Upload
kxanwebteam
View
217
Download
0
Embed Size (px)
Citation preview
8/16/2019 Utility Relocation Report
1/35
Utility Relocation
8/16/2019 Utility Relocation Report
2/35
INTRODUCTION
It is the Texas Department of Transportation’s (TxDOT) mission, through collaboration and
leadership, to deliver a safe, reliable and integrated transportation system that enables the
movement of people and goods.
The employees and leaders of TxDOT take our roles as public servants seriously. We know
that the public and the Texas Legislature have entrusted TxDOT with the state’s resources,
and we must use those resources in a responsible and efficient manner to meet the
following goals:
•
Deliver the Right Projects – Implement effective planning and forecasting processes
that deliver the right projects on-time and on-budget;
•
Focus on the Customer – People are at the center of everything we do;
• Foster Stewardship – Ensure efficient use of state resources;
• Optimize System Performance – Develop and operate an integrated transportation
system that provides reliable and accessible mobility, and enables economic growth;
•
Preserve our Assets – Deliver preventative maintenance for TxDOT’s system andcapital assets to protect our investments;
• Promote Safety – Champion a culture of safety; and
• Value our Employees – Respect and care for the well-being and development of our
employees.
UTILITY RELOCATION PROCEDURES AND POLICIES
Timely utility relocation with minimal disruption of utility services is an important part in thesuccessful delivery of transportation improvements to the citizens of Texas. TxDOT is
committed to continuing the dialogue with the utility industry and contractors to improve the
tilit l ti ti l l f j j t d id l i g T DOT’ g l
8/16/2019 Utility Relocation Report
3/35
be a lengthy and complex process due to coordination efforts among many different entities.
These efforts require a partnership between TxDOT and the utility industry in order to
successfully move projects forward to the construction phase.
PROCEDURES FOR ACCOMMODATION
TxDOT’s utility relocation overarching philosophy includes:
• Avoidance of conflicts;
• Minimize impacts; and
• Relocate if necessary.
TxDOT contracts 900 to 1,000 highway projects annually, the majority of which do not haveutility conflicts or issues. Historically on average 20 percent of these projects have had
outstanding utility adjustments and 10 percent have outstanding right of way to purchase or
clear, at the time the construction contract is awarded. TxDOT obtains the expected
relocation clear dates from the utility, which then becomes a commitment from the utility for
relocation work to be completed by the specified date. Contract provisions are then added to
notify prospective highway construction contractors of the remaining utility relocations.
These provisions place the contractor on notice to work around known utility conflict areas
and include an expected clear date provided by the utility.
When a conflict is identified, TxDOT and the utility jointly evaluate various design options to
avoid the relocation of the utility. However, during the evaluation of design options it may be
determined that conflicts cannot be eliminated. In these cases, both the utility and TxDOT
will investigate options to minimize the impact of the conflict. Lastly, the utility will relocate
to eliminate the transportation improvement conflict. This procedure is routinely
accomplished prior to the construction phase of the project.
8/16/2019 Utility Relocation Report
4/35
delays. The third point considers delays by the utility to relocate and perform their work,
which causes late clearances for the TxDOT contractor. During Fiscal Year (FY) 2013, FY
2014 and FY 2015, TxDOT has paid highway contractors over $21.9 million in additional
costs and delay claims due to untimely utility relocations. During this same period, the time
delays caused prolonged safety risks for approximately 10,432 days for construction workers
and the traveling public.
FIGURE 1: CURRENT PROJECT DEVELOPMENT PROCESS
The majority of utility relocation conflicts occur in the metropolitan areas of Texas, with the
exception to Beaumont, Lufkin and Waco TxDOT districts. Metropolitan areas have a larger
volume of construction work impacting more utilities in congested right of way corridors. The
Beaumont, Lufkin and Waco TxDOT districts have had significant reconstruction projects onIH 10, US 59 and IH 35 corridors. (See Appendix A for a complete list of transportation
projects impacted by additional costs and delays associated with utility relocations.)
8/16/2019 Utility Relocation Report
5/35
Texas Transportation Code, §203.094(b) states that TxDOT may reduce the reimbursement
to the utility by 10 percent for each 30-day period or portion of a 30-day period by which the
relocation exceeds the limit specified in the relocation agreement. If TxDOT determines that
a delay in relocation is the result of circumstances beyond the control of the utility, full
reimbursement shall be paid. Unfortunately, this remedy requires a utility agreement to be
executed and in many cases the untimely utility does not sign a utility agreement until their
schedule is more certain considering procurement of manufactured materials and labour for
installation. Oftentimes, multiple utilities are untimely making it difficult for TxDOT to reduce
reimbursements to the utility implement.
On average, reimbursements total approximately $100 million per year on TxDOT projects.The process involves a public utility determining reimbursement eligibility in partnership with
TxDOT, performing the relocation activity and then submitting invoices to TxDOT for payment.
NON REIMBURSABLE UTILITIES
Non-reimbursable utilities are authorized for relocation by a permit issued by TxDOT. The
permit sets forth the utility’s timeline for relocation.
UTILITY INDUSTRY WORKSHOPS
In an effort to make the utility relocation process TxDOT hosted a series of Utility Industry
Workshops during the Fall of 2015 and Spring of 2016. The workshops were well attended
by utilities and respective associations. Over the course of the workshops discussions were
focused on the issues of construction delays and additional costs to our customers. Open
communication and early engagement of utilities in the transportation project development
process was also emphasized.
During the workshops TxDOT staff discussed best practices which included monthly utility
coordination meetings for the metropolitan areas of the state and certain TxDOT districts
8/16/2019 Utility Relocation Report
6/35
manage construction delays and additional costs.
Mid-term improvements in procedures and processes will include TxDOT minimizing the
number of projects going to construction without clear right of way and utility relocations. As
previously stated, 20 percent of projects have had outstanding utility adjustments and 10
percent have outstanding right of way to purchase or clear, at the time the construction
contract is awarded. This practice has exasperated timeliness of utility relocations and is
within TxDOT’s control assuming there is industry cooperation. Better collaboration is
paramount to success of the proposed model.
The proposed procedures on major transportation projects include the acquiring of ROW twoyears prior to construction (Figure 2). This two-year period allows TxDOT designers to
complete detailed construction plans while utilities begin their relocation efforts. Projects
clear of ROW and utilities provides contractors unobstructed access to the project with a
more efficient and streamlined sequencing of work. In this model, construction time will
improve and minimize work zone risks for the traveling public and construction workers.
An additional benefit of this proposed model is to allow more A+B bidding on major transportation projects. Traditionally projects are contracted with simply the A component
which is the bid items of work. A+B bidding allows time to be bid thereby encouraging the
contractors to bid construction duration. Following this model, the project is awarded to the
contractor with the lowest aggregate bid of work items plus shortest construction duration.
Implementation of this model will not occur rapidly due to letting obligations already
underway. Therefore, this method of improving coordination and timeliness of utilityrelocations is a mid-term action item. However, TxDOT can immediately begin to incorporate
this model into our business practices and performance measures.
