Upload
others
View
1
Download
0
Embed Size (px)
Citation preview
Use of Numerical Modelling to Mitigate Ground Risk
Gavin & Doherty Geosolutions Ltd.
CECA MEETING – SEPT 2017
Overview
o Introduction to GDG
o Finite Element Modelling & Calibration
o Case Studies
o Flood Defences
o Retaining Walls
o High rise foundations
o Risk Analysis
o Conclusions
Todays Presentation….
GDG Introduction
o Gavin & Doherty Geosolutions (GDG) is a specialist geotechnical & civil engineering consultancy
o Offices in London, Edinburgh, Dublin, and Belfast,
o GDG was formed in 2011 in a challenging market
o Grown throughout the last five years
o Team of 40 highly talented engineers
o Majority of our staff are PhD qualified
o We provide innovative geotechnical solutions & efficient civil engineering designs for challenging projects
About us ….
Engineering Design Services
Structures Infrastructure
Offshore Renewables
R&D
Engineering Design Services
o Concept Design
o Site Investigation Scoping
o Site Investigation Interpretation
o Civil Engineering Design
o Temporary Works Design
o Numerical Modelling (FEA)
o Performance monitoring / instrumentation analysis
o Expert Witness Services
INFRASTRUCTURE
INFRASTRUCTURE
o Geotechnical Interpretation & Ground Modelling for Road, Railway and Flood Defence Schemes
o Geological Assessments & Mapping
o Earthworks Design
o Material Suitability
o Hydrogeological review
o Civil Engineering Design
o Numerical Modelling
o Soil-Structure-Water Interaction Analysis
o Back-analysis of failures & Root Cause Analysis
SERVICES & EXPERTISE
URBAN STRUCTURES
URBAN STRUCTURES
SERVICES & EXPERTISE
o Basement & Foundation Engineering
o Soil-Structure Interaction
o Ground Movement Assessments
o Retaining Wall Analysis
o Excavation Support and Propping Design
o Construction Sequencing & Temporary Works
o Pile Design & Piled Raft Analysis
o Tunnel and basement impact assessments
o Ground Improvement Engineering
OFFSHORE & MARINE
OFFSHORE & MARINE
SERVICES & EXPERTISE
o Analysis and Design of Ports & Harbours
o Quay Wall Numerical Modelling
o Offshore Substructure Analysis
o Offshore wind foundation engineering
o Gravity structures, monopiles, jacket piles, etc…
o Pile Installation analysis & Interpretation of offshore driving data
o Site suitability assessments
o Jack-up vessel studies
o Back-analysis of failures & Root Cause Analysis
• NNG Wind Farm
• Rampion Wind Farm
• Zawtika Gas Jacket Pile Analysis
• Hornsea Met Mast
• Firth of Forth Wind Farm Forensics
• Dogger Bank Jackup Analysis
• Shell Conductor Installation Studies North Sea
• Horizont Jacket Pile FEED
RELEVANT PROJECTS RENEWABLES
RENEWABLES
SERVICES & EXPERTISE
o Site suitability and feasibility studies for onshore wind and onshore solar farms
o Geotechnical risk studies
o Peat stability assessments
o Earthworks engineering for roads, crane bases, hardstands, etc.
o Foundation design for gravity and piled bases
o Interaction analysis for soil-structure-turbine behaviour.
Technical Presentation Sept 2017
www.gdgeo.com
• What is Ground Risk ?
