Upload
others
View
3
Download
0
Embed Size (px)
Citation preview
THE GAUHATI HIGH COURT (THE HIGH COURT OF ASSAM : NAGALAND : MIZORAM AND
ARUNACHAL PRADESH) Writ Petition (C) No. 2711 OF 2012
GUWAHATI MUNICIPAL CORPORATION, PANBAZAR, GUWAHATI - 781001, THROUGH ITS COMMISSIONER. ………… Petitioner
-Versus-
1. M/S. INTERNATIONAL CONSTRUCTION LTD., DUGAR BUILDING, HB ROAD, FANCY BAZAR, GUWAHATI, TROUGH ITS MD. 2. MR. NC DEKA BE, FIE, FICA, P.G. DIP (SURREY, UK) COMMISSIONER & SPL. SECRETARY (RETD.), PWD, GOVT. OF ASSAM, OPP. NEHRU STADIUM, DR. B BAROOAH ROAD, GUWAHATI – 781007.
….…… Respondents
Writ Petition (C) No. 2789 OF 2012 GUWAHATI MUNICIPAL CORPORATION, PANBAZAR, GUWAHATI - 781001, THROUGH ITS COMMISSIONER. ………… Petitioner
-Versus-
1. M/S. SPM ENGINEER LTD., DUGAR BUILDING, HB ROAD, FANCY BAZAR, GUWAHATI, TROUGH ITS MD. 2. MR. NC DEKA BE, FIE, FICA, P.G. DIP (SURREY, UK) COMMISSIONER & SPL. SECRETARY (RETD.), PWD, GOVT. OF ASSAM, OPP. NEHRU STADIUM, DR. B BAROOAH ROAD, GUWAHATI – 781007.
….…… Respondents
WPC Nos. 2790, 2789 & 2711 Of 2012 Page 2 of 28
Writ Petition (C) No. 2790 OF 2012 GUWAHATI MUNICIPAL CORPORATION, PANBAZAR, GUWAHATI - 781001, THROUGH ITS COMMISSIONER. ………… Petitioner
-Versus-
1. M/S. ZOOM INDUSTRIAL SERVICES LTD., DUGAR BUILDING, HB ROAD, FANCY BAZAR, GUWAHATI, TROUGH ITS MD. 2. MR. NC DEKA BE, FIE, FICA, P.G. DIP (SURREY, UK) COMMISSIONER & SPL. SECRETARY (RETD.), PWD, GOVT. OF ASSAM, OPP. NEHRU STADIUM, DR. B BAROOAH ROAD, GUWAHATI – 781007.
….…… Respondents
BEFORE
THE HON’BLE MR. JUSTICE UJJAL BHUYAN
For the Petitioner : Mr. B Singh, Advocate. Mr. SC Keyal, Advocate. For the Respondents : Mr. BR Bhattacharjee, Sr. Advocate. Mr. GN Sahewalla, Sr. Advocate. Mr. SR Ganguli, Advocate.
Date of Hearing : 30.10.2013. Date of Judgment : 05.05.2014
Judgment & Order (CAV)
Issue raised in all the three writ petitions i.e., WP(C)
Nos.2711/2012, 2789/2012 and 2790/2012 being identical, those were
heard together and are being disposed of by this common order.
WPC Nos. 2790, 2789 & 2711 Of 2012 Page 3 of 28
02. In all the three writ petitions, Guwahati Municipal
Corporation (GMC) is the writ petitioner. In WP(C) 2711/2012, the
contesting respondent i.e., respondent No. 1 is M/s. Industrial
Construction Ltd, in WP(C) No. 2789/2012, it is M/s. SPM Engineers
Ltd; whereas in WP(C) No.2790/2012, it is M/s. Zoom Industrial
Services Ltd. All the three writ petitions seek quashing of arbitral
awards dated 20.01.2004, passed by the respondent No. 2 as the
Arbitrator as well as the proceedings in the money execution cases
instituted by the claimants/respondent No. 1 in all the three cases for
execution of the arbitral awards. The challenge has been made on the
sole ground of the arbitral awards being vitiated by fraud and
collusion.
03. For the sake of convenience, facts relating to WP(C)
No.2711/2012 are briefly referred to hereunder.
04. GMC invited tender vide Notice Inviting Tender (NIT),
dated 01.02.1990 for execution of the work ‘improvement of existing
water supply’ in the city of Guwahati. A company called M/s.
International Pumps & Projects (I) Pvt. Ltd. had participated in the
tender and whose tender was accepted. The said company informed
the petitioner that for effective and speedy implementation of the
contract work, it would be executed by its associate company called,
International Pumps and Projects (Eastern) Pvt. Ltd. The associate
WPC Nos. 2790, 2789 & 2711 Of 2012 Page 4 of 28
company was awarded the formal work order on 05.10.1990.
Subsequently, on 20.09.1993, the associate company was taken over
by a company called, M/s. SPML Industries Ltd. On 04.08.1994, M/s.
