Upload
others
View
1
Download
0
Embed Size (px)
Citation preview
Value for Money Test in KoreaValue for Money Test in Korea
PIMAC
JungwookJungwook [email protected]@kdi.re.krFellow of PPP DivisionFellow of PPP DivisionPublic and Private Infrastructure Public and Private Infrastructure Investment Management CenterInvestment Management Center
2
1. Value for Money Test1. Process of PPP Project Implementation2. VFM : The Theory3. VFM : The Practice in Korea
2. Case Study :
Light Rail Transit of New Boundang Line1. Project Overview2. Estimation of Transportation Demand3. Estimation of Cost4. Feasibility Study5. Quantitative VFM Analysis6. Formulation of PFI Alternatives
Value for Money TestPart-01
1. Process of PPP Project Implementation
5
Project Initiation
qq Both the government and a private company can initiate a Both the government and a private company can initiate a PPP projectPPP project
qq Solicited ProjectsSolicited Projectsll A solicited project is that the competent authority identifies a project for A solicited project is that the competent authority identifies a project for
private investment and announces a RFPprivate investment and announces a RFP
ll Competent authorities develop a potential project after considering Competent authorities develop a potential project after considering related plans and demands for the facility. They then weight the related plans and demands for the facility. They then weight the procurement options in order to determine whether the PPP procurement options in order to determine whether the PPP procurement is more efficient than the conventional procurementprocurement is more efficient than the conventional procurement
q Unsolicited ProjectsUnsolicited Projectsll For an unsolicited project, a private company (project proponent) For an unsolicited project, a private company (project proponent)
submits a project proposal, and then the competent authority submits a project proposal, and then the competent authority examines and evaluates the contents and value for money of the examines and evaluates the contents and value for money of the private proposal, and designates it as a PPP projectprivate proposal, and designates it as a PPP project
6
Competent AuthorityReview by PIMAC
Competent Authority
Competent Authority
Selection of PPP Project
Designation as the PPP Project
Announcement of RFPs
Submission of Project Proposals
Evaluation and Selection ofPreferred Bidder
VFM Test
Negotiation and Contract Award(Designation of Concessionaire)
Application for Approval of Detailed Implementation Plan
Construction and Operation
Competent Authority
Private Sector → Competent Authority
Competent Authority
Competent Authority →Preferred Bidder
Concessionaire →Competent Authority
Concessionaire
Solicited ProjectSolicited Project
Procurement Steps of a Solicited Project
7
Submission of Project Proposal
VFM Test
Notification of ProjectImplementation
PIMAC
Private Sector →Competent Authority
Competent Authority →Proponent
Announcement of RFPs
Submission of Project Proposals
Evaluation and Selection ofPreferred Bidder
Negotiation and Contract Award(Designation of Concessionaire)
Application for Approval of Detailed Implementation Plan
Construction and Operation
Competent Authority
Private Sector → Competent Authority
Competent Authority
Competent Authority →Preferred Bidder
Concessionaire →Competent Authority
Concessionaire
Unsolicited ProjectUnsolicited Project
Procurement Steps of an Unsolicited Project
2. VFM : The Theory
qq What is Value for Money? What is Value for Money?
ll The best available outcome after taking account of all benefits, costs and The best available outcome after taking account of all benefits, costs and risk over the whole life of the project (HM TREASURY)risk over the whole life of the project (HM TREASURY)
ll Not lowest priceNot lowest price
qq Why it is Used?Why it is Used?
ll Seek the best use of available resourcesSeek the best use of available resources
ll Efficient and effective public service deliveryEfficient and effective public service delivery
ll “ The competent authority uses VFM reports as basic material to make a “ The competent authority uses VFM reports as basic material to make a judgment on whether to move forward with the PPP project proposed by judgment on whether to move forward with the PPP project proposed by the private proponent” according to the Article 7, Paragraph 3 of the the private proponent” according to the Article 7, Paragraph 3 of the Enforcement Decree of the PPP ActEnforcement Decree of the PPP Act
9
The VFM Concept
qq VFM is often a comparative assessmentVFM is often a comparative assessmentll Requires a benchmark cost : PSC (Public Sector Comparator)Requires a benchmark cost : PSC (Public Sector Comparator)
qq PSC is a benchmarking and evaluation tool : a Key toolPSC is a benchmarking and evaluation tool : a Key toolll Benchmarks the cost of government service delivery Benchmarks the cost of government service delivery ll Evaluates whether VFM is delivered from bidsEvaluates whether VFM is delivered from bids
qq A Procurement principle, not only for PPPA Procurement principle, not only for PPP
qq Adopted by different countries to meet governmentAdopted by different countries to meet government’’s s procurement practicesprocurement practicesll Not a universal toolNot a universal tool
qq Applied on a project or program basisApplied on a project or program basis
qq Innovation, asset utilization, risk sharing, competition, service Innovation, asset utilization, risk sharing, competition, service integration ate main key drivers of VFMintegration ate main key drivers of VFMll Presence of VFM drivers confirms suitability for PPPPresence of VFM drivers confirms suitability for PPP
10
Key Elements of VFM
qq Promote whole life costing early in the projectPromote whole life costing early in the project’’s development s development
qq Assist in assessing the project affordabilityAssist in assessing the project affordability
qq Provide a means for demonstrating VFMProvide a means for demonstrating VFMll Provide a consistent benchmarking and evaluation toolProvide a consistent benchmarking and evaluation tool
qq Encourage bidding competition Encourage bidding competition
qq Based on :Based on :ll Reference Project Reference Project ll Risk analysis Risk analysis ll Cash flow over the life of the project (inflation, cost, revenue, discount Cash flow over the life of the project (inflation, cost, revenue, discount
rate..)rate..)ll Government procurement costs to asses project affordabilityGovernment procurement costs to asses project affordability
11
The Role of PSC
12
qq Compare to PSC or between biddersCompare to PSC or between bidders
qq Presence of VFM confirms suitability for PPP.Presence of VFM confirms suitability for PPP.
