UPCOMING DESIGN & CONSTRUCTION PROJECTS4th Quarter 2018

(Project & Construction Management)

Page 2: UPCOMING DESIGN & CONSTRUCTION PROJECTS 4th Quarter …

DESIGN PHASE PROJECTS

Page 3: UPCOMING DESIGN & CONSTRUCTION PROJECTS 4th Quarter …

BCT - Building Program Development and Design for Maintenance and Administration Buildings Complex

Development of a building program for the future Administration and Maintenance Buildings Complex at Barbours Cut Terminal.

Design Time Frame NIGP Codes Small Business Opportunities

PHA Contact

1st Qtr. 2019 – 2nd Qtr. 2019 Consultants962589071492533

Contractors90924 9143890976 9145091316 914689136091430

• Utility Systems• Electrical Work• Plumbing• HVAC• Building Fixtures & Finishes • Photography

Jessica [email protected]

EXISTING ADMIN BUILDING

EXISTING M&R BUILDING

Page 4: UPCOMING DESIGN & CONSTRUCTION PROJECTS 4th Quarter …

Portwide - FICAP Marine Assets - Corrosion

As part of the broad asset management program, a specific Corrosion Management (CM) program has been started to supplement the asset management information provided by the Structural (wharves) FICAP; the corrosion management program will provide a more complete indication of the corrosion-related condition, degradation rate and remaining service life.

Design Time Frame NIGP Codes Small Business Opportunities

PHA Contact

1st Qtr. 2019 – 4th Qtr. 2019 Consultants9252192568

Contractors • Engineering Consultants Bill Aguirre [email protected]

Page 5: UPCOMING DESIGN & CONSTRUCTION PROJECTS 4th Quarter …

Portwide - FICAP Utilities - Electrical and Communications

As part of the broad asset management program currently developed by the Port Authority, a specific electrical distribution and communications program has been conceptualized to document and evaluate the condition of all electrical and communications assets. The program will include the development of a facility inspection and condition assessment program (FICAP) manuals for electrical and communication assets

Design Time Frame NIGP Codes Small Business Opportunities

PHA Contact

1st Qtr. 2019 – 4th Qtr. 2019 Consultants9253192578

Contractors • Engineering Consultants Bill Aguirre [email protected]

Page 6: UPCOMING DESIGN & CONSTRUCTION PROJECTS 4th Quarter …

CONSTRUCTION PHASE PROJECTS

Page 7: UPCOMING DESIGN & CONSTRUCTION PROJECTS 4th Quarter …

Barbours Cut - Expansion of Gate Facilities

This design objective is to increase the gate capacity to handle anticipated future growth at this terminal.

Construction Time Frame NIGP Codes Small Business Opportunities PHA Contact

4th Quarter 2019 90976 9143891316 28500 91430 91461

• Site Preparation• Demolition• Earthwork

Rohit Saxena [email protected]

Page 8: UPCOMING DESIGN & CONSTRUCTION PROJECTS 4th Quarter …

Rehabilitation of Wharf 3 and Electrical and Communications Infrastructure Through C4, C5 and C6 at Barbours Cut Terminal

The wharf will be upgraded in order to support 100 feet gauge dock cranes and to accommodate larger ships. This project consists of the upgrade of 1000 feet of wharf, a new stevedore support building, structural elements, high mast pole lighting, and electrical infrastructure required to power three new dock cranes. It also includes the construction of 3,600 feet of concrete duct bank for power and communications

Construction Time Frame NIGP Codes Small Business Opportunities PHA Contact

1st Qtr. 2019 – 3rd Qtr. 2020 90976 91430 91438 9147990976 91223 91485 90924

• Material Testing• Surveying • Storm Water Controls• Photography• Chain Link Fence• Security• Electrical• Signs and Paint Striping

Bill Aguirre [email protected]

Page 9: UPCOMING DESIGN & CONSTRUCTION PROJECTS 4th Quarter …

BCT - Rehabilitation of Container Yard C1N and C2N

The scope of work includes the construction of approximately 20 acres of concrete pavement for storage of containers as well as traffic lanes to maintain circulation into and around storage areas.

Construction Time Frame NIGP Codes Small Business Opportunities PHA Contact

1st Qtr. 2019 – 2nd Qtr. 2020 91360 9132790976

• Demolition• Concrete• Grading • Excavation

Don [email protected]

Page 10: UPCOMING DESIGN & CONSTRUCTION PROJECTS 4th Quarter …

Bayport and Barbours Cut - Annual Pavement Replacement 2019

This is a one year contract concrete and asphaltic replacement at two Terminals, Barbours Cut and Bayport. The work will consist of removing damaged and or deteriorating pavement in 2019.

Construction Time Frame NIGP Codes Small Business Opportunities PHA Contact

1st Qtr. 2019 - 4th. Qtr. 2019 91327 • Concrete placement• Saw-cutting• Excavation• Concrete Traffic Barriers

Barbara H. Smith [email protected]

Page 11: UPCOMING DESIGN & CONSTRUCTION PROJECTS 4th Quarter …

Bayport and Barbours Cut - Annual Wharf Crane & RTG Crane Painting - 2019

This project will consist of blasting, priming and painting the wharf cranes and RTG cranes on an "as needed" basis.

