27
1 Fulvio TESSAROTTO Update on the thin RICH beam pipe project - tests on prototypes - pipe production by Lamina - gluing exercises - time schedule - conclusions COMPASS TB meeting, CERN, 10/11/2011 Fulvio Tessarotto

Update on the thin RICH beam pipe project

  • Upload
    sunila

  • View
    65

  • Download
    0

Embed Size (px)

DESCRIPTION

Update on the thin RICH beam pipe project. Fulvio Tessarotto. - tests on prototypes - pipe production by Lamina - gluing exercises - time schedule - conclusions. Activity on prototypes. We received from Lamina 4 “non aluminized” pipe pieces: - PowerPoint PPT Presentation

Citation preview

Page 1: Update on the thin RICH beam pipe project

1Fulvio TESSAROTTO

Update on thethin RICH beam pipe project

- tests on prototypes

- pipe production by Lamina

- gluing exercises

- time schedule - conclusions

COMPASS TB meeting, CERN, 10/11/2011

Fulvio Tessarotto

Page 2: Update on the thin RICH beam pipe project

2Fulvio TESSAROTTO COMPASS TB meeting, CERN, 10/11/2011

Activity on prototypes- We received from Lamina 4 “non aluminized” pipe pieces:

- diam. = 100 mm, L = 1.3 m, tot. thickness ~ 180 μm- 4 layers of 36 μm thick Mylar wound and glued with S100 bonding agent

- One was cut to measure the material properties and perform gluing tests- inner diam. = 100.1 +- 0.1, good compatibility with Araldite 2011, …

- The second one has been equipped with aluminum end-cups to perform:- pressure tests (cylinder only for overpressure > 6 mbar)- deformation tests- He leak tests

- Progress was possible because we solved problems of:- location (we equipped a room dedicated to these tests in Trieste)- technical manpower (two technicians are now helping on this project) - budget (INFN accepted to support the new RICH pipe)

Page 3: Update on the thin RICH beam pipe project

3Fulvio TESSAROTTO COMPASS TB meeting, CERN, 10/11/2011

The prototypes without Al coating

Page 4: Update on the thin RICH beam pipe project

4Fulvio TESSAROTTO COMPASS TB meeting, CERN, 10/11/2011

The Al flanges for this test

Page 5: Update on the thin RICH beam pipe project

5Fulvio TESSAROTTO COMPASS TB meeting, CERN, 10/11/2011

The gluing for this test

Page 6: Update on the thin RICH beam pipe project

6Fulvio TESSAROTTO COMPASS TB meeting, CERN, 10/11/2011

The result

Page 7: Update on the thin RICH beam pipe project

7Fulvio TESSAROTTO COMPASS TB meeting, CERN, 10/11/2011

The first He leak test

Page 8: Update on the thin RICH beam pipe project

8Fulvio TESSAROTTO COMPASS TB meeting, CERN, 10/11/2011

Temperature and pressure recording

Page 9: Update on the thin RICH beam pipe project

9Fulvio TESSAROTTO COMPASS TB meeting, CERN, 10/11/2011

Page 10: Update on the thin RICH beam pipe project

10Fulvio TESSAROTTO COMPASS TB meeting, CERN, 10/11/2011

Simple He leak measurement- Volume = 10 l, fluxed with He, overpressure = 10 mbar, input closed. - Internal overpressure monitored for several hours:- External pressure, tempereature, humidity recorded too.- The overpressure evolves with T and P- Once corrected for temperature and pressure the observed leak

is ~ 0.3 mbar/h or less. This corresponds to ~ 3 ml/h leak

PRELIMINARY CONCLUSION: MYLAR AND GLUE ARE VALIDATED

A stainless steel pipe with 240 mm radius and 2 m length, withflanges and gas connections has been bought and will host thehigher accuracy He leak measurements and the other tests.

Page 11: Update on the thin RICH beam pipe project

11Fulvio TESSAROTTO COMPASS TB meeting, CERN, 03/02/2011

at 25 ºC and for 1 bar pressure difference,a 25 μm thick Mylar foilwith a surface of 645 cm2

leaks “typically” 150 cc/day 1 m2 will leak ~0.1 l/h

From the datasheet of the DuPont Teijin Mylar polyester film

(the measurements have been performed using a 25 μm thick Mylar foil)

Our validation figure is 10 ml/h

Which includes a safety factor of 4 with respectTo the maximum allowed leak rate of 1l/day

For the prototype which has a surface of 0.4 m2 and no coating we would

expect a leak of ~ 40 ml/h divided by a “thickness factor”

Page 12: Update on the thin RICH beam pipe project

12Fulvio TESSAROTTO COMPASS TB meeting, CERN, 10/11/2011

For water vapor, the increase from 25 μmto 144 μm of the mylar thickness corresponds to a decrease of a factor ~8 in the transmission rate

If the factor is the same for He, we would expect ~ 5 ml/h leak.