NPV of Transferable
Risk
PSC PFI
NPV of PPP Contract
QUANTITATIVE VFMNPV of
Retained Risk
NPV of CompetitiveNeutrality
NPV of Raw PSC
NPV of Retained Risk
VFM Assesment
3. VFM : The Practice in Korea
14
qq PIMAC of KDIPIMAC of KDI is in charge of VfM test as stipulated by the is in charge of VfM test as stipulated by the PPP ActPPP Act
qq VfM test is carried out in accordance with ‘Guidelines for VfM test is carried out in accordance with ‘Guidelines for implementation of VfM Test/Review of Proposal for implementation of VfM Test/Review of Proposal for unsolicited BTO projects’.unsolicited BTO projects’.
qq Five interim review meetings are held during the VfM testFive interim review meetings are held during the VfM test
qq The duration of each project research should take up to six The duration of each project research should take up to six monthsmonths
qq Same methodology and procedure are applied both to VfM Same methodology and procedure are applied both to VfM Test and Review of ProposalTest and Review of Proposal
qq Objectivity, consistency, independence as well as Objectivity, consistency, independence as well as professional expertise are important elements in conducting professional expertise are important elements in conducting VfM tests.VfM tests.
Implementation
15
qq A VfM test is carried out by a multiA VfM test is carried out by a multi--disciplinary research teamdisciplinary research team
qq KDI (Project Manager)KDI (Project Manager)ll Experts with relevant skills and expertise for the project are selected at Experts with relevant skills and expertise for the project are selected at
the preliminary stagethe preliminary stage
qq External experts (selected from human resource pool)External experts (selected from human resource pool)ll Demand forecasting : university professorsDemand forecasting : university professorsll Cost estimation: engineering companies Cost estimation: engineering companies ll Accounting: accounting firmsAccounting: accounting firms
Organization of a Research Team
16
qq Phase 1: Feasibility study (Decision to Invest)Phase 1: Feasibility study (Decision to Invest)ll The costThe cost-- benefit analysis is conducted to determine feasibility of the benefit analysis is conducted to determine feasibility of the
project from a national economy perspective.project from a national economy perspective.
qq Phase 2: Value for Money Assessment (Decision on PFI)Phase 2: Value for Money Assessment (Decision on PFI)ll The government payment of PSC (Public Sector Comparator) is The government payment of PSC (Public Sector Comparator) is
compared against that of PFI (Private Finance Initiative) to assess compared against that of PFI (Private Finance Initiative) to assess whether the PFI achieves VfM. whether the PFI achieves VfM.
qq Phase 3: Formulation of PFI alternativesPhase 3: Formulation of PFI alternativesll Based on the results of phase 2, an appropriate PFI alternatives are Based on the results of phase 2, an appropriate PFI alternatives are
formulatedformulatedll The level of project cost, user fee, subsidy scale, etc. are suggested from The level of project cost, user fee, subsidy scale, etc. are suggested from
the government.the government.
qq Phase 4: Award bonus points to the initial proponentPhase 4: Award bonus points to the initial proponentll Bonus points (10% max.) awarded to the initial proponent are estimated Bonus points (10% max.) awarded to the initial proponent are estimated
based on the results of VfM tests and the quality of the proposal.based on the results of VfM tests and the quality of the proposal.