8/16/2019 Utility Relocation Report
7/35
counterparts in the utility industry. The training also includes an implementation monitoring
phase for the major metropolitan districts to ensure TxDOT’s largest and busiest districts are
implementing the strategies taught. Training will begin in June of 2016 in the Austin District.
Additionally, TxDOT district engineers have been given the authority to execute utility
agreements within their respective districts. Previously, signature authority for utility
agreements rested with the TxDOT Right of Way Division Director. Moving signature authority
to the district engineers will maximize local control over the transportation project and
expedite utility agreements.
Lastly, TxDOT is in the process of developing a master agreement for use with recurringutility companies that states the relocation and accommodation process. The master
agreements will guarantee that once the utility is given a notice to proceed on a particular
project, TxDOT will pay for any costs associated with highway design changes that cause the
utility to change its relocation plans. A smaller supplemental agreement with the technical
aspects would then be entered into on a project-by-project basis. This simplifies the
agreement process and allows utilities to start their process upon a notice to proceed from
TxDOT.
FIGURE 2: PROPOSED PROJECT DEVELOPMENT PROCESS
8/16/2019 Utility Relocation Report
8/35
TxDOT does have the authority to make loans to utilities from the State Infrastructure Banks
(SIB). The SIB was authorized in 1995, as part of the National Highway Designation Act to
help accelerate needed mobility improvements through a variety of financial assistance
options made to local entities through state transportation departments. Texas was chosen
as one of the 10 states to test the pilot program and the Texas Legislature authorized TxDOT
to administer the SIB program in 1997. The overall goal of the SIB program is to provide
innovative financing methods to communities to assist them in meeting their infrastructure
needs. The SIB program allows borrowers to access capital funds at market interest rates
with favourable terms. This has been advantageous to smaller utilities and municipalities
who may have capital difficulty to relocate their facilities.
TxDOT continues to be willing to include utility relocations in our transportation contracts.
This is fairly common in our metropolitan areas with water, wastewater and communication
utilities. Specifications for each utility must be prepared and included in the contract for
bidding purposes. TxDOT encourages this type of partnering because it places control of the
utility relocation process largely in the prime contractor’s responsibility. Additionally, many
prime contractors will subcontract the utility relocation work to the same companies
performing the work for the utility owner.
Texas Transportation Code, §203.0935(e) provides TxDOT with the authority to relocate an
uncooperative utility after due diligence and proper notice is provided to the utility. It is
possible to seek restitution for TxDOT expenses through legal means. TxDOT may request
the Office of Attorney General to seek an injunction requiring the utility company to relocate
its property, if the utility fails to cooperate in a timely relocation. This legal remedy takes
time to resolve and is rarely used in normal practice as TxDOT uses every opportunity toresolve these differences.
8/16/2019 Utility Relocation Report
9/35
expedite the relocation work while transportation improvements begin. Doing so allows a
more overall coordinated effort by the TxDOT contractor delivering transportation
improvements sooner to our customers.
8/16/2019 Utility Relocation Report
10/35Appendix A.
8/16/2019 Utility Relocation Report
11/35
Texas Department of Transportation
1
District Highway Description Ut ility Owner Time Delay (Days) Additional Costs Comments
CR 357 Replace Bridge AT&T
5 $0.00
Time suspended from 7/10/2014 - 7/15/2015 due to
utility adjustments
FM 2230
Widen, Rehabilitate, Replace
Culverts And Construct New
Bridge
WesTex Telephone
18 $0.00
N/A
VA Construct New Relief Route Millennium Resources
40 $0.00
N/A
BS 70-G Rehabilitation, Acp, Sidewalks AT&T
0 $18,000.00
Adjust utility poles
BS 70-G Rehabilitation, Acp, Sidewalks City of Sweetwater0 $3,000.00
Adjusted water meters
IH 20 Con struct New In terch ange LEVEL 3 COM
100 $0.00
Time suspended from 1/1/2015 - 5/11/2015 due to utilityadjustments
CS Rehab Existing Roadway Atmos
18 $10,650.00
Utility encountered during construction
SH 15Rehabilitation And Re-
Designation Of Cr To ShCity of Stratford (SEWER)
20 $0.00 N/A
SH 15Rehabilitation And Re-
Designation Of Cr To ShCity of Stratford (WATER)
20 $0.00 N/A
CS Rehab Existing Roadway City of Amarillo
19 $0.00
Additional costs undetermined. Contractor has claim
pending.
LP 335Additional 2 Lanes And
BridgesAT&T
90 $0.00
Contract time charges suspended due to unclear utility.
Additional costs not yet determined.
LP 335Additional 2 Lanes And
BridgesCity of Amarillo
30 $0.00
Contract time charges suspended due to unclear utility.
Additional costs not yet determined.
ABILENE
AMARILLO
8/16/2019 Utility Relocation Report
12/35
Texas Department of Transportation
2
District Highway Description Ut ility Owner Time Delay (Days) Additional Costs Comments
LP 335Additional 2 Lanes And
BridgesATMOS ENERGY
20 $0.00
Contract time charges suspended due to unclear utility.
Additional costs not yet determined.
LP 335Additional 2 Lanes And
BridgesZAYO GROUP
20 $0.00
Contract time charges suspended due to unclear utility.
Additional costs not yet determined.
FM 1402
Improve Alignment And Add
Turn Lanes At Hart'S Bluff
School
Bowie-Cass Electric Coop
34 $0.00
Only indirect cost to this conflict
FM 1402
Improve Alignment And Add
Turn Lanes At Hart'S Bluff
School
Centerpoint Energy
12 $0.00
Only indirect cost to this conflict
FM 1402
Improve Alignment And Add
Turn Lanes At Hart'S Bluff
School
Suddenlink
10 $0.00
Only indirect cost to this conflict
FM 1402
Improve Alignment And Add
Turn Lanes At Hart'S Bluff
School
AT&T
8 $0.00
Only indirect cost to this conflict
FM 1402
Improve Alignment And Add
Turn Lanes At Hart'S Bluff
School
Tri Special Utility District
8 $0.00
Only indirect cost to this conflict
US 80Replace Bridge And
ApproachesSprint
7 $0.00
Only indirect cost to this conflict
SH 155Replace Bridges And
ApproachesAEP
37 $0.00
Cost associated with this delay are yet undertermined we
expect to go to claims with this contract due to utility
delays and a redesign issue
RM 1826Add Center Turn Lane And
ShouldersAT&T
33 $0.00N/A
ATLANTA
AUSTIN
8/16/2019 Utility Relocation Report
13/35
Texas Department of Transportation
3
District Highway Description Ut ility Owner Time Delay (Days) Additional Costs Comments
US 290Provide Signalized
IntersectionsAT&T
46 $375,000.00
Time Suspended from 1/27/14 - 3/31/14.
