Upload
eduardo-miranda-caceres
View
282
Download
7
Embed Size (px)
Citation preview
8/10/2019 VERTIMILL Maintenance and Layout_Escondida Meeting-Aug 18.pptx
http://slidepdf.com/reader/full/vertimill-maintenance-and-layoutescondida-meeting-aug-18pptx 1/44
VERTIMILL ® Grinding Mills
8/10/2019 VERTIMILL Maintenance and Layout_Escondida Meeting-Aug 18.pptx
http://slidepdf.com/reader/full/vertimill-maintenance-and-layoutescondida-meeting-aug-18pptx 2/44
This submittal is to be used bythe Recipient only for the
purpose for which it is provided. All documents, drawings,pricing, descriptions, literature,data, etc. contained herein(whether hard copy or
electronic) are ConfidentialInformation and are to be treatedas such by Recipient, to include,but not be limited to, protectingthe Confidential Information fromunauthorized disclosure or use.
8/10/2019 VERTIMILL Maintenance and Layout_Escondida Meeting-Aug 18.pptx
http://slidepdf.com/reader/full/vertimill-maintenance-and-layoutescondida-meeting-aug-18pptx 3/44
© Metso
VERTIMILL ® Grinding MillPresentation Outline
• Vertimill Overview• Maintenance Activities
• Layout Considerations
• New VTM-3000-WB at Newcrest Cadia
27-10-20143
8/10/2019 VERTIMILL Maintenance and Layout_Escondida Meeting-Aug 18.pptx
http://slidepdf.com/reader/full/vertimill-maintenance-and-layoutescondida-meeting-aug-18pptx 4/44
© Metso
The VERTIMILL ® Overview
10/27/20144
• > 330 Units Worldwide• > 175,000 kW Total power
• Unit Sizes from 15 to 3000 HP
• Feed Size from 6 mm
• Product Sizes to 15 µm• Low Intensity = Low Wear
• High Density media
• Media Size Matched with Grind
38 – 5 mm
8/10/2019 VERTIMILL Maintenance and Layout_Escondida Meeting-Aug 18.pptx
http://slidepdf.com/reader/full/vertimill-maintenance-and-layoutescondida-meeting-aug-18pptx 5/44
© Metso
The VERTIMILL ®
Applications
• Grinding- Secondary - 6 mm to 75 µm- Tertiary - 400 µm to 75 µm- Regrind - 200 µm to 15 µm- Flue Gas Desulphurization - 6 mm
to 20 µm
• Lime Slaking- Flue Gas Desulphurization- Acid Neutralization- Additive
10/27/20145
Regrind Flue Gas Desulfurization
Lime Slaking Secondary and Tertiary
Other
8/10/2019 VERTIMILL Maintenance and Layout_Escondida Meeting-Aug 18.pptx
http://slidepdf.com/reader/full/vertimill-maintenance-and-layoutescondida-meeting-aug-18pptx 6/44
© Metso
VERTIMILL ® Maintenance Activities
10/27/20146
• Grease Motor Bearings
• Change Motor Brushed
• Grease VTM Bearings
• Change Lube oil & filters• Change Screw Liners
8/10/2019 VERTIMILL Maintenance and Layout_Escondida Meeting-Aug 18.pptx
http://slidepdf.com/reader/full/vertimill-maintenance-and-layoutescondida-meeting-aug-18pptx 7/44
© Metso 10/27/20147
8/10/2019 VERTIMILL Maintenance and Layout_Escondida Meeting-Aug 18.pptx
http://slidepdf.com/reader/full/vertimill-maintenance-and-layoutescondida-meeting-aug-18pptx 8/44
© Metso
VERTIMILL ® MaintenanceDesign Considerations
• Access for greasing all bearings• Access to mill motor brushes
• Access to lube skid
• Crane and Fork Lift capacity and access for screw liner changes
• Crane for recharging Vertimill with balls• Access for screw transport pockets
• Vertimill pier height for use of ball bins
10/27/20148
8/10/2019 VERTIMILL Maintenance and Layout_Escondida Meeting-Aug 18.pptx
http://slidepdf.com/reader/full/vertimill-maintenance-and-layoutescondida-meeting-aug-18pptx 9/44
© Metso
VERTIMILL ® MaintenanceDaily Activities
• Daily equipment walk-down by operators
• No daily maintenance required
• All maintenance and troubleshooting detailed in manual
