Edition 2 / Revision 1 TRANSPORT FOR NSW
June 2020
TRANSPORT FOR NSW (TfNSW)
SPECIFICATION GUIDE NR44
GUIDE TO QA SPECIFICATION R44
EARTHWORKS
REVISION REGISTER
Ed/Rev
Number
Clause
Number Description of Revision
Authorised
By Date
Ed 1/Rev 0 First issue.
Ed 2/Rev 0 Updated to accord with R44 Ed 4 Rev 1.
Ed 2/Rev 1 Global References to “Roads and Maritime
Services” or “RMS” changed to
“Transport for NSW” or “TfNSW”
respectively.
DCS 22.06.20
Edition 2 / Revision 1 TRANSPORT FOR NSW
June 2020
SPECIFICATION GUIDE NR44
GUIDE TO QA SPECIFICATION R44 EARTHWORKS
Copyright – Transport for NSW IC-QA-NR44
VERSION FOR:
DATE:
Guide to R44 Earthworks NR44
Ed 2 / Rev 1 i
CONTENTS
CLAUSE PAGE
1 GENERAL ........................................................................................................................................ 1 1.1 Introduction .................................................................................................................... 1 1.2 Scope .............................................................................................................................. 3 1.3 Structure of Specification ............................................................................................... 5 1.4 Definitions ...................................................................................................................... 6 1.5 Earthworks Plan.............................................................................................................. 9 1.6 Surveying ...................................................................................................................... 12 1.7 Protection of Earthworks .............................................................................................. 12
2 EARTHWORKS MATERIALS .......................................................................................................... 13 2.1 General ......................................................................................................................... 13 2.2 Materials Management ................................................................................................. 13 2.3 Topsoil .......................................................................................................................... 13 2.4 Unsuitable Material ...................................................................................................... 15 2.5 Spoil .............................................................................................................................. 17 2.6 Stockpile Sites .............................................................................................................. 18 2.7 Borrow Sites ................................................................................................................. 19 2.8 Material in Upper Zone of Formation and Verges ....................................................... 20
3 FOUNDATIONS .............................................................................................................................. 22 3.1 General ......................................................................................................................... 22 3.2 Foundations for Embankments ..................................................................................... 22 3.3 Foundation Treatment for Hillside Embankments ....................................................... 27 3.4 Foundation Treatments for Cuttings ............................................................................. 28 3.5 Shallow Embankment and Cut/Fill Transition ............................................................. 34
4 CUTTINGS ..................................................................................................................................... 37 4.1 General ......................................................................................................................... 37 4.2 Excavation .................................................................................................................... 37 4.3 Cuttings in Rock ........................................................................................................... 38 4.4 Batter Tolerances .......................................................................................................... 38 4.5 Benching in Cuttings .................................................................................................... 39 4.6 Pre-splitting or Line Drilling ........................................................................................ 40 4.7 Blasting ......................................................................................................................... 40
5 EMBANKMENTS ............................................................................................................................ 42 5.1 General ......................................................................................................................... 42 5.2 Earth Fill Embankments ............................................................................................... 43 5.3 Rock Fill Embankments ............................................................................................... 46 5.4 Embankment Batters .................................................................................................... 48 5.5 Rock Facing of Embankments ...................................................................................... 49 5.6 Fill Placed Adjacent to Structures ................................................................................ 50
6 STRUCTURAL TREATMENTS ......................................................................................................... 51 6.1 Upper Zone of Formation ............................................................................................. 51 6.2 Verges ........................................................................................................................... 53 6.3 Other Treatments .......................................................................................................... 54
7 ADDITIONAL CONFORMITY REQUIREMENTS ............................................................................... 54 7.1 General ......................................................................................................................... 54 7.2 Earth Fill ....................................................................................................................... 54
NR44 Guide to R44 Earthworks
ii Ed 2 / Rev 1
7.3 Rock Fill ...................................................................................................................... 57 7.4 Deflection Testing........................................................................................................ 58 7.5 Level Control ............................................................................................................... 60
ANNEXURE R44/A – PROJECT SPECIFIC INFORMATION ........................................................................ 62 A1 Surveys (Clause 1.6) .................................................................................................... 62 A2 Materials ...................................................................................................................... 63 A3 Foundation Treatment .................................................................................................. 65 A4 Shallow Embankment, Cut/Fill Transition, Upper Zone of Formation and Verges .... 66 A5 Compaction Moisture Requirements (Clause 7.2) ....................................................... 67 A6 Blasting (Clause 4.7).................................................................................................... 68
ANNEXURE R44/B – MEASUREMENT AND PAYMENT ........................................................................... 70
ANNEXURE R44/C – SCHEDULES OF HOLD POINTS, WITNESS POINTS AND IDENTIFIED RECORDS ...... 77 C1 Schedule of Hold Points .............................................................................................. 77 C2 Schedule of Witness Points .......................................................................................... 77 C3 Schedule of Identified Records .................................................................................... 78
ANNEXURES R44/D TO R44/K – (NOT USED) ....................................................................................... 78
ANNEXURE R44/L – TEST METHODS, MINIMUM FREQUENCY OF TESTING AND ACCEPTANCE
CRITERIA ..................................................................................................................................... 79
ANNEXURE R44/M – REFERENCED DOCUMENTS .................................................................................. 87
LAST PAGE OF TFNSW R44 (EXCLUDING SUPPLEMENTARY SECTION ON BLASTING) IS ....................... 88
Guide to R44 Earthworks NR44
Ed 2 / Rev 1 iii
FOREWORD
Guide NR44 is not a contract document. It has been prepared to assist readers of TfNSW R44 with
guidance as to the intent of R44 and understanding of the Principal’s expectations for earthworks.
Normal shaded text replicates text found in TfNSW R44. The text in italics provides commentary on
the various R44 clauses.
This Guide is based on Specification R44 Edition 4 Revision 1 (April 2013).
(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)
Ed 2 / Rev 1 1
SPECIFICATION GUIDE NR44
GUIDE TO QA SPECIFICATION R44
EARTHWORKS
1 GENERAL
1.1 INTRODUCTION
The purpose of earthworks is to create a stable formation suitable for the pavement to be constructed
so that it meets its intended life. Earthworks is undertaken using materials from within the site, or if
suitable materials are not available from within the site, using suitable materials from offsite.
Earthworks must be executed in conjunction with other processes including, but not limited to, surface
and subsurface drainage works and environmental control measures.
The earthwork formation comprises a series of earth or rock structures, which must be constructed by
the controlled excavation and placement of materials, and the use of associated Structural Treatments.
The material in the Upper Zone of Formation must be selected, placed and controlled to achieve the
best possible support for the road pavement.
The execution of earthworks involves safety and environmental risks, and the requirements of the
relevant TfNSW Specifications for safety and environmental protection must be complied with.
All earthworks jobs are different.
When designing and constructing earthworks, it is essential that all types of loads expected during
service as well as all likely failure modes are taken into account.
Dead loads and live loads must be considered. Failure due to dead loads can be sudden, such as
slope stability failure of a cut or a fill; or gradual, such as settlement of a fill adjacent to a fixed
bridge abutment or shrink/swell of a moisture sensitive material during seasonal climate changes.
Failures due to live loads from traffic are usually evidenced by surface distortion as a result of large
deflections at the top surface of the formation. These can happen during construction or following
completion as a result of vehicular traffic.
Earthworks generally use the natural materials occurring on the job, with the prime aim being to
provide a stable platform out of those materials on which a pavement for traffic can be constructed.
The main issues to be addressed are:
slope stability of cuttings and embankments (short term during construction and long term).
foundation stability of cuttings and embankments (short term during construction and long term).
volumetric stability of embankments (long term shrink/swell due to moisture changes, or long term
settlement due to poor initial compaction). This might also be expressed as dimensional stability.
What we want, as far as possible, is for the constructed earthworks to stay exactly as they were
placed.
stability of the top of earthworks to enable vehicle movements during pavement construction and
to resist vehicular loads transferred by the pavement during service.
surface edge and slope protection during and after construction to prevent erosion.
It is therefore essential that earthworks structures be designed to manage the materials expected and
encountered on site. The detailed materials investigation must be integrated with the geometric design
(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)
NR44 Guide to R44 Earthworks
2 Ed 2 / Rev 1
process, together with careful pre-construction planning, in order to avoid unnecessary delays during
construction.
The main factor which affects an earthworks job is the effect of wet weather. Where possible, seasonal
effects should be taken into account when planning the timing of earthworks projects. Also, where
possible, major earthworks involving moisture-sensitive materials should not be planned to commence
when wet winter weather is approaching. Too often, in these conditions, the working days are short
and evaporation rates are low, making it very difficult for materials to dry out.
In such cases where it is not practicable to defer commencement, special treatments such as
stabilisation of materials or, subject to geotechnical advice, permitting construction of lower layers at
higher than normal moisture contents, could be considered during the planning stage.
In many cases, it is possible to anticipate the measures needed to establish foundations. This and
other constructability issues need to be thought through before going to tender and their implications
understood. Doing so will ensure that appropriate provisions and pay items are included (which may
involve job-specific amendments to the model specification after geotechnical consultation and thus
assist the TfNSW representative during construction to make decisions which are both quick and also
correct.
During construction, it is particularly important that decisions required of the TfNSW representative
on the treatment of foundation areas are made quickly, as foundation areas are particularly
susceptible to damage by rain or seepage and any delays will increase the risk of damage and even
further delays.
(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)
Guide to R44 Earthworks NR44
Ed 2 / Rev 1 3
1.2 SCOPE
The work to be executed under this Specification is summarised in Table R44.1.
Table R44.1 – Summary of Earthworks Process
Task Reference
General – Prepare and submit for consideration an EARTHWORKS PLAN and
PROJECT QUALITY PLAN. Protect the earthworks and the environment by
installing and maintaining effective drainage, and control measures for erosion and
sedimentation. Set out the earthworks by survey, and carry out surveys for process
control and determining quantities.
Clause 1
Materials – Manage the use of materials from within the site, stockpile sites, remove
and stockpile topsoil, remove, replace or treat any unsuitable material, spoil or borrow,
and import materials as necessary.
Clause 2
Foundations – Prepare and compact the floors of cuttings, cut/fill transitions and
foundations for embankments, including subsurface drainage, and the use of drainage
layers, bridging layers, stabilisation, and geotextiles/geogrids as Foundation
Treatments.
Clause 3
Cuttings – Excavate cuttings with specified benches, drainage and batter tolerances.
Blasting of rock may be required.
Clause 4
Embankments – Place and compact suitable material to the specified dimensions and
batter tolerances, including subsurface drainage and the use of rock facing, Select Fill
to structures, stabilisation, and geotextiles/geogrids. Control the quality of material for
the Upper Zone of Formation.
Clause 5
Structural Treatments – Where shown on the Drawings, supply, place and compact
Upper Zone Material and verge material to the specified quality over the full length of
the earthworks, or provide other geotechnical treatments as required.
Clause 6
Conformity Requirements – Complete the earthworks to the specified quality and
tolerances. Undertake all inspection and testing necessary to demonstrate that the
quality requirements of this Specification are achieved.
Clause 7
The earthworks process outline by activity sequence is given in Figure R44.1.
(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)
NR44 Guide to R44 Earthworks
4 Ed 2 / Rev 1
Figure R44.1 – Earthworks Process Outline By Activity Sequence
Notes:
(a) Notwithstanding that some clearing and grubbing may be necessary before erosion and sedimentation
control can commence, staged construction of drainage works including sedimentation control, culverts,
catch drains and ancillary activities must generally precede clearing and grubbing activities.
(b) Pavement construction is to be carried out to the appropriate TfNSW specifications (shown as “
TfNSW ** ” above) included within the Contract.
Batter treatment
Clause 4.2
Excavate cutting
to DFL
Clause 4
Foundation
Treatments
Clause 3.2
R44 Process Outline Erosion and
Sedimentation
Control
TfNSW G38
Clear and Grub
TfNSW G40 One-way
interaction
Two-way
Interaction
Remove
topsoil
Clause 2.3
Cut
or
Fill
Cutting Embankment
Unsuitable
Material
Clause 2.4
Excavate
embankment
foundations
Clause 3
Terracing
Clause 3.3
Foundation
Treatments
Clause 3.4
Shallow
Embankmen
t
Clause 3.5.1
Cut/Fill
Transition
Clause 3.5.2
Embankment
Construction
Clause 5
Structural
Treatments
Clause 6
Pavement
construction
TfNSW **
Conformity
Requirements
Clause 7
(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)
Guide to R44 Earthworks NR44
Ed 2 / Rev 1 5
This figure should be studied carefully to understand the arrangement of the specification clauses
relative to the actual construction sequence. It also indicates the other major sections of the
specification which may be relevant to a particular activity.
1.3 STRUCTURE OF SPECIFICATION
This Specification includes a series of Annexures that detail additional requirements.
1.3.1 Project Specific Information
Details of work specific to this Contract are shown in Annexure R44/A.
The completion of Annexure A prior to tendering must not be done without a fully detailed site
investigation and careful thought given to an earthworks management plan. Each project will have
different materials to work with and different requirements to be specified. It is also important that
environmental requirements are known as these could affect the way the work is carried out; e.g.
restrictions may be placed on blasting, vibration, dust, working hours, etc.
1.3.2 Measurement and Payment
The method of measurement and payment is detailed in Annexure R44/B.
As for the previous annexure, EVERY pay item should be considered here. THIS IS ONE OF THE
MOST IMPORTANT PARTS OF A DOCUMENT AS IT DESCRIBES JUST HOW EACH WORK ITEM
WILL BE MEASURED AND PAID FOR. Good documents will have EVERY pay item reviewed and a
conscious decision made on which items are relevant to this project and which are not. The specific
wording for each item should be checked and proof-read by someone independent of the production of
the documents and the person responsible for estimated quantities must be aware of the specific words
which describe how each work item is to be measured and paid. Following compilation of the
documents in draft form, this section, together with the estimated quantities should be reviewed for
sensibility, i.e. provide a reality check with the question “Does this look reasonable?” If documents
are compiled hastily, it is very easy for errors to be made with unintentional results.
Additional pay items may need to be developed where an item of work is not covered by the provisions
in the model. Alternatively, the definition of a pay item may be modified. Particular care is needed
with this when job-specific changes are made.
If a quantity cannot reasonably be estimated or if we are unsure if the item will be required at all, the
item of work should be labelled as “provisional” and a nominal quantity attached to the item. Care
should be taken when nominating the provisional quantities and also in tender evaluation to ensure
that the effect on tender prices reflects the risk of the work item, i.e. the extended price for that item
does not unfairly skew the apparent order of tenders.
It is important that every member of the supervisory team be aware of the methods specified for
measurement and payment before the work commences. Good teamwork between Surveillance
Officers and survey staff will ensure that adequate warning is given and enable staff to manage the
task. At times, site staff from both the Contractor and TfNSW will be hard pushed to measure all
quantities in short timeframes. In such cases, for smaller and more easily measured quantities, it is
often preferable to agree with the Contractor on quantities and for quantity agreement sheets to be
signed by both Contractor and TfNSW site representatives. In making such agreements, the financial
significance of minor discrepancies in the measurements needs to be considered when determining the
level of accuracy for the measurements in the field.
(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)
NR44 Guide to R44 Earthworks
6 Ed 2 / Rev 1
1.3.3 Schedules of HOLD POINTS, WITNESS POINTS and Identified Records
The schedules in Annexure R44/C list the HOLD POINTS and WITNESS POINTS that must be
observed. Refer to Specification TfNSW Q for the definitions of HOLD POINTS and WITNESS
POINTS.
The records listed in Annexure R44/C are Identified Records for the purposes of TfNSW Q
Annexure Q/E.
This list is crucial to the control of processes and quality on the project and should not be negotiated.
Prior to commencement of work on site, the TfNSW Contract Manager and his/her staff should
arrange a meeting with the Contractor and staff to ensure these hold and witness points are
understood by everyone who supervises the work. Thereafter, constant communication between
Surveillance staff and their counterparts on progress with the work and regular reminders on these
hold points is essential to the efficient management of the project. Good communication and
appropriate action will build trust. Dealing with Hold Points and Witness Points should be
considered in the Surveillance Management Plan.
1.3.4 Planning Documents
The PROJECT QUALITY PLAN must include each of the documents and requirements shown in
Clause 1.5 and must be implemented.
If the Contract does not require you to implement a PROJECT QUALITY PLAN, the documents
shown in Clause 1.5 must be submitted to the Principal for consideration at least 5 working days prior
to work commencing and must be implemented.
1.3.5 Minimum Frequency of Testing
The Inspection and Test Plan must nominate the proposed testing frequency to verify conformity of
the item, which must not be less than the frequency specified in Annexure R44/L. Where a minimum
frequency is not specified, nominate an appropriate frequency. Frequency of testing must also
conform to the requirements of TfNSW Q.
1.3.6 Referenced Documents
Unless otherwise specified or is specifically supplied by the Principal, the applicable issue of a
referenced document is the issue current at the date one week before the closing date for tenders, or
where no issue is current at that date, the most recent issue.
Standards, specifications and test methods are referred to in abbreviated form (e.g. AS 2350). For
convenience, the full titles are given in Annexure R44/M.
1.4 DEFINITIONS
All personnel involved in the administration of contracts should familiarise themselves with these
terms and ensure that correct terminology is used at all times. This is particularly important in
written communications. Only by using correct terminology can we communicate accurately with
other people involved in the contract.
The terms “you” and “your” mean “the Contractor” and “the Contractor’s” respectively.
The following definitions apply to this Specification:
Borrow site An area (either within or outside the Site), other than cuttings and specified
excavations, from which material may be excavated for placing in embankments.
(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)
Guide to R44 Earthworks NR44
Ed 2 / Rev 1 7
Capping layer A layer of graded rock material of sizes varying between 19 mm and 150 mm,
placed over rock fill as a transition layer between rock fill layers and the overlying
earth fill layer(s) in an embankment.
Contaminated
material
Material classified as Restricted, Hazardous or Special Waste in accordance with
EPA Waste Classification Guidelines.
Cutting An earth or rock excavation within the Site that is made below an existing surface to
create the road formation.
Designed Floor
Level
The level of excavation in a cutting at the underside of the Selected Material Zone.
Drainage layer A layer located at the foundation of the formation in an embankment or a cutting,
constructed of free draining material with grading as specified in Clauses 3.2.5 and
3.4.5. The purpose of the layer is to provide a pathway for the free drainage of
excess water from the foundations of embankments or cuttings. The drainage layer
is usually wrapped in geotextile to prevent its contamination or blockage over time
from adjacent fine grained material.
Earthworks The activities covered by this Specification.
Earth fill See Clause 5.2. Material consisting of fine material and coarse particles distributed
throughout the layer filling voids so that when compacted produces a dense stable
embankment.
Embankment An earth or rock fill structure above an existing and/or excavated surface to create
the road formation.
Floor of cutting The trimmed base of the cutting excavation at either the level of the Designed Floor
Level or at the level of the Foundation Level depending on the type of foundation
treatment shown on the Drawings or directed by the Principal.
Formation The earthworks structure including all Foundation and Structural Treatments on
which the road pavement will be constructed.
Foundation
Level
The level from which the formation is constructed. This is the level achieved after
excavation is undertaken for foundation treatments and the removal of unsuitable
material.
Foundation
Treatment
A special layer or treatment zone at the base of a formation for the purpose of
reinforcing, strengthening or drainage.
General fill Embankment material other than the Upper Zone of Formation, and Foundation
Treatments.
Imported
material
Material incorporated into the earthworks from sources other than that generated by
excavation in cuttings and other specified excavations.
Joint survey See Specification TfNSW G71. A survey carried out in the presence of, or in
conjunction with, the Principal’s surveyor.
Limit of Works A boundary within which the contracted works are undertaken. This is either
indicated in Specification TfNSW G1 or shown on the Drawings.
(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)
NR44 Guide to R44 Earthworks
8 Ed 2 / Rev 1
Road
Formation
Same as Formation.
Rock fill See Clause 5.3. Material composed of hard, sound, durable rock with only a small
amount of fine particles, which when placed and compacted produces an
embankment deriving its stability from the mechanical interlock of the coarser
particles and not from the compaction of finer material.
Roller pass Compactive effort of a single movement of the roller over all segments of the Lot
nominated in the PROJECT QUALITY PLAN.
Select Fill Fill material of specified quality placed against or adjacent to structures (refer
Clause 5.6). This material is different from Selected Material (see below).
Selected
Material
Material of specified quality used in the Selected Material Zone as specified in
Clause 2.8.3 and Annexure R44/A2.2.
Selected
Material Zone
The top part of the Upper Zone of Formation in which material of a specified higher
quality is required – see Figures R44.2 (a) and (b).
Shallow
Embankment
A part of an embankment where the height from the Stripped Surface Level to the
Top of Formation is less than the height specified in Annexure R44/A4.
Spoil Spoil is surplus material from excavations under the Contract which is not required
to complete the Works as specified, and/or contaminated material or material from
excavations under the Contract whose quality renders it unacceptable for
incorporation in the Works.
Stripped
Surface Level
Level of the surface after stripping of topsoil.
Structural
Treatment
A special layer or zone within a formation for the purpose of reinforcing or
strengthening. It also includes other treatments where shown on the Drawings or
directed by the Principal.
Topsoil Topsoil is natural surface soil that may contain organic matter.
Cut/Fill
Transition
Zone
The area of special formation treatment where the road formation transitions from a
cutting to an embankment, as shown in Figure R44.6(b), and described in Clause
3.5.2.
Unsuitable
Material
Unsuitable material is that occurring below the Designed Floor Level of cuttings
and below the Stripped Surface Level of embankments, which the Principal deems
to be unsuitable for embankment or pavement support in its existing position in
accordance with Clause 2.4.
It excludes materials excavated for Foundation Treatment Types C1 to C5 inclusive.
The Principal will deem any contaminated material occurring below the Designed
Floor Level of excavations and below the Stripped Surface Level beneath
embankments to be unsuitable material if it cannot remain in its existing position.
Upper Zone of
Formation
The Upper Zone of Formation includes the Selected Material Zone and is the top
part of the formation. The depth and quality of the material is specified in
Annexure R44/A4 and R44/A2.2 respectively.
(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)
Guide to R44 Earthworks NR44
Ed 2 / Rev 1 9
Verge material Material placed in the zone adjacent to the edge of the pavement which is subjected
to occasional traffic from vehicles leaving the pavement, comprised of materials
which have the specified mechanical properties set out in Annexure R44/A2.2.
Upper Zone
Material
Material of specified quality used in the Upper Zone of Formation.
Working
platform
See Foundation Treatment and Structural Treatment. A construction technique
(even if directed).
[See Figures R44.3(a) to (e) for details of Foundation Treatment types for embankments]
Figure R44.2(a) – Embankment Nomenclature
[See Figures R44.5(a) to (d) for details of Foundation Treatment types for cuttings]
Figure R44.2(b) – Cutting Nomenclature
1.5 EARTHWORKS PLAN
The Earthworks Plan is a document detailing the Contractor’s planned movement of material
throughout the work. It should identify expected quality and quantity of materials throughout the work
and how the Contractor proposes to deal with them. To be useful, it must show a range of estimated
quantities of each type of material in each cutting and where it is planned to use these materials in the
various embankments or other works being constructed under the contract, i.e. the quality, quantity
and movement plan for all materials must be shown, based on the best information available at the
time.
Designed Finished Surface Level
Selected Material Zone
General Fill (zoned construction may be required - see Drawings)
MEDIAN (dual carriageways only) BATTER
Pavement
Topsoil (may be removed)
Top of Formation
Foundation Level
Verge or Pavement (see Drawings)
Upper Zone of Formation
Selected Material Zone
may extend to edge
- see Drawings
Designed Floor Level *
MEDIAN (dual carriageways only)
Designed Finished Surface Level
Selected Material Zone
BATTER
Top of Formation Pavement
Cutting Floor Foundation Treatment
Refer to Drawings
for drainage details
Verge or Pavement (see Drawings)
Upper Zone of Formation
Foundation Level
Selected Material Zone may extend to edge - see Drawings
* unless shown otherwise on the Drawings
Height of
embankment
(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)
NR44 Guide to R44 Earthworks
10 Ed 2 / Rev 1
It is essential that this document be prepared by the Contractor and that the TfNSW Contract Manager
examines and discusses the Plan with the Contractor before the work begins. While the times for
revision are specified, the plan should be discussed at regular (monthly as a minimum) meetings with
the Contractor. It is also important that whenever it is necessary to depart from the Plan, the reasons
for each departure are recorded at the time of the departure so that, if necessary, the TfNSW Contract
Manager will be able to evaluate the effect on the construction program.
The EARTHWORKS PLAN must address all requirements and constraints imposed by the
Specification, the physical conditions at the site and your proposed work methods. The
EARTHWORKS PLAN must include details of:
(a) excavation sequence and proposals for the management of all materials in the earthworks for
each construction stage, including the use of topsoil and surplus excavated material resulting
from other works under the Contract (such as trenching for drainage pipes or utility conduits);
(b) procedures for the management of excavation and placement of earth and rock fill in
embankments and rock facing, to ensure that no deficiency of fill material occurs including a
mass haul diagram detailing the types and quantities of materials to be excavated from each
cutting, and the locations within the Works for placement of the materials (refer Clauses 2.1,
2.2, 4, 5 and 7);
(c) procedures to ensure the effective use of nominated stockpile sites, including maximising the
volume of material to be stored at each location. Do a preliminary assessment of likely
stockpiled quantities and the available quantities that can be placed in nominated stockpile
areas. Any inadequacies must be brought to the attention of the Principal together with other
potential stockpile sites (refer Clause 2.6);
(d) procedures proposed for procuring and managing materials from borrow sites or imported
materials where applicable (refer Clause 2.7);
(e) preliminary identification of zones of potentially unsuitable materials, and management of the
disposal and replacement of the unsuitable materials (refer Clause 2.4);
(f) methods to be employed to ensure that materials of the specified or higher quality are identified,
made available and incorporated into the Works at the locations where the quality of the
material has been specified. The details will include any sorting, isolating, processing, and
placement of the materials proposed for such use. Processing may include screening, crushing,
blending, and modification of materials (refer Clauses 2.8 and 6);
(g) methods to be employed to ensure that all materials placed within the Works conform to
maximum stone (or rock) size and other dimensional requirements, where specified (refer
Clauses 2.8, 3 and 5);
(h) procedures proposed for the treatment of foundations (refer Clause 3);
(i) sources of, and testing proposed for, materials in Upper Zone of Formation, Shallow
Embankments and verges (refer Clause 2.8);
(j) methods to demonstrate that the specified compaction has been achieved over the full depth of
each layer and that the specified layer thickness is not exceeded (refer Clauses 5, 6 and 7);
(k) procedures proposed for protection of earthworks, including drainage of working areas,
minimising ingress of excess water into earthworks, dealing with over-wet materials and over-
dry materials (refer Clause 1.7);
(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)
Guide to R44 Earthworks NR44
Ed 2 / Rev 1 11
(l) locations and extent of each Cut/Fill Transition Zone (refer Clause 3.5.2); and
(m) procedures to ensure that damage does not occur to adjacent structures from blasting, or by
hammering or ripping during excavation, or from vibrating compaction plant.