US 290Innovative Intersection
ImprovementAT&T
198 $275,000.00
Project had several month delay p ast item 8 clear date
due to AT&T
SH 304Upgrade To 3-Lane Section
With ShouldersAT&T
31 $84,300.28
N/A
SH 304Upgrade To 3-Lane Section
With ShouldersCenterpoint Energy
17 $46,229.19N/A
SH 304
Improve Guardrail To Design
Standards & Safety Treat
Fixed Objects
AT&T
45 $75,000.00
N/A
SH 80 Intersection ImprovementsCity of San Marcos Electric
Utility5 $7,620.55
N/A
SH 71Add Left Turn Lane &
ShouldersAT&T
60 $50,000.00
N/A
RM 1431Innovative Intersection
ImprovementsAtmos
TBD TBD
Delay claim because of utilities -- AT&T, Time Warner, City
of CP
IH 10Replace Bridge And
ApproachesAir Liquide
21 $0.00
Unexpected utility conflict. Place protection sheet pile for
10" oxygen line for concrete pile operation. Phase 2
protection has been complete. Phase 3 & 4 protection still
needs to be done.
US 90Add 2 Lanes To Existing 2
Lane HighwayCity of Devers
0 $28,750.00
Utility relocated in June 2014 before creating a time delay.
US 69
Overlay Existing Roadway
And Add A Continuous Left
Turn Lane
AT&T
130 $0.00
Contract allowed until March 2015 for utilities to b e
relocated. Unresolved to date. Possibe cost escalation of
materials. Request has been sen t to contractor. Awaiting
their response.
US 69
Overlay Existing Roadway
And Add A Continuous Left
Turn Lane
Windstream (FiberOptic)
108 $0.00
Contract allowed until March 2015 for utilities to b e
relocated. Relocations complete in August 2015. Possible
cost escalation of materials. Request has been sent to
contractor. Awaiting their response.
BEAUMONT
8/16/2019 Utility Relocation Report
14/35
Texas Department of Transportation
4
District Highway Description Ut ility Owner Time Delay (Days) Additional Costs Comments
BROWNWOOD
IH 20Construct Two Safety Rest
AreasAT&T
59 $27,676.00
N/A
SH 30
Safety Improvement Work
Consisting Of Grading,
Structures, Flexible Base,
Surfacing And Pavement
Markings
AT&T
60 $0.00
Total project delay is anticipated to be approximately 6months. ROW acquisition activities have delayed utility
relocation (~4 months). The contractor is currently
developing a material escalation submittal for the
Department. Additional costs to be determined at a later
date.
BRYAN
8/16/2019 Utility Relocation Report
15/35
Texas Department of Transportation
5
District Highway Description Ut ility Owner Time Delay (Days) Additional Costs Comments
SH 30
Safety Improvement Work
Consisting Of Grading,
Structures, Flexible Base,
Surfacing And Pavement
Markings
Century Link
60 $0.00
Total project delay is anticipated to be approximately 6
months. ROW acquisition activities have delayed utility
relocation (~4 months). The contractor is currently
developing a material escalation submittal for the
Department. Additional costs to be determined at a later
date.
SH 30
Safety Improvement WorkConsisting Of Grading,
Structures, Flexible Base,
Surfacing And Pavement
Markings
Enterprise Products
60 $0.00
Total project delay is anticipated to be approximately 6
months. ROW acquisition activities have delayed utility
relocation (~4 months). The contractor is currently
developing a material escalation submittal for the
Department. Additional costs to be determined at a later
date.
SH 30
Safety Improvement Work
Consisting Of Grading,
Structures, Flexible Base,
Surfacing And Pavement
Markings
Mid-South Synergy
60 $0.00
Total project delay is anticipated to be approximately 6
months. ROW acquisition activities have delayed utility
relocation (~4 months). The contractor is currently
developing a material escalation submittal for the
Department. Additional costs to be determined at a later
date.
SH 30
Safety Improvement Work
Consisting Of Grading,
Structures, Flexible Base,
Surfacing And Pavement
Markings
Wickson Creek SUD
60 $0.00
Total project delay is anticipated to be approximately 6
months. ROW acquisition activities have delayed utility
relocation (~4 months). The contractor is currentlydeveloping a material escalation submittal for the
Department. Additional costs to be determined at a later
date.
US 77Construct Main Lanes And
OverpassesAEP Telecom
61 $0.00
Completed 10/2015. This was prompted by ROW
acquisition and above average rainfall events.
US 77Construct Main Lanes And
OverpassesVerizon
30 $0.00
Complete October 2015. This was prompted by ROW
acquisition and above average rainfall events.
FM 2444Construct Additional Lanes
And Access ManagementAEP
50 $0.00
District is currently reviewing contractor submitted delay
impact for $ 322,335
CORPUS CHRISTI
8/16/2019 Utility Relocation Report
16/35
Texas Department of Transportation
6
District Highway Description Ut ility Owner Time Delay (Days) Additional Costs Comments
FM 2444Construct Additional Lanes
And Access ManagementAT&T
50 $0.00
District is currently reviewing contractor submitted delay
impact for $ 322,335
FM 2444 Construct Additional LanesAnd Access Management
City of Corpus Christi
50 $0.00
District is currently reviewing contractor submitted delayimpact for $ 322,335
FM 1069 Widen Roadway Boardwalk Pipeline 48 $0.00 No claims have been made to date
US 59
Rehab Roadway At
Intersection And Add
Concrete
AEP 67 $4,667 Project completed and accepted on 6/4/14
SH 78Widen From 2 Lane To 6 Lane
Divided UrbanVERIZON
TBD TBDImpact has not been determined yet
FM 720Widen Two Lane Rural To Six
Lanes Urban DividedAT&T
0 $200,000.00Working on Localized conflicts at this time
FM 720Widen Two Lane Rural To Six
Lanes Urban DividedCoServ Electric
0 $200,000.00Relocation complete.
FM 720Widen Two Lane Rural To Six
Lanes Urban Divided
Grande Communications
0 $200,000.00
Relocation complete
FM 720Widen Two Lane Rural To Six
Lanes Urban DividedSuddenlink
0 $200,000.00
Working on localized conflicts at this time.
