent to
Westend settlement occupies the Escarpment Foot slopes (5A), whilst the south-western section
adjacent to the A419 lies within the Lowland Plain (5B). It should be noted that no development
Eco Park, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol.1 Main Text
December 2015
Page | 182
is proposed in the River Frome Valley (5C). More detail on landscape character is provided in RS
Appendix 10.2.
Cotswold AONB Landscape Character Assessment 2004
10.90 A wider study area extent (to within 10km of the Site) for the assessment of the character of the
Cotswolds AONB is considered appropriate due to the high sensitivity of the designated
landscape. The following Cotswold AONB LCTs and LCAs are located within the bare ground ZTV
of the Revised Scheme in the Study Area:
• LCT 3 Rolling Hills and Valleys / LCA 3B Stinchcombe and North Nibley;
• LCT 1 Escarpment Outlier / LCA 1A Cam Longdown, Peaked Down and Downham Hill;
• LCT 2 Escarpment / LCA 2C Uley to Coopers Hill;
• LCT 7 High Wold / LCA 7A Nympsfield and Kingscote Plateau & Minchinhampton Common;
• LCT 18 Settled Unwooded Vale / LCA 18A Vale of Gloucester Fringe.
10.91 More information on the landscape character of the Site and the Study Area including the
Cotswolds AONB is provided at RS Appendix 10.2 and RS Appendix 10.9 and in RS Figure 10.5b.
Stroud District Landscape Sensitivity Appraisal (URS 2013)
10.92 The Council commissioned URS to conduct a high-level landscape sensitivity appraisal (LSA) of
Potential Locations (termed ‘PLs) for housing, mixed use and employment, considered as part of
the Local Development Plan process. The resulted was the ‘Landscape Sensitivity Appraisal’ (URS,
July 2013)80. A map of the relevant areas is provided on page 45 of the LSA.
10.93 The Site is located in the previously identified PL No.9 ‘Employment north of Eastington’ which
is assessed in the LSA as having ‘medium sensitivity’ and possessing the following characteristics:
• “Predominantly flat pastoral agricultural landscape dissected by the A419 to the east of
Junction 13 of the M5;
• Bound to the north by the Grove Lane, to the west by the M5 road corridor (and Junction
13) and by the River Frome to the south;
• Agricultural character is eroded by the presence of road corridors;
• Hedgerows in some locations appear degraded with landscape elements otherwise in
moderate condition;
• Generally, tree cover and vegetation along field boundaries act to provide visual
containment although degraded hedgerows act to increase intervisibility in some locations
where tree cover is sparse;
• Some distant views are available to the elevated Cotswolds uplands to the east from
elevated locations;
• Receptors primarily consist of users of the PRoWs, residents of adjacent farmsteads and
users of local roads/ M5;
• Tranquility heavily degraded by the influence of context of road infrastructure with traffic
noise associated with the A419 and M5 immediately to the west notable from most
locations;
80http://www.stroud.gov.uk/info/plan_strat/Landscape_Sensitivity_Appraisal.pdf
Eco Park, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol.1 Main Text
December 2015
Page | 183
• A small number of PRoW along the River Frome and surrounding the village suggest a
moderate amenity value.” (Landscape Sensitivity Appraisal, URS, July 2013. Page 2)
10.94 Fieldwork carried out as part of this LVIA confirms the above description is consistent with the
landscape characteristics of the site and its immediate surroundings.
10.95 An outline assessment of the sensitivity of the Stroud District local landscape character types /
areas to the Revised Scheme is provided as part of this LVIA at RS Appendix 10.2 as summarised
in the Assessment of Effects section below. The approach to the sensitivity assessment is based
on current best practice guidance which states that sensitivity should be determined by
combining judgements of landscape susceptibility to the type of change or development being
proposed and the value attached to the receiving landscape.
Stroud District Landscape Sensitivity Assessment (White Consultants 2016).
10.96 The 2016 Stroud District Landscape Sensitivity Assessment (LSA) issued in 2016 builds upon the
2013 URS appraisal, providing a more detailed assessment of local landscape sensitivity and
capacity for built development. Around 220 potential land parcels are considered in the 2016
LSA including the area relevant to the Site which falls within LSA Sensitivity Parcels ‘St04’ (to the
south of A419) and ‘St05’ (to the north of the A419). More details on 2016 LSA are provided in
RS Appendices 10.9c and 10.9d including extracts from this study as summarised below.
10.97 Sensitivity Parcel St05 – the Development Footprint area is located wholly within Sensitivity
Parcel St05, as shown RS Figure 10. 8a Landscape Sensitivity with Project Components (SDC),
which is assessed as exhibiting Medium / Low landscape sensitivity to employment uses defined
as follows:
“Landscape and/or visual characteristics of the land parcel are resilient to change and/or its
values are medium/low or low and it can accommodate the relevant type of development in
many situations without significant character change or adverse effects. Thresholds for
significant change are high.” (2016 LSA, Table 1, p6) [author emphasis]
10.98 It is important to note the SLA 2016 finding that, across the entirety of Stroud District, only
Sensitivity Parcel St05 (encompassing the Development Footprint) qualifies as a Medium / Low
landscape sensitivity to employment uses, with no potential sites qualifying in the low sensitivity
category. There are also very few potential sites qualifying in the medium sensitivity category,
with most potential employment sites exhibiting a high sensitivity to such uses.
10.99 Thus, from a landscape perspective, the Site is considered an appropriate location for built form
of a similar nature to employment development (B1, B2 and B8 Use Classes), with Sensitivity
Parcel St05 having the lowest sensitivity rating (medium-low) of any Sensitivity Parcel in Stroud
District. Relatively speaking, the Site therefore has notably fewer constraints in landscape and
visual terms for the type of development proposed, when assessed objectively, compared with
other locations in Stroud District. This reinforces the Site’s potential to accommodate the Revised
Scheme, subject to sympathetic design and a detailed assessment.
10.100 Notwithstanding the maximum height of 19.5m of the stadium proposal (see RS Figure 5.1
Building Height Parameter Plan, the variable height, sloped roof (12m at its lowest point)
combined with the gentle, sweeping lines of its organic form, will be broadly in accordance with
the building scales defined in the 2016 LSA for employment uses (see RS Appendix 10.2,
Paragraph 10.2.98).
Eco Park, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol.1 Main Text
December 2015
Page | 184
10.101 Regarding the design of the development and landscape enhancement opportunities it is
instructive to note the following observation in SLA 2016 regarding Sensitivity Parcel St05:
“The sensitivity of the area lies in its role as a buffer between Stonehouse which is expanding with the
M5 and vale to the west, its contribution to the setting of the traditional, rural linear settlement of
Westend including listed buildings and the trees within the area. The value of the area lies in the
PROWs and the listed buildings in Westend adjacent. Employment use would definitely extend the
current development corridor towards the vale and M5. This may be acceptable providing
development provides a suitable high-quality gateway to Stonehouse with substantial landscape
treatment and considered in the context of the overall road corridor through to, and including, Stroud.
Also, a buffer would be needed with more sensitive buildings in Westend including the orchard with
smaller scale development on this boundary.” (SALA page 341, St05) [author emphasis]
10.102 The Revised Scheme, with the landmark stadium as its centerpiece, provides an opportunity to
facilitate just such a ‘high quality gateway’, as referred elsewhere in this LVIA and described
further in the Planning Statement and Design and Access Statement provided as separate
documents as part of the submission.
Valued Landscapes
10.103 There are no known national landscape designations or local/ non-statutory landscape
designations covering the Site or its immediate environs. The Cotswolds Area of Outstanding
Natural Beauty (AONB) is the closest national landscape designation located to the south and
east of the Site, at a distance of approximately 2km at its closest point east of Stonehouse.
The Industrial Heritage Conservation Area (IHCA)
10.104 The part of the Site (Redline Boundary) to the east of the M5 and south of the A419 lies partly
within The Industrial Heritage Conservation Area (IHCA) – see RS Figure 10.5c and RS Appendix
7.1. The IHCA is a linear conservation area occupying the valleys of the River Frome and
Nailsworth Stream, extending to the east, west and south of Stroud. The linear form of the IHCA
reflects the various transport and other infrastructure which developed over the 18th and 19th
centuries, principally around the River Frome / Stroudwater Canal corridor.
10.105 The Council has produced various Supplementary Planning Advice and a Supplementary Planning
Document on the IHCA – all of which are listed as separate documents (carrying different weight)
under the umbrella title of the ‘Industrial Heritage Conservation Area Statement’ (Adopted Nov
2008); more information on this is provided in RS Appendix 10.2 The LVIA has considered the
conservation area designation in terms of the contribution it makes to the character of the
contemporary landscape which forms part of the assessment of local landscape character set out
in RS Appendix 10.3 Landscape Assessment Schedules. An assessment of potential effects on
the IHCA is provided in Chapter 7 Archaeology and Cultural Heritage and RS Appendix 7.1.
10.106 It should be noted that the Development Footprint is situated to the north of the A419, outside
the IHCA, and separated from it by the part of the Site south of the A419 which will remain in its
current undeveloped state.
Cotswolds Area of Outstanding Natural Beauty (AONB)
10.107 The Cotswolds AONB is a limestone upland landscape with a prominent west facing scarp and
elevated open plateau and gentle dip slope extending southeast. The scarp extends over 52km
between Bath and Broadway marking the transition of the Cotswolds and Severn / Avon Vales,
Eco Park, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol.1 Main Text
December 2015
Page | 185
providing a backdrop to views as well as long views out over the Severn Estuary and Vale towards
the Forest of Dean.
10.108 The character of the AONB is described in the Cotswolds Landscape Assessment 2004 as referred
to in the previous landscape character section. Also of importance to this LVIA is the Cotswold
Area of Outstanding Natural Beauty Management Plan (2013-18)81 which describes the
overarching ‘special qualities’ of the Cotswolds as follows:
• “the unifying character of the limestone geology – its visible presence as natural outcrops,
its use as a building material and through the plant and animal communities it supports;
• the Cotswold escarpment, including views to and from it;
• the high wolds – a large open, elevated landscape with commons, ‘big’ skies and long-
distance views;
• river valleys, the majority forming the headwaters of the Thames, with high-quality water;
• dry stone walls, which give the AONB its essential character in many areas;
• internationally important flower-rich limestone grasslands;
• internationally important ancient broadleaved woodland, particularly along the crest of
the escarpment;
• variations in the colour of the stone from one part of the AONB to another which add a
vital element of local distinctiveness;
• the tranquility of the area82;
• well-managed arable and livestock farms;
• distinctive settlements, developed in the Cotswold vernacular, high architectural quality
and integrity;
• accessible landscape for quiet recreation; and
• historic associations.” (p8 The Cotswold AONB Management Plan, 2013-2018)
10.109 The character assessment of the Cotswolds AONB and the analysis of its special qualities both
inform the assessment of likely effects of the Revised Scheme on the designated landscape
presented in the Landscape Assessment Schedules at RS Appendix 10.3.
Wye Valley Area of Outstanding Natural Beauty (AONB)
10.110 Wye Valley AONB (Forest of Dean District) is located approximately 19km northwest of the
Revised Scheme at its closest point and therefore lies outside the 10km LVIA Study Area. It is
considered here as a precautionary measure, bearing in mind the nature of the Revised Scheme.
It should be noted that the Forest of Dean is not formally designated for its landscape value.
10.111 RS Appendix 10.10 Bare ground ZTV to 25km including Wye Valley AONB illustrates the
extremely limited visibility of the Revised Scheme across the Wye Valley AONB. This figure is
based on a bare ground ZTV, with all ZTV markers set to 19.5m height (the maximum height of
81 http://www.cotswoldsaonb.org.uk/management_plan/index.html 82 Where this report states that “Tranquillity is very difficult to define but is essentially the absence of inappropriate
noise, development, visual clutter and pollution, ‘a feeling of being away from it all’.” (p8 The Cotswold AONB
Management Plan, 2013-2018). The Cotswold Conservation Board have also produced a position statement on
tranquillity.
Eco Park, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol.1 Main Text
December 2015
Page | 186
the stadium) and is therefore illustrative of a worst-case scenario. The figure indicates a small
area of theoretical visibility on the SE boundary of Wye Valley AONB near St Briavels and
Tidenham Chase at approximately 22-24km distance from the Site. At this distance, even in more
exposed areas, where more open views may be available, the project components are likely to
be barely discernable or ‘lost’ within the wider landscape and visual context. No further
assessment of the Wye Valley AONB is therefore provided.
Local Landscape Designations
10.112 There are no local landscape designations recorded in the Study Area, or described in the current
Local Plan.
Other Relevant Designations
10.113 Other landscape related designations considered in the LVIA or elsewhere in the EIA include:
• Registered Parks and Gardens including Frampton Court and Woodchester Park (refer to
RS Appendix 10.2 of the LVIA); and
• Industrial Heritage Conservation Area83 (referred to in RS Appendix 10.2 and 10.3 in the
context of landscape character; assessed from a historic setting perspective in Chapter 7
Archaeology and Cultural Heritage and RS Appendix 7.1)
10.114 More information on the valued landscapes and designated areas within the Study Area is
provided at RS Appendix 10.2 with the geographic extent of the designations shown in RS Figure
10.6.
Visual Resource
10.115 The baseline assessment considers the visual resource of the Study Area and identifies key visual
receptors and representative viewpoints lying within the (screened and unscreened) ZTV of the
Revised Scheme.
Visual Receptors and Viewpoints
10.116 The visual resource of a particular area is made up of both specific views and general visual
amenity. Visual amenity is defined by GLVIA3:
“The overall pleasantness of the views people enjoy of their surroundings, which provides an
attractive visual setting or backdrop for the enjoyment of activities of the people living,
working, recreating, visiting or travelling through an area.”
10.117 Principal visual receptors can be either static or dynamic. The following receptors (visual
sensitivity in brackets) are identified as being of ‘high’ sensitivity due to their susceptibility to
visual change and/ or the value placed on views and visual amenity (with the exception of public
highways which are assigned ‘low sensitivity’) – see RS Appendix 10.1 Methodology:
• Residential properties within 0.5km (high);
• Small and small / medium sized settlements within 2km (high)84;
• Small / medium to large settlements within 2-5km (high)85;
83 http://www.stroud.gov.uk/info/IHCA_SPD_Nov08.pdf 84 Hamlets and villages in the immediate vicinity of the Site e.g. Westend, Eastington and Whitminster. 85 Villages and towns in the wider surrounding area e.g. Stonehouse, Frampton-on-Severn and Stroud.
Eco Park, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol.1 Main Text
December 2015
Page | 187
• Places of interest with public access within 10km (high);
• Publicly accessible land within 10km – including Common Land, Open Access Land (as
defined by Countryside and Rights of Way Act 2000 (CRoW)), Country Parks and National
Trust Land (high);
• National Recreational Trails and Cycle Routes within 10km – including the Cotswold Way,
and Thames and Severn Way (high);
• PRoW within 2km - Footpaths, bridleways, byways and tracks, local cycle ways, canal
towpaths etc (focusing on those within 1km of the site and where views are potentially
available due to reduced vegetative cover (high);
• Public highways within 10km – people in vehicles and others using main roads and local
roads (low).
10.118 In addition to site visits in 2015 and 2016, further fieldwork was undertaken in 2017 to verify and
identify receptors surrounding the Site with potential views of the Revised Scheme.
10.119 In practice, at a local level, excluding the Cotswolds escarpment, the visual envelope of the Site
is broadly contained within an area extending from Whitminster Court 400m to the north (near
Grove Lane), Fromebridge and Netherhill Cottages 800m to the west (near A38), ‘Claypits’
1,200m to the south west (near A38), Eastington Footpaths 800m to the south (near Alkerton),
Chipmans Platt roundabout 150m to the east (near A419) and the minor road/ rise to Nupend
450m to the northeast. These views are further interrupted by intervening hedgerows and
woodland.
10.120 Longer distance views from the Cotswold escarpment lying to the east of the Site are available
which are discussed in the following sections.
10.121 Potential visual receptors include the local PRoW network crossing and immediately adjacent to
the site, places of interest, residential properties and settlements such as Westend, Nupend,
Chipmans Platt and Eastington, as well as users of the M5, A419 and local road network including
Grove Lane (National Cycle Network Route No.45) as shown below in Table 10.3 below.
Table 10.3: Representative viewpoints and visual receptors
Viewpoint Distance* from Site
(Stadium) (m)
Direction
of view
Receptors (representative of)
1. A419 at M5 Junction 13 0 W
(144)
SE Road users
2. Footpath at Westfield Bridge
(EEA 41)
0 S
(489)
NW PRoW users (and residents)
3. Footpath east of Westend
(EEA 22)
99 NE
(224)
SE to SW PRoW users (and residents)
4. A419 at Chipmans Platt
roundabout
0 SE
(568)
NW Road users
5. Thames and Severn Way east
of M5 (also Footpath EEA 46)
180 SW
(631)
NE PRoW users
Eco Park, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol.1 Main Text
December 2015
Page | 188
Viewpoint Distance* from Site
(Stadium) (m)
Direction
of view
Receptors (representative of)
6. Footpath West of Nupend
(EEA 23)
337 ENE
(581)
SW PRoW users (and residents)
7. Grove Lane M5 over bridge 213 N
(424)
S Road users and NCN cyclists
8. Footpath north of Eastington
(EEA 51)
660 SSW
(1126)
NNE PRoW users (and residents)
9. Maiden Hill (Cotswold Way) 3,885 E
(4,171)
W PRoW users
10. Haresfield Hill (Cotswold
Way)
4,699 ENE
(4,886)
WSW PRoW users, National Trust
and open access land users
11. Selsey Common (Cotswold
Way)
5,296 SE
(5,837)
NW PRoW and common land /
open access land users
12. Cam Long Down (Cotswold
Way)
6,698 S
(7,216)
N PRoW and open access land
users
13. A38 at Claypits 917 SW
(1,509)
NE Road users (and residents)
14. A38 / Thames and Severn
Way intersection
425 WNW
(1,035)
ESE PRoW / road users and
residents
15. Footpath at Doverow Hill
(MST 30)
2,927 ESE
(3,377)
WNW PRoW users
16. Footpath west of Westend
(EEA 38)
0 E
(293)
W PRoW users (and residents)
A. St Michael’s and Angels
Church, Eastington)
420 SSE
(942)
NNW PRoW / road users and
residents
D. A38 Whitminster ridge
(garden centre car park)
930 NNW
(1,140)
SSE Road users (and residents)
E. Footpath at Barrow Hill,
Fretherne
5,800 NW
(5,926)
SE PRoW users
F. Footpath at Pleasant Stile,
Littledean (Forest of Dean)
12,000 NW
(12,124)
SE PRoW users (and residents)
G. Field Lane, Cam (minor road) 7,300 SSW
(7,772)
NNE Road users (and residents)
H. Layby on Frocester Hill (minor
road)
4,670 SSE
(5,083)
NNW Road, PRoW, common land /
and open access land users
*distance in metres and direction from Redline Boundary (Stadium in brackets)
10.122 A previously agreed selection of the representation viewpoints (with one additional location
substituted (VP16) due to lack of visibility of the Revised Scheme from that location (VP13)) have
been modelled, and ‘enhanced wireframe visualisations’ prepared to illustrate the scale and
outline appearance of the Revised Scheme in the landscape which are identified in Table 10.4
Eco Park, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol.1 Main Text
December 2015
Page | 189
Enhanced Wireframe Visualisation Viewpoints below. Night-time baseline photographs have also
been taken for these seven viewpoints. All viewpoints are marked on various figures, for example
RS Figure 10.1 and RS Figure 10.4.
Table 10.4: Enhanced Wireframe Visualisation Viewpoints (and Night-time Viewpoints)
VP Ref Dist*
(m)
Title Night-time base
photo included
4 0 A419 at Chipmans Platt roundabout Yes
6 337 Footpath west of Nupend Yes
8 660 Footpath north of Eastington Yes
9 3,885 Cotswold Way at Maiden Hill Yes
12 6,698 Cotswold Way at Cam Long Down Yes
15 2,927 Pleasant Stile, Littledean (Forest of Dean) Yes
16 0 Footpath west of Westend Yes
*distance in metres from Redline Boundary
Night time baseline
10.123 With respect to baseline lighting levels, in keeping with the LVIA, Chapter 14 Lighting notes that
the Site area is currently agricultural land with no existing artificial light sources within the
boundary. Lighting does spill onto the Site from adjacent sources including the M5 motorway,
car parks, industrial and ancillary buildings located adjacent to it as outlined in the night time
baseline assessment contained in RS Appendix 10.1 and RS Appendix 10.2. The existing sources
of lighting which characterise the immediate and surrounding area within 500m – 2km of the Site
are primarily:
• Dairy Crest (renamed Muller) and Ryeford Buisness Park, Stonehouse;
• Stonehouse urban/ street lighting;
• A419 street lighting (Stonehouse to Chipmans Platt);
• Chipmans Platt service station;
• WMC;
• Eastington Trading Estate;
• Eastington settlement/ street lighting;
• M5 Junction 13 highways depot;
• Whitminster settlement/ street lighting;
• A38 street lighting;
• A38 transport/ logistics depots/ quarry;
• A38 vehicle auction yards.
10.124 Notwithstanding the baseline lighting assessment contained in Chapter 14 the night time
observations in the field noted levels of existing lighting in the immediate and surrounding area
of the Site are typically higher to the east (A419 corridor, Dairy Crest and Stonehouse) and west
(A38 commercial depots and logistics yards, sand and gravel works, salt storage depot on J13 and
traffic on M5 adjacent to Site). Levels of lighting are lower to the north and south (e.g. River
Frome Corridor and areas around Nupend / Westend). The existing night time environment is
illustrated in the baseline photographs provided at RS Figure 10.13 for a range of representative
Eco Park, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol.1 Main Text
December 2015
Page | 190
viewpoints surrounding the Site. Existing levels of illuminance / light pollution in the Study Area
are shown on RS Figure 10.10a Cotswolds AONB Light Pollution Map, RS Figure 10.10b Night-
time Baseline / Existing Light Sources / Lighting Levels (Study Area) and RS Figure 10.10c Night-
time Baseline / Existing Light Sources / Lighting Levels (Detailed Area).
10.125 As a consequence, based on the observations in the field at night time, there are variable
patterns of lighting across the area due to its settled and agricultural nature on the one hand,
and its peri-urban qualities on the other (see also Chapter 14).
Future Baseline
Overview
10.126 Landscape is a constantly evolving resource, reflecting developments in agriculture,
transportation, industry and energy, in addition to the ever-changing nature of settlement.
Planned new housing and employment development to the west of Stonehouse (known as WOS
and currently under construction in phases), accompanied by associated improvements in
access, services and green infrastructure/ landscape, is and will extend the existing settlement
westwards along the A419 towards the M5 motorway and the Site. This general trajectory of
landscape change is considered appropriate in SDC’s recent strategic landscape study SALA 2016.
Climate Change
10.127 Natural England published its ‘climate change risk assessment and adaptation plan’ report in
2015, part of the statutory requirement on Government Agencies to provide such advice, arising
from the Climate Change Act 2008. In the report Natural England sets out the risks and threats
posed by current climate change predictions and how the agency proposes to respond to them.
As part of its strategy Natural England recognises that climate change offers opportunities as well
as threats. For instance:
“There is an opportunity to facilitate landscape change in ways that create valuable new
landscapes that are more resilient to climate change and deliver improved benefits for society
(sense of place, biodiversity and other ecosystem services).” (page 10)
10.128 The Landscape Institute’s position statement on climate change86 acknowledges that changes in
average temperatures, precipitation and extreme weather events will have an effect on the
landscape. However, it is difficult to quantify the potential effects arising and it is unlikely that
the anticipated changes in climate will appreciably change either the baseline landscape
conditions or the landscape and visual effects predicted in this LVIA.
10.129 Increased rainfall and flooding events, coupled with rising temperatures, are likely to modify UK
flora and fauna over time (partly due to changes is hydrology / ground conditions), and landscape
design measures can be introduced to cope with and adapt to the anticipated change. Such
measures form part of the SUDS proposals (embedded mitigation) for the Revised Scheme, as
outlined in the landscape strategy (refer RS Appendix 10.7) which will be the subject of detailed
design at the Reserved Matters Application stage. This will include details of climate change
adaption measures at this particular location, for example by specifying suitably resilient plant
species, so as to exploit the opportunity climate change presents to create ‘valuable new
landscapes’, in line with Natural England guidance.
86 Landscape architecture and the challenge of climate change (2008) Landscape Institute Position Statement.
Eco Park, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol.1 Main Text
December 2015
Page | 191
10.130 Other climate change adaption measures relating to SUDS and green infrastructure / ecosystem
services, which form part of the embedded mitigation and promote a quality and healthy
environment, are set out in the landscape strategy at RS Appendix 10.7 and include:
• extensive tree planting to establish ‘parkland’ landscape and wildlife corridors / networks
will create shade for cooling effect and sequestrate of carbon.
• hard landscape materials will be sustainably sourced and permeable paving used for all
parking areas and footpaths which together with other SUDS elements such as swales and
ponds will form part of a comprehensive drainage strategy.
Cotswold Canals
10.131 The Cotswold Canals Trust (CCT) aims to restore navigation along the Stroudwater Canal. The
Cotswold CCT has already embarked on a £37 million restoration project for ‘Phase 1a’ from
Stonehouse Court to Brimscombe Port; Phase 1b westwards to Saul Junction, including the
section immediately to the south of the Site is currently at the bid-submission stage.
10.132 For the purposes of this EIA, it has been assumed that the Cotswold Canals Trust will be successful
in acquiring their Heritage Lottery funding and subsequent planning permissions in the near
future and, therefore, the project is considered to be a ‘committed’ development in planning
terms, and is included in the Cumulative Landscape and Visual Impact Assessment (CLVIA) of the
Revised Scheme (see RS Figure 18.1 – cumulative scheme No.9 ‘Indicative Canal Realignment’).
10.133 The canal network is a historically important part of the local landscape and its restoration/
renaissance will offer a number of social, economic and environmental benefits, including
enhancement of both the landscape fabric and local character and distinctiveness of the historic
canal corridor within the IHCA. Such environmental enhancement measures within the Frome
River corridor are likely to benefit landscape character and visual amenity, a factor taken into
account in the CLVIA provided in this chapter.
Design Evolution
Introduction
10.134 The design of the Revised Scheme has evolved to support the overarching ethos of Eco Park, to
provide for exemplar innovative sustainable building design and landscape works as laid out in
Chapter 5. A key consideration informing the design evolution and landscape strategy was the
need to ensure that the Revised Scheme responds sensitively to its landscape context and, as far
as possible, preserves the character and visual amenity of surrounding landscape, property,
settlements and designated areas, particularly the Cotswolds AONB. Central to the design
strategy has been the ‘parkland’ landscape theme. The Revised Scheme as presented in RS Figure
1.1 Indicative Concept Plan, described in Chapter 5 Description of the Revised Scheme and
summarised in this chapter above.
Embedded versus Further Mitigation
10.135 The Revised Scheme has evolved in response to a range of environmental constraints and
opportunities identified during the design and EIA process. Mitigation measures have been
incorporated into the design to as far as possible avoid, reduce, and/ or offset potentially
significant adverse landscape and visual effects, thus demonstrating an iterative approach to the
Eco Park, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol.1 Main Text
December 2015
Page | 192
EIA in order to achieve the optimum outcome. EIA procedures follow a process of describing the
overall predicted level of effect prior to mitigation (Year 1), followed by the overall predicted
level of effect following mitigation (for example Year 15), termed the ‘residual effect’. However,
when carrying out an EIA, it is important to distinguish between those measures which are
integral to the design and those which proposed in addition.
10.136 For the purposes of this LVIA, and due to the outline status of the planning application, the
proposed mitigation is ‘embedded mitigation’ – measures integral to the proposal, formulated
during the design process and incorporated into the landscape strategy and the Indicative Green
Infrastructure Parameter Plan (RS Figure 5.3). All embedded mitigation will be subject to
approval as Reserved Matters at the detailed consents stage. ‘Further mitigation’ measures in
order to avoid, reduce, control, manage or compensate potential significant adverse landscape
and/ or visual effects identified in this LVIA will form part of the detailed design process should
the Revised Scheme be granted outline consent.
Enhancement
10.137 Where amelioration measures are proposed in order to ‘mitigate’ non-significant environmental
effects, this is termed enhancement. Beneficial/ positive effects may also be associated with
landscape or ecological enhancement measures that have a positive effect on landscape
character and visual amenity. Enhancement is not a formal requirement of the EIA Regulations
but is an implicit objective of the Revised Scheme. GLVIA3 states that:
“[Enhancement] is often referred to incorrectly as an outcome of proposed mitigation measures
– for example where planting is proposed to mitigate landscape and / or visual effects but will
also achieve an enhancement of the baseline condition of the landscape. In practice
enhancement is not specifically related to mitigation of adverse landscape and visual effects but
means any proposals that seek to improve the landscape and / or visual amenity of the Proposed
Development site and its wider setting beyond its baseline condition.” (GLVIA3 Para 3.39, p 43).
Landscape Constraints and Opportunities Plan
10.138 The Indicative Concept Plan (RS Figure 1.1) has evolved in response to the potential landscape
and visual constraints and opportunities identified during project inception, feasibility, design
development and consultation. Plans showing and describing these constraints and
opportunities are included at RS Figures 10.11a Offsite Constraints and Opportunities and
10.11b Onsite Landscape Constraints and Opportunities.
10.139 RS Figure 10.11a identifies offsite constraints and opportunities in relation to:
• Topography and Key Views;
• Landscape Character and Historical Context;
• Movement, Transport and Circulation;
• Settlement and Properties.
10.140 RS Figure 10.11b identifies onsite constraints and opportunities in respect of:
• Riparian Landscape and History;
Eco Park, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol.1 Main Text
December 2015
Page | 193
• Landscape Character and Historical Context;
• Movement, Transport and Circulation.
10.141 Together, the combined landscape and visual constraints and opportunities inform the landscape
design, Green Infrastructure and landscape mitigation strategies for the Revised Scheme as set
out in the next section.
Landscape Strategy and Green Infrastructure
10.142 Central to the design of the Revised Scheme is the aim to respect local landscape character and
visual amenity and, as far as possible, to contribute to their enhancement. Following
identification of the landscape and visual constraints and opportunities described above, a
bespoke landscape strategy has been devised outlining proposals for landscape mitigation and
enhancement. This information feeds into and underpins RS Figure 5.3 Indicative Green
Infrastructure Parameter Plan which sets out the proposed enhancements alongside the
embedded and further mitigation for biodiversity, ecosystem services and landscape
improvements.
10.143 The Landscape Strategy included at RS Appendix 10.7 and RS Figures 10.11c and 10.11d
describes the landscape design strategy and mitigation rationale using a combination of graphics
and text, and sets out the overall Vision, the Key Objectives and the Key Landscape Elements and
Design Principles. The Landscape Strategy articulates how the landscape and visual constraints
and opportunities identified in RS Figure 10.11a and RS Figure 10.11b and as summarised above,
have been translated into the landscape design and mitigation proposals embedded in the
Indicative Green Infrastructure Parameter Plan (RS Figure 5.3) and the Indicative Concept Plan
(RS Figure 1.1).
10.144 The key landscape strategies presented in RS Figure 10.11c are:
• Create a ‘parkland’ landscape setting;
• Retention of long distance views across the Site;
• Setting back of built form from adjacent settlement/ residential properties;
• Translocation of existing native species hedgerow; a
• Protection of cultural heritage and archaeology (onsite and offsite).
10.145 Regarding landscape mitigation and enhancement, a range of measures are proposed (see RS
Figure 10.11d) in order to avoid or minimise potential landscape and visual effects and enhance
local landscape character, visual amenity and biodiversity in the medium to long term including
the following:
• Generous set back of built form from the Redline Boundary to protect local character,
visual amenity and the setting of the IHCA;
• Planted belts of appropriate tree species to create ‘parkland’ setting;
Eco Park, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol.1 Main Text
December 2015
Page | 194
• Landscape buffer / ‘woodland meadow’ planting incorporating earth bunds and ‘dark bat
corridors’ to protect adjacent residential amenity and wildlife and provide landscape and
visual benefit (see RS Figure 5.6)87.
Landscape and Habitat Management Strategy Plan
10.146 In order to ensure the lasting success and longevity of the landscape and ecology strategies, a
combined management plan is proposed. It is intended that a landscape and habitat
management plan (secured by an appropriate planning condition) will be produced and
implemented.
Potential Effects
Introduction
Assessment Process
10.147 A detailed assessment of potential landscape and visual effects of the Revised Scheme is
provided in Volume 3 of the ES at RS Appendix 10.3 Landscape Assessment Schedules, RS
Appendix 10.4 Visual Assessment Schedules and RS Appendix 10.5 Cumulative Assessment
Schedules. The baseline situation is taken to be that pertaining at the time of submission in 2017,
as outlined earlier in this chapter and described in more detail in RS Appendix 10.2.
10.148 The assessment of potential effects considers the construction and operation phases of the
development separately; for operation the likely effects at the outset (Year 1) and following
establishment of the landscape works (Year 15) are assessed. A commentary on the night time
baseline situation and potential effects arising is also provided.
10.149 The cumulative assessment follows a similar format and considers the likely additional effect of
the Revised Scheme in combination with significant ‘committed’ and planned developments
within 5km of the Site.
10.150 The significant adverse landscape and visual effects predicted to result from the Revised Scheme
are summarised below based on the detailed assessments provided in RS Appendices 10.3-10.5.
Non-significant effects are described in RS Appendix 10.8.
Nature of Revised Scheme
10.151 As confirmed in the methodology section above, landscape and visual effects are assessed as
adverse / negative unless stated otherwise in order to test worst-case. That said, it is important
to note that this is a landmark building designed by internationally renowned architects Zaha
Hadid Associates, constructed in natural (timber) materials, placed within a ‘parkland’ setting at
a ‘gateway’ location to Stroud, which will be perceived positively by some members of the public.
Bearing in mind the European Landscape Convention definition of landscape quoted above in the
main Introduction section these positive perceptual factors cannot be discounted from the
assessment and therefore have been taken into account in the assessment of residual effects. In
practical terms this means that the establishment and maturing of the proposed landscape
87 It is assumed that planting on the earth bund would reach a height of approximately 5m by Year 15 as shown on
RS Figure 5.6 having regard to variations in growth rates dependent on species mixes and growing conditions.
Eco Park, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol.1 Main Text
December 2015
Page | 195
mitigation / new planting will provide increasing landscape and visual benefit over time which
will moderate adverse effects in the longer term.
Sources of Effects
10.152 The sources of landscape and visual effects will vary across the lifecycle of the Revised Scheme
from construction through initial completion (Year 1) to longer term operation (Year 15). The
sources of temporary/ short term and permanent/ long term effects including embedded
mitigation are summarised below.
During Construction (Temporary / Short Term)
10.153 The Revised Scheme will be constructed as set out in Chapter 5. Construction will generate
temporary and short-term effects lasting for the duration of works for each phase. In summary
the sequence of works will involve all elements (except the training pitches) being be completed
before the stadium is brought into us. Effects likely to arise on the landscape and visual resource
during construction will include those emanating from:
• Site clearance, removal / trimming of vegetation etc.;
• Stripping and temporary earthworks including storage of topsoil and spoil;
• Construction of access roads, public highway improvements and associated infrastructure
and landscape works;
• Construction of stadium building and associated parking facilities and sports pitches;
• Construction compound(s) for delivery and storage of materials and temporary parking;
• Temporary buildings (cabins and storage containers), hoarding and other security fencing;
• Construction traffic and temporary activity associated with vehicles and machinery.
10.154 Construction effects will affect landscape and visual receptors temporarily in different ways
depending on their location / proximity to the Development Footprint.
During Operation (Permanent / Long Term)
10.155 Effects likely to arise following completion and during the operational life of the Revised Scheme
will include those arising from:
• The stadium, training pitches and ancillary facilities used primarily by FGRFC First Team;
• Access roads and highways improvements and associated movement of vehicles;
• New planting and other landscape works including hedges, tree cover, bunding and areas
of grassland.
10.156 Operational landscape and visual effects will tend to decrease over time as the proposed
landscape mitigation and enhancement becomes established and matures. Fifteen years is
generally considered an appropriate timeframe for this. Thus Year 15 is adopted as the suitable
point at which to judge the level of residual landscape and visual effect. In reality, the landscape
mitigation and enhancement will continue to mature after Year 15 providing increasing benefits
to landscape character, visual amenity and biodiversity.
Landscape Resource
Eco Park, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol.1 Main Text
December 2015
Page | 196
10.157 Predicted significant adverse effects potentially occurring during construction and operation in
relation to the various aspects of the landscape resource, as described in the baseline assessment
section, are set out below. Non-significant landscape effects are described in RS Appendix 10.8.
The level of residual landscape effect is judged by assessing the magnitude of landscape change
against the sensitivity of the receptor, the latter being a product of its value and susceptibility to
change of the type proposed.
Scope of Landscape Assessment
10.158 As outlined in the Baseline Conditions section above the landscape assessment examines the
following aspects of the landscape resource in the study area:
• Landscape fabric of the Site including PRoW;
• Landscape character;
• Valued or designated landscapes.
Effect on Landscape Fabric
10.159 The landscape fabric of the Site is shown on RS Figure 10.2 and includes the following landscape
elements:
• Landform/ Topography;
• Vegetation and Boundary features;
• Other Site Elements including PRoW.
Predicted Significant Effects on Landscape Fabric
10.160 The Revised Scheme will transform the landscape fabric of the Development Footprint from
agricultural land to a mixture of built development, sports pitches, access roads, car parking areas
and open spaces / new planting. The remainder of the Site will remain in its current undeveloped
state.
10.161 Notwithstanding the agricultural grassland and hedgerows and tree planting within the
Development Footprint that will need to be removed, translocated and replanted to
accommodate the proposed stadium, access and parking areas, the majority of existing trees will
be retained and incorporated within the Revised Scheme. A number of hedges will be
translocated and new ones planted; where translocation is not possible hedgerows will be
replanted in appropriate locations / alignments using suitable native species as shown on RS
Figure 8.2 Trees and Hedgerows Balance.
10.162 The Revised Scheme provides an opportunity to achieve synergies between hedgerow
translocation / replanting and future PRoW improvements / realignment. It is proposed to
increase the total length of hedgerows currently on the Site in order to maximise biodiversity
and wildlife benefits, and enhance landscape character and visual amenity locally. The current
proposal is for the PRoW to be retained as existing but, in accordance with Eastington
Neighbourhood Development Plan (NDP) Policy EP9 Public Rights of Way and Wildlife
Corridors, the intention is for them to be realigned (within the Development Footprint boundary)
to follow new green corridors incorporating double hedgerows (see NDP EP9 Map 4 Wildlife
Corridors and RS Figure 8.2). PRoW and hedgerow realignment will be the subject of detailed
design at the Reserved Matters Application stage, secured by a suitable planning condition.
Eco Park, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol.1 Main Text
December 2015
Page | 197
Considered together with the new A419 pedestrian crossing for footpath EEA 37 the outcome of
these realignments and hedgerow enhancements will be a benefit to the local PRoW network.
10.163 Drawing these various adverse and positive effects together, on balance, the magnitude of
effect on the generally low to medium sensitivity landscape fabric of the Site overall during
construction and Year 1 of operation will be medium to high, leading to a moderate / major
significant level of adverse effect at most during construction and at Year 1 of operation which
will be temporary and short term. As the proposed mitigation and enhancements become
established through operation, thus creating the ‘parkland’ setting for the Revised Scheme, these
effects will reduce so that at Year 15 the predicted magnitude of effect on the landscape fabric
will be low to medium, leading to a moderate / minor or lower (and not significant) residual
effect. In all likelihood adverse landscape effects will reduce over time becoming increasingly
beneficial / positive as the proposed mitigation and enhancement measures mature in the longer
term.
10.164 The same variation in magnitude of landscape change is predicted in relation onsite PRoW EEA
37 and EEA 38. In this instance, given the high sensitivity of this receptor and medium / high
magnitude of change predicted a major / moderate (and significant) level of adverse effect is
predicted in construction and at Year 1. This level of effect is though predicted to reduce during
operation to become moderate level and not significant by Year 15.
10.165 No adverse effects on landscape fabric are predicted in relation to existing structures on the
Site such as the various onsite barns and Westfield Bridge. These structures do not form part of
the proposed works for the Revised Scheme and will be retained in their existing form. A low to
medium magnitude of change and a minor / moderate level of adverse effect is predicted in
relation to site landform during construction and operation which will be direct, permanent
and not significant both in the short and longer terms.
10.166 Taking into account both the negative and positive aspects of the Revised Scheme, the predicted
residual effect on the landscape fabric of the Site overall at Year 15 will be moderate adverse
at most and not significant in the EIA context. This includes PRoW EEA 37 and EEA 38 which,
although being subject to significant physical effects initially, will be retained in their current
alignment in the short term, and appropriately integrated into the Site landscape in an attractive
manner at the detailed design stage in line with local planning policy objectives. Thus, the
significant adverse effects arising initially during construction and the first year of operation
(i.e. in the short term) will reduce to a not significant residual level during operation in the
longer term (by Year 15).
Assessment of Effect on Landscape Character
10.167 The baseline assessment above examined landscape character in the Study Area at the national,
county and local authority level in addition to considering the Cotswolds AONB. Based on scoping
and pre-application / post application consultation responses, particularly those received from
SDC and Natural England, it is considered appropriate to focus the assessment of potential
landscape character effects to the local level but to consider the regional and nation character
context as well. Thus the focus here is on the landscape units defined in the published Landscape
Character Assessments listed below:
• Stroud District Landscape Assessment (SDLA), 2000;
• Cotswolds AONB Landscape Assessment, 2004; and
Eco Park, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol.1 Main Text
December 2015
Page | 198
• Stroud Industrial Heritage Conservation Area (IHCA) Statement – Supplementary Planning
Advice (Adopted), 2008 – Volume 1: Summary and Character Overview (Parts 1-4) and
Volume 2: Character Parts.
10.168 A comprehensive assessment of landscape character effects is set out in RS Appendix 10.3 in
which the following landscape character assessments are also considered:
• Gloucestershire County Character Assessment 2006;
• Natural England National Character Assessment.
10.169 The various Landscape Character Assessment information referred to above and in the baseline
section (including RS Appendix 10.2) is displayed graphically at RS Figures 10.4a and 10.4b.
Landscape Character Sensitivity
10.170 The sensitivity of the local landscape to the Revised Scheme is discussed in the baseline section
above and an outline evaluation provided at RS Appendix 10.2. A summary of this high-level
assessment of local landscape sensitivity is provided in Table 10.5 below; RS Figure 10.8b
Landscape Sensitivity of Stroud District Landscape Character Types with Project Components
(Ecotricity) and RS Appendix 10.9 displays the SDLA information graphically:
Table 10.5: Landscape Sensitivity
Stroud District Landscape Assessment 2000 (SDLA)
Landscape Character Unit Ref Dist* Susceptibility Value Sensitivity
Escarpment Footslopes 5A Onsite
Medium /
High
Medium /
High
Medium /
High
Lowland Plain 5B Onsite Medium Medium Medium
Frome River Valley 5C Onsite
Medium /
High
Medium /
High
Medium /
High
Wold Tops 1 5.0 High High High
Secluded Valleys 3 3.5 High High High
Escarpment 4 2.8 High High High
Severn Vale Grazing Marshes 8 3.0 Medium Medium Medium
Severn Vale Hillocks (No.7) 7 4.0 Medium Medium Medium
Cotswolds AONB Landscape Character Assessment 2004
Landscape Character Unit Ref Dist* Susceptibility Value Sensitivity
Escarpment Outlier / Cam
Longdown, Peaked Down and
Downham Hill.
LCT 1 /
LCA 1A 6.5 High High High
Eco Park, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol.1 Main Text
December 2015
Page | 199
Cotswolds AONB Landscape Character Assessment 2004
Landscape Character Unit Ref Dist* Susceptibility Value Sensitivity
Escarpment / Uley to Coopers
Hill. LCT 2 /
LCA 2C 3.0 High High High
Rolling Hills and Valleys /
Stinchcombe and North Nibley. LCT 3 /
LCA 3B 7.0 High High High
High Wold / Nympsfield and
Kingscote Plateau
&Minchinhampton Common.
LCT 7 /
LCA 7A 5.0 High High High
Settled Unwooded Vale / Vale
of Gloucester Fringe
LCT 18
/ LCA
18A
2.0 High High High
Stroud Industrial Heritage Conservation Area Statement 2008
Landscape Character Unit Ref Dist* Susceptibility Value Sensitivity
Stroudwater settlement LCT 1 0.0 Medium High
Medium-
High
Core Vale Settlement East of
Eastington LCT 2 0.3 Medium High
Medium-
High
Green Corridor: Rural Frome
Vale LCT 4 0.0 Medium High
Medium-
High
Meadow Mill LCT 7 0.0 Medium High
Medium-
High
* approximate distance from Redline Boundary in km at closest point
10.171 The landscape sensitivities recorded for each relevant character unit in the Study Area above
inform the assessment of effects on landscape character below.
Predicted Significant Effects on Landscape Character
10.172 The Revised Scheme will significantly change the character of the Development Footprint and
immediately adjacent landscape falling within SDC’s LCT 5A Escarpment Footslopes and LCT 5B
Lowland Plain (both forming part of the Rolling Agricultural Plan LCT 5), up to a distance of
approximately 250m, where uninterrupted visibility of the proposal occurs. The same level of
significant, adverse residual landscape effect would apply in respect of SV6A Vale of Berkeley
(Gloucestershire Landscape Assessment 2006). The adjacent Frome River Valley (LCT 5C) and
IHCA Green Corridor: Rural Frome Vale (LCT 4) which both lie to the south of the Development
Footprint (see RS Figure 10.5a and RS Figure 10.5c) will not be affected to any significant level
character wise.
Eco Park, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol.1 Main Text
December 2015
Page | 200
10.173 The magnitude of character change during construction and the first year of operation on and
immediately adjacent to the Development Footprint will be high which, taking account of the
medium to high landscape sensitivity of the host landscape, will generate a major to major /
moderate, adverse landscape effect initially at most on the Escarpment Footslopes (LCT5a) and
the Lowland Plain (LCT5b) within approximately 250m of the Development Footprint that will
be direct, temporary and significant in the context of this EIA.
10.174 Broadly similar extent and levels (or slightly lower) of significant adverse character effect will
apply in the short term in respect of the corresponding part of SV6A Vale of Berkeley (medium
sensitivity) and the SALA landscape units (low / medium, medium and high / medium sensitivity
as shown on RS Figure 10.8a both on and adjacent to the Development Footprint. It is important
to also consult RS Figure 10.5d which is provided to help understand the relationship between
the various levels of LCA, from the local IHCA and SDC LCAs, through to the national level NCAs.
10.175 As the proposed, embedded landscape mitigation establishes and matures during operation the
effect on the Escarpment Footslopes (LCT5a) and the Lowland Plain (LCT5b) will reduce to a
moderate / major (or lower) level of significant adverse residual effect in the longer term (by
Year 15) which will be direct and indirect, and permanent. The same level of significant, adverse
residual landscape effect would apply in respect of SV6A Vale of Berkeley (Gloucestershire
Landscape Assessment 2006).
10.176 It should be noted that the predicted significant adverse effects on landscape character will be
localised and limited. Furthermore, the proposed embedded mitigation and enhancement
including new planting and the creation of a ‘parkland’ setting for the stadium will provide
substantial landscape character and visual amenity benefits in the longer term.
10.177 Beyond approximately 250m from the Site, landscape character effects will be less, diminishing
with distance, and will therefore be not significant. The remainder of Stroud District’s landscape
and the associated character types/ areas within the Study Area, including those within and
defined by the IHCA, will not be affected to any significant degree character wise, and the
majority of the District’s landscape lying beyond will be unaffected.
10.178 There will be no significant adverse effect on the character of the high sensitivity Cotswolds
Area of Outstanding Natural Beauty (AONB) landscape, including the prominent escarpment,
the closest part of the AONB. This will be subject to a low magnitude of change and affected to
a moderate/minor, not significant level at its nearest point to the Site in the vicinity of
Stonehouse. The vast majority of the Cotswolds AONB will be unaffected by the Revised Scheme.
The setting of the Cotswolds AONB is dealt with in the following Valued Landscapes section.
Assessment of Effect on Valued / Designated Landscapes
10.179 There is one national level landscape designation in the Study Area – the Cotswolds AONB
located to the east of the Site, and several Registered Parks and Gardens situated within the
Study Area (see RS Figure 10.6). There are no local level landscape designations within the Study
Area; Conservation Areas such as the Stroud IHCA are assessed in Chapter 7 Archaeology and
Cultural Heritage and RS Appendix 7.1.
Predicted Significant Effects on Valued Landscape
10.180 No significant, adverse landscape and visual effects are predicted to arise on valued landscapes
in the Study Area as a result of the Revised Scheme. The worst case potential effect of the
Eco Park, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol.1 Main Text
December 2015
Page | 201
proposal on the high sensitivity Cotswolds AONB landscape is assessed as low magnitude, causing
an indirect and moderate/minor level effect, extending up to approximately 5km from the Site.
Due to the sensitive design layout, form and appearance of the Revised Scheme, there will be no
significant adverse effect on either the setting or the special qualities of the Cotswolds AONB,
including the ‘escarpment’, the ‘high wold’ and ‘tranquillity’ aspects of the designated area.
Registered Parks and Gardens in the Study Area will be unaffected by the Revised Scheme.
Summary of Significant Effects on Landscape Resource
10.181 The Revised Scheme will transform the Development Footprint from its current agricultural land
use to a sensitively designed, landmark stadium building set in ‘parkland’ grounds incorporating
sports pitches, access roads, car parking areas and open spaces/ new planting, all planned and
constructed to the highest sustainability specification.
10.182 This change will have a significant adverse effect on part of the Site’s landscape fabric initially
during construction and the first year of operation, including short stretches of PRoW EEA 37
and EEA 38. However, these direct effects on the landscape fabric will be short to medium term,
reducing overtime during operation to become not significant in the longer term (Year 15 and
beyond).
10.183 The transformation of the Development Footprint will significantly change the character of both
the Development Footprint itself, and the immediate surroundings up to a distance of
approximately 250m from its boundary, where uninterrupted visibility of the proposal exists.
Although the level of adverse effect will reduce over time as the proposed embedded mitigation
and enhancement matures, and notwithstanding the positive attributes of the landmark stadium
and its ‘parkland’ setting, a significant adverse residual effect is predicted on the character of
the Development Footprint and immediately adjacent landscape up to approximately 250m
which will remain in the longer term.
10.184 No significant adverse landscape effects are predicted to arise on valued / designated
landscapes in the Study Area as a result of the Revised Scheme. There will be no significant effect
on the character or special qualities of Cotswolds AONB including its prominent escarpment.
Other valued landscapes in the Study Area, including Registered Parks and Gardens, will be
unaffected by the Revised Scheme.
10.185 Overall, the extent of likely significant adverse character effects will be limited and the
remainder Stroud District’s landscape will not be affected to any significant degree and will be
largely unaffected by the Revised Scheme.
10.186 Furthermore, although it is assumed in this LVIA that people will perceive the change as negative,
bearing in mind the European Landscape Convention definition of landscape quoted above, and
the nature of the Revised Scheme, it is reasonably likely that many will perceive it in a neutral or
even a positive way.
10.187 A summary of significant adverse landscape effects predicted to arise during construction and
operation as a result of implementing the Revised Scheme is set out in Table 10.6 below.
Significant landscape effects are highlighted in bold
Table 10.6: Summary of Significant Effects on Landscape Resource
Eco Park, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol.1 Main Text
December 2015
Page | 202
Effect Recept
or
Sensiti
vity
Magnitude
of Residual
Effect
Level of
Landscape
Effect on
Completion
(Year 1)*
Significant
or not?
Level of
Residual
Landscape
Effect (Year
15)*
Significant
or not?
Effect on
landscape
character
Escarpm
ent
Footslo
pes
(Stroud
No 5A)
Medium
to High
High within
250m of
Developme
nt Footprint
(Medium /
Low or Less
beyond
250m)
Major to Major
/ Moderate
within 250m of
Development
Footprint
(Moderate to
Moderate /
Minor or lower
beyond 250m)
Significant
within
250m
(Not
significant
beyond
250m)
Moderate /
Major within
250m of
Development
Footprint
(Moderate /
Minor or
lower beyond
250m)
Significant
within
250m
(Not
significant
beyond
250m)
Effect on
landscape
character
Lowland
Plain
(Stroud
No 5B)
Medium High
within
250m of
Developme
nt Footprint
(Medium /
Low or less
beyond
250m)
Major /
Moderate
within 250m of
Development
Footprint
(Moderate /
Minor or lower
beyond 250m)
Significant
within
250m
(Not
significant
beyond
250m)
Moderate to
Moderate /
Major within
250m of
Development
Footprint
(Minor /
moderate or
lower beyond
250m)
Significant
within
250m
(Not
significant
beyond
250m)
Effect on
landscape
character
LCT SV6
Settled
Unwood
ed Vale
(Glos),
LCA
SV6A
Vale of
Berkeley
Medium High up to
250m of
Developme
nt Footprint
Medium /
Low beyond
250m
Major /
Moderate
up to 250m of
Development
Footprint
Moderate /
Minor or less
beyond 250m
Significant
within
250m
(Not
significant
beyond
250m)
Moderate /
Major within
250m of
Development
Footprint
(Minor /
moderate or
lower beyond
250m)
Significant
within
250m
(Not
significant
beyond
250m)
* the 250m distance threshold for significant character effects is approximate and will vary
depending on visibility of the proposal on the ground.
Visual Resource
10.188 Predicted significant adverse effects in relation to the visual resource, as set out in the baseline
assessment section, are assessed below. Non-significant visual effects are described in RS
Appendix 10.8.
Scope of Visual Assessment
10.189 The visual assessment concerns the effect of the Revised Scheme on views and visual amenity
experienced by people in the following receptor groups, which are assessed below with
reference to RS Figures 10.1 to 10.7.
• Residential properties within 0.5km;
• Small to medium sized settlements within 2km (medium to large settlements within 5km);
• National recreational trails and cycle routes within 10km;
Eco Park, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol.1 Main Text
December 2015
Page | 203
• Public rights of way within 2km;
• Public highways within 10km;
• Places of interest with public access within 10km;
• Publicly accessible land within 10km.
10.190 In addition, to assist in the visual (and landscape) assessment, the previously agreed88
representative viewpoints have been photographed in summer and winter as presented in RS
Figure 10.13 and visualisations prepared for an agreed selection of these viewpoints in RS Figure
10.14 Enhanced Wireframe Visualisations.
Assessment of Effect on Visual Resource
10.191 An assessment of the potential effect on representative viewpoints and key sensitive visual
receptors (including settlement and residential properties surrounding the Site) lying within the
ZTV of the Revised Scheme is provided at RS Appendix 10.4 Visual Assessment Schedules. The
level residual visual effect is judged by assessing the magnitude of change to visual amenity
against the sensitivity of the receptor (the latter being a product of its value and susceptibility to
visual change of the type proposed). The visualisations provided at RS Figure 10.14 are a useful
aid to visual assessment. A summary of this assessment identifying the predicted significant
effects on the visual resource is set out below.
Summary of Effects on Viewpoints
10.192 A summary of likely residual effects of the Revised Scheme on the representative viewpoints
previously agreed with consultees and SDC during pre-application and post-application
consultations relating to the original submission is set out in Table 10.7 below. Significant visual
effects are highlighted in bold.
Table 10.7: Assessment of Representative Viewpoints
Viewpoint Distance
from Site*
(Stadium)
Visual
Receptor
(and
Sensitivity)
Magnitude
of Visual
Effect
Level of
Adverse
Effect
(Year 1)
Significant
or not?
Level of
Adverse
Residual
Effect (Yr
15)
Significant
or not?
1. A419 at
M5
Junction
13
0m W
(144)
Road users
(Low)
Medium to
Low
Minor /
Moderate
Not
Significant
Minor Not
Significant
2.
Footpath
at
Westfield
Bridge
(EEA 41)
0m S
(489)
PRoW
users (High)
Low Moderate /
Minor
Not
Significant
Moderate /
Minor
Not
Significant
3.
Footpath
east of
Westend
(EEA 22)
99m NE
(224)
PRoW
users and
residents
(High)
Low Moderate /
Minor
Not
Significant
Minor /
Moderate
Not
Significant
4. A419 at
Chipmans
0m SE Road users
(Low)
Medium to
Low
Minor /
Moderate
Not
Significant
Minor Not
Significant
88 previously agreed with Natural England, the Cotswolds AONB Conservation Board and SDC during pre-application
and post-application consultations relating to the original submission.
Eco Park, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol.1 Main Text
December 2015
Page | 204
Viewpoint Distance
from Site*
(Stadium)
Visual
Receptor
(and
Sensitivity)
Magnitude
of Visual
Effect
Level of
Adverse
Effect
(Year 1)
Significant
or not?
Level of
Adverse
Residual
Effect (Yr
15)
Significant
or not?
Platt
roundabo
ut
(568)
5.
Thames
and
Severn
Way east
of M5
(Also
Footpath
EEA 46)
180mSW
(631)
PRoW
users (High)
Low to
Negligible
Minor /
Moderate
Not
Significant
Minor /
Moderate
Not
Significant
6.
Footpath
West of
Nupend
337m ENE
(581)
PRoW
users and
residents
(High)
Medium to
Low
Moderate Not
Significant
Moderate to
Moderate /
Minor
Not
Significant
7. Grove
Lane M5
over
bridge
213m N
(424)
Road users
and NCR
cyclists
(Low and
Medium)
Medium to
High
Moderate /
Major
Significant
Moderate to
Moderate /
Major
(Adverse
and
Beneficial)
Significant
8.
Footpath
north of
Eastingto
n (EEA
51)
660m
SSW
(1,126)
PRoW
users and
residents
(high)
Low Moderate /
Minor
Not
Significant
Moderate /
Minor
Not
Significant
9. Maiden
Hill
(Cotswold
Way)
3,885m E
(4,171)
PRoW
(High)
Low Moderate /
Minor
Not
Significant
Minor /
Moderate
Not
Significant
10.
Haresfield
Hill
(Cotswold
Way)
4,699m
ENE
(4,886)
PRoW,
national
trust and
open
access land
users (High)
Low Moderate /
Minor
Not
Significant
Minor /
Moderate
Not
Significant
11. Selsey
Common
(Cotswold
Way)
5,296m
SE
(5,837)
PRoW and
common
land / open
access land
users (High)
Low to
Negligible
Minor /
Moderate
Not
Significant
Minor Not
Significant
12. Cam
Long
Down
(Cotswold
Way)
6,698m S
(7,216)
PRoW and
open
access land
users (High)
Negligible Minor Not
Significant
Minor Not
Significant
13. A38 at
Claypits
917m SW
(1,509)
Road users
and
residents
(Low and
High
respectively
)
Low for
property
Low to
Negligible
for road
users
Moderate /
Minor for
property
Minor /
Negligible
for road
users
Not
Significant
Minor /
Moderate for
property
Negligible
for road
users
Not
Significant
Eco Park, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol.1 Main Text
December 2015
Page | 205
Viewpoint Distance
from Site*
(Stadium)
Visual
Receptor
(and
Sensitivity)
Magnitude
of Visual
Effect
Level of
Adverse
Effect
(Year 1)
Significant
or not?
Level of
Adverse
Residual
Effect (Yr
15)
Significant
or not?
14. A38 /
Thames
and
Severn
Way
intersecti
on
425m
WNW
(1,035)
Road,
PRoW
users and
residents
(Low and
High
respectively
)
Negligible Minor for
property /
PRoW
Negligible
for road
users
Not
Significant
Minor for
property /
PRoW
Negligible
for road
users
Not
Significant
15.
Footpath
at
Doverow
Hill (MST
30)
2,927m
ESE
(3,377)
PRoW
users (High)
Low Moderate /
Minor
Not
Significant
Minor /
Moderate
Not
Significant
16.
Footpath
west of
West End
Cross
(EEA 38)
0m E
(293)
PRoW users (High)
Medium to
High
Major /
Moderate
Significant Moderate /
Major
(Adverse &
Beneficial)
Significant
A. St
Micheal
and
Angels
Church
420m SSE
(942)
Historic Asset Grade
II*
(High)
Negligible Minor Not
Significant
Minor Not
Significant
D. A38
Whitminst
er Ridge
930m
NNW
(1,140)
Road Users (Low)
Low to
Negligible
Minor /
Negligible
Not
Significant
Minor /
Negligible
Not
Significant
E. Barrow
Hill
5,800m
NW
(5,926)
PRoW Users (High)
Low to
Negligible
Minor /
Moderate
Not
Significant
Minor Not
Significant
F. Little
Dean,
Forest of
Dean
12,000m
NW
(12,124)
PRoW Users
(High)
Negligible Minor Not
Significant
Minor Not
Significant
G. Field
Lane,
Cam
7,300m
SSW
(7,772)
Road Users / Nearby PRoW
(High)
Negligible Minor Not
Significant
Minor Not
Significant
H.
Frocester
Hill
4,60km
SSE
(5,083)
PRoW Low to
Negligible
Minor /
Moderate
Not
Significant
Minor Not
Significant
*distance in metres from Redline Boundary (and Stadium in brackets)
10.193 Those viewpoints which have been identified as significant are significant because they are
sensitive receptors located on, or close to, the Site. They are therefore predicted to experience
medium to high or high magnitude of visual change due to their proximity to, and relatively
unobstructed visibility of, the Revised Scheme.
Eco Park, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol.1 Main Text
December 2015
Page | 206
Summary of Significant Effects on Visual Resource
10.194 Residents of a small number of residential properties located adjacent to the Site, and people
using several short lengths of PRoW (both high sensitivity visual receptors) and public highway
in the vicinity of the Site, are predicted to be significantly affected visually as a result of
implementing the Revised Scheme, both during construction and early operation (Year 1) of the
development. However, adverse visual effects will be ameliorated by the embedded mitigation
including new planting which will reduce adverse effects and increase beneficial effects in the
longer term (Year 15 and beyond).
10.195 Moderate/Major to Major levels of significant adverse residual visual effects are predicted in
relation to short stretches of Eastington Footpath Nos 37 and 38 crossing the Development
Footprint, and public highway immediately adjacent to the Site, namely the A419, the M5
motorway and Grove Lane M5 overbridge. This level of effect would result from medium to
high magnitudes of visual change occurring initially at these high sensitivity receptors, reducing
to medium magnitude over time as the proposed embedded mitigation becomes established
over time.
10.196 The visual amenity of three dwellings adjacent to the Site, namely Westend House, Ivy Cottage
and Mole Cottage will experience major/moderate, direct adverse visual effects initially during
construction, reducing during operation to become moderate level and not significant in the
longer term. This level of effect would result from medium to high magnitudes of visual change
occurring initially at these high sensitivity receptors, reducing to low to medium magnitude over
time as the proposed landscape buffer / new planting matures. The predicted initial significant
visual effects are due to the visibility of the Revised Scheme (or part of, including the landscape
works) at close range from these receptors.
10.197 Other properties and settlements surrounding the Site and further afield, for example Westend,
Nupend, Chipmans Platt, Eastington and Claypits, and the remainder of the public highway and
PRoW network in the Study Area, including Eastington Footpath No.46 (Thames and Severn Way)
and Eastington Footpath No. 41 (near Westfield Bridge), will be affected visually to a moderate
or lesser degree, which is not significant in the EIA context.
10.198 No other visual receptors surrounding the Site are predicted to be affected to any significant
degree and the majority of receptors and people in the wider Study Area will be relatively
unaffected by the Revised Scheme. No significant visual effects are predicted to arise on the
Cotswold Way or any publicly accessible land such as commons, access land, National Trust
property, country parks and village greens.
10.199 A summary of likely significant effects of the Revised Scheme on the visual resource of the Site
and surrounding area is provided below in Table 10.8 based on the assessment describing the
magnitude of visual change and sensitivity of receptor provided at RS Appendix 10.4. It should
be noted that all visual receptors are assessed as high sensitivity except public highways which
are classified as low unless stated otherwise. A summary all visual effects (significant and non-
significant) is provided in Table 10.9 at the end of LVIA.
Table 10.8: Summary of Significant Effects on Visual Resource
Eco Park, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol.1 Main Text
December 2015
Page | 207
Effect Receptor Distanc
e (m)*
Sensiti
vity
Magnitu
de of
Visual
Effect
Level of
Adverse
Effect at
Year 1
Significant
or not?
Level of
Adverse
Residual
Effect (Yr
15)
Significant
or not?
Effect on
views
and
visual
amenity
Westend
House
11
(219)
High Medium Moderat
e / Major
Significant Moderate Not
Significant
Effect on
views
and
visual
amenity
Mole
Cottage
19
(97)
High Medium Moderat
e / Major
Significant Moderate Not
Significant
Effect on
views
and
visual
amenity
Ivy
Cottage
18
(133)
High Medium Moderat
e / Major
Significant Moderate Not
Significant
Effect on
views
and
visual
amenity
PRoW
Eastingto
n
Footpath
No.37
On-site High High Major Significant Major/
Moderate
Significant
Effect on
views
and
visual
amenity
PRoW
Eastingto
n
Footpath
No.38
On-site High High Major Significant Major /
Moderate
Significant
Effect on
views
and
visual
amenity
M5 10
(100)
Low High for
approx.
250m
Low
overall
Moderat
e / Major
for
approx.
250m
north of
J13
Minor
overall
Significant
for
approx.
250m
Not
significant
overall
Moderate
to
Moderate
/ Major for
approx.
250m
north of
J13
Minor
overall
Significant
for
approx.
250m
Not
significant
overall
Effect on
views
and
visual
amenity
A419 0
(100)
Low High
between
Chipman
s Platt &
J13
Low
overall
Moderat
e / Major
between
Chipman
s Platt &
J13
Minor
overall
Significant
between
Chipmans
Platt & J13
Not
significant
overall
Moderate
to
Moderate
/ Major
between
Chipman’s
Platt & J13
Significant
between
Chipmans
Platt & J13
Not
significant
overall
Eco Park, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol.1 Main Text
December 2015
Page | 208
Effect Receptor Distanc
e (m)*
Sensiti
vity
Magnitu
de of
Visual
Effect
Level of
Adverse
Effect at
Year 1
Significant
or not?
Level of
Adverse
Residual
Effect (Yr
15)
Significant
or not?
Minor
overall
* approximate distance from Redline Boundary (distance to Stadium in brackets)
Commentary on night time effects
10.200 The Revised Scheme will introduce some new lighting into the area adjacent to the A419 between
the M5 J13 and the existing / planned development including WOS on the ‘fringe’ of Stonehouse.
This will extend the existing pattern of lighting along the A419 corridor as far as the M5.
10.201 Within the Revised Scheme area there will be variable levels of lighting associated with the new
stadium building and a new lit section of the A419 and M5 J13, in addition to the lowest practical
level of lighting required for parking and access. The latter will include use of lighting in the car
parking area only when in use, with parking unlit when not required. No lighting is proposed for
the practice pitches.
10.202 The lit elements will be set within the proposed framework of retained vegetation and newly
planted green spaces (refer RS Appendix 5.1 Revised Indicative Concept Plan, RS Figure 1.1
Indicative Concept Plan and RS Figure 5.3 Indicative Green Infrastructure Parameter Plan)
which will break up the light sources to create a mosaic of lighter and darker areas including dark
corridors for nature conservation.
10.203 The development as a whole is predicted to cause a localised increase in illumination in the
evening on match nights in winter months experienced in the context of existing / planned
development in the surrounding area including WOS. Lighting associated with the Revised
Scheme will be most readily perceptible in close / localised views – particularly in the vicinity of
Westend, Chipmans Platt and Nupend (western edge). The proposed bunds / screen planting
incorporating ‘dark bat corridors’ will limit both visual and light intrusion / spillage at adjacent
properties, such as those at Westend, and other visual receptors. More detail is provided in
Chapter 14 Lighting which assesses the ‘worst case scenario’ luminous intensity on neighbouring
properties as negligible and light intrusion (spill) as minor adverse. The latter is also below
industry guidelines, prior to the consideration and application of further mitigation measures. In
addition, building lighting will be switched off at night and accompanying sensitive design
measures will further control and minimise potential light pollution. These matters can be
secured by means of appropriate planning conditions.
10.204 Regarding the wider Study Area and medium to long range views, the predicted lighting effects
will relate to visibility of light sources and ‘sky glow’ as described in Chapter 14. Lighting
associated with all aspects of Revised Scheme will be seen in the context of existing lighting in
the surrounding area, as identified above and shown in RS Figures 10.10 (a-c) and RS Figure
10.13. From the AONB the most notable source of new light will be the occasional floodlighting
of the stadium. However, the use of floodlighting will be limited and only needed on certain
Eco Park, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol.1 Main Text
December 2015
Page | 209
evenings. All lighting will utilise downwards / directional lighting to minimise spill and light
pollution.
10.205 Commentary regarding the potential effect on landscape character at night time is provided in
RS Appendix 10.2 where the localised increase in illumination predicted in Chapter 14 is assessed
in the context of existing lighting sources described above and shown on RS Figures 10.10(a-c).
As a separate topic, a commentary on the cumulative landscape effects of lighting, particularly
in relation to the WOS development, is provided below, and in RS Appendix 10.5 Cumulative
Assessment Schedules.
10.206 Overall, whilst the Revised Scheme will introduce new forms of lighting visible from the
surrounding area, including from parts of the Cotswold AONB escarpment and foothills, it will be
viewed in the context of the relatively high levels of existing background lighting. These include
Stonehouse (and in the near future the now consented WOS), the M5, as well as a variety of
other significant local light sources. In addition, the Revised Scheme will be seen beyond existing
sources of significant lighting such as Dairy Crest (refer RS Figure 10.10c). The existing night time
environment is illustrated in RS Figure 10.13– see Viewpoint 9 Cotswold Way at Maiden Hill for
a representative view of the current night time environment and context of the Site as
experienced from one of the closest, elevated parts of the Cotswolds AONB. Further information
on lighting in respect to the Cotswolds AONB is also provided at RS Appendix 10.6 Cotswolds
AONB Position Statements.
10.207 It is important to note, as the night time photograph from Viewpoint 9 illustrates, that the
Revised Scheme lighting will be experienced in the context of the existing pattern of lit
development and transport corridors (refer RS Figure 10.10 (a-b)). It will avoid impinging on the
darker areas surrounding the Site and in the wider Study Area, helping to keep them free from
light pollution, including the fringes of the AONB as well as within the designated area itself.
Cumulative Effects
Introduction
10.208 The Cumulative Landscape and Visual Impact Assessment (CLVIA) deals with the potential
‘additional’ effect on the landscape and visual resource of the Study Area attributable to the
Revised Scheme when considered in combination with other existing and proposed
developments of a similar type and scale. Cumulative effects are understood to be the additional
effects which arise over and above those which are likely to result from the Revised Scheme
considered on its own.
Scope of Cumulative Assessment
10.209 The CLVIA considers significant existing and planned development (i.e. validated planning
applications and schemes at appeal) in the Study Area – the cumulative schemes. Also included
is the CCT Phase1b Proposals for restoration of the Stroudwater Canal, currently at the pre-
planning stage (refer RS Figure 18.1 Cumulative Schemes No.9 ‘Indicative Canal Realignment’).
10.210 Ten cumulative schemes situated in the Study Area which have the potential to cause cumulative
landscape and visual effects are included in the cumulative assessment as listed in Chapter 2,
Table 2.5. Cumulative effects generally are described in Chapter 18 Cumulative Effects which
Eco Park, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol.1 Main Text
December 2015
Page | 210
includes RS Figure 18.1 showing the location of the cumulative schemes in the Study Area. More
information on the distribution of cumulative schemes is provided in RS Appendix 10.9a Extract
of Stroud District Local Plan 2015 Proposals Map – Map 1.