There is a need to ensure that construction water quality does not compromise the design life of either
pavement or structures in contact with earthworks (including via leachates or runoff). An example is
the adverse effects which can arise from the use of saline water for compaction or from the
incorporation of acid generating soils or rocks within the works without appropriate control
measures.
Specific requirements should be included in R44 and other specification parts for those cases where
there is known to be a potential problem. A possible approach would be to include construction water
sources in the earthworks plan, with a requirement to demonstrate the suitability if other than potable
water is being proposed. That would cover changes to sources of water quality during construction
and allow flexibility in assessment to suit the types of structures and other in service environmental
considerations.
In the event that water quality cannot be adequately controlled, changes to the design or specification
of pavement and/or structures would be needed. It must be emphasised that any problems may need
not show up until well after the end of the specified defect liability period, so the temptation to deal
with the issue by simply ignoring it must be resisted.
In such cases, similar changes would need to be made to other spec parts, as relevant, including R11,
R22, R57, R58, B30 and possibly G1, G36 and G38. It is essential to keep consistency between the
different parts when job specific changes are being made. Likewise it is important to ensure that
changes to one part do not end up compromising another, given the high level of cross-referencing
between parts.
Notwithstanding the staged submission provisions of Specification TfNSW Q, provide the
EARTHWORKS PLAN in its entirety with the first stage submission of the PROJECT QUALITY
PLAN.
Amend the EARTHWORKS PLAN in accordance with the requirements of Specification TfNSW Q.
Submit to the Principal an updated EARTHWORKS PLAN:
(a) at intervals not exceeding three months during the currency of the Contract;
(b) within two weeks of any change of the EARTHWORKS PLAN for any Milestone or for the
Works; and
(c) within two weeks of receipt of the Principal's determination in respect of the earthworks
construction, if such determination alters any details in the EARTHWORKS PLAN.
An updated EARTHWORKS PLAN must show:
(i) the same level of detail as specified for the original EARTHWORKS PLAN;
(ii) the “as-built” EARTHWORKS PLAN in respect of all work completed up to the date of
updating; and
(iii) reasons for any deviation from the previously submitted EARTHWORKS PLAN, and actions if
any, to correct any deviation within your control.
(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)
NR44 Guide to R44 Earthworks
12 Ed 2 / Rev 1
1.6 SURVEYING
1.6.1 Setting Out of Earthworks
The position and extent of all cuttings and embankments shown on the Drawings and transitions from
cuttings to embankments must be marked, using pegs and batter profiles or equivalent, prior to
commencement of construction. Setting out must take into account any formation widening necessary
to accommodate the design requirements.
Where the Specification refers to dimensions or setting out relevant to the underside of the Selected
Material Zone, and the Drawings do not provide for a Selected Material Zone, adopt the dimensions
for setting out relevant to the underside of the pavement.
1.6.2 Joint Survey
Where specified in Annexure R44/A1 or where directed by the Principal, carry out a joint survey in
accordance with Specification TfNSW G71. The Survey Report, where specified, must include a
computer file containing data in a format that is suitable for creating accurate models using the
standard TfNSW CADD software.
1.6.3 Specified Surveys
To determine quantities for payment or for process control, carry out the surveys specified in
Annexure R44/A1.
1.7 PROTECTION OF EARTHWORKS
Your responsibility for care of the Works includes the protection of earthworks. Specifically:
(a) Install and maintain effective erosion and sedimentation control measures in accordance with
Specification TfNSW G35 or G36, and Specification TfNSW G38 or G39.
(b) Maintain drainage of all working areas at all times to ensure run-off of water without scour,
except where ponding is off the formation and forms part of a planned erosion and
sedimentation control system. Do not allow water to pond in the working areas resulting in
wetting up of the existing pavement or formation or foundation material.
It also means that sub-surface flow must be cut off to avoid wetting up of placed fill or backfill.
(c) When rain is likely, or when no work is planned for the following day in a particular area being
worked, take precautions to minimise any ingress of water into the earthworks material. Seal
off ripped material remaining in cuttings, and material placed on embankments, using a smooth
drum roller.
(d) Should earthworks material become over-wet (above the specified moisture content for
compaction), you are responsible for replacing and/or drying out the material, and for any
consequent costs. Refer also to Clauses 2.4 and 7.2.
(e) Do not allow the earthworks material to dry out to the point where excessive shrinkage occurs in
the embankment, and the surface is pulverised by traffic generating excessive dust.
(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)
Guide to R44 Earthworks NR44
Ed 2 / Rev 1 13
2 EARTHWORKS MATERIALS
2.1 GENERAL
You are responsible for:
(a) any of your assumptions made in relation to the nature and types of the materials as encountered
in excavations or imported, and the bulking and compaction characteristics of all such materials
which are then incorporated in the Works;
(b) determining suitable sources of material and any processing needed to satisfy the quality
requirements; and
(c) the design, and the cost of construction and/or maintenance of all tracks, roads, haul roads, pads
and other earthworks structures required for the proper execution of the Works.
General earthworks includes all types of material, both earth and rock, encountered during excavation
and placed in embankments or disposed of in other than embankments.
When surplus excavated material from other works under the Contract (such as trenching for drainage
pipes or utility conduits) is used in the construction of embankments, the requirements of this
specification also apply to such material.
Unless otherwise specified, do not place imported material in the Works until all material of suitable
quality available from the cuttings in the Works has been placed or has been assigned to be placed in
the formation.
If you cause a deficiency of material for embankment construction and other specified materials, by
electing not to use acceptable material from excavations in the embankments or by constructing
embankments with dimensions other than those shown on the Drawings or authorised in accordance
with Clause 5.4, you must make good that deficiency from sources of material meeting the quality
requirements specified in Clause 5. The cost of making good such deficiency of material will be borne
by you.
2.2 MATERIALS MANAGEMENT
Manage your procurement of materials, whether obtained from sources external to the Site or from
nominated sources or from within the Site, to ensure that the materials incorporated into the
earthworks is of the specified quality.
The EARTHWORKS PLAN must include a mass haul diagram detailing the types and quantities of
materials to be excavated from each cutting, and the locations within the Works for placement of the
material (refer Clause 1.5, item (b)).
2.3 TOPSOIL
2.3.1 Removal of Topsoil
Commence removal of topsoil on any section of the Works only after erosion and sedimentation
controls have been implemented and clearing, grubbing and removal of cleared materials has been
completed on that section of the Works.
(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)
NR44 Guide to R44 Earthworks
14 Ed 2 / Rev 1
Topsoil is usually removed as it contains a quantity of vegetable matter which is weak structurally and
because it is a source of seed and nutrients needed for re-spreading over and re-vegetation of
completed work.
The depth of topsoil directed by the Principal should be sufficient to remove vegetation material which
would be deleterious to earthworks, keeping in mind the needs of the project for spreading topsoil over
disturbed areas for revegetation of the site. It is undesirable to allow stripping depths to markedly
exceed the true topsoil depth as the resulting product may be unusable for the purpose of re-
vegetation.
Care should be exercised in determining depths of topsoil removal and in estimating the quantities
which will be generated. Standardised nominal depths, unrelated to the actual site conditions, should
not be used. These depths are normally chosen using site investigation data.
Often, if deeper fills are being constructed and the foundation conditions are suitable, topsoil and
grass can be left in place provided it is in a flat, level ground and will not compromise the stability of
the embankment. Construction sites usually have very limited space for stockpiles. This is
particularly the case, where sedimentation basins are necessary, clearing needs to be minimised and
the road boundaries are very narrow. The removal and stockpiling of materials needs to be carefully
considered in the planning phase.
Do not remove topsoil in locations where a bridging layer is to be constructed in accordance with
Clause 3.2.2, unless directed otherwise by the Principal.
Where specified in Annexure R44/A2.1 or where directed by the Principal, after removal of the
topsoil,:
(i) stockpile the topsoil within the Site separately from other materials and clear of the Works for
use in revegetation, or
(ii) stockpile the topsoil as a windrow longitudinally and adjacent to the toe of embankment batter,
or
(iii) spoil the topsoil outside the Site in accordance with Clause 2.5.1; or
(iv) if the topsoil has been identified as contaminated material, spoil the topsoil in accordance with
Clause 2.5.2.
2.3.2 Topsoil Stockpiles
Locate topsoil stockpiles in accordance with Clause 2.6.
Before stockpiling topsoil, carry out a survey in accordance with TfNSW G71 to determine the surface
levels at each stockpile site at sufficient locations to later determine the volumes of topsoil placed at
the site. When shown in Annexure R44/A1, the survey must be a joint survey in accordance with
Clause 1.6.
Topsoil stockpiles must:
(a) be free from subsoil, other excavated materials, contaminated materials, refuse, clay lumps and
stones, timber or other rubbish;
(b) be trimmed to a regular shape to facilitate measuring with a height not exceeding 2.5 m and
batter slopes not steeper than 2H : 1V;
(c) have their batters track rolled or stabilised by other means acceptable to the Principal; and
(d) be seeded with a sterile cover crop in accordance with Specification TfNSW R178, to encourage
vegetation cover. Seeding must be carried out progressively within seven days of completion of
each 500 m2 of exposed batter face.
(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)
Guide to R44 Earthworks NR44
Ed 2 / Rev 1 15
2.3.3 Survey after Removal of Topsoil
After removing the topsoil, determine the surface levels in each cutting and embankment at sufficient
locations to determine the volume of excavation for general earthworks and the volume of unsuitable
material.
When shown in Annexure R44/A1, the survey must be a joint survey in accordance with Clause 1.6.
HOLD POINT
Process Held: Any works which will alter the ground surface as surveyed.
Submission Details: At least three working days before the proposed date for altering the
surfaces, submit a Survey Report of the existing surface levels, and a
notification that the set out specified in Clause 1.6.1, including set out of the
cut/fill intersection point and extent of the Transition Zone as specified in
Clause 3.5, have been carried out.
Release of Hold Point: The Principal will inspect the surfaces and set out, and may direct further
action prior to authorising the release of the Hold Point. Further action may
include altering the limits of the cut/fill transition.
2.4 UNSUITABLE MATERIAL
After the stripping of topsoil covering each embankment foundation, or upon reaching the Designed
Floor Level, or Foundation Level, of cuttings, subsequent earthworks processes are held (refer to Hold
Points in Clauses 3.2 and 3.4) to allow inspection of the foundation.
Where unsuitable material is found, such unsuitable material must be excavated to the extent directed
by the Principal.
Identification of unsuitable material is a difficult task, requiring not only physical inspection and
possibly testing of material but also a great deal of judgement on the part of the decision-maker. For
any particular material, variation in moisture content will provide differences in the strength of the
material. Some materials will lose strength rapidly with increased moisture content, whilst others will
not.
In the foundations for embankments higher than approximately 1.5 metres, the main consideration is
usually to ensure that the foundation provides a reasonable platform for subsequent earthworks. (In
the case of very soft deep soils, special measures need to be taken in the design of the foundations and
these are not detailed in this specification.)
Under deep embankments, the quality of the material itself is rarely an issue in the long term and the
cause of the “unsuitable” is usually its high moisture content in situ. Whilst it can be argued that the
material itself is not unsuitable, it is often impractical to try and adjust the moisture content to allow it
to be compacted. Quick decisions on treatment, including the use of bridging layers will allow
earthworks to proceed without undue delay.
For embankment foundations less than 1.2 metres from the top of Selected Material Zone and also for
the Designed Floor Level of cuttings, testing of the material to determine its in situ properties is
usually necessary. It should be pointed out that such testing will take time and that sufficient time
needs to be allowed for in construction programs to allow the testing to take place.
Decisions to remove unsuitable material should be made as quickly as they conveniently can, as it is at
this stage that the foundation areas are exposed to weather. Wet weather and subsequent wetting up
(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)
NR44 Guide to R44 Earthworks
16 Ed 2 / Rev 1
of foundation material will cause the material to be difficult to handle and will delay earthworks
operations.
Removal and replacement of unsuitable material in the foundations for embankments has been the
cause of many delays. Such delays can generally be avoided or minimised by timely decisions and
directions which minimise disruptions to the earthworks program. A quick decision which avoids a
delay but which results in a small cost for material removal, is usually a good decision.
Experienced Geotechnical Scientists and experienced Surveillance Officers can provide practical
advice on the need for removal of unsuitable and the best ways to treat foundation areas.
A useful distinction is to divide “unsuitable” into three categories:
Inherently unsuitable. The material cannot be included in the works, even as general earthworks
because of its inherent properties (e.g. peat and muck, some silts). It would normally be spoiled.
It is best dealt with by specifying it to be spoiled, rather than going through the process of testing
it and then making the decision. This type of material mostly (but not always) occurs in culvert or
embankment foundations and may be recognised at the pre-tender stage.
Where possible, the embankments should be made high enough so that this type of material can be
bridged over. This saves much time and effort. If embankments are too low, the offending
material will have to be removed and replaced, under adverse circumstances and at the unsuitable
rate. The actual volume to be handled will be greater than if the level had been raised and the
cost will be higher by a factor of typically three to five. Any apparent saving in earthworks
volume (measured from the nominal “stripped surface”, pre-tender) is illusory.
Unsuitable by virtue of position. This is the issue that the R44 clause actually deals with e.g. low
CBR material in the floor of cuts. Where there are extensive areas of such materials it is often
possible to recognise them and deal with them using one of the foundation treatments in Clause 3
e.g. extensive low CBR materials in cuts can be dealt with using the C2 or C3 floor treatment.
Material of this type is usually acceptable for incorporation in general earthworks,
“Unsuitably wet”. The major problem with the material is excessive moisture (although it may
also fall into the second category). This is usually encountered following periods of rain or in
cases where the site has been inundated. There are various options: dry, stabilise, spoil, use as is.
The decision will depend on many factors, most of which are specific to the job e.g. earthworks
balance, embankment design, material characteristics, availability of spoil or borrow sites,
availability of sites to dry the materials, climate, implications for long term performance.
Where a treatment can be designated at the pre-tender stage, there will be a significant saving in time
and cost, as the offending material can be removed as part of general earthworks and the need to stop
and wait for testing (which often simply confirms what is already known) can be avoided.
Promptly notify the Principal of any areas of the foundation or any layer within the formation that rut
excessively, yield or show signs of distress or instability.
HOLD POINT
Process Held: Replacement of each Lot of unsuitable material.
Submission Details: Notification that unsuitable material has been removed as directed.
Release of Hold Point: The Principal will inspect the excavation and may direct removal of further
material as unsuitable material prior to authorising the release of the Hold
Point.
Incorporate any material removed as unsuitable in embankments in accordance with Clause 5, unless
directed to spoil in accordance with Clause 2.5.
(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)
Guide to R44 Earthworks NR44
Ed 2 / Rev 1 17
Remove from the site any contaminated materials that cannot be treated and re-used within the Works,
or stockpiled on the site. Remove such material from the site in accordance with Clause 2.5 of this
specification, and Specification TfNSW G35 or G36 as appropriate.
Replace any material that has been removed in accordance with this Clause with either:
(a) suitable material in accordance with Clause 5.1; or
(b) if directed, with foundation treatments in accordance with Clause 3 or as shown on the
Drawings.
The replacement of unsuitable material is deemed to form part of embankment construction.
If you allow any material to become unsuitable because of your inappropriate construction activities,
all costs associated with reworking or replacing such unsuitable material must be borne by you.
Examples of inappropriate construction activities include poor surface drainage, restricted or
inoperative subsurface drains, contamination, excessive sized construction plant where the imposed
load exceeds the material strength, poorly maintained construction plant allowing leakage of oils and
water onto the formation, and leaving the surface unsealed allowing moisture ingress during wet
weather.
Before and after removal of unsuitable material, carry out a survey in accordance with Specification
TfNSW G71 to determine the surface levels at sufficient locations to later determine the volume of
unsuitable material removed. Where shown in Annexure R44/A1, the survey must be a joint survey in
accordance with Clause 1.6. Alternatively, the Principal may agree to determination of volume by
measurement and calculation.
2.5 SPOIL
2.5.1 Non-contaminated Materials
Except for contaminated materials, dispose of spoil generated from the Works under the Contract in
the manner and at locations authorised or agreed to by the Principal. Use up all available areas within
the site before proposing alternative locations.
Dispose of non-contaminated material by the following means:
(a) flatter batter slopes being provided on embankments; or
(b) uniform widening of embankments; or
(c) stockpiling within the site; or
(d) disposal at an approved off-site location.
Embankment widening or batter flattening work is deemed to form part of the embankment
construction and must be carried out in accordance with Clause 5. Spread and compact the spoil as
specified in Clauses 5 and 7 for material in embankments. Maintain effective drainage for the whole
of the embankment.
For spoil locations outside the limits of the Works, obtain all necessary written approvals, including
environmental approvals, and provide copies to the Principal seven days prior to commencing the
disposal of material offsite. Such spoil material located outside of the Site is deemed to be your
property.
Re-use of spoil
(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)
NR44 Guide to R44 Earthworks
18 Ed 2 / Rev 1
Excavated public road materials (EPRM) are defined by the Environment Protection Authority (EPA)
as comprising any of the following materials: uncontaminated waste rock, soil, sand, bitumen and
asphalt products, gravel, slag from iron and steel manufacturing, fly and bottom ash and concrete,
excavated during the construction and maintenance of roads and road infrastructure facilities.
EPRM may be applied to land within a road corridor for public road related activities including road
construction and maintenance and installation of road infrastructure facilities provided all conditions
attached to the EPA’s resource recovery exemption “The excavated public road material exemption
2012” are complied with.
Virgin Excavated Natural Material (VENM) and Excavated Natural Material (ENM)
Materials classified as virgin excavated natural material (VENM), as defined in the POEO Act may be
applied to land provided its use is consistent with land use zoning and planning consents.
Materials that meet the definition of excavated natural material (ENM) as defined by the EPA’s
resource recovery exemption “The excavated natural material exemption 2012” may be transported
and applied to land off-site provided all conditions attached to the ENM exemption are complied with
and provided its use is consistent with land use zoning and planning consents.
Section 143 Notices
A completed and signed section 143 notice (POEO Act) must be obtained from the landholder prior to
transporting and applying any materials to a site that is not owned by TfNSW and is not a licensed
landfill in accordance with TfNSW Specifications G35 or G36. The landholder must provide written
evidence that planning consent has been given for the material to be deposited on the site (e.g. local
council development consent or a letter from the council stating that the activity is exempt
development) and you must attach this written evidence to the completed section 143 notice.
Payment for disposal of spoil within the limits of the Works is deemed to be included in the rates
generally. However, where an approved location for spoil disposal is outside the limits of the Works,
payment for disposal of spoil will be made under Pay Item R44P6 or Pay Item R44P1.2.
2.5.2 Contaminated Materials
Contaminated materials must be stockpiled and/or removed from the site in accordance with Clause
2.4 of this Specification and Specification TfNSW G35 or G36, as applicable. If disposal methods and
sites are not specified, it is your responsibility to determine the location(s) and method(s) for the
disposal of the contaminated material.
Notify the Principal at least 24 hours prior to the removal of any contaminated material from the
Works, and provide details of the proposed method and location of disposal.
Payment for excavation and stockpiling of contaminated material on site will be made under Pay Item
R44P1.2 or Pay Item R44P2. Additional payment will be made under Pay Item R44P8 for the
identification, treatment, classification in accordance with EPA Waste Classification Guidelines and
disposal of the contaminated material at sites legally authorised to accept the contaminated material.
Treatment and disposal of contaminated material caused by your operations will be at no cost to the
Principal.
2.6 STOCKPILE SITES
There should be sufficient sites available for the storage of topsoil required for later re-use on site and
these should be located as close as possible to the locations from which the material is removed, with
access available for convenient recovery later in the project.
(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)
Guide to R44 Earthworks NR44
Ed 2 / Rev 1 19
Locate stockpile sites so that they are outside the drip lines of trees and such that material from the
stockpiles does not enter drainage lines or watercourses. Arrange stockpile sites to minimise damage
to natural vegetation and trees and maintain the existing surface drainage. Locate the stockpile sites
such that the stockpiled material is accessible for carting away at any time.
Carry out any clearing and grubbing required for these sites in accordance with Specification TfNSW
G40. Install and maintain appropriate erosion and sedimentation control measures, in accordance with
Specification TfNSW G38 or G39.
The Principal will only consider requests for new stockpiles sites if all stockpile sites nominated on the
Drawings have already been allocated for full use. You must obtain all the necessary written
approvals, including environmental approvals, and provide copies of such approvals to the Principal
when seeking to use a stockpile site other than those nominated. Such requests must be made at least
ten working days before stockpiling is due to commence, specifying the maximum dimensions of the
proposed stockpile.
Following completion of the Works, carry out restoration of the stockpile sites in accordance with
Specification TfNSW R178.
2.7 BORROW SITES
2.7.1 General
Detail the selection and quality control of materials obtained from borrow sites in the
EARTHWORKS PLAN. Materials to be incorporated in the Works must comply with the
requirements of this Specification.
Where any material is to be obtained from borrow sites, site preparation must be in accordance with
Clause 2.3.1 of this Specification and Specification TfNSW G40. Carry out restoration of borrow sites
in accordance with Specification TfNSW R178.
2.7.2 Specified Borrow Sites
Where borrow sites are specified, the edges of any batter from the resulting excavation must not be
closer than 3 m to any existing or proposed fence line, road reserve boundary or edge of excavation or
embankment. Borrow sites must have adequate drainage outlets.
Cut batter slopes must be as specified in Annexure R44/A2.1, and the borrow sites must be left in a
tidy and safe condition and meet the requirements of Specification TfNSW G35 or G36, as applicable.
Proper planning of the project and consideration of the earthworks balance and materials expected on
site should minimise the likelihood of surprises during the contract. Where it is likely they will be
needed, borrow sites should be identified in the Specification and testing for material qualities should
be carried out as part of the site investigation work.
2.7.3 Contractor Arranged Borrow Sites
For borrow sites arranged by you, take responsibility for obtaining any permits required for entry on to
the land and for payment of any royalty for such borrow material.
Comply with any requirements of the Environmental Planning and Assessment Act, Office of Rural
Affairs, Department of Planning and Infrastructure, Natural Resources Commission, the local
Councils, and landowners as appropriate. Provide copies of all approvals to the Principal ten days
prior to commencing work at these borrow sites.
(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)
NR44 Guide to R44 Earthworks
20 Ed 2 / Rev 1
You are responsible for all costs involved in opening up, maintaining and restoring any borrow sites
arranged by you.
2.8 MATERIAL IN UPPER ZONE OF FORMATION AND VERGES
The material placed in the Upper Zone of Formation must be selected, placed and controlled to meet
the Contract requirements. The Upper Zone of Formation in embankments consists of 2 main
components as shown in Figure R44.2. The top component of Upper Zone of Formation is the
Selected Material Zone.
2.8.1 Material Source
Unless specified to be imported in Annexure R44/A2.1 (from sources as detailed in
Annexure R44/A2.1), obtain Upper Zone Material of the specified quality from cuttings or borrow
sources from within the Limit of Works.
In the event of a planned or unplanned shortage of site won Upper Zone Material, source the imported
material from those detailed in Annexure R44/A2.1, unless otherwise approved by the Principal.
Where the source of imported material is not specified in Annexure R44/A2.1, source them from
legally operating quarries or recycling facilities or other sources acceptable to the Principal. Provide
the Principal with details of the proposed source locations, quantities and types of material before the
imported material is delivered to site.
Prior to testing, pre-treat any Upper Zone Material which may be susceptible to breakdown or
weathering, by crushing to size, artificial weathering in accordance with Test Method TfNSW T103
and repeated compaction in accordance with Test Method TfNSW T102 (Method A).
Before placement of material from any source, establish the response of that material to pre-treatment
and adopt an appropriate pre-treatment regime for subsequent conformity testing.
This is important as such materials may change their strength characteristics significantly as they are
handled during the earthworks processes. Whilst they may appear to be satisfactory by testing
material in a cutting or borrow pit, we need to be able to predict their quality after compaction when
they are in place in the formation. Pre-treatment by artificial weathering and repeated compaction is
an attempt to simulate the breakdown of material which will occur in the actual construction.
2.8.2 Upper Zone of Formation Material other than Selected Material
2.8.2.1 Site Won Material
Material in the Upper Zone of Formation for the thickness and depth specified in Annexure
R44/A4, must:
(a) have a CBR value as that stated in Annexure R44/A2.2;
(b) have a Plasticity Index (PI) value as that stated in Annexure R44/A2.2;
(c) (i) be free from stone larger than 100 mm maximum dimension; and
(ii) have no less than 50% passing the 19.0 mm AS sieve.
This requirement is an attempt to avoid problems with subsequent installation of barrier rail
posts, guideposts, signposts and subsoil drainage. If material is stabilised to produce these
qualities, difficulties with subsequent operations involving excavation or driving posts through
it, may arise.
(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)
Guide to R44 Earthworks NR44
Ed 2 / Rev 1 21
2.8.2.2 Imported Material
Sources and quality of imported material must be as detailed in Annexure R44/A2.1 and
R44/A2.2 respectively, or approved by the Principal.
Clause 2.8.2.1 part (c) also applies to the imported material.
2.8.3 Selected Material
2.8.3.1 Site Won Selected Material
Material excavated from within the Site and processed, placed and compacted in the Selected
Material Zone must:
(a) have a characteristic CBR value as stated in Annexure R44/A2.2, for the fraction passing
19.0 mm AS sieve; and
(b) have a PI value as stated in Annexure R44/A2.2;
(c) (i) be free from stone larger than 100 mm maximum dimension; and
(ii) have no less than 50% passing the 19.0 mm AS sieve.
When modification of the material is specified in Annexure R44/A4 or shown in the Drawings
to be required for purposes other than to only meet the specified CBR requirements in Annexure
R44/A2.2 (for example, as part of structural treatment in Clause 6), or directed, the Selected
Material immediately prior to incorporation of the binder must satisfy the requirements stated in
the preceding paragraph.
These properties must be specified for each job and the values specified should only be
determined following proper site investigation, interpretation of results and planning of the
earthworks operation by experienced personnel. We should ensure that realistic values are
specified and that the material can reasonably be available to the contractor at a time during
the contract when it is required.
2.8.3.2 Imported Selected Material
Material imported for the Selected Material Zone must meet the requirements of Specification
TfNSW 3071.
Specification drafters should ensure that the specified materials are available at reasonable
costs. TfNSW 3071 may not be appropriate or cost-effective and the properties of known
economical sources for the area should be specified.