Scope of a VFM Test
UnsolicitedUnsolicited
With Public PlanSolicited
Private Finance InitiatePFIp
(based on proposal)
PFIp (proposal) PFIG(research team)PFIG (research team)
Public Sector Comparator
PSCp
(estimated by research team)
PSCp (research team) PSCG
(research team)PSCG (research team)
17
VfM Analysis Implementation MethodVfM Analysis Implementation MethodVfM Analysis Implementation MethodVfM Analysis Implementation Method
Setting Comparators for VFM Test
18Implementation of PPP Project Rejection
Calculation of bonus points
Project Proposal(PFI0)
Construction of PSC(PSC0)
Construction of PSC1, PFI1
Construction of PFI2-i,
PFI Alternative (PFI2*)
VFM test of private proposal(VFM1=PSC1-PFI1≥0)
VFM test of PFI alternative(VFM2=PSC1-PFI2 * ≥0)
Feasibility analysis
N
N
N
Y
Y
Phase 1
Phases3 & 4
Phase 2
Flowchart of a VFM Test (Unsolicited)
Flowchart of a VFM Test (Unsolicited with Public Plan)
Construction of PSC (PSCp )
VFM test (VFMP1) VFM test (VFMG1)
Construction of PFIs2
Calculation of Bonus Points(VFMp )
Calculation of Bonus Points(VFMp )
PFI Alternative (PFI2* )
With bigger NPV PFI Alternative (PFI2
* )With bigger NPV
Rejection RejectionImplementation of PPPImplementation of PPP
VFM test(VFMP2=PFIp1-PFIp2≥0)
VFM test(VFMg2=PFIg1-PFIg2≥0)
PSCp1, PFIs1 PSCG1, PFIG1
N
Y
Y Y
N N
Y Y
YY
N N
PSC by Public Plan (PSCG)
Phase 1
Phase 2
Phases3 & 4
Construction of PFIs2
Feasibility Test (PSCp PSCG)
Project Proposal (PFIp)
Construction of PSC (PSCG)
Feasibility Test (PSCG)
VFM test (VFMG1)
Construction of PFI AlternativeConstruction of PFI Alternative
RejectionRejectionImplementation of PPPImplementation of PPP
N
Y
N
Y
Construction of PSCG1, PFIG1
Phase 1
Phase 2
Phases3 & 4
Flowchart of a VFM Test (Solicited Project)
21
qq Assess project feasibility and necessity in the context of Assess project feasibility and necessity in the context of national economy and policy directionsnational economy and policy directions
qq CostCost--benefit analysis method is used to assess the economic benefit analysis method is used to assess the economic feasibility of a projectfeasibility of a projectll CBA is conducted in accordance with sectoral guidelines (e.g. roads, CBA is conducted in accordance with sectoral guidelines (e.g. roads,
railroads, ports, seaports, dams, and environment facilities) for PFS railroads, ports, seaports, dams, and environment facilities) for PFS (Preliminary Feasibility Study)(Preliminary Feasibility Study)
ll B/C ratios calculated based on Estimation of demand, costs, and B/C ratios calculated based on Estimation of demand, costs, and benefitsbenefits
ll Sensitivity analysisSensitivity analysis
qq Policy analyses, if necessary, are carried outPolicy analyses, if necessary, are carried out
Phase 1: Feasibility Study (1)
22
qq Setting a PSC (Public Sector Comparator)Setting a PSC (Public Sector Comparator)ll Setting an appropriate PSC option is very important both to feasibility and Setting an appropriate PSC option is very important both to feasibility and
VfM of a projectVfM of a project
qq A basic assumption of VfM test (including FS) is that theA basic assumption of VfM test (including FS) is that the same same level of servicelevel of service will be provided by both PSC and PFI optionswill be provided by both PSC and PFI optionsll In reality, a PSC option that is compatible with PFI proposal is formulatedIn reality, a PSC option that is compatible with PFI proposal is formulated
qq Total, (risk adjusted) wholeTotal, (risk adjusted) whole--ofof--life cost of the project is life cost of the project is estimated if government is to undertake the project.estimated if government is to undertake the project.
qq User fee and project cost of PSC are not necessarily same as User fee and project cost of PSC are not necessarily same as those of PFIthose of PFIll The user fee of PFI is usually larger than that of PSCThe user fee of PFI is usually larger than that of PSC
Phase 1: Feasibility Study (2)
23
qq Policy analyses are carried out if necessaryPolicy analyses are carried out if necessaryll Evaluation in qualitative/quantitative terms whether the project is justified Evaluation in qualitative/quantitative terms whether the project is justified
in relation to relevant policy issuesin relation to relevant policy issuesll Relevant policy issues: balanced regional development; consistency with Relevant policy issues: balanced regional development; consistency with
higher level plan and policy directions; and environment impact analysis, higher level plan and policy directions; and environment impact analysis, etc.etc.
qq The overall feasibility of a project is assessed based on The overall feasibility of a project is assessed based on economic and policy analyseseconomic and policy analyses
qq If the FS results demonstrate that the project is feasible, then If the FS results demonstrate that the project is feasible, then VfM assessment ensues. VfM assessment ensues. ll If not, the VfM test process as a whole is suspended, and PIMAC If not, the VfM test process as a whole is suspended, and PIMAC
recommends the Competent Authority to reject the project proposal.recommends the Competent Authority to reject the project proposal.
Phase 1: Feasibility Study (3)
24
qq Government spending of the PSC is compared against Government spending of the PSC is compared against government payment requested by PFI proposal to assess if government payment requested by PFI proposal to assess if PPP procurement improves the value of tax payer’s moneyPPP procurement improves the value of tax payer’s money
qq Features of VfM assessmentFeatures of VfM assessmentll It assists government making decision on appropriate procurement It assists government making decision on appropriate procurement
options: conventional public procurement vs. PPP procurement.options: conventional public procurement vs. PPP procurement.ll It provides a quantitative VfM level and a justification for the decision It provides a quantitative VfM level and a justification for the decision
on procurement option.on procurement option.ll It provides a reliable benchmark and specifies project scope.It provides a reliable benchmark and specifies project scope.ll It encourages project appraiser to consider risks early in the project It encourages project appraiser to consider risks early in the project
lifecycle, and address risk transfer options in the bidding process.lifecycle, and address risk transfer options in the bidding process.ll It reduces negotiation time and increases the efficiency of bidding It reduces negotiation time and increases the efficiency of bidding
costs as the scope of private sector bids are more aligned with the costs as the scope of private sector bids are more aligned with the public sector needs, and risk transfer profiles.public sector needs, and risk transfer profiles.
