    PROJECT SYSTEM

    TRAINING MANUAL

    On

    Investment Management Program Structure & Appropriation Request

    FOR

    Druk Green Power Corporation Limited/ Druk Holdings and Investments Limited

    Wipro Ltd.Date:

    Version 0.1

  • 7/31/2019 UM_MM IM Program Structure & AR

    2/27

    ii

    Table of Contents

    1. Create Investment Program ............................................................................................ 12 Create Investment Program Position .............................................................................. 33 Create Investment Program Structure ............................................................................ 54 Create Appropriation Request ........................................................................................ 95 To send appropriation request (proposed project) for approval ..................................... 156 To approve appropriation request by approver. ............................................................ 167 Create project upon approval ........................................................................................ 238 Create Project Structure ............................................................................................... 25

  • 7/31/2019 UM_MM IM Program Structure & AR

    3/27

    1

    1. Create Investment Program

    Procedural Steps

    I. Access transaction by:

    Via Menus Accounting Investment Management Program Master Data Investment Program Definition Create.

    Via Transaction Code IM01

    II. On screen , enter the followinginformation:

    Field Name Description R/O/C User Action and Values Comments

    InvestmentProgram

    InvestmentProgram

    R Enter the description of theInvestment Program

    Approval Year Approval Year R Type the Financial year fore.g. 2011

    Program Type Program Type R Select from the dropdownlist DGPC

  • 7/31/2019 UM_MM IM Program Structure & AR

    4/27

    2

    III. On screen , enter the following information:

    Field Name Description R/O/C User Action and Values Comments

    ProgramDescription

    Investment ProgramDescription

    R Type investmentprogram description

    BudgetDistributedannually

    Budgeting distributionannual

    R Activate

    FI variant Financial Year Variant R Select the option fromthe drop down list K4Jan. to Dec.

    Currency Currency R Company code currencyBTN

    (Note: on above table, in column R/O/C: R = Required, O = Optional, C = Conditional)

  • 7/31/2019 UM_MM IM Program Structure & AR

    5/27

    3

    IV. Go to Menu bar then select Inv. Prg. Definition Save, the following screen will bedisplayed.

    2 Create Investment Program Position

    I. Access transaction by:

    Via Menus Accounting Investment Management Programs Master Data Investment Program position Create.

    Via Transaction Code IM11

    II. Create inv. Program Position and enter information in the fields as specified in thetable below:

  • 7/31/2019 UM_MM IM Program Structure & AR

    6/27

    4

    Field Name Description R/O/C User Action and Values

    Investment program Investment program R Enter investment program IDPosition ID Top level position

    IDR Enter Top position ID similar to

    program definition ID

    Approval Year Approval year R Type the fiscal year e.g., 2011

    Click on button

    III. Create inv. Program Position under organizational unit tab enter information in thefields as specified in the table below:

  • 7/31/2019 UM_MM IM Program Structure & AR

    7/27

    5

    Field Name Description R/O/C User Action and Values

    Position IDdescription

    Investment program R Enter description for top position ID

    Controlling

    area

    Controlling area R Select controlling area from dropdown

    listCompanyCode

    Company code O Select company code from thedropdown list

    IV. Go to menu bar select Inv. Prog. Position Save

    3 Create Investment Program Structure

    I. Access transaction by:

    Via Menus Accounting Investment Management Programs Master Data Investment Program structure Change.

    Via Transaction Code IM22

    II. Create inv. Program structure, enter information in the fields as specified in the tablebelow:

    Field Name Description R/O/C User Action and ValuesInvestmentprogram

    Investmentprogram

    R Enter investment program ID

    Position ID Top level positionID

    R Enter Top position ID

    Approval Year Approval year R Enter approval year

  • 7/31/2019 UM_MM IM Program Structure & AR

    8/27

    6

    III. Select enter button or click on button

    IV. Select top position ID and click on create button to create program structure whichresults Create Inv. Program positions screen popup.

