8/10/2019 Unit II Cocomo
1/24
UNIT-II
COCOMO
8/10/2019 Unit II Cocomo
2/24
BACKGROUND
COCOMO (COnstructive COst estimation MOdel) considers the
size of the software and several other characteristics of the
proposed software. Dr Berry Boehm in 1981 proposed this
approach when software engineers started using OOD,
automated tools for code generation, testing and so on.
A series of mathematical formulae are used to predict effort
base on software size and other factors such as maturity of
process and capability of development team, risk etc.
COCOMO considers the software product attributes, platform
attributes, development team attributes and project
management attributes and weighs them suitably to improve
the estimation.
8/10/2019 Unit II Cocomo
3/24
BACKGROUND
According to Boehm any software project can be classified into
any of the three categories based upon the development
complexity.
Organic: If the project is deals with developing a well-understoodapplication program, the size of the development team is reasonably
small, and the team members are experienced in developing similar
types of projects.
Semidetached: A development project can be considered to be of
semidetached type, if the development team consists of a mixture ofexperienced and inexperienced staff. Team members may have limited
experience on related systems by may be unfamiliar with some aspects
of the system being developed.
Embedded: A development project is considered to be of embeddedtype, if the software being developed is strongly coupled to complex
8/10/2019 Unit II Cocomo
4/24
STAGES
According to Boehm, Software cost estimation should be done
through three stages:
Basic COCOMO Intermediate COCOMO
Complete COCOMO.
8/10/2019 Unit II Cocomo
5/24
BASIC COCOMO
The Basic COCOMO model gives an approximate estimate of the
project parameters. The basic COCOMO estimation model is
given by the following expressions:
Effort= a1 X (KLOC)a2
PM
Tdev= b1 X (Effort)b2Months
Where:
a) KLOC is the estimated size of the software product expressed in Kilo
Lines of code.b) a1,a2,b1,b2 are constants for each category of software products.
c) Tdev is the estimated time to develop the software, expressed in
months,
d)
Effort is the total effort required to develop the software product,expressed in person months.
E ti ti f d l t
8/10/2019 Unit II Cocomo
6/24
-Estimation of developmenteffort
- Estimation of development
timeFor the three classes of software products, the formulas forestimating the effort based on the code size are shown below:
Organic: Effort: 2.4(KLOC)1.05
PM
Semidetached Effort: 2.4(KLOC)1.12
PM
Embedded Effort: 2.4(KLOC)1.20
PM
For the three classes of software products, the formulas for
estimating the development time based on the effort are given
below:
Organic: Tdev= 2.5 (Effort)0.38Months
Semidetached: Tdev= 2.5 (Effort)0.35
Months
Embedded: Tdev= 2.5 (Effort)0.32
Months
8/10/2019 Unit II Cocomo
7/24
BASIC COCOMO Example
Assume that the size of an organic type software product has
been estimated to be 32,000 lines of source code. Assume that
the average salary of software developers is 15,000 per month.
Determine the effort required to develop the software product, the
nominal development time, and the cost to develop the product.
From the basic COCOMO estimation formula for organic software:
Effort = 2.4 X (32)
1.05
PM = 91 Person monthNominal development time = 2.5 X (91) 0.38= 14 months
Cost required to develop the product = 91 X 15,000 = 1,465,000
8/10/2019 Unit II Cocomo
8/24
INTERMEDIATE COCOMO
The basic COCOMO model assumes that effort and development
time are functions of the product size alone. But beside size
some other project parameters is required to develop the product
as well as the development time.
In order to obtain an accurate estimation of the effort and project
duration, the effect of all relevant parameters must be taken into
account. The intermediate COCOMO model recognizes this fact
and refines the initial estimate obtained using the basic
COCOMO expressions by using a set of 15 cost drivers based onvarious attributes of software development.
