USJE Integrated Environmental Permit Application
Bosko [email protected]
USJE Integrated Environmental Permit Application
Willingness
Already achieved results
Location
Human resources
USJE Integrated Environmental Permit Application
Established
1968 Kiln #3
1970 Kiln #4
TITAN TAKES OVER
PRESENTLYPRESENTLY:
574 Employees:574 Employees:
Products:Products:
1955
1998
1980 Major reconstruction Clinker Cement Insulation materialRMC
USJE Integrated Environmental Permit Application
Location
USJE Integrated Environmental Permit Application
Dry process Cyclone preheater
No precalciner
Fabric filters
USJE Integrated Environmental Permit Application
Dust (TPM) Point sources
Fugitive (incl. Quarrying and transport)
16 mg/Nm3
0.198 kg/t
SO2Point sources 73 g/t
NOxPoint sources 835 mg/Nm3
USJE Integrated Environmental Permit Application
Quality Management ISO 9000/2000
Environmental Management System
Emissions Monitoring System:
Preparations for ISO 14001
Centralized and computerized data acquisition and reporting
General Issues (Reputation/image) Operational (Equipment, health and
safety, security, human resources) Finantial Sources/reasons for emergency Preventiov/response Accidents reported
USJE Integrated Environmental Permit Application
Stright the way orvia an adjustment (compliance) plan?
Gap between the current practice and BAT
Investments required
Time required
Technical viability
Financial burden
USJE Integrated Environmental Permit Application
Law on Environment
Ordinance on IPPC
Application form
Not addoptedyet
Waiting to beissued
Main company’sactivity
USJE Integrated Environmental Permit Application
Collecting data on raw materials, energy and auxiliary materials
Emission measurements carried outby authorized laboratories
Public communication established
USJE Integrated Environmental Permit Application
Nox (mg/m3) 200-500 835
SO2 (mg/m3) 200-400 68
Dust (mg/m3) 20-30 16
Energy use (MJ/t) 3000 3700
Electricity (kWh/t cement) 90-130 99
BABATT
USJEUSJEIndicatorIndicator
USJE Integrated Environmental Permit Application
Products handlingProducts handling Improvement required
Process optimisationProcess optimisation Required
MonitoringMonitoring Satisfactory
EMSEMS On the way
Emergency responseEmergency response Modifications required
Raw materials preparingRaw materials preparing Improvement required
USJE Integrated Environmental Permit Application
Usje cement plant is seriously being prepared for submitting the application form for integrated permit
In order to reduce the financial burden they will rather apply for adjustment permit as soon as the new Law on the environment comes into force