Ground Risk
Technical Presentation Sept 2017
www.gdgeo.com
• Analytical – Traditional Theoretical Hand (spreadsheet) Calculations
• Empirical – Traditional Approaches based on experience of empirical evidence
• Numerical – Finite Element (or Finite Difference)
• Observational Design Approaches
Pick the most appropriate tool for your project
(consider the limitations of the tool, the complexity of the project and the accuracy required)
Design Tools Available
Technical Presentation Sept 2017
www.gdgeo.com
• Numerical Modelling Procedure to Determine Soil-Structure Response
• Modern Software Capable of Considering Complex Geometries
• The geometry is discretised into a mesh and the stresses and strains are resolved as loads/actions are applied
• Can accurately determine ground movements and structural stresses, provided the model is well calibrated
• Calibration requires (a) DATA and (b) EXPERTISE
Finite Element Method
Technical Presentation Sept 2017
www.gdgeo.com
• Soil is highly non-linear
– Pick an appropriate constitutive model
Basics of Geotechnics
Stre
ss
Strain
Real Soil
Elastic-Plastic
Technical Presentation Sept 2017
www.gdgeo.com
• FEM CALIBRATION
– Simulation of Lab Testing
– Look for repeatability
– Use range of test types
Finite Element Method
Technical Presentation Sept 2017
www.gdgeo.com
• FEM CALIBRATION
– Simulation of Field Testing
Finite Element Method
Technical Presentation Sept 2017
www.gdgeo.com
• TORONTO SEWER NETWORK TUNNEL ACCESS SHAFTS
• Access Shaft for TBM
• Complex Ground Conditions
• Underlying Aquifer
• Base Heave a Serious Concern !
• Design Solution Needed
CASE STUDY 1
Technical Presentation Sept 2017
www.gdgeo.com
• Model Calibration
CASE STUDY 1
Non-Plastic Till Fine Sand to Silt Plastic Till Sand to Sand and Gravel
𝑫𝒓𝒂𝒊𝒏𝒂𝒈𝒆 𝑻𝒚𝒑𝒆 - Drained Drained Undrained Drained
𝑷𝒆𝒓𝒎𝒆𝒂𝒃𝒊𝒍𝒊𝒕𝒚 𝑚 𝑠 1 × 10−6 4 × 10−5 8 × 10−8 3 × 10−4
𝜸𝒖𝒏𝒔𝒂𝒕 𝑘𝑁 𝑚3 18 18 24 18
𝜸𝒔𝒂𝒕 𝑘𝑁 𝑚3 20 20 24.3 20
𝒆𝟎 - 0.5 0.5 0.301 0.5
𝑬𝟓𝟎𝒓𝒆𝒇
𝑀𝑃𝑎 30 30 20 30
𝑬𝒐𝒆𝒅𝒓𝒆𝒇
𝑀𝑃𝑎 30 30 20 30
𝑬𝒖𝒓𝒓𝒆𝒇
𝑀𝑃𝑎 90 90 80 90
𝑷𝒐𝒘𝒆𝒓 (𝒎) - 0.5 0.5 0.5 0.5
𝒄𝒓𝒆𝒇 𝑘𝑃𝑎 0 0 0 0
𝝋 ° 35 35 35.9 35
𝝍 ° 5 5 9 5
𝒑𝒓𝒆𝒇 𝑘𝑃𝑎 100 100 100 100
𝑹𝒇 - 0.9 0.9 0.9 0.9
𝒌𝟎,𝒙 - 1 0.8 1.2 0.8
Technical Presentation Sept 2017
www.gdgeo.com
• TORONTO SEWER NETWORK TUNNEL ACCESS SHAFTS
• Undrained versus Drained
CASE STUDY 1
Technical Presentation Sept 2017
www.gdgeo.com
• TORONTO SEWER NETWORK TUNNEL ACCESS SHAFTS
CASE STUDY 1
Technical Presentation Sept 2017
www.gdgeo.com
• TORONTO SEWER NETWORK TUNNEL ACCESS SHAFTS
CASE STUDY 1
Technical Presentation Sept 2017
www.gdgeo.com
• TORONTO SEWER NETWORK TUNNEL ACCESS SHAFTS
CASE STUDY 1
Technical Presentation Sept 2017
www.gdgeo.com
• TORONTO SEWER NETWORK TUNNEL ACCESS SHAFTS
• Pore Pressures
(a) End of Excavation
(b) 10 weeks
(c) 20 weeks
(d) 50 weeks
CASE STUDY 1
(a) (b)
(c) (d)
Technical Presentation Sept 2017
www.gdgeo.com
• TORONTO SEWER NETWORK TUNNEL ACCESS SHAFTS
• Failure Avoided
• Facilitated Economic Construction Sequence
• Observational Method Used to Minimise Risk
CASE STUDY 1
Technical Presentation Sept 2017
www.gdgeo.com
• NATIONAL GALLERY UNDERPINNING ANALYSIS
CASE STUDY 2
Facilitate basement extension Geotechnical interpretation Geophysical profiling 3D Settlement Analysis of
Construction Stages Recommendation about
underpinning construction Final settlement design for
temporary and permanent works.
