1 1 CAP CAP - - REDEO MEETING REDEO MEETING 4 4 th th April 2007. Vientiane, LAO PDR April 2007. Vientiane, LAO PDR Department of Electricity, Department of Electricity, Ministry of Energy and Mines Ministry of Energy and Mines LAO PDR LAO PDR Tel: 856 Tel: 856 - - 21 21 - - 415714 415714 Fax; 856 Fax; 856 - - 21 21 - - 415388 415388 Email: Email: [email protected] [email protected] Rural Electrification Situation Rural Electrification Situation in Lao PDR in Lao PDR

Update on Current Development of Power Sector in Lao PDR · Power Sector Policy Maintain and expand affordable, reliable and sustainable supply electricity to promote economic and

  • Upload
    others

  • View
    2

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Update on Current Development of Power Sector in Lao PDR · Power Sector Policy Maintain and expand affordable, reliable and sustainable supply electricity to promote economic and

11

CAPCAP--REDEO MEETINGREDEO MEETING44thth April 2007. Vientiane, LAO PDRApril 2007. Vientiane, LAO PDR

Department of Electricity, Department of Electricity, Ministry of Energy and MinesMinistry of Energy and Mines

LAO PDRLAO PDRTel: 856Tel: 856--2121--415714415714Fax; 856Fax; 856--2121--415388415388

Email: Email: [email protected][email protected]

Rural Electrification SituationRural Electrification Situationin Lao PDRin Lao PDR

Page 2: Update on Current Development of Power Sector in Lao PDR · Power Sector Policy Maintain and expand affordable, reliable and sustainable supply electricity to promote economic and

22

OUT LINEOUT LINE

1.1. INTRODUCTIONINTRODUCTION2.2. ROLES AND RESPONSIBILITIESROLES AND RESPONSIBILITIES3.3. CURRENT STATUS AND ONCURRENT STATUS AND ON--

GOING RE PROGRAM GOING RE PROGRAM 4.4. GOVERNMENT TARGET FOR REGOVERNMENT TARGET FOR RE5.5. POLICY AND PLANNINGPOLICY AND PLANNING6.6. CONCLUSIONCONCLUSION

Page 3: Update on Current Development of Power Sector in Lao PDR · Power Sector Policy Maintain and expand affordable, reliable and sustainable supply electricity to promote economic and

33

1. INTRODUCTION1. INTRODUCTION

11. . Country: Centrally located in Country: Centrally located in GMR Area = 236,800 kmGMR Area = 236,800 km2, 2,

Mountainous, land locked Mountainous, land locked 2. Population: 5.6 million, 80% in 2. Population: 5.6 million, 80% in

rural areas, 2.6% annual Growth, rural areas, 2.6% annual Growth, 3. Economy: 3. Economy: Narrow base Narrow base -- resource exploitationresource exploitationGNP per capita of US$ 400, GNP per capita of US$ 400, GDP growth of 7% annually, 26.6% of GDP growth of 7% annually, 26.6% of

GDP from industry and other GDP from industry and other remaining from Agriculture, and remaining from Agriculture, and services sectorservices sector

4.4. Hydropower Potential: over Hydropower Potential: over 23,000 MW.23,000 MW.

47 % of Household electrified (2005)

Lao PDR

Page 4: Update on Current Development of Power Sector in Lao PDR · Power Sector Policy Maintain and expand affordable, reliable and sustainable supply electricity to promote economic and

44

2.2. Power Sector for Lao PDRPower Sector for Lao PDRPrime Minister

Office

State Planning Committee

Council of Ministers

CabinetSecretariat

Ministry of Transport,Communications &

Construction

Ministry of Agriculture &

Forestry

Cabinet

Ministry of Energy and

MinesMinistry of Finance

Science, Technology & Environment Agency

National Committeefor Energy

Department of Electricity

Department of Promotion And Power Development

Provincial Departments

Electricity Units

Power Sector Construction Companies

Eletricitedu Laos IPP/SPP

Other Departments

Page 5: Update on Current Development of Power Sector in Lao PDR · Power Sector Policy Maintain and expand affordable, reliable and sustainable supply electricity to promote economic and