Approach to Cumulative Assessment
10.211 The CLVIA identifies the ‘combined’ and ‘sequential’ effect of the Revised Scheme in conjunction
with the cumulative schemes and describes a) the potential cumulative landscape character
effects for individual character units relating to the various levels of LCA; and b) the potential
cumulative effects on views and visual amenity assessed from the representative viewpoints. The
likely cumulative effects arising during the construction and operational phases are considered,
with a distinction made between the effects at Year 1 of operation and Year 15 following
establishment and maturing of the proposed landscape mitigation – the residual cumulative
effect.
10.212 The mitigation measures that have been embedded into the design in order to avoid, reduce and
/ or offset potentially significant adverse landscape and visual effects, including cumulative
effects, include landscape works described in RS Appendix 10.7 and RS Figures 10.11c and
10.11d. These landscape measures, for example the proposed planted bund separating the
development from Westend / Grove Lane, will take time to establish and mature. Therefore, as
a rule of thumb, it is assumed that the proposed embedded landscape mitigation will not become
fully effective until Year 15 of operation, the point at which residual effects are predicted.
10.213 The methodology used to carry out the CLVIA is based on current guidance contained in GLVIA3,
informed by professional experience and judgement, as set out in RS Appendix 10.1. The CLVIA
is structured as follows:
• Cumulative Landscape Effects;
• Cumulative Visual Effects.
10.214 The following figures are provided in Volume 2 in support of the CLVIA:
• RS Figure 10.12a Cumulative Schemes and Landscape Character (SDC and National);
• RS Figure 10.12b Cumulative Schemes and Landscape Character (Gloucestershire and
Cotswolds AONB);
• RS Figure 10.12c Cumulative Schemes and Viewpoint Location with Revised Scheme ZTV.
10.215 A full assessment of cumulative effects is presented in RS Appendix 10.5 Cumulative Assessment
Schedules.
10.216 A summary of the significant adverse cumulative effects likely to arise during construction and
operation of the Revised Scheme, as set out below.
Cumulative Effects on Landscape
10.217 There will be no significant (and negligible non-significant) additional cumulative effects on the
landscape fabric of the Site, either during construction or operation.
Eco Park, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol.1 Main Text
December 2015
Page | 211
Regarding landscape character the West of Stonehouse (WOS) and Pike Lock cumulative schemes
have potential to generate significant adverse cumulative effects in conjunction with the Revised
Scheme due to their proximity to the Development Footprint. The other cumulative schemes
including Javelin Park, Bond's Mill Unit 27, Former Standish and Westridge Hospital Standish, and
Land Adjoining Station Road are located too far away from the Site to cause significant adverse
cumulative landscape effects. Westend Courtyard is of a type and scale, and configured in such
a way, so as to prevent adverse cumulative landscape effects from arising in conjunction with
the Revised Scheme. A full cumulative assessment is provided in RS Appendix 10.5.
10.218 The WOS scheme is a large scale mixed development (housing and employment) proposed on
land north of the A419 in the vicinity of Nastend, situated between Stonehouse and Chipmans
Platt. The employment uses will be located adjacent to Stonehouse (Oldends) and the mainline
railway whilst housing, open space and recreation uses will occupy the remainder of the WOS
site as far Chipmans Platt, Grove Lane and Westend. Pike Lock is a proposed three storey hotel
and restaurant development located east of Chipmans Platt roundabout, south of the A419.
10.219 The Revised Scheme on its own is predicted to significantly change the character of the
Development Footprint and immediate adjacent landscape falling within SDC’s LCT5 Rolling
Agricultural Plain (incorporating the LCT5a Escarpment Footslopes to the north, and LCT5b
Lowland Plain to the south), up to a distance of approximately 250m from the Development
Footprint, where uninterrupted views of the proposal exist.
10.220 It is anticipated that, when completed, the WOS development will have a similar to slightly
greater sphere of influence locally character wise (250-500m). A significant, moderate to
moderate / major, adverse residual cumulative effect on landscape character attributable to
the proposal is predicted in conjunction with WOS and Pike Lock within approximately 500m
of the Development Footprint, occurring in the Grove Lane area between Chipmans Platt and
Westend. This will be the result of a medium to high magnitude of cumulative landscape effect
during construction on the medium to high sensitivity Escarpment Footslopes (LCT5a), as shown
in RS Figure 10.8b, reducing to medium magnitude in the longer term (Year 15).
10.221 Regarding the medium sensitivity Lowland Plain (LCT5b), as the proposed landscape mitigation
establishes and matures during operation, the initial significant adverse cumulative effect arising
in combination with WOS will reduce to moderate and become a not significant adverse residual
effect by Year 15. The same level of not significant residual cumulative landscape effect would
apply in respect of SV6A Vale of Berkeley (Gloucestershire Landscape Assessment 2006). It
should be noted that the predicted significant cumulative landscape effects will be localised and
limited.
10.222 A broadly similar extent and levels (or slightly lower) of adverse cumulative landscape character
effect will apply in respect of the corresponding SALA landscape units (low / medium, medium
and high / medium sensitivity), both on and adjacent to the Site (Development Footprint), as
shown on RS Figure 10.8a. It is important to also consult RS Figure 10.5d which is provided to
help understand the relationship between the various levels of LCA, from the local IHCA and SDC
LCAs through to the national level NCAs.
Cumulative Effects on Visual Amenity
Eco Park, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol.1 Main Text
December 2015
Page | 212
10.223 Significant adverse cumulative visual effects are predicted to arise during construction and
Year 1 of operation of the Revised Scheme, in conjunction with the WOS and Pike Lock
cumulative schemes, in the vicinity of Grove Lane / Westend / Chipmans Platt, up to a distance
of approximately 500m from the Development Footprint. These effects will result from a medium
magnitude of visual change when the Revised Scheme is visible in combination or sequentially
with WOS and Pike Lock from certain medium and high sensitivity visual receptors within
approximately 500m of the Site, for example PRoW EEA23 in the vicinity of Westend / Nupend
where moderate / major sequential cumulative visual effects are predicted as recorded in
relation to Viewpoint 6 at RS Appendix 10.5.
10.224 Localised, moderate / major, significant adverse cumulative visual effects are also likely to be
experienced by users of footpaths north of Eastington (see Viewpoint 8) during construction.
This temporary, short term effects would be attributable mainly to the proximity and strong
visual presence of the Land adjacent to Eastington Trading Estate and the proposed Stroudwater
Indicative Canal Realignment cumulative schemes, seen in conjunction with the Revised Scheme,
WOS and Pike Lock.
10.225 Upon commencement of operation, the embedded landscape mitigation having been
implemented, levels of adverse cumulative effects on views and visual amenity occurring
initially during construction (in combination and sequentially) in conjunction with the various
cumulative schemes (particularly WOS and Pike Lock) will be moderate or less and not
significant in the medium to longer term. No additional, significant adverse cumulative visual
effects are predicted elsewhere in the Study Area attributable to the Revised Scheme when
considered in combination with the other cumulative schemes listed in RS Figure 18.1, for
instance at the representative viewpoints shown on RS Figure 10.12c.
10.226 Other cumulative schemes such as Javelin Park, Bond's Mill Unit 27, Former Standish and
Westridge Hospital Standish, and Land Adjoining Station Road and are located too far away from
the Site to give rise to significant adverse cumulative visual effects, or are of such type and scale
and / or configured in such a way (for instance Westend Courtyard) so as to prevent or minimise
adverse cumulative visual effects.
Conclusion on Residual Cumulative Effects
10.227 Significant additional, adverse cumulative landscape and visual effects attributable to the
Revised Scheme are predicted to arise during construction up to Year 1 of operation within
approximately 0.5km of the Development Footprint in the general vicinity of Grove Lane from
Westend to Chipmans Platt. These short term, additional cumulative effects will result from the
combined and sequential visibility of the proposal in conjunction with WOS and Pike Lock
cumulative schemes.
10.228 The adverse cumulative effects will reduce over time as the proposed landscape mitigation
establishes and matures. Significant additional, adverse residual cumulative landscape
character effects are predicted to remain during operation with respect to a small area of the
Escarpment Footslopes (LCT5a) on and adjacent to the Development Footprint. However, other
cumulative landscape and visual effects predicted to be significant during construction will be
not significant during operation in the medium to long term.
Eco Park, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol.1 Main Text
December 2015
Page | 213
10.229 Adverse cumulative effects potentially arising across the wider Study Area potentially arising in
conjunction with these and other cumulative schemes assessed and shown in RS Figure 18.1 are
predicted to be not significant.
Overall Conclusions
10.230 The Revised Scheme is predicted to have a significant adverse effect during construction and
operation on a small area of landscape and a limited number of visual receptors located on
and/ or immediately surrounding the Site within approximately 250m (up to 500m for
cumulative landscape effects) of the Development Footprint. Receptors predicted to be so
affected in the longer term comprise primarily a small portion of the Rolling Agricultural Plain
(LCT5 incorporating LCT5a Escarpment Footslopes and LCT5b Lowland Plain), onsite footpaths
EEA 37 and 38, and short stretches of the A419 and M5 (including Grove Lane overbridge)
adjacent the Development Footprint.
10.231 Due to the sensitive siting and design of the Revised Scheme the predicted residual significant
adverse residual effects will be localised and will not attain levels that might compromise local
landscape character or visual amenity, or prevent local residents and the public from enjoying
the landscape and visual environment. In addition, adverse effects will be ameliorated over time
as the proposed embedded landscape mitigation matures and the Revised Scheme becomes
assimilated into the landscape.
10.232 The new stadium will be placed within a sensitively designed ‘parkland’ setting so that local
landscape character and visual amenity is preserved as far as possible and potentially enhanced
in the longer term. The Revised Scheme has been rigorously designed and configured to ensure
that none of the significant adverse visual effects predicted to occur initially in relation to
residential amenity can be reasonably judged as unacceptable in terms of the public interest test.
No significant adverse effects are predicted to arise on the Cotswolds AONB and its setting, or
the Cotswold Way. In addition, the Thames and Severn Way will not be subject to any significant
residual adverse effects.
10.233 It is important not to overlook the care that has been taken in the design of the Revised Scheme
in order to respect the existing landscape and visual context. The design objective has been to
create an exciting stadium building set in attractive grounds that will provide a positive landscape
experience for visitors and passers-by, whilst at the same time integrating as seamlessly as
possible into its rural surroundings. This design rationale is central to the landscape mitigation
embedded within the Revised Scheme. The intention is to present the new stadium as a
memorable landmark feature in a ‘parkland’ setting at a ‘gateway’ location in a way that avoids
and minimises adverse effects as far as possible, while maximising the longer term benefit it
offers to Stroud District’s landscape and visual environment.
Eco Park, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol.1 Main Text
December 2015
Page | 214
Table 10.9: Summary of Landscape and Visual Effects and Mitigation
*Significant effects are highlighted in bold.
** Predicted effects are assessed as adverse (negative) unless stated otherwise, for example where they will be beneficial (positive), or both adverse
and beneficial, for instance in cases where embedded mitigation (such as new planting) increasingly provides landscape and visual benefit over time.
Development Phase
O = Operational C = Construction
Nature of Effects
Short Term = S/T Medium Term = M/T Long term = L/T
Permanent = P Temporary = T
Direct = D Indirect = I
Receptor Effect Phase
(Construction /
Operation)
Sensitivity of
Receptor
Magnitude of
Change (Year
1)
Level of
Adverse Effect
and
Significance* in
Year 1,
including
embedded
mitigation
Mitigation
(Embedded)
Enhancement Level of
Residual
Adverse
Effect** (and
Significance) in
Year 15 with
embedded
mitigation
Nature of effect
(short, medium
or long term;
permanent or
temporary;
direct and / or
indirect)
Landscape Effects
Site Landscape
Fabric
(Landform)
Physical effects
on landscape
fabric
C & O Low to Medium Low / Medium Minor /
Moderate
See RS Figure
5.6 and TBC Site
Levels.
See RS Figure
5.6 and TBC Site
Levels.
Minor /
Moderate
L/T, P, D
Site Landscape
Fabric
(Vegetation &
Boundary
Features)
Physical effects
on landscape
fabric
C & O Low to Medium Medium / High Moderate /
Major to
Moderate
(Significant)
See RS Figures
5.3, 10.11c &
10.11d and RS
Appendix 10.7.
See RS Figures
5.3, 10.11c &
10.11d and RS
Appendix 10.7.
Moderate /
Minor to Minor
/ moderate
(Not Significant)
S/T, M/T & L/T,
P & T, D
Site Landscape
Fabric (Built
structures -
Barns)
Physical effects
on landscape
fabric
C & O Low None None N/A N/A N/A N/A
Eco Park, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol.1 Main Text
December 2015
Page | 215
Site Landscape
Fabric (Built
Structures –
Westfield
Bridge)
Physical effects
on landscape
fabric
C & O High None None N/A N/A N/A N/A
Site Landscape
Fabric (PRoW)
Physical effects
on landscape
fabric
C & O High Medium / High Major /
Moderate
(Significant)
See RS Figures
5.3, 10.11c &
10.11d and RS
Appendix 10.7.
See RS Figures
5.3, 10.11c &
10.11d and RS
Appendix 10.7.
Moderate
(Not Significant)
S/T & L/T, P & T,
D
NCA 106:
Severn and
Avon Vales
Effect on
landscape
character /
value
C & O Medium Negligible Minor /
Negligible
See RS Appendix
10.3
See RS Appendix
10.3
Minor /
Negligible
S/T & L/T, P &
T, D & I
NCA 107:
Cotswolds
Effect on
landscape
character /
value
C & O Medium to High Negligible Minor to Minor
/ Negligible
See RS Appendix
10.3
See RS Appendix
10.3
Minor /
Negligible
S/T & L/T, P &
T, I
LCT SV6 Settled
Unwooded
Vale, LCA SV6A
Vale of Berkeley
Effect on
landscape
character /
value
C & O Medium High up to
250m from
Development
Footprint
Medium / Low
beyond 250m
Major /
Moderate
up to
approximately
250m from
Development
Footprint
Moderate /
Minor or less
beyond 250m
(Significant
within 250m)
See RS Appendix
10.3
See RS Appendix
10.3
Moderate /
Major up to
Approximately
250m from
Development
Footprint
Minor /
Moderate or
less beyond
250m
(Significant
within 250m)
S/T & L/T, P & T,
D & I
LCT SV2 Drained
Riverine
Farmland and
Effect on
landscape
C & O Medium Negligible Minor /
Negligible
N/A N/A Minor /
Negligible
S/T & L/T, P &
T, I
Eco Park, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol.1 Main Text
December 2015
Page | 216
Grazed Salt
Marsh / LCA
SV2B Slimbridge
and New
Grounds
Marshes
character /
value
LCT SV11 Vale
Hillocks / LCA
SV11A Overton
and Barrow Hill
Effect on
landscape
character /
value
C & O Medium Negligible Minor /
Negligible
N/A N/A Minor /
Negligible
S/T & L/T, P &
T, I
Escarpment
Footslopes
(Stroud No 5A)
Effect on
landscape
character /
value
C & O Medium to High High up to
250m from
Development
Footprint
Medium / Low
beyond 250m
Major /
Moderate to
Major
up to 250m
from
Development
Footprint
Moderate to
Moderate /
Minor
or less beyond
250m
(Significant
within 250m)
See RS Figures
5.3, 10.11c &
10.11d and RS
Appendices 10.3
& 10.7.
See RS Figures
5.3, 10.11c &
10.11d and RS
Appendices 10.3
& 10.7
Moderate /
Major up to
250m from
Development
Footprint
Moderate /
Minor or less
beyond
250m
(Significant
within 250m)
S/T & L/T, P &
T, D & I
Lowland Plain
(Stroud No 5B)
Effect on
landscape
character /
value
C & O Medium High up to
250m from
Development
Footprint
Medium /
Low beyond
250m
Major /
Moderate
up to 250m
from
Development
Footprint
See RS Figures
5.3, 10.11c &
10.11d and RS
Appendices 10.3
& 10.7.
See RS Figures
5.3, 10.11c &
10.11d and RS
Appendices 10.3
& 10.7.
Moderate to
Moderate /
Major up
to 250m from
Development
Footprint
S/T & L/T, P &
T, D & I
Eco Park, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol.1 Main Text
December 2015
Page | 217
Moderate /
Minor
or less beyond
250m
(Significant
within 250m)
Minor /
Moderate or
less
beyond
250m
(Significant
within 250m)
Frome River
Valley (Stroud
No 5C)
Effect on
landscape
character / value
C & O Medium to High Negligible within
250m and
elsewhere
Minor to Minor
/ Negligible
within 250m
and elsewhere
See RS Appendix
10.3
See RS Appendix
10.3
Minor to Minor /
Negligible within
250m and
elsewhere
S/T & L/T, P & T,
I
Wold Tops
(Stroud No. 1)
Effect on
landscape
character /
value
C & O High Negligible Minor N/A N/A Minor S/T & L/T, P & T,
I
Secluded
Valleys (Stroud
No. 3)
Effect on
landscape
character /
value
C & O High Negligible Minor N/A N/A Minor S/T & L/T, P & T,
I
Escarpment
(Stroud No. 4)
Effect on
landscape
character /
value
C & O High Low Moderate /
Minor
See RS Figures
5.3, 10.11c &
10.11d and RS
Appendices 10.3
& 10.7.
See RS Figures
5.3, 10.11c &
10.11d and RS
Appendices 10.3
& 10.7.
Minor /
Moderate
S/T & L/T, P & T,
I
Severn Vale
Grazing
Marshes
(Stroud No.8)
Effect on
landscape
character /
value
C & O Medium Negligible Minor /
Negligible
N/A N/A Minor /
Negligible
S/T & L/T, P & T,
I
Severn Vale
Hillocks (Stroud
No.7)
Effect on
landscape
character /
value
C & O Medium Negligible Minor /
Negligible
N/A N/A Minor /
Negligible
S/T & L/T, P &
T, I
Eco Park, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol.1 Main Text
December 2015
Page | 218
Escarpment
Outlier / Cam
Longdown,
Peaked Down
and Downham
Hill (Cotswolds
No.1A).
Effect on
landscape
character /
value
C & O High Negligible Minor See RS Figures
5.3, 10.11c &
10.11d and RS
Appendices 10.3
& 10.7.
See RS Figures
5.3, 10.11c &
10.11d and RS
Appendices 10.3
& 10.7.
Minor S/T & L/T, P & T,
I
Escarpment /
Uley to Coopers
Hill (Cotswolds
No. 2C)
Effect on
landscape
character /
value
C & O High Low Moderate /
Minor
See RS Figures
5.3, 10.11c &
10.11d and RS
Appendices 10.3
& 10.7.
See RS Figures
5.3, 10.11c &
10.11d and RS
Appendices 10.3
& 10.7.
Minor /
Moderate
S/T & L/T, P & T,
I
Rolling Hills and
Valleys /
Stinchcombe
and North
Nibley
(Cotswolds
No.3B).
Effect on
landscape
character /
value
C & O High Negligible Minor N/A N/A Minor S/T & L/T, P & T,
I
High Wold /
Nympsfield and
Kingscote
Plateau
&Minchinhamp
ton Common.
Rodborough
and Amberley
Common
(Cotswolds No.
7A)
Effect on
landscape
character /
value
C & O High Negligible Minor See RS Figures
5.3, 10.11c &
10.11d and RS
Appendices 10.3
& 10.7.
See RS Figures
5.3, 10.11c &
10.11d and RS
Appendices 10.3
& 10.7.
Minor S/T & L/T, P & T,
I
Settled
Unwooded Vale
/ Vale of
Gloucester
Fringe
(Cotswolds
No.18A)
Effect on
landscape
character /
value
C & O High Low Moderate /
Minor
See RS Figures
5.3, 10.11c &
10.11d and RS
Appendices 10.3
& 10.7.
See RS Figures
5.3, 10.11c &
10.11d and RS
Appendices 10.3
& 10.7.
Minor /
Moderate
S/T & L/T, P & T,
I
Eco Park, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol.1 Main Text
December 2015
Page | 219
LCT 1
Stroud-water
settlement (Part
1.2)
Effect on
landscape
character /
value
C & O Medium to High Negligible on
western edge
and elsewhere
Minor to Minor
/ Negligible on
western edge
and elsewhere
See RS Appendix
10.3
See RS Appendix
10.3
Minor to Minor
/ Negligible
S/T & L/T, P & T,
I
LCT 4
Green Corridor:
Rural Frome
Vale
(Part 4.4)
Effect on
landscape
character /
value
C & O Medium to High Negligible within
250m and
elsewhere
Minor to Minor
/ Negligible
within 250m
and elsewhere
See RS Appendix
10.3
See RS Appendix
10.3
Minor to Minor
/ Negligible
S/T & L/T, P & T,
I
LCT 7
Meadow Mill
(Part 7.1)
Effect on
landscape
character /
value
C & O Medium to High Negligible Minor to Minor
/ Negligible
See RS Appendix
10.3
See RS Appendix
10.3
Minor to Minor
/ Negligible
S/T & L/T, P & T,
I
LCT 2
Core Vale
Settlement East
of Eastington
(Part 2.2)
Effect on
landscape
character /
value
C & O Medium to High Negligible Minor to Minor
/ Negligible
See RS Appendix
10.3
See RS Appendix
10.3
Minor to Minor
/ Negligible
S/T & L/T, P & T,
I
Cotswolds
AONB
Effect on
landscape
character /
value
C & O High Low reducing to
Negligible
Moderate /
Minor reducing
to Minor
See RS Figures
5.3, 10.11c &
10.11d and RS
Appendices 10.3
& 10.7.
See RS Figures
5.3, 10.11c &
10.11d and RS
Appendices 10.3
& 10.7.
Minor /
Moderate
reducing to
Minor
S/T & L/T, P & T,
I
Frampton Court
Registered Park
and Gardens
Effect on
landscape
character /
value
C & O High Negligible Minor N/A N/A Minor S/T & L/T, P & T,
I
Visual Effects
Viewpoint 1.
A419 at M5
Junction 13
Effect on views
and visual
amenity
C & O Low Medium to Low Minor /
Moderate
See RS Figures
5.3, 10.11c &
10.11d and RS
Appendices 10.4
& 10.7.
See RS Figures
5.3, 10.11c &
10.11d and RS
Appendices 10.4
& 10.7.
Minor S/T & L/T, P & T,
D
Eco Park, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol.1 Main Text
December 2015
Page | 220
Viewpoint 2.
Footpath at
Westfield
Bridge
Effect on views
and visual
amenity
C & O High Low Moderate /
Minor
See RS Appendix
10.4
See RS Appendix
10.4
Moderate /
Minor
S/T & L/T, P & T,
D
Viewpoint 3.
Footpath east
of Westend
Effect on views
and visual
amenity
C & O High Low Moderate /
Minor
See RS Figures
5.3, 10.11c &
10.11d and RS
Appendices 10.4
& 10.7.
See RS Figures
5.3, 10.11c &
10.11d and RS
Appendices 10.4
& 10.7.
Minor /
Moderate
S/T & L/T, P & T,
D
Viewpoint 4.
A419 at
Chipmans Platt
roundabout
Effect on views
and visual
amenity
C & O Low Medium to Low Minor /
Moderate
See RS Figures
5.3, 10.11c &
10.11d and RS
Appendices 10.4
& 10.7.
See RS Figures
5.3, 10.11c &
10.11d and RS
Appendices 10.4
& 10.7.
Minor S/T & L/T, P & T,
D
5. Viewpoint
Thames and
Severn Way
east of M5
Effect on views
and visual
amenity
C & O High Low / Negligible Minor /
Moderate
See RS Appendix
10.4
See RS Appendix
10.4
Minor /
Moderate
S/T & L/T, P & T,
D
6. Viewpoint
Footpath West
of Nupend
Effect on views
and visual
amenity
C & O High Medium to Low Moderate
See RS Figures
5.3, 10.11c &
10.11d and RS
Appendices 10.4
& 10.7.
See RS Figures
5.3, 10.11c &
10.11d and RS
Appendices 10.4
& 10.7.
Moderate to
Moderate /
Minor
S/T & L/T, P & T,
D
7. Viewpoint
Grove Lane M5
over bridge
Effect on views
and visual
amenity
C & O Medium Medium to High Moderate /
Major
(Significant)
See RS Figures
5.3, 10.11c &
10.11d and RS
Appendices 10.4
& 10.7.
See RS Figures
5.3, 10.11c &
10.11d and RS
Appendices 10.4
& 10.7.
Moderate to
Moderate /
Major
(Adverse and
Beneficial)
(Significant)
S/T & L/T, P & T,
D
8. Viewpoint
Footpath north
of Eastington
Effect on views
and visual
amenity
C & O High Low Moderate /
Minor
See RS Figures
5.3, 10.11c &
10.11d and RS
Appendices 10.4
& 10.7.
See RS Figures
5.3, 10.11c &
10.11d and RS
Appendices 10.4
& 10.7.
Moderate /
Minor
S/T & L/T, P & T,
D
Eco Park, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol.1 Main Text
December 2015
Page | 221
9. Viewpoint
Maiden Hill
(Cotswold Way)
Effect on views
and visual
amenity
C & O High Low Moderate /
Minor
See RS Figures
5.3, 10.11c &
10.11d and RS
Appendices 10.4
& 10.7.
See RS Figures
5.3, 10.11c &
10.11d and RS
Appendices 10.4
& 10.7.
Minor /
Moderate
S/T & L/T, P & T,
D
10. Viewpoint
Haresfield Hill
(Cotswold Way)
Effect on views
and visual
amenity
C & O High Low Moderate /
Minor
See RS Figures
5.3, 10.11c &
10.11d and RS
Appendices 10.4
& 10.7.
See RS Figures
5.3, 10.11c &
10.11d and RS
Appendices 10.4
& 10.7.
Minor /
Moderate
S/T & L/T, P & T,
D
11. Viewpoint
Selsey Common
(Cotswold Way)
Effect on views
and visual
amenity
C & O High Low to
Negligible
Minor /
Moderate
See RS Appendix
10.4
N/A Minor S/T & L/T, P & T,
D
12. Viewpoint
Cam Long Down
(Cotswold Way)
Effect on views
and visual
amenity
C & O High Negligible Minor See RS Appendix
10.4
N/A Minor S/T & L/T, P & T,
D
13. Viewpoint
A38 at Claypits
Effect on views
and visual
amenity
C & O High for
property
Low for road
users
Low for
property
Negligible for
road users
Moderate /
Minor for
property
Minor /
Negligible for
road users
See RS Appendix
10.4
See RS Appendix
10.4
Minor /
Moderate for
property
Negligible for
road users
S/T & L/T, P & T,
D
14. Viewpoint
A38 / Thames
and Severn Way
intersection
Effect on views
and visual
amenity
C & O High for PRoW
Low for Road
Users
Negligible Minor for
property /
PRoW
Negligible for
road users
N/A N/A Minor for
property /
PRoW
Negligible for
road users
S/T & L/T, P & T,
D
15 Viewpoint
Footpath at
Doverow Hill
Effect on views
and visual
amenity
C & O High Low Moderate /
Minor
See RS Figures
5.3, 10.11c &
10.11d and RS
Appendices 10.4
& 10.7.
See RS Figures
5.3, 10.11c &
10.11d and RS
Appendices 10.4
& 10.7.
Minor /
Moderate
S/T & L/T, P & T,
D
16. Footpath
west of West
Effect on views
and visual
amenity
C & O High High to Medium Major /
Moderate
See RS Figures
5.3, 10.11c &
10.11d and RS
See RS Figures
5.3, 10.11c &
10.11d and RS
Moderate /
Major (Adverse
& Beneficial
S/T & L/T, P & T,
D
Eco Park, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol.1 Main Text
December 2015
Page | 222
End Cross (EEA
38)
(Significant) Appendices 10.4
& 10.7.
Appendices 10.4
& 10.7.
(Significant)
A. St Micheal
and Angels
Church
Effect on views
and visual
amenity
C & O High Negligible Minor See RS Appendix
10.4
See RS Appendix
10.4
Minor S/T & L/T, P & T,
D
D. A38
Whitminster
Ridge
Effect on views
and visual
amenity
C & O Low Low / Negligible Minor /
Negligible
See RS Appendix
10.4
See RS Appendix
10.4
Minor /
Negligible
S/T & L/T, P & T,
D
E. Barrow Hill Effect on views
and visual
amenity
C & O High Low / Negligible Minor /
Moderate
See RS Appendix
10.4
See RS Appendix
10.4
Minor S/T & L/T, P & T,
D
F. Little Dean,
Forest of Dean
Effect on views
and visual
amenity
C & O High Negligible Minor See RS Appendix
10.4
See RS Appendix
10.4
Minor S/T & L/T, P & T,
D
G. Field Lane,
Cam
Effect on views
and visual
amenity
C & O High Negligible Minor See RS Appendix
10.4
See RS Appendix
10.4
Minor S/T & L/T, P & T,
D
H. Frocester Hill Effect on views
and visual
amenity
C & O High Low / Negligible Minor /
Moderate
See RS Appendix
10.4
See RS Appendix
10.4
Minor S/T & L/T, P & T,
D
Residential
Properties (15
Properties)
1-6 Chimans
Platt & William
Morris College
(WMC), The
Old Chapel
House,
Sunnycroft, 1-4
West End
Cottages,
Mulgrove,
Westend Farm
Effect on views
and visual
amenity
C & O High Low Moderate /
Minor
See RS Appendix
10.4
See RS Appendix
10.4
Moderate /
Minor
To Minor /
Moderate
S/T & L/T, P & T,
D
Eco Park, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol.1 Main Text
December 2015
Page | 223
Residential
Properties (4
Properties)
Beech House, 1-
2 Cressignton
Cottages,
Whitminster
Court
Effect on views
and visual
amenity
C & O High Low / Negligible Minor /
Moderate
See RS Figures
5.3, 10.11c &
10.11d and RS
Appendices 10.4
& 10.7.
See also ES
Figure 5.6.
See RS Figures
5.3, 10.11c &
10.11d and RS
Appendices 10.4
& 10.7.
See also ES
Figure 5.6.
Minor /
Moderate
S/T & L/T, P & T,
D
Residential
Properties (11
Properties)
Bridle Path
Cottage, Rose
Cottage, Half
Acres, Elmcote,
Hill Crest,
Nupend Farm,
Nupend Court,
Sundial,
Nestings,
Rosetree,
Budloe)
Effect on views
and visual
amenity
C & O High Negligible Minor See RS Figures
5.3, 10.11c &
10.11d and RS
Appendices 10.4
& 10.7.
See also ES
Figure 5.6.
See RS Figures
5.3, 10.11c &
10.11d and RS
Appendices 10.4
& 10.7.
See also ES
Figure 5.6.
Minor S/T & L/T, P & T,
D
Residential
Properties (6
Properties)
Yew Tree Villa,
St Loy Cottage,
Paradise, Yew
Tree Cottage,
Effect on views
and visual
amenity
C & O High Medium / Low Moderate
See RS Figures
5.3, 10.11c &
10.11d and RS
Appendices 10.4
& 10.7.
See also ES
Figure 5.6.
See RS Figures
5.3, 10.11c &
10.11d and RS
Appendices 10.4
& 10.7.
See also ES
Figure 5.6.
Moderate to
Moderate /
Minor
S/T & L/T, P & T,
D
Eco Park, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol.1 Main Text
December 2015
Page | 224
Grove Farm ,
Oakdene)
Residential
Property
Westend House
Effect on views
and visual
amenity
C & O High Medium Moderate /
Major
(Significant)
See RS Figures
5.3, 10.11c &
10.11d and RS
Appendices 10.4
& 10.7.
See also ES
Figure 5.6.
See RS Figures
5.3, 10.11c &
10.11d and RS
Appendices 10.4
& 10.7.
See also ES
Figure 5.6.
Moderate
(Not Significant)
S/T & L/T, P & T,
D
Residential
Properties (2
Properties)
Ivy Cottage,
Mole Cottage
Effect on views
and visual
amenity
C & O High Medium Moderate /
Major
(Significant)
See RS Figures
5.3, 10.11c &
10.11d and RS
Appendices 10.4
& 10.7.
See also ES
Figure 5.6.
See RS Figures
5.3, 10.11c &
10.11d and RS
Appendices 10.4
& 10.7.
See also ES
Figure 5.6.
Moderate
(Not Significant)
S/T & L/T, P & T,
D
Fromebridge
Cluster of
properties
Effect on views
and visual
amenity
C & O High Negligible Minor N/A N/A Minor S/T & L/T, P & T,
D
Claypits cluster
of properties
Effect on views
and visual
amenity
C & O High Low for fringe
properties
Low / Negligible
elsewhere
Moderate /
Minor for fringe
properties
Minor /
Moderate
elsewhere
See RS Figures
5.3, 10.11c &
10.11d and RS
Appendices 10.4
& 10.7
See RS Figures
5.3, 10.11c &
10.11d and RS
Appendices 10.4
& 10.7
Minor /
Moderate for
fringe
properties
Minor
elsewhere
S/T & L/T, P & T,
D
Westend
settlement
Effect on views
and visual
amenity
C & O High Medium to Low
(or less) for
settlement
overall.
Moderate (or
less) for
settlement
overall
See RS Figures
5.3, 10.11c &
10.11d and RS
Appendices 10.4
& 10.7
See RS Figures
5.3, 10.11c &
10.11d and RS
Appendices 10.4
& 10.7
Moderate /
Minor (or less)
for settlement
overall
S/T & L/T, P & T,
D
Eco Park, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol.1 Main Text
December 2015
Page | 225
Whitminster
settlement
Effect on views
and visual
amenity
C & O High Negligible Minor N/A N/A Minor S/T & L/T, P & T,
D
Eastington
settlement
Effect on views
and visual
amenity
C & O High Low / Negligible Minor /
Moderate
See RS Figures
5.3, 10.11c &
10.11d and RS
Appendices 10.4
& 10.7
See RS Figures
5.3, 10.11c &
10.11d and RS
Appendices 10.4
& 10.7
Minor /
Moderate
S/T & L/T, P & T,
D
Nupend
settlement
Effect on views
and visual
amenity
C & O High Low (or less) for
settlement
overall
Moderate /
Minor (or less)
for settlement
overall
See RS Figures
5.3, 10.11c &
10.11d and RS
Appendices 10.4
& 10.7
See RS Figures
5.3, 10.11c &
10.11d and RS
Appendices 10.4
& 10.7
Minor /
Moderate (or
less) for
settlement
overall
S/T & L/T, P & T,
D
Nastend
settlement
Effect on views
and visual
amenity
C & O High Negligible Minor N/A N/A Minor S/T & L/T, P & T,
D
Stonehouse
settlement
Effect on views
and visual
amenity
C & O High Negligible Minor N/A N/A Minor S/T & L/T, P & T,
D
Leonard Stanley
settlement
Effect on views
and visual
amenity
C & O High Negligible Minor N/A N/A Minor S/T & L/T, P & T,
D
Kings Stanley
settlement
Effect on views
and visual
amenity
C & O High Negligible Minor N/A N/A Minor S/T & L/T, P & T,
D
Frampton on
Severn
settlement
Effect on views
and visual
amenity
C & O High Negligible Minor N/A N/A Minor S/T & L/T, P & T,
D
Saul settlement Effect on views
and visual
amenity
C & O High Negligible Minor N/A N/A Minor S/T & L/T, P & T,
D
Cotswold Way Effect on views
and visual
amenity
C & O High Negligible
overall
Minor overall
Moderate /
Minor at
See RS Figures
5.3, 10.11c &
10.11d and RS
See RS Figures
5.3, 10.11c &
10.11d and RS
Minor overall
Minor /
Moderate at
S/T & L/T, P & T,
D
Eco Park, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol.1 Main Text
December 2015
Page | 226
Low at Maiden
Hill &Haresfiled
Hill
Maiden Hill &
Haresfield Hill
Appendices 10.4
& 10.7
Appendices 10.4
& 10.7
Maiden Hill &
Haresfiled Hill
Thames and
Severn Way
Effect on views
and visual
amenity
C & O High Low Moderate /
Minor
See RS Figures
5.3, 10.11c &
10.11d and RS
Appendices 10.4
& 10.7
See RS Figures
5.3, 10.11c &
10.11d and RS
Appendices 10.4
& 10.7
Minor /
Moderate
S/T & L/T, P & T,
D
Severn Way Effect on views
and visual
amenity
C & O High Negligible Minor N/A N/A Minor S/T & L/T, P & T,
D
Gloucester and
Sharpness Canal
Effect on views
and visual
amenity
C & O High Negligible Minor N/A N/A Minor S/T & L/T, P & T,
D
Wysis Way Effect on views
and visual
amenity
C & O High Negligible Minor N/A N/A Minor S/T & L/T, P & T,
D
PRoW
Eastington
Footpath No.37
Effect on views
and visual
amenity
C & O High High Major
(Significant)
See RS Figures
5.3, 10.11c &
10.11d and RS
Appendices 10.4
& 10.7
See RS Figures
5.3, 10.11c &
10.11d and RS
Appendices 10.4
& 10.7
Major/
Moderate
(Significant)
S/T & L/T, P & T,
D
PRoW
Eastington
Footpath No.38
Effect on views
and visual
amenity
C & O High High Major
(Significant)
See RS Figures
5.3, 10.11c &
10.11d and RS
Appendices 10.4
& 10.7
See RS Figures
5.3, 10.11c &
10.11d and RS
Appendices 10.4
& 10.7
Major /
Moderate
(Significant)
S/T & L/T, P & T,
D
PRoW Cluster
East of site
around Grove
Lane / Westend
Cross
Effect on views
and visual
amenity
C & O High Low / Negligible Minor /
Moderate
See RS Appendix
10.4
See RS Appendix
10.4
Minor /
Moderate
S/T & L/T, P & T,
D
PRoW Cluster
North east of
M5 to Nupend
Effect on views
and visual
amenity
C & O High Low to medium
(Footpaths No.
22 & 23).
Moderate
(Footpaths No.
22 & 23).
See RS Figures
5.3, 10.11c &
10.11d and RS
See RS Figures
5.3, 10.11c &
10.11d and RS
Moderate to
Moderate /
Minor
S/T & L/T, P & T,
D
Eco Park, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol.1 Main Text
December 2015
Page | 227
Low (Footpaths
No. 20,21,24)
Moderate /
Minor
(Footpaths No.
22 & 23).
Appendices 10.4
& 10.7
Appendices 10.4
& 10.7
(Footpaths No.
22 & 23)
Minor
(Footpaths No.
20, 21 & 24)
PRoW Cluster
South east of
site and along
Stroudwater
Canal
Effect on views
and visual
amenity
C & O High Low from
Westfield Bridge
Negligible from
all other parts of
these PRoW
Moderate /
Minor from
Westfield Bridge
Minor from all
other parts of
these PRoW
N/A See RS Figures
5.3, 10.11c &
10.11d and RS
Appendices 10.4
& 10.7
Minor /
Moderate from
Westfield Bridge
Minor from all
other parts of
these PRoW
S/T & L/T, P & T,
D
PRoW No. 46
south of site
along River
Frome
(*Thames and
Severn Way)
Effect on views
and visual
amenity
C & O High Low Moderate /
Minor
See RS Figures
5.3, 10.11c &
10.11d and RS
Appendices 10.4
& 10.7
See RS Figures
5.3, 10.11c &
10.11d and RS
Appendices 10.4
& 10.7
Minor /
Moderate
S/T & L/T, P & T,
D
PRoW Cluster
South of site
Alkerton /
Eastington
fringe paths
connecting to
River Frome
Effect on views
and visual
amenity
C & O High Low Moderate /
Minor
See RS Figures
5.3, 10.11c &
10.11d and RS
Appendices 10.4
& 10.7
See RS Figures
5.3, 10.11c &
10.11d and RS
Appendices 10.4
& 10.7
Minor /
Moderate
S/T & L/T, P & T,
D
PRoW Cluster
North west of
M5 towards
Whitminster
Effect on views
and visual
amenity
C & O High Low / Medium Moderate
See RS Figures
5.3, 10.11c &
10.11d and RS
Appendices 10.4
& 10.7
See RS Figures
5.3, 10.11c &
10.11d and RS
Appendices 10.4
& 10.7
Moderate /
Minor
S/T & L/T, P & T,
D
PRoW No.48
Claypits
Footpath
Effect on views
and visual
amenity
C & O High Low Moderate /
Minor
See RS Figures
5.3, 10.11c &
10.11d and RS
See RS Figures
5.3, 10.11c &
10.11d and RS
Minor /
Moderate
S/T & L/T, P & T,
D
Eco Park, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol.1 Main Text
December 2015
Page | 228
Appendices 10.4
& 10.7
Appendices 10.4
& 10.7
National Cycle
Route No.41
Effect on views
and visual
amenity
C & O High Negligible Minor N/A N/A Minor S/T & L/T, P & T,
D
National Cycle
Route No.45
Effect on views
and visual
amenity
C & O High Low Moderate /
Minor
See RS Figures
5.3, 10.11c &
10.11d and RS
Appendices 10.4
& 10.7
See RS Figures
5.3, 10.11c &
10.11d and RS
Appendices 10.4
& 10.7
Minor /
Moderate
S/T & L/T, P & T,
D
Grove Lane Effect on views
and visual
amenity
C & O Medium Low Minor /
Moderate
See RS Figures
5.3, 10.11c &
10.11d and RS
Appendices 10.4
& 10.7
See RS Figures
5.3, 10.11c &
10.11d and RS
Appendices 10.4
& 10.7
Minor /
Moderate to
Minor
S/T & L/T, P & T,
D
M5 Effect on views
and visual
amenity
C & O Low High 250m
north of J13
Low
Overall
Moderate /
Major for 250m
north of J13
Minor
Overall
(Significant for
250m)
See RS Figures
5.3, 10.11c &
10.11d and RS
Appendices 10.4
& 10.7
See RS Figures
5.3, 10.11c &
10.11d and RS
Appendices 10.4
& 10.7
Moderate to
Moderate /
Major for 250m
Minor Overall
(Significant for
250m)
S/T & L/T, P, D
A38 Effect on views
and visual
amenity
C & O Low Low Minor N/A N/A Minor /
Negligible
S/T & L/T, P & T,
D
A419 Effect on views
and visual
amenity
C & O Low High between
Chipmans Platt
roundabout &
J13
Low Overall
Moderate /
Major between
Chipmans Platt
roundabout &
J13
Minor Overall
N/A See Green
Infrastructure
Plan
Moderate to
Moderate /
Major between
Chipmans Platt
round-about &
J13
S/T & L/T, P & T,
D
Eco Park, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol.1 Main Text
December 2015
Page | 229
(Significant
between
Chipmans Platt
roundabout &
J13)
Minor /
Negligible
Overall
(Significant
between
Chipmans Platt
roundabout &
J13)
Saul Visitor
Centre
Effect on views
and visual
amenity
C & O High Negligible Minor N/A N/A Minor S/T & L/T, P & T,
D
Slimbridge
WWT
Observation
Tower
Effect on views
and visual
amenity
C & O High Negligible Minor N/A N/A Minor S/T & L/T, P & T,
D
Common Land -
Stinchcombe
Golf Course
Effect on views
and visual
amenity
C & O High Negligible Minor N/A N/A Minor S/T & L/T, P & T,
D
Common Land –
Selsey
Effect on views
and visual
amenity
C & O High Low / Negligible Minor /
Moderate
N/A N/A Minor /
Moderate
S/T & L/T, P & T,
D
Common Land –
Rodborough
Effect on views
and visual
amenity
C & O High Low / Negligible Minor /
Moderate
N/A N/A Minor /
Moderate
S/T & L/T, P & T,
D
Robinswoodhill
Country Park -
Effect on views
and visual
amenity
C & O High Negligible Minor N/A N/A Minor S/T & L/T, P & T,
D
National Trust –
Area around
Haresfield
Effect on views
and visual
amenity
C & O High Low / Negligible Minor /
Moderate
N/A N/A Minor /
Moderate
S/T & L/T, P & T,
D
National Trust –
Area around
Rodborough
Common
Effect on views
and visual
amenity
C & O High Low / Negligible Minor /
Moderate
N/A N/A Minor /
Moderate
S/T & L/T, P & T,
D
Eco Park, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol.1 Main Text
December 2015
Page | 230
Open access –
Cam Long Down
Effect on views
and visual
amenity
C & O High Low / Negligible Minor /
Moderate
N/A N/A Minor /
Moderate
S/T & L/T, P & T,
D
Open access -
Coaley Peak
Effect on views
and visual
amenity
C & O High Low / Negligible Minor /
Moderate
N/A N/A Minor /
Moderate
S/T & L/T, P & T,
D
Open access –
Haresfield
Effect on views
and visual
amenity
C & O High Low / Negligible Minor /
Moderate
N/A N/A Minor /
Moderate
S/T & L/T, P & T,
D
Open access -
Coaley Peak
Effect on views
and visual
amenity
C & O High Low / Negligible Minor /
Moderate
N/A N/A Minor /
Moderate
S/T & L/T, P & T,
D
Open access –
Haresfield
Effect on views
and visual
amenity
C & O High Low / Negligible Minor /
Moderate
N/A N/A Minor /
Moderate
S/T & L/T, P & T,
D
Cumulative Effects
NCA 106:
Severn and
Avon Vales
Cumulative
effect on
landscape
character /
value
C & O Medium Low / negligible
Minor See RS Appendix
10.3
See RS Appendix
10.3
Minor /
Negligible
S/T & L/T, P &
T, D & I
NCA 107:
Cotswolds
Cumulative
effect on
landscape
character /
value
C & O Medium to High Negligible Minor /
Moderate to
Minor
See RS Appendix
10.3
See RS Appendix
10.3
Minor S/T & L/T, P & T,
I
LCT SV6 Settled
Unwooded
Vale, LCA SV6A
Vale of Berkeley
Cumulative
effect on
landscape
character /
value
C & O Medium Medium / High
up to
500m from
Development
Footprint
Low reducing to
negligible
beyond 500m
Moderate /
Major up to
500m from
Development
Footprint
Minor /
Moderate
See RS Appendix
10.3
See RS Appendix
10.3
Moderate up to
500m from
Development
Footprint
Minor beyond
500m
S/T & L/T, P &
T, D & I
Eco Park, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol.1 Main Text
December 2015
Page | 231
reducing to
minor beyond
500m
(Significant
within 500m)
(Not Significant
within 500m or
elsewhere)
LCT SV2 Drained
Riverine
Farmland and
Grazed Salt
Marsh / LCA
SV2B Slimbridge
and New
Grounds
Marshes
Cumulative
effect on
landscape
character /
value
C & O Medium Negligible Minor /
Negligible
N/A N/A Minor /
Negligible
S/T & L/T, P & T,
I
LCT SV11 Vale
Hillocks / LCA
SV11A Overton
and Barrow Hill
Cumulative
effect on
landscape
character /
value
C & O Medium Negligible Minor /
Negligible
N/A N/A Minor /
Negligible
S/T & L/T, P & T,
I
Escarpment
Footslopes
(Stroud No 5A)
Cumulative
effect on
landscape
character /
value
C & O Medium to High Medium / High
up to
500m from
Development
Footprint
Low beyond
500m
Moderate /
Major to Major
–Moderate up
to 500m
Development
Footprint
Minor /
Moderate to
Moderate /
Minor beyond
500m
(Significant
within 500m)
See RS Figures
5.3, 10.11c &
10.11d and RS
Appendices 10.3
& 10.7.
See RS Figures
5.3, 10.11c &
10.11d and RS
Appendices 10.3
& 10.7
Moderate to
Moderate /
Major up to
500m from
Development
Footprint
Minor /
Moderate to
Minor beyond
500m
(Significant
within 500m)
S/T & L/T, P & T,
D & I
Eco Park, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol.1 Main Text
December 2015
Page | 232
Lowland Plain
(Stroud No 5B)
Cumulative
effect on
landscape
character /
value
C & O Medium Medium/
High up to
500m from
Development
Footprint
Low beyond
500m
Moderate/
Major up to
500m from
Development
Footprint
Minor /
Moderate
beyond 500m
(Significant
within 500m)
See RS Figures
5.3, 10.11c &
10.11d and RS
Appendices 10.3
& 10.7.
See RS Figures
5.3, 10.11c &
10.11d and RS
Appendices 10.3
& 10.7.
Moderate up to
500m from
Development
Footprint
Minor beyond
500m
(Not Significant
within 500m or
elsewhere)
S/T & L/T, P &
T, D & I
Frome River
Valley (Stroud
No 5C)
Cumulative
effect on
landscape
character /
value
C & O Medium to High Low / Negligible
within 500m
Negligible
beyond 500m
Minor /
Moderate to
Minor within
500m
Minor to Minor
/ Negligible
beyond 500m
See RS Appendix
10.3
See RS Appendix
10.3
Minor within
500m
Minor /
Negligible
beyond 500m
S/T & L/T, P & T,
I
Wold Tops
(Stroud No. 1)
Cumulative
effect on
landscape
character /
value
C & O High Negligible Minor N/A N/A Minor /
Negligible
S/T & L/T, P & T,
I
Secluded
Valleys (Stroud
No. 3)
Cumulative
effect on
landscape
character /
value
C & O High Negligible Minor N/A N/A Minor /
Negligible
S/T & L/T, P & T,
I
Escarpment
(Stroud No. 4)
Cumulative
effect on
landscape
character /
value
C & O High Low Moderate /
Minor
See RS Figures
5.3, 10.11c &
10.11d and RS
Appendices 10.3
& 10.7.
See RS Figures
5.3, 10.11c &
10.11d and RS
Appendices 10.3
& 10.7.
Minor /
Moderate to
Minor
S/T & L/T, P & T,
I
Eco Park, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol.1 Main Text
December 2015
Page | 233
Severn Vale
Grazing
Marshes
(Stroud No.8)
Cumulative
effect on
landscape
character /
value
C & O Medium Negligible Minor /
Negligible
N/A N/A Negligible S/T & L/T, P & T,
I
Severn Vale
Hillocks (Stroud
No.7)
Cumulative
effect on
landscape
character /
value
C & O Medium Negligible Minor /
Negligible
N/A N/A Negligible S/T & L/T, P & T,
I
Escarpment
Outlier / Cam
Longdown,
Peaked Down
and Downham
Hill (Cotswolds
No.1A).
Cumulative
effect on
landscape
character /
value
C & O High Negligible Minor See RS Figures
5.3, 10.11c &
10.11d and RS
Appendices 10.3
& 10.7.
See RS Figures
5.3, 10.11c &
10.11d and RS
Appendices 10.3
& 10.7.
Minor /
Negligible
S/T & L/T, P & T,
I
Escarpment /
Uley to Coopers
Hill (Cotswolds
No. 2C)
Cumulative
effect on
landscape
character /
value
C & O High Low Moderate /
Minor
See RS Figures
5.3, 10.11c &
10.11d and RS
Appendices 10.3
& 10.7.
See RS Figures
5.3, 10.11c &
10.11d and RS
Appendices 10.3
& 10.7.
Minor /
Moderate
S/T & L/T, P & T,
I
Rolling Hills and
Valleys /
Stinchcombe
and North
Nibley
(Cotswolds
No.3B).
Cumulative
effect on
landscape
character /
value
C & O High Negligible Minor N/A N/A Minor /
Negligible
S/T & L/T, P & T,
I
High Wold /
Nympsfield and
Kingscote
Plateau
&Minchinhamp
ton Common.
Rodborough
and Amberley
Cumulative
effect on
landscape
character /
value
C & O High Negligible Minor See RS Figures
5.3, 10.11c &
10.11d and RS
Appendices 10.3
& 10.7.
See RS Figures
5.3, 10.11c &
10.11d and RS
Appendices 10.3
& 10.7.
Minor /
Negligible
S/T & L/T, P & T,
I
Eco Park, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol.1 Main Text
December 2015
Page | 234
Common
(Cotswolds No.
7A)
Settled
Unwooded Vale
/ Vale of
Gloucester
Fringe
(Cotswolds
No.18A)
Cumulative
effect on
landscape
character /
value
C & O High Low Moderate /
Minor
See RS Figures
5.3, 10.11c &
10.11d and RS
Appendices 10.3
& 10.7.
See RS Figures
5.3, 10.11c &
10.11d and RS
Appendices 10.3
& 10.7.
Minor /
Moderate to
Minor
S/T & L/T, P & T,
I
LCT 1
Stroud-water
settlement (Part
1.2)
Cumulative
effect on
landscape
character /
value
C & O Medium to High Negligible Minor to Minor
/ Negligible
See RS Appendix
10.3
See RS Appendix
10.3
Minor /
Negligible
S/T & L/T, P & T,
I
LCT 4
Green Corridor:
Rural Frome
Vale
(Part 4.4)
Cumulative
effect on
landscape
character /
value
C & O Medium to High Low to
Negligible
Minor /
Moderate to
Minor
See RS Appendix
10.3
See RS Appendix
10.3
Minor S/T & L/T, P & T,
I
LCT 7
Meadow Mill
(Part 7.1)
Cumulative
effect on
landscape
character /
value
C & O Medium to High Low to
Negligible
Minor /
Moderate to
Minor
See RS Appendix
10.3
See RS Appendix
10.3
Minor S/T & L/T, P & T,
I
LCT 2
Core Vale
Settlement East
of Eastington
(Part 2.2)
Cumulative
effect on
landscape
character /
value
C & O Medium to High Negligible
Minor /
Negligible to
Minor
See RS Appendix
10.3
See RS Appendix
10.3
Minor /
Negligible to
Negligible
S/T & L/T, P & T,
I
Viewpoint 1.
A419 at M5
Junction 13
Cumulative
effect on views
and visual
amenity
C & O Low Low Minor See RS Figures
5.3, 10.11c &
10.11d and RS
Appendices 10.4
& 10.7.
See RS Figures
5.3, 10.11c &
10.11d and RS
Appendices 10.4
& 10.7.
Minor S/T & L/T, P & T,
D
Eco Park, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol.1 Main Text
December 2015
Page | 235
Viewpoint 2.
Footpath at
Westfield
Bridge
Cumulative
effect on views
and visual
amenity
C & O High Low Moderate /
Minor
See RS Appendix
10.4
See RS Appendix
10.4
Minor
(Adverse and
Beneficial)
S/T & L/T, P & T,
D
Viewpoint 3.
Footpath east
of Westend
Cumulative
effect on views
and visual
amenity
C & O High Low/Negligible Minor/
Moderate
See RS Figures
5.3, 10.11c &
10.11d and RS
Appendices 10.4
& 10.7.
See RS Figures
5.3, 10.11c &
10.11d and RS
Appendices 10.4
& 10.7.
Minor S/T & L/T, P & T,
D
Viewpoint 4.
A419 at
Chipmans Platt
roundabout
Cumulative
effect on views
and visual
amenity
C & O Low Medium Moderate /
Minor
See RS Figures
5.3, 10.11c &
10.11d and RS
Appendices 10.4
& 10.7.
See RS Figures
5.3, 10.11c &
10.11d and RS
Appendices 10.4
& 10.7.
Minor /
Moderate
S/T & L/T, P & T,
D
5. Viewpoint
Thames and
Severn Way
east of M5
Cumulative
effect on views
and visual
amenity
C & O High Low Moderate /
Minor
See RS Appendix
10.4
See RS Appendix
10.4
Minor
(Adverse and
Beneficial)
S/T & L/T, P & T,
D
6. Viewpoint
Footpath West
of Nupend
Cumulative
effect on views
and visual
amenity
C & O High Medium Moderate /
Major
(Significant)
See RS Figures
5.3, 10.11c &
10.11d and RS
Appendices 10.4
& 10.7.
See RS Figures
5.3, 10.11c &
10.11d and RS
Appendices 10.4
& 10.7.
Moderate to
Moderate /
Minor
(Not Significant)
A, S/T & L/T, P &
T, D
7. Viewpoint
Grove Lane M5
over bridge
Cumulative
effect on views
and visual
amenity
C & O Medium Low to
Negligible
Minor See RS Figures
5.3, 10.11c &
10.11d and RS
Appendices 10.4
& 10.7.
See RS Figures
5.3, 10.11c &
10.11d and RS
Appendices 10.4
& 10.7.
Minor S/T & L/T, P & T,
D
8. Viewpoint
Footpath north
of Eastington
Cumulative
effect on views
and visual
amenity
C & O High Low / Medium Moderate
See RS Figures
5.3, 10.11c &
10.11d and RS
Appendices 10.4
& 10.7.
See RS Figures
5.3, 10.11c &
10.11d and RS
Appendices 10.4
& 10.7.
Moderate /
Minor
S/T & L/T, P & T,
D
Eco Park, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol.1 Main Text
December 2015
Page | 236
9. Viewpoint
Maiden Hill
(Cotswold Way)
Cumulative
effect on views
and visual
amenity
C & O High Low Moderate /
Minor
See RS Figures
5.3, 10.11c &
10.11d and RS
Appendices 10.4
& 10.7.
See RS Figures
5.3, 10.11c &
10.11d and RS
Appendices 10.4
& 10.7.
Minor S/T & L/T, P & T,
D
10. Viewpoint
Haresfield Hill
(Cotswold Way)
Cumulative
effect on views
and visual
amenity
C & O High Low Moderate /
Minor
See RS Figures
5.3, 10.11c &
10.11d and RS
Appendices 10.4
& 10.7.
See RS Figures
5.3, 10.11c &
10.11d and RS
Appendices 10.4
& 10.7.
Minor S/T & L/T, P & T,
D
11. Viewpoint
Selsey Common
(Cotswold Way)
Cumulative
effect on views
and visual
amenity
C & O High Low to
Negligible
Minor /
Moderate
See RS Appendix
10.4
N/A Minor S/T & L/T, P & T,
D
12. Viewpoint
Cam Long Down
(Cotswold Way)
Cumulative
effect on views
and visual
amenity
C & O High Negligible Minor See RS Appendix
10.4
N/A Minor /
Negligible
S/T & L/T, P & T,
D
13. Viewpoint
A38 at Claypits
Cumulative
effect on views
and visual
amenity
C & O High for
property
Low for road
users
Low / Negligible Minor /
Moderate for
property, Minor
/ Negligible for
road users
See RS Appendix
10.4
See RS Appendix
10.4
Minor for
property
Negligible for
road users
S/T & L/T, P & T,
D
14. Viewpoint
A38 / Thames
and Severn Way
intersection
Cumulative
effect on views
and visual
amenity
C & O High Low to
Negligible
Minor/
Moderate
N/A N/A Minor S/T & L/T, P & T,
D
15 Viewpoint
Footpath at
Doverow Hill
Cumulative
effect on views
and visual
amenity
C & O High Low Moderate /
Minor
See RS Figures
5.3, 10.11c &
10.11d and RS
Appendices 10.4
& 10.7.
See RS Figures
5.3, 10.11c &
10.11d and RS
Appendices 10.4
& 10.7.
Minor S/T & L/T, P & T,
D
16. Footpath
west of West
End Cross (EEA
38)
Cumulative
effect on views
and visual
amenity
C & O High Medium to High Major/Moderat
e
(Significant)
See RS Figures
5.3, 10.11c &
10.11d and RS
See RS Figures
5.3, 10.11c &
10.11d and RS
Moderate
(Not Significant)
S/T & L/T, P & T,
D
Eco Park, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol.1 Main Text
December 2015
Page | 237
Appendices 10.4
& 10.7.
Appendices 10.4
& 10.7.
A. St Micheal
and Angels
Church
Cumulative
effect on views
and visual
amenity
C & O High Negligible Minor See RS Appendix
10.4
See RS Appendix
10.4
Minor /
Negligible
S/T & L/T, P & T,
D
D. A38
Whitminster
Ridge
Cumulative
effect on views
and visual
amenity
C & O Low Negligible Negligible See RS Appendix
10.4
See RS Appendix
10.4
Negligible S/T & L/T, P & T,
D
E. Barrow Hill Cumulative
effect on views
and visual
amenity
C & O High Negligible Minor See RS Appendix
10.4
See RS Appendix
10.4
Minor /
Negligible
S/T & L/T, P & T,
D
F. Little Dean,
Forest of Dean
Cumulative
effect on views
and visual
amenity
C & O High Negligible Minor See RS Appendix
10.4
See RS Appendix
10.4
Minor /
Negligible
S/T & L/T, P & T,
D
G. Field Lane,
Cam
Cumulative
effect on views
and visual
amenity
C & O High Low / Negligible Minor /
Moderate
See RS Appendix
10.4
See RS Appendix
10.4
Minor S/T & L/T, P & T,
D
H. Frocester Hill Cumulative
effect on views
and visual
amenity
C & O High Low Moderate /
Minor
See RS Appendix
10.4
See RS Appendix
10.4
Minor /
Moderate
S/T & L/T, P & T,
D
Eco Park, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol.1 Main Text
December 2015
Page | 238
11 SOCIO-ECONOMICS
Summary
11.1 This chapter assesses the potential effect of the Revised Scheme on socio-economic conditions
in Stroud District. It assesses potential effects on the construction sector, total employment and
access to community facilities.
11.2 Stroud has a successful economy and strong labour market, with low rates of unemployment and
highly skilled residents. Recent trends show that employment in the District are slowly recovering
from the economic downturn. The construction sector is an important source of employment,
however the sector is mostly made up of small businesses and there are very few large
companies specialising in commercial construction which may limit the potential for a large
proportion of construction expenditure to be retained locally.
11.3 The New Lawn Stadium includes a private gym and fitness studio which are available to members,
and a conference room which is available for community use. Although the gym is well-used,
demand for the conference room is very low, with no regular community events using the room
at present. There are alternative gym facilities and a well used community centre located in the
centre of Nailsworth. There is also a bar within the New Lawn Stadium which is only open on
match days and for events held at the club. There are no pubs or restaurants in the immediate
vicinity of the ground which are highly dependent on the income generated through match day
supporters.
11.4 The Revised Scheme will provide some socio-economic benefits for Stroud District. The Revised
Scheme is expected to create 120 FTE jobs per annum during the construction phase, and 47
permanent FTE jobs once completed (of which 2 are net additional). The increased capacity and
attendances at the new stadium will result in some increase in expenditure in Stroud District but
this is likely to be negligible. There may also be socio-economic benefits from the new housing
which is proposed for the New Lawn site under a separate planning application. These benefits
have not been assessed in this ES.
11.5 The closure of the New Lawn stadium will result in the loss of some sporting facilities to local
communities, including the private gym and fitness studios. However local residents could use
alternative gym facilities available in Nailsworth. Therefore, there will be limited loss of
amenities for local residents.
Introduction
11.6 This chapter assesses the potential effect of the Revised Scheme on socio-economic conditions
in Stroud District. The assessment has been prepared by Regeneris Consulting, and includes the
following:
• The methodology for assessing the socio-economic effects;
• The baseline conditions currently existing in Stroud and in the area around the New Lawn
stadium and Revised Scheme, including the local population and economy, labour market
and community facilities;
• Design evolution – which describes any embedded mitigation measures in the design of
the Revised Scheme;
• The potential direct and indirect effects of the Revised Scheme, both positive and negative
(as well as mitigation measures if required and whether these are temporary or
permanent effects);
Eco Park, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol.1 Main Text
December 2015
Page | 239
• The cumulative effect of the Revised Scheme with a number of other proposed
developments on socio-economic conditions in the local area.
Legislation, Policy and Guidance
National Policy
National Planning Policy Framework
11.7 The National Planning Policy Framework89 (NPPF) sets out Government planning policies for
England and how these are expected to be applied.
11.8 The presumption in favour of sustainable development is central to the NPPF. It is identified as
“‘the golden thread running through both plan-making and decision taking” (Paragraph 14).
Three dimensions of sustainable development are defined by the NPPF in setting out the role of
the planning system:
• Economic: the planning system is able to perform an economic role through supporting
growth and innovation;
• Social: the planning system is able to perform a social role through supporting strong,
vibrant and healthy communities;
• Environmental: the planning system is able to perform an environmental role through
protecting and enhancing the natural, built and historic environment.
11.9 Of particular relevance to the assessment of socio-economic benefits of the Revised Scheme are
the "positive improvements" identified by NPPF which the planning system should seek to
achieve (Paragraph 9).
• Making it easier for jobs to be created in cities, towns and villages;
• Improving the conditions in which people live, work, travel and take leisure.
11.10 The NPPF makes clear that Local Planning Authorities should give significant weight to supporting
economic growth. They should:
• “proactively drive and support sustainable economic development to deliver the homes,
businesses and industrial units, infrastructure and thriving local places that the country
needs” (Paragraph 17);
• “plan proactively to meet the development needs of business” (Paragraph 20) and
encourage rather than impede sustainable growth.
Local Policy
11.11 This section summarises some of the key policies, strategy and guidance document which are
directly relevant to the assessment of socio-economic effects. Chapter 6 of the ES provides a full
planning policy assessment and RS Appendix 6.1 of the ES sets out the planning policy context.
Stroud District Local Plan, Adopted, November 201590
11.12 The Local Plan sets out the vision for the development of Stroud District up to 2031. The
development strategy outlines the following relevant objectives within the Emerging Local Plan:
• Generating the equivalent of two new jobs for every new allocated home built;
89 CLG (2012): National Planning Policy Framework, Department for Communities and Local Government 90 Stroud District Council (2015). Your District Your Future, Stroud District Local Plan, November 2015
Eco Park, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol.1 Main Text
December 2015
Page | 240
• Supporting the provision of 6,800 to 12,500 new jobs;
• At least 11,400 new homes;
• Regenerating key areas including the main town of Stroud;
• Supporting mixed use schemes to promote sustainable communities and reduce the
carbon footprint.
11.13 In order to achieve these objectives, the plan sets out six Core Policies as part of the development
strategy. The relevant policies to this socio-economic assessment are:
• CP2: Strategic growth and development locations. The policy identifies a number of
strategic locations for the delivery of new housing and employment land across Stroud
District;
• CP3: A hierarchy for growth and development across the District's settlements. The policy
identifies the town of Stonehouse as a first tier settlement, and aims to enhance its role
as an employment and service centre for the District. The towns identified as first tier will
be the main focus for delivering employment and housing. The Revised Scheme site is in
close proximity to Stonehouse, but falls just outside the designated growth area in the key
diagram accompanying policy CP3;
• CP4: Place making. The policy aims to create attractive, high quality developments
throughout the district for people to live, work and play. The policy aims to support local
community services, enhance the sense of place and create safe streets, homes and
workplaces.
Gloucestershire Local Enterprise Partnership Strategic Economic Plan, March 2014
11.14 Gloucestershire LEP has developed a Strategic Economic Plan91 (SEP) in order to make the case
for a £52m investment from the Single Local Growth Fund, in which it outlines its ambition to
create over 33,900 jobs (a 12% increase) and protect 2,100 jobs, build over 3,200 new homes
and grow the economy of Gloucestershire by £493m by 2021 (an increase of 4%).
11.15 The focus of the SEP is therefore largely on promoting business and enterprise, and providing the
necessary conditions for the existing business base to prosper, as well as attracting inward
investment. This resulted in the development of three key projects that will deliver this growth:
• Gloucestershire Growth Hub. The Hub will provide support services to businesses with
high growth potential, as well as entrepreneurs and start-ups, encouraging individuals into
apprenticeships and other employment routes.
• GREEN. The project aims to establish Gloucestershire as the centre of excellence in
Renewable Energy, Engineering and Nuclear skills.
• Gloucestershire Growth Zone. The Growth Zone is focused on ensuring provision of
employment land in the vicinity of the M5 motorway, which provides connectivity links
with the rest of the country and the LEP.
Assessment Methodology and Significance Criteria
11.16 The assessment has been undertaken by Oliver Chapman at Regeneris Consulting. Oliver is an
Associate Director at Regeneris with ten years’ experience in economic development, specialising
in land and property economics. He has undertaken socio-economic impact assessments for a
number of large and complex projects and drafted the socio-economics chapters for
Environmental Statements and Preliminary Environmental Information Reports. This includes
91 Gloucestershire Local Enterprise Partnership (2014): Strategic Economic Plan, March 2014
Eco Park, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol.1 Main Text
December 2015
Page | 241
major energy projects, large housing developments and urban extensions and new stadium
developments (Scunthorpe United FC). Oliver also regularly provides evidence in relation to
economic matters at local plan examinations. He is therefore a competent expert to undertake
the assessment.
11.17 The assessment considers the expected temporary socio-economic effects during construction
of the Revised Scheme and the permanent effects once the development is completed and
occupied.
Study Area
11.18 Selecting suitable study areas for socio-economic assessments is complex because of the nature
of how labour markets and supply chains work, which in many cases extend over a wide
geographical area. These factors will play a key role in determining where potential socio-
economic effects will be generated.
11.19 The assessment has focused on the effects in the local authority area of Stroud District. The
reasons for selecting this area are as follows:
• This is where all of the direct jobs will be located (once operational) and therefore where
the majority of economic value will be generated;
• Data from the 2011 Census shows that 71% of the jobs located in Stroud District were
taken by residents of the District, meaning a high proportion of jobs may be expected to
be taken by local residents.
11.20 There will inevitably be some leakage of socio-economic effects outside this Study Area. This will
be as a result of residents from other districts taking jobs at the Revised Scheme, and firms from
outside Stroud District accessing supply chain opportunities during the construction and
operational phase. However, predicting where these effects might occur is subject to a large
degree of uncertainty.
11.21 Supply chain effects in particular could occur over a very wide area, and will be dependent on
the locations of firms which secure the largest contracts during the construction phase. The
latter will not be known until a procurement exercise has been undertaken. It is noted that
Ecotricity (the developers) have an intention to source local contractors wherever possible,
however the size of the construction project (with estimated costs of £31.6m) means there may
be a limited number of local suppliers with the capacity to secure the largest contracts. However,
it is not possible to say with any certainty the area from which these suppliers will be drawn.
11.22 Therefore, given the uncertainty in predicting where socio-economic effects will occur, Stroud
District is considered to be the most reasonable and practical Study Area for assessing socio-
economic effects. The full extent of Stroud District is shown in RS Figure 11.1.
Datasets
11.23 The datasets which are drawn upon in the socio-economic baseline and assessment are all from
secondary data sources or based on information provided by Forest Green Rovers (FGR) FC or
Ecotricity. No primary research or surveys were undertaken. The secondary data sources
include:
• Census 2001 and 201192
92 Office for National Statistics (2011) Census of Population. Accessed via nomisweb.co.uk October 2017
Eco Park, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol.1 Main Text
December 2015
Page | 242
• Office for National Statistics (ONS), Mid-Year Population Estimates, 201693
• ONS, 2014 Sub-National Population Projections (SNPP)94
• ONS, Annual Population Survey (APS), 201695
• Business Register and Employment Survey (BRES), 201696
• ONS UK Business Counts97
• Duedil Business Database98
Potential effects included in assessment
11.24 The main effects that are assessed in this socio-economics chapter are as follows:
• Temporary construction expenditure and employment. The Revised Scheme could
generate temporary employment and economic activity during the construction phase;
both directly through the employment on site and the supply chain of contractors.
• Permanent increase in employment levels in Stroud district. The increased capacity could
support additional direct, on site employment which could then generate off-site
multiplier effects. This includes the attraction of additional visitors to Stroud, whose
expenditure in the local economy could support additional employment. As this scheme
involves the relocation of an existing asset, the issue of displacement needs to be properly
assessed.
• Loss of recreational and sporting facilities. The closure of the New Lawn Stadium could
result in the loss of amenity for residents who use the facilities, which include a private
gym, bar and conference room.
11.25 The socio-economic assessment has analysed the potential effects of the development as a
whole. The methods for assessing each of the potential effects are as follows:
• Construction jobs. Effects have been calculated by drawing upon guidance published by
OFFPAT/Homes and Communities Agency99.. This provides official benchmarks for the
number of construction jobs per £1 million of expenditure for different types of
construction projects which have been adjusted to take account of inflation. The
construction cost estimates have been provided by Ecotricity.
