Using the Underground Traverse Calculator
Team #1 Begins a Traverse
• Luke Skywalker and Sandra Bullock begin an underground traverse as Team #1
• There first action is to go to Grate above their “Mine Shaft” and hang their two plumb bobs
They Carefully Measure How Far the Plumb-Bobs are from the
corners
1 foot
1 foot
1 foot
1foot
Now They Enter Their Data in the Spreadsheet
The Spreadsheet calls for these distances to be entered in inches
They Set Up Their Instrument Underground
• So that they can sight directly across the strings that hold the plumb bobs
• They set the backsight angle on their Nikon 20 Total Station to 0
• They measure the distance to the closest plumb bob (called plumb-bob 2 by the spreadsheet)
• And they measure their height of instrument.
They Enter Their Measurements into the Spreadsheet
The distance fromThe plumb bob toTheir instrument was10.25 feet
The height of theirInstrument is 4.6 feet(note that the unitsMust be by decimalFeet)
The spreadsheet is now reporting their backsight azimuth and the coordinatesOf their station location.
Luke and Sandra Set Up a Foresight Point Through Where the
Pipes Cross the TunnelThey put in theirAngle to the right(289 30 00)
And their verticalAngle(92 05 00)
They put in oneTo indicate theyWorked DMS
And another 1 toIndicate they hadA zenith angleinstrument
They Also Put In Their EDM Data
The Coordinates of the Foresight Point Appear
Luke and Sandra Next Move to Point B and Shoot Down the
Tunnel to Where there is a BranchCalculation of Foresight Point Location
Instrument Location B Coordinates of Foresight Point
Back Sight Point A Northing Easting Elev
Foresight Point C 381097.7 2570623 434.6192
Instrument Used Nikon 20
Survey Date Sept 11 2021Angle Conversions Grads Mills Degrees Minutes Seconds
Horizontal Angle 90 20 10Zenith Angle 1 Vertical Angle 90(1=Yes, 2=Horizontal) Set 1 by units 1
Shot DataBack Sight Present Station Angles Rod Readings EDMAzimuth N E Elev Height Ins H to Right Vert Angle Center R Upper R Lower R Dist Height Pole275.5017 381082.8 2570622 434.6192 4.6 90.33611 0 15 4.6
Offset to Left side #DIV/0!Offset to Right side
They put in their Horizontal andVertical Angles Their EDM dat
Their height of instruments
And the 1’s that indicateThey had a Zenith AngleInstrument working inDegrees Minutes and Sec.
They Move Down to Point CStation 3 Point information
Instrument Location C
Back Sight Point B
Instrument Used Total Station
Survey Date Sept 18 2021
Back Sight Present StationAzimuth N E Elev Height Ins185.8379 381097.7 2570623 434.6192 4.3
Grate(intermediate shot points)
ManholeGrate(intermediate shot points)
Foresight Point
From Here They Will TakeThree Types of Shots
1- They will turn and takeA side shot down theBranch Tunnel. (TheSpreadsheet calls this aBranch shot)
2- They will shoot down toA manhole using a sideShot. (The SpreadsheetCalls this an intermediateShot).
3- They will shoot to aForesight where the tunnelturns
They Take the Side Shot Down the Tunnel and Put in the Data
Calculations for the Coordinates for Branch ShotBranch Shot 1 from point C
Instrument Location C Coordinates of Sideshot PointBack Sight Piont B Northing Easting ElevSideShot Point C1 381089.6 2570701 434.6192Instrument Used Nikon 20Survey Date Sept 11 2021
Angle Conversions Grads Mills Degrees Minutes SecondsHorizontal Angle 270 10 0
Zenith Angle 1 Vertical Angle 90(1=Yes, 2=Horizontal) Set 1 by units 1
Shot DataBack Sight Present Station Angles Rod Readings EDMAzimuth N E Elev Height Ins H to Right Vert Angle Center R Upper R Lower R Dist Height Pole185.8379 381097.7 2570623 434.6192 4.6 270.1667 0 78 4.6
Offset to Left sideOffset to Right side
Angles EDM Data
Height of Instrument
Instrument Type
They get the coordinates at the end of the side tunnel
They Take A Shot Down the Tunnel to Where the Reflector is Placed
Beneath the Manhole CoverCalculation of Intermediate Shots from Point C
Instrument Location C Coordinates of Intermediate Shot PointBack Sight Piont B Northing Easting ElevSideShot Point C2 381366.6 2570647 431.085Instrument Used Total StationSurvey Date Sept 11 2021
Angle Conversions Grads Mills Degrees Minutes SecondsHorizontal Angle 179 15 0
Zenith Angle 1 Vertical Angle 90 45(1=Yes, 2=Horizontal) Set 1 by units 1
Shot DataBack Sight Present Station Angles Rod Readings EDMAzimuth N E Elev Height Ins H to Right Vert Angle Center R Upper R Lower R Dist Height Pole185.8379 381097.7 2570623 434.6192 4.6 179.25 -0.75 270 4.6
Offset to Left sideOffset to Right side
They get the coordinates under the Manhole Cover.
