13
American Institute of Aeronautics and Astronautics 1 Update on SPHERES Slosh for Acquisition of Liquid Slosh Data aboard the ISS Sunil Chintalapati 1 , Charles A. Holicker 2 , Richard E. Schulman 3 , Brian D. Wise 4 , Gabriel D. Lapilli 5 , Hector M. Gutierrez 6 , and Daniel R. Kirk 7 Florida Institute of Technology, Melbourne, Florida, 32901 A current problem that severely affects the performance of spacecraft is related to slosh dynamics in liquid propellant tanks under microgravity conditions. The confidence in computational fluid dynamics (CFD) predictions are low because of the lack of benchmark against experimental data. The goal of the SPHERES Slosh Experiment (SSE) is to acquire long-duration, low-gravity liquid slosh data aboard the International Space Station. The proposed experimental platform consists of a tank, partially filled with fluid, cameras, and inertial sensors to monitor the fluid distribution in the tank. Currently the SSE has passed NASA’s Critical Design Review (CDR) and Phase 0/I-II Flight Safety Review (FSR). The manufacture and qualification testing of the flight article has been completed. The Slosh payload is scheduled to be launched in December 2013 with on-orbit experiments to begin shortly thereafter. I. Introduction and Background ropellant slosh has been an issue from the inception of liquid rocket engines. Typically rockets are spun at a specified rotation after launch for stability purposes. Rocket upper-stages and satellites are spun for thermal control to ensure even heating of propellant tank caused by the Sun. Liquid propellant tends to swirl insides the fuel tank during these times. When coupled with resonance effects, sloshing increases tremendously causing attitude change of vehicle and impede fuel ingestion into engine intake. Sloshing problem in liquid rocket engines have been a concern since as early as 1960; there are many cited references where a space mission was either deemed failure or could not be fully completed due to sloshing problems in rockets or spacecraft and or satellites. For example, on April 26th, 1957 the second Jupiter missile AM-1B terminated flight at 93 seconds at an altitude of 27.3 kilometers due to propellant slosh [1]. As another example, an experimental test rig for Atlas Centaur 4 was deemed failure due to sloshing and spillage of liquid hydrogen propellant, the tank was later modified [2].In another example, the NEAR satellite went into safety mode because of an unexpected reaction that was possibly due to propellant slosh after an orbital maneuver which caused a one year delay of the project [3]. Another example of dramatic propellant slosh problem occurred at the end of a yaw maneuver during the Apollo 11 first moon landing mission and additional thruster activity was needed for course corrections before the Lunar Lander finally landed at a different spot than originally planned [4]. In another example, NASA’s spin-stabilized Applications Technology Satellite 5 (ATS5) began to wobble, sending the spacecraft into an unplanned flat spin and crippling the mission. The reason for was determined to be propellant slosh [5]. Finally, recently in March of 2007, SpaceX Falcon 1 1 Graduate Research Assistant, Mechanical and Aerospace, 150 West University Blvd, and AIAA Student Member. 2 Graduate Research Assistant, Mechanical and Aerospace, 150 West University Blvd. 3 Graduate Research Assistant, Mechanical and Aerospace, 150 West University Blvd, and AIAA Student Member. 4 Graduate Research Assistant, Mechanical and Aerospace, 150 West University Blvd. 5 Graduate Research Assistant, Mechanical and Aerospace, 150 West University Blvd. 6 Associate Professor, Mechanical and Aerospace Engineering Department. 7 Associate Professor, Mechanical and Aerospace Engineering Department, AIAA Associate Fellow. P Downloaded by FLORIDA INSTITUTE OF TECHNOLOGY on July 27, 2014 | http://arc.aiaa.org | DOI: 10.2514/6.2013-3903 49th AIAA/ASME/SAE/ASEE Joint Propulsion Conference July 14 - 17, 2013, San Jose, CA AIAA 2013-3903 Copyright © 2013 by the American Institute of Aeronautics and Astronautics, Inc. All rights reserved. Joint Propulsion Conferences

Update on SPHERES-Slosh for Acquisition of Liquid …my.fit.edu/~chintals/index_files/2013-3903.pdfFlorida Institute of Technology, Melbourne, Florida, 32901 A current problem that

  • Upload
    others

  • View
    4

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Update on SPHERES-Slosh for Acquisition of Liquid …my.fit.edu/~chintals/index_files/2013-3903.pdfFlorida Institute of Technology, Melbourne, Florida, 32901 A current problem that

American Institute of Aeronautics and Astronautics

1

Update on SPHERES Slosh for Acquisition of Liquid Slosh

Data aboard the ISS

Sunil Chintalapati1, Charles A. Holicker

2, Richard E. Schulman

3, Brian D. Wise

4, Gabriel D. Lapilli

5,

Hector M. Gutierrez6, and Daniel R. Kirk

7

Florida Institute of Technology, Melbourne, Florida, 32901

A current problem that severely affects the performance of spacecraft is related to slosh

dynamics in liquid propellant tanks under microgravity conditions. The confidence in

computational fluid dynamics (CFD) predictions are low because of the lack of benchmark

against experimental data. The goal of the SPHERES Slosh Experiment (SSE) is to acquire

long-duration, low-gravity liquid slosh data aboard the International Space Station. The

proposed experimental platform consists of a tank, partially filled with fluid, cameras, and

inertial sensors to monitor the fluid distribution in the tank. Currently the SSE has passed

NASA’s Critical Design Review (CDR) and Phase 0/I-II Flight Safety Review (FSR). The

manufacture and qualification testing of the flight article has been completed. The Slosh

payload is scheduled to be launched in December 2013 with on-orbit experiments to begin

shortly thereafter.

