98
Edition 2 / Revision 1 TRANSPORT FOR NSW June 2020 TRANSPORT FOR NSW (TfNSW) SPECIFICATION GUIDE NR44 GUIDE TO QA SPECIFICATION R44 EARTHWORKS REVISION REGISTER Ed/Rev Number Clause Number Description of Revision Authorised By Date Ed 1/Rev 0 First issue. Ed 2/Rev 0 Updated to accord with R44 Ed 4 Rev 1. Ed 2/Rev 1 Global References to “Roads and Maritime Services” or “RMS” changed to “Transport for NSW” or “TfNSW” respectively. DCS 22.06.20

TRANSPORT FOR NSW (TfNSW) SPECIFICATION GUIDE NR44 GUIDE …

  • Upload
    others

  • View
    198

  • Download
    0

Embed Size (px)

Citation preview

Page 1: TRANSPORT FOR NSW (TfNSW) SPECIFICATION GUIDE NR44 GUIDE …

Edition 2 / Revision 1 TRANSPORT FOR NSW

June 2020

TRANSPORT FOR NSW (TfNSW)

SPECIFICATION GUIDE NR44

GUIDE TO QA SPECIFICATION R44

EARTHWORKS

REVISION REGISTER

Ed/Rev

Number

Clause

Number Description of Revision

Authorised

By Date

Ed 1/Rev 0 First issue.

Ed 2/Rev 0 Updated to accord with R44 Ed 4 Rev 1.

Ed 2/Rev 1 Global References to “Roads and Maritime

Services” or “RMS” changed to

“Transport for NSW” or “TfNSW”

respectively.

DCS 22.06.20

Page 2: TRANSPORT FOR NSW (TfNSW) SPECIFICATION GUIDE NR44 GUIDE …
Page 3: TRANSPORT FOR NSW (TfNSW) SPECIFICATION GUIDE NR44 GUIDE …

Edition 2 / Revision 1 TRANSPORT FOR NSW

June 2020

SPECIFICATION GUIDE NR44

GUIDE TO QA SPECIFICATION R44 EARTHWORKS

Copyright – Transport for NSW IC-QA-NR44

VERSION FOR:

DATE:

Page 4: TRANSPORT FOR NSW (TfNSW) SPECIFICATION GUIDE NR44 GUIDE …
Page 5: TRANSPORT FOR NSW (TfNSW) SPECIFICATION GUIDE NR44 GUIDE …

Guide to R44 Earthworks NR44

Ed 2 / Rev 1 i

CONTENTS

CLAUSE PAGE

1 GENERAL ........................................................................................................................................ 1 1.1 Introduction .................................................................................................................... 1 1.2 Scope .............................................................................................................................. 3 1.3 Structure of Specification ............................................................................................... 5 1.4 Definitions ...................................................................................................................... 6 1.5 Earthworks Plan.............................................................................................................. 9 1.6 Surveying ...................................................................................................................... 12 1.7 Protection of Earthworks .............................................................................................. 12

2 EARTHWORKS MATERIALS .......................................................................................................... 13 2.1 General ......................................................................................................................... 13 2.2 Materials Management ................................................................................................. 13 2.3 Topsoil .......................................................................................................................... 13 2.4 Unsuitable Material ...................................................................................................... 15 2.5 Spoil .............................................................................................................................. 17 2.6 Stockpile Sites .............................................................................................................. 18 2.7 Borrow Sites ................................................................................................................. 19 2.8 Material in Upper Zone of Formation and Verges ....................................................... 20

3 FOUNDATIONS .............................................................................................................................. 22 3.1 General ......................................................................................................................... 22 3.2 Foundations for Embankments ..................................................................................... 22 3.3 Foundation Treatment for Hillside Embankments ....................................................... 27 3.4 Foundation Treatments for Cuttings ............................................................................. 28 3.5 Shallow Embankment and Cut/Fill Transition ............................................................. 34

4 CUTTINGS ..................................................................................................................................... 37 4.1 General ......................................................................................................................... 37 4.2 Excavation .................................................................................................................... 37 4.3 Cuttings in Rock ........................................................................................................... 38 4.4 Batter Tolerances .......................................................................................................... 38 4.5 Benching in Cuttings .................................................................................................... 39 4.6 Pre-splitting or Line Drilling ........................................................................................ 40 4.7 Blasting ......................................................................................................................... 40

5 EMBANKMENTS ............................................................................................................................ 42 5.1 General ......................................................................................................................... 42 5.2 Earth Fill Embankments ............................................................................................... 43 5.3 Rock Fill Embankments ............................................................................................... 46 5.4 Embankment Batters .................................................................................................... 48 5.5 Rock Facing of Embankments ...................................................................................... 49 5.6 Fill Placed Adjacent to Structures ................................................................................ 50

6 STRUCTURAL TREATMENTS ......................................................................................................... 51 6.1 Upper Zone of Formation ............................................................................................. 51 6.2 Verges ........................................................................................................................... 53 6.3 Other Treatments .......................................................................................................... 54

7 ADDITIONAL CONFORMITY REQUIREMENTS ............................................................................... 54 7.1 General ......................................................................................................................... 54 7.2 Earth Fill ....................................................................................................................... 54

Page 6: TRANSPORT FOR NSW (TfNSW) SPECIFICATION GUIDE NR44 GUIDE …

NR44 Guide to R44 Earthworks

ii Ed 2 / Rev 1

7.3 Rock Fill ...................................................................................................................... 57 7.4 Deflection Testing........................................................................................................ 58 7.5 Level Control ............................................................................................................... 60

