Upload
the-state-newspaper
View
215
Download
0
Embed Size (px)
Citation preview
7/29/2019 USC building and grounds projects, Feb. 28, 2013
1/44
Buildings and Grounds Committee
February 28, 2013
Buildings & GroundsFebruary 28, 2013
7/29/2019 USC building and grounds projects, Feb. 28, 2013
2/44
Meeting AgendaOpen Session
Call to OrderExecutive Session
Contractual MattersI. Gift Naming Opportunities CommitteeII. Other Matters
Open Session
A. Project ApprovalsB. 2013 CPIP ApprovalC. Project Budget AdjustmentsD. Administrative NotificationsE. Five Year Plan 2013
F. Planning ItemsGift Naming OpportunitiesAdjournment
Buildings & GroundsFebruary 28, 2013
7/29/2019 USC building and grounds projects, Feb. 28, 2013
3/44
A. Project Approvals
New School of Law Building Hamilton College Renovation
Athletics Projects Other Projects
Buildings & GroundsFebruary 28, 2013
7/29/2019 USC building and grounds projects, Feb. 28, 2013
4/44
New School of Law Building
This project is to construct a new facility for the School of Law. The projectwas previously approved for design and acquisition of property with abudget of $10 million funded with Capital Improvement Bonds. The new
facility will contain 187,500 gross square feet and will accommodate aprogram with an enrollment of 660 students. It will be located on propertyowned by the University in the block bordered by Senate, Bull, Gervais, andPickens Streets. Construction is scheduled to begin in Summer 2014 withprojected completion in Summer 2016.
Subject:
Buildings & GroundsFebruary 28, 2013
THE UNIVERSITY OF
SOUTH CAROLINA
SCHOOL OF LAW
7/29/2019 USC building and grounds projects, Feb. 28, 2013
5/44
New School of Law Building
Approval is requested to fund Phase II design and construction fora total project budget of $80 million funded with up to $48.1 millionin State Institution Bonds, $10 million in State Capital ImprovementBonds, $10 million in State Capital Reserve Funds, and a minimumof $11.9 million in Private Funds.
CommitteeAction
Requested:
Buildings & GroundsFebruary 28, 2013
7/29/2019 USC building and grounds projects, Feb. 28, 2013
6/44
Hamilton College Renovation
Subject:
Buildings & GroundsFebruary 28, 2013
The project was previously approved for design with a budget of $300,000funded with Capital Improvement Bonds. This project will renovate the wingof the building parallel with Pendleton Street and add an additional floor inthe gymnasium. Renovations will include a complete mechanical, plumbing,and electrical infrastructure. This area will consolidate the College of SocialWork. Mechanical, electrical and finish upgrades are proposed for the wing
parallel with Pickens Street. This wing will be predominantly used by thePsychology Department. The total project area is approximately 58,000square feet. Windows will be refurbished and an extensive amount ofdeferred maintenance is addressed with this project. Construction isscheduled to begin in May 2014 with projected completion in August 2015.
7/29/2019 USC building and grounds projects, Feb. 28, 2013
7/44
Approval is requested to fund Phase II design and construction for a total
project budget of $15.0 million funded with $14.7 million in InstitutionalCapital Project Funds, and $300,000 in Capital Improvement Bonds. In theevent that State Capital Reserve Funds are received, the funding will bechanged to reduce the Institutional Capital Project Funds by the amount ofState funds received.
Hamilton College Renovation
Committee
ActionRequested:
Basement Level
First Level
New Second Level
Buildings & GroundsFebruary 28, 2013
7/29/2019 USC building and grounds projects, Feb. 28, 2013
8/44
Buildings & GroundsFebruary 28, 2013
A. Project Approvals
Athletics Projects
7/29/2019 USC building and grounds projects, Feb. 28, 2013
9/44
Outdoor Football Practice Fields Construction
Committee ActionRequested:
Approval is requested to fund Phase II design and construction fora total project budget of $3 million funded with Athletic OperatingFunds.