I. Introduction and Background

ropellant slosh has been an issue from the inception of liquid rocket engines. Typically rockets are spun at a

specified rotation after launch for stability purposes. Rocket upper-stages and satellites are spun for thermal

control to ensure even heating of propellant tank caused by the Sun. Liquid propellant tends to swirl insides the

fuel tank during these times. When coupled with resonance effects, sloshing increases tremendously causing attitude

change of vehicle and impede fuel ingestion into engine intake. Sloshing problem in liquid rocket engines have

been a concern since as early as 1960; there are many cited references where a space mission was either deemed

failure or could not be fully completed due to sloshing problems in rockets or spacecraft and or satellites. For

example, on April 26th, 1957 the second Jupiter missile AM-1B terminated flight at 93 seconds at an altitude of 27.3

kilometers due to propellant slosh [1]. As another example, an experimental test rig for Atlas Centaur 4 was deemed

failure due to sloshing and spillage of liquid hydrogen propellant, the tank was later modified [2].In another

example, the NEAR satellite went into safety mode because of an unexpected reaction that was possibly due to

propellant slosh after an orbital maneuver which caused a one year delay of the project [3]. Another example of

dramatic propellant slosh problem occurred at the end of a yaw maneuver during the Apollo 11 first moon landing

mission and additional thruster activity was needed for course corrections before the Lunar Lander finally landed at

a different spot than originally planned [4]. In another example, NASA’s spin-stabilized Applications Technology

Satellite 5 (ATS5) began to wobble, sending the spacecraft into an unplanned flat spin and crippling the mission.

The reason for was determined to be propellant slosh [5]. Finally, recently in March of 2007, SpaceX Falcon 1

1 Graduate Research Assistant, Mechanical and Aerospace, 150 West University Blvd, and AIAA Student Member. 2 Graduate Research Assistant, Mechanical and Aerospace, 150 West University Blvd. 3 Graduate Research Assistant, Mechanical and Aerospace, 150 West University Blvd, and AIAA Student Member. 4 Graduate Research Assistant, Mechanical and Aerospace, 150 West University Blvd. 5 Graduate Research Assistant, Mechanical and Aerospace, 150 West University Blvd. 6 Associate Professor, Mechanical and Aerospace Engineering Department. 7 Associate Professor, Mechanical and Aerospace Engineering Department, AIAA Associate Fellow.

P

Dow

nloa

ded

by F

LO

RID

A I

NST

ITU

TE

OF

TE

CH

NO

LO

GY

on

July

27,

201

4 | h

ttp://

arc.

aiaa

.org

| D

OI:

10.

2514

/6.2

013-

3903

49th AIAA/ASME/SAE/ASEE Joint Propulsion Conference

July 14 - 17, 2013, San Jose, CA

AIAA 2013-3903

Copyright © 2013 by the American Institute of Aeronautics and Astronautics, Inc. All rights reserved.

Joint Propulsion Conferences

Page 2: Update on SPHERES-Slosh for Acquisition of Liquid …my.fit.edu/~chintals/index_files/2013-3903.pdfFlorida Institute of Technology, Melbourne, Florida, 32901 A current problem that

American Institute of Aeronautics and Astronautics

2

vehicle tumbled out of control [6]. An oscillation appeared in the upper stage control system approximately 90

seconds into the burn and instability grew in pitch and yaw axes initially and after about 30 seconds also induced a

noticeable roll torque .This roll torque eventually overcame 2nd stage’s roll control thrusters and centrifuged

propellants, causing flame-out of the Kestrel engine. There is high confidence that LOX slosh was the primary

contributor to this instability. This conclusion has been verified by third party industry experts that have reviewed

the flight telemetry [7].

These examples show the lack of predictive capability for mission planners to accurately model slosh within a

propellant tank during a critical maneuver such as docking of cargo vehicles or pointing of observational satellites.

CFD models can be used to predict slosh events during a specified maneuver; however, confidence in the CFD tool

predictions with experimental results is severely lacking. Florida Tech has been actively involved in slosh research

since 2007; some of the activities include successful characterization of slosh on a 2- Degree of Freedom (DOF)

motion table, drop tower testing, one sounding rocket test, and two three-day reduced gravity aircraft sessions [8]

[9]. Although the series of ground experiments and trials on reduced gravity aircraft have provided valuable

experimental data-set, there is a lack of long duration, low-gravity experimental liquid slosh data which can be used

to benchmark the CFD models. Liquid behavior in micro-gravity is different from liquid behavior under the

influence of the Earth’s gravity and the need to capture the long duration, low-gravity liquid slosh data gave rise to

the SPHERES-Slosh Experiment (SSE).

II. SPHERES Slosh Experiment (SSE) Overview

The primary objective of the SPHERES Slosh Experiment (SSE) is to acquire long duration, low-gravity liquid

slosh data aboard the International Space Station [10]. The core of the SSE consists of a partially filled (with water)

transparent tank fitted to a structural frame and two cameras (in orthogonal configuration) recording the liquid

distribution. Two sets of Inertial Measurement Units (IMUs) are used to record the inertial measurements. The SSE

utilizes the manifested SPHERES laboratory and will use the VERTIGO platform (already on-board the ISS). The

SPHERES unit would propel the SSE and the VERTIGO units are used to record the caputured IMU /camera data

on its local hard drive. Figure 1 shows the three elements (Slosh payload, SPHERES, and VERTIGO) that combine

to form the SSE. The partially filled water tank is located within the backdrop and hood (labeled in Figure 1) to

mimimize the interference of the external lights on image capture.

