UNAA_ED's Presentation on the NDP

Embed Size (px)

Citation preview

  • 8/3/2019 UNAA_ED's Presentation on the NDP

    1/55

    NATIONAL PLANNING

    AUTHORITYPRESENTATION ON UGANDAS NATIONALDEVELOPMENT PLAN (NDP) 2010/11-2014/15

    By

    LONGINO TISASIRANA

    EXECUTIVE DIRECTOR, NPA

  • 8/3/2019 UNAA_ED's Presentation on the NDP

    2/55

    OUTLINE OF THE PRESENTATION

    Introduction

    Why NDP?

    The NDP formulation process

    The NDP conceptual framework

    The NDP synopsis NDP themes and objective

    NDP Thrust Binding Constraints

    Priority Investment areas

    National Core Projects (flagships)

  • 8/3/2019 UNAA_ED's Presentation on the NDP

    3/55

    INTRODUCTION

    The NDP was launched on 19th April, 2010 by H.E ThePresident

    The NDP is a costed plan that provides strategic directionfor Ugandas development for the five years spanningfrom FY 2010/11-2014/15

    3

  • 8/3/2019 UNAA_ED's Presentation on the NDP

    4/55

    INTRODUCTION CONTS...

    The plan stipulates the medium termdevelopment goals and strategic objectives

    It also identifies priority interventions includingpriority investment programmes and projects forstrategic intervention by: Government

    Private sector

    Civil society

    5/1/2012 4

  • 8/3/2019 UNAA_ED's Presentation on the NDP

    5/55

    Why NDP?

    1. Proliferation of several development strategiessuch as PMA, NAADS, PFA, PRDP, electionManifestos during the later years of the PEAP.

    Thus the need to integrate emerging strategiesinto a single policy framework

    The NDP will be Ugandas only strategicframework guiding development during the

    period of its implementation (FY 2010/11-2014/15)

    5/1/2012 5

  • 8/3/2019 UNAA_ED's Presentation on the NDP

    6/55

    Why NDP?

    2. The high growth rates recorded during PEAPperiod did not result into significant socio-economic transformation.

    A number of structural challenges persistedwhich include:

    Dominance of primary products over industrial andmanufactured products

    Slow growth than desirable in agricultural and industrialsectors

    5/1/2012 6

  • 8/3/2019 UNAA_ED's Presentation on the NDP

    7/55

    Primary Products

    5/1/2012 7

  • 8/3/2019 UNAA_ED's Presentation on the NDP

    8/55

    Selling primary products5/1/2012 8

  • 8/3/2019 UNAA_ED's Presentation on the NDP

    9/55

    Why NDP?

    New sectors not absorbing rapidly growing labour force

    Capital market not effectively intermediating capital (High cost offinance)

    Slow accumulation of economic infrastructure

    The NDP would therefore accelerate socio-economictransformation.

    5/1/2012 9

  • 8/3/2019 UNAA_ED's Presentation on the NDP

    10/55

    Why NDP?

    3. New developments in the global, regional and nationaleconomies raised a number of challenges andopportunities. They include;

    The Global economic crisis (2007-2009)

    Regional integration ( EAC CU, CM and politicalfederation)

    At the national scene, return to multiparty system, oildiscovery and deepening of decentralisation etc.

    The plan offers a concerted, holistic comprehensive andsystematic approach to global, regional and nationalchallenges and opportunities.

    5/1/2012 10

  • 8/3/2019 UNAA_ED's Presentation on the NDP

    11/55

    Why NDP?

    The Cabinet in 2007 adopted the overallplanning framework linking the short termpriorities to medium and long term goals andobjectives.

    The framework provides for the following: 30 year National Vision 10 year Outline Perspective Plan 5 year NDP 2 year mid term review

    Annual plans & budgetsThe NDP is a medium term strategy thatoperationalises the national visioning framework.

