Upload
others
View
1
Download
0
Embed Size (px)
Citation preview
Unlocking the Value of a
World Class Resource Base
March 2017
BMO Global Metals & Mining Conference
Denis Alexandrov, Chief Executive Officer
AIM: HGM.L
Disclaimer
Certain statements within this presentation constitute forward looking statements. Such forward looking statements involve
risks and other factors which may cause the actual results, achievements or performance of the Group to be materially
different from any future results, achievements or performance expressed or implied by such forward looking statements.
Such risks and other factors include, but are not limited to, general economic and business conditions, changes in
government regulations, currency fluctuations (including the US$/RUR rate), the gold price, the Group’s ability to recover its
reserves or develop new reserves, competition, changes in development plans and other risks.
There can be no assurance that the results and events contemplated by the forward looking statements contained in this
presentation will, in fact, occur. These forward-looking statements are correct or represent honestly held views only as at
the date of delivery of this presentation.
The Company will not undertake any obligation to release publicly any revisions to these forward looking statements to
reflect events, circumstances and unanticipated events occurring after the date of this presentation except as required by
law or by regulatory authority.
***
Total cash costs include mine site operating costs such as mining, processing, administration, royalties and production
taxes, but are exclusive of depreciation, depletion and amortisation, capital and exploration costs. Total cash costs are then
divided by ounces sold to arrive at the total cash costs of sales. This data provides additional information and is a non-
GAAP measure.
In line with guidance issued by the World Gold Council, the formula used to define all-in sustaining cash costs measure
commences with total cash costs per ounce sold and then adds sustaining capital expenditures, corporate general and
administrative costs, mine site exploration and evaluation costs and environmental rehabilitation costs. This data seeks to
represent the total costs of producing gold from current operations, and therefore it does not include capital expenditures
attributable to projects or mine expansions, exploration and evaluation costs attributable to growth projects, income tax
payments, interest costs or dividend payments.
2
3
Highland Gold at a Glance
Kekura
Klen
Belaya Gora
Mnogovershinoye
(MNV)
Baley Hub
Novoshirokinskoye
(Novo)
Blagodatnoye
Lyubov
Khabarovsk
Cluster
Chukotka
Cluster
Baikal
Cluster
Operating Mine
PFS Stage
Scoping Study
46%
54%
2016 Production
43%
15%
20%
22%
Mineral Resources
261
koz
16.4
mmoz
---
3.4 g/tUnkurtash Kyrgyzstan
US$
444
US$
609
Total Cash Costs All-In Sustaining Costs
- JORC-compliant measured, indicated & inferred resources of gold and
gold equivalent as of 31 December 2015, adjusted for Kekura PFS.
- TCC and AISC for H1 2016
4
Our Strategy: Unlocking Value
Maximize upside potential of
operating assets
Develop existing high-grade
resources in our portfolio
Focus development on
regions of presence
Maintain commitment to operating
safety and protecting the environment
MNV
1.6 mmoz
3.4 g/t
Novo
1.5 mmoz
7/6 g/t
Belaya Gora
0.8 mmoz
2.3 g/t
Kekura
2.1 mmoz
8.6 g/t
Klen
0.6 mmoz
5.0 g/t
Lyubov
0.5 mmoz
1.3 g/t
Taseevskoye
5.1 mmoz
5.1 g/t
Unkurtash
3.7 mmoz
1.7 g/t
- JORC-compliant measured, indicated & inferred resources of gold and
gold equivalent as of 31 December 2015, adjusted for Kekura PFS.
Corporate Overview
5
Listed on London AIM
Publicly-listed company since 2002
Shareholders include a broad range of major high-
quality UK and European institutional investors
Committed to Best Practice in
Corporate Governance
Led by an experienced Board of Directors and
management team
Seven directors – executive chairman, one
executive director, and five non-executive directors
Committed to Returning Capital to
Shareholders
H1 2016 interim dividend of £0.05 per share
FY 2015 total dividends - £0.045
AIM HGM.L
Shares 325,222,098
Market Cap* US$ 767m
Enterprise Value* US$ 970m
Net Debt** US$ 198m
Net Debt/EBITDA** 1.3
H1 2016 Earnings/Share US$ 0.113
* On 20 February 2017 ** On 1 July 2016
26,6%
10,0%
46,4%
17,0%
Prosperity Capital
Management
Board &
Management
Institutions
& Retail
Primerod Int’l &
Affiliated Parties
Shareholder Structure
56%
Free
Float
6
Low Cost Producer…
984 980 965 925 904 856800 770 730 725
609 572
All-In Sustaining Costs (US$)
All figures based on most recent financial data published by company. HGML data for H1 2016.
7
…With Good Operating Margins
All figures based on most recent financial data published by company. For HGML, H1 2016.