Figure 1 Slosh Payload (left), SPHERES (top-right), and VERTIGO Avionics Stack (bottom-left)

Dow

nloa

ded

by F

LO

RID

A I

NST

ITU

TE

OF

TE

CH

NO

LO

GY

on

July

27,

201

4 | h

ttp://

arc.

aiaa

.org

| D

OI:

10.

2514

/6.2

013-

3903

Page 3: Update on SPHERES-Slosh for Acquisition of Liquid …my.fit.edu/~chintals/index_files/2013-3903.pdfFlorida Institute of Technology, Melbourne, Florida, 32901 A current problem that

American Institute of Aeronautics and Astronautics

3

Adequete lighting for image capture is provided via LED panels, installed within the Backdrop and Hood. The

Slosh Avionics Box contains the IMUs and also provides power to the Camera and the LED panels through the

VERTIGO unit. The Slosh Avionics Box also ensures that the captured IMU data and Camera data is recorded to the

VERTIGO harddrive. Each of the Slosh Avionics Boxes connects to a VERTIGO unit. The VERTIGO-Slosh

Avionics Box packages then connect to the SPHERES units via the SPHERES expansion port. Each SPHERES unit

resides within the Frame Arm saddles and is clamped down during the SSE operation.

During the test sessions, the SSE will conduct translational and rotational maneuvers. The experiment will

measure the resulting water behavior within the tank. Data obtained from the SSE will be used to calibrate numerical

slosh models to improve the design and reliability of future rocket vehicles and spacecraft. An isometric CAD view

of the SSE is shown in Figure 2 (top) and the manufactured SSE is shown in the bottom image.

Figure 2 SPHERES Slosh Experiment (SSE)

Dow

nloa

ded

by F

LO

RID

A I

NST

ITU

TE

OF

TE

CH

NO

LO

GY

on

July

27,

201

4 | h

ttp://

arc.

aiaa

.org

| D

OI:

10.

2514

/6.2

013-

3903

Page 4: Update on SPHERES-Slosh for Acquisition of Liquid …my.fit.edu/~chintals/index_files/2013-3903.pdfFlorida Institute of Technology, Melbourne, Florida, 32901 A current problem that

American Institute of Aeronautics and Astronautics

4

III. SSE Operation on the ISS

In order to complete the primary objectives, the SSE design is presented. The initial design is based on the

scientific requirement, which is an experimental platform capable of measuring liquid slosh via an image acquisition

system and a set of inertial measurement units. The final design is a culmination of many design iterations which

satisfies the requirements set forth by the ISS office and NASA (for launch activities). The final design iteration

also takes into account dynamics, kinematics, and CFD analysis to verify that the SSE is capable of producing

detectable liquid slosh and capturing it. The SSE will perform three different maneuvers on the ISS at two different

liquid fill levels (20 % liquid filled tank, and 40 % liquid filled tank) and a 40 % solid mass ( no liquid, dry weight,

which mimic the mass and initial inertia of a 40 % liquid filled tank). The three maneuvers are as follows:

1. Settling thrust maneuver: Accelerate the motionless SSE on its major axis for a fixed duration and then

apply reverse thrust to accelerate the system in the opposite direction.

2. Passive thermal control maneuver: Slowly spin the SSE on its minor axis to attain constant spin rate and

settle the fluid. Following which thermal roll about the major axis while maintaining constant major axis spin

rate.

3. Pitch to reorient maneuver: Spin the SSE about the minor axis to settle the fluid and make a sharp 45 degree

turn out of the spin plane to 2nd burn attitude.

Figure 3 shows a notional overview of each maneuver.

Figure 3 Notional overview of the three maneuvers

A summary of analyses leading to the current design of the SSE is presented in the following sub-sections.

A. Summary of the Dynamics and Kinematics of the SSE

A dynamics analysis of the SSE is performed to verify its stability and a kinematic analysis is performed to quantify

the behavior of the SSE due to an application of external forces. This behavior is sensitive to change in center of

gravity (CG) and inertia matrix of the the SSE; hence, first the maximum CG shift due to location of fluid in the

Slosh tank is computed, followed by a CG shift due to the changing fuel level in SPHERES CO2 tank is quantified.

This combination of CG shift due to the fluid location and changing fuel level provides a maximum envelope of CG

shift for the SSE. Inertia matrixes from the maximum CG shift cases are examined and further cases are developed

by changing the inertia matrix. A list of cases is developed, which include the baseline cases and different

acceleration (or force) inputs are employed on list of cases. Using a MATLAB 6 degrees of freedom (DOF) [11]

solver, the deviations in translation and rotation rates as compared with baseline cases are tabulated and plotted.

These deviations are examined to check for the impact of CG and inertia matrix on a maneuver or acceleration input

[12] [13].

Dow

nloa

ded

by F

LO

RID

A I

NST

ITU

TE

OF

TE

CH

NO

LO

GY

on

July

27,

201

4 | h

ttp://

arc.

aiaa

.org

| D

OI:

10.

