letter

31st May 2013Projct Manager,Qserve ( Pvt. ) Ltd.,No. 31B, Albert Place,Dehiwala.

Dear Sir,

PROPOSED BUILDING OF MOVENPICK CITY HOTEL AT DHARMAPALA MAWARHACOLOMBO 03 FOR SOFTLOGIC CITY HOTELS ( PVT ) LTD.

We are pleased to submit our quotation for above work. Cost for additional concrete filling in skin wall = Rs.

The above prices does not include VAT.Additional time duration for above work - minimum 10 days

We hope that our quotation will meet your requirements and waiting for your kind approval.

Thanking you,

Yours faithfully

C C Mr. Stepahn Anthonisz ( CEO ) - Softlogic City Hotels ( Pvt. ) Ltd. Prof. Chitra Weddikkara ( E.P.M.) - Qserve (Pvt) Ltd.

SummaryPROPOSED MOVENPICK CITY HOTEL PROJECT

SUMMARY

ITEM NODESCRIPTIONRATE (Rs.)

AADDITIONiAdditional concrete filling , formwork & reinforcement for basement second floor area.Total Cost of Addition0.00

BOMMISSIONReduced slab area at basement second floor.iConcrete Work

iiiReinforcement WorkTotal Cost of Ommission 0.00

Total cost for additional ( item 'A' - 'B' ) ( =10,369,924.26 - 1,449,367.20)0.00

Note :01. All above rates are exclusive of VAT.

Break DownPROPOSED MOVENPICK CITY HOTEL PROJECT

V.06 ADDITIONAL COST FOR PILE CAP INSTEAD OF CAPPING BEAM IN GROUND FLOOR FRONT SIDE. ( ALONG GRID 'L' )

Item No.DescriptionUnitQty. Rate ( Rs. )Amount (Rs.)

AAddition and ommission of front pile cap (Along Grid 'L' )iAdditional concrete for pile capm356.9317,081.00972,421.33Rate: BOQ / Concrete / item no F.040.000.00iiAdditional form work for pile capm238.951,337.0052,076.15Rate: BOQ / Formwork / item no F.1510.000.00iiiAdditional reinforcement for pile capt18.04174,640.003,150,505.60Rate: BOQ / Reinforcement / item no F.3090.00

Additional cost for pile cape instead of capping beam in ground floor front side4,175,003.08

Note :01. All above rates are exclusive of VAT.

Block A

REINFORCEMENT QUANTITY OF CAPPING BEAM( ACCORDING TO TENDER DRAWINGS )

Block B

REINFORCEMENT QUANTITY OF CAPPING BEAM( ACCORDING TO NEW DRAWINGS )

Block C

ommit

OMMISSION