FM 720Widen Two Lane Rural To Six
Lanes Urban DividedTown of Little Elm
0 $200,000.00
Relocation complete
SH 78 9 Intersection Improvemen ts AT&T Tex asTBD TBD
DALLAS
8/16/2019 Utility Relocation Report
17/35
Texas Department of Transportation
7
District Highway Description Ut ility Owner Time Delay (Days) Additional Costs Comments
SH 78 9 Intersection Improvements Oncor Electric DeliveryTBD TBD
SH 78 9 Intersection Improvements Time Warner CableTBD TBD
SH 78 9 Intersection Improvements Atmos Energy DeliveryTBD TBD
SH 78 9 Intersecti on Improvemen ts Fiberli ght TBD TBD
IH 30
Construct Managed/Hov
Lanes With Two Sets Of
Wishbone Ramps
AT&T
0 $355,000.00
N/A
IH 30
Construct Managed/Hov
Lanes With Two Sets Of
Wishbone Ramps
Oncor
12 $62,389.00
N/A
US 75
Widen And Reconstruct 6
Lane Freeway To 8 Lanes;
Improve 2/3 Lane Frontage
Roads And Ramps
CITY OF PLANO
125 $0.00
N/A
US 75
Widen And Reconstruct 6
Lane Freeway To 8 Lanes;
Improve 2/3 Lane Frontage
Roads And Ramps
GRANDE COMMUNICATIONS
125 $0.00
TxDOT did not inform utililty they needed to relocatefacilities until
construction was nearly ready to begin
US 75
Widen And Reconstruct 6
Lane Freeway To 8 Lanes;
Improve 2/3 Lane Frontage
Roads And Ramps
ONCOR ELECTRIC DELIVERY
125 $0.00
TxDOT did not inform utililty they needed to relocate
facilities until
construction was nearly ready to begin
FM 2786
Widen 2 To 4 Lane Divided
(Six Lane Ultimate) With
Intersection Improvement At
Sh 5
Oncor
48 $150,000.00
Multiple companies are dependent on Oncor to complete
their own relocations including TWC, Grande, and Atmos
Energy
FM 2786
Widen 2 To 4 Lane Divided
(Six Lane Ultimate) With
Intersection Improvement At
Sh 5
AT&T
48 $0.00
N/A
FM 2786
Widen 2 To 4 Lane Divided
(Six Lane Ultimate) With
Intersection Improvement At
Sh 5
Atmos
48 $0.00
N/A
Potential escalation costs due to project start delay.
AT&T, Oncor, Time Warner Cable, and Fiberlight i n
conflict.
f
8/16/2019 Utility Relocation Report
18/35
Texas Department of Transportation
8
District Highway Description Ut ility Owner Time Delay (Days) Additional Costs Comments
FM 2786
Widen 2 To 4 Lane Divided
(Six Lane Ultimate) With
Intersection Improvement At
Sh 5
CoServ Gas
48 $0.00
N/A
FM 2786
Widen 2 To 4 Lane Divided
(Six Lane Ultimate) WithIntersection Improvement At
Sh 5
Grande Communication
48 $0.00
N/A
FM 2786
Widen 2 To 4 Lane Divided
(Six Lane Ultimate) With
Intersection Improvement At
Sh 5
Grayson Collin EC
48 $0.00
N/A
FM 2786
Widen 2 To 4 Lane Divided
(Six Lane Ultimate) With
Intersection Improvement At
Sh 5
Time Warner
48 $0.00
N/A
FM 663 Widen Existing Overpass AndApproaches
AT&T264 $0.00
N/A
FM 663Widen Existing Overpass And
ApproachesOncor
22 $0.00N/A
FM 455
Widen Facility To 4 Lane
Urban Divided, Ultimate 6
Lane Divided
AT&T
462 $367,000.00
TxDOT contractor delayed by untimely AT&T relocations.
CSReplace Bridge And
ApproachesOncor
66 $0.00N/A
CSReplace Bridge And
ApproachesAT&T
22 $0.00N/A
FM 1171Widen Two Lane Rural To Six
Lane Divided Urban HighwayAT&T
0 $100,000.00
N/A
CRReplace Bridge And
ApproachesAT&T
14 $0.00N/A
FM 1387Realign Existing Highway In
City Of MidlothianAT&T
90 $0.00N/A
FM 1387Realign Existing Highway In
City Of Midlothian
Hilco Electric Cooperative
Incorporated 90 $0.00N/A
SH 289 Nb/Sb Dual Left Turn Lanes AT&T0 $56,000.00
TxDOT contractor delayed by untimely AT&T and Oncor
relocations.
SH 289 Nb/Sb Du al Left Turn Lan es Oncor Energy0 $24,000.00
N/A
Texas Department of Transportation
8/16/2019 Utility Relocation Report
19/35
Texas Department of Transportation
9
District Highway Description Ut ility Owner Time Delay (Days) Additional Costs Comments
FM 423
Sh 121 To Cougar Alley;Widen
4 To 8 Ln Divided
Urban;Cougar Alley To
Stewarts Crk Rd; Widen 4 To
6 Ln Divided Urban
AT&T
0 $6,415,000.00
Project had to be Re-Let due to AT&T delays.
SL 12 Intersection Improvements AT&T 0 $198,000.00 N/A
FM 1378Replace Bridge And
ApproachesCity of Lucas
125 $0.00N/A
FM 1378Replace Bridge And
ApproachesSuddenlink Communications
125 $0.00
TxDOT did not inform utililty they needed to relocate
facilities until
construction was nearly ready to begin
FM 1378Replace Bridge And
ApproachesUnite Private Network
125 $0.00
TxDOT did not inform utililty they needed to relocate
facilities until
construction was nearly ready to begin
FM 740Widen 2 Lane To 4 Lane
Divided UrbanAT&T
0 $244,000.00N/A
FM 981Replace Bridge And
ApproachesFrognot WSC
62 $0.00N/A
FM 544 Replace Bridge AndApproaches
Atmos10 $0.00
Conflict discovered Ph I. Relocation Complete Ph II.
SS 1966 Construction Of Spur AT&T
0 $110,779.00
Cost associated with shoring of utility in place and FOC
was relocated concurrent with construction. No time
impacts
SS 1966 Construction Of Spur Texas Gas0 $70,732.00
Cost associated with shoring of utility in place. No time
impacts
EL PASO
Texas Department of Transportation
8/16/2019 Utility Relocation Report
20/35
Texas Department of Transportation
10
District Highway Description Ut ility Owner Time Delay (Days) Additional Costs Comments
US 62
Roadway Widening (Shoulder
Improve, Sidewalks, Traffic
Signals, Signing, Striping & Rt
Turn Lanes)
AT&T
40 $173,512.00
During construction of sound walls, the contractor hit an
unknown AT&T utility causing sequencing inefficiencies
and a redesign of the sound wall.
US 62
Roadway Widening (Shoulder
Improve, Sidewalks, TrafficSignals, Signing, Striping & Rt
Turn Lanes)
El Paso Electric
3 $1,000.00
N/A
Horizon Blvd Urban Reconstruction AT&T 357 $566,560.00 N/A
Horizon Blvd Urban Reconstruction El Paso Electric 28 $0.00 N/A
CS
Reconstruct From 4 Lanes To
4 Lane Divided With Raised
Median -Phase 2
Oncor (Electric)
90 N/A
CS
Reconstruct Bridge To
Accommodate The Upgrade
Of Dirks/Alta Mesa To A 6
Lane Divided Roadway
Atmos
37 $105,000.00
The total delay claim is for 146 days and $420,000 for all
four utilities. The cost and time is equally divided between
four utilities
CS
Reconstruct Bridge To
Accommodate The Upgrade
Of Dirks/Alta Mesa To A 6
Lane Divided Roadway
Oncor
37 $105,000.00
The total delay claim is for 146 days and $420,000 for all
four utilities. The cost and time is equally divided between
four utilities
CS
Reconstruct Bridge To
Accommodate The Upgrade
Of Dirks/Alta Mesa To A 6
Lane Divided Roadway
Chater
36 $105,000.00
The total delay claim is for 146 days and $420,000 for all
four utilities. The cost and time is equally divided between
four utilities
CS
Reconstruct Bridge To
Accommodate The Upgrade
Of Dirks/Alta Mesa To A 6
Lane Divided Roadway
AT&T
36 $105,000.00
The total delay claim is for 146 days and $420,000 for all
four utilities. The cost and time is equally divided between
four utilities
SL 12 Intersection Improvement Oncor20 $20,093.00
TxDOT contractor delayed by untimely AT&T relocations.