2.8.4 Verge Material
The intention is to supply material which can be compacted in thin layers (hence maximum size is
specified) and which will have reasonable ability to carry errant traffic in service. Knowledge of site
materials and locally available quarried materials should provide and economical solution
2.8.4.1 Site Won Verge Material
Material excavated from within the Site and processed, placed and compacted in the verges
must meet the following requirements:
(a) have a CBR value as stated in Annexure R44/A2.2, for the fraction passing 19.0 mm
AS sieve; and
(b) have a PI value within the range specified in Annexure R44/A2.2;
(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)
NR44 Guide to R44 Earthworks
22 Ed 2 / Rev 1
(c) be free from stone larger than 50 mm maximum dimension and have no less than 50%
passing the 19.0 mm AS sieve.
2.8.4.2 Imported Verge Material
Material imported to the project site and placed and compacted in the verges must meet the
requirements of TfNSW 3071 for Selected Material Type B and must:
(a) have a CBR value not less than that specified in Annexure R44/A2.2, for the fraction
passing 19.0 mm AS sieve; and
(b) have a PI value within the range specified in Annexure R44/A2.2.
If, prior to tender, TfNSW 3071 is considered too restrictive and uneconomical, it should be
modified to suit the project.
2.8.5 “Spill-Through” Bridge Abutment Fill Material
For both Type ST1 material (at waterway crossings) and Type ST2 material (at overbridges), the fill
material must:
(a) have a CBR value as that stated in Annexure R44/A2.2;
(b) have a PI value as that stated in Annexure R44/A2.2;
(c) have a grading of 100% passing the 53 mm sieve.
3 FOUNDATIONS
3.1 GENERAL
Embankment foundation treatments are applied after removal of unsuitable material, excavating
further in Shallow Embankment areas to provide a minimum embankment height (refer to Clause
3.5.1), and where relevant, terracing of hillside embankment foundations.
Foundation treatments in cuttings are applied after excavation to the Designed Floor Level and
removal of unsuitable material.
Taking into account the site, traffic, access, environmental/climatic conditions and insitu materials,
select your equipment and techniques and use them in such a manner that minimises surface heaving
or other foundation damage during preparation of the foundation and construction of overlying layers.
Construct other measures (such as trench and foundation drains, constructed in accordance with
Specification TfNSW R33) in conjunction with the foundation treatments, as shown on the Drawings,
or as authorised or directed by the Principal.
3.2 FOUNDATIONS FOR EMBANKMENTS
After preparation of the foundation area, present the embankment foundation area for inspection by the
Principal prior to placing embankment materials.
(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)
Guide to R44 Earthworks NR44
Ed 2 / Rev 1 23
HOLD POINT
Process Held: Treatment of each Lot of embankment foundation.
Submission Details: (a) Survey report;
(b) Notification of completion of: clearing operations;
and,
(c) in the areas other than beneath Shallow Embankments, notification of:
(i) topsoil removal in accordance with Clause 2.3; or
(ii) flattening/mowing of grasses if indicated on the Drawings or
specified;
or,
(d) in the areas beneath Shallow Embankments:
(i) notification that topsoil has been removed and surface excavated in
accordance with Clause 3.5.1; and
(ii) CBR and PI test results, if required in accordance with Clause
3.5.1.
Release of Hold Point: The Principal:
(a) will consider the submitted documents;
(b) may inspect the excavated floor for the embankment foundation; and
(c) may direct further action prior to authorising the release of the Hold
Point. Further action may include removal of unsuitable material in
accordance with Clause 2.4, or treatment in accordance with Clause 3.2.
Maintain the embankment foundation in its conforming condition until embankment construction
commences. You must bear the cost of additional foundation treatments required as a result of
damage to the foundations that is caused, or allowed to occur, by you.
Treat all foundations for embankments in accordance with Type E1, unless otherwise shown on the
Drawings or specified in Annexure R44/A3, or directed or authorised by the Principal, to treat
foundations for embankments in accordance with Type E2 to Type E6, installed individually or in
combination.
These treatments are described below and depicted in Figures R44.3 (a), (b), (c), (d) and (e) or under
Clause 3.2.6
Every effort should be made to anticipate appropriate treatments and indicate on the Drawings where
they are to be applied. Use provisional items where the need for a treatment or its extent will be
determined by factors such as weather.
3.2.1 Type E1 Treatment – Loosen and Compact
Unless otherwise specified or directed by the Principal, and after any unsuitable material has been
treated or replaced, the remaining area of the foundation must be:
(i) prepared for embankment construction by loosening by ripping the material exposed (to a depth
of 300 mm);
(ii) terracing as required by Clause 3.3;
(iii) adjusting the moisture content of the loosened material; and
(iv) compacting to the specified relative compaction specified in Clause 7.
(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)
NR44 Guide to R44 Earthworks
24 Ed 2 / Rev 1
There will often be difficulties here in compacting material, particularly in relation to moisture
contents when moistures in situ are higher than optimum. The practicality of adjusting moisture needs
to be considered and some relaxation of requirements will usually be necessary. In cases where
moistures are high and wet weather interrupts earthworks, TfNSW geotechnical experts should be
consulted to identify if a relaxation can be achieved.
Where loosening and re-compaction is impractical, consideration should be given to one or more of
the alternatives in the following clauses, depending on the circumstances. The situation regarding
moisture contents will differ from the above in drier areas (ie west of the range).
Figure R44.3(a) – Embankment Foundation Treatment Type E1 – Loosen and Compact
No account will be taken of the volume involved in loosening when measuring the volume of
excavations for payment.
3.2.2 Type E2 Treatment – Bridging Layer
Where specified or where directed by the Principal, or where you demonstrate that it is impracticable
to achieve the degree of compaction specified for the foundation in Clause 7, the Principal may
approve the placement of a bridging layer.
Do not place a bridging layer within the depth below the underside of the pavement stated in Annexure
R44/A3. The thickness of the bridging layer must not exceed the value stated in Annexure R44/A3.
Figure R44.3(b) – Embankment Foundation Treatment Type E2 – Bridging Layer
The bridging layer must be constructed from earth fill or rock fill materials conforming to the
requirements of Clauses 5.2 or 5.3. If earth fill is used, it must consist of granular material with strong
mechanical interlock and low sensitivity to moisture. The bridging layer material must provide a
stable platform upon which a conforming earthworks layer can be constructed.
Topsoil
(removed)
Earth Fill / Rock Fill
Designed Finished Surface Level
Selected Material Zone
MEDIAN (dual carriageways only) BATTER
Pavement Top of Formation
Verge or Pavement (see Drawings)
Upper Zone of Formation
Selected Material Zone
may extend to edge
- see Drawings
Foundation Level
Unsuitable Material
(replaced as required)
Loosened and Compacted
Topsoil
(usually left in place)
Earth Fill / Rock Fill
Geotextile
(if directed) Bridging Layer
Designed Finished Surface Level
Selected Material Zone
MEDIAN (dual carriageways only) BATTER
Pavement Top of Formation
Verge or Pavement (see Drawings)
Upper Zone of Formation
Selected Material Zone
may extend to edge
- see Drawings
Foundation Level
Refer Annex A3 for minimum depth from
underside of pavement to top of bridging layer
(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)
Guide to R44 Earthworks NR44
Ed 2 / Rev 1 25
The material must be end-dumped and spread in a single layer with a thickness no greater than that
specified in Annexure R44/A3 and of sufficient thickness to allow the passage of earthmoving
equipment over the bridging layer with minimal surface heaving. The compaction requirements of
Clause 7 do not apply to the bridging layer.
Bridging should only be used when the foundation cannot be compacted. The bridging layer is a
construction expedient, to allow the work to proceed, and is not an inherently desirable method of
building an embankment. It must be remembered that bridging is an uncompacted layer which will be
compressed/compacted by the weight of the overlying material etc. Its presence will eventually result
in deformation of the surface. Therefore:
bridging material should normally be coarse, free-draining material which will not break down in
service
Material quality in bridging layers should not be compromised. Particularly avoid the placement
of moisture susceptible materials (e.g. “clay bridging”) and very coarse materials with a high
void content, into which overlying material may infiltrate over time.
The thickness of bridging layers should be kept to the minimum necessary to allow fully compliant
construction of the overlying layers.
The practice of placing multiple bridging layers should be avoided.
Compaction of layers immediately above bridging needs to be conducted with care, particularly
avoiding the use of large vibrating rollers, to prevent the development of compaction-induced pore
pressures and de-stabilisation of the embankment.
If specified or directed by the Principal, place a geotextile complying with the quality requirements of
Specification TfNSW R63. Payment for the geotextile will be made under Pay Item R44P7.3(a).
The purpose of the geotextile is to prevent infiltration of fines from one layer to another at some later
time. A geotextile will normally be used at the boundary of a free-draining layer and could be at the
top, as well as at the bottom of a bridging layer.
3.2.3 Type E3 Treatment – Working Platform
Where specified or where directed by the Principal, strengthen the insitu material to form a Working
Platform on which to construct the formation. The Working Platform is created by the chemical
stabilisation of insitu material in accordance with Specification TfNSW R50.
Alternatively, a Working Platform of imported stabilised material may be specified in Annexure
R44/A2.1 or directed by the Principal.
Figure R44.3(c) – Embankment Foundation Treatment Type E3 – Working Platform
Topsoil
(removed or overlain
by Working Platform)
Earth Fill / Rock Fill
Working Platform
Designed Finished Surface Level
Selected Material Zone
MEDIAN (dual carriageways only) BATTER
Pavement Top of Formation
Verge or Pavement (see Drawings)
Upper Zone of Formation
Selected Material Zone
may extend to edge
- see Drawings
Foundation Level
(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)
NR44 Guide to R44 Earthworks
26 Ed 2 / Rev 1
When specified or directed, this work will be paid for under the appropriate Pay Items in Specification
TfNSW R50, and this Specification for Imported Material (Pay Item R44P3).
3.2.4 Type E4 Treatment – Geotextile/Geogrid Layer(s)
Where specified or directed by the Principal, construct Type E4 treatment, consisting of a layer or
layers of geotextile and/or geogrid. Supply and place the geotextile and geogrid in accordance with
Specifications TfNSW R63 and TfNSW R67 respectively.
Figure R44.3(d) – Embankment Foundation Treatment Type E4 – Geotextile/Geogrid Layer(s)
3.2.5 Type E5 Treatment – Drainage Layer
Where specified or directed by the Principal, treat embankment foundations with a drainage layer
consisting of a rock layer enclosed by geotextile.
Figure R44.3(e) – Embankment Foundation Treatment Type E5 – Drainage Layer
Shape and trim the embankment foundation to ensure drainage of the embankment. Ensure that post
construction, a clear drainage path through the layer is maintained, particularly at the outer edges of
the embankment.
Construct the drainage layer so that the completed thickness of the layer is that shown in Annexure
R44/A3, and comprising material meeting the properties in Table R44.2.
Topsoil
(removed or
overlain by Geotextile)
Geotextile / Geogrid
(one or more layers)
Earth Fill / Rock Fill
Designed Finished Surface Level
Selected Material Zone
MEDIAN (dual carriageways only) BATTER
Pavement Top of Formation
Verge or Pavement (see Drawings)
Upper Zone of Formation
Selected Material Zone
may extend to edge
- see Drawings
Foundation Level
Topsoil
(removed or overlain
by Drainage Layer)
Earth Fill / Rock Fill
Geotextile
Drainage Layer
Designed Finished Surface Level
Selected Material Zone
MEDIAN (dual carriageways only) BATTER
Pavement Top of Formation
Verge or Pavement (see Drawings)
Upper Zone of Formation
Selected Material Zone
may extend to edge
- see Drawings
Foundation Level
(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)
Guide to R44 Earthworks NR44
Ed 2 / Rev 1 27
Table R44.2 – Drainage Layer Material Properties
Property Requirement
Maximum dimension 125 mm
Percentage passing:
19.0 mm AS sieve 0 – 15%
1.18 mm AS sieve 0 – 5%
75 m AS sieve < 0.5%
Percentage of + 19.0 mm fraction with
Is(50) < Annexure R44/A2.2
10% (max)
Wet/Dry Strength Variation Annexure R44/A2.2
Adjust the grading of the drainage layer as necessary within the above limits to ensure that it provides
a stable foundation for compaction of the overlying embankment.
Place and spread the drainage layer material in such a way as to avoid segregation and to ensure that it
is not contaminated with foreign materials. Compact the layer using the nominated compaction
routine developed as specified in Clause 7.3.
Place a geotextile of Strength Class C and Filtration Class 5 in accordance with Specification TfNSW
R63, at both the interface between the rock layer and the embankment foundation, and the interface
between the rock layer and the embankment fill.
Provide outlet/drainage treatment at the ends as shown on the Drawings or directed by the Principal.
3.2.6 Type E6 - Other Treatments
Adopt other foundation treatments as shown on the Drawings or as directed or agreed by the Principal.
3.3 FOUNDATION TREATMENT FOR HILLSIDE EMBANKMENTS
Where embankments are to be constructed on or against any slopes or batter of existing embankments
(including batters resulting from the partial construction of embankments under the Contract), and the
existing slope or batter is steeper than 10H:1V in any direction, cut horizontal terraces into such slopes
or batters which will be covered by the embankment to be constructed.
Step the existing slope or batter progressively in successive terraces, each at least 1 metre in width as
shown in Figure R44.4. Cut the terraces to a minimum depth of 300 mm at the steps except where the
existing slope or batter is 4H:1V or steeper, in which case the terraces must be cut to a minimum depth
of 600 mm at the steps.
(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)
NR44 Guide to R44 Earthworks
28 Ed 2 / Rev 1
Figure R44.4 – Hillside Terracing Requirements
Cut the terraces progressively as the embankment is placed.
Inspect the floor of each terrace in accordance with Clause 2.4 to check for any unsuitable material.
Unless directed otherwise by the Principal, incorporate the material thus excavated in embankments in
accordance with Clause 5, or spoil it off site in accordance with Clause 2.5.
No account will be taken of the material removed in terracing when determining the general
earthworks excavated volume.
The purpose of terracing is to provide a roughened “saw-tooth” surface on the natural slope and to
ensure the freshly-place embankment is “keyed into” the natural slope, so that a potential slip surface
between the old and new material is removed. The cutting into the existing slope should be done just
before a new layer is placed as it can be done conveniently at this time by using the surface of the
previous layer as a working platform. The material cut from the terrace can if suitable, be mixed with
and incorporated into the next layer with minimal disruption to the work.
Consideration also needs to be given to the potential for springs under the embankment and the need
to construct drainage in conjunction with the terraces. This drainage should be incorporated in the
design drawings where possible.
3.4 FOUNDATION TREATMENTS FOR CUTTINGS
Excavate cuttings to the Designed Floor Level. The finished levels of the excavated cutting floor must
comply with the tolerances given in Clause 7.5.
Prior to placing formation materials and carrying out any designed foundation treatments, the cutting
floor must be tested and presented for inspection by the Principal. Determine the CBR and PI values
of the material in the floors of cuttings by the Test Methods stated in Annexure R44/A2.2.
Topsoil (removed)
Natural Surface Level
Material to be removed
Minimum depth of terrace:
for slope > 4H:1V 600 mm
for slope > 10H:1V and < 4H:1V 300 mm
Terraces not required on slopes < 10H:1V
(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)
Guide to R44 Earthworks NR44
Ed 2 / Rev 1 29
HOLD POINT
Process Held: Treatment of each Lot of floors of cuttings.
Submission Details: (a) Notification that:
(i) excavation to Designed Floor Level; and
(ii) depth specified for Cut/Fill Transition Zone (refer to Clause 3.5),
has been reached;
(b) CBR and PI test results.
(The submission must be concurrent with the submission for any adjoining
Shallow Embankment foundation required by the Hold Point in Clause 3.2.)
Release of Hold Point: The Principal:
(a) will consider the submitted documents;
(b) will inspect the excavated floor; and
(c) may direct further action prior to authorising the release of the Hold
Point.
Further action may include the removal of unsuitable material in accordance
with Clause 2.4; installation of trench drains in accordance with
Specification TfNSW R33, or foundation treatments in accordance with
Clause 3.4, treatment in accordance with Specification TfNSW R50, or other
treatments in accordance with this Clause or changes to the area to be
excavated.
Treat foundations within cuttings in accordance with Type C1, unless otherwise shown on the
Drawings or specified in Annexure R44/A.3 or directed or authorised by the Principal to treat
foundations within cuttings in accordance with Foundation Treatments Type C2 to Type C5.
The treatments are described below and depicted in Figures R44.5 (a), (b), (c) and (d), in Clause 3.4.4
for Type C4 Treatment – Geotextile and Geogrids, and in Clause 3.4.6 for Other Treatments. These
may be applied individually or in combination, as specified in Annexure R44/A3.
Where CBR and PI conform to the requirements of Annexure R44/A2.2, loosen and recompact the
underlying material in accordance with Foundation Treatment Type C1. Where the CBR of the
material in the floor of the cutting is less than, or where the PI is greater than the requirement
nominated in Annexure R44/A2.2, remove the material to the appropriate depth to provide for the
directed foundation treatment (Foundation Treatment Types C2 to C5).
Maintain the cutting floor in its conforming condition until any subsurface drainage is completed and
backfilling and construction of Upper Zone of Formation commence.
You must bear the cost of treatment selected for your convenience or required as a result of damage to
the foundations caused by, or allowed to occur by you.
3.4.1 Type C1 Treatment – Loosen and Compact
Unless shown on the Drawings or otherwise specified or directed by the Principal, treat the floors of
cuttings as described below.
(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)
NR44 Guide to R44 Earthworks
30 Ed 2 / Rev 1
(a) Following excavation and removal of unsuitable material, loosen all material remaining in the
floor by ripping to a minimum depth of 300 mm below the Designed Floor Level for the width
of the Selected Material Zone as shown on the Drawings, or the width of the pavement layers
plus one metre on each side (whichever width is the greater).
(b) Recompact the loosened material in accordance with Clause 7. The maximum dimension of
particles in the compacted material must not exceed 200 mm.
(c) After recompaction, trim the floors of cuttings parallel with the finished wearing surface so that
their levels do not vary from the Designed Floor Levels by more than the tolerances shown in
Clause 7.5.
Figure R44.5(a) – Cutting Floor Treatment Type C1 – Loosen and Compact
As part of the trimming operation, prepare the surface in accordance with Test Method TfNSW T199,
for deflection monitoring as required in Clause 7.4.
No account will be taken of the volume involved in loosening when measuring the volume of
excavations.
As for embankment foundations, the foundation area must be prepared to assess its ability to carry
subsequent layers. Surveillance of plant working in the area will usually give an indication of this
ability and facilitate decisions to remove unsuitable material. Repetitive loading by heavy
construction plant will cause failures in low CBR and high moisture content materials and
unnecessary plant movements should be avoided if this is the case. Material of CBR value 8 or higher
would normally be satisfactory.
3.4.2 Type C2 Treatment – Excavation and Backfill
Normally this treatment is required when the material in the particular cutting floor is of poor quality
and better quality material is available on the site and is needed to satisfy the pavement design
criteria. It is equivalent in function to removal and replacement of unsuitable material. When
completing Annexure details for the backfill material, the properties specified must be realistic, taking
into account the availability of material from other cuttings on the job. Alternatives to removal and
replacement would be chemical stabilisation of the bottom of the cutting, increasing the thickness of
SMZ, stabilising the selected material or re-designing the pavement). The backfill material quality
would normally be the same as for upper zone of formation
Where specified or directed by the Principal, treat the floors of the cuttings as described below:
(a) The floors of cuttings must be excavated, parallel to the designed grade line, to a foundation
level that will be at a depth below the Designed Floor Level equal to the nominated thickness of
backfill. Trim the floors to the tolerance stated in Clause 7.5. Loosen, compact and trim the
floor of the cutting in accordance with Clause 3.4.1.
MEDIAN (dual carriageways only)
Designed Finished Surface Level
Selected Material Zone
BATTER
Top of Formation Pavement
Refer to Drawings
for drainage details
Verge or Pavement (see Drawings)
Unsuitable Material
(replaced as directed) Upper Zone of Formation
Foundation Level
Selected Material Zone may extend to edge - see Drawings
Foundations (loosened and compacted) Designed Floor Level *
* unless shown otherwise on the Drawings
(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)
Guide to R44 Earthworks NR44
Ed 2 / Rev 1 31
(b) Place, compact and trim backfill material meeting the requirements of Annexure R44/A2.2 in
accordance with the requirements for earth fill.
Figure R44.5(b) – Cutting Floor Treatment Type C2 – Excavation and Backfill
The material excavated between the underside of the Selected Material Zone and the Foundation Level
is to be included in the excavated volume for general earthworks.
3.4.3 Type C3 Treatment – Working Platform
An appropriate treatment if there is a shortage of good quality material on the project. This is an
alternative to excavation and backfill. It may also be expedient if the quantity of material to be
removed is excessive, on cost grounds, even where removal and replacement is physically possible.
This treatment may also be used where the floor is making water, in conjunction with drainage
measures. This is particularly so if the floor is susceptible to softening and the material extends to
some depth.
Where specified or directed by the Principal, treat the floors of the cuttings as described below:
(a) Increase the strength of the insitu material to form a Working Platform on which to construct the
formation. The Working Platform is created by the chemical stabilisation of insitu material in
accordance with TfNSW R50.
(b) Alternatively, a Working Platform of imported stabilised material may be specified in Annexure
R44/A2.1 or directed.
Figure R44.5(c) – Cutting Floor Treatment Type C3 – Working Platform
Where specified or directed, this work will be paid for under the appropriate Pay Items in
Specification TfNSW R50) and this Specification for imported material (Pay Item R44P3). The
material excavated between the Designed Floor Level and the Foundation Level, at the underside of
MEDIAN (dual carriageways only)
Designed Finished Surface Level
Selected Material Zone
BATTER
Top of Formation Pavement
Refer to Drawings
for drainage details
Verge or Pavement (see Drawings)
Unsuitable Material
(replaced as required)
Upper Zone of Formation
Foundation Level
Selected Material Zone may extend to edge - see Drawings
Backfill (see Drawings) Designed Floor Level *
* unless shown otherwise on the Drawings
MEDIAN (dual carriageways only)
Designed Finished Surface Level
Selected Material Zone
BATTER
Top of Formation Pavement
Refer to Drawings
for drainage details
Verge or Pavement (see Drawings)
Unsuitable Material
(replaced as directed)
Upper Zone of Formation
Foundation Level
Selected Material Zone may extend to edge - see Drawings
Designed Floor Level *
* unless shown otherwise on the Drawings
Working Platform
(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)
NR44 Guide to R44 Earthworks
32 Ed 2 / Rev 1
the Working Platform, is to be included in the excavated volume for General Earthworks and paid in
accordance with Pay Item R44P2.
3.4.4 Type C4 Treatment – Geotextile/Geogrid Layer(s)
This is a specific treatment which needs to be properly designed to ensure that deflections are reduced
to a level which will allow subsequent earthworks and pavement operations to be carried out and that
strains in the finished pavement do not result in premature failures. Numerous geotextiles and
geogrids are available, with different characteristics. Proper design by a suitably experienced person
is necessary in order to determine the most cost-effective treatment
Where specified or directed by the Principal, construct a Type C4 treatment, consisting of a layer or
layers of geotextile and/or geogrid on the floor of the cutting.
Supply and place the geotextile and geogrid in accordance with TfNSW R63 and/or TfNSW R67
respectively. Payment for the geotextile and geogrid used in the Works will be paid for in accordance
with Pay Item R44P7.3 or Pay Item R67P1.
3.4.5 Type C5 Treatment – Drainage Layer
Where specified or where directed by the Principal, treat the floors of the cuttings as described below:
This is a treatment which should be used where water is entering or can be expected to enter from the
floor of the cutting. Remember that any drainage layer will collect water and clear instructions must
also be given regarding the construction of an outlet drain. In the case of water entering from the side
of the cutting, a longitudinal subsoil drain is more appropriate, although if it is difficult to identify the
exact location of the entry, a small drainage layer in combination with a longitudinal subsoil drain
may be appropriate.
It is desirable that the use of drainage layers and their locations be part of the design, not a decision
made exclusively on site. Be aware that long term groundwater behaviour may be different from what
is observed at the time of excavation, particularly after prolonged dry weather. Outlets of drainage
layers need to be considered inthe design. Care needs to be taken to ensure that this is compatible
with the remainder of the design and that it is constructible in a reasonable manner. Drainage layers
and their outlets are difficult, often impossible, to access and maintain in service and should be
designed with considerable excess capacity. Outlet arrangements should be both robust and as simple
as possible.
Take care to understand how water will flow in three dimensions, rather than simply relying on
longitudinal or cross sections.
(a) Excavate cuttings parallel to the designed grade line, to a foundation level which will be at a
depth below the Designed Floor Level equal to the thickness of the drainage layer. Trim the
excavation to the same crossfall as the pavement above and in such a manner as to ensure
drainage of the cutting occurs. Where the horizontal alignment of the road is in crossfall
transition, ensure that the floor of the cutting has a minimum 1% crossfall.
The requirement for trimming is not appropriate if the floor has been excavated by blasting or ripping
and the floor is essentially broken rock. In such cases, consider the alternative of over excavation by
a small amount (e.g. 0.5 m), followed by compacting the shot rock back into the untrimmed floor and
removal of any protruding “spines” etc of rock. There is only a need to ensure that water will flow to
the outlet. Local ponding is usually not a concern under these circumstances, although there may be
exceptions e.g. if downslope stability is a concern adjacent to a side cut.
(b) Compact the material exposed at the base of the excavation with not less than six passes of a
vibrating roller.
(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)
Guide to R44 Earthworks NR44
Ed 2 / Rev 1 33
The material at the base of the drainage layer should not be susceptible to marked strength change
with increased moisture. If the material in the floor of the cutting will soften under soaking, it may
then result in loss of stability of the drainage layer once it is placed
(c) Place the drainage layer at the base of the Selected Material Zone with a minimum thickness of
300 mm material meeting the properties in Table R44.2.
Prior to placing the drainage layer, place a geotextile meeting the requirements of Class C and
Filtration Class 5 of TfNSW R63, over the floor of the cutting, except where the cutting is in
rock. Place a geotextile of the same type over the top of the drainage layer.
Adjust the grading of the drainage layer as necessary within the limits in Table R44.2 to ensure
that it provides a stable foundation for compaction of the overlying Selected Material.
Place and spread the drainage layer material in such a way as to avoid segregation and to ensure
that it is not contaminated with foreign materials. Compact the layer using the nominated roller
routine developed as specified in Clause 7.3.
Requirements for drainage layer materials and construction may be modified to suit site conditions,
particularly for site-won materials. Factors to be considered include the excavation method, floor
condition and availability of materials. For instance, in a large cutting with a very irregular floor in
high strength blasted rock:
A thicker blanket may be appropriate, to eliminate the need for extensive trimming of the
irregularities in the floor. The remnants of the shot rock in the irregularities should then be
compacted to form a base for the drainage layer construction.
