33
Using Alternative Delivery Methods to Increase Competiveness on Tunnel Projects Steven R. Kramer, PE, FASCE [email protected] August 14, 2017

Using Alternative Delivery Methods to Increase

  • Upload
    others

  • View
    5

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Using Alternative Delivery Methods to Increase

Using Alternative Delivery Methodsto Increase Competiveness on Tunnel Projects

Steven R. Kramer, PE, [email protected]

August 14, 2017

Page 2: Using Alternative Delivery Methods to Increase

Presentation Outline

1. Alternative Project Delivery Methods

2. Owner's Needs on Major Capital Projects / Current Trends in Tunneling

3. Comparison of Cost Drivers

4. Case Studies in Delivery of Tunnel Projects

5. Bidding Strategies for Increasing Competitiveness

2

Page 3: Using Alternative Delivery Methods to Increase

Types of Project Delivery Alternatives

▪ Design-Bid-Build

▪ CM At Risk

▪ Progressive Design-Build

▪ Design-Build Competitive

▪ Design-Build-Operate

▪ DBOF/P3 Concession

Design-BidBuild PrivatizationCMAR DBFO/P3Progressive DB Design-Build DBO

Public-Private-Partnership (PPP)

3

Page 4: Using Alternative Delivery Methods to Increase

Overview Alternative Delivery Methods

› CM At Risk (CMAR): constructor selected based on qualifications shortly after the designer selection. Provides pre-construction services. Between 50-60% design development, CMAR provides price & schedule proposal.

› Progressive Design-Build: involves the design-build team during the earliest stages of the owner’s project development. Promotes collaboration between owner, designer and contractor.

› Design-Build Lump Sum: risk and responsibility for providing both design and construction with one entity under one contract with the Owner.

› Design-Build-Operate: form of project financing, wherein a private entity receives a concession from the public sector to finance, design, construct, own, and operate a facility.

› DBFOM / P3 / Concession: contractual arrangement between a public agency and the private sector. Through this agreement, the skills and assets of each sector shared in delivering facility for the use of the general public.

4

Page 5: Using Alternative Delivery Methods to Increase

Collaborative Delivery Methods

Provides Owners Solutions Addressing:

› Project Delivery Risk Allocation

› Schedule Constraints

› Knowledge of Project Cost

› Performance Assurance

5

Page 6: Using Alternative Delivery Methods to Increase

Alternative Delivery Project Structures

6

Page 7: Using Alternative Delivery Methods to Increase

Collaborative Project Delivery Integrates Design, Long Lead Item Procurement and Construction Activities

Det

ail

Dra

win

gsan

dSp

ecifi

catio

ns

ConstructionBidPrelim.Plans

Feasibility Studies

Detail Drawings &Specifications

Construction

Feasibility Studies

Des

ign

Crit

eria

Perf

orm

ance

Req

mt’s

10 – 30%

Bidor GMP

TimeSaved

7

Page 8: Using Alternative Delivery Methods to Increase

Alternative Delivery Methods

› What are the Benefits:

› Single entity responsible for design, construction, technology integration and overall project delivery performance

› Shorter schedule and less schedule risk (reduced interfaces)

› Early cost certainty (less potential cost growth)

› Efficient administration for Owner

› Fewer potential disputes and change orders

8

Page 9: Using Alternative Delivery Methods to Increase

Additional Collaborative/Alternative Delivery Methods

› CM At Risk (CMAR)

› Progressive Design-Build

› Design-Build Lump Sum

› Design-Build-Operate

› DBFOM / P3 / Concession

› Contract Packaging

› CMGC

› Modified Fix Fee Plus Cost Reimbursable

› Early Contractor Involvement

› Pre-qualification of Contractor

› Advance Purchase of TBM

9

Page 10: Using Alternative Delivery Methods to Increase

› Competitive Bidding Atmosphere

› Delivered On-Time and On-Budget

› Safety Culture

› Understand Owner Policy and Procedures

› Willingness to Partner and Resolve Issues

› Provide People with Right Experience & Right Equipment

› Be Proactive Before Problems Arise

› Understands Public Outreach and How to Respond to Public

Owner's Needs on Major Capital Projects

10

Page 11: Using Alternative Delivery Methods to Increase

Current Trends in Tunneling & Procurement

• Contract documents tailored to industry standards• Differing Site Conditions (DSC), Geotechnical

Baseline Reports (GBR), Dispute Review Boards (DRB)

Contractor’s Expectations

• Generally small, close-knit community• Good understanding of project risks & contract

savvy • Frequently team on large projects

Nature of Tunneling Contractors

• International contractors now bidding & winning North America projects

• Movement away from conventional delivery for very large projects

• Relationship changing between owners and consulting engineers with alternative delivery

Current Atmosphere for Bidding in North America

• Start early to gain interest• Create forums to foster relationships• Identify opportunities for M/WBE Firms• Identify contract packages