8/10/2019 Unit II Cocomo
9/24
INTERMEDIATE COCOMO
Ratings upon the 15 cost drivers are asked from project managers
on a scale of one to three. Depending on these ratings,
appropriate cost driver values which should be multiplied with the
initial estimate obtained using the basic COCOMO. The cost
drivers can be classified as being attributes of the following items:
Product:
Computer:Personnel:
Development environment:
8/10/2019 Unit II Cocomo
10/24
INTERMEDIATE COCOMO
The Intermediate COCOMO formula now takes the form:
Effort=ai(KLoC)(b
i).EAF
Where E is the effort applied in person-months, KLOCis the
estimated number of thousands of delivered lines of code for the
project, and EAFis the factor calculated above. The value of ai
and bi are given in the next table.
The Development time calculation uses Effortin the same way as
in the Basic COCOMO.
Software project ai bi
Organic 3.2 1.05
Semi-detached 3.0 1.12
Embedded 2.8 1.20
8/10/2019 Unit II Cocomo
11/24
COMPLETE COCOMO
A major shortcoming of both the basic and the intermediate
COCOMO models is that they consider a software product as a
single homogeneous entity. Most of the times large systems are
made up of several smaller subsystems.
The complete COCOMO model considers these differences in
characteristics of the subsystems and estimates the effort and
development time as the sum of the estimates for the individual
subsystems. The cost of each subsystem is estimated separately.
This approach reduces the margin of error in the final estimate.
8/10/2019 Unit II Cocomo
12/24
COMPLETE COCOMO
In case of a Distributed Management Information System product
for an organization having offices at several places across the
country can have the following sub components:
Database Part
Graphical User Interface Part
Communication Part
The communication part can be considered as embeddedsoftware. The database part could be semidetached software,
and the GUI part can be considered as Organic Software. The
costs for these three components can be estimated separately,
and summed up to give the overall cost of the system.
8/10/2019 Unit II Cocomo
13/24
COCOMO - II
The latest version of COCOMO model is COCOMO-II, released in
1997. This model has three estimation model to estimate effort
and cost. The models are:
Application Suite Model/Application Composition Model:
This model as the name suggests, can be used to estimate cost
for prototyping, e.g. to resolve user interface issues.
Early Design Model: This supports estimates of cost at the
architectural design stage.
Post Architectural Model/ Final Design Architectural Model:
This provides cost estimation during detailed design and coding
stage. The post architectural model can be considered as an
update of the original COCOMO.
8/10/2019 Unit II Cocomo
14/24
uModel/Application Composition
ModelThe Application composition model is based on counting the
number of screens, reports and 3GL modules. Each of these
components is considered to be an object.
Effort is estimated in the application composition model as follows:
1) Estimate the number of screens, reports and 3GL components from an
analysis of the SRS document.
2) Determine the complexity level of each screen and report and rate these as
either simple, medium or difficult.
Screen Complexity table:Number of views Tables
8/10/2019 Unit II Cocomo
15/24
uModel/Application Composition
Model3. Determine the number of object points
4. Estimate percentage of reuse expected in the system. Then
evaluate new object point.
5. Determine a productivity rate, PROD=NOP/person-month. Theproductivity depends on the experience of the developers as
well as the maturity of the CASE environment used.
Developers
experience
Very low Low Nominal High Very high
CASE
maturity
Very low Low Nominal High Very high
PROD 4 7 13 25 50
8/10/2019 Unit II Cocomo
16/24
uModel/Application Composition
ModelThe object points count needs modification by way of reduction as
the software may use reusable components and libraries.
Therefore:
Revised Object Point (ROP)=Object Point X
For this ROP, the effort in man month is computed using a
productivity constant, based on the software developmentteams experience and capability. COCOMO-II prescribes
productivity constant expressed as the number of object points
per man month as shown in previous table.