ANNEXURE R44/A – PROJECT SPECIFIC INFORMATION ........................................................................ 62 A1 Surveys (Clause 1.6) .................................................................................................... 62 A2 Materials ...................................................................................................................... 63 A3 Foundation Treatment .................................................................................................. 65 A4 Shallow Embankment, Cut/Fill Transition, Upper Zone of Formation and Verges .... 66 A5 Compaction Moisture Requirements (Clause 7.2) ....................................................... 67 A6 Blasting (Clause 4.7).................................................................................................... 68

ANNEXURE R44/B – MEASUREMENT AND PAYMENT ........................................................................... 70

ANNEXURE R44/C – SCHEDULES OF HOLD POINTS, WITNESS POINTS AND IDENTIFIED RECORDS ...... 77 C1 Schedule of Hold Points .............................................................................................. 77 C2 Schedule of Witness Points .......................................................................................... 77 C3 Schedule of Identified Records .................................................................................... 78

ANNEXURES R44/D TO R44/K – (NOT USED) ....................................................................................... 78

ANNEXURE R44/L – TEST METHODS, MINIMUM FREQUENCY OF TESTING AND ACCEPTANCE

CRITERIA ..................................................................................................................................... 79

ANNEXURE R44/M – REFERENCED DOCUMENTS .................................................................................. 87

LAST PAGE OF TFNSW R44 (EXCLUDING SUPPLEMENTARY SECTION ON BLASTING) IS ....................... 88

Page 7: TRANSPORT FOR NSW (TfNSW) SPECIFICATION GUIDE NR44 GUIDE …

Guide to R44 Earthworks NR44

Ed 2 / Rev 1 iii

FOREWORD

Guide NR44 is not a contract document. It has been prepared to assist readers of TfNSW R44 with

guidance as to the intent of R44 and understanding of the Principal’s expectations for earthworks.

Normal shaded text replicates text found in TfNSW R44. The text in italics provides commentary on

the various R44 clauses.

This Guide is based on Specification R44 Edition 4 Revision 1 (April 2013).

Page 8: TRANSPORT FOR NSW (TfNSW) SPECIFICATION GUIDE NR44 GUIDE …
Page 9: TRANSPORT FOR NSW (TfNSW) SPECIFICATION GUIDE NR44 GUIDE …

(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)

Ed 2 / Rev 1 1

SPECIFICATION GUIDE NR44

GUIDE TO QA SPECIFICATION R44

EARTHWORKS

1 GENERAL

1.1 INTRODUCTION

The purpose of earthworks is to create a stable formation suitable for the pavement to be constructed

so that it meets its intended life. Earthworks is undertaken using materials from within the site, or if

suitable materials are not available from within the site, using suitable materials from offsite.

Earthworks must be executed in conjunction with other processes including, but not limited to, surface

and subsurface drainage works and environmental control measures.

The earthwork formation comprises a series of earth or rock structures, which must be constructed by

the controlled excavation and placement of materials, and the use of associated Structural Treatments.

The material in the Upper Zone of Formation must be selected, placed and controlled to achieve the

best possible support for the road pavement.

The execution of earthworks involves safety and environmental risks, and the requirements of the

relevant TfNSW Specifications for safety and environmental protection must be complied with.

All earthworks jobs are different.

When designing and constructing earthworks, it is essential that all types of loads expected during

service as well as all likely failure modes are taken into account.

Dead loads and live loads must be considered. Failure due to dead loads can be sudden, such as

slope stability failure of a cut or a fill; or gradual, such as settlement of a fill adjacent to a fixed

bridge abutment or shrink/swell of a moisture sensitive material during seasonal climate changes.

Failures due to live loads from traffic are usually evidenced by surface distortion as a result of large

deflections at the top surface of the formation. These can happen during construction or following

completion as a result of vehicular traffic.

Earthworks generally use the natural materials occurring on the job, with the prime aim being to

provide a stable platform out of those materials on which a pavement for traffic can be constructed.

The main issues to be addressed are:

slope stability of cuttings and embankments (short term during construction and long term).

foundation stability of cuttings and embankments (short term during construction and long term).

volumetric stability of embankments (long term shrink/swell due to moisture changes, or long term

settlement due to poor initial compaction). This might also be expressed as dimensional stability.

What we want, as far as possible, is for the constructed earthworks to stay exactly as they were

placed.

stability of the top of earthworks to enable vehicle movements during pavement construction and

to resist vehicular loads transferred by the pavement during service.

surface edge and slope protection during and after construction to prevent erosion.

It is therefore essential that earthworks structures be designed to manage the materials expected and

encountered on site. The detailed materials investigation must be integrated with the geometric design

Page 10: TRANSPORT FOR NSW (TfNSW) SPECIFICATION GUIDE NR44 GUIDE …

(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)

NR44 Guide to R44 Earthworks

2 Ed 2 / Rev 1

process, together with careful pre-construction planning, in order to avoid unnecessary delays during

construction.

The main factor which affects an earthworks job is the effect of wet weather. Where possible, seasonal

effects should be taken into account when planning the timing of earthworks projects. Also, where

possible, major earthworks involving moisture-sensitive materials should not be planned to commence

when wet winter weather is approaching. Too often, in these conditions, the working days are short

and evaporation rates are low, making it very difficult for materials to dry out.

In such cases where it is not practicable to defer commencement, special treatments such as

stabilisation of materials or, subject to geotechnical advice, permitting construction of lower layers at

higher than normal moisture contents, could be considered during the planning stage.