• Permanent increase in employment levels. Evidence has been provided by Ecotricity and
FGR on the operational labour requirements of the proposed new stadium and facilities,
including a breakdown of job types and a split between full time and part time
employment. These have been combined with a wider literature review of multiplier
effects and the socio-economic effects of new stadium developments to estimate the
indirect economic effects.
93 Office for National Statistics (2016). Mid Year Population Estimates. Accessed via nomisweb.co.uk October 2017 94 Office for National Statistics (2015) 2014 Sub-national Population Projections. Accessed via nomiweb.co.uk during
October 2017 95 Office for National Statistics (2016). Annual Population Survey. Accessed via nomisweb.co.uk during October 2017 96 Office for National Statistics (2017). Business Register and Employment Survey. Accessed via nomisweb.co.uk
October 2017 97 Office for National Statistics (2017). UK Business Counts. Accessed via nomisweb.co.uk October 2017 98 Duedil (2017). Duedil Business Counts. Accessed via duedil.com October 2017 99 OffPAT and Homes and Communities Agency (2009): Guidance on Calculation Construction Jobs
Eco Park, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol.1 Main Text
December 2015
Page | 243
• Loss of facilities at The New Lawn stadium: Information has been provided by FGR on the
nature of current facilities at The New Lawn stadium and the usage of these facilities by
the local community.
Significance Criteria
11.26 The assessment of socio-economic effects has been based on a widely used and accepted
methodology which considers the sensitivity of the receptor and the magnitude of effect. These
are combined to arrive at an assessment of the significance of effect.
11.27 The following indicators have been defined as the key receptors for the Revised Scheme:
• Employment in the construction sector in Stroud District
• Total employment in Stroud District.
• Access to community facilities at The New Lawn stadium
11.28 The sensitivity of receptor is based on the importance attached to the receptor in local, regional
and national economic development and regeneration policy, and whether there is evidence of
underperformance across Stroud District. Examples of how sensitivity may be determined for a
particular feature are provided in Table 11.1: .
Table 11.1: Criteria for assessing sensitivity of socio-economic receptors
Sensitivity Criteria Example Criteria
High Receptor is given a high
priority in local, regional
and national economic
development and
regeneration policy.
Identification as a key thematic or spatial priority (as a result
of economic potential and/or need).
Evidence of major socio-economic challenges, under-
performance or vulnerability e.g. patterns of deprivation,
employment and wealth generation, employment forecasts,
exposure to socio-economic threats.
Or, evidence of major socio-economic opportunity e.g.
development of key sectors
Medium Receptor is given a
medium priority in local,
regional and national
economic development
and regeneration policy.
No identification as a key thematic or spatial priority (as a
result of economic potential and/or need), but nevertheless
a consideration identified in policy and strategy
Evidence of significant socio-economic challenges, under-
performance or vulnerability or evidence of significant socio-
economic opportunity.
Low Receptor is given a low
priority in local, regional
and national economic
development and
regeneration policy.
No identification as a thematic or spatial priority (as a result
of economic potential and/or need) in any regard
Evidence of economic prosperity, buoyancy and resilience
e.g. low levels of deprivation, relatively high employment
and wealth generation rates, relatively strong employment
forecasts.
11.29 Socio-economic effects magnitude will be determined by consideration of the predicted
deviation from baseline conditions. The criteria used for the assessment of magnitude of socio-
economic effects (both positive and negative) are shown in Table.2.
11.30 The assessment of magnitude of socio-economic effects requires an element of professional
judgement and cannot be made solely on the basis of percentage thresholds. This is for the
following reasons:
• A number of the potential effects cannot easily be quantified and therefore require a
qualitative assessment to be made (e.g. loss of community amenities);
Eco Park, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol.1 Main Text
December 2015
Page | 244
• Where potential effects can be quantified, the assessment may need to consider a number
of possible contextual indicators to assess the potential magnitude of effect in Stroud.
This is particularly the case for construction employment, where the jobs may be based in
Stroud but the contractor and workforce may be drawn from other locations. In this case,
the assessment would need to consider both the number of jobs that may be created and
the likelihood that local workers might be used.
11.31 When measuring the magnitude of effect of increases in total employment in Stroud, any
increase over 1% is considered to be high. An increase of between 0.5% and 1% is considered to
be medium. An increase of 0.1% to 0.5% is considered to be low, and anything below 0.1% is
negligible. These thresholds have been determined by reviewing average annual changes in
employment in Stroud over the last ten years.
Table 11.2: Criteria for assessing magnitude of socio-economic effects
Magnitude
of Effect
Description
High Proposals would cause a large change to existing environmental conditions in terms of
absolute and/or percentage change.
Medium Proposals would cause a moderate change to existing environmental conditions in
terms of absolute and/or percentage change.
Low Proposals would cause a slight change to existing environmental conditions in terms of
absolute and/or percentage change.
Negligible No discernible change in baseline environmental conditions
11.32 Magnitude and sensitivity is combined as shown in to determine the significance of the effect.
All socio-economic effects that are assessed as moderate or higher are regarded as significant
within the meaning of the EIA Regulations (shown in green in Table 11.3).
Table 11.3: Criteria for assessing significance of socio-economic effects
Magnitude
High Medium Low Negligible
Se
nsi
tiv
ity
High Major Major Moderate Negligible
Medium Major Moderate Minor Negligible
Low Moderate Minor Negligible Negligible
Baseline Conditions
Population
11.33 Stroud District had a population of over 117,400 people in 2016100. The district has an ageing
population; more than 22% of residents are aged over 65 compared with a national average of
18%. The district has also seen significant growth in the number of retired people, increasing by
6,800 people (36%) between 2001 and 2016, compared with a national average of 26%. These
trends are set to continue; the latest sub-national population projections show the number
people aged 65 or over could increase by a further 10,300 people (40%) over the next fifteen
years.
100 ONS, Mid-year Population Estimates, 2016
Eco Park, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol.1 Main Text
December 2015
Page | 245
11.34 This ageing effect is expected to cause a modest fall in the number of people who are of working
age (16-64) and therefore most likely to be active in the labour market (see Graph11.1). There
are currently almost 70,500 residents aged 16-64 in Stroud District, representing 60% of the total
population of the district. This is projected to decrease by 200 people over the next fifteen years
(a 0.3% decrease).
Graph 11.1: Past and Future Population Change by Age Group in Stroud, 2001-2031
Source: ONS (2015): 2014 based sub-national population projections
Unemployment and Inactivity
11.35 Stroud has a healthy labour market, with high rates of participation. The economic activity rate
in Stroud District is very high, with nearly 90% of the working age population reporting that they
are either in work or actively seeking work101. This compares to 78% in England. Data from the
Annual Population Survey (APS) shows there are around 1,600 unemployed people in Stroud in
2017, representing an unemployment rate of circa 2.6%. Graph11.2 shows that this is
significantly lower than the national average (4.8%) and has fallen from a peak of 6.4% in 2009
(at the peak of the recession).
Graph 11.2: Unemployment Rate, 2005-2017
101 ONS, Annual Population Survey 2017. Subject to large margins of error.
Eco Park, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol.1 Main Text
December 2015
Page | 246
Source: ONS (2017): Annual Population Estimates model based estimates of unemployment
Employment
11.36 There were around 48,000 jobs based in Stroud District in 2016. The District experienced a slow
recovery from the economic downturn, with the number of jobs falling between 2009 and 2013.
Since then, the District has created 4,000 jobs and the level of employment is now 2,000 jobs
above the level it was at in 2009 (+2%). However, this rate of growth is still well below the UK
average (+10%).
Graph 11.3: Employment Change Index, 2009-2016 (2009=100)
Source: ONS (2016): Business Register and Employment Survey
Eco Park, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol.1 Main Text
December 2015
Page | 247
11.37 Table shows that manufacturing remains a very important source of employment in Stroud,
accounting for 21% of employment, which is more than double the national average. The area
has traditionally been associated with the cloth industry, and while the area still has a strong
base of textile manufacturers, this sub-sector has been overtaken by hi tech sectors such as
manufacture of computers and electronic products, which has grown by 1,000 jobs since 2010.
It is the strong performance of these highly skilled sub-sectors that have driven the recent growth
of Stroud’s manufacturing sector, and therefore bucked the trend of declining manufacturing
employment experienced in other parts of the country. The other sectors which have
contributed to recent growth are health and social care and construction which have both
created around 1,000 jobs since 2010.
Table 11.4: Employment by Sector in Stroud, 2010-2016
Employment
(2016)
Change
since
2010
Share of
employment
Agriculture, forestry & fishing102 75 25 0%
Mining, quarrying & utilities 1,500 800 3%
Manufacturing 10,000 1,000 21%
Construction 3,000 1,000 7%
Motor trades 900 100 2%
Wholesale 2,000 -250 4%
Retail 4,500 500 9%
Transport & storage 2,000 -1,000 3%
Accommodation & food services 3,500 500 8%
Information & communication 1,500 500 4%
Financial & insurance 350 -50 1%
Property 600 250 1%
Professional, scientific & technical 3,500 500 6%
Business administration & support
services
2,000 -250 4%
Public administration & defence 900 -350 2%
Education 3,500 -1,000 8%
Health 5,000 1,000 12%
Arts, entertainment, recreation &
other services
2,000 500 5%
Total 46,825 3,725 100%
Source: ONS (2016) BRES 2016. Note: Figures are rounded to the nearest hundred, and may not sum.
Construction Sector
11.38 The latest BRES data shows there were around 3,000 people employed in the construction sector
in Stroud District in 2016 (5.6% of employment). ABI data show that the sector grew rapidly in
the 2000s, creating around 1,000 new jobs between 1998 and 2008. This rate of growth slowed
after the economic downturn, but has grown rapidly in recent years, creating 1,000 jobs between
2010 and 2015.
102 SIC subclass 01000 farm agriculture is not estimated at district level and it is excluded from this analysis.
Eco Park, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol.1 Main Text
December 2015
Page | 248
11.39 The figure of 3,000 employees is likely to be a significant underestimate of the total size of the
sector as it excludes a large number of self-employed people who are not captured by
employment datasets. Data from the Census shows that there were around 4,900 Stroud District
residents working in the construction sector in 2011, of whom around 2,100 were self-employed
(43%). The majority of these self-employed people will be the proprietors of very small
construction businesses with no registered employees. ONS Business Counts data shows over
640 of the 690 construction businesses registered in Stroud employ fewer than ten employees,
with 560 employing fewer than five employees. The dataset shows there are only five businesses
in the sector employing more than 50 employees in 2015103, which suggests there are a limited
number of firms that might have the capacity to secure large contracts.
11.40 Analysis of the Duedil business dataset, which is based on Companies House records, shows that
the largest firms in the local construction sector include UK Power Solutions (a utility connections
company), Precast Concrete Structures Limited (specialising on the design, manufacture, and
erection of offsite modular building techniques), RF Gardiner (which specialises in buildings
maintenance and minor civils), Progressive Precast Erection Limited (related to Precast Concrete
Structures Limited), and Bowmore Estates Ltd.
11.41 Further analysis of BRES shows that there are only 150 employees in sub-sectors which specialise
in the construction of commercial buildings and 130 employees in civil engineering. These are
the services likely to be in greatest demand during the construction phase of the Revised Scheme.
However, a large proportion of employment is in skilled trades such as electrical installation and
plumbing which are also likely to be in demand.
Table 11.5: Construction Employment by Sub-sector, 2016
Employees % of employment
in sector
Electrical installation 530 18%
Specialised construction activities (other than
scaffold erection) not elsewhere classified
520 17%
Construction of domestic buildings 490 16%
Plumbing, heat and air-conditioning installation 360 12%
Other construction installation 210 7%
Joinery installation 150 5%
Other building completion and finishing 150 5%
Construction of commercial buildings 150 5%
Development of building projects 130 4%
Construction of other civil engineering projects
not elsewhere classified
130 4%
Painting 90 3%
Source: ONS (2016): BRES 2016. NB. Figures may not sum exactly due to rounding
Travel to Work
11.42 The district of Stroud has a low jobs density relative to its population, meaning a large
number of residents need to commute out of the district for work. The 2011 Census shows that
the district had a net outflow of around 7,200 workers leaving the area for work on a typical day
(see
Graph 11.4: ). These commuting patterns reflect the location of Stroud in between a number of
much larger employment centres, including Gloucester, Cheltenham and Bristol which account
103 ONS Business Counts data is rounded to the nearest 5 so the actual number will be between 3 and 7
Eco Park, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol.1 Main Text
December 2015
Page | 249
for a large proportion of the outflows. This has been identified as a key issue in the adopted
Local Plan104; bullet point 9 on page nine states “Many people who currently live in the District
commute out of it to work. One of the challenges is to ensure that new developments are planned
to ensure that they do not become simply dormitories for commuters.”
Graph 11.4: Commuting Flows and Top 10 Destinations and Residences, 2011
Source: ONS (2011): Census of Population 2011
Deprivation
11.43 Based on a standard measure of deprivation (Index of Multiple Deprivation 2015), Stroud ranked
as the 284th most deprived district in the country. This means that Stroud is among the 25% least
deprived districts in the country, reflecting its reputation as a desirable place to live. There are
however, a number of locations which have higher rates of deprivation, shown in darker shading
in RS Figure 11.2. These include areas close to the site for the Revised Scheme around
Stonehouse, which have higher levels of unemployment, lower average incomes and lower
quality of health than elsewhere in the district. The development West of Stonehouse which is
currently under construction may help to address some of these challenges.
Sports Facilities
11.44 Nailsworth Recreation Centre is Nailsworth’s only purpose built public recreation facility and is
available for use by a number of clubs for a wide range of sports activities, including badminton,
basketball and table tennis. The Recreation Centre also has a football pitch which is used by the
school and Taverners Football Club, with further football pitches located at the King George V
Playing Fields. Nailsworth Subscription Rooms also has a small sports hall which can be booked
for sports uses or exhibitions, plays and private parties. There are also private recreation facilities
at Nailsworth Tennis Club and Nailsworth Mill Bowling Green and a number of play areas and
other open spaces.
11.45 Stroud District Council runs four leisure centres, located at Dursley, Eastcombe, Stroud and
Stonehouse (close to the site of the Revised Scheme), but none in Nailsworth. There are two
gyms located in Nailsworth, one of which is within The New Lawn stadium development and
operates a number of classes as well as providing gym equipment. The other is Nailsworth
Strength and Fitness which is more centrally located.
104 Stroud District Council (2015). Your District Your Future, Stroud District Local Plan, November 2015
Eco Park, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol.1 Main Text
December 2015
Page | 250
Other Facilities in and around New Lawn
11.46 In addition to the gym facilities at The New Lawn, which can be accessed by the public, the
stadium also includes a large conference room that can accommodate up to 200 delegates. This
can be hired for conferences, weddings and other events, and can also be used by the local
community. However, FGRFC has reported that demand for these facilities is low, mainly due to
the location of the stadium which is inconvenient for many community users as it sits at the top
of a hill and is remote from the rest of the village facilities.
11.47 FGRFC has encouraged the community to use the facilities, and it has been used in the past for
events such as breakfast meetings and Slimming World, but there are no regular community
events at present. The club report that the local Arkell community centre attracts most of the
local community events, given that its prices are much lower and is more conveniently located.
11.48 There are no pubs or restaurants in the immediate vicinity of the ground, with the majority of
pubs located in the centre of Nailsworth town. This means that there are very few (if any)
establishments which are highly dependent on the income generated through match day
supporters. On match days, the vast majority of supporters use the Green Man bar which is built
in to the main stand and will be relocated to the new development. This bar used to be open to
the public seven days a week. However, this was not well used and lost money on a continual
basis, so is now only open on match days and for events held at the club.
Design Evolution
11.49 There are no embedded mitigation measures in the design of the Revised Scheme which are
relevant to socio-economics. However, there is potential to increase local economic benefits
during the construction stage if Ecotricity encourages contractors to work with local sub-
contractors wherever possible and to offer apprenticeship opportunities to Stroud residents.
Potential Effects
Construction Phase Effects: Employment created during construction
11.50 The total construction cost of the Revised Scheme is estimated to be £31.6m in current prices105.
This includes the stadium itself, partial dual carriageway, grass pitches, car parking, hard
surfacing, landscape works, and set up/ preliminaries. Using CLG/Offpat guidance106 on the level
of construction output per full-time equivalent (FTE) job, it is estimated that the Revised Scheme
would create around 120 FTE jobs over a five-year build period. These jobs will cover both on-
site and off-site roles, including those jobs created in contractor’s supply chain.
11.51 The baseline section shows that the construction sector is an important source of employment
for Stroud, employing around 3,000 people. The creation of 120 FTE jobs will represent a 4%
uplift in employment in the total construction sector in Stroud. Given the small number of large
firms in Stroud District, it is unlikely that a local business will secure the main contract during the
construction phase, meaning a large proportion of these economic benefits may occur outside
Stroud District. However, there are likely to be opportunities for local firms to secure lower value
contracts through the supply chains of the main contractors and opportunities for local workers
105 This is based on initial estimates provided by the applicant, but will be subject to revision as the plans are
developed 106 Office of Project and Programme Advice and Training (Offpat) and the Homes and Communities Agency (HCA)
(2009) Briefing Note on Calculating Construction Employment, HMSO, London
Eco Park, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol.1 Main Text
December 2015
Page | 251
to be used during construction. There are also likely to be some indirect benefits within Stroud
as a result of contractors and their workers spending money in the local economy. This includes
local hotels and restaurants if the contractors are from outside the area. The magnitude of effect
for Stroud District is assessed as low.
11.52 Though the sector is an important source for employment in Stroud, it is not identified as a high-
ranking priority in local economic development strategies. The sensitivity of the receptor is
therefore assessed as medium.
11.53 The significance of the effect is therefore assessed as minor beneficial, which is not considered
to be significant in EIA terms. This will be a temporary effect during the five-year construction
period. However, there may be some permanent positive effects if local residents receive
training or gain experience as a result of the Revised Scheme, potentially increasing their future
employability or earnings.
11.54 If contractors from outside Stroud District were appointed to deliver the largest construction
contracts, then Ecotricity could enhance local benefits by encouraging these contractors to work
with local sub-contractors wherever possible and to offer apprenticeship opportunities to
residents in Stroud seeking work in the construction sector, particularly young residents.
11.55 It should also be noted that the New Lawn is proposed for re-development of 90 new houses
with 30% being affordable, and that a commitment to this has already been made in the form of
a planning application. This would also generate additional construction employment. However,
the socio-economic effects/ benefits of this are not assessed in this ES as the housing application
is subject to separate consenting (and associated environmental assessment) procedures.
Completed Development: Employment supported by completed development
11.56 This section assesses the potential effects of the Revised Scheme on employment levels in Stroud
District. This includes the following:
• Direct effects: this captures those full and part time jobs based at the Revised Scheme;
• Indirect supply-chain effects: off-site jobs supported through the supply chain
expenditure of the occupier of the Revised Scheme (FGR);
• Induced effects: additional jobs supported through the local expenditure of employees of
FGRFC and its suppliers;
• Indirect visitor expenditure effects: additional jobs supported by the off-site expenditure
of visitors to the development.
11.57 The first three types of effect (direct, indirect and induced) are included in the majority of
economic appraisals of development schemes. The fourth type of effect (indirect visitor
expenditure effects) has been included to take account of the fact that the Revised Scheme could
increase the number of visitors to Stroud District.
Direct Effects (On-Site)
11.58 The proposed stadium development is replacing an existing stadium based within Stroud District
(The New Lawn Stadium). The assessment of socio-economic effects therefore needs to take
account of the jobs which are displaced from this site in order to estimate the net effect of the
development.
11.59 Table 11.6 provides a breakdown of staff at the existing New Lawn stadium and those expected
at the Revised Scheme and estimates the net additional FTE jobs. A large number of the jobs
which are created will be part time or casual positions. The assessment has assumed that all part
Eco Park, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol.1 Main Text
December 2015
Page | 252
time staff are equivalent to 0.5 FTEs, with the exception of match day casual staff, where each
job is equal to 0.1 FTE.
Table 11.6: Employment at Existing and Proposed Stadium
Existing Stadium Proposed Stadium
Total employees FTEs Total employees FTEs
Stadium 15 8.1 18 9.4
Green Man (casual) 8 0.5 9 0.6
Events General 2 2.0 2 2.3
Match Day Snacks
(casual)
6 0.5 7 0.6
Football Management 7 6.5 7 6.5
Gym 3 2.5 3 2.5
Football First Team 25 25.0 25 25.0
Total 65 45 70 47
11.60 Table 11.6 shows that the Revised Scheme could create 70 jobs in total, which are equivalent to
47 gross FTEs. After accounting for displacement, this results in two net additional FTEs.
Indirect Supply Chain and Induced Effects
11.61 The Revised Scheme may also support additional employment through indirect supply chain and
induced effects. HCA’s 2014 Additionality Guide107 recommends a local employment multiplier
of 1.38 for recreation developments. This is a composite multiplier which captures both indirect
supply chain and induced effects. However, given that the Revised Scheme is only expected to
create two net additional jobs, any multiplier effects will be negligible.
Indirect Visitor Expenditure Effects (Off-site)
11.62 The Revised Scheme could support additional off-site employment by attracting visitors to Stroud
District, who spend money in local shops, bars and restaurants. The main source of these visits
will be visiting away fans. Although the Revised Scheme could also lead to an increase in
attendances from home fans, it is assumed that the majority of these will be residents of Stroud
District and therefore their expenditure will not be net additional to the local economy.
11.63 FGR has attracted an average attendance of 2,234 per match so far in the 2017/18 season
(compared to 1,753 in the 2016/17 season before promotion), with an average away attendance
of 608 (roughly 20%). Future attendances will depend on a range of factors in addition to the
new stadium, including the performance of FGR in the football league. FGR predict that average
match attendances will increase to 4,350 by the 2030/31 season. Assuming that 20% of
attendees are away fans, this will mean average away attendances increase to 870.
11.64 The additional employment supported through an increase in indirect visitor expenditure effects
is likely to be low. A number of football visitor surveys have been reviewed as part of this
assessment108. These suggest that average off-site expenditure on food and drink for visiting
fans is around £10 per visitor. Even a large percentage increase in attendances will therefore
result in only a modest increase in expenditure over the course of the season, and would not be
expected to support an additional FTE job.
107 Homes and Communities Agency (HCA) (2014) Additionality Guide, 4th Edition, HMSO, London 108 For example, a study by the Campaign for Better Transport: Who are the champions of football travel? (2012/13
football seasons), based on a survey of more than 1,000 fans found that on average League 1 football fans spend £10
on match day travel.
Eco Park, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol.1 Main Text
December 2015
Page | 253
11.65 The loss of home fans’ match day expenditure may also potentially have a negative economic
effect at a local level (in Nailsworth). However, the baseline of this chapter showed that there
are very few pubs and restaurants in the immediate vicinity of the site which may be dependent
on match day revenue, with the majority of supporters using the facilities which are provided at
the New Lawn stadium (e.g. snack bars, Green Man pub) and will be relocated to the Revised
Scheme site. While there may be some home supporters using bars, restaurants and other
amenities in the town of Nailsworth, a large proportion of these are likely to be local people who
will spend their money in the local area anyway meaning there is likely to be no loss of income.
Total Operational Employment Effect
11.66 It is estimated that the total potential net additional effect on employment in Stroud from the
Revised Scheme is under 3 FTEs, including all direct, indirect and induced effects. The magnitude
of effect is therefore considered to be negligible, and not significant within the meaning of the
EIA Rgeulations.
Completed Development: Loss of Community Facilities at New Lawn
11.67 The relocation of FGR to a different site in Stroud means that there is the potential for the local
community around the existing New Lawn site to lose access to a range of community services
and facilities which were provided on site. However, as set out in the baseline section of this
chapter, community usage of most of these facilities, including the conference rooms and Green
Man bar, is very low. This is due to the location of the New Lawn at the top of a hill which is
remote from the town centre. The only facilities which are well used by local residents are the
gym and class studios.
11.68 The loss of these facilities will result in some loss of amenity for gym users. However, the baseline
of this chapter showed that there is another gym in Nailsworth which provides alternative
facilities. The magnitude of effect is therefore considered to be low. The sensitivity of receptor
is considered to be low since the gym is a privately owned facility and therefore not a strategic
priority for Stroud District Council. If there was a high level of local demand for private gym
facilities in Nailsworth as a result of the relocation of FGR, there is also the potential for the
market to respond through the creation of a new facility. The significance of effect is therefore
assessed as negligible, which is not significant in EIA terms.
Cumulative Effects
11.69 The assessment of socio-economic effects has also considered the cumulative effects of a
number of other specific developments in the surrounding area, as set out in Table 2.5 and RS
Figure 18.1. A number of the planning applications which have been submitted for these
proposed developments have not provided quantitative estimates of the socio-economic effects
of the schemes. There is therefore insufficient information to fully quantify the cumulative socio-
economic effects. However, the following points should be noted:
• All of the proposed schemes will create some temporary construction employment,
however these effects have only been quantified in two of the planning applications for
projects. These were West of Stonehouse (S.14/0810/OUT) which is estimated to create
2,025 direct person years of employment over a ten year construction period (average of
202 jobs per annum), and Land at Javelin Park (13/0001/INQUIR) which is estimated to
create 300 jobs over a three year construction period. In both cases it is understood that
work has now commenced on these sites. The other proposed developments are smaller
in scale and therefore likely to create fewer temporary jobs. They are also likely to be built
Eco Park, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol.1 Main Text
December 2015
Page | 254
out over different time periods, meaning any increase in construction employment may
occur at different points in time. It is also possible that a number of the contracts are
secured by firms which are not based in Stroud District, meaning some of the economic
benefits will be lost to the area. With these caveats in mind, the sensitivity of receptor
and magnitude of effect are both considered to be medium, meaning the significance of
effect is moderate beneficial, which is significant in EIA terms.
• A number of the developments will create permanent jobs located within Stroud District.
The commercial developments will create jobs directly through the provision of new
employment space, while residential-led developments could create jobs indirectly
through the expenditure of new residents. These effects are not quantified in any of the
planning applications except for Javelin Park which is estimated to create 40 jobs when
operational. It is not expected that any of the other developments will be in competition
with the Revised Scheme because they are targeted at different markets and will not
compete for the same customers or occupiers. Based on the nature of the proposals and
expert judgment about their potential for job creation, the magnitude of effect is assessed
as negligible. The sensitivity of receptor is also high meaning the significance of effect is
negligible which is not significant in EIA terms.
• The Revised Scheme is a sports facility which is complementary to residential led
developments, providing residents with opportunities to watch football and make use of
the club facilities such as the stadium bar.
Conclusions
11.70 The Revised Scheme is not expected to have any socio-economic effects which are significant
in EIA terms.
11.71 The main conclusions are as follows:
• Construction of the Revised Scheme is expected to create 120 FTE jobs in the construction
sector over a five year construction period.
• Once completed, the Revised Scheme is expected to create two net additional direct FTEs
in Stroud.
• The closure of the New Lawn stadium will result in a loss of some sporting facilities,
including the private gym and fitness studios. However local residents could use
alternative gym facilities available in Nailsworth. Other facilities at the New Lawn are not
well used by local residents. Therefore, there will be limited loss of amenities for local
residents.
Eco Park, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol.1 Main Text
December 2015
Page | 255
Table 11.7: Summary of Socio economics Effects and Mitigation
Receptor Effect Phase
(Construction /
Operation)
Embedded
Mitigation
Sensitivity of
Receptor
Magnitude
of Change
Level of Effect and
Significance Prior to
Mitigation
Mitigation Enhancement Level of
Effect (and
Significance)
after
Mitigation
Nature of effect (short
term / medium term /
long term, permanent /
temporary, direct /
indirect)
Construction
employment
120 FTE jobs
created
Construction Medium Low Minor beneficial Minor
beneficial
Short-term temporary
Employment 2 net additional
FTE jobs created
Operational High Negligible Negligible Negligible Permanent
Community
facilities
Loss of private
gym facilities
Operational Low Low Negligible Negligible Permanent
Eco Park, Land at M5 Junction 13, West of Stonehouse | Environmental Statement
December 2015
Page | 256
12 TRANSPORT AND ACCESS
Summary
12.1 The potential effects of the Revised Scheme have been assessed in terms of transport. A
comprehensive Transport Assessment (TA) has been prepared and examines in detail the
transport effects of the Revised Scheme on the existing transport system and provides the basis
for this EIA.
12.2 During the construction phase of the Revised Scheme, construction traffic is expected to result
in around a 2% increase in total traffic on the A419, and 12% - 13% increase in HGV traffic. The
majority of construction traffic is expected to be routed via the A419 and M5 to the west of the
site; no construction traffic will be permitted to use Grove Lane or Spring Hill. The construction
period is medium-term and therefore only temporary in its effects. Mitigation measures to
address the transport effects associated with the construction of the Revised Scheme will be
coordinated and implemented by means of a Construction Traffic Management Plan which will
be secured by a planning condition.
12.3 The Revised Scheme during its operational phase will increase travel demand in the area before
and after an FGRFC match. A number of improvement measures are embedded in the proposal
including:
• Signalised junction on the A419;
• Pedestrian crossing phase of the A419 within the traffic signals;
• Dualling of the A419 from the M5 Junction 13 to Chipmans Platt;
• The creation of a new footway to the south of the A419 carriageway, connecting to
Chipmans Platt, the southern part of Stonehouse and the canal towpath;
• Bus and emergency vehicle entrance from Grove Lane;
• Pedestrian and cycle access from Grove Lane, including additional footway and crossing
points.
12.4 Measures to encourage walking, cycling and public transport are to be implemented through a
Travel Plan.
12.5 The traffic modelling indicates that journey times on the A419 corridor between the A38 and
Horsetrough roundabout could increase by up to 1 minute 37 seconds during the match arrival
and departure periods on a Saturday and up to 45 seconds during the weekday evening match
arrival period. This could be perceived as a moderate negative effect by existing road users,
although infrequent.
12.6 There could be a moderate negative effect in terms of severance, amenity, delay and fear and
intimidation to users of PROW Footpaths Eastington 37 and 38, and National Cycle Route 45
before and after a match. However, this effect will be infrequent.
Eco Park, Land at M5 Junction 13, West of Stonehouse | Environmental Statement
December 2015
Page | 257
12.7 In terms of frequency, based on the 2017 – 2018 season, FGRFC home matches are expected to
occur approximately thirty times per year, or two to three times per month on average. Dates
and times of matches will be known in advance from the FGRFC website. Given the relative
infrequency of home matches, and the fact that the timing of a non-match related journey
(vehicular, by cycle or on foot) could be adjusted if required to minimise the effect on an
individual, the moderate negative effect before and after matches is considered acceptable.
12.8 On non-match days, pedestrians and cyclists could experience a moderate positive effect as a
result of the introduction of the traffic signal controlled crossing of the A419 and improvements
at Chipmans Platt roundabout. Drivers could experience a moderate positive effect as a result
of the dualling of the A419 between the M5 Junction 13 and Chipmans Platt.
12.9 It is concluded that the additional travel demand can be safely and satisfactorily accommodated
on the local transport network with the above improvement measures incorporated into the
proposals.
Introduction
12.10 This chapter considers the potential significant effects of the Revised Scheme in terms of
transport and access.
12.11 A comprehensive Transport Assessment (TA) has been prepared and forms RS Appendix 12.1 to
this ES. The TA includes more detailed traffic and transport information, and examines the
transport effects of the Revised Scheme on the existing transport system. It provides the basis
for this assessment.
12.12 This chapter and accompanying appendices replace previous documents in connection with Eco
Park.
Legislation, Policy and Guidance
12.13 The assessment, and the TA, has been carried out with reference to national and local policy
and guidance, itemised below.
National Planning Policy Framework, 2012 (NPPF)109
12.14 Paragraph 14 of the NPPF states that a presumption in favour of sustainable development should
be seen as a golden thread running through both plan-making and decision taking. When
development is likely to generate significant movement, the NPPF states that plans and decisions
should ensure that such developments are located “where the need to travel will be minimised
and the use of sustainable travel modes can be maximised. However, this needs to take account
of policies set out elsewhere in this Framework, particularly in rural areas.” (Paragraph 34.)
Paragraph 32 states that “development should only be prevented or refused on transport grounds
where the residual cumulative impacts of development are severe.”
109 DCLG (2012) National Planning Policy Framework. DCLG: London. Available:
https://www.gov.uk/government/uploads/system/uploads/attachment_data/file/6077/2116950.pdf. Last accessed
23rd October 2017.
Eco Park, Land at M5 Junction 13, West of Stonehouse | Environmental Statement
December 2015
Page | 258
Planning Practice Guidance, 2014110111
12.15 The Government’s Planning Practice Guidance to the NPPF was launched as a web-based
resource by DCLG in March 2014, and includes guidance on travel plans, transport assessments
and statements in decision-taking, as well as on Environmental Impact Assessment.
Highways England: The strategic road network – Planning for the future, 2015112
12.16 Since April 2015, Highways England has been responsible for operating, maintaining and
improving the strategic road network in England, which includes the M5 motorway. The
document ‘The strategic road network: Planning for the future’, published in September 2015,
describes the approach that Highways England takes to engaging in the planning system and the
issues considered in relation to draft planning documents and planning applications. Paragraph
101 explains that assessment should be carried out at opening year to determine the type and
extent of mitigation needed. Assessment at a later date is used to determine the risk which will
transfer to Highways England; this should be either a date 10 years’ after the registration of the
planning application (which was registered in 2016) or the end of the Local Plan period (2031),
whichever is later.
12.17 For this assessment the opening year is 2021, and the forecast year is 2031, the end of the Local
Plan period (see below).
Gloucestershire’s Local Transport Plan 2015-2031113
12.18 Gloucestershire County Council (GCC) adopted its fourth Local Transport Plan (LTP4) in June
2016. The overarching strategy acts as guidance on how GCC will manage the transport network
in Gloucestershire up to 2031. The overall vision of LTP4 is for a resilient transport network that
enables sustainable economic growth by providing door to door travel choices. The LTP is
structured around a transport picture of Gloucestershire based on a geographical patchwork of
travel corridors, each of which has distinctive transport opportunities and pressures. This is
addressed through six area Connecting Places Strategies (CPS).
12.19 The Stroud CPS explains that by concentrating development within or adjacent to the District’s
larger settlements, the strategy should make delivery of new and improved transport
infrastructure easier. Potential links to rail, bus and other forms of public transport and the
strategic road network are all maximised by choosing to locate major employment growth at the
larger settlement areas of Stroud, Cam and Stonehouse.
110 Department for Communities and Local Government (DCLG). (2014). Travel Plans, Transport Assessments and
Statements in Decision-Taking Guidance. DCLG: London. Available:
http://planningguidance.communities.gov.uk/blog/guidance/travel-plans-transport-assessments-and-statements.
Last accessed 23rd October 2017. 111 Department for Communities and Local Government (DCLG). (2017). Environmental Impact Assessment
Guidance. DCLG: London. Available: https://www.gov.uk/guidance/environmental-impact-assessment. Last
accessed 23rd October 2017. 112 Highways England. (2015). The strategic road network Planning for the future: A guide to working with Highways
England on planning matters. Birmingham: Highways England. Available:
https://www.gov.uk/government/uploads/system/uploads/attachment_data/file/461023/N150227_-
_Highways_England_Planning_Document_FINAL-lo.pdf. Last accessed 23rd October 2017. 113 Gloucestershire County Council (GCC). (2016). Gloucestershire’s Local Transport Plan 2015-2031 Gloucester:
GCC. Available: http://www.gloucestershire.gov.uk/media/2190/1_-_overarching_strategy_june_2016-66789.pdf.
Last accessed 23rd October 2017.
Eco Park, Land at M5 Junction 13, West of Stonehouse | Environmental Statement
December 2015
Page | 259
12.20 Short term capital priorities (2015 – 2021) for Stroud CPS include improvements for the A419
corridor, Stonehouse. Long term capital priorities include access improvements to national cycle
route 45, Stroud. However, the Stroud CPS notes that the identification of priorities does not
reflect a commitment by GCC for funding.
Strategic Economic Plan for Gloucestershire (SEP), 2014114115
12.21 In 2012, the Government confirmed a significant change in the way funding of major transport
schemes is allocated. Responsibility for major schemes is now devolved to the Local Enterprise
Partnerships (LEPS) through new Strategic Economic Plans (SEPs). The LEP for Gloucestershire is
GFirst LEP.
12.22 Under the Gloucestershire Growth Deal, the Government has agreed to invest £4.4m by 2020 to
2021 via GFirst LEP for junction improvements and carriageway widening within the A419
Stonehouse corridor to support planned growth, improve access to jobs and support the efficient
movement of goods. According to information provided at the public share events held in June
2017, the aim is to commence construction during Summer 2018, and complete during Summer
2019.
12.23 The Eco Park project was successfully short listed for LEP Growth Deal funding in 2016.
Stroud District Local Plan 2015116 (SDLP)
12.24 SDLP 2015 was adopted by Stroud District Council (SDC) on 19 November 2015 and covers the
period 2015 to 2031.
12.25 Strategic objective SO4 under the heading ‘Economy and infrastructure’ is relevant to the Revised
Scheme. SO4 is aimed at “promoting healthier alternatives to the use of the private car and
seeking to reduce CO2 emissions by using new technologies and encouraging an integrated
transport system to improve access to local goods and services.”
12.26 Site Allocations Policy SA2 West of Stonehouse (WoS) allocates land between the Oldends
industrial estate and Grove Lane, immediately east of the Revised Scheme Site, for mixed use
development; a planning application (Reference 14/0810/OUT) received planning consent in
April 2016.
12.27 Delivery Policy EI11, on promoting sport, leisure and recreation, states that planning applications
for new sports, leisure, cultural and recreational facilities will be permitted provided that they
meet a number of criteria including those relating to accessibility by sustainable modes of
transport. The importance of transport networks which deliver a high level of accessibility to key
114 GFirst LEP. (2014). Strategic Economic Plan for Gloucestershire. Available: http://www.gfirstlep.com/about-
us/our-vision/strategic-economic-plan/. Last accessed 23rd October 2017. 115 Gloucestershire County Council (GCC), (2016). Stonehouse A419 Improvements. Gloucester: GCC. Available:
http://www.gloucestershire.gov.uk/roads-parking-and-rights-of-way/major-projects/stonehouse-a419-
improvements/. Last accessed 23rd October 2017. 116 Stroud District Council. (2015). Your district Your future Stroud District Local Plan Adopted November 2015.
Stroud District Council: Stroud. Available: http://www.stroud.gov.uk/docs/planning/planning_strategy.asp. Last
accessed 20th November 2015.
Eco Park, Land at M5 Junction 13, West of Stonehouse | Environmental Statement
December 2015
Page | 260
services and facilities is emphasised in Delivery Policy EI12 on promoting transport choice and
accessibility. Where appropriate, new developments will be required to connect into the
surrounding infrastructure and contribute towards new or improved walking, cycling and rail
facilities within the District and the provision of an integrated public transport network across
the District.
Eastington Neighbourhood Development Plan (NDP) 117
12.28 SDC brought the Eastington Neighbourhood Plan (NDP) into force on 27th October 2016, and it
now forms part of the statutory Development Plan for Stroud District.
12.29 Eastington NDP has four main themes, including Infrastructure. The infrastructure objectives
include:
• “to support development proposals that conserve or enhance the route, character,
function and recreational value of Public Rights of Way (PROW)
• to ensure any new development allows for adequate car and bicycle parking provision.”
12.30 Policy EP9: Public Rights of Way and Wildlife Corridors states that “new development should
protect the existing rights of way network and its ambiance. Where public footpaths or
bridleways are routed or realigned through new development, they should be designed as part of
landscaped wildlife corridors rather than being routed along estate road pavements as part of
the highway network.”
Assessment Methodology and Significance Criteria
Qualifications and Experience
12.31 This chapter on Transport and Access has been prepared by Caroline Jane Mumford, Associate
Director of PFA Consulting Ltd, a civil engineering and transport planning consultancy of Stratton
Park House, Wanborough Road, Swindon.
12.32 Caroline Mumford has an MSc in Transportation and Traffic Planning, and is a chartered member
of the Institute of Logistics and Transport, a member of the Chartered Institution of Highways
and Transportation, and a member of the Transport Planning Society. She has over 30 years’
experience in the field of transport assessment and the preparation of transport chapters for
Environmental Statements.
Transport Assessment Methodology
12.33 The methodology for the assessment of traffic predicted to be generated by the Revised Scheme
is set out in the TA (RS Appendix 12.1) and summarised here.
Consultation
12.34 A transport scoping study for Eco Park was submitted to GCC and Highways England in August
2015. Comments were received from Highways England in late August 2015 and from GCC in
117 Eastington Parish Council (2016). Neighbourhood Development Plan 2015 – 2031. Available
https://www.stroud.gov.uk/media/208406/eastington-ndp-referendum-version_typos-correct-ready-for-adoption-
oct-2016.pdf Last accessed 22nd November 2017.
Eco Park, Land at M5 Junction 13, West of Stonehouse | Environmental Statement
December 2015
Page | 261
September 2015. A draft of the Transport Assessment and ES Transport and Access Chapter were
submitted to GCC and Highways England via SDC in October 2015.
12.35 A TA and associated documents were submitted in support of the Eco Park application (Reference
S.16/0043/OUT) in January 2016. A number of consultations and discussions were subsequently
held with GCC and Highways England. Further submissions in response to discussions were made
in July 2016, September 2016, February 2017 and July / August 2017.
12.36 A transport scoping study for the Revised Scheme was submitted to GCC and Highways England
in mid-November 2017, and a response on behalf of Highways England was received in late
November.
12.37 The outcomes from all these consultations and discussions have been taken into account in the
preparation of the TA for the Revised Scheme (RS Appendix 12.1).
Existing Transport Conditions
12.38 Existing transport conditions in the vicinity of the Revised Scheme are described in Section 3 of
the TA (RS Appendix 12.1). This includes a summary of the traffic surveys undertaken during
September 2015, a review of road safety and a review of options for sustainable travel.
The Revised Scheme
12.39 The Revised Scheme, including means of access, is described in transport terms in Section 4 of
the TA (RS Appendix 12.1).
Trip Generation and Distribution
12.40 The methodology for the assessment of trip generation and distribution is described in Section 5
of the TA (RS Appendix 12.1). Trip generation by the Forest Green Rovers Football Club (FGRFC)
Stadium during a home match has been estimated for a full 5,000 capacity event as requested
during consultation to allow for the ‘worst case’. Modal split has been based upon surveys of car
occupancy at the current FGRFC New Lawn ground, and on an assessment of the potential for
walking, cycling and bus / coach travel to the Site.
12.41 Trip distribution has been based upon postcode data for advance ticket sales provided by FGRFC.
In terms of assignment, the road network in the immediate vicinity of the site is straightforward,
with limited route choice options. Distributed traffic has therefore been manually assigned to
the most logical route.
Effect on the Road Network
12.42 The methodology for the assessment of the effect on the road network is set out in Section 6 of
the TA (RS Appendix 12.1).
12.43 The traffic effect of the Revised Scheme on the operation of the surrounding highway network
has been assessed for the following time periods:
• Saturday 14:00 – 15:00 – match day arrivals
• Saturday 17:00 – 18:00 – match day departures
• Weekday 18:00 – 19:00 – match day arrivals
Eco Park, Land at M5 Junction 13, West of Stonehouse | Environmental Statement
December 2015
Page | 262
12.44 Departures from weekday matches occur after 21:30 in the evenings, when background traffic
flows are low and fewer people are expected to use the PROW in the area, and this period has
therefore not been included in the assessment.
12.45 The assessment has been undertaken for the 2015 baseline, and for the 2021 opening year and
2031 forecast year without and with the Revised Scheme. The 2021 and 2031 baseline scenarios
include:
• Background traffic growth irrespective of the FGRFC Stadium and WoS development;
• Development WoS allocated in SDLP 2015 and consented in April 2016; and
• The A419 Stonehouse corridor improvements funded under the Gloucestershire Growth
Deal, expected to be completed in summer 2019.
12.46 In accordance with the Highways England document ‘The strategic road network: Planning for
the future’, the assessment at the 2021 opening year is used to determine mitigation
requirements, whilst the 2031 forecast year assessment provides an indication of the future
demands for the benefit of the highway authority.
12.47 Existing and predicted total two way traffic flows are set out on RS Figures 12.1 and 12.2 for a
Saturday and RS Figure 12.3 for a weekday.
12.48 Within the TA (RS Appendix 12.1), roundabouts have been modelled using the TRL software
program ‘Junctions 9’. The operational performance is summarised in Section 6 of the TA (RS
Appendix 12.1) for all approach arms and movements in terms of their Ratio of Flow / Capacity
(RFC), maximum queues in vehicles and maximum queuing delay in seconds per vehicle.
12.49 Traffic signal controlled junctions, including the proposed site access, have been modelled using
the JCT Consultancy software program LinSig. The operational performance is summarised in
Section 6 of the TA (RS Appendix 12.1) for all approach arms and movements in terms of their
Degree Of Saturation (DOS), average delay in seconds per Passenger Car Unit (PCU) and mean
max queue in PCUs. The practical reserve capacity (PRC) is also provided for each scenario.
12.50 During discussions on the Eco Park application both Highways England and GCC requested that a
micro-simulation model should be developed for the A419 corridor in the vicinity of the Site. An
S-Paramics micro-simulation model has been prepared covering the A419 from the A38 west of
the M5 to Horsetrough Roundabout in Stonehouse, based upon the traffic surveys undertaken
in September 2015 and described in Section 3 of the TA (RS Appendix 12.1). The report on the
S-Paramics traffic model forms RS Appendix 12.2 to this chapter.
12.51 The junctions assessed are identified on RS Figure 12.4.
Environmental Assessment Methodology
12.52 The EIA in relation to transport and access has been based upon the Guidelines for the
Environmental Assessment of Road Traffic (the IEMA Guidelines)118. The IEMA Guidelines
118 Institute of Environmental Management & Assessment (IEMA). (1993). Guidelines for the Environmental
Assessment of Road Traffic (IEMA Guidelines), 1993. IEMA: Lincoln
Eco Park, Land at M5 Junction 13, West of Stonehouse | Environmental Statement
December 2015
Page | 263
suggest in Paragraph 3.15 that two broad rules-of-thumb can be used as a screening process to
delimit the scale and extent of the assessment. These are:
‘Rule 1 include highway links where traffic flows will increase by more than 30% (or the number of
heavy goods vehicles will increase by more than 30%)
Rule 2 include any other specifically sensitive areas where traffic flows have increased by 10% or
more.’
12.53 These rules-of-thumb form the starting point for the assessment of effects. Paragraph 3.16 of
the IEMA Guidelines comments that projected changes in traffic flows of 10% or less create no
discernible environmental impact. Paragraph 3.20 explains that sensitive locations under Rule 2
include accident black-spots, conservation areas, hospitals, and routes with high pedestrian
flows.
12.54 Based upon these rules-of-thumb, and the findings of the TA (RS Appendix 12.1), the Study Area
for this chapter covers the A419 / A38 roundabout, Junction 13 on the M5, the A419 / Grove
Lane / Spring Hill roundabout at Chipmans Platt, Oldends Lane roundabout, Downton Road traffic
signals and Horsetrough roundabout together with the length of the A419 linking these junctions.
These junctions and the relevant section of the A419 can be identified on RS Figure 12.4.
12.55 The Revised Scheme is not intended to be accessible to the public except during matches.
12.56 The significance of the transport effects of the Revised Scheme is considered in the context of
the following subject areas, which are based on the IEMA Guidelines:
• Severance;
• Pedestrian Delay;
• Pedestrian Amenity;
• Fear and Intimidation;
• Driver Delay;
• Accidents and Safety.
12.57 Hazardous Loads have not been included because no hazardous loads are anticipated.
12.58 Air quality and dust effects are addressed in Chapter 13 and noise and vibration effects are
addressed in Chapter 15. Traffic data prepared as part of the TA work has been provided, and
used as the basis for the air quality and noise assessments.
12.59 The groups and special interests that may be affected by the Revised Scheme have been
considered and the following list of potential ‘receptors’ has been identified, based upon
Paragraph 3.20 of the IEMA Guidelines:
• Sensitive groups including children, the elderly and the disabled;
• Accident ‘black spots’;
• Highway corridor operating close to or over capacity;
• People walking;
Eco Park, Land at M5 Junction 13, West of Stonehouse | Environmental Statement
December 2015
Page | 264
• People cycling;
• Sensitive locations – schools, hospitals and town centre.
Significance Criteria
12.60 To record the likely significant environmental effects of the Revised Scheme, the following
methodology has been adopted.
12.61 First a magnitude of change scale in respect of each of the transport and access subject areas is
defined in Table 12.1. This scale is based on the thresholds identified in the IEMA guidelines
supplemented by best practice and professional judgement.
Table 12.1: Magnitude of Change Scale
Subject Area
Magnitude of Change
Substantial Medium Minor Negligible
Severance
Change in traffic
flow of over 60%
Change in traffic
flow of 30% to
60%
Change in traffic
flow of 10% to
30%
Change in traffic
flow of less than
10%
Driver Delay
Change to journey
time that would
be noticeable to
all drivers
Change to journey
time that would
be noticeable to
most drivers
Change to journey
time that would
be noticeable to
some drivers
No change to
journey time or a
change that would
not be noticeable
to drivers
Pedestrian Delay
Change in traffic
flow of over 60%
Change in traffic
flow of 30% to 60
Change in traffic
flow of 10% to
30%
Change in traffic
flow of less than
10%
Pedestrian
Amenity
Change in traffic
flow of over 60%
Change in traffic
flow of 30% to
60%
Change in traffic
flow of 10% to
30%
Change in traffic
flow of less than
10%
Fear and
Intimidation
Change in traffic
flow of over 60%
Change in traffic
flow of 30% to
60%
Change in traffic
flow of 10% to
30%
Change in traffic
flow of less than
10%
Accidents and
Safety
Personal injury
accident rate
changed and
above national
average
Personal injury
accident rate
changed but
below national
average
Slight change to
personal injury
accident rate
No change to
personal injury
accident rate
12.62 A Sensitivity of Receptor Scale is defined in Table 12.2.
Eco Park, Land at M5 Junction 13, West of Stonehouse | Environmental Statement
December 2015
Page | 265
Table 12.2: Sensitivity of Receptor Scale
High Medium Low / Negligible
Sensitive groups including
children, elderly and disabled
Accident ‘black spots’
Sensitive locations – schools,
hospitals and town centre
People walking
People cycling
Accidents at national average
Key highway junction operating
close to or over capacity
No sensitive groups or locations
No pedestrians or cyclist
Accidents below national
average
Key highway junction operating
within capacity
12.63 A matrix is then developed which identifies the significance of the effects as follows.
Table 12.3: Matrix for determining the level of effects
Sensitivity of receptor/ Receiving Environment to Change/ Effect
High Medium Low Negligible
Ma
gn
itu
de
of
Ch
an
ge
/ e
ffe
ct Substantial Major Moderate Minor Negligible
Medium Moderate Moderate Minor Negligible
Minor Minor Minor Minor Negligible
Negligible Negligible Negligible Negligible Negligible
12.64 As is highlighted in the table, Major and Moderate effects are considered significant within the
meaning of the EIA Regulations.
12.65 The significance of the effects is also assessed in relation to the sensitivity of the receptor,
whether the effects are temporary / short term or permanent / long term, and how frequently
they occur. Chapter 2 explains that short term has been considered as less than one year,
medium term effect as between one and ten years in duration, and long term as greater than
ten years.
Baseline Conditions
Site Description and Context
12.66 The Site is located on land adjacent to Junction 13 of the M5 Junction, west of Stonehouse near
Stroud (see also RS Figure 1.1). The Revised Scheme, described in more detail in Chapter 5, is for
a 5,000 capacity football stadium for Forest Green Rovers Football Club (FGRFC) to the north of
the A419. The proposal incorporates other ancillary uses (Use Class D2) within the stadium
structure itself, which will include, inter alia, cafes, bars, FGRFC Club Shop, changing rooms and
private gym for FGR team players. The proposal also includes two full-sized grass pitches (the
same size as the stadium pitch) and a goal practice area for First Team use only.
12.67 None of the outlets will be available to the public except during matches.
2015 Baseline
Eco Park, Land at M5 Junction 13, West of Stonehouse | Environmental Statement
December 2015
Page | 266
12.68 Baseline information collected during the preparation of the TA (RS Appendix 12.1) is
summarised in Table 12.4.
Table 12.4: Baseline Information
Source Information
Site Visits / OS Mapping / Topographic
Survey
Existing Highway Network
Traveline South West Public Transport Information
Gloucestershire County Council Collision Data
Axiom Traffic Ltd Traffic Surveys
Forest Green Rovers Football Club Attendance Figures, Postcode Data for Advance Ticket
Sales
Existing Road Network
12.69 The A419 forms the main road corridor into Stonehouse and Stroud from the west. To the west
the A419 has a grade separated roundabout junction with the M5 (Junction 13) and, beyond the
M5, a roundabout junction with the A38 south of Whitminster. In this area the A38 runs parallel
to the M5 and provides an alternative route between Bristol and Gloucester. The M5, and the
section of the A38 entering Gloucester, form part of the strategic road network (SRN). To the
east the A419 continues to Cirencester, where it joins the A417 / A419 strategic route linking the
M4 at Swindon with the M5 at Gloucester.
12.70 The section of the A419 fronting the site, between the M5 and Chipmans Platt Roundabout, is a
single carriageway road subject to the national 60mph speed limit. There is no street lighting
and no footway along this section. Immediately adjacent to the site there are laybys which are
subject to a two hour waiting restriction between 8am and 6pm, with no return within four
hours. The layby on the northern side contains a snack waggon operating under licence from
SDC.
12.71 Chipmans Platt roundabout to the south east of the site forms the junction between the A419,
Spring Hill to the south and Grove Lane to the north, and is street lit. A service area is located at
this junction, and includes a filling station, a coffee shop and a hotel. Entrance is from the
roundabout, with exit on to Grove Lane to the north.
12.72 South east of Chipmans Platt, the A419 continues around the southern part of Stonehouse
through a number of junctions, including Oldends Lane, Downton Road and Horsetrough, to
Stroud.
12.73 North of Chipmans Platt, Grove Lane leads north and west to join the A38 at Whitminster. It
forms part of NCN Route 45. A weight restriction of 7.5t except for loading applies along the
whole length of Grove Lane from Chipmans Platt to the A38. At present, the southernmost
section of Grove Lane is a two-lane single carriageway, with street lighting as far as the service
area exit and a footway on the eastern side, and subject to a 50mph speed limit. The footway
Eco Park, Land at M5 Junction 13, West of Stonehouse | Environmental Statement
December 2015
Page | 267
stops at the northern boundary of the service area compound, where Eastington Footpath 36
leads off to the north east. North of the service area exit (and north of the proposed WoS access),
the width of Grove Lane reduces to around 6 – 6.1m.
12.74 In future, from Chipmans Platt into the consented WoS development, Grove Lane is understood
to be proposed as a 6.75m wide road, suitable for use as a bus route. The WoS proposals for
Grove Lane are understood to include traffic calming features in the form of a Gateway north of
the WoS entrance, to inhibit rat running between Chipmans Platt and the A38.
12.75 A 40mph speed limit commences on the approach to the settlement of Westend, just to the
south of the Ecotricity landholding frontage. The speed limit returns to 50mph to the south east
of the bridge over the M5. Within Westend, and northwards to the A38, Grove Lane reduces in
width to 5m or less in places. Grove Lane has a priority junction with the A38 / School Lane at
Whitminster, with left turns out permitted only, although no physical measures to enforce this
are in place.
12.76 South of Chipmans Platt, Spring Hill / Alkerton Road leads south west to the village of Eastington
where it has a roundabout junction with Bath Road. Bath Road is the former A419 and leads
north west over the M5 to a traffic signal controlled junction with the A38.
Road Safety
12.77 Collision data have been obtained from GCC for the roads surrounding the Site. The collision data
cover a period of five years from 1 August 2012 to 31 July 2017. Collisions in the immediate
vicinity of the Site, excluding the M5 main carriageway, have been analysed. Out of 17 accidents,
six (all involving a moped / motorcycle, cyclist or pedestrian) resulted in serious injury and the
remainder resulted in slight injury. More details are given in the TA (RS Appendix 12.1).
12.78 A COBALT analysis of the collision records has been undertaken, to determine whether the
accident record is at, above or below the national average. The results are summarised in Table
12.5. Grove Lane is divided into a number of links in accordance with the speed limit, since
speeds affect the predicted accident rate.
Eco Park, Land at M5 Junction 13, West of Stonehouse | Environmental Statement
December 2015
Page | 268
Table 12.5: Summary of COBALT analysis
Link / Junction Expected Accident Rate Actual Accident Rate
Link 1 A38 from Grove Lane to A419 0.2 0.6
Link 2 A419 from A38 to M5 0.3 0.0
Link 3 A419 from M5 to Chipmans
Platt
0.6 0.0
Link 4 Grove Lane (50mph, A419 to
Nupend)
0.0 0.0
Link 5 Grove Lane (40mph, Nupend -
Westend)
0.1 0.4
Link 6 Grove Lane (50mph, Westend
to A38)
0.2 0.0
Link 7 A38 from A419 to Frome
Bridge
0.4 0.2
Junction 1 - A38 / A419 Roundabout 3.4 0.0
Junction 2 - A38 / Grove Lane /
School Lane
1.4 0.4
Junction 3 - M5 Junction 13 3.2 1.0
Junction 4 - A419 / Grove Lane /
Spring Hill (Chipmans Platt)
5.2 0.6
12.79 The actual accident rate is at or below the expected (national average) accident rate for all links
and junctions, except for the A38 between Grove Lane and the A419, and for Grove Lane from
Nupend to Westend.
Existing Traffic Conditions
12.80 To establish existing traffic levels on the highway network in the Study Area, traffic surveys were
carried out by an independent specialist survey company in September 2015. The surveys were
undertaken during the afternoon of Saturday 12th September to cover a typical football match
period, and during the AM and PM peak periods on Tuesday 15 September. Hourly traffic flows
are summarised on RS Figure 12.1 for the Saturday match arrival time (14:00 – 15:00) on RS
Figure 12.2 for the Saturday match departure time (17:00 – 18:00) and on RS Figure 12.3 for the
weekday match arrival time (18:00 – 19:00).
12.81 Weekday FGRFC matches, which take place less frequently than Saturday matches, occur outside
the normal road network peak hours, when background traffic flows are lower. Existing total
two-way hourly traffic flows in the vicinity of the Revised Scheme are summarised in Table 12.6
for a Saturday and Table 12.7 for a weekday.
Eco Park, Land at M5 Junction 13, West of Stonehouse | Environmental Statement
December 2015
Page | 269
Table 12.6: Summary of Saturday Total Two Way Hourly Traffic Flows
Location 14:00 – 15:00 17:00 – 18:00
A38 North of A419 1,034 808
A38 South of A419 1,294 1,183
A419 West of M5 840 725
A419 East of M5 1,281 1,270
Grove Lane 195 172
Spring Hill 358 346
Table 12.7: Summary of Weekday Total Two Way Hourly Traffic Flows
Location 08:00 – 09:00 17:00 – 18:00 18:00 – 19:00
A38 North of A419 974 952 698
A38 South of A419 1,476 1,583 1,068
A419 West of M5 1,125 1,133 736
A419 East of M5 1,787 2,274 1,539
Grove Lane 483 249 194
Spring Hill 699 698 445
12.82 Tables 12.6 and 12.7 confirm that hourly traffic flows on a Saturday are generally below those
during weekday peak hours, the exception being the A38 north of the M5 early on Saturday
afternoon. Table 12.7 shows that on a weekday, traffic flows during the hour 18:00 – 19:00,
when a significant proportion of traffic will arrive for a 19:45 kick-off, is well below the level in
the preceding hour 17:00 – 18:00.
12.83 Delay to traffic normally arises as a result of congestion at junctions. Traffic capacity and delay
in the 2015 base year has been analysed at the following junctions (identified on RS Figure 12.4)
which make up the Study Area:
• A419/A38 roundabout;
• M5 Junction 13 roundabout;
• A419/Spring Hill/Grove Lane roundabout (Chipmans Platt);
• A419 / Oldends Lane roundabout;
• A419 / Downton Road traffic signals;
• A419 / Bath Road / Ebley Road roundabout (Horsetrough).
12.84 The analysis was undertaken using the Junctions 9 ARCADY module for the roundabouts, and
LinSig for the Downton Road traffic signals; more details are contained in the TA (RS Appendix
12.1). In summary, on a Saturday afternoon and on a weekday evening after the main peak hour
all junctions are operating within capacity without significant queues or delays.
Eco Park, Land at M5 Junction 13, West of Stonehouse | Environmental Statement
December 2015
Page | 270
12.85 In addition, the existing operation of the A419 corridor from the A38 to Horsetrough roundabout
was analysed with an S-Paramics microsimulation model. More details are contained in the S-
Paramics Report (RS Appendix 12.2). This includes a summary of eastbound and westbound
journey times between the A38 and Horsetrough roundabout for each scenario, reproduced in
Tables 12.11 and 12.2 below.
Walking and Cycling
12.86 There is currently no footway or cycleway alongside the A419 fronting the site.
12.87 PROW Footpath Eastington 37 crosses the A419 into the Site towards the eastern boundary, then
dividing into two paths, Eastington 37 and Eastington 38 (see RS Figure 10.2). No formal crossing
of the A419 is provided.
12.88 National Route 45 of the National Cycle Network, which links Chester with Salisbury via
Gloucester, Cirencester and Swindon, runs along Grove Lane to the north east of the Site, and
then south along Spring Hill south of Chipmans Platt for a short distance (see RS Figure 10.6
accompanying the LVIA). It offers a route for pedestrians and cyclists, largely off road, to
Stonehouse and Stroud.
Public Transport
12.89 Although no regular bus services directly pass the site at present, there are a number of bus
services in the area. Service 61 routes from Cheltenham to Dursley, via Stonehouse and Cam &
Dursley train station. It operates on a day time frequency of around 60 minutes on a weekday
and a Saturday, with one evening service in each direction. It travels along the A419 to Chipmans
Platt before turning south along Spring Hill towards Eastington. Service 64 starts in Stonehouse,
routeing to Bussage via Stroud. It also operates on a frequency of around 60 minutes throughout
the daytime on a weekday and a Saturday. Service 66S/66E routes between Gloucester and
Stroud, via Stonehouse High Street. It operates at a daytime frequency of 30 minutes in each
direction on a weekday and a Saturday, and hourly in the evenings.
12.90 Stonehouse station is approximately 4km to the east of the Site on the Gloucester to London line
and is served by the Great Western Railway. Cam & Dursley Station is located approximately
10km by road to the south of the Site; it is situated on the Bristol to Birmingham line and is
currently also served by the Great Western Railway. A feasibility study has been undertaken into
the reopening of the Stonehouse Bristol Road station, a little over 2km from the Site on the
Bristol to Birmingham line. The location for this station is safeguarded in the SDLP 2015.
2021 and 2031 Baseline
12.91 The opening year for this assessment is 2021; the FGRFC Stadium is assumed to be open for the
start of the 2021 - 2022 season. The forecast year is 2031, the end of the SDLP period.
Background traffic flows have been factored to 2021 and 2031 based upon the National
Transport Model (NTM) adjusted using TEMPRO (NTEM Dataset 7.0). This takes account of
changes in car ownership as well as local planning forecasts regarding housing and employment.
More details are given in Section 6 of the TA (RS Appendix 12.1).
12.92 Policy SA2 of SDLP 2015 allocates land to the west of Stonehouse for mixed use development;
planning application Reference S. 14/0810/OUT for up to 1,350 dwellings and 9.3 ha employment
Eco Park, Land at M5 Junction 13, West of Stonehouse | Environmental Statement
December 2015
Page | 271
plus local centre and primary school received consent in April 2016. The location of the WoS Site
is identified on RS Figure 18.1 of this ES. Traffic generation by the WoS development, derived
from the submitted WoS TA and subsequent documents, forms part of the 2021 and 2031
baselines.
12.93 The transport effects of other committed development in Stroud District, shown on RS Figure
18.1, are taken into account through the application of TEMPRO growth factors.
12.94 Improvements to the A419 corridor to be funded under the Gloucestershire Growth Deal are also
assumed to form part of the 2021 and 2031 baselines.
12.95 Hourly traffic flows in the 2021 and 2031 baselines including WoS are summarised on RS Figure
12.1 for the Saturday match arrival time (14:00 – 15:00), on RS Figure 12.2 for the Saturday match
departure time (17:00 – 18:00) and on RS Figure 12.3 for the weekday match arrival time (18:00
– 19:00).
12.96 Individual junction modelling was repeated for the 2021 and 2031 baselines. More details are
provided in the TA (RS Appendix 12.1). However, on both a Saturday afternoon and a weekday
evening all junctions assessed operated satisfactorily in the 2021 and 2031 baselines, without
significant queues or delays.
12.97 The operation of the A419 corridor from the A38 to Horsetrough roundabout was assessed with
an S-Paramics microsimulation model for the 2021 and 2031 baselines. More details are
contained in the S-Paramics Report (RS Appendix 12.2). This includes a summary of eastbound
and westbound journey times between the A38 and Horsetrough roundabout for each scenario,
reproduced in Tables 12.11 and 12.12 below.
Design Evolution
12.98 The planning application is an outline application, with all matters reserved save for access.
Consultations with GCC and Highways England, from prior to the submission of the original Eco
Park application in January 2016, have been taken into account in the development of the
Revised Scheme transport and access proposals.
12.99 The principal vehicle access will be from a new traffic signal junction on the A419 east of the M5
Junction 13. The proposed access includes the dualling of the A419 between the M5 Junction 13
and Chipmans Platt roundabout. The proposed layout for the access and dualling (Drawing
E191/01 Rev B) is reproduced in the TA (RS Appendix 12.1).
12.100 The provision of the access will result in the loss of the existing laybys on this section of the A419.
However, it has been agreed with GCC that the laybys can be re-provided on the A419 to the
west of the M5. More details are provided in the TA (RS Appendix 12.1).
12.101 The existing public footpath (Eastington Footpath 37) which crosses the A419 to the east of the
proposed access will be incorporated into a pedestrian crossing phase at the site access traffic
signals.
Eco Park, Land at M5 Junction 13, West of Stonehouse | Environmental Statement
December 2015
Page | 272
12.102 The proposed improvements also include a footway on the south side of the A419 from the
proposed access to Chipmans Platt, providing a link to the southern part of Stonehouse, and on
to Stroud via the canal towpath.
12.103 A second vehicular entrance for buses/ coaches and emergency vehicles only is proposed from
Grove Lane, as indicated on the Concept Plan (RS Figure 1.1 of this ES). This entrance will include
‘bus only’ signage plus an ANPR camera to enforce the restriction, and may be gated when not
in use. It will enable buses serving the WoS development to divert through the Site on match
days, without joining the flow of traffic entering via the main entrance from the A419. Coach
parking will be provided on site for away supporter coaches. The proposed layout for this
entrance (Drawing E191/05) is reproduced in the TA (RS Appendix 12.1).
12.104 A pedestrian and cycle access will be provided adjacent to the bus access from Grove Lane, and
will be kept open at all times to allow continued use of Eastington Footpath 38 as well as access
to the Stadium from the WoS development. A footway will be continued along Grove Lane to
connect with the WoS proposals. Crossing points will be located to the north of the proposed
entrance on Grove Lane, and at Nupend.
12.105 The public footpaths through the Revised Scheme will be re-assessed at the Reserved Matters
stage, and there is an intention that they will be incorporated into green links and landscape
corridors as appropriate, in accordance with Policy EP 9 of the Eastington NDP. This will ensure
improved integration into the landscape.
12.106 Within the Site, the area around the Stadium will be vehicle free during matches, as indicated on
the Concept Plan (RS Figure 1.1).
12.107 A total of 1,700 parking spaces is currently proposed within the Revised Scheme Site to cater for
the 5,000 capacity Stadium. This number of parking spaces is based upon the estimated modal
split for travel to the Stadium, discussed below.
12.108 Electric vehicle charging points will be provided within the parking area.
12.109 Up to 100 cycle parking spaces will be available initially, with scope to increase this number if
demand requires.
12.110 In summary, there is much embedded mitigation associated with the Revised Scheme for traffic
and transportation. This includes:
• Signalised junction on the A419;
• Pedestrian crossing phase of the A419 within the traffic signals;
• Dualling of the A419 from the M5 Junction 13 to Chipmans Platt;
• The creation of a new footway to the south of the A419 carriageway, connecting to
Chipmans Platt, the southern part of Stonehouse and the canal towpath;
• Bus and emergency vehicle entrance from Grove Lane;
• Pedestrian and cycle access from Grove Lane including additional footway and crossing
points;
• Car and cycle parking;
Eco Park, Land at M5 Junction 13, West of Stonehouse | Environmental Statement
December 2015
Page | 273
• Vehicle free area adjacent to the Stadium during matches;
• Electric vehicle charging points.
12.111 Without the embedded mitigation described above, the effects below would have greater
significance. However, with the embedded mitigation, most effects are reduced as the
embedded mitigation has reduced the sensitivity of the receptor or the magnitude of change
that the receptor might experience. In some cases, the embedded mitigation results in positive
effects at non-match times.
Potential Effects
Sensitivity of Receptors
12.112 The rule-of-thumb described in the EIA Methodology above suggests that highway links with an
increase in traffic flows of more than 30%, or more than 10% in specifically sensitive areas, should
be included in the assessment.
12.113 By reference to Table 12.2, Sensitivity of Receptor Scale, and Section 12.3, there are no sensitive
groups or locations and no pedestrian or cycle routes running alongside the A419 in the vicinity
of the Revised Scheme Site, west of Chipmans Platt roundabout. The sensitivity of the receptor
adjacent to the A419 in terms of sensitive groups or locations and pedestrians and cyclists is
therefore negligible. Only increases in traffic of more than 30% are relevant, in the light of the
rule-of-thumb described above.
12.114 However, Public Footpath Eastington 37 runs approximately north – south and crosses the A419
east of the access to the Revised Scheme. By reference to Table 12.2, the sensitivity of the
receptor in terms of Footpath 37 where is crosses the A419 is medium, so that increases in traffic
of more than 10% are considered relevant.
12.115 National Cycle Route 45 crosses the A419 from Spring Hill to Grove Lane at Chipmans Platt
roundabout and continues along Grove Lane, and may be used by walkers and cyclists. By
reference to Table 12.2, National Cycle Route 45 can be regarded as a receptor of medium
sensitivity, so that increases in traffic of more than 10% are relevant.
12.116 The accident rate on the A419 in the vicinity of the Revised Scheme, including the A38, M5 and
Chipmans Platt junctions, and on the 50mph sections of Grove Lane, is below the expected
national average (Table 12.5). By reference to Table 12.2 the sensitivity of the receptor in
relation to accidents and road safety on the A419 is low or negligible, so that only increases in
traffic of more than 30% are relevant.
12.117 Table 12.5 indicates that the accident rate on the 40mph section of Grove Lane from Nupend to
Westend is above the national average, as is the accident rate on the A38 between Grove Lane
and the A419. By reference to Table 12.2, the sensitivity of these two sections of road in terms
of road safety is high so that increases in traffic of more than 10% are relevant.
12.118 The Government has agreed to fund junction improvements within the A419 Stonehouse
Corridor under the Gloucestershire Growth Deal. By implication, Chipmans Platt, Oldends Lane,
Downton Road and Horsetrough are key junctions operating close to capacity during weekday
Eco Park, Land at M5 Junction 13, West of Stonehouse | Environmental Statement
December 2015
Page | 274
peak hours, and by reference to Table 12.2 can be regarded as a receptor with medium sensitivity
at peak periods, so that increases in traffic of more than 10% would be relevant. However, on a
Saturday and during a weekday evening after the peak hour the junctions along the A419 corridor
operate within capacity, as demonstrated within the TA (RS Appendix 12.1). Sensitivity can be
regarded as low or negligible, so that increases in traffic of more than 30% are relevant.
