R E P O R T I N G
L I V E F R O M T H E
F I E L D
S T A T U S O F W O R K P R O G R E S S
A S O N
0 9 / 0 1 / 2 0 1 5
BLOCK BLOCK BLOCK BLOCK –––– AAAA (AMIGO BLOCK)(AMIGO BLOCK)(AMIGO BLOCK)(AMIGO BLOCK)
BLOCK BLOCK BLOCK BLOCK –––– BBBB (B(B(B(BELLAMYELLAMYELLAMYELLAMY BLOCK)BLOCK)BLOCK)BLOCK)
BLOCK BLOCK BLOCK BLOCK –––– CCCC (KADIN BLOCK)(KADIN BLOCK)(KADIN BLOCK)(KADIN BLOCK)
BLOCK BLOCK BLOCK BLOCK –––– DDDD (C(C(C(CARA BLOCK)ARA BLOCK)ARA BLOCK)ARA BLOCK)
BLOCK BLOCK BLOCK BLOCK –––– EEEE (RAYA BLOCK)(RAYA BLOCK)(RAYA BLOCK)(RAYA BLOCK)
BLOCK BLOCK BLOCK BLOCK –––– FFFF (BONARO BLOCK)(BONARO BLOCK)(BONARO BLOCK)(BONARO BLOCK)
BLOCK BLOCK BLOCK BLOCK –––– GGGG (SUHUBA BLOCK)(SUHUBA BLOCK)(SUHUBA BLOCK)(SUHUBA BLOCK)
PROGRESS PROGRESS PROGRESS PROGRESS STATUS STATUS STATUS STATUS –––– CENTRAL COURTYARDCENTRAL COURTYARDCENTRAL COURTYARDCENTRAL COURTYARD
PROGRESS STATUS PROGRESS STATUS PROGRESS STATUS PROGRESS STATUS –––– MAIN ENTRANCE DRIVEWAYMAIN ENTRANCE DRIVEWAYMAIN ENTRANCE DRIVEWAYMAIN ENTRANCE DRIVEWAY
FINISHING WORKS - BLOCK WISE STATUS
BLOCK A - AMIGO BLOCK
• Completed in all respects.
• Independent Third Party (Cushman & Wakefield) check in Progress.
BLOCK B - BELLAMY BLOCK
• Door frame fixing is completed.
• 3rd coat Patti work completed.
• Marble 2nd coat polishing completed.
• External painting finishes: 85% complete.
BLOCK C - KADIN BLOCK
• Completed in all respects.
• Independent Third Party (Cushman & Wakefield) check in Progress.
BLOCK D - CARA BLOCK
• Balcony SS Railings fixing: 80% completed
• Lifts in high speed mode testing.
• Door frame fixing completed.
• Hardware Fixing is in Progress.
• First coat painting nearing completion.
BLOCK E - RAYA BLOCK
• Completed in all respects.
• Final Snag rectifications is progress.
BLOCK F - BONARO BLOCK
• Balcony S.S. Railings Fixing: 70% Completed.
• Door frame fixing completed.
• 3rd coat Patti work completed.
• Shutter fixing is in progress.
• Lifts in slow speed testing mode.
BLOCK G - SUHUBA BLOCK
• Completed in all respects.
• Independent Third Party (Cushman & Wakefield) check in Progress.
PODIUM
• Planter box construction Completed & water proofing at Centre courtyard
completed.
• Granite top finishing work is in progress.
STATUS OF OTHER EXTERNAL DEVELOPMENT WORKS
• Amenity Block: External painting is completed.
• Club house: Structure completed, External plastering is in progress.
• Entrance Plaza: Plastering is in Progress.
• Macadam road completed, ready to receive final concrete surface.
• Entrance approach road formation finishing work to start this week.
• Transformer Yard, pedestal work is completed.
• Electrical room panel work in all tower is in progress.
• Basement IPS floor finish is 90% area completed.
• Fire Safety work 90% completed.
• Lift lobby granite clouding & floor finishes is in progress.
• Jogging track is in progress.
• Drive way – Finishing work is in Progress.
• Amphitheatre – Location stepped formation is in progress.
• Entrance Approach – Both side landscape work is in progress.