Buildings & GroundsFebruary 28, 2013
7/29/2019 USC building and grounds projects, Feb. 28, 2013
10/44
Approval is requested to fund Phase II design and construction for
a total project budget of $14.55 million funded with $12.1 million inAthletic Revenue Bonds and $2.45 million in Athletic OperatingFunds.
Indoor Practice Facility Construction
Buildings & GroundsFebruary 28, 2013
Committee Action
Requested:
7/29/2019 USC building and grounds projects, Feb. 28, 2013
11/44
Athletic Village Sand Volleyball Court Construction
Committee Action
Requested:
Approval is requested to establish and fully fund this project with a
budget not to exceed $995,000 to be funded with AthleticOperating Funds.
Buildings & GroundsFebruary 28, 2013
7/29/2019 USC building and grounds projects, Feb. 28, 2013
12/44
Committee ActionRequested:
Williams Brice Stadium Plaza Site Work
Buildings & GroundsFebruary 28, 2013
Approval is requested to establish this project for Phase I Designwith a budget of $210,000 funded with Private Funds.
7/29/2019 USC building and grounds projects, Feb. 28, 2013
13/44
Other Williams-Brice Stadium Athletic Projects
Williams-Brice Stadium Field Site WorkApproval is requested to establish and fully fund this
project with a budget of $995,000 to be funded withAthletic Operating Funds.
Williams-Brice Stadium The Zone HVAC ReplacementApproval is requested to establish and fully fund this
project with a budget of $550,000 to be funded withAthletic Operating Funds.
Williams-Brice Stadium Waterproofing IIIApproval is requested to establish and fully fund thisproject with a budget of $500,000 to be funded with
Athletic Operating Funds.
Buildings & GroundsFebruary 28, 2013
CommitteeApproval
Requested:
7/29/2019 USC building and grounds projects, Feb. 28, 2013
14/44
Committee
ActionRequested:
Athletic Village Track and Field Upgrades
Approval is requested to establish this project for Phase I Design
with a budget of $150,000 funded with Athletic Operating Funds.
Buildings & GroundsFebruary 28, 2013
7/29/2019 USC building and grounds projects, Feb. 28, 2013
15/44
Approval is requested to establish this project for Phase I Design
with a budget of $15,000 funded with Athletic Operating Funds.
Tennis Complex Addition
Committee Action
Requested:
Buildings & Grounds
February 28, 2013
7/29/2019 USC building and grounds projects, Feb. 28, 2013
16/44
Soccer Building Construction
CommitteeApproval
Requested:
Approval is requested to establish this project for Phase I Designwith a budget of $37,500 funded with Athletic Operating Funds.
Buildings & Grounds
February 28, 2013
7/29/2019 USC building and grounds projects, Feb. 28, 2013
17/44
Committee ActionRequested:
Approval is requested to establish this project for Phase I Designwith a budget of $75,000 funded with Athletic Revenue Bonds.Athletic operating funds will be used as interim funding untilRevenue Bonds are issued.
Field House Conversion
Buildings & Grounds
February 28, 2013
7/29/2019 USC building and grounds projects, Feb. 28, 2013
18/44
Buildings & Grounds
February 28, 2013
Project Approvals
Other Projects
7/29/2019 USC building and grounds projects, Feb. 28, 2013
19/44
Approval is requested to fund Phase II design and construction fora total project budget of $64.5 million funded with $49.5 millionfrom the Department of Justice and $15 million in InstitutionalCapital Project Funds.
Close-Hipp Building Renovation
Committee ActionRequested:
Buildings & Grounds
February 28, 2013
7/29/2019 USC building and grounds projects, Feb. 28, 2013
20/44
War Memorial Renovation
Committee ActionRequested:
Approval is requested to establish this project for Phase I Designwith a budget of $45,000 funded with Institutional Capital ProjectFunds (ICPF).
Buildings & Grounds
February 28, 2013
7/29/2019 USC building and grounds projects, Feb. 28, 2013
21/44
Other Projects
Approval is requested for the following energy projects with the budgets listed:
East Energy Cooling Tower No. 2 CellAddition$292,000
West Energy Switchgear and Transformer Replacements.$350,000
Columbia Campus Control Valve Installation$670,000
Energy Plant Asbestos Abatement (Phase I).$400,000
West Energy BoilerReplacement$950,000
Utility Line Replacement, Davis College to Currell College........$986,000
West Energy No. 3 Chiller Replacement.$995,000
All projects are to be funded with Institutional Funds.