    5/1/2012 11

  • 8/3/2019 UNAA_ED's Presentation on the NDP

    12/55

    NDP formulation process

    Formed Core Technical Committee (CTC)

    Composed of MFPED, OPM and NPA

    Each sector formed a task force

    Composed of private sector, Government and CSO to write sectorpapers

    Adhoc patriotic team to discuss issues in NDP

  • 8/3/2019 UNAA_ED's Presentation on the NDP

    13/55

    NDP process cont

    Held over 40 sector consultations discussingplans for each sector

    Separate private sector consultation (PSFU,

    UMA) Separate Civil society organization consultations

    Consulting and collection of data from LGs

    Intense discussion between NPA, MFPED andBOU especially over the macro economicframework

  • 8/3/2019 UNAA_ED's Presentation on the NDP

    14/55

    NDP process cont

    Consultative meeting of PSs and Ministers

    2 Consultative meetings of the MPs

    Consultations with H.E the President

    Submitted NDP to Cabinet and approved Laid the NDP on the table in Parliament and approved

  • 8/3/2019 UNAA_ED's Presentation on the NDP

    15/55

    NDP Conceptual framework

    Macro-economic modeling to determine the appropriatelevel of investment

    Identified the most binding constraints

    Linked the various strategies to unlock the constraints totheir respective sectors

    Egg concept to harness synergies

    Determined the MTEF

  • 8/3/2019 UNAA_ED's Presentation on the NDP

    16/55

    Egg conceptual framework

  • 8/3/2019 UNAA_ED's Presentation on the NDP

    17/55

    5/1/2012 17

    NDP SYNOPOSIS

    5/1/2012 18

  • 8/3/2019 UNAA_ED's Presentation on the NDP

    18/55

    Arrangement of the Plan

    The outlay of the plan is such that:

    i. Part 1: Overview Background& context, NDPThrust, situational analysis (macroeconomic

    analysis &binding constraints),ii. Part 2: Strategic direction & NDP strategy

    (Vision, NDP Theme & objectives, principlesand Strategy)

    iii. Part 3: Sectoral performance sector by sectorsituational analysis, objective and strategy

    iv. Part 4: M&E and Implementation Strategy

    5/1/2012 18

    5/1/2012 19

  • 8/3/2019 UNAA_ED's Presentation on the NDP

    19/55

    PART I SITUATIONAL ANALYSIS

    Notable progress recorded in the past 25 years!!!

    1987-1996 GDP growth at 6.5%, inflation from200% to 7.15

    1997/98 to 2000/01 GDP growth rate of 7.2%2000/01 to 2003/04 GDP grew at 6.8%

    2004/5 to 2007/08 GDP grew at 8%

    However, the progress is slow compared toemerging industrialised nations that we strive tobenchmark

    5/1/2012 19

    5/1/2012 20

  • 8/3/2019 UNAA_ED's Presentation on the NDP

    20/55

    5/1/2012 20

    Comparison of income Per Capita of Uganda against Korea, Kenya, Ghana and Malaysia

    0

    3000

    6000

    9000

    12000

    15000

    18000

    21000

    1970

    1971

    1972

    1973

    1974

    1975

    1976

    1977

    1978

    1979

    1980

    1981

    1982

    1983

    1984

    1985

    1986

    1987

    1988

    1989

    1990

    1991

    1992

    1993

    1994

    1995

    1996

    1997

    1998

    1999

    2000

    2001

    2002

    2003

    2004

    2005

    2006

    2007

    2008

    Years

    IncomeperCapit

    a(US$)

    Uganda Kenya Ghana

    Malaysia Korea

    5/1/2012 21

  • 8/3/2019 UNAA_ED's Presentation on the NDP

    21/55

    Part II -Strategic Direction & NDP Strategy

    The vision of the country is

    A Transformed Ugandan Society from a Peasant toModern and Prosperous Country Within 30 Years

    This is to be manifested in:

    Stable, peaceful, independent and sovereign state

    A strong state in federated East Africa with an effectiveAfrican Common Market and a strong African DefenseMechanism

    Democratic and law abiding citizens

    Knowledge based, informed and skilled citizenry changing from predominantly peasant society to middle

    income country by 2017.