In many cases, it is possible to anticipate the measures needed to establish foundations. This and

other constructability issues need to be thought through before going to tender and their implications

understood. Doing so will ensure that appropriate provisions and pay items are included (which may

involve job-specific amendments to the model specification after geotechnical consultation and thus

assist the TfNSW representative during construction to make decisions which are both quick and also

correct.

During construction, it is particularly important that decisions required of the TfNSW representative

on the treatment of foundation areas are made quickly, as foundation areas are particularly

susceptible to damage by rain or seepage and any delays will increase the risk of damage and even

further delays.

Page 11: TRANSPORT FOR NSW (TfNSW) SPECIFICATION GUIDE NR44 GUIDE …

(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)

Guide to R44 Earthworks NR44

Ed 2 / Rev 1 3

1.2 SCOPE

The work to be executed under this Specification is summarised in Table R44.1.

Table R44.1 – Summary of Earthworks Process

Task Reference

General – Prepare and submit for consideration an EARTHWORKS PLAN and

PROJECT QUALITY PLAN. Protect the earthworks and the environment by

installing and maintaining effective drainage, and control measures for erosion and

sedimentation. Set out the earthworks by survey, and carry out surveys for process

control and determining quantities.

Clause 1

Materials – Manage the use of materials from within the site, stockpile sites, remove

and stockpile topsoil, remove, replace or treat any unsuitable material, spoil or borrow,

and import materials as necessary.

Clause 2

Foundations – Prepare and compact the floors of cuttings, cut/fill transitions and

foundations for embankments, including subsurface drainage, and the use of drainage

layers, bridging layers, stabilisation, and geotextiles/geogrids as Foundation

Treatments.

Clause 3

Cuttings – Excavate cuttings with specified benches, drainage and batter tolerances.

Blasting of rock may be required.

Clause 4

Embankments – Place and compact suitable material to the specified dimensions and

batter tolerances, including subsurface drainage and the use of rock facing, Select Fill

to structures, stabilisation, and geotextiles/geogrids. Control the quality of material for

the Upper Zone of Formation.

Clause 5

Structural Treatments – Where shown on the Drawings, supply, place and compact

Upper Zone Material and verge material to the specified quality over the full length of

the earthworks, or provide other geotechnical treatments as required.

Clause 6

Conformity Requirements – Complete the earthworks to the specified quality and

tolerances. Undertake all inspection and testing necessary to demonstrate that the

quality requirements of this Specification are achieved.

Clause 7

The earthworks process outline by activity sequence is given in Figure R44.1.

Page 12: TRANSPORT FOR NSW (TfNSW) SPECIFICATION GUIDE NR44 GUIDE …

(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)

NR44 Guide to R44 Earthworks

4 Ed 2 / Rev 1

Figure R44.1 – Earthworks Process Outline By Activity Sequence

Notes:

(a) Notwithstanding that some clearing and grubbing may be necessary before erosion and sedimentation

control can commence, staged construction of drainage works including sedimentation control, culverts,

catch drains and ancillary activities must generally precede clearing and grubbing activities.

(b) Pavement construction is to be carried out to the appropriate TfNSW specifications (shown as “

TfNSW ** ” above) included within the Contract.

Batter treatment

Clause 4.2

Excavate cutting

to DFL

Clause 4

Foundation

Treatments

Clause 3.2

R44 Process Outline Erosion and

Sedimentation

Control

TfNSW G38

Clear and Grub

TfNSW G40 One-way

interaction

Two-way

Interaction

Remove

topsoil

Clause 2.3

Cut

or

Fill

Cutting Embankment

Unsuitable

Material

Clause 2.4

Excavate

embankment

foundations

Clause 3

Terracing

Clause 3.3

Foundation

Treatments

Clause 3.4

Shallow

Embankmen

t

Clause 3.5.1

Cut/Fill

Transition

Clause 3.5.2

Embankment

Construction

Clause 5

Structural

Treatments

Clause 6

Pavement

construction

TfNSW **

Conformity

Requirements

Clause 7

Page 13: TRANSPORT FOR NSW (TfNSW) SPECIFICATION GUIDE NR44 GUIDE …

(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)

Guide to R44 Earthworks NR44

Ed 2 / Rev 1 5

This figure should be studied carefully to understand the arrangement of the specification clauses

relative to the actual construction sequence. It also indicates the other major sections of the

specification which may be relevant to a particular activity.

1.3 STRUCTURE OF SPECIFICATION

This Specification includes a series of Annexures that detail additional requirements.

1.3.1 Project Specific Information

Details of work specific to this Contract are shown in Annexure R44/A.

The completion of Annexure A prior to tendering must not be done without a fully detailed site

investigation and careful thought given to an earthworks management plan. Each project will have

different materials to work with and different requirements to be specified. It is also important that

environmental requirements are known as these could affect the way the work is carried out; e.g.

restrictions may be placed on blasting, vibration, dust, working hours, etc.

1.3.2 Measurement and Payment

The method of measurement and payment is detailed in Annexure R44/B.

As for the previous annexure, EVERY pay item should be considered here. THIS IS ONE OF THE

MOST IMPORTANT PARTS OF A DOCUMENT AS IT DESCRIBES JUST HOW EACH WORK ITEM

WILL BE MEASURED AND PAID FOR. Good documents will have EVERY pay item reviewed and a

conscious decision made on which items are relevant to this project and which are not. The specific

wording for each item should be checked and proof-read by someone independent of the production of

the documents and the person responsible for estimated quantities must be aware of the specific words

which describe how each work item is to be measured and paid. Following compilation of the

documents in draft form, this section, together with the estimated quantities should be reviewed for

sensibility, i.e. provide a reality check with the question “Does this look reasonable?” If documents

are compiled hastily, it is very easy for errors to be made with unintentional results.