2514

/6.2

013-

3903

Page 5: Update on SPHERES-Slosh for Acquisition of Liquid …my.fit.edu/~chintals/index_files/2013-3903.pdfFlorida Institute of Technology, Melbourne, Florida, 32901 A current problem that

American Institute of Aeronautics and Astronautics

5

B. Application of the Non-dimensional Parameters

Experimentation aboard the ISS needs a definitive approach, and the motion profile employed on the SSE needs

to have semblance to rocket upper-stage maneuvers. Three typical rocket upper-stage propellant maneuvers are

examined. A literature study was performed and relevant data was gathered and tabulated. The literature review

yielded an operation range of the rocket upper-stages. The operation range of the SSE was identified, which also

included the constraints of experimentation on ISS. The two distinct operations were mapped via non-dimensional

parameters and regime influences were analyzed. Specific results from this study were:

1. For Settling Thrust maneuver, rocket upper-stage is matched to the SSE by Froude number matching.

2. For Passive Thermal Control maneuver, rocket upper-stage is matched to the SSE by matching rotation

rates for each individual upper-stage non-dimensional number. High degree of rotation rates that are not

possible in the SSE are filtered in results.

3. For Pitch to Reorient maneuver, rocket upper-stage is matched to the SSE by matching rotation rates for

each individual upper-stage non-dimensional number. High degree of rotation rates that are not possible in

SSE are filtered in results.

Supplemental studies involve identification of working fluid for SSE, which best mimic cryogenic propellants

employed in rocket upper-stages [12] [13].

C. Summary of the Numerical Study of the SSE

Numerical simulations were performed to analyze the liquid behavior and quantify the deviation with a solid

counterpart. Figure 4 shows the sample CFD results of Passive Thermal Control (BBQ Roll) maneuver. This figure

is a compilation of input and results for this maneuver. Figure 4a shows the sample input thrust profile for this

maneuver. At time equals zero, a positive torque applied in +y direction for a duration of 10 seconds, followed by a

positive torque in +z direction for an additional 10 seconds. The SSE is allowed to coast for another 20 seconds and

changing liquid distribution is monitored. Figure 4b, Figure 4c, and Figure 4d shows results of position, velocity and

rotational rates in inertial frame of reference. These plots show three different plot lines, an empty SSE, SSE with

solid at 20% fill volume (frozen liquid), and SSE with liquid at 20% fill volume. Figure 4b shows CG position in x,

y and z direction. Figure 4e shows series of time-stamped numerical images of liquid distribution in Slosh tank. The

initial condition in this sample simulation in liquid in the end-cap of the tank (this initial condition is same for both

solid and liquid cases).

Dow

nloa

ded

by F

LO

RID

A I

NST

ITU

TE

OF

TE

CH

NO

LO

GY

on

July

27,

201

4 | h

ttp://

arc.

aiaa

.org

| D

OI:

10.

2514

/6.2

013-

3903

Page 6: Update on SPHERES-Slosh for Acquisition of Liquid …my.fit.edu/~chintals/index_files/2013-3903.pdfFlorida Institute of Technology, Melbourne, Florida, 32901 A current problem that

American Institute of Aeronautics and Astronautics

6

Figure 4 Sample numerical result for Passive Thermal Control maneuver, (a)Thrust profile, (b)

Position (x, y, z) vs. time result, (c) Velocity (x, y, z) vs. time result, (d) Rotation rate (x, y, z) vs. time

result, (e) Time stamped numerical images of liquid distribution

Specific results from the numerical study are as follows:

1. Liquid distribution within the Slosh tank before the start of experimentation on the ISS needs to be known

apriori. A random liquid distribution captured by the camera is a challenging input to CFD simulation and

results of CFD and experiment depend largely on getting the correct initial condition. A target initial

Dow

nloa

ded

by F

LO

RID

A I

NST

ITU

TE

OF

TE

CH

NO

LO

GY

on

July

27,

201

4 | h

ttp://

arc.

aiaa

.org

| D

OI:

10.

2514

/6.2

013-

3903

Page 7: Update on SPHERES-Slosh for Acquisition of Liquid …my.fit.edu/~chintals/index_files/2013-3903.pdfFlorida Institute of Technology, Melbourne, Florida, 32901 A current problem that

American Institute of Aeronautics and Astronautics

7

condition study was initiated, where a random liquid distribution would be forced to a known initial

condition. Three favorable initial conditions were identified and labeled as IC1 (liquid in end-cap), IC2

(uneven split of liquid in either of end-caps), and IC3 (liquid coated to tank walls). IC1 was attainable

through an abrupt acceleration and retarding motion for a distance of a longitudinal length of the tank. IC1

and IC2 were attainable through spinning on minor axis and the magnitude of torque and duration

determined the initial condition that would be achieved. IC3 was tough to achive in numerical simulations.

2. Based on the guidance from kinematics study and non-dimensional mapping study, a variety of motion

profiles were developed for a specific maneuver. Comparison of fluid simulation with a frozen liquid

(solid) simulation to quantify the deviations in position, velocity, acceleration, rotation rates, and angular

acceleration were accomplished. An optimized motion profile was developed for each maneuver based on

conclusions from this study.

3. A fill volume sub-study was also performed in tandem to find the optimal fill volume for the SSE. A 20%

to 40% fill volume was determined to be ideal range for experimentation; hence, two sealed tanks, one with

20% fill volume of water and another tank with 40% fill volume of water will be sent to the ISS for

experimentation.

4. An optimized list of motion profiles for three different maneuvers was derived from the numerous

numerical simulations performed. Each session is approximately 5.5 hours, which includes assembly and

disassembly of experimental platform (including SPHERES and VERTIGO integration). This list also

included a consumable usage to conserve the resources and not lose precious time in replacing the

consumable during experimentation. Table 1 shows the three maneuvers to be performed by the SSE on the

ISS. The three maneuevres will be repeated three times.

