52
1 TUNNELLING IN ROCKS – PRESENT TECHNOLOGY AND FUTURE CHALLENGES ZHAO Jian Professor of Rock Mechanics and Tunnelling Swiss Federal Institute of Technology (EPFL) Lausanne, Switzerland Inaugural Lecture, EPFL 24 May 2007 Laboratoire de Mécanique des Roches LMR

TUNNELLING IN ROCKS – PRESENT TECHNOLOGY AND FUTURE CHALLENGES

  • Upload
    others

  • View
    3

  • Download
    0

Embed Size (px)

Citation preview

Page 1: TUNNELLING IN ROCKS – PRESENT TECHNOLOGY AND FUTURE CHALLENGES

1

TUNNELLING IN ROCKS – PRESENT TECHNOLOGY AND FUTURE

CHALLENGES

ZHAO JianProfessor of Rock Mechanics and TunnellingSwiss Federal Institute of Technology (EPFL)

Lausanne, Switzerland

Inaugural Lecture, EPFL24 May 2007

Laboratoire de Mécanique des Roches − LMR

Page 2: TUNNELLING IN ROCKS – PRESENT TECHNOLOGY AND FUTURE CHALLENGES

2

Contents

Laboratoire de Mécanique des Roches − LMR

Introduction– Including Brief History of Rock Tunnels

Rock Excavation Technology – Past Development and Today

Rock Support Technology – Past Development and Today

Challenges and Future Development – Including R&D Needs

Page 3: TUNNELLING IN ROCKS – PRESENT TECHNOLOGY AND FUTURE CHALLENGES

3

Introduction: Rock Tunnelling

Laboratoire de Mécanique des Roches − LMR

Rock tunnelling involves: Rock excavation – to make a hole.Rock support – to sustain the hole.

Rock Excavation:Excavation technology is primarily driven by rock excavation machine technology.

Rock Support:Support technology is largely driven by rock mechanics science together with support material technology.

Page 4: TUNNELLING IN ROCKS – PRESENT TECHNOLOGY AND FUTURE CHALLENGES

4

Introduction: Rock Tunnel History

Laboratoire de Mécanique des Roches − LMR

Canal du Midi (Languedoc) tunnel (1666-81), first use of explosive (black powder).Hoosac tunnel (1851-75), first of use of dynamite (invented in 1860s). Also the first attempt of a tunnel boring machine (TBM).Mont Cenis (Fréjus) tunnel (1857-71), used compressed air drill, made 5 m/day advance rate.Gotthard tunnel (1872-1880), the longest (15 km) then.Simplon tunnel (1898-1906), for years (until 1982) as the longest tunnel, 19.8 km.

Page 5: TUNNELLING IN ROCKS – PRESENT TECHNOLOGY AND FUTURE CHALLENGES

5

Introduction: Rock Tunnel History

Laboratoire de Mécanique des Roches − LMR

Start of rock TBM (1951), at the Oahe Dam (shale) and later at the Humber Sewer (hard rock) tunnels.Seikan tunnel (1972-88), 54 km long with undersea length of 23 km.Gjovik cavern (1991-1993), largest rock cavern of 61 m span. Channel tunnel (1994), 52 km long with longest undersea length of 39 km, by TBMs.Gotthard base tunnel, longest tunnel (57 km), with maximum overburden of 2.4 km, 90% by TBM.Niagara tunnel, with largest rock TBM, ø14.4 m.

Page 6: TUNNELLING IN ROCKS – PRESENT TECHNOLOGY AND FUTURE CHALLENGES

6

Rock Excavation

Laboratoire de Mécanique des Roches − LMR

Modern rock tunnels are excavated by primarily two methods:

Drill-and-Blast (D&B): It involves drilling charge holes advancing into rocks and using explosives to blast the rocks.Tunnel Boring Machine (TBM): It involves cutting rock by a full face boring machines. Tunnelling machines for partial face (roadheader) are also used for rock excavation.