Technical Presentation Sept 2017
www.gdgeo.com
• NATIONAL GALLERY UNDERPINNING ANALYSIS
CASE STUDY 2
Technical Presentation Sept 2017
www.gdgeo.com
• NATIONAL GALLERY UNDERPINNING ANALYSIS
CASE STUDY 2
Technical Presentation Sept 2017
www.gdgeo.com
• NATIONAL GALLERY UNDERPINNING ANALYSIS
CASE STUDY 2
Technical Presentation Sept 2017
www.gdgeo.com
• NATIONAL GALLERY UNDERPINNING ANALYSIS
CASE STUDY 2
Technical Presentation Sept 2017
www.gdgeo.com
• NATIONAL GALLERY UNDERPINNING
• Settlements predicted to be less than 10mm in worst case
• Generally less than 5 mm
• Concrete underpinning shown to be appropriate, however construction quality control critical
• Monitoring system tailored to target critical area of the building and critical point in the construction timeline
• Constant monitoring compared to design predictions with target levels set to stop construction if required.
CASE STUDY 2
Technical Presentation Sept 2017
www.gdgeo.com
• Flood Defences
CASE STUDY 3
Technical Presentation Sept 2017
www.gdgeo.com
• Flood Wall Analysis
CASE STUDY 3
• Stability Modelling
• Seepage Analysis Deemed Critical
Technical Presentation Sept 2017
www.gdgeo.com
• Flood Defence Design
CASE STUDY 3
Technical Presentation Sept 2017
www.gdgeo.com
• Flood Risk Analysis
CASE STUDY 3
Technical Presentation Sept 2017
www.gdgeo.com
• Flood Risk Analysis
CASE STUDY 3
0.2
0.4
0.6 0.8 1
1
.2
1
.4
1.6 1.8 2 2.2 2.4 2.6
Design Flood Level
Gravel
Gravel
Silt
Peat
0.6
8202
m³/d
ays
2
.85
37 m
³/days
0
.12
612
m³/
days
Distance (m)
0 5 10 15 20 25 30 35
Ele
vatio
n (
m)
-13.5
-12.5
-11.5
-10.5
-9.5
-8.5
-7.5
-6.5
-5.5
-4.5
-3.5
-2.5
-1.5
-0.5
0.5
1.5
2.5
3.5
4.5
5.5
Technical Presentation Sept 2017
www.gdgeo.com
• Flood Risk Analysis
CASE STUDY 3
0.2
0.4
0.6 0.8 1
1
.2
1
.4
1.6 1.8 2 2.2 2.4 2.6
Design Flood Level
Gravel
Gravel
Silt
Peat
0.6
8202
m³/d
ays
2
.85
37 m
³/days
0
.12
612
m³/
days
Distance (m)
0 5 10 15 20 25 30 35
Ele
vatio
n (
m)
-13.5
-12.5
-11.5
-10.5
-9.5
-8.5
-7.5
-6.5
-5.5
-4.5
-3.5
-2.5
-1.5
-0.5
0.5
1.5
2.5
3.5
4.5
5.5
0.4
0.6
0
.8
1
1.2
1
.4
1
.6
1.8 2 2.2 2.4 2.6 2.8
Gravel
Gravel
Silt
Peat
Distance (m)
0 5 10 15 20 25 30 35
Ele
va
tio
n (
m)
-13.5
-12.5
-11.5
-10.5
-9.5
-8.5
-7.5
-6.5
-5.5
-4.5
-3.5
-2.5
-1.5
-0.5
0.5
1.5
2.5
3.5
4.5
5.5
Technical Presentation Sept 2017
www.gdgeo.com
• Flood Risk Analysis
CASE STUDY 3
Technical Presentation Sept 2017
www.gdgeo.com
• Flood Wall Analysis
CASE STUDY 3
• Conceptual hyrogeological model developed
• Model Developed for Current Condition
• Model Calibrated Against Dynamic Borehole Records
Current Ground Level
Current Low River Level 0.75 mOD
Max Expected Tide appox. 1.60 mOD
Distance (m)
0 5 10 15 20 25 30 35 40 45 50 55
Ele
va
tion
(m
)
-9.55
-8.55
-7.55
-6.55
-5.55
-4.55
-3.55
-2.55
-1.55
-0.55
0.45
1.45
2.45
3.45
4.45
5.45
Technical Presentation Sept 2017
www.gdgeo.com
• Flood Wall Analysis
CASE STUDY 3