=
8/10/2019 Unit II Cocomo
17/24
uModel/Application Composition
ModelFor example, object points, say are 40 and the re-use possibility is
10%, then
ROP= = 40 X 0.90 = 36
Further, if the development teamsexperience and maturity is at
level normal, then productivity constant is 13. hence
MME= 36/13 = 3 Man Months
8/10/2019 Unit II Cocomo
18/24
Early Design Model
The COCOMO uses the base equation:
MME = A X (size)B
Where:MME = Man month effort
A = constant representing nominal productivity
B = factor indicating economies/diseconimies of scale. B is known
as scaling factor.Size = KLOC.
8/10/2019 Unit II Cocomo
19/24
Early Design Model
The emphasis in the COCOMO-II model is on scaling factors,
which together give rise to B. The model uses five factors for
arriving at economies/diseconimies in scale, namely
precedentness, development flexibility, risk resolution, team
cohesion and organization process maturity.
B is the value of scaling factor is computed as below:
B = 0.91 + 0.01( Ratings)
The rating for each of the five factors is based on the
organization's level on each of these factors.
8/10/2019 Unit II Cocomo
20/24
Early Design Model
Factor Code Very low Low Nominal High Factor Name
PREC 6.20 4.96 3.72 2.48 Precedentness
FLEX 5.07 4.05 3.04 2.03 Flexibility
RESL 7.07 5.65 4.24 2.83 Risk Resolution
TEAM 5.48 4.38 3.29 2.19 Team CohesionPMAT 7.80 6.24 4.68 3.12 Process Maturity
Let us assume that in a given software development scenario, the
organization's level on these factors is very low.
Then B= 0.91 + 0.01 X(6.20 +5.07+7.07+5.48+7.80) = 1.2262
A=13, size=10 KLOC, then MME=13 X (10)1.2262person month.
8/10/2019 Unit II Cocomo
21/24
Post Architectural Model
In addition to the 5 factors that affect development efforts, some
factors have a large impact on MME. In Post Architectural
Model the MME(Modified) is calculated based upon 16 more
factors which are significant.
MME(Modified) = MME X (Product of ratings of 16 factors)
8/10/2019 Unit II Cocomo
22/24
Post Architectural Model
Code Name Very
low
Low Nomina
l
High
Product Factors
RELY Software Reliability 0.82 0.92 1.00 1.10
DATA Database Size 0.80 0.90 1.00 1.14
CPLX Software Complexity 0.73 0.87 1.00 1.17
RUSE Required Reusability 0.85 0.95 1.00 1.07
DOC
U
Documentation 0.81 0.91 1.00 1.11
Platform Factors
TIME Time constraint on execution NRA NRA 1.00 1.11
STPR Main storage constraint NRA NRA 1.00 1.05
PVOL PLATFORM VOLATILITY NRA NRA 1.00 1.15
8/10/2019 Unit II Cocomo
23/24
Post Architectural Model
Code Name Very
low
Low Nomina
l
High
Personnel Factors
ACAP Analyst capability 1.42 1.19 1.00 0.85
PCAP Programmer capability 1.34 1.15 1.00 0.88
AEXP Analyst experience 1.22 1.10 1.00 0.88
PEXP Programmer experience 1.19 1.09 1.00 0.91
LTXP Language and tool experience 1.20 1.09 1.00 0.91
PCON
Personnel Continuity 1.29 1.12 1.00 0.90
Project Factors
TOOL Use of software tools 1.17 1.09 1.00 0.90
SITE Site environment 1.22 1.09 1.00 0.93
8/10/2019 Unit II Cocomo
24/24
Post Architectural Model
Suppose we have to calculate the MME(Modified) in a post architectural
scenario according to the previous example where the size is 10 KLOC.
Let us evaluate tow possibilities of an extreme nature. One assumption is that
the organization scores very low on all architectural factors, and the second
possibility is that the organization scores high on all factors.
Possibility 1: (All ratings are very low)
Product of ratings of 16 factors = 2.01
Possibility 2: (All ratings are high)Product of ratings of 16 factors = 0.98
MME 1 = 220 X 2.01 = 442 Man Months
MME 2 = 142 X 0.98 = 139 Man Months