Page 7: TUNNELLING IN ROCKS – PRESENT TECHNOLOGY AND FUTURE CHALLENGES

7

Rock Excavation: Drill-and-Blast

Laboratoire de Mécanique des Roches − LMR

Drilling Charging

Blasting

Ventilation

Mucking outShotcrete

Bolt

Survey

Page 8: TUNNELLING IN ROCKS – PRESENT TECHNOLOGY AND FUTURE CHALLENGES

8

Rock Excavation: Drilling Technology

Laboratoire de Mécanique des Roches − LMR

In 1850s, compressed air drilling was invented for rock drilling. Since 1945, tungsten carbide drilling bits have been used. In 1960s, pneumatic drilling was introduced.In 1970s, hydraulic drilling was introduced and remains the main drilling method today.Since 1980s, computer aided rock drilling started.

Page 9: TUNNELLING IN ROCKS – PRESENT TECHNOLOGY AND FUTURE CHALLENGES

9Laboratoire de Mécanique des Roches − LMR

Drilling performance increased from 5 m/hour 100 years ago to 450 m/hour today.

Page 10: TUNNELLING IN ROCKS – PRESENT TECHNOLOGY AND FUTURE CHALLENGES

10

Rock Excavation: Blasting Technology

Laboratoire de Mécanique des Roches − LMR

Before 1860s, black powder was used. In 1860s, dynamite was invented and used in hard rock tunnelling.1922, Electric initiation (1 second delay) introduced. 1940s, short delay detonators (10-100 ms) used.1955, ANFO (ammonium nitrate fuel oil) introduced.In 1960s, water gel and slurries. In 1970s, non-electric initiation developed.In 1980s, emulsion explosive developed and used in tunnelling since 1990s.

Page 11: TUNNELLING IN ROCKS – PRESENT TECHNOLOGY AND FUTURE CHALLENGES

11

Rock Excavation: Blasting Technology

Laboratoire de Mécanique des Roches − LMR

Emulsion explosives are water resistant, safe and pumpable, and produce less toxic gases.

Charging blast holes with emulsion explosives to excavate the Singapore Underground Ammunition Facility (UAF) storage caverns.

Page 12: TUNNELLING IN ROCKS – PRESENT TECHNOLOGY AND FUTURE CHALLENGES

12

Rock Excavation: D&B Today

Laboratoire de Mécanique des Roches − LMR

Computerized and automated hydraulic drilling jumbos are widely used. Drilling plans are stored in computer, precise positioning and navigation are by laser. Excavated profiles can be scanned for guiding next drilling and blasting.

In Lötschberg base tunnel (section about 70 m2), over 6 m/day average progress for 4.6 km in granite, gneiss, schist and limestone, with maximum 16 m/day in granite.

Page 13: TUNNELLING IN ROCKS – PRESENT TECHNOLOGY AND FUTURE CHALLENGES

13

Rock Excavation: D&B Today

Laboratoire de Mécanique des Roches − LMR

Computerized and automated hydraulic drilling jumbo, with drill plan stored in

computer. No marks on the face.

Computerised 3-boom drilling jumbos used in Singapore UAF caverns

PilotSlash

Bench, 3.5-m high

Chamber section: 275 m2

Chamber section: 275 m2

Page 14: TUNNELLING IN ROCKS – PRESENT TECHNOLOGY AND FUTURE CHALLENGES

14

Rock Excavation: D&B Today

Laboratoire de Mécanique des Roches − LMR

Emulsion explosives combined with non-electric initiation system are used to provide a safer and more efficient tunnelling operation. Quantity of pumpable emulsion can be controlled by computerized system.

Emulsion explosives were use to blast this and other granite caverns in Singapore (1999-2002). Emulsion explosive were stored on site.

Page 15: TUNNELLING IN ROCKS – PRESENT TECHNOLOGY AND FUTURE CHALLENGES

15

Rock Excavation: D&B Today

Laboratoire de Mécanique des Roches − LMR

Full large face excavation, even in poor rock mass,

with face auxiliary methods.

Gotthard base tunnel, Sedrun

Various face auxiliary methods have been

developed, including forepole umbrella,

fibreglass reinforcement.