    5/1/2012 21

    5/1/2012 22

  • 8/3/2019 UNAA_ED's Presentation on the NDP

    22/55

    A pictorial impression of a desiredUganda

    5/1/2012 22

    5/1/2012 23

  • 8/3/2019 UNAA_ED's Presentation on the NDP

    23/55

    Visual impression of the desiredrural Uganda

    5/1/2012 23

    5/1/2012 24

  • 8/3/2019 UNAA_ED's Presentation on the NDP

    24/55

    5/1/2012 24

    NDP Theme & Objectives

    NDP ThemeGrowth, Employment and Socio-Economic Transformation for

    Prosperity

    NDP Objectives

    1.Increasing household incomes and promotingequity

    2.Enhancing the availability of gainful employment3.Enhancing human capital development

    5/1/2012 25

  • 8/3/2019 UNAA_ED's Presentation on the NDP

    25/55

    NDP Objectives cont...

    4. Improving stock and quality of economicinfrastructure

    5. Increasing access to quality social services

    6. Promoting Science, Technology and Innovation(STI) and Information CommunicationTechnology (ICT)

    7. Strengthening good governance, defense and

    security8. Promoting a sustainable population and

    harness natural resources

    5/1/2012 25

    5/1/2012 26

  • 8/3/2019 UNAA_ED's Presentation on the NDP

    26/55

    5/1/2012 26

    Thrust of Plan Accelerate socio-economic transformation implies

    Raising per capita incomes from USD 506 to USD 900 by 2015

    Proportion of people below poverty line from 28% to 24.5 % by2015

    Expand GDP from 41.397tn to 72.094tn

    Improving labor force distribution in line with sectoral GDPcomposition

    Raising countrys human development indicators from 0.514 to

    0.572

    5/1/2012 27

  • 8/3/2019 UNAA_ED's Presentation on the NDP

    27/55

    Thrust of Plan cont Improve Country's competitiveness index to 4.2 score

    Share of manufactured products to total export toincrease to 30%

    Share of manufactured products to total GDP to increaseto 25%

    5/1/2012 27

    5/1/2012 28

  • 8/3/2019 UNAA_ED's Presentation on the NDP

    28/55

    5/1/2012 28

    Most Binding Constraints1. Inadequate stock and quality of physical

    Infrastructure (Energy, Transport)

    Only 11 % of the population has access to electricitycompared to 15% in Kenya & 98% in Malaysia

    Only 4% of total road network are paved yet itcarries 96.4% of total cargo

    Only 3.5% of cargo is carried by rail compared to

    over 90% in India & China. (triples the cost of doingbusiness)

    5/1/2012 29

  • 8/3/2019 UNAA_ED's Presentation on the NDP

    29/55

    Obsolete locomotives and tracks

    5/1/2012 29

    5/1/2012 30

  • 8/3/2019 UNAA_ED's Presentation on the NDP

    30/55

    Inadequate electricity?

    5/1/2012 30

    5/1/2012 31

  • 8/3/2019 UNAA_ED's Presentation on the NDP

    31/55

    Most Binding Constraints

    2. Weak Public Sector Management and Administration

    Poor accountability

    Poor coordination

    Duplication of mandates

    Inadequate policy and regulatory framework

    31

    5/1/2012 32

  • 8/3/2019 UNAA_ED's Presentation on the NDP

    32/55

    Most Binding Constraints

    3. Inadequate financing and financial services

    4. Inadequate quantity and quality of humanresources

    5. Gender issues, mindset, cultural practicesattention and perceptions

    6. Low application of Science and technology,

    Innovations7. Inadequate Supply of Critical Production Inputs

    3

    5/1/2012 33

  • 8/3/2019 UNAA_ED's Presentation on the NDP

    33/55

    Strategies to Unlock Most Binding

    Constraints

    Increasing stock and improving quality of publicphysical infrastructure (Energy, Transport, oil andgas, Water, ICT, etc)