Phase 2: VFM Assessment (1)
25
qq Cost items adjusted for competitive neutrality between PSC Cost items adjusted for competitive neutrality between PSC and PFI optionsand PFI options
ll Revenue from user fee is deducted from government payment of PSCRevenue from user fee is deducted from government payment of PSC
ll Revenue from supplementary project is taken into account in Revenue from supplementary project is taken into account in consideration of both optionsconsideration of both options
ll VAT and other tax payments are adjustedVAT and other tax payments are adjusted
ll Same amount and payment schedule of land acquisition is applied to Same amount and payment schedule of land acquisition is applied to both optionsboth options
ll Administrative costs incurred by governments for project management Administrative costs incurred by governments for project management are excluded from both optionsare excluded from both options
ll Insurance fee are estimated in different ways, reflecting the difference Insurance fee are estimated in different ways, reflecting the difference in market valuation of project risk by project ownersin market valuation of project risk by project owners
ll Additional government support if requested by private company is Additional government support if requested by private company is included in both options based on estimated spendingincluded in both options based on estimated spending
Phase 2: VFM Assessment (2)
26
Item PSC PFI
Capital costs
Project costs
Constructioncost
(1) Cost of survey(2) Design cost(3) Construction cost
Constructioncost
(1) Cost of survey(2) Design cost(3) Construction cost
Landacquisitioncost
(4) Compensation for landand other possessions
Landacquisitioncost
(4) Compensation for landand other possessions
Supplementarycost
(5) Cost for feasibility study(6) Cost for transportation
impact assessment(7) Cost for environmental
impact assessment(8) Cost for supervision(9) Insurance costs
Supplementarycost
(5) Cost for feasibility study(6) Cost for transportation
impact assessment(7) Cost for environmental
impact assessment(8) Cost for supervision(9) Insurance costs
(10) Cost for operation equipment (10) Cost for operation equipment(11) Taxes and fees (11) Taxes and fees(12) Business setup costs (12) Business setup costs
Financing costs (13) Financing costs (13) Financing costs
operating costs(14) Operation costs(15) Maintenance costs(16) Management and supervision costs
(14) Operation costs(15) Maintenance costs(16) Management and supervision costs
① Base cost born by the government
(Capital costs + operating costs)- operating revenue
Construction subsidy + land acquisition cost +additional government support
② Risk adjustment costs Cost and time overrun
Total government payment ① + ②
Phase 2: VFM Assessment (3)
27
qq Present value of government payments for PSC and PFI Present value of government payments for PSC and PFI options are estimated (discount rate = 5.5%) and VfM(%) is options are estimated (discount rate = 5.5%) and VfM(%) is calculatedcalculated
qq GP(PSC) = Capital costs + operating costs GP(PSC) = Capital costs + operating costs –– RevenueRevenue
qq GP(PFI) = Construction subsidy + Compensation costs + GP(PFI) = Construction subsidy + Compensation costs + Additional government supportAdditional government supportll GP(PFI) is the government subsidy requested by the private party in GP(PFI) is the government subsidy requested by the private party in
the project proposalthe project proposal
)()()((%)
PSCGPPFIGPPSCGPVfM -
=
Phase 2: VFM Assessment (4)
28
qq Qualitative VfM assessmentQualitative VfM assessmentll Allocation of risks (construction, operation risks, etc.)Allocation of risks (construction, operation risks, etc.)
ll Improvement of service qualitiesImprovement of service qualities
ll And other ripple effects (positive externalities): Promote the financial And other ripple effects (positive externalities): Promote the financial market through the adoption of an advanced financial technique, etc.market through the adoption of an advanced financial technique, etc.Ø Quantification of project risk transfer is not satisfactory and those qualitative effects are
not incorporated into overall VfM assessment so far
Phase 2: VFM Assessment (5)
29
qq Financial analysis and sensitivity analysis are carried out to Financial analysis and sensitivity analysis are carried out to assess the profitability (bankability) of a projectassess the profitability (bankability) of a project
qq Based on the VfM assessment and financial analyses, PFI Based on the VfM assessment and financial analyses, PFI alternatives including the following components, are alternatives including the following components, are formulated:formulated:ll Total project costsTotal project costsll User feeUser feell IRR (Internal Rate of Return)IRR (Internal Rate of Return)ll Total government paymentsTotal government paymentsll Other components related to the implementation of the projectOther components related to the implementation of the project
qq The Competent Authority chooses the most appropriate PFI The Competent Authority chooses the most appropriate PFI option and invites third parties to tenderingoption and invites third parties to tenderingll If it is impossible to formulate a PFI alternative that delivers VfM at a If it is impossible to formulate a PFI alternative that delivers VfM at a
reasonable level of IRR, then the PFI option is rejectedreasonable level of IRR, then the PFI option is rejected
Phase 3: Formulation of PFI Alternatives
30
qq The VfM test team makes decision on bonus points (10% The VfM test team makes decision on bonus points (10% max) to be awarded to the initial proponents based on the max) to be awarded to the initial proponents based on the VfM(%) and quality of the proposalVfM(%) and quality of the proposal
qq The quality of a proposal is evaluated based on the following The quality of a proposal is evaluated based on the following criteria:criteria:① Priority of the project in the mid- to long-term government investment
plan (10 points)② Composition of equity investors (10 points)③ Excellency of construction and operation plan (30 points)④ Accuracy of demand forecast (30 points)⑤ Prior consultation with relevant government agencies and plan of
addressing of civil complaints (10 points)⑥ Adequacy of required documentation (10 points)
Phase 4: Bonus Points for Initial Proponent (4)
31
qq The VfM test sets the bottom line to meet the condition ofThe VfM test sets the bottom line to meet the condition of‘VfM≥0’‘VfM≥0’ in selecting preferred bidder and following phases of a in selecting preferred bidder and following phases of a project.project.
