Inventory Management IILot Sizing
Caplice
Lecture 5ESD.260 Fall 2003
© Chris Caplice, MIT2MIT Center for Transportation & Logistics – ESD.260
Outline
EOQ ModelSensitivity AnalysisDiscounting
All UnitsIncrementalOne Time Special
© Chris Caplice, MIT3MIT Center for Transportation & Logistics – ESD.260
Assumptions: Basic EOQ ModelDemandConstant vs VariableKnown vs RandomContinuous vs Discrete
Lead timeInstantaneousConstant or Variable (deterministic/stochastic)
Dependence of itemsIndependentCorrelatedIndentured
Review TimeContinuous vs Periodic
Number of EchelonsOne vs Many
Capacity / ResourcesUnlimited vs Limited
DiscountsNoneAll Units or Incremental
Excess DemandNoneAll orders are backorderedLost ordersSubstitution
PerishabilityNoneUniform with time
Planning HorizonSingle PeriodFinite PeriodInfinite
Number of ItemsOneMany
© Chris Caplice, MIT4MIT Center for Transportation & Logistics – ESD.260
Notation
TC = Total Cost (dollar/time)
D = Average Demand (units/time)
Co = Ordering Cost (dollar/order)
Ch = Holding Cost (dollars/dollars held/time)
Cp = Purchase Cost (dollars/unit)
Q = Order Quantity (units/order)
T = Order Cycle Time (time/order)
© Chris Caplice, MIT5MIT Center for Transportation & Logistics – ESD.260
Lot Sizing: Many Potential Policies
I(t)
TimeT
Q
Objective: Pick the policy with the lowest total cost
Inve
ntor
y O
n H
and
© Chris Caplice, MIT6MIT Center for Transportation & Logistics – ESD.260
What is the total cost?
TC = Purchase + Order + Holding + Shortage Cost
Which costs are relevant? Purchase Costs Ordering CostsHolding CostsShortage Costs
( )2o h p
D QTC Q C C CQ
⎛ ⎞ ⎛ ⎞= +⎜ ⎟ ⎜ ⎟⎝ ⎠⎝ ⎠
© Chris Caplice, MIT7MIT Center for Transportation & Logistics – ESD.260
Economic Order Quantity (EOQ)
2][
QCCQ
DCQTC pho +=
2* o
h p
DCQC C
= * 2 o h pTC DC C C=
© Chris Caplice, MIT8MIT Center for Transportation & Logistics – ESD.260
Simple EOQ Example
Annual demand of widgets is 2,000. The cost of ordering is $500. Widgets are procured for $50 each and are sold for $95 each. Holding cost is estimated to be 25%.
What is the EOQ, Total Cost, and Cycle Time?
Q* = 400 unitsTC* = $5,000 / yearT* = 0.20 years or 73 days
Annual Cost vs. Order Quantity
$-
$5,000
$10,000
$15,000
$20,000
$25,000
50 150
250
350
450
550
650
750
850
950
1050
1150
1250
1350
1450
1550
1650
1750
1850
1950
Lot Size
Ann
ual C
ost
Total Cost versus Lot (Order) Size
© Chris Caplice, MIT10MIT Center for Transportation & Logistics – ESD.260
The Effect of Non-Optimal Q
Q DCo/Q ChCpQ/2 TC2000 $500 $12,500 $13,000500 $2,000 $3,125 $5,125400 $2,500 $2,500 $5,000200 $5,000 $1,250 $6,25020 $50,000 $125 $50,125
So, how sensitive is TC to Q?
© Chris Caplice, MIT11MIT Center for Transportation & Logistics – ESD.260
Sensitivity of EOQ
How does TC change with Q?
*
*
* *
( )2
( ) 2
( ) 1( ) 2
o p h
o p h
D QTC Q C C CQ
TC Q C C C D
TC Q Q QTC Q Q Q
⎛ ⎞ ⎛ ⎞= +⎜ ⎟ ⎜ ⎟⎝ ⎠⎝ ⎠
=
⎡ ⎤= +⎢ ⎥
⎣ ⎦
© Chris Caplice, MIT12MIT Center for Transportation & Logistics – ESD.260
Sensitivity of EOQ
Sensitivity TC wrt Q
90%110%130%150%170%190%
50%
63%
75%
88%
100%
113%
125%
138%
150%
163%
175%
188%
200%
213%
225%
238%
250%
263%
Q/Q*
TC/T
C*
© Chris Caplice, MIT13MIT Center for Transportation & Logistics – ESD.260
Sensitivity of EOQ
What if our estimate of demand was off?E = Actual Demand / Estimated DemandQ’ = Estimated EOQQ* = Actual EOQ, given actual demand that occurred
D ActualE = = D Estimate′ CC
CD2 = Qph
o′′
E 2E + 1 =
TCTC
*
'E =
'*
© Chris Caplice, MIT14MIT Center for Transportation & Logistics – ESD.260
Sensitivity of EOQ to Parameter Error
So, for D’ = 2000 units/year, if the actual demand was …
D E Q*/Q' TC'/TC*200 0.10 0.32 1.74
1,000 0.50 0.71 1.06 1,500 0.75 0.87 1.01 1,800 0.90 0.95 1.00 2,000 1.00 1.00 1.00 3,000 1.50 1.22 1.02 4,000 2.00 1.41 1.06
20,000 10.00 3.16 1.74
© Chris Caplice, MIT15MIT Center for Transportation & Logistics – ESD.260
Insights from EOQ
There is a direct trade off between lot size and total inventoryTotal cost is relatively insensitive to changes
Very robust with respect to changes in:Q – rounding of order quantitiesD – errors in forecastingCh, Co, Cp – errors in cost parameters
Thus, EOQ is widely used despite its highly restrictive assumptions
© Chris Caplice, MIT16MIT Center for Transportation & Logistics – ESD.260
Introduce Discounts to Lot Sizing
Types of discountsAll units discountIncremental discountOne time only discount
How will different discounting strategies impact your lot sizing decision?
