2
ROUGH ESTIMATE (PWD 2008) FOR THE PROJECT Construction of 5 Story + 1 Parking at Ground Floor (Total 6 Story) at R-4, S-12, Uttara ,Dhaka. 1 Tk. 20,000.00 2 Tk. 2,539,820.00 Tk. 50,796.40 Tk. 2,590,616.40 145 sqm 8,624.00 Tk. per sqm 1,250,480.00 Tk. 1st Floor 145 sqm 13,119.00 Tk. per sqm 1,902,255.00 Tk. 145 sqm 13,174.00 Tk. per sqm 1,910,230.00 Tk. 145 sqm 13,182.00 Tk. per sqm 1,911,390.00 Tk. 145 sqm 13,217.00 Tk. per sqm 1,916,465.00 Tk. 145 sqm 13,257.00 Tk. per sqm 1,922,265.00 Tk. Tk. 10,813,085.00 i) Tk. 216,261.70 ii) Tk. 223,300.00 iii) Tk. 125,010.00 iv) Tk. 100,000.00 Tk. 664,571.70 Tk. 598,125.00 Tk. 1,036,750.00 Tk. 450,000.00 Tk. 500,000.00 Tk. 50,000.00 Tk. 150,000.00 Tk. 50,000.00 Tk. 1,200,000.00 Tk. 18,125.00 Tk. 72,500.00 Tk. 66,672.00 Tk. 50,000.00 Tk. 285,626.40 Tk. 50,000.00 Tk. 50,000.00 Tk. 10,000.00 Tk. 400,000.00 Tk. 5,037,798.40 Tk. 478,151.79 Tk. - 19,604,223.29 Tk. 3,528,760.19 Tk. 16,075,463.10 Tk. iv)External Electrification iii) External water supply b. Main Gate Less 18% as mentioned in the PWD schedule Contingency (Probable unforeseen expenditure related to work): 2.5.00% on SubTotal J. TESTING OF MATERIALS K. ABORICULTURE / LANDSCAPE L. FIRE FIGHTING (b) Pump & Motor Set i/c Installation Sub Total = Cost of land a. Construction of boundary wall (Total 58.53rm @ Tk. 4880 Per rm) (c) Stand by power (Generator 35 kva) E. ELECTRO-MECHANICAL COMPONENT F. GAS CONNECTION WORKS D. OTHER BUILDING COST Extra cost of Roof Top RCC Water tank : 1000 Gallon @Tk. 100 Per Gallon a) Ground Floor : Consider 50% cost as Parking .5 x 145@ 250 per sqm b) Other Floor : 5 x 145 @ Tk 100 per sqm. 5STORY + 1 PARKING Soil Investigation Construction of Building A. FOUNDATION COST (i) Pile foundation : Plinth area 145sqm, @Tk.17516.00 per sqm a) 1 no. of 6 Passenger lift ,8 stops (1m/s) (d) Compound Light, Wiring System & Other safety system (ii) Add extra 2% cost for wind & earthquake : Plinth area 145 Sqm 5th Floor @ Sub Total H. APPROACH ROAD (rcc) (a) Construction of underground reservoir 9000 gallon @ 50 per gallonn Sub-Total = Sub-Total = @ @ G. CONSTRUCTION OF COMPOUND DRAIN ( 55.56 rm, @Tk.1200 per rm) Add Additional Cost for wind and earthquake 2% of 'B' (a) Supplying and installation of Sub- Station Equipment/ Transformer (Oil Type) (75KVA) ii) Internal Electrification (Consider G.F area cost 50% : 5.5 x 145 sqm @ 1300 per sqm) C. ADDITIONAL SUPERSTRUCTURE COST : @ 2nd Floor 3rd Floor 4th Floor @ Total Grand Total Extra cost of Roof Top & Chilakotha 145sqm @ Tk.1540 Per Sqm Extra cost of Roof Top RCC parapet 55.56 m x 1.25m ht. @Tk. 1800 Per Sqm B. SUPER STRUCTURE (i) Frame structure (1:1.5:3) with stone chips. Gr. Floor (Parking) @ I. PERIMETER WORK i) Internal Sanitary & Water supply (Consider G.F area cost 50% : 5.5 x 145 sqm @ 750 per sqm)

Uttara Project Cost

Embed Size (px)

DESCRIPTION

Project Cost Estimation

Citation preview

  • ROUGH ESTIMATE (PWD 2008) FOR THE PROJECT Construction of 5 Story + 1 Parking at Ground Floor (Total 6 Story) at R-4, S-12, Uttara ,Dhaka.