EBITDA Margin
63
5450
46 46 45 43 40 37 36 35 33
Strong 12-Month Share Performance…
8
0,0
0,5
1,0
1,5
2,0
2,5
3,0
0
20
40
60
80
100
120
140
160
180
200
Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb
Share Price
Liquidity
(Average Daily
Trading Volume)
0
50
100
150
200
250
300
350
HGM
FTSE All Share MINING
Gold Price
GB
X
mln
GB
P
…With Upside Remaining
9
183 178 176
149 148
87
56 5440 36
19
EV/Resources
All figures based on most recent resource data published by company and share price on 20 February 2017.
171142 160
29119
140
200
2010 2016 2020
2017 Production Guidance: 255-265 koz
2020 Production Target: 500 koz
– Includes only operating mines and Kekura
– Additional upside potential with Klen, Baley Hub (Taseevskoye,
Sredy Golgotay), and Unkurtash
Delivering Growth
10
BaikalNovo
ChukotkaKekura
KhabarovskMNV
Belaya Gora
Blagodatnoye
500
200
2614.4%
CAGR
Location Khabarovsk Cluster
Opened 1991 (HGM 1999)
LoM 2021
Mine Type Open pit & underground
Processing Gravity + Cyanide Leaching
Processing Capacity 1.4 mtpa
Au Production (2016) 96,188 oz
Avg Head Grade (2016) 2.35 g/t
Total Cash Costs* US$ 602
11
Mnogovershinnoye (MNV)
* H1 2016
Oldest operating mine in our portfolio
Recently extended life of mine by three years
following broad review and regulatory approval
of reserves under Russian (GKZ) classification
New JORC reserve audit currently in progress
Key Challenge: To identify additional resources
to feed the MNV mill beyond 2021
122,3
94,6 96,291,8 90,4 91,5
722691
602
2014 2015 2016
Production (koz) Recovery (%) Grade (g/t) TCC (US$)
3.04
2.29 2.36
MNV Snapshot
Unlocking Value:
Extending life of mine
Extensive near-mine exploration focused on
upgrading existing resources and targeting
additional resources to enhance life of mine for
both underground and open-pit operations
– Over 18,000m of drilling carried out on the
lower horizons of the Northern, Southern
and Central ore zones and the Upper ore
body in 2016
– 2017 drilling programme to focus on the
Southern, Flank, Upper, and Quiet ore
zones, as well as on the MNV North-
Western Flank licence (Bear ore body).
Ongoing re-evaluation of MNV's historic rock
dumps
– Identified 758.2k tonnes of ore in 2016 at
~1 g/t
– Programme continues in 2017
12
Mnogovershinnoye (MNV)
Northern
Southern
Flank
97,8105,9
117,6
84,9 86,0 85,9
428
302248
2014 2015 2016
Production (koz) Recovery (%) Grade (g/t) TCC (US$)13
Novoshirokinskoye (Novo)
13
Location Baikal Cluster
Opened 2009
LoM 2029
Mine Type Underground
Processing Gravity-flotation circuit
Processing Capacity 0.8 mtpa
Au Production (2016) 117,577 oz gold equivalent
Avg Head Grade (2016) 5.62 g/t
Total Cash Costs* US$ 248
* H1 2016
Polymetallic mine – gold, silver, lead, and zinc
Produces lead and zinc concentrates
Outside Processing Costs of 178 US$/oz*
Highest contributor to EBITDA
45% of production, 55% of EBITDA*
Key Challenge: Increase throughput to offset
expected decline in average grade
Novo Snapshot
6.20
5.58 5.62
Unlocking Value:
Expanding mine capacity
Russian-standard (GKZ) reserves re-
estimation resulted in a 77% increase in ore
volumes and 36% decrease in average grade
(to 5.13 g/t), with total gold equivalents rising
by 13% to 85.7 tonnes (2.6 mln oz)
– New JORC reserve statement in Q2
Larger ore volume at lower grades justified
boosting mill capacity from 700 ktpa to 1.3
mtpa.
Underground expansion underway in order to
gain access to new horizons
Engineering and design documentation,
preparations for construction work, and
selection of contractors all underway.