Construction
Traffic Estimates
12.119 Construction of the Revised Scheme will give rise to deliveries of materials and products that will
be transported by Heavy Goods Vehicles (HGVs). It is intended that excavated material will be
retained within the Site, to minimise HGV movements.
12.120 Construction, and associated deliveries, are expected to take place on weekdays and on Saturday
mornings only. More details of the construction schedule and associated traffic arrangements,
including phasing, routing, and more precise estimated vehicle numbers, will be identified at the
Reserved Matters stage and included as appropriate in a Construction Traffic Management Plan
which can be secured by condition.
12.121 However, at present it is estimated that there could be 100 HGV movements (50 in, 50 out) daily
at the peak of construction, with fewer on a Saturday. It is likely that a restriction might be placed
on HGV deliveries during peak hours. Assuming an 8-hour day for deliveries, this amounts to 6 –
7 HGVs or 12 to 14 HGV movements per hour or approximately one HGV movement every 4 to 5
minutes.
12.122 In addition, there will be construction employees on site, the number varying according to
construction activity. Again, more details will be available at a later stage in the planning process.
At this stage it is estimated that there could be 130 people on site at the peak, fitting out the
Stadium. This would give rise to a maximum of 260 vehicle movements per day (130 in, 130 out).
However, many construction companies transport their employees in work buses, particularly
for a development of this scale, and the employee vehicle trip generation is expected to be well
below this in practice. Furthermore, peak hours for travel to and from construction sites
generally occur before the peak hours for the normal road network peak hours. For example, a
condition of the WoS planning consent (Reference S.14/0810/OUT) restricts demolition or
construction works outside a building to 07:30 – 18:30 on Mondays to Fridays, and 08:00 – 17:00
on a Saturday. The expectation is that construction work will commence at around 07:30 – 08:00,
before the morning peak hour. In the location of the Revised Scheme, where there are few
existing buildings to be affected, construction may commence earlier than this.
12.123 The construction period is expected to be two to three years, or medium term as set out in
Chapter 2 of this ES, so that the effect of construction traffic will be temporary.
Increase in Traffic
12.124 Daily traffic flows on the A419 in 2015, as set out in the TA (RS Appendix 12.2), are summarised
in Table 12.8, together with the predicted increases arising from construction traffic. For this
assessment it is assumed that all construction employees will be on site on Saturday morning,
but that that HGV movements will reduce to 50 (25 in, 25 out).
Eco Park, Land at M5 Junction 13, West of Stonehouse | Environmental Statement
December 2015
Page | 275
Table 12.8: Increase in Daily Traffic Flows during Construction
Two Way Daily Traffic on A419 East of M5 (07:00 – 19:00)
Total Traffic HGVs
Existing Construc
tion
(Employ
ee plus
HGV)
Total %
Increase
Existing Construc
tion
(HGV)
Total %
Increase
Weekda
y
19,468 360 19,828 1.8% 812 100 912 12.3%
Saturda
y
14,082 310 14,392 2.2% 374 50 424 13.4%
12.125 Construction of the Revised Scheme is expected to result in increases of only 1.8% to 2.2% in
total traffic and 12.3% to 13.4% in HGV traffic on the A419. Construction traffic will not be
permitted to use Grove Lane or Spring Hill.
Severance, Pedestrian Delay, Pedestrian Amenity, and Fear and Intimidation
12.126 There are no existing buildings or pedestrian and cycle routes adjacent to the A419 between the
site access and the M5. Assuming that PROW Footpath Eastington 37 remains open (across the
A419) during construction, construction traffic is not expected to affect either this footpath or
National Cycle Route 45 where they cross the A419, as these recreational routes lie to the east
of the proposed site access, and construction traffic will primarily be routed from the M5 west
of the site access. By reference to Table 12.2, the sensitivity of the receptor in relation to
severance, pedestrian delay, pedestrian amenity, and fear and intimidation is negligible. By
reference to Table 12.1, the magnitude of the change in HGV traffic flow during construction is
expected to be minor (and negligible in terms of the change in total traffic flow). By reference
to Table 12.3, the level of the effect on Footpath Eastington 47 and NCN Route 45, where they
cross the A419, in terms of severance, pedestrian delay and amenity, fear and intimidation due
to traffic during construction would be negligible and therefore not significant within the
meaning of the EIA Regulations.
12.127 However, there is a possibility that it may become necessary to temporarily close PROW
Footpaths Eastington 37 and Eastington 38 within the Revised Scheme Site during construction.
The need or otherwise will be assessed as part of a Recreational Impact Assessment in a more
detailed Reserved Matters Applications.
12.128 If the footpaths remain open within the site during construction, since construction traffic will
be introduced in the vicinity of Footpaths Eastington 37 and 38 where there is currently no traffic
at all, by reference to Table 12.2 the sensitivity of the receptor is medium, and by reference to
Table 12.1 the magnitude of change would be substantial. By reference to Table 12.3 the level
of the effect in terms of severance, pedestrian delay and amenity, fear and intimidation due to
traffic during construction would be moderate and therefore significant within the meaning of
the EIA Regulations, but would be temporary.
Driver Delay
Eco Park, Land at M5 Junction 13, West of Stonehouse | Environmental Statement
December 2015
Page | 276
12.129 Few construction companies are located within Stonehouse or Stroud, and the majority of
construction traffic is expected to be routed via the A419 and the M5 to the west of the site. By
reference to Table 12.2, the sensitivity of the receptor here is low.
12.130 The rule-of-thumb described in the EIA Methodology above suggests that highway links with an
increase in traffic flows of more than 30% should be included in the assessment or more than
10% in specifically sensitive areas. The A419 is not a sensitive receptor, and the increase in both
total and HGV traffic due to construction is well below the suggested level of 30%.
12.131 By reference to Table 12.1, the magnitude of the change in driver delay during construction is
expected to be minor to negligible. By reference to Table 12.3, the level of effect in relation to
driver delay during construction is minor and therefore not significant within the meaning of
the EIA Regulations.
Accidents and Safety
12.132 The accident rate on the A419 in the vicinity of the Revised Scheme Site is below the national
average (Table 12.5). As discussed above by reference to Table 12.2, the sensitivity of the
receptor in relation to accidents and road safety on the A419 is low or negligible.
12.133 Properly managed construction traffic should not result in any change to the accident rate, and
by reference to Table 12.1 the magnitude of change in relation to personal injury accidents will
be negligible. By reference to Table 12.3, the level of effect in relation to accidents and safety
during construction is negligible, and therefore not significant within the meaning of the EIA
Regulations.
12.134 The above effects during construction are summarised on Table 12.15 at the end of this chapter.
Operation
Traffic Estimates
12.135 The FGRFC Stadium is intended to be open for the start of the 2021 - 2022 season. The opening
year for this assessment is therefore 2021; the forecast year is 2031, the end of the SDLP period.
As explained above, assessment is required at opening year to determine the type and extent of
mitigation needed. Assessment at a later date is used to determine the risk which will transfer
to the highway authority.
12.136 As set out within the FGRFC website,119a total of thirty matches are currently (as at the end of
November) programmed during the 2017 – 2018 season: twenty two on a Saturday; six on a
normal weekday evening; and two on Bank Holidays. Two of these are pre-season friendly
matches, twenty three are League matches, and five are cup / trophy matches; more matches
may be added to the programme depending on progress in the League and FA Cups.
12.137 FGRFC has achieved promotion from the National League to League 2 for the 2017-2018 season.
Attendance at home games at the New Lawn this season (up to the end of November 2017), as
obtained from the FGRFC website, is summarised in Table 12.9.
119 https://www.forestgreenroversfc.com/games/results-fixtures/first-team/2017-18
Eco Park, Land at M5 Junction 13, West of Stonehouse | Environmental Statement
December 2015
Page | 277
Table 12.9: Match Attendance at The New Lawn, 2017 – 2018 Season
Date Against Attendance Notes
Saturday 22 July Bristol Rovers 1,589
Saturday 29 July Kidderminster
Harriers
Not available
Saturday 5 August Barnet 3,171
Tuesday 8 August MK Dons 1,608 League Cup
Saturday 19 August Yeovil 2,615
Tuesday 29 August Newport County 1,090 LeagueTrophy
Saturday 9 September Exeter 2,909
Tuesday 12 September Lincoln City 1,887
Friday 22 September Swindon 3,305
Saturday 30
September
Accrington Stanley 2,594
Saturday 14 October Newport County 2,864
Saturday 28 October Morecambe 2,515
Tuesday 31 October Swansea City Not available League Trophy
Saturday 4 November Macclesfield 1,387 FA Cup
Saturday 18 November Crewe 2,221
Saturday 25 November Cheltenham Not available
Average Attendance 2,234
Note: Average attendance excludes Kidderminster Harriers, Swansea City and Cheltenham, for
which data are not available
12.138 The maximum attendance so far is 3,305 against ‘local’ side Swindon, with an average of 2,234.
However, to take the worst case for this assessment, a full 5,000 capacity stadium has been
assumed. The methodology for the assessment of trip generation by mode is set out in Section
5 of the TA (RS Appendix 12.1) and is based upon the following assumptions:
4% home supporters walk or cycle (170 walk / cycle in total)
800 home and away supporters travel by bus / coach
10% arrive by taxi or other lift, and don’t need to park, but vehicle makes a return
journey at both the start and end of the match
Private car occupancy 2.2
Eco Park, Land at M5 Junction 13, West of Stonehouse | Environmental Statement
December 2015
Page | 278
12.139 Since the estimate is for a full stadium, the predicted traffic flows are the same in both 2021 and
2031. Vehicle trip generation and parking demand for a 5,000 capacity match are summarised
in Table 12.10.
Table 12.10: Predicted Vehicles and Parking Demand: 5,000 Capacity Match
Total Crowd Total Cars One
Way Lifts & Taxis Parking Demand
5,000 1,882 188 1,694
12.140 Saturday matches commence at 15:00, and weekday evening matches at 19:45. Not all traffic
arriving for a match arrives in the hour before the start, and not all traffic leaves in the hour after
the finish. Arrival and departure profiles have been based upon the observed profiles at the
existing New Lawn ground and are:
Saturday
14:00 – 15:00 67.1% 1,389 vehicle trips (total two way)
17:00 – 18:00 76.2% 1,577 vehicle trips (total two way)
Weekday
18:00 – 19:00 55.3% 1,145 vehicle trips (total two way)
12.141 RS Figure 12.1 shows the predicted total two-way traffic flows in 2021 and 2031 without and
with the Revised Scheme for the Saturday arrival peak hour (14:00 – 15:00); RS Figure 12.2 shows
the predicted traffic flows for the Saturday departure peak hour (17:00 – 18:00) and RS Figure
12.3 shows the predicted traffic flows for the weekday arrival period (18:00 – 19:00). As
explained above, the WoS development and relevant highway improvements are included in
both 2021 and 2031.
Increase in Traffic
12.142 RS Figure 12.5 shows the percentage change in traffic flows with a Saturday home match in 2021
and 2031, and RS Figure 12.6 shows the percentage change for weekday evening match arrivals.
The greatest percentage impact occurs in the 2021 opening year; the percentage impact reduces
slightly in 2031, since the background traffic flows are greater as a result of general traffic growth.
This assessment therefore focusses on the effect in 2021.
12.143 The Magnitude of Change Scale in Table 12.1 sets out bands for change in traffic flow: less than
10%; 10% to 30%; 30% to 60%; and over 60%. Table 12.11 groups the road links within the Study
Area into these bands, based upon RS Figures 12.5 and 12.6.
Table 12.11: Summary of Percentage Change in Traffic Flows by Road Link
Saturday Weekday
14:00 – 15:00 17:00 – 18:00 18:00 – 19:00
Less than 10% A38, Grove Lane, M5
on slips, Bath Road
A38, Grove Lane, M5
off slips, Bath Road
A38, Grove Lane, M5
on slips, Bath Road
10% - 30% A419 West of M5 A419 West of M5
A419 West of M5,
M5 off slips, A419
from M5 to Site
Access
Eco Park, Land at M5 Junction 13, West of Stonehouse | Environmental Statement
December 2015
Page | 279
30% - 60%
M5 off slips, A419
from Site Access to
M5, A419 from
Chipmans Platt to
east of Horsetrough,
Spring Hill
M5 on slips, A419
from M5 to Site
Access, A419 from
Chipmans Platt to
Oldends Lane, A419
east of Horsetrough,
Spring Hill
M5 from Site Access
to Chipmans Platt,
A419 from Chipmans
Platt to east of
Horsetrough, Spring
Hill
Over 60%
A419 from Site
Access to Chipmans
Platt
A419 from Site
Access to Chipmans
Platt, A419 from
Oldends Lane to
Horsetrough
12.144 Increases in traffic on the A38, on Grove Lane and on Bath Road in Stonehouse are predicted to
be below 10%, and by reference to Table 12.1 and to the Rules of Thumb included in the IEMA
Guidelines (see Section 12.3 above) the magnitude of change is negligible, and there will
therefore be no discernible environmental impact in transport and access terms. These road
links are all therefore excluded from the assessment below.
12.145 Predicted increases in traffic on the A419 west of the M5 lie in the range 10% - 30% for all time
periods assessed. By reference to Table 12.2, the sensitivity of this section of the A419 as a
receptor is low to negligible, having no publicly accessible development or footways / cycleways
alongside, and no personal injury accidents over the past five years. By reference to Table 12.1
the magnitude of change is minor, and by reference to Table 12.3 the level of effect is minor to
negligible and therefore not significant within the meaning of the EIA Regulations. No further
assessment has therefore been undertaken for this road link.
12.146 Predicted increases in traffic on the A419 between the M5 and the site access lie in the range
20.1% to 34.0% for the periods analysed. By reference to Table 12.2, the sensitivity of this
section of the A419 as a receptor is low to negligible, having no publicly accessible development
or footways / cycleways alongside, and no personal injury accidents over the past five years. By
reference to Table 12.1 the magnitude of change is minor to medium, and by reference to Table
12.3 the level of effect is minor and therefore not significant within the meaning of the EIA
Regulations. No further assessment has therefore been undertaken for this section of the A419.
12.147 Predicted increases in traffic on the A419 between the site access and Chipmans Platt exceed
60% in both the match arrival and departure periods on a Saturday, and lie in the range 30% to
60% in the match arrival period on a weekday evening. Public Footpath Eastington 37 crosses
this section of the A419, and by reference to Table 12.2 the sensitivity of the receptor is therefore
medium. By reference to Table 12.1 the magnitude of change is medium to substantial, and by
reference to Table 12.3 the level of effect is moderate and therefore significant within the
meaning of the EIA Regulations. Further assessment has therefore been undertaken for this
section of the A419.
12.148 Predicted increases in traffic on the A419 between Chipmans Platt and Horsetrough generally lie
in the range 30% - 60% in both the Saturday match arrival and departure periods, and in the
weekday match arrival period. The exception is the section between Oldends Lane and
Eco Park, Land at M5 Junction 13, West of Stonehouse | Environmental Statement
December 2015
Page | 280
Horsetrough with a predicted increase of just over 60% in the Saturday match departure period.
Pedestrian and cycle facilities are provided in the vicinity of these sections of road, including NCN
45 which crosses the A419 to the east of Chipmans Platt roundabout. During match arrival and
departure periods, with a full 5,000 capacity Stadium, some junctions along the A419 corridor
are likely to be operating at close to capacity (see RS Appendix 12.1). By reference to Table 12.2
the sensitivity of the receptor is therefore medium. By reference to Table 12.1 the magnitude
of change is medium to substantial, and by reference to Table 12.3 the level of effect is moderate
and therefore significant within the meaning of the EIA Regulations. Further assessment has
therefore been undertaken for the A419 east of Chipmans Platt to Horsetrough.
12.149 Predicted increases in traffic on Spring Hill south of Chipmans Platt lie in the range 30% - 60% in
both the Saturday match arrival and departure periods, and in the weekday match arrival period.
NCN 45 uses this section of Spring Hill. By reference to Table 12.2 the sensitivity of the receptor
is therefore medium. By reference to Table 12.1 the magnitude of change is medium, and by
reference to Table 12.3 the level of effect is moderate and therefore significant within the
meaning of the EIA Regulations. Further assessment has therefore been undertaken for Spring
Hill.
12.150 For comparison, on the day of a match there can be a significant increase in traffic within the
residential areas in the vicinity of the existing FGRFC ground at The New Lawn in Nailsworth.
Based upon automatic traffic counts (ATCs) undertaken on Nympsfield Road in September and
October 2015, this can range from 300 – 400 additional vehicles each way for an average match
to 700 – 800 additional vehicles each way for the match against Cheltenham Town, with an
attendance of 3,127. This includes those parking on site or at Nailsworth Primary School, and
those searching for parking in surrounding streets. This compares with background traffic flows
of some 4,300 – 4,800 vehicles per day on Nympsfield Road, and is an issue for residents and
supporters alike.
12.151 The hourly increases in traffic on Nympsfield Road on two match days in September 2015, based
upon the ATCs, are summarised in Table 12.12 for the Saturday arrival and departure and
weekday arrival periods.
Eco Park, Land at M5 Junction 13, West of Stonehouse | Environmental Statement
December 2015
Page | 281
Table 12.12: Increases in Match Traffic on Nympsfield Road approaching The New Lawn
Saturday
Direction
26.09.15 03.10.15 Difference
% Increase
Time v Gateshead No Match
14:00 – 15:00 Westbound (arrivals) 368 162 +206 127%
17:00 - 18:00 Eastbound (departures) 383 156 +227 146%
Tuesday
Direction
22.09.15 29.09.15 Difference % Increase
v Cheltenham No Match
18:00 – 19:00 Westbound (arrivals) 571 227 +344 152%
12.152 The increase in traffic in each case is well over 100%. Although there is a primary school adjacent
to the New Lawn, hours of operation do not coincide. However, footways are provided along
Nympsfield Road, so by reference Table 12.2 the sensitivity of the receptor is medium, and by
reference to Table 12.1 the magnitude of change is substantial. If the assessment were being
undertaken for The New Lawn, by reference to Table 12.3 the level of effect would be moderate
and therefore significant within the meaning of the EIA Regulations.
Severance, Pedestrian Delay, Pedestrian Amenity, and Fear and Intimidation
12.153 This section of the assessment considers the effect on road links as follows, based upon the
analysis above:
• A419 from the Site access to Chipmans Platt
• A419 east of Chipmans Platt
• Spring Hill
A419 from the Site access to Chipmans Platt
12.154 In relation to people walking on Footpath Eastington 37 as it crosses the A419, the increase in
traffic on Saturday afternoon before and after matches is predicted to be over 60%, and on a
weekday evening lies in the range 30% to 60%. By reference to Table 12.1, the magnitude of
change is medium to substantial. By reference to Table 12.2, the sensitivity of the receptors in
relation to severance, pedestrian delay, pedestrian amenity, and fear and intimidation is
medium. By reference to Table 12.3, the level of the effect on severance, pedestrian delay,
pedestrian amenity, and fear and intimidation for users of Eastington Footpath 37 as it crosses
the A419 is moderate and therefore significant within the meaning of the EIA Regulations,
permanent but infrequent i.e. approximately thirty times a year or two to three times a month
on average. Dates and times of matches will be known in advance from the FGRFC website, so
that use of the footpath during busy periods could be avoided if required. As part of the Revised
Scheme a signal controlled crossing of the A419 will be provided as a permanent feature. This
could be regarded as a positive effect by users of the footpath.
12.155 Footpaths Eastington 37 and 38 which cross the site are to be kept open during operation.
Immediately before and after matches the transport and access effect of the development on
these footpaths will be as in the paragraph above, i.e. moderate and therefore significant within
the meaning of the EIA Regulations, but infrequent i.e. approximately thirty times a year or two
to three times a month on average. Dates and times of matches will be known in advance from
the FGRFC website, so that use of the footpaths during busy periods could be avoided if required.
Eco Park, Land at M5 Junction 13, West of Stonehouse | Environmental Statement
December 2015
Page | 282
A419 East of Chipmans Platt
12.156 As set out above, predicted increases in traffic on the A419 between Chipmans Platt and
Horsetrough generally lie in the range 30% - 60% in both the Saturday match arrival and
departure periods, and in the weekday match arrival period, apart from the section between
Oldends Lane and Horsetrough which has a predicted increase of just over 60% in the Saturday
match departure period. By reference to Table 12.1, the magnitude of change is medium to
substantial. The sensitivity of the receptors in relation to severance, pedestrian delay, pedestrian
amenity, and fear and intimidation is medium (Table 12.2), as the A419 is crossed by National
Cycle Route 45 at Chipmans Platt, and footways are provided along some sections of the route.
By reference to Table 12.3, the level of the effect on severance, pedestrian delay, pedestrian
amenity, and fear and intimidation immediately before and after matches is moderate and
therefore significant within the meaning of the EIA Regulations. However, the effect is
infrequent i.e. approximately thirty times a year or two to three times a month on average.
Furthermore, improvements to NCN Route 45 where it crosses the A419 are included in the
GFirst LEP funded A419 corridor improvements at Chipmans Platt. Improvements to NCN 45
more generally form part of the Revised Scheme.
Spring Hill
12.157 The maximum increase in traffic on Spring Hill before and after a match is predicted to lie in the
range 30% - 60% for all time periods. The magnitude of change is medium (Table 12.1). NCN
Route 45 runs along the northern end of Spring Hill, and may be used by both cyclists and
pedestrians. The sensitivity of the receptor is therefore medium (Table 12.2). The level of the
effect on severance, pedestrian delay, pedestrian amenity, and fear and intimidation
immediately before and after a match is moderate and therefore significant within the meaning
of the EIA Regulations (Table 12.3). However, the effect is infrequent i.e. approximately thirty
times a year or two to three times a month on average. Furthermore, a shared pedestrian / cycle
route is to be provided along the northern part of Spring Hill as part of the GFirst LEP funded
A419 corridor improvements. A pedestrian crossing point over Spring Hill is proposed as part of
the Revised Scheme, together with a footway linking Spring Hill to Eastington Footpath 37 just
east of the proposed Site access.
Driver Delay
12.158 The predicted change in driver delay has been estimated with the S-Paramics micro simulation
model. Journey times along the A419 in each direction between the A38 and Horsetrough
roundabout are summarised in Table 12.13 for each Saturday afternoon scenario and in Table
12.14 for the weekday evening arrival period. More details of the S-Paramics model are given in
RS Appendix 12.2.
Eco Park, Land at M5 Junction 13, West of Stonehouse | Environmental Statement
December 2015
Page | 283
Table 12.13: Summary of Saturday Modelled Journey Times, A419 from A38 to Horsetrough
Scenario
Saturday Match Arrivals and Departures (Minutes: Seconds)
14:00 – 15:00 17:00 – 18:00
A419
Westbound
A419
Eastbound
A419
Westbound
A419
Eastbound
2015 Baseline 07:00 06:24 07:03 06:22
2021 Baseline 06:47 06:30 06:47 06:25
2021 with
Revised Scheme
07:26 07:17 07:11 07:51
Change + 0:39 +0.47 +0.24 +1:26
2031 Baseline 06:52 06:33 06:49 06:28
2031 with
Revised Scheme
07:38 07:25 07:15 07:55
Change +0.46 +0.52 +0.26 +1:37
Note: minor differences between 2021 and 2031 journey times partly due to varying model runs
Table 12.14: Summary of Weekday Modelled Journey Times, A419 from A38 to Horsetrough
Scenario
Weekday Match Arrivals (Minutes: Seconds)
18:00 – 19:00
A419 Westbound A419 Eastbound
2015 Baseline 06:52 06:31
2021 Baseline 06:45 06:38
2021 with Revised Scheme 07:08 07:22
Change +0:23 +0:44
2031 Baseline 07:23 06:45
2031 with Revised Scheme 07:14 07:30
Change -0.09 +0.45
Note: minor differences between 2021 and 2031 journey times partly due to varying model runs
12.159 It is noted that journey times show a slight improvement westbound between the 2015 baseline
and 2021 baseline scenarios, as a result of the GFirst LEP funded A419 corridor improvements,
currently expected to be in place in 2019.
12.160 The Revised Scheme is predicted to result in increased journey times, or delay, in 2021 of 39 to
47 seconds during the Saturday match arrival period, and 24 seconds to 1 minute 26 seconds in
the Saturday match departure period, depending on the direction of travel. This will increase
slightly by 2031, because of the effect of background traffic growth.
12.161 During the weekday evening arrival period, the Revised Scheme is predicted to result in increased
journey times, or delay, in 2021 of 23 to 44 seconds during the weekday evening match arrival
period, depending on the direction of travel. In 2031, heading westbound towards the M5,
journey times show a slight improvement with the Revised Scheme, as a result of the dualling
proposals.
Eco Park, Land at M5 Junction 13, West of Stonehouse | Environmental Statement
December 2015
Page | 284
12.162 It is envisaged that the change in journey time before and after a match will be noticeable to
most drivers, because it will be clear from the level of activity that a match is taking place, and
the magnitude of change is therefore medium (Table 12.1). During match arrival and departure
periods, with a full 5,000 capacity Stadium, some junctions along the A419 corridor are likely to
be operating at close to capacity (see RS Appendix 12.1). The sensitivity of the receptor can
therefore be regarded as medium (Table 12.2), and the level of effect as moderate and therefore
significant within the meaning of the EIA Regulations (Table 12.3). However, the effect is
infrequent i.e. approximately thirty times a year, or two to three times per month on average.
Dates and times of matches will be known in advance from the FGRFC website, so that the timing
of a journey could be adjusted accordingly if required.
12.163 The proposed access arrangements include the dualling of the A419 from the M5 Junction 13 to
Chipmans Platt. This dualling is expected to be of benefit to drivers outside match periods.
Accidents and Safety
12.164 The accident rate on the A419 in the vicinity of the Revised Scheme is below the national average
(Table 12.5). The sensitivity of the receptor in relation to accidents and road safety on the A419
is therefore low or negligible (Table 12.2).
12.165 The traffic signal controlled Site access has been designed to serve the development, in
accordance with guidance in the Design Manual for Roads and Bridges120. It includes a pedestrian
crossing of the A419, and a new footway along the south side of the A419 between the Site
access and Chipmans Platt roundabout. The proposed layout will be the subject of a Road Safety
Audit at each relevant stage of the design.
12.166 No change to the personal injury accident rate is therefore expected as a result of the
development and by reference to Table 12.1 the magnitude of change in relation to accidents
and safety is negligible. By reference to Table 12.3, the level of the effect on accidents and safety
is negligible and therefore not significant within the meaning of the EIA Regulations.
Mitigation and Enhancement Measures
Construction
Construction Traffic Management Plan
12.167 Mitigation and enhancement of the effects of construction will be achieved through controls
imposed by planning conditions, health and safety requirements and good construction site
practices. The mitigation and enhancement measures to address the transport effects
associated with the construction of the Revised Scheme will be co-ordinated and implemented
by means of a Construction Traffic Management Plan which can be secured by a planning
condition. More details of construction phasing and logistics, and more precise estimated
construction vehicle numbers, will be identified at the Reserved Matters stage and included as
appropriate in the Construction Traffic Management Plan.
12.168 Mitigation and enhancement measures during construction are likely to include:
120 Highways England: Design Manual for Roads and Bridges (DMRB), WilliamsLeatag, (2017) Available at:
http://www.standardsforhighways.co.uk/ha/standards/dmrb/. Last accessed October 2017.
Eco Park, Land at M5 Junction 13, West of Stonehouse | Environmental Statement
December 2015
Page | 285
• Appropriate signing of the delivery route to ensure vehicles use the approved route to and
from the site. No construction vehicles will be permitted to use Grove Lane or Spring Hill.
• Warning signs for vehicles and pedestrians as appropriate
• Co-ordination of delivery times to ensure that as far as possible deliveries take place
outside peak periods
• Layout of construction compound to allow adequate space for goods vehicle manoeuvring
and ensure that vehicles are not required to wait on the public highway
• Temporary traffic management for short periods if delivery of oversized loads may cause
obstruction to the public highway
• Design of the site access to ensure that vehicles have appropriate visibility upon leaving
the site
• Wheel washing facilities for vehicles leaving the site, and road sweeping when necessary
Operation
Embedded Mitigation Measures
12.169 A number of measures are embedded in the design in transport terms, as described in Section
12.4 above. These have been taken into account in the assessment above.
Mitigation and Enhancement Measures
12.170 In the interests of sustainability and to ensure the Revised Scheme accords with national and
local planning policy, measures to encourage walking, cycling and the use of public transport will
be implemented through a Travel Plan for Forest Green Rovers Football Club (FGRFC).
12.171 An Outline Travel Plan (OTP) has been prepared for submission with the planning application,
and is attached at RS Appendix 12.3. The full Travel Plan can be secured by condition.
12.172 To encourage sustainable travel, the following measures are proposed:
• Public transport information available through FGRFC’s website;
• As required additional buses to/ from local supporter hotspots including Stonehouse,
Stroud and Nailsworth;
• As required shuttle buses to/ from Stonehouse and Cam & Dursley rail stations;
• Bus and coach drop off areas within the Site;
• Supporter carshare link via FGRFC’s website;
• Safe linkage to pedestrian routes from Stonehouse and WoS;
• Vehicle free area around the Stadium;
• Convenient cycle parking.
12.173 The interim target set out in the Outline Travel Plan is:
• Cars parked are not to exceed 34% of the total match attendance
12.174 This target will be refined in consultation with GCC following a baseline travel survey; the
baseline travel survey will be conducted between three and six months after opening of the
FGRFC Stadium.
Assessment of residual effects
Eco Park, Land at M5 Junction 13, West of Stonehouse | Environmental Statement
December 2015
Page | 286
12.175 An assessment of the significance of the effects likely to arise as a result of the Revised Scheme,
assuming a full 5,000 capacity Stadium and after the mitigation and enhancement measures have
been employed, is included in Table 12.15. Major and moderate effects are considered
significant for the purposes of the EIA Regulations.
12.176 The aim is for measures identified in the FGRFC Travel Plan to constrain growth in car travel to
the Revised Scheme in the future, rather than to alter the residual transport effects as assessed.
12.177 The residual effects considered significant in relation to the EIA Regulations can be summarised
as:
Construction
• Construction traffic - PROW Footpaths Eastington 37 and 38: moderate, negative but
medium term / temporary (severance, pedestrian delay, pedestrian amenity, fear and
intimidation).
Operation - Match Day
• Increase in traffic at Site entrance and within site – PROW Footpaths Eastington 37 and
37: Moderate, negative, long term but infrequent (severance, pedestrian delay,
pedestrian amenity, fear and intimidation);
• Increase in traffic at Chipmans Platt – NCN Route 45 and Spring Hill: Moderate, negative,
long term but infrequent (severance, pedestrian delay, pedestrian amenity, fear and
intimidation);
• Increase in traffic on A419 Corridor: Moderate, negative, long term but infrequent (driver
delay).
Operation - Non-Match Day
• Provision of crossing at signalised site access – PROW Footpath Eastington 37: Moderate,
positive, long term (severance, pedestrian delay, pedestrian amenity, fear and
intimidation);
• Pedestrian/ cyclist improvements - NCN Route 45 and at Chipmans Platt roundabout:
Moderate, positive, long term (severance, pedestrian delay, pedestrian amenity, fear and
intimidation);
• Dualling of A419 between A419 and Chipmans Platt: Moderate, positive, long term (driver
delay).
12.178 In terms of match day frequency, as stated above a total of thirty home matches are currently
(as at the end of November) programmed during the 2017 – 2018 season: twenty two on a
Saturday; six on a normal weekday evening; and two on Bank Holidays. This equates to two to
three home games per month on average. Two of these are pre-season friendly matches, twenty
three are League matches, and five are cup / trophy matches; a small number of additional
matches may be added to the programme depending on progress in the League and FA Cups.
12.179 Dates and times of matches will be known in advance from the FGRFC website, so that the timing
of a journey (vehicular, by cycle or on foot) could be adjusted accordingly to minimise the effect
on an individual if required.
Eco Park, Land at M5 Junction 13, West of Stonehouse | Environmental Statement
December 2015
Page | 287
Cumulative Effects
12.180 Section 12.4 explains that the consented development on the land West of Stonehouse (Policy
SA2 in SDLP 2015) is included in the 2021 baseline, as are improvements to junctions within the
A419 Corridor to be funded by GFirst LEP under the Gloucestershire Growth Deal.
12.181 Traffic generated by the remaining developments identified in Table 2.5 and Chapter 18 of this
ES is taken into account through the application of traffic growth factors obtained from the NTM
adjusted using TEMPRO (NTEM Dataset 7.0). The TEMPRO program is based on the National Trip
End Model and takes into account changes in car ownership, and local planning forecasts
regarding housing and employment.
12.182 The access to the Revised Scheme has been designed to accommodate future traffic flows
allowing for committed developments. There are therefore no further cumulative effects to be
taken into account during operation.
Conclusions
12.183 This chapter assesses the potential effects of the Revised Scheme in terms of transport.
12.184 A comprehensive Transport Assessment (TA) has been prepared and forms RS Appendix 12.1 to
this chapter. The TA examines in detail the transport effects of the Revised Scheme on the
existing transport system and provides the basis for this assessment.
12.185 During the construction phase of the Revised Scheme it is estimated that there may be up to 100
HGV movements and 260 employee vehicle movements per day. The majority of construction
traffic is expected to be routed via the A419 and M5 to the west of the site; no construction
traffic will be permitted to use Grove Lane or Spring Hill. The construction period is medium-
term and therefore temporary in its effects. Mitigation and enhancement measures to address
the transport effects associated with the construction of the Revised Scheme will be co-ordinated
and implemented by means of a Construction Traffic Management Plan which will be secured by
a planning condition.
12.186 The Revised Scheme during its operational phase will increase travel demand in the area before
and after FGRFC home matches. A number of improvement measures are embedded in the
proposal including:
• Signalised junction on the A419;
• Pedestrian crossing phase of the A419 within the traffic signals;
• Dualling of the A419 from the M5 Junction 13 to Chipmans Platt;
• The creation of a new footway to the south of the A419 carriageway, connecting to
Chipmans Platt, the southern part of Stonehouse and the canal towpath;
• Bus and emergency vehicle entrance from Grove Lane;
• Pedestrian and cycle access from Grove Lane including additional footway and crossing
points.
Eco Park, Land at M5 Junction 13, West of Stonehouse | Environmental Statement
December 2015
Page | 288
12.187 In the interests of sustainability and to ensure the Revised Scheme accords with national and
local planning policy, measures to encourage walking, cycling and public transport are to be
implemented through a Travel Plan. An Outline Travel Plan (OTP) has been prepared for
submission with the planning application, and forms RS Appendix 12.3 of the ES. The full Travel
Plan can be secured by condition.
12.188 The traffic modelling indicates that journey times on the A419 corridor between the A38 and
Horsetrough roundabout could increase by up to around 1 minute 26 seconds during the match
arrival and departure periods in the opening year on a Saturday and up to 44 seconds during the
weekday evening match arrival period. This could be perceived as a moderate negative effect,
although infrequent.
12.189 There could be a moderate negative effect in terms of severance, amenity, delay and fear and
intimidation to users of PROW Footpaths Eastington 37 and 38, and National Cycle Route 45
before and after a match. However, this effect will be infrequent.
12.190 In terms of frequency, FGRFC home matches are expected to occur around 30 times per year, or
two to three times per month on average. Dates and times of matches will be known in advance
from the FGRFC website. Given the relative infrequency of home matches, and the fact that the
timing of a non-match related journey (vehicular, by cycle or on foot) could be adjusted if
required to minimise the effect on an individual, the moderate negative effect before and after
matches is considered acceptable.
12.191 On non-match days, pedestrians and cyclists could experience a moderate positive effect as a
result of the introduction of the traffic signal controlled crossing of the A419 and improvements
at Chipmans Platt roundabout. Drivers could experience a moderate positive effect as a result
of the dualling of the A419 between the M5 Junction 13 and Chipmans Platt.
12.192 It is concluded that the additional travel demand can be safely and satisfactorily accommodated
on the local transport network.
Eco Park, Land at M5 Junction 13, West of Stonehouse | Environmental Statement
December 2015
Page | 289
Table 12.15: Residual Transport Effects
Receptor Effect Development
Phase
Embedded
Mitigation
Sensitivity/
importance of
receptor
Magnitude
of change
Level of
Effect (and
Significance)
prior to
additional
mitigation
Mitigation Enhancement Level of Effect
(and Significance)
after mitigation/
enhancement
Nature of
effect
Key highway
junction
operating close to
capacity:
A419 Corridor
Driver Delay
Construction
(Weekdays,
and Saturday morning)
Excavated
material to
be retained on site where
possible
Low / Medium Minor Minor/ not
significant
Deliveries to
take place
outside peak hours where
possible
Construction
Traffic
Management Plan/
Minor/ not significant
Negative,
Medium
Term
People
walking on
PROW Footpaths
Easington 37
& 38
Severance,
pedestrian
delay, pedestrian
amenity, fear
& intimidation
Construction
(Weekdays,
and Saturday morning)
PROW to be
kept open as
far as possible
Medium Substantial Moderate/
significant
No
construction
to take place on Saturday PM, Sunday
or Bank Holidays
Construction
Traffic
Management Plan
Moderate /
significant
Negative,
Medium
Term
Road network
users
Accidents
and safety
Construction
(Weekdays, and Saturday
morning)
Site access to
be provided in
accordance with
standards
Low/
negligible
No change
anticipated - Negligible
N/A N/A Construction
Traffic Management
Plan
Negligible / not significant
Negligible
People
walking on PROW
Footpath Easington 37 as it crosses
A419
Severance,
pedestrian delay,
pedestrian amenity, fear
&
intimidation
Operation
(Match)
Signal
controlled crossing of
A419 embedded in
proposals
Medium Substantial Moderate / significant
Travel Plan
to encourage sustainable
travel
N/A
Moderate /
significant
Negative,
Long Term, Infrequent
(during FGRFC match)
Positive, Long Term (No FGRFC
match)
Eco Park, Land at M5 Junction 13, West of Stonehouse | Environmental Statement
December 2015
Page | 290
People
walking on PROW
Footpaths
Easington 37 & 38 within
Site
Severance,
pedestrian delay,
pedestrian
amenity, fear &
intimidation
Operation
(Match)
PROW to be
kept open
Medium Medium Moderate /
significant
Travel Plan
to encourage sustainable
travel
N/A
Moderate/
significant
Negative,
Long Term, Infrequent
(during
FGRFC match)
People
walking or
cycling on Spring Hill
Severance,
pedestrian
delay, pedestrian
amenity, fear
& intimidation
Operation
(Match)
Pedestrian
crossing and
additional footway
embedded in
proposals
Medium Medium Moderate /
significant
Travel Plan
to encourage
sustainable travel
N/A Moderate /
significant
Negative,
Long Term,
Infrequent (during FGRFC
match)
Positive, Long Term
(No FGRFC match)
People
walking or cycling on
Cycle Route
45 at Chipmans
Platt
Severance,
pedestrian delay,
pedestrian
amenity, fear &
intimidation
Operation
(Match)
Improvement
s to NCN 45 associated
with Revised
Scheme
Medium Medium to
Substantial
Moderate/
significant
Travel Plan
to encourage sustainable
travel
N/A Moderate /
significant
Negative,
Long Term, Infrequent
(during
FGRFC match)
Positive,
Long Term (No FGRFC
match)
Key highway
junctions
operating within
capacity:
A419 Corridor
Driver Delay
Operation
(Match)
Dualling of
A419
between M5 Junction 13
and
Chipmans Platt
embedded in
proposals
Medium Medium Moderate /
significant
Travel Plan
to encourage
sustainable travel
N/A
Moderate /
significant
Negative,
Long Term,
Infrequent (during FGRFC
match)
Positive, Long Term
between M5 J13 and
Chipmans
Platt (No FGRFC
Eco Park, Land at M5 Junction 13, West of Stonehouse | Environmental Statement
December 2015
Page | 291
match)
Road network
users
Accidents
and safety
Operation
(Match)
Site Access to
be provided
in accordance
with
standards
Low or
negligible
No change
anticipated -
Negligible
Negligible Travel Plan
to encourage
sustainable travel
N/A Negligible / not significant
Negligible
Eco Park, Land at M5 Junction 13, West of Stonehouse | Environmental Statement
December 2015
Page | 292
13 AIR QUALITY AND DUST
Summary
13.1 An air quality assessment report was prepared for the Eco Park development in 2015; this is a
Revised Scheme for the Forest Green Rovers Football Club (FGRFC) stadium only development.
The Revised Scheme is not located within or near to a declared Air Quality Management Area
(AQMA).
Construction Phase
13.2 During the construction phase, effects of the Revised Scheme may potentially arise due to
fugitive dust emissions. The risk of dust effects assessed according to a widely used method
published by the Institute of Air Quality Management (IAQM). Mitigation measures appropriate
to the construction phase will be secured by a Dust Management Plan (DMP) agreed with Stroud
District Council (SDC); therefore, significant residual effects in EIA terms are not anticipated.
Operational Phase
13.3 A dispersion modelling assessment of the operational phase air quality effects associated with
emissions from the increase in traffic on local roads associated with the Revised Scheme has
been carried out, the results of which are summarised below:
Effect of the Revised Scheme on Local Air Quality
13.4 The predicted nitrogen dioxide (NO2) and particulate matter (PM10 and PM2.5) concentrations at
all the assessed existing receptors, and for all modelled scenarios, will not exceed the relevant
air quality objectives. As a result of the development (operational in 2021 including cumulative
development), there is a ‘negligible’ air quality effect predicted with respect to annual mean NO2,
PM10 and PM2.5 at all modelled existing sensitive receptors. Therefore, the air quality effects of
the development on local air quality are not significant in EIA terms.
13.5 Fixed energy source details are not available at this stage of the project for the Revised Scheme.
Once identified (Reserved Matters stage) these sources may require additional assessment.
Effect of Future Air Quality on the Revised Scheme Sensitive Receptors
13.6 None of the modelled proposed receptors are predicted to experience pollutant concentrations
above the short term NO2, annual mean NO2, PM10 or PM2.5 objectives. It is considered that
increased exposure to poor air quality at the Revised Scheme is unlikely and therefore, the air
quality effect of the development may be considered not significant in EIA terms.
13.7 Operational phase mitigation is not required. However, good practice enhancement measures
to reduce the effect of emissions to air at sensitive receptors are recommended to ensure the
air quality effects are minimised. These include good design principles, and measures to help
minimise vehicular trips and encourage more sustainable modes of travel.
Eco Park, Land at M5 Junction 13, West of Stonehouse | Environmental Statement
December 2015
Page | 293
Introduction
13.8 This chapter reviews existing air quality conditions at the Revised Scheme with respect to air
quality standards and objectives, national planning policy guidelines and local policies. The
assessment methodology and likely effect of the Revised Scheme upon surrounding existing
sensitive receptors and the effect of future local air quality upon the Revised Scheme receptors
during both the construction and operational phases have been described in this chapter. If
significant effects are expected, mitigation measures will be proposed to minimise significant
effects on local air quality. The mitigation already built into the Revised Scheme as part of the
Design Evolution will also be considered. The likely residual effects on air quality following the
implementation of any mitigation or enhancements are then described. Cumulative effects of
surrounding proposed developments have also been considered and an explanation of how the
scheme will be designed to consider the air quality effects on relevant receptors provided.
13.9 This chapter is accompanied by the technical air quality assessment report (RS Appendix 13.1)
which contains the technical details including those on the guidance used, assessment approach,
and isopleths plots. The isopleths plots can also be found on RS Figure 13.4, 13.5 and 13.6. These
figures show the variation in concentration of NO2, PM10 and PM2.5 and highlight the level of
dispersion with distance from the roads. As the development is for commercial use, the NO2
concentrations within the Revised Scheme are compared against the short-term objective of
200µg/m3.
Legislation, Policy and Guidance
Air Quality Strategy
13.10 UK air quality policy is published under the umbrella of the Environment Act 1995121, Part IV and
specifically Section 80, the National Air Quality Strategy. The latest Air Quality Strategy for
England, Scotland, Wales and Northern Ireland – Working Together for Clean Air, published in
July 2007 sets air quality standards and objectives for ten key air pollutants to be achieved
between 2003 and 2020122.
13.11 The Air Quality Framework Directive (1996)123 established a framework under which the
European Commission (EC) could set limit or target values for specified pollutants. The directive
identified several pollutants for which limit or target values have been, or will be set in
subsequent ‘daughter directives’. The framework and daughter directives were consolidated by
Directive 2008/50/EC on Ambient Air Quality and Cleaner Air for Europe124, which retains the
existing air quality standards and introduces new objectives for fine particulates (PM2.5).
Air Quality Standards
121 Environment Act 1995 [Online] http://www.legislation.gov.uk/ukpga/1995/25/part/IV [Accessed 28th November
2017] 122 DEFRA (2007) The Air Quality Strategy for England, Scotland, Wales and Northern Ireland [Online] Available from:
www.defra.gov.uk [Accessed: 28th November 2017] 123 European Council Directive 96/62/EC 27 September 1996 on ambient air quality assessment and management 124 The European Council Directive 2008/50/EC 21 May 2008 on ambient air quality and cleaner air for Europe
[Online]
http://eur-lex.europa.eu/LexUriServ/LexUriServ.do?uri=OJ:L:2008:152:0001:0044:en:PDF [Accessed: 28th
November 2017]
Eco Park, Land at M5 Junction 13, West of Stonehouse | Environmental Statement
December 2015
Page | 294
13.12 Many of the air quality standards in the United Kingdom are derived from EC directives and are
adopted into English law via the Air Quality (England) Regulations 2000125 and Air Quality
(England) Amendment Regulations 2002126. The Air Quality Limit Values Regulations 2003127 and
subsequent amendments implement the EU Air Quality Framework Directive into English Law.
Directive 2008/50/EC was translated into UK law in 2010 via the Air Quality Standards
Regulations 2010128.
13.13 The relevant129 objectives for England and Wales to protect human health are summarised in
Table 13.1. The objectives present the level to which the standards are expected to be achieved
by a certain date. A Department for Environment, Food and Rural Affairs (Defra) report130
published in 2009 found that measurements of hourly NO2 are unlikely to be exceeded where
the annual mean concentrations are below 60µg/m3.
Table 13.1: Air Quality Objectives Relevant to the Revised Scheme
Substance Averaging
period
Exceedances allowed per year Ground level concentration limit
(µµµµg/m3)
Nitrogen
dioxide (NO2)
1 calendar
year
- 40
1 hour 18 200
Particles
(PM10)
1 calendar
year
- 40
24 hours 35 50
Fine particles
(PM2.5)
1 year N/A 25*
Note: *Target date is 01.01.2020.
The Environment Act
13.14 The set of air quality standards are to be used in the review and assessment of air quality by local
authorities under Section 82 of the Environment Act (1995). If exceedances are measured or
predicted through the review and assessment process, the local authority must declare an AQMA
under Section 83 of the Act, and produce an Air Quality Action Plan (AQAP) to outline how air
quality is to be improved to meet the objectives under Section 84 of the act.
Planning Policy
13.15 The land use planning process is a key means of improving air quality, particularly in the long
term, through the strategic location and design of new developments. Any air quality concern
125 Environmental Protection, 2000. Air Quality (England) Regulations 2000
http://www.legislation.gov.uk/uksi/2000/928/contents/made 126 Environmental Protection, England, 2002. The Air Quality (England) (Amendment) Regulations 2002
http://www.legislation.gov.uk/uksi/2002/3043/contents/made 127 Environmental Protection, 2003. The Air Quality Limit Values Regulations 2003
http://www.legislation.gov.uk/uksi/2003/2121/contents/made 128 Environmental Protection, 2010. The Air Quality Standards Regulations 2010
http://www.legislation.gov.uk/uksi/2010/1001/contents/made 129 Relevance, in this case, is defined by the scope of the assessment. 130 Department for Environment, Food and Rural Affairs, 2009. Part IV of the Environment Act 1995: Local Air Quality
Management: Technical Guidance LAQM.TG(09).
Eco Park, Land at M5 Junction 13, West of Stonehouse | Environmental Statement
December 2015
Page | 295
that relates to land use and its development can, depending on the details of the Revised
Scheme, be a material consideration in the determination of planning applications.
National Planning Policy Framework
13.16 In March 2012 the National Planning Policy Framework131 (NPPF) was published, superseding the
bulk of previous Planning Policy Statements with immediate effect. The NPPF was intended to
simplify the planning system and includes a presumption in favour of sustainable development.
13.17 Section 11 of the NPPF deals with Conserving and Enhancing the Natural Environment, and states
that the intention is that the planning system should prevent “development from contributing to
or being put at unacceptable risk from, or being adversely affected by unacceptable levels of soil,
air, water or noise pollution or land instability” and goes on to state that “new development
[should be] appropriate for its location’ and ‘the effects (including cumulative effects) of pollution
on health, the natural environment or general amenity, and the potential sensitivity of the area
or Revised Scheme to adverse effects from pollution, should be taken into account.”
13.18 With specific regard to air quality, the NPPF states that, “Planning policies should sustain
compliance with and contribute towards EU [European Union] limit values or national objectives
for pollutants, taking into account the presence of Air Quality Management Areas and the
cumulative impacts on air quality from individual sites in local areas. Planning decisions should
ensure that any new development in Air Quality Management Areas is consistent with the local
air quality action plan”.
Local Planning Policy
13.19 The Stroud District Local Plan132 was adopted in 2015. The plan contains Deliver Policy ES5
regarding air quality and states, “Development proposals which by virtue of their scale, nature or
location are likely to exacerbate existing areas of poor air quality, will need to demonstrate that
measures can be taken to effectively mitigate emission levels in order to protect public health and
well being, environmental quality and amenity. Mitigation measures should demonstrate how
they will make a positive contribution to the aims of any Air Quality Strategy for Stroud District
and may include:
1. Landscaping, bunding or separation to increase distance from highways and junctions
2. possible traffic management or highway improvements to be agreed with the local
authority
3. abatement technology and incorporating site layout / separation and other conditions in
site planning
4. traffic routing, site management, site layout and phasing
5. managing and expanding capacity in the natural environment to mitigate poor air quality.”
13.20 The Eastington Neighbourhood Development Plan133 (made in October 2016) now forms part of
the Development Plan for the local planning authority. Whilst there are no specific policies
relating to air quality, the overarching Neighbourhood Development Plan is in line with higher
level planning policy including the NPPF which has a presumption in favour of sustainable
development. The NPPF Paragraph 7 defines sustainability in terms of:
131 Department for Communities and Local Government, 2012. National Planning Policy Framework. 132 Stroud District Council, 2015. Stroud District Local Plan. 133 Eastington Parish Council, 2016. Neighbourhood Development Plan 2015-2031
Eco Park, Land at M5 Junction 13, West of Stonehouse | Environmental Statement
December 2015
Page | 296
“an environmental role – contributing to protecting and enhancing our natural, built and historic
environment; and, as part of this, helping to improve biodiversity, use natural resources
prudently, minimise waste and pollution, and mitigate and adapt to climate change including
moving to a low carbon economy.”
13.21 Further information in relation to planning policy is provided in Chapter 6 – Planning Policy
Context.
Guidance Documents
Guidance on the Assessment of Dust from Demolition and Construction
13.22 The IAQM published a guidance document in 2014134 on the assessment of construction phase
impacts. The guidance was produced to provide advice to developers, consultants and
environmental health officers on how to assess the impacts arising from construction activities.
The emphasis of the methodology is on classifying sites according to the risk of impacts (in terms
of dust nuisance, PM10 impacts on public exposure and impact upon sensitive ecological
receptors) and to identify mitigation measures appropriate to the level of risk identified.
Local Air Quality Management Review and Assessment Technical Guidance135
13.23 Defra has published technical guidance for use by local authorities in their air quality review and
assessment work. This guidance, referred to in this document as LAQM.TG(16), has been used
where appropriate in the operational phase assessment presented herein.
Land-Use Planning & Development Control: Planning for Air Quality136
13.24 Environmental Protection UK (EPUK) and the IAQM jointly published a revised version of the
guidance note ‘Land-Use Planning & Development Control: Planning for Air Quality’ in 2017
(herein the ‘EPUK-IAQM’ guidance) to facilitate the consideration of air quality in the land-use
planning and developmental control process. It provides a framework for air quality
considerations within local development control processes, promoting a consistent approach to
the treatment of air quality issues within development control decisions.
Assessment Methodology and Significance Criteria
Project team
13.25 Srinivas Srimath is the Director of Air Quality at RSK and has over twenty five years’ experience
of engineering and environmental projects relating to infrastructure development, pollution
prevention and control and air quality assessment. His work experience covers numerous
industrial, local authority and environmental planning related assessments that have sought to
minimise the environmental effects of developments and devise suitable environmental
improvement policies and plans. He has completed a number of detailed air quality assessments
in support of planning applications, Environmental Statements and Environmental Permit
134 The Institute of Air Quality Management, 2014. Guidance of the Assessment of dust from demolition and
construction [pdf] [Online] Available at: http://iaqm.co.uk/text/guidance/construction-dust-2014.pdf [22nd
November 2017]. 135 Department for Environment, Food and Rural Affairs, 2016. Part IV of the Environment Act 1995: Local Air Quality
Management: Technical Guidance LAQM.TG(16). 136 Institute of Air Quality Management and Environmental Protection UK, 2017. Land-Use Planning & Development
Control: Planning for Air Quality v1.2. [Online] Available at http://www.iaqm.co.uk/text/guidance/air-quality-
planning-guidance.pdf [22nd November 2017].
Eco Park, Land at M5 Junction 13, West of Stonehouse | Environmental Statement
December 2015
Page | 297
applications for nationally significant infrastructure development projects. He is experienced in
preparing and presenting evidence at public inquiries. Over a period of two years, he has
developed an air quality assessment system (for urban and highly trafficked areas) for a project
funded by the European Commission that covers several of Europe’s most populous areas where
traffic, domestic and industrial activities inter-relate. He is a full member of the IAQM and one
of the Working Group members of this Institute set up to develop guidance to assess dust
impacts from mineral extraction sites. He is the lead consultant and technical reviewer for the
work presented in this chapter.
13.26 Christina Higgins is a Senior Consultant with over three years’ experience in undertaking and
managing air quality assessments. She is an associate member of the IAQM and the Institute of
Environmental Sciences (IES). She has undertaken the air quality impact assessment work
presented in this chapter.
Consultation and Scoping Overview
13.27 As part of the scoping phase of the EIA for the original Eco Park scheme, a Scoping Report was
prepared in July 2015 (RS Appendix 1.3). Subsequently a Scoping Opinion was issued (RS
Appendix 1.2).
13.28 A summary of the main Scoping Opinion representations for the original scheme still relevant to
air quality assessment for the Revised Scheme are provided below:
Table 13.2: Scoping Responses
Consultee Issue Raised
Location in
Chapter where
addressed
Stroud District Council
Scoping Response
dated 30/09/15
The proposal could generate substantial traffic unless
alternative sustainable transport is established. There
is the potential for an increase in car borne pollutants
and bearing in mind the surrounding residents it is felt
that this should be included in the scope. This may
impact on ecology and the aquatic environment.
Potential Effects
13.29 Whilst these comments were provided for the original Eco Park scheme, they have been carried
forward as part of the assessment for the Revised Scheme. Additionally, SDC were consulted on
the availability of the latest monitoring data to undertake the assessment. As the Redline
Boundary remains unchanged from the previous application, further consultation regarding the
assessment methodology was not considered necessary.
13.30 The approach taken for assessing the potential air quality effects of the Revised Scheme during
the construction and operational phases is summarised below:
• Baseline characterisation of local air quality;
• Qualitative impact assessment of the construction phase of the development;
• Quantitative assessment of operational phase effects of the Revised Scheme using an
advanced dispersion model under the following three scenarios:
o ‘Base case’ scenario representing the ‘existing’ air quality situation in 2016;
Eco Park, Land at M5 Junction 13, West of Stonehouse | Environmental Statement
December 2015
Page | 298
o ‘Without Development’ scenario (2021, the expected year of opening with other
committed/consented development but without the Revised Scheme in place);
o ‘With Development’ scenario (2021, the expected year of opening with other
committed/consented development and with the Revised Scheme in place).
• Recommendation of mitigation measures, where appropriate, to ensure any adverse
effects on air quality are minimised;
Identification of residual effects resulting from the Revised Scheme
Construction Phase Assessment Methodology
13.31 There are no formal assessment criteria to measure the significance of construction dust. As a
result, the construction phase effects have been assessed as per the IAQM guidance. The
construction dust assessment methodology is presented in RS Appendix 13.1 and described
below.
13.32 The first step in the assessment is to determine whether there is a need for a detailed
assessment. An assessment is said to be required where there are human and/ or ecological
receptors within certain distances of the site:
• a ‘human receptor’ within:
o 350m of the boundary of the site; or
o 50m of the route used by construction vehicles on the public highway, up to 500m
from the site entrance(s).
• an ‘ecological receptor’:
o 50m of the boundary of the site; or
o 50m of the route(s) used by construction vehicles on the public highway, up to 500m
from the site entrance(s).
13.33 Construction of the Revised Scheme may lead to the release of fugitive dust. There are human
receptors within 350m of the Redline Boundary of the site and within 50m of the trackout137
route; therefore, construction dust may have the potential to cause annoyance in the local area.
13.34 Human receptors include residential properties, hospitals, schools, commercial buildings, parks
and footpaths. Ecological receptors in terms of air quality include, Special Areas of Conservation
(SAC), Sites of Special Scientific Interest (SSSI) and local Nature Reserves. No designated
ecological receptors or Key Wildlife Sites (KWS) have been identified within 50m of the Redline
Boundary or the anticipated trackout route. The receptors considered in the assessment can be
seen on RS Figure 13.1.
13.35 Due to the presence of sensitive receptors within the distances identified in the IAQM guidance,
an assessment of construction dust effects is considered to be required. A qualitative assessment
of construction effects has been undertaken to identify the potential risk of dust effects and the
level of mitigation required to reduce these effects.
137 Trackout is defined as the transport of dust and dirt from the construction / demolition sites onto public road
network, where it may be deposited and then re-suspended by vehicles using the network.
Eco Park, Land at M5 Junction 13, West of Stonehouse | Environmental Statement
December 2015
Page | 299
13.36 The potential dust emission magnitude is defined as Small, Medium, Large and is based on the
scale and nature of works during the construction phase. The activities are separated into
demolition, earthworks, construction and trackout and assessed individually.
Demolition
13.37 The dust emission magnitude category for demolition is varied for each site in terms of timing,
building type, duration and scale. Examples of the potential dust emission classes are provided
in the guidance as follows:
• Large: Total building volume >50,000m3, potentially dusty construction material, on-site
crushing and screening, demolition activities >20m above ground level;
• Medium: Total building volume 20,000m3 – 50,000m3, potentially dusty construction
material, demolition activities 10m – 20m above ground level;
• Small: Total building volume <20,000m3, construction material with low potential for dust
release, demolition activities <10m above ground, demolition during wetter months.
Earthworks
13.38 The dust emission magnitude category for earthworks is varied for each site in terms of timing,
geology, topography and duration. Examples of the potential dust emission classes are provided
in the guidance as follows:
• Large: Total site area >10,000m2, potentially dusty soil type (e.g. clay), >10 heavy earth
moving vehicles active at any one time, formation of bunds >8m in height, total material
moved >100,000 tonnes;
• Medium: Total site area 2,500 – 10,000m2, moderately dusty soil type (e.g. silt), 5 – 10
heavy earth moving vehicles active at any one time, formation of bunds 4 – 8m in height,
total material moved 20,000 – 100,000 tonnes;
• Small: Total site area < 2,500m2, soil type with large grain size (e.g. sand), <5 heavy earth
moving vehicles active at any one time, formation of bunds <4m in height, total material
moved <10,000 tonnes, earthworks during wetter months.
Construction
13.39 The dust emission magnitude category for construction is varied for each site in terms of timing,
building type, duration, and scale. Examples of the potential dust emissions classes are provided
in the guidance as follows:
• Large: Total building volume >100,000m3, piling, on site concrete batching;
• Medium: Total building volume 25,000 – 100,000m3, potentially dusty construction
material (e.g. concrete), piling, on site concrete batching;
• Small: Total building volume <25,000m3, construction material with low potential for dust
release (e.g. metal cladding or timber).
Trackout
13.40 Factors which determine the dust emission magnitude class of trackout activities are vehicle size,
vehicle speed, vehicle number, geology and duration. Examples of the potential dust emissions
classes are provided in the guidance as follows:
• Large: >50 Heavy Duty Vehicles (HDV) (>3.5t) trips in any one day, potentially dusty surface
material (e.g. high clay content), unpaved road length >100m;
Eco Park, Land at M5 Junction 13, West of Stonehouse | Environmental Statement
December 2015
Page | 300
• Medium: 10 – 50 HDV (>3.5t) trips in any one day, moderately dusty surface material (e.g.
high clay content), unpaved road length 50 – 100m;
• Small: <10 HDV (>3.5t) trips in any one day, surface material with low potential for dust
release, unpaved road length <50m.
Definition of the Sensitivity of the Area
13.41 The sensitivity of the area is defined for dust soiling, human health and ecosystems as Low,
Medium or High. The sensitivity of the area takes into account the following factors:
• The specific sensitivities of human and ecological receptors in the area;
• The proximity and number of those receptors;
• In the case of PM10, the local background concentration;
• Site-specific factors, such as whether here are natural shelters such as trees, to reduce the
risk of wind-blown dust.
13.42 High sensitivity human and dust soiling receptors include residential properties, hospitals and
schools. High sensitivity ecological receptors in terms of air quality include Special Areas of
Conservation (SAC).
13.43 Medium sensitivity human and dust soiling receptors include offices, commercial buildings,
places of work and parks. Medium sensitivity ecological receptors include Sites of Special
Scientific Interest (SSSI).
13.44 Low sensitivity human and dust soiling receptors include playing fields, farmland, footpaths and
short term car parks. Low sensitivity ecological receptors include Local Nature Reserves.
13.45 No designated ecological receptors have been identified within 50m of the Revised Scheme or
the anticipated trackout route. Therefore, following the IAQM guidance, ecological receptors
have been screened out of the assessment and are not considered further.
13.46 There are several human receptors within 350m of the Revised Scheme and within 50m of the
trackout route. In particular, properties along Grove Lane R9 and R10 are in close proximity to
the Revised Scheme.
13.47 Based on the receptor sensitivity value assigned, the number of receptors and distance from the
Revised Scheme, a sensitivity classification for the area can be defined for each construction
activity in terms of dust soiling, human health and ecological effects. The tables below show how
the effect is calculated.
Table 13.3: Sensitivity of the area to dust soiling effects on people and property
Receptor Sensitivity Number of Receptors Distances from the Source (m)
<20 <50 <100 <350
High >100 High High Medium Low
10-100 High Medium Low Low
1-10 Medium Low Low Low
Medium >1 Medium Low Low Low
Low >1 Low Low Low Low
Eco Park, Land at M5 Junction 13, West of Stonehouse | Environmental Statement
December 2015
Page | 301
Table 13.4: Sensitivity of the area to Human Health Effects
Receptor Sensitivity Annual
Mean
PM10
Conc.
Number
of
Receptors
Distances from the Source (m)
<20 <50 <100 <200 <350
High >100 High High High Medium Low
>32µg/m3 10-100 High High Medium Low Low
1-10 High Medium Low Low Low
28-32
µg/m3
>100 High High Medium Low Low
10-100 High Medium Low Low Low
1-10 High Medium Low Low Low
24-28
µg/m3
>100 High Medium Low Low Low
10-100 High Medium Low Low Low
1-10 Medium Low Low Low Low
<24µg/m3 >100 Medium Low Low Low Low
10-100 Low Low Low Low Low
1-10 Low Low Low Low Low
Medium - >10 High Medium Low Low Low
- 1-10 Medium Low Low Low Low
Low - >1 Low Low Low Low Low
Table 13.5: Sensitivity of the area to Ecological Effects
Receptor Sensitivity Distances from the Source (m)
<20 <50
High High Medium
Medium Medium Low
Low Low Low
Definition of the Significance of the Effect
13.48 The dust emission magnitude classification and the sensitivity of the area are used to determine
a potential significance for each construction activity, before the application of mitigation. Tables
13.6 to 13.8 indicate the method used to assign the overall level of significance for each
construction activity.
Table 13.6: Significance of Dust Effects from Demolition
Sensitivity of Area Dust Emission Magnitude
Large Medium Small
High High Medium Medium
Medium High Medium Low
Low Medium Low Negligible
Table 13.7: Significance of Dust Effects from Earthworks/Construction
Eco Park, Land at M5 Junction 13, West of Stonehouse | Environmental Statement
December 2015
Page | 302
Sensitivity of Area Dust Emission Magnitude
Large Medium Small
High High Medium Medium
Medium Medium Medium Low
Low Low Low Negligible
Table 13.8: Significance of Dust Effects from Trackout
Sensitivity of Area Dust Emission Magnitude
Large Medium Small
High High Medium Medium
Medium Medium Low Negligible
Low Low Low Negligible
13.49 The IAQM guidance does not recommend assigning the significance of construction activities
without mitigation. However, in EIA terms, high, medium, low and negligible are equivalent to
major, moderate, minor and negligible. Only those effects identified as high and medium are
considered to be significant within the meaning of the EIA Regulations, low and negligible are
considered not significant.
Definition Potential Mitigation and Residual Effects
13.50 Mitigation is divided into general measures, applicable to all sites and measures specific to
demolition, earthworks, construction and trackout. The mitigation recommended will build on
any embedded mitigation identified during the design evolution. Mitigation is only required
when significant effects are calculated. When effects are not significant, mitigation is not
required in accordance with the EIA regulations. However, enhancement measures will be
considered where appropriate.
Operational Phase Assessment Methodology
Need for operational effects assessment
13.51 The EPUK-IAQM guidance identifies various thresholds to determine whether an air quality
assessment is likely to be required for the operational phase of any development. The
assessment can be a qualitative assessment or a detailed assessment involving dispersion
modelling of emissions to air as determined by the consultation with the local authority. Based
on the number of vehicles generated, it is considered that an assessment of operational phase
air quality assessment is required. Following the consultation made with SDC, the requirement
to undertake a detailed operational assessment has been established.
13.52 A dispersion modelling assessment of operational phase effects on local air quality and at
sensitive receptor locations has been undertaken. The Study Area for the road traffic emissions
dispersion modelling was based on roads predicted to be affected by the Revised Scheme and
other cumulative development traffic generation, as identified on RS Figure 13.1.
13.53 There are two types of air quality effects considered for the Revised Scheme:
Eco Park, Land at M5 Junction 13, West of Stonehouse | Environmental Statement
December 2015
Page | 303
• The effect of existing sources in the local area on the Revised Scheme (governed by
background pollutant levels and proximity to sources of air pollution);
• The effect of the Revised Scheme on the local area.
13.54 The magnitude of effects has been determined by the predicted ground level pollutant
concentrations. Sensitivity of the area has been determined by the presence of worst-case
exposed sensitive receptor locations. The significance of effects has been determined as per the
EPUK-IAQM guidance and is further described in the sections below.
Identifying the Significance of Effects
13.55 A dispersion modelling study has been conducted using an advanced model, ADMS-Roads. It is
widely used and validated within the UK and Europe. The model allows for the skewed nature of
turbulence within the atmospheric boundary layer. ADMS-Roads facilitates the prediction of
ground level concentrations of pollutants of concern at multiple receptor locations. The
predicted pollutant concentrations have then been compared with relevant air quality objectives
to identify the significance of effects and the level of mitigation required to reduce the potential
effects.
13.56 The effects of a development are usually assessed at selected ‘receptors’. In accordance to the
EPUK-IAQM guidance, the significance of effects is derived by the percentage of change in
pollution concentration relative to an Air Quality Assessment Level (AQAL) and long term average
pollutant concentration at receptor, as presented in Table 13.9.
13.57 Selected receptors according to the EPUK-IAQM guidance include residential receptors where
long term concentrations will be the appropriate air quality assessment level (1 calendar year
averaging period limit value). This is due to the extended period of time people will spend in their
residential properties and surrounding area. Conversely, any commercial developments assessed
will be compared to short term air quality assessment levels (24-hour averaging period limit
value) due to the reduced period of time spent in these types of areas.
Table 13.9: Effect Descriptors for Individual Receptors
Long term average
concentration at
receptor in
assessment year
% Change in concentration relative to Air Quality Assessment Level (AQAL)
1-2 2-5 5-10 >10
75% or less of AQAL Negligible Negligible Slight Moderate
79 – 94% of AQAL Negligible Slight Moderate Moderate
95 – 102% of AQAL Slight Moderate Moderate Substantial
103 – 109% of AQAL Moderate Moderate Substantial Substantial
110% or more of AQAL Moderate Substantial Substantial Substantial
13.58 A significant environmental effect is considered if the percentage of change in pollution
concentration relative to the AQAL is Moderate or Substantial.
Model Scenarios
13.59 Three scenarios have been modelled to predict the change in air quality as a consequence of the
Revised Scheme. The scenarios are as follows:
Eco Park, Land at M5 Junction 13, West of Stonehouse | Environmental Statement
December 2015
Page | 304
• Scenario 1 (S1) - Base case scenario representing the ‘existing’ air quality situation in 2016;
• Scenario 2 (S2) - Without Development scenario for the future operation year (2021)
including any other committed/consented developments;
• Scenario 3 (S3) - With Development scenario for the future operation (2021) with the
Revised Scheme and including any other committed/consented developments (cumulative
effects).
Meteorological Data
13.60 Hourly sequential meteorological data has been employed in the dispersion model. Data was
recorded in 2016 at the Gloucestershire Airport meteorological monitoring station which is
located around 18km away from the Revised Scheme site.
Verification
13.61 The dispersion model results were ‘verified’ by comparison with monitoring data and adjusted
according to the procedure descried in LAQM.TG(16). The verification procedure is detailed at
Annex D of RS Appendix 13.1. The model was verified against the diffusion tube located at Mole
Cottage, Grove Lane, as illustrated on RS Figure 13.1.
Traffic Data
13.62 The transport consultants for the development scheme, PFA Consulting Ltd., provided the traffic
data for use in the model. The data provided is presented in Annex C of RS Appendix 13.1, and
described as follows:
• Scenario 1 – 2017 traffic data based on traffic counts taken at the relevant roads on 15th
September 2015. The transport consultants provided a TEMPRO growth factor to convert
2017 flows to 2016.
• Scenario 2 – 2021 opening year traffic data including traffic data from all other committed
developments.
• Scenario 3 – 2021 opening year traffic data including traffic data from all other committed
developments and the Revised Scheme.
13.63 The committed developments included within the traffic data are:
• Land West of Stonehouse
• Javelin Park
• Bond’s Mill Unit 27
• Westend Courtyard
• Land Adjacent to Eastington Trading Estate
• Land Adjoining Station Road
Receptor Locations
13.64 The receptors included in the Study Area, to a certain extent, are determined by the traffic data
provided for the modelling study. Sensitive receptor locations (for example, residential
properties) included in the assessment represents the worst-case exposed locations. The
receptors chosen include both existing receptors, such as at residential properties close to the
roads deemed to be affected by the Revised Scheme, and future receptors within the Revised
Eco Park, Land at M5 Junction 13, West of Stonehouse | Environmental Statement
December 2015
Page | 305
Scheme. The receptors and roads included in the model are summarised in Table 13.10 and
illustrated in RS Figure 13.1. D3, D4, D6 and D8 – D11 are future onsite commercial receptors.
D1, D2, D5, D7 and D12 are future offsite receptors. R1, R3 – R14, R16 and R17 are residential
receptors and R18 is a school receptor.