qq VfM reports are used as an important reference when tender VfM reports are used as an important reference when tender evaluation committee conducts their work.evaluation committee conducts their work.
qq VfM reports provide useful information to prompt negotiation VfM reports provide useful information to prompt negotiation process.process.
qq VfM reports are used as reference when exVfM reports are used as reference when ex--post VfM tests are post VfM tests are conducted.conducted.
Use of VFM Test Results
Case Study:
Light Rail Transit of New Bundang Line
Part-02
1. Project Overview
Jeongja
Kwankyo
12.7km
qq SiteSite MapMap
Rail Transit of New Bundang LineRail Transit of New Bundang Line
Keymap
SB01
SB02
SB03
SB04
34
Project Overview
qq Project SizeProject Size
ll Total length : 12.7km (main line : 11.1km, entranceTotal length : 12.7km (main line : 11.1km, entrance--exit lines : 1.6km)exit lines : 1.6km)
ll Number of Stations : 6 (underground: 5, ground: 1)Number of Stations : 6 (underground: 5, ground: 1)
ll Operation at Commencement : 6 railroad cars 7 operations/dayOperation at Commencement : 6 railroad cars 7 operations/day
ll Operation at Termination : 6 railroad cars 7 operations/dayOperation at Termination : 6 railroad cars 7 operations/day
ll Minimum Operation Interval : 5.0 min (commencement year, 2014)Minimum Operation Interval : 5.0 min (commencement year, 2014)3.5 min (target year, 2044)3.5 min (target year, 2044)
qq Project PeriodProject Period
ll Construction Period : 2009~2014Construction Period : 2009~2014
ll Gratuitous Operation Period : 2014~2044 (30years)Gratuitous Operation Period : 2014~2044 (30years)
35
Project Overview
qq Total Investment CostTotal Investment Costll Total Project Cost : 1,136.6 billion WonTotal Project Cost : 1,136.6 billion Wonll Construction Cost : 926.5 billion WonConstruction Cost : 926.5 billion Wonll Total Investment Cost : 1,551.1 Billion WonTotal Investment Cost : 1,551.1 Billion Wonll Financial Subsidy during Financial Subsidy during Construction (current) : 728.2 Billion Won
(46.9% of Total investment cost)ll Total Private Sector Investment : 822.9 Billion WonTotal Private Sector Investment : 822.9 Billion Won
(53.1% of total investment cost)ll Minimum Operation Interval : 5.0 min (commencement year, 2014)Minimum Operation Interval : 5.0 min (commencement year, 2014)
3.5 min (target year, 2044)
qq Rate of Return and Usage FeeRate of Return and Usage Feell Real Rate of Return : 7.24%(After Tax 6.52%)Real Rate of Return : 7.24%(After Tax 6.52%)ll Usage Fee : 130.0 billion Won (June 2006, Credit card usage basis)Usage Fee : 130.0 billion Won (June 2006, Credit card usage basis)
36
Project Overview
qq Financial Aid Financial Aid
ll 566 billion Won during construction period i.e. 49.8% of total project cost566 billion Won during construction period i.e. 49.8% of total project cost
qq Support for Compensation CostsSupport for Compensation Costsll Request the government’s responsibility and cost charges to be Request the government’s responsibility and cost charges to be
completed before the commencement of constructioncompleted before the commencement of construction
qq No Request for Guarantee of Operation RevenueNo Request for Guarantee of Operation Revenue
qq Support for Toll Fee DiscountSupport for Toll Fee Discountll Request for financial aid in case of free rides and passenger discounts Request for financial aid in case of free rides and passenger discounts
excluding student discountsexcluding student discounts
qq Aid of Other Administrative CostsAid of Other Administrative Costs37
Requests for Gov’t Subsidy
2. Estimation of Transportation Demand
qq Traditional 4Traditional 4--Step Model of Transportation Demand EstimationStep Model of Transportation Demand Estimation
ll Trip Generation → Trip Distribution → Mode Choice → Trip AssignmentTrip Generation → Trip Distribution → Mode Choice → Trip Assignment
qq Additional adjustment only in the case of a new development Additional adjustment only in the case of a new development business using OD and network provided by KTDBbusiness using OD and network provided by KTDB
qq Estimation of commuters by station using Emme/2, TransCAD, etc.Estimation of commuters by station using Emme/2, TransCAD, etc.