55

3. Ownership of Generation3. Ownership of Generation

öÁ¹ìȤ°½ìò© Ã− ó̄ 2004

44.6%

52.5%

2.9%

³³ì ²¾¡Àº¡½§ö− êûº¤«†−

²¾¡Àº¡½§ö− ³³ì

êºÉ¤«†−

EDL IPP Provincial

IPP EDL

Provincial

Installed Capacity: 690 MW: EdL 307.5 MW

IPP: 362.5 MW, Provincial: 20

Page 6: Update on Current Development of Power Sector in Lao PDR · Power Sector Policy Maintain and expand affordable, reliable and sustainable supply electricity to promote economic and

66

-- Location of ExistingLocation of ExistingHydropower PlantsHydropower Plants

-- Installed Capacity: 690 MWInstalled Capacity: 690 MW

Nam Ngum 1 (150)

Nam Ngai 1.2)

Theun-Hinboun (210) Xelabam (5)

Xeset 1 (45)

Houay Ho (150)

Nam Ko (1.5)

Nam Leuk (60)

Existing Hydropower ProjectsExisting Hydropower Projects

Nam Mang 3 (40)

Page 7: Update on Current Development of Power Sector in Lao PDR · Power Sector Policy Maintain and expand affordable, reliable and sustainable supply electricity to promote economic and

77

Small Hydro for the PeopleSmall Hydro for the People

The Nam The Nam MongMong and and HouayHouay Se Hybrid System Se Hybrid System Projects have supported Villages.Projects have supported Villages.

Small HydroSmall Hydro

Page 8: Update on Current Development of Power Sector in Lao PDR · Power Sector Policy Maintain and expand affordable, reliable and sustainable supply electricity to promote economic and

88

Nam Bo Village,Nam Bo Village,LuangLuang PrabangPrabangProvinceProvinceCapacity: 3 kWCapacity: 3 kW

Village Hydro Village Hydro StationStation

ThapenThapen Village,Village,LuangLuang PrabangPrabangProvinceProvinceCapacity: 2 kWCapacity: 2 kWAbout 50 customersAbout 50 customers

Page 9: Update on Current Development of Power Sector in Lao PDR · Power Sector Policy Maintain and expand affordable, reliable and sustainable supply electricity to promote economic and

99

HouseholdHouseholdPicoPico--HydroHydro

In most of villagesIn most of villagesNorthern ProvinceNorthern Province

Capacity: 0.2 Capacity: 0.2 –– 3 3 kWkWUse for Use for lightinglighting and and TVTV

Page 10: Update on Current Development of Power Sector in Lao PDR · Power Sector Policy Maintain and expand affordable, reliable and sustainable supply electricity to promote economic and

1010

Solar Home Solar Home SystemSystem(Off(Off--Grid Grid Project)Project)

SHS is the most popular SHS is the most popular system for villagers, system for villagers, especially in the isolated especially in the isolated areas.areas.

Capacity: 20 Capacity: 20 –– 50 50 WpWpUse for lighting and TVUse for lighting and TV

Page 11: Update on Current Development of Power Sector in Lao PDR · Power Sector Policy Maintain and expand affordable, reliable and sustainable supply electricity to promote economic and

1111

GOL aims to electrify 90% of GOL aims to electrify 90% of households by 2020.households by 2020.GOL aims to electrify 70% of GOL aims to electrify 70% of household by 2010.household by 2010.