A higher proportion of non-plastic fines may be allowable, as these will be trapped in the floor
irregularities and will not clog the drainage
Care needs to be taken if placing a drainage layer on a floor which may soften due to the effects of
moisture or compaction. The compaction routine should be developed to minimise these effects e.g. by
using static rather than vibrating rollers.
After compaction, the upper surface of the drainage layer must not vary from the designed
levels by more than shown in Clause 7.5.1.
The above grading is intended for cases where the design calls for substantial drainage provision in
rock cuttings. This can be particularly useful where good quality rock is available in cuttings on the
job. Where not specified but required as a Variation to the contract, small area drainage layers are to
be used to drain particular problem areas, the specified rock grading may not be readily available and
in such cases a clean coarse aggregate, of nominal size ranging from 100mm to 14mm might be more
appropriate. Crushed aggregate rather than river gravel is preferred as the crushed faces will cause
the material to “lock in” better during compaction. The MS (macadam sub-base) gradings in TfNSW
3051 may also be suitable.
(d) Provide end outlet/drainage treatment as shown on the Drawings, or directed by the Principal.
(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)
NR44 Guide to R44 Earthworks
34 Ed 2 / Rev 1
Figure R44.5(d) – Cutting Floor Treatment Type C5 – Drainage Layer
Payment for the drainage layer will be made in accordance with Pay Item R44P7.4. Material
excavated will be measured and paid in accordance with Pay Item R44P2 or R44P4. The geotextile
will be paid for in accordance with Pay Item R44P7.
3.4.6 Other Treatments
Other foundation treatments may be adopted as shown on the Drawings or as directed or agreed by the
Principal.
3.5 SHALLOW EMBANKMENT AND CUT/FILL TRANSITION
3.5.1 Shallow Embankment
Where the height of the embankment is less than that stated in Annexure R44/A4 for a Shallow
Embankment, excavate the area further to a depth necessary to achieve the minimum height, unless
otherwise shown on the Drawings or directed by the Principal.
You may propose to the Principal a height that is less than the minimum height stated for a Shallow
Embankment to reduce the depth of excavation required. Carry out CBR and PI tests on the
embankment foundation at this proposed higher level and submit them to the Principal. For this lesser
height to be approved by the Principal, the CBR and PI values must comply with those stated in
Annexure R44/A2.2.
This is to confirm design assumptions for the subsequent formation and pavement to be constructed.
Observe the Hold Point in Clause 3.2 and carry out embankment foundation treatments in accordance
with Clause 3.2, before placing the overlying formation.
The thickness of the Upper Zone of Formation will be that corresponding to “shallow embankment” in
Annexure R44/A4, and will generally be the entire formation from Foundation Level to Top of
Formation, unless shown otherwise in Annexure R44/A4. Fill placed within this zone must comply
with that for Upper Zone of Formation material.
MEDIAN (dual carriageways only)
Designed Finished Surface Level
Selected Material Zone
BATTER
Top of Formation Pavement
Refer to Drawings
for drainage details
Verge or Pavement (see Drawings)
Unsuitable Material
(replaced as directed)
Upper Zone of Formation
Foundation Level
Selected Material Zone may extend to edge - see Drawings
Drainage Layer
Geotextile
Designed Floor Level *
* unless shown otherwise on the Drawings
(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)
Guide to R44 Earthworks NR44
Ed 2 / Rev 1 35
Notes:
(1) Where the height from Stripped Surface Level to Top of Formation is less than minimum height for Shallow Embankment
(refer to Annexure R44/A4), further excavation to achieve the minimum height for Shallow Embankment is required.
(2) The thickness of the Upper Zone of Formation will be that corresponding to “shallow embankment” in Annexure R44/A4,
and will generally be the entire formation from Foundation Level to Top of Formation, unless shown otherwise in
Annexure R44/A4.
Figure R44.6(a) – Shallow Embankment Nomenclature
The volume of material excavated is to be included in the measured volume for General Earthworks.
This effectively changes the shallow embankment into a cutting. The requirement is intended to deal
with the major problems that occur with poor drainage and unsuitable materials in this situation, in
the same way as the cut/fill transition treatment. It effectively converts the necessary excavation into
the foundations from unsuitable to general earthworks and makes it necessary to take the resultant
quantities into account in the earthworks balance. The temptation to minimise the nominated depth
should be resisted. It may reduce the physical work required, but could mean that it is paid for at a
higher rate and ordered up piecemeal (thus minimising the chances of it being programmed properly).
As a general guide, embankments should be designed for a minimum height of 1.5 m (2 m is
preferable) from the foundation level to the top of the Selected Material Zone to allow for bridging
and minimise the potential need for excavation below the natural surface.
Shallow embankments commonly arise under the following circumstances:
Adjacent to cut/fill transitions (the requirement applies to the full width of the embankment, not
just the area underneath the pavement
Local topographic highs which do not reach the grade line
Urban situations where embankment levels are dictated by the need to match adjoining properties
Extensive low fills on flat, low-lying or gently sloping ground, where the natural slope follows the
gradient of the control line.
Shallow embankments are inevitable under the first three circumstances, but should be avoided, as far
as possible, in the fourth.
3.5.2 Cut/Fill Transition
Following excavation to the Designed Floor Level at the cut/fill transition, within the area classed as
Shallow Embankment in accordance with Clause 3.5.1, carry out further excavation, parallel to the
cutting floor, below the Designed Floor Level, to a depth necessary to achieve the minimum height
specified in Annexure R44/A4 for a Shallow Embankment, as shown in Figure R44.6(b).
Care needs to be taken to ensure that depths of excavation for the cut/fill transition and shallow
embankment are compatible. It is also important to consider the stability of the vertical faces of the
excavation, particularly if the vertical face is at the base of a planned cutting slope. The cutting
stability will likely be reduced by the excavation and backfilling should be carried out as soon as
practicable to eliminate this risk
Stripped Surface Level (after removal
of topsoil)
Selected Material Zone
Pavement
Designed Finished Surface Level
MEDIAN (dual carriageways only) BATTER
Top of Formation
Verge or Pavement (see Drawings) Selected Material Zone
may extend to edge
- see Drawings
Foundation Level after excavation to minimum depth
for Shallow Embankment (1)
Upper Zone of
Formation (2)
(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)
NR44 Guide to R44 Earthworks
36 Ed 2 / Rev 1
This additional excavation must extend into the cut for a distance of 10 m from the line resulting from
the intersection of the plane of the Designed Floor Level with the plane of the stripped surface, as
shown in Figure R44.6(b). The 10 m is measured perpendicular to the line of intersection between the
two planes.
This cut/fill transition treatment must not however extend into the cutting batter.
Plan View Notes:
(1) Where the height from the Stripped Surface Level to the Top of Formation is greater than the minimum height for a
Shallow Embankment, no further excavation below the Stripped Surface Level, other than terracing, is necessary. The
thickness of the Upper Zone of Formation will be that corresponding to “embankment” in Annexure R44/A4. The fill
below the Upper Zone of Formation may be General Fill.
(2) Where the height from the Stripped Surface Level to the Top of Formation is less than the minimum height for a Shallow
Embankment, further excavation to achieve the minimum height for Shallow Embankment is necessary. This excavation
extends into the cut for a further 10 m as part of the Cut/Fill Transition Zone.
The thickness of the Upper Zone of Formation will be that corresponding to “cut/fill transition” in Annexure R44/A4.
(3) Beyond the Cut/Fill Transition Zone, the thickness of the Upper Zone of Formation will be that corresponding to
“cutting” in Annexure R44/A4.
(4) The 10 m is measured perpendicular to the line resulting from the intersection of the plane of the Designed Floor Level
with the plane of the stripped surface.
Figure R44.6(b) – Cut/Fill Transition Treatment
Within this transition zone, the requirements of Clause 3.5.1 for Shallow Embankment apply.
The volume of material excavated is to be included in the measured volume for General Earthworks.
Ensure that the excavation is free-draining by either sloping toward the nearest exit of the cutting at a
minimum grade of 1%, or installing a subsurface drain at the lower end of the excavation unless
otherwise shown on the Drawings or directed by the Principal. Installation, and payment, of the
subsurface drains must be in accordance with Specification TfNSW R33.
The purpose of the excavation of the cut/fill line is to remove potentially poor quality near surface
material from the upper zone of formation. Note that the requirement applies equally to side cuts.
Upper Zone
of Formation (2)
Foundation Level
after excavation to minimum
height for Shallow Embankment
Top of Formation
Terracing
as required
Designed Floor Level
(base of Selected Material Zone)
Stripped Surface Level
(after removal of topsoil)
Selected Material Zone
10 m (4)
Intersection
line
Transition Zone
Extent of additional excavation
Upper Zone
of Formation (1)
General Fill
Upper Zone of Formation (2)
Upper Zone of Formation (3)
“Shallow
Embankment”
10 m (4)
Cutting batter after excavation
to Designed Floor Level
Intersection
line
Extent of additional
excavation into cut
(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)
Guide to R44 Earthworks NR44
Ed 2 / Rev 1 37
The thickness of the zone should be chosen and specified in the Annexure to suit each individual
project and its materials.
We need to be aware of very flat existing side slopes which can result in very long skewed transitions
resulting in significant increases in earthworks volumes. It is worthwhile to prepare plan drawings
which show the intersection line after topsoil stripping, together with an additional contour at the
cut/fill transition depth.
The location of the back of the excavation (10 m on the cut side of the intersection line, measured
normal to that line) can also be shown. This will help avoid the problem described above and will
provide a good basis for deriving quantities. It makes the scale of the task explicit to tenderers and
provides tenderers with a breakdown of cut/fill line quantities throughout the job for inclusion in the
earthworks plan).
Material removed from beyond the 10 m line is treated as unsuitable.
4 CUTTINGS
4.1 GENERAL
Construction of cuttings includes all operations associated with the excavation of material within the
limits of the batters including benching, terracing of cut batters, cleaning of batter surfaces, treatment
of cutting floors, foundation treatments in accordance with Clause 3.4, beneath Shallow Embankments
in accordance with Clause 3.5.1, and cut/fill transition in accordance with Clause 3.5.2.
4.2 EXCAVATION
Loosen and process the excavated materials as required to meet the Specification requirements for
incorporation in the Works, in particular Clauses 2, 5.6 and 6 of this Specification.
Good site investigations and interpretation of results will assist greatly in this area. Whilst designers
provide changes of slope at changes in expected materials, it is rare that the actual material changes
will be as uniform and clear as the design may imply. For that reason, where changes to slope are
required by the design, good design will where possible also include a bench at that transition from
soft to hard material.
It is important that the cuttings are inspected regularly as they are excavated to confirm the design
parameters and to enable minor adjustments to bench levels and slopes as required. Upper slopes
should be trimmed (and re-vegetated if required) before lower slopes are excavated as it will become
more difficult and more expensive to repair slopes and make changes when the cutting has been more
fully excavated and large plant and equipment cannot access the upper levels with ease.
Benches will also occur for other reasons than a change of material and will not always coincide with
rock quality transitions. The need to allow for access to the upper parts of a slope for maintenance
should be considered in the design. Persons supervising cut batter construction should be familiar
with the design philosophy of the cut and its implications, to avoid making decisions “on site” which
conflict with design objectives.
The batter slopes in cuttings must be in accordance with those shown on the Drawings, or as
re-determined by the Principal, following a site inspection and investigation during excavation.
(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)
NR44 Guide to R44 Earthworks
38 Ed 2 / Rev 1
Round off the tops of cuttings to the dimensions shown on the Drawings unless otherwise directed.
Batters will generally require progressive flattening at the ends of cuttings owing to the presence of
less stable material. In all cuttings, undulations in the general plane of the batter are not acceptable.
The cutting must be free of rills running down the face of the batter (except for pre-splitting holes).
Treat the face of the batter if such treatment is shown on the Drawings.
Clear the cut faces of any loose or unstable material progressively as the excavation proceeds.
4.3 CUTTINGS IN ROCK
Clean the cut batters in rock with slopes of 1H:1V or steeper, using compressed air, to allow
inspection of the batter and assessment of its stability immediately following completion of excavation
to the level of each bench. Do not use water jets and air-water jets unless specifically approved by the
Principal for specific areas. Remove any loose or unstable blocks which are too large to be removed
by the above means, by hand or machine, unless otherwise directed by the Principal.
Clean also the surface of the bench at the top of the batter by compressed air, unless otherwise directed
by the Principal.
Continue cleaning until all loose rock and soil material is removed, and all rock and joint surfaces are
sufficiently exposed so that the Principal can assess their condition and likely effect on the stability of
the batter.
HOLD POINT
Process Held: Excavation below bench level for slopes of 1H:1V or steeper.
Submission Details: Presentation of cleaned batter and bench/floor surfaces for geotechnical
inspection.
Release of Hold Point: The Principal will inspect the cleaned surfaces and may direct further action
prior to authorising the release of the Hold Point. Further action may include
additional cleaning (if the condition of the faces cannot, in the opinion of the
Principal, be adequately assessed), and stabilisation works, prior to or
concurrent with any further work within the cutting.
Following inspection, the Principal may direct additional stabilisation works, including changes to the
batter slope.
The scope of stabilisation works should be determined, as far as possible, prior to tender and suitable
treatment quantities allowed. In some cases, special provisions may be needed in R44.
4.4 BATTER TOLERANCES
Excavation of batters must comply with the tolerances given in Table R44.3.
Table R44.3 – Excavation Tolerances for Batters in Cuttings
Location Tolerance (mm)
Slope 1H:1V or flatter Steeper than 1H:1V
Batters at toe of batter +0 / –150 +0 / –200
2 m above toe of batter and higher +300 / –300 +300 / –600
(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)
Guide to R44 Earthworks NR44
Ed 2 / Rev 1 39
Between level of toe of batter and
2 m above toe of batter pro rata basis pro rata basis
Note: Plus (+) is towards the roadway and minus (–) is away from the roadway. Tolerances are
measured perpendicular to the plane of the slope.
If the batter is over-excavated beyond the tolerance applicable for the batter slope line, or after
cleaning the batter is beyond the tolerance applicable, restore the batter to the specified slope and
stability to the Principal's satisfaction. Proposals for restoration must take into account long term
stability, durability, and consideration of urban design solutions. The cost of restoring or re-forming
the batter must be borne by you.
Restoration of earth batters would normally be carried out using conventional small plant,
remembering to terrace the natural material before compacting fresh material in layers. In rock
cuttings, restoration could be by coloured concrete or by hand placed mortared stone pitching. Urban
design issues and the likelihood of impacting by errant vehicles will influence this decision.
Restoration of rock cuttings could also involve rock bolting of potentially unstable material.
The appropriateness of the standard tolerances should be considered against the expected condition of
the rock mass after excavation. Alternative requirements may be specified if conditions warrant them.
Such requirements could include pre-splitting, closely-spaced line drilling and/or the use of specialist
mining equipment. Economics and urban design aesthetic values will govern the decisions against the
alternative solutions of rock-bolting and shotcreting. Safety considerations for the severity of vehicle
impacts govern the finish requirements for the lower 2 m of the batter.
For batters steeper than 1H:1V, if any section of the batter up to a height of 3 m above the toe of batter
has been over excavated beyond the tolerance limit specified, the Principal may direct that the batter
be re-formed to the average batter slope using randomly mortared stone or other treatments. Where
stone is directed, it must be similar to the sound rock in the cutting and the mortar must be coloured to
match the colour of the rock.
Alternatively, you may request a minor change in the general slope of the batter for your convenience.
If the Principal approves such a change, it will not be regarded as a redetermination of the batter slope
under Clause 4.2 and no additional payment will be made. If your request is denied, restore the batter
to the specified slope and stability to the satisfaction of Principal.
4.5 BENCHING IN CUTTINGS
Cut batters must be benched as shown on the Drawings to provide drainage and erosion control, to
provide geotechnical stability, and to allow access for maintenance purposes. Notwithstanding the
tolerances permitted under Clause 4.4, bench widths must not be less than those shown on the
Drawings.
The floor of the bench must not vary from levels shown on the Drawings by more than the tolerances
shown in Clause 7.5, but the bench must have a crossfall to drain water away from the cut face
immediately below the bench. Provide and maintain longitudinal drainage to prevent ponding of water
on the benches.
Construct bench drains, where shown on the Drawings, progressively as each batter face is completed.
Payment for this work will be made in accordance with TfNSW R33.
Maintain and regularly clean the benches of any loose materials throughout the Contract period. The
cost of such maintenance and cleaning of benches is deemed to be included in the rates generally.
(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)
NR44 Guide to R44 Earthworks
40 Ed 2 / Rev 1
4.6 PRE-SPLITTING OR LINE DRILLING
Use pre-splitting or line drilling to produce a uniform and neat batter surface after excavation or to
ensure protection of batters prior to burden blasts.
Extensive blasting is not usually required in cuttings with a 1:1 or flatter slope, as the material will
usually be able to be ripped. There are however many exceptions, particularly in igneous rocks such
as granite which weather variably. Batter design may be governed by the more weathered rock (or its
ultimate condition if it is expected to degrade with time) and excavation by the less weathered. We
need to be very careful not to imply that excavation characteristics can be predicted from batter
slopes.
Pre-splitting and line drilling are very difficult to do on such slopes due to the difficulty in controlling
the direction of drilling when angled so far from the vertical plane. Where blasting is required in
these conditions (usually because of variable rock strength), most contractors will propose an
alternative of normal drill and blast and cleaning up/trimming of the batter using rock hammers to
achieve the specified tolerances.
Where flat batters e.g. 2:1 are specified, consideration needs to be given to modifying the specified
tolerances.
The Principal will give consideration to an alternative method of excavation and preparation of the cut
face so as to produce a result equivalent to that produced from pre-splitting or line drilling. Approval
to such alternative methods will be granted at the absolute discretion of the Principal, who may require
a trial section of the proposed method to be carried out to demonstrate its suitability.
Where pre-splitting or line drilling is carried out, the centre-to-centre spacing of drill holes must not
exceed the values in Table R44.4.
Table R44.4 – Hole Diameter and Spacing for Pre-splitting or Line Drilling
Cut Batter Treatment Hole Diameter (mm) Maximum Hole Spacing (mm)
Pre-splitting 38 – 51 450
Pre-splitting 51 – 64 750
Pre-splitting 76 – 89 900
Line Drilling Up to 51 150
Line Drilling 51 – 76 250
4.7 BLASTING
4.7.1 General
The following applies only where blasting is permitted under the Contract, as indicated in Annexure
R44/A6.
Obtain all necessary licences from the appropriate authorities and comply with all Government
regulations relating to transport, storage, handling and the use of explosives and also the rules set out
in AS 2187 Parts 1 and 2. Comply with the requirements of all external agencies including, but not
limited to, the Environment Protection Authority (EPA) and the WorkCover Authority and
demonstrate compliance.
Do not use exposed detonating cord in built-up areas. Demonstrate compliance with Clause 6.8 of
Specification TfNSW G35 or G36, as applicable.
(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)
Guide to R44 Earthworks NR44
Ed 2 / Rev 1 41
The Vibration and Air Blast Management Plan (refer to Specification TfNSW G35 or G36, as
applicable) must contain details of review and verification of the above requirements and its
operations to ensure that the public, building structures and infrastructure are protected.
HOLD POINT
Process Held: Start of each blasting operation.
Submission Details: Written details of the proposed blasting procedure including the quantity and
type of explosive to be detonated, the blasting pattern to be used and
measures proposed to limit noise and to ensure that vibration from blasting
does not adversely affect nearby structures. This must be contained in the
Vibration and Air Blast Management Plan.
Release of Hold Point: The Principal will consider the submitted documents, prior to authorising the
release of the Hold Point.
Provide certification of the adequacy of the Building Condition Inspection to the Principal at least
three days before the blasting is due to commence. Monitor and report the Building Condition during
the blasting operations. You are responsible for all costs associated with the inspections and reports if
no Pay Item has been provided in Specification TfNSW G36 for this work.
Monitor all blasts for ground vibration and air blast to ensure that the ground vibration and air blast
level caused by blasting does not exceed the respective values of peak particle velocity and air blast
overpressure listed in Annexure R44/A6 and the requirements of Specification TfNSW G35 or G36, as
applicable.
Implement and maintain a community liaison program during blasting activities to keep people in the
vicinity of the Works informed of any activities. Address levels of vibration or air blast.
Advise all residents within a radius of 1 km from the site of the proposed blasting, before blasting
operations commence. Written advice must include the likely times, frequency and duration of
blasting and precautions being taken to ensure that damage to property will not result.
Confine your blasting operations to the weekdays of Mondays to Fridays but excluding public
holidays, between the hours of 9 am and 3 pm, unless otherwise approved by the Principal.
Do not detonate a blast prior to the time that has been announced for that blast, unless otherwise
approved by the Principal.
When blasting operations are being carried out, take precautions relating to the safety of persons and
animals. Close any roads likely to be affected by the blasting to traffic and erect the appropriate signs
in accordance with Specification TfNSW G10. Establish a standard warning procedure such as that
given in the NAASRA Explosives in Roadworks Users Guide 1982 and observe the procedure at all
times.
Clearly outline in the Vibration and Air Blast Management Plan a detailed procedure to be followed in
the event of a misfire.
4.7.2 Pre-splitting or Line Drilling Prior to Blasting
Prior to commencing blasting, batters with gradients 1H:1V or steeper must be pre-split or line drilled
in accordance with Clause 4.6 to the design batter profile at sufficiently close centres to produce a
uniform and neat batter surface after excavation acceptable to the Principal.
(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)
NR44 Guide to R44 Earthworks
42 Ed 2 / Rev 1
4.7.3 Blasting Records
Maintain accurate records of each blast including the details listed below:
(a) Date, identification number and time of blast;
(b) Location, number and diameter of blast holes loaded;
(c) Depth of each drill hole loaded;
(d) Inclination of drill holes;
(e) Burden(s) and spacing(s);
(f) Types and amounts of explosives used;
(g) Maximum instantaneous charge;
(h) Initiation Plan;
(i) Length and type of stemming in each blast hole;
(j) Ground vibration and noise levels at measuring locations.
The records must be written as the holes are loaded, and must be signed by the shotfirer. Provide a
copy of the records to the Principal on the day of the blast.
Blasting is a hazardous operation and may be an issue with nearby residents. Contractors usually
sub-contract this work to blasting specialists and it needs to be stressed to all involved that the main
contractor must take interest in the details of the blasts so as to minimise damage to properties and
adverse community reactions.
We must ensure that full details of each blast are properly recorded as specified above, as a minimum.
The above items (a) to (i) should be recorded and available for inspection before the blast is carried
out. If difficulties occur with vibration or airblast damage, we will usually require a thorough review
of the blast procedure, specifically dealing with the maximum instantaneous charge, the types and
number of delays and the type of stemming in the holes. We must therefore be able to examine full
details of all blasts and satisfy ourselves that appropriate steps are being taken.
This is a difficult situation as subsequent blasts need to be very conservative in order to ensure no
further damage. Insistence of review of the blasting proposal by an independent experienced and
qualified person is suggested. Re-commencement of blasting should be on a trial basis, be very
conservative and be closely monitored by measuring equipment as well as in person by TfNSW
engineers and inspectors.
5 EMBANKMENTS
5.1 GENERAL
Embankment construction includes:
(a) the preparation of the foundation areas over which fill material is to be placed as described in
Clause 3 and backfilling of excavations undertaken for foundation treatments for both cuttings
and embankments;
(b) the placement and compaction of conforming material within areas from which unsuitable
material has been removed in accordance with Clause 2.4 and within areas where material has
been removed below the pavement zone in cuttings and cut/fill transitions;
(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)
Guide to R44 Earthworks NR44
Ed 2 / Rev 1 43
(c) the placement and compaction of fill material and of materials of specified quality in nominated
zones throughout the Works, including “spill-through” bridge abutments zones where
subsequent pile foundation works are to be undertaken;
(d) all other activities required to produce embankments as specified, to the alignment, grading and
dimensions shown on the Drawings.
Earth fill embankments are embankments not conforming to rock fill requirements (refer Clause 5.3).
Material for embankment construction must be obtained from excavations within the Works and,
where authorised by the Principal, may be supplemented with borrowed or imported material in
accordance with Clauses 2.7 and 2.8. The material must be free of tree stumps, roots and refuse.
Embankment construction (other than for foundation treatments as specified in Clause 3, Upper Zone
of Formation and verges) must be in accordance with the requirements of either Clause 5.2 or 5.3, as
applicable.
Process those materials which do not meet the requirements of these Clauses to ensure conformity
prior to placement. Select the methods of excavation, transport, depositing and spreading of the fill
material so as to ensure that the placed material in any Lot is homogeneous.
Place fill material for embankment construction in layers parallel to the grade line.
Achieve relative compaction specified in Clause 7 over the full depth of the layer. Describe in the
EARTHWORKS PLAN the method used to verify that the specified compaction has been achieved
over the full layer depth and that the layer depth has not been exceeded.
Compaction must also be achieved over the full width of the formation. At times, this may mean
construction of over-wide embankments and subsequent trimming of loose material from the edges.
Programme and manage the Works as detailed in EARTHWORKS PLAN (Clauses 1.5 and 2.2) so
that material of the quality specified in Clause 2.8 for the Upper Zone of Formation and verges is
available when required.
Generally, material for selected material zone and verge material will need to be stockpiled (and often
processed by crushing or screening) before placement in an embankment.
Embankment material zones are as illustrated in Figure R44.2.
5.2 EARTH FILL EMBANKMENTS
Construct the embankment so as to derive its stability from compaction of the fine material around the
coarser particles. Rock material must be broken down and evenly distributed throughout the layer to
prevent the formation of voids and to produce a dense compact embankment. To meet this
requirement, additional fine material may need to be obtained from other places within the Works or
by a change in the method of winning and processing the material.
Maximum layer thicknesses and particle size limitations are given in Table R44.5.
(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)
NR44 Guide to R44 Earthworks
44 Ed 2 / Rev 1
Table R44.5 – Maximum Layer Thickness and Material Properties of Rock in Earth Fill
Embankments
Maximum Layer
Thickness (mm)
Minimum Quantity
Rock (by volume)
Maximum Rock
Size
(any dimension, mm)
% Passing 37.5 mm
AS Sieve (by mass)
300 Not specified 200 > 60%
500 25% > 200 mm 300 > 60%
Maximum layer thicknesses are specified to help ensure that the specified compaction can be obtained
throughout the full depth of each layer. The ability to achieve compaction in a layer is limited by the
thickness, material type and condition and the available plant. In general, compaction within a layer
will never be uniform and as the thickness increases will be much lower towards the base of the layer.
The requirement means that even the least compacted parts of the layer must reach the specified
relative density. The Contractor is required to have an acceptable method which will demonstrate
that this has been achieved.
In order to demonstrate compaction over the full layer thickness that thickness must be known.
Therefore a method of demonstrating layer thickness must be available. Possible methods include
direct measurement (by extending sampling holes for T111/T112 to the base of he layer), survey or
differential GPS measurements from compaction plant or graders.