IH 35WReconstruct Roadway And
Add 4 Managed (Toll) LanesAT&T
0 $40,900.00
Contractor had to demobilize and remobilize due to a
conflict with AT&T facilities.
IH 35WReconstruct Roadway And
Add 4 Managed (Toll) LanesUnknown
0 $2,443.23
N/A
SH 146 Direct Connector (Nb) AT&T256 $60,000.00
N/A
FORT WORTH
HOUSTON
Texas Department of Transportation
8/16/2019 Utility Relocation Report
21/35
Texas Department of Transportation
11
District Highway Description Ut ility Owner Time Delay (Days) Additional Costs Comments
US 290
Construct Five Main Lanes
With Auxiliary Lanes and Two
or Three Lane Frontage Roads
and Grade Separations
(Inbound Only)
Phonoscope
88 $166,923.24
N/A
US 290
Construct Five Main Lanes
With Auxiliary Lanes and Two
or Three Lane Frontage Roads
and Grade Separations
(Inbound Only)
Centerpoint gas
0 $166,923.24
N/A
US 290
Construct 5 Mainlanes With
Auxillary Lanes, Frontage Rd,
Grade Seperation
Unknown Utilities
0 $53,869.80
The contractor left a gap in the proposed storm sewer at
multiple locations until the utility could be relocated.
US 290Construct 5 Mainlanes WithAuxillary Lanes, Frontage Rd,
Grade Seperation
Unknown Utilities
0 $43,076.63
The contractor left a gap in the proposed storm sewer at
multiple locations until the utility could be relocated.
US 290
Construct 5 Mainlanes With
Auxillary Lanes, Frontage Rd,
Grade Seperation
Qwest
0 $12,746.20
Locate the quest line using SUE location methods so an
18" gas line can be relocated.
US 290
Widen To 8 Mainlanes,
Auxillary Lanes & 2-Lane
Frontage Roads
CenterPoint
0 $163,941.00
Revise storm sewer to eliminate conflict with 2-30" high
pressure natural gas pipelines.
US 290
Widen To 8 Mainlanes,
Auxillary Lanes & 2-Lane
Frontage Roads
AT&T
0 $117,110.51
Revise storm sewer to eliminate conflict with utili ty ductbank.
US 290
Widen To 8 Mainlanes,
Auxillary Lanes & 2-Lane
Frontage Roads
CenterPoint
0 $91,845.54
Revise storm sewer to eliminate conflict with 18" gas
pipeline.
Texas Department of Transportation
8/16/2019 Utility Relocation Report
22/35
p p
12
District Highway Description Ut ility Owner Time Delay (Days) Additional Costs Comments
US 290
Widen To 8 Mainlanes,
Auxillary Lanes & 2-Lane
Frontage Roads
Enterprise Pipelines
0 $66,646.89
The contractor left a gap in the proposed storm sewer
until gas line could be relocated. A siphon was installed
and removed due to the opening of the US 290 Eastbound
Frontage Road and the storm sewer system becoming
active prior to the relocation of the gas line. Since this was
a temporary condition, asphalt pavement was installed in
this area and subsequently removed and replaced with12" fast track paving.
US 290
Widen To 8 Mainlanes,
Auxillary Lanes & 2-Lane
Frontage Roads
AT&T
0 $40,463.53
Revise storm sewer to eliminate conflict with utili ty duct
bank.
US 290
Widen To 8 Mainlanes,
Auxillary Lanes & 2-Lane
Frontage Roads
Enterprise Pipelines
0 $32,033.70
The contractor left a gap in the proposed storm sewer
until the gas line could be relocated. A siphon was
installed and removed to allow proper storm water
drainage.
US 290
Widen To 8 Mainlanes,
Auxillary Lanes & 2-Lane
Frontage Roads
AT&T
0 $30,362.00
Revise storm sewer to eliminate conflict with 24" steel
casing.
US 290
Widen To 8 Main Lanes With
3 Reversible Managed Lanes,
, Auxiliary Lanes And Two 2-
Lane Frontage Roads
CenterPoint
0 $19,747.50
Revise storm sewer to eliminate conflict with CenterPoint
Energy transmission tower foundation.
US 290
Widen To 8 Mainlanes,
Auxillary Lanes & 2-Lane
Frontage Roads
CenterPoint
0 $5,189.39
Place concrete storm sewer collar where the contractor
left a gap in the proposed storm sewer until CenterPoint
could relocate their gas line.
Texas Department of Transportation
8/16/2019 Utility Relocation Report
23/35
13
District Highway Description Ut ility Owner Time Delay (Days) Additional Costs Comments
US 290
Reconstruct And Widen To 8
Main Lanes And 2-Lane
Frontage Roads
CenterPoint Energy
0 $70,255.05
Temporarily relocate a portion of the 8" gas line for
installation of proposed storm sewer.
US 290
Reconstruct And Widen To 8
Main Lanes And 2-Lane
Frontage Roads
Kinder Morgan
0 $56,502.75
Contractor placed asphalt over 175' gap in the proposed 7'
x 5' RCB strom sewer until the 4 gas lines can be relocated
in 2016.
US 290
Reconstruct And Widen To 8
Main Lanes And 2-Lane
Frontage Roads
AT&T
0 $50,914.93
Revise storm sewer system to avoid utilities that will notbe relocated until 2016.
US 290
Reconstruct And Widen To 8
Main Lanes And 2-Lane
Frontage Roads
CenterPoint Gas
0 $50,914.93
Revise storm sewer system to avoid utilities that will not
be relocated until 2016.
US 290
Reconstruct And Widen To 8
Main Lanes And 2-Lane
Frontage Roads
Exxon Crude Oil
0 $50,914.93
Revise storm sewer system to avoid utilities that will not
be relocated until 2016.
US 290
Reconstruct And Widen To 8
Main Lanes And 2-Lane
Frontage Roads
Houston Pipeline
0 $50,914.93
Revise storm sewer system to avoid utilities that will not
be relocated until 2016.
US 290
Reconstruct And Widen To 8
Main Lanes And 2-Lane
Frontage Roads
Teppco Crude Oil
0 $50,914.93
Revise storm sewer system to avoid utilities that will not
be relocated until 2016.
US 290
Reconstruct And Widen To 8
Main Lanes And 2-Lane
Frontage Roads
Kinder Morgan and Gulf
South0 $43,514.55
Contractor to install and later remove temporary asphalt
concrete pavement and 6" concrete dowel curb u ntil
relocation in spring 2015.