SPML Industries Ltd., changed its name to M/s. Subhas Capital City
Ltd and finally on 08.06.1998, the name was changed to M/s.
International Construction Ltd. (respondent No. 1).
05. Differences and disputes arose between respondent No. 1
and the petitioner with regard to execution of the contract. The
completion date of the contract work was extended from time to time,
but the entire work could not be completed for various reasons. These
were disputed by the parties.
06. Respondent No. 1 moved the Commissioner of GMC in
September, 2001, to be precise on 10.09.2001, seeking his
intervention for resolution of the disputes by way of arbitration in
terms of the agreement entered into between the parties. Since the
matter could not be amicably settled, respondent No. 1 moved this
Court for appointment of an Arbitrator under section 11 (6) (c) of the
Arbitration and Conciliation Act, 1996 (briefly the Act hereafter) vide
Arbitration Petition Nos. 17, 18 and 19 of 2001. This Court after
hearing learned counsel for both the sides and after going through the
agreements entered into between the parties while disposing the
above arbitration petitions, held that there was an arbitration clause in
WPC Nos. 2790, 2789 & 2711 Of 2012 Page 5 of 28
the agreements. Since there was failure on the part of the
Commissioner to act as Arbitrator, the Hon’ble Chief Justice, vide his
common order dated 26.03.2002 decided to appoint an Arbitrator
under section 11 (6) (c) of the Act. As the dispute related to
engineering contract, it was felt that it would be better if an engineer
was appointed as an Arbitrator. Since respondent No. 2, a retired
Commissioner & Special Secretary to the Govt. of Assam, Public Works
Department, was an empanelled arbitrator in the list of arbitrators
maintained by the Indian Council of Arbitration, Assam, he was
appointed as the Arbitrator in all the three cases.
07. In the present case, the arbitration proceeding was
registered as Arbitration Case No. 18/2001 and the first hearing was
held on 25.04.2002. The arbitration proceeding was contested by both
the sides, whereafter the Arbitrator passed the award on 20.01.2004,
awarding a sum of Rs. 1,14,02,150.00 and other incidental amounts
with interest at the rate of 12% per annum in favour of respondent
No. 1.
08. Respondent No. 1/claimant as the decree holder instituted
execution proceedings for execution of the award dated 20.01.2004,
passed in Arbitration Case No. 18/2001, in the Court of District Judge,
Kamrup at Guwahati. The said execution case was registered as
Execution Case No. 30/2004.
WPC Nos. 2790, 2789 & 2711 Of 2012 Page 6 of 28
09. Objection filed by the petitioner as judgment debtor was
dismissed by the executing Court vide order dated 27.03.2006.
Petitioner thereafter filed a petition on 21.04.2012 before the
executing Court to dismiss the execution case and/or for stay of the
execution proceeding. The said prayer was made on the ground that
certain documents were obtained subsequently which showed that the
arbitral award was obtained by the decree holder fraudulently.
10. Learned District Judge, Kamrup at Guwahati passed order
on 21.04.2012 itself, dismissing the said petition filed by the
petitioner.
11. Aggrieved thereby, petitioner has filed the present writ
petition for quashing the award as well as the execution proceeding
including the order dated 21.04.2012.
12. Contention of the petitioner is that the arbitral award was
obtained by fraud and collusion between respondent No. 1 on the one
hand, lawyer and certain officials of the petitioner and the Arbitrator
on the other hand. The claims made by respondent No. 1 were bogus,
based on forged and fabricated documents. Since the impugned award
is vitiated by fraud, the same cannot be sustained, and question of
executing such award does not arise.
WPC Nos. 2790, 2789 & 2711 Of 2012 Page 7 of 28
13. This Court, by order dated 07.06.2012 issued notice and
passed an interim order to the effect that since fraud has been
alleged, Money Execution Case No. 30/2004, pending in the Court of
District Judge, Kamrup, should remain stayed.
14. Respondent No. 1 has filed affidavit. Maintainability of the
writ petition has been questioned. Writ would not lie for quashing of
an award as well as against a private party. Petitioner had adequate
and efficacious remedy under the Act, which it did not pursue. There
is delay in resisting the award and filing of the writ petition which
reflects lack of bonafide. On merit, it is submitted that arbitration
proceeding was initiated on orders of the Hon’ble Chief Justice by
appointment of respondent No. 2 as Arbitrator. The arbitration
proceeding was contested by the parties, whereafter award was
passed. Petitioner did not challenge the award under section 34 of the
Act. The award has attained finality. The same cannot be challenged
now on the false plea of fraud. Though fraud has been alleged, no
material has been placed before the Court to prove such allegation.
Executing Court was justified in rejecting the objection filed by the
petitioner. Petitioner acted on the basis of an undated complaint
received on 19.04.2012 written by one person called Prashanta
Changkakati without any verification. Strongly denying any wrong
doing, respondent No. 1 seeks dismissal of the writ petition both on
the ground of maintainability as well as on merit.