Density testing by T173 cannot demonstrate full depth compaction of 500 mm layers as the test is
limited to 300 mm by the maximum extension of the probe of the nuclear gauge. Such a layer will
also, by definition, contain too much oversized rock to allow use of the method T119 (the sand
replacement method) can by used with thicker layers.
Demonstrating conforming average density over the layer depth is not sufficient to meet the specified
requirement, due to the depth effects described above. This is not normally an issue with layers
conforming to thickness requirements but is a major concern where 500 mm layers are being used or
the 300 mm limit is not being observed. Geotechnical advice should be sought if here is a need to
investigate this issue.
The conformance requirements (Clause 7) are intended to ensure that the smaller particles and fines
between cobbles and boulders in the layer are properly compacted. Obviously, density testing of
boulders themselves is not relevant to compaction testing. The 60% by mass passing a 37.5mm sieve,
quoted in the table above, is assessed from the samples recovered for compaction testing. It should be
understood that the requirement refers to the material forming the layer, not the individual samples.
Sampling effects mean that if the oversize content for the layer as a whole is near the specified limit,
some samples will exceed that limit.
The maximum size of rock is specified in any direction. This is to ensure that each rock particle is
wholly contained within the layer being placed and compacted. Rocks which break into large flat
plates are undesirable as they will tend to leave gaps underneath the edges and be unstable in a thin
layer.
Where more than 20% by mass of fill material is retained on the 37.5 mm AS sieve, or the compacted
layer thickness exceeds 300 mm, do not use nuclear density gauges for insitu density tests.
The T173 test (nuclear density gauge test) measures the average density of the material between two
points (the source at the end of the probe, at or near the bottom of the layer, and the detector at the
top of the layer, with a horizontal offset of about 300 mm between them), including any boulders that
may be present. The 20% limit applies because the relationship used to calculate the field density
within the nuclear gauge breaks down if there is too much large rock of much greater density than the
finer matrix.
Sand replacement densities (T119) can be conducted up to a rock content of 40%, which is the overall
limit in the specification for rock content of an earth fill. The reference density (T162 or T111)
(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)
Guide to R44 Earthworks NR44
Ed 2 / Rev 1 45
excludes the larger rock (> 37.5 mm) simply because the test can’t be done if it is included. There is a
correction applied for the proportion of larger rock and its density, to allow comparison with the field
density.
The layer thickness (after compaction) must not be less than 100 mm.
The maximum size of rock pieces should not exceed 2/3 the layer thickness. For a thin 100mm layer,
the maximum particle size would be approximately 60mm.
In placing embankment layers, use equipment and techniques to avoid surface heaving or other
damage to the foundations and underlying embankment layers.
If heavy haulage equipment is required to pass over the completed work, the paths of the haulage
vehicles need to be varied to avoid failures caused by repeated loading in the same location.
5.2.1 Earth Fill at “Spill-Through” Bridge Abutments
For the earth fill at “spill-through” bridge abutments, the geometry is as shown in Figure R44.7.
At one end, it forms the exposed sloping part of the “spill-through” embankment. At the other end, at
the top, it extends a distance of 2h from the rear face of the bridge abutment headstock; at the bottom
at embankment foundation level, it extends a distance of h/2 from this rear face.
(For the purpose of this Clause, the height “h” is the distance between the soffit of the headstock and
the embankment foundation level. Where excavation is required for foundation improvement, the
height “h” is measured to the base of the excavation.)
Figure R44.7 – Dimensions of Fill at “Spill-Through” Bridge Abutments
The fill material must comply with the requirements of Clause 2.8.5.
Prior to placement, the material must be stockpiled, sampled and tested for conformity in accordance
with the requirements of Clause 6.1.2.
Each layer must not exceed 300 mm in thickness when compacted and must be compacted to the
requirements stated in Table R44.11.
h
h/
2
2h
Soffit of Headstock
Embankment
Foundation Level
h/2
Note: Dashed line above indicates location of
batter behind abutment, and extent of earth fill
complying with Clause 5.2.1, if abutment fill is
placed prior to adjoining embankment.
Earth fill
complying with
Clause 5.2.1
UZF other than SMZ
Selected Material Zone
Slope terraced
in accordance
with Clause 3.3
(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)
NR44 Guide to R44 Earthworks
46 Ed 2 / Rev 1
Rocks must not be dumped against the columns or retaining walls but must be built up evenly by hand
placing around or against such structures.
Scour protection of the embankment is not considered in this Clause and, where necessary, must be
considered separately.
5.3 ROCK FILL EMBANKMENTS
5.3.1 Introduction
For the purpose of this Clause, a rock fill embankment is an embankment constructed of hard, sound
rock, containing only a small amount of fine particles, which derives its stability from the mechanical
interlock of the coarser particles, rather than from the compaction of the finer material.
Except where shown on the Drawings, do not place rock fill in areas where earth fill has previously
been constructed. If you elect to construct a rock fill embankment, adjust the working methods
employed in the excavation of cuttings so as to produce rock fill material of the grading and rock
strength specified in Clause 5.3.2. Such working methods must include screening and, if necessary,
secondary processing.
Place and spread the rock fill material in such a way as to avoid segregation and to ensure that it is not
contaminated with foreign material. The compacted rock fill layer thickness must not exceed 550 mm.
Compact the rock fill using the nominated compaction routine, developed as specified in Clause 7.3.
Material that does not meet the requirements for rock fill specified in this Clause must be broken down
further into finer particles, or have additional fines incorporated, and used in earth fill embankments in
accordance with Clause 5.2.
Nominate to the Principal the proposed areas of rock fill. If you elect to construct earth fill in part or
all of the nominated rock fill locations, and a surplus of rock, capable of being processed for rock fill,
is later found to exist, then treat the surplus by:
(a) processing the material for use as earth fill; or
(b) removal of earth fill and placement of the surplus rock as rock fill at your cost.
Shape and treat the foundations under rock fills to maintain drainage and to ensure that erosion of the
foundation will not occur.
Protection from future erosion of the foundation area below the rock fill should be carried out by
construction of suitable diversion drains and the placement of geo-textile material at the foundation
level of the rock fill.
Special measures may also be needed to protect culvert backfill material from erosion by water
flowing through a rockfill when the culvert is operating under afflux. This may involve the use of a
non-erodable and free draining select bedding and backfill material around the pipe, such as a 14mm
or 20mm crushed aggregate.
5.3.2 Rock Fill Material
Rock fill material must comply with Table R44.6. The constituent particles must be of uniform
strength and soundness.
The values specified in the Annexure should be chosen following discussions with experienced
geotechnical experts and extensive site investigation and testing of expected materials. The limit
should be specified to make distinction between acceptable and unacceptable materials as easy as
(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)
Guide to R44 Earthworks NR44
Ed 2 / Rev 1 47
possible. This will require good knowledge of the expected strength characteristics of the rock and
their distribution. It is not desirable to set the limit so as to require extensive testing of “marginal”
materials to determine their suitability.
The properties in the table below are specified to limit the fines in the fill and to ensure that stability of
the fill is achieved by point contact of rock particles and to ensure that fines do not prevent that point
contact.
Table R44.6 – Rock Fill Material Properties
Property Requirement
Maximum particle dimension 300 mm
Percentage passing:
100 mm AS sieve 0 – 20%
19.0 mm AS sieve 0 – 10%
1.18 mm AS sieve 0 – 5%
Percentage of +100 mm fraction with
Is(50) < Annexure R44/A2.2
10% (max)
Wet/Dry Strength Variation Annexure A2.2
5.3.3 Overlying Layers
Do not place rock fill within 600 mm of the underside of the Selected Material Zone. The minimum
depth to rock fill below the underside of the Selected Material Zone is increased to 1.0 m where safety
barrier, posts, subsurface drainage or services are to be installed.
This requirement is to ensure deflections at the surface are reasonably consistent and that, in service,
the material from the Selected Material Zone does not migrate downwards into the voids of the rock
fill. The remaining requirement is so that large rocks are not near the surface where they would
impede the driving of guardrail posts or the future construction of other trenches.
Place a capping layer of 300 mm (+100 mm / –0 mm) thickness after compaction, composed of graded
rock fill immediately above the completed rock fill embankments. The material in the capping layer
must comply with the properties shown in Table R44.7.
Table R44.7 – Capping Layer Material Properties
Property Requirement
Maximum particle dimension 150 mm
Percentage passing:
19.0 mm AS sieve 0 – 10%
1.18 mm AS sieve 0 – 5%
Percentage of +19.0 mm fraction with
Is(50) < Annexure R44/A2.2 10% (max)
Wet/Dry Strength Variation Annexure A2.2
The grading of the capping layer has been chosen so that it behaves as a “graded filter” to minimise
the material from subsequent layers of fine material migrating down to the voids of the rock fill. In
addition to this capping layer, geo-textile separation layers specified below are also required.
(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)
NR44 Guide to R44 Earthworks
48 Ed 2 / Rev 1
Place and spread the material for the capping layer in such a way as to avoid segregation and to ensure
that it is not contaminated with foreign material. Compact the capping layer using the nominated
compaction routine, developed as specified in Clause 7.3.
5.3.4 Rock Fill Around Structures
Notwithstanding requirements elsewhere in this Specification, the thickness of backfill around
structures specified in Clause 5.6.3 within rock fill embankments must be at least:
horizontally: 2.0 m (measured normal to the axis of the structure)
vertically: 1.0 m (where rock fill is to be placed over the structure).
The requirement is to avoid damage to structures by impact during construction or point loads in
service.
5.3.5 Geotextiles
Place geotextile separation layers conforming to the requirements of TfNSW R63 as follows:
Class D: beneath the first layer of rock fill.
Class D: between backfill to structures and the adjacent rock fill.
Class C: between the capping layer defined in Clause 5.3.3 and the overlying layer of earth fill.
Payment for geotextiles will be made under Pay Item R44P7.3 for Treatment Type E4.
5.4 EMBANKMENT BATTERS
The batter slopes shown on the Drawings may be subject to re-determination by the Principal
depending upon the materials encountered.
When completed, the batters of embankments must conform to those shown on the Drawings unless
otherwise authorised or re-determined by the Principal.
The tolerances for construction of embankment batters are detailed in Table R44.8.
Table R44.8 – Tolerances for Embankment Batters
Location Tolerance (mm)
Slope 1H:1V or flatter Steeper than 1H:1V
At level of Top of Formation/underside of
pavement +0 / –150 +0 / –150
1 m below Top of Formation and higher +150 / –150 +150 / –150
1 m below Top of Formation and lower +300 / –300 +300 / –300
Note: Plus (+) is towards the roadway and minus (–) is away from the roadway. Tolerances are measured
perpendicular to the plane of the slope.
Near the surface of the completed pavement, the shape of the batter is particularly important to ensure
safety for motorists in an out of control run-off.
Notwithstanding the above, the edge of the formation at the level of the underside of the pavement
must not be nearer to the roadway than that shown on the Drawings.
This is required so that the pavement can be constructed to its full width as designed.
(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)
Guide to R44 Earthworks NR44
Ed 2 / Rev 1 49
Undulations in the general plane of the batter are not acceptable. The completed batter must be free of
rills running down the face of the batter.
Rills should be repaired as soon as practicable, as they are areas where water flow concentrates and
they generally develop into larger gullies through repeated scouring, eventually compromising the
stability of the formation. This matter is closely related to the batter slope angle and the face length
provided. Excessive face lengths or over-steep slopes will make rill formation inevitable in most
earthfill materials. The provision of berms to break up long slopes should be considered. Good
design, together with early revegetation, are essential in order to avoid these problems.
Promptly remove any loose material on the batters as the work progresses.
Placement of additional material on the existing embankment batters must be carried out in the same
manner as that specified for placement of hillside embankments in Clause 3.3.
This is so the new material is keyed in to the original material. Without the key, slope failure will be
more likely.) It also allows the new fill to be compacted against the interface. Consideration needs to
be given to drainage arrangements at the interface when widening on the downslope side of side fills.
5.5 ROCK FACING OF EMBANKMENTS
Where shown on the Drawings, provide a rock facing of clean, hard, durable rock over embankment
batters (including embankments at bridge structures) separated from the earth fill material with a
geotextile complying with TfNSW R63. Place the rock facing outside of the general embankment
dimensions.
Rock facing serves two purposes. It is a way of preventing scour of steep embankments and also an
economical way of dealing with large rock pieces. It is often specified under spill through bridge
abutments where lack of sunlight and water make revegetation difficult. The geotextile is placed
under the rock facing to prevent water running below the rock facing, causing erosion of the
underlying material.
Rock used for rock facing must have a Point Load Strength Index (Is(50)), as determined by Test
Method TfNSW T223, and a Wet/Dry Strength Variation, meeting the respective requirements stated
in Annexure R44/A2.2, and have a minimum dimension of 500 mm.
It is important that the rock is subjected to artificial weathering tests to ensure that it will not break
down prematurely in service. Some shales and siltstones particularly are very hard in situ but
deteriorate rapidly when exposed to cycles of wetting and drying. The test requirements need to be set
appropriately for the materials being considered. This must be job-specific.
You may elect, with the approval of the Principal, to place surplus rock conforming to the above as
rock facing.
The rock facing must be built up in layers ahead of each layer of filling. Place rock in such a manner
that its least dimension is vertical and that mechanical interlock between the larger stones occurs.
Remove any excess of fine material surrounding any rock placed within the rock facing by removing
the rock, removing the excess fine material and re-placing the rock.
Adjust the working methods and program of work to obtain sufficient hard and durable rock of the
specified dimensions to complete the facing as is required. Fill the space between larger batter rocks
and adjacent fill material with progressively smaller rocks to form a graded filter which prevents the
leaching out of fines from the fill material but which does not overfill the voids between larger rocks,
or cause the larger rocks to lose contact with one another.
(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)
NR44 Guide to R44 Earthworks
50 Ed 2 / Rev 1
Exercise extreme caution whilst placing the rock facing. Where embankment material is placed in the
formation above other roads in use, place the outer rock layer in such a manner as to prevent spillage
down the batter. Implement measures to prevent any rock being dislodged and allowed to roll down
on to any adjacent roadway or track in use.
Payment for the rock facing and drainage layer will be in accordance with Pay Item R44P2. Payment
for the geotextile will be in accordance with Pay Item R44P7.3(a).
5.6 FILL PLACED ADJACENT TO STRUCTURES
5.6.1 General
Supply and placement of fill adjacent to structures is considered to be part of general earthworks. For
the purpose of this Clause, structures include bridges, box and pipe culverts, headwalls and
concrete/masonry retaining walls.
This Clause does not apply to reinforced soil walls (refer to Specifications TfNSW R58 and TfNSW
R59 for their requirements).
Select Fill placed adjacent to culverts and drainage structures, except that adjacent to weep holes, must
be provided in accordance with Specifications TfNSW R11 or TfNSW R22, as applicable. Select Fill
placed against other structures must conform to the requirements of Specification TfNSW B30. Fill
material within the Upper Zone of Formation must also comply with the relevant requirements of
Clause 2.8.
5.6.2 Treatment at Weepholes
Provide drainage adjacent to weepholes using broken stone or river gravel comprising clean, hard,
durable particles, with the following grading:
(i) the maximum particle dimension does not exceed 50 mm; and
(ii) no more than 5% by mass passes the 9.5 mm AS sieve.
The layer of broken stone or river gravel must be continuous in the line of the weep holes, extend at
least 300 mm horizontally into the fill and extend at least 450 mm vertically above the level of the
weepholes.
Alternatively, you may provide a synthetic membrane of equivalent drainage capacity at no extra cost
to the Principal. Store and install it in accordance with manufacturer's instructions. The use of
synthetic membrane as a substitute is subject to the Principal's concurrence.
Many synthetic materials deteriorate when exposed to sunlight. Covering and storing on site should
generally be arranged to avoid exposure to the sun.
5.6.3 Placing Fill Adjacent to Drainage and Bridge Structures
After completion of any backfilling required by Specifications TfNSW B30, TfNSW R11 and TfNSW
R22, place fill complying with Clause 5.6.1 adjacent to structures in accordance with Table R44.9.
Place the fill in accordance with Clauses 3.3 and 5.2 except that layers must have a compacted
thickness between 100 mm and 150 mm. Place layers simultaneously on both sides of box culverts to
avoid differential loading. Compaction must start at the wall and proceed away from it, and must meet
the requirements of Clause 7.
(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)
Guide to R44 Earthworks NR44
Ed 2 / Rev 1 51
Cut the existing slope behind the structures listed in Table R44.9 in the form of successive horizontal
terraces, each terrace being at least 1 metre in width, 600 mm in height, and place the fill in
accordance with Clause 5.2.
Do not place fill against structures within twenty-one days after placing concrete in these structures,
unless the concrete strength is verified to have reached the specified 28-day strength.
Where a bridge deck is being concreted adjacent to an abutment, do not place fill against the abutment
within twenty-one days after placing concrete in the bridge deck, unless the concrete strength in the
bridge deck is verified to have reached the specified 28-day strength.
In the case of framed structures, bring up embankments at both ends of the structure simultaneously
and the difference between the levels of the embankments at the respective abutments must not exceed
500 mm unless otherwise shown on the Drawings or within the Specification.
Table R44.9 – Placing of Select Fill
Structure Select Fill
Width Height
Bridge Abutments 2 m H
Box Culverts H/3 H + 300 mm
Retaining Walls H/3 H
(where H = height of structure)
6 STRUCTURAL TREATMENTS
6.1 UPPER ZONE OF FORMATION
6.1.1 General
An Upper Zone of Formation, including a Selected Material Zone (see Figures R44.2(a), R44.2(b),
R44.6(a) and R44.6(b)), must be provided to the thickness specified in Annexure R44/A3 and must
meet the quality requirements specified in Clause 2.8.
Unless otherwise specified, do not place imported material in the Works until all material of suitable
quality available from the cuttings in the Works has been placed or has been assigned to be placed in
the formation.
For economy, projects are usually designed for balanced earthworks with a small excess of spoil or
small amount of borrow material. Imported material if not needed may not only be costly, it may also
result in an unwanted large excess of material towards the end of the job.
Experience suggests that it is prudent to allow for a 7 to 10% surplus in the design and have sufficient
space to spoil any that is not used. There is always wastage for various reasons, accompanied by a
tendency to overbuild embankments, the latter in part to ensure that compaction can be safely
achieved out to the design line.
Where it is apparent that special care will be needed to ensure that the required quantities of
materials for specialised uses can be obtained it may be necessary to impose more restrictive
requirements on working materials management. The TfNSW Contract Manager should then ensure
(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)
NR44 Guide to R44 Earthworks
52 Ed 2 / Rev 1
that any measures needed, whether specified or not, are reflected in the Earthworks Plan.
Note: This comment applies equally to any issue involving materials management.
HOLD POINT
Process Held: Delivery of imported and site won material for the Upper Zone of
Formation.
Submission Details: Proposed location, quantities and type of material, and verification of
conformity. Verification that all possible sources of the material within the
site have been exhausted.
Release of Hold Point: The Principal will examine details and may inspect the source and stockpiles
of material prior to authorising the release of the Hold Point.
Before placing imported Upper Zone Material in any formation, carry out a survey in accordance with
TfNSW G71 to determine the surface levels at sufficient locations to later determine the volume of
compacted imported material placed in the Works. When shown in Annexure R44/A1, the survey
must be a Joint Survey in accordance with Clause 1.6.
This survey is done to establish the need for imported material and is necessary for payment purposes.
Compaction must be in accordance with Clause 7.
6.1.2 Selected Material Zone
Provide a Selected Material Zone (see Figures R44.2(a), R44.2(b), R44.6(a) and R44.6(b)) where
specified or shown on the Drawings. The Selected Material Zone must be placed and compacted in
layers with the compacted thickness of each layer not exceeding 150 mm unless otherwise specified in
Annexure R44/A4.
The properties specified in the Annexure must be to suit site conditions and must be chosen with
economy in mind. The Selected Material Zone is intended to ensure that the better materials available
from cuttings on the job are used at the surface of the formation, immediately below the pavement.
Sometimes, very hard materials will be available but processing costs may be high. In such cases, a
lesser material which still has an adequate CBR may be preferable due to its lower processing and
handling costs. The limitations on size of particles, layer thickness and compaction requirements are
to provide the best support possible for the pavement with these materials. Often, if good quality
material is not available from within the job, the material is specified to be imported. The choice of
imported material is usually based on economy as whilst this material is of better earthworks quality,
it is usually not as high a quality as pavement material.
Where specified in Annexure R44/A2.1, the material placed in the upper layer of the Selected Material
Zone at any particular location must be from the same source, produced using the same process and
exhibit similar properties prior to any chemical modification which may be required, as that placed in
the lower layer at that same location.
Prior to placement, all material intended for use in the Selected Material Zone must be stockpiled and
tested for conformity with the requirements of Clause 2.8.3 and Annexure R44/A2.2. The total mass
of each Lot of stockpiled material must not exceed 4000 tonnes.
Sampling must be in accordance with Table R44.10 and the characteristic value (Q) of the CBR for
each Lot calculated in accordance with Specification TfNSW Q. For the purpose of this calculation,
report the individual CBR values to the nearest 1% and the characteristic value (Q) to the nearest 0.1%
(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)
Guide to R44 Earthworks NR44
Ed 2 / Rev 1 53
Table R44.10 – Sampling Frequency for Selected Material Zone Lots Before Placement
Total Mass of Lot Represented (tonnes) 1 – 500 501 – 1000 1001 – 2000 2001 – 4000
Minimum Number of Samples per Lot 2 3 4 5
HOLD POINT
Process Held: Placement of each Lot of Selected Material Zone.
Submission Details: Submit test reports verifying conformity of each Lot of stockpiled material
for use in Selected Material Zone.
Release of Hold Point: The Principal will consider the submitted documents, prior to authorising the
release of the Hold Point.
After placement, the Selected Material must be homogeneous and free from patches containing
segregated stone or excess fines. The placement methods used must ensure conformity with the
requirements of Clause 2.8.3 and Annexure R44/A2.2.
Trim the Selected Material Zone to meet the tolerances shown in Clause 7.5.1. As part of the
trimming operation, prepare the surface in accordance with Test Method TfNSW T199, for deflection
monitoring as required in Clause 7.4.
HOLD POINT
Process Held: Covering of each Lot of Selected Material Zone.
Submission Details: Verification of conformity of each Lot of Selected Material Zone with
relevant test and survey reports.
Release of Hold Point: The Principal will consider the submitted documents, prior to authorising the
release of the Hold Point.
6.2 VERGES
Provide verges as shown on the Drawings to meet the quality requirements specified in Clause 2.8.
Unless otherwise specified, do not place imported material in the Works until all material of suitable
quality available from the cuttings in the Works has been placed or has been assigned to be placed in
the formation.
HOLD POINT
Process Held: Delivery of imported material for the verges.
Submission Details: Proposed location, quantities and type of material, and verification of
conformity. Verification that all possible sources of the material within the
site have been exhausted.
Release of Hold Point: The Principal will examine details and may inspect the source and stockpiles
of material prior to authorising the release of the Hold Point.
(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)
NR44 Guide to R44 Earthworks
54 Ed 2 / Rev 1
Carry out a survey in accordance with Specification TfNSW G71:
(a) before placing material in any verge to determine the surface levels at sufficient locations to
later determine the volume of compacted verge material placed in the Works; and
(b) before placing imported material to determine the surface levels at sufficient locations to later
determine the volume of compacted imported material placed in the Works.
When shown in Annexure R44/A1, the surveys must be a Joint Survey in accordance with Clause 1.6.
Place and compact the verge material in layers with the compacted thickness of each layer between
100 mm and 200 mm unless otherwise specified in Annexure R44/A4.
After placement, the material must be homogeneous and free from patches containing segregated stone
or excess fines.
Compaction must be as specified in Clause 7. You may compact adjacent to a concrete pavement only
after at least 10 days after the placement of concrete, or after joint sealing is completed, whichever is
the later.
Damage to freshly placed concrete must be avoided and placement of verge material before sealing of
joints in concrete pavement will result in fine material being deposited in the joints and prevent them
from achieving their designed movement.
Trim the verge to meet the tolerances shown in Clause 7.5.
6.3 OTHER TREATMENTS
Provide other Structural Treatments where shown on the Drawings, to comply with geotechnical or
other design requirements.
7 ADDITIONAL CONFORMITY REQUIREMENTS
7.1 GENERAL
Compact all layers of material placed in the Works uniformly over the full area and depth of the layer
to achieve the relative compaction specified before the next layer is commenced. Trim each layer of
material prior to and during compaction. Complete the compaction promptly to ensure that moisture
content remains conforming and uniform and to minimise the possibility of rain damage.
Unless the treatment of each layer is consistent throughout the layer, the analysis of testing of a layer
using statistical methods becomes irrelevant. This uniformity of treatment is essential to the definition
of a “Lot”.
7.2 EARTH FILL
For all areas and materials listed in Table R44.11, uniformly compact each layer over the full area and
depth of the layer to achieve the relative compaction specified in Clause 7.2.1 before the next layer is
commenced.
(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)
Guide to R44 Earthworks NR44
Ed 2 / Rev 1 55
At the time of compaction, maintain the moisture content within the range specified in Annexure
R44/A5 at all locations within the Lot. Adjust the moisture content within that range to enable the
specified compaction to be achieved. Address monitoring and adjusting of moisture content in the
EARTHWORKS PLAN.
Do not compact material that has been placed with a moisture content greater than that specified in
Annexure R44/A5, or has become wetted-up after placement, until it has dried out so that the moisture
content is within the specified range. The drying process may be assisted by aeration or, where
approved by the Principal, by the use of hydrated lime or quick lime, complying with Specification
3211, at your cost.
Alternatively, you may remove the wet material to a stockpile site for drying out and later use as fill
material. Any cost of removal to stockpile, for drying out and later use is deemed to be included in the
rates generally.
The drying out of over-wet material can become very difficult, particularly in very wet seasons and in
winter when drying days and sunlight are short. We ought to be trying to let our contracts in such a
timeframe that these situations are avoided, particularly at the start of a project when large areas for
drying material are simply not available. If we are aware of very wet heavy clays in cuttings and we
know it will be difficult to dry, we should consider specifying and paying for stabilisation to improve
the material properties. Such decisions often result in better pricing by contractors, better site
management as well as an early finish and an overall reduced cost to the project. There may be other
solutions (e.g. spoiling, if the circumstances allow it). The solution should be thought out beforehand
and as far as possible, the work timed to minimise the need for drying or other treatments.
If over optimum material is excavated from cuttings and it is placed deep down in high fills, it may be
possible, with Geotechnical Branch concurrence, to build a stable fill which does not compromise
pavement support or embankment stability. With these materials it is usually easy to achieve
compaction but it is difficult to achieve the specified moisture content. In these cases, there will be
excess pore-water pressures from the compaction and the completed work will tend to “heave” under
heavy plant and machinery.