US 290
Reconstruct And Widen To 8
Main Lanes And 2-Lane
Frontage Roads
AT&T
0 $33,336.37
Revise storm sewer system to avoid utilities that will not
be relocated until 2016.
US 290
Reconstruct And Widen To 8
Main Lanes And 2-Lane
Frontage Roads
CenterPoint Electric
0 $33,336.37
Revise storm sewer system to avoid utilities that will not
be relocated until 2016.
US 290
Reconstruct And Widen To 8
Main Lanes And 2-Lane
Frontage Roads
CenterPoint Gas
0 $33,336.37
Revise storm sewer system to avoid utilities that will not
be relocated until 2016.
US 290
Reconstruct And Widen To 8
Main Lanes And 2-LaneFrontage Roads
Comcast0 $33,336.37
Revise storm sewer system to avoid utilities that will not
be relocated until 2016.
US 290
Reconstruct And Widen To 8
Main Lanes And 2-Lane
Frontage Roads
Kinder Morgan
0 $33,336.37
Revise storm sewer system to avoid utilities that will not
be relocated until 2016.
US 290
Reconstruct And Widen To 8
Main Lanes And 2-Lane
Frontage Roads
Phonoscope
0 $33,336.37
Revise storm sewer system to avoid utilities that will not
be relocated until 2016.
US 290
Reconstruct And Widen To 8
Main Lanes And 2-Lane
Frontage Roads
CenterPoint Energy
0 $28,283.07
Temporarily relocate a portion of the 2" IP plastic gas line
for installation of proposed storm sewer.
Texas Department of Transportation
8/16/2019 Utility Relocation Report
24/35
14
District Highway Description Ut ility Owner Time Delay (Days) Additional Costs Comments
US 290
Reconstruct And Widen To 8
Main Lanes And 2-Lane
Frontage Roads
Gulf South
0 $18,834.25
Contractor placed asphalt over 175' gap in the proposed 7'
x 5' RCB strom sewer until the 4 gas lines can be relocated
in 2016.
US 290
Reconstruct And Widen To 8
Main Lanes And 2-Lane
Frontage Roads
Unknown Utility
0 $4,624.12
Contractor left a gap in the proposed strom sewer until
the pipe line could be relocated. After pipe line was
relocted contractor pour a concrete collar to close the
system.
US 290
Reconstruct And Widen To 8
Main Lanes And 2-Lane
Frontage Roads
CenterPoint Energy
0 $4,169.07
Contractor to leave out a section of the 4'x4' RCB and
install a 24'x7'x1' concrete collar with a 2' overlap on each
side of the 4'x4' RCB due to an existing 2" gas line not
being previously relocated.
US 290
Reconstruct And Widen To 8
Main Lanes And 2-Lane
Frontage Roads
CenterPoint Energy
0 $2,121.00
Contractor has to de-energize power line that had not
been relocated to continue to work.
US 290
Reconstruct And Widen To 8
Main Lanes And 2-Lane
Frontage Roads
Unknown Utility
0 $297.74
Locate & relocate unidentified existing 3" gas line to avoid
conflict with 36" RCP jack and bore.
US 290
Reconstruct And Widen To 8
Main Lanes With 3 Reversible
Managed Lanes, Auxiliary
Lanes And Two 2-LaneFrontage Roads
AT&T
0 $8,468.85
Relocate conduit in conflict with the proposed storm
sewer.
US 290
Reconstruct And Widen To 8
Main Lanes With 3 Reversible
Managed Lanes, Auxiliary
Lanes And Two 2-Lane
Frontage Roads
CenterPoint
0 $5,261.14
relocate down guy wire in conflict with proposed storm
sewer system.
FM 2920 Widening AT&T 132 $20,000.00 N/A
US 290Widen To 8 Main Lanes With
2 Reversible Managed LanesUnknown Utility
0 $6,875.30
Revise storm sewer lateral to bypass existing utility.
US 290
Reconstruct And Widen To 8
Main Lanes With 2 Reversible
Managed Lanes, Auxiliary
Lanes And Two 2-Lane
Frontage Roads
AT&T
0 $2,422.82
Locate existing AT&T duct bank as to not damage to duct
bank during installation of proposed storm sewer.
Texas Department of Transportation
8/16/2019 Utility Relocation Report
25/35
15
District Highway Description Ut ility Owner Time Delay (Days) Additional Costs Comments
IH 610
Reconstruct Us 290/Ih 610
Including Ih 10 To Us 290
Outbound Direct Connectors
AT&T
0 $165,000.00
N/A
IH 45
Widen And Reconstruct To 10
Main Lanes, Two 3-Lane
Frontage Roads And 1 Hov
Reversible Lane
AT&T
156 $30,000.00
N/A
US 290
Reconstruct And Widen To 8
Main Lanes With 2 Reversible
Managed Lanes, Auxiliary
Lanes And Two 2-Lane
Frontage Roads
CenterPoint Gas
0 $24,005.61
Temporary relocate 6" gas line for installation of proposed
storm sewer.
CS
Reconstruct And Widen To 6
Lane Divided (With RaisedMedian)
AT&T
66 $15,000.00
N/A
CR
Widen From 2 To 4-Lane
Divided Rural Section With 10-
Foot Outside Shoulders
CenterPointElectric
0 $15,618.91
N/A
US 290
Widen To 8 Main Lanes With
3 Reversible Managed Lanes,
, Auxiliary Lanes And Two 2-
Lane Frontage Roads
Williams Pipeline
0 $163,941.00
N/A
Texas Department of Transportation
8/16/2019 Utility Relocation Report
26/35
16
District Highway Description Ut ility Owner Time Delay (Days) Additional Costs Comments
US 290
Widen To 8 Main Lanes With
3 Reversible Managed Lanes,
, Auxiliary Lanes And Two 2-
Lane Frontage Roads
Enterprise Products (Mobil
PL)
0 $98,680.59
N/A
US 290
Reconstruct And Widen To 8
Main Lanes With 3 Reversible
Managed Lanes And Two 2-
Lane Frontage Roads
Sprint
0 $188,799.60
N/A
US 290
Reconstruct And Widen To 8
Main Lanes With 3 Reversible
Managed Lanes And Two 2-
Lane Frontage Roads
CenterPoint Gas
0 $146,226.53
N/A
US 290
Reconstruct And Widen To 8
Main Lanes With 3 Reversible
Managed Lanes And Two 2-
Lane Frontage Roads
Kinder Morgan
0 $76,850.90
N/A
US 290
Reconstruct And Widen To 8
Main Lanes With 3 Reversible
Managed Lanes And Two 2-
Lane Frontage Roads
AT&T
0 $43,519.34
N/A
Texas Department of Transportation
8/16/2019 Utility Relocation Report
27/35
17
District Highway Description Ut ility Owner Time Delay (Days) Additional Costs Comments
US 290
Reconstruct And Widen To 8
Main Lanes With 3 Reversible
Managed Lanes And Two 2-
Lane Frontage Roads
CenterPoint Electric
0 $35,457.36
N/A
US 290
Reconstruct And Widen To 8
Main Lanes With 3 Reversible
Managed Lanes And Two 2-
Lane Frontage Roads
Comcast
0 $33,336.36
N/A
US 290
Reconstruct And Widen To 8
Main Lanes With 3 Reversible
Managed Lanes And Two 2-
Lane Frontage Roads
Phonoscope
0 $33,336.36
N/A
US 290 FALSE Energy Transfer Pipeline
0 $19,630.25
Temporarily placed two 18" HDPE pipe and brick plug to
avoid 24" gas line until the middle of 2015.