Pro-Active Approach

11

Page 12: Using Alternative Delivery Methods to Increase

Comparison of Cost Drivers

General Construction Cost Drivers

Tunnel Cost Drivers

Materials

Labor

Equipment

Design Quality

Business Climate / Market

Contract Method

Environment / Location

Indirects / Insurance

Inflation

Differing Site Conditions

Design Development & Unforeseen Design Changes

Linear Nature of the Work

Scope Changes & Transfer

Shaft Construction

Bonding & Limitations

Limited Contractor Pool

Specialized Labor

Ownership of Risk

12

Page 13: Using Alternative Delivery Methods to Increase

Case Studies in Tunneling & Procurement

Pentagon Renovation Program – Water Intake Tunnel

Implementing Target Price to Incentivize Team

Port of Miami Tunnel

Using Novel Contingency Approach for High-Risk Tunnel

Hong Kong Highways Dept. / Tuen Mun-ChekLap Kok Link

Procuring the World’s Largest TBM

Portland CSO Program

Alliance Contract to Create a Partnership

13

Page 14: Using Alternative Delivery Methods to Increase

Port of Miami Tunnel, Miami, FL

14

Page 15: Using Alternative Delivery Methods to Increase

✓ World’s busiest port for cruise ship dockings

✓ Largest container port in Florida (10th largest worldwide)

✓ $12 Billion economic impact

✓ 16,000 vehicles/day to and from Port

✓ 28% truck traffic

✓ 5,500 trucks & buses travel to/from POM through downtown streets

Facts on Port of Miami Tunnel

15

Page 16: Using Alternative Delivery Methods to Increase

Deal with FDOT

› Financial close: October 15, 2009

› 55-months for construction

› Project cost: $1.062 Billion (Bank Debt, TIFIA Loans, Concessionaire

› Description: 30-year Design, Build, Finance, Operation & Maintenance (DBOFM) Concession

› Operate until October 15, 2044

› DB Contractor/Designer: Bouygues/Jacobs

› Owner's Rep: WSP (PB)

16

Page 17: Using Alternative Delivery Methods to Increase

› Owner: Florida DOT

› Twin tunnels each 4,200 ft long, 39 ft ID between Watson and Dodge Islands

› Fill, Plastic Sandy Silt / Silty Sand, Limestone

› Closed Face EPBM/Water Control Process

› One-pass Precast Concrete Segmental Lining

Port of Miami Tunnel

Sand With Inclusion of Interbedded Zones of Sandstone

17

Page 18: Using Alternative Delivery Methods to Increase

Port of Miami Tunnel

Success Factors

› Risk Allocation Tools Used

› GBR

› DRB

› Risk Sharing

› Defined Contingency

› $180 million contingency

› Contractor responsible for initial $10 million of overruns for unexpected geotechnical conditions

› Owner responsible for next $150 million

› Contractor responsible for final $20 million

› Over $180 million either party can terminate

18

Page 19: Using Alternative Delivery Methods to Increase

Tuen Mun—Chek Lap Kok Link, China

Overview

› Iconic project as a direct road connection between Tuen Mun, Hong Kong international airport and for routes south to developing industrial zones

› $6B project includes dual two lane (+ slow lane) roads of 6 miles long using 57.7 ft and 46 ft Slurry TBM’s under the seabed with a water head of 70psi

› Geology of mainly Alluvium and decomposed granite

19

Page 20: Using Alternative Delivery Methods to Increase

Contract Type & Special Conditions

› Standard DB contract with revaluation for quantity and change of conditions (Contractor: Bouygues, Designer: Arup, Owner's Rep: AECOM)

› Early milestone payments to cover TBM

› Slurry type TBM specified in the tender. Ground conditions specified in general terms for the TBM capability but no GBR supplied

› Proposer estimated rate for different ground conditions so the payment could be adjusted if required without a formal claims process

20

Page 21: Using Alternative Delivery Methods to Increase

DB Delivery Method

› Late change from bridge link to tunnel due to environmental issues and to maintain schedule

› Bored Tunnel increased construction risk due to the 70psi water pressure

› General Consultants opinion that only a special slurry TBM would be suitable and reduce risk

› Heavily specified TBM and method & support services, eliminated lower cost alternative such as EPB TBM

› Provided a technical “level playing field”

21

Page 22: Using Alternative Delivery Methods to Increase

Pentagon Renovation Program – Water Intake Tunnel

MANAGING COSTS USING FEE AT RISK

› 8 ft diameter intake tunnel

› Complex soft ground beneath the water table

› Integrated team using DB

› Cost reimbursable contract with award fee structure

22

Page 23: Using Alternative Delivery Methods to Increase

Pentagon Renovation Program – Water Intake Tunnel

SITE CONSTRAINTS DURING DESIGN & CONSTRUCTION› Installing the intake through a complex

geology beneath the water table› Crossing beneath neighboring structures

and roadways› Coordination of the work with multiple

outside agencies including local, state and federal groups

› Fast track design and construction using the design/build process

23

Page 24: Using Alternative Delivery Methods to Increase

Pentagon Renovation Program – Water Intake Tunnel

CONTRACTUAL APPROACH › Design – Build Cost Plus Incentive/Award Fee Contract› 10% Award Fee Pool based on Performance (award fee

only profit)› Performance criteria: quality, safety, cost control &

management› Negotiated Target Cost› Changes to Target Cost

› Increases due to cost overruns do not result in adjustment

› Government caused changes result in adjustment› Differing site conditions w/o substantial impact result in

adjustment to target but not award fee› Differing site conditions w/ substantial impact result in

adjustment to target and award fee

24

Page 25: Using Alternative Delivery Methods to Increase

Portland CSO Program

› 6 miles of 22 ft diam. CSO tunnel

(East Side Tunnel)