4. GOVERMENT TARGET4. GOVERMENT TARGET

Page 12: Update on Current Development of Power Sector in Lao PDR · Power Sector Policy Maintain and expand affordable, reliable and sustainable supply electricity to promote economic and

1212

5. POLICY AND PLANNING5. POLICY AND PLANNING

Page 13: Update on Current Development of Power Sector in Lao PDR · Power Sector Policy Maintain and expand affordable, reliable and sustainable supply electricity to promote economic and

1313

Power Sector PolicyPower Sector PolicyMaintain and expand affordable, reliable and Maintain and expand affordable, reliable and sustainable supply electricity to promote sustainable supply electricity to promote economic and social developmenteconomic and social developmentPromote power generation for export to provide Promote power generation for export to provide revenues to meet GOL development objectivesrevenues to meet GOL development objectivesDevelop and enhance the legal and regulatory Develop and enhance the legal and regulatory framework to effectively direct and facilitate framework to effectively direct and facilitate power sector developmentpower sector developmentStrengthen institutions and institutional Strengthen institutions and institutional structures and enhance the commercial function structures and enhance the commercial function and streamline administration and streamline administration

Page 14: Update on Current Development of Power Sector in Lao PDR · Power Sector Policy Maintain and expand affordable, reliable and sustainable supply electricity to promote economic and

1414

Objectives of the power Objectives of the power development policydevelopment policy

Provide a source of foreign exchange to Provide a source of foreign exchange to fund economic and social development fund economic and social development and alleviate poverty;and alleviate poverty;

Meet the commitments specified in Meet the commitments specified in intergovernmental intergovernmental MOUsMOUs with Thailand, with Thailand, Vietnam and Cambodia;Vietnam and Cambodia;

Expand the customer base through grid Expand the customer base through grid extensions and satisfy growth in extensions and satisfy growth in domestic demand;domestic demand;

Page 15: Update on Current Development of Power Sector in Lao PDR · Power Sector Policy Maintain and expand affordable, reliable and sustainable supply electricity to promote economic and

1515

Objectives of the power Objectives of the power development policy (development policy (ConCon’’tt))

Explore and exploit mutually beneficial cross Explore and exploit mutually beneficial cross border exchanges of electricity with neighbouring border exchanges of electricity with neighbouring countries of the subcountries of the sub--region.region.

Extend offExtend off--grid rural electrification to promote grid rural electrification to promote better sociobetter socio--economic conditions within isolated economic conditions within isolated communities.communities.

Tariff policy support the move to cost recovery Tariff policy support the move to cost recovery pricing over a period of time. Transparency and pricing over a period of time. Transparency and predictability in electricity pricing will assist predictability in electricity pricing will assist present and potential developers and lenders in present and potential developers and lenders in making informed decisions about electricity making informed decisions about electricity investment. investment.

Page 16: Update on Current Development of Power Sector in Lao PDR · Power Sector Policy Maintain and expand affordable, reliable and sustainable supply electricity to promote economic and

1616

DOMESTIC SUPPLY BALANCE

-

1,000

2,000

3,000

4,000

5,000

6,000

2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020

(GW

h)

EDL Import from:Purchased from IPPs: Purchased from SPPs:

Page 17: Update on Current Development of Power Sector in Lao PDR · Power Sector Policy Maintain and expand affordable, reliable and sustainable supply electricity to promote economic and

1717

ELECTRICITY DEMAND FORECASTELECTRICITY DEMAND FORECAST

Page 18: Update on Current Development of Power Sector in Lao PDR · Power Sector Policy Maintain and expand affordable, reliable and sustainable supply electricity to promote economic and