Page 16: TUNNELLING IN ROCKS – PRESENT TECHNOLOGY AND FUTURE CHALLENGES

16

Rock Excavation: TBM

Laboratoire de Mécanique des Roches − LMR

Tunnel Boring Machine (TBM) is an excavation machine cutting the rock full face by pushing and rotating the cutterhead. Tunnel support is done behind.

Page 17: TUNNELLING IN ROCKS – PRESENT TECHNOLOGY AND FUTURE CHALLENGES

17

Rock Excavation: TBM Technology

Laboratoire de Mécanique des Roches − LMR

1851, invented by Wilson, first attempted at the Hoosac tunnel.In 1950s, TBMs made by Robbins successfully excavated the Oahe Dam (shale) and Humber Sewer (hard rock) tunnels.

In 1990s, >50% tunnel volume in Switzerland are by TBMs.Channel tunnel (1994), 52 km (39 km undersea), by TBMs.In 1960s, roadheader was introduced to tunnelling.

Page 18: TUNNELLING IN ROCKS – PRESENT TECHNOLOGY AND FUTURE CHALLENGES

18

Rock Excavation: TBM Technology

Laboratoire de Mécanique des Roches − LMR

Gotthard base tunnel, longest tunnel (57 km), with maximum overburden of 2.4 km to be completed soon, about 90% by TBM.Niagara tunnel, with largest TBM, ø14.4 m.

TBM used for the Lötschberg base tunnel

Page 19: TUNNELLING IN ROCKS – PRESENT TECHNOLOGY AND FUTURE CHALLENGES

19

Rock Excavation: TBM Technology

Laboratoire de Mécanique des Roches − LMR

Development of TBM CutterheadCutter diameter (mm): 280 (1956), 356 (1970s), 483 (1980s), 500 (1990s).Maximum cutter force (kN/cutter): 55 (1956), 160 (1970s), 280 (1980s), 320 (1990s). Cutterhead rotation speed (RPM);32 (1970s), 50 (1980s).

TBM in Switzerland• 1965, first TBM (ø3.5 m)• 1979, Gubristtunnel

(ø11.52 m)• In 1970s, 83 km road and

railway tunnels• 1985 – 1999, 17 large

scale TBM used • largest diameter:

Adlertunnel ø12.58 m

Page 20: TUNNELLING IN ROCKS – PRESENT TECHNOLOGY AND FUTURE CHALLENGES

20

Rock Excavation: TBM Technology

Laboratoire de Mécanique des Roches − LMR

TBM

TBM

Length

Volume

D&

BD

&B

Tunnelling in Switzerland and

Use of TBM

Page 21: TUNNELLING IN ROCKS – PRESENT TECHNOLOGY AND FUTURE CHALLENGES

21

Rock Excavation: TBM Today

Laboratoire de Mécanique des Roches − LMR

Wide choice of TBMs for rock tunnelling, with diameter >14m, gripper, single shield, double shield, EPB, slurry and mix-shield, for different ground conditions.

Convertible EPB–slurry TBM for poor rock and mixed ground Slurry ModeEPB Mode

Page 22: TUNNELLING IN ROCKS – PRESENT TECHNOLOGY AND FUTURE CHALLENGES

22

Rock Support

Laboratoire de Mécanique des Roches − LMR

Rock tunnel support are divided into two categories:Temporally support: This is a short-term measure only to provide a safe working environment for continuous excavation. Common techniques are bolts and shotcrete.Permanent support: This is long-term support for a life-span of the tunnel. The methods available are steel set, cast-in concrete, concrete segment, bolt, shotcrete (with or without steel fibre reinforcement).

Page 23: TUNNELLING IN ROCKS – PRESENT TECHNOLOGY AND FUTURE CHALLENGES

23

Rock Support

Laboratoire de Mécanique des Roches − LMR

Two main rock support systems: bolt and shotcrete (left, for D&B and TBM tunnels) and concrete segment (right, for TBM tunnels).

Page 24: TUNNELLING IN ROCKS – PRESENT TECHNOLOGY AND FUTURE CHALLENGES

24

Rock Support: Mechanics and Design

Laboratoire de Mécanique des Roches − LMR

1942, based on rail tunnel experiences in the Alps, Terzaghiintroduced Rock Load Factor, first time classified rock into 9 behaviour classes, ranging from solid massive to squeezing and swelling. It allows to estimate the total load that the steel arch need to design for.