› 9 – 84 inch microtunnel connector drives (one at 3,055 ft)

› 7 shafts 49 to 60 ft diameter, up to 165 ft deep

25

Page 26: Using Alternative Delivery Methods to Increase

Portland CSO Program

CHALLENGES

› Urban construction

› Complex geology

› New technology

› Sensitive urban public

SOLUTION

› Alliance Contract – modified fixed fee / cost reimbursable

› Contractor selected at 50% design stage

› Single voice public liaison

26

Page 27: Using Alternative Delivery Methods to Increase

Portland CSO Program

WHY AN ALLIANCE CONTRACT (NOT DESIGN-BUILD)?

› City controls the design

› City retained opportunity to use conventional bid

› History – poor cost control with guaranteed maximum price underground projects

WHAT WENT RIGHT?

› On time, on budget

› Strong partnership between Owner / Designer / Contractor

› Good public relations

› Most issues solved before construction began

› Rapid resolution of field issues

27

Page 28: Using Alternative Delivery Methods to Increase

Portland CSO Program

28

Page 29: Using Alternative Delivery Methods to Increase

Bidding Strategies for Increasing Competiveness

› Progressive design build

› Modified fixed fee plus cost reimbursable

› Fee at risk approaches

› Risk mitigation techniques with shared contingency

› Best value formulas

› Advance purchase of TBM

› Pre-qualification approaches

› Contract packaging

› CMGC (construction manager general contractor)

› CM at risk

29

Page 30: Using Alternative Delivery Methods to Increase

Where Innovative Strategies Implemented

G

A

E

C

FK

IJ

HB

D

30

North America

A. CSO Program Portland, OR (Modified Fixed Fee)

B. LA County MTA – Purple Line Ext., CA (DB)

C. Atlanta Raw Water Tunnel, GA (CMAR)

D. ATL Plane Train Tunnel Expansion, GA (Progressive DB)

E. Port of Miami, FL (Shared Contingency)

F. Toronto Transit (Pre-Purchase TBM)

G. DC Water CSO Program, DC (Pre-Qual & DB)

H. Pentagon Intake – Outfall Tunnel, Arlington, VA (Fee at Risk)

I. FDOT – Midtown Tunnel, VA (P3)

J. CBBT – Parallel Thimble Shoal Tunnel, VA (Pre-Qual & DB)

K. Narragansett Bay (Shared Savings)

Page 31: Using Alternative Delivery Methods to Increase

Benefits of Using Alternative Bid Strategies

Approach Successfully Implemented

Used at agencies

US Application

Produced Cost

SavingsImproved Schedule

Reduced Claims

Increased Competitive-

ness

Modified Fixed Fee plus Cost Reimbursable ✓ ✓ ✓ ✓ ✓ ✓ ✓

Fee at Risk ✓ -- ✓ ✓ ✓ ✓ ✓

Risk Mitigation with Shared Contingency ✓ ✓ ✓ ✓ ✓ ✓ ✓

Pre-qualification ✓ ✓ ✓ -- -- ✓ ✓

Advanced Purchase of Equipment ✓ ✓ ✓ ? ✓ ? ✓

Share Risk Register with Contractors ✓ ✓ ✓ ✓ ✓ ✓ ✓

Early Contractor Buy-In ✓ ✓ ✓ ✓ ✓ ✓ ✓

Identification of Contractor Means and Methods ✓ ✓ ✓ ✓ ✓ ✓ ✓

31

Page 32: Using Alternative Delivery Methods to Increase

Using Early Contractor Involvement

EARLY CONTRACTOR BUY-IN

› Contractor has his “head in the job” before construction begins

› Takes advantage of contractor experience and insight into the design

› Fosters synergy and teamwork between owner/designer/contractor

Benefit: Develops realistic schedule and accurate pre-construction cost estimate

RISK SHARING

› Contractor(s) included in risk register development and mitigation measures at design stage

Benefit: Reduce disputes for unforeseen condition

EARLY CONTRACTOR INVOLVEMENT / INCORPORATE CONTRACTOR MEANS & METHODS

› Design is open to the strengths of the potential contractors

Benefit: Focused, efficient design. Avoids designer guessing contractor’s means & methods

32

Page 33: Using Alternative Delivery Methods to Increase

Project Success

33