10/27/20149
8/10/2019 VERTIMILL Maintenance and Layout_Escondida Meeting-Aug 18.pptx
http://slidepdf.com/reader/full/vertimill-maintenance-and-layoutescondida-meeting-aug-18pptx 10/44
© Metso
VERTIMILL ® MaintenanceSchedule
Mill SystemComponent
TaskDescription
TaskDuration
Interval Mill Condition forProcedure
System Overall Check 10 min Daily Operating
Mill Motor GreaseBearings 5 min 3000 hrs Operating or Stopped
Reducer Change Oil 4 hrs Yearly Mill Stopped
Mill Bearings Inspect GreaseSystem 5 min Weekly Operating or Stopped
Mill Internals Inspect 12-16 hrs TBD Mill Stopped
10/27/201410
8/10/2019 VERTIMILL Maintenance and Layout_Escondida Meeting-Aug 18.pptx
http://slidepdf.com/reader/full/vertimill-maintenance-and-layoutescondida-meeting-aug-18pptx 11/44
© Metso
VERTIMILL ® MaintenanceTypical Steps to Change Liners
1. Grind-out2. Ball discharge
- To floor
- Use of ball bins
3. Door opening
4. Liner/screw replacement- Inside mill
- Complete screw change out
5. Door closing
6. Ball loading- Use of ball bins
- Continuous system
10/27/201411
8/10/2019 VERTIMILL Maintenance and Layout_Escondida Meeting-Aug 18.pptx
http://slidepdf.com/reader/full/vertimill-maintenance-and-layoutescondida-meeting-aug-18pptx 12/44
© Metso
VERTIMILL ® MaintenanceOpen the Ball Discharge Port
12
8/10/2019 VERTIMILL Maintenance and Layout_Escondida Meeting-Aug 18.pptx
http://slidepdf.com/reader/full/vertimill-maintenance-and-layoutescondida-meeting-aug-18pptx 13/44
© Metso
VERTIMILL ® MaintenanceOpen the Ball Discharge Port
13
• Loose all nucking nuts “A” • Back off jacking bolt “B” by one turn
• Tighten bolts “C” to push the shaft awayfrom the mill body and release the seal onthe ball discharge port
• Operate the valve by pulling the handleaway the mill body
• If necessary in step 2, turn bolt “B” morethan one turn
• To close, reverse the above by looseningbolt “C” and tighten bolts “B” to seal the
valve, then tighten nuts “A” to lock the bolts • Warning, do not open the valve with bolts
“B” beyond one and a half turns since largematerial can enter the sealing surface andmake it difficult to seal
8/10/2019 VERTIMILL Maintenance and Layout_Escondida Meeting-Aug 18.pptx
http://slidepdf.com/reader/full/vertimill-maintenance-and-layoutescondida-meeting-aug-18pptx 14/44
© Metso
VERTIMILL ® MaintenanceBall Discharge Using Bins – Option 1
• Ball Bins provide a clean andeasy way to handle media
• Manual discharge port
• Allows for easy loading andunloading of grinding media
10/27/201414
8/10/2019 VERTIMILL Maintenance and Layout_Escondida Meeting-Aug 18.pptx
http://slidepdf.com/reader/full/vertimill-maintenance-and-layoutescondida-meeting-aug-18pptx 15/44
© Metso
VERTIMILL ® MaintenanceBall Discharge To Floor – Option 2
15
8/10/2019 VERTIMILL Maintenance and Layout_Escondida Meeting-Aug 18.pptx
http://slidepdf.com/reader/full/vertimill-maintenance-and-layoutescondida-meeting-aug-18pptx 16/44
© Metso
VERTIMILL ® MaintenanceDoor Opening
• Remove the bolts in the access door flange,pump up the hydraulic door flange jackswith the pump provided with the screwtransport system. The jacks and plumbingshould have been previously filled with oiland the lines bled to remove any air.
• As the hydraulic jacks are being extended,the manual jacks installed at the hingepoints should be extended to keep the doorvertical and in the outer most position in thehinge slots as the door is opened.
• After the door is opened, wash theremaining balls out with high
• pressure hoses, or remove with shovels andrakes.