Then they Take the Foresight Shot to Where the Tunnel Turns Sharply
LeftCalculation of Foresight Point Location
Instrument Location C Coordinates of Foresight Point
Back Sight Point B Northing Easting Elev
Foresight Point D 381473.8 2570661 429.6713
Instrument Used Nikon 20
Survey Date Sept 11 2021Angle Conversions Grads Mills Degrees Minutes Seconds
Horizontal Angle 179 56Zenith Angle 1 Vertical Angle 90 45(1=Yes, 2=Horizontal) Set 1 by units 1
Shot DataBack Sight Present Station Angles Rod Readings EDMAzimuth N E Elev Height Ins H to Right Vert Angle Center R Upper R Lower R Dist Height Pole185.8379 381097.7 2570623 434.6192 4.6 179.9333 -0.75 378 4.6
Offset to Left side #DIV/0!Offset to Right side
They get the coordinates of the next pointThey will occupy
Sandra and Luke Continue Their Survey
• They work their way down to where they will get the coordinates of the two points used by other teams to go further down the tunnels
• Of course their own tunnel did a T at one point. Now they must go back and survey where the Tunnel went the other direction.
Here is Their Situation
They reset their instrument underTheir Point B (which they already have theCoordinates of)
They set a plumb-bob on their old station C(Which they also have the coordinates of).They will use point C as a Backsight
They set up a Foresight Point down the Branch ofThe tunnel they will now survey.
The Spreadsheet is Arranged Like This
Team #1 calculations Starting at the Plumb-Bobs hangingDown the shaft.
Calculations for any other team starting a survey givenTwo known points (surveyed in by another team thatBrought control positions and directions in from thePlumb-bobs hanging down the shaft).
Luke and Sandra Take A Look At This Area of the Spreadsheet
Beginning of Surveys Using 2 Initial PointsN E Elev
Point 1 200 200 443Point 2 225 170 443
Assume that instrument is set up Under Point 2and is backsighting point 1
Sandra and Luke note that virtually any team that started withTwo points provided by another team would begin here.
Point 2 is where they are set-up
Point 1 is the backsight.
They Put in the Point Coordinates and Get the Direction of Their
Backsight Line
N E ElevPoint 1 381098 2570623 434.6Point 2 381083 2570622 434.6
Assume that instrument is set up Under Point 2and is backsighting point 1
Delta N 15Delta E 1Quadrant 1Azimuth 3.814075
Now They Get Ready for Their First Foresight Shot Down the Tunnel
Calculation of Foresight Point LocationInstrument Location Point 2 Coordinates of Foresight Point
Back Sight Point Point 1 Northing Easting Elev
Foresight Point B 381065 2570621 434.6
Instrument Used Nikon 20
Survey Date Sept 18 2021Angle Conversions Grads Mills Degrees Minutes Seconds
Horizontal Angle 180 15Zenith Angle 1 Vertical Angle 90(1=Yes, 2=Horizontal) Set 1 by units 1
Shot DataBack Sight Present Station Angles Rod Readings EDMAzimuth N E Elev Height Ins H to Right Vert Angle Center R Upper R Lower R Dist Height Pole3.814075 381083 2570622 434.6 4.6 180.25 0 18 4.6
Offset to Left side #DIV/0!Offset to Right side
They put in their data and get the coordinates of theNext station they will move on to occupy.
Things for You To Note
• This Slide Set Shows you how to– Establish a backsight direction and instrument position from two
plumb-bobs hanging down the shaft.– Establish a backsight direction and instrument position if you
have the coordinates of two points and set up under the 2nd.– How to take a shot down a tunnel that branches off of the main
tunnel– How to take a shot to an intermediate point down a tunnel such
as a manhole cover of vent grate
• These same operations should allow any of our Underground Survey Teams to get the coordinates of the points running down the center line of our underground steam tunnels.