    Increasing the Quantity and enhancing Quality of the

    Human Resource (Skills, health, education) Improving Public Sector Management and

    Administration Increasing Public Sector Financing and Improving

    Financial Services

    5/1/2012 34

  • 8/3/2019 UNAA_ED's Presentation on the NDP

    34/55

    Strategies to Unlock Most BindingConstraints (Contd)

    Transformation of Attitudes, Mind-set, Culturalpractices, Perceptions and Promotion of GenderEquality

    Promoting Science, Technology and Innovation (STI)

    Facilitating Availability and Access to CriticalProduction Inputs

    5/1/2012 35

  • 8/3/2019 UNAA_ED's Presentation on the NDP

    35/55

    Investment Priorities

    Increasing stock and improving quality of infrastructure(Energy, Transport, Oil and Gas)

    5/1/2012 36

  • 8/3/2019 UNAA_ED's Presentation on the NDP

    36/55

    Working on Infrastructure

    5/1/2012 37

  • 8/3/2019 UNAA_ED's Presentation on the NDP

    37/55

    Investment Priorities

    Human resource Development (Health, Education, Skills)

    Promoting Science and Technology and innovation

    Facilitating availability and access to critical Productioninputs

    5/1/2012 38

  • 8/3/2019 UNAA_ED's Presentation on the NDP

    38/55

    National Core Projects

    Construction of Karuma, Ayago and Isimba HEP andtransmission infrastructure

    Construction of standard rail gauge and rehabilitationof existing railway

    Development of greater metropolitan Kampala andimplement rapid transport systems

    5/1/2012 39

  • 8/3/2019 UNAA_ED's Presentation on the NDP

    39/55

    National Core Projects (Contd)

    Development of Oil and gasrefinery,

    Construction of oil and gaspipeline

    Development of ICT park

    National skills programme

    5/1/2012 40

  • 8/3/2019 UNAA_ED's Presentation on the NDP

    40/55

    National Core Projects (Contd)

    Development of S &T Incubationcenters

    Construction and development offive large irrigation systems

    Development of fertilizer industry

    Development of iron-ore ingot(cement industry)

    5/1/2012 41

  • 8/3/2019 UNAA_ED's Presentation on the NDP

    41/55

    Macro-Economic Strategy

    Consolidate gains made and put in placenecessary condition to ensure furthereconomic growth

    Maintaining Macro-economic stability and

    acceleration of economic growth and povertyreduction

    Avoidance of unsustainable public sectorindebtedness and increased donor

    dependencyIncreased mobilization of domestic resources

    5/1/2012 42

  • 8/3/2019 UNAA_ED's Presentation on the NDP

    42/55

    Key Macro and Financial TargetsPARAMETER 2010/11 2011/12 2012/13 2013/14 2014/15

    GDP Real

    growth6.6% 7% 7.2% 7.4% 7.5%

    Revenue 13.1% 13.6% 14.1% 14.6% 15.1%

    Net Aid (%

    GDP)

    5.4% 5.6% 5.1% 4.6% 3.7%

    Domestic

    Borrowing

    0.6% 0.6% 0.6% 0.6% 0.6%

    Fiscal deficit(%

    of GDP)6.1% 6.2% 5.7% 5.2% 4.3%

    Government

    expenditure( %

    of GDP)

    19.2% 19.8% 19.8% 19.8% 19.4%

    GDP (trillion)41.397 46.934 53.904 62.227 72.094

    5/1/2012 43

  • 8/3/2019 UNAA_ED's Presentation on the NDP

    43/55

    Other Key Strategies

    Outwardoriented policies by encouragingFDI and exports with high added valuePlanned-market-economy approach (quasi) (Private

    Sector engine of growth, PPP will be key

    Business approach to public sector servicedelivery citezen-centredness

    5/1/2012 44

  • 8/3/2019 UNAA_ED's Presentation on the NDP

    44/55

    Sector-based Strategies

    Following a results chain approach, the NDP containssector objectives, strategies and interventions by sector