Page 25: TUNNELLING IN ROCKS – PRESENT TECHNOLOGY AND FUTURE CHALLENGES

25

Rock Support: Mechanics and Design

Laboratoire de Mécanique des Roches − LMR

1960-70s, Ground-support interaction and observation based support design concept introduced. It allows ground deformation and stress redistribution, to optimise the support applied to the rock, by taking the rock-support interaction into account.

Displacement

p

Pre

ssu

re r

equ

ired

to

limit

dis

plac

emen

t

(a)

(c)

(e)

(d)

(b)

δp

δ

Rock behaviour

Support behaviour

Page 26: TUNNELLING IN ROCKS – PRESENT TECHNOLOGY AND FUTURE CHALLENGES

26

Rock Support: Mechanics and Design

Laboratoire de Mécanique des Roches − LMR

1970s, Rock mass quality classifications (RMR and Q) introduced as tools for rock mass quality assessment and basis for rock support design.

Page 27: TUNNELLING IN ROCKS – PRESENT TECHNOLOGY AND FUTURE CHALLENGES

27

Rock Support: Mechanics and Design

Laboratoire de Mécanique des Roches − LMR

Since 1980s numerical modelling methods were used for analysis and design. Notably, discrete element method (DEM) was applied to model discontinuous rock masses.

DEM modelling on support design and stability

analysis for the 61 m span cavern in Gjovik, Norway.

Page 28: TUNNELLING IN ROCKS – PRESENT TECHNOLOGY AND FUTURE CHALLENGES

28

Rock Support: Mechanics and Design

Laboratoire de Mécanique des Roches − LMR

1980s, Hoek-Brown strength criterion was developed, and was improved with the introduction of Geological Strength Index (GSI) in 1990s.It is the most widely used criterion to estimate rock mass strength, and to provide rock mass parameters for design.

Page 29: TUNNELLING IN ROCKS – PRESENT TECHNOLOGY AND FUTURE CHALLENGES

29

Rock Support: Methods and Materials

Laboratoire de Mécanique des Roches − LMR

Before 1950s, steel arch is the main support method.In 1920s, rock bolts were tried and became widely used since 1950s, seeing the development of expansion shell anchor.1970s, split set, and 1980s, Swellex was introduced.

Expansion shell anchor bolt

Swellex

Page 30: TUNNELLING IN ROCKS – PRESENT TECHNOLOGY AND FUTURE CHALLENGES

30

Rock Support: Methods and Materials

Laboratoire de Mécanique des Roches − LMR

1950s, dry-mix and 1960s wet-mix sprayed concrete introduced, and since 1980s, wet-mix became widely applied.1970s, steel fibre reinforced sprayed concrete (SFRS) was experimented and in 1980s it gained wide applications.

Page 31: TUNNELLING IN ROCKS – PRESENT TECHNOLOGY AND FUTURE CHALLENGES

31

Rock Support: Support Design Today

Laboratoire de Mécanique des Roches − LMR

Support design based on rock mass quality classifications, mainly, RMR and Q, mostly for competent rock masses.Support design and implementation based on sequential excavation and observation, particularly for poor ground.Physical and numerical modelling for non-precedent or special cases.

Page 32: TUNNELLING IN ROCKS – PRESENT TECHNOLOGY AND FUTURE CHALLENGES

32

Rock Support: Support Design Today

Laboratoire de Mécanique des Roches − LMR

Prediction of squeezing combining strength criterion and numerical modelling,

for different rock mass strength to in

situ stress ratios (Hoek 2000)

Strength values considered reliableStrength values estimated

Strength values considered reliableStrength values estimated

Case Histories

predictions from modelling

Support design criteria coupling analysis, modelling and in situ measurement, i.e., integrated design.

Page 33: TUNNELLING IN ROCKS – PRESENT TECHNOLOGY AND FUTURE CHALLENGES

33

Rock Support: Support Methods Today

Laboratoire de Mécanique des Roches − LMR

A wide selection of end-anchored, frictional, and fully grouted rock bolts are available.