Table 1 Experiment List per Test Session

References [12] and [13] provide a detailed overview of the analyses performed and specific results obtained.

IV. SSE - Ground Testing

The goals of the SSE Ground Testing was to verify that the Slosh payload when combined with the SPHERES and

the VERTIGO unit would function normally as intended. Major aspects of the Ground Testing was to verify the

following:

A. Mechanical Fit Check

The mechanical fit check of the SSE was performed in three different operations. The first mechanical fit check was

to verify the assembly of the manufactured Slosh payload was performed as per the CAD design intent. The second

mechanical fit check was to verify the mechanical connectivity between the Slosh Avionics Box and the VERTIGO

avionics stack. The third mechanical fit check was to verify the mechanical connectivity between the SPHERES and

the Slosh Frame Arm. Figure 5 shows images of the successful mechanical fit checks.

Dow

nloa

ded

by F

LO

RID

A I

NST

ITU

TE

OF

TE

CH

NO

LO

GY

on

July

27,

201

4 | h

ttp://

arc.

aiaa

.org

| D

OI:

10.

2514

/6.2

013-

3903

Page 8: Update on SPHERES-Slosh for Acquisition of Liquid …my.fit.edu/~chintals/index_files/2013-3903.pdfFlorida Institute of Technology, Melbourne, Florida, 32901 A current problem that

American Institute of Aeronautics and Astronautics

8

Figure 5 Mechanical Fit Check; a) Slosh payload, b)VERTIGO – Slosh Avionics, and c) SPHERES

–Slosh Frame Arm

B. Electrical Integration Test (VERTIGO-Slosh Avionics Box)

The verification for electrical integration is performed when the Slosh Avionics Box is connected electrically

with VERTIGO. Upon the VERTIGO power ‘ON’, the following have to be achieved:

1. The camera connected to the Slosh Avionics Box is able to receive power, capture images and record

image data on the VERTIGO hard drive.

2. The IMUs in the Slosh Avionics Boxes are able to receive power, receive inertial data and record that data

to the VERTIGO hard drive.

3. The light panels in the backdrop and hood are able to receive power and operate nominally.

The electrical integration was successfully accomplished on ground motion tables. The captured camera and

IMU data was analysed post-electrical integration test.

C. Flat Floor Testing

The purpose of the flat floor test is to verify correct functionality of the integrated SSE, and to verify the impact of

depleting SPHERES CO2 propellant level and water tank fill level on the intended motion profiles of the SSE. In

order to perform flat floor testing, the SSE must be mounted on an adaptor which is capable of levitating the

experiment. Specifically, the flat floor adapter must be capable of levitating the mass of the SSE without binding on

the flat floor for any of the motion trajectories being studied. The flat floor adapter must not require any design

changes to the SSE and must not restrict the capabilities of the SSE. Figure 6 shows a sample image of the SSE on

the flat floor table. The SSE shown in Figure 6 has ground units (not flight certified) of backdrop, hood, Slosh

Avionics Box, which are used for ascertain the flat floor test procedures for the SSE.

Dow

nloa

ded

by F

LO

RID

A I

NST

ITU

TE

OF

TE

CH

NO

LO

GY

on

July

27,

201

4 | h

ttp://

arc.

aiaa

.org

| D

OI:

10.

2514

/6.2

013-

3903

Page 9: Update on SPHERES-Slosh for Acquisition of Liquid …my.fit.edu/~chintals/index_files/2013-3903.pdfFlorida Institute of Technology, Melbourne, Florida, 32901 A current problem that

American Institute of Aeronautics and Astronautics

9

Figure 6 Preliminary Flat Floor Testing

The key purpose of flat floor testing is to quantify the impact of CO2 tank fill level on the SSE trajectory for each of

the three motion profiles. The trajectories for translation (settling maneuver), rotation (passive thermal control

maneuver), and combined rotation and translation maneuvers (pitch to reorient maneuver) will be executed with a

single water tank for both equal CO2 tank fill levels between the two SPHERES units as well as different CO2 tank

levels between the two SPHERES units. This process is then repeated again for a different water volume. The data

acquired from these tests will provide an understanding of the sensitivity of the experiment to CO2 and water fill

volume as well benchmarking for the 6-DOF CFD and analytical models used to predict the behavior of the SSE

trajectories. The impact of the CO2 slosh on the trajectory deviation of the SSE during flat floor operation is also

negligible; instead the CO2 fuel imbalance changes the overall CG and inertia of the SSE and results in a different

trajectory. The adapter used for levitating the SSE employs two large CO2 tanks and the changing mass of this CO2

used for levitation also changes the overall mass of the experiment. Therefore, the mass of the levitation CO2 will be

monitored through weight measurement and the updated total mass of the system will be used for trajectory analysis.

The SSE Flat Floor testing is currently underway and scheduled to be completed by mid-July 2013.