US 290
Reconstruct And Widen To 8
Main Lanes With 3 Reversible
Managed Lanes And Two 2-
Lane Frontage Roads
Energy Transfer (Houston PL)
0 $10,182.98
N/A
Texas Department of Transportation
8/16/2019 Utility Relocation Report
28/35
18
District Highway Description Ut ility Owner Time Delay (Days) Additional Costs Comments
US 290
Reconstruct And Widen To 8
Main Lanes With 3 Reversible
Managed Lanes And Two 2-
Lane Frontage Roads
Enterprise Products
(Seminole PL)
0 $10,182.98
N/A
US 290
Reconstruct And Widen To 8
Main Lanes With 3 Reversible
Managed Lanes And Two 2-
Lane Frontage Roads
ExxonMobil
0 $10,182.98
N/A
US 290
Reconstruct And Widen To 8
Main Lanes With 3 ReversibleManaged Lanes, Auxiliary
Lanes And Two 2-Lane
Frontage Roads
CenterPoint Gas
0 $119,688.93
N/A
US 290
Reconstruct And Widen To 8
Main Lanes With 3 Reversible
Managed Lanes, Auxiliary
Lanes And Two 2-Lane
Frontage Roads
Zayo Group
0 $119,688.93
N/A
US 290
Reconstruct And Widen To 8
Main Lanes With 3 Reversible
Managed Lanes, Auxiliary
Lanes And Two 2-Lane
Frontage Roads
Comcast
0 $119,203.54
N/A
Texas Department of Transportation
8/16/2019 Utility Relocation Report
29/35
19
District Highway Description Ut ility Owner Time Delay (Days) Additional Costs Comments
US 290
Reconstruct And Widen To 8
Main Lanes With 3 Reversible
Managed Lanes, Auxiliary
Lanes And Two 2-Lane
Frontage Roads
Phonoscope
0 $119,203.54
N/A
US 290
Reconstruct And Widen To 8
Main Lanes With 3 Reversible
Managed Lanes, Auxiliary
Lanes And Two 2-Lane
Frontage Roads
Wavevision
0 $119,203.54
N/A
CSWiden 2-Lane Roadway To 4-Lane Boulevard With Curb &
Gutter
Telephone Line- Verizon
0 $3,936.06
N/A
IH 45
Construct Entrance And Exit
Ramps, Remove And Replace
Existing Us 59 Nb And Sb
Direct Connectors
AT&T
260 $60,000.00
N/A
LUBBOCK FM 1730 Widen Non-Freeway AT&T240 $375,000.00
N/A
US 287 Reconstruct Pavement Centerpoint
23 $0.00
Centerpoint worked from early January 2016 to March 4,
2016 relocating gas lines. They were given over a years
advance notice and knew the lines were in conflict.
According to Centerpoint, turnover in personnel caused
them to drop "the ball". No claims anticipated due to
other construction difficulties occuring at the same time.
US 59 Construct Grade Separation AT&T19 $0.00
Contractor says potential 19 day delay claim.
LUFKIN
Texas Department of Transportation
8/16/2019 Utility Relocation Report
30/35
20
District Highway Description Ut ility Owner Time Delay (Days) Additional Costs Comments
SH 7Reconstruct And Add Passing
Lanes
Consolidated
Communications 25 $0.00
Project was delayed from November 13, 2014 to January
2, 2015
US 59Add Sb Frontage Rd &
Reconstruct Main LanesAT&T
0 $1,500,000.00
The project was let July 2013. TxDOT completed ROW
purchasing in June 2014. AT&T agreement was approved
December 2014. AT&T had 90 days to relocate upon
completion of Prep ROW per the plans. 90 days ended
February 4, 2015. AT&T is scheduled to start work
8/24/15. Entergy began relocating 8/1/2015. At this time
we do not know the cost of the damages. AT&T
completed tie in Nov 12, 2015.
Texas Department of Transportation
8/16/2019 Utility Relocation Report
31/35
21
District Highway Description Ut ility Owner Time Delay (Days) Additional Costs Comments
SL 224 Construct Curb Ramps AT&T 40 $19,000.00 N/A
SL 224 Construct Curb Ramps Atmos Energy 0 $0.00 N/A
SH 24Upgrading Of Existing 2-Lane
To A 4-Lane Divided HighwayWest Delta Water Supply
15 $0.00
Contractor worked around Utility
US 82
Construct Main Lanes Of A 4-
Lane Section With Depressed
Median
Oncor Transmission
0 $260,000.00
Ongoing Utility Adjustment. Estimated Cost Only.
Working to Eliminate Time Delay Potential.
BUS. 83 Constr 4- Ln Div ided Ur ban Texas Gas Ser vice54 $114,729.00
TGS HAD SEVERAL CROSSINGS TO ADDRESS. SP 004-017
USED TO CALCULATE COST/DAY.
BUS. 83 Constr 4- Ln Divided Ur ban CITY OF MERCEDE S
12 $25,495.00
CITY OF MERCEDES RELOCATED WATER AND SEWER
LINES. SP 004-017 USED TO CALCULATE COST/DAY.
SH 364Widen To 4 Lane Divided
UrbanAEP
64 $10,958.00 Used Item 4.6.2 to calculate cost.
SH 364Widen To 4 Lane Divided
UrbanAUGA SUD
64 $10,958.00 Used Item 4.6.2 to calculate cost.
SH 364Widen To 4 Lane Divided
UrbanSWSC
64 $10,958.00 Used Item 4.6.2 to calculate cost.
SH 364Widen To 4 Lane Divided
UrbanCity of Mission
64 $10,958.00 Used Item 4.6.2 to calculate cost.
SH 364Widen To 4 Lane Divided
UrbanAT&T
64 $10,958.00 Used Item 4.6.2 to calculate cost.
SH 364Widen To 4 Lane Divided
UrbanTGS
64 $10,958.00 Used Item 4.6.2 to calculate cost.
US 83Replace Sb And Nb Bridge
And Reconstruct Approaches
WIND STREAM
COMMUNICATIONS
161 $305,077.29
Windstream was notified 6/29/15 that IBWC permit was
approved. Windstream is in conflict of drill shaft
construcion. Windstream completed adjustment on
2/25/16. During conflict time, contractor was able to
continue work on other items and locations.
CSReconstruct & Widen To 2 Ln
Rdwy With ShouldersAEP
5 $3,420.00
AEP RELOCATED POWER POLES TO NEW ROW. SP 004-017
USED TO CALCULATE COST/DAY.