Buildings & Grounds
February 28, 2013
CommitteeAction
equested:
7/29/2019 USC building and grounds projects, Feb. 28, 2013
22/44
Greek Village Site ImprovementsApproval is requested to establish and fully fund this project with abudget of $400,000 to be funded with Institutional Funds from Greek
Life Operations.
Approval is requested to establish and fully fund the classroomenhancement projects with the budgets listed:
2014 LeConte Classroom Enhancements
The budget for the project is $400,000 and will be funded with$300,000 in ICPF and $100,000 in Institutional Funds.
2014 Swearingen Classroom EnhancementsThe budget for the project is $330,000 and will be funded with$255,000 in ICPF and $75,000 in Institutional Funds.
2014 Booker T. Washington Auditorium/Classroom
EnhancementsThe budget for the project is $460,000 and will be funded with$240,000 in ICPF, $100,000 in Institutional Funds, and $120,000 inRenovation Reserve Funds.
Buildings & Grounds
February 28, 2013
Other Projects (continued)
CommitteeAction
equested:
7/29/2019 USC building and grounds projects, Feb. 28, 2013
23/44
McKissick Fire Alarm UpgradeApproval is requested to establish and fully fund this project with a
budget of $490,000 to be funded with Institutional Capital ProjectFunds (ICPF).
Strom Thurmond Wellness & Fitness Center Outdoor Pool Repair
Approval is requested to establish and fully fund this project with a
budget of $575,000 to be funded with Institutional Funds from
Campus Recreation Maintenance Reserve Funds.
USC Upstate North Campus Boulevard Repairs/ImprovementApproval is requested to establish and fully fund this project with a
budget of $400,000 to be funded with USC Upstate Parking Revenue.
Capstone 17th Floor RenovationsApproval is requested to establish and fully fund this project with a
budget of $600,000 to be funded with Auxiliary Funds.
Buildings & Grounds
February 28, 2013
Other Projects (continued)
CommitteeAction
equested:
7/29/2019 USC building and grounds projects, Feb. 28, 2013
24/44
2013 CPIP Approval
Buildings & Grounds
February 28, 2013
7/29/2019 USC building and grounds projects, Feb. 28, 2013
25/44
2013 CPIP
Buildings & Grounds
February 28, 2013
Project Budget Funding Approval Phase
Law Center Renovation $25,000,000 $20 million State Institution Bonds; $5 millionInstitutional Funds
Phase I
1244 Blossom Street (UTS) Renovation $10,000,000 Institutional Capital Project Funds Phase I
War Memorial Renovation $3,000,000 Institutional Capital Project Funds Phase II
Library Annex Addition $5,000,000 Institutional Capital Project Funds Phase IHorry-Guignard House Renovation $1,500,000 Institutional Capital Project Funds Phase I
Taylor House Renovation $4,000,000 Institutional Capital Project Funds Phase ICentral Steam/Condensate Line
Repair/Replacement
$2,350,000 Institutional Capital Project Funds Phase I
Student Health Center Construction $27,000,000 $13 million State Institution Bonds; $14 millionHealth Center Reserve Fund
Phase II
Bates West Comprehensive Renovation $29,300,000 Housing Revenue Bonds Phase I
Athletic Village Track and Field ComplexUpgrades
$10,000,000 $9.0 million Athletic Revenue Bonds, $1.0 millionAthletic Operating Funds
Phase II
Soccer Building Construction $2,500,000 $2.0 million Athletic Revenue Bonds, $500,000Athletic Operating Funds
Phase II
Athletic Village Tennis ComplexAddition
$1,000,000 Athletic Operating Funds Phase II
Williams Brice Stadium Plaza Site Work $14,000,000 $11.8 million Athletic Revenue Bonds, $2.2 millionPrivate Funds
Phase II
Field House Conversion $5,000,000 Athletic Revenue Bonds Phase II
Farmers Market West End Site Work $3,000,000 $2 million Athletic Operating Funds; $1 millionPrivate Funds
Phase I
No projects submitted for senior and regional campuses.