© Chris Caplice, MIT17MIT Center for Transportation & Logistics – ESD.260
All Units Discount
Unit Price [Cpi ]
Price Break Quantity [PBQI]
$50.00 0
$45.00 500
$40.00 1000
© Chris Caplice, MIT18MIT Center for Transportation & Logistics – ESD.260
All Units Discount
Need to introduce purchase cost into TC function
2QCC +
QDC + DC =] CTC[Q, piho
pipi
© Chris Caplice, MIT19MIT Center for Transportation & Logistics – ESD.260
All Units Discount
Annual Costs
$80,000
$85,000
$90,000
$95,000
$100,000
$105,000
$110,000
$115,000
100
300
500
700
900
1100
1300
1500
1700
1900
Lot Size
Dol
lars
© Chris Caplice, MIT20MIT Center for Transportation & Logistics – ESD.260
All Units Discount
Annual Costs
$80,000
$85,000
$90,000
$95,000
$100,000
$105,000
$110,000
$115,000
100
300
500
700
900
1100
1300
1500
1700
1900
Lot Size
Dol
lars
© Chris Caplice, MIT21MIT Center for Transportation & Logistics – ESD.260
All Units Discount: Method
1 Cpi $40.00 $45.00 $50.00
2 PBQ 1000 500 0
3 EOQ[Cpi] 447 421 400
4 Qpi 1000 500 400
5 DCpi $80,000 $90,000 $100,000
6 CoD/Qpi $1,000 $2,000 $2,500
7 ChCpiQpi/2 $5,000 $2,812 $2,500
8 TC[Qpi] $86,000 $94,812 $105,000
Same Example: D=2000 Units/yrCh=.25Co=$500
Cpi Price Breaks: $50 for 0 to <500 units$45 for 500 to <1000 units$40 for 1000+ units
© Chris Caplice, MIT22MIT Center for Transportation & Logistics – ESD.260
Incremental Discount
© Chris Caplice, MIT23MIT Center for Transportation & Logistics – ESD.260
Incremental Discount
Annual Cost
$80,000$90,000
$100,000$110,000$120,000$130,000$140,000$150,000
100
300
500
700
900
1100
1300
1500
1700
1900
2100
2300
2500
2700
2900
Lot Size
$/ye
ar
© Chris Caplice, MIT24MIT Center for Transportation & Logistics – ESD.260
Incremental Discount
Index i=3 i=2 i=1
1 Cpi $40.00 $45.00 $50.00
2 PBQi 1000 500 0
3 Fi $7500 $2500 $0
4 EOQ[Cpi] 1789 1033 400
5 Qpi 1789 400
6 Cpe $44.19 $50.00
7 DCpe $88,384.57 $100,000
8 CoD/Qpi $558.97 $2,500
9 (Ch C pe Qpi)/2 $9,882.50 $2,500
10 TC[Qpi] $98,826.04 $105,000
© Chris Caplice, MIT25MIT Center for Transportation & Logistics – ESD.260
One Time Discount
© Chris Caplice, MIT26MIT Center for Transportation & Logistics – ESD.260
Let, Cpg = One time deal purchase price ($/unit)Qg = One time special order quantity (units)TCsp=TC over time covered by special purchase ($)
Then, g g
pg h pg osp g g
Q QTC [ /D] = + + Q QC C C C
2 D
One Time Discount
© Chris Caplice, MIT27MIT Center for Transportation & Logistics – ESD.260
One Time Discount
C + DQ
2Q
CC + QC =/D] QTCsp[ ogg
pghgpgg
C + D
)Q-Q(2
QCC +
DQ
2Q
CC + )Q-Q(C + QC =/D] Q[TCw
go
wgwph
wwpghwgpwpggnsp
© Chris Caplice, MIT28MIT Center for Transportation & Logistics – ESD.260
One Time Discount
CQC +
CC
)DC-C( = Q
pg
wp
hpg
pgpg
*
2
1 - QQ
CCC =] QSAVINGS[
w
g*
p
pgog
*
⎦
⎤
⎣
⎡
© Chris Caplice, MIT29MIT Center for Transportation & Logistics – ESD.260
One Time Discount
A quick numerical example...
D = 2000 units / yearCo = $500.00 / orderCh = 25%Cp = $50.00 / unitQ* = 400 unitsTC* = $5000.00 / year
Cpg = $45.00 / unitQ*g = 1333Savings* = $2448.25