For quick initial support, both in D&B and gripper TBM tunnelling, anchored and frictional bolts are used.To combine initial and permanent support, anchored bolts are used and followed by full grouting. Initial support by bolts, wire mesh and

shotcrete at Lötschberg base tunnel.

Page 34: TUNNELLING IN ROCKS – PRESENT TECHNOLOGY AND FUTURE CHALLENGES

34

Rock Support: Support Methods Today

Laboratoire de Mécanique des Roches − LMR

Wet-mix sprayed concrete is the main method, and often with steel fibre reinforcement (SFR).

Additives can be added to improve concrete performance, mainly to gain strength faster.

This 30 m span cavern was supported typically by fully grouted spot anchor bolts, and SFRS concrete. UAF

caverns in granite, Singapore (1999-2002).

Page 35: TUNNELLING IN ROCKS – PRESENT TECHNOLOGY AND FUTURE CHALLENGES

35

Challenges and Future Development

Laboratoire de Mécanique des Roches − LMR

Tunnelling also faces much great challenges due to geological and environmental constrains. Tunnels have to be built for large size in dense urban areas, under great depth below mountains, across deep rivers and seas. Tunnels also have to be operated safely for massive transportation, and ensure the safety under unusually circumstances such as terrorism. To large extent, the challenges to build and operate tunnels safely in modern environments have to be met by technology innovations, with research and development, training and technical exchange.

-- Jian Zhao, World Tunnel Congress 2004, Chairman’s Welcome Message

Page 36: TUNNELLING IN ROCKS – PRESENT TECHNOLOGY AND FUTURE CHALLENGES

36

Challenges and Future Development

Laboratoire de Mécanique des Roches − LMR

European Vision of Underground Construction in 2030

“Free above ground space for the use of the citizens, taking infrastructures underground.”“Underground construction will be safe and with no impact on the environment.”

--European Construction Technology Platform, 2006

Page 37: TUNNELLING IN ROCKS – PRESENT TECHNOLOGY AND FUTURE CHALLENGES

37

Challenges and Future Development

Laboratoire de Mécanique des Roches − LMR

Tunnelling Activities in Europe by 2030:• 2100 km new tunnel,• Over 500 tunnels to be refurbished,• Tunnelling a major European industry, involving

450,000 people.

Tunnelling in China by 2010:• 300 km for rail, • 150 km for road, • 100 km for metro.

This 32 km tunnel on Qinghai-Tibet rail line is to be constructed within 3 years (by 2010) by TBM and D&B,

in some poor rocks and with 1100 m overburden.

Existing tunnel

Page 38: TUNNELLING IN ROCKS – PRESENT TECHNOLOGY AND FUTURE CHALLENGES

38

Challenges and Future Development

Laboratoire de Mécanique des Roches − LMR

European Vision of Underground Construction 2030Break-through:2010 – Self learning equipment (equipment making

automatic modification during construction); Cost efficient large diameter tunnels; Intelligent lining system (automatic modification of lining with ground condition).

2020 – Breakthrough in rock cutting technology (e.g., laser cutting); Complete knowledge of geological conditions (transparent ground); Universal tunnel boring machine.

Page 39: TUNNELLING IN ROCKS – PRESENT TECHNOLOGY AND FUTURE CHALLENGES

39

Challenges and Future Development

Laboratoire de Mécanique des Roches − LMR

European Vision of Underground Construction 2030Break-through:2030 – No environmental impact (complete waste

reuse and no air and water pollution); Complete knowledge of underground facilities behaviour; Similar cost for underground and above ground infrastructures; No workers inside tunnel during construction (totally automated remotely controlled tunnel construction work).

Page 40: TUNNELLING IN ROCKS – PRESENT TECHNOLOGY AND FUTURE CHALLENGES

40

Future R&D: Excavation Machine

Laboratoire de Mécanique des Roches − LMR

Full automation of drilling jumbo and remote control.Laser and other new rock cutting technologies.Invention of pollution-free explosives.TBM to increase net penetration rate and cutter life in very hard and abrasive rocks.TBM able to excavate through complex and variable geology, i.e., universal TBM.