39
Process of Estimation for Transportation Demand
qq DemandDemand (Origin(Origin –– DestinationDestination Trips)Trips)
Origin
Destination
O/D Trips : Car, Bus, Truck, SubwayO/D Trips : Car, Bus, Truck, Subway
40
Estimation for Transport Demand
Network (Zone, Link, Volume – Delay Functions)Network (Zone, Link, Volume – Delay Functions)
qq SupplySupply (Highway/Transit(Highway/Transit Network)Network)
Zone
Transit line summary
Transit line itinerary(line by line)
41
Estimation for Transport Demand
Traffic Assignment resultTraffic Assignment result
qq FutureFuture TrafficTraffic DemandDemand
ConstructionStation Upbound Downbound
Jeongja 50,075 25,284 13,191 53,626
SB01 6,894 1,721 8,504 3,609
SB02 19,105 4,349 4,100 14,916
SB03 22,304 3,034 2,722 20,369
SB04 1,329 3,415 3,566 1,006
Kwankyo 17,923 - - 15,846
Total 117,630 37,803 32,083 109,372
Jeongja
Kwankyo
Year : 2015 (Unit : trip/days)
SB01
SB02
SB03
SB04
42
Estimation for Transport Demand
3. Estimation of Cost
qq Method of Construction Cost EstimationMethod of Construction Cost Estimationll Estimated on the basis of the proposed design and recent actual construction costsEstimated on the basis of the proposed design and recent actual construction costsll Referred to the “New Bundang Line: Kangnam ~ JungJa” Double Track Subway Referred to the “New Bundang Line: Kangnam ~ JungJa” Double Track Subway
construction project, expected to directly connected to this project and is in construction project, expected to directly connected to this project and is in completion of government agreementcompletion of government agreement
qq Method of Supplementary Cost EstimationMethod of Supplementary Cost Estimationll Estimate the cost according to the project compensation standard and standard Estimate the cost according to the project compensation standard and standard
estimating, and by applying estimating, and by applying 「「Revised and Complemented Study on Standard Revised and Complemented Study on Standard Guidelines for Preliminary Feasibility Studies on Railroad Sector Projects (4Guidelines for Preliminary Feasibility Studies on Railroad Sector Projects (4thth
edition)edition)」」ll Basic design cost is generally not reflected in PFI, but is included in the case of Basic design cost is generally not reflected in PFI, but is included in the case of
PSCPSCqq Cost for Trial run : Estimate the cost for six months including both Cost for Trial run : Estimate the cost for six months including both
technical trial run and business trial runtechnical trial run and business trial runll During PFI construction period, insurance cost includes construction insurance, During PFI construction period, insurance cost includes construction insurance,
preliminary benefit lost insurance, user indemnity responsibility insurance, movable preliminary benefit lost insurance, user indemnity responsibility insurance, movable asset insurance, etc. PSC excludes user indemnity responsibility insurance, asset insurance, etc. PSC excludes user indemnity responsibility insurance, preliminary benefit lost insurancepreliminary benefit lost insurance
ll Financial supplementary cost of PFI consists of interest payment cost which occurs Financial supplementary cost of PFI consists of interest payment cost which occurs according to the capital financing plan, and excludes PSCaccording to the capital financing plan, and excludes PSC.
44
Result of Estimation for Total Project Cost
qq Result of Total Project Cost EstimationResult of Total Project Cost Estimation
PFI(0) PSC(0) Reference
Construction Cost 926,500 1,092,879
Cost of survey 0 6,698
Design Cost 29,400 38,307
Supplementary cost 53,293 74,479Cost for design supervision, Cost for supervision, Cost for transportation impact assessment, Cost for construction project management, etc.
Trial run cost 4,047 6,150
Construction Insurance Cost 13,943 14,492
Project Implementation Guarantee Insurance 911 0
Financial Supplementary Cost 8,680 0
Operation Equipment Cost 74,829 40,648
Taxes and fees 0 0
Project Setup Cost 24,997 0
Land Compensation Cost 238,057 185,189
Total Project Cost 1,374,657 1,458,842
Vehicle Purchase Cost 82,449 78,282
(in millions of Korean won)
45
Result of Estimation for Total Project Cost
qq Method of Operating Cost Estimation Method of Operating Cost Estimation ll Of the proposed operation cost, wellOf the proposed operation cost, well--grounded portion of the cost will grounded portion of the cost will
incorporate the initiator’s intention to the maximum, but unfounded portion incorporate the initiator’s intention to the maximum, but unfounded portion will be subject to a separate criteria assuming that it is operated by the will be subject to a separate criteria assuming that it is operated by the government. government.
ll Estimated on the basis of operation plan and operation personnel plan, Estimated on the basis of operation plan and operation personnel plan, both of which are recalculated according to the reboth of which are recalculated according to the re--estimated demandestimated demand
ll Major costs : Labor cost, General management cost, Maintenance cost, Major costs : Labor cost, General management cost, Maintenance cost, Electricity cost, Additional purchase cost, alternative investment costElectricity cost, Additional purchase cost, alternative investment cost
qq Operation Personnel PlanOperation Personnel Planll Maintenance staff: Track maintenance & repair (Engineering, Track, Maintenance staff: Track maintenance & repair (Engineering, Track,
Building, Station equipment repair), electric railway maintenance & repair Building, Station equipment repair), electric railway maintenance & repair (Electricity, Signal, Telecommunication system and substation facility repair)(Electricity, Signal, Telecommunication system and substation facility repair)
ll Vehicle maintenance staff, Operation control staff, Train crew, Station staff, Vehicle maintenance staff, Operation control staff, Train crew, Station staff, AdministratorAdministrator
46
Result of Estimation for Operating Cost
qq Result of Personnel Cost EstimationResult of Personnel Cost Estimationll Based on the average wage of Seoul Metro and Seoul Metropolitan Based on the average wage of Seoul Metro and Seoul Metropolitan
Rapid Transit CorporationRapid Transit Corporation
qq Result of Maintenance Cost EstimationResult of Maintenance Cost Estimationll Classified into Station building maintenance, carriage maintenance, Classified into Station building maintenance, carriage maintenance,
System maintenance, etc. System maintenance, etc.