Table 13.10: Receptors Included in the Dispersion Modelling Assessment
Receptor ID Receptor Location
Grid reference Height (m)
X Y
D1
Northwest area of Redline
Boundary, north of M5 377603 206664 1.5
D2
Within Redline Boundary–
south of M5 and A419 377847 206721 1.5
D3
Within Redline Boundary–
south of M5 and north of
A419 377932 206812
1.5
D4
Within Redline Boundary–
south of M5 and north of
A419 377969 206716
1.5
D5
Within Redline Boundary–
south of M5 and A419 377716 206591 1.5
D6
Within Redline Boundary–
south of M5 and north of
A419 378026 207005
1.5
D7
Within Redline Boundary–
south of M5 and A419 377914 206687 1.5
D8
Within Redline Boundary–
south of M5 and north of
A419 378131 206547
1.5
D9
Within Redline Boundary–
south of M5 and north of
A419 - close to Grove Lane 378173 206907
1.5
D10
Within Redline Boundary–
south of M5 and north of
A419 378305 206390
1.5
D11
Within Redline Boundary–
south of M5 and north of
A419 - close to Grove Lane 378436 206612
1.5
D12
Within Redline Boundary–
south of M5 and A419 377889 206383 1.5
R1
Residential property close
to A419 378264 206325 1.5
R2
Commercial property close
to Grove Lane 378463 206306 1.5
R3
Residential property close
to Spring Hill 378398 206080 1.5
R4
Residential property close
to Spring Hill 378322 205982 1.5
R5
Residential property close
to Spring Hill 378171 205862 1.5
Eco Park, Land at M5 Junction 13, West of Stonehouse | Environmental Statement
December 2015
Page | 306
Receptor ID Receptor Location
Grid reference Height (m)
X Y
R6
Residential property close
to Spring Hill 378175 205810 1.5
R7
Residential property close
to Spring Hill 378116 205774 1.5
R8
Residential property close
to Spring Hill 377963 205530 1.5
R9
Residential property close
to Grove Lane 378402 206731 1.5
R10
Residential property close
to Grove Lane 378324 206817 1.5
R11
Residential property close
to Grove Lane 378275 206956 1.5
R12
Residential property close
to Grove Lane 378289 207000 1.5
R13
Residential property close
to A38 377400 207543 1.5
R14
Residential property close
to A38 377296 207457 1.5
R15
Commercial property close
to M5/A419 junction 377710 206880 1.5
R16
Residential property on
Bristol Road 379894 205225 1.5
R17
Residential property on
Downtown Road 380485 204870 1.5
R18 School on Ebley Road 381389 204722 1.5
V1
Verification site - Mole
Cottage, Grove Lane 378290 206899 2.0
*Verification site (Mole Cottage, Grove Lane diffusion tube)
Baseline Conditions
13.65 Existing or ‘baseline’ air quality refers to the existing concentrations of relevant substances
present in ambient air. These substances may be emitted by various sources, including road
traffic, industrial, domestic, agricultural and natural sources. Baseline air quality data employed
in this study have been obtained from diffusion tube monitoring stations maintained by SDC and
from the Local Air Quality Management (LAQM) Support website maintained by Defra.
13.66 According to SDC’s 2016 Air Quality Progress Report, there were no automatic monitoring
stations operating within the district. NO2 was monitored using passive diffusion tubes at 25
sites.
13.67 The annual average NO2 concentrations obtained at monitoring locations within 6km from the
Revised Scheme are reproduced in Table 13.11. These data show that there were no
exceedances of the annual mean standard for NO2 at the listed monitoring locations.
Table 13.11: Annual Average Measured Pollutant Concentrations at Monitoring Sites Nearest to
the Revised Scheme Site
Eco Park, Land at M5 Junction 13, West of Stonehouse | Environmental Statement
December 2015
Page | 307
Site Approx. distance from
Redline Boundary(km)
2015 Annual Average
NO2 (µg/m3)
2016 Annual Average
NO2 (µg/m3)
Stonehouse –
Mole Cottage,
Grove Lane
0.3 NA 16.7
10 Bristol Road 2.7 20.9 NA
Haresfield – The
Lodge 4.3 NA 24.1
Cainscross – 22
Westward Road 5.6 29.5 29.1
Cainscross – 2 The
Rosaries Paganhill
Lane
5.6 37.5 35.4
Hardwicke –
Trevose 5.6 NA 34.6
Air quality objective (annual mean) 40µg/m3
13.68 In addition to the local monitoring data, estimated background air quality data available from
the LAQM Support website are also used to establish likely background air quality conditions at
the Site. The LAQM website provides estimated annual average background concentrations of
NOx, NO2 PM10 and PM2.5 on a 1km2 grid basis (see Section 4.4 of RS Appendix 13.1). No
exceedance of annual average air quality objectives for human health, for NO2 or PM10 is
predicted at background locations.
13.69 As no background automatic monitoring is undertaken at the Site, the estimated background
pollutant concentrations from the LAQM website for 2016 (with in-square A-road and motorway
contributions removed to avoid ‘double counting’) will be used in the assessment as identified in
Table 13.12. This is considered representative of local air quality conditions at the Site.
Table 13.12: Baseline air quality conditions to be used in model
Assessment
Year
Estimated Annual Average Pollutant Concentrations Derived from the LAQM
Website
Annual Average
NOX (µg/m3)
Annual Average
NO2 (µg/m3)
Annual Average
PM10 (µg/m3)
Annual Average
PM2.5 (µg/m3)
2016 14.0 10.3 16.2 11.1
Air Quality
Objective 30^ 40 40 25
^ air quality objective designated for the protection of vegetation and ecosystems only.
13.70 The baseline air quality estimated at the Site does not exceed the relevant air quality objectives
for NOx, NO2, PM10 and PM2.5.
2017 Traffic Baseline
13.71 The opening year for this assessment is 2017, when the Revised Scheme is assumed to be in
place. Background traffic flows have been factored to 2017 based upon the National Transport
Model (NTM) adjusted using TEMPRO (NTEM Dataset 6.2). This takes account of changes in car
ownership, as well as local planning forecasts regarding housing and employment. More details
are provided in Chapter 12 and the accompanying Transport Assessment (RS Appendix 12.1).
Eco Park, Land at M5 Junction 13, West of Stonehouse | Environmental Statement
December 2015
Page | 308
13.72 Policy SA2 of Stroud District Local Plan 2015 allocates land to the West of Stonehouse for mixed
use development including residential, employment and community uses, and a planning
application (Reference S. 14/0810/OUT) has been granted with work now commencing on site
following the approval of Reserved Matters. The location of the site is identified on RS Figure
18.1 of this ES, and traffic generated by this development is included in the 2017 baseline traffic
forecasts.
13.73 As part of the West of Stonehouse development, improvements to Chipmans Platt roundabout,
which form part of the A419 Stonehouse Corridor scheme approved under the Gloucestershire
Growth Deal, will be brought forward. The improvements include widening to two lane entry
and exit on each of the A419 approaches. The West of Stonehouse proposals also include
improvements to the northbound on-slip to the M5 at Junction 13. This will upgrade the slip
road to current standards but is not expected to have a significant effect on junction capacity.
Both of these schemes are assumed to be in place in the 2017 Baseline. The remaining schemes
which form part of the Gloucestershire Growth Fund A419 Corridor Improvement lie outside the
Study Area for this Chapter.
Design Evolution
Embedded Mitigation/Enhancements
13.74 Mitigation measures that have been identified and adopted as part of the evolution of the project
design (embedded into the project design) and that are relevant to air quality are as follows:
• The provision and compliance with a Green Travel Plan which will have examined all
options for sustainable travel to and from the Site.
• Source energy from renewable energy sources, including the provision of on-site
renewable energy production;
• Principal benchmark to be adopted will be BREEAM;
• The provision of a footway/cycleway on the south side of the A419, that would link
Stonehouse to the Revised Scheme helping to encourage people to walk and cycle.
• Sustainable construction;
• Encourage procurement of energy-efficient equipment;
• Construction site operative awareness and training in sustainable practices.
Potential Effects
Construction Phase
13.75 Construction activities, including the transport of material to and from the Revised Scheme may
cause dust nuisance and deterioration of air quality, albeit for a limited period. The scale of the
Revised Scheme is considered to be ‘medium’ and there are sensitive receptors located within
20m of the Revised Scheme on Grove Lane. Appropriate mitigation or enhancement measures
to reduce dust and air quality effects will be implemented through a DMP.
Exhaust Emissions from Plant and Vehicles
13.76 The operation of vehicles and equipment powered by internal combustion engines results in the
emission of exhaust gases containing the pollutants NOx, PM10, volatile organic compounds
(VOCs), and carbon monoxide (CO). The quantities emitted depend on factors such as engine
type, service history, pattern of usage and fuel composition. The operation of site equipment,
Eco Park, Land at M5 Junction 13, West of Stonehouse | Environmental Statement
December 2015
Page | 309
vehicles and machinery will result in emissions to atmosphere of exhaust gases, but such
emissions are unlikely to be significant, particularly in comparison with levels of similar emission
components from vehicle movements on the local road network surrounding the Site.
13.77 Construction traffic will comprise haulage/ construction vehicles and vehicles used for workers’
trips to and from the Site. The estimated number of car and Heavy Goods Vehicle (HGV)
movements from the Revised Scheme associated with construction traffic are 260 and 100,
respectively. As construction phase impacts are temporary and local to the Site, further
assessment is not considered necessary. Traffic management would be dealt with via the DMP
to reduce air quality impacts.
13.78 It is noted that as shown on the Indicative Construction Compound Plan (RS Figure 5.4), the
construction compound will be located in the southern parts of the Revised Scheme and is not in
proximity to the sensitive receptors along Grove Lane.
13.79 The cumulative effect of construction traffic will not be significant and the effect will be low due
to the distance of the other committed developments to the Revised Scheme site.
Fugitive Dust Emissions
13.80 Fugitive dust emissions arising from construction activities are likely to be variable in nature and
will depend upon the type and extent of the activity, soil type and moisture, road surface
conditions and weather conditions. Periods of dry weather combined with higher than average
wind speeds have the potential to generate more dust.
13.81 Construction activities that are considered to be the most significant potential sources of fugitive
dust emissions are:
• Demolition of existing buildings and the size reduction and handling of materials;
• Earth moving, due to the handling, storage and disposal of soil and subsoil materials;
• Construction aggregate usage, due to the transport, unloading, storage and use of dry and
dusty materials (such as cement and sand);
• Movement of heavy site vehicles on dry or untreated haul routes;
• Movement of vehicles over surfaces where muddy materials have been transferred off-
site (for example, on to public highways).
13.82 Fugitive dust arising from construction and demolition activities is mainly of a particle size greater
than the PM10 fraction (that which can potentially impact upon human health), however it is
noted that demolition and construction activities may contribute to local PM10 concentrations.
Appropriate dust control measures can be highly effective for controlling emissions from
potentially dust generating activities identified above, and adverse effects can be greatly reduced
or eliminated.
Potential Dust Magnitude
13.83 With reference to the IAQM guidance criteria, the dust emissions magnitude for demolition,
earthworks, construction and trackout activities are summarised in Tables 13.13 to 13.16. Risk
categories for the four construction activities are summarised in Table 13.17. Worst case
assumptions have been made throughout.
Table 13.13: Summary of Dust Emissions Magnitude of Demolition Activities (Before mitigation)
Eco Park, Land at M5 Junction 13, West of Stonehouse | Environmental Statement
December 2015
Page | 310
Demolition Criteria Dust Emissions Class Evaluation of the Effects
Total volume of buildings to be
demolished Small <20,000m3
On-site crushing and screening Medium Yes, on-site crushing and screening
proposed
Height of demolition activities
above ground Small <10m above ground
Dust potential of demolition
materials Medium Potentially dusty construction materials
Overall Rating Medium Worst case
Table 13.14: Summary of Dust Emissions Magnitude of Earthworks Activities (Before mitigation)
Earthworks Criteria Dust Emissions Class Evaluation of the Effects
Total site area Large >10,000m2
Soil type Large Clay
Earth moving vehicles at any one
time Medium
Maximum of 5-10 heavy earth moving
vehicles active at any one time
Height of bunds Small <4m
Total material moved Large > 100,000 tonnes material to be moved
Work times Medium Earthworks proposed in all seasons
Overall Rating Large Worst case
Table 13.15: Summary of Dust Emissions Magnitude of Construction Activities (Before
mitigation)
Construction Criteria Dust Emissions Class Evaluation of the Effects
Total building volume Large > 100,000m3
On-site concrete batching or
sandblasting proposed Small None proposed
Dust potential of construction
materials Medium Potentially dusty materials
Overall Rating Medium Worst case
Table 13.16: Summary of Dust Emissions Magnitude of Trackout Activities (Before mitigation)
Trackout Criteria Dust Emissions Class Evaluation of the Effects
Number of HDV>3.5t per day Large >50 heavy vehicles per day
Surface type of the site Medium Mix of hard and soft
Length of unpaved road Small <50m unpaved roads
Overall Rating Medium Worst case
Table 13.17: Summary of Dust Emission Magnitude of the Site (Before mitigation)
Construction Activities Dust Emissions Class
Demolition Medium
Earthworks Large
Construction Medium
Trackout Medium
Eco Park, Land at M5 Junction 13, West of Stonehouse | Environmental Statement
December 2015
Page | 311
13.84 The construction activities have the potential to have a significant effect on the surrounding
environment. Therefore, the sensitivity of the area must be evaluated to determine whether the
construction activities will have a significant effect in relation to the level of sensitivity of the
area.
Sensitivity of the Area
13.85 As per the IAQM Guidance, the sensitivity of the area takes into account a number of factors;
consideration is given to human and ecological receptors from the effect of the construction of
the Revised Scheme and the trackout route proposed.
13.86 RS Figure 13.2 shows a map indicating the construction buffer and RS Figure 13.3 shows the
trackout buffer for identifying the sensitivity of the area. It is noted that the majority of
construction traffic is expected to be routed via the A419 and M5 to the west of the Site; no
construction traffic will be permitted to use Grove Lane or Spring Hill, as per Chapter 12. Table
13.18 presents the determined sensitivity of the area with the factors itemised which have
helped to define this.
13.87 Construction activities are relevant up to 350m from the Revised Scheme whereas trackout
activities are only considered relevant up to 50m from the edge of the road, as per the guidance.
Only 20m and 50m buffers have been included for trackout for this reason.
13.88 The table below details the receptor sensitivity to dust soiling and human health. Receptor
sensitivity is determined by the types of receptors present near the Revised Scheme. High
sensitivity receptors include residential dwellings, hospitals and schools. The overall sensitivity
of the area is then calculated with reference to Table 13.18.
Table 13.18: Sensitivity of the area
Potential
Effect
Sensitivity of the surrounding area
Demolition Earthworks Construction Trackout
Annoyance
from Dust
soiling
Receptor
sensitivity High High High High
Number of
receptors 1-10 1-10 1-10 1-10
Distance from
the source <20m <20m <20m <20m
Sensitivity of
the area Medium Medium Medium Medium
Risk to
Human
health
Receptor
sensitivity High High High High
Annual mean
PM10
concentration
<2424c3 <2424c3 <2424c3 <2424c3
Number of
receptors 1-10 1-10 1-10 1-10
Distance from
the source <20m <20m <20m <20m
Sensitivity of
the area Low Low Low Low
Eco Park, Land at M5 Junction 13, West of Stonehouse | Environmental Statement
December 2015
Page | 312
Potential
Effect
Sensitivity of the surrounding area
Demolition Earthworks Construction Trackout
Risk to
Ecology
Receptor
sensitivity There are no designated ecologically sensitive sites within 50m
of the Site or proposed trackout routes. Distance from
the source
Sensitivity of
the area Negligible
13.89 Grove Lane properties are the closest receptors to the Revised Scheme. It is likely that residents
at these properties will receive the largest effects associated with the construction phase.
Mitigation should be geared towards ensuring the effect of dust soiling and to human health is
minimised as much as possible for the residents along Grove Lane.
Significance of Effects
13.90 The dust emission magnitude summarised in Table 13.17 have been combined with the
sensitivity of the area in Table 13.18 to determine the potential effects of construction activities
before mitigation. The potential of dust effects from construction activities is identified in Table
13.19. Site specific mitigation measures to reduce construction phase effects are defined based
on this assessment.
Table 13.19: Summary of the Potential Effect from Construction Activities (prior to mitigation)
Potential Effect Dust Effect on Receptors
Demolition Earthworks Construction Trackout
Dust soiling Medium Medium Medium Medium
Human health Low Low Low Low
Ecological Negligible Negligible Negligible Negligible
13.91 In EIA terms, the construction activities will not have a significant effect on human health and
the local ecology. However, there will be a significant effect on the surrounding environment as
a result of dust soiling if no mitigation measures are put into place.
Mitigation and Enhancement Measures
Construction phase
13.92 Further to the embedded mitigation relevant to air quality summaries in the Design Evolution
section, the following mitigation measures will be adopted in order to further minimise
significant effects and non-significant effects of dust soiling on air quality.
13.93 The detailed specification of mitigation measures in the DMP will depend on the selection of
construction techniques and programme. However typical recommended mitigation measures for
construction phase effects are likely to include:
Site Planning
• No bonfires on site;
Eco Park, Land at M5 Junction 13, West of Stonehouse | Environmental Statement
December 2015
Page | 313
• Plan site layout – plant/vehicles/dust-generating activities should be located away from
sensitive receptors as far as practicable;
• All site personnel to be trained in awareness of site environmental controls;
• Trained and responsible manager on site during working hours to maintain logbook and
carry out site inspections.
Construction Plant and Traffic Emissions
• No idling vehicles on site;
• Vehicle wheel washing facilities to be provided at site exit;
• All loads/vehicles-entering site to be covered;
• Prevention of site runoff of mud and water;
• On-road vehicles to comply with emissions standards;
• All non road mobile machinery to use ultra low sulphur diesel where available and be fitted
with exhaust after-treatment, where appropriate;
• Minimise vehicle speeds and movements on site.
Site Activities
• Use water as a dust suppressant as appropriate;
• Cover, seed or fence stockpiles to prevent wind whipping;
• Minimise dust-generating activities as far as is practicable;
• Ensure any cutting equipment has water suppression or suitable local exhaust ventilation
system.
Operational Phase
13.94 Sensitive receptors have been selected at residential properties located along the A38, M5, A419,
Spring Hill and Grove Lane. Annex D of RS Appendix 13.1 presents the predicted NO2, PM10 and
PM2.5 concentrations for all of the assessed scenarios at the assessed receptor locations. Table
13.20 shows the comparison of annual mean NO2 concentrations under the ‘S2 Without
development 2021’ and ‘S3 With Development 2021’ scenarios at the assessed existing receptor
locations. The percentage changes in annual mean NO2 concentrations relative to the air quality
objective and the classification of effect magnitudes with reference to the EPUK-IAQM guidance
are also presented.
13.95 The maximum annual mean NO2 increase and air quality effect as a result of the development is
predicted to be 1.3µg/m3 at R16 (residential property Bristol Road) (3.3% change relative to the
Air Quality Assessment Level (AQAL)). This 3.3% change corresponds to a ‘negligible’ air quality
effect, as the existing concentration is <75% of the AQAL. RS Figure 13.4 presents the annual
mean NO2 concentration isopleth for the ‘S3 With Development 2021’ scenario.
Table 13.20: Comparison of Predicted Long-Term NO2 Concentrations between the ‘S2 Without
development 2021’ and ‘S3 With Development 2021’ Scenarios
Eco Park, Land at M5 Junction 13, West of Stonehouse | Environmental Statement
December 2015
Page | 314
Receptor
ID
Without Development
2021
With Development
2021 Change
Predicted
Effect
(µg/m3) % of AQAL (µg/m3) % of AQAL (µg/m3)A % Change
NO2
concentra
tion
relative to
AQALA
D1 - - 19.9 - - - -
D2 - - 23.0 - - - -
D3 - - 24.0 - - - -
D4 - - 24.6 - - - -
D5 - - 23.2 - - - -
D6 - - 29.7 - - - -
D7 - - 20.9 - - - -
D8 - - 24.6 - - - -
D9 - - 15.4 - - - -
D10 - - 21.3 - - - -
D11 - - 15.0 - - - -
D12 - - 13.6 - - - -
R1 16.3 40.8 16.8 42.0 0.5 1.2 Negligible
R2 19.5 48.7 20.0 50.1 0.6 1.4 Negligible
R3 16.6 41.4 17.0 42.4 0.4 1.0 Negligible
R4 18.0 44.9 18.4 46.0 0.4 1.1 Negligible
R5 14.4 36.0 14.6 36.6 0.2 0.6 Negligible
R6 15.6 39.0 15.9 39.8 0.3 0.8 Negligible
R7 16.7 41.7 17.0 42.6 0.4 0.9 Negligible
R8 18.1 45.2 18.5 46.3 0.4 1.1 Negligible
R9 16.6 41.5 16.7 41.7 0.1 0.2 Negligible
R10 17.2 43.1 17.3 43.3 0.1 0.2 Negligible
R11 18.5 46.2 18.6 46.5 0.1 0.2 Negligible
R12 22.4 56.1 22.5 56.3 0.1 0.2 Negligible
R13 20.7 51.9 20.9 52.2 0.2 0.4 Negligible
R14 15.6 38.9 15.6 39.1 0.1 0.2 Negligible
R15 18.9 47.3 19.1 47.8 0.2 0.4 Negligible
R16 24.5 61.2 25.8 64.5 1.3 3.3 Negligible
R17 20.1 50.1 20.8 52.1 0.8 1.9 Negligible
R18 18.3 45.9 18.4 46.1 0.1 0.3 Negligible AChange based on unrounded values
13.96 The predicted PM10 and PM2.5 concentrations at all the assessed receptors and under all scenarios
will not exceed the relevant air quality objectives. With reference to the EPUK-IAQM guidance,
the Revised Scheme will have a ‘negligible’ predicted effect upon annual mean PM10 and PM2.5
concentrations, as all concentration changes are equal to or less that 0.7% of the standard and
existing concentrations are likely to be ‘well below’ (<75%) the relevant AQALs. Isopleths for the
‘S3 With Development 2021’ scenario for annual mean PM10 and PM2.5 concentration are
presented on RS Figure 13.5 and RS Figure 13.6, respectively.
13.97 In regard to exposure, future receptors within the Revised Scheme have been assessed. As the
Revised Scheme is commercial only the short-term NO2 objective applies to receptors. Short-
term NO2 refers to the 1 hour mean objective which is relevant for commercial sites where
exposure time is limited to the working hours.
13.98 No exceedances at any receptors have been predicted with the maximum short-term
concentration being 45.6µg/m3 at receptor D6 (D6 being adjacent to the M5 motorway and
Eco Park, Land at M5 Junction 13, West of Stonehouse | Environmental Statement
December 2015
Page | 315
therefore representing worst case within the Revised Scheme). This is below the air quality
objective of 200µg/m3 and therefore exposure to future receptors within the Revised Scheme is
considered to not be significant.
Mitigation and Enhancement Measures
Operational Phase Mitigation
13.99 The assessment demonstrates that the operational phase air quality effects of the Revised
Scheme are negligible and therefore, not significant following the embedded mitigation
discussed under the Design Evolution heading above. The provision and compliance with an
Outline Travel Plan (as included in RS Appendix 12.2), which has examined all options for
sustainable travel to and from the Site, will help to encourage travel by more sustainable
methods of transport. The following measures are proposed:
• Public transport information available through FGRFC’s website;
• As required additional buses to/ from local supporter hotspots including Stonehouse,
Stroud and Nailsworth;
• As required shuttle buses to/ from Stonehouse and Cam & Dursley rail stations;
• Bus and coach drop off areas within the Site;
• Supporter carshare link via FGRFC’s website;
• Safe linkage to pedestrian routes from Stonehouse and West of Stonehouse;
• Vehicle free area around the Stadium;
• Convenient cycle parking.
13.100 These enhancement measures should reduce any potential adverse effect further.
13.101 Fixed energy source details are not available at this stage of the project for the Revised Scheme.
Once identified (Reserved Matters stage) these sources may require additional assessment.
Residual Effects
13.102 With the proposed mitigation measures (in relation to the significant effect of the construction
phase on dust soiling) and enhancements (in relation to the operational phase where no
significant effects were found) in place, the significance of the residual effects is considered to
be ‘not significant’. Table 13.21 located at the end of the chapter summarises the residual effects
before and after mitigation during the construction and operational phase.
Cumulative Effects
Construction Effects
13.103 Due to the separation distance between the Revised Scheme site and the other committed
developments nearby and also due to different traffic routes, it is not considered likely that
cumulative effects during the construction phase are significant. Furthermore, the potential
effects of this development during the construction phase will be temporary i.e. only during the
construction and demolition period. The estimated number of car and HGV movements from the
Revised Scheme are 260 and 100, respectively. The cumulative effect of construction traffic was
not assessed within the scope of this report. However, construction traffic is localised to the
roads nearby the Revised Scheme.
Eco Park, Land at M5 Junction 13, West of Stonehouse | Environmental Statement
December 2015
Page | 316
13.104 With regards to nearby residential receptors, there is potential for a significant effect as a result
of dust soiling during the construction phase if the Revised Scheme construction activities occur
at the same time as the Land West of Stonehouse developments. In such an eventuality, traffic
management would be dealt with via the DMP and necessary legal agreements for each of the
respective developments. This will ensure no significant effect. The same assessment will apply
when considering both the effect on human health and ecology.
Operational Effects
13.105 The Baseline Conditions section explains that the proposed development on the land West of
Stonehouse (Policy SA2 in Stroud District Local Plan 2015) is included in the 2017 baseline.
Improvements to Chipmans Platt roundabout and to the northbound on slip to the M5 at
Junction 13, which lie within the Study Area, are also assumed to be implemented. The proposals
for the land West of Stonehouse also include contributions towards public transport, and it is
assumed that the Revised Scheme can build upon these.
13.106 Traffic generated by the remaining developments identified in Chapter 18 of this ES is taken into
account through the application of traffic growth factors obtained from the NTM adjusted using
TEMPRO (NTEM Dataset 6.2). The TEMPRO program is based on the National Trip End Model
and takes into account changes in car ownership, and local planning forecasts regarding housing
and employment.
13.107 The access to the Revised Scheme has been designed to accommodate future traffic flows
allowing for committed developments. There are therefore no further cumulative effects to be
taken into account during operation. The assessment found that the cumulative effect of traffic
will not be significant in relation to air quality during the operational phase.
Conclusions
13.108 With the implementation of the proposed construction phase mitigation measures (detailed in
Annex F of RS Appendix 13.1), the residual effects are considered to be negligible.
13.109 The modelled proposed receptors are not predicted to experience pollutant concentrations
above the annual mean NO2, PM10 or PM2.5 objectives; hence, it is not considered that there
would be a risk of increased exposure at the Site. The Revised Scheme is predicted to have a
‘negligible’ air quality effect on all of the surrounding sensitive receptors and proposed
receptors.
13.110 The potential for dust effects on receptors was predicted to be a maximum of ‘medium’ during
the construction phase without mitigation. With mitigation in place the construction phase effect
will not be significant. However, residential receptors located near to the Revised Scheme should
be considered within the Air Quality Management Plan during the construction phase as the
largest effect will be seen at these. Site specific enhancements have also been assigned to
reduce the effect for general site activities and construction activity-specific activities.
13.111 The principal air quality effects once the Revised Scheme is complete and operational is likely to
be emissions from increased road traffic associated with the scheme. An assessment of
operational effects has been undertaken using the latest version of the ADMS-Roads
atmospheric dispersion model.
Eco Park, Land at M5 Junction 13, West of Stonehouse | Environmental Statement
December 2015
Page | 317
13.112 Concentrations of the key pollutants (NO2, PM10 or PM2.5) were predicted at the most relevant
receptor locations for the base year 2016, and for the year 2021. The air quality effects of the
Revised Scheme on existing receptors and the effect of future local air quality upon the Revised
Scheme receptors have been assessed.
13.113 The predicted pollutant concentrations have been verified and adjusted against the measured
concentrations.
Effect of the Development on Local Air Quality
13.114 No exceedance of any of the relevant air quality objectives was predicted at any of the assessed
existing receptor locations under any of the assessed scenarios. As a result of the development
(S3 2021 With Development), there is a ‘negligible’ air quality effect predicted with regard to
annual mean NO2, PM10 or PM2.5 on existing sensitive receptors assessed, as per the EPUK-IAQM
guidance. This effect will also be very infrequent given the number of games FGR play at home
every year. Therefore, the effect will not be significant in EIA terms.
Effect of Future Air Quality on the Proposed Sensitive Receptors
13.115 The predicted long-term PM10 and PM2.5 and short-term NO2 and PM10 concentrations, at all of
the assessed receptors within the Development Footprint will not exceed the relevant air quality
objectives under any of the assessed scenarios.
13.116 The Revised Scheme is designed for commercial use and therefore the short-term NO2 objective
applies to the Revised Scheme receptors (rather than the annual mean NO2 objective). No
exceedance of the short-term NO2 air quality objective has been predicted at any of the proposed
receptor locations within the Redline Boundary or the Revised Scheme. Therefore, the effect will
not be significant in EIA terms.
13.117 In view of the above, and with reference to EPUK-IAQM guidance, the Revised Scheme is
considered to have no significant effects on local air quality including those at the existing and
proposed receptor locations.
Eco Park, Land at M5 Junction 13, West of Stonehouse | Environmental Statement
December 2015
Page | 318
Table 13.21: Summary of Air Quality and Dust Effects and Mitigation
Receptor Effect Development Phase Sensitivity/
importance of
receptor
Magnitude change Level of Effect (and
Significance) prior
to mitigation
Mitigation Enhancement Level of Effect (and
Significance) after
mitigation
Nature of Effect
Residential
receptors (R1, R3 to
R14, R16, and R17)
and School
Receptor (R18)
Dust Soiling Construction Residential
dwelling/ School
Sensitivity high.
N/A Medium effect /
significant
Implement a
construction phase
air quality
management plan
N/A Dust levels
acceptable / not
significant
Negative, Medium
Term
Residential
receptors (R1, R3 to
R14, R16 and R17)
and School
Receptor (R18)
Human Health Construction Residential
dwelling/ School
Sensitivity high.
N/A Low effect / not
significant
N/A Implement a
construction phase
dust management
plan
Dust levels
acceptable / not
significant
Negative, Medium
Term
Residential
receptors (R1, R3 to
R14, R16 and R17)
and School
Receptor (R18)
Exhaust Emissions Construction Residential
dwelling/ School.
Sensitivity high.
N/A Low effect / not
significant
N/A Implement a
construction phase
dust management
plan
Dust levels and
exhaust emissions
acceptable / not
significant
Negative, Medium
Term
Commercial
receptors (R2, R15)
Human Health /
Dust Soiling /
Exhaust Emissions
Construction Commercial
dwelling Sensitivity
low.
N/A Low effect / not
significant
N/A Implement a
construction phase
dust management
plan
Dust levels and
exhaust emissions
acceptable / not
significant
Negative, Medium
Term
All residential
receptors (R1, R3-
R14, R16 and R17)
and School
Receptor (R18)
Exposure to NO2,
PM10 and PM2.5
from exhaust
emissions
Operational Residential
dwelling/ School.
Sensitivity high.
Negligible Not significant Embedded
mitigation (see
Design Evolution)
N/A Air quality levels
acceptable / not
significant
Negative, Long
Term
Commercial
receptors (R2, R15)
Exposure to NO2,
PM10 and PM2.5
from exhaust
emissions
Operational Commercial sites.
Sensitivity low.
Negligible Not significant Embedded
mitigation (see
Design Evolution)
N/A Air quality levels
acceptable / not
significant
Negative, Long
Term
Eco Park, Land at M5 Junction 13, West of Stonehouse | Environmental Statement
December 2015
Page | 319
Future receptors
within the Redline
Boundary (D1 to
D12)
Exposure to NO2,
PM10 and PM2.5
from exhaust
emissions
Operational Commercial sites.
Sensitivity low.
Negligible Not significant Embedded
mitigation (see
Design Evolution)
N/A Air quality levels
acceptable / not
significant
Negative, Long
Term
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 320
14 LIGHTING
Summary
14.1 This chapter describes the assessment work undertaken by Hopkins Coats Associates (HCA) to
detail and describe the likely significant environmental effects of the proposed external lighting,
in association with the Revised Scheme. This chapter assesses artificial lighting in all areas of the
Development Footprint, as well as the additional lighting required along the A419.
14.2 The lighting impact assessment also assesses the potential effects on the existing adjacent
properties, users of the M5 and A419 carriageways, as well as other sensitive receptors such as
the existing Industrial Heritage Conservation Area (IHCA) and local wildlife.
14.3 The lighting strategy produced should be considered as a provisional design in accordance with
the Institution of Lighting Professionals (ILP). The provisional design is based on the Indicative
Concept Plan (RS Figure 1.1), along with the indicative parameter plans (RS Figures 5.1 to 5.3)
and the Indicative Construction Compound Plan (RS Figure 5.4) submitted with this
Environmental Statement (ES). The lighting impact assessment has also been undertaken in
accordance with the parameters set out by the ILP. In the event that planning permission is
granted, a final design will need to be generated in accordance with the parameters set out by
the ILP at a later date, to discharge the Reserved Matters. For this Revised Scheme, a provisional
lighting scheme has been generated for the entire development requiring artificial light. This
includes the Development Footprint applied for in outline, and the access arrangements applied
for in full.
14.4 The Development Footprint consists of a stadium and two training pitches for the Forest Green
Rovers Football Club (FGRFC) together with supporting ancillary facilities (such as changing
rooms, food and drink outlets, Club shop etc., public realm and car parking areas).
14.5 The existing Redline Boundary (which also includes the development parcels south of the A419
and west of the M5), contains no artificial light sources and has a negligible lighting effect on the
surrounding area. There is some light spill into the existing undeveloped site within the Redline
Boundary from adjacent properties. This is particularly noticeable around the William Morris
College (WMC) car park, where light spills from the car park into the Redline Boundary.
Stadium Lighting
14.6 The development will introduce an addition to the existing sky glow when the stadium lighting is
in operation (i.e. during evening matches). The increase in sky glow has been identified as a major
adverse effect in accordance with Table 14.3 below. This in turn has been identified as a
significant environmental effect within the meaning of the Environmental Impact Assessment
(EIA) Regulations. However, in terms of frequency, based on the 2017 – 2018 season, FGRFC
home matches are expected to occur approximately thirty times per year, or two to three times
per month on average, with not all of these taking place in the evening or a time of year when
stadium lighting will create the same significant effect (for example, during lighter evenings).
Significant effects caused by sky glow are thus infrequent.
Site wide Lighting (other than the Stadium)
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 321
14.7 The provisional lighting scheme also shows that minimal light will be spilled into the bat corridors
designated for the Revised Scheme (as identified on RS Figure 5.3), which has been categorised
as a minor negative effect in accordance with Table 14.3. This in turn is deemed not significant
in EIA terms. Light intrusion, threshold increment, and luminance intensity are assessed as minor
negative or negligible effects in accordance with Table 14.3 and not EIA significant.
14.8 Mitigation and enhancement measures have been suggested to minimise the above effects.
These accord with mitigation methods recommended by the ILP. This includes the use of LED
lighting with specialist optics to further mitigate the backward spill of light. This, in tandem with
back shields, will help to eradicate the light spill into sensitive areas.
14.9 The use of an additional screened fence around the periphery of the site could be considered.
Particular attention should be made to areas observing the highest level of light spill, as identified
on RS Figure 14.5.
14.10 Following the implementation of mitigation and enhancement measures, whilst an overall
negative lighting effect remains on what is currently an unlit environment, in accordance with
Table 14.3, this is to be considered not significant in EIA terms.
Introduction
14.11 This chapter presents the findings of an assessment of baseline artificial lighting levels and
predicted effects on the local area resulting from the proposed lighting design assumed for the
Revised Scheme. The assessment covers the effects of artificial lighting from the Revised Scheme
on existing residential properties, motorists along the M5 and A419, the IHCA and local wildlife.
The Development Footprint will have year-round use and it is important for the lighting strategy
to provide adequate safe illumination levels for users of the facilities while minimising light spill
to existing residential and ecological receptors around the perimeter of the Site.
Lighting legislation and Guidance
14.12 This lighting impact assessment has been written by HCA, a Chartered Building Services
Engineering Consultancy registered with the Charted Institution of Building Services Engineers
(CIBSE). Specifically, this assessment has been carried out by Peter Hopkins. Peter has a Bachelor
Degree in Engineer, 7 years’ experience as a Consultant Engineer; 3 years of which as a Partner
at HCA.
Governing regulations and guidance documents
14.13 The Revised Scheme must comply with the Building Regulations amongst other governing
guidance documents and regulations (typically stipulated by the Building Regulations) as noted
below. These documents evaluate task areas, illuminance levels and allowable negative effects.
The guidance documents considered in this lighting assessment are detailed below:
• British Standards Institution, 2013, BS 5489-1, ‘Light of roads and public amenity areas’
• British Standards Institution, 2014, BS EN 12464-2, ‘Light and lighting. Lighting of work
places. Outdoor work places’
• British Standards Institution, 2007, BS EN 12193, ‘Light and lighting. Sports lighting’
• British Standards Institution, 2015, BS EN 13201-2, ‘Road Lighting. Performance
requirements’
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 322
• Chartered Institution of Building Services Engineers, 2006, LG04, ‘Lighting Guide 04: Sports
Lighting’
• Chartered Institution of Building Services Engineers, 2016, LG06/16, ‘Lighting Guide 06:
The Exterior Environment’
• Bat Conservation Trust, 2014, ‘Artificial lighting and wildlife – Interim Guidance:
Recommendations to help minimise the impact artificial lighting’
• Bat Conservation Trust, 2009, ‘Bats And Lighting In The UK Bats and the Built Environment
Series’
• International Commission on Illumination, 2003, CIE 150, ‘Guide on the Limitation of the
Effects of Obtrusive Lighting from Outdoor Lighting Installations’
• Institution of Lighting Professionals, 2011, GN01, ‘Guidance Notes for the Reduction of
Obtrusive Light’
• Institution of Lighting Professionals, 2013, PLG02, ‘The Application of Conflict Areas on the
Highway’
• Institution of Lighting Professionals, 2013, PLG04, ‘Guidance on Undertaking
Environmental Lighting Impact Assessments’
14.14 Site usage/ task areas and associated illuminance levels, together with the relevant guidance
documents are as defined in Table 14.1 and as detailed on RS Figure 14.2. There are a number
of different task areas/ uses for the Revised Scheme. Artificial lighting is required to allow users
of each task area to see hazards, orientate themselves, recognise other users and to help them
feel more secure. Each use/ task area requires a different level of illumination governed by its
associated governing guidance document. Provisional task areas are identified in RS Figure 14.3.
Table 14.1: Guidance Illumination Levels for Each Task Area
Task area Illumination
level
Standard Other notes
Public car
park
20 lux average
0.25 uniformity
BS 5489-1 clause
7.4.8.3 table 5.
Car park areas likely to contain heavy traffic
(vehicular and pedestrian) at certain times.
Private
roads
15 lux average
0.40 uniformity
BS EN 13201 class
CE3
Roads likely to have conflict areas138 as
motorised traffic will intersect pedestrians at
certain times.
General
roads
15 lux average
0.40 uniformity
BS EN 13201 class
CE3
Roads likely to have conflict areas as
motorised traffic will intersect pedestrians at
certain times.
Footpaths
and
amenity
areas
5 lux average
1 lux minimum
maintained
BS 5489-1 clause
A3.3.1 table A5.
Footpath and amenity areas likely to be
conflict areas.
Principal
club
stadium
200 lux average
0.7 uniformity
LG04 section 3.23. Association football pitch class II (suitable for
principal/ small club).
A419 dual
carriageway
20 lux average
0.4 uniformity
BS EN 13201-2
section 5.
Class CE2 following recommendations of
transport consultant.
138 A Conflict area shall be as defined in section 7.5 of BS5489 as “Conflict areas are typically junctions, intersections,
roundabouts and pedestrian crossings, where significant streams of motorised traffic intersect with each other or with
other road users such as pedestrians and cyclists.” Road users will intersect other road users as well as pedestrians
and cyclists in the Development Footprint.
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 323
14.15 This lighting assessment has been written in accordance with the ILP PLG 04 guidance document,
and illumination levels have been designed in accordance with the documents identified above.
Guidance on Permissible Lighting Levels
14.16 The allowable environmental conditions are detailed in ILP PLG04. It is suggested (although it is
to be clarified by the Local Planning Authority at Reserved Matters stage) that the environmental
zone of the development area is E2 (Low District Brightness, see Table 14.2). Environmental zone
E2 has been deduced based on the location of the site, acknowledging that the Cotswolds AONB
is located approximately 2km away from the north-eastern site boundary. Given the relatively
close proximity to the AONB, the environmental conditions identified in Table 14.2 must be
adhered to as far as practicable. The ILP PLG04 guidance document suggests the following
lighting constraints in E2 environmental zones.
Table 14.2: Obtrusive Light Limitations for Exterior Lighting Installations
Environmental
Zone
Sky
Glow
ULR
(Max)
%
Lighting
intrusion (into
windows) Ev
(lux)
Luminance
intensity I
Candelas (cd)
Building luminance L (cd/m2)
Pre-
curfew
Post-
curfew
Pre-
curfew
Post-
curfew
Pre-curfew
E2 Low district
brightness.
Rural, small
village,
relatively dark
urban
location.
2.5 5 1 7,500 500 5
14.17 The terms in the table have the following meanings:
ULR upward light ratio of installation
Ev vertical illuminance in lux (centre of windows)
I light source intensity
L luminance
14.18 The curfew is the time after which stricter requirements for control of obtrusive light apply (likely
to be a condition imposed by the local planning authority at Reserved Matters stage). The
Revised Scheme has a provisional curfew time of 21:00. The FGR stadium (and associated
ancillary areas) will be allowed to extend on this curfew time in exceptional circumstances; such
as for periodic evening matches or extra time in knock out tournaments. Hours of operation of
the Development Footprint are explored in further detail later in this chapter.
National Planning Policy Framework
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 324
14.19 In March 2012, The National Planning Policy Framework (NPPF) was published, superseding the
majority of previous Planning Policy Statements with immediate effect. The National Planning
Policy Framework was intended to simplify the planning system and includes a presumption in
favour of sustainable development. Section 11 of the NPPF deals with Conserving and Enhancing
the Natural Environment, and states that the intention is that the planning system should
prevent ‘development from contributing to or being put at unacceptable risk from, or being
adversely affected by unacceptable levels of soil, air, water or noise pollution or land instability’
and goes on to state that ‘new development [should be] appropriate for its location’ and ‘the
effects (including cumulative effects) of pollution on health, the natural environment or general
amenity, and the potential sensitivity of the area or proposed development to adverse effects
from pollution, should be taken into account.’
Stroud District Local Plan (2015)139
14.20 The adopted Stroud District Local Plan contains the following reference to lighting or light
pollution.
“Policy ES3: Permission will not be granted to any development which would be likely to lead to,
or result in an unacceptable level of Environmental pollution to water, land or air.”
Eastington Parish Council Neighbourhood Development Plan
14.21 The Eastington Parish Council (Eastington PC) Neighbourhood Development Plan (NDP), 2016,
does not suggest any constraints pertaining to artificial lighting.
Statutory Documents
14.22 The Clean Neighbourhoods and Environment Act 2005140 has made light pollution a statutory
nuisance under the Environmental Protection Act 1990, which came into force on 6th April 2006.
Section 79 of the Environmental Protection Act 1990 has been amended to include artificial light
emitted from premises that potentially could be prejudicial to health or a nuisance.
Assessment Methodology and Significance Criteria
Consultation
14.23 HCA initially provided a lighting assessment in September 2016 for a Further Environmental
Information (FEI) document. This was in response to a number issues raised by SDC via their
appointed consultants, Arup, as part of the original Eco Park submission in January 2016. The
scope and content of the assessment provided by HCA in September 2016 was confirmed as
appropriate. This assessment follows the same format and methodology as that previous
assessment.
Methodology
139 Stroud District Local Plan (2015) 140 The Clean Neighbourhoods and Environment Act 2005
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 325
14.24 In order to assess the environmental effects of the proposed lighting scheme, a baseline
condition survey has been completed. This is detailed further in the baseline conditions section
of this chapter.
14.25 Potential sensitive receptors have been defined as:
• The existing adjacent properties;
• Users of the M5 and A419 carriageways;
• The existing Industrial Heritage Conservation Area (IHCA);
• Local wildlife.
14.26 Each receptor has been considered in this assessment.
14.27 Construction will predominantly be carried out during daytime hours where natural light is
available. Overnight lighting will likely be required for security purposes only within the
construction compound (likely to observe less than 5lux around the periphery of the construction
compound, see also RS Figure 5.4). The short-term lighting effects are likely to be negligible and
therefore the construction phase can be assessed as level 4 (none/ negligible) in accordance with
ILP’s recommendations. In view of this conclusion, for the purposes of this EIA, the potential
effects have been confined to, and evaluated based on, the final construction/ occupation of the
entire site (i.e. Operational effects only).
14.28 The provisional design has been assessed to ensure that the Revised Scheme is not excessively
illuminated; but is still designed in accordance with the guidance documentation previously
identified. This includes the consideration of achieving minimum and average illumination levels,
as well as conformity with minimum uniformity levels. These levels are identified in Table 14.1.
Constraints have also been thoroughly considered (and discussed under the Design Evolution
heading below), and mitigation methods are discussed and applied, as required, later in this
chapter.
14.29 The provisional lighting design has been modelled as a ‘worst case’. Therefore, enhancements
have not been considered in the Site wide horizontal contour plots, although all embedded
mitigation (such as the earth bund along the northern and eastern Redline Boundary) has been
included. Worst-case has been modelled to reflect both the needs of EIA, as well as to
demonstrate that a considerate lighting strategy can be attained without the requirement of
extensive enhancement measures. Enhancement measures will be assessed in the horizontal
contour plots in full at Reserved Matters stage.
14.30 In the worst-case areas, where light spill has been observed, a localised strategy has been
modelled to discuss the mitigation measures required to overcome the spill as far as possible,
and demonstrate their compliance with the guidance documentation. Digital models have been
generated using Relux Pro lighting calculation software.
Describing Different Lighting Effects
14.31 Lighting effects fall into several different types which can be identified as spilled light, light
intrusion, increase in luminance intensity to neighbouring properties, intrusive threshold
increments to adjacent highways and increase in sky glow.
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 326
14.32 Spilled light – Spilled light is the unwanted spill of light away from the area which is being
illuminated (task area). Spilled light can be considered a nuisance if it were to trespass on to third
party land.
14.33 Light intrusion – Light intrusion is light that trespasses into windows of properties lying adjacent
to the Development Footprint. This is typically as a consequence of spilled light.
14.34 Intrusive threshold increment – The threshold increment is a measure of the loss of visibility
that is caused by the glare from obtrusive lighting installations. In particular, the threshold
increment effects on users of the adjacent highways (M5 and A419).
14.35 Increase in luminance intensity – Luminance intensity is similar to the intrusive threshold
increment, as the luminance intensity causes the loss of visibility caused by glare.
14.36 Sky Glow – Sky glow is, as suggested by the name, the glowing of the sky directly above an area
that is being illuminated. This is typically a consequence of light reflecting from the lit area back
up into the sky. The amount of sky glow being observed depends on a number of parameters,
including level of illumination and weather conditions.
Significance Criteria
Institution of Lighting Professionals Criteria for the Assessment of Lighting Effects
14.56 The effects of each phase of the Revised Scheme (prior to mitigation and enhancement) are to
be assessed in accordance with the criteria from the ILP outlined in Table 14.3 (which is
extracted from Figure 12 of ILP PLG04). Each environment (unique to each phase) is to be
assessed based on the below.
Table 14.3: Reference categories for positive and negative lighting effects (from Figure 12 from
ILP PLG04)
14.57 ILP PLG04 does not define the terms used in the above table. Therefore, terms such as significant,
substantial, minor etc. all remain subjective and open to interpretation. These terms do not
Nature Ref Level Description Remedial works
Positive 1 Major/
substantial
beneficial
effects
Significant improvement in
night environment and/ or
reductions in glare, spill
light and sky glow
2 Moderate
beneficial
effects
Noticeable improvement in
night environment and/ or
reductions in glare, spill
light and sky glow etc.
3 Minor beneficial
effects
Slight improvement in night
environment and/ or
reductions in glare, spill
light and sky glow
Neutral 4 None/
negligible
No significant effect or
overall effects balancing out
Negative 5 Minor adverse
effects
Slight increase in visibility of
site, glare, and sky glow etc.
Develop appropriate
levels and type of
mitigation 6 Moderate
adverse effects
Noticeable increase in
visibility of site, glare and
sky glow etc.
7 Major adverse
effects
Significant issues with
increase in visibility of site,
glare, and sky glow etc.
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 327
directly correspond to the EIA terms significant and non-significant. Each potential effect is
evaluated in its own right and given an EIA significance designation later in this chapter.
14.58 The effects observed in the following assessment are prior to mitigation and enhancement
measures being applied, and will pertain to those that are identified as negative effects as noted
in the table above. The embedded mitigation, such as the planted bund, has been included in the
assessment.
14.59 It should be reiterated that this provisional strategy has been modelled using standard fittings.
Where required, further mitigation measures or enhancements are to be applied at final design
stage as part of Reserved Matters applications. Possible mitigation and enhancement measures
are discussed later in this chapter.
On-site Survey Methodology
Study Area
14.60 The Study Area for the Site survey is defined as the Redline Boundary and immediate environs.
Time, date and weather
14.37 The baseline condition lighting assessment was carried out by HCA, on 26th July 2016,
commencing the study at 22:00. The weather, as described by the Met Office, was 17°C and
overcast with good visibility. The stars and the moon were not visible during the survey. The
weather started to deteriorate towards the end of the survey, as it started to precipitate.
14.38 The conditions defined above were adequate for the onsite survey to proceed.
Measuring methodology
14.39 The Site survey was carried out over the Development Footprint north of the A419, and the area
of the Redline Boundary south of the A419 and east of the M5. No baseline survey was
undertaken west of the M5. The survey was conducted in accordance with ILP PLG04.
Measurements were taken at key points (i.e. sensitive areas predominantly around the periphery
of the Site, see RS Figure 14.1). Horizontal readings were taken at a height of 1.5m. At each point,
in accordance with ILP PLG04, vertical measurements were also taken from each cardinal
direction, at the same height.
14.40 A fixed height monopole was used to ensure that readings were taken at consistent heights. The
measuring equipment (to the specification noted below), measures ‘live’ illuminance levels. The
equipment was left in place until a steady illuminance reading was observed on the output
screen.
Measuring equipment
14.41 An ISO-TECH ILM 1337 light meter was used at the locations noted in RS Figure 14.1 and Table
14.4. The light meter was previously calibrated in July 2016, just prior to the survey (see RS
Appendix 14.1 for calibration certificate).
Baseline Conditions
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 328
14.42 This section details the existing site conditions. The existing site comprises of agricultural land.
There are no existing artificial light sources within the Development Footprint, although there
are some external light sources which trespass (spill) into the Development Footprint.
14.43 In accordance with the ILP PLG04, a baseline condition assessment was carried out.
Sensitive receptors
14.44 Potential sensitive receptors have been defined as:
• The existing adjacent properties: There are existing properties running adjacent around
the periphery of the Redline Boundary. These areas will most likely be vulnerable to light
spill and light intrusion;
• Users of the M5 motorway: The M5 carriageway and adjoining junction 13 are unlit.
Although an average illumination spill from the carriage way (for users of the carriageway)
is low, the intrusive light from users of the carriage way was notable;
• Users of the A419: The A419 carriage way running adjacent to the Site is also unlit.
Observations were as identified for the M5 carriageway;
• IHCA: The IHCA extends and includes part of the Redline Boundary south of the A419,
although the Development Footprint is away from the IHCA and north of the intervening
A419. The IHC currently comprises of agricultural land and does not contain any artificial
light within the Redline Boundary;
• Local wildlife: Local wildlife has been identified in the area. This detailed further in RS
Chapter 8.
Table 14.4: Illumination levels observed at the locations identified on RS Figure 14.1
Position
number
Description Sensitive
receptor
Position Illuminance (lux)
Easting Northing Horizontal North East South West
1
North corner
area south of
A419
Dark
corridor 377868 206726 0.22 0.04 0.08 0.08 0.04
2
Middle of
north western
Redline
Boundary of
area south of
A419
Dark
corridor
377750 206626 0.10 0.06 0.06 0.06 0.02
3
Western
corner of area
south of A419
Dark
corridor 377700 206560 0.09 0.02 0.02 0.05 0.06
4
Middle of
southern
Redline
Boundary of
area south of
A419
Dark
corridor
377882 206402 0.08 0.02 0.03 0.03 0.04
5
Southern
corner of area
south of A419
Dark
corridor &
WMC
378027 206268 0.05 0.03 0.02 0.02 0.02
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 329
6
Corner of
existing
carpark
Dark
corridor &
WMC
378107 206354 0.08 0.05 0.01 0.02 0.04
7 Adjacent to
WMC
WMC &
residential
premises
378206 206293 0.06 0.04 0.06 0.05 0.05
8
Middle of
dwelling
boundary
Residential
premises 378225 206317 0.05 0.04 0.04 0.02 0.03
9
Eastern corner
of area south
of A419
Residential
premises 378261 206363 0.07 0.03 0.04 0.04 0.09
10
Southern
corner of area
north of A419
Dark
corridor 378298 206394 0.06 0.04 0.05 0.02 0.03
11
Corner
adjacent to
Westend
House
Dark
corridor &
residential
premises
378386 206711 0.06 0.03 0.04 0.03 0.02
12
Corner
adjacent to St.
Lay Cottage
Dark
corridor &
residential
premises
378290 206802 0.06 0.04 0.01 0.02 0.02
13
Reading
adjacent to
Mole cottage
Dark
corridor &
residential
premises
378220 206870 0.07 0.03 0.03 0.03 0.03
14
North western
boundary of
area north of
A419
Dark
corridor 378012 206979 0.10 0.03 0.04 0.05 0.06
Summary of results
14.45 The Site survey found that there was minimal light intrusion into the Redline Boundary area; light
intrusion originating from buildings and highways surrounding the Site. The recorded horizontal
illuminance levels (i.e. levels of light travelling vertically onto the horizontal plane) were relatively
consistent, with little variance, across the entire area. An average horizontal illuminance of 0.08
lux was observed. A relatively high level of light intensity originating from the WMC carpark was
also observed.
14.46 Similarly, the cardinal illumination measurements141 (light travelling horizontally north, east,
south and west onto the vertical planes) were also relatively consistent and low averaging less
than 0.5 lux; as detailed on Table 14.4. This indicates a low level of intrusive light into the Site.
Additional observations from Redline Boundary
14.47 As noted earlier in this chapter, the existing Redline Boundary does not contain any artificial light
sources. Light ingress on the Redline Boundary is via adjacent buildings, developments, carparks
and highways (in addition to natural light). Light ingress can be considered negligible.
141 The Cardinal illumination measurement is the measurement of illumination observed on the vertical plane due
north, east, south and west at the same point as the measurement of the horizontal plane; perpendicular to the
horizontal plane.
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 330
14.48 Dwellings adjacent to the Development Footprint also provide negligible light intrusion into the
Development Footprint. This is reinforced by readings 11, 12 and 13 detailed in the Table 14.4.
14.49 Although the light spill into the Redline Boundary is generally minimal, an unexpected level of
luminaire intensity was observed from the adjacent WMC car park.
14.50 No other significant light spill Into the Redline Boundary was observed. Intrusive light spill from
the Easting Trading Estate was anticipated directly south of the Redline Boundary. However
intrusive light was not discovered originating from this direction.
14.51 Other light spill into the Site was deemed insignificant and predominantly came from dwellings
with building mounted flood lights in various positions around the Redline Boundary.
14.52 Sky glow was experienced in all cardinal directions (sky glow being observed in the north, east,
south and westerly directions relative to the Site), and was found to be most intense towards
Stroud (east). This is believed to originate from Dairy Crest, and is illustrated in RS Figures 10.13,
as well as on the light pollution maps at RS Figure 10.10
Baseline summary
14.53 In summary, the existing Redline Boundary contains no artificial light sources and has a negligible
lighting effect on the surrounding area. Minimal light spill was observed into the Redline
Boundary, with the majority of spill into the Redline Boundary coming from WMC car park.
Intrusive light from the car park was also identified.
14.54 Sky glow was experienced in all directions, but predominantly in the direction of Stonehouse/
Stroud, Easington and Frampton.
Design Evolution
14.55 This section identifies the Revised Scheme and proposes a provisional lighting scheme. The
lighting scheme has been generated to achieve the levels set out in RS Figure 14.3.
Site Constraints to lighting
14.56 A number of constraints have been identified as considered in the design. Constraints are
detailed below.
Ecological Constraints
14.57 An Ecological assessment has been undertaken as part of this Revised Scheme (Chapter 8). A
number of potential ecological constraints have been identified and these have been considered
in the lighting design forming part of this assessment. In particular, this has focused on the need
for ‘bat corridors’ that follow the perimeter of the Development Footprint (RS Figure 1.1). Such
constraints are identified on the Ecological Designations (RS Figure 8.6).
Other Constraints
14.58 Further landscape site constraints are discussed in the LVIA chapter (Chapter 10). Other
constraints having an influence on the potential lighting scheme are summarised below:
• Buildings/ structures on the FGR site are restricted to a maximum height of 19.5m AFFL
(including luminaire columns etc.);
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 331
• Mitigation against light spill into adjacent dwellings, farms, streams etc.;
• Limiting the threshold increment to adjacent highways;
• Environmental conditions to comply with Table 14.2.
The Provisional Lighting Scheme
14.59 The provisional lighting scheme has been designed to eliminate potential significant
environmental lighting effects identified as part of this assessment through luminaire selection,
location and orientation. The lighting scheme should be considered as a ‘worst case’, to achieve
the requirements set out in the previously discussed guidance. This is due to lack of enhancement
measures implemented in the provisional design model.
14.60 As previously discussed, the scheme has been modelled in this way to demonstrated that a
considerate lighting scheme (generating minimal significant effects) is possible without the use
of mitigation measures. This lighting scheme has not been generated for construction and should
be considered as original investigation/ provisional design in accordance with ILP PLG04.
14.61 In reality, the final design, submitted with the Reserved Matters Application, will consider the
use of all the mitigation and enhancement methods as discussed later in this chapter. This will
reduce the residual effects created by the use of the standard fittings evaluated in this
assessment.
14.62 It should be reiterated that the whole site will be subject to final design to discharge Reserve
Matters Applications at a later date.
Methods of mitigation for the provisional design
14.63 The provisional design has considered the embedded mitigation only; the bund with planting.
Spilled light into dark corridors and nearby residential receptors is predominantly been avoided
by the use of the embedded mitigation (a bund with planting).
Revised Scheme and Horizontal lighting contours
14.64 The Revised Scheme is set out in RS Figure 1.1. It is this Revised Scheme which the lighting
strategy has been designed against. The development has been modelled across three design
drawings. The Development Footprint, A419 road only and both the road and Development
Footprint modelled together.
14.65 RS Figure 14.3 identifies the horizontal lighting contours for the Development Footprint. RS
Figure 14.4 identifies the horizontal lighting contours for the A419 road. RS Figure 14.5 identifies
the horizontal lighting contours of both the Development Footprint and the A419.
Development Footprint Site
14.66 The current architectural design for the stadium identifies a canopy and seating arrangement
that fully encloses the playing field. This surround acts as a screen and ensures that light does
not spill away from the field and into potentially sensitive areas. The canopy will not mitigate
against sky glow. Although the luminaires specified will not produce upward light, light is
reflected from the playing surface upward towards the sky. The sky glow generated by the
stadium is evaluated in more detail later in this chapter.
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 332
A419 Road
14.67 In consultation with the transport consultants, the dual carriageway has been designed to ensure
that the average illuminance levels and minimum uniformity levels have been achieved in
accordance with class CE2 as defined in the British Standards. Column heights are restricted as
stipulated with the Site constraints.
Summary of provisional design
14.68 Having identified the sensitive receptors as noted earlier in this chapter, the provisional lighting
design identified six potential negative effects across the Development Footprint:
• Spill light into bat corridors;
• Spill light into neighbouring properties;
• Light intrusion into neighbouring properties;
• Increase in luminance intensity to neighbouring properties (especially to sensitive
receptors);
• Intrusive threshold increment to adjacent highways;
• Increase in sky glow.
14.69 All potential effects are discussed below.
Potential effects
14.70 The potential effects observed in this section are prior to mitigation or enhancements being
applied.
14.71 It should be reiterated that this provisional strategy has been modelled using standard LED
fittings. Mitigation or enhancement measures are to be fully applied at final design stage prior
to a Reserved Matters Application, in accordance with ILP guidance. Possible measures of
mitigation/ enhancement are discussed later in this chapter.
Construction phase effects
14.72 As noted previously under the Methodology section, construction will predominantly be carried
out during daytime hours where natural light is available. Overnight lighting will likely be required
for security purposes only within the construction compound (likely to observe less than 5lux
around the periphery of the construction compound, see also RS Figure 5.4). The short-term
lighting effects are likely to be negligible, and therefore the construction phase can be assessed
as level 4 (none/ negligible) in accordance with ILP’s recommendations and therefore not EIA
significant. In view of this conclusion, for the purposes of this EIA, the potential effects have been
confined to, and evaluated based on, the final construction/ occupation of the entire site (i.e.
Operational effects only). Construction phase effects are not therefore considered further in this
chapter.
Operational (Post Construction) Phase
14.73 There are a number of potential residual effects as a consequence of this development. The
potential negative lighting effects have been identified upon review of the proposed lighting
scheme, and are as follows:
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 333
• Spill light into bat corridors;
• Spill light into neighbouring properties;
• Light intrusion into neighbouring properties;
• Increase in luminance intensity to neighbouring properties (especially to sensitive
receptors);
• Intrusive threshold increment to adjacent highways;
• Increase in sky glow.
14.74 Each environmental effect is to be assessed against Table 14.3, with the effects identified below.
Methods of mitigation and/ or enhancement are discussed later in this chapter.
Spilled Light
14.75 Dark Corridors: Spilled light into dark corridors has predominantly been avoided by the use of
the embedded mitigation (the bund with planting). The worst case of light spill has been
observed adjacent to the bus route as it leaves the Site via the northern access route.
14.76 Bat corridors are shown as observing less than 0.5lux. This complies with the guidance
documents previously identified and is therefore considered as a minor adverse effect in
accordance with Table 14.3; and not significant in EIA terms.
14.77 Roads: Minimal light spill from the road into the Development Footprint has been observed.
However, it is likely that no more than 5 lux will be observed in the borders/ hedges offering
segregation between the carriageway and the Site.
14.78 Neighbouring Properties: The worst case of spill light has been observed adjacent to the bus
route as it leaves the Site at Grove Lane.
Light intrusion into neighbouring properties and windows
14.79 Although the area adjacent to the northern site entrance (bus route) off Grove Lane will
experience the worst case of spill light as noted in the preceding section, Westend House will be
subject to the worst case of light intrusion into a neighbouring property, given its proximity to
site when compared other neighbouring properties.
14.80 Light intrusion is the light observed at ‘window height’ on the vertical plane (as defined in ILP
PLG04). This is modelled digitally by locating a vertical measuring plane in the position of the
windows subject to the light intrusion.
14.81 RS Figures 14.6 and 14.8 details the indicative light spill and intrusion before any mitigation or
enhancements have been considered, and confirms that less than 1lux is being observed prior to
applying any mitigation or enhancement measures. As detailed in Table 14.2, up to 1lux light
intrusion is permitted post curfew. Therefore, this level of light intrusion falls below the post-
curfew threshold in areas of Low District Brightness. This can be described as a minor adverse
effect in accordance with Table 14.3; and not significant in EIA terms.
Increase in luminous intensity on neighbouring properties
14.82 Section 2.7.5 of CIE150 notes that luminous intensities do not need to be calculated where
‘luminaires cannot be seen from directions of concern due to permanent physical obstructions
such as high opaque fence, retaining wall or evergreen trees with dense foliage.’
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 334
14.83 The receptor most sensitive to luminous intensity is Westend House adjacent to the main car
parking area of the Development Footprint. It is unlikely that luminaires will be seen from the
neighbouring property in question, due to the planted bund and other permanent physical
obstructions (see Chapter 10). The receptor is also unlikely to experience this effect due to the
position and orientation of the luminaires themselves. Therefore, a calculation is not required.
14.84 Due to the fact that the most sensitive receptor to light intrusion does not require a calculation,
the luminous intensity on neighbouring properties therefore can be considered as a negligible
effect in accordance with Table 14.3 and not significant in EIA terms.
Intrusive threshold increment to adjacent highways
14.85 The threshold increment is a measure of the loss of visibility that is caused by the glare from
obtrusive lighting installations on users of the adjacent highways (M5 and A419).
14.86 The majority of the Site will be enclosed by the planted bund to the detail identified in Chapter
10. There is also significant existing vegetation along the A419. Users of the adjacent highways
(M5 and A419) will not have direct line of sight on the luminaires due to the obstructions
mentioned above (see also RS Figure 10.14, Visualisations). Therefore, users of the adjacent
highways shall not perceive glare or intrusive light from Revised Scheme.
14.87 The effect associated with the threshold increment can therefore be considered as a negligible
effect in accordance with Table 14.3, and therefore not significant in EIA terms.
Increase in sky glow
14.88 The existing undeveloped Development Footprint does not contain any artificial light sources.
The future site will contain a large number of luminaires and this will have a negative effect on
sky glow.
14.89 The greatest contributor to sky glow will be the stadium flood lighting, although it should be
stressed that the stadium lighting will normally be switch off; unless a game is in progress in low
levels of ambient lighting.
14.90 The anticipated upward light ratio (ULR) for the stadium has been calculated at 14.6% (calculated
in accordance with section 5.5 of CIE 150). This is in excess of the recommendations set out in
ILP guidance (as noted in Table 14.2, where the maximum ULR in an area of Low District
Brightness is 2.5%). Furthermore, Table 14.2 notes that the calculated ULR for the FGR Stadium
would only be allowable in Zone E4 (high district brightness areas), where a maximum of 15%
ULR is acceptable. Due to the very intermittent nature of the ULR, the maximum allowable ULR
for sports pitches and stadiums are to be considered and agreed on a case by case basis with the
Local Planning Authority.
14.91 Given the non-compliance with the ILP guidance, sky glow should be considered as a major
adverse environmental effect in accordance with Table 14.3, and therefore significant in EIA
terms – albeit the actual occurrence of such an effect is infrequent. Mitigation measures, to
reduce the effect are discussed later in this chapter.
Summary Potential Effects on Sensitive Receptors.
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 335
14.92 The provisional design has identified above the following effects associated with each sensitive
receptor.
Table 14.5: Effects on sensitive receptors
Sensitive
receptor
Potential effects Description Significance of
effect in EIA
terms
Existing
adjacent
properties
Light Spill
Light intrusions
Light intensity
The embedded mitigation has reduced the
effect.
Not significant
Users of
adjacent
carriageways
(M5 and
A419)
Intrusive
threshold
increment
Users do not have direct line of sight of
lumianires and therefore cannot observe the
intrusive threshold increment.
Not significant
IHCA Light Spill
The IHCA is not within the vicinity of the
Development Footprint and will not observe
the potential effect identified.
Not significant
Local wildlife Light Spill Light spill is within the requirements set out by
the governing documents.
Not significant
All receptors Sky Glow It is likely that sky glow will be observed from
all receptors. Although very infrequent, the
Stadium sky glow ULR is calculated at 14.6%.
This is above the Obtrusive Light Limitations
for Exterior Lighting Installations specified for
areas of Low District Brightness of 2.5%.
Significant.
Summary of potential effects
14.93 Sky glow has been identified as a significant effect in EIA terms. Methods of mitigation are
discussed in more detail in the following section.
14.94 Light spill, light intrusion, threshold increment and illuminance intensity are considered as not
significant in EIA terms. Nevertheless, measures of enhancement should be considered in an
attempt to further minimise these effect as far as possible.
Mitigation and Enhancement
14.95 This section of the lighting chapter discusses potential mitigation and enhancement measures
that can be used to minimise the potential effects discussed above.
14.96 Any one of the methods below are considered an appropriate means of mitigation or
enhancement to reduce the effects discussed earlier in this chapter, and are in accordance with
the ILP guidance documents:
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 336
• Luminaire selection;
• Back shields/ louvers;
• Screened fences;
• Bunds;
• Limited operational hours.
14.97 The measures are described in more detail below.
Luminaire selection
14.98 Luminaires have been selected for compliance with the recommended guidance documents,
including the Bat Conservation Trust guidance documents; as detailed in RS Appendix 14.2.
14.99 Standard luminaires have somewhat rudimental optics. Modern LED luminaires, such as the
Thorn Area Flood LED Pro, are much more efficient in directing the output light towards the task
to further mitigate illuminance intensity. It is recommended that this class of luminaire is
specified when the final lighting strategy is being developed.
Back shield/ louvres
14.100 Back shields have been considered as an enhancement only and were not part of the tested
provisional lighting scheme in RS Figures 14.3 -14.5 as they are not embedded mitigation. This
has allowed the study to identify the areas subject to the worst possible lighting spill; utilising
the embedded mitigation only. Back shields and louvres are options that can be fitted to
luminaires to limit the direction of light and prevent it from intruding into adjacent receptors. RS
Appendix 14.2 details an example of a hooded luminaire accessory and louver accessory that can
be used to control the direction of light from the luminaires.
14.101 The use of back shields/ louvers will allow light to travel in the direction of the task area only.
This will drastically reduce the amount of light being spilled into sensitive areas, which has been
assessed as a minor negative effect.
14.102 RS Figure 14.7 considers the enhancement of a luminaire back shield, in addition to the
embedded mitigation already considered. The vertical measuring plane in this instance identifies
less than 0.5lux being observed as intrusive light (whereas prior to use of the back shield the
vertical measuring plane identified 1lux of intrusive light).
Screened fences
14.103 Screened fence lines can be created by utilising planted trees/ bushes or by the installation of a
prefabricated fence. The planting of trees/ bushes will clearly have a lesser environmental effect
than a prefabricated alternative.
Building of bunds
14.104 A 2m high earth bund will be constructed around the Site as detailed on the RS Figure 1.1 and
detailed in the landscape Chapter 10. In addition to the bund; bushes, shrubs and trees will be
planted on and around the bund in an attempt to create a natural screen with the intention of
reducing the effects of protruding light and noise. This is also detailed in Chapter 10.
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 337
14.105 The bund has been designed so that the top and the bank facing towards the Site are to observe
a degree of light spill. This is an attempt to obstruct light ingress into neighbouring land and dark
corridors (where the dark corridor is assumed to be the bund bank corridor facing away from the
Site). Therefore, the bund bank facing away from the Site is restricted to the illuminance levels
stipulated in the guidance documents (for dark corridors). The dark corridor should achieve an
increase of illuminance as a result of the Revised Scheme of less than 0.5lux, in accordance with
Bat Conservation Trust guidance documents.
Limiting hours of operation/ enhancing lighting control
14.106 Limiting the hours of operation of the external lights is a more controlled way to limit the
negative effects of the new lighting scheme. The lighting models/ drawings considered in this
lighting assessment/ scheme are static and do not consider the dynamic operation of the Site. In
reality, the control methods should be adopted as part of the future strategy and secured by
condition, as appropriate.
14.107 Further controls may include limiting the hours of operation, the use of dimmable lights, active
control based on movement etc. The practicality of using such control should be evaluated in
more detail at design/ Reserved Matters stage.
14.108 It is assumed that a site manager/ facilities manager will have overriding control over the lighting
on the Site; and that all luminaires will be deactivated when the Site is not in use. It is likely that
areas of the Site will contain security barriers to prevent access to car parks, training pitches etc.
It is also envisaged that the facilities manager will be responsible for deactivating private lighting
when the Site is not in use.