WPC Nos. 2790, 2789 & 2711 Of 2012 Page 8 of 28
15. Petitioner has filed rejoinder-affidavit to the counter-
affidavit filed by respondent No. 1. While reiterating the contentions
made in the writ petition, petitioner has contended that the procedure
adopted by the arbitral tribunal was not fair, rather it was conducted
in a manner unknown to law. It is also contended that respondent No.
1 had filed a writ appeal against stay order granted by the Single
Bench, but the same was dismissed. It is further contended that
respondent No. 1 had raised 16 claims for a total amount of
Rs.22,42,10,322.00, excluding interest, out of which
Rs.1,94,77,619.00 was awarded to the respondent No. 1 excluding
interest. In addition to the above, interest was also awarded
separately at the rate of 12% per annum, which would come to
Rs.1,07,38,994.00 (approximately).
16. Heard Mr. B Singh, learned counsel for the petitioner and
Mr. BR Bhattacharjee, learned Senior Counsel assisted by Mr. SR
Ganguli, learned counsel along with Mr. GN Sahewalla, learned Senior
Counsel for the respondents. None appeared for the respondent No. 2.
17. Learned counsel for the petitioner has based his entire
argument on fraud. He has submitted that respondent No. 1 had
colluded with the lawyer of the petitioner as well as the Chief Engineer
and the Arbitrator also became a party to the fraud. Most of the claims
were allowed on admission. He submits that fraud vitiates everything
WPC Nos. 2790, 2789 & 2711 Of 2012 Page 9 of 28
and, therefore, the impugned award cannot be allowed to stand. He
further submits that petitioner has lodged FIR against the respondent
No. 1. Even the Govt. of Assam has taken serious note of the matter
and the matter is being investigated. He has referred to a number of
decisions, including the one reported in (2000) 3 SCC 581, UNITED
INDIA INSURANCE COMPANY LTD. VS. RAJENDRA SINGH & ORS., in
support of his submission that if any benefit has been obtained by way
of fraud, the same cannot be allowed to be sustained by taking
technical plea. High Court has plenary powers to undo the mischief
caused by fraud and collusion.
18. Mr. Bhattacharjee, learned Senior Counsel appearing for
the respondent No. 1, at the outset, questioned the maintainability of
the writ petition. The award having not been challenged, even though
effective and adequate statutory remedy was available, had attained
finality. The plea of fraud taken by the petitioner is an afterthought to
resist the execution proceeding. He asserts that there was no fraud in
the passing of the award, which was passed following the procedure
laid down under the law. Petitioner has made serious allegations of
fraud against its own lawyer and Chief Engineer, that too, after the
lawyer had expired. Referring to the various documents on record,
learned Senior Counsel submits that contrary to what is being
contended by the petitioner, it was because of the effort of the lawyer
that the petitioner was quite successful in the arbitration proceeding,
WPC Nos. 2790, 2789 & 2711 Of 2012 Page 10 of 28
inasmuch as what was finally awarded was a fraction of what was
claimed by the respondent No. 1. Perhaps this would explain why the
award was not challenged under section 34 of the Act. He submits
that the so called complaint dated 19.04.2012 was an engineered
document, which was immediately lapped up by the petitioner and
was used to file the belated objection in the executing Court. To give it
a bonafide look, the said complaint was forwarded to the police
authorities for registration of criminal case without any independent
verification of the complaint by the petitioner. Referring to various
provisions of the Act and the decision of the Apex Court in the case of
VENTURE GLOBAL ENGINEERING VS. SATYAM COMPUTER SERVICES
LTD. & ORS., reported in (2010) 8 SCC 660, he submits that fraud is a
question of fact which has to be proved and demonstrated. Mere
insinuation or allegation would not constitute fraud. Contending that
the writ petition is an abuse of the process of the Court, Mr.
Bhattacharjee, learned Senior Counsel for the respondent No. 1 seeks
dismissal of the writ petition with exemplary costs.
19. In his reply, Mr. Singh, learned counsel for the petitioner
submits that objection regarding maintainability of the writ petition
based on the ground of availability of alternative remedy and finality of
award would not be tenable inasmuch as the award having been
obtained through fraudulent means would be non est in the eye of
law. In the facts and circumstances of the case, no amount of
WPC Nos. 2790, 2789 & 2711 Of 2012 Page 11 of 28
technical plea raised by respondent No. 1 can repel the challenge and
sustain the award.
20. I have heard learned counsel for the parties and I have
also perused the materials on record.
21. Before proceeding further, it would be apposite to refer to
those provisions of the Act which are relevant for the present case.