Additional pay items may need to be developed where an item of work is not covered by the provisions

in the model. Alternatively, the definition of a pay item may be modified. Particular care is needed

with this when job-specific changes are made.

If a quantity cannot reasonably be estimated or if we are unsure if the item will be required at all, the

item of work should be labelled as “provisional” and a nominal quantity attached to the item. Care

should be taken when nominating the provisional quantities and also in tender evaluation to ensure

that the effect on tender prices reflects the risk of the work item, i.e. the extended price for that item

does not unfairly skew the apparent order of tenders.

It is important that every member of the supervisory team be aware of the methods specified for

measurement and payment before the work commences. Good teamwork between Surveillance

Officers and survey staff will ensure that adequate warning is given and enable staff to manage the

task. At times, site staff from both the Contractor and TfNSW will be hard pushed to measure all

quantities in short timeframes. In such cases, for smaller and more easily measured quantities, it is

often preferable to agree with the Contractor on quantities and for quantity agreement sheets to be

signed by both Contractor and TfNSW site representatives. In making such agreements, the financial

significance of minor discrepancies in the measurements needs to be considered when determining the

level of accuracy for the measurements in the field.

Page 14: TRANSPORT FOR NSW (TfNSW) SPECIFICATION GUIDE NR44 GUIDE …

(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)

NR44 Guide to R44 Earthworks

6 Ed 2 / Rev 1

1.3.3 Schedules of HOLD POINTS, WITNESS POINTS and Identified Records

The schedules in Annexure R44/C list the HOLD POINTS and WITNESS POINTS that must be

observed. Refer to Specification TfNSW Q for the definitions of HOLD POINTS and WITNESS

POINTS.

The records listed in Annexure R44/C are Identified Records for the purposes of TfNSW Q

Annexure Q/E.

This list is crucial to the control of processes and quality on the project and should not be negotiated.

Prior to commencement of work on site, the TfNSW Contract Manager and his/her staff should

arrange a meeting with the Contractor and staff to ensure these hold and witness points are

understood by everyone who supervises the work. Thereafter, constant communication between

Surveillance staff and their counterparts on progress with the work and regular reminders on these

hold points is essential to the efficient management of the project. Good communication and

appropriate action will build trust. Dealing with Hold Points and Witness Points should be

considered in the Surveillance Management Plan.

1.3.4 Planning Documents

The PROJECT QUALITY PLAN must include each of the documents and requirements shown in

Clause 1.5 and must be implemented.

If the Contract does not require you to implement a PROJECT QUALITY PLAN, the documents

shown in Clause 1.5 must be submitted to the Principal for consideration at least 5 working days prior

to work commencing and must be implemented.

1.3.5 Minimum Frequency of Testing

The Inspection and Test Plan must nominate the proposed testing frequency to verify conformity of

the item, which must not be less than the frequency specified in Annexure R44/L. Where a minimum

frequency is not specified, nominate an appropriate frequency. Frequency of testing must also

conform to the requirements of TfNSW Q.

1.3.6 Referenced Documents

Unless otherwise specified or is specifically supplied by the Principal, the applicable issue of a

referenced document is the issue current at the date one week before the closing date for tenders, or

where no issue is current at that date, the most recent issue.

Standards, specifications and test methods are referred to in abbreviated form (e.g. AS 2350). For

convenience, the full titles are given in Annexure R44/M.

1.4 DEFINITIONS

All personnel involved in the administration of contracts should familiarise themselves with these

terms and ensure that correct terminology is used at all times. This is particularly important in

written communications. Only by using correct terminology can we communicate accurately with

other people involved in the contract.

The terms “you” and “your” mean “the Contractor” and “the Contractor’s” respectively.

The following definitions apply to this Specification:

Borrow site An area (either within or outside the Site), other than cuttings and specified

excavations, from which material may be excavated for placing in embankments.

Page 15: TRANSPORT FOR NSW (TfNSW) SPECIFICATION GUIDE NR44 GUIDE …

(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)

Guide to R44 Earthworks NR44

Ed 2 / Rev 1 7

Capping layer A layer of graded rock material of sizes varying between 19 mm and 150 mm,

placed over rock fill as a transition layer between rock fill layers and the overlying

earth fill layer(s) in an embankment.

Contaminated

material

Material classified as Restricted, Hazardous or Special Waste in accordance with

EPA Waste Classification Guidelines.

Cutting An earth or rock excavation within the Site that is made below an existing surface to

create the road formation.

Designed Floor

Level

The level of excavation in a cutting at the underside of the Selected Material Zone.

Drainage layer A layer located at the foundation of the formation in an embankment or a cutting,

constructed of free draining material with grading as specified in Clauses 3.2.5 and

3.4.5. The purpose of the layer is to provide a pathway for the free drainage of

excess water from the foundations of embankments or cuttings. The drainage layer

is usually wrapped in geotextile to prevent its contamination or blockage over time

from adjacent fine grained material.

Earthworks The activities covered by this Specification.

Earth fill See Clause 5.2. Material consisting of fine material and coarse particles distributed

throughout the layer filling voids so that when compacted produces a dense stable

embankment.

Embankment An earth or rock fill structure above an existing and/or excavated surface to create

the road formation.

Floor of cutting The trimmed base of the cutting excavation at either the level of the Designed Floor

Level or at the level of the Foundation Level depending on the type of foundation

treatment shown on the Drawings or directed by the Principal.

Formation The earthworks structure including all Foundation and Structural Treatments on

which the road pavement will be constructed.