Page 41: TUNNELLING IN ROCKS – PRESENT TECHNOLOGY AND FUTURE CHALLENGES

41

Future R&D: Rock-Machine Interaction

Laboratoire de Mécanique des Roches − LMR

A rock mass classification scheme, incorporating appropriate rock mass properties for TBM excavation;

A TBM perfor-mance prediction model for various rock and complex geology; A guide for TBM operation in complex ground.

Rock Mass TBM

TBM Performance

Rock-TBMInteractionMechanics

GroundImprovement

TBMImprovement

TBM Design

Rock Mass TBM

TBM Performance

Rock-TBMInteractionMechanics

GroundImprovement

TBMImprovement

TBM Design

Page 42: TUNNELLING IN ROCKS – PRESENT TECHNOLOGY AND FUTURE CHALLENGES

42

Future R&D: Rock Support Mechanics

Laboratoire de Mécanique des Roches − LMR

Short and long term behaviour of complex grounds, e.g., squeezing and spalling.Effects of changing ground condition and environment on the durability and long term stability of tunnels.Support mechanism of large opening, the effectiveness of bolts.Rock support mechanism and method for tunnel under dynamic loads.

Page 43: TUNNELLING IN ROCKS – PRESENT TECHNOLOGY AND FUTURE CHALLENGES

43

Future R&D: Underground Space Safety and Environment

Laboratoire de Mécanique des Roches − LMR

Fire and safety in underground facilities.

Environmental integration during underground construction.Architecture and environment in underground space utilisation.

Proposed Underground Science City, Singapore

Page 44: TUNNELLING IN ROCKS – PRESENT TECHNOLOGY AND FUTURE CHALLENGES

44

Examples of Challenges: Unforeseen Ground Conditions?

Laboratoire de Mécanique des Roches − LMR 0.0 0.5 1.0 1.5 2.0 2.5 3.0 3.5 4.0

0

10

20

30

40

50

60

70

80

90

Ratio of borehole length to tunnel length

Cha

nges

requ

este

d:as

% o

f eng

inee

rs e

stim

ate

as

% o

f con

tract

ors

bid

(Data given by Hoek)

How much site investigation is required in orderto minimize “unforeseen”ground conditionsin tunnelling?

?

Page 45: TUNNELLING IN ROCKS – PRESENT TECHNOLOGY AND FUTURE CHALLENGES

45

Examples of Challenges: Empirical or Numerical Design?

Laboratoire de Mécanique des Roches − LMR

Case example, minimum rock separation between two near parallel tunnels, UAF Project, Singapore

Original empirical design: 15 mOptimised by numerical modelling: 8 m

Considering rock mass properties, stress conditions, effects of rock reinforcement, and construction method/sequence.

Construction implication: saved 200 m tunnelling in granite.

10 m

?

8 m

Page 46: TUNNELLING IN ROCKS – PRESENT TECHNOLOGY AND FUTURE CHALLENGES

46

Examples of Challenges: TBM in Blocky and Faulted Rocks

Laboratoire de Mécanique des Roches − LMR

Face at Lötschberg tunnel

TBMs have difficult to progress through highly fractured rock mass, faulted zones, mixed ground, squeezing and spalling rocks. A re-examine of TBM fragmentation mechanism is needed.

Page 47: TUNNELLING IN ROCKS – PRESENT TECHNOLOGY AND FUTURE CHALLENGES

47

Examples of Challenges: TBM in Rock-Soil Mixed Ground

Laboratoire de Mécanique des Roches − LMR

TBMs in mixed ground and rock-soil interface are having low advance rate, low utilization, and excessively high cutter damage and wear. Improved knowledge on excavation mechanism in complex ground is needed.

Mixed ground at granite-soil interface, Singapore DTSS tunnel

Original TBM

Page 48: TUNNELLING IN ROCKS – PRESENT TECHNOLOGY AND FUTURE CHALLENGES

48

Examples of Challenges: Rock Self-Support Mechanism

Laboratoire de Mécanique des Roches − LMR

Low load on bolts suggests rock is self-supporting. How effective are bolt and shotcrete in rock support?