14.109 The task zones identified in RS Figure 14.3 are to have the following modes of operation:
Cark park areas
14.110 Private car parks are to be operational via a photocell and time clock arrangement. The car park
lighting will switch on upon call from the photocell and will switch off at a limiting time dictated
by the Site curfew. The facilities manager will be able to override the operation of the lights
should the car park not be in use prior to the curfew.
14.111 Car park areas will have barriers preventing the public from using all car parks unless made
accessible by the facilities manager. Lighting circuits shall be interlocked to the entrance barrier
whereby the lighting will remain switched off until the barrier is opened. Once opened, the car
park lighting will operate in the same way as other public car parks (i.e. upon activation of the
photocell). On closure of the barrier, the lighting will switch off.
Roads
14.112 Street lighting for the roads will likely be required to be switched on only when the Site is in use
by FGR, or on match days. The facilities manager will have overriding control over the road
lighting and will switch off the lights when the Site is no longer in use.
Footpaths
14.113 Footpaths are generally used in private areas. These areas shall have a similar control strategy as
the roads.
A419 Dual carriageway and Junction 13
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 338
14.114 The A419 carriageway shall be modified so that it is dualled. This road will require illuminating
through the entire duration of the night. Luminaires to the carriageway will switch on at dusk by
call from the photocell, and will switch off at dawn again by call from the photocell.
Principal club (mid-level competition) stadium
14.115 The stadium pitch lighting will normally be off. This will only be switched on in low ambient
lighting conditions during matches and any other agreed exceptional circumstance. Luminaires
will be manually controlled to ensure that lighting is not switched on unnecessarily or switched
off whilst a match is in progress. This will be controlled by the facilities manager. The curfew will
be as described earlier and will be manually enforced.
14.116 Further controls could be considered to ensure that the stadium lighting is deactivated when not
in use. Such controls may include an alarm (whether that be email, text etc.) alerting the facilities
manager when the stadium lighting is active after the curfew time.
Residual effects
14.117 This section identifies the residual effects after enhancement methods have been applied.
Residual effects of spill into dark corridors
14.118 Although not identified as a significant effect, the worst case of spill into a dark corridor has been
investigated further as described above and detailed in RS Figure 14.6 and 14.7. The
enhancement measure considered in RS Figure 14.7 considers the use of back shields/ louvers,
as well as the embedded mitigation of the planted bund.
14.119 RS Figure 14.7 shows that with embedded mitigation (the planted bund) and enhancement
(luminaire back shields) in place, a residual spill level of less than 0.5lux is observed.
Residual effects of sky glow
14.120 Sky glow is considered as a potential significant effect in EIA terms. The anticipated upward light
ratio (ULR) for the stadium has been calculated at 14.6% (calculated in accordance with section
5.5 of CIE 150). This is in excess of the recommendations set out in ILP guidance (as noted in
Table 14.2, where the maximum ULR in an area of Low District Brightness is 2.5%). Due to the
very intermittent nature of the ULR, the maximum allowable ULR for sports pitches and stadiums
are to be considered and agreed on a case by case basis with the Local Planning Authority.
14.121 The principal method of mitigation against ULR/ sky glow is to limit the hours of operation of
these facilities. The stadium lighting will normally be off, and therefore falls in line with the
requirements of Table 14.2. Stadium lighting will be activated when a match is being played in
low levels of ambient light. This is typically due to weeknight matches or tournament matches.
When these matches are not in progress, the stadium lighting will be switched off.
14.122 By way of comparison with the current season, a total of thirty home matches are currently (as
at the end of November) programmed during the 2017 – 2018 season. These include 22 on a
Saturday, two on Bank Holidays, and six on a normal weekday evening.
Summary of enhancement/ mitigation measures and residual effects
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 339
14.123 All mitigation methods recommended by the ILP have been considered and utilised to some
extent in this scheme; whether considered as embedded mitigation or enhancement.
14.124 The Site will benefit from embedded mitigation by way of a planted bund.
14.125 The hours of operation across the Site will be limited by the curfew time defined earlier in this
chapter. Artificial light sources causing the more onerous adverse effects will be subject to more
stringent hours of operation as discussed above.
14.126 Sky glow has been identified as the only significant effect, in EIA terms. This is mitigated in part
by limiting the use of the stadium. Lighting of this will normally be switch off. When switched on,
the ULR will likely be above the recommendation of the ILP, although this will be verified upon
final design. The maximum allowable (intermittent) ULR should be discussed and agreed with the
Local Planning Authority.
Cumulative Effects
14.127 Cumulative developments considered as part of this assessment are illustrated on Figure 18.1
and detailed in Table 2.5.
14.128 Due to an assumed lighting design shown with no upward light and sharp cut-off characteristics
to minimise light spill beyond the Redline boundary, no significant cumulative effects are
anticipated. It is anticipated that the other developments (if granted planning permission) in
Table 2.5 would have similar lighting mitigation and enhancement measures secured both by
design and suitably worded planning conditions, therefore minimising their own potential
lighting effects.
Conclusions
14.129 The existing Redline Boundary contains no artificial light sources and has a negligible lighting
effect on the surrounding area. Some light is spilling into the Redline Boundary area from
adjacent properties, with the majority of spill into the Redline Boundary coming from WMC car
park.
14.130 The Revised Scheme will introduce light and this will have an overall negative lighting effect on
the currently unlit environment (when all luminaires are switched on). Potential effects due to
lighting have been identified as:
• Spill light into dark corridors;
• Spill light into neighbouring properties;
• Increase in luminance intensity to neighbouring properties (especially to sensitive
receptors);
• Intrusive threshold increment to adjacent highways;
• Increase in sky glow.
14.131 Spilled light into dark corridors has been identified as a minor adverse effect and therefore not
significant in EIA terms. Enhancement by utilising back shields on lighting will further reduce any
effects. Such measures of enhancement will be modelled as part of the final design.
14.132 Spilled light into neighbouring properties has been identified as negligible and therefore not
significant in EIA terms. Although some light spilled into such areas, levels are below the
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 340
maximum levels recommended by the ILP as identified in Table 14.2. Performance against this
table will be enhanced further by utilising additional enhancement methods.
14.133 Increase in luminance intensity to neighbouring properties has been identified as negligible and
therefore not significant in EIA terms. Neighbouring properties will not be subject to a direct line
of sight of the luminaires.
14.134 Intrusive threshold increment to adjacent highways have been identified as negligible, and
therefore not significant in EIA terms, as road users will not have a direct line of sight of the
luminaires.
14.135 Increase to sky glow has been identified as a significant effect in EIA terms. This is mitigated in
part by limiting the hours of operation of the stadium. The acceptable intermittent ULR should
be agreed with the local planning authority. It should be reiterated that the stadium lighting will
only be switched on whilst a game is in progress in low levels of ambient light.
14.136 It may be possible to eradicate the light spill into dark corridors by way of utilising back shields.
This should be considered further upon final design of the lighting scheme, in accordance with
ILP guidance.
14.137 Sky glow poses the only significant environmental lighting effect on the local area. Sky glow is
predominantly controlled by limiting the hours of operation, which can be agreed with the local
planning authority. It is also suggested that the ULR is again reviewed upon issue of the final
design.
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 341
Table 14.6: Summary of Lighting Effects and Mitigation
Receptor Effect
Phase
(Construction
/ Operation)
Embedded
Mitigation
Sensitivity of
Receptor
Magnitude
of Change
Level of Effect
and
Significance
Prior to
Mitigation
Mitigation Enhancement Level of Effect
(and
Significance)
after
Mitigation
Nature of
effect (short
term /
medium term
/ long term,
permanent /
temporary,
direct /
indirect)
Existing
adjacent
properties
Light spill Operation Planted bund Not significant Embedded
mitigation
Back shields Not significant n/a
Existing
adjacent
properties
Light
intrusion
Operation Planted bund Not significant Embedded
mitigation
n/a Not significant n/a
Existing
adjacent
properties
Light
intensity
Operation Planted bund Not significant Embedded
mitigation
n/a Not significant n/a
XXXVIII. Users of
adjacent
highways
Intrusive
threshold
increment
Operation Planted bund Not significant Embedded
mitigation
n/a Not significant n/a
IHCA Light spill Operation Planted bund Not significant Embedded
mitigation
Back shields Not significant n/a
Local wildlife Light spill Operation Planted bund Not significant Embedded
mitigation
Back shields Not significant n/a
All receptors Sky glow Operation Planted bund Significant Limiting hours
of operation
n/a Significant Long term,
but very
infrequent in
occurrence
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 342
15 NOISE AND VIBRATION
Summary
15.1 The noise and vibration assessment considers noise and vibration generated during the
construction of the Revised Scheme and noise during its operation. Operational noise has been
calculated for five scenarios that would occur in isolation of each other; namely: crowd noise
during a football match, noise from the use of the training pitches, noise from any fixed plant
associated with the stadium, vehicular noise from the use of the car park and the change in road
traffic noise from vehicles using the existing highway network.
15.2 The assessment has been based on worst case assumptions that will result in noise levels at the
higher end of the range anticipated. The maximum noise level events from the stadium are most
likely to occur when goals are scored during matches. However, the duration and frequency of
these events is very limited – during 2017 there will have been an average of three home games
per month and three goals per game.
15.3 The noise level impacts have been calculated and assessed at five of the nearest noise-sensitive
receptors to the Revised Scheme, including William Morris College (WMC) and associated
Chipmans Platt. WMC is a specialist facility offering work-related learning and independence for
young people with autistic spectrum and learning difficulties. It is recognised that sudden noise
events of sufficient amplitude and character has the potential to disturb some people with
autism. Therefore, this assessment has included additional criteria that accounts for the
potential different magnitude of noise that can affect some people with autism.
15.4 Baseline noise data gathered for the 2016 application has been supplemented with a further
survey comprising two locations between Wednesday 28th June and Tuesday 4th July 2017.
Introduction
15.5 This chapter presents the findings of an assessment of the potential effects of noise and vibration
at existing and future receptors surrounding the Revised Scheme. The assessment follows
nationally and locally recognised policies, standards and guidelines to determine the potential
significance of any effects during the construction and operational phases of the proposals, and
the suitability of the site for the proposed stadium and supporting facilities.
Legislation, Policy and Guidance
Legislation
Control of Pollution Act 1974142
15.6 Section 60 of this Act relates to the ‘Control of Noise on Construction Sites’ and Section 61 relates
to ‘Prior Consent for Work on Construction Sites’. These sections include the serving of notices
and the formation of agreements specifying acceptable levels of noise, hours of operation,
working methods and use of specific plant and noise mitigation.
Policy
142 Statutory Instruments, (1974) ‘Control of Pollution Act’, SI
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 343
Noise Policy Statement for England143
15.7 Noise Policy Statement for England (NPSE) advises that noise impacts should be assessed on the
basis of adverse and significant adverse effect but does not provide any specific guidance on
assessment methods or noise limits.
15.8 The NPSE introduces the concepts summarised in Table 115.1 that can be applied when
considering the significance of noise impacts, which are applied by the World Health
Organization.
Table 15.1: Observed Effect Levels
Effect Level Activities
No Observed Effect Level
(NOEL)
This is the noise level below which no effect can be detected. In simple
terms, below this level of noise, there is no detectable effect on health
and quality of life due to the noise being assessed.
Lowest Observed Adverse
Effect Level (LOAEL)
This is the level of noise above which adverse effects on health and
quality of life can be detected.
Significant Observed Adverse
Effect Level (SOAEL)
This is the level of noise above which significant adverse effects on
health and quality of life occur.
15.9 The document advises that it is not possible to have 'a single objective noise based measure…
that is applicable to all sources of noise in all situations'. It further advises that the sound level at
which an adverse effect occurs is likely to be different for different noise sources, for different
receptors at different times.
National Planning Policy Framework144
15.10 National Planning Policy Framework (NPPF) sets out the Government's planning policies and how
these are expected to be applied. In relation to noise and vibration, NPPF section 11 Paragraph
109 states:
‘The planning system should contribute to and enhance the natural and local environment
by:
• preventing both new and existing development from contributing to or being put at
unacceptable risk from, or being adversely affected by unacceptable levels of soil,
air, water or noise pollution or land instability’
15.11 Whilst Paragraph 123 states:
‘Planning policies and decisions should aim to:
• avoid noise from giving rise to significant adverse impacts on health and quality of
life as a result of new development;
• mitigate and reduce to a minimum other adverse impacts on health and quality of
life arising from noise from new development, including through the use of
conditions;
• recognise that development will often create some noise and existing businesses
wanting to develop in continuance of their business should not have unreasonable
143 Noise and Nuisance Team DEFRA, (2010) ‘Noise Policy Statement for England’, DEFRA 144 Department for Communities and Local Government, (2012) ‘National Planning Policy Framework’, DCLG
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 344
restrictions put upon them because of changes in nearby land uses since they were
established; and
• identify and protect areas of tranquillity which have remained relatively undisturbed
by noise and are prized for their recreational and amenity value for this reason.’
Planning Practice Guidance145
15.12 Online Planning Practice Guidance (PPG) has been published to provide greater details in relation
to the relevance of noise to the planning process following the introduction of the NPPF and
NPSE.
15.13 This guidance states, under the heading 'How to Determine the Noise Impact', that the following
should be considered by local authorities:
• whether or not a significant adverse effect is occurring or likely to occur;
• whether or not an adverse effect is occurring or likely to occur; and
• whether or not a good standard of amenity can be achieved.
15.14 In line with NPSE, this includes identifying where noise exposure is above or below the significant
observed adverse effect level and the lowest observed adverse effect level for a given situation,
during both construction and operation of the Revised Scheme.
15.15 Further guidance on each of the various observed effect levels set out in the NPSE is provided in
the table detailed in the section headed 'How to Recognise when Noise could be a concern?’
which is reproduced below.
Table 15.2: Observed Effects
Perception Examples of outcomes Increasing effect
level
Action
Not
noticeable
No effect No Observed
Effect
No specific
measures
required
Noticeable
and not
Intrusive
Noise can be heard, but does not cause any change
in behaviour or attitude. Can slightly affect the
acoustic character of the area but not such that
there is a perceived change in the quality of life.
No specific
measures
required
Lowest Observed Adverse Effect Level
Noticeable
and
Intrusive
Noise can be heard and causes small changes in
behaviour and/or attitude, e.g. turning up volume
of television; speaking more loudly; closing
windows for some of the time because of the noise.
Potential for non-awakening sleep disturbance.
Affects the acoustic character of the area such that
there is a perceived change in the quality of life.
Observed Adverse
Effect
Mitigate and
reduce to a
minimum
Noticeable
and
disruptive
The noise causes a material change in behaviour
and/or attitude, e.g. having to keep windows
closed most of the time, avoiding certain activities
during periods of intrusion. Potential for sleep
disturbance resulting in difficulty in getting to
Significant
Observed Adverse
Effect
Avoid
145 Department for Communities and Local Government, (2014) ‘Planning Practice Guidance, Noise’, DCLG (web
based guidance, update date 24/12/2014)
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 345
Perception Examples of outcomes Increasing effect
level
Action
sleep, premature awakening and difficulty in
getting back to sleep. Quality of life diminished due
to change in acoustic character of the area.
Noticeable
and
disruptive
Extensive and regular changes in behaviour and/or
inability to mitigate effect of noise leading to
psychological stress or physiological effects, e.g.
regular sleep deprivation/awakening; loss of
appetite, significant, medically definable harm, e.g.
auditory and non-auditory.
Unacceptable
Adverse Effect
Prevent
15.16 It is important to note that no specific noise parameters are defined in the text or target noise
levels provided.
15.17 Under the heading 'What factors influence whether noise could be a Concern?’, the subjective
nature of noise is discussed. It is stated that there is no simple relationship between noise levels
and the impact on those affected. This depends on how various factors combine in particular
situations, these include:
• the source and absolute level of the noise together with the time of day it occurs.
Some types and level of noise will cause a greater adverse effect at night than if
they occurred during the day - this is because people tend to be more sensitive to
noise at night as they are trying to sleep. The adverse effect can also be greater
simply because there is less background noise at night;
• for non-continuous sources of noise, the number of noise events, and the frequency
and pattern of occurrence of the noise;
• the spectral content of the noise (i.e. whether or not the noise contained particular
high or low frequency content) and the general character of the noise (i.e. whether
or not the noise contains particular tonal characteristics or other particular
features). The local topology and topography should also be taken into account
along with the existing and, where appropriate, the planned character of the area.
15.18 More specific factors to consider when relevant:
• Consideration should also be given to whether adverse internal effects can be
completely removed by closing windows and, in the case of new residential
development, if the proposed mitigation relies on windows being kept closed most
of the time. In both cases a suitable alternative means of ventilation can be found in
the Building Regulations.
• In cases where existing noise sensitive locations already experience high noise
levels, a development that is expected to cause even a small increase in noise may
result in a significant adverse effect occurring even though little to no change in
behaviour would be likely to occur.
• If external amenity spaces are an intrinsic part of the overall design, the acoustic
environment of those spaces should be considered so that they can be enjoyed as
intended.
• Some commercial developments including fast food restaurants, night clubs and
public houses can have particular impacts, not least because activities are often at
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 346
their peak in the evening and late at night. Local planning authorities will wish to
bear in mind not only the noise that is generated within the premises but also the
noise that may be made by customers in the vicinity.
Stroud District Council Local Plan (Policy ES3)146
15.19 Policy ES3 of the Stroud District Council Local Plan details the requirements to maintain the
quality of life within environmental limits. Permission will not be granted to any development
which would be likely to lead to, or result in, an unacceptable level of:
• Noise, general disturbance, smell, fumes, loss of daylight or sunlight, loss of privacy
or an overbearing effect;
• Noise sensitive development in locations where it would be subject to unacceptable
noise levels;
15.20 These core policies are also included within CP14 of the same Local Plan, which specifies the
requirements of every building and development project in Stroud in order to achieve the highest
quality with regards to construction and design.
Guidance
Professional Practice Guidance on Planning and Noise ProPG147 2017
15.21 ProPG Planning & Noise is a recently published document aimed at providing practitioners
guidance on a recommended approach to the management of noise in the context of the
planning system. The document was published jointly by the three professional bodies in the
acoustics industry: Acoustics and Noise Consultants (ANC); the Institute of Acoustics (IOA); and
the Chartered Institute of Environmental Health (CIEH).
15.22 Whilst the guide is focussed on new residential development being affected by transport noise,
the principle of the guidance is considered helpful to this assessment. Its primary goal is to assist
in the delivery of sustainable development by promoting good health and wellbeing through the
effective management of noise. It seeks to do this by encouraging good acoustic design processes
in and around proposed new residential development, having particular regard to national policy
on planning and noise.
15.23 ProPG highlights the importance of considering noise as an early part of development design,
with the aim to avoid mitigation that appears to be a last resort and could have consequential
non-acoustic effects.
British Standard (BS) 5228:2009+A1:2014
15.24 British Standard 5228-1:2009+A1:2014148 'Code of practice for noise and vibration control on
construction and open sites - Part 1: noise' (BS 5228-1) provides guidance on a range of
considerations relating to construction noise including the legislative framework, general control
measures, example methods for estimating construction noise levels and example criteria which
may be considered when assessing the significance of any impacts.
146 Stroud District Council, (2015), ‘Stroud District Local Plan’, SDC. 147 ANC, IOA, CIEH, (2017), ‘ProPG: Planning & Noise’, ANC, IOA, CIEH. 148 British Standards Institution, (2014) ‘BS 5228-1:2009+A1:2014 Code of practice for noise and vibration control on
construction and open sites - Part 1: Noise’, BSI Standards.
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 347
15.25 Similarly, BS 5228- 2:2009+A1:2014149 'Code of practice for noise and vibration control on
construction and open sites - Part 2: vibration' (BS 5228-2) provides general guidance on
legislation, prediction, control and assessment criteria for construction vibration. These
standards have been adopted as the relevant method to predict and assess the impacts of
construction noise and vibration.
British Standard (BS) 4142:2014150
15.26 Current Government advice to Local Planning Authorities in both England and Wales makes
reference to BS 4142 as being the appropriate guidance for assessing commercial operations and
fixed building services plant noise. This British Standard provides an objective method for rating
the likelihood of complaint from industrial and commercial operations. It also describes means
of determining noise levels from fixed plant installations and determining the background noise
levels that prevail on a site.
15.27 The assessment of impacts is based on the subtraction of the measured background noise level
from the rating level determined. The rating level is the source noise level (either measured or
predicted) corrected for tone or character (if necessary). The difference is compared to the
following criteria to evaluate the impact:
• a difference of around +10 dB or more is likely to be an indication of a significant
adverse impact, depending on the context;
• a difference of around +5 dB indicates is likely to be an indication of an adverse
impact, depending on the context; and
• where the rating level does not exceed the background noise level, this is an
indication of the specific sound source having a low impact, depending on the
context.
15.28 This method is only applicable for external noise levels.
BS 8233: Sound Insulation and Noise Reduction for Buildings151
15.29 BS 8233:2014 ‘Guidance on sound insulation and noise reduction for buildings’ (BS 8233) is
intended to be used routinely where noise sources are brought to existing noise-sensitive
buildings, such as housing. However, the scope of the document states it ‘does not provide
guidance on assessing the effects of changes in the external noise levels to occupants of an
existing building’. The proposed guidance criteria are to satisfy most people. It is also stated that
‘it is necessary to remember that people vary widely in their sensitivity to noise, and the levels
suggested might need to be adjusted to suit local circumstances.’
15.30 BS 8233 provides guidance for control of noise in and around buildings, and suggests appropriate
criteria and limits for different situations. BS 8233 provides desirable internal ambient noise
levels for spaces in residential dwellings and non-domestic buildings when they are unoccupied.
The main guidance criteria are reproduced below in Table 1.3.
Table 15.3: Indoor Ambient Noise Levels in Spaces for Dwellings
149 British Standards Institution, (2014) ‘BS 5228-2:2009+A1:2014 Code of practice for noise and vibration control on
construction and open sites - Part 2: Vibration’, BSI Standards. 150 British Standards Institution, (2014), ‘BS 4142 - Method for rating and assessing industrial and commercial sound’,
BSI Standards. 151 British Standards Institution, (2014) ‘BS 8233 - Guidance on Sound Insulation and Noise Reduction for Buildings’,
BSI Standards.
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 348
Activity Location Daytime
(0700 to 2300)
Night-time
(2300 to 0700)
Resting Living room 35 dB LAeq, 16 hr -
Dining Dining room / area 40 dB LAeq, 16 hr -
Sleeping (daytime resting) Bedroom 35 dB LAeq, 16 hr 30 dB LAeq, 8 hr
Listening Meditation / relaxation area 30 – 35 dB LAeq, T -
15.31 Supplementary Note 2 and 4 to Table 4 within BS 8233 are copied below for reference:
NOTE 2 - The levels shown in Table 4 are based on the existing guidelines issued by the
World Health Organization…
NOTE 4 - Regular individual noise events (for example, scheduled aircraft or passing
trains) can cause sleep disturbance. A guideline value may be set in terms of SEL or
LAmax, F depending on the character and number of events per night.’
15.32 No guidance is provided in terms of daytime maximum event noise levels. At night maximum
event noise levels are advised to be considered but no actual adverse effect level is provided.
15.33 BS 8233 provides recommendations for external noise levels. It recommends that for external
areas that are used for amenity space, such as gardens and patios, it is desirable that the external
noise levels do not exceed 50 dB LAeq,T, with the upper guideline value of 55 dB LAeq,T which would
be acceptable in noisier environments.
15.34 Guidance is also provided in terms of steady ambient noise levels in occupied rooms of non-
domestic buildings where speech communication is important. The noise levels advised in Table
15.4.4 are the internal steady state ambient noise levels that permits ‘normal voice’ or ‘raised
voice’ to be reliably audible at a certain distance between the speaker and the listener.
Table 15.4: Reliable speech communication levels
Distance between speaker and
listener, m
Normal voice noise level, dB(A) Raised voice noise level, dB(A)
1 57 62
2 51 56
4 45 50
8 39 44
World Health Organization Guidelines (2000 and 2009)
15.35 The World Health Organization (WHO) has published a series of guidelines that relate to
acceptable levels of noise from a health perspective. These are detailed in two separate
documents, the WHO ‘Guidelines for Community Noise’152, 2000 and the WHO ‘Night Noise
Guidelines for Europe’153, 2009. The Guidelines for Community Noise set out the following
criteria in Table 15. that relate to noise levels experienced in outdoor living areas (e.g. gardens).
Table 15.5: Guideline values for noise levels in outdoor areas during the day
152 World Health Organization, (2000) ‘Guidelines for Community Noise’, WHO. 153 World Health Organization, (2009) ‘Night Noise Guidelines for Europe’, WHO.
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 349
Specific
Environment
Health Effect Guideline Values
dB LAeq, 16 hr
Outdoor
living area
Serious annoyance, daytime and evening 55
Moderate annoyance, daytime and evening 50
15.36 The WHO ‘Night Noise Guidelines for Europe’ provide further criteria that relate external noise
levels at dwellings to specific health impacts during the night-time (2300 hours to 0700 hours).
The Revised Scheme will not be operational during the night-time, therefore, this guidance is not
considered to be relevant to this assessment.
Building Bulletin 93154
15.37 BB93 has been compiled by various acoustic education experts and is based on the available
research (prior to publication) regarding all aspects of inclusion of pupils in mainstream
education.
15.38 Section 0.4 of BB93 defines the term ‘children having special hearing or communication needs’
as encompassing but not limited to the following:
• children with permanent hearing impairment
• speech, language and communication difficulties
• visual impairments
• fluctuating hearing impairments caused by conductive hearing loss
• attention deficit hyperactivity disorders (ADHD)
• an auditory processing disorder or difficulty
• being on the autistic spectrum
15.39 Section 0.4.1 of BB93 refers to ‘special school accommodation and special units attached to
mainstream schools’ and provides guidance on the required acoustic conditions being dependent
‘on a pupil’s individual special needs and may be accommodated by a specialist provision (e.g. a
quiet room for private study and communication, or an assisted listening device for participation
in general teaching), or by improving the general acoustic conditions of teaching and learning
spaces.’ The acoustic criteria for these types of accommodation should be specifically signed off
as they may vary from the starting point guidance criteria which may not be suitable for the
particular needs of the children in some types of accommodation.
15.40 The guidance design criteria for external noise intrusion contained in BB93 are listed in Table 15..
Table 15.6: External noise intrusion school design criteria for autistic spectrum teaching and
learning
Type of space Upper limit for new
build
Upper limit for
refurbishment
Allowance if naturally
ventilated
Classroom 30 dB LAeq, 30 min 35 dB LAeq, 30 min +5 dB
SEN* Calming 35 dB LAeq, 30 min 35 dB LAeq, 30 min +5 dB
*Note SEN stands for pupils with Special Educational Needs
15.41 BB93 also states ‘In order to protect students from regular discrete noise events, e.g., aircraft or
trains, indoor ambient noise levels should not exceed 60 dB LA1,30mins’. This is an important design
154 Building Bulletin 93, (2015) ‘Acoustic Design of Schools: Performance Standards’, DfES
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 350
criterion to be considered in conjunction with the Table 15. levels for general ambient noise. It
can’t be directly compared to LAFmax,T dB values, although, an LAFmax,T dB value will always be
greater than the LA1,T dB value for the time period ‘T’.
Acoustics of Schools155
15.42 Acoustics of Schools is a design guide providing further details of methods of achieving the BB93
design criteria for new built education developments. It has been produced by acoustic experts
in the UK and Chapter 6 of the document provides additional considerations for ‘children having
special hearing or communication needs’.
15.43 Pertinent guidance statements included in Acoustics of Schools are:
‘Noise not only masks the speech signal, making it difficult to understand what is being
said, but also leaves a pupil tired from the effort required to listen. It is therefore essential
that attention be given to creating a quiet classroom. This requires insulation against noise
from outside the school, sound insulation between rooms, control of noise from plant and
equipment inside the classroom, and control of reverberant noise within the room. These
will help to ensure that a good signal to noise level can be achieved. Typically a signal to
noise level of at least +20 dB is considered desirable.’
‘Effective acoustic absorption within the teaching space is required which will lead to short
reverberation times, particularly at low frequencies. This is essential to ensure that
reverberant sound does not build up when pupils are working in groups, or more than one
person is talking at any one time.’
15.44 A summary comparison of the guidance from the British Association of Teachers of the Deaf
(BATHOD) and American Speech- Language Hearing Association (ASHA) is presented in Acoustics
of Schools and shown in Table 15.7.
Table 15.7: Comparison of BATHOD and ASHA guidance for acoustic conditions in classrooms
Acoustic parameter British Association of Teachers
of the Deaf
American Speech- Language
Hearing Association
Unoccupied sound level ≤ 35 dBA ≤ 35 dBA
Reverberation time
(unoccupied)
≤ 0.4 s across frequencies 125 Hz
to 4000 Hz
≤ 0.6 s for smaller rooms
(< 10,000 ft3)
≤ 0.7 s for larger rooms (≥ 10,000
and ≤ 20,000 ft3)
Signal to noise ratio > 20 dB across the frequency
range 125 Hz to 750 Hz
> 15 dB across the frequency
range 750 Hz to 4000 Hz
≥ 15 dB
Research papers relating noise affecting persons with autism
15.45 Two research papers, both prepared in the United States of America (USA), which bear some
relevance to the potential behavioural aspects of persons with autism that can be attributed to
noise influences, have been reviewed.
Exploratory Survey
155 IOA, ANC, (2015) ‘Acoustics of Schools: a design guide’, IOA, ANC.
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 351
15.46 A paper titled ‘Noise and autism spectrum disorder in children: An exploratory survey’156 was
published in February 2017. The aim of the study was to explore ‘existing empirical research on
the impact of noise on children with ASD’ and to provide ‘recommendations regarding design
features that can contribute to noise reduction’ in schools. (Note ASD stands for Autism Spectrum
Disorder).
15.47 Pertinent findings included in ‘Noise and autism spectrum disorder in children: An exploratory
survey’ are:
‘Children with autism may demonstrate unique sensory profiles that influence the way they
perceive and process different stimuli in the environment. However, few researchers have
carefully examined the specific ways in which the acoustic environment of a facility may be
modified to accommodate such unique sensory needs.’
‘By modifying the built environment in acoustically friendly ways, the treatment and
education of children with autism may be greatly enhanced.’
‘There remains a significant knowledge gap in the current scientific literature as to how to
build acoustically friendly environments for children with ASD. Specifically, the authors
advocate for a controlled investigation of the behaviours of children with autism that
might be specifically correlated with certain acoustical environments. Common behaviours
reported by various caregivers related to noise in the environment have included fear
responses such as covering ears, distractibility, and self-stimulatory behaviours., By
understanding how behaviours are affected by environmental features such as carpet,
walls, ceilings, furniture, and other stimuli, we can begin to create more therapeutic and
academically compatible settings for children with autism in the school environment.’
15.48 The survey concludes that the classroom design and room acoustics potentially play a significant
role as well as control of external noise intrusion.
Observational Study
15.49 A paper titled ‘An Observational Study of Classroom Acoustical Design and Repetitive Behaviours
in Children With Autism’157 was published in 2016. The objective of the study was to ‘explore the
impact of acoustical design on children with autism in school classrooms’ and ‘Specifically, the
connection between repetitive behaviours and ambient noise levels in school classroom
environments was observed in four classrooms’.
15.50 The observational survey undertaken analysed different behaviours associated with noise
exposure in individuals with autism in three types of “classrooms”; the quiet or normal (41 to 55
dB LAeq,T range inside a classroom); the loud (55 to 70 dB) and; the potentially damaging (>70 dB).
15.51 Pertinent findings included in ‘An Observational Study of Classroom Acoustical Design and
Repetitive Behaviours in Children With Autism’ are:
156 Shireen M. Kanakri, Mardelle Shepley, James W. Varni, Louis G. Tassinary (2017), ‘Noise and autism spectrum
disorder in children: An exploratory survey’, Research in Developmental Disabilities 63 (2017) 85-94 157 Shireen M. Kanakri, Mardelle Shepley, Louis G. Tassinary, James W. Varni, Haitham M. Fawaz (2016), ‘An
Observational Study of Classroom Acoustical Design and Repetitive Behaviours in Children With Autism’,
Environment and Behaviour 1-27
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 352
‘Overall, as noise increased, both the number (and type) of behaviours as well as their
frequency increased.’
‘The most frequently occurring behaviour for the normal classroom was repetitive motor
movement followed by repetitive speech.’
‘At higher noise levels other types of behaviours start to be observed, such as covering ears
(linked to anxiety), blinking eyes (that is a way to measure social disengagement) and
hitting others.’
‘Recommendations for noise control in environments for children with autism include
acoustical tiles, draperies, resilient flooring, padded seating, sound-absorbing ceiling
materials, and distance from fluorescent lighting… Finally, it is recommended that sound
proofing elements be installed to reduce echoes and noise levels in spaces where a long
attention span is desirable.’
‘Although the data indicate that a positive relationship exists between decibel level and
general behavioural occurrences, disaggregation of the data illustrates the variability that
exists with regard to specific decibel ranges. Repetitive motor movements, repetitive
speech, producing loud sounds, covering ears, blinking eyes, complaining, and hitting
others occurred much more frequently in the loud range (55-70 dB). For the potentially
damaging range (>70 dB), repetitive speech and covering ears occurred much more
frequently than in the lower ranges, whereas repetitive motor movements decreased.
Notably, at the damaging range, the increased behaviours are those overt behaviours that
would signal direct distress, whereas the loud, but not damaging range, is the range that
elicits non-direct expressions of distress.’
‘Overall, findings suggest that attention to acoustic design and modifications to existing
environments are essential to providing a supportive educational environment.’
‘Specific recommendations for modifications could include use of a better HVAC system or
alternative methods of air regulation; egg cartons fixed to the walls, carpet, and other
sound-absorbing materials on the floors; a buffer between classrooms and exterior spaces;
and attention to whether access to natural views enhances well-being or increases
acoustic problems. Efforts should be made to keep the average sound level at
approximately 50 dB or below.’
‘It should be considered that idiosyncratic needs of individuals cannot all be met, and
design that perfectly accommodates every individual need is not feasible.’
‘It remains though, that acoustics appear to be one of, if not the most, important factor in
a well-designed environment for individuals with autism.’
15.52 The paper provides an indication that an ambient internal noise level of approximately LAeq,T 50
dB is considered a reasonable level to avoid significant increases in observed adverse behaviour
of persons with autism. Furthermore, designing for or trying to perfectly accommodate every
individual is not feasible.
Calculation of Road Traffic Noise (1988)158
15.53 In England and Wales, the standard method for predicting road traffic noise levels is given in the
Calculation of Road Traffic Noise 1988 (CRTN). This methodology utilises a number of input
158 Department of Transport Welsh Office, (1988) ‘Calculation of Road Traffic Noise’, HMSO
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 353
parameters (e.g. road traffic flow, composition, speed, gradient road, road surface, distance of
receptor from road etc.) to enable predictions of noise levels due to road traffic to be produced.
This method enables the calculation of average levels over a period of either 18 hours or 1 hour.
Predictions are produced in terms of LA10, as this is considered the measurement descriptor that
best describes road traffic noise.
Design Manual for Roads and Bridges (2011)159
15.54 The Design Manual for Roads and Bridges (DMRB) was originally published by the Department of
Transport in 1993 and sets out procedures for undertaking the design of road schemes. Volume
11, Section 3, Part 7 sets out a methodology for assessing the impacts of noise and vibration.
This methodology can be applied to the assessment of new road schemes or schemes that result
in changes in traffic flows on existing road links. The most recent revision of this section of the
Design Manual for Roads and Bridges was published in November 2011 with a Design Manual
Road Bridges Interim Advice Note (DMRB IAN) published in 2015. The DMRB IAN provides noise
speed bands that are to be used when predicting road traffic noise for motorways and urban/
rural roads. It is therefore this version of the guidance that is referred to in this assessment.
15.55 Table 3.1 of the DMRB, reproduced below in Table 15., provides guidance on the magnitude of
short term road traffic noise impacts, such as those that would be experienced due to short term
construction traffic flows. DMRB defines ‘short term’ as when the project is opened, which has
been taken to be the year of opening i.e. 12 months.
Table 15.8: Classification of magnitude of short term road traffic noise impacts
Noise Change, dB LA10, 18 hr Magnitude of Impact
0 No change
0.1 – 0.9 Negligible
1.0 – 2.9 Minor
3.0 – 4.9 Moderate
5.0+ Major
15.56 Similarly, Table 3.2 of DMRB, reproduced below in Table 15., provides the following criteria
relating to long term changes in road traffic noise levels, such those that could be experienced
during the operational phase of the Revised Scheme. DMRB defines ‘long term’ as typically 15
years after the project is opened.
Table 15.9: Classification of magnitude of long term road traffic noise impacts
Noise Change, dB LA10, 18 hr Magnitude of Impact
0 No change
0.1 – 2.9 Negligible
3.0 – 4.9 Minor
5.0 – 9.9 Moderate
10.0+ Major
Assessment Methodology and Significance Criteria
159 The Highways Agency, (2011) ‘Design Manual for Roads and Bridges, Volume 11, Section 3, Part 7, Traffic Noise
and Vibration’, HA.
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 354
Methodology
15.57 This noise assessment has been carried out by Richard Carter of Hoare Lea. Richard is an
Associate Director with Hoare Lea running the environmental noise group, which has a focus on
environmental impact assessments. Richard is a bachelor of Mechanical Engineering, holds a
post-graduate diploma in Acoustics and Noise Control, is a Chartered Engineer, a Chartered
Environmentalist and a member of the Institute of Acoustics. He has over 20 years of experience
working on technical engineering projects and has specialised in environmental acoustics since
2005.
Consultation
15.58 Consultation took place with Stroud District Council Environmental Protection Department on
26th October 2017 via email. The Environmental Protection Manager confirmed that the Council
was in broad agreement of the overall assessment method on 2nd November 2017. Discussion
continued on the subject of the day-time LAmax criteria adopted for WMC. Further information
was provided in this regard to SDC until no further questions were raised. SDC reserved
judgement on this issue until receipt of the finalised ES Chapter.
Study Area
15.59 The Study Area encompasses the Development Footprint and adjacent land in the direction of
nearby noise sensitive receptors. This includes properties off Grove Lane, the Hotel near to the
junction of Grove Lane and the A419 and William Morris College and Chipmans Platt. Receptors
and land beyond these properties need not be considered in detail provided that acceptable
noise levels can be achieved at these closer areas.
Construction Phase
15.60 Construction noise has been predicted using the calculation methodology identified in BS 5228-
1, indicative construction methodology, and sound power levels for different plant items as
presented in the Appendices to BS 5228-1. At this stage, the specific construction methodology
for the development has not been identified and therefore an indicative construction schedule
has been used for the assessment, based on worst-case assumptions, development phasing and
with plant operating at closest approach to the nearest receptors.
15.61 The construction works have been split into the following phases of works:
• Earthworks – assumed to be undertaken throughout the Development Footprint;
• Foundations – assumed to be undertaken at the location of the proposed stadium;
• Access road – roads extending off A419 into the stadium carpark;
• General construction - assumed to be undertaken throughout the Development Footprint
buildings and facilities.
15.62 The tables within RS Appendix 15.5 present the source inputs for construction noise divided into
phases of the works and the different stages of each phase.
15.63 In addition to noise generated through construction activity within the Development Footprint,
consideration has been given to construction traffic noise. The basic noise level has been
calculated for the section of the A419 between the site access and the M5 Junction 13 in
accordance with the Calculation of Road Traffic Noise (CRTN). A correction for Heavy Goods
Vehicles (HGV) has been applied to the basic noise level. Two scenarios were calculated based
on the existing road Average Annual Weekday Traffic (AAWT) flow and % HGV and a second with
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 355
the peak anticipated daily construction traffic added to this. The difference in the basic noise
level with HGV corrections was considered to represent the likely difference in road traffic noise.
Operational Phase
15.64 Five key operational scenarios have been considered in this assessment:
• Crowd noise during a football match;
• Noise from the use of training pitches;
• Noise from any fixed plant associated with the stadium;
• Vehicle noise from the use of the carpark; and
• Changes in road traffic noise from vehicles using the existing highway network.
15.65 A 3-dimensional acoustic model has been constructed as a tool for understanding noise
propagation of the sources across the Development Footprint and assessment Study Area to
evaluate noise levels incidents on the façades of the nearest noise sensitive receptor locations.
The acoustic model has been generated using the CadnaA software package which calculates
propagation based on the principles of ISO 9613-2 or CRTN. Topographical information used in
the model is from Ordnance Survey OpenData topographical survey drawings. Due to the nature
of the noise source, continuous crowd noise and maximum levels have been predicted during a
game at full capacity to represent the constant and occasional louder events associated with
stadium noise using the LAeq, 2hour and LAmax noise parameters respectively.
15.66 Data presented for an ARUP Acoustics study (2007)160 inside the existing Anfield stadium during
two Premiership football matches has been used to provide confidence in the sound power data
used in the noise model. This study is included in RS Appendix 15.6 for convenience. Particular
regard was given to the second match between Liverpool and Aston Villa on 11th January 2003
as the score was 1-1 and therefore included a goal by the home team, Liverpool. The match was
attended by 43,210 people, with a stadium capacity at the time of approximately 45,000. Whilst
it is recognised that there are several factors influencing ambient and maximum crowd noise at
football matches, it is proven161 that the change in level is proportional to the number of people
within the crowd, N, at a rate of 10 logN.
15.67 The stadium was modelled as a 3-dimensional object with the seating defined as an area source
of sound power LWA 91.4 dB / m2 of seating for steady noise and LWA 107.4 dB / m2 for louder
event Lmax noise. The noise source used for the predictions of steady crowd noise from a 5,000
capacity attendance is based on the sound power level of a male voice ‘as loud as possible
without strain’ assuming 5,000 people constantly creating this level of noise for the entire
assessment period. The proposed Forest Green Rovers Football Stadium (FGRFC) stadium
building construction was refined and discussed in detail with Zaha Hadid Architects. This results
in the stadium construction itself representing an effective screen for sources of noise within it,
equivalent to a solid barrier with a height of 11 m. This was included in the 3D model.
15.68 A receptor was placed within the noise model at an equivalent location to S3 used in the ARUP
Acoustics study to compare the modelled noise levels with those measured during a game with
high levels of crowd noise. Table 15.10 presents a comparison of the ARUP measured noise level
corrected from 43,210 to 5,000 people using -9 dB with the noise level modelled for the Revised
160 Stadium Internal Noise Survey New Anfield 66143/PBA, ARUP Acoustics, 15 May 2007 161 Prediction of Crowd Noise, Hayne et al, 2006
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 356
Scheme. The match noise used in the model equates to the highest LAeq, 30 secs data measured and
the LAmax event noise is 4 dB higher in the noise model, presenting a worst case.
Table 15.10: Comparison of noise model data with measured data during Aston Villa vs Liverpool
at Anfield 11/01/2003
Noise parameter A-weighted sound pressure level, dB
ARUP S3 S3 corrected
to 5,000
Hoare Lea
noise model
Difference
Match LAeq 90 81 - -
Highest LAeq, 30 secs 102 93 93 0
Lowest LAeq, 30 secs 77 68 - -
LAmax 114 105 109 +4
15.69 The Training Pitches comprise two full-size grass external pitches and a penalty and goal practice
area. These have been modelled using the CadnaA software package as area sources. The sound
power of the training pitches used in the noise model is LWA 70 dB / m2 for steady noise and LWA
88 dB / m2 for the higher maximum event noise. As a worst case assumption, all three training
spaces have been modelled to be in use at the same time.
15.70 Exact details of any plant that is likely to be installed to service the Revised Scheme is not yet
known. At this stage the most pragmatic approach would be to set appropriate noise limits for
any such plant so as to minimise any impacts.
15.71 The stadium Car Park has also been modelled using the CadnaA software package as an area
source based on representative measurements of vehicle manoeuvres in a car park. The model
includes car movement with a sound power level of LWA 86.7 dB per vehicle and cars manoeuvring
with a sound power level of LWA 68.8 dB. It is assumed that in half an hour 1,800 vehicles drive
around the car park and carryout a manoeuvre for the entire period as a worst-case.
15.72 Traffic flows for the various development scenarios have been provided by PFA Consulting
Limited. In accordance with DMRB, traffic data has been provided for the following scenarios:
• Scenario 1 – 2017 traffic data based on Annual Average Weekday Totals
• Scenario 2 – 2036 design year, 15 years after opening, including general traffic growth and
committed development
• Scenario 3 – 2036 design year with scenario two above and the Revised Scheme assuming
a worst case of a full 5,000 capacity match.
15.73 The traffic consultants have advised that the %HGV movements would be consistent throughout
each scenario. The committed developments included within the traffic data are listed in Table
2.5 and illustrated in RS Figure 18.1.
15.74 This assessment uses the 3-dimensional acoustic model of the road traffic flow Scenarios 2two
and 3three to calculate the change in road traffic noise as a result of the Revised Scheme. The
change in road traffic noise has been taken as the traffic noise during a 5,000 capacity match
(Scenario 3) less the traffic noise without a match (Scenario 2) during the design year.
Significance Criteria
Approach
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 357
15.75 The assessment criteria takes into account the following:-
• A consideration of the ‘significance of effect’, which takes into account the sensitivity of
receptor and magnitude of change based on guidance criteria within BS 4142, BS 8233 and
DMRB, the latter relating to a relative difference in noise between a future baseline level
and development level; and
• Mitigation requirements from the various guidance documents and legislation, such as
sound insulation trigger levels within BS 5228.
Value of Receptor Sensitivity
15.76 The example for sensitivity within the IEMA Noise Assessment Guidelines has been followed to
provide the criteria for sensitivity as follows.
Table 15.11: Receptor Sensitivity
Sensitivity Criteria
High
Receptors where occupants or activities are particularly susceptible to noise. Examples
include: residences, quiet outdoor areas used for recreation, conference facilities,
auditoria/studios, schools in daytime, hospitals/residential care homes and religious
institutions e.g. churches or mosques.
Medium
Receptors moderately sensitive to noise, where it may cause some distraction or
disturbance. Examples include: offices, restaurants and sports grounds where spectator
noise is not a normal part of the event and where quiet conditions are necessary (e.g. golf
or tennis).
Low
Receptors where distraction or disturbance from noise in minimal. Examples include
residences and other buildings not occupied during working hours, factories and working
environments with existing high noise levels and sports grounds where spectator noise is
a normal part of the event.
15.77 The area surrounding the development is a combination of transport corridors, residential
dwellings, educational buildings and agricultural land. This includes William Morris College
(WMC) which contains some individuals which are particularly susceptible to noise and as such
is classed as being of the highest sensitivity. For the purposes of the assessment of noise, all
receptors included are considered of high sensitivity. In addition, the nature of noise and the
magnitude of effects has been considered separately for residential dwellings and the buildings
associated with WMC, and this is discussed below.
Magnitude of Effect
15.78 The ‘magnitude of effect’ is used to describe a numerical impact in effect terms, and is used
differently for each of the various aspects of change to the noise environment. Table 15.2 and
Table 15.14 presents a summary of the criteria for effect based on appropriate guidance set out
at the beginning of this chapter for construction noise and operational noise respectively. Table
15.13 presents a summary of the criteria for effect for construction vibration based on Table B.1
of BS 5228-2.
Table 15.12: Magnitude of effect criteria for external construction noise impacts
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 358
Effect
(negative)
Criteria
Construction Noise Construction Traffic
Noise
Major
> 82 dB LAeq, 10 hour
Trigger level for temporary rehousing, or reasonable cost thereof,
as set out in E.4 of BS 5228. Considered to be the Unacceptable
Adverse Effect Level.
Change in LA10, 18 hour
of 5 dB or more
Moderate
> 72 dB LAeq, 10 hour ≤ 82 dB LAeq, 10 hour
Trigger level for noise insulation works, or cost thereof, as set out
in E.4 of BS 5228 and therefore the onset of SOAEL.
Change in LA10, 18 hour
of 3.0 – 4.9 dB
Minor
> 65 dB LAeq, 10 hour ≤ 72 dB LAeq, 10 hour
Most stringent threshold value for impact given in Annex E of BS
5228 for example methods relevant to Revised Scheme.
Considered to be between LOAEL and SOAEL.
Change in LA10, 18 hour
of 1.0 – 2.9 dB
Negligible
> 55 dB LAeq, 10 hour ≤ 65 dB LAeq, 10 hour
Noise is likely to be audible, but unlikely to change behaviour.
Considered as the onset of LOAEL.
Change in LA10, 18 hour
of 0.1 – 0.9 dB
No Impact ≤ 55 dB LAeq, 10 hour
Construction noise may be audible
No change in
LA10, 18 hour
Positive
Impact N/A N/A
Table 15.13: Magnitude of effect criteria for external construction vibration impacts
Effect
(negative) Criteria
Major
> 10 mm.s-1
Vibration is likely to be intolerable for any more than a very brief exposure to this level in
most building environments. Considered to be the Unacceptable Adverse Effect Level.
Moderate
> 1.0 mm.s-1 ≤ 10 mm.s-1
It is likely that vibration of this level in residential environments will cause complaint, but
can be tolerated if prior warning and explanation has been given to residents and therefore
considered to be the onset of SOAEL.
Minor
> 0.3 mm.s-1 ≤ 1.0 mm.s-1
Vibration might be just perceptible in residential environments. Considered to be between
LOAEL and SOAEL.
Negligible
> 0.14 mm.s-1 ≤ 0.3 mm.s-1
Vibration might be just perceptible in the most sensitive situations for most vibration
frequencies associated with construction. At lower frequencies, people are less sensitive to
vibration. Considered as the onset of LOAEL.
No Impact ≤ 0.14 mm.s-1
The level of vibration is not likely to be perceptible even in the most sensitive situations.
Positive
Impact N/A
Table 15.14: Magnitude of effect criteria for external operational noise impacts at residential
receptors
Effect
(negative)
Criteria
Fixed Plant Noise Stadium, Training Pitch and Car
Park Noise Operational Traffic
Major 10 dB or more above existing
background noise (LA90)
10+ dB exceedance of
prevailing noise
Change in LA10, 18 hour
of 10 dB or more
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 359
Effect
(negative)
Criteria
Fixed Plant Noise Stadium, Training Pitch and Car
Park Noise Operational Traffic
Moderate 5.0 – 9.9 dB above existing
background noise (LA90)
5.0 – 9.9 dB exceedance of
prevailing noise
Change in LA10, 18 hour
of 5-9.9 dB
Minor 3.0 – 4.9 dB above existing
background noise (LA90)
3.0 – 4.9 dB exceedance of
prevailing noise
Change in LA10, 18 hour
of 3-4.9 dB
Negligible 0.1 – 2.9 dB above existing
background noise (LA90)
0.1 – 2.9 dB exceedance of
prevailing noise
Change in LA10, 18 hour
of 0.1-2.9 dB
No Impact Rating level below existing
background noise (LA90)
No exceedance of prevailing
noise
No change in LA10, 18
hour
Positive
Impact N/A N/A N/A
15.79 Further consideration has been given to WMC as a nearby sensitive receptor. Whilst its
sensitivity is classified as the highest (see Table 15.11), additional consideration has been given
to the potential noise impacts upon the residences of this location. WMC is a specialist college
promoting work-related learning and independence for young people with autistic spectrum and
learning difficulties. It should be noted that several receptors were positioned at WMC covering
multiple buildings and floors. The assessment presents the data from the receptor with the
highest predicted noise level as a worst-case.
15.80 The following additional operational daytime magnitude of effect criteria set out in Table 15.15
for external noise events and internal noise has been developed from the aforementioned
guidance documentation and papers and has been applied at WMC and associated residential
properties at Chipmans Platt only. In the absence of any guidance of the magnitude of effect of
daytime maximum noise levels (LAmax), the relevant criteria have been based on the measured
LAmax noise level already experienced near to WMC which are described in the baseline section
of the present Chapter.
Table 15.15: Magnitude of effect criteria for noise impacts at WMC and Chipmans Platt
Effect
External Criteria Internal Criteria
Maximum Noise
Level
Ambient noise
contribution to
classroom
Event noise
contribution to
classroom
Ambient noise
contribution to
resting space
Major
More than two
events > LAFmax,T
79 dB in a day
> 55 dB LAeq,30min > 70 dB LA1,30min > 50 dB LAeq,T
Moderate
More than six events
> LAFmax,T 75 dB
occurring in a day
> 50 dB to 55 dB
LAeq,30min
> 65 dB to 70 dB
LA1,30min
> 45 dB to 50 dB
LAeq,T
Minor
Any number of
events > LAFmax,T
61 dB in a day
40.1 dB to 50 dB
LAeq,30min
60.1 dB to 65 dB
LA1,30min
40.1 dB to 45 dB
LAeq,T
Negligible LAFmax,T 54 dB to
61 dB
35.1 dB to 40 dB
LAeq,30min
≤ 60 dB LA1,30min 35.1 dB to 40 dB
LAeq,T
No Impact < LAFmax,T 54 dB ≤ 35 dB LAeq,30min N/A ≤ 35 dB LAeq,T
Positive
Impact N/A N/A N/A N/A
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 360
Significance of Effect
15.81 The nearest receptors to the development are classed as ‘high’ sensitivity. As this assessment
considers one level of sensitivity, the normal approach to significance cross referencing
sensitivity and magnitude of impact has been substituted with a dual approach. Impacts are
considered significant within the meaning of the EIA Regulations if the magnitude of effect is
either moderate or major as highlighted in Table 15.16 below. Mitigation will be applied where
a significant effect has been assessed.
Table 15.16: Matrix of Significance
Sensitivity of receptor/ Receiving Environment to Change/ Effect
High Medium Low Negligible
Ma
gn
itu
de
of
Ch
an
ge
/ e
ffe
ct
Major Significant Significant Not Significant Not Significant
Moderate Significant Not Significant Not Significant Not Significant
Minor Not
Significant
Not Significant Not Significant Not Significant
Negligible Not
Significant
Not Significant Not Significant Not Significant
Baseline Conditions
15.82 Baseline noise measurements were in 2015, and further measurements were undertaken at the
end of June and the start of July in 2017.
2015 baseline measurements
15.83 The 2015 measurements were taken between Thursday 3rd and Friday 4th September 2015. Four
unattended noise monitoring stations were installed towards the north and south of the then
proposed previous site Redline Boundary, and at nearest receptors. In addition, attended
measurements were taken during the daytime at four locations representing road noise at
boundaries of the site.
15.84 Further details of the 2015 survey and results can be found in Chapter 15 and RS Appendix 15.1
of the ES which accompanied the 2015 planning application RS Appendix 15.2 and RS Appendix
15.3. A summary of the relevant baseline data is provided below in Table 15..
Table 15.17: 2015 Baseline Noise Levels
Location Time Period LAeq, T dB LA90, T dB LA10, T dB LAFmax, T dB* LA10, 18h dB**
MP2 07.00 – 23.00 53.4 50.3 54.0 81.6 53.8
23.00 – 07.00 50.5 44.7 51.6 73.4
MP3 07.00 – 23.00 57.0 54.8 58.1 81.8 57.8
23.00 – 07.00 50.8 44.0 50.8 76.8
MP4 07.00 – 23.00 54.5 51.2 55.5 74.4 55.3
23.00 – 07.00 48.0 40.2 45.5 72.9
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 361
Location Time Period LAeq, T dB LA90, T dB LA10, T dB LAFmax, T dB* LA10, 18h dB**
MP7 10.02 – 13.02 58.6 47.1 62.6 82.2 n/a
2017 baseline measurements
15.85 Additional measurements were carried out in 2017 between Wednesday 28th June and Tuesday
4th July. Two unattended noise monitoring stations were installed near to William Morris College
to the south of the site Redline Boundary and near to Westend House to the north of the site
Redline Boundary. Table 15.18 lists the 2017 survey locations and noise sources heard locally
and RS Figure 15.1 illustrates all the survey locations used in this assessment.
Table 15.18: Summary of Measurement Locations
Location Location description Coordinates (E, N) Description of noise environment
L1
South of site the Redline
Boundary near to
previous MP3 location
and William Morris
College
378188, 206333
Road traffic noise from vehicles using
the A419 with possible contribution
from the M5 was dominant. Other
sounds heard include birds, wind
disturbed vegetation, intermittent
aircraft and occasional cattle.
L2
North east of the site
Redline Boundary near
to previous MP2
location and Westend
House
378368, 206748
Noise from motor vehicles passing on
the local road was dominant when
these events took place. In the
absence of passing vehicles noise from
the M5 motorway and birds were the
dominant observed sources.
15.86 For both locations L1 and L2 the microphones of the sound level meters were mounted
approximately 1.4 m above the ground and at least 5 m from any other acoustically reflective
surface. The measurement systems were field calibrated before and after the measurements
and no significant drift was recorded.
15.87 A summary of the 2017 baseline survey results is presented below in Table 15.19, separated into
weekday and weekend results. The daytime is defined as between the hours of 07.00 and 23.00
and the night-time between the hours of 23.00 and 07.00.
Table 15.19: 2017 Baseline Noise Levels
Location Time Period LAeq, T dB LA90, T dB LA10, T dB LAFmax, T dB LA10, 18h dB
L1
Week daytime 56.9 52.7 57.1 84.2 56.8
Week night-time 51.8 46.2 53.0 72.5
Weekend daytime 53.5 50.0 54.6 74.2 54.1
Weekend night-time 49.1 42.7 50.2 73.3
L2
Week daytime 52.9 49.1 53.9 80.7 54.3
Week night-time 48.4 43.0 50.0 71.1
Weekend daytime 52.3 48.6 53.7 74.6 53.5
Weekend night-time 48.7 42.5 50.2 71.2
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 362
15.88 The maximum noise events measured during the 2015 and 2017 baseline surveys at MP3 and L1
respectively has been combined to provide a broader data-set of the LAmax noise events near
WMC. RS Figure 15.3.6 in RS Appendix 15.3 graph (see Figure 15.3.6 of the appendix) illustrates
the data. A summary of the modelled baseline road traffic noise is illustrated in RS Figure 15.7.
15.89 To provide a representative noise source for the training pitches, a review of available data and
further measurements at Durdham Downs in Bristol were undertaken. During the survey four
simultaneous football matches were played on external grass pitches. The measurements were
undertaken on the evening of 6th April 2017 by Hoare Lea at a distance of 20 m from the side of
the nearest of the four pitches. The activity noise included shouts from players and instructions
from the referee (including use of a whistle) but there were very few spectators or people moving
about on the side lines making any noise. The measured levels were LAeq,T 51 dB and LAFmax,T 68
dB.
15.90 To provide a representative noise source for the carpark, noise measurements at the carpark of
155 Aztec West offices in Bristol were undertaken. The level of noise resulting from a range of
activities were measured. These covered the typical noisy activity associated with vehicles within
a carpark: car doors and boots opening and closing, car engines starting, idling and pulling away
and manoeuvring in and out of parking bays.
Design Evolution
15.91 Embedded mitigation measures that have been identified and adopted as part of the evolution
of the project design (embedded into the project design) that are relevant to noise are as follows:
• Appropriate design and positioning of the development, including the location of outdoor
sports provisions away from William Morris College;
• Careful positioning and orientation of the stadium to balance site constraints and to
minimise noise impacts at nearby noise-sensitive receptors;
• Close collaboration between the architects and acoustic engineers to ensure the design
and fabric of the stadium minimises the noise breaking out, including a solid barrier behind
the seating area up to a height of 11 m above pitch level;
• A 2 m high earth bund acoustic barrier running from the road access to the A419 along the
southern and eastern boundaries of the carpark, continuing north toward the M5 and
around the eastern and northern edge of the northern most training pitch.
Potential Effects
15.92 The noise assessment in relation to both construction and operation phases has identified no
significant environmental effects at any of the receptor locations. Therefore, in accordance with
the EIA Regulations, which require ESs to focus on the significant environmental effects (as well
as to accord with the approach taken in other chapters of this ES), information describing how
the non-significant effects were assessed is detailed in RS Appendix 15.4. Table 15.20 at the end
of this chapter summarises noise effects before and after any mitigation or enhancements. RS
Figures 15.2 to 15.8 are referenced in RS Appendix 15.4 when assessing non-significant effects.
15.93 Furthermore, the non-significant effects identified will only occur over a short-term, in particular
those associated with operational impacts. The assessment considers the likely greatest level of
noise during a football match in a 30 second period, which is most likely to be linked to a goal
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 363
from the home team. T and therefore, this may not occur during a match, or may occur three or
four times. We understand that matches will be are typically fortnightly; therefore, it is unlikely
that the effects reported will occur regularly. In addition, there will be a planning condition that
will prevent the use of the stadium for other uses, such as music concerts.
Mitigation and Enhancement Measures
15.94 No significant effects have been identified, and therefore in accordance with the EIA Regulations,
no mitigation measures are required beyond those embedded mitigation measures incorporated
into the scheme design. Below are recommended enhancement measures to further control or
reduce noise during the construction and operation phases of the Revised Scheme.
15.95 A detailed Construction Management Plan should be drafted, and this can be secured by
condition, to maintain best practice procedures during the construction phase in line with BS
5228, and this can be secured by condition. Such measures will include well maintained
equipment, mobile equipment positioned away from receptor locations and where provided,
silencers or soundproof enclosures to construction equipment to be utilised and properly
maintained. The Construction Management Plan is to also include a section on the management
of traffic to and from the construction site, to restrict vehicles using smaller roads such as Grove
Lane. In addition, it can be seen in RS Figure 5.4, the Indicative Construction Compound Plan,
that it has been designed to locate construction noise sources away from sensitive receptors
along Grove Lane.
15.96 The stadium should produce and adhere to an Operational Noise Management Plan. The plan
should include measures to monitor and control noise from spectators, the stadium public
address system and training sessions. Again, this should be secured via planning condition, see
RS Appendix 6.1.
Residual Effects
15.97 Table 15.20 details the significance of the effects likely to arise as a result of the development
after enhancement measures have been employed. There will be no significant effects (and thus
no residual effects) as a result of the development.
Cumulative Effects
Construction Effects
15.98 At this stage it is not envisaged that the construction of any other large-scale development will
coincide with the construction of the Revised Scheme. We understand that construction of the
West of Stonehouse development has commenced and that all major construction works, such
as ground remediation and sub-structure works will be complete before any construction will
take place for the Revised Scheme. Therefore, no significant cumulative effects are anticipated
during the construction phase.
Operational Effects
15.99 The cumulative effects of the Revised Scheme in terms of noise impact are restricted to the long-
term impacts in changing road traffic levels. Road traffic noise levels calculated from flow data
provided by PFA, the appointed traffic consultant, have included vehicles accessing the Revised
Scheme plus further committed developments in the area. Therefore, the road traffic noise
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 364
assessment carried out in this Chapter includes the cumulative effects from other committed
developments as part of the baseline, and are not predicted to be significant. Information on
committed developments in the area is provided in Chapter 12, Table 2.5 and RS Figure 18.1.
15.100 In development terms, the cumulative effect of the proposed stadium, training pitches and car
park noise will not be significant.
Conclusions
15.101 A baseline noise survey has been undertaken to identify appropriate noise criteria and to
compare with potential future noise levels as a result of the development proposals.
15.102 Noise and vibration from the construction phase has been predicted and assessed. Absolute
noise levels and changes to the baseline noise from construction and operation of the
development have been predicted and assessed.
15.103 The maximum noise level events from the stadium will only are most likely to occur when goals
are scored during matches. However, the duration and frequency of these events is very limited
– in 2017 there will have been an average of three home games per month and three goals per
game (this excludes June during which there were no home games and goal data for December
which is not yet available). Although not found to be significant it is important to recognise that
these effects are predicted to only occur on average for approximately 1.5 minutes per game (30
seconds per goal) around three times per month.
15.104 Noise generated by the operation of the Revised Scheme has been calculated at nearby receptor
locations. Consideration has been given to noise generated during a football match with 5,000
spectators, training sessions, the use of the car park and changes in noise from vehicles using the
local road network.
Significant residual effects
Construction phase
15.105 Based on mitigation embedded within the design no significant adverse effects are predicted
during the construction phase of the development.
Operational phase
15.106 Based on mitigation embedded within the design no significant adverse effects are predicted
during the operational phase of the development.
Eco Park, Land at M5 Junction 13, West of Stonehouse | Environmental Statement
December 2015
Page | 365
Table 15.20: Summary of Noise and Vibration Effects and Mitigation
Receptor Effect Phase
(Construction
/ Operation)
Embedded
Mitigation
Sensitivity
of
Receptor
Magnitude
of Change
Level of Effect
and
Significance
Prior to
Mitigation
Mitigation Enhancement Level of
Effect (and
Significance)
after
Mitigation
Nature of effect (i.e.
short term / medium
term / long term,
permanent /
temporary, direct /
indirect)
William
Morris
Colleage
and
Chipmans
Platt
Construction noise Construction Not applicable. High Minor Not
significant
Not
applicable
CEMP Not
significant
Negative, medium term,
direct Construction vibration Negligible
Construction traffic Negligible
Stadium noise highest LAeq, 30 Sec Operation Stadium design
and location
and 2 m high
earth bund.
Minor Operational
Management
Plan for
stadium and
training
pitches
Negative, permanent,
direct, in-frequent, short
duration.
Stadium noise event LAmax Minor
Training pitch noise LAeq, T No impact
Training pitch event noise LAmax Negligible
Car park noise No impact
Fixed plant noise Negligible
Road traffic noise Negligible Not applicable
Grove
Lane
Dwellings
nearby
Construction noise Construction Not applicable. Minor CEMP Negative, medium term,
direct Construction vibration Minor
Construction traffic Negligible
Stadium noise highest LAeq, 30 Sec Operation Stadium design
and location
and 2 m high
earth bund.
Minor OMP for
stadium and
training
pitches
Negative, permanent,
direct Training pitch noise LAeq, T No impact
Car park noise Negligible
Fixed plant noise Negligible
Road traffic noise No impact Not applicable
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 366
16 CLIMATE CHANGE
Summary
16.1 An assessment has been undertaken of the potential effects of the Revised Scheme on climate
change (‘climate change mitigation’) and of the vulnerability of the Revised Scheme to climate
change (‘climate change adaptation’).
16.2 As this is an amended application, this EIA has been carried out in accordance with the 2011 EIA
Regulations. However, it should be noted that the 2017 Regulations now contain additional
matters which were not required to be assessed in the 2011 Regulations – which includes an
assessment of Climate Change relevant to the project concerned. As these matters are clearly
important, whilst this ES will be determined in line with the 2011 Regulations, the additional
matters which would have been required under the 2017 Regulations have also been assessed.
The scope of this EIA is explained in more detail within Chapter 2.
16.3 The assessment has been undertaken in accordance with published guidance on considering
climate change in EIA and consequently reviews how climate change has been considered at all
stages of project progression and assessment. This includes, for example, the review of
alternatives and the project design, how baseline environmental conditions may change with a
changing climate, and the resilience of mitigation measures to climate change. As advised in
guidance, it is informed by an understanding of future climate change scenarios (for the south-
west of England) and of the potential range of effects associated with these projections. These
projections suggest that, in future, the Site and its surroundings will experience warmer, drier
summers and warmer wetter winters. Whilst heavy rain days are likely to increase throughout
the year, there is still considerable uncertainty with respect to likely changes in both wind speed
and storm frequency/intensity.
16.4 The applicant is committed to implementing a range of outlined design, and additional
mitigation, measures to aspire to deliver a ‘carbon neutral’ development (which achieves net
zero carbon emissions) or ‘a carbon negative’ development (which removes more carbon
emissions from the atmosphere than it creates). Adopting a precautionary approach to the
assessment, it is assumed that the development will be ‘carbon neutral’ rather than ‘carbon
negative’. On the assumption that a robust and verified carbon accounting approach is adopted,
and the development can be constructed and operated as a carbon neutral development, it is
therefore considered that the Revised Scheme will have no significant effects in relation to
climate change mitigation.
16.5 It is not anticipated that the scale of projected climate change identified will fundamentally alter
baseline conditions or the effect judgements included in this ES. It is also not considered that
the Revised Scheme will materially affect the ability of receptors to respond to climate change.
Overall, with the design and mitigation measures proposed, the Revised Scheme is considered
to be resilient to projected climate change. It is therefore considered that the Revised Scheme
will have no significant effects in relation to climate change adaptation.
Introduction
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 367
16.6 Over recent decades, climate change has become a more important environmental, social and
economic policy concern. Consequently, climate change is also seen to be an important
consideration in relation to project level assessment and decision-making. The 2017 EIA
Regulations162 therefore require:
“A description of the likely significant effects of the development on the environment
resulting from, inter alia: (f) the impact of the project on climate (for example the nature
and magnitude of greenhouse gas emissions) and the vulnerability of the project to climate
change”.
16.7 As this is an amended application, this EIA has been carried out in accordance with the 2011 EIA
Regulations163. However, it should be noted that the 2017 Regulations now contain additional
matters which were not required to be assessed in the 2011 Regulations – which includes an
assessment of Climate Change relevant to the project concerned. As these matters are clearly
important, whilst this ES will be determined in line with the 2011 Regulations, the additional
matters which would have been required under the 2017 Regulations have also been assessed.
The scope of this EIA is explained in more detail within Chapter 2.
16.8 This chapter therefore considers the following:
(i) The potential effects of the Revised Scheme on climate change, with measures included in
the project to reduce the emissions of greenhouse gases (GHGs) referred to as climate
change mitigation (not to be confused with ‘EIA mitigation’);
(ii) The vulnerability of the Revised Scheme to climate change, with measures included in the
project to ensure resilience to climate change referred to as climate change adaptation.
16.9 The chapter makes significant reference to other chapters within this ES and also to other
documents which support the planning application, including the Design and Access Statement.
As a consequence, the structure of this chapter differs in part from other assessment chapters.
Legislation, Policy and Guidance
16.10 This section sets out legislation, policy and related assessments at the international, national and
local level, with respect to both climate change mitigation and adaptation. It also outlines
guidance relevant to the undertaking of this assessment.
International Agreements
16.11 In December 2015, the adoption of the ‘Paris Agreement’ was established through the twenty
first session of the Conference of Parties (COP21), which outlined the motives of UNFCCC164
member states to refocus and meet the ambitions of climate change targets first introduced in
the ‘Kyoto Protocol’ in 1992. The Paris Agreement165stresses the “urgency of accelerating the
implementation of the Convention and its Kyoto Protocol” and within this, ensuring that the long
term temperature goals are met.
162 The Town and Country Planning (Environmental Impact Assessment) Regulations 2017. 163 The Town and Country Planning (Environmental Impact Assessment) Regulations 2011. 164 The United Nations Framework Convention on Climate Change. 165 UNFCCC (2015) Adoption of the Paris Agreement, 21st Conference of the Parties, Paris, United Nations.
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 368
16.12 Article 2 of the Paris Agreement sets out the ambition of holding the increase of global average
temperature to “well below 2°C” and to pursue efforts to limit temperature increase to 1.5 °C. It
was acknowledged that to achieve these ambitions, there is a requirement to ensure Parties
reach global peaking of greenhouse gas emissions as soon as possible and do so by employing
means that allow pathways toward “low greenhouse gas emissions and climate-resilient
development”.
16.13 On 5 October 2016, the threshold for entry into force of the Paris Agreement was achieved, with
at least 55 countries, which account for at least 55% of the world’s greenhouse gas emissions,
ratifying the Agreement. The Paris Agreement entered into force on 4th November 2016 and the
UK ratified the Agreement on 18th November 2016.
UK Context
16.14 The UK Climate Change Act became law in November 2008166. This legislation sets legally binding
targets for reducing emissions of greenhouse gases by 2020 and 2050. The Act makes it the duty
of the Secretary of State to ensure that the net UK carbon account for the year 2050 is at least
80% lower than the 1990 baseline.