CSReconstruct & Widen To 2 Ln
Rdwy With ShouldersAT&T
37 $25,308.00N/A
CSReconstruct & Widen To 2 Ln
Rdwy With ShouldersMagic Valley Electric Co-op
5 $3,420.00
MVEC RELOCATED POLES TO NEW ROW. SP 004-017 USED
TO CALCULATE COST/DAY.
PARIS
PHARR
Texas Department of Transportation
8/16/2019 Utility Relocation Report
32/35
22
District Highway Description Ut ility Owner Time Delay (Days) Additional Costs Comments
FM 681Widen To 4 Lane Divided
UrbanAT&T 600 $1,122,742.00
AT&T is currently adjusting their non-compensable lines
and is working on providing areas were the contractor can
work. The estimated completion date for the adjustments
of their non-compensable lines was 8/28/15. AT&T
continues with adjustments as of today (May 13, 2016).
The adjustment of AT&T's compensable strucutres
(remote terminals) has not begun.
US 83 Interchange Improvements AT&T
357 $1,200,000.00
Contractor has been able to work in other areas of the
project. TxDOT communicates with AT&T on a bi-weekly
basis.
US 83 Interc hang e Improvement s Texas Gas Serv ic e
281 $0.00
N/A
US 83 Interchange Improvements AEP
236 $0.00
N/A
CS
Construct Sidewalks,
Redesign Crosswalks, & Install
Bike Racks
AT&T
70 $46,685.00
The overhead AT&T lines were in conflict with the
proposed pedestrian bridge. Plan Sheet 97, Sta. 6+00.
FM 78Reconstruct And Widen
Existing RoadwayAT&T
180 $0.00
N/A
FM 1101
Widen Existing Roadway To
Provide A Continuous Left
Turn Lane, Bike
Accommodation Lane And
Sidewalks
AT&T
180 $0.00
Delay claim anticipated from contractor
IH 10
Widen & Convert Frontage
Roads To One Way, Add New
Ramp & Convert Existing
Ramps To One Way
Operation
AT&T
180 $0.00
Delay claim anticipated from contractor
SAN ANTONIO
Texas Department of Transportation
8/16/2019 Utility Relocation Report
33/35
23
District Highway Description Ut ility Owner Time Delay (Days) Additional Costs Comments
FM 306
Expand 2 To 4 Lanes With
Continuous Left Turn Lane,
Bike Lanes And Sidewalks
AT&T
180 $0.00
N/A
TYLER
SH 64Widen 2 Ln Roadway To
Super-2 (3 Lane) CriteriaAT&T
60 $0.00
AT&T was notified of future construction project inOctober 2013. Upon reviewing the plans, they responded
that no conflicts were present. Conflicts during
construction were encountered in October 2014 and was
resolved at the end of August 2015. TxDOT contractor
time was suspended 2 months and has been working
around the conflict areas.
FM 2311
Widen Pavement To Add
Shoulders, Provide Safety
Upgrades And Resurface
AT&T
130 $13,018.18
Contractor requested amount is in negotiations.
SH 317Widen From Two To Four
Lanes With Raised MedianAT&T
83 $50,225.28
N/A
FM 933
Widen From Two To Four
Lanes With Continuous Left
Turn Lane And Resurface
Texas New Mexico Power
45 $45,000.00
This is an estimated delay cost. The contractor has not
submitted an actual claim.
FM 933
Widen From Two To Four
Lanes With Continuous Left
Turn Lane And Resurface
Windstream
45 $45,000.00
This is an estimated delay cost. The contractor has not
submitted an actual claim.
FM 933
Widen From Two To Four
Lanes With Continuous Left
Turn Lane And Resurface
City of Whitney buried Water
and Sanitary Sewer
20 $20,000.00
This is an estimated delay cost. The contractor has not
submitted an actual claim.
FM 933
Widen From Two To Four
Lanes With Continuous Left
Turn Lane And Resurface
City of Whitney
0 $4,138.16
Contract canceled
WACO
Texas Department of Transportation
8/16/2019 Utility Relocation Report
34/35
24
District Highway Description Ut ility Owner Time Delay (Days) Additional Costs Comments
IH 35Construct Southbound And
Northbound Frontage RoadsAtmos Gas
50 $150,000.00
This is an estimated delay cost. The contractor has not
submitted an actual claim.
IH 35Construct Southbound And
Northbound Frontage RoadsCity of Waco Water
30 $60,000.00
This is an estimated delay cost. The contractor has not
submitted an actual claim.
IH 35Construct Southbound And
Northbound Frontage Roads
Grande Communications
Fiber Optics4 $10,000.00
This is an estimated delay cost. The contractor has not
submitted an actual claim.
IH 35Construct Southbound And
Northbound Frontage RoadsWindstream
4 $10,000.00
This is an estimated delay cost. The contractor has not
submitted an actual claim.
IH 35Construct Southbound And
Northbound Frontage RoadsCity of Waco Sanitary Sewer
60 $50,000.00
This is an estimated delay cost. The contractor has not
submitted an actual claim.
FM 1637
Reconstruct And Widen From
Two To Four Lanes With
Raised Median
City of Waco (Water &
Sewer)60 $87,500.00
This is an estimated delay cost. The contractor has not
submitted an actual claim.
FM 1637
Reconstruct And Widen From
Two To Four Lanes With
Raised Median
Time Warner Cable
60 $87,500.00
This is an estimated delay cost. The contractor has not
submitted an actual claim.
FM 2837Intersection Operational
ImprovementSunoco Logistics
153 $10,506.25N/A
SH 6Add Continuous Left Turn
Lane And ShouldersAT&T
108 $0.00
Time was suspended and contractor did not request
additional payment
IH 35Reconstruct And Widen From
Four To Eight LanesAT&T
125 $500,000.00
This is an estimated delay cost. The contractor has not
submitted an actual claim.
Texas Department of Transportation
8/16/2019 Utility Relocation Report
35/35
25
District Highway Description Ut ility Owner Time Delay (Days) Additional Costs Comments
IH 35Reconstruct And Widen From
Four To Eight LanesTime Warner
50 $200,000.00
This is an estimated delay cost. The contractor has not
submitted an actual claim.
SH 240Replace Bridge And
ApproachesAT&T
100 TBD
Additional AT&T conflict identified on July 15, 2015. Delay
from September 15, 2015, to February 16th, 2016 while
the contractor waited for the line to be relocated.
CRReplace Bridge And
ApproachesAT&T
12 $0.00
Contractor was delayed from November 18th, 2014, to
December 8th, 2014.
FM 108Replace Bridge And
ApproachesAT&T
6 $0.00N/A
FM 155Replace Bridge And
ApproachesFayette Electric Coop., Inc.
13 $0.00N/A
CRReplace Bridge And
ApproachesSan Bernard Electric CO-OP
4 $0.00N/A
US 59 Construct Frontage Roads AT&T159 $529,847.89
The utility delay occurred between 10/28/13 to 9/29/14
10,432 $21,900,639.34Total Delay in Days and Cost
WICHITA FALLS
YOAKUM