V. SSE - Flight Safety Review

The Flight Safety Review (FSR) process is defined in Space Shuttle Program (SSP) 30599, Safety Review

Process, International Space Station Program. SSP 30599 provides information and guidance on flight certifying

payloads for both launch and operations aboard the ISS. The safety review process for the Slosh payload is managed

by a Payload Safety Review Panel (PSRP) in four different safety review meetings held at different junctures of the

project. A Phase 0 FSR was held (July 19, 2012) so that the Payload Developer (PD) can provide a detailed

description of the payload material, construction and intended operations aboard the ISS. The PSRP then identifies

applicable hazards, which then has to be eliminated or mitigated by the PD. The standard list of hazards causes,

controls, and verification methods are provided in Johnson Space Center (JSC) form 1230, Flight Payload

Standardized Hazard Control Report. Phase I-II FSR (March 6, 2013) was held to verify the completion status of the

applicable hazards. Typically the Phase III FSR is held to verify the completion of analysis, testing, and relevant

waivers for payloads flight certification. All the applicable hazards for the Slosh payload have been addressed either

by analysis, testing, and or procurement of official waivers. A brief summary of applicable hazards, hazard controls,

and verification method for the Slosh payload is provided in Table 2.

Dow

nloa

ded

by F

LO

RID

A I

NST

ITU

TE

OF

TE

CH

NO

LO

GY

on

July

27,

201

4 | h

ttp://

arc.

aiaa

.org

| D

OI:

10.

2514

/6.2

013-

3903

Page 10: Update on SPHERES-Slosh for Acquisition of Liquid …my.fit.edu/~chintals/index_files/2013-3903.pdfFlorida Institute of Technology, Melbourne, Florida, 32901 A current problem that

American Institute of Aeronautics and Astronautics

10

Table 2 Slosh Standard Hazard Controls Summary

Hazard Hazard Controls

(Complies with)Verification Method Status

MAPTIS approved materials

Perform flammability assessment (tests)

By analysis

MAPTIS approved materials

Perform offgassing assessment (tests)

By analysis

Review the SSE CAD drawings

Sharp edge inspection (Nylon Glove Test)

4Touch Temperature IVA Resulting in

Crew InjurySSP 50005 Perform Test Temperature Test Completed

Review and modify Stowage bag

configuration

Pass a vibration test at flight levels/post-

test visual inspection is needed

6

Electromagnetic Radiation (Non-

Ionizing) causing injury to crew or

interference with ISS systems

SSP 30237 Perform EMI testing Completed

7 Lasers causing injury to crew

8

Noise Exposure causing hearing damage

or crew injury/death from communication

interference or inability to detect cautions

and alarms

9Battery Failure causing crew injury

(shock, burn, fire, toxicity hazard)

10Capacitors used as energy storage

devices

Review of design to assure implementation

of proper wire sizing and circuit.

Protection for Slosh Experiment to verify it

meets requirements in TA-92-038.

Inspection of "as-built" hardware to ensure

wire sizing and circuit protection is in

accordance with drawing/design.

12

Mating/Demating Power Connectors

causing crew injury due to generation of

molten metal or damage to ISS mission-

or life-critical electrical equipment

Meets the low power

criteria of letter MA2-99-

170

Verify circuit protection keeps current

under 3A.Completed

13 Rotating Equipment causing crew injury

14 Interference with Translation Paths

Design does not impede

emergency IVA egress to

the remaining adjacent

pressurized volumes.

Per desktop analysis, the SSE is a free-

floating experiment which does not impede

emergency IVA egress to the remaining

adjacent pressurized volumes

Completed

15 Structural Failure

16 Structural Failure of Sealed Containers

17 Structural Failure of Vented Containers JSC 1230

Check the design of the avionics box to

ensure Maximum Effective Vent Ratio

(MEVR) for a 0.01 psid pressure

differential is less than or equal to 2000 in.

Completed

Material Flammability NASA STD-6001B Completed1

2 Material Offgassing NASA STD-6001B Completed

Mechanical Hazards Causing Injury to

IVA Crew (sharp edges, pinch points,

etc.)

3 SSP 51700 Completed

CompletedSSP 50835Shatterable Material releasing 50 micron

or larger fragments causing injury to crew5

Not Applicable

Not Applicable

Not Applicable

Not Applicable

Not Applicable

11 SSP 57000 Completed

Refer Unique Hazard

Refer Unique Hazard

Electrical Power causing crew injury or

damage to electrical equipment

Dow

nloa

ded

by F

LO

RID

A I

NST

ITU

TE

OF

TE

CH

NO

LO

GY

on

July

27,

201

4 | h

ttp://

arc.

aiaa

.org

| D

OI:

10.

2514

/6.2

013-

3903

Page 11: Update on SPHERES-Slosh for Acquisition of Liquid …my.fit.edu/~chintals/index_files/2013-3903.pdfFlorida Institute of Technology, Melbourne, Florida, 32901 A current problem that

American Institute of Aeronautics and Astronautics

11

Flammability and offgassing assessment was performed as per NASA STD 6001B on the 3D printed plastic

components of the SSE. All the components of the SSE are either Materials and Processes Technical Information

System (MAPTIS) approved, have passed flammability and offgassing assessment and or deemed acceptable by

analysis.

A sharp edge inspection of each individual component, as well as the assembled experiment, was conducted to

verify that edges, corners, or protrusion geometries are in compliance with SSP 51700 Section 3.22.1, Sharp Edges

and Corner Protection. A nylon glove test was used to perform this verification.

Requirements for touch temperature are based of SSP 50005, section 6.5.3, where a minimum temperature of 4

ºC (39 ºF) and a maximum temperature of 45 ºC (113 ºF) is passable for any components susceptible to temperature

changes. The Touch Temperature testing was performed at NASA MSFC, EMC/EMI facility for the flight Slosh

hardware articles in the ISS configuration (complete operational SSE assembly). Temperature readings were taken at

pre-defined locations on the surface of the SSE. The temperature readings were taken every five minutes after the

SSE startup for a total duration of 60 minutes. The detailed procedure for performing the Touch Temperature is

defined in the Touch Temperature Test Plan, which was reviewed and witnessed by Government personnel. The

touch temperature ranges of the Slosh hardware are within the prescribed temperature limits as defined in SSP

50005.