Foundation

Level

The level from which the formation is constructed. This is the level achieved after

excavation is undertaken for foundation treatments and the removal of unsuitable

material.

Foundation

Treatment

A special layer or treatment zone at the base of a formation for the purpose of

reinforcing, strengthening or drainage.

General fill Embankment material other than the Upper Zone of Formation, and Foundation

Treatments.

Imported

material

Material incorporated into the earthworks from sources other than that generated by

excavation in cuttings and other specified excavations.

Joint survey See Specification TfNSW G71. A survey carried out in the presence of, or in

conjunction with, the Principal’s surveyor.

Limit of Works A boundary within which the contracted works are undertaken. This is either

indicated in Specification TfNSW G1 or shown on the Drawings.

Page 16: TRANSPORT FOR NSW (TfNSW) SPECIFICATION GUIDE NR44 GUIDE …

(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)

NR44 Guide to R44 Earthworks

8 Ed 2 / Rev 1

Road

Formation

Same as Formation.

Rock fill See Clause 5.3. Material composed of hard, sound, durable rock with only a small

amount of fine particles, which when placed and compacted produces an

embankment deriving its stability from the mechanical interlock of the coarser

particles and not from the compaction of finer material.

Roller pass Compactive effort of a single movement of the roller over all segments of the Lot

nominated in the PROJECT QUALITY PLAN.

Select Fill Fill material of specified quality placed against or adjacent to structures (refer

Clause 5.6). This material is different from Selected Material (see below).

Selected

Material

Material of specified quality used in the Selected Material Zone as specified in

Clause 2.8.3 and Annexure R44/A2.2.

Selected

Material Zone

The top part of the Upper Zone of Formation in which material of a specified higher

quality is required – see Figures R44.2 (a) and (b).

Shallow

Embankment

A part of an embankment where the height from the Stripped Surface Level to the

Top of Formation is less than the height specified in Annexure R44/A4.

Spoil Spoil is surplus material from excavations under the Contract which is not required

to complete the Works as specified, and/or contaminated material or material from

excavations under the Contract whose quality renders it unacceptable for

incorporation in the Works.

Stripped

Surface Level

Level of the surface after stripping of topsoil.

Structural

Treatment

A special layer or zone within a formation for the purpose of reinforcing or

strengthening. It also includes other treatments where shown on the Drawings or

directed by the Principal.

Topsoil Topsoil is natural surface soil that may contain organic matter.

Cut/Fill

Transition

Zone

The area of special formation treatment where the road formation transitions from a

cutting to an embankment, as shown in Figure R44.6(b), and described in Clause

3.5.2.

Unsuitable

Material

Unsuitable material is that occurring below the Designed Floor Level of cuttings

and below the Stripped Surface Level of embankments, which the Principal deems

to be unsuitable for embankment or pavement support in its existing position in

accordance with Clause 2.4.

It excludes materials excavated for Foundation Treatment Types C1 to C5 inclusive.

The Principal will deem any contaminated material occurring below the Designed

Floor Level of excavations and below the Stripped Surface Level beneath

embankments to be unsuitable material if it cannot remain in its existing position.

Upper Zone of

Formation

The Upper Zone of Formation includes the Selected Material Zone and is the top

part of the formation. The depth and quality of the material is specified in

Annexure R44/A4 and R44/A2.2 respectively.

Page 17: TRANSPORT FOR NSW (TfNSW) SPECIFICATION GUIDE NR44 GUIDE …

(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)

Guide to R44 Earthworks NR44

Ed 2 / Rev 1 9

Verge material Material placed in the zone adjacent to the edge of the pavement which is subjected

to occasional traffic from vehicles leaving the pavement, comprised of materials

which have the specified mechanical properties set out in Annexure R44/A2.2.

Upper Zone

Material

Material of specified quality used in the Upper Zone of Formation.

Working

platform

See Foundation Treatment and Structural Treatment. A construction technique

(even if directed).

[See Figures R44.3(a) to (e) for details of Foundation Treatment types for embankments]

Figure R44.2(a) – Embankment Nomenclature

[See Figures R44.5(a) to (d) for details of Foundation Treatment types for cuttings]

Figure R44.2(b) – Cutting Nomenclature

1.5 EARTHWORKS PLAN

The Earthworks Plan is a document detailing the Contractor’s planned movement of material

throughout the work. It should identify expected quality and quantity of materials throughout the work

and how the Contractor proposes to deal with them. To be useful, it must show a range of estimated

quantities of each type of material in each cutting and where it is planned to use these materials in the

various embankments or other works being constructed under the contract, i.e. the quality, quantity

and movement plan for all materials must be shown, based on the best information available at the

time.

Designed Finished Surface Level

Selected Material Zone

General Fill (zoned construction may be required - see Drawings)

MEDIAN (dual carriageways only) BATTER

Pavement

Topsoil (may be removed)

Top of Formation

Foundation Level

Verge or Pavement (see Drawings)

Upper Zone of Formation

Selected Material Zone

may extend to edge

- see Drawings

Designed Floor Level *

MEDIAN (dual carriageways only)

Designed Finished Surface Level

Selected Material Zone

BATTER

Top of Formation Pavement

Cutting Floor Foundation Treatment

Refer to Drawings

for drainage details

Verge or Pavement (see Drawings)

Upper Zone of Formation

Foundation Level

Selected Material Zone may extend to edge - see Drawings

* unless shown otherwise on the Drawings

Height of

embankment

Page 18: TRANSPORT FOR NSW (TfNSW) SPECIFICATION GUIDE NR44 GUIDE …

(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)

NR44 Guide to R44 Earthworks

10 Ed 2 / Rev 1

It is essential that this document be prepared by the Contractor and that the TfNSW Contract Manager

examines and discusses the Plan with the Contractor before the work begins. While the times for

revision are specified, the plan should be discussed at regular (monthly as a minimum) meetings with

the Contractor. It is also important that whenever it is necessary to depart from the Plan, the reasons

for each departure are recorded at the time of the departure so that, if necessary, the TfNSW Contract

Manager will be able to evaluate the effect on the construction program.