Novo is expected to achieve its new target
production capacity in late 2018, boosting Au
equivalent output by ~40%
14
Novoshirokinskoye (Novo)
Ore body outlines before reserve re-estimation
Ore body outlines after reserve re-estimation
38,8
61,3
45,9
61,775,4 71,4
926
465
613
2014 2015 2016
Production (koz) Recovery (%) Grade (g/t) TCC (US$)15
Belaya Gora
1515
Location Khabarovsk Cluster
Opened 2014
LoM 2023
Mine Type Open pit
Processing Gravity-flotation circuit
Processing Capacity 1.8 mtpa
Au Production (2016) 45,909 oz
Avg Head Grade (2016) 1.21 g/t
Total Cash Costs* US$ 613
* H1 2016
Youngest operating mine, developed fromgreenfield
Mining currently focused on stockpiles due toongoing operational reassessment
Key Challenges
– Dilution and irregular grade distribution
– Unstable mill operation and recovery
Belaya Gora Snapshot
1.58 1.641.21
Unlocking Value:
Upgrading mill to improve recovery
+ adding new resources
Successful programme to stabilise mill input rate
in 2016 resulted in lower tailings grade
Currently working with SRK on designs for adding
cyanide leach (CIL) capacity to further boost
recovery to 90% or more
3,000 metres of drilling in 2016 for reserve
confirmation and improved mine planning
A new JORC-compliant reserve statement is
expected by April
Targeted for adding resources to Belaya Gora
Preliminarily-measured С2 category reserves for
open pit mining of about 10 million tonnes of ore.
Initial metallurgical testwork supports gold
recovery of over 90% via cyanidation.
15,000 metres of drilling in 2016 to confirm
reserves
– JORC-compliant reserves statement by April16
Belaya Gora & Blagodatnoye
Belaya Gora
Blagodatnoye
MNV
30 km
Blagodatnoye
17
Kekura – a World-Class Project…
Location Chukotka Cluster
Start Date 2019
LoM 2029
Mine Type Open pit & underground
Processing Gravity + Cyanide Leaching
Processing Capacity 0.8 mtpa
Au Production (est. annual) 209,000 oz
Reserve Grade 10.73 g/t
Kekura Snapshot
1.58 1.641.21
Kekura Mineral Resources*
ClassificationTonnage
(Mt)
Au Grade
(g/t)
Metal Au
(Moz)
Indicated 7.412 8.64 2.06
Inferred 3.266 4.80 0.51
Total 10.678 7.47 2.57
Kekura Ore Reserves*
ClassificationTonnage
[Mt]
Au Grade
[g/t]
Metal Au
[Moz]
Proven - - -
Probable Open Pit 4.296 10.94 1.51
Underground 0.541 9.04 0.16
Total 4.837 10.73 1.67
* Reserves & resources compliant to JORC Code 2012. Resources cut-off grade of 1.0
g/t Au. Reserves cut-off grade of 2.2 g/t Au at the open pit and 4.2 g/t Au for the
underground mine. A gold price of US$1,150 per troy ounce has been applied.
Highland Gold’s premier development project
Licence Area: 1,497 sq km
High grade, open pit and underground mining
and favourable metallurgy to make Kekura a
low cost operation
25,000 m exploration drilling program
completed in 2016
Drilling focused on the eastern flank of the
deposit with the aim of resource confirming
and potentially adding reserves for
underground mining.
11 prospects have been identified within the
Kekura licence area as warranting further
prospecting work
18
…with Great Upside Potential
1 – Zabytiy
2 – Granat
3 – Ryzhiy
4 – Iris
5 – Bond
6 – Zakol
7 – Gonch
8 – Zapadny 2
9 – Zapadny 1
10 – Iris (detailed)
11 – Alpinist
Kekura Deposit
Western site
Central site
Eastern site
Kekura
Exploration Grid
Site Drill holes grid Reserves, %
Western 20х25m 37.7
Central 20х50m 43.3
Eastern 80х100m 19.0
Fluor Canada developing definitive feasibility study (DFS)
SRK drafting the mining section of the DFS.
The process is expected to continue in Q1 2017, during
which Fluor will consolidate the various sections of the
DFS into a single report.
Preparations for 2017 construction and installation
ongoing, including the procurement of construction
materials and working with contractors for construction of
key infrastructure facilities.
A winter road to the site has already been built, the first
shipment of diesel fuel has been delivered to site, and key
commodity supplies from Pevek and Magadan are
expected in February-March 2017.
Fluor is also involved in the process of issuing and
approving purchase orders for the main processing plant
equipment.
– Quotes have already been received for milling and
crushing equipment, power generators and press
filters.
19
Kekura Project Status
Key Project Parameters*
Unit Total
Post-Tax IRR % 38
Post-Tax NPV (5%) US$ m 357
Milling Capacity ktpa 800
Average Annual
Production (LoM)k oz 209
Capital Cost Estimate US$ m 188
Payback Period Years 3
Life of Mine Years 8
* A gold price of US$1,150 per troy ounce has been applied. Project
parameters based on 2016 PFS, without historical costs.