22. The Act was enacted to consolidate and amend the law
relating to arbitration, both domestic and international and for
enforcement of foreign arbitral awards, after repealing the earlier
Arbitration Act, 1940. The Act also deals with conciliation proceedings
and matters connected therewith or incidental thereto. Section 4 of
the Act deals with waiver of right to object. It says that a party to an
arbitration should know that any provision relating to arbitration from
which the parties may derogate or any requirement under the
arbitration agreement has not been complied with and yet proceeds
without stating his objection to such non-compliance without undue
delay or if a time limit is provided for stating that objection within the
prescribed period of time, shall be deemed to have waived his right to
object. Section 11 of the Act deals with appointment of Arbitrator and
lays down the procedure for such appointment. Under sub-section (6),
if an Arbitrator is not appointed as per the agreed procedure, a party
may request the Chief Justice or any person or institution designated
WPC Nos. 2790, 2789 & 2711 Of 2012 Page 12 of 28
by him, to appoint the Arbitrator and such appointment shall be final.
Appointment of an Arbitrator can be challenged on the grounds
mentioned in section 12. Under sub-section (3), an Arbitrator may be
challenged if justifiable doubts arise as to his independence or
impartiality or on the ground of lack of qualification. The arbitral
tribunal shall lay down its own procedure which will not be bound by
the provisions of the Civil Procedure Code, 1908 or by the Indian
Evidence Act, 1872. Section 25 deals with default of a party. If the
claimant does not submit its statement of claim, the arbitral tribunal is
empowered to terminate the proceedings. Likewise, if the respondent
does not submit its statement of defence or fails to appear or produce
documentary evidence, the arbitral tribunal shall continue with the
proceedings and make the arbitral award. Under section 34 of the Act,
a party may apply for setting aside of an arbitral award by making an
application before the Principal Civil Court of the district having
jurisdiction over the arbitration proceeding. Various grounds are
mentioned on the basis of which an arbitral award may be questioned
under section 34. As per section 34 (2) (b) (ii), if an arbitral award is
in conflict with the public policy of India, it may be set aside by the
Principal Civil Court. As per the explanation below the said sub-section,
it is declared that an award would be construed to be in conflict with
the public policy of India, if the making of the award was induced or
affected by fraud or corruption or was in violation of section 75 or
WPC Nos. 2790, 2789 & 2711 Of 2012 Page 13 of 28
section 81. While section 75 relates to confidentiality clause, section
81 deals with admissibility of evidence in other proceedings. Under
section 35, an arbitral award would be final and binding on the parties,
subject to any challenge under section 34. Enforcement of arbitral
award is provided in section 36, which says that after the period of
making an application under section 34 has expired, the award shall
be enforced under the Civil Procedure Code in the same manner as if
it were a decree of the Court. Section 37 is the appellate provision.
23. Having broadly noticed the provisions of the Act relevant
for the present case, we may now turn to the facts of the case.
24. It is not disputed that there were differences and disputes
between petitioner and respondent No. 1 relating to execution of the
contract in question so much so that respondent No. 1 had to
approach the Hon’ble Chief Justice of this Court for appointment of
Arbitrator. The Hon’ble Chief Justice noticed the dispute between the
parties which could not be amicably settled and passed order dated
26.03.2002, appointing respondent No. 2 as the Arbitrator in exercise
of the power conferred under section 11(6) (c) of the Act. As already
noticed above, the Arbitrator convened the first hearing on
25.04.2002. From 25.04.2002, the proceedings continued and finally
culminated in the making of the award on 20.01.2004. In other words,
the proceedings lasted for almost two years. During the entire
WPC Nos. 2790, 2789 & 2711 Of 2012 Page 14 of 28
proceedings, not only the lawyer of the petitioner was present, he was
assisted by the Chief Engineer, Water Works, GMC and other
engineers from time to time. They were throughout in touch with the
Commissioner, GMC pertaining to the arbitration proceedings. Minutes
of the day to day proceedings were also forwarded to the
Commissioner, GMC by the Arbitrator.
25. I am of the view that at this stage, details of the claims
lodged by the claimant would not be required to be gone into as this
Court is not examining the award as an appellate court. Suffice it to
say that respondent No. 1 made 16 claims for various amounts before
the Arbitrator. According to the rejoinder-affidavit of the petitioner, the
total amount claimed by the respondent No. 1 was
Rs.22,42,10,322.00, out of which the Arbitrator awarded
Rs.1,94,77,619.00. According to the petitioner, out of the aforesaid
amount, an amount of Rs.70,03,664.00 was awarded on the alleged
admission of the petitioner and a further amount of Rs.6,97,000.00
was awarded on the ground that petitioner could not place any
document relating to the said claim. Against claim of 21%, pre-suit,
pendente lite and future interest, the Arbitrator awarded 12% per
annum pre-suit and pendente lite interest and 18% per annum as
future interest. A perusal of the award would show that majority of the
claims raised by respondent No. 1 were not granted by the Arbitrator.
It further indicates that at the instance of the Arbitrator negotiations
WPC Nos. 2790, 2789 & 2711 Of 2012 Page 15 of 28
were held between the parties for settlement of the dispute, but
conciliation was not possible. In this connection, a meeting was also
held in the office of the Commissioner, GMC on 18.07.2003.