By waiting a period of time (usually the next day) the pore-water pressures reduce and provided the
material does not heave badly, the next layer can be placed. The best practical method of testing for
heaving is to proof roll in accordance with Clause 7.4.1 with a fully-loaded item of plant and to watch
the surface for movement. There will usually be some movement, however minor movement at depth
will not normally be detrimental to the finished pavement higher up in the fill.).
An alternative location which would usually be suitable for the placement of over optimum moisture
content material is in a wide median area or in very flat, wide batters, sufficiently clear of the
carriageway to not be an influence on the pavement deflections.
Care needs to be taken in placing over-wet material in large embankments. Zoned construction may
be appropriate (placing the wet material in the core of the fill, where large future moisture changes
are unlikely). Placing over-wet clay material full width can lead to stability problems, particularly if
it is highly expansive. Problems with instability under rolling tend to become worse if multiple layers
are placed in quick succession, before compaction-induced pore-pressures can dissipate. Depending
on the nature of the material (including matters such as permeability) it is also possible for apparently
stable layers to become unstable following rain or after wet material is placed on them.
If there is insufficient moisture in the material for it to be compacted as specified, add water. The
added water must be applied uniformly and thoroughly mixed with the material until a homogeneous
mixture is obtained. The cost of such wetting of the material must be borne by you.
(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)
NR44 Guide to R44 Earthworks
56 Ed 2 / Rev 1
7.2.1 Relative Compaction Conformity Criteria
Carry out compaction control using Standard compaction on Lots using statistical techniques in
accordance with Specification TfNSW Q. Conformity of a Lot will be achieved if the characteristic
value of relative compaction of that Lot is not less than the lower limit specified in Table R44.11.
Table R44.11 – Lower Limit for Characteristic Values of Relative Compaction
Location Lower Limit of Characteristic
Value of Relative Compaction
Earth mounds
Spoil 90.0%
Foundation for Embankments (except where a bridging layer is used, as provided for in Clause 3.2.2).
Each layer of material replacing unsuitable material as detailed in Clause 2.4 (except within 300 mm of design level of floor of cuttings).
Foundation Treatment Types E1 and E3, and Working Platforms in embankments specified in Clause 3.2.3.
95.0%
Each layer of material placed in formations up to the underside of the Selected Material Zone, including that in Shallow Embankments and Cut/Fill Transition Zone.
The entire area on the floors of cuttings.
Material in verges or within medians up to the level at which topsoil is placed.
Select Fill placed adjacent to structures, as specified in Clause 5.4.
Other areas not specifically mentioned herein.
98.0%
Materials placed in the “spill-through” bridge embankment zone, as specified in Clause 5.2.1.
100.0%
Each layer of the Selected Material Zone. 102.0%
A Lot must contain only areas of work that are essentially homogeneous. This occurs when material
origin and properties, general appearance, moisture condition during compaction, compaction
technique, response to compactors, and state of underlying materials are substantially alike.
Areas that fail to meet these conditions must be excluded from the Lot and must be tested separately as
one or more additional Lots.
Failure to ensure compliance with these requirements in Lot definition invalidates the compaction
acceptance scheme. Also ensure that changes to Lot boundaries are accounted for in future testing.
7.2.2 Sampling and Testing
Engineers and Surveillance Officers engaged on contract work should be thoroughly familiar with the
requirements and shortcomings of the sampling and testing specified. They should spend some time
with an experienced laboratory technician and a geotechnical scientist in a soils laboratory to fully
understand test results presented. There are many opportunities for errors in sampling and testing
techniques which can result in erroneous results.
Particular care is needed to ensure that samples are taken to the full depth of the layer. Materials
may not be uniform through the layer depth, particularly in general earthworks. While strictly this is
in breach of the specification requirements, some variation in material properties is inevitable and can
be tolerated provided it is not too extreme. Sampling and testing of the full depth is necessary to
ensure that compaction requirements are being met.
Ensure that the laboratory independently carries out its responsibilities, as detailed in TfNSW Q, for
locating and carrying out sampling and testing.
(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)
Guide to R44 Earthworks NR44
Ed 2 / Rev 1 57
Provide a smooth surface at each sampling location for the purpose of obtaining samples.
The PROJECT QUALITY PLAN must ensure that Lots are inspected for homogeneity as defined in
TfNSW Q Annexure Q/L Clause L1.
At each sample location selected for determination of compaction, carry out a field density test and a
field moisture test and obtain a sample for a laboratory maximum dry density test.
Carry out field (insitu) density tests in accordance with either Test Methods TfNSW T119 or
TfNSW T173.
Conduct all tests within a particular Lot using only one of the above Test Methods. Do not combine
results obtained from more than one Test Method for a statistical assessment of a particular Lot.
Where Test Method TfNSW T173 is used for the insitu density determination, extend the probe to be
located within the layer and close to the bottom of the nominated layer. Once the test is completed,
take a sample from below the test site, within the circle of area between the probe and the detector and
for the full depth of the nominated layer. The size of this sample must be sufficient for the laboratory
determination of maximum density.
Repair test holes using freshly mixed material of the same type as used in the surrounding earthworks
layer. Compact repair material to a degree equal to that of the surrounding earthworks layer. Detail in
the PROJECT QUALITY PLAN the method of repairing the test holes.
Irrespective of the Test Method used to determine the insitu density, the proportion and density of
oversize material retained on the 37.5 mm AS sieve in the sample for the laboratory maximum dry
density test must also be determined, in accordance with the procedure described in Test Method
TfNSW T119.
Determine field moisture content in accordance with Test Methods TfNSW T120, TfNSW T121, or
TfNSW T180. Only use TfNSW T121 and TfNSW T180 where results have previously been
calibrated against those of TfNSW T120 for the range of materials being compacted.
Determine maximum density using Test Methods TfNSW T111 or TfNSW T162.
7.2.3 Relative Compaction
Calculate relative compaction using Test Method TfNSW T166.
Round off the relative compaction value and the characteristic relative compaction value to the nearest
0.1%.
7.3 ROCK FILL
Conformity of a Lot of rock fill is based on compliance with the nominated compaction routine
verified in accordance with this Clause, and proof rolling in accordance with Clause 7.4.1.
Develop a materials grading, mixing, watering and rolling routine after construction and testing of trial
sections, and nominate the verified routine to the Principal. If the routine includes insitu modification
(e.g. with a grid roller or similar), then verify the after-compaction grading of the material.
The length of a trial section must not exceed 50 m, and the width must be greater than or equal to 2
times the maximum roller drum width. Do not construct trial sections within 1.5 m of the bottom of
the Selected Material Zone.
(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)
NR44 Guide to R44 Earthworks
58 Ed 2 / Rev 1
Verification of a compaction routine will be based on results from two (2) successive trial sections.
Two contiguous trial sections, constructed over the same time period in a continuous operation, will
not be deemed to be two successive trial sections.
The compaction routine must include at least one vibrating roller.
WITNESS POINT
Process Witnessed: Construction of each trial section of rock fill
Submission Details: Notification of the place, date and time of construction of the trial section, at
least 3 working days prior to commencement with details of:
(i) Test results of all previous trial sections;
(ii) Material type(s) and specifications, including moisture conditioning
prior to and during rolling;
(iii) Plant types and specifications;
(iv) Number of roller passes;
(v) Maximum and minimum roller speed and frequency of vibration;
(vi) In-process testing regime and proof that there is no remaining internal
settlement and proof that embankment stability exists.
HOLD POINT
Process Held: Compaction of rock fill.
Submission Details: Verification, including test results, of conformity of each trial section
including details of the proposed compaction routine, any test results and
survey reports.
Release of Hold Point: The Principal will consider the submitted documents, prior to authorising the
release of the Hold Point.
Where in-process testing of the compaction routine reveals nonconforming results, cease placing and
compacting, and redevelop the routine using trial sections in accordance with the above or break down
and/or sort rock material to achieve an earth fill in accordance with Clause 5.2. The above Hold Point
applies to the redeveloped routine prior to recommencement of placement and compaction operations.
All costs associated with the development and nomination and verification of the compaction routine,
and the utilisation of the nominated compaction routine on rock fill layers is deemed to be included in
the rate for General Earthworks.
7.4 DEFLECTION TESTING
7.4.1 Proof Rolling
All embankment Lots, and all other surfaces within 1.5 metres of the underside of the Selected
Material Zone must be capable of withstanding proof rolling to verify their stability.
Unless otherwise approved by the Principal, undertake proof rolling in accordance with Test Method
TfNSW T198 in the presence of the Principal.
(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)
Guide to R44 Earthworks NR44
Ed 2 / Rev 1 59
This clause is not intended to require proof rolling of every lift. It specifies the method by which proof
rolling should be done and when it is required. This should only be where there is a need to confirm
the stability of the formation as a platform for further construction. The procedure is T198. This
specifies the plant to be used. Alternative plant can be used providing it applies a loading at least
equivalent to that specified. Whilst the requirement is that each layer “must be capable…”, the
testing is not mandatory and is usually only required if instability and “heaving” are suspected.
The moisture content of the compacted material being proof rolled must be within the range specified
in Annexure R44/A5. Proof roll each layer immediately following compaction. For the purpose of
deflection testing by proof rolling, take the testing paths along the full width and length of each Lot.
WITNESS POINT
Process to be Witnessed: Proof rolling of any embankment fill layer, or any other surface within 1.5
metres of the underside of the Selected Material Zone.
Submission Details: At least 1 working day’s notice of intention to proof roll any surface with the
proof rolling plan and verification of the layer or surface conforms (except
proof rolling).
The tests must not exhibit visible deformation, rutting, or yielding and/or show signs of distress or
instability.
If further proof rolling is required at a later date, the layer must be re-conditioned such that the
moisture content is within the range specified in Annexure R44/A5, re-verified as conforming for
density and survey requirements of this Specification, and given not less than eight (8) passes with the
roller to be subsequently used for the proof rolling operation.
7.4.2 Benkelman Beam
Where shown in Annexure R44/A4, carry out deflection testing following completion of the formation
to the underside and top of the Selected Material Zone (or underside of pavement where no Selected
Material Zone is specified) using the Benkelman Beam in accordance with Test Method TfNSW T199.
Where the required characteristic deflection does not exceed 1.2 mm, the standard deviation of the Lot
must not exceed 0.2 mm. If the required characteristic deflection exceeds 1.2 mm, the coefficient of
variation of the Lot must not exceed 25%.
Limiting the deflection of the formation under the pavement limits the amount of deflection which must
be withstood by the pavement in service. If deflections are too high for a particular pavement design,
premature failure will occur.
The CV requirement will need to be reconsidered where deflections are very low, e.g. a Lot with a
mean deflection of 0.5 mm and SD of 0.2 mm will fail, with a CV of 40%, even though there may not
be a single deflection greater than 1.0 mm. A Lot with a mean of 0.8 mm and the same SD would pass
the CV requirement.
For the purpose of deflection testing with the Benkelman Beam, a Lot must consist of a continuous
length of formation of at least 300 m and of at least a single carriageway width that is generally
homogeneous with respect to material and appearance. In urban areas or area with severe restrictions,
the Principal may reduce the length of the Lot. Mark the boundaries of each Lot such that they are
clearly identifiable in the field.
(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)
NR44 Guide to R44 Earthworks
60 Ed 2 / Rev 1
Take deflection testing by Benkelman Beam within 3 days of compaction of the material. Undertake
testing over the plan area of the Selected Material Zone within each Lot and any other area within the
Lot as directed by the Principal.
Obtain the Characteristic Deflection for each Lot from the equation:
CD = u + f.σ
where CD = Characteristic Deflection
u = average maximum deflection
f = value as shown in Annexure R44/A4
σ = standard deviation
Where the characteristic deflection exceeds the value in Annexure R44/A4, re-examine the Lot
boundaries, re-check the Lot for homogeneity, and subsequently re-nominate the Lot (or parts thereof)
for further testing.
WITNESS POINT (when Benkelman Beam Testing is specified)
Process to be Witnessed: Benkelman Beam testing of the surface under the first layer of pavement.
Submission Details: Notification of time, date and location of Benkelman Beam testing and
results of proof rolling at least 1 working day prior to the proposed date of
Benkelman Beam testing.
HOLD POINT
Process Held: Placing each Lot of Selected Material Zone or pavement (where there is no
Selected Material Zone).
Submission Details: Deflection test results, Survey Report of the finished surface and verification
of conformity of each Lot of formation at least 3 working days before the
work is programmed to be covered up.
Release of Hold Point: The Principal will consider the submitted documents, and may direct further
action prior to authorising the release of the Hold Point.
7.5 LEVEL CONTROL
7.5.1 Tolerances
Finish the surface levels of the floors of cuttings, transitions, earthworks layers and zones, and verges
to the design surface levels less the nominated thicknesses of the relevant overlying courses and zones
to within the tolerances detailed in Table R44.12.
(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)
Guide to R44 Earthworks NR44
Ed 2 / Rev 1 61
Table R44.12 – Level Control - Tolerances
Position Tolerance
(a) Top of Selected Material Zone or top of formation where there is no Selected Material Zone:
(i) where overlying layer is part of the Contract, and quantity for payment for overlying layer is in units of square meters
(ii) where overlying layer is part of the Contract, and quantity for payment for overlying layer is in units of cubic meters
(iii) where overlying layer is not part of the Contract
+0 mm / –20 mm
+0 mm / –20 mm
+0 mm / –20 mm
(b) Formation at level of underside of Selected Material Zone:
(i) where underlying layer is a drainage layer in a cutting
(ii) all other cases
+0 mm / –20 mm
+0 mm / –20 mm
(c) Surface of verges +0 mm / –20 mm
(d) Floor of cutting before carrying out foundation treatment:
(i) Type C1 - Loosen and compact
(ii) Type C2 - Excavate and backfill
(iii) Type C3 - Working platform
(iv) Type C4 - Geotextile and geogrids
(v) Type C5 - Drainage layer
+0 mm / –20 mm
+0 mm / –100 mm
+0 mm / –100 mm
+0 mm / –20 mm
+0 mm / –100 mm
(e) Top of foundation treatment under embankment
(i) Type E3 - Working platform
(ii) Type E5 - Drainage layer
+20 mm / –20 mm
+20 mm / –20 mm
(f) Floor of terrace at Cut/Fill Transition +0 mm / –100 mm
(g) Floor of benching in cuttings +0 mm / –100 mm
(h) Top of rock fill +0 mm / –100 mm
7.5.2 Areas Below Level Tolerances
Where the overlying layer is not part of the Contract, and the finished surface level of the top of the
Selected Material Zone is not higher than the upper limit of the tolerance shown in Table R44.12
(+0 mm), but is lower than the lower limit of the tolerance (-20 mm), the work may be accepted by the
Principal, under the following conditions:
(a) Deductions are made at the rate shown in Annexure R44/A6;
(b) Your methods for carrying out the survey and calculation, and the calculated values, are agreed
to by the Principal.
7.5.3 Median Areas
The batter slopes for median areas must comply with those shown on the Drawings and undulations in
the general plane of the batter slope will not be permitted outside of the following tolerances.
For a horizontal distance of up to 2 m from the edge of the shoulder (except areas where verges are
required), no point on the completed batter may vary from the specified slope line by more than
35 mm when measured at right angles to the slope line. At distances greater than 2 m horizontally
from the edge of the shoulder, no point on the completed batter may vary from the specified slope line
by more than 75 mm when measured at right angles to the slope line.
Notwithstanding the tolerance of construction above, grade medians so as not to pond water.
(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)
NR44 Guide to R44 Earthworks
62 Ed 2 / Rev 1
ANNEXURE R44/A – PROJECT SPECIFIC INFORMATION
NOTES TO TENDER DOCUMENTER: (Delete this boxed text after completing Annexure A)
Review the default values shown in Annexure A and amend if appropriate, fill in the missing details as
required, and delete as applicable where “Yes/No” options are provided in Annexure A, taking into
account the geotechnical information and the pavement design for the project.
For Annexure A1, consult TfNSW Survey Section on the practicality of the surveys.
These requirements must be complied with when compiling tender documents. They should be project
specific requirements and be based on a thorough knowledge of the site, the expected materials and
the makeup and availability of the site team and available personnel, i.e. it is a plan which is
considered practical and which TfNSW’s site team, as well as the Contractor, will be expected to
follow during the course of the contract. Engineers should consult with survey staff on the practicality
of these surveys.
A1 SURVEYS (Clause 1.6)
Carry out surveys and joint surveys (in accordance with TfNSW G71) where required in the following
table:
Clause Location Survey Joint
Survey
Model File (1)
2.3.2 Topsoil stockpile site before stockpiling Yes Yes Yes/No
2.3.3 Surfaces of each cutting and embankment after
stripping of topsoil
Yes Yes Yes/No
2.4 Before removal of unsuitable material Yes No Yes/No
2.4 After removal of unsuitable material Yes No Yes/No
4.4, 5.4 Completed cut and fill batters prior to
topsoiling, vegetation or other treatments
Yes No Yes/No
5.1, 6.1.1 Surfaces prior to placing imported material Yes Yes Yes/No
6.1.2 Surfaces prior to placing Selected Material Yes No Yes/No
6.2 Before placing verge material Yes No Yes/No
7.5.1 Floor of cutting before placing foundation
treatment materials or formation
Yes No Yes/No
7.5.1 Top of finished Formation Yes Yes Yes/No
7.5.3 Finished surface of median Yes No Yes/No
Note:
(1) If this requirement is “Yes”, the survey report must include a computer file containing data in a format that
is suitable for creating accurate models using the current standard TfNSW CADD software.
(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)
Guide to R44 Earthworks NR44
Ed 2 / Rev 1 63
A2 MATERIALS
A2.1 Sources
Clause Description Requirement
2.3.1 Topsoil
2.3.1(i) - Stockpile within the Site Yes/No
2.3.1(ii) - Stockpile as a windrow Yes/No
2.3.1(iii) - Spoil outside the Site Yes/No
2.3.1(iv) - Spoil as contaminated material Yes/No
2.7.2 Borrow sites
- Specified location ………………….
- Maximum batter slope of borrow site excavation ……..
2.8.1 The following materials must only be from imported sources:
- Upper Zone of Formation material other than Selected
Material
Yes/No
- Selected Material Yes/No
- Verge material Yes/No
3.2.3, 3.4.3 - Working Platform stabilized material Yes/No
Sources of imported material:
2.8.2.2 - Upper Zone of Formation material other than Selected
Material
………………….
2.8.3.2 - Selected Material Zone material ………………….
2.8.4.2 - Verge material ………………….
5.1 - Imported fill ………………
3.2.3, 3.4.3 - Imported stabilized material ………………
6.1.2 Material in the Selected Material Zone at any location must be
from the same source (1)
Yes/No
Note:
(1) If this requirement is “Yes”, the material placed in the upper layer of the Selected Material Zone at any
particular location must be from the same source, produced using the same process and exhibit similar
properties prior to any chemical modification which may be required, as that placed in the lower layer at
that same location.
A2.2 Properties
All material properties to be entered below are site specific. The properties, Test Nos and values
entered should be chosen so that the best use is made of available materials.
The choice of 4 or 10 day soaks for CBR values should only be made after gaining knowledge of site
materials. Some very fine materials will have a high CBR value at 4 days soak but will deteriorate
after further soaking and the CBR at 10 days can be significantly less than at 4. Whilst a test done
after 4 days soak may give a quick answer, the four day soak result may not properly represent the
material properties in service. As a guide, 4 day soak will be specified for granular materials and 10
day soaks will be specified for lower permeability silts and clays.
(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)
NR44 Guide to R44 Earthworks
64 Ed 2 / Rev 1
In a practical sense, the specified tests are meant to provide an indication of the suitability or
otherwise of materials before placement in each zone. They are an indication only. Most materials
break down to a degree during excavation, haulage, spreading, mixing with water or other material,
drying, compacting and trimming and many will provide a significantly different test result after these
operations have taken place and the material is in place in its specified zone. Pre-treatment and
accelerated weathering tests should be carried out prior to placement in a zone, in order to best
predict its behaviour in place. (See Note 1 below table.
Clause Location Value Test Pre-treatment
(1)
2.8.2, 3.5
Material for Upper Zone of Formation other than Selected Material, including at Shallow Embankment and Cut/Fill Transition:
a) CBR10 day (2) 8 min T117 T102/T103 (3)
b) Plasticity Index 25 max T109 T102/T103
2.8.3.1 Site won Selected Material:
a) Selected Material Zone top 150 mm layer CBR4 day (2), characteristic value (Q) (3) Refer Note 4
30 min (4) T117 T102/T103 (5)
b) rest of Selected Material Zone CBR4 day (2), characteristic value (Q) (3) Refer Note 4
15 min (4) T117 T102/T103 (5)
c) Plasticity Index 15 max T109 T102/T103 (5)
2.8.4 Verge material:
a) CBR4 day (2) 15 min T117 T102/T103 (5)
b) Plasticity Index 6 and 12 T109 T102/T103 (5)
3.5 Foundation of Shallow Embankment and Cut/Fill Transition where depth of excavation less than specified:
a) CBR10 day (2) 8 min T117 T102/T103 (5)
b) Plasticity Index 25 max T109 T102/T103 (5)
3.4 Floor of Cutting:
a) CBR10 day (2) 8 min T117 T102/T103 (5)
b) Plasticity Index 25 max T109 T102/T103 (5)
3.2.5, 3.4.5
Drainage Layer (Foundation Treatment Type E5 and C5):
a) Point Load Strength Index Is(50) 1 MPa min T223 NA
b) Wet/Dry Strength Variation 35% max T215 T102
3.4.2 Backfill material for Type C2 Foundation Treatment:
a) CBR10 day (2) 8 min T117 T102/T103 (5)
b) Plasticity Index 25 max T109 T102/T103 (5)
5.2.1 Earth fill at “spill-through” bridge abutment zone:
Material Type ST1, for waterway crossings
a) CBR10 day (2), characteristic value (Q) (3) 8 min T117 T102/T103 (5)
b) Plasticity Index 15 max T109 T102/T103 (5)
Material Type ST2, for overbridges
a) CBR10 day (2), characteristic value (Q) (3) 8 min T117 T102/T103 (5)
b) Plasticity Index 25 max T109 T102/T103 (5)
5.3.2 Rock fill:
a) Point Load Strength Index Is(50) 1 MPa min T223 NA
b) Wet/Dry Strength Variation 35% max T215 T102
(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)
Guide to R44 Earthworks NR44
Ed 2 / Rev 1 65
Clause Location Value Test Pre-treatment
(1)
5.5 Rock facing:
a) Point Load Strength Index Is(50) 1 MPa min T223 NA
b) Wet/Dry Strength Variation 35% max T215 T102
Legend: NA = not applicable max = maximum min = minimum
Notes:
(1) Pre-treatment is not required where samples are taken from the compacted formation.
(2) Compaction for CBR test must be at 100% of MDD under standard compaction.
(3) When calculating CBR characteristic value, report values calculated to the nearest 1%.
(4) (Refer Clause 2.8.3.1.) If any Lot of Selected Material in the top 150mm layer has a CBR less than the value specified above, the material must be modified with hydrated lime at an application rate of 2% by mass. The modified material must have a UCS of less than 1.5MPa, when tested in accordance with TfNSW T131 using 7 days accelerated curing. Other suitable binders may be used where approved by the Principal. However, do not use binders which are prone to give rise to rapid or uneven strength gain or excessive shrinkage.
(5) Where pre-treatment is shown as “T102/T103”, determine the appropriate pre-treatment regime for the material in accordance with Clause 2.8.1.
The intention of Note (4) is that CBR values are selected to make best use of available materials and
that the Contractor should be able to achieve the result using the naturally occurring materials by
taking reasonable care. The option of stabilising in this specification is one which recognises that the
Contractor may actually not finish up with the required material quality. Stabilisation is usually an
option available which would improve the quality and reduce the moisture-susceptibility of the
particular material.
Whilst 2% lime is specified here together with a minimum UCS, other stabilising agents and
properties may be specified. In each case, the treatments and material properties need to be tailored
to suit the material available and the pavement design for the project. The pavement is generally
designed on the CBR of the material prior to modification on the assumption that in the long term the
lime may be leached from the SMZ.
Where the CBR in the SMZ is less than CBR = 30%, the 2% lime will reduce moisture susceptibility
during construction, will reduce the risk of pavers getting bogged and is consistent with achieving an
increase in strength upwards through the Upper Zones of Formation.
Care should be exercised, and Pavements Branch help sought, if a contractor proposes to use Steel
Furnace Slag (SFS) or other waste product materials as a pavement, SMZ or Upper Zone material.
SFS is prone to expansion when exposed to moisture in a pavement layer if not properly weathered for
at least three to four months beforehand. This comment does not apply to Blast Furnace Slag which
has successfully been used as a pavement material in a number of regions.
A3 FOUNDATION TREATMENT
Clause Description Requirement
3.2.2 Type E2 Foundation Treatment - Bridging Layer
- Minimum depth from underside of pavement to top of bridging
layer 600 mm
- Maximum thickness of bridging layer 800 mm
3.2.5 Type E5 Foundation Treatment - Drainage Layer
- Completed thickness of drainage layer 300 mm
(+100 mm, –0 mm)
(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)
NR44 Guide to R44 Earthworks
66 Ed 2 / Rev 1
3.2, 3.4 Specified Foundation Treatments
- Location ‘A’ Type: …………..
- Location ‘B’ Type: …………..
A4 SHALLOW EMBANKMENT, CUT/FILL TRANSITION, UPPER ZONE OF
FORMATION AND VERGES
Job specific dimensions should be entered here.
Clause Description Requirement
3.2, 3.5.1 A Shallow Embankment exists where the height from the Stripped
Surface Level to the Top of Formation is less than: 1,200 mm
6.1 Thickness of Upper Zone of Formation (incorporating Selected
Material Zone) for:
- Cutting 300 mm
- Cut/Fill Transition Zone 1,200 mm
- Embankment 600 mm
- Shallow embankment 1,200 mm
6.1.2 Selected Material Zone:
- Thickness 300 mm
2.8.3.1 - Depth for modification of material, other than to only meet
specified CBR requirements
6.1.2 Maximum compacted thickness of each layer in the Selected
Material Zone:
150 mm
6.2 Compacted layer thickness of each layer of verge material 100 mm – 200 mm
7.4.2 Monitor deflection at underside and top of Selected Material Zone
with Benkelman Beam.
Yes/No
7.4.2 Maximum Characteristic Deflection (CD) recorded for any Lot
must not exceed:
- Top of Selected Material Zone 1.0 mm
- Underside of Selected Material Zone 1.2 mm
- Factor “f” to be used in determining CD 1.65
7.5.2 Deduction to be applied for out of tolerance surface level where
the overlying layer is not part of the Contract
……..