• Calibration Process • Consider River Levels
• Tidal Variations
Technical Presentation Sept 2017
www.gdgeo.com
• Flood Wall Analysis
CASE STUDY 3
• Model Storm Events • Consider River Levels
• Tidal Variations
• Design Options
-1
0
1
2
3
4
5
0 6 12 18 24 30 36
He
ad (
m)
Time (hours)
The change in Head (m) over time (hours)
-0.2 0
0.2
0.4
0.6 1
Low River Level -0.20 mOD
Gravel
Design Flood Level 3.80 mOD
Gravel
Silt
Swale
River Wall
Flood Defence Wall
Golf Course Road Hight Tide 1.54 mOD
0
.32
51
2 m
³/d
ays
0.2
852
9 m
³/days
Distance (m)
0 5 10 15 20 25 30 35 40 45 50 55
Ele
vation (
m)
-9.55
-8.55
-7.55
-6.55
-5.55
-4.55
-3.55
-2.55
-1.55
-0.55
0.45
1.45
2.45
3.45
4.45
5.45
Technical Presentation Sept 2017
www.gdgeo.com
• Piled-Raft for High Rise Development
CASE STUDY 4
• 32 Storey High Rise Development
• Several Concentrated Column Loads with very high forces
• High wind moment on tower
• Piled-Raft deemed most appropriate solution
• Stratigraphy consisted of London Clay
Technical Presentation Sept 2017
www.gdgeo.com
• Piled-Raft for High Rise Development
CASE STUDY 4
Technical Presentation Sept 2017
www.gdgeo.com
• Piled-Raft for High Rise Development
CASE STUDY 4
• Non-linear soil model used
• Moment applied as an eccentric force on a lever arm above the raft
• Pile Design optimised iteratively
Technical Presentation Sept 2017
www.gdgeo.com
• Piled-Raft for High Rise Development
CASE STUDY 4
• Designed to a settlement criteria rather than to a capacity value
• S<35mm
Technical Presentation Sept 2017
www.gdgeo.com
• Piled-Raft for High Rise Development
CASE STUDY 4
• Examine pile utilisation & optimise design
• Piles shortened by 7m
Technical Presentation Sept 2017
www.gdgeo.com
• Piled-Raft for High Rise Development
CASE STUDY 4
• Analyse the impact of the new raft on existing contiguous wall along site boundary
• Contig wall predicted to displace by approximately 9 mm
• Existing inclinometer casings used as a cheap/efficient monitoring solution
Technical Presentation Sept 2017
www.gdgeo.com
• MARINA PILE SETTLEMENT ANALYSIS • Redevelopment of Harbour, involving residential & office buildings on
piled pier
• Focus on estimating settlement of pipe piles
CASE STUDY 5
Technical Presentation Sept 2017
www.gdgeo.com
• MARINA PILE SETTLEMENT ANALYSIS
CASE STUDY 5
Technical Presentation Sept 2017
www.gdgeo.com
• MARINA PILE SETTLEMENT ANALYSIS
CASE STUDY 5
• Using state of the art settlement models to assess foundation performance (in-house design tools)
• Excellent prediction
• Confirmed pile acceptability
Technical Presentation Sept 2017
www.gdgeo.com
• Risk Modelling on a Large Scale (Rail Network)
CASE STUDY 6
2,800Km Track
4,900 Earthworks
5,100 Bridges
900 Level Crossings
Technical Presentation Sept 2017
www.gdgeo.com
Portarlington Derailment Aug 2008
Manulla Junction Landslide Aug 2007
Wicklow Derailment Nov 2009
Rushbrooke Rock Falls March 2014
• Recent Failures