26. Coming to the claims of respondent No. 1, in all, the
respondent No. 1 made 16 claims. Though details of the claims need
not be gone into, the headings of the claims and the decision of the
Arbitrator may be briefly noticed. Claim No. 1 and claim No. 6 were
taken up together as the GMC had admitted a part of the principal
amount claimed against claim No. 1 and the full amount against claim
No. 6. Claim No. 1 is ‘claim for an amount of Rs.44,46,337.00 towards
work done bills’, whereas claim No. 6 is ‘claim for 5% amount withheld
on account of certificate of completion and commissioning
(Rs.41,09,079.00)’. Under Claim No. 1, the Arbitrator awarded Rs.
35,91,585.00 and the full amount under Claim No. 6 as the said
amount was admitted by the GMC to be payable to the respondent No.
1. Against claim No. 2 which is ‘claim for payment due to extra work
done beyond scope of original agreement (Rs.7,61,000.00)’, the
Arbitrator found that the said claim was not maintainable and
accordingly rejected the same. Claim Nos. 3,4 & 5 are as under: -
“Claim No. 3 : Claim for interest on delayed payments Rs.1,77,87,201.00 upto 30.03.2000.” “Claim No. 4 : Claim for interest on delayed payment of 1st installment of mobilization advance (Rs.3,22,666.00).”
WPC Nos. 2790, 2789 & 2711 Of 2012 Page 16 of 28
“Claim No. 5 : Claim for interest on delayed payment of 2nd installment of mobilization advance (Rs.7,16,261.00).”
Against claim No. 3, Arbitrator held that the claimant was entitled to
interest on delayed payment and held that the interest would be
calculated at the rate of 12% per annum. However, claim Nos. 4 & 5
were disallowed. Claim No. 7 is ‘claim for escalation for work done and
supply made after 1994 (Rs.15,00,000.00)’. Under this claim, the
Arbitrator awarded Rs.3,74,805.00. Claim Nos. 8 to 13 are as under:-
“Claim No. 8 : Claim for an amount of Rs.15,23,74,103.00 on account of damages.” “Claim No. 9 : Claim for an amount of Rs. 1,71,03,225.00 on account of compensation for payment of idle time suffered.” “Claim No. 10 : Claim for an amount of Rs. 2,00,000.00 on account of compensation for additional bank charges for bank guarantee during the extended period of contract.” “Claim No. 11 : Claim for an amount of Rs. 40,00,000.00 on account of compensation towards depreciation of machinery/equipment etc. during the extended period of contract.” “Claim No. 12 : Claim for an amount of Rs. 16,74,000.00 on account of expenses incurred for visits to and from the site in the extended period.” “Claim No. 13 : Claim for an amount of Rs. 58,59,000.00 towards expenditure incurred on hiring of accommodation during the extended period.”
The above claims were taken together as those related to claim of
compensation for prolongation of the contract period and losses
suffered due to the same. The Arbitrator held that GMC had breached
WPC Nos. 2790, 2789 & 2711 Of 2012 Page 17 of 28
the contract which led to prolongation of the contract period. It was
also found that un-rebutted documentary evidence on record had
clearly revealed the fact that GMC had grossly delayed in making
payment on time. The Arbitrator calculated the period of delay to be
the period from 05.06.1992 to 08.04.1996 i.e. the date when the
claimant submitted the incomplete final bill. The Arbitrator awarded
Rs.1,14,02,150.00 against Claim Nos. 8 & 9, but held that claimant
would not be entitled to any further amount under claim Nos. 10 to
13. Accordingly claim Nos. 10 to 13 were rejected. Thus for claim
Nos.8 to 13, against the claim of Rs. 18,12,10,328.00, the sum
awarded was 1,14,02,150.00. Claim No. 14 is for ‘claim on account of
loss of goodwill (Rs.1,31,07,450.00). The Arbitrator, however, declined
to award any amount under this claim and rejected the same. Claim
No. 15 is ‘claim for pre-suit, pendente lite and future interest at the
rate of 21%’. After holding that the claimant was entitled to payment
of interest, the Arbitrator held that pre-suit and pendente lite interest
to the claimant would be at the rate of 12% per annum, which would
be calculated from the various dates mentioned in the award. It was
further held that the claimant would be entitled to future interest at
the rate of 18% per annum on the principal amount awarded from the
date of award till the date of payment. Claim No. 16 is ‘claim for an
amount of Rs.2,50,000.00 on account of costs’. But the Arbitrator
declined to award any cost, leaving the parties to bear their own costs.
WPC Nos. 2790, 2789 & 2711 Of 2012 Page 18 of 28
27. Thus even from a cursory glance at the award, it is seen
that many of the claims made by the claimant were rejected. As
pointed out by the GMC in its reply-affidavit, against total claim of
Rs.22,42,10,322.00, the Arbitrator awarded only Rs.1,94,77,619.00.