16.15 The Climate Change Act established the principle of five year ‘carbon budgets’, with a carbon
budget referring to a permitted level of greenhouse gas emissions in the UK over a five year
period. The carbon budgets run to 2032 (2008- 2012, 2013-2017, 2018-2022, 2023-2027, and
2028-2032). The levels of the first three carbon budgets were approved by Parliament in May
2009, and are now set in law. The fourth carbon budget (2023 -2027)167 became law at the end
of June 2011 and requires greenhouse gas emissions to be reduced by at least 50% in the fourth
budget period, relative to 1990 levels. The fifth carbon budget168 became law in July 2016 and
requires greenhouse gas emissions to be reduced by 57% by 2030169.
16.16 The Climate Change Act also established the Committee on Climate Change as an independent
statutory body to advise the UK and Devolved Governments on setting and meeting carbon
budgets and preparing for climate change. In June 2017, the Committee on Climate Change
published ‘Meeting Carbon Budgets – 2017 Progress Report to Parliament’170. The Report states
that whilst good progress has been made to date, progress is stalling. Since 2012, emissions
reductions have been largely confined to the power sector, whilst emissions from transport and
building stock are rising. It is argued that effective new strategies and policies are urgently
needed to ensure emissions continue to fall in line with the commitments agreed by Parliament.
16.17 The Climate Change Act 2008 also requires the Government, on a five-yearly cycle, to compile an
assessment of the risks for the UK arising from climate change, and then to develop an adaptation
programme to address those risks and deliver resilience to climate change on the ground. In
January 2017, the government published the second risk assessment171, which identified six
priority risk areas:-
166 Climate Change Act, 2008. 167 The Carbon Budget Order 2011 (SI 2011 No.1603). 168 The Carbon Budget Order 2016 (SI 2016 No.785). 169 2030 is selected as the mid-point – see for example https://www.theccc.org.uk/2016/07/20/fifth-carbon-budget-
infographic/ 170 Committee on Climate Change (2017) Meeting Carbon Budgets: Closing the policy gap. 2017 Report to Parliament. 171 HM Government (2017) UK Climate Change Risk Assessment 2017.
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 369
• Flooding and coastal change risks to communities, businesses and infrastructure;
• Risks to health, well-being and productivity from high temperatures;
• Risks of shortages in the public water supply, and for agriculture, energy generation and
industry;
• Risks to natural capital, including terrestrial, coastal, marine and freshwater ecosystems,
soils and biodiversity;
• Risks to domestic and international food production and trade;
• New and emerging pests and diseases, and invasive no-native species affecting people,
plants and animals.
16.18 The updated risk assessment will be followed by an updated national adaptation programme in
2018.
National Planning Context
16.19 The National Planning Policy Framework (NPPF) was published in March 2012 and aims to deliver
sustainable development. In achieving this goal, the NPPF requires developments to “mitigate
and adapt to climate change.” Section 10 of the NPPF ‘Meeting the challenge of climate change,
flooding and coastal change’ emphasises the planning system’s pivotal role in sustainable
development through “minimising vulnerability and providing resilience to the impacts of climate
change”.
16.20 Furthermore, Paragraph 99 of the NPPF states:
“Local Plans should take account of climate change over the longer term, including factors
such as flood risk, coastal change, water supply and changes to biodiversity and landscape.
New development should be planned to avoid increased vulnerability to the range of
impacts arising from climate change. When new development is brought forward in areas
which are vulnerable, care should be taken to ensure that risks can be managed through
suitable adaptation measures, including through the planning of green infrastructure.”
16.21 The national Planning Policy Guidance (PPG) was published in June 2014 and recognises that the
planning system can “increase resilience to climate change impact through the location, mix and
design of development”.
Local Context
16.22 The site is located within the administrative boundary of Stroud District Council, with the Council
adopting their Local Plan172 in November 2015. Made in 2016, the Eastington Neighbourhood
Development Plan173 is also a material planning consideration.
16.23 Climate change is considered in a number of the Local Plan policies, as identified below.
16.24 Core Policy CP14: High Quality Sustainable Development addresses climate change by requiring
all new developments to achieve the following:
• “Sustainable construction techniques ...[that include] measures to minimise energy use and
maximise renewable energy production;
172 Stroud District Council (2015) Stroud District Local Plan. 173 Eastinton Parish Council (2016) Neighbourhood Development Plan 2015-2031.
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 370
• No increased risk of flooding on or off the site, and inclusion of measures to reduce the
causes and impacts of flooding as a consequence of that development;
• Attractive accesses on foot and by cycle and suitable connections with existing footways,
bridleway, cycleways, local facilities and public transport”.
16.25 Delivery Policy ES1: Sustainable construction and design requires the “consideration of climate
change adaptation” to be evidenced in planning applications as the policy states that
“Sustainable design and construction will be integral to new development in Stroud District”.
16.26 Delivery Policy ES2: Renewable or low carbon energy generation supports proposals that
maximise the generation of energy from renewable or low carbon sources, provided that the
installation would not have significant adverse impact (either alone or cumulatively) and includes
an impact statement that demonstrates a number of stated factors.
16.27 Delivery Policy ES6: Providing for biodiversity and geo-diversity states that all new developments
should “enable and not reduce species” ability to move through the environment in response to
predicted climate change, and to prevent isolation of significant populations of species.
16.28 With respect to climate change mitigation, the Eastington Neighbourhood Development Plan
provides policy support for developments encouraging sustainable means of transport,
promoting the development of small scale renewable energy developments (with appropriate
safeguards) and supporting the planting of new trees and hedges.
Guidance Documents
16.29 This chapter has been written with reference to the following guidance documents:
• The Environmental Impact Assessment Guide to Assessing Greenhouse Gas Emissions
and Evaluating their Significance (IEMA , 2017a);
• The Environmental Impact Assessment Guide to Climate Change Resilience and
Adaptation (IEMA, 2015);
• The Environmental Impact Assessment Guide to Delivering Quality Development (IEMA,
2016);
• Delivering Proportionate EIA: A Collaborative Strategy for Enhancing UK Environmental
Impact Assessment Practice (IEMA, 2017b).
Assessment Methodology and Significance Criteria
16.30 This chapter has been written by LUC, an environmental consultancy established over 50 years
ago. LUC’s EIA experience dates back to the 1970s when the concept was first introduced in the
UK and, since this time, the Company has prepared over 100 ESs, across a range of sectors, and
has undertaken over 100 independent ES reviews on behalf of local authorities. The Company
has also undertaken EIA research projects at the national and European level and has prepared
EIA good practice guidance. LUC has also secured the Institute of Environmental Management
and Assessment (IEMA)’s Quality Mark, which demonstrates the Consultancy’s commitment to
best EIA practice and preparation of ESs of a very high standard. As part of the requirements as
EIA Quality Mark registrants, LUC is required to submit all of their ESs to IEMA for independent
review.
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 371
16.31 The chapter has been authored by Joanna Wright MA MSc MIEMA, a full Member of the Institute
of Environmental Management & Assessment (IEMA) and a Chartered Environmentalist. Joanna
is a Director of Environmental Planning at LUC with over 24 years of professional EIA experience.
In addition to holding an MSc degree in Environmental Impact Assessment, Joanna also qualified
recently to provide EIA input in relation to climate change, having successfully completed a
Postgraduate Diploma in Carbon Management at the University of Edinburgh.
16.32 IEMA guidance stresses that climate change should be an integrated consideration within the
EIA, including, for example, in the review of alternatives and the project design, how baseline
environmental conditions may change with a changing climate and the resilience of mitigation
measures to climate change. It should be informed by an understanding of future climate change
scenarios and of the potential range of effects associated with these projections. The remaining
sections of this chapter therefore focus on climate change projections for the area in which the
Revised Scheme is located and the consideration given to climate change mitigation and
adaptation in the ES and other documentation supporting the planning application, with
reference to a ‘checklist’ of requirements, compiled using the above IEMA guidance.
The Study Area
16.33 With respect to the Study Area, this assessment considers the effects of the scheme on global
climate, with specific reference to the climate changes expected in the UK. These have been
defined using the UK’s climate change projections (UKCP09), which allow climate changes to be
projected at the regional level; in this case, south-west England. The effects of a changing climate
on the scheme have largely been assessed in relation to the site as defined by the Redline
Boundary and its immediate surrounds. In the case of flood risk, the Study Area (see RS Figure
9.1) extends to approximately 250m downstream of the Redline Boundary for direct impacts
(ensuring appropriate consideration of the River Frome).
Consultation
16.34 Given the timing of the introduction of the 2017 EIA Regulations, the proposed approach to
addressing climate change was not set out in the EIA Scoping Report for the project, which
continues to be considered in accordance with the 2011 EIA Regulations. However, this is not
considered to represent a significant assessment limitation, since established climate change
projections have been adopted and that relevant assessment guidance has been followed.
Assessment of Significance
Climate Change Mitigation
16.35 With respect to climate change mitigation and effect significance, as yet, there are no established
thresholds for assessing the significance of an individual project’s contribution to climate change.
However, the IEMA EIA Guide to Assessing Greenhouse Gas Emissions states the following (in
section 6):
“GHG emissions have a combined environmental effect that is approaching a scientifically
defined environmental limit, as such any GHG emissions or reductions from a project might
be considered to be significant…..Therefore in the absence of any significance criteria or a
defined threshold, it might be considered that all GHG emissions are significant and an EIA
should ensure the project addresses their occurrence by taking mitigating action”.
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 372
16.36 Appendix C of the IEMA guidance also refers to the following principles (taken from IEMA, 2016):
• “Where GHG emissions cannot be avoided, the EIA should aim to reduce residual significance of a project’s emissions at all stages”
• “Where GHG emissions remain significant, but cannot be farther reduced… approaches to
compensate the project’s remaining emissions should be considered.”
16.37 The IEMA guidance also suggests that in the absence of defined GHG thresholds, the
performance of a development could be measured against a benchmark, for example an un-
mitigated ‘standard’ development.
16.38 Furthermore, the IEMA EIA Guide to Assessing Greenhouse Gas Emissions also states the
following (in Appendix C):
“When evaluating significance, all new GHG emissions contribute to a significant negative
environmental effect; however; some projects will replace existing development that have higher
GHG profiles. The significance of a project’s emissions should therefore be based on its net impact,
which may be positive or negative.”
16.39 For the purposes of this assessment, the above guidance has been interpreted as outlined in
Table 16.1 below.
Table 16.1: Defining significance for climate change mitigation
Significance of
Effect
Criteria
No significant
effect
The project will aspire to achieve net zero carbon emissions (i.e. it is a
‘carbon neutral development’).
Positive effect
(major,
moderate, minor
significance)
The project will remove more carbon emissions from the atmosphere than it
creates (i.e.it is a ‘carbon negative development’). Further evaluation against
established thresholds and/or other benchmarks for performance will be required
to determine whether this is of major, moderate or minor significance. If a project
is replacing an existing development, this may include comparison against the GHG
profile of the development that is being replaced.
Negative effect
(major,
moderate, minor
significance)
The project will create more carbon emissions than it removes from the
atmosphere (i.e. it is a ‘carbon positive’ development), Further evaluation against
established thresholds and/or other benchmarks for performance will be required
to determine whether this is of major, moderate or minor significance. If a project
is replacing an existing development, this may include comparison against the
GHG profile of the development that is being replaced.
Climate Change Adaptation
16.40 With respect to climate change adaptation and effect significance, section 6.2.5. of IEMA’s
Environmental Impact Assessment Guide to Climate Change Resilience and Adaptation explains
that in determining significance, account should be taken of the susceptibility or resilience of a
receptor to climate change as well as the value of the receptor. A high value receptor that has
very little resilience to changes in climatic conditions should be considered more likely to be
significantly affected than a high value receptor that is very resilient to changes in climatic
conditions. If there is uncertainty about how a receptor will adapt to a changing climate, then a
precautionary approach should be adopted.
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 373
Approach to Identifying Likely Climate Change Scenarios
16.41 In considering future climate change scenarios, IEMA guidance recommends the use of the UK
Climate Projections Website, which is managed by the Met Office and the Environment
Agency174. ‘Probabilistic’ projections are provided for a range of variables including temperature,
precipitation and sea level rise. Wind speed and storm frequency/ intensity are considered
separately as global modelling information is currently more limited.
16.42 Whilst the current projections175, UKCP09, date back to 2009 and are due to be updated in 2018,
the Climate Projections website states that UKCP09 continues to provide a valid assessment of
the UK’s future climate over land. However, when considering decisions that are sensitive to
projected future changes in summer rainfall, additional information should also be used176.
16.43 The UKCP09 projections for temperature and precipitation are presented for the UK as a whole
and also on a regional basis, with the Revised Scheme located within the South West England
administrative region. The UK projections consider three variables:
(i) Timeframe: the projections are presented for three overlapping time periods (2020s,
2050s and 2080s)177
(ii) Probability: The projections are provided as probability distributions rather than single
values, with figures provided for 10, 50 and 90% probability, in addition to the lowest and
highest projected figures.
(iii) Emission scenario: Three scenarios have been adopted; ‘low’, ‘medium’ and ‘high’
emissions178. All scenarios are considered to be equally plausible.
16.44 Table 16.2 below explains the assumptions made in applying the UKCP09 projections to the
Revised Scheme.
Table 16.2: Assessment assumptions
Variable
Assumptions Rationale
Timeframe 2080s This is considered a realistic timeframe given the design
life of the Project and is consistent with timeframes
adopted elsewhere for the purposes of assessment, such
as in the Flood Risk Assessment (see Chapter 9 and
associated documents).
Probability Probability of 50%
with 10% and 90%
range also provided.
The UK Climate Projections Website states that:
• By providing a range of results rather than single best
estimate values, a clearer picture can be provided
174 http://ukclimateprojections.metoffice.gov.uk/ 175 UKCP09 provides ‘projections’ rather than ‘predictions’ because the results are conditional on certain
assumptions that cannot be quantified, such as the likelihood that an assumed pathway of future emissions of
greenhouse gases will turn out to be correct. 176 From the 5th Coupled Model Inter-comparison Project (CMIP5) archive which informed the most recent
Intergovernmental Panel on Climate Change assessment (Intergovernmental Panel on Climate Change (IPCC) AR5). 177 For example, the ‘2020s’ actually refers to the period 2010-2039 whilst the ‘2020s’ actually refers to the time
period 2070 – 2099. 178 These equate to the IPCC scenarios B1, A1B and A1FI respectively.
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 374
Variable
Assumptions Rationale
regarding the level of confidence in different
outcomes.
• Projections in the 10-90% probability level range
should be used for decision-making. There is limited
confidence in the extreme values beyond these
ranges.
Emission scenario Medium Whilst all three scenarios considered equally plausible,
to provide a ‘balanced and appropriate’ assessment, the
medium scenario has been taken forward.
The Revised Scheme and Consideration of Scope of Climate Change
16.45 Table 16.3 below outlines the consideration to be given to climate change mitigation and
adaptation in the ES and other documentation supporting the planning application, with
reference to the coverage advised in the IEMA guidance documents.
Table 16.3: Scope of climate change factors to be considered in the ES and other supporting
documents
Relevance to
EIA
Coverage required179
Policy
context
Are there relevant sector-specific GHG strategies and targets that should be
recognised by the EIA in addressing GHG emissions?
Are there any local and national climate change adaptation plans?
Baseline with
changing
climate
Confirm climate change parameters adopted for baseline and assessment (time
period/emissions scenario/ probability level selected).
Are there readily identifiable thresholds beyond which the scale of change will
fundamentally alter the baseline (e.g. move from wetland to grassland)?
Review of
alternatives:
Has the review of alternatives considered likely contribution to GHG emissions?
Has the review of alternatives considered resilience to climate change?
Project
Design:
Has climate change mitigation and adaptation been considered as part of the project
design?
Has GHG emission mitigation formed part of the project brief (e.g. reducing the
extent of new build, using low carbon technologies, materials and products and
reducing resource consumption generally)?
Is there an overall judgement on the resilience of the project to climate change - both
change in average conditions and extreme events (e.g. design features and
construction materials).
179 Reflecting advice provided in the two IEMA guidance documents on climate change and EIA.
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 375
Impact
assessment:
What are project impacts on measures to reduce climate change? Are project impacts
worse, the same, less than without climate change?
Will the project alter the baseline and/or ability of receptors to respond to climate
change?
Will the value of the receptor change under the influence of climate change?
Is there a statement on the sensitivity of environmental receptors to climate change
(high/moderate/low sensitivity)?
Will the scale/geographic spread of impact change due to the sensitivity of the
baseline to climate change?
Has an assessment of GHG emissions been undertaken if appropriate (to agreed
methodology)?
Mitigation
and
monitoring:
Are there ’carbon mitigation measures’ (e.g. consideration of energy demand/
management, technology or process improvements, management of transport and
travel demands, planting/ afforestation)?
What measures are required to ensure the project is resilient to climate change and
how will these be monitored?
Are mitigation measures ‘climate proof’?
Is/should carbon management considered in any Environmental Management Plan
proposals?
Summary and
NTS:
IEMA guidance recommends that findings relating to the consideration of climate
change are summarised.
Baseline Conditions with Changing Climate
16.46 Table 16.4 below outlines the projected changes in temperature, precipitation and wind speed
and storms by the 2080s, assuming a medium emissions scenario.
Table16.4: Projected climate change
LXXXVIII. Climat
e Variable
LXXXIX.
Projected Change
Temperature Temperatures in the South-West are projected to increase, with projected
increases in summer temperatures greatest. The central estimate of increase in
winter mean temperature is 2.8ºC; it is very unlikely to be less than 1.6ºC and is
very unlikely to be more than 4.3ºC. The central estimate of increase in summer
mean temperature is 3.9ºC; it is very unlikely to be less than 2.1ºC and is very
unlikely to be more than 6.4ºC.
Precipitation Winter rainfall is projected to increase and summer rainfall is most likely to
decrease. The central estimate of change in winter mean precipitation is 23%; it is
very unlikely to be less than 6% and is very unlikely to be more than 54%. The
central estimate of change in summer mean precipitation is -24%; it is very unlikely
to be more than -50% and is very unlikely to be more than 6%.
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 376
LXXXVIII. Climat
e Variable
LXXXIX.
Projected Change
Central estimates are for heavy rain days (rainfall greater than 25mm) over most
of the lowland UK to increase by a factor of between 2 and 3.5 in winter, and 1 to
2 in summer.
With respect to the continued validity of UKCP09 projections for summer rainfall
(see above), whilst the full range of summer rainfall outcomes from UKCP09 are
considered to remain valid in informing planning decisions, it is possible that there
is a somewhat larger chance of an increase, and a smaller risk of substantial future
reductions in summer rainfall, especially for England and Wales180.
Wind speed
and storms
Whilst there is considerable uncertainty with respect to wind speed, there are
small changes in projected wind speed181. Wind speed in summer is projected to
vary by -0.2 to +0.2ms-1 whilst wind speed in winter is projected to vary by -0.3 to
+0.1ms-1.
There is no evidence within the UKCP09 projections of an increase in the frequency
or intensity of storms across the UK. However, it is important to note that there
are still large uncertainties in the future predictions of storms182
16.47 With respect to the baseline for climate change mitigation, greenhouse gas emissions associated
with the construction and operation of the existing facility have not been quantified. However,
it is noted that whilst a previous application to demolish the existing football stadium and re-
develop the site for housing and community uses has been withdrawn (S.17/0850/OUT), it is
expected that this application will be resubmitted and would be dependent on the replacement
facilities being provided as part of the Revised Scheme.
16.48 With respect to climate change adaptation, all environmental topic area authors were provided
with a summary of the climate change projections and were asked to consider the relevance of
this for their baseline descriptions. It is not considered that baseline conditions will be materially
influenced by the projected climate change for the following assessments:
• Socio-Economics (Chapter 11): it is assumed that, at a national/regional level, appropriate
measures will be put in place to ensure flood risk is managed and does not have long term
impacts on economic activity or human welfare. Temperatures are likely to increase and
this is considered below in relation to the potential for crowd overheating.
• Transport & Access (Chapter 12): it is assumed that, at a national/ regional level,
appropriate measures will be put in place to ensure flood risk is managed and does not
have long term impacts on transport infrastructure. Increased summer temperatures may
cause some disruption and discomfort, although this will be temporary in nature and
should be balanced against the likelihood that freezing conditions in winter will be less
likely.
180 Defra, DECC, Met Office and Environment Agency (April 2016) Is UKCP09 still an appropriate tool for adaptation
planning? Land Projections. 181 Met Office and Environment Agency (November 2010) UKCP09: Probabilistic projections of wind speed. 182 Met Office and Environment Agency (undated) UKCP09: Technical Note on Storm Projections.
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 377
16.49 With respect to Archaeology and Cultural Heritage (Chapter 7), given that there are only small
changes in projected wind speed and that there is no evidence of an increase in the frequency or
intensity of storms, baseline conditions are not anticipated to change materially for above ground
heritage features. The possible exception to this is damage as a consequence of the projected
increase in days with heavy rain.
16.50 With respect to sub-surface features, professional guidance recognises the potential effects of
changes in hydrology upon sub-surface archaeological remains, and particularly water-logged
remains. The Historic England publication ‘Preserving Archaeological Remains: Decision-Taking for
Sites under Development’ (2016) sets out key issues in this regard in Chapter 4 ‘Water Availability
and Stresses’. Superficial geological deposits, particularly palaeoenvironmental deposits, may be
subject to quite localised groundwater conditions, making them sensitive to change. Organic
remains may sometimes be preserved in anaerobic conditions, below localised water tables, with
de-watering occurring not only near-surface, but also in deeper strata. However, as the geology
within the Redline Boundary does not contain superficial geological deposits, and does not have
potential for sealed organic or other palaeoenvironmental remains, the baseline conditions with
respect to sub-surface features are not expected to alter as a consequence of any climate related
changes. The possible exception to this is the exposure of previously undiscovered archaeological
remains through erosion, as a consequence of projected warmer temperatures and/ or an increase
in days with heavy rain.
16.51 With respect to Ecology and Nature Conservation (Chapter 8), Natural England’s ‘Climate Change
Risk Assessment and Adaptation Plan’183 sets out the risks and threats posed by current climate
change projections. In association with the RSPB, Natural England has also published a Climate
Change Adaptation Manual which details the potential effects of climate change on different
habitat types.184
16.52 There are no protected habitats within the Development Footprint, and the majority of the habitat
is lowland neutral agriculturally improved and semi-improved grassland divided by mature
hedgerows. Natural England’s Climate Change Adaptation Manual identifies both lowland
grasslands and hedgerows as having low sensitivity to climate change.
16.53 Increased rainfall and flooding events, coupled with rising temperatures, are also likely to modify
UK flora over time, with shifts in species’ ranges. All bat species will potentially benefit from higher
temperatures and more insect food; although an increase in heavy rain days in summer could
prove detrimental. Milder winters may also cause them to leave their hibernation sites early.
Higher temperatures may also benefit slow worm and grass snake.
16.54 With respect to hydrology, the historic flood records referred to in Chapter 9 identify two isolated
events in the vicinity of the Northern and Southern Site areas, an unknown flood event within the
Development Footprint to the north of the A419, and a flood event from artificial drainage on the
A419. By contrast, a total of 18 flood events are recorded within the area west of the M5
motorway or at the neighbouring Eastington Maintenance Compound.
183 Natural England (2015) Climate Change Risk Assessment and Adaptation Plan (NE612). 184 Natural England (2014) Climate Change Adaptation Manual – Evidence to support nature conservation in a
changing climate (NE546).
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 378
16.55 The modelling of flood risk for the Revised Scheme includes a 25% increase in peak river flows
and a 40% increase in rainfall intensity over a 60 year development design lifetime, in accordance
with the Environment Agency’s Climate Change Allowances Guidance185.
16.56 With respect to the Landscape and Visual Assessment (Chapter 10), the Landscape Institute’s
position statement on climate change186 acknowledges that changes in average temperatures,
precipitation and extreme weather events will have an effect on the landscape. However, whilst
a change in rainfall and rising temperatures are anticipated, it is not considered that this will
appreciably change the baseline landscape conditions.
16.57 With respect to Air Quality and Dust (Chapter 13), the baseline air quality estimated at the Site
does not exceed the relevant air quality objectives for NOx, NO2, PM10 and PM2.5 An increase in
dry and hot weather in summer is expected to lead to an increase in PM10 (dust) concentrations,
particularly re-suspended dust which is coarse in size when compared to vehicle exhaust
particles. With regards to ultrafine particles and gaseous pollutants, their concentrations tend
to be lower because of favourable conditions for dispersion and dilution of their emissions. An
increase in winter rainfall and/or in heavy rain days (rainfall greater than 25mm) could lead to a
possible decrease in pollutant concentrations, with a decrease in summer rainfall leading to a
possible increase in concentrations. However, it is not anticipated that baseline air quality at the
Site will fail to meet relevant air quality objectives as a consequence of projected climate change.
16.58 Given that there are only small changes in projected wind speed and that there is no evidence of
an increase in the frequency or intensity of storms, baseline conditions are not anticipated to
change materially for Major Accidents and Disasters (Chapter 17).
Review of Alternatives
16.59 Chapter 4 provides an outline of the main alternatives considered for the future location of the
Forest Green Rovers Football Club. At the outset, it is important to note that the main driver for
finding a new site is that the existing location cannot accommodate a growing football club in
line with long term sustainability objectives.
16.60 With respect to climate change mitigation, the criteria for reviewing alternatives included access
by public transport. With respect to climate change resilience, Flood Zones 2 and 3 were
removed from the area of the search for the project.
Project Design
16.61 Chapter 4 provides an overview of the project’s design evolution whilst Chapter 5 describes the
development for which planning permission is being sought. Further information is also provided
in the Design and Access Statement which supports the planning application.
16.62 The following measures have been incorporated into the project design to seek to reduce the
generation of greenhouse gases through the production and use of construction materials, and
energy usage:
• The stadium design is predominantly of cross-laminated timber construction, which has a
lower carbon footprint than a stadium constructed of steel and concrete. The limited
185 https://www.gov.uk/guidance/flood-risk-assessments-climate-change-allowances 186 Landscape Institute (2008) Landscape architecture and the challenge of climate change: Position Statement.
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 379
amounts of steel required will have a high recycled content, whilst the concrete will
contain recycled components such as fly ash and furnace slag.
• To avoid resource wastage, the roof support structure aims for minimal material usage,
whilst the sustainable materials strategy will also see the use of locally sourced products.
Consideration will be given to constructing some internal site roads of KWS Infra recycled
‘plastic roads’.
• An aim for internal rooms within the stadium to meet ‘Passivhaus’ standards, which have
excellent thermal performance and air-tightness, with mechanical ventilation to minimise
heating/ energy demand.
• The facility has been designed to ensure the maximum use of natural daylight, limited
use of artificial lighting (both internal and external), and to use both energy efficient
lighting technology (such as the use of LEDs) and sustainable occupant controls to
minimise energy consumption.
• Whilst not included in the current layout, it is intended that a biomass boiler and small
anaerobic digestion plant will be incorporated at the detailed design stage (Reserved
Matters), with a separate planning application submitted if required.
• The design team is also reviewing options for incorporating solar panels into the final
design.
16.63 Natural England’s ‘Climate Change Risk Assessment and Adaptation Plan’187 recognises that
climate change offers opportunities as well as threats. The Plan states, for example, that:
“There is an opportunity to facilitate landscape change in ways that create valuable new
landscapes that are more resilient to climate change and deliver improved benefits for society
(sense of place, biodiversity and other ecosystem services).” (page 10)
16.64 Landscaping is an important component of the project design. This includes the translocation of
existing native species hedgerows and new tree planting to create a ‘parkland’ setting for the
stadium (see RS Appendix 10.7) and RS Figures 10.11c and 10.11d. This will sequester (capture
and store) carbon and also create shade for cooling.
16.65 Ultimately, the aim is that over time the Revised Scheme will be a carbon neutral or carbon
negative development.
Potential Effects
Climate Change Mitigation
16.66 Sources of greenhouse gas emissions associated with the Revised Scheme include the following:
(i) Direct CO2 and NOx emissions from vehicles and plant during construction, operation and
decommissioning;
187 Natural England (2015) Climate Change Risk Assessment and Adaptation Plan (NE612).
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 380
(ii) Indirect emissions arising from the demand for energy produced using fossil fuels (e.g.
electricity for heating, cooling and lighting); and
(iii) ‘Embodied carbon’ in the materials and systems which form temporary and permanent
structures, arising as a result of the extraction and manufacture of materials, fabrication,
transport to site, waste and the future demolition and potential for re-use.
16.67 With respect to the potential for likely significant effects, the following are ’scoped in’ for more
detailed consideration:
(i) Direct CO2 and NOx emissions associated with vehicle movements during the operational
phase;
(ii) Indirect emissions arising from the demand for energy produced using fossil fuels during
the operational phase;
(iii) Embodied carbon in the permanent structures forming part of the Revised Scheme.
Direct Emissions
16.68 Transport accounts for around a quarter of UK greenhouse gas emissions with government policy
seeking to reduce these emissions by promoting public transport choices, supporting the market
for innovative forms of transport and encouraging a move to cleaner and lower carbon
vehicles188. The highest levels of vehicle movements associated with the stadium will occur on
match days, with the transport and access assessment (Chapter 12) assessing a maximum case
of a full 5,000 capacity attendance. For a crowd of 5,000, this suggests a total of 1,694 car
movements one way.
16.69 Mitigation for CO2 and NOx emissions has been identified and included in the project to reduce
overall car movements and encourage alternative modes of transport includes:
• A signal controlled pedestrian and cycle crossing of the A419, with a combined footway /
cycleway on the south side of the A419. This will link to National Cycle Network (NCN)
Route 45 at Grove Lane, which connects eastwards towards Stroud.
• A scheme for improvements to NCN Route 45 from Stonehouse.
• A bus-only connection between the Revised Scheme and Grove Lane to enable buses
serving the West of Stonehouse (WOS) development to serve the stadium.
• A full Park & Ride service from all appropriate locations (such as the railway station and
Nailsworth) on match days.
16.70 Reducing the overall number of vehicle movements will reduce direct CO2 and NOx emissions
associated with the operational phase of the development when compared with the level of
‘unmitigated’ emissions.
Indirect Emissions
16.71 The primary objective is to reduce overall energy demand, which will reduce indirect emissions
arising from energy produced using fossil fuels. The proposed measures are outlined above
188 https://www.gov.uk/government/policies/transport-emissions
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 381
under ‘Project Design’. It is also proposed to incorporate small scale renewable energy
generation into the project (see ‘Project Design’ above).
16.72 Energy use will also be monitored, recorded and reported during both the construction and
operational phases. BREEAM (the Building Research Establishment Environmental Assessment
Method) will be used to ensure that the design measures outlined above under ‘Project Design’
are carried through into the construction phase, with an aspiration for achieving the
‘outstanding’ standard. BREEAM is part of The Code for a Sustainable Built Environment which is
a strategic international framework for the sustainability assessment of the built environment.
The Code defines an integrated approach to the design, construction, management, evaluation
and certification of environmental, social and economic impacts across the full life cycle of the
building projects. It includes consideration of energy performance.
16.73 Reducing overall energy demand and generating energy from renewable sources will reduce
indirect emissions of greenhouse gas emissions when compared to the level of ‘unmitigated’
emissions.
Embodied Carbon
16.74 The stadium design includes a number of measures to reduce embodied carbon. As noted above,
BREEAM (the Building Research Establishment Environmental Assessment Method) will be used
to ensure that the design measures outlined above under ‘Project Design’ are carried through
into the construction phase.
16.75 During construction, a Site Waste Management Plan will also be used to design out waste, reduce
waste generated on site, and implement procedures to sort and reuse/ recycle construction
waste on and off site.
16.76 Incorporating measures to reduce embodied carbon will reduce emissions of greenhouse gas
emissions when compared with the level of ‘unmitigated’ emissions.
Residual Effects
16.77 The level of anticipated greenhouse gas emissions has not been calculated at this stage, as the
detailed design will be secured under future Reserved Matters applications. It is not therefore
possible to compare the GHG profile of the Revised Scheme against the profile of the existing
facility. The applicant is committed to implementing a range of measures to aspire to deliver a
‘carbon neutral’ or ‘carbon negative’ development, and these are outlined in this chapter. This
is considered to accord with the principle of adopting a proportionate approach to assessment
(see IEMA, 2017b), particularly given the level of detailed design information available at this
stage.
16.78 Adopting a precautionary approach to the assessment, it is assumed that the development will
aspire to be ‘carbon neutral’ rather than ‘carbon negative’. On the assumption that a robust and
verified carbon accounting approach is adopted at a later stage, and the Development can aspire
to be constructed and operated as a carbon neutral development, it is considered that the
Revised Scheme will have no significant effects in relation to climate change mitigation.
Climate Change Adaptation
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 382
16.79 Taking account of those receptors identified above, under ‘baseline conditions’, as potentially
susceptible to a changing climate, this section gives further consideration as to whether or not
the Revised Scheme is likely to affect impact judgements and/ or ability to adapt to climate
change in relation to the following:
• Flood risk, hydrology and drainage;
• Ecology and nature conservation;
• Landscape and visual amenity;
• Socio-economics (spectator welfare).
Flood risk, hydrology and drainage
16.80 Chapter 9 explains that in the Severn River Basin District, wetter winters and more rain falling in
wet periods may increase river flooding for rivers and tributaries. More intense rainfall causes
more surface runoff, increasing localised flooding and erosion. In turn, this may increase pressure
on drains, sewers and water quality. Rising river levels may increase local flood risk inland or
away from major rivers because of interactions with drains, sewers and smaller watercourses.
16.81 To reflect the Environment Agency’s Flood Risk Assessments: Climate Change Allowances, an
allowance of a 40% increase in the rainfall intensity values for the period 2060 to 2115 will be
included in the detailed design of the drainage, to ensure that there is no flooding to properties
during high rainfall events.
16.82 Furthermore, the incorporation of SuDS (Sustainable Drainage Systems) infiltration features into
the surface water drainage network will also assist in ensuring adaptation to climate change (see
RS Appendix 9.1). This will include the use of permeable surfaces for all parking areas and
footpaths in addition to other SuDs elements such as swales and ponds.
16.83 Projected climate change is already reflected in the effects. Whilst flood risk receptors are
considered as of high value, measures will be incorporated to help to ensure that there are no
significant effects on the Revised Scheme’s ability to adapt to climate change.
Ecology
16.84 Given the low sensitivity of identified receptors, it is not anticipated that projected climate
change will materially alter predicted effects on habitats. Whilst of higher value, given the
timescale in question and the projected rate of change, it is not anticipated that projected
climate change will materially alter predicted effects on protected species.
16.85 Notwithstanding this, habitat management measures can be introduced to assist habitats and
species adapt to the anticipated change. Such measures form part of the SuDS proposals
(embedded mitigation) for the Revised Scheme, which will be the subject of detailed design at
the Reserved Matters Application stage. This will include details of climate change adaption
measures at this particular location, for example by specifying suitably resilient plant species or
pollinator species suitable for invertebrates shifting their range northward, so as to exploit the
opportunity climate change presents to create valuable new habitats, in accordance with Natural
England Guidance. Ensuring a resilient habitat management plan will help to ensure that there
are no significant effects on the Revised Scheme’s ability to adapt to climate change.
Landscape and visual amenity
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 383
16.86 It is not anticipated that the projected climate change will materially alter predicted landscape
and visual effects. Landscape design measures will be introduced to adapt to the anticipated
change in rainfall and temperature, as outlined in the proposed landscape strategy (RS Appendix
10.7), which will be the subject of detailed design at the Reserved Matters Application stage. As
discussed above under ‘ecology’, this will include details of measures to cope with climate change
at this particular location, for example by specifying suitably resilient plant species, so as to
exploit the opportunity climate change presents to create ‘valuable new landscapes’, in line with
Natural England guidance. Ensuring a resilient landscaping plan will help to ensure that there are
no significant effects on the Revised Scheme’s ability to adapt to climate change.
Socio-economics (spectator welfare)
16.87 Summer temperatures are projected to increase by between is 2.1ºC and 6.4ºC (with a central
estimate of 3.9ºC). To manage the increased risk of potential crowd ‘overheating’, which is only
a potential risk at the start of the football season, measures will include the provision of drinking
water fountains and public announcements encouraging people to remain hydrated and to stay
in the shade if possible. Ensuring adequate measures are in place to respond to potential
spectator heat stress will help to ensure that there are no significant effects on the Revised
Scheme’s ability to adapt to climate change.
Wider Mitigation and Monitoring
16.88 A review of the wider resilience of the mitigation measures which are identified in Chapter 19 in
relation to predicted significant effects has not identified any concerns in relation to their
resilience to climate change, noting that this is already being considered in the SuDs drainage
design and the proposed Green Infrastructure Plan/ landscaping strategy. This also applies to
other enhancement measures identified elsewhere in the ES in relation to non-significant effects.
16.89 With respect to monitoring the Revised Scheme’s resilience to climate change, it is noted that
the UK climate change projections will be updated on a regular basis over the lifetime of the
Revised Scheme, with the next updates due in 2018. These should be reviewed to ensure that
the Revised Scheme remains resilient, with particular attention paid to revised projections for
wind, storms and extreme events, where uncertainty is currently greatest.
Cumulative Effects
16.90 Chapter 2 outlines the list of committed developments which have been identified for
cumulative assessment.
16.91 With respect to climate change mitigation, climate change is, in essence, a cumulative effect and
all greenhouse gas emissions from projects are arguably significant. All the developments listed
in Chapter 2 will involve the generation of direct, indirect and embodied greenhouse gas
emissions during construction and further emissions during operation. It is not possible to
compare the level of these emissions against a ‘baseline’ of those associated with the previous
use of the sites and/ or any existing developments which would be replaced by the committed
developments. It is, however, noted that application 13/0001/INQUIR relates to the
development of an Energy from Waste (EfW) facility, a low carbon technology.
16.92 In accordance with the criteria set out earlier in this chapter, as all emissions are arguably
significant, it is important that all developments include climate change mitigation measures.
Whilst not all of these developments are subject to EIA, and the requirement to consider climate
in EIA is a recent one, all planning applications are subject to review against Local Plan policy
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 384
which states that “Sustainable design and construction will be integral to new development in
Stroud District” (Delivery Policy ES1) and requires consideration of access on foot and bicycle and
public transport (Core Policy CP14). On this basis, it is considered appropriate to assume that
any applications that are consented include ‘reasonable’ measures to avoid, reduce and/or offset
the generation of greenhouse gas emissions.
16.93 With respect to climate change adaption, this is largely a project specific consideration, namely
the resilience of the project in question to climate change and the extent to which projected
climate change could alter the predicted impact judgements. More widely, in relation to
potential interactions with other developments, and following the same logic with respect to
required compliance with planning policy, it is noted that Core Policy CP14: High Quality
Sustainable Development requires all new developments to achieve “no increased risk of flooding
on or off the site, and inclusion of measures to reduce the causes and impacts of flooding as a
consequence of that development” whilst Delivery Policy ES1: Sustainable construction and
design requires the “consideration of climate change adaptation”.
Conclusions
Climate change mitigation
16.94 The applicant is committed to implementing a range of outlined measures to aspire to deliver a
‘carbon neutral’ or ‘carbon negative’ development. Adopting a precautionary approach to the
assessment, it is assumed that the development will be ‘carbon neutral’ rather than ‘carbon
negative’. On the assumption that a robust and verified carbon accounting approach is adopted,
and the Revised Scheme can be constructed and operated as a carbon neutral development, it is
considered that the Revised Scheme will have no significant effects in relation to climate change
mitigation.
Climate change adaptation
16.95 It is not anticipated that the scale of projected climate change identified will fundamentally alter
baseline conditions or the effects included in this ES. It is also not considered that the Revised
Scheme will materially affect the ability of receptors to respond to climate change. Overall, with
the design and mitigation measures proposed, the Revised Scheme is considered to be resilient
to projected climate change. It is therefore considered that the Revised Scheme will have no
significant effects in relation to climate change adaptation.
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 385
17 MAJOR ACCIDENTS AND DISASTERS
Summary
17.1 An assessment has been undertaken of any potentially significant adverse effects on the
environment deriving from the vulnerability of the development to risks of major accidents and/
or disasters.
17.2 As this is an amended application, this EIA has been carried out in accordance with the 2011 EIA
Regulations. However, it should be noted that the 2017 Regulations now contain additional
matters which were not required to be assessed in the 2011 Regulations – which includes an
assessment on Major Accidents and Disasters relevant to the project concerned. As these
matters are clearly important, whilst this ES will be determined in line with the 2011 Regulations,
the additional matters which would have been required under the 2017 Regulations have also
been assessed. The scope of this EIA is explained in more detail within Chapter 2.
17.3 To date, there is no specific guidance on how to consider Major Accidents and Disasters within
the context of EIA. However, the assessment takes account of emerging EIA good practice, which
refers to other relevant documentation, including the Cabinet Office’s National Risk Register of
Civil Emergencies.
17.4 A two-stage tiered scoping process has been adopted for the assessment. Firstly, and in
accordance with emerging EIA practice elsewhere, health and safety matters were excluded from
the assessment as they are covered elsewhere by detailed legislation. Secondly, the use of an
‘Initial Risk Screening List’ ruled out any potential accidents and disasters that are considered to
be highly unlikely to occur in the context of the project, such as earthquakes, wildfires or coastal
flooding. Those major accidents and disasters that could not be screened out formed a further
‘Refined List’ and were subject to more detailed consideration. The Refined List includes, for
example, surface water flooding; hurricanes, storms and gales; extreme temperatures and
pollution incidents.
17.5 Given a number of proposed design and operational measures, which are all considered and
reported in the assessment, it is not anticipated that the Revised Scheme is vulnerable to any
major accidents and/ or disasters which could result in significant effects on the environment.
Introduction
17.6 As major accidents and disasters can potentially result in significant adverse environmental
effects, it is prudent for them to be considered at the planning stage of a development. Through
identifying major accidents and disasters at an early stage, it is possible to prevent such events
from occurring, reduce the risk of this happening, or decrease the extent of their potential harm
in the local area and on local communities.
17.7 The structure of this chapter does not confirm to the typical chapter structure used elsewhere in
this Environmental Statement (ES) as it is recognised that existing legislation and health and
safety requirements already identify risks and help protect human beings and the
environment189. For this chapter to remain proportionate, it is not a full risk assessment in itself.
189 Examples include the Construction Design and Management (CDM) 2015 Regulations; Safety at Sports Grounds
Act 1975; The Fire Safety and Safety Places of Sports Act 1987; and the Guide to Safety at Sports Grounds (Green
Guide) 5th Edition.
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 386
Rather this chapter identifies risks and explains whether or not they are relevant for the Revised
Scheme, and signposts other documentation where these risks have been addressed.
Legislation, Policy and Guidance
17.8 This ES is the output of the EIA process which has been undertaken in accordance with the Town
and Country Planning (Environmental Impact Assessment) Regulations 2011, as amended in 2015
(hereafter referred to as the ‘EIA Regulations’).
17.9 As this is an amended application, this EIA has been carried out in accordance with the 2011 EIA
Regulations. However, it should be noted that the 2017 Regulations now contain additional
matters which were not required to be assessed in the 2011 Regulations – which includes an
assessment on Major Accidents and Disasters relevant to the project concerned. As these
matters are clearly important, whilst this ES will be determined in line with the 2011 Regulations,
the additional matters which would have been required under the 2017 Regulations have also
been assessed. The scope of this EIA is explained in more detail within Chapter 2.
International
17.10 Paragraph 18 of Directive 2014/52/EU190 states:
“In order to ensure a high level of protection of the environment, precautionary actions need to
be taken for certain projects which, because of their vulnerability to major accidents, and/or
natural disasters (such as flooding, sea level rise, or earthquakes) are likely to have significant
adverse effects on the environment. For such projects, it is important to consider their
vulnerability (exposure and resilience) to major accidents and/or disasters, the risk of those
accidents and/or disasters occurring and the implications for the likelihood of significant adverse
effects on the environment.”
National
17.11 The above has been transposed into UK law under Schedule 4 (8) of the 2017 EIA Regulations191
which require:
“A description of the expected significant adverse effects of the development on the
environment deriving from the vulnerability of the development to risks of major accidents
and/or disasters which are relevant to the project concerned”.
17.12 It is worth noting that the UK approach has removed the word ‘natural’. An article written by a
registrant of the EIA Quality Mark Registrant Scheme of Institute of Environmental Management
and Assessment (IEMA) suggests that given the intention underlying this aspect of the 2017
Directive, both manmade and natural disasters should be considered192.
17.13 There is no specific guidance available at present on the assessment of major accidents and
disasters, and as this is a new topic within the realms of EIA, its approach will evolve over time.
190 EU Directive 2014/52EU amending Directive 2011/92/EU on the assessment of the effects of certain public and
private projects on the environment. 191 The Town and Country Planning (Environmental Impact Assessment) Regulations 2017. 192 IEMA (2016) EIA Quality Mark Article: Assessing Risks Of Major Accidents / Disasters In EIA. Available at:
https://www.iema.net/assets/uploads/EIA%20Articles/wsp_assessing_risks_of_major_accidents_disasters_in_eia_
revised.pdf
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 387
However, taking account of emerging EIA practice, and advice from a recent EIA webinar advising
on Major Accidents and Disasters in EIA193, the following have been consulted:
• The Cabinet Office National Risk Register of Civil Emergencies (2017 Edition)194. This
document is the unclassified version of the National Risk Register and it identifies the main
types of civil emergencies that could affect the UK in the next five years. It is recognised,
however, that this document does not provide an all-encompassing list of all potential
accidents and disasters and its timescales are short term.
• The International Federation of Red Cross & Red Crescent Societies Early Warning, Early
Action (2008). This guidance looks to other countries including those in warmer climates,
thereby identifying risks that the UK may encounter in the future in light of climate change
and global warming.
• The International Disaster Database. This online source contains data covering over 22,000
mass disasters in the world since 1900 to the present day and aims to “rationalise decision
making for disaster preparedness, as well as provide an objective base for vulnerability
assessment and priority setting.”
17.14 Using these documents ensures that all potential major accidents and disasters are identified.
Assessment Methodology and Significance Criteria
17.15 This chapter has been written by LUC, an environmental consultancy established over 50 years
ago. LUC’s EIA experience dates back to the 1970s when the concept was first introduced in the
UK and, since this time, the Company has prepared over 100 ESs, across a range of sectors and
undertaken over 100 independent ES reviews on behalf of local authorities. The Company has
also undertaken EIA research projects at the national and European level and has prepared EIA
good practice guidance. LUC has also secured the Institute of Environmental Management and
Assessment (IEMA)’s Quality Mark, which demonstrates the Consultancy’s commitment to best
EIA practice and preparation of ESs to a very high standard. As part of the requirements as EIA
Quality Mark registrants, LUC is required to submit all of their ESs to IEMA for independent
review. LUC is therefore well placed to address the new requirement to consider the potential
for significant adverse effects on the environment deriving from the vulnerability of the
development to relevant risks of major accidents and/or disasters.
17.16 This chapter was authored by Joanna Wright and Katie Norris of LUC. Joanna Wright MA MSc
MIEMA CEnv has an MSc in Environmental Impact Assessment, is a full Member of the Institute
of Environmental Management & Assessment and a Chartered Environmentalist. Joanna is a
Director of Environmental Planning at LUC and has over 24 years of professional EIA experience.
She has led on the integration of the new EIA regulations into LUC’s work, including incorporation
of the new requirement to consider the risk of major accidents and disasters, and spoke earlier
this year at the joint Scottish Government/IEMA conference on the implementation of the new
regulations. Katie Norris BA (Hons) MSc GradIEMA is a Senior Environmental Planner and since
joining LUC in 2015, has contributed to a wide range of EIAs, including mixed use schemes, a
193 IEMA (2017) EIA Quality Mark Webinar: Major Accidents and Natural Disasters in EIA. 13th July 2017. 194 Cabinet Office (2017) National Risk Register Of Civil Emergencies. Available at:
https://www.gov.uk/government/uploads/system/uploads/attachment_data/file/644968/UK_National_Risk_Regis
ter_2017.pdf
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 388
railway reinstatement project (a National Significant Infrastructure Project) and the nearby
reinstatement of the Cotswold Canals Phase 1B: Missing Mile.
Definitions
17.17 Although ‘accident’, ‘risk’ and ‘disaster’ are well known terms and are used in everyday language,
there is potential for their meaning to be interpreted differently. Currently, there are no standard
definitions adopted for EIA. The article written by a registrant of the EIA Quality Mark Registrant
Scheme in 2016 advised that the definition of accidents should be similar to the following:
“man-made and natural risks which are considered to be likely, and are anticipated to
result in substantial harm that the normal functioning of the project is unable to cope
with/ rectify i.e. a significant effect”.
17.18 However, a recent IEMA EIA webinar on Major Accidents and Disasters used definitions taken
from various sources that were already used in previous EIAs, and are, for the purposes of this
chapter, therefore deemed to be appropriate.
17.19 The Oxford English Dictionary defines ‘accident’ as:
“An unfortunate incident that happens unexpectedly and unintentionally, typically resulting in
damage or injury”.
17.20 The International Federation of Red Cross and Red Crescent Societies’ definition of ‘disaster’ is:
“A sudden, calamitous event that seriously disrupts the functioning of a community or society and
causes human, material, and economic or environmental losses that exceed the community’s or
society’s ability to cope using its own resources. Though often caused by nature, disasters can
have human origins”195.
17.21 Risk is defined in this chapter as:
“The product of the likelihood of an event occurring and the severity of the impact.196”
Significant effects
17.22 As the purpose of this chapter is to identify risks that result in ‘significant adverse effects’ this
definition is considered to mean:
“The loss of life or permanent injury, and/or permanent or long lasting damage to an
environmental receptor.197”
17.23 All effects are considered to be adverse. The duration of effects is highlighted in the definition of
‘significant adverse effects’ and is therefore considered within this chapter.
195 International Federation of Red Cross and Red Crescent Societies (no date) What is a disaster? Available at:
http://www.ifrc.org/en/what-we-do/disaster-management/about-disasters/what-is-a-disaster/ 196 Burrohappold Engineering (2016) Resilience Insight. Available at: https://www.burohappold.com/wp-
content/uploads/2016/06/2016-Royal-Charter-International-Research-Award-BuroHappold-Resilience-Insight-12-
Cities-Assessment-v2.pdf 197 IEMA (2017) EIA Quality Mark Webinar: Major Accidents and Natural Disasters in EIA. 13th July 2017.
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 389
17.24 Two categories of effect are identified: ‘significant effects’ or ‘no significant effects’; there are no
degrees of significance identified.
Major Accidents and Disasters Scoped In
17.25 Significant adverse effects have been considered both within and outside the Redline Boundary
of the Revised Scheme.
17.26 In line with Part 1 4 (2) of the EIA Regulations, the chapter considers these receptors:
• Population and human health;
• Biodiversity, with particular attention to species and habitats protected under Directive
92/43/EEC(a) and Directive 2009/147/EC(b);
• Land, soil, water, air and climate;
• Material assets, cultural heritage and the landscape;
• The interaction between the factors of the above.
Major Accidents and Disasters Scoped Out
17.27 Low likelihood and low consequence events, such as minor spills, have been scoped out as these
events are unlikely to result in significant adverse effects as they do not fall into the category of
a major accident or disaster. Highly likely and low consequence events are also scoped out as
they will not lead to significant adverse effects. Furthermore, high likelihood and high
consequence events are also scoped out, as it is assumed that existing legislation and regulatory
controls would not permit the project to be progressed under these circumstances.
17.28 A two stage tiered scoping process has taken place:
• The first component is in accordance with emerging EIA practice elsewhere, whereby
health and safety is scoped out of this chapter as it is covered by detailed legislation. This
includes risks to employees which are covered by the Management of Health and Safety
at Work Regulations 1999, The Workplace (Health, Safety and Welfare) Regulations 1992
and The Reporting of Injuries, Diseases and Dangerous Occurrences Regulations 1995.
Ecotricity has committed to constructing and managing the Revised Scheme in accordance
with, inter alia:
o Health and safety management systems;
o Supplier management health and safety standards;
o Risk management systems;
o Construction and Environmental Management Systems (which are considered
under the planning conditions).
o Similarly, match day crowds are covered under licence.
• The Initial Risk List forms the second component of the scoping process by ruling out any
potential accidents and disasters that are considered to be highly unlikely to occur. This
screening process illustrates that due account has been taken of the full range of potential
accidents, risks and disasters and that the assessment process is fully transparent.
Initial Risk List
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 390
17.29 Based on the sources identified in the Legislation, Policy and Guidance section above, and taking
specific account of the type of development in question (a sports stadium) and its location, Table
17.1 below provides an initial screening list of major accidents and disasters for consideration. It
is important to note that as this covers all risks and disasters on a global scale, some risks will not
be applicable to the Revised Scheme and the justification for a major accident or disaster to be
screened out is explained in the last column of the Initial Risk List. Those major accidents and
disasters that cannot be screened out, and therefore require further consideration in this
Chapter, are considered in the ‘Baseline Conditions’ section below the Initial Risk List and in Table
17.2: The Refined List.
17.30 For the Initial Risk List (Table 17.1), if the major accident or disaster type is not considered a
potential risk for the location of the Revised Scheme, a ‘x’ is indicated under the ‘location risk’
column. Similarly, if the major accident or disaster is not associated with the proposed use of
the development, either at the construction or operational phase, a ‘x’ is indicated. Where all
columns receive a ‘x’, for an identified major accident or disaster, this major accident or disaster
is screened out.
17.31 If the major accident or disaster is considered a potential risk owing to either the location of the
Revised Scheme or its use during construction or operation, a ‘’ is given. If a ‘’ is identified in
either column, or in both columns, the major accident or disaster is screened in and taken to the
next stage, the Refined List (Table 17.2). The Refined List considers whether or not the Revised
Scheme could make the major accident/ disaster worse (in the absence of any mitigation) and
whether or not the Revised Scheme could in turn be affected by the major accident or disaster.
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 391
Table 17.1: The Initial Risk List
Disaster group Disaster sub group Accident/ Disaster type Location
risk
Proposed use risk Is further consideration required?
Construction
risk
Operational
risk
Natural
hazards
Geophysical Earthquakes x x x No – screened out:
Earthquakes do occur in Britain owing to the motion of the Earth’s tectonic plates causing
regional compression. In addition, uplift resulting from the melting of the ice sheets that
covered many parts of Britain thousands of years ago can also cause movement.
Earthquakes experienced in Britain can cause considerable damage to buildings, but the
British Geological Survey (BGS) notes that this is relatively small compared to the devastation
resulting from earthquakes occurring in other parts of the world. Between 1580 and 1940,
11 people have died as a result of earthquakes occurring in Britain (largely as a result of
falling stones, falls from upper floors or shock). However, no deaths related to earthquakes
in the UK have been recorded since 1940.
The BGS acknowledges that on average, a magnitude 4 earthquake happens in Britain
roughly every two years and a magnitude 5 earthquake occurs around every 10 to 20 years.
Their research found that the largest possible magnitude earthquake in the UK is around 6.5.
Smaller magnitude earthquakes can be felt by people and the BGS estimate that between 20
and 30 earthquakes each year occur with a few hundred smaller ones recorded by sensitive
instruments.
According to the BGS, the largest earthquake in Britain occurred in 1931 near the Dogger
Bank, around 60 miles offshore and 345km north east of the Revised Scheme. Due to this
remote location, the magnitude 6.1 earthquake only caused minor damage to buildings on
the east coast of England. The BGS record that one person died in Hull of shock, but this is
uncertain.
The BGS notes that the most damaging earthquake in Britain occurred in 1884 around
Colchester, approximately 225km east of the Revised Scheme, where structural damage such
as collapsed chimneys and cracked walls occurred to approximately 1,200 buildings. The
earthquake’s magnitude was 4.6 and records held by BGS suggest that there were two
fatalities.
In terms of geographic proximity, the closest epicenter of an earthquake to the Revised
Scheme occurred in Hereford in 1896 with a magnitude of 5.3 and is recorded as being the
largest onshore earthquake in England.
As such, the Cabinet Office National Risk Register of Civil Emergencies states that
“Earthquakes in the UK are moderately frequent but rarely result in large amounts of
damage. An earthquake of sufficient intensity (determined on the basis of the earthquake’s
local effect on people and the environment) to inflict severe damage is unlikely.”
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 392
Disaster group Disaster sub group Accident/ Disaster type Location
risk
Proposed use risk Is further consideration required?
Construction
risk
Operational
risk
As earthquakes have not caused any deaths in the UK since 1940, and buildings are damaged
(not devastated) this disaster is screened out.
Volcanic activity x x x No – screened out: Volcanic activity does not occur in the UK and is not linked to the Revised
Scheme.
It is noted that volcanic activity originating in other countries can disrupt air travel, but this is
unlikely to create any significant risk for the Revised Scheme.
Landslides x x x No – screened out: No historical landslides have been recorded within the Redline Boundary
of the Revised Scheme198.
Tsunamis x x x No – screened out: the Revised Scheme is located inland, outside a tsunami risk zone199.
Hydrological Coastal flooding x x x No – screened out: the Revised Scheme is located inland, outside a coastal area.
Fluvial flooding x x x No – screened out: The Development Footprint is not located within or adjacent Flood
Zones 2 or 3 (see RS Figure 9.1).
Surface water flooding x Yes
Avalanches x x x No - screened out: The Revised Scheme’s topography is relatively flat and therefore an
avalanche will not occur.
Climatological
and metrological
Cyclones/ hurricanes/
typhoons, storms and gales x x Yes
Note that hurricanes, typhoons and cyclones are the same weather phenomenon; different
names are used in different parts of the world. Hurricane is the correct term for locations in
the North Atlantic Ocean.
Wave surges x x x No – screened out: the Revised Scheme is located inland, and is therefore not subject to
wave surges.
Extreme temperatures:
• Heatwaves
• Low (sub-zero)
temperature and heavy
snow
x x Yes
Droughts x x Yes
Severe Space Weather: x x Yes
198 British Geological Survey (2017) Geo Index Onshore. Available at: http://mapapps2.bgs.ac.uk/geoindex/home.html 199 Prevention Web (2005) Europe: tsunami hazard map. Available at: http://www.preventionweb.net/english/professional/maps/v.php?id=3831
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 393
Disaster group Disaster sub group Accident/ Disaster type Location
risk
Proposed use risk Is further consideration required?
Construction
risk
Operational
risk
• Solar flares
• Solar energetic particles
• Coronal mass ejections
The exception is solar energetic particles which cause solar radiation storms, but only in
outer space, so this disaster sub-type can be screened out.
Fog x x Yes
Wildfires:
Forest Fire
Brush/bush
Pasture
x x x No – screened out: the Revised Scheme and the surrounding area does not contain
vegetation with a potential high fuel load such as gorse.
Poor Air Quality x x Yes – during the construction phase. No significant effects on local air quality are predicted
during the operational phase.
Biological Disease epidemics:
• Viral
• Bacterial
• Parasitic
• Fungal
• Prion
x x x No - screened out: The Revised Scheme is located in a developed country where the
population is in general good health. Furthermore, the use of the Revised Scheme, a football
stadium, is not going to give rise to any disease epidemics.
Public Health England, the executive agency of the Department of Health, is responsible for
protecting the nation from public health hazards preparing for and responding to public
health emergencies. One of Public Health England’s functions is to protect the public from
infectious disease outbreaks and the Agency has produced a document providing operational
guidance for the management of outbreaks of communicable disease, ‘Communicable
Disease Outbreak Management: Operational Guidance’.
Technological
or man-made
hazards
Complex emergencies:
• Extensive violence and
loss of life;
• Displacements of
populations;
• Widespread damage to
societies and economies;
• The need for large-scale,
multi-faceted
humanitarian assistance;
• The hindrance or
prevention of
humanitarian assistance
x x x No – screened out: The Revised Scheme is located in a developed country that has a steady,
yet small population growth. England is politically stable with no direct border with
countries experiencing conflicts. (However, see also bottom of table)
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 394
Disaster group Disaster sub group Accident/ Disaster type Location
risk
Proposed use risk Is further consideration required?
Construction
risk
Operational
risk
by political and military
constraints;
• Significant security risks
for humanitarian relief
workers in some areas
Famine x x x No – screened out: The Revised Scheme is located in a developed country that produces its
own crops and imports food. It is politically stable and not subject to hyperinflation and
therefore food is available, whether it produced within the UK or imported. Famine is also
not relevant to the use of the Revised Scheme.
Displaced populations x x x No – screened out: The Revised Scheme is located in a developed country that has a steady,
yet small population growth and is politically stable with no direct border with countries
experiencing conflicts. Furthermore, the UK does not lie on any tectonic plate boundary and
has a temperate climate. Displaced populations are also not relevant to the use of the
Revised Scheme.
Industrial accidents x x Yes
Transport accidents x Yes
Pollution accidents x x Yes
Electricity, gas, water supply
or sewage system failures Yes
Acts of Terrorism x x Yes
Urban fires x x x No – screened out: The Revised scheme is not located in an urban area.
Fire within the stadium x Yes
Crowd disasters x x Yes
Football related violence and
disorder x x Yes
Innovative Design of the
Stadium, poor design could
lead to:
• Crowd control issues
• Crowd crushing
incidents
x Yes
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 395
Baseline Conditions
17.32 The Revised Scheme will be constructed on a greenfield site that is in agricultural use. The grass
is managed through grazing and mowing.
Surface Water Flooding
17.33 Historic flood records used in the Baseline Condition’s section of Chapter 9: Hydrology, Flood
Risk and Drainage chapter explain that two events have been recorded in the vicinity of the Site.
Two isolated records are located within the vicinity of both the Northern area (the Revised
Scheme or Development Footprint) and Southern Site area (south of the A419). An unknown
flood event occurred within the Development Footprint to the north of the A419, and a flood
event from artificial drainage occurred on the A419). By contrast, a total of 18 flood events are
mapped by SDC within the area of the Redline Boundary west of the M5, or at the neighbouring
Eastington Maintenance Compound (two surface water records, five artificial drainage records,
one fluvial record and 11 unknown records).
Hurricanes, storms and gales
17.34 Hurricanes cannot form in or around the United Kingdom as the sea temperatures are not warm
enough to sustain a wind of at 120km/h, which is one of the measurements used to classify a
hurricane. However, deep depressions that were originally hurricanes are experienced in the
United Kingdom.
17.35 The weather records from the past two decades taken from the closest available data source to
Stroud200 found that the greatest recorded wind speed was 93km/h201.
Extreme temperatures: Heatwaves, Low (sub-zero) temperature and heavy snow
17.36 According to the weather station at Ross on Wye (the nearest weather station that provides
historic weather data202, approximately 25km northwest to the Revised Scheme), the warmest
recorded temperature between the years of 1930 and 2016 was 26.8°C in 2006, and the coolest
temperature in the same time period was -6.7°C in 1963203. Closer to the Revised Scheme, the
highest daily maximum temperature of 37.1°C was recorded in Cheltenham on 3rd August
1990204. As no other weather stations near to the Revised Scheme have logged the daily
minimum temperature record in the District or country, there is no further comparable data.
200 Location unknown 201 My weather 2 (no date) Local Weather: Stroud Climate History. Available at: http://www.myweather2.com/City-
Town/United-Kingdom/Gloucestershire/Stroud/climate-profile.aspx?month=2 202 Chapter 13: Air Quality and Dust uses the Gloucestershire Airport meteorological monitoring station, however
this does not supply historic metrological data. 203 Met Office (2017) UK climate - Historic station data. Available at:
https://www.metoffice.gov.uk/public/weather/climate-historic/#?tab=climateHistoric 204 Met Office (2017) UK climate – Extremes. Available at: https://www.metoffice.gov.uk/public/weather/climate-
extremes/#?tab=climateExtremes
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 396
17.37 The weather records from the past two decades taken from the closest available data source to
Stroud205 indicate that on average, February is the month with the greatest snowfall with two
days of snow206.
Droughts
17.38 Droughts are caused by insufficient rainfall and in the UK context, a drought is defined as at least
15 consecutive days where there is no more than 0.2mm of precipitation.
17.39 There is no historic record of droughts for the Revised Scheme, however the drought between
the winter of 2009/10 to March 2012 was one of the most substantial droughts of one to two
years duration in the last 100 years. Across southern England, the two-year period April 2010 to
March 2012 was the equal-driest such two year period in records from 1910, shared with April
1995 to March 1997.
17.40 Between April 2010 to March 2012, Stroud only received 65-75% of rainfall compared with the
1981 average207.
Severe Space Weather: Solar flares and Coronal mass ejections
17.41 There is no data for severe space weather specifically at the site of the Revised Scheme.
17.42 The Cabinet Office National Risk Register of Civil Emergencies (2017 Edition)208 notes that a
coronal mass ejection storm caused Global Positioning Systems to malfunction in the UK aviation
sector in 2003. Solar storms recorded between 1921 and 1960 resulted in widespread radio
disruption on railway signalling and switching systems in the UK.
Fog
17.43 According to the Met Office, the historical stations observations do not hold data for fog209.
Poor Air Quality (construction phase)
17.44 According to Chapter 13: Air Quality and Dust, the baseline air quality estimated at the Site does
not exceed the relevant air quality objectives for NOx, NO2, PM10 and PM2.5.
Industrial Accidents
17.45 There are no records of any industrial accidents or disasters located in close proximity to the
Revised Scheme.
Pollution Accidents
205 Location unknown 206 My weather 2 (no date) Local Weather: Stroud Climate History. Available at: http://www.myweather2.com/City-
Town/United-Kingdom/Gloucestershire/Stroud/climate-profile.aspx?month=2 207 Met Office (2013) England and Wales drought 2010 to 2012. Available at:
https://www.metoffice.gov.uk/climate/uk/interesting/2012-drought 208 Cabinet Office (2017) National Risk Register Of Civil Emergencies. Available at:
https://www.gov.uk/government/uploads/system/uploads/attachment_data/file/644968/UK_National_Risk_Regis
ter_2017.pdf 209 Met Office (2016) Historical Station Observations. Available at:
https://www.metoffice.gov.uk/datapoint/product/historical-station-obs
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 397
17.46 According to the central government database, a pollution accident occurred on 19th April 2016.
The location of the incident is not within the Development Footprint, but to the west of the
Redline Boundary.
Transport Accidents
17.47 The Revised Scheme is a greenfield and no traffic accidents have occurred.
Electricity, gas, water supply or sewage system failures
17.48 It is understood that potable water supply and foul drainage services are not currently present
on-site. The nearest foul water drainage and water supply are within close proximity to the Site
at properties directly to the east of the southern parcel of land at Chipmans Platt, and properties
located off Grove Lane adjacent to the Revised Scheme.
Acts of Terrorism
17.49 No acts of terrorism have been recorded at the site.
Fire within the stadium
17.50 There is no stadium currently at the location of the Revised Scheme.
Crowd disasters, football related violence and disorder
17.51 The site of the Revised Scheme does not hold large crowd events.
Innovative Design of the Stadium
17.52 There is no stadium currently at the location of the Revised Scheme.
Design Evolution
17.53 The design of the Revised Scheme continues to be informed by a suite of health and safety
regulations, design codes and other legislation. Adhering to these requirements minimises the
risk of major accidents and disasters from occurring.
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 398
Table 17.1: The Refined List
Refined list Could the Revised
Scheme make the major
accident/ disaster
worse?
Could the use of the Revised Scheme be
affected by the major accident or disaster?
Additional comments, including mitigation Where the major accident/
disaster is addressed in the
ES or other planning
documentation
Residual risks
Surface water
flooding
Yes (in the absence of
embedded mitigation or
further mitigation). The
Revised Scheme is
located on greenfield
land and development
here is likely to increase
impermeable surfaces.
This will lead to increase
surface run off and
increase the risk of
surface water flooding.
Yes – potentially. RS Appendix 9.1: Flood Risk
Assessment uses the 60 year development
design lifetime and explains that the site is at
minimal risk of flooding from surface water at
the western boundary of the Development
Footprint due to the M5 and heavily silted
culvert drain under the A419.
Surface water flooding risk has been designed
into the surface water drainage plan and the
flood risk from surface water will reduce from a
medium to a low risk.
The Design Evolution section of Chapter 9:
Hydrology, Flood Risk and Drainage explains
that:
“The proposed surface water network on the Site
has been designed to ensure exceedance of the
network has been considered and that there is no
flooding of properties during a 1 in 100-year
rainfall event.
A SuDS system will be utilised on Site, and a new
attenuation pond designed as part of the
drainage strategy for the Site.
The development of the Site will be designed to
ensure that any excess surface water during
storm events is contained within the road
network and away from properties and released
to the sewer network as capacity dictates.”
In relation to climate change projections for
2080 using the medium emissions scenario (see
Chapter 16), central estimates are for heavy rain
days (rainfall greater than 25mm) over most of
the lowland UK to increase by a factor of
between 2 and 3.5 in winter, and 1 to 2 in
summer. However, the flood risk assessment
incorporates ‘climate change allowances’ in
accordance with standard practice.
Chapter 9 and associated
appendices: Flood Risk,
Hydrology and Drainage
The low risk
for surface
water
flooding is
not expected
to have
significant
adverse
effects on
receptors.
Hurricanes,
storms and gales
No Yes – Whilst climate change projections for 2080
and the medium emissions scenario do not
suggest an increase in the frequency or intensity
The Met Office and Environment Agency forecast
extreme adverse weather conditions and issue
weather warnings accordingly using the National
The Revised Scheme will be
designed to the best
information available in
Hurricanes,
storms and
gales are
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 399
Refined list Could the Revised
Scheme make the major
accident/ disaster
worse?
Could the use of the Revised Scheme be
affected by the major accident or disaster?
Additional comments, including mitigation Where the major accident/
disaster is addressed in the
ES or other planning
documentation
Residual risks
of storms across the UK, it is important to note
that there are still large uncertainties in the
future predictions of storms. Again, whilst there
are only small changes in projected wind speed,
there is considerable uncertainty with respect to
likely changes in wind speed (Chapter 16).
Severe Weather Warning Service and Flood
Information Service respectively. This
information can be used by the stadium
managers to cancel or postpone matches or any
other activities on site.
relation to hurricanes,
storms and gales whilst also
adhering to the current
design guidelines and
building standards that
have included specialist
input. These will feature in
the design, method and
sustainability statements
and detailed at the
Reserved Matters Stage in
the planning application
process.
Chapter 16: Climate
Change
expected to
have no
significant
adverse risks
on any
receptors.
Extreme
temperatures:
Heatwaves
Low (sub-zero)
temperature and
heavy snow
No Yes - Climate change projections for 2080 using
the medium emissions scenario suggest that
temperatures in the South-West will increase
both in summer and winter months. This is most
likely to be of concern in summer, with an
estimated increase of between 2.1ºC and 6.4ºC.
Conversely, with a projected temperature
increase in winter, heavy snow is likely to occur
less than at present.
These changes are unlikely to cause major
accidents or disasters in relation to the Revised
Scheme.
The Cold Weather Alerts and Heat Health Watch
Service provided by the Met Office and Public
Health England respectively can also be used to
inform stadium managers to cancel or postpone
matches in light of these warnings. These
warnings can also be used to advise fans to wear
appropriate clothing and drink plenty of water.
This is particularly important as the football
season occurs between August and May,
therefore occurring in the height of summer and
depths of winter where fans and players would
be exposed to high and freezing temperatures
respectively.
A significant adverse risk is not expected for
extreme temperatures on any receptors.
The ‘Design and Access
Statement notes that there
will be natural ventilation
entering the stadium
thereby helping to ensure
that crowds are not
exposed to extreme
temperatures.
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 400
Refined list Could the Revised
Scheme make the major
accident/ disaster
worse?
Could the use of the Revised Scheme be
affected by the major accident or disaster?
Additional comments, including mitigation Where the major accident/
disaster is addressed in the
ES or other planning
documentation
Residual risks
Droughts No Yes - Climate change projections for 2080 using
the medium emissions scenario, suggest that
summer rainfall is most likely to decrease.