    The presentation follow categorisation of sectors basedon the egg analogy:

    Primary growth sectors Complementary sectors

    Social services sector

    Enabling sectors

    5/1/2012 45

  • 8/3/2019 UNAA_ED's Presentation on the NDP

    45/55

    Monitoring and Evaluationframework

    Rationalize the M&E functions of OPM, NPA, MDAs andLGs

    Unified, integrated, robust and well coordinatedgovernment-wide monitoring and evaluation framework

    Provide staff for M&E in MDAs and LGs

    Clear reporting mechanisms

    5/1/2012 46

  • 8/3/2019 UNAA_ED's Presentation on the NDP

    46/55

    NDP Monitoring & evaluationframework

    Progress Reporting

    Quarterly Planning Forum

    Annual Planning Forum

    Mid term Review Evaluation

    5/1/2012 47

  • 8/3/2019 UNAA_ED's Presentation on the NDP

    47/55

    PLAN IMPLEMENTATION

    Implementation of the NDP is carried out through theexisting institutional arrangements

    Building capacity of the relevant institutions at nationaland local government level will be undertaken

    Political Commitment and dedicated technicalexpertise

    5/1/2012 48

  • 8/3/2019 UNAA_ED's Presentation on the NDP

    48/55

    Implementation Strategy

    National Planning and Policy Committee sit to assessNDP implementation

    Cabinet Secretariat will be watchdog for ownershipand leadership by Cabinet

    Parliament to provide overall oversight to maintainconsensus and participation

    5/1/2012 49

  • 8/3/2019 UNAA_ED's Presentation on the NDP

    49/55

    Implementation Strategy (Contd)

    OPMcoordination of implementation

    PSs and CAOs responsibility for oversight

    Changes in institutions, structures and systems ofgovernment

    Linkage to MTEF

  • 8/3/2019 UNAA_ED's Presentation on the NDP

    50/55

    PRE-REQUISITE FOR NDPIMPLEMENTATION

    Ownership

    Implementation is a shared responsibility Political will at the national and LG levels.

    ProgressReporting

    Sustained annual and quarterly planning&commitment of resources Effective monitoring and evaluation to

    support implementation.

    ChangeManagement

    Behaviour change, patriotism andprogressive reduction of corruption.

    Increased private sector capacity.

    5/1/2012 51

  • 8/3/2019 UNAA_ED's Presentation on the NDP

    51/55

    Financing Strategy

    Overall NDP resource Envelope is 54 trillions

    Sources of financing Tax and Non Tax Revenue

    Efficiency gains utilizing good efficiency framework

    Public Private Partnerships (PPP) Borrowing from Capital Markets

    Grants and concessionary Loans

    5/1/2012 52

  • 8/3/2019 UNAA_ED's Presentation on the NDP

    52/55

    Challenges

    Only 55% of the costs for core projects are government.We expect 45% from Private sector

    Overall resource envelope 54 trillion, many unfundedinterventions, the resource envelope should increase to-

    65 trillions

    Funding gap of about 11 trillions

    5/1/2012 53

  • 8/3/2019 UNAA_ED's Presentation on the NDP

    53/55

    Challenges (Contd)

    Keeping Fiscal deficit under 5% in line with East AfricaProtocol

    Urgent Action on Public Sector Management to increaseabsorption of funds and improve public service delivery

    Harmonize sector BFPs to be in line with NDP

    5/1/2012 54

  • 8/3/2019 UNAA_ED's Presentation on the NDP

    54/55

    Wayforward

    In light of the financing deficit, harmonisation ofNDP and budget has been carried out jointly byNPA, MFPED and OPM together with sectors

    Sectors have been able to rank their priorities forFY 2011/12 and link them with relevant votefunctions and vote function outputs

    The exercise of localisation sector priorities intheir respective Local Governments is ongoing

    5/1/2012 55

  • 8/3/2019 UNAA_ED's Presentation on the NDP

    55/55

    THANK YOU

    FOR GOD AND MY COUNTRY