Though we are not concerned with the quantum of the award, yet the
fact that the Arbitrator had awarded only a fraction of what was
claimed cannot be overlooked. Full participation of the GMC in the
arbitration proceeding cannot also be overlooked. It is evident from
the award that the lawyer representing the GMC was assisted by the
Chief Engineer and other staff of GMC throughout the proceeding with
the Commissioner being kept abreast of the proceedings on regular
basis.
28. When a copy of the award was forwarded to their lawyer
by the Chief Engineer, Water Works, GMC for opinion, the lawyer
replied back on 12.07.2004, firstly, clarifying that he was not the
Standing Counsel, GMC and secondly, on the legal opinion sought for,
he stated that he had discussed the matter with the Commissioner,
GMC about the possibility of an out of Court settlement, but not much
headway was made in this regard. He finally stated that for a variety
of personal reasons, he had decided not to deal with arbitration cases
any further and declined to tender any advice. Request was also made
to take away the briefs from his custody. This was a letter of
WPC Nos. 2790, 2789 & 2711 Of 2012 Page 19 of 28
12.07.2004. The Chief Engineer also put up a note before the
Commissioner on 28.08.2004 stating that the award goes in favour of
GMC and, therefore, process for out of Court settlement may be
initiated. It was pointed out that representative of respondent No. 1
had approached the Chief Engineer for out of Court settlement and he
opined that it was a good proposal which was in the best interest of
GMC. What followed thereafter has not been brought on record.
However, the materials on record do not indicate that GMC had sought
for legal opinion of any other counsel or that any view was expressed
to challenge the award under section 34 of the Act.
29. In the meanwhile, as the award was not complied with and
as no headway was made for out of Court settlement, respondent No.
1 initiated execution proceedings in the year 2004 itself under section
36 of the Act. It further appears that objection filed by the petitioner
as judgment debtor was dismissed by the executing Court on
27.03.2006. Long thereafter, notification dated 22.06.2011 was issued
by the Commissioner and Secretary to the Govt. of Assam, Guwahati
Development Department constituting a ‘Bids Finalization Committee’
with the following members: -
Joint Secretary to the Govt. of Assam, Guwahati Development Department : Chairman. Joint Commissioner, Guwahati Municipal Corporation : Member.
WPC Nos. 2790, 2789 & 2711 Of 2012 Page 20 of 28
Chief Engineer, GMC : Member. Standing Counsel, GMC : Member. Sr. FA to the Govt. of Assam, Guwahati Development Department : Member.
for settlement of amount of the awards dated 20.01.2004 in the three
arbitration cases. By a corrigendum issued on 30.06.2011, the
Commissioner & Secretary clarified that ‘Bids Finalization Committee’
should be read as ‘Awards Negotiation Committee’. It was further
mentioned that Joint Commissioner, GMC would be the Member
Secretary of the said Committee.
30. What steps the Award Negotiation Committee took
regarding the awards in question or the outcome of such steps are not
known, as nothing has been placed on record. But what is clear is that
the Committee was constituted for settlement of the amount made by
the awards and not for scrutiny of the awards. In other words, the
objective was to negotiate on the quantum of the awards and not to
challenge the basis of the awards. Be that as it may, surprisingly, a
complaint written by one Prashanta Changkakati, Guwahati – 3
addressed to the Commissioner, GMC without any date, suddenly
appeared, which is available on record. Though there is an
endorsement dated 19.04.2012 on the body of the complaint, it is not
known as to whose endorsement it was as the endorsement was
WPC Nos. 2790, 2789 & 2711 Of 2012 Page 21 of 28
without any official seal. There is no description of who Prashanta
Changkakati was and the address given was also very vague, as he
simply described himself as Prashanta Changkakati, Guwahati-3. He,
however, alleged that respondent No. 1 had entered into a criminal
conspiracy with officials of GMC to misappropriate public money by
forgery and cheating. In the course of the complaint, the said
Prashanta Changkakati stated that the accused-company got an
Arbitrator appointed without an arbitration clause. The complainant
further went on to say that having ‘secured’ appointment of an
Arbitrator i.e., respondent No. 2, the accused-company filed claims
based on forgery and fabricated documents. The complainant called
for a comprehensive enquiry into the matter, threatening that if the
Commissioner failed to take action, he would approach the High Court
and the Supreme Court for a Court monitored CBI enquiry.