    Field Name Description R/O/C User Action and ValuesPosition ID Position ID R Position ID for second levelName Description for position

    IDR Enter description

  • 7/31/2019 UM_MM IM Program Structure & AR

    9/27

    7

    Click on button

    V. To expand top level program, click on + so that user can view subordinate programsas follows.

    VI. To create sub-programs further select required program and go to menu bar selectobject create. System will popup create Inv. Program Positions window.

    Choose radio button of subordinate.

  • 7/31/2019 UM_MM IM Program Structure & AR

    10/27

    8

    VII. Select Copy button from status bar of the window Create Inv. Program Position.

    VIII. User can create desired no. of programs by entering following information in eachrow.

    Field Name Description R/O/C User Action and ValuesPosition ID Position ID R Position IDName Description for position

    IDR Enter description

    If you want to find errors select Check button.

  • 7/31/2019 UM_MM IM Program Structure & AR

    11/27

    9

    Go to menu bar and select object save then system will take you following screen.

    To exit go to menu bar select Inv. Program struct. Exit

    4 Create Appropriation Request

    Procedural StepsI. Access transaction by:

    Via Menus Accounting Investment Management AppropriationRequest Edit Appropriation Request Individualprocessing

    Via Transaction Code IMA11

    System will display following Display Appropriate Request: screen

  • 7/31/2019 UM_MM IM Program Structure & AR

    12/27

    10

    II. To create new appropriation request, go to menu bar select Approp. Request create then system will popup Create Appropriat. window as follows.

    III. Choose Approp. Request type as 3 for DGPC and 4 for DHI and click on button.

    If system popup set controlling area window then select DP01 for DGPC andDagachhu companies. For DHI select DI01 as company code.

    IV. System will display following screen to create new appropriation request.

  • 7/31/2019 UM_MM IM Program Structure & AR

    13/27

    11

    V. On screen enter theinformation in the fields as specified in the table below:

    Field NameDescription R/O/C User Action and Values

    Reason forinvestment

    Reason for investment O Choose relevant reason fromdropdown list

    Scale Investment sizeclassification

    O Choose relevant scale fromdropdown list

    Priority Priority of the

    appropriation request

    O Choose priority from the dropdown

    listApproval year Approval year for

    projectR Enter approval year

    PlannedApproval

    Specifies the date onwhich the applicantwould like to have theproposed projectapproved

    R Enter expected approved date

    Implementationstart

    Plan start date forproject implementation

    R Enter expected start date

    External

    authorities

    Projects which require

    approval from externalauthorities

    Activate indicator if project requires

    external authority approval (Govt.environment authorities)

  • 7/31/2019 UM_MM IM Program Structure & AR

    14/27

    12

    Person Involved

    Projectapplicant

    SAP user ID of projectapplicant

    R Enter SAP User ID of projectapplicant

    Fuct. Partner Function R Select no. of approvers as per DoPfrom drop down list

    Partner Partner R Select relevant approver SAP userID from the dropdown list as perapprover level

    VI. Select Control data tab.

    On screen enter the information inthe fields as specified in the table below:

    Field Name Description R/O/C User Action and ValuesInvestmentprogram

    Investment program ID R Enter relevant program definition ID

    Approval year R Enter Approval year of investmentprogram

    Position ID Position ID R Choose relevant position ID for whichappropriation request is related

  • 7/31/2019 UM_MM IM Program Structure & AR

    15/27

    13

    VII. Select Organizational unit tab

    On screen enter theinformation in the fields as specified in the table below:

    Field Name Description R/O/C User Action and Values

    Resp. Costcentre

    Responsible costcenter

    R Enter the cost center that is responsiblefor the appropriation request

    Resp. Plant Plant R Enter Plant code for which appropriationrequest is relevant

  • 7/31/2019 UM_MM IM Program Structure & AR

    16/27

    14

    VIII. Select variants tab

    To carry out rough cut cost planning, select tab under variant tab ofappropriation request (optional).

    IX. To attach supporting documents of proposed project, select tab undervariant tab of appropriation request (optional).

    Prerequisite: All relevant documents must be assigned to Document info record (DIR)using CN01N (T-code). System assigns an internal number for DIR.