Construction Time Frame NIGP Codes Small Business Opportunities PHA Contact

1st Qtr. 2019 - 4th. Qtr. 2019 914849146192900

• Photography• Fuel Supplier• Portable Toilets

Don [email protected]

Page 12: UPCOMING DESIGN & CONSTRUCTION PROJECTS 4th Quarter …

Barbours Cut and Bayport - Annual Fender System Maintenance - 2019

This project includes surface preparation, repair and replacement of various fender system elements at Barbours Cut and Bayport Terminals in 2019.

Construction Time Frame NIGP Codes Small Business Opportunities PHA Contact

1st Qtr. 2019 - 4th Qtr. 2019 91223 • Metal Fabrication• Storm Water Controls• Photography

Barbara H. Smith [email protected]

Page 13: UPCOMING DESIGN & CONSTRUCTION PROJECTS 4th Quarter …

Bayport - Remodel Gate Services Building for USDA

Remodel approximately 1345 SF of the existing Gate Services Building (GSB) at Bayport Container Terminal to be utilized by the USDA as an inspection laboratory. The project includes enclosing the roof overhang around the building to create a larger than existing tenant space. It also includes the installation of laboratory equipment, office space, a communications equipment room,additional HVAC and associated items.

Construction Time Frame NIGP Codes Small Business Opportunities PHA Contact

1st Qtr. 2019 - 3rd Qtr. 2019 9092491461914479143891450

• Painting• Roofing• Drywall Installers• Electrical Controls

Bill Aguirre [email protected]

Page 14: UPCOMING DESIGN & CONSTRUCTION PROJECTS 4th Quarter …

Bayport - Fire Boat Dock at Bayport West End

This project will consist of the construction of a treated wooden boat dock, utilities building, and gravel roadway with utilities connecting to adjacentcontainer yard.

Construction Time Frame NIGP Codes Small Business Opportunities PHA Contact

1st Qtr. 2019 – 2nd Qtr. 2019 9097691360, 91316236220

• Earthwork• Water and Sewer Line/Power

and Communication Line• Commercial Building

Construction

Don [email protected]

Page 15: UPCOMING DESIGN & CONSTRUCTION PROJECTS 4th Quarter …

Bayport - Rehabilitation of Wharf 5

Structural concrete repair and upgrade.

Construction Time Frame NIGP Codes Small Business Opportunities PHA Contact

3rd Qtr. 2019 - 3rd Qtr. 2020 9148491223914389097691430

• Structural Concrete Repair• Pile Driving• Steel Rebar• Concrete forming• Striping• Photography

Eddy Kharrazi [email protected]

Page 16: UPCOMING DESIGN & CONSTRUCTION PROJECTS 4th Quarter …

Bayport - Construct Electrical and Telecommunication Infrastructure under Port Road and ExxonMobil Corridor

Install 600 LF Electrical Duct Bank under Port Road

Construction Time Frame NIGP Codes Small Business Opportunities PHA Contact

2nd Qtr. 2019 – 2nd Qtr. 2020 238910237130423610

• Site Preparation• Power and Communication

Line Construction• Electrical Apparatus and

Equipment

Barbara H. Smith [email protected]

Page 17: UPCOMING DESIGN & CONSTRUCTION PROJECTS 4th Quarter …

Bayport - 138Kv Substation Security

The project includes the installation of five surveillance cameras, 300 feet of new fencing, underground conduits, two poles, two manual gates and access control equipment for doors.

Construction Time Frame NIGP Codes Small Business Opportunities PHA Contact

1st Qtr. 2019 – 2nd Qtr. 2019 990509902292037287558388391484

• Surveillance cameras• Network Switches• UPS• Card access• Fencing

Bill Aguirre [email protected]

Page 18: UPCOMING DESIGN & CONSTRUCTION PROJECTS 4th Quarter …

Install Fender System at Wharf Nos. 1 & 2 at CARE Terminal

Project will remove the existing fenders and install new fenders at Wharf 1 & 2 at the CARE Terminal.

Construction Time Frame NIGP Codes Small Business Opportunities PHA Contact

2nd Qtr. 2019 – 3rd Qtr. 2019 914849122391438

• Fender Replacement• Pile Diving

Jessica [email protected]

Page 19: UPCOMING DESIGN & CONSTRUCTION PROJECTS 4th Quarter …

Industrial Park East - Annual Pavement, Drainage and Dust Control 2019

Dust Suppression, road patching and paving

Construction Time Frame NIGP Codes Small Business Opportunities PHA Contact

1st Qtr. 2019 - 4th Qtr. 2019 237310238910

• Highway, Street, Bridge Construction

• Site Clearing

Don [email protected]

Page 20: UPCOMING DESIGN & CONSTRUCTION PROJECTS 4th Quarter …

Relocation of Communications Infrastructure Along Peninsula Boulevard

Harris County is developing a project to expand, repave and provide drainage improvements along Peninsula boulevard between the JacintoPort and Care Terminals. As a result it is necessary to relocate existing storm sewers, outfalls and inlets; some of their relocated utilities are in conflict with existing PHA's manholes, duct banks and conduits carrying fiber optics cables for communications among terminals. This project identifies such conflicts and relocates PHA's infrastructure in conflict with the Harris county project.