Rock Conditions & Bolt Parameters

Gjovik Cavern, Norway(Based on Broch at el. 1996)

UAF Cavern, Singapore

Typical Rock Mass Quality 1~30 4~36 Vertical Stress, MPa 1 2~3Maximum Horizontal Stress 3.5 8.2Minimum Horizontal Stress 2 4.6Ratio of Horizontal to Vertical Stress 2~3.5 2~3Tunnel/cavern span, meters 61 30Type of Rock Bolts Fully grouted rebars Fully grouted boltsBolt lengths 6 (with alternating 12 m

long cables5

Spacing, meters 2.5 x 2.5 1.5~2.4 Bolt Capacity, KN 220 250Minimum Measured Loads, KN 1~1.5 3~12 Typical Measured Loads, KN 30~60 20~60Typical Load Percentage 13~27% 8~24% Maximum Measured Load, KN 87 70Max Load Percentage 40% 28%

Rock Conditions & Bolt Parameters

Gjovik Cavern, Norway(Based on Broch at el. 1996)

UAF Cavern, Singapore

Typical Rock Mass Quality 1~30 4~36 Vertical Stress, MPa 1 2~3Maximum Horizontal Stress 3.5 8.2Minimum Horizontal Stress 2 4.6Ratio of Horizontal to Vertical Stress 2~3.5 2~3Tunnel/cavern span, meters 61 30Type of Rock Bolts Fully grouted rebars Fully grouted boltsBolt lengths 6 (with alternating 12 m

long cables5

Spacing, meters 2.5 x 2.5 1.5~2.4 Bolt Capacity, KN 220 250Minimum Measured Loads, KN 1~1.5 3~12 Typical Measured Loads, KN 30~60 20~60Typical Load Percentage 13~27% 8~24% Maximum Measured Load, KN 87 70Max Load Percentage 40% 28%

Page 49: TUNNELLING IN ROCKS – PRESENT TECHNOLOGY AND FUTURE CHALLENGES

49

Examples of Challenges: Squeezing and Weak/Poor Rocks

Laboratoire de Mécanique des Roches − LMR

Although known as a stress induced problem, it is still difficult to predict and to quantify deformation and load inserted on lining, for tunnels in squeezing and weak/poor rock masses. 1.5 m of displacement in a fault zone in the

16 m span Mucha highway tunnel in Taiwan

Page 50: TUNNELLING IN ROCKS – PRESENT TECHNOLOGY AND FUTURE CHALLENGES

50

Examples of Challenges: Earthquake and Explosion

Laboratoire de Mécanique des Roches − LMR

Load Transfer

Area

Access Tunnel

Main Tunnel

Storage Chamber

Debris Traps

Sorting Area

Load Transfer

Area

Load Transfer

Area

Access TunnelAccess Tunnel

Main TunnelMain Tunnel

Storage ChamberStorage Chamber

Debris Traps

Sorting Area

Sorting Area

How does dynamic stress wave propagate in rock mass? How do rock mass and support respond to dynamic loads?How to design tunnels subjected to dynamic loads?

Safe separation distance between caverns?

Page 51: TUNNELLING IN ROCKS – PRESENT TECHNOLOGY AND FUTURE CHALLENGES

51

Examples of Challenges: Durability and Long-Term Stability

Laboratoire de Mécanique des Roches − LMR

To understand the effects of time and environment change on rock and support, and to be able to quantify structural degradation and damage.

Cracking in some old road tunnel linings in Switzerland

Page 52: TUNNELLING IN ROCKS – PRESENT TECHNOLOGY AND FUTURE CHALLENGES

52

Tunnelling in Rock: Continuing Battles

Laboratoire de Mécanique des Roches − LMR

Tunnelling is fighting through the ground. We certainly need good weapons (machines and materials). More importantly we need to know enemy (ground): what are they, and how do they respond when under attack (construction)?To win the complete battle, we must know the ground before, during and after tunnelling, i.e., in situ properties of rock, and the mechanics of rock-construction-environment interaction.

Thank You !