User Provisioning Project Design Phase Presented to ITLC March 24, 2011 David Walker, ITAG Co-Chair Information and Educational Technology, UC Davis Mary Doyle, ITAG ITLC Liaison Information Technology Services, UC Santa Cruz

User Provisioning Project Design Phase Presented to ITLC March 24, 2011 David Walker, ITAG Co-Chair Information and Educational Technology, UC Davis Mary

Embed Size (px)

DESCRIPTION

Overview Charge from the ITLC Recap of work through September 2010 Actions at September 28, 2010 ITLC meeting Work on design phase Next steps Possible value to shared systems (PPS/HR) Discussion

Citation preview

Page 1: User Provisioning Project Design Phase Presented to ITLC March 24, 2011 David Walker, ITAG Co-Chair Information and Educational Technology, UC Davis Mary

User Provisioning ProjectDesign Phase

Presented to ITLC March 24, 2011

David Walker, ITAG Co-ChairInformation and Educational Technology, UC Davis

Mary Doyle, ITAG ITLC LiaisonInformation Technology Services, UC Santa Cruz

Page 2: User Provisioning Project Design Phase Presented to ITLC March 24, 2011 David Walker, ITAG Co-Chair Information and Educational Technology, UC Davis Mary

Project TeamDede Bruno, UCOP

Chet Burgess, UCOP

Dedra Chamberlain, UCB

Mary Doyle, UCSC

Datta Mahabalagiri, UCLA

Tony Merriweather, UCLA

Jeff McCullough, UCB

Benn Oshrin, UCB

David Walker, UCD

Albert Wu, UCLA

Page 3: User Provisioning Project Design Phase Presented to ITLC March 24, 2011 David Walker, ITAG Co-Chair Information and Educational Technology, UC Davis Mary

OverviewCharge from the ITLCRecap of work through September 2010Actions at September 28, 2010 ITLC meetingWork on design phaseNext stepsPossible value to shared systems (PPS/HR)Discussion

Page 4: User Provisioning Project Design Phase Presented to ITLC March 24, 2011 David Walker, ITAG Co-Chair Information and Educational Technology, UC Davis Mary

The Charge from ITLC

1. ITAG should recommend a specific middleware platform/approach to evaluate and pilot

2. ITAG should consider various projects/initiatives that could serve as a pilot for the approach

3. ITAG should present thoughts/observations relating to resources required to complete a successful pilot.

Page 5: User Provisioning Project Design Phase Presented to ITLC March 24, 2011 David Walker, ITAG Co-Chair Information and Educational Technology, UC Davis Mary

ITLC Meeting September 28, 2010Recap of work through September 2010Approval to begin work on design phaseFurther work approval contingent on design plan to be

complete in early 2012 (or accelerated depending on PPS/HRIS interface)

Allocation of up to $30k fundingFunding plan proposal needed

Page 6: User Provisioning Project Design Phase Presented to ITLC March 24, 2011 David Walker, ITAG Co-Chair Information and Educational Technology, UC Davis Mary

Work Through September 2010

High level design Roadmap for future phases Potential use cases

Page 7: User Provisioning Project Design Phase Presented to ITLC March 24, 2011 David Walker, ITAG Co-Chair Information and Educational Technology, UC Davis Mary

Proposal for User Provisioning A Service Provider (SP) specifies the identity attributes it

requires and the people it requires those attributes for. Identity Providers (IdP) configure their Attribute Release

Policies (ARP) for the SP. The IdP also defines the group of its community members required by the SP.

At a time determined by the SP, the SP requests all attributes allowed by the ARP.

Page 8: User Provisioning Project Design Phase Presented to ITLC March 24, 2011 David Walker, ITAG Co-Chair Information and Educational Technology, UC Davis Mary

High-Level Design

Page 9: User Provisioning Project Design Phase Presented to ITLC March 24, 2011 David Walker, ITAG Co-Chair Information and Educational Technology, UC Davis Mary

Proposed Project Phases and Tasks

Phase 1Detailed Planning – 16 weeks*

commencing January 28, 2011 and completed April 30, 2011

1.1 Staffing/Recruiting1.2 Develop Detailed Project Plan1.3 Develop Detailed Architecture

(*timing adjusted to reflect actual duration estimates as of March 17, 2011)

Page 10: User Provisioning Project Design Phase Presented to ITLC March 24, 2011 David Walker, ITAG Co-Chair Information and Educational Technology, UC Davis Mary

Phases and Tasks continued….Phase 2

Design, Build, Test – Approximately one year

2.1 Technology evaluation and selection2.2 Develop Communications Plan

2.3 Design and Implement Common IAM Interface2.4 Prepare Product Documentation2.5 Test, QA2.6 Release Product2.7 Pilot Deployment

Page 11: User Provisioning Project Design Phase Presented to ITLC March 24, 2011 David Walker, ITAG Co-Chair Information and Educational Technology, UC Davis Mary

Phases and Tasks, continued…..