The lens of the camera is susceptible to shattering during launch or stowage due to vibration loads. Each camera

will be stowed in a double bag configuration, where the inner most bag is optically clear so that a crew member can

visually inspect the camera lens prior to opening the bag. If a crack exists or the lens has been damaged, the camera

is not removed and will not be used. The Slosh hardware was vibration tested in its stowage configuration (bubble

wrapped and packed in class III triple CTB and tested to a maximum flight random vibration envelope as specified

in SSP 50835 (Table 3.1.1.2.1.2.3.2-3 and Table 3.1.1.2.1.2.3.2-4). All the three axis of the triple CTB was vibration

tested for a duration of 180 seconds per axis (Qualification standard or three time the duration of proto-flight

standard). The lenses of the camera were in no way damaged during the vibration test and the cameras continue to

function as intended (post-vibration). The LED panels in the Hood and Backdrop were not damaged or shattered

during the vibration test. The structural integrity of the Slosh tank was not damaged and there was no leakage

present post vibration.

An EMI test for Radiated Emissions (RE02) was performed on the operational SSE at NASA MSFC, EMI Test

Facility. The entire SSE (SPHERES/VERTIGO/SLOSH system) complement was subjected to Electromagnetic

Emissions testing as specified in SSP 30237 and SSP 30238.

The power source for all electronic equipment in the SSE is supplied by VERTIGO’s internal battery. The Slosh

Avionics Box consists of 4 pairs of LEDs on the external surface that provide visual confirmation regarding the

proper functionality of the various internal components. The colored LEDs provide a quick visual feedback to the

operator confirming that the box is working properly. If the LEDs indicate the box is not working, a replacement

box will be installed on the experiment and the defective box will not be used. In the order of operations, two red

LEDs indicate an incoming voltage of 5V and 12V from VERTIGO (Figure 7). Two green LEDs indicate proper

circuit protection and the power output for camera/lighting system and IMUs (Figure 7). Two yellow LEDs indicate

input commands to the IMUs. Finally, two blue LEDs indicate data being received from the IMUs. For example, a

non-lit green LED would indicate problems with the circuit protection line. This would result in no power output to

the corresponding system as the box is designed to prevent any power distribution in case of hardware failure.

Dow

nloa

ded

by F

LO

RID

A I

NST

ITU

TE

OF

TE

CH

NO

LO

GY

on

July

27,

201

4 | h

ttp://

arc.

aiaa

.org

| D

OI:

10.

2514

/6.2

013-

3903

Page 12: Update on SPHERES-Slosh for Acquisition of Liquid …my.fit.edu/~chintals/index_files/2013-3903.pdfFlorida Institute of Technology, Melbourne, Florida, 32901 A current problem that

American Institute of Aeronautics and Astronautics

12

Figure 7 SPHERES-VERTIGO-Slosh Avionics Box package in operation; two lit red LEDs indicate

correct voltage, two lit green LEDs indicate circuit protection and power output

A review of the mechanical and electrical drawings, as well as an inspection of the Slosh Avionics Box was

performed to satisfy the guidelines of the section 11 and 12 in Table 2.

The verification for Structural Failure of Vented Container was performed using the criteria outlined in the

standard hazard document. The criteria states that the ratio of the total volume of the container to the open vent area

should be less than 2,000 in. The total volume of the Slosh Avionics Box is 242.5 cm3 (14.8 in

3) and the vent area is

0.32 cm2 (0.05 in

2), which provides a volume-to-area ratio of 296 in, and results in a factor of safety of over 6.

The PSRP combined the Standard hazard 15 and 16 with additional hazards to form a unique hazard titled

“Leakage of the Slosh Tank”. The unique hazard required pressure testing the tank to maximum delta pressure of 1.5

atms, review of manufacture procedure, review of fill procedures and evaluating the toxic rating of the liquid

contained in the Slosh tank. The Slosh tank was pressure tested for a 1.5 atm pressure differential to verify the

structural integrity. Structural integrity was verified through a leak test and visual inspection for cracks. Four

different types of pressurization tests were completed and summary of the results are provided below:

1. The first pressure test is a gradual increase of pressure within the Wet Slosh tank (full of water) from

ambient pressure to a pressure differential of 1.5 atmospheres (22.0 ± 1.0 psig). The gradual increase of

pressure took 80 seconds. The increased internal pressure was held constant for 60 second duration and the

tank was then inspected. Result: PASS

2. The second pressure test is a rapid increase of pressure within the Wet Slosh tank from ambient pressure to

a pressure differential of 1.5 atmospheres (22.0 ± 1.0 psig). The rapid increase of pressure took 0.5 seconds.

The increased internal pressure was held constant for 60 second duration and the tank was then inspected.

Result: PASS

3. The third pressure test is a gradual increase of pressure within the Dry Slosh tank (no water) from ambient

pressure to a pressure differential of 1.5 atmospheres (22.0 ± 1.0 psig). The gradual increase of pressure

took 80 seconds. The increased internal pressure was held constant for 60 second duration and the tank was

inspected. Result: PASS

4. The fourth pressure test is a rapid increase of pressure within the Dry Slosh tank from ambient pressure to a

pressure differential of 1.5 atmospheres (22.0 ± 1.0 psig). The rapid increase of pressure took 0.5 seconds.