31. Without entering into the substance of the allegations
made by the complainant, it is evident, as already noticed, that the
complainant did not disclose his identity. He also did not disclose as to
how, in what manner and in what capacity he had come to know
about the alleged forgery and cheating by respondent No. 1. The GMC
Commissioner or the other authorities of GMC ought to have been
careful and circumspect when the said complainant stated that the
accused-company got an Arbitrator appointed without an arbitration
clause and that it had ‘secured’ appointment of respondent No. 2 as
WPC Nos. 2790, 2789 & 2711 Of 2012 Page 22 of 28
the Arbitrator when the fact is that it was because of the judgment
and order of the Hon’ble Chief Justice dated 26.03.2002, which held
that there existed an arbitration clause in the contract agreement, the
Arbitrator was appointed. It was further held that the named
Arbitrator i.e., Commissioner, GMC had failed to enter into the dispute
referred and, therefore, the Hon’ble Chief Justice proceeded to appoint
an Arbitrator under section 11 (6) (c) of the Act. This is what was held
by the Hon’ble Chief Justice in his judgment and order dated
26.03.2002:-
“ Really speaking it is to be seen whether the parties to the agreement intended that any disputes arising between them should be decided by a particular person after holding an enquiry in the nature of judicial enquiry and after hearing the cases of respective parties. If such is the intention, then it is an arbitration clause irrespective of the fact that the words ‘arbitrator’ or ‘arbitration’ are not used in such clause. In the present case, reading of the clauses 26 and 30, as well as clause D-6.21 of the agreements quoted above, it is apparent that it was envisaged that any dispute arising out of the agreements, the decision thereon shall be taken by the Commissioner. Consequently, I do not agree with the contention of the learned counsel for the respondent, GMC, and hold that there exists an arbitration clause. In Arbitration Petition No. 17/2001, the first communication which was received after September 10, 2001 from the Commissioner, GMC is dated 13.11.2001. Admittedly, it is after 30 days of the receipt of the notice dated 10th September, 2001. In Arbitration Petition No. 18/2001, the notice dated 10.09.2001 was duly received by the respondent, but there was no reply to it till the filing of the petition, i.e., 18.10.2001. In Arbitration Petition No. 19/2001, the learned counsel for the respondent referred to a communication dated 28th September, 2001, from the Commissioner, GMC. In that communication, reference is being made to the Chief Engineer’s letter dated 13.03.2001,
WPC Nos. 2790, 2789 & 2711 Of 2012 Page 23 of 28
which was addressed to the applicant asking them to attend the office of the Chief Engineer along with copy of the agreement and other relevant documents in respect of the work ‘Labour charge and supply of barge, installation of MS pipeline for Kamakhya Water Supply Scheme’ on 15.03.2001 at 3:00 p.m. The communication dated 28th September, 2001 is not in response to the notice dated 10th September, 2001 in which disputes were referred. This petition was filed on 18.10.2001. From the aforesaid facts, I am of the considered view that the named arbitrator, i.e., the Commissioner, GMC failed to enter upon the reference and act as an arbitrator within 30 days of the receipt of the notices dated 10.09.2001. In view of the above, I proceed to appoint an arbitrator under section 11(6)(c) of the Act. The matter relates to engineering disputes and it would be better if some engineer is appointed as an arbitrator. One such arbitrator is in the list of arbitrators maintained by the Indian Council of Arbitration, Assam. In these three cases, Mr. N. C. Deka, Commissioner, PWD (Retd), opposite Nehru Stadium, Dr. B. Barooah Road, Guwahati, is appointed as arbitrator.”
Thus, on the face of it, the allegation made by the complainant
that the accused-company got an Arbitrator appointed without an
arbitration clause or that it had ‘secured’ appointment of an Arbitrator,
is not only untenable and false, but is also highly contemptuous.
Inspite of that, the Commissioner or other higher authorities of GMC
did not think it necessary to verify the antecedents of the complainant
and the genuineness of the complaint. Instead, he got a FIR
registered against respondent No. 1 though the Joint Commissioner,
GMC and the entire complaint was enclosed as the first information.
WPC Nos. 2790, 2789 & 2711 Of 2012 Page 24 of 28
32. Be that as it may, it was only after receipt of the alleged
complaint on 19.04.2012 that the GMC filed an objection immediately
thereafter on 21.04.2012 before the executing Court seeking stay of
the execution proceeding. Learned District Judge, Kamrup, Guwahati
by his order dated 21.04.2012 dismissed the said petition. It was held
as under: -
“The parties are present. The judgment-debtor has filed a petition No.580/12 with a prayer to stay execution proceeding of this case.
I have heard learned counsel for both sides. Learned counsel for judgment-debtor has referred
to the provisions of Section 47 of the CPC to justify his prayer for stay of the proceeding. The judgment-debtor has alleged in the instant petition that the arbitral award was fraudulently obtained by the decree-holder. This is the sole ground on which he has prayed to stay the execution proceeding.
I have visited the provisions of Section 47 of the CPC and I have not found therein that any provision is made therein to condone such a prayer. The provisions of Section 47 have given the power to the Court to decide dispute between the parties arising out of the execution proceeding. The dispute, alleged in the petition between the parties, does not appear to have arisen out of this execution proceeding. In fact the judgment-debtor has challenged the arbitral award which is put to execution in this execution proceeding on the ground that the arbitral award was obtained fraudulently. That being so, the judgment-debtor, instead of resorting to the option of filing a separate suit seeking declaration that the arbitral award was fraudulently obtained or to the provisions for appeal against the arbitral award, has preferred to file this petition which has no approval of the provisions referred to by the learned advocate for the judgment-debtor, as indicated above. The learned advocate for judgment-debtor has also made a prayer to this court to exercise its inherent power u/s 151 of the CPC. The provision of section 151 of the CPC cannot be applied in the instant case in view of the fact that there is a legal provision available for judgment-debtor either
WPC Nos. 2790, 2789 & 2711 Of 2012 Page 25 of 28
to prefer an appeal against the arbitral award or to file a separate suit seeking a declaration.