    1 Tk. 20,000.00 2

    Tk. 2,539,820.00 Tk. 50,796.40 Tk. 2,590,616.40

    145 sqm 8,624.00Tk. per sqm 1,250,480.00Tk.

    1st Floor 145 sqm 13,119.00Tk. per sqm 1,902,255.00Tk. 145 sqm 13,174.00Tk. per sqm 1,910,230.00Tk. 145 sqm 13,182.00Tk. per sqm 1,911,390.00Tk. 145 sqm 13,217.00Tk. per sqm 1,916,465.00Tk. 145 sqm 13,257.00Tk. per sqm 1,922,265.00Tk.

    Tk. 10,813,085.00

    i) Tk. 216,261.70 ii) Tk. 223,300.00 iii) Tk. 125,010.00 iv) Tk. 100,000.00

    Tk. 664,571.70

    Tk. 598,125.00 Tk. 1,036,750.00

    Tk. 450,000.00

    Tk. 500,000.00 Tk. 50,000.00 Tk. 150,000.00 Tk. 50,000.00

    Tk. 1,200,000.00

    Tk. 18,125.00 Tk. 72,500.00 Tk. 66,672.00 Tk. 50,000.00

    Tk. 285,626.40 Tk. 50,000.00 Tk. 50,000.00 Tk. 10,000.00 Tk. 400,000.00 Tk. 5,037,798.40 Tk. 478,151.79 Tk. -

    19,604,223.29Tk. 3,528,760.19Tk.

    16,075,463.10Tk.

    iv)External Electrification

    iii) External water supply

    b. Main Gate

    Less 18% as mentioned in the PWD schedule

    Contingency (Probable unforeseen expenditure related to work): 2.5.00% on SubTotal

    J. TESTING OF MATERIALS K. ABORICULTURE / LANDSCAPE L. FIRE FIGHTING

    (b) Pump & Motor Set i/c Installation

    Sub Total =

    Cost of land

    a. Construction of boundary wall (Total 58.53rm @ Tk. 4880 Per rm)

    (c) Stand by power (Generator 35 kva)

    E. ELECTRO-MECHANICAL COMPONENT

    F. GAS CONNECTION WORKS

    D. OTHER BUILDING COST

    Extra cost of Roof Top RCC Water tank : 1000 Gallon @Tk. 100 Per Gallon

    a) Ground Floor : Consider 50% cost as Parking .5 x 145@ 250 per sqmb) Other Floor : 5 x 145 @ Tk 100 per sqm.

    5STORY + 1 PARKING

    Soil InvestigationConstruction of BuildingA. FOUNDATION COST(i) Pile foundation : Plinth area 145sqm, @Tk.17516.00 per sqm

    a) 1 no. of 6 Passenger lift ,8 stops (1m/s)

    (d) Compound Light, Wiring System & Other safety system

    (ii) Add extra 2% cost for wind & earthquake : Plinth area 145 Sqm

    5th Floor @

    Sub Total

    H. APPROACH ROAD (rcc)

    (a) Construction of underground reservoir 9000 gallon @ 50 per gallonn

    Sub-Total =

    Sub-Total =

    @@

    G. CONSTRUCTION OF COMPOUND DRAIN ( 55.56 rm, @Tk.1200 per rm)

    Add Additional Cost for wind and earthquake 2% of 'B'

    (a) Supplying and installation of Sub- Station Equipment/ Transformer (Oil Type) (75KVA)

    ii) Internal Electrification (Consider G.F area cost 50% : 5.5 x 145 sqm @ 1300 per sqm)

    C. ADDITIONAL SUPERSTRUCTURE COST :

    @2nd Floor 3rd Floor 4th Floor

    @

    Total

    Grand Total

    Extra cost of Roof Top & Chilakotha 145sqm @ Tk.1540 Per Sqm Extra cost of Roof Top RCC parapet 55.56 m x 1.25m ht. @Tk. 1800 Per Sqm

    B. SUPER STRUCTURE(i) Frame structure (1:1.5:3) with stone chips.Gr. Floor (Parking) @

    I. PERIMETER WORK

    i) Internal Sanitary & Water supply (Consider G.F area cost 50% : 5.5 x 145 sqm @ 750 per sqm)

  • ROUGH ESTIMATE (PWD 2008) FOR THE PROJECT Construction of 5 Story + 1 Parking at Ground Floor (Total 6 Story) at R-4, S-12, Uttara ,Dhaka.

    Rate per sqm =Tk.18477.50.00(Excluding the cost of land)Rate per sft =Tk.1718.00(Excluding the cost of land)