ll Estimate the maintenance cost based on the cost calculated in the Estimate the maintenance cost based on the cost calculated in the New Bundang Line project New Bundang Line project
ll Estimate carriage site maintenance & repair cost with reference to Estimate carriage site maintenance & repair cost with reference to data provided by project initiatordata provided by project initiator
qq Result of Other Operation Cost EstimationResult of Other Operation Cost Estimationll Estimate insurance cost, credit card commission cost, etc. with Estimate insurance cost, credit card commission cost, etc. with
reference to rate of cost presented by proposed by project initiatorreference to rate of cost presented by proposed by project initiator
47
Result of Estimation for Operating Cost
qq Result of Operation Cost estimation Result of Operation Cost estimation
(in millions of Korean Won)
PFI(0) PSC(0) Reference
Labor cost 318,036 338,577
General management cost 165,235 118,110
Maintenance cost 583,216 787,456
Insurance cost 82,403 81,950
Malfunction Asset Substitute cost 52,959 95,768
Total Operation cost 1,201,848 1,421,861
48
Result of Estimation for Operating Cost
4. Feasibility Study
Cost Benefit
Construction OperationOperation Cost Reduction
Reduction in Commute Time
Reduction in Traffic Accidents
Reduction in Environmental Cost
2008 160.2 - - - - -
2009 332.2 - - - - -
2010 1,721.8 - - - - -
2011 3,045.7 - - - - -
2012 2,915.6 - - - - -
2013 4,316.1 - - - - -
2014 1,988.2 50.1 89.6 190.1 10.3 16.6
2015 - 200.3 358.3 760.6 41.1 66.5
2020 - 218.7 363.6 811.9 38.5 76.9
2025 - 244.0 490.2 1,109.4 46.8 89.6
2030 - 244.0 504.1 1,183.7 47.9 100.5
2035 - 258.0 506.9 1,198.5 48.1 102.7
2040 - 336.7 506.9 1,198.5 48.1 102.7
2044 -3,782.0 252.5 380.2 898.9 36.1 77.0
Sum* 15,071.3 7,725.1 14,151.8 32,658.4 1,375.2 2,787.6*
(in millions of Korean Won)
qq PV( B ) = 14,611.05 , PV( C ) = 12,919.1 , B/C = 1.131 , IRR = PV( B ) = 14,611.05 , PV( C ) = 12,919.1 , B/C = 1.131 , IRR = 6.65% , NPV = 1,691.96.65% , NPV = 1,691.9
* Sum is the summation from 2008 through 2044 50
Results of Economic Analysis
5. Quantitative VFM Analysis
qq Formulation of PFI AlternativesFormulation of PFI Alternatives
Contents
VFM
PSC(1)Project finance alternative where the rate of bidding was applied to PSC(0) Public transportation integrated payment system applied
PFI(1) Reassessed demand applied to project initiator’s PFI(0) proposal (e.g. cost, revenue rate, user fee)
52
Basic Assumptions for Analysis
qq Basic Assumptions for Analysis (financial conditions)Basic Assumptions for Analysis (financial conditions)
PSC PFI
Construction Period Oct. 2009~Sep. 2014 (60months) Oct. 2009~Sep. 2014 (60months)
Operating Period Oct. 2014~Sep. 2044 (30 yrs) Oct. 2014~Sep. 2044 (30 yrs
Rate of Interest
5.25%(Oct. 2005 ~Sep. 2006 5-year
provincial bonds weighted average interest)
5.25%(Oct. 2005 ~Sep. 2006 5-year provincial
bonds weighted average interest)
Financial Discount Rate 5.50(constanct) 5.50(constant)
Provincial Bond Procurement Cost
Total required fund procured through provincial bonds
Total financial support fund procured through provincial bonds
Conditions for Repayment 5-year due full repayment 5-year due full repayment
Own Capital - 20.0
Other’s Capital - 80.0
Consumer Price Index 4.0 4.0
53
Basic Assumptions for Analysis
qq Result of Total Project Cost and Operating Cost CalculationsResult of Total Project Cost and Operating Cost Calculations(in millions of Korean won)
PSC(1) PFI(1)
Cost of Survey 64 -
Design Cost 376 267
Construction Cost 10,466 9,265
Compensation Cost 1,894 1,894
Supplementary Costs 836 738
Cost for Operation Equipment 836 738
Project Setup Cost - 244
Financing Cost 3,369 2,025
Total 17,426 15,172
Labor Cost 3,386 3,180
General Management Cost 1,112 1,571
Insurance Cost 819 818
Electric/Water Supply Charges 2,329 1,405
Maintenance Cost 3,239 2,232
Alternative Investment Cost 4,381 2,208
Operation Total 15,267 11,416
54
Result of LCC Calculations by Category