3.5.1 The removal of material from the transition zone is designed to address the often poor quality of
the natural material occurring in that zone. It is, by its nature, naturally occurring material near the
surface of the earth and is often weathered and of poor or variable quality. There are cases where the
cut/fill transition can extend over a great length and careful consideration should be given to the need
to specify its special treatment as a location needs to be found for the material excavated. The depth
of 900mm has been chosen as this is the depth from finished pavement level (approx 1500mm) which
would normally be affected by heavy vehicles travelling on a granular pavement. In order to be cost
effective, the pavement and earthworks need to be considered together.
(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)
Guide to R44 Earthworks NR44
Ed 2 / Rev 1 67
6.1 The depths of materials in the upper zone of formation, including the select material zone needs to
be chosen to suit the best usage of available materials and the pavement design for the work. These
depths are site specific and should be chosen after careful consultation with geotechnical staff and
with due consideration of practicality and cost. The specifying of a select material zone is done to
ensure the most appropriate cost effective material is reserved for the surface immediately beneath the
pavement layers. The specifying of a deeper upper zone of formation in fills is done to try and ensure
the better materials available during earthworks excavation from cuttings (usually from towards the
bottom of cuttings), are utilised towards the tops of fills where they will experience the highest traffic
loading.
As explained above, deflections will change with time and moisture content. It will be in the
Contractor’s interests to measure some time after compaction, after no site traffic and after a dry
period of weather. Constraints are placed on the timing of deflection testing in both Clause 7.4.2 and
T199. If it is expected that this issue will be critical, further constraints should be specified.
There may be circumstances where requiring Benkelman Beam readings to be taken at the top of the
SMZ in addition to the underside of the SMZ can be waived but not without seeking prior Pavement
Branch advice.
The shape of the deflection bowl, measured during Benkelman beam readings, will provide a better
indication of quality and will indicate whether any “soft” layer is near the surface or some depth
below it.
A5 COMPACTION MOISTURE REQUIREMENTS (Clause 7.2)
Material Description (1) Source / Location Moisture Range (2)
Earthworks Material 60 – 90%
Notes:
(1) Material types above are project specific.
(2) The Moisture Range is expressed as the ratio of Field Moisture Content to Optimum Moisture Content at
standard compactive effort and is reported as a percentage.
Project specific requirements should be entered here. Whilst 60-90% will generally provide a
satisfactory result, it is conservative from TfNSW’s viewpoint.
In general, there will be difficulties compacting materials at moisture contents below 60% of optimum
and in any case, water will probably need to be added for dust control. It may not be practicable for
many materials to be compacted below 90% of optimum moisture content, particularly with heavy
clays in high rainfall or low-lying areas which are often at or above this moisture content in situ.
Consideration needs to be given to allowing higher moisture contents where this occurs and
permitting its placement at some depth in the fill, where it would not adversely affect the finished
pavement (usually 1500mm minimum below finished surface).
Compaction above optimum moisture content is likely to lead to a degree of “heaving” of the fill
immediately following placement due to the build-up of pore-water pressure. This results in difficulty
in compaction of the next overlying layer. If left overnight, the pore pressures built up during
compaction can often partly dissipate and with the heaving reduced, the next layer can be
satisfactorily placed and compacted.
See also comments in 7.2, regarding placement of high moisture materials in the core area of fills at
or near their equilibrium contents.
(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)
NR44 Guide to R44 Earthworks
68 Ed 2 / Rev 1
A6 BLASTING (Clause 4.7)
A decision needs to be made. Excavation of hard rock can be achieved by a number of alternative
means, such as ripping, rock breakers or self-expanding chemicals incorporated into closely-spaced
drill holes. Whilst blasting can be a sensitive process in or near residential areas, often the
alternatives involve protracted durations of very noisy work with rock hammers and drills. These
issues should be resolved in the planning phase of the project.
Blasting permitted under Contract? Yes/No
Limiting Peak Particle Velocity and Blast Overpressure:
Blast overpressure is commonly known as “airblast” and is best described as a measure of the level of
noise experienced. The energy in the pressure wave, which is often in the low frequencies, can cause
significant damage to walled structures facing the blast and may cause window breakage. This
airblast is often responsible for the rattling of windows and glassware in houses.
Its effects are harshest on cloudy days and can be accentuated by atmospheric conditions. The effects
can be minimised by appropriate blast design that minimises rapid venting of the expanding gasses,
avoiding blasting on cloudy days, in humid conditions, choosing a suitable time of day (usually around
midday) for blasting and minimising the amount of exposed detonating cord lying on the surface of the
cutting being excavated.
Peak Particle Velocity is a measure of the blast vibration exerted on a structure. It is usually
transmitted through the hardest bands of rock below the surface and can be affected by the level of the
water table. With properly designed blast patterns, damage to buildings caused by blasting is
extremely rare but if any damage to buildings is caused, it is usually because of an excessive Peak
Particle Velocity.
In order to properly manage claims for damage to buildings, it is important to carry out thorough
building inspections before any blasting takes place and then again at the end of a blasting program.
It is advisable to have housing inspections carried out by an independent, reputable architect or
builder, with copies of all reports being provided to residents and owners before and after the blasting
has taken place.
There are many things other than blasting which can cause a building to exhibit cracking. Most
common is the effect of seasonal moisture changes near foundations of buildings, causing movement of
the foundations and cracking of walls.
It is also notable that most newly constructed houses will exhibit minor cracking near cornices of
plaster ceilings and walls within a few years of completion as a result of normal shrinkage of the
construction materials. Blasting can be a sensitive issue in residential areas and for this reason, any
blasting needs to be extremely well managed and must address community concerns.
Point of Potential Damage (within 1 km from the proposed blast site)
Blast Overpressure Level
(dB[linear])
Peak Particle Velocity (1)
(mm/s)
Completed and cured bridge structures or
sub-structures (e.g. completed abutment) – 10 mm/s
Bridgeworks and structural retaining walls
under construction – 10 mm/s
Residential premises, schools, hospitals
and other buildings 115 dB (2) 5 mm/s (2)
Building or monument of historical
significance 115 dB 2 mm/s
(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)
Guide to R44 Earthworks NR44
Ed 2 / Rev 1 69
Notes:
(1) Peak Particle Velocity is the vector peak particle velocity, defined as the maximum of the resultant vector
particle velocity vp and is the amplitude of the vector sum of three time-synchronised velocity components
directly measured by an instrument.
vp is determined by the equation vp = √(vx2 + vy
2 + vz2),
where vx, vy and vz are the synchronized instantaneous velocity components in the x, y and z axes
respectively.
(2) 5% of readings may exceed 115 dB and 5 mm/s but must not exceed 120 dB and 10 mm/s.
(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)
NR44 Guide to R44 Earthworks
70 Ed 2 / Rev 1
ANNEXURE R44/B – MEASUREMENT AND PAYMENT
Payment will be made for all activities associated with completing the work detailed in TfNSW R44 in
accordance with Pay Items below.
Unless otherwise specified, a lump sum price for any of these items will not be accepted.
If any item for which a quantity of work is listed in the Schedule of Rates has not been priced by you,
it will be deemed that due allowance has been made in the prices of other items for the cost of the
activity which has not been priced.
Pay Item R44P1 - Topsoil
Pay Item R44P1.1 - Removal and Stockpiling of Non-contaminated Topsoil
The schedule rate for Pay Item R44P1.1 is an average rate to cover the removal, loading,
handling, transporting and stockpiling of all non-contaminated topsoil within the limits of
Works.
The unit of measurement is the cubic metre measured in the stockpile of topsoil removed in
accordance with Clause 2.3.
The volume must be determined by measurement or survey, and calculation.
Note-measured loose in stockpile, although we can estimate the bank volume from depth times
area.
Pay Item R44P1.2 - Removal and Disposal Off-Site of Topsoil
The schedule rate for Pay Item R44P1.2 is an average rate to cover the removal, loading,
handling, transporting and disposal of topsoil off-site, including tipping fees and any other
disposal costs.
Topsoil removed as contaminated material in accordance with Clause 2.5.2 will be measured
and paid in accordance with Pay Item R44P8 and Pay Item R44P1.2.
The unit of measurement of topsoil directed to be removed and disposed of off-site in
accordance with Clause 2.3.1 items (iii) and (iv) is the cubic metre measured as bank volume of
excavation.
The volume must be determined by measurement or survey, and calculation.
Pay Item R44P2 - General Earthworks (Cut/Fill)
The schedule rate for Pay Item R44P2 is an average rate to cover all types of material encountered
during excavation and placed in embankments, including both earth and rock, and disposed of
otherwise than in embankments.
When a contractor encounters harder rock or more rock than anticipated, under the contract, this is
the contractor’s risk as there is no distinction between earth and rock in TfNSW contracts. Resident
Engineers should ensure that they get a survey of each cutting when the method of excavation changes
from rip & load by conventional diggers to a drill and blast operation, so that accurate records are
kept of the actual excavation method adopted by the contractor.
There has been at least one project where a separate rate has been introduced at pre-tender
(successfully) for part of a project, due to expected excavation and geotechnical conditions being very
(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)
Guide to R44 Earthworks NR44
Ed 2 / Rev 1 71
different from the remainder of the work. This is a possible alternative approach, but requires very
good knowledge of the conditions.
The unit of measurement is the cubic metre measured as bank volume of excavation. Payment for
General Earthworks includes all activities associated with the excavation of material from cuttings
(including table drains and gutters), the excavation of material in/under Shallow Embankments,
excavation of material in Foundation Treatment Types C2, C3 and C5 and the construction of
embankments, including:
(a) preparation of the foundation areas, other than work paid under Pay Item R44P7;
(b) placing and compacting conforming material to replace unsuitable material, contaminated
material, and that required in Foundation Treatment Types C2 and C3, that has been removed;
(c) placing and compacting formation material and materials of specified quality in the Upper Zone
of Formation, other than work paid under Pay Item R44P5;
(d) placing and compacting earth fills and rock fills;
(e) rock facing of embankments;
(f) rounding of the tops of batters;
(g) haulage of material and any pre-treatment such as breaking down or blending material for
purposes such as rock fill;
(h) restoring, stabilising or re-forming any over-excavation;
(i) working General Fill and Upper Zone materials to bring moisture content of the Lot to within
the specified range including drying out material containing excess moisture;
(j) deflection testing and proof rolling;
(k) addressing any deficiency in sites for stockpiling, including disposal of unsuitable materials and
supplying their replacement;
(l) double handling of materials excavated from the site that are stored temporarily in stockpiles
before being returned for incorporation into the Works due to any staging of the Works;
The above list of inclusions and the following list of exceptions must be fully understood by people
administering this document. The document reviewer should check to ensure these exceptions are
relevant to this project.
Surveyors in particular, working on the project, need to be briefed and any issues clarified before the
work commences.
except that:
(i) supply and placing of imported or borrowed General Fill material and Upper Zone Material will
be paid under Pay Item R44P3;
(ii) removal of unsuitable material will be paid under Pay Item R44P4;
(iii) additional costs of disposal of non-contaminated spoil off site will be paid under Pay Item
R44P6;
(iv) materials from excavations for drainage and drainage structures (other than materials from
excavation for table drains and gutters) must not be included in the measurement for this Pay
Item as this is paid for under TfNSW R11;
(v) additional costs for identification, treatment and disposal of contaminated material will be paid
under Pay Item R44P8;
(vi) additional costs for foundation treatments will be paid under Pay Items R44P7.1 to R44P7.4;
(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)
NR44 Guide to R44 Earthworks
72 Ed 2 / Rev 1
(vii) additional costs for stabilisation and imported material required in Foundation Treatment Types
E3 and C3 will be paid under TfNSW R50 and Pay Item R44P3;
(viii) additional costs for placing materials from excavations as Selected Material will be paid under
Pay Item R44P5.1;
(ix) additional costs for placing materials from excavation as verge material will be paid under Pay
Item R44P5.3;
(x) payment for incorporation into embankments of surplus material from other works under the
Contract will be included in the relevant pay items for excavation in the specifications for those
other works.
For the purposes of measurement and payment, the base of the excavation is the Foundation Level in
accordance with Clause 3.4 or as specified on the Drawings, before the removal of unsuitable material.
The sides of the excavation are the design cut batters as shown on the Drawings or as determined by
the Principal. No account will be taken of level or batter tolerances.
The volume is determined by calculation of the difference between the base of the excavation defined
in the above paragraph and the stripped surface surveyed under Clause 2.3.3. When measuring the
volume of excavations for payment, no account will be taken of the volume involved in:
(a) ripping and loosening the floor of the cutting (Foundation Treatment Type C1)
(b) loosening embankment floor (Foundation Treatment Type E1)
(c) material removed in terracing (Clause 3.3)
(d) insitu stabilising material in Foundation Treatment Type C3.
Pay Item R44P3 - Imported or Borrowed Material
This Pay Item covers all activities associated with supply and placing of imported or borrowed
material in the formation except for Selected Material, verge material and imported or borrowed
material for fill above and behind reinforced soil block (refer Specifications TfNSW R58 and TfNSW
R59).
The unit of measurement is the compacted volume of imported fill in cubic metres measured in place.
The volume is determined by calculation from the Drawings and survey. The calculation must
exclude the volumes in the Selected Material Zone, verges and zone of imported or borrowed material
for fill above and behind reinforced soil block.
Payment will include all activities associated with the opening up of the borrow site, excavation of
material from the borrow site and the construction of embankments, the supply, haulage and
placement of imported or borrowed material and any pre-treatment such as breaking down or blending
material or drying out material containing excess moisture, maintenance of the borrow site, and
restoration of the borrow site.
Payment will not be made for excess widening of embankments or wastage by you.
Pay Item R44P4 - Unsuitable Material
This Pay Item refers only to unsuitable material as defined in Clause 1.4 and described in Clause 2.4.
The unit of measurement is the cubic metre measured as bank volume of excavation. If the material is
such that the bank volume of excavation cannot be measured, the Principal will determine the
conversion factors to be applied to the loose volumes measured in haulage units or to the measured
stockpile volumes.
(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)
Guide to R44 Earthworks NR44
Ed 2 / Rev 1 73
The schedule rate(s) under Pay Item R44P4 will include all operations involved in the excavation,
temporary stockpiling, drying out, haulage, compaction or other activity required under Clause 2.4 for
the incorporation of unsuitable material in embankments or all activities required for disposal within
the Site in accordance with clause 2.5.1.
The practicality of re-incorporation depends on why the material was removed in the first place and
on what can actually be done with it subsequently. It is unwise to insist on reincorporation under
adverse circumstances, unless there is no choice. However, low CBR material removed from cut
foundations (for instance) can readily be incorporated into general fill if it is not too wet and there is
still space for it. This is not generally suitable if it is anticipated that the material will be over wet and
drying out will be difficult. Unless it is known that the material can be easily compacted, it would be
best to spoil it.
Where the Principal directs that non-contaminated unsuitable material be disposed of off-site,
additional payment will be made for disposal under Pay Item R44P6.
Additional payment will be made under Pay Item R44P8 for identification, treatment and disposal of
contaminated unsuitable material.
When the schedule of quantities under Pay Item R44P4 provides for ranges of provisional quantities,
the rates must be applied successively, but not cumulatively, as the volume of unsuitable material
increases from one provisional quantity range to the next higher range.
Each rate must be applied for all unsuitable material removed within each quantity range, irrespective
of the nature of the material removed.
Pay Item R44P5 - Selected Material in the Selected Material Zone and Verge
Material
This pay item covers all activities associated with the identification, winning/purchasing, processing
(including blending), stockpiling (including double handling to suit you), testing, haulage, placement,
compaction and trimming of material in the Selected Material Zone and material in the verges.
This pay item covers the costs of modification of materials necessary to meet the CBR requirements of
TfNSW 3071. Should stabilisation/modification of the material be specified, other than only to meet
specified CBR requirements of imported Selected Material, payment for stabilisation will be made
under TfNSW R50.
The unit of measurement is the cubic metre measured in place in the Selected Material Zone and
verges. The width, depth and length must be taken as shown on the Drawings, and no account is taken
of the allowable placement tolerances. Where additional areas or volumes are directed by the
Principal, the volume must be determined by measurement or survey, and calculation.
Pay Item R44P5.1 - Selected Material from cuttings within the Limits of Works area
Where the material is obtained from cuttings within the Limits of Works area, the rate is an
“extra over” rate to cover any extra costs over and above those costs allowed for under Pay Item
R44P2.
Pay Item R44P5.2 - Selected Material Imported from beyond the Limits of Works area
Where the material is imported from beyond the Limits of Works area, the rate must cover all
costs (including any stabilisation required to conform to TfNSW 3071).
(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)
NR44 Guide to R44 Earthworks
74 Ed 2 / Rev 1
Pay Item R44P5.3 - Verge Material from cuttings within the Limits of Works area
Where the material is obtained from cuttings within the Limits of Works area, the rate is an
“extra over” rate to cover any extra costs over and above those costs allowed for under Pay Item
R44P2.
Pay Item R44P5.4 - Verge Material Imported from beyond the Limits of Works area
Where the material is imported from beyond the Limits of Works area, the rate must cover all
costs.
Pay Item R44P6 - Disposal of Non-Contaminated Spoil Off Site
The schedule rate is an average rate to cover all additional costs associated with the disposal of all
types of non-contaminated material off site, except for topsoil encountered during excavation in
accordance with Clause 2.5.1.
Payment under Pay Item R44P6 is additional to payment under R44P2 or R44P4.
Payment for disposal of non-contaminated topsoil off-site will be made under Pay Item R44P1.2.
The unit of measurement is the bank cubic metre. The volume must be determined by measurement or
survey and calculation using a bulking factor proposed by you and agreed by the Principal or
otherwise determined by the Principal.
Pay Item R44P7 - Foundation Treatments
Pay Item R44P7.1 - Treatment Type E1 and Type C1 - Loosen and Recompact
The schedule rate for this Pay Item is an average rate to cover loosening the floor, terracing,
adjusting the moisture content, processing the material to achieve the specified quality
requirements, and compacting as specified. The Pay Item covers over and above those costs
allowed for under Pay Item R44P2.
The unit of measurement is the square metre.
The area must be determined by measurement, or survey, and calculation. The area must
exclude changes in designed quantities resulting from over-clearing or over-excavation, and
changes to suit you.
Pay Item R44P7.2 – Treatment Type E2 – Bridging Layer
The measured quantity of bridging layer material must exclude changes in designed quantities
resulting from excess widening of the bridging layer, and wastage or changes to suit you.
Geotextile is measured and paid in accordance with the Pay Item for Treatment Type E4
R44P7.3(a).
Pay Item R44P7.2(a) – Material obtained from excavations within the Works.
The unit of measurement must be the cubic metre in place. The quantity must be
determined by measurement, or survey, and calculation.
(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)
Guide to R44 Earthworks NR44
Ed 2 / Rev 1 75
This Pay Item covers all activities associated with the identification, selection, winning,
processing (including breaking down), stockpiling (including double-handling to suit
you), haulage and placing of site won material in the bridging layer, over and above those
costs allowed for under Pay Item R44P2.
Pay Item R44P7.2(b) – Imported Material
The unit of measurement is the tonnes of material placed.
This Pay Item covers all activities associated with the identification, winning/purchasing,
processing (including breaking down), stockpiling (including double-handling to suit
you), testing, haulage and placing of imported material in the bridging layer.
Pay Item R44P7.3 – Treatment Type E4 and Type C4 – Geotextile and Geogrid
This Pay Item covers payment for all works associated with the use of geotextile and geogrids in
earthworks operations, including use in rock fills, and foundation treatments.
Pay Item R44P7.3(a) Geotextile
Pay Item R44P7.3(b) Geogrid
The unit of measurement is the plan square metre of each type of geotextile or geogrid
installed.
The area of geotextile or geogrid must be based on the theoretical cross-section shown on
the Drawings and the length measured in place to provide a continuous length or width of
geotextile or geogrid.
Measurement must not include the areas of laps required to provide a continuous length
or width of geotextile or geogrid.
The rate will include all specific activities required to procure and place geotextile or
geogrid.
Pay Item R44P7.4 – Treatment Type E5 and Type C5 – Drainage Layer
The costs of excavation will be included in Pay Item R44P2.
Geotextile is measured and paid in accordance with the Pay Item for Type E4 Embankment
R44P7.3(a).
The volume of drainage layer material will be included in the following rates.
Pay Item R44P7.4(a) Drainage Layer Material obtained from excavations within the
Works
This Pay Item covers all activities associated with the identification, selection, winning,
haulage, processing (including breaking down), stockpiling (including double-handling to
suit you), haulage and placing of won-on-site material in the drainage layer, over and
above those costs allowed for under Pay Item R44P2.
The unit of measurement is the cubic metre of drainage layer material placed. The
volume must be determined by specified thickness, measured area, and calculation. The
volume must exclude changes in designed quantities resulting from excess widening of
the layer, wastage, local depressions, settlement, or changes to suit you.
(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)
NR44 Guide to R44 Earthworks
76 Ed 2 / Rev 1
Pay Item R44P7.4(b) Imported Drainage Layer Material
This Pay Item covers all activities associated with the identification, winning/purchasing,
processing (including breaking down), stockpiling (including double-handling to suit
you), testing, transportation and placing of imported material in the drainage layer.
The unit of measurement is the cubic metre of drainage layer material placed. The
volume must be determined by specified thickness, measured area, and calculation. The
volume must exclude changes in designed quantities resulting from excess widening of
the layer, wastage, local depressions, settlement, or changes to suit you.
Pay Item R44P8 - Identification, Treatment and Disposal Off Site of Contaminated
Material
NOTES TO TENDER DOCUMENTER: (Delete this boxed text after customising Pay Item R44P8)
Use Pay Item R44P8.1 where the presence of specific types of contaminated materials has been
identified during site investigation. Provide separate sub-pay items R44P8.1(a), R44P8.1(b), etc for
each type of identified contaminated material, with descriptions of the contaminated material.
Use Pay Item R44P8.2 for any potential contaminated material which have not been identified at time
of tender.
This Pay Item covers additional costs of all activities associated with the identification, classification
in accordance with OEH Waste Classification Guidelines, treatment, loading, haulage and disposal of
contaminated material at sites legally authorised to accept the contaminated material, whether the
contaminated material is topsoil, general fill or unsuitable material.
Payment under Pay Item R44P8 is additional to payment made under Pay Items R44P1.2, R44P2 or
R44P4 as applicable.
Pay Item R44P8.1 – Identified Contaminated Material
The unit of measurement is the tonne of disposed material. The quantity must be determined
using weighbridge dockets or invoices issued by the disposal facility.
Pay Item R44P8.2 – Other Contaminated Material
The Pay Item is a Provisional Sum.
Payment will be made for the costs of the activities required by Clause 2.5.2 for any
contaminated material other than those provided in Pay Item R44P8.1 plus the provisional sum
margin added in accordance with Clause 55.4 of the General Conditions of Contract.
(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)
Guide to R44 Earthworks NR44
Ed 2 / Rev 1 77
ANNEXURE R44/C – SCHEDULES OF HOLD POINTS, WITNESS
POINTS AND IDENTIFIED RECORDS
C1 SCHEDULE OF HOLD POINTS
Clause Description
TfNSW G71
Cl 3.2
Notification of Joint Survey.
2.3.3 &
TfNSW G71
Cl 3.2
Submission of Joint Survey results.
2.4 Inspection after removal of unsuitable material and prior to backfilling.
3.2 Presentation of embankment foundation after removal of topsoil.
3.2 Presentation of CBR and PI of materials in the foundation of Shallow Embankments.
3.4 Presentation of each Lot of floor of cuttings.
4.3 Presentation of cleaned batter and bench/floor surfaces for Geotechnical inspection.
4.7.1 Submission of blasting procedure details.
Submission of altered blasting procedure details.
6.1.1 Details of material for Upper Zone of Formation (including Selected Material)
arranged by you. Submission of details of location, quantities, type and verification of
conformity. Verification that all possible onsite sources of material have been
exhausted.
6.1.2 Verification of conformity of Selected Material.
6.1.2 Verification of conformity of each Lot of Selected Material Zone with test and survey
reports.
6.2 Details of imported verge material arranged by you.
7.3 Compaction of rock fills – verification of conformity of each trial section including
submission of Compaction Routine, test results and survey reports.
7.4.2 Placing Selected Material Zone (or pavement where no Selected Material Zone is
specified) – deflection testing results, finished surface levels and verification of
conformity of the formation.
C2 SCHEDULE OF WITNESS POINTS
Clause Description
7.3 Construction of each trial section of rock fill.
7.4.1 Proof rolling of embankment layers and other surfaces within 1.5 m of the underside of
the Selected Material Zone.
7.4.2 Benkelman Beam testing of Selected Material Zone.
(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)
NR44 Guide to R44 Earthworks
78 Ed 2 / Rev 1
C3 SCHEDULE OF IDENTIFIED RECORDS
The records listed below are Identified Records for the purposes of TfNSW Q Annexure Q/E.
Clause Description of Identified Record
2.4 Notification that unsuitable material has been removed as directed
2.3.2 Survey report of surface levels after removal of topsoil
2.3.3 Submission or survey report and notification that topsoil has been removed from
foundation for embankment
2.8.1 Details of source, location, quantities and type of Selected Material. Verification, with
test results, of conformity of material
3.2 CBR and PI test results and notification that topsoil has been removed from each
Shallow Embankment foundation
3.4.1 CBR and PI test results and notification that floor of cutting has been ripped or
loosened
4.7.1 Report of Buildings Conditions Inspection of all structures likely to be affected by any
blast
4.7.1 Blasting procedure, including quantity and type of explosives and pattern and
certification of the proposed structural survey
4.7.3 Blasting records
6.1 Proposed location, quantities and type of imported Upper Zone of Formation materials
6.1.2 Test reports of each Lot of stockpiled material for use in Selected Material Zone.
Verification of conformity of each Lot of Selected Material Zone with relevant test and
survey reports
7.4 Deflection testing results of each Lot of formation
ANNEXURES R44/D TO R44/K – (NOT USED)
(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)
Guide to R44 Earthworks NR44
Ed 2 / Rev 1 79
ANNEXURE R44/L – TEST METHODS, MINIMUM FREQUENCY OF
TESTING AND ACCEPTANCE CRITERIA
A summary of the appropriate test methods, minimum frequencies of testing and acceptance criteria in
the earthworks construction process is given in Table R44/L.1.
Table R44/L.1 – Control of Earthworks Process
Work Sequence Reference
Clause Test Method
Minimum Frequency
Acceptance Criteria
1. Project Planning 1.5
PROJECT QUALITY PLAN TfNSW Q TfNSW Q TfNSW Q
EARTHWORKS PLAN 1.5 & 2.2 1.5 1.5
2. Clearing and Grubbing 2.3.1
Completion of clearing and grubbing TfNSW G40 Each section Complete
3. Erosion and Sedimentation Control 1.7
Installing and maintaining effective erosion and sedimentation control measures.
TfNSW G38 or G39
Inspection Each section Approved E&SC Plan
4. Setting Out of Earthworks 1.6
Establish and maintain batter profiles and Transition Zones.