Accordingly, I am not inclined to exercise the power of this court u/s 151 of the CPC.
The petition stands dismissed, accordingly, after hearing both sides.
Since no out of Court settlement has taken place in this execution proceeding the decree-holder will take steps within 7 days for issuance of the writ.”
33. The executing Court was right in saying that the petitioner
ought to have filed a separate suit for declaring the award as being
fraudulently obtained or it could have challenged the award under
section 34 of the Act on the ground that the arbitral award is in
conflict with the public policy of India, which has been explained to
mean making of the award by fraud or corruption. Petitioner chose not
to take recourse to any of the aforesaid two legal options open to it.
For eight years i.e., from January, 2004 when the award was made to
19.04.2012 when the so-called complaint was received, petitioner
never raised any objection that the award was vitiated by fraud. From
the documents placed on record, it is evident that fraud was alleged
for the first time in the complaint received on 19.04.2012. As already
noticed above, without making any preliminary verification or enquiry
about the antecedent of the complainant or the veracity of the
complaint, petitioner accepted the complaint as if it was a gospel truth
and immediately filed the petition before the executing Court not to
execute the award alleging fraud. This itself raises doubt about the
WPC Nos. 2790, 2789 & 2711 Of 2012 Page 26 of 28
bonafides of the complaint and the action taken by the petitioner
based thereon.
34. There is no dispute to the proposition of law advanced on
behalf of the petitioner that an award obtained by fraud is a nullity
and that the High Court has got plenary powers to set at nought an
award obtained through fraud. No amount of technicalities or delay
can sustain or rescue an award obtained by fraud from judicial
excision. The Apex Court very rightly pointed out in the case of
RAJENDRA SINGH (Supra), that fraud and justice never dwell
together. However, having said that, it must also be borne in mind
that fraud is essentially a question of fact which has to be
proved/demonstrated to the satisfaction of the Court by the party
alleging fraud. Section 17 of the Indian Contract Act, 1872, defines
fraud. It reads as under: -
“17. ‘Fraud’ defined – Fraud’ means and includes any of the following acts committed by a party to a contract, or with his connivance, or by his agent, with intent to deceive another party thereto or his agent, or to induce him to enter into the contract: -
(1) the suggestion, as a fact, of that which is not true, by one who does not believe it to be true; (2) the active concealment of a fact by one having knowledge or belief of the fact; (3) a promise made without any intention of performing it; (4) any other act fitted to deceive;
WPC Nos. 2790, 2789 & 2711 Of 2012 Page 27 of 28
(5) any such act or omission as the law specially declares to be fraudulent.
Explanation – Mere silence as to facts likely to affect the willingness of a person to enter into a contract is not fraud, unless the circumstances of the case are such that, regard being had to them, it is the duty of the person keeping silence to speak, or unless his silence, is, in itself, equivalent to speech.”
35. Section 17 of the Indian Contract Act, 1872, has to be read
with the provisions of section 34 (2) (b) (ii) of the Act. When a
challenge is made to an arbitral award on the ground of the award
being induced or affected by fraud, this has to be proved in the
appropriate court either by filing application under section 34 of the
Act or by filing an independent suit. Admittedly, petitioner has not
availed any of the above remedies. Even in the present writ petition,
the pleadings as to fraud are extremely bald and general in nature to
warrant or justify coming to any conclusion that fraud or collusion had
played a part in making of the award. On the contrary, it is the
inordinate delay on the part of the petitioner in making the allegation
of fraud and the manner in which the allegation of fraud had surfaced
through an anonymous complaint which was immediately acted upon
by the petitioner without even any initial verification raises question
mark about the bonafides of the petitioner itself in instituting a very
belated challenge to the arbitral award by clutching on to the only
ground that could be available to sustain such a challenge at this
belated stage i.e., fraud.
WPC Nos. 2790, 2789 & 2711 Of 2012 Page 28 of 28
36. For the aforesaid reasons, this Court is not inclined to
accede to the contentions advanced on behalf of the petitioner. This
petition is, therefore, devoid of any merit and is accordingly dismissed.
Interim order passed by this Court on 07.06.2012 stands vacated.
37. For the grounds and reasons mentioned above, the other
two writ petitions i.e., WP(C) No.2789/2012 and WP(C) No.2790/2012
are also dismissed. Stay order passed in those cases on 12.06.2012
are also vacated. No costs.
Judge
Beep!