The EARTHWORKS PLAN must address all requirements and constraints imposed by the

Specification, the physical conditions at the site and your proposed work methods. The

EARTHWORKS PLAN must include details of:

(a) excavation sequence and proposals for the management of all materials in the earthworks for

each construction stage, including the use of topsoil and surplus excavated material resulting

from other works under the Contract (such as trenching for drainage pipes or utility conduits);

(b) procedures for the management of excavation and placement of earth and rock fill in

embankments and rock facing, to ensure that no deficiency of fill material occurs including a

mass haul diagram detailing the types and quantities of materials to be excavated from each

cutting, and the locations within the Works for placement of the materials (refer Clauses 2.1,

2.2, 4, 5 and 7);

(c) procedures to ensure the effective use of nominated stockpile sites, including maximising the

volume of material to be stored at each location. Do a preliminary assessment of likely

stockpiled quantities and the available quantities that can be placed in nominated stockpile

areas. Any inadequacies must be brought to the attention of the Principal together with other

potential stockpile sites (refer Clause 2.6);

(d) procedures proposed for procuring and managing materials from borrow sites or imported

materials where applicable (refer Clause 2.7);

(e) preliminary identification of zones of potentially unsuitable materials, and management of the

disposal and replacement of the unsuitable materials (refer Clause 2.4);

(f) methods to be employed to ensure that materials of the specified or higher quality are identified,

made available and incorporated into the Works at the locations where the quality of the

material has been specified. The details will include any sorting, isolating, processing, and

placement of the materials proposed for such use. Processing may include screening, crushing,

blending, and modification of materials (refer Clauses 2.8 and 6);

(g) methods to be employed to ensure that all materials placed within the Works conform to

maximum stone (or rock) size and other dimensional requirements, where specified (refer

Clauses 2.8, 3 and 5);

(h) procedures proposed for the treatment of foundations (refer Clause 3);

(i) sources of, and testing proposed for, materials in Upper Zone of Formation, Shallow

Embankments and verges (refer Clause 2.8);

(j) methods to demonstrate that the specified compaction has been achieved over the full depth of

each layer and that the specified layer thickness is not exceeded (refer Clauses 5, 6 and 7);

(k) procedures proposed for protection of earthworks, including drainage of working areas,

minimising ingress of excess water into earthworks, dealing with over-wet materials and over-

dry materials (refer Clause 1.7);

Page 19: TRANSPORT FOR NSW (TfNSW) SPECIFICATION GUIDE NR44 GUIDE …

(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)

Guide to R44 Earthworks NR44

Ed 2 / Rev 1 11

(l) locations and extent of each Cut/Fill Transition Zone (refer Clause 3.5.2); and

(m) procedures to ensure that damage does not occur to adjacent structures from blasting, or by

hammering or ripping during excavation, or from vibrating compaction plant.

There is a need to ensure that construction water quality does not compromise the design life of either

pavement or structures in contact with earthworks (including via leachates or runoff). An example is

the adverse effects which can arise from the use of saline water for compaction or from the

incorporation of acid generating soils or rocks within the works without appropriate control

measures.

Specific requirements should be included in R44 and other specification parts for those cases where

there is known to be a potential problem. A possible approach would be to include construction water

sources in the earthworks plan, with a requirement to demonstrate the suitability if other than potable

water is being proposed. That would cover changes to sources of water quality during construction

and allow flexibility in assessment to suit the types of structures and other in service environmental

considerations.

In the event that water quality cannot be adequately controlled, changes to the design or specification

of pavement and/or structures would be needed. It must be emphasised that any problems may need

not show up until well after the end of the specified defect liability period, so the temptation to deal

with the issue by simply ignoring it must be resisted.

In such cases, similar changes would need to be made to other spec parts, as relevant, including R11,

R22, R57, R58, B30 and possibly G1, G36 and G38. It is essential to keep consistency between the

different parts when job specific changes are being made. Likewise it is important to ensure that

changes to one part do not end up compromising another, given the high level of cross-referencing

between parts.

Notwithstanding the staged submission provisions of Specification TfNSW Q, provide the

EARTHWORKS PLAN in its entirety with the first stage submission of the PROJECT QUALITY

PLAN.

Amend the EARTHWORKS PLAN in accordance with the requirements of Specification TfNSW Q.

Submit to the Principal an updated EARTHWORKS PLAN:

(a) at intervals not exceeding three months during the currency of the Contract;

(b) within two weeks of any change of the EARTHWORKS PLAN for any Milestone or for the

Works; and

(c) within two weeks of receipt of the Principal's determination in respect of the earthworks

construction, if such determination alters any details in the EARTHWORKS PLAN.

An updated EARTHWORKS PLAN must show:

(i) the same level of detail as specified for the original EARTHWORKS PLAN;

(ii) the “as-built” EARTHWORKS PLAN in respect of all work completed up to the date of

updating; and

(iii) reasons for any deviation from the previously submitted EARTHWORKS PLAN, and actions if

any, to correct any deviation within your control.