1818

1

Domestic Generation Domestic Generation 20062006ŒŒ20202020

1. Xeset 2 (76MW/ 309 GWh),

2. Viengphoukha Lignite Power Plant (50 MW/225 GWh)

3. Nam Sim 7.8 MW/34 GWh,

4. Nam Beng (20MW/67 GWh),

5. Nam Theun 2 off take (75 MW/275 GWh

6. Nam Lik1/2 100 MW/347GWh

7. Xepone 3 (75 MW/301 GWh)

8. Nam Ngiep 1 offtake 16 MW/200 GWh

9. Nam Bak 2B 116 MW/ 563 GWh

10. Houay Lamphan Ngai 60MW/ 354 GWh

11. Xekatam 60MW/210 GWh

12. Nam Long 11MW/ 53 GWh

13. Nam Pot 20 MW/105 GWh

14. Nam Ngum 4 (54 MW/267Gwh)

15. Nam Pot (20 MW/105 GWh)

16. Nam Sane 3 (30 MW/285 GWh)

17. Xeset 3 (20 MW/69 GWh)

234

5

7

6

Page 19: Update on Current Development of Power Sector in Lao PDR · Power Sector Policy Maintain and expand affordable, reliable and sustainable supply electricity to promote economic and

1919

EXISTING PLANNING TOOLSEXISTING PLANNING TOOLS

SWEDNETSWEDNET-- EDL is used for rural EDL is used for rural electrification planning in early 90electrification planning in early 90’’s s and;and;CYMDISKCYMDISK-- is a software that also is a software that also using in EDL planning and system using in EDL planning and system analysis. analysis.

Page 20: Update on Current Development of Power Sector in Lao PDR · Power Sector Policy Maintain and expand affordable, reliable and sustainable supply electricity to promote economic and

2020

1

Plan up to 2020Plan up to 2020

2

À§¡º¤ 5

Houay Ho

Theun-Hinboun 1. Nam Theun 2- Savannakhet (Lao-Thai border) and Nam Theun 2- Hatinh (Lao-Viet Nam border) 2. Nam Ngum ( Ban Nabong) to Lao-Thai border 3.Hongsa Lignite to Maemo (Lao-Thai border )4. SekongBasin (Ban Sok or Pa Am) to Plekeu5.Sekong Basin to Savannakhet

6.Nam Ngum Basin (Nabong)-NamTheun 27.Xienghoung ( China)-Bangkok(Thailand)

NamTheun2

À§¡º¤ 4À§¡½Ï¾− 1

À§ È̄¼−ŒÀ§−Õ− ɺ¨

−ÕÀêó− 1

−Õ¤ˆ´ 3

−Õ¤ˆ´ 2 −Õ¤¼® 1−Õ´É

−Õê¾ 1

−Õºø 8

2009

2009

2010

2012

2012

2012

2020

¹ö¤¦¾ìó¡Ä−

Nabong500/230 kV

Savannakhet

Transmission line Transmission line

Page 21: Update on Current Development of Power Sector in Lao PDR · Power Sector Policy Maintain and expand affordable, reliable and sustainable supply electricity to promote economic and

2121

6.6. CONCLUSSIONCONCLUSSION

There is needed an appropriated tool There is needed an appropriated tool for RE planning, in order to provide for RE planning, in order to provide various options to the decision various options to the decision makers and the Government;makers and the Government;Capacity building essentially need for Capacity building essentially need for both at central level and local level of both at central level and local level of Government officer as planner and Government officer as planner and utility, such as EDL.utility, such as EDL.

Page 22: Update on Current Development of Power Sector in Lao PDR · Power Sector Policy Maintain and expand affordable, reliable and sustainable supply electricity to promote economic and

2222

TourismTourism1. Eco-tourism2. Culture-Tourism3. Agro-Tourism

Page 23: Update on Current Development of Power Sector in Lao PDR · Power Sector Policy Maintain and expand affordable, reliable and sustainable supply electricity to promote economic and

2323

EcoEco--tourismtourism•Clean air•Beautiful landscape•Attractive for health-improving purposes

Page 24: Update on Current Development of Power Sector in Lao PDR · Power Sector Policy Maintain and expand affordable, reliable and sustainable supply electricity to promote economic and

2424

CultureCulture--tourismtourism

• Rich in well-preserved culture and traditions

• World heritage sites

Page 25: Update on Current Development of Power Sector in Lao PDR · Power Sector Policy Maintain and expand affordable, reliable and sustainable supply electricity to promote economic and