We see ~3 ml/h

expected leak: tickness factor

Page 13: Update on the thin RICH beam pipe project

13Fulvio TESSAROTTO COMPASS TB meeting, CERN, 10/11/2011

End-caps and gluing studies

Page 14: Update on the thin RICH beam pipe project

14Fulvio TESSAROTTO COMPASS TB meeting, CERN, 10/11/2011

microflange

Page 15: Update on the thin RICH beam pipe project

15Fulvio TESSAROTTO COMPASS TB meeting, CERN, 10/11/2011

microflange

Page 16: Update on the thin RICH beam pipe project

16Fulvio TESSAROTTO

production of the pipes by Lamina

The base material, coated by Sheldahl, has been checked by Lamina:- measured thickness = 27 μm,

- surface resistivity = 0.5 Ω / □(The amount of material is sufficient for 10 pipes)4 pipes are being produced this week:100 mm diameter, 1800 mm long pipes

- 4 layers of Mylar, 25 μm thick, with 200 nm Al coating- spiral winding and gluing via 5 μm thick cross-linking polyester- 2 pieces will have an extra layer of Mylar, 36 μm thick (no Al coating)

(total thickness ~170 μm)- 2 pieces without the 36 μm extra layer

(total thickness ~130 μm Mylar)

Page 17: Update on the thin RICH beam pipe project

17Fulvio TESSAROTTO COMPASS TB meeting, CERN, 10/11/2011

The base material is the same as:

Page 18: Update on the thin RICH beam pipe project

18Fulvio TESSAROTTO COMPASS TB meeting, CERN, 10/11/2011

Technical data

Page 19: Update on the thin RICH beam pipe project

19Fulvio TESSAROTTO COMPASS TB meeting, CERN, 10/11/2011

Engineering drawings from

Draw Code MIN MAX

I.D 99,7 100,30

W.T 0,100 0,130

O.L 1800,0 1810,0

Confidential Property of:

Lamina Dielectrics Ltd, Daux Rd, Billingshurst, RH14 9SJ

Tel: +44(0) 1403 783131Fax: +44(0) 1402 782237

Email: [email protected]     CUSTOMER: INFNPROJECT:  Drawn by: PMH 9.11.2011Approved by: DGMaterial:

Polyester non shrink film thickness 0.025 mm coated with 2,000 Angstroms of Al

  

All dimensions in mm:  

Tolerances  

Linear: Angular:  

X +/- 0.5mm +/- 0.5 0  

X.X +/- 0.1mm  

X.XX +/- 0.05mm  

Unless otherwise stated on drawing  

DEBURR AND REMOVE ALL SHARP EDGES UNLESS STATED OTHERWISE

Notes:      Bond agent S100. 4 Layers of film wound at half pitch all Aluminium surfaces to point to the inner bore of the tube

TITLE:

100 mm internal diameter detector Drawing No.: 51.962.01

Issue: 1Date: 3.10.2011

Page 20: Update on the thin RICH beam pipe project

20Fulvio TESSAROTTO COMPASS TB meeting, CERN, 10/11/2011

Pictures of the pipe:

Page 21: Update on the thin RICH beam pipe project

21Fulvio TESSAROTTO COMPASS TB meeting, CERN, 10/11/2011

Pictures of the pipe:

Page 22: Update on the thin RICH beam pipe project

22Fulvio TESSAROTTO COMPASS TB meeting, CERN, 10/11/2011

Pictures of the pipe:

Page 23: Update on the thin RICH beam pipe project

23Fulvio TESSAROTTO COMPASS TB meeting, CERN, 10/11/2011

Summary of default choices:

Issue default choice

Removal of presently used pipe Cutting and extracting it

Material for the thin pipe 4 layer aluminized Mylar, < 0.8 ‰ X

Geometry 2 pipes 100 mm diam, 1600 mm long

Gas He, flowing at few l/h, 20 mbar overpr.

End caps PET or microflange: still to be defined

Fixation system Rings + wires: still to be defined

Page 24: Update on the thin RICH beam pipe project

24Fulvio TESSAROTTO COMPASS TB meeting, CERN, 10/11/2011

Time schedule

Pipe prototype production and tests November

RICH beam pipe production: December

Validation tests: January

Installation: February

Contingency in case of problems: March

RICH operation tests with new pipe Aprile

Page 25: Update on the thin RICH beam pipe project

25Fulvio TESSAROTTO COMPASS TB meeting, CERN, 10/11/2011

Conclusions:The thin RICH pipe project is progressing, and problems about procurement,logistics, budget and manpower are being solved.

The uncoated prototype allowed to test stiffness, gluing, He tightness.

Technical solutions are being tested for end-caps and fixation system.

Real RICH pipe prototypes are being produced.

They will be tested in the incoming weeks.

The present time schedule is compatible with installation in Feb. - March 2012

Page 26: Update on the thin RICH beam pipe project

26Fulvio TESSAROTTO COMPASS TB meeting, CERN, 05/09/2011

Material budgetactual pipe material budget: (0.15 mm / 17.6 mm) 8.523 ‰ X0

goal for the material budget of the new pipe: 10% actual = 0.852 ‰ X0

4 layers of 25 μm thick Mylar : (0.1 mm / 287 mm) 0.348 ‰ X0

4 layers of 200 nm thick Al coating: (0.8 μm / 89 mm) 0.009 ‰ X0

1 layer of 36 μm thick Mylar: (36 μm / 287 mm) 0.125 ‰ X0

4 layers of 5 μm thick Mylar glue: (20 μm / 287 mm) 0.070 ‰ X0

-----------------------------------------------------------------------------------------------------------estimated total material budget for orthogonal crossing: 0.552 ‰ X0

(with respect to the goal we have a margin of 50% with the present design)

The contribution from end caps, fixation rings, gas connections will be relevant

For a 5 mrad particle (thickness * 200) 0.110 X0 from the pipe,

5 x 2 mm thick nylon (10 mm / 367 mm) = 0.027 X0 from the support rings

Page 27: Update on the thin RICH beam pipe project

27Fulvio TESSAROTTO COMPASS TB meeting, CERN, 05/09/2011

We needAccurate description of the mechanical properties of the pipe

Estimate of the mechanical stresses applied to the RICH pipe

Preliminary definition of the support – fixation system

Computing the stresses and the deformations of the pipe (help needed!)

Define the acceptable figures for the deformations (are 2 mm o.k.?)

Building a testing device for the validation of the prototypes

To measure the effect and validate the prototypes and the fixation system scheme