Construction Time Frame NIGP Codes Small Business Opportunities PHA Contact

1st Qtr. 2019 – 3rd Qtr. 2019 913167252321018

• Concrete work• Fiber Optics Cables• Directional Boring• HDPE Conduit

Bill Aguirre [email protected]

Page 21: UPCOMING DESIGN & CONSTRUCTION PROJECTS 4th Quarter …

Manchester - Rehabilitation and Repair of Wharf 2

Structural concrete repair, fender replacement, pile replacement, and geotechnical rehabilitation.

Construction Time Frame NIGP Codes Small Business Opportunities PHA Contact

2nd Qtr. 2019 – 2nd Qtr. 2020 9148491223914389097691430

• Structural Concrete Repair• Fender Replacement• Pile Driving• Steel Rebar• Concrete forming• Striping• Photography

Eddy Kharrazi [email protected]

Page 22: UPCOMING DESIGN & CONSTRUCTION PROJECTS 4th Quarter …

Drainage System at Volkswagen Yard at Turning Basin Terminal

Improvement of existing drainage system tied to IH-610 feeder road at the Volkswagen yard at the Turning Basin terminal.Project 1: TxDot construction of drainage improvements to the 610 feeder road. (Procured by TxDot)Project 2: PHA construction of drainage improvements to the Volkswagen Yard.

Project 2 Construction Time Frame Project 2 NIGP Codes Project 2 Small Business Opportunities PHA Contact

1st Qtr. 2019 - 2nd Qtr. 2019 9136091223

• Storm Drainage Structures• Grading• Concrete

Barbara H. Smith [email protected]

PROJECT 2 PROJECT 1

Page 23: UPCOMING DESIGN & CONSTRUCTION PROJECTS 4th Quarter …

Turning Basin North - Splash Zone Painting 2018

Painting and preservation of splash zone area.

Construction Time Frame NIGP Codes Small Business Opportunities PHA Contact

1st Qtr. 2019 914849146191484

• Water blasting• Painting• Sandblasting

Don [email protected]

Page 24: UPCOMING DESIGN & CONSTRUCTION PROJECTS 4th Quarter …

Turning Basin - Transit Sheds 30-31 - Roof Repair

Roof removal and replacement for Transit Sheds 30/31

Construction Time Frame NIGP Codes Small Business Opportunities PHA Contact

1st Qtr. 2019 – 2nd Qtr. 2019 914739097692678

• Roofing• Site Clearing• Waste and Remediation

Don [email protected]

Page 25: UPCOMING DESIGN & CONSTRUCTION PROJECTS 4th Quarter …

Turning Basin - Bi-Annual Rail and Switch Replacement - 2019

Repairs or replaces rail and rail switches throughout the Turning Basin Terminal

Construction Time Frame NIGP Codes Small Business Opportunities PHA Contact

1st Qtr. 2019 - 4th Qtr. 2020 90976929009122392533

• Rail and Ballast• Concrete and Rebar• Rail Switches• Drainage

Barbara H. Smith [email protected]

Page 26: UPCOMING DESIGN & CONSTRUCTION PROJECTS 4th Quarter …

Turning Basin - Rehabilitation and Repair of Wharf 9

Structural concrete repair, fender replacement, and geotechnical rehabilitation.

Construction Time Frame NIGP Codes Small Business Opportunities PHA Contact

2nd Qtr. 2019 - 2nd Qtr. 2020 9148491223914389097691430

• Structural Concrete Repair• Fender Replacement• Pile Driving• Steel Rebar• Concrete forming• Striping• Photography

Eddy Kharrazi [email protected]

Page 27: UPCOMING DESIGN & CONSTRUCTION PROJECTS 4th Quarter …

Turning Basin - Annual Concrete Replacement 2019

This is a one year contract of concrete replacement at Turning Basin Terminal. The work will consist of removing damaged and or deteriorating concrete pavement in 2019.

Construction Time Frame NIGP Codes Small Business Opportunities PHA Contact

1st Qtr. 2019 - 4th Qtr. 2019 91327 • Concrete• Excavation• Saw-cutting• Concrete Traffic Barriers

Barbara H. Smith [email protected]

Page 28: UPCOMING DESIGN & CONSTRUCTION PROJECTS 4th Quarter …

Woodhouse - Water and Sewer line Replacement

This project work will consist of furnishing and installing approximately 5,000 linear feet of 6” to 8” water main and 2,000 linear feet of sewage force main and a duplex sewage pump station.

Construction Time Frame NIGP Codes Small Business Opportunities PHA Contact

4th Qtr. 2018 - 2nd. Qtr. 2019 9136091223

• Underground utilities installation

Barbara H. Smith [email protected]