16
8/10/2019 VERTIMILL Maintenance and Layout_Escondida Meeting-Aug 18.pptx
http://slidepdf.com/reader/full/vertimill-maintenance-and-layoutescondida-meeting-aug-18pptx 17/44
© Metso
VERTIMILL ® MaintenanceDoor Opening
17
ManualJack
HydraulicJack
8/10/2019 VERTIMILL Maintenance and Layout_Escondida Meeting-Aug 18.pptx
http://slidepdf.com/reader/full/vertimill-maintenance-and-layoutescondida-meeting-aug-18pptx 18/44
© Metso
VERTIMILL ® MaintenanceDoor Opening
Most common options:• Winches
• Cranes
• Loader/Excavator
18
8/10/2019 VERTIMILL Maintenance and Layout_Escondida Meeting-Aug 18.pptx
http://slidepdf.com/reader/full/vertimill-maintenance-and-layoutescondida-meeting-aug-18pptx 19/44
© Metso
VERTIMILL ® MaintenanceScrew Liner Wear
10/27/201419
8/10/2019 VERTIMILL Maintenance and Layout_Escondida Meeting-Aug 18.pptx
http://slidepdf.com/reader/full/vertimill-maintenance-and-layoutescondida-meeting-aug-18pptx 20/44
© Metso
VERTIMILL ® MaintenanceDoor/Ball Charge Height
10/27/201420
8/10/2019 VERTIMILL Maintenance and Layout_Escondida Meeting-Aug 18.pptx
http://slidepdf.com/reader/full/vertimill-maintenance-and-layoutescondida-meeting-aug-18pptx 21/44
© Metso
VERTIMILL ® MaintenanceLiner Change Option 1
• Change liners inside the mill, most common solution
10/27/201421
8/10/2019 VERTIMILL Maintenance and Layout_Escondida Meeting-Aug 18.pptx
http://slidepdf.com/reader/full/vertimill-maintenance-and-layoutescondida-meeting-aug-18pptx 22/44
© Metso
VERTIMILL ® MaintenanceLiner Change Option 2
• Change Entire Screw
10/27/201422
8/10/2019 VERTIMILL Maintenance and Layout_Escondida Meeting-Aug 18.pptx
http://slidepdf.com/reader/full/vertimill-maintenance-and-layoutescondida-meeting-aug-18pptx 23/44
VERTIMILL ® InstallationsLayout Examples
8/10/2019 VERTIMILL Maintenance and Layout_Escondida Meeting-Aug 18.pptx
http://slidepdf.com/reader/full/vertimill-maintenance-and-layoutescondida-meeting-aug-18pptx 24/44
© Metso
VERTIMILL ® InstallationsLayout Examples
• Cerro Verde• Hibbing Taconite
• Los Pelambres
• Candelaria
• Codelco Andina• Esperanza
Not Recommended Layouts (Safety Issues):
• Escondida• Las Tortolas (Los Bronces)
10/27/201424
8/10/2019 VERTIMILL Maintenance and Layout_Escondida Meeting-Aug 18.pptx
http://slidepdf.com/reader/full/vertimill-maintenance-and-layoutescondida-meeting-aug-18pptx 25/44
© Metso
Cerro VerdeThree (3) VTM-1500-WBs
• No structure in front of millto allow easy crane accessfor screw insert and removal
• Modest pier height for easymaintenance
• Bins used for mediaaddition as well
10/27/201425
8/10/2019 VERTIMILL Maintenance and Layout_Escondida Meeting-Aug 18.pptx
http://slidepdf.com/reader/full/vertimill-maintenance-and-layoutescondida-meeting-aug-18pptx 26/44
© Metso
Cerro VerdeMedia addition – Same bin used for media handling
10/27/201426
8/10/2019 VERTIMILL Maintenance and Layout_Escondida Meeting-Aug 18.pptx
http://slidepdf.com/reader/full/vertimill-maintenance-and-layoutescondida-meeting-aug-18pptx 27/44
© Metso
Hibbing TaconiteTwo (2) VTM-1250-WB
10/27/201427
8/10/2019 VERTIMILL Maintenance and Layout_Escondida Meeting-Aug 18.pptx
http://slidepdf.com/reader/full/vertimill-maintenance-and-layoutescondida-meeting-aug-18pptx 28/44
© Metso
Los PelambresOne (1) VTM-1500-WB
10/27/201428
8/10/2019 VERTIMILL Maintenance and Layout_Escondida Meeting-Aug 18.pptx
http://slidepdf.com/reader/full/vertimill-maintenance-and-layoutescondida-meeting-aug-18pptx 29/44
© Metso
CandelariaOne (1) VTM-1250-WB
10/27/201429
8/10/2019 VERTIMILL Maintenance and Layout_Escondida Meeting-Aug 18.pptx
http://slidepdf.com/reader/full/vertimill-maintenance-and-layoutescondida-meeting-aug-18pptx 30/44
© Metso
Codelco AndinaTwo (2) VTM-1250-WB
10/27/201430
8/10/2019 VERTIMILL Maintenance and Layout_Escondida Meeting-Aug 18.pptx
http://slidepdf.com/reader/full/vertimill-maintenance-and-layoutescondida-meeting-aug-18pptx 31/44
© Metso
Minera EsperanzaTwo (2) VTM-1500-WB
10/27/201431
8/10/2019 VERTIMILL Maintenance and Layout_Escondida Meeting-Aug 18.pptx
http://slidepdf.com/reader/full/vertimill-maintenance-and-layoutescondida-meeting-aug-18pptx 32/44