Three deposits in close proximity
– Taseevskoye
– Sredny Golgotay
– Baley ZIF-1 Tailings
Brownfield sites, substantially explored
Several scenarios being studied for joint
development of Baley Hub licenses
Deposit being evaluated for providing additional
resources for Novo mill or stand-alone operation
2016 pilot mining programme at the Kaftan site
– 15k tonnes of ore at 3.22 g/t for treatment at
Novo, adding 1,315 oz Au to total production
7,000m of grade control drilling on Kaftan in 2016
16,000 m and 2,000 m of trenching completed last
year to validate state-registered reserves across
the Sredny Golgotay licence
Baley ZIF-1 tailings being assessed for potential
to improve economics of Sredny Golgotay
development, including possible heap leach
20
Baley Hub Projects
Bulkhead Structure
Taseeevskoye
Sredny Golgotay
ZIF-1 Tailings
Baley Pit
Town of
Baley
ZIF-2 Tailings
2kmSource: Google
Sredny Golgotay
Baley Hub Projects
Major resources of 5.1 mmoz at 5.1 g/t
Refractory ore
Previously mined both open pit and
underground in mid-20th century
Currently de-risking the project by pumping
water out of the Taseevskoye pit and monitoring
inflow from the Baley pit.
– Three pumps are up and running, current
daily volume is 21.6k m3
– 3.3M m3 pumped out in in H2 2016 and
January 2017
– 5.7m decrease in water level
– No water inflow from Baley pit detected at
the present water levels
– De-watering programme to continue
throughout 2017
After de-watering the pit, a drilling programme
will be implemented to confirm reserves
21
Baley Open Pit Taseevskoye Open Pit
Taseevskoye
567
568
569
570
571
572
573
574
AS
L,
m
Water Level Change in Pits
Тасеевский БалейскийBaleyTaseevskoye
Jul Aug Sep Oct Nov Dec Jan
New PFS currently being developed by Hatch
Preliminary estimates show favorable
economics
Full results expected by Q2 2017
JORC-compliant resource (Indicated &
Inferred) of 0.63 Moz with 5.04 g/t average
grade, open pit
Plans initiated to draft a PFS for the project
with a revision of CAPEX and OPEX including
optimisation of processing solutions for the
proposed mill
Potential capacity of 350 ktpa at over 90%
recovery
Outside contractor for a resource verification
project in the second half of last year.
4,200 m3 of trenching and 96 metres of
exploratory drilling
A total of 5,680 tonnes of ore mined and
treated, yielding 170 oz of gold.
63 km² licence zone with four distinct
prospects, three of which – Unkurtash,
Sarytube and Karatube – have been the focus
of extensive exploration activity
JORC compliant resource audit in 2013
defines combined 3.7 Moz at ore grade of 1.7
g/t (82% Measured and Indicated) for the three
prospects
Scoping study underway by SRK with
completion expected in Q1 2017
22
Development Pipeline
Klen Unkurtash
LyubovUnkurtash
Sarytube
Karatube
Baikonur0 1000 m
0
20
40
60
80
100
120
2014 2015 2016 2017
MNV
Belaya Gora
Novo
Kekura
Other
23
Capital Expenditure
2017 capex to be funded largely through cash flow
Low-cost debt available for additional funding
Debt Status
Total debt decreased by US$ 38 m
in H1 2016
Effective interest rate as of
01.07.2016 – 5.1% p.a.
(was 5.43% on 01.01.2016)
Average tenor – 23 months.
45%
34%
21%Novo; $97,5m
Belaya Gora; $72m
MNV; $46m55%
23%
16%
6%
Gazprombank; $118m
UniCredit; $50m
Alfa bank; $35m
Sberbank; $12,5m
303
254
216247
229198
0
100
200
300
01.01.2015 01.01.2016 01.07.2016
Net Debt / EBITDA ratio = 1.3
as of 01.07.2016
Debt by Division Debt by Lender
Gross Debt (m US$) Net Debt
24
Commitment to Dividends
25
0,0%
1,0%
2,0%
3,0%
4,0%
5,0%
6,0%
7,0%
8,0%
9,0%
0
1
2
3
4
5
6
7
8
9
2011 2012 2013 2014 2015 H1 2016
GB
X
Dividend per share (pence) Yield (%)
PFS
MNV
Novo
Belaya Gora
Blagodatnoye
26
Upcoming Milestones for 2017
Updated JORC Reserves
Unkurtash
Baley Hub
Scoping Study
MNV
Novo
Belaya Gora + Blagodatnoye
Kekura
DFS
27
The Highland Gold Investment Case
Upside Potential in Existing
Operating Assets
Growth Potential in High
Grade Deposits
Development Strategy
Focused on Regional Hubs
Disciplined Capital
Allocation
Unlocking the
Value of
Highland Gold’s
Resource Base
Commitment to Dividend
0Thank You
[email protected]+7 495 424-95-21