Category PSC(1) PFI(1)
Facility Invest-ment Cost
Total Project Costs
Construction Cost(1) Cost of Survey(2) Design Cost(3) Construction Cost
64376
10,466
0267
9,265
Compensation Cost (4) Compensation for Land and other Possessions 1,894 1,894
Supplementary Cost
(5) Construction Supervision Cost(6) Construction Project Managing Cost(7) Trial Run Cost(8) Financing costs(9) Others
316195630
262
1941503772
285
(10) Cost for Operation Equipment 421 739
(12) Cost for Operation Preparation 0 244
Sum of Total Project Cost 14,057 13,147
Financing Costs (13) Financing Costs 3,369 2,025
Operation Costs(14) Operation and Management Costs
(Labor cost, Overhead expenses)(15) Maintenance Costs(16) Cost for Gov’t monitoring and oversee
5,3189,949
0
5,5705,845
0
① Base Cost born by gov’t
Provincial bonds repayment at face valueFinancial Cost (Provincial Bonds)Operating CostOperating RevenueAffiliate Project Revenue Financial Subsidy during Operating period
11,5543,369
15,267(8,843)(3,656)
0
6,9442,025
000
2,927
② Risk Adjustment Costs 0 0
Total Gov’t Payment (①+②) 17,690 11,895
Sum of Current Value 8,355 5,671
55
Cash Payment Summary Sheet
PSC(1) PFI(1) Reference
1. Total Amount of Provincial Bonds (constant) 14,057 7,870
A. Total Construction Subsidy 0 5,977
Initial Amount of Construction Subsidy 0 5,383
Additional (Reduced) Amount of Construction Subsidy 0 594
B. Compensation for Land 0 1,894
2. Total Gov’t Payment (constant) 16,533 11,437
A. Provincial Bonds Repayment at Face Value 11,554 6,469
B. Financial Cost (Provincial Bond Interests) 3,369 1,886
C. Management Cost 15,284 0
D. Operation Revenue (10,018) 0
E. Affiliate Project Revenue (3,656) 0
F. Financial Subsidy during Operating Period 0 3,082
3. Total Gov’t Payment at Current Price 7,994 5,400
4. VfM Amount - 2,594 (PSC(1)-PFI(1))
5. VFM Rate - 32.45% (PSC(1)-PFI(1))/PSC(1)*100)%
6. Real Revenue Rate before Tax - 7.24%
56
Result of Quantitative VFM Analysis
6.Formulation of PFI Alternatives
qq Total Project Cost EstimateTotal Project Cost Estimatell Apply more reasonable and lower amount (competitive amount) after Apply more reasonable and lower amount (competitive amount) after
comparing PFI and PSC costs by categorycomparing PFI and PSC costs by category
PSC(1) PFI(0)PFI Alternatives
PSC(2-1) PSC(2-2)
Cost of Survey 64 - 64 64
Design Cost 376 267 376 376
Construction Cost 10,466 9,265 9,136 9,136
Compensation Cost 1,894 1,894 1,894 1,894
Supplementary Costs 836 759 770 756
Cost for Operation Equipment 421 739 421 421
Project Setup Cost - 245 246 245
Total 14,057 13,160 12,906 12,892
Labor Cost 3,386 3,180 3,180 3,180
General Management Cost 1,130 1,593 1,331 1,331
Insurance Cost 819 820 799 796
Electric/Water Supply Charges 2,329 1,405 1,405 1,405
Maintenance Cost 3,239 2,232 2,232 2,232
Alternative Investment Cost 4,381 2,208 2,460 2,460
Operation Total 15,284 11,439 11,409 11,406
(in millions of Korean won)
58
Result of PFI Alternative Formulation
qq VfM Result VfM Result ll PFI Alternative PSC(2PFI Alternative PSC(2--1) : Estimation of construction subsidy to satisfy 1) : Estimation of construction subsidy to satisfy
6.00% of rate of return 6.00% of rate of return ll PFI Alternative PSC(2PFI Alternative PSC(2--2) : Apply construction subsidy rate (49.8%) 2) : Apply construction subsidy rate (49.8%)
proposed by project initiatorproposed by project initiator
PFI(0)PFI Alternatives
PSC(2-1) PSC(2-2)
Rate of Return 7.24% 6.00% 6.81%
Construction Subsidy/Compensation
Construction Subsidy (Rate) 5,977(53.05%) 4,813(43.70%) 5,477(49.80%)
Amount of Compensation 1,894 1,894 1,894
Current Amount of Gov’t Payment
Provincial Bonds Repayment at Face Value 6,469 5,512 6,058
Financing Cost 1,886 1,607 1,766
Financial Subsidy during Operating Period 3,082 3,082 3,082
Total Gov’t Payment 11,437 10,202 10,907
Current Amount of Gov’t Payment 5,400 4,742 5,117
VfM 2,594 3,252 2,876
VFM Rate 32.45% 40.68% 35.98%
59
Result of PFI Alternative Formulation
60
Thank youThank you