© Metso
EscondidaFour (4) VTM-1500-WB (Not Recommended)
10/27/201432
8/10/2019 VERTIMILL Maintenance and Layout_Escondida Meeting-Aug 18.pptx
http://slidepdf.com/reader/full/vertimill-maintenance-and-layoutescondida-meeting-aug-18pptx 33/44
© Metso
Los BroncesThree (3) VTM-1500-WB (Not Recommended)
10/27/201433
8/10/2019 VERTIMILL Maintenance and Layout_Escondida Meeting-Aug 18.pptx
http://slidepdf.com/reader/full/vertimill-maintenance-and-layoutescondida-meeting-aug-18pptx 34/44
Newcrest CadiaVTM-3000-WB
8/10/2019 VERTIMILL Maintenance and Layout_Escondida Meeting-Aug 18.pptx
http://slidepdf.com/reader/full/vertimill-maintenance-and-layoutescondida-meeting-aug-18pptx 35/44
© Metso
The 1 st VTM-3000-WB InstallationNewcrest Mining Ltd. Cadia Valley Operations
21 September 201035
8/10/2019 VERTIMILL Maintenance and Layout_Escondida Meeting-Aug 18.pptx
http://slidepdf.com/reader/full/vertimill-maintenance-and-layoutescondida-meeting-aug-18pptx 36/44
© Metso
Newcrest CadiaHigh Grade Concentrator Simplified Flow Sheet
21 September 201036
Secondary VTM-1250-WB
Tertiary VTM-3000-WB
Regrind VTM-1250-WB
8/10/2019 VERTIMILL Maintenance and Layout_Escondida Meeting-Aug 18.pptx
http://slidepdf.com/reader/full/vertimill-maintenance-and-layoutescondida-meeting-aug-18pptx 37/44
© Metso
Newcrest CadiaThe 1 st VTM-3000-WB
• Grinding Design• F80 – 150 µm
• P80 – 90µm
• 780 mtph
• Exceeded efficiency predictions
• Flotation Recovery High thananticipated
- Sharper particle size distribution
- Finer feed to flotation
• Tertiary circuit stabilizes feed torougher flotation circuit
21 September 201037
8/10/2019 VERTIMILL Maintenance and Layout_Escondida Meeting-Aug 18.pptx
http://slidepdf.com/reader/full/vertimill-maintenance-and-layoutescondida-meeting-aug-18pptx 38/44
© Metso
Newcrest CadiaOperation of Separating Tank
27-10-201438
8/10/2019 VERTIMILL Maintenance and Layout_Escondida Meeting-Aug 18.pptx
http://slidepdf.com/reader/full/vertimill-maintenance-and-layoutescondida-meeting-aug-18pptx 39/44
© Metso
VTM-3000-WB PerformanceSummary to Date
• No Installation complications
• No Mechanical complications
• No Process complications
• With in 3 days of the start of commissioning, the mill became anactive part of plant operations
• Improving Recovery
• Increasing capacity
• Project and Installation executed with efficiency, quality, andfunctionality of a typical smaller VTM project
• Original set of liners replaced on May 2011 after 9 months ofoperation (no complications in the replacement, it took 30 hours).
21 September 201039
8/10/2019 VERTIMILL Maintenance and Layout_Escondida Meeting-Aug 18.pptx
http://slidepdf.com/reader/full/vertimill-maintenance-and-layoutescondida-meeting-aug-18pptx 40/44
© Metso
VTM-3000-WB MaintenanceFirst Internal Inspection After 3 Months of Operation
21 September 201040
October, 2010
8/10/2019 VERTIMILL Maintenance and Layout_Escondida Meeting-Aug 18.pptx
http://slidepdf.com/reader/full/vertimill-maintenance-and-layoutescondida-meeting-aug-18pptx 41/44
© Metso
VTM-3000-WB MaintenanceFirst Liner Replacement on May 2011
21 September 201041
9 months of life
8/10/2019 VERTIMILL Maintenance and Layout_Escondida Meeting-Aug 18.pptx
http://slidepdf.com/reader/full/vertimill-maintenance-and-layoutescondida-meeting-aug-18pptx 42/44
© Metso
VTM-3000-WB MaintenanceFirst Liner Replacement on May 2011
10/27/201442
8/10/2019 VERTIMILL Maintenance and Layout_Escondida Meeting-Aug 18.pptx
http://slidepdf.com/reader/full/vertimill-maintenance-and-layoutescondida-meeting-aug-18pptx 43/44
© Metso
VTM-3000-WB MaintenanceTypical Steps to Change Liners
1. Grind-out – 8 hours2. Ball discharge
- To floor – 11 hours
- Use of ball bins
3. Door opening
4. Liner/screw replacement- Inside mill – 4 hours (2 diggers)
- Complete screw change out
5. Door closing
6. Ball loading- Use of ball bins – 5 hours (10 ton)
- Continuous system
Cadia Total Time: 28 hours
10/27/201443
8/10/2019 VERTIMILL Maintenance and Layout_Escondida Meeting-Aug 18.pptx
http://slidepdf.com/reader/full/vertimill-maintenance-and-layoutescondida-meeting-aug-18pptx 44/44
© Metso