Droughts already occur in England and parts of
the country are often subject to water
restrictions such as the hose pipe ban in the
summer months. Although this could potentially
disrupt the management of the grass within the
stadium and training pitches as well as
landscaping within the Revised Scheme, it will
not result in the loss of life or permanent injury,
and/or permanent or long lasting damage to a
receptor.
The Revised Scheme is likely to help mitigate the
impact of drought through the inclusion of
rainwater harvesting through the Sustainable
Drainage System (SuDS).
A significant
adverse risk is
not expected
for drought
on any
receptors.
Severe Space
Weather
• Solar flares
• Coronal mass
ejections
No Yes – Space weather can cause electricity
blackouts, loss and disruption of Global
Navigation Satellite Systems and can also disrupt
services including the energy and
communications networks.
The Government has produced a Space Weather
Preparedness Strategy (2015) that sets out three
elements in preparing for space weather;
designing mitigation into infrastructure where
possible; developing the ability to provide alerts
and warnings of space weather and its potential
impacts; and having in place plans to respond to
severe events.
Space weather could result in electrical and
communication blackouts, however these
disruptions are unlikely to give rise to the loss of
life or permanent injury, and/or permanent or
long lasting damage to an environmental
receptor.
The Revised Scheme will be
designed to the best
information available on
blackouts whilst also
adhering to the current
design guidelines and
building standards that
have included specialist
input. These will feature in
the design, method and
sustainability statements
and detailed at the
Reserved Matters Stage in
the planning application
process.
No significant
adverse
effects are
expected in
relation to
space
weather.
Fog No Yes - Fog reduces visibility and this increases risk
for fast moving vehicles such as those travelling
to/from football matches.
When fog is present precautionary approaches
such as warning drivers to slow down are
implemented on roads and announcements
asking drivers to take care after events can also
be adopted as mitigation.
N/A No significant
adverse
effects are
expected in
relation to
fog.
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 401
Refined list Could the Revised
Scheme make the major
accident/ disaster
worse?
Could the use of the Revised Scheme be
affected by the major accident or disaster?
Additional comments, including mitigation Where the major accident/
disaster is addressed in the
ES or other planning
documentation
Residual risks
If the fog was very severe, event organisers may
postpone the match or stop the match if play
had begun.
When taking into account these mitigation
measures, fog is unlikely to result in the loss of
life or permanent injury, and/or permanent or
long lasting damage to an environmental
receptor.
Taking the above into account, a significant
adverse risk is not expected on receptors.
Poor Air Quality
(construction
phase)
Yes –
Chapter 13 Air Quality and
Dust
The CEMP will be included
in the planning conditions.
The
implementati
on of the
mitigation
measures
outlined in
the CEMP will
result in no
significant
residual
effects during
the
construction
phase.
Industrial
accidents
No Yes – The Development footprint lies within
close proximity to:
• the Petroleum Garage (Shell) located
approximately 125m to the east.
• Oldends Lane Industrial Estate located
approximately 500m to the east. This
industrial Estate includes an
automotive supplier, a manufacturer in
precision measurement and probing
The industrial sites and businesses located within
close proximity to the Revised Scheme will have
established their own Health and Safety
measures and procedures to follow if incident
occurs.
Calling the 999 emergency services is a response
measure that will assist with all types of accident
and/or disaster.
N/A
The safety of nuclear power
stations is not the
responsibility of the
developer of the Revised
Scheme.
There are no records of any
industrial accidents or
disasters located in close
No significant
adverse
effects are
expected in
relation to
industrial
disasters.
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 402
Refined list Could the Revised
Scheme make the major
accident/ disaster
worse?
Could the use of the Revised Scheme be
affected by the major accident or disaster?
Additional comments, including mitigation Where the major accident/
disaster is addressed in the
ES or other planning
documentation
Residual risks
equipment, a manufacturer providing
technology for the oil and gas industry
and a research and development
company specialising in industrial
digitalisation.
• Stonehouse Paper and Bag Mill (near
Bridgend) is located approximately
2.4km to the south east.
In addition, the nuclear power stations at Hinkley
Point are located approximately 75km south
west of the Revised Scheme. The three power
stations are in various stages of use:
• Construction for Hinkley Point A
started in 1957 and it began operation
in 1965. In 2000, Hinkley Point A was
shut down and the site entered the
decommissioning phase;
• Construction for Hinkley Point B
started in 1967 and it began operation
in 1976. The decommissioning phase is
likely to start in 2023.
• Although it is not expected to begin
operation until 2023, construction
work began in 2017 for Hinkley Point C.
If there is an incident at one of the nuclear sites
at Hinkley Point, the Revised Scheme could be
affected by radioactive material.
The World Nuclear Association210 states that
“The risk of accidents in nuclear power plants is
low and declining…. the design and operation of
nuclear power plants aims to minimise the
likelihood of accidents, and avoid major human
consequences when they occur”.
proximity to the Revised
Scheme.
Pollution
accidents
Yes – during the
construction phase, a
large spillage of
No During the construction of the revised Scheme, a
Construction and Environmental Management
Plan (CEMP) will be produced and all
Chapter 8: Ecology and
Nature Conservation
A significant
adverse risk is
210 The World Nuclear Organisation (2016) Safety of Nuclear Power Reactors. Available at: http://www.world-nuclear.org/information-library/safety-and-security/safety-of-
plants/safety-of-nuclear-power-reactors.aspx
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 403
Refined list Could the Revised
Scheme make the major
accident/ disaster
worse?
Could the use of the Revised Scheme be
affected by the major accident or disaster?
Additional comments, including mitigation Where the major accident/
disaster is addressed in the
ES or other planning
documentation
Residual risks
materials, particularly
liquids, could result in
significant adverse effects
on environmental
receptors.
Chapter 8: Ecology and
Nature Conservation
notes that there is a very
low potential risk for silt
run- off. It is considered
highly unlikely that any
fine silts, sediments or
chemical contamination
will enter Selbrook or the
River Frome courses or
reach the River Severn
SAC 3km downstream. It
is identified that there
will be no potential
negative effect on Sea
Lamprey, River Lamprey
and Twaite shad.
It is not anticipated that
activities associated with
the Revised Scheme
during the operational
phase would lead to
significant polluting
accidents.
Furthermore, other
polluting activities do not
occur within close
proximity of the site.
construction activities will need to adhere to this
document which will reduce the risk of a major
accident/ disaster occurring.
The CEMP will be included
in the planning conditions.
not expected
on receptors.
Transport
accidents
Yes – The construction
phase of the Revised
No The Transport Assessment concludes that effects
in relation to accidents and safety to road
Chapter 12: Transport and
Access
No significant
adverse
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 404
Refined list Could the Revised
Scheme make the major
accident/ disaster
worse?
Could the use of the Revised Scheme be
affected by the major accident or disaster?
Additional comments, including mitigation Where the major accident/
disaster is addressed in the
ES or other planning
documentation
Residual risks
Scheme will involve
materials and
construction workers
travelling to the site.
Events and facilities that
will be provided by the
Revised Scheme during
the operational phase will
increase the need to
travel which will increase
the risk of transport
accidents.
network users will be negligible during
construction, and minor to negligible during
operation.
effects are
expected on
receptors.
Electricity, gas,
water supply or
sewage system
failures
Yes – during construction
there is potential for an
accident interrupting the
gas/ water/ electrical
supplies.
Yes – A system failure could potentially lead to
significant adverse effects on human health
damage and/or built structures.
The natural environment within and beyond the
Development Footprint could be adversely
affected if chemicals enter watercourses or
contaminate land.
There are a number of response measures in
place (such as emergency contact numbers) that
can deal with any of these failures provided by
the utility provider. In addition, 999 is an
emergency service response that deals with all
accidents and disasters.
These responses reduce potential significant
adverse effects on human receptors and the built
environment.
However, a utility system failure such as a
sewage leak can have long term significant
adverse environmental effects.
Long term significant
adverse effects are on
environmental receptors
are considered in:
Chapter 8: Ecology and
Nature Conservation
Chapter 9: Flood Risk,
Hydrology and Drainage
The mitigation measures
explained in these chapters
will remove the significant
adverse environmental
effects.
No significant
adverse
effects are
expected on
receptors.
Acts of Terrorism Yes - The proposed
scheme will attract large
crowds to the site, into a
relatively confined space.
Yes - The proposed scheme will attract large
crowds to the site which could be vulnerable to
acts of terrorism.
Acts of terrorism are not accidental, they are
organised plots and are a result of human
actions, rather than natural occurrences.
The detailed design of the stadium and site
(during reserved matters) will be undertaken in
full compliance with The Construction (Design
and Management) Regulations 2015.
The Design and Access
Statement
A significant
adverse risk is
not expected
on receptors.
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 405
Refined list Could the Revised
Scheme make the major
accident/ disaster
worse?
Could the use of the Revised Scheme be
affected by the major accident or disaster?
Additional comments, including mitigation Where the major accident/
disaster is addressed in the
ES or other planning
documentation
Residual risks
Acts of terrorism have been screened out as no
significant adverse effects are expected on any
receptor.
Fire within the
stadium
No Yes - The Revised Scheme will attract large
crowds to the site who could become trapped in
the event of a fire if measures such as
extinguishers and sprinkler systems (active
measures) and passive measures such as fire
compartmentation and fire doors are not
implemented in suitable locations.
Under the Safety of Sports Grounds Act 1975,
the stadium is legally required to obtain a safety
certificate from Stroud District Council. This
certificate is unique to each sports ground and
details exits, entrances, means of access, crash
barriers and means of escape in case of fire. It is
an offence for sports grounds not to have a
safety certificate or to not obey the certificate’s
requirements.
The Fire Safety and Safety of Places of Sports Act
1987 and the Guide to Safety at Sports Grounds
(Fifth Edition, Stationery Office, 1997 - also
known as The Green Guide) also detail the safety
measures required at sports grounds. These
documents have been informed by incidents
such as the crowd disaster at the Ibrox Stadium
in 1971, the fire at Bradford football ground in
1985, and the Hillsborough disaster in 1989.
Zaha Hadid Architect’s Concept Design Proposal
for the Revised Scheme discusses the use of
engineered timber in ‘significant elements’ of the
stadium. This type of timber is recognised as
having a resistance to ignition and can be further
enhanced with fire retardant treatments. The
Structural Engineering Consultant statement
asserts that “the steel elements, such as bracing
rods, stabilizing pipes and joint connectors, must
be fire-protected by applying an intumescent
coating system.”
The stadium is considered to be a ‘normal fire
risk’ as it has been calculated that it can be
evacuated in six minutes. The design code states
The Design and Access
Statement
The long term significant
adverse effects on
environmental receptors
can be found in:
Chapter 8: Ecology and
Nature Conservation
Chapter 9: Flood Risk,
Hydrology and Drainage
As the River Frome is
relatively far from the
Development Footprint, the
risks of industrial pollution
or fire retardant chemicals
reaching the River directly
are highly unlikely,
particularly as chemicals
would be directed into the
drains along the A419.
Therefore, there will be no
potential negative effect on
Sea Lamprey,
River Lamprey and Twaite.
The pollution and major
accident pollution plan as
part of the planning
The pollution and major
accident pollution plan
No residual
significant
adverse
effects are
identified.
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 406
Refined list Could the Revised
Scheme make the major
accident/ disaster
worse?
Could the use of the Revised Scheme be
affected by the major accident or disaster?
Additional comments, including mitigation Where the major accident/
disaster is addressed in the
ES or other planning
documentation
Residual risks
that the structure and design of the stadium
were based on a number of design codes
including:
• BS EN 1995-1-2:2004 Eurocode 5: Design of
timber structures – Part 1-2: General –
Structural fire design; and,
• The UK National Annex to Eurocode 5: BS
EN 1995-1-2:2004: Design of timber
structures – Part 1-2: General – Structural
fire design.
Further consideration of fire risk has been
considered at the masterplan stage of the
stadium, with exits being located strategically,
limiting the distances occupants need to travel,
and where necessary, providing a choice of
exists. Dedicated refuge areas have also been
designated for disabled occupants on Level High
risk areas will be segregated from escape routes
and egress routes are designed to minimise
queuing in the concourse areas.
The structure of the building has been sub-
compartmentalised to ensure that fire and
smoke is inhibited from spreading beyond the
source of the fire and the building has a
structural fire resistance of 60 minutes.
The use of fire retardant chemicals when fighting
fire can have long term adverse environmental
effects.
The detailed design of the stadium and site
(during reserved matters) will be undertaken in
full compliance with The Construction (Design
and Management Regulations 2015.
proposed by planning
condition will ensure that if
any toxic substance were to
reach the ditches, it would
be prevented from reaching
the River Frome.
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 407
Refined list Could the Revised
Scheme make the major
accident/ disaster
worse?
Could the use of the Revised Scheme be
affected by the major accident or disaster?
Additional comments, including mitigation Where the major accident/
disaster is addressed in the
ES or other planning
documentation
Residual risks
No significant adverse effects from fire are
expected on human health or the built
environment. However, potentially significant
adverse effects on environmental receptors can
be identified using the source, pathway, receptor
process for fire retardant chemicals. These,
however, have been addressed in Chapter 8:
Ecology and Nature Conservation and Chapter
9: Flood Risk, Hydrology and Drainage. They will
be addressed further at Reserved Matters
Application(s).
Crowd disasters,
football related
violence and
disorder
No Yes – Crowd disasters, football related violence
and disorder are a potential risk within the
Revised Scheme, both within and beyond the
Development Footprint.
The Revised Scheme will attract large crowds (up
to 5,000 people) to the site. However, as
outlined above, the Safety of Sports Grounds Act
1975, The Fire Safety and Safety of Places of
Sports Act 1987 and the Guide to Safety at
Sports Grounds (Fifth Edition, Stationery Office,
1997) also known as The Green Guide, are all
adhered to in the design of this Revised Scheme.
The detailed design of the stadium and site
(during Reserved Matters) will be undertaken in
full compliance with The Construction (Design
and Management Regulations 2015.
There is still a risk of significant adverse effects
on human populations, however this is
addressed and mitigated in Chapter 12:
Transport ES Chapter/ Transport Assessment
(TA) and the Operational Management Plan
which will be drafted at Reserved Matters.
Chapter 12: Transport ES
Chapter/ Transport
Assessment (TA)
A significant
adverse risk is
not expected
on receptors.
Innovative
Design of the
Stadium
No Yes - The Revised Scheme includes a football
stadium that encompasses innovative design.
Previous major accidents and disasters in
stadiums include failures of stand structures,
resulting in crowd crushing.
The structure and design of the stadium adhere
to a number of design codes, thereby ensuring
that all materials and the structural design are
safe.
A significant
adverse risk is
not expected
on receptors.
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 408
Refined list Could the Revised
Scheme make the major
accident/ disaster
worse?
Could the use of the Revised Scheme be
affected by the major accident or disaster?
Additional comments, including mitigation Where the major accident/
disaster is addressed in the
ES or other planning
documentation
Residual risks
The detailed design of the stadium and site
(during Reserved Matters) will be undertaken in
full compliance with The Construction (Design
and Management) Regulations 2015.
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 409
Cumulative Effects
17.54 As this chapter considers low likelihood events, it is unlikely that a major accident or disaster will
occur at one development and at another simultaneously. Furthermore, the developments
considered in the cumulative assessment, as with the Revised Scheme, are regulated by
environmental protection legislation, health and safety regulations and design standards, all of
which are focussed on preventing and/ or mitigating major accidents and disasters.
17.55 Table 17.3 below lists the developments that are identified within the scope of the assessment
of cumulative effects and explains the potential interactions of the Revised Scheme and these
developments.
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 410
Table 17.3: Cumulative Effects
Reference Address Development Status Co-ordinates Distance from site
(km)
Potential interactions Residual effect?
S.14/0810/OUT Land West of
Stonehouse, Nastend
Lane, Nastend,
Stonehouse,
Gloucestershire
A mixed use development comprising up to
1,350 dwellings and 9.3 hectares of
employment land for use classes B1, B2 and
B8; a mixed use local centre comprising use
classes A1, A2, A3, A4, A5, D1, D2 and B1;
primary school, open space and landscaping,
parking and supporting infrastructure and
utilities; and the creation of new vehicular
accesses from Grove Lane, Oldends Lane and
Brunel Way. Reserved Matters ow approved
under S.17/0095/REM.
Application
Permitted
379312, 206558
0.1 This housing development will
result in an increased number of
human receptors that could be
adversely affected by a major
accident or disaster occurring at
the Revised Scheme.
However, as no residual risks are
identified in this chapter, no
significant adverse effects are
likely.
No residual effect is
identified
S.12/0763/FUL Bonds Mill, Unit 27,
Bristol Road, Stonehouse
Demolition of part of an existing warehouse
including a hoist on the adjacent building,
renovation of the remainder as office space
and erection of a two storey extension.
Application
Permitted
379344, 205327 1.51 This development will remove
the risk of industrial and/ or
pollution accidents occurring at
Bonds Mill. However, the office
space could increase the number
of human receptors. However, it
is noted that the use of the
stadium is generally likely to
occur outside office hours.
As no residual risks are identified
in this chapter, no significant
adverse effects are likely.
No residual effect is
identified
S.15/1088/FUL Westend Courtyard,
Grove Lane, Westend,
Stonehouse,
Gloucestershire
Proposed extension to Westend courtyard to
provide 10 additional offices (B1 use).
Application
Permitted
378312, 207018 0.1 The provision of increased office
space could increase the number
of human receptors. However, it
is noted that the use of the
stadium is generally likely to
occur outside office hours.
As no residual risks are identified
in this chapter, no significant
adverse effects are likely.
No residual effect is
identified
N/A Infilled canal to the south
of the Site
Canal restoration and realignment scheme
subject to successful bid funding from
Cotswold Canals Trust
No
planning
history,
however
Scoping
Opinion
soon to be
requested.
Directly to the
south of
Redline
Boundary.
Directly to the south
of Redline Boundary.
The reinstatement of the canal
will increase a number of both
human and environmental
receptors within close proximity
to the Revised Scheme.
However, users of the canal are
unlikely to increase the risk of a
major accident or disaster or
increase the risk of a major
No residual effect is
identified
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 411
accident or disaster occurring at
the Revised Scheme.
As no residual risks are identified
in this chapter, no significant
adverse effects are likely.
13/0001/INQUIR Land at Javelin Park Proposed Development of an Energy from
Waste (EfW) facility for the combustion of
non-hazardous waste and the generation of
energy
Appeal
Allowed
380040, 210430 3.92 The provision of this
development could increase the
risk of an industrial and/ or
pollution accident occurring in
relative close proximity to the
Revised Scheme. This EfW
development will however
contain its own pollution and
accident management plans so
any risks will be mitigated.
As no residual risks are identified
in this chapter, no significant
adverse effects are likely.
No residual effect is
identified
S.15/2089/OUT Land Adjacent To
Eastington Trading Estate
Churchend, Eastington,
Gloucestershire.
Erection of three industrial employment
buildings with associated access, car parking
and service yards (Outline application - Access,
Layout and Scale included).
Application
Permitted
TBC 0.1 The provision of increased office
space could increase the number
of human receptors. However, it
is noted that the use of the
stadium is generally likely to
occur outside office hours.
As no residual risks are identified
in this chapter, no significant
adverse effects are likely.
No residual effect is
identified
S.17/0563/OUT Land Off School Lane,
Whitminster,
Gloucestershire
Residential development for up to 60
dwellings including infrastructure, ancillary
facilities, open space and landscaping.
Construction of a new vehicular access from
School Lane.
Application
Refused
377106, 208403 3.0 This housing development will
result in an increased number of
human receptors that could be
adversely affected by a major
accident or disaster occurring at
the Revised Scheme.
However, as no residual risks are
identified in this chapter, no
significant adverse effects are
likely.
No residual effect is
identified
S.17/1133/FUL Former Standish Hospital
and Former Westridge
Hospital Standish,
Stonehouse,
Gloucestershire
Conversion and refurbishment of the former
Standish Hospital complex, including Standish
House (Building A), Stable Block (Building B),
Ward Blocks (Buildings C & G), Standish Lodge
(Building L), Building I, and demolition and
works to associated out-buildings and
Pending
Considerati
on
381646, 206566 3.5 This housing development will
result in an increased number of
human receptors that could be
adversely affected by a major
accident or disaster occurring at
the Revised Scheme.
No residual effect is
identified
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 412
gatehouse to form 50 dwellings; demolition of
Westridge Hospital and associated building.
Development of 98 new build homes within
the grounds; conversion; associated surface
vehicle and cycle car parking, pedestrian and
vehicular access and associated ancillary
development, landscaping, ancillary storage
and plant and ecological bat housing; and all
associated engineering works and operations
However as no residual risks are
identified in this chapter, no
significant adverse effects are
likely.
S.16/0922/REM Land Adjoining Station
Road Bristol Road,
Stonehouse,
Gloucestershire, GL10
3RB
Approval of Reserved Matters Appearance
and Landscaping from appeal
APP/C1625/A/13/2195656 (S.12/2538/OUT) -
residential development for 49 units, new
access way and associated works.
Application
Permitted
This residential development will
result in an increased number of
human receptors that could be
adversely affected by a major
accident or disaster occurring at
the Revised Scheme.
However, as no residual risks are
identified in this chapter, no
significant adverse effects are
likely.
No residual effect is
identified
S.17/2331/OUT
Land Adjoining Oldbury
Lodge Pike Lock Lane
Eastington
Gloucestershire
Erection of new buildings for uses within use
class C1 (Hotel) up to 1,908 Sqm (56 Beds), and
use classes A3 / A4 Pub (Pub/Restaurant) up
to 711 Sqm (Including ancillary manager's
apartment) and associated access, servicing,
parking, drainage and landscaping (outline
application: all matters reserved except for
access and scale)
Awaiting
Decision
This housing development will
result in an increased number of
human receptors that could be
adversely affected by a major
accident or disaster occurring at
the Revised Scheme.
No residual effect is
identified
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 413
Conclusions
17.56 This chapter has sought to identify all potential major accidents and disasters, and using a
screening process, has eliminated a number that are not relevant to the Revised Scheme. Those
major accidents and disasters that are considered as a potential risk have all been considered in
the ES or with other documents that are submitted for this application. It is not anticipated that
the Revised Scheme is vulnerable to major accidents and/or natural disasters which could result
in significant effects on the environment.
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 414
18 CUMULATIVE EFFECTS
Introduction
18.1 This chapter summarises the cumulative effects associated with the Revised Scheme. There is a
requirement to undertake an assessment of cumulative effects of the Revised Scheme through
Schedule 4 of the EIA Regulations 2011. At present, there is no widely accepted methodology or
best practice for the assessment of cumulative effects although there are a number of guidance
documents available. The following approach is based on previous experience, the types of
receptors being assessed, the nature of the Revised Scheme and the environmental information
available to inform the assessment.
18.2 Cumulative effects have been considered within each of the technical assessments. In
consultation with SDC, Table 2.5 lists the committed developments that have been identified as
part of this assessment, and RS Figure 18.1 illustrates the locations of these sites. In this list Land
West of Stonehouse (S.14/0810/OUT) now forms a strategic site allocation within the recently
adopted SDC Local Plan, and it has also recently been subject to a successful Reserved Matters
application allowing the development to commence. Each consultant has reviewed the
respective ES chapters of the planning submission to ensure any cumulative effect has been fully
assessed within the respective technical chapters.
18.3 For the assessment of transport effects, as detailed within Chapter 12 – Transport and Access, a
different approach has been adopted, in that Land West of Stonehouse has formed part of the
baseline rather than being treated as a cumulative effect. This is because all the traffic modelling
has included West of Stonehouse (and associated A419 junction improvements) as part of the
baseline traffic flows in order to assess worst case. Given the allocation of the site within SDC’s
Local Plan and near certain likelihood of development, together with the fact that access is not a
Reserved Matter at the Revised Scheme, this is considered the correct approach.
18.4 Traffic generated by the remaining developments (other than West of Stonehouse) identified in
Table 2.5 is taken into account through the application of traffic growth factors obtained from
the National Transport Model adjusted using the TEMPRO program, which also factors in changes
in car ownership, and local planning forecasts regarding housing and employment. Given Chapter
13 – Air Quality and Dust and Chapter 15 – Noise and Vibration utilise the data from the traffic
assessment, these chapters have also included Land West of Stonehouse, the A419 junction
improvements, and the committed developments as part of the baseline to their assessments.
18.5 The following Chapter provides a summary of the potential cumulative effects already described
in each Technical Chapter. It highlights where and how other committed development may alter
and influence the potential effects from the Revised Scheme, and indicates whether these effects
are considered to be significant or not, so that they may be taken fully into account by the
planning determination process.
Effects Interactions
18.6 The approach to the assessment of different environmental features considers the changes in
baseline conditions at key common sensitive receptors. The key common sensitive receptors
considered within this chapter are those which are assessed within two or more of the Technical
Chapters 7 – 17.
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 415
18.7 Common sensitive receptors identified throughout the ES are outlined within matrices alongside
their residual effects per technical discipline. The common receptors assessed are:
• Existing residential properties (including schools, care homes and William Morris College);
• Local Population (comprising existing and future users of the local road and footpath
network, third parties and local economic, housing and community receptors);
• Ecological receptors (including designated sites and protected species);
• Designated landscape and heritage assets.
18.8 An overall assessment of the cumulative effect on the common sensitive receptors identified
above has been made using professional judgement as well as through the utilisation of
recognised industry standards with regards to the technical assessments provided in Chapters 7
– 17.
18.9 Table 18.1 comprises a summary matrix showing the effect interactions between environmental
topics assessed following the implementation of the recommended mitigation measures set out
in Technical Chapters 7 – 17 of this ES. This enables a summary assessment of the interactions
of residual effects outlining the overall significance to the identified common sensitive receptors.
18.10 For the purposes of this assessment, residual effects that have been identified in the Technical
Chapters 7-17 which do not affect the common sensitive receptors identified above have not
been presented below as no effect interactions are anticipated. In addition, negligible residual
effects have not been considered during the assessment of interactions.
18.11 The effects listed in Table 18.1 are all based on worst-case assumptions, and cover both
construction and operation phases. Effects will vary depending on the particular activity, location
of works, duration of work and type of operation being undertaken. Similarly, the effects vary
from temporary in nature during construction and permanent in nature during operation. The
significant residual effects in the table are reliant on the mitigation measures being implemented
as discussed within the respective Technical Chapters 7 – 17.
Table 18.1: Matrix of Effects Interactions
Technical
Topic
Common Sensitive Receptors
Existing
residential
properties
Local Population
Ecological receptors
Designated heritage
assets
Archaeology
and Cultural
Heritage
N/A N/A N/A Lower end of less
than substantial harm
but no residual
significant effects.
Ecology and
Nature
Conservation
N/A N/A Negligible to high
negative effects but no
significant residual
effects.
N/A
Hydrology,
Flood Risk and
Drainage
N/A N/A Moderate positive
long-term significant
effects.
N/A
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 416
Technical
Topic
Common Sensitive Receptors
Existing
residential
properties
Local Population
Ecological receptors
Designated heritage
assets
Landscape
and Visual
Minor to major
negative long-
term effects some
of which are
significant
adverse residual
effects.
Minor to major
negative long-
term effects
some of which
are significant
adverse residual
effects.
N/A N/A
Socio-
Economics
N/A Minor beneficial
effects but no
significant
residential
effects.
N/A N/A
Transport and
Access
N/A Moderate
infrequent but
long-term
negative to
moderate long-
term positive
effects which are
significant
residual effects.
N/A N/A
Air Quality Low to medium
negative effects
but no significant
residual effects.
Low to medium
negative effects
but no significant
residual effects.
N/A N/A
Lighting Significant
infrequent but
long-term
adverse residual
effects.
Significant
infrequent but
long-term
adverse residual
effects.
Significant infrequent
but long-term adverse
residual effects.
Significant
infrequent but long-
term adverse
residual effects.
Noise
Minor negative
effects but no
residual
significant effects.
Minor negative
effects but no
residual
significant
effects.
N/A N/A
Climate
Change
No residual
significant effects
identified in
relation to climate
change mitigation
or climate change
adaption
No residual
significant
effects identified
in relation to
climate change
mitigation or
climate change
adaption
No residual significant
effects identified in
relation to climate
change mitigation or
climate change
adaption
No residual
significant effects
identified in relation
to climate change
mitigation or climate
change adaption
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 417
Technical
Topic
Common Sensitive Receptors
Existing
residential
properties
Local Population
Ecological receptors
Designated heritage
assets
Major
Accidents and
Disasters
No residual
significant effects
identified
No residual
significant
effects identified
No residual significant
effects identified
No residual
significant effects
identified
18.12 In summary, the effects associated with existing residential receptors vary from minor to major
negative. The latter arises from the assessment of landscape and visual effects, which constitute
a significant adverse long-term residual effect, for a small number of residential properties
located adjacent to the Site. Specifically, the visual amenity of Mole Cottage, Ivy Cottage and
Westend House are likely to experience significant adverse change in the long term due to
relatively unrestricted visibility of the Revised Scheme (or part of) at close range. Additionally,
the Revised Scheme will introduce an addition to the existing sky glow when the stadium lighting
is in operation (i.e. during evening matches). The increase in sky glow has been identified as a
major adverse effect and therefore significant in EIA terms, although this will be infrequent.
During the 2017-18 season, there are six weekday evening matches programmed when sky glow
effects would be most apparent.
18.13 The local population is anticipated to experience a range of effects ranging from major negative
to moderate positive, both of which would result in long-term residual significant effects. Again,
like residential receptors, major negative effects are anticipated in relation to landscape and
visual from short stretches of Eastington Footpath Nos 37 and 38 crossing the Development
Footprint due to relatively unrestricted visibility of the Revised Scheme (or part of) at close range.
Significant visual effects are also predicted to arise on short stretches of public highway adjacent
to the Site including the M5 motorway, the A419 and Grove Lane. With regards to transport
effects, on non-match days, pedestrians and cyclists could experience a moderate long-term
positive effect as a result of the introduction of the traffic signal controlled crossing of the A419
and improvements at Chipmans Platt roundabout. Like residential receptors, significant long-
term effects are anticipated in relation to sky glow, however, this effect would be infrequent.
18.14 In relation to ecological receptors, substantial negative and moderate positive effects are
anticipated. The substantial negative effects are however considered not to be significant when
mitigation is taken into account. Moderate long-term positive effects are anticipated in relation
to hydrology following the incorporation of the SuDS infiltration features into the surface water
drainage network, as these will provide beneficial ecological and conservation effects. The SuDS
features will introduce attractive planting features, and increased biodiversity whilst helping to
ensuring adaptation to climate change. These will be a significant positive residual effect. The
Revised Scheme will introduce an addition to the existing sky glow when the stadium lighting is
in operation (i.e. during evening matches). The increase in sky glow has been identified as a long-
term major adverse effect and therefore significant in EIA terms, although this will be infrequent.
18.15 With regards to designated assets, the lower end of less than substantial harm is anticipated.
These relate to the effect on the Grade II listed Westend Farmhouse and Mulgrove, both on
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 418
Grove Lane, but will not comprise a significant heritage effect in EIA terms. Sky glow will be a
long-term negative significant, this effect is infrequent.
Cumulative Effects from other Committed Developments
18.16 An assessment of the effects from other developments in proximity to the Revised Scheme has
been provided for each of the technical assessments within Chapter 7 – 17 of the ES. Table 18.2
provides a summary of the likely potential cumulative effects that may result from the
construction and operation of the Revised Scheme, in combination with the other committed
developments described in Table 5.2.
Table 18.2: Summary of Likely Potential Cumulative Effects from other Committed Developments
Environmental
Topics
Potential Cumulative Effects
Construction Phase Operational Phase
Archaeology
and Cultural
Heritage
No significant cumulative effects
are anticipated.
No significant cumulative effects are
anticipated.
Ecology and
Nature
Conservation
No significant cumulative effects
are anticipated.
No significant cumulative effects are
anticipated.
Flood Risk,
Hydrology and
Water
Resource
Pre-mitigation, minor to moderate
negative significant effects are
anticipated if West of Stonehouse
and the Revised Scheme are
constructed at the same time,
therefore if left unmitigated it will
be considered significant in EIA
terms.
Following mitigation if both
developments are constructed
simultaneously - negligible
cumulative effects are expected and
therefore it will not be significant in
EIA terms.
No significant cumulative effects are
anticipated as there is hydrological
separation.
Landscape and
Visual Significant additional, adverse cumulative landscape and visual effects
attributable to the Revised Scheme are predicted to arise during
construction up to Year 1 of operation within approximately 0.5km of the
Development Footprint in the general vicinity of Grove Lane from Westend
to Chipmans Platt. These short term, additional cumulative effects will result
from the combined and sequential visibility of the proposal in conjunction
with WOS and Pike Lock cumulative schemes.
The adverse cumulative effects will reduce over time as the proposed
landscape mitigation establishes and matures. Significant additional,
adverse residual cumulative landscape character effects are predicted to
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 419
Environmental
Topics
Potential Cumulative Effects
Construction Phase Operational Phase
remain during operation with respect to a small area of the Escarpment
Footslopes (LCT5a) on and adjacent to the Development Footprint.
However, other cumulative landscape and visual effects predicted to be
significant during construction will be not significant during operation in the
medium to long term.
Adverse cumulative effects potentially arising across the wider Study Area in
conjunction with these and other cumulative schemes assessed and shown
in RS Figure 18.1 are predicted to be not significant.
Socio-
Economics
All of the proposed schemes will
create some temporary
construction employment, however
these effects have only been
quantified in two of the planning
applications for projects. These
were West of Stonehouse
(S.14/0810/OUT) which is
estimated to create 2,025 direct
person years of employment over a
ten-year construction period
(average of 202 jobs per annum),
and Land at Javelin Park
(13/0001/INQUIR) which is
estimated to create 300 jobs over a
three-year construction period. In
both cases, it is understood that
work has now commenced on these
sites. The other proposed
developments are smaller in scale
and therefore likely to create fewer
temporary jobs. They are also likely
to be built out over different time
periods, meaning any increase in
construction employment may
occur at different points in time and
thus not be cumulative. It is also
possible that a number of the
contracts are secured by firms
which are not based in Stroud
District, meaning some of the
economic benefits will be lost to the
area. With these caveats in mind,
the sensitivity of receptor and
No significant cumulative effects are
anticipated.
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 420
Environmental
Topics
Potential Cumulative Effects
Construction Phase Operational Phase
magnitude of effect are both
considered to be medium, meaning
the significance of effect is
moderate beneficial, which is
significant in EIA terms.
Transport and
Access
There is the potential for the
Revised Scheme, the land West of
Stonehouse and the A419 Corridor
Improvements to be under
construction simultaneously. In
such an eventuality, traffic
management will be dealt with via
the Construction Traffic
Management Plan and necessary
legal agreements for each of the
respective developments to ensure
no significant cumulative effects.
The traffic data applied to the model
takes account of all committed
developments as part of the baseline
assessment. Cumulative effects have
therefore already been incorporated
- and mitigated where necessary - as
part of the assessment. The access to
the Revised Scheme has been
designed to accommodate the future
modelled traffic flows allowing for
committed developments. There are
therefore no further cumulative
effects to be taken into account
during operation.
Air Quality Due to the separation distance
between the Revised Scheme site
and the other committed
developments nearby and also due
to different traffic routes, it is not
considered likely that cumulative
effects during the construction
phase are significant. Furthermore,
the potential effects of this
development during the
construction phase will be
temporary i.e. only during the
construction and demolition period.
The estimated number of car and
HGV movements from the Revised
Scheme are 260 and 100,
respectively. The cumulative effect
of construction traffic was not
assessed within the scope of this
report. However, construction
traffic is localised to the roads
nearby the Revised Scheme.
With regards to nearby residential
receptors, there is potential for a
The air quality assessment has taken
into consideration the cumulative
effects, as the traffic data applied to
the model takes account of all
committed developments. No
additional cumulative effects are
anticipated.
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 421
Environmental
Topics
Potential Cumulative Effects
Construction Phase Operational Phase
significant effect as a result of dust
soiling during the construction
phase if the Revised Scheme
construction activities occur at the
same time as the Land West of
Stonehouse development. In such
an eventuality, traffic management
would be dealt with via the Dust
Management Plan and necessary
legal agreements for each of the
respective developments. This will
ensure no significant effect. The
same assessment will apply when
considering both the effect on
human health and ecology.
Lighting West of Stonehouse is located
approximately 23m from the
Redline Boundary of the Revised
Scheme. There is potential for
cumulative effects if both
developments are constructed
simultaneously. In such an
eventuality, construction lighting
effect would be dealt with via the
Construction Environmental
Management Plan and necessary
legal agreements for each of the
respective developments. This
would ensure no significant effect.
No significant cumulative effects are
anticipated.
Noise No significant cumulative effects
are anticipated.
The cumulative effects of the Revised
Scheme in terms of noise effects are
restricted to the long-term effects in
changing road traffic levels. The noise
assessment has taken into account
cumulative effects as the traffic
model considers all committed
developments. No significant
cumulative effects are anticipated.
Major
Accidents and
Disasters
No significant cumulative effects
are anticipated.
No significant cumulative effects are
anticipated.
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 422
Environmental
Topics
Potential Cumulative Effects
Construction Phase Operational Phase
Climate
Change
With respect to climate change mitigation, climate change is, in essence, a
cumulative effect and all greenhouse gas emissions from projects are
arguably significant. All the developments considered in this chapter will
involve the generation of direct, indirect and embodied greenhouse gas
emissions during construction and further emissions during operation, albeit
it is not possible to compare the level of these emissions against a ‘baseline’
of those associated with the previous use of the sites and/or any existing
developments which would be replaced by the committed developments. It
is, however, noted that application 13/0001/INQUIR relates to the
development of an Energy from Waste (EfW) facility, a low carbon
technology.
As all emissions are arguably significant, it is important that all
developments include climate change mitigation measures. Whilst not all
of these developments are subject to EIA, and the requirement to consider
climate in EIA is a recent one, all planning applications are subject to review
against Local Plan policy which states that “Sustainable design and
construction will be integral to new development in Stroud District” (Delivery
Policy ES1) and requires consideration of access on foot and bicycle and
public transport (Core Policy CP14). On this basis, it is considered
appropriate to assume that any applications that are consented include
‘reasonable’ measures to avoid, reduce and /or offset the generation of
greenhouse gas emissions.
With respect to climate change adaption, this is largely a project specific
consideration, namely the resilience of the project in question to climate
change, and the extent to which projected climate change could alter the
predicted impact judgements. More widely, in relation to potential
interactions with other developments, and following the same logic with
respect to required compliance with planning policy, it is noted that Core
Policy CP14: High Quality Sustainable Development requires all new
developments to achieve “no increased risk of flooding on or off the site, and
inclusion of measures to reduce the causes and impacts of flooding as a
consequence of that development” whilst Delivery Policy ES1: Sustainable
construction and design requires the “consideration of climate change
adaptation”. On this basis, again, it is considered appropriate to assume
that any applications that are consented include measures to ensure their
resilience to climate change.
18.17 In summary, based on Table 18.2, significant cumulative effects from different developments are
anticipated from:
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 423
• Landscape and Visual: Significant additional, adverse cumulative landscape and visual
effects attributable to the Revised Scheme are predicted to arise during construction up
to Year 1 of operation within approximately 0.5km of the Development Footprint in the
general vicinity of Grove Lane from Westend to Chipmans Platt. These short term,
additional cumulative effects will result from the combined and sequential visibility of the
proposal in conjunction with West of Stonehouse and Pike Lock cumulative schemes. The
adverse cumulative effects will reduce over time as the proposed landscape mitigation
establishes and matures.
• Landscape and Visual: Significant additional, adverse residual cumulative landscape
character effects are predicted to remain during operation with respect to a small area of
the Escarpment Footslopes (LCT5a) on and adjacent to the Development Footprint.
However, other cumulative landscape and visual effects predicted to be significant during
construction will be not significant during operation in the medium to long term.
• Socio-Economics: In relation to construction sector jobs, a significant, moderate, medium
term beneficial effect has been identified.
• Climate Change: With respect to climate change mitigation, climate change is, in essence,
a cumulative effect and all greenhouse gas emissions from projects are arguably
significant. However, it is considered appropriate to assume that any applications that are
consented include ‘reasonable’ measures to avoid, reduce and/or offset the generation of
greenhouse gas emissions.
Conclusion
18.18 This chapter has summarised the effect interactions and cumulative effects anticipated by the
Revised Scheme in relation to effects from different environmental features and effects from
different committed developments respectively.
18.19 With regards to cumulative effects from different environmental features, existing residential
properties and the local population of the common receptors included within Table 18.1 are
anticipated to be affected by more than one significant effect from different environmental
features from the technical assessments undertaken as part of this ES.
18.20 With regards to cumulative effects from different committed developments, negative significant
cumulative effects are anticipated in relation to landscape and visual receptors within 500m and
small areas of the Enscarpment Footslopes (LCT5a) from both the Revised Scheme, West of
Stonehouse and Pike Lock. However, positive significant cumulative effects are anticipated in
relation to socio-economics and the creation of construction jobs. With regards to climate
change, all greenhouse gas emissions are arguably significant, however, any application
considered should include ‘reasonable’ measures to avoid, reduce and/or offset the generations
of greenhouse gas emissions.
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 424
19 SUMMARY AND STATEMENT OF SIGNIFICANCE
Introduction
19.1 This summary chapter brings together a summary of the significant effects for each of the
Technical Chapters of the ES. The respective Technical Chapters (other than Chapter 16 –
Climate Change and Chapter 17 – Major Accidents and Disasters) provide a Summary of Effects
and Mitigation table at the end of the chapter. These can be found in the following locations:
• Chapter 7 – Archaeology and Cultural Heritage (Table 7.7)
• Chapter 8 – Ecology and Nature Conservation (Table 8.10)
• Chapter 9 – Hydrology, Flood Risk and Drainage (Table 9.8 and 9.9)
• Chapter 10 – Landscape and Visual (Table 10.9)
• Chapter 11 – Socio-Economics (Table 11.7)
• Chapter 12 – Transport and Access (Table 12.13)
• Chapter 13 – Air Quality (Table 13.21)
• Chapter 14 – Lighting (Table 14.6)
• Chapter 15 – Noise (Table 15.20)
19.2 Table 19.1 (located at the end of this chapter) combines the residual significant effects of these
into a single table, detailing any mitigation measures. No residual significant effects (either
positive or negative), following the implementation of all identified mitigation, are anticipated in
relation Archaeology and Cultural Heritage (Chapter 7), Ecology and Nature Conservation
(Chapter 8), Socio-Economics (Chapter 11), Air Quality and Dust (Chapter 13), Noise and
Vibration (Chapter 15), Climate Change (Chapter 16) and Major Accidents and Disasters (Chapter
17). Therefore, these are not included within Table 19.1.
Statement of Significance
19.3 In terms of the assessments undertaken as part of the ES, significant effects are anticipated in
relation to the following technical assessments (full details are included in Table 19.1).
• Flood Risk, Hydrology and Drainage: Significant positive effects associated with
biodiversity and conservation.
• Landscape and Visual: Significant adverse effects are anticipated on a small area of
landscape and a limited number of visual receptors located on and/ or immediately
surrounding the Site within approximately 250m of the Development Footprint (500m for
cumulative effects).
• Transport and Access: During construction, the users of Footpaths Eastington 37 and 38
will experience a moderate, negative but medium term / temporary effects in terms of
severance, pedestrian delay, pedestrian amenity, fear and intimidation. During operation,
there could also be a moderate negative effect in terms of severance, amenity, delay and
fear and intimidation to users of PROW Footpaths Eastington 37 and 38, and National
Cycle Route 45 before and after a match. Although significant, this effect will be
infrequent. On non-match days, pedestrians and cyclists on these routes could experience
a moderate positive effect as a result of the introduction of the traffic signal controlled
crossing of the A419 and improvements at Chipmans Platt roundabout. The traffic
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 425
modelling indicates that during operation on a moderate negative effect on journey times
is experienced by existing road users on the A419 corridor between the A38 and
Horsetrough roundabout during the match arrival and departure periods on a Saturday
and during the weekday evening match arrival period. On non-match days, drivers could
experience a moderate positive effect as a result of the dualling of the A419 between the
M5 Junction 13 and Chipmans Platt.
• Lighting: Significant adverse effects are anticipated from sky glow associated with when
the stadium lighting is in operation, albeit this effect will be infrequent.
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 426
Table 19.1: Summary of Significant Effects211
211 Note: Cumulative effects are dealt within the preceding Chapter 18 and so are not re-stated in this chapter. In summary, negative significant cumulative effects are anticipated
in relation to landscape and visual receptors within 500m and small areas of the Enscarpment Footslopes (LCT5a) from both the Revised Scheme, West of Stonehouse and Pike Lock.
However, positive significant cumulative effects are anticipated in relation to socio-economics and the creation of construction jobs. With regards to climate change, all greenhouse
gas emissions are arguably significant, however, any permitted application should include ‘reasonable’ measures to avoid, reduce and/or offset the generations of greenhouse gas
emissions.
Environmental
Topic
Receptor Effect Development
Phase
Sensitivity /
importance
of receptor
Magnitude
Change
Level of Effect (and
Significance) prior to
mitigation
Mitigation /
Enhancement
Level of Effect (and
Significance) after mitigation /
enhancement
Nature of
effect
Chapter 9:
Flood Risk,
Hydrology and
Drainage
The Stadium
Location
Biodiversity
enhancements
Operation Medium N/A Minor positive SuDS drainage
network design
Moderate (significant) Positive, Long
Term
Chapter 10:
Landscape and
Visual
LCT SV6
Settled
Unwooded
Vale, LCA
SV6A Vale of
Berkeley
Effect on landscape
character / value
C & O Medium High up to
250m from
Development
Footprint
Medium / Low
beyond 250m
Major / Moderate
up to approximately 250m
from
Development Footprint
Moderate / Minor or less
beyond 250m
(Significant within 250m)
See RS Appendix
10.3 Moderate / Major up to
approximately250m from
Development Footprint
Minor / Moderate or less
beyond 250m
(Significant within 250m)
Adverse and
Positive, Short
and Long Term,
Permanent and
Temporary,
Direct and
Indirect
Chapter 10:
Landscape and
Visual
Escarpment
Footslopes
(Stroud No
5A)
Effect on landscape
character / value
C & O Medium to
High
High up to
250m from
Development
Footprint
Medium / Low
beyond 250m
Major / Moderate to
Major
up to approximately 250m
from
Development Footprint
Moderate to Moderate /
Minor
or less beyond 250m
(Significant within 250m)
See RS Figures
5.3, 10.11c &
10.11d and RS
Appendices 10.3
& 10.7.
Moderate / Major up to 250m
from
Development Footprint
Moderate / Minor or less
beyond
250m
(Significant within 250m)
Adverse and
Positive, Short
and Long Term,
Permanent and
Temporary,
Direct and
Indirect
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 427
Chapter 10:
Landscape and
Visual
Lowland Plain
(Stroud No
5B)
Effect on landscape
character / value
C & O Medium High up to
250m from
Development
Footprint
Medium /
Low beyond
250m
Major / Moderate
up to approximately 250m
from
Development Footprint
Moderate / Minor
or less beyond 250m
(Significant within 250m)
See RS Figures
5.3, 10.11c &
10.11d and RS
Appendices 10.3
& 10.7.
Moderate to Moderate / Major
up
to 250m from
Development Footprint
Minor / Moderate or less
beyond
250m
(Significant within 250m)
Adverse and
Positive, Short
and Long Term,
Permanent and
Temporary,
Direct and
Indirect
Chapter 10:
Landscape and
Visual
7. Viewpoint
Grove Lane
M5 over
bridge
Effect on views and
visual amenity
C & O Medium Medium to High Moderate / Major
(Significant)
See RS Figures
5.3, 10.11c &
10.11d and RS
Appendices 10.4
& 10.7.
Moderate to Moderate / Major
(Adverse and Beneficial)
(Significant)
Adverse and
Positive, Short
and Long Term,
Permanent and
Temporary,
Direct
Chapter 10:
Landscape and
Visual
16. Footpath
west of West
End Cross
(EEA 38)
Effect on views and
visual amenity
C & O High Medium to High Major / Moderate
(Significant)
See RS Figures
5.3, 10.11c &
10.11d and RS
Appendices 10.4
& 10.7.
Moderate / Major (Adverse &
Beneficial
(Significant)
Adverse and
Positive, Short
and Long Term,
Permanent and
Temporary,
Direct
Chapter 10:
Landscape and
Visual
Residential
Property
Westend
House
Effect on views and
visual amenity
C & O High Medium Moderate / Major
(Significant)
See RS Figures
5.3, 10.11c &
10.11d and RS
Appendices 10.4
& 10.7.
See also ES Figure
5.6.
Moderate
(Not Significant)
Adverse and
Positive, Short
and Long Term,
Permanent and
Temporary,
Direct
Chapter 10:
Landscape and
Visual
Residential
Properties (2
Properties)
Effect on views and
visual amenity
C & O High Medium Moderate / Major
(Significant)
See RS Figures
5.3, 10.11c &
10.11d and RS
Appendices 10.4
& 10.7.
Moderate
(Not Significant)
Adverse and
Positive, Short
and Long Term,
Permanent and
Temporary,
Direct
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 428
Ivy Cottage,
Mole Cottage
See also ES Figure
5.6.
Chapter 10:
Landscape and
Visual
PRoW
Eastington
Footpath
No.37
Effect on views and
visual amenity
C & O High High Major
(Significant)
See RS Figures
5.3, 10.11c &
10.11d and RS
Appendices 10.4
& 10.7
Major/ Moderate
(Significant)
Adverse and
Positive, Short
and Long Term,
Permanent and
Temporary,
Direct
Chapter 10:
Landscape and
Visual
PRoW
Eastington
Footpath
No.38
Effect on views and
visual amenity
C & O High High Major
(Significant)
See RS Figures
5.3, 10.11c &
10.11d and RS
Appendices 10.4
& 10.7
Major / Moderate
(Significant)
Adverse and
Positive, Short
and Long Term,
Permanent and
Temporary,
Direct
Chapter 10:
Landscape and
Visual
M5 Effect on views and
visual amenity
C & O Low High 250m
north of J13
Low
Overall
Moderate / Major for
250m north of J13
Minor
Overall
(Significant for 250m)
See RS Figures
5.3, 10.11c &
10.11d and RS
Appendices 10.4
& 10.7
Moderate to Moderate / Major
for 250m
Minor Overall
(Significant for 250m)
Adverse and
Positive, Short
and Long Term,
Permanent and
Temporary,
Direct
Chapter 10:
Landscape and
Visual
A419 Effect on views and
visual amenity
C & O Low High between
Chipmans Platt
roundabout &
J13
Low Overall
Moderate / Major
between Chipmans Platt
roundabout & J13
Minor Overall
(Significant between
Chipmans Platt
roundabout & J13)
See Green
Infrastructure
Plan
Moderate to Moderate / Major
between Chipmans Platt
round-about & J13
Minor / Negligible Overall
(Significant between Chipmans
Platt roundabout & J13)
Adverse and
Positive, Short
and Long Term,
Permanent and
Temporary,
Direct
Chapter 12:
Transport and
Access
People
walking on
PROW
Footpaths
Severance, pedestrian
delay, pedestrian
amenity, fear &
intimidation
Construction
(Weekdays,
and Saturday
morning)
Medium Substantial Moderate/ significant No construction
to take place on
Saturday PM,
Sunday or Bank
Holidays /
Construction
Traffic
Moderate / significant Negative,
Medium Term
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 429
Easington 37
& 38
Management Plan
Chapter 12:
Transport and
Access
People
walking on
PROW
Footpath
Easington 37
as it crosses
A419
Severance, pedestrian
delay, pedestrian
amenity, fear &
intimidation
Operation
(Match)
Medium Substantial Moderate / significant Travel Plan to
encourage
sustainable travel
Moderate / significant Negative, Long
Term,
Infrequent
(during FGRFC
match)
Positive, Long
Term (No
FGRFC match)
Chapter 12:
Transport and
Access
People
walking on
PROW
Footpaths
Easington 37
& 38 within
Site
Severance, pedestrian
delay, pedestrian
amenity, fear &
intimidation
Operation
(Match)
Medium Medium Moderate / significant Travel Plan to
encourage
sustainable travel
Moderate/ significant Negative, Long
Term,
Infrequent
(during FGRFC
match)
Chapter 12:
Transport and
Access
People
walking or
cycling on
Spring Hill
Severance, pedestrian
delay, pedestrian
amenity, fear &
intimidation
Operation
(Match)
Medium Medium Moderate / significant Travel Plan to
encourage
sustainable travel
Moderate / significant Negative, Long
Term,
Infrequent
(during FGRFC
match)
Positive, Long
Term (No
FGRFC match)
Chapter 12:
Transport and
Access
People
walking or
cycling on
Cycle Route
45 at
Chipmans
Platt
Severance, pedestrian
delay, pedestrian
amenity, fear &
intimidation
Operation
(Match)
Medium Medium to
Substantial
Moderate/ significant Travel Plan to
encourage
sustainable travel
Moderate / significant Negative, Long
Term,
Infrequent
(during FGRFC
match)
Positive, Long
Term (No
FGRFC match)
Chapter 12:
Transport and
Access
Key highway
junctions
operating
within
capacity:
A419 Corridor
Driver Delay
Operation
(Match)
Medium Medium Moderate / significant Travel Plan to
encourage
sustainable travel
Moderate / significant Negative, Long
Term,
Infrequent
(during FGRFC
match)
Positive, Long
Term between
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 430
M5 J13 and
Chipmans Platt
(No FGRFC
match)
Chapter 14:
Lighting
All receptors Sky glow Operation Significant Limiting hours of
operation Significant Permanent,
Adverse, Long
term,
Infrequent.
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 431
20 GLOSSARY
Term Definition
Air Quality Standard Concentration of a pollutant, over a specified period, above which adverse
effects on health and/or the environment may occur and which should not be
exceeded
Ambient Of or relating to the immediate surroundings of something (e.g. ambient noise
level)
APS Annual Population Survey – a quarterly population survey conducted
throughout the UK, which gathers information on demographic and labour
market characteristics
ARCADY The roundabout module in Junctions 9
Assessment Process by which information about effects of a proposed plan, project or
intervention is collected, assessed and used to inform decision making
Automatic Traffic Count (ATC) Normally two rubber tubes laid across the carriageway linked to a road side
recorder box to measure speed, number and type of vehicle movements over a
24-hour period for a number of days
Background Sound Level Sound level measured in the absence of a specific sound source being studied. It
is common practice to measure the background sound level using statistical
analysis using the level of sound that is exceeded for 90% of the time: often
presented using the L90 descriptor
Barriers Other structures and buildings which are likely to impact on the propagation of
noise from construction works have also been included within the model. This
includes permanent surrounding residential and non-residential buildings and
any substantial barriers located in the surrounding area
Baseline Conditions Environment as it appears (or would appear) immediately prior to the
implementation of the project together with any known or foreseeable future
changes that will take place before completion of the project
Best Available Technique (BAT) The most effective and advanced engineering practices and methods of
operation, which are available and practicable, to prevent, and where this is not
practicable, reduce emissions and the impact on the environment as a whole
BRES Business Register and Employment Survey – an annual survey of employment
based on a sample of firms from the Interdepartmental Business Register
BS42020 British Standard Biodiversity. Code of Practice for Planning and Development
Catchment Drainage/basin area within which precipitation drains into a river system and
eventually into the sea
Climate Change Adaption The vulnerability of the Revised Scheme to climate change, with measures
included in the project to ensure resilience to climate change
Climate Change Mitigation The potential effects of the Revised Scheme on climate change, with measures
included in the project to reduce the emissions of greenhouse gases climate
change adaptation
CLG Department for Communities and Local Government – Government department
with responsibility for local government, communities, local enterprise
partnerships, the planning system and local fire and rescue authorities
Committed Development Development projects that are either under construction or have valid planning
permissions/consents
Conservation (for heritage policy) The process of maintaining and managing change to a heritage asset in a way
that sustains and, where appropriate, enhances its significance
Construction Phase Period during which the building or assembling of infrastructure is undertaken
Construction Traffic Management Plan (CTMP) Plan setting out proposals for the management of construction traffic including
vehicle routes and signing, construction traffic hours, site access and means of
protecting the public highway from detritus
Consultation Process by which those organisations or individuals with an interest in the area
associated with the proposed scheme are identified and engaged as part of the
EIA process
Culvert Pipe or box-type conduit through which water is carried under a structure
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 432
Cumulative Effect Effects that result from incremental changes caused by other past, present or
reasonably foreseeable actions together with the project.
A cumulative effect may arise as the result of (a) the combined effect of a
number of different environmental topic-specific effects from a single
environmental impact assessment project on a single receptor/ resource or (b)
the combined effect of a number of different projects within the vicinity (in
combination with the environmental impact assessment project) on a single
receptor/resource
Curfew Refers to a time when the local planning authority has agreed that the lighting
installation should be switched off; this typically refers to 11pm - 7am
dBA (A-weighted Decibel) A single value in decibels used to represent the noise level from the entire
hearing frequency range
Decommissioning Period during which a development and its associated processes are removed
from active operation
Degree of Saturation (DOS) Measure of capacity of a traffic signal junction
Designated heritage assets a World Heritage Site, Scheduled Monument, Listed building, Protected Wreck
Site, Registered Park and Garden, Registered Battlefield or Conservation Area
Do-minimum Scenario Also known as the ‘do-nothing’ scenario: the conditions that would persist in
the absence of the implementation of a development
ECoW Ecological Clerk of the Works
Effect Term used to express the consequence of an impact (expressed as the
‘significance of effect’), which is determined by correlating the magnitude of the
impact with the importance (or sensitivity) of the receptor or resource in
accordance with defined significance criteria. For example, land clearing during
construction results in habitat loss, the effect of which is the significance of the
habitat loss on the ecological resource.
Embedded Mitigation Mitigation that has been embedded into the design of the Revised Scheme.
Emergency Noise For the purposes of this document, Emergency Noise is defined as acoustic
emission due to unplanned pressure valve release, emergency flaring, or
operation/procedures necessary to protect life or property. The duration of
emission is short and the frequency of operation is expected to be very low.
Longer duration but infrequent noise sources such as start-up/shutdown
venting and flaring and audible announcement/alarm systems sounding do not
meet the Emergency Noise definition
Enhancement Measure that is over and above what is required to mitigate the adverse effects
of a project
Environmental Impact Assessment (EIA) Statutory process by which certain planned projects must be assessed before a
formal decision to proceed can be made. Involves the collection and
consideration of environmental information, which fulfils the assessment
requirements of the EIA Directive, including the publication of an environmental
statement
Environmental Statement (ES) Document produced in accordance with the EIA Directive (as transposed into
UK law by the EIA Regulations) that reports the outcomes of the EIA process
Evaluation Determination of the significance of effects. Evaluation involves making
judgements as to the value of the receptor/resource that is being affected and
the consequences of the effect on the receptor/resource based on the
magnitude of the impact
Existing Environment See ‘baseline conditions’
Façade Corrections a 3 dB(A) correction has been applied to convert a free-field noise prediction to
a façade level
Forest Green Rovers (FGR) Football club based in Stroud District
Field of view The horizontal and / or vertical extent of the prospect in view as depicted in the
photographs, defined by the angle subtended between the extremities of view
frame
FTE Full Time Equivalent – a measurement of the number of jobs in an area which
takes account of full time and part time work, so that employment can be
compared on a consistent basis
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 433
Glare The uncomfortable brightness of the light source against a dark background
which results in dazzling the observer, which may cause nuisance to residents
and a hazard to road users
Green Infrastructure Networks of Green Spaces and water courses and water bodies that connect
rural areas, villages, towns and cities
Ground Absorption Hard, acoustically reflective ground (0.5 coefficient) – roads, pavements and
hard standing areas
Acoustically soft (assumed 0.8 coefficient) – grass or vegetated areas
Heavy Goods Vehicle (HGV) goods vehicle over 3.5 tonnes gross weight
Heritage Asset A building, monument, site, place, area or landscape identified as having a
degree of significance meriting consideration in planning decisions, because of
its heritage interest
Hertz Unit of frequency defined as one cycle per second
Illuminance The luminous flux incident on unit area of a surface. The unit is the lux which is
one lumen per square metre
IMD Index of Multiple Deprivation – an index which assesses a wide range of
indicators to provide an assessment of deprivation in every local super output
area in England. This covers income, employment, crime, access to services,
health and living environment
Impact Sound The sound that results when two masses collide (typical peak sound level
duration of each impact would be between 25 microseconds and 1 second).
Typical examples are hammering and gunfire
Impulse Sound A sound created by the sudden impulse of pressure. Mathematically expressed
as the integral of a force over the time interval during which the force is
applied. Sometimes also referred to as impact sound
Intermittent For the purposes of this document, intermittent is defined as acoustic emissions
or operations that occur less than 5% of the time during a work shift and fewer
than six times per hour. Longer duration but infrequent noise sources such as
start-up/shutdown venting do not meet the intermittent definition
JSA Jobseekers Allowance – an out of work benefit for those people who are
actively seeking employment
Junctions 9 Industry standard package for modelling roundabouts and priority junctions.
Key Characteristics Those combinations of elements which are particularly important to the current
character of the landscape and help to give an area its particularly distinctive
sense of place
LA90, T A-weighted sound level which is exceeded for 90% of the duration of
measurement, often used to provide a value for the ‘background sound level’. T
is the period upon which the statistical level relates
LAeq, T A-weighted equivalent continuous sound pressure level, where A-weighted
refers to a frequency dependent correction that is applied to a measured or
calculated sound of moderate intensity to mimic the varying sensitivity of the
ear to sound for different frequencies. T is the period upon which the sound
pressure relates
Landscape An area, as perceived by people, whose character is the result of the action and
interaction of natural and/or human factors
Landscape and Visual Assessment (LVIA) A tool used to identify and assess the likely significance of the effects of change
resulting from development both on the landscape and as an environmental
resource in its own right and on people’s views and visual amenity
Landscape Capacity The degree to which a particular landscape character type or area is able to
accommodate change without unacceptable adverse effects on its character.
Capacity is likely to vary according to the type and nature of the change being
proposed
Landscape Character A distinct, recognisable and consistent pattern of elements in the landscape
that makes one landscape different from another, rather than better or worse
Landscape Character Areas (LCAs) These are single unique areas which are the discrete geographical areas of a
particular landscape type
Landscape Character Types (LCTs) These are distinct types of landscape that are relatively homogeneous in
character. They are generic in nature in that they may occur in different areas in
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 434
different parts of the country, but wherever they occur they share broadly
similar combinations of geology, topography, drainage patterns, vegetation,
historical land use, and settlement pattern, and perceptual and aesthetic
attributes
Landscape Quality (or condition) A measure of the physical state of the landscape. It may include the extent to
which typical character is represented in individual areas, the intactness of the
landscape and the condition of individual elements
Landscape receptors Defined aspects of the landscape resource that have the potential to be
affected by a proposal
Landscape Susceptibility The ability of the landscape receptor…to accommodate the Revised Scheme
without undue consequences for maintenance of the baseline situation and/or
the achievement of landscape planning policies and strategies
Landscape Value The relative value that is attached to different landscapes by society. A
landscape may be valued by different stakeholders for a whole variety of
reasons
LEP Local Enterprise Partnership – business-led organisations tasked with delivering
economic development for their local area. There are 39 LEPs in the country,
with the boundaries determined by local economic geography
Light Spill The unwanted spillage of light onto adjacent areas and may affect sensitive
receptors, particularly residential properties and ecological sites
Light Trespass (into Windows) The spilling of light beyond the boundary of a property which may cause
nuisance to others
Lux: The SI unit of illuminance, equal to one lumen per square metre
LinSig Industry standard software for the assessment and design of traffic signal
junctions
LOAEL This is the level above which adverse effects on health and quality of life can be
detected. The term is defined within the Noise Policy Statement for England
LSOA Lower Super Output Area – geographical units used for data analysis at a local
level in England and Wales. There are nearly 33,000 LSOAs in England and
Wales, each with a minimum population of 1,000 people
MAGIC Multi-Agency Geographic Information for the countryside
Mitigation Measures that are necessary to avoid, minimize, or offset anticipated adverse
impacts and, where appropriate, to incorporate these into an environmental
management plan or system.
Monitoring Continuing assessment of the performance of the project, including mitigation
measures. This determines if effects occur as predicted or if operations remain
within acceptable limits, and if mitigation measures are as effective as
predicted.
MSOA Middle Super Output Area - geographical units used for data analysis at a local
level in England and Wales. Middle super output areas are made up of several
smaller lower super output areas and have a minimum population of 5,000
people
National Cycle Network (NCN) A series of safe, traffic free paths and quiet on-road cycling and walking routes
that connect to every major town and city
National Planning Policy Framework (NPPF) Sets out the Government's planning policies for England and how these are
expected to be applied
National Transport Model (NTM) Government model to forecast long term trends in road traffic
National Trip End Model (NTEM) Used with TEMPRO to estimate local growth for transport planning purposes
NOEL This is the level below which no effect can be detected. In simple terms, below
this level, there is no detectable effect on health and quality of life due to the
noise. The term is defined within the Noise Policy Statement for England
Noise/Sound Vibrations in air that are in the audible frequency range from 20Hz–20 kHz. The
word "sound" is used within this document in relation to emissions which are
independent of the effect on the receptor (e.g. a ‘sound power level’ is related
to the source and is not related to the receptor). The word "noise" is used
where a sound is related to its affect on a receptor and constitutes an unwanted
effect of sound (e.g. occupational noise exposure)
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 435
Non-technical Summary Information for the non-specialist reader to enable them to understand the
main predicted environmental effects of the proposal without reference to the
main Environmental Statement.
NPPF National Planning Policy Framework – the main national planning policy
document which was published in March 2012, consolidating the previously
issued Planning Policy Statements and Planning Policy Guidance Notes for use in
England
Octave Bands Subdivision of sound spectrum based on set frequency ranges
OffPAT Office of Project Advice and Training - a membership network that operates a
value for money, shared services approach to programme and project best
practice. OffPAT closed in 2011
ONS Office for National Statistics - the UK’s largest independent producer of official
statistics and the recognised national statistical institute of the UK
Operation Functioning of a project on completion of construction
Passenger Car Unit (PCU) Method used in transport modelling to allow the different vehicle types within a
traffic flow group to nbe assessed in a consistent manner. Typical values are 1
for a car or light goods vehicle and 2 for a bus or heavy goods vehicle
PICADY The priority junction module in Junctions 9
Pollution Any increase of matter or energy to a level that is harmful to living organisms of
their environment (when it becomes a pollutant)
Programme Series of steps that have been identified by the applicant, or series of projects
that are linked by dependency
Project One (or more) aspect of a programme or plan that has been identified by the
applicant and usually involves a direct physical intervention
Pure Tone A narrow band component that is noticeable as a sound of distinguishable pitch
and that represents a dominant feature of the facility sound source.
Quantitatively, a measured 1/3 octave band sound level that is a minimum of 6
dB higher than both adjacent 1/3 octave band sound levels
RAMSAR Convention on Wetlands of International Importance, especially as Waterfowl
Habitat
Ratio of flow to capacity (RFC) Measure of traffic capacity of a junction
Receptor Defined individual environmental feature usually associated with population,
fauna and flora with the potential to be affected by a project
Receptor Height Ground Floor 1.5m above ground
First Floor 4.5m above ground
Residential Amenity Is understood to involve a combination of sensory factors which inform the
living conditions of a property including the visual, sound / noise and olfactory
(smell) environments
Resource Defined but generally collective environmental feature usually associated with
soil, water, air, climatic factors, landscape, material assets, including the
architectural and archaeological heritage that has potential to be affected by a
project
Run-off Precipitation that flows as surface water from a site, catchment or region to the
sea
Scoping Process of identifying the issues to be addressed by the environmental impact
assessment process. It is a method of ensuring that an assessment focuses on
the important issues and avoids those that are considered not significant.
Scoping Opinion Opinion provided by a competent authority that indicates the issues an
environmental impact assessment of a proposed development should consider
Screening Formal process undertaken to determine whether it is necessary to carry out a
statutory environmental impact assessment and publish an Environmental
Statement in accordance with the EIA Regulations
Section 106 Agreement A legally binding agreement between a Local Planning Authority and a land
developer, often to fund necessary improvments
Sediment Organic and inorganic material that has precipitated from water to accumulate
on the floor of a water body, watercourse or trap
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 436
Sensitivity A term applied to specific receptor, combining judgements of the susceptibility
of the receptor to the specific type of change or development proposed and the
value to that receptor
SEP Strategic Economic Plan – strategy document produced by each of the local
enterprise partnerships in England which identifies the key economic priorities
and interventions for the area
Significance See ‘significance of effect’
Significance (for heritage policy) The value of a heritage asset to this and future generations because of its
heritage interest
Significance of Effect Measure of the importance or gravity of the environmental effect, defined by
either generic significance criteria or criteria specific to the environmental topic
Significant Effect Environmental effect considered material to the decision-making process
Sky Glow The upward spill of light into the sky which can cause a glowing effect and is
often seen above cities when viewed from a dark area
SOAEL This is the level above which significant adverse effects on health and quality of
life occur. The term is defined within the Noise Policy Statement for England
Sound (Pressure) Level In air, 20 times the log (base 10) of the given sound pressure to the reference
sound pressure of 20 micro-Pascal; the resultant unit is dB. Sound pressure is
the root-mean-square of the instantaneous pressure fluctuations caused by an
acoustic wave during a specified time interval in a stated frequency band; the
unit is Pascal
Sound Power Level 10 times the log (base 10) of the given sound power to the reference sound
power of 1 pico-Watt; the resultant unit is dB. The sound power (of a source) is
the rate per unit time at which sound energy is radiated in a given frequency
band in Watts. Sound power is typically calculated as a function of sound
pressure and surface area
Source Modelling External noise sources have been treated as omni-directional point sources;
Plant complement assumed to be operating on the closest boundary of the
construction site to each receptor;
Shortest distance from façade of noise sensitive receptor to site assumed;
Buildings and structures identified modelled as structures;
Average construction source emission height of 1.5m;
Construction Plant Data taken from BS5228:2009+A01:2014
Strategic Road Network (SRN) Network of motorways and all-purpose trunk roads in England managed by
Highways England
Study Area Spatial area within which environmental effects are assessed (i.e. extending a
distance from the project footprint in which significant environmental effects
are anticipated to occur). This may vary between the topic areas.
Sustainable Transport All forms of transport which minimise emissions of carbon dioxide and
pollutants. Can refer to public transport, car sharing, walking and cycling as well
as technology such as electric and hybrid cars and biodiesel.
Terrain OS terrain data has been included within the model
Threshold Specified level in grading effects (e.g. the order of significance)
Traffic Information Traffic data used within the assessment has been provided by PFA Consulting
Limited
Transport Assessment (TA) Comprehensive review of the potential transport impacts of a proposed
development, with proposals to mitigate any adverse consequences
Travel Plan Long term management strategy for encouraging sustainable travel, often
prepared in parallel to development proposals
TRICS A database of trip rates for estimating trip generation by development
Trip End Model Presentation Program (TEMPRO) Used with the NTEM forecasts to estimate local growth for transport planning
purposes
Visual amenity The overall pleasantness of the views people enjoy of their surroundings, which
provides an attractive visual setting or backdrop for the enjoyment of activities
for people, living, working, recreating, visiting or travelling through an area
Eco Park – Revised Scheme, Land at M5 Junction 13, West of Stonehouse | Environmental Statement Vol. 1 Main Text
December 2017
Page | 437
Visual Receptors Individuals and / or defined groups of people who have the potential to be
affected by a proposal
With Development Noise predictions taking into account the impact of road traffic flows with the
Revised Scheme
Without Development Noise predictions taking into account the impact of road traffic flows without
the Revised Scheme
Worst Case Principle applied where environmental effects may vary (e.g. owing to seasonal
variations) to ensure the most severe effect is assessed
Zone of Theoretical Visibility (ZTV) A map, usually digitally produced, showing areas of land within which a
development is theoretically visible