7/29/2019 USC building and grounds projects, Feb. 28, 2013
26/44
Project Budget Adjustments
Buildings & Grounds
February 28, 2013
P j t B d t Adj t t
7/29/2019 USC building and grounds projects, Feb. 28, 2013
27/44
Project Budget Adjustments
Committee ActionRequested:
Approval is requested to increase the budget for the School ofMedicine to address maintenance issues in Building #1 on the V. A.campus including renovations to the fourth floor to renew interior
finishes and repair/replace mechanical, electrical, and plumbingsystems by $301,672.39 funded with School of MedicineInstitutional Funds, State Supplemental Funds, and State CapitalReserve Funds resulting in a total project budget of $4,989,405.39funded with $4,687,733 SC Education Lottery Funds and $300,000in School of Medicine Institutional Funds, $1,664.28 in StateSupplemental Funds, and $8.11 in State Capital Reserve Funds.
Buildings & Grounds
February 28, 2013
7/29/2019 USC building and grounds projects, Feb. 28, 2013
28/44
Administrative Notifications
Buildings & Grounds
February 28, 2013
Ad i i t ti P j t I ( )
7/29/2019 USC building and grounds projects, Feb. 28, 2013
29/44
Administrative Project Increase(s)
In accordance with the policy approved by the Board of Trustees,administrative approval was obtained to increase the budget for thefollowing project(s):
Baruch Marine Field Laboratory Roof/Mechanical ReplacementThe project budget for the Baruch Marine Field LaboratoryRoof/Mechanical Replacement was increased by $49,500. Theproject to replace the roof was bid with two components. The basebid to replace the membrane roof systems and the alternate toreplace the asphalt shingle system exceeded the constructionbudget. It is important that both components of the roofing systembe replaced at the same time to ensure a water tight system. Theincrease was required to provide adequate funding to award thetotal construction contract and to provide a construction
contingency.The increase was funded with Institutional funds from the Collegeof Arts and Sciences and resulted in a total budget of $544,500funded entirely with Institutional Funds from the College of Arts andSciences.
Buildings & Grounds
February 28, 2013
7/29/2019 USC building and grounds projects, Feb. 28, 2013
30/44
Five Year Plan 2013 Update
Buildings & Grounds
February 28, 2013
Fi Y C it l I t Pl
7/29/2019 USC building and grounds projects, Feb. 28, 2013
31/44
Five Year Capital Improvement Plan
Buildings & Grounds
February 28, 2013
7/29/2019 USC building and grounds projects, Feb. 28, 2013
32/44
Planning Items
Public Private Partnership
Land Acquisitions Greene Street Closure (Pickens to Bull Streets) Greene Street (Innovista)
Buildings & Grounds
February 28, 2013
W t C Di t i t P bli P i t P t hi
7/29/2019 USC building and grounds projects, Feb. 28, 2013
33/44
West Campus District Public Private Partnership
Phasing Plan
DMSB
Buildings & Grounds
February 28, 2013
7/29/2019 USC building and grounds projects, Feb. 28, 2013
34/44
Land Acquisitions Update
SCANA
Columbia Venture
The Wedge
Buildings & Grounds
February 28, 2013
Greene Street Closure at Pickens Street and Bull Street
7/29/2019 USC building and grounds projects, Feb. 28, 2013
35/44
Greene Street Closure at Pickens Street and Bull Street
Corner of Greene & Bull Street
Corner of Greene & Pickens Street