CASE STUDY 6
Technical Presentation Sept 2017
www.gdgeo.com
Waterford Rockfall Dec 2013
Kilkenny Waterford Line Landslip Dec 2013
Tullamore Soil Slips and Rock Falls 2011/2012
Cabra Slope Failures 2012
CASE STUDY 6
Technical Presentation Sept 2017
www.gdgeo.com
PROBABILISTIC MODELLING
• High Level of Uncertainty Across the Asset Characteristics
• Consider COV of input parameters depending on data source
• Develop quantifiable risk profiles
• Hasofer Lind method used to calculate the probability of failure associated with each asset and its coupled limit state
• Outputs: reliability index (β), probability of failure
CASE STUDY 6
g(X) = R-SPf
probability
of failure
0
ßs[g(x)]
E[g(x)]
E[g(x)]
s [g(x)]ß[g(x)] =
Outputs: reliability index (β), probability of failure
Technical Presentation Sept 2017
www.gdgeo.com
• Risk Modelling on a Large Scale (Rail Network)
• Possible to quantify ground risk
• 4000 Assets
• No excuses for individual sites!
CASE STUDY 6
Technical Presentation Sept 2017
www.gdgeo.com
• Karst Risk Analysis
• Importance of Desk study research
CASE STUDY 7
Technical Presentation Sept 2017
www.gdgeo.com
CASE STUDY 7
Soil Profile from Intrusive Investigation
Layer
No.
Depth below
ground level (bgl)
Soil Type Description
1 0.6 to 0.9 m Made
Ground
Grey sandy GRAVEL with cobbles
2 0.9 m to 4 m*
Dynamic Probe No.
T2 encountered
soft soil to 11.1 m
bgl.
Glacial Till The till comprises reddish brown
sandy gravelly, low plasticity CLAY.
The fines content of the soil was
between 35 and 50%.
3 Below 4 m Waulsortian
Limestone
Light Grey, massive reef
LIMESTONE. The rock is strong to
very strong, with strong evidence
of karst solution features
Technical Presentation Sept 2017
www.gdgeo.com
CASE STUDY 7
Soil Profile from Intrusive Investigation
Layer
No.
Depth below
ground level (bgl)
Soil Type Description
1 0.6 to 0.9 m Made
Ground
Grey sandy GRAVEL with cobbles
2 0.9 m to 4 m*
Dynamic Probe No.
T2 encountered
soft soil to 11.1 m
bgl.
Glacial Till The till comprises reddish brown
sandy gravelly, low plasticity CLAY.
The fines content of the soil was
between 35 and 50%.
3 Below 4 m Waulsortian
Limestone
Light Grey, massive reef
LIMESTONE. The rock is strong to
very strong, with strong evidence
of karst solution features
Technical Presentation Sept 2017
www.gdgeo.com
CASE STUDY 7
• Geophysics used to map risk
Technical Presentation Sept 2017
www.gdgeo.com
CASE STUDY 7
• Pragmatic Construction Regime Proposed
Technical Presentation Sept 2017
www.gdgeo.com
SUMMARY
o Advanced design tools have a place in the right projects
o FEM can allow more efficient design, save money and decrease risk
o Calibration is critical
o Recommend numerical modelling coupled with observational approach
o Monitoring provides the confidence to allow construction to proceed on time and in budget
Technical Presentation Sept 2017
www.gdgeo.com
• QUESTIONS ???
Contact:
Paul Doherty
Conclusions