Upload
others
View
2
Download
0
Embed Size (px)
Citation preview
U.S. DEPARTMENT OF
ENERGY Nuclear Energy
National Aeronautics and Space Administration
ADVANCED STIRLING RADIOISOTOPE GENERATOR INTEGRATED FEDERAL PROJECT
Advanced Stirling Radioisotope Generator: Teamwork and System Reliability
Chris Steffen, Jr.
1-May-2013
Government & Contractor Partnership
Advanced Stirling Radioisotope Generator (ASRG)
AC Power DC Power from ASCs Connector ~--~t.~~ 7li::;;.,~,..,......_~
to SV
ASC Controller
Unit (ACU)
Fins Advanced Stirling
Convertor (ASC) (2)
3
Cold-Side Adapter Flange
(CSAF) (2)
Shunt Dissipater
Unit (SOU)
GPHS (2)
ASRG Project Key Deliverables
Qualification Test Unit
Fueled & Tested 2016
Flight #1 Unit
shipped for Fueling
& Testing 2016
Flight #2 Unit
shipped for Fueling
& Testing 2017
ASRG Mass Metric- March 2013
45
40 RPS PO Reserve
--;:o 35 .::t:. -
--,. - I
Jan-08 Jan-09 Jan-10 Jan-11 Ja n-12 Jan-13 Jan-14 Jan-15
5
150 -
145
-! 140
\.,.
<1> ~ 0
Q,.
E 135 Q) ... ~
> V'l
G) ... ~ 130 a. E 0 u
~ 125 V) <{
120
115
ASRG Power Metric- March 2013
CBE Power
••••••••••• Output Power Req (Original) = 140 W • •••• ••••••••••••• •
•••••• •
New Monte Carlo Estimate: Cumulative Probab ility of Achieving 130.0 W = 99%
CBE Power = 140.8 W
Cont ingency
Predrcted Power (Worst Case) .... ••••••••
Worst Case Power loss I ~'Total Power Margin = 3.99%
Predicted Power(RSS) = 10.00~ ..~~T~T~T~~~~=~l735~.~47\~~~~-~J' ..
LM Margin = 4.15% •••••• Output Power Req (Updated) = 130 W : ... ..,.*-
,,.
RPS PO Reserve = 1. 56% t '~ RPS PO Power Commitment = 128 W
Jan-os Jan-09 Jan -10 Jan-11 Jan-13 Jan -14 Jan-15
6
ASRG Reliability Metric- March 2013
Heate r Head
Spring
Transit ion & Feedt hru
ASC Common
Cause
Gas Bearings
ASRG System
Probability of
Failure (POF)
3.1%
Other POF
0.06%
ACU Common
Cards#l & #2
ASRG System Probability of Success
(Delivered power for 17 years) 96.9%
Card #1 (Primary)
5.4%
Output current sense & voltage
.monitor
control monitor
card lt3 (Alternate) PDF
5.4%
Questions about this graphic, Chr is Steffen (stelfen@nasa gav)
• Reliability challenge: heater head casting
• Thin-walled metallic Heater Head component (outlined in yellow)
• Ni-based super alloy Heater Head machined from casting
• Casting is known for potential oxide inclusions (ceramic flakes)
• Micro-focused Computed Tomography (CT) key to "seeing" these flaws
• Component yield was developing as an issue; parts could meet criteria
• NASA Engineering Safety Center: "criteria needs test-verified basis"
Potential orientations for oxide inclusion
Hot End (850° C)
Stirling Engine
Cold End (90° C)
Linear Alternator
ArJV;:)fJl~ArJ Stirlinn ConvArtor
(/')
u 0.. c.o rl
(/')
u 0.. 0 N
Plan: Heater Head development 1st znd
Pair Pair
ASC-Engineering Units _____ _ Need: 50% yield
Jrd
Pair
• Qual Pair MIP
• • znd Jrd
Pair Pair MIP MIP
4th
Pair
• 4th
Pair MIP
Apr-11 May-11 Jun-11 Jul-1 1 Aug-11 Sep-1 1 Oct-11 Nov-11 Dec-11 Jan-12 Feb-12 Mar-12 Apr-1 2 Moy-12 Jun-12 Jul-12 Aug-12 Sep-12 Oct-12 Nov-12 Dec-1:
Mar-11 ASC-E3 Deliveries
10 ASC-Q S-F Deliveries
• Reality: Heater Head development
ASC- Engineerin 44% yield
1st 2nd
Pair Pair Jrd
Pair
Mitigation: 5 more @ 6 months
... Qual Pair MIP
ASC-E3s: Need 4 more
Spares: Have 6 more
ASC-Fs: Need 7 more
. I
... ... 2nd 3rd
Pair Pair MIP MIP
4fh
Pair
... 4th
Pair MIP
Apr-11 May-11 Jun-11 Jul-11 Aug-11 Sep-11 Oct-11 Nov-1 1 Dec-11 Jan-12 Feb-12 Mar-12 Apr-12 May-12 Jun-12 Jul-12 Aug-12 Sep-12 Ocl-12 Nov-12 Dec-1:
Mar- 11
. 11 ASC-E3 Deliveries
ASC- Q 6- F Deliveries
Reliability challenge: heater head casting
Technical Risk: Oxide Inclusions present a risk to meeting fatigue life requirement (68 years)
Schedule Consequence: Insufficient component yield threatens critical path schedule with 3 months
Approach: Assemble investigation team and resolve in 3 months
1. Verification: Material coupon testing -+ batch specific matl props
2. Verification: Fracture mechanics & selection criteria -+ test-verified properties
3. Validation: Component stress testing -+ design specific reliability data
Goal: Resulting in test verified, design specific acceptance criteria for 4x design life on fatigue, validated with component testing
12
Skills and Assets Required
FEM Analysis
Rapid design & manufacturing
ally
Micro-focused CT scanning
Material Properties testing & Fracture Mechanics analysis
•
Structural Dynamics Testing & cumulative damage analysis
SEM Imagery
• Key Results
1. .Comprehensive approach: Sixteen* separate fatigue crack growth specimen tests Design trade study on "critical-flaw-size vs wall thickness" Refined (tighter!) acceptance criteria, supported by test-verified material.s properties
Eight qualification level vibe stress tests on five different components
2. NESC concurrence: results conclusions
residual risk for the ASRG project
3. · Timely closure: preserved system reliability and margin for fatigue life Preserved project schedule despite tighter acceptance criteria
Only possible with a badge-less team working pulling together
15
Thanks to the investigation team
• Greg McNelis- LM (co-lead)
• Dennis Petrakis- LM
• Glen Davis- Sun power
• Kyle Wilson - Sun power
• Lou Qual Is- ORNL
• Louis Ghosn - NASA GRC
• Wayne Wong - NASA GRC
• Kate McGinnis- NASA GRC
• Jeff Schreiber- Consultant, formerly GRC
• Brad Kirkwood, INL
• Jack Chan - LM
• Scott Benson, GRC -- Project Management Rep.
16
• Randy Bowman - GRC
• Ramesh Kalluri - GRC
• Dave Krause - GRC
• Jack Telesman -GRC
• Chuang Ha - LM
• Ron McNally - LM
• Gary Wood - Sun power
• Aaron Thomas- Sun power
• Kim Otten - GRC
• Sal Oriti - GRC
• Zach Williams - GRC
Consultants (NESC):
Dawn Emerson, Bob Piascik, Bill Prosser, Raju lvatury, Dave Dawicke