Buildings & Grounds
February 28, 2013
7/29/2019 USC building and grounds projects, Feb. 28, 2013
36/44
PROJECT ZONE
Buildings & Grounds
February 28, 2013
PETIGRU
Signage:
7/29/2019 USC building and grounds projects, Feb. 28, 2013
37/44
Existing Gate
Womens Quad Renovation
Construction Laydown Plan
WOMENS QUAD
PETIGRU
Greene Street
BullStreet
PickensStreet
CALLCOTT
RUSSELL HOUSE
PATTERSON
ACCESS/DELIVERY ROUTE
TRACTOR
TRAILERPANEL TRUCK
PEDESTRIAN ROUTECAR DETOUR
( when gates are open)
WOMENS
QUAD SECURE
LAYDOWN
5/132/14
Temporary Gate
SECURE LAYDOWN AREA
Temporary Gate
No Right Turn
No Thru Traffic
Deliveries Only
Signage:
No Thru Traffic
Deliveries Only
Schedule for May 2013 Feb 2014
PETIGRU
Signage:
7/29/2019 USC building and grounds projects, Feb. 28, 2013
38/44
Existing Gate
Womens Quad Renovation
Construction Laydown Plan
WOMENS QUAD
PETIGRU
Greene Street
BullStreet
PickensStreet
CALLCOTT
RUSSELL HOUSE
PATTERSON
PEDESTRIAN ROUTECAR DETOUR
( when gates are open) ACCESS/DELIVERY ROUTE
TRACTOR
TRAILERPANEL TRUCK
New Gate
CONSTRUCTIONZONE
2/14 to 4/14
CONSTRUCTIONZONE
WOMENS
QUAD SECURE
LAYDOWN
5/132/14
Temporary Gate
SECURE LAYDOWN AREA
Temporary Gate
No Right Turn
No Thru Traffic
Deliveries Only
Signage:
No Thru Traffic
Deliveries Only
Schedule for Feb 2014 April 2014
PETIGRU Signage:i h
7/29/2019 USC building and grounds projects, Feb. 28, 2013
39/44
Existing GateNew Gate
RUSSELL HOUSEWOMENS QUAD
BullStreet
PickensStreet
CALLCOTT
CONSTRUCTIONZONE
4/14 to7/31/2014
CONSTRUCTION ZONE
Schedule for April 2014 July 31, 2014
No Public Access on Greene St. 4/1/2013 4/6/2013
Greene Street
No Right Turn
No Thru Traffic
Deliveries Only
Signage:
No Thru Traffic
Deliveries Only
Limited Tractor Trailer Access
PanelTruckAccess
SECURELAYDOWNAREA
Greene Street Pedestrian Safety ProjectConstruction Area
Gate
WOMENS
QUAD SECURE
LAYDOWN
4/14 to
7/31/14
NEW ROUNDABOUT
ROUNDABOUT
4/14 to
7/31/2014
PEDESTRIAN ROUTEPEDESTRIAN ROUTE
LimitedTr
ailerAccess
Greene Street Closure at Bull Street
7/29/2019 USC building and grounds projects, Feb. 28, 2013
40/44
Greene Street Closure at Bull Street
Greene Street SouthBull StreetProject Scope:
16
9
30
New Gate
BusStop
Car
BullStreet
Greene Street
New Gate
No Street ParkingBus Stop
Buildings & Grounds
February 28, 2013
Greene Street Closure at Pickens Street
7/29/2019 USC building and grounds projects, Feb. 28, 2013
41/44
Project Scope:
Greene Street East
Pickens Street
PickensStreet
Greene Street
New Gate
Bike Lane
Bike Lane
New Gate
Buildings & Grounds
February 28, 2013
Greene Street Closure at Pickens Street
Greene Street at Innovista
7/29/2019 USC building and grounds projects, Feb. 28, 2013
42/44
Greene Street at Innovista
Project Scope: We are intent upon leveraging the penny tax revenue to foster theimplementation of the Sasaki Innovista Master Plan. This work will
construct a bridge over the railroad to extend Greene Street andultimately connect with the proposed Waterfront Park. We alsoseek the completion of Foundation Square and to further the visionfor Greene Street.
Buildings & Grounds
February 28, 2013
7/29/2019 USC building and grounds projects, Feb. 28, 2013
43/44
Gift Naming Opportunities
Buildings & Grounds
February 28, 2013
7/29/2019 USC building and grounds projects, Feb. 28, 2013
44/44
Adjournment
Buildings & Grounds