The increased internal pressure was held constant for 60 second duration and the tank was inspected.

Result: PASS

Dow

nloa

ded

by F

LO

RID

A I

NST

ITU

TE

OF

TE

CH

NO

LO

GY

on

July

27,

201

4 | h

ttp://

arc.

aiaa

.org

| D

OI:

10.

2514

/6.2

013-

3903

Page 13: Update on SPHERES-Slosh for Acquisition of Liquid …my.fit.edu/~chintals/index_files/2013-3903.pdfFlorida Institute of Technology, Melbourne, Florida, 32901 A current problem that

American Institute of Aeronautics and Astronautics

13

Besides the Standard hazards and the unique hazard, the PD had to perform a collision analysis for a scenario in

which the SSE would strike the walls of the ISS. The PD also had to verify (analysis and testing) the effectiveness of

the clamp mechanism (which secures the SPHERES unit with the Slosh Frame) during a potential collision scenario.

VI. Conclusion

The primary objective of the SSE is to acquire long duration, low-gravity liquid slosh data aboard the ISS. This

paper presents a progress update of the SSE, which is scheduled to be launched in December 2013 and perform

experiments during increment 37-38. An initial check-out session will be done to ensure all components of the SSE

are functioning as intended. There are three allotted session for the SSE; a 20% liquid fill level tank will be used for

session 1 (three maneuvers as defined in Table 1), a 40% liquid fill level tank will be used for session 2 (three

maneuvers as defined in Table 1), and a 40% fill level solid mass tank will be used for session 3 (three maneuvers as

defined in Table 1). The experimental data acquired will be part of NASA Kennedy Space Center (KSC) Launch

Services Program (LSP) Slosh catalog, which will be openly available to fluid slosh researcher in industry and

academia.

Acknowledgments

The authors wish to express gratitude to Dr. Paul Schallhorn, Jacob Roth, Brandon Marsell (NASA KSC,

Launch Services Program), and David Piryk from a.i solutions for technical input and funding this project. The

authors also wish to thank Dr. Alvar Saenz-Otero and Dr. David Miller from MIT Space Systems Lab for technical

advice regarding SPHERES and VERTIGO.

References

1 Kyle,. Space Launch Report. http://www.spacelaunchreport.com/jupiter4.html (accessed July 2012).

2 Hydrogen vent test rig in Space Power Chamber No.2. http://awt.grc.nasa.gov/siteimgdetail/detail.np/detail-90.html (accessed

July 2012).

3 Strikwerda, T. E. and et al. NEAR Shoemaker: Major anomaly survival, delayed rendezvous and mission success; Guidance

and control 2001: Breckenridge, CO, 2001.

4 Jones, E. M. The First Lunar Landing. http://www.history.nasa.gov/alsj/a11/a11.landing.html (accessed Oct 24, 2011).

5 Schlee, K. Modeling Spacecraft Fuel Slosh at Embry-Riddle Aeronautical University.

http://www.mathworks.com/company/newsletters/articles/modeling-spacecraft-fuel-slosh-at-embry-riddle-aeronautical-

university.html (accessed July 2012).

6 Musk, E. Space Exploration Technologies Corporation - Update Archive.

http://www.spacex.com/updates_archive.php?page=0107-0707. (accessed June 25, 2013).

7 F1-DemoFlight2-Flight-Review. http://www.spacex.com/F1-DemoFlight2-Flight-Review.pdf. (accessed June 25, 2013).

8 Zhou, R., Vergalla, M., Chintalapati, S., Kirk, D., and Gutierrez, H., "Experimental and Numerical Investigation of Liquid

Slosh Behavior Using Ground-Based Platforms," Journal of Spacecraft and Rockets, Vol. 49, No. 6, Nov-Dec 2012, pp. 1194-

1204.

9 Faure, J., Vergalla, M., Zhou, R., Chintalapati, S., Gutierrez, H., and Kirk, D., "Experimental Platform for the Study of Liquid

Slosh Dynamics Using Sounding Rockets," International Review of Aerospace Engineering, Vol. 3, No. 1, 2010, pp. 59-66.

10 Schallhorn, P., Roth, J., Marsell, B., Kirk, D., Gutierrez, H., Saenz-Otero, A., Dorney, D., and Moder, J. "Acquisition of

Long-Duration, Low-Gravity Slosh Data Utilizing Existing ISS Equipment (SPHERES) for Calibration of CFD Models of

Coupled Fluid-Vehicle Behavior," 1st Annual International Space Station (ISS) Research and Development Conference,

Denver, CO, 26-28 Jun. 2012.

11 MATLAB Documentation. http://www.mathworks.com/help/matlab/ (accessed Apr 21, 2013).

12 Chintalapati, S., Holicker, C. A., Schulman, R. E., Contreras, E., Gutierrez, H. M., and Kirk, D. R. "Design of an

Experimental Platform for Acquisition of Liquid Slosh Data aboard the International Space Station," 48th

AIAA/ASME/SAE/ASEE Joint Propulsion Conference & Exhibit , Atlanta, Georgia, July 2012.

13 Chintalapati, S. Design of an Experimental Platform for Acquisition of Liquid Slosh Data aboard the International Space

Station, Florida Institute of Technology; Master's Thesis, Melbourne, 2012.

Dow

nloa

ded

by F

LO

RID

A I

NST

ITU

TE

OF

TE

CH

NO

LO

GY

on

July

27,

201

4 | h

ttp://

arc.

aiaa

.org

| D

OI:

10.

2514

/6.2

013-

3903