Phase 3Deployment (~ 9 months done by each UC location)

3.1 Implement Group Manager (Grouper)3.2 Implement eduPersonTargetedID3.3 Campus policy, procedure, relationships for

brokering requests3.4 Integrate Common IAM Interface with local

IAM (Snapshot)3.5 Integrate Common IAM with local IAM

(Subscription and Change Log)

Page 12: User Provisioning Project Design Phase Presented to ITLC March 24, 2011 David Walker, ITAG Co-Chair Information and Educational Technology, UC Davis Mary

Design Phase Kick-off meeting @ UCOP January 28th Create conceptual design Create component diagram Create use case diagram Complete detailed design – end of April Review of design – early May Request approval to move forward at May ITLC meeting

Page 13: User Provisioning Project Design Phase Presented to ITLC March 24, 2011 David Walker, ITAG Co-Chair Information and Educational Technology, UC Davis Mary

Conceptual Design

Page 14: User Provisioning Project Design Phase Presented to ITLC March 24, 2011 David Walker, ITAG Co-Chair Information and Educational Technology, UC Davis Mary

Component Diagram

Page 15: User Provisioning Project Design Phase Presented to ITLC March 24, 2011 David Walker, ITAG Co-Chair Information and Educational Technology, UC Davis Mary

Use Case Diagram

Page 16: User Provisioning Project Design Phase Presented to ITLC March 24, 2011 David Walker, ITAG Co-Chair Information and Educational Technology, UC Davis Mary

Next Steps

• Gain understanding of similar work occurring outside UC through consultation with non-UC IdM resources to validate approach and finalize design

• Complete detailed design• Continue to conduct bi-weekly check-ins• Explore potential relationship to PPS/HRIS project

needs

Page 17: User Provisioning Project Design Phase Presented to ITLC March 24, 2011 David Walker, ITAG Co-Chair Information and Educational Technology, UC Davis Mary

Funding Proposal

Travel reimbursement for in-person meetings

January 28, 2011

next meeting TBD

Page 18: User Provisioning Project Design Phase Presented to ITLC March 24, 2011 David Walker, ITAG Co-Chair Information and Educational Technology, UC Davis Mary

Can User Provisioning Support PPS/HRIS?

With the release of the PPS/HRIS rfp and the impending selection of a vendor, depending on the winning proposal, is there an opportunity to leverage the work of the user provisioning project in the PPS/HRIS project?

Page 19: User Provisioning Project Design Phase Presented to ITLC March 24, 2011 David Walker, ITAG Co-Chair Information and Educational Technology, UC Davis Mary

Discussion

• Questions/comments?

Page 20: User Provisioning Project Design Phase Presented to ITLC March 24, 2011 David Walker, ITAG Co-Chair Information and Educational Technology, UC Davis Mary

UCTrust StatusPresented to ITLC March 24,

2011

David Walker, UCTrust Work Group Co-ChairUC Davis

Dedra Chamberlin, UCTrust Work Group Co-ChairUC Berkeley

Page 21: User Provisioning Project Design Phase Presented to ITLC March 24, 2011 David Walker, ITAG Co-Chair Information and Educational Technology, UC Davis Mary

Current State UCTrust Basic certifications

All campuses, plus LBNL and UCOP, except... UCSB very soon

Current UCTrust Work Group Activities Assessment of InCommon Silver with UCITPS

Interoperability with UCTrust Basic Single certification process

Next generation campus IAM software components

The user provisioning project

Page 22: User Provisioning Project Design Phase Presented to ITLC March 24, 2011 David Walker, ITAG Co-Chair Information and Educational Technology, UC Davis Mary

Potential 2011 UCTrust Activities

Required by user provisioning project Group management TargetedID

User-controlled attribute release Administration of virtual organizations Guidance for service providers

Useful attributes and identifiers Determination of required level of assurance When should an application be federated?