Page 20: TRANSPORT FOR NSW (TfNSW) SPECIFICATION GUIDE NR44 GUIDE …

(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)

NR44 Guide to R44 Earthworks

12 Ed 2 / Rev 1

1.6 SURVEYING

1.6.1 Setting Out of Earthworks

The position and extent of all cuttings and embankments shown on the Drawings and transitions from

cuttings to embankments must be marked, using pegs and batter profiles or equivalent, prior to

commencement of construction. Setting out must take into account any formation widening necessary

to accommodate the design requirements.

Where the Specification refers to dimensions or setting out relevant to the underside of the Selected

Material Zone, and the Drawings do not provide for a Selected Material Zone, adopt the dimensions

for setting out relevant to the underside of the pavement.

1.6.2 Joint Survey

Where specified in Annexure R44/A1 or where directed by the Principal, carry out a joint survey in

accordance with Specification TfNSW G71. The Survey Report, where specified, must include a

computer file containing data in a format that is suitable for creating accurate models using the

standard TfNSW CADD software.

1.6.3 Specified Surveys

To determine quantities for payment or for process control, carry out the surveys specified in

Annexure R44/A1.

1.7 PROTECTION OF EARTHWORKS

Your responsibility for care of the Works includes the protection of earthworks. Specifically:

(a) Install and maintain effective erosion and sedimentation control measures in accordance with

Specification TfNSW G35 or G36, and Specification TfNSW G38 or G39.

(b) Maintain drainage of all working areas at all times to ensure run-off of water without scour,

except where ponding is off the formation and forms part of a planned erosion and

sedimentation control system. Do not allow water to pond in the working areas resulting in

wetting up of the existing pavement or formation or foundation material.

It also means that sub-surface flow must be cut off to avoid wetting up of placed fill or backfill.

(c) When rain is likely, or when no work is planned for the following day in a particular area being

worked, take precautions to minimise any ingress of water into the earthworks material. Seal

off ripped material remaining in cuttings, and material placed on embankments, using a smooth

drum roller.

(d) Should earthworks material become over-wet (above the specified moisture content for

compaction), you are responsible for replacing and/or drying out the material, and for any

consequent costs. Refer also to Clauses 2.4 and 7.2.

(e) Do not allow the earthworks material to dry out to the point where excessive shrinkage occurs in

the embankment, and the surface is pulverised by traffic generating excessive dust.

Page 21: TRANSPORT FOR NSW (TfNSW) SPECIFICATION GUIDE NR44 GUIDE …

(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)

Guide to R44 Earthworks NR44

Ed 2 / Rev 1 13

2 EARTHWORKS MATERIALS

2.1 GENERAL

You are responsible for:

(a) any of your assumptions made in relation to the nature and types of the materials as encountered

in excavations or imported, and the bulking and compaction characteristics of all such materials

which are then incorporated in the Works;

(b) determining suitable sources of material and any processing needed to satisfy the quality

requirements; and

(c) the design, and the cost of construction and/or maintenance of all tracks, roads, haul roads, pads

and other earthworks structures required for the proper execution of the Works.

General earthworks includes all types of material, both earth and rock, encountered during excavation

and placed in embankments or disposed of in other than embankments.

When surplus excavated material from other works under the Contract (such as trenching for drainage

pipes or utility conduits) is used in the construction of embankments, the requirements of this

specification also apply to such material.

Unless otherwise specified, do not place imported material in the Works until all material of suitable

quality available from the cuttings in the Works has been placed or has been assigned to be placed in

the formation.

If you cause a deficiency of material for embankment construction and other specified materials, by

electing not to use acceptable material from excavations in the embankments or by constructing

embankments with dimensions other than those shown on the Drawings or authorised in accordance

with Clause 5.4, you must make good that deficiency from sources of material meeting the quality

requirements specified in Clause 5. The cost of making good such deficiency of material will be borne

by you.

2.2 MATERIALS MANAGEMENT

Manage your procurement of materials, whether obtained from sources external to the Site or from

nominated sources or from within the Site, to ensure that the materials incorporated into the

earthworks is of the specified quality.

The EARTHWORKS PLAN must include a mass haul diagram detailing the types and quantities of

materials to be excavated from each cutting, and the locations within the Works for placement of the

material (refer Clause 1.5, item (b)).

2.3 TOPSOIL

2.3.1 Removal of Topsoil

Commence removal of topsoil on any section of the Works only after erosion and sedimentation

controls have been implemented and clearing, grubbing and removal of cleared materials has been

completed on that section of the Works.

Page 22: TRANSPORT FOR NSW (TfNSW) SPECIFICATION GUIDE NR44 GUIDE …

(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)

NR44 Guide to R44 Earthworks

14 Ed 2 / Rev 1

Topsoil is usually removed as it contains a quantity of vegetable matter which is weak structurally and

because it is a source of seed and nutrients needed for re-spreading over and re-vegetation of

completed work.

The depth of topsoil directed by the Principal should be sufficient to remove vegetation material which

would be deleterious to earthworks, keeping in mind the needs of the project for spreading topsoil over

disturbed areas for revegetation of the site. It is undesirable to allow stripping depths to markedly

exceed the true topsoil depth as the resulting product may be unusable for the purpose of re-

vegetation.

Care should be exercised in determining depths of topsoil removal and in estimating the quantities

which will be generated. Standardised nominal depths, unrelated to the actual site conditions, should

not be used. These depths are normally chosen using site investigation data.

Often, if deeper fills are being constructed and the foundation conditions are suitable, topsoil and

grass can be left in place provided it is in a flat, level ground and will not compromise the stability of

the embankment. Construction sites usually have very limited space for stockpiles. This is

particularly the case, where sedimentation basins are necessary, clearing needs to be minimised and

the road boundaries are very narrow. The removal and stockpiling of materials needs to be carefully

considered in the planning phase.

