Air Force Civil Engineer Center
Battle Ready … Built Right!
Brig Gen Patrice Melançon
PMO Executive Director
30 Oct 2019
Tyndall AFB
Reconstruction
Program
11
Battle Ready … Built Right!
What We Do
The mission of the PMO is to Repair,
Reshape, and Rebuild Tyndall AFB to
support both near-term resumption of
mission operations and long-term
development of Tyndall as the model Air
Force Installation of the Future.
“Not the Base We Had but
The Base We Need”
2
Battle Ready … Built Right!
Background
• Hurricane Michael
hit 10 Oct 2018
• Immediate
Response
• TDY Manning
• Long Term Manning
33
Battle Ready … Built Right!
By the Numbers
• Tent City w/Power
Plant
• Initial Facility
Assessments
• AFCAP work
• Huge Demo
Requirement
4
Battle Ready … Built Right!
Planning & Guidance
Siting Multi-Use ConsolidationImprove functional
compatibility and enhance organizational efficiency
Expandable Multi-Use
Consolidation Reserve CapacityReduce future
operating costs
Adaptive Reuse Innovative Procurement
P3/P4Reduce rebuilding costs
ECPs Perimeter Improve perimeter security
Walkability One Stop ShoppingImprove the traffic flow / reduce reliance on autos
ATFPImprove safety
Resiliency EAMinimize downtime after disruption
Battle Ready … Built Right!
Installation Development Plan
6
Flightline
District
Support
DistrictCrooked
Island
District
Battle Ready … Built Right!
Installation Development Plan Crooked Island District
9
A – Consolidated Lab
Facility
B – Ballistics Lab
C – Vehicle Maintenance
Facility
D – Robotics / UAS Range
E – Material Testing Runway
F – Energy Tent City
G – EOD Robotics
Maintenance
H – Vehicle / Equipment
Open Storage
Consolidates 20 Facilities into 4
Battle Ready … Built Right!
Qrt 1 Qrt 2 Qrt 4 Qrt 1
FY20
Qrt 2 Qrt 3 Qrt 4 Qrt 1
FY21
Qrt 2 Qrt 3 Qrt 4 Qrt 1
FY22
Qrt 2 Qrt 3 Qrt 4 Qrt 1
FY23
Qrt 2 Qrt 3 Qrt 4 Qrt 1
FY24
Qrt 2 Qrt 3 Qrt 4
Design
First F-35
Arrives
FY19
Qrt 3
Debris
Temp
Modular
Planning & Pre-Design
Demolition
Assess
Permanent Construction
Permanent Repairs
Overall Timeline
10
NOWTODAY
10
Battle Ready … Built Right!
MILCON Overview
• Program Scope
• Funding
• Execution
• Risks & Mitigation
• Challenges
• Near Term Actions
11
Battle Ready … Built Right!
MILCON Program Scope
• USACE execution
• $3.0B for the non-MQ9 rebuild
• 42 projects across 12 zones
• Evolving requirements and project
programming
• Programming estimates include factors:
– Post-hurricane market conditions
– Enhance resiliency
– Cybersecurity for facility-related control systems
– Smart facility and installation technology
12
Battle Ready … Built Right!
MILCON Funding
• FY19 Disaster Recovery Appropriation Bill
– $1B unspecified MILCON
• $577.6M for Tyndall
– $147.6M P&D
– $430M Construction
– 5 Aug – Spend Plan briefed
• Draft FY20 VA/MILCON Appropriation Bill
– ~$1B HASC & HAC mark MILCON for Tyndall & Offutt
– ~$1.5B SASC mark MILCON for Tyndall
– Awaiting SAC marks & conference reports
– Likely Line Item appropriated
– Committees may fund higher
13
Battle Ready … Built Right!
MILCON Execution
14
• Design-Build (DB) acquisition/execution by Zone1. Fifth Gen Fighter $466M
2. Flightline Ops $145M
3. WEG $326M
4. Infrastructure $410M
5. Industrial $221M
6. Airfield Drainage $144M
7. MSA $ 36M
8. Administrative $ 91M
9. MWR $ 80M
10. Lodging/Dorms $455M
11. Community Commons $131M
12. Silver Flag/TTA $291M
• 10 USC 2854 Authority – ABM Simulator $18M (awarded)
– Fire Station #2 $12M (awarded)
• Design Integrator to coordinate across Zones/Program
Battle Ready … Built Right!
MILCON Execution
• Design Contracts (12 Zones)
– AFCEC AE13DCS Contract
– Mobile District – Design Agent for Zones 1-9
– Savanah District – Design Agent for Zones 10-12
• Construction Contracts
– Acquisition Plan under development
– Alternatives under consideration
• SATOC by Zone
• MATOC by Zone
• C-Contract by Zone
~2 years to award MATOC or SATOC
15
Battle Ready … Built Right!
Recent/Near Term Actions
• FY19 projects awarded under 10 USC 2854 authority
– ABM Simulator (100% of scope, 80% of PA)
– Fire Station #2 (100% of scope, 86% of PA)
• A&AS support contract awarded
• Design/Build RFP contract awards (Sep-Oct)
– Design charrettes for 26 facilities scheduled
• Publish revised Installation Facility Standards (IFS)
and Tyndall specific guide specifications (Nov)
• Publish governance docs and Program Management
Plan (PgMP) (Nov)
• Design Integration (DI) contract award (Dec)
16
Battle Ready … Built Right!
325 FW O&M Program
• FY19
– 143 Projs for $338M
• FSRM – 84 projs for $263M
– Σ $39M over PA // Primarily 325 CONS and USACE
• Non-FSRM – 59 projs for $75M
– 325 CONS, USACE, DLA, GSA, 772 ESS
– 2 MilCon Projs – Sec 2854 Auth - $30M
• FY20
– $278M in FSRM (80 Projs)
– $144M in Non-FSRM Requirements
– $50M in 2854 Authority
17
Battle Ready … Built Right!
Smart Sensors Smart Grids
Innovation Areas
Engaging on multiple fronts
HAF/A4C/L/S AFRL
AFCEC/CO AFWERX
Battle Ready … Built Right!
• Smart Distribution
• Base Defense
• Automated Entry
Innovation Areas
• Tie into FLoF
• GeoBase
• Facility 3D Printing
Battle Ready … Built Right!
Installation of the Future
• Today’s requirements with flexibility for growth
• Cost effective / cost efficient
• Right-sized, consolidated facilities
• Improved land use
• Campus organizations – Mission & Support
• Connected campus – walkable/bike-able
• Maximized use of smart & resilient buildings
20