  • 7/31/2019 UM_MM IM Program Structure & AR

    17/27

    15

    Field Name Description R/O/C User Action and Values

    Ty. Document type R Choose relevant document type

    Document Document number R Enter relevant document number

    X. Go to menu bar select Approp. Request Save.System displays a message Appropriation request 1############## was createdon status bar.

    5 To send appropriation request (proposed project) for approval.

    Procedural Steps

    I. Access transaction by:

    Via Menus Accounting Investment Management Appropriation

    Request

    Edit Appropriation Request

    Individual processingVia TransactionCode

    IMA11

    System will display following Display Appropriate Request: screen

    II. In the tool bar of appropriation request Worklist on displays, click onbutton which will open worklist area.

  • 7/31/2019 UM_MM IM Program Structure & AR

    18/27

    16

    III. Select appropriation request from the worklist which requires to send for approval

    and click on icon.

    IV. Appropriation request will open.

    V. Select Control data tab.

    VI. Click on button.

    System status will be changed from Created to For approval and system will display

    message on status bar. System will triggermail to 1st

    approver.

    VII. Go to menu bar select Approp. Request Save.

    6 To approve appropriation request by approver.

    I. Access transaction by:

    Via Menus SAP Menu OfficeWorkplaceVia Transaction Code SBWP

  • 7/31/2019 UM_MM IM Program Structure & AR

    19/27

    17

    II. Click on workflow, system will open workflow pane where pending appropriationrequest for approval can be viewed.

  • 7/31/2019 UM_MM IM Program Structure & AR

    20/27

    18

    III. Double click on appropriation request to review and approve, then system will openappropriation request with display mode.

    IV. To review appropriation request select each tab one by one.

  • 7/31/2019 UM_MM IM Program Structure & AR

    21/27

  • 7/31/2019 UM_MM IM Program Structure & AR

    22/27

  • 7/31/2019 UM_MM IM Program Structure & AR

    23/27

    21

    System will display create note window

    X. To approve or reject go to tool bar and click on button or press F3 button fromyour keyboard then system will display following screen.

    If Appropriation request to be approved, Click on Approve button.

    If more than one approver is existed for appropriation request then system forwardappropriation request to next level approver. Otherwise Applicant will receive a mail withapproved status of appropriation request in his/her business SAP workplace.

    If Appropriation request to be rejected, Click on Rejected button.Applicant will receive a mail with rejected status of appropriation request in his/her businessSAP workplace and system will update appropriation status as rejected.

  • 7/31/2019 UM_MM IM Program Structure & AR

    24/27

    22

    If Appropriation request to be postponed, Click on Postpone button.Applicant will receive a mail with Appropriation request 0001000000XX was postponed inhis/her business SAP workplace and system will update appropriation status as created.

    If Appropriation request to be cancel for further decision, Click on cancel button.Appropriation request message would be available in SAP business workplace for furtherdecision.

    XI. Once clicked on approve button appropriation request will disappear from workflowview.

    XII. Repeat above steps to approve or reject by next level approver.

    Upon approval Appropriation Request system status will be changed as Approved

  • 7/31/2019 UM_MM IM Program Structure & AR

    25/27

    23

    7 Create project upon approval

    I. Change appropriation request from display mode to change mode by clicking icon

    Select tab.

    II. Click on button to create new project then system will displayfollowing screen.

  • 7/31/2019 UM_MM IM Program Structure & AR

    26/27

    24

    III. Select tab.

    IV. Click on button then system will display message

    Then another system status will be changed from measure created to replaced bymeasure.

    V. Click on button to assign status as Technically completed.System will display message

    on status bar.

    VI. Click on button to close appropriation request.System will change status from technically completed to close status and messagewill be displayed on status bar

  • 7/31/2019 UM_MM IM Program Structure & AR

    27/27

    8 Create Project Structure

    Procedural Steps

    Via Menus Logistics or Accounting > Project System > Project >Project Builder

    Project BuilderVia Transaction Code CJ20N

    I. Go for menu Project Open.

    II. Using selection criteria in the pop up, open the appropriate project which is createdusing appropriation request.

    III. Create remaining project structure as described in project structure creation manual.