1.6 TfNSW G71 Each section In place
Remove pegs at the completion of work Inspection Each section All removed
5. Stockpile Sites 2.6
Stockpile sites not shown on the Drawings - Obtain the Principal’s approval at least 10 working days in advance
2.6 Each stockpile Approval
Install erosion and sedimentation measures 2.6, TfNSW G38 or G39
Inspection Each stockpile Complete
Restoration of stockpile sites 2.6 Inspection Each stockpile TfNSW R178
6. Topsoil 2.3
6.1 Removal of Topsoil 2.3.1
Survey of stripped surfaces Hold Point
2.3.3, 1.6 TfNSW G71
6.2 Stockpiling Topsoil
Survey of stockpile sites 2.3.2, 1.6 TfNSW G71 Each stockpile TfNSW G71
Stockpile height and shape 2.3.2 Measure Each stockpile Height < 2.5m Slope < 2:1
Contents of stockpile 2.3.2 Inspection Each stockpile 2.3.2
Seeding of stockpile 2.3.2, TfNSW R178
Inspection TfNSW R178 TfNSW R178
7. Embankment Foundations 3
7.1 Preparation of Embankment Foundations 3.2
Removal of topsoil 2.3.1 Inspection Each section Complete
Stripped surface survey 1.6.3 Survey TfNSW G71 Complete
Excavate foundation to ensure a minimum height of formation
3.5.1 Survey TfNSW G71 Report
Excavated surface survey 1.6.3 Survey TfNSW G71 Report
Test Shallow Embankment for 3.5.1
- CBR R44/A2.2 1000 m2 Report
- PI R44/A2.2 1000 m2 Report
Preparation of each Lot of embankment foundation Hold Point
3.2 Each section Complete
7.2 Unsuitable Material 2.4
(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)
NR44 Guide to R44 Earthworks
80 Ed 2 / Rev 1
Work Sequence Reference
Clause Test Method
Minimum Frequency
Acceptance Criteria
Removal of unsuitable material Hold Point
2.4 Inspection Each Lot Complete
Replacement of unsuitable material 2.4 Inspection Each Lot Complete
- Compaction 5.1 TfNSW T111, T119, T162, T166, T173
TfNSW Q Table R44.11
- Moisture content 5.1 TfNSW T120, T121, T180
TfNSW Q R44/A5
7.3 Loosen and Compact (E1) 3.2.1
Authorisation given 3.2.1 Each section Authorised
Ripping depth & extent 3.2.1 Inspection Each section 3.2.1
- Compaction 7.2 TfNSW T111, T119, T162, T166, T173
TfNSW Q Table R44.11
- Moisture content 7.2 TfNSW T120, T121, T180
TfNSW Q R44/A5
7.4 Use of Bridging Layer (Treatment Type E2) 3.2.2
Authorisation given 3.2.2 Each section Authorised
Material suitability 3.2.2 Inspection Each section 3.2.2
Bridging layer placed 3.2.2 Inspection Each section 3.2.2
7.5 Use of Chemical Stabilisation (Treatment Type E3) 3.2.3
Authorisation given 3.2.3 Each section Authorised
Foundation stabilised 3.2.3 TfNSW R50 TfNSW R50 TfNSW R50
7.6 Use of Geotextile or Geogrid (Treatment Type E4) 3.2.4
Authorisation given 3.2.4 Each section Authorised
Material suitability 3.2.4 TfNSW R63, R67
TfNSW R63, R67
TfNSW R63, R67
Geotextile or geogrid installation 3.2.4 TfNSW R63, R67
TfNSW R63, R67
TfNSW R63, R67
7.7 Use of Drainage Layer (Treatment Type E5) 3.2.5
Authorisation given 3.2.5 Each section Authorised
Material Suitability:
- Grading 3.2.5 AS Sieve 200 m3 3.2.5
- Point Load Strength of rock 3.2.5 TfNSW T223 200 m3 R44/A2.2
- Wet/Dry Strength Variation 3.2.5 TfNSW T215 Each source R44/A2.2
Drainage layer placed 3.2.5 Inspection Each section Complete
7.8 Use of Foundation Treatment Type E6 3.2.6
8. Cuttings 3.4, 4
8.1 Preparation of Cutting Area
Removal of topsoil 2.3.1 Inspection Each section Complete
Stripped surface survey 1.6.3 TfNSW G71 Each section Report
8.2 Excavation 4.2
Material loosened and broken down such that it can be incorporated into the Works, meeting the requirements for:
2.1, 2.2, 4.2 Inspection & Audit
Materials available and conform
- Rock facing of batters 5.5
- Placing adjacent to weepholes 5.6.2
- Select Fill adjacent to structures 5.6.3
- Upper Zone of Formation 6.1.1
(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)
Guide to R44 Earthworks NR44
Ed 2 / Rev 1 81
Work Sequence Reference
Clause Test Method
Minimum Frequency
Acceptance Criteria
- Transition Zone 3.5.2
- Selected Material Zone 6.1.2
- Verge 6.2
- Backfill in cuttings 3.4.2
- Other treatments 6.3
- Earth fill 5.2
- Rock fill 5.3
- Bridging layers 3.2.2
- Drainage layers 3.2.5, 3.4.5
- Working platforms 3.2.3, 3.4.3
Protection of earthworks 1.7 Inspection Daily 1.7
8.3 Batters 4.4
Batters conform to specification tolerances 4.4 Survey Each batter Table R44.3
Tops and ends of cuttings treated 4.2 Inspection Each batter 4.2
Rock cuttings cleaned down Hold Point
4.3 Inspection Each batter 4.3
Batter stabilisation works 4.3 As directed As directed As directed
Treatment of batters 4.2 As directed As directed 4.2
8.4 Benching in Cuttings 4.5
Benches must conform to tolerances and drain 4.5 Survey Each bench 7.5
8.5 Blasting 4.7
Obtaining of licences and meeting regulatory requirements
4.7.1 Before blasting starts
AS 2187 Parts I & II
Conducting Building Condition Inspection 4.7.1 Inspection TfNSW G35 or G36 Clause 6.8
TfNSW G35 or G36 Clause 6.8
Implement and maintain a community liaison program 4.7.1 Monitor Each blast TfNSW G35 or G36 Clause 6.8
Presplitting of batters with slopes 1:1 Drill hole spacing
4.6
Measure
Each blast
4.6
Start of each blasting operation – submit details Hold Point
4.7.1 Each blast Details OK
Control airblast 4.7.4 AS2187.2 Each blast Annex R44/A6
Control ground vibration 4.7.5 AS2187.2 Each blast Annex R44/A6
Blasting records 4.7.3 Inspection Each blast Submitted on day of blast
8.6 Cut/Fill Transition 3.5.2
Survey and mark the position of the intersection line between cutting and embankment occurring at the underside of the Selected Material Zone
1.6.1 Survey Each transition Report
Excavate a Transition Zone 3.5.2 Survey Each transition 3.5.2 & R44/A4
Excavated terrace should be made free-draining 3.5.2 Inspection Each transition Drainage achieved
9. Foundation Treatments for Cuttings 3.4
9.1 Preparation of Cutting Foundations 3.4
Removal of topsoil 2.3.1 Inspection Each section Complete
Excavate cutting to Designed Floor Level 3.4 Survey TfNSW G71 7.5
Test cutting floor for: 3.4
- CBR R44/A2.2 1000 m2 R44/A2.2
(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)
NR44 Guide to R44 Earthworks
82 Ed 2 / Rev 1
Work Sequence Reference
Clause Test Method
Minimum Frequency
Acceptance Criteria
- PI R44/A2.2 1000 m2 R44/A2.2
Preparation of each Lot of cutting foundation Hold Point
3.4 Each section Complete
9.2 Unsuitable Material 2.4
Removal of unsuitable material Hold Point
2.4 Inspection Each Lot Complete
Replacement of unsuitable material 2.4 Inspection Each Lot Complete
- Compaction 7.2 TfNSW T111, T119, T162, T166, T173
TfNSW Q Table R44.11
- Moisture content 7.2 TfNSW T120, T121, T180
TfNSW Q R44/A5
9.3 Loosen and Compact (Treatment Type C1) 3.4.1
Authorisation given 3.4.1 Each section Authorised
Ripping depth and extent and particle size 3.4.1 Inspection 1000 m2 3.4.1
- Compaction 7.2 TfNSW T111, T119, T162, T166, T173
TfNSW Q Table R44.11
- Moisture content 7.2 TfNSW T120, T121, T180
TfNSW Q R44/A5
9.4 Excavation and Backfill (Treatment Type C2) 3.4.2
Authorisation given 3.4.2 Each section Authorised
Excavate cutting to Foundation Level 3.4.2 Survey TfNSW G71 7.5
Loosen and compact as above 3.4.2, 3.4.1
Backfill material suitability: 3.4.2
- CBR R44/A2.2 500 m3 R44/A2.2
- PI R44/A2.2 500 m3 R44/A2.2
Compaction of backfill 7.2 TfNSW T111, T119, T162, T166, T173
TfNSW Q Table R44.11
Moisture content of backfill 7.2 TfNSW T120, T121, T180
TfNSW Q R44/A5
Trimming of backfill 3.4.2 Survey TfNSW G71 7.5
9.5 Use of Working Platform (Treatment Type C3) 3.4.3
Authorisation given 3.4.3 Each section Authorised
Foundation stabilised 3.4.3 TfNSW R50 TfNSW R50 TfNSW R50
Trimming of working platform 3.4.3 Survey TfNSW G71 7.5
9.6 Use of Geotextile or Geogrid (Treatment Type C4) 3.4.4
Authorisation given 3.4.4 Each section Authorised
Material suitability 3.4.4 TfNSW R63, R67
TfNSW R63, R67
TfNSW R63, R67
Geotextile or geogrid installation 3.4.4 TfNSW R63, R67
TfNSW R63, R67
TfNSW R63, R67
9.7 Use of Drainage Layer (Treatment Type C5) 3.4.5
Authorisation given Each section Authorised
Excavate cutting to Foundation Level 3.4.5 Survey TfNSW G71 7.5
Material Suitability:
- Grading 3.4.5 AS Sieve 200 m3 3.4.5
- Point Load Strength of Rock 3.4.5 TfNSW T223 200 m3 R44/A2.2
- Wet/Dry strength variation 3.4.5 TfNSW T215 Each source R44/A2.2
(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)
Guide to R44 Earthworks NR44
Ed 2 / Rev 1 83
Work Sequence Reference
Clause Test Method
Minimum Frequency
Acceptance Criteria
Drainage layer placed 3.4.5 Inspection Each section 3.4.5, 7.3
Trimming of drainage layer 3.4.5 Survey TfNSW G71 7.5
9.8 Use of Other Foundation Treatment Types 3.4.6
10. Embankments 5
10.1 Embankment Materials 2.2, 5
Site won earth fill material: 5.2
- Deleterious materials and homogeneity 5.2 Inspection Each Lot 5.2
- Particle dimensions 5.2 AS Sieve 1000 m3 5.2
Rock fill material: 5.3
- Maximum particle dimension 5.3.2 AS Sieve 5.3.2
- Point load strength 5.3.2 TfNSW T223 500 m3 R44/A2.2
- Wet/Dry strength variation 5.3.2 TfNSW T215 Each source R44/A2.2
Rock fill capping layer material: 5.3.3
- Maximum particle dimension 5.3.3 AS Sieve 5.3.3
- Point load strength 5.3.3 TfNSW T223 500 m3 R44/A2.2
- Wet/Dry strength variation 5.3.3 TfNSW T215 Each source R44/A2.2
10.2 Borrow Sites and Imported Materials 2.7, 2.8, 6
Source of imported fill 2.7 Identify source(s)
10 days prior to commencing work at each source
Approvals for source
Delivery of imported materials Hold Point
6.1.1, 6.2 6.1.1, 6.2 Each source R44/A2
Survey to determine quantity of imported materials placed in the Works
1.6.3, 6.1.1, 6.2
Survey Each site for imported materials
TfNSW G71
Site preparation of borrow sites 2.7.1 Inspection Each borrow site
2.7.1, TfNSW G40
Location and shape of borrow sites 2.7.2 Inspection Each borrow site
2.7.2, R44/A2.1
Restoration of borrow sites 2.7.1 Inspection Each borrow site
TfNSW R178
10.3 Earth Fill Construction 5.2
Placing earth fill for embankment construction:
- Layer thickness 5.2 Measure Each Lot 5.2
- Lot homogeneity 5.1 Inspection Each Lot 5.2
- Compaction TfNSW T111, T119, T162, T166, T173
TfNSW Q Table R44.11
- Moisture TfNSW T120, T121, T180
TfNSW Q R44/A5
Hillside embankment foundations 3.3 Inspection Each earthworks Lot
Terraced as per 3.3
Protection of earthworks 1.7 Inspection Daily 1.7
Placing earth fill at “spill-through” bridge abutment zone: 5.2.1 5.2.1
- Width and height of zone 5.2.1 Measure Each Lot 5.2.1
- Earth fill material:
▪ Grading 5.2.1 AS sieve 400 m3 5.2.1
▪ CBR 5.2.1 R44/A2.2 400 m3 5.2.1
▪ PI 5.2.1 R44/A2.2 400 m3 5.2.1
(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)
NR44 Guide to R44 Earthworks
84 Ed 2 / Rev 1
Work Sequence Reference
Clause Test Method
Minimum Frequency
Acceptance Criteria
- Layer thickness 5.2.1 Measure Each Lot 5.2.1
- Lot homogeneity 5.1 Inspection Each Lot 5.2.1
- Compaction 5.2.1 TfNSW T111, T119, T162, T166, T173
TfNSW Q Table R44.11
- Moisture TfNSW T120, T121, T180
TfNSW Q R44/A5
10.4 Rock Fill Construction
Placing rock fill for embankment construction
- Trial sections Witness Point / Hold Point
7.3 7.3 Each trial section
7.3
- Layer thickness 5.3 Measure Each Lot 5.3
- Lot homogeneity 5.1 Inspection Each Lot 5.3.1
- Compaction Witness Point
7.3 Inspection & Proof Roll
Each Lot 7.3, 7.4.1
Hillside embankment foundations 3.3 Inspection Each earth-works Lot
Terraced as per 3.3
Placing rock fill capping layer for embankment construction
- Trial sections Witness Point / Hold Point
7.3 7.3 Each trial section
7.3
- Layer thickness 5.3.3 Measure Each Lot 5.3.3
- Lot homogeneity 5.1 Inspection Each Lot 5.3.3
- Compaction Witness Point
7.3 Inspection & Proof Roll
Each Lot 7.3, 7.4.1
Geotextiles:
- Material suitability 5.3.5 TfNSW R63 TfNSW R63 TfNSW R63
- Geotextile or geogrid installation 5.3.5 TfNSW R63 TfNSW R63 TfNSW R63
Protection of earthworks 1.7 Inspection Daily 1.7
10.5 Embankment Batters 5.4
Batters conform to specification tolerances 5.4 Survey Each batter 5.4
Batters free of loose material 5.4 Inspection Each batter 5.4
Treatment of batters 5.4 As directed As directed 5.4
10.6 Rock Facing 5.5
Rock facing material: 5.5
- Maximum particle dimension 5.5 AS Sieve 5.5
- Point load strength 5.5 TfNSW T223 500 m3 R44/A2.2
- Wet/Dry strength variation 5.5 TfNSW T215 Each source R44/A2.2
Placing Rock Facing for embankment construction 5.5 Inspection Each section 5.5
10.7 Fill adjacent to Structures 5.6
Materials 5.6.1 TfNSW R11, R22, B30
TfNSW R11, R22, B30
TfNSW R11, R22, B30
Placing fill adjacent to structures:
- Width & height 5.6.3 Measure Each Lot Table R44.9
- Layer thickness 5.6.3 Measure Each Lot 5.6.3
- Lot homogeneity 5.6.3 Inspection Each Lot 5.6.3
- Compaction 5.6.3 TfNSW T111, T119, T162, T166, T173
TfNSW Q Table R44.11
(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)
Guide to R44 Earthworks NR44
Ed 2 / Rev 1 85
Work Sequence Reference
Clause Test Method
Minimum Frequency
Acceptance Criteria
- Moisture 5.6.3 TfNSW T120, T121, T180
TfNSW Q R44/A5
Treatment at weepholes:
- Materials 5.6.2 AS Sieve 10 m3 5.6.2
- Placement 5.6.2 Measure Each Lot 5.6.2
- Synthetic membrane 5.6.2 Inspection Each Lot Manufacturer’s Spec
11. Structural Treatments
11.1 Material in the Upper Zones of Formation other than Selected Material Zone
2.8.2
Site won 2.8.2.1
- Maximum particle dimension (where applicable) 2.8.2.1 AS Sieve 1000 m3 2.8.2.1
- Minimum CBR value 2.8.2.1 R44/A2.2 1000 m3 R44/A2.2
- Maximum PI value 2.8.2.1 R44/A2.2 1000 m3 R44/A2.2
Imported 2.8.2.2
- Maximum particle dimension (where applicable) 2.8.2.1 AS Sieve 1000 m3 2.8.2.1
- Minimum CBR value 2.8.2.2 R44/A2.2 1000 m3 R44/A2.2
- Maximum PI value 2.8.2.2 R44/A2.2 1000 m3 R44/A2.2
11.2 Material in the Selected Material Zone 2.8.3
Site won 2.8.3.1
- Maximum particle dimension (where applicable) 2.8.3.1 AS Sieve 1000 m3 2.8.3.1
- Minimum CBR value 2.8.3.1 R44/A2.2 1000 m3 R44/A2.2
- Maximum PI value 2.8.3.1 R44/A2.2 1000 m3 R44/A2.2
Imported 2.8.3.2 TfNSW 3071 TfNSW 3071 TfNSW 3071
11.3 Material in Verges 2.8.4
Site won 2.8.4.1
- Maximum particle dimension and grading 2.8.4.1 AS Sieve 1000 m3 2.8.4.1
- Minimum CBR value 2.8.4.1 R44/A2.2 1000 m3 R44/A2.2
- Maximum PI value 2.8.4.1 R44/A2.2 1000 m3 R44/A2.2
Imported 2.8.4.2 TfNSW 3071 TfNSW 3071 TfNSW 3071 (Type B) & R44/A2.2
11.4 Placing Material for Upper Zone of Formation Hold Point
6.1.1
- Layer thickness 6.1.1 Measure Each Lot R44/A4
- Compaction 6.1.1 TfNSW T111, T119, T162, T166, T173
TfNSW Q Table R44.11
- Moisture 6.1.1 TfNSW T120, T121, T180
TfNSW Q R44/A5
11.5 Placing Material in the Selected Material Zone 6.1.2
- Layer thickness 6.1.2 Measure Each Lot R44/A4
- Compaction 6.1.2 TfNSW T111, T119, T162, T166, T173
TfNSW Q Table R44.11
- Moisture 6.1.2 TfNSW T120, T121, T180
TfNSW Q R44/A5
Verification of conformity for covering Hold Point
6.1.2 Reports Each Lot, Table R44.10
6.1.2
11.6 Placing Fill for Verges 6.2
- Layer thickness 6.2 Measure Each Lot R44/A4
(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)
NR44 Guide to R44 Earthworks
86 Ed 2 / Rev 1
Work Sequence Reference
Clause Test Method
Minimum Frequency
Acceptance Criteria
- Compaction 6.2 TfNSW T111, T119, T162, T166, T173
TfNSW Q Table R44.11
- Moisture 6.2 TfNSW T120, T121, T180
TfNSW Q R44/A5
11.7 Other Treatments 6.3
12. Deflection Testing 7.4
Proof rolling Witness Point
7.4.1 TfNSW T198 7.4.1 7.4.1
Benkelman Beam testing at underside of the Selected Material Zone. Hold Point
7.4.2 TfNSW T199 R44/A4 7.4.2, R44/A4
Benkelman Beam testing at top of the Selected Material Zone. Witness Point / Hold Point
7.4.2 TfNSW T199 R44/A4 7.4.2, R44/A4
13. Level Control 7.5
Surface levels of Selected Material Zone, formation, floor of cutting, drainage layer, working platform, cut/fill transitions, benches in cuttings, rock fill and verges
7.5.1 Survey TfNSW G71 7.5.1
Median areas 7.5.3 Survey TfNSW G71 7.5.3
14. Spoil 2.5
14.1 Non-contaminated Materials 2.5.1
Authorisation given within the site 2.5.1 Each location Authorised
Authorisation given for off site 2.5.1
10 days prior to commencing work at each location
Approvals provided & authorised
Compaction 2.5.1 TfNSW T111, T119, T162, T166, T173
TfNSW Q Table R44.11
14.2 Contaminated Materials 2.5.2
Method & location of disposal 2.5.2 Submission Each source/ location
TfNSW G35 or G36
(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)
Guide to R44 Earthworks NR44
Ed 2 / Rev 1 87
ANNEXURE R44/M – REFERENCED DOCUMENTS
TfNSW Specifications
TfNSW G1 Site Specific Requirements
TfNSW G10 Traffic Management
TfNSW G35 or G36 Environmental Protection
TfNSW G38 or G39 Soil and Water Management
TfNSW G40 Clearing and Grubbing
TfNSW G71 Construction Surveys
TfNSW Q Quality Management System
TfNSW B30 Excavation and Backfill for Bridgeworks
TfNSW R11 Stormwater Drainage
TfNSW R22 Corrugated Metal Structures
TfNSW R33 Trench Drains
TfNSW R50 Stabilisation of Earthworks
TfNSW R58 or R59 Construction of Reinforced Soil Walls
TfNSW R63 Geotextiles (Separation and Filtration)
TfNSW R67 High Strength Geosynthetic Reinforcement
TfNSW R178 Vegetation
TfNSW 3071 Selected Material for Formation
TfNSW Test Methods
TfNSW T102 Pretreatment of Samples of Road Materials by Compaction
TfNSW T103 Pretreatment of Road Materials by Artificial Weathering
TfNSW T105 Preparation and Division of Samples for Testing
TfNSW T108 Liquid Limit of Road Materials
TfNSW T109 Plastic Limit and Plasticity Index of Road Materials
TfNSW T111 Dry Density/Moisture Relations of Road Materials (Standard Compaction)
TfNSW T117 California Bearing Ratio of Remoulded Specimens of Road Materials
TfNSW T119 Determination of Density of Road Materials insitu using the Sand Replacement
Method
TfNSW T120 Determination of Moisture Content of Road Materials (Standard Method)
TfNSW T121 Determination of Moisture Content of Road Materials (Sand Bath or Hot Plate
Method)
TfNSW T131 Determination of Unconfined Compressive Strength of Road Materials
Stabilised or modified with Proportions of Cement Lime or Other Cementitious
Materials
TfNSW T160 Benkelman Beam Deflection Test
(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)
NR44 Guide to R44 Earthworks
88 Ed 2 / Rev 1
TfNSW T162 Compaction Control Test (Rapid Method)
TfNSW T166 Determination of Relative Compaction
TfNSW T173 Determination of Field Wet Density of Pavement Materials using a Nuclear
Gauge in Direct Transmission Mode
TfNSW T180 Determination of Moisture Content of Road Materials (Microwave Oven
Method)
TfNSW T198 Proof Rolling Test
TfNSW T199 Deflection Monitoring Test
TfNSW T215 Wet/Dry Strength Variation
TfNSW T223 Point Load Strength of Rock Specimens, Field Method
Australian Standards
AS 1289.3.8.1 Methods of testing soils for engineering purposes – soil classification tests –
Dispersion – Determination of Emerson class number of a soil
AS 2187 Parts 1 and 2. Explosives – Storage, transport and use
AS 3725 Loads on buried concrete pipes
Other References
NAASRA Explosives in Roadworks Users Guide 1982
ANZECC Technical Basis for Guidelines to Minimise Annoyance due to
Blasting Overpressure and Ground Vibration
(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)
Guide to R44 Earthworks NR44
Ed 2 / Rev 1 89
(Note: Next 2 clauses to be added as an amendment to this Specification only in appropriate
situations)
4.7.4 Control of Airblast
This Clause will apply only where a noise sensitive location exists within 1 km of the blasting site.
Comply with the criteria recommended in the “ANZECC Technical Basis for Guidelines to Minimise
Annoyance Due to Blasting Overpressure and Ground Vibration (ANZECC)”. The Measurement
process for determining verification of compliance with the ANZECC criteria is to be in accordance
with "AS 2187.2 Explosives - Storage, Transport and Use, Appendix J - Ground Vibration and
Airblast (Informative)".
The noise emanating from blasting operations must not exceed the limits in Annexure R44/A6 at any
noise sensitive location, measured at the noise monitoring location nearest to the noise sensitive
location.
Provide and operate equipment for the monitoring of airblast to ensure compliance with the specified
limits. All monitoring must be carried out by personnel possessing current NATA accreditation for
such monitoring unless approved otherwise by the Principal. Equipment used for monitoring must be
calibrated annually by a recognised testing facility. All test results must be reported on test certificates
which must include a clear statement as to compliance or non-compliance with the requirements of
this Specification. In general, a monitoring location will be near the perimeter of the noise sensitive
location at the point closest to the maximum charge. Provide a copy of the monitoring record to the
Principal.
In the event that the measured airblast exceeds the specified limits, suspend further blasting work and
take additional steps and precautions to ensure that, for any future blast, the limiting airblast must not
be exceeded. Do not resume any blasting until details of the additional steps and precautions have
been provided to the Principal.
4.7.5 Control of Ground Vibration
Provide and operate equipment for the monitoring of ground vibrations to ensure compliance with
Annexure R44/A6. All monitoring must be carried out by personnel possessing current NATA
accreditation for such monitoring unless approved otherwise by the Principal. The measurement
process for determining verification of compliance with the ANZECC criteria is to be in accordance
with AS 2187.2.
Equipment used for monitoring must be calibrated annually by a NATA accredited testing facility or
manufacturer’s facility approved by the Principal. All test results must be reported on test certificates,
which must include a clear statement as to compliance or non-compliance with the requirements of
this Specification. In general, a monitoring location will be near the perimeter of the structure or
building at the point closest to the maximum charge. Provide a copy of the monitoring record to the
Principal.
To minimise the risk of peak particle velocity limits being exceeded, develop a blasting site
relationship between peak particle velocity, distance and blasting charge.
For the first blast, monitors must be set up at not less than five points at varying distances away from
the blasting site. The Maximum Instantaneous Charge for the first blast must not exceed that
calculated from the following formula:
(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)
NR44 Guide to R44 Earthworks
90 Ed 2 / Rev 1
where MIC = Maximum Instantaneous Charge in kilograms
D = Distance in metres from charge to the point of potential damage
p.p.v = limiting peak particle velocity from Annexure R44/A6
For subsequent blasts, the charge weight and other aspects of blast design may be adjusted provided
that further ground vibration monitoring is undertaken and the blasting site relationship re-determined
to demonstrate that charge weight limits are not exceeded. Make the graphs available to the Principal,
if so requested.
MIC 0.5
D
p p v. . ..
1140
0 625
2