Do not remove topsoil in locations where a bridging layer is to be constructed in accordance with

Clause 3.2.2, unless directed otherwise by the Principal.

Where specified in Annexure R44/A2.1 or where directed by the Principal, after removal of the

topsoil,:

(i) stockpile the topsoil within the Site separately from other materials and clear of the Works for

use in revegetation, or

(ii) stockpile the topsoil as a windrow longitudinally and adjacent to the toe of embankment batter,

or

(iii) spoil the topsoil outside the Site in accordance with Clause 2.5.1; or

(iv) if the topsoil has been identified as contaminated material, spoil the topsoil in accordance with

Clause 2.5.2.

2.3.2 Topsoil Stockpiles

Locate topsoil stockpiles in accordance with Clause 2.6.

Before stockpiling topsoil, carry out a survey in accordance with TfNSW G71 to determine the surface

levels at each stockpile site at sufficient locations to later determine the volumes of topsoil placed at

the site. When shown in Annexure R44/A1, the survey must be a joint survey in accordance with

Clause 1.6.

Topsoil stockpiles must:

(a) be free from subsoil, other excavated materials, contaminated materials, refuse, clay lumps and

stones, timber or other rubbish;

(b) be trimmed to a regular shape to facilitate measuring with a height not exceeding 2.5 m and

batter slopes not steeper than 2H : 1V;

(c) have their batters track rolled or stabilised by other means acceptable to the Principal; and

(d) be seeded with a sterile cover crop in accordance with Specification TfNSW R178, to encourage

vegetation cover. Seeding must be carried out progressively within seven days of completion of

each 500 m2 of exposed batter face.

Page 23: TRANSPORT FOR NSW (TfNSW) SPECIFICATION GUIDE NR44 GUIDE …

(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)

Guide to R44 Earthworks NR44

Ed 2 / Rev 1 15

2.3.3 Survey after Removal of Topsoil

After removing the topsoil, determine the surface levels in each cutting and embankment at sufficient

locations to determine the volume of excavation for general earthworks and the volume of unsuitable

material.

When shown in Annexure R44/A1, the survey must be a joint survey in accordance with Clause 1.6.

HOLD POINT

Process Held: Any works which will alter the ground surface as surveyed.

Submission Details: At least three working days before the proposed date for altering the

surfaces, submit a Survey Report of the existing surface levels, and a

notification that the set out specified in Clause 1.6.1, including set out of the

cut/fill intersection point and extent of the Transition Zone as specified in

Clause 3.5, have been carried out.

Release of Hold Point: The Principal will inspect the surfaces and set out, and may direct further

action prior to authorising the release of the Hold Point. Further action may

include altering the limits of the cut/fill transition.

2.4 UNSUITABLE MATERIAL

After the stripping of topsoil covering each embankment foundation, or upon reaching the Designed

Floor Level, or Foundation Level, of cuttings, subsequent earthworks processes are held (refer to Hold

Points in Clauses 3.2 and 3.4) to allow inspection of the foundation.

Where unsuitable material is found, such unsuitable material must be excavated to the extent directed

by the Principal.

Identification of unsuitable material is a difficult task, requiring not only physical inspection and

possibly testing of material but also a great deal of judgement on the part of the decision-maker. For

any particular material, variation in moisture content will provide differences in the strength of the

material. Some materials will lose strength rapidly with increased moisture content, whilst others will

not.

In the foundations for embankments higher than approximately 1.5 metres, the main consideration is

usually to ensure that the foundation provides a reasonable platform for subsequent earthworks. (In

the case of very soft deep soils, special measures need to be taken in the design of the foundations and

these are not detailed in this specification.)

Under deep embankments, the quality of the material itself is rarely an issue in the long term and the

cause of the “unsuitable” is usually its high moisture content in situ. Whilst it can be argued that the

material itself is not unsuitable, it is often impractical to try and adjust the moisture content to allow it

to be compacted. Quick decisions on treatment, including the use of bridging layers will allow

earthworks to proceed without undue delay.

For embankment foundations less than 1.2 metres from the top of Selected Material Zone and also for

the Designed Floor Level of cuttings, testing of the material to determine its in situ properties is

usually necessary. It should be pointed out that such testing will take time and that sufficient time

needs to be allowed for in construction programs to allow the testing to take place.

Decisions to remove unsuitable material should be made as quickly as they conveniently can, as it is at

this stage that the foundation areas are exposed to weather. Wet weather and subsequent wetting up

Page 24: TRANSPORT FOR NSW (TfNSW) SPECIFICATION GUIDE NR44 GUIDE …

(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)

NR44 Guide to R44 Earthworks

16 Ed 2 / Rev 1

of foundation material will cause the material to be difficult to handle and will delay earthworks

operations.

Removal and replacement of unsuitable material in the foundations for embankments has been the

cause of many delays. Such delays can generally be avoided or minimised by timely decisions and

directions which minimise disruptions to the earthworks program. A quick decision which avoids a

delay but which results in a small cost for material removal, is usually a good decision.

Experienced Geotechnical Scientists and experienced Surveillance Officers can provide practical

advice on the need for removal of unsuitable and the best ways to treat foundation areas.

A useful distinction is to divide “unsuitable” into three categories:

Inherently unsuitable. The material cannot be included in the works, even as general earthworks

because of its inherent properties (e.g. peat and muck, some silts). It would normally be spoiled.

It is best dealt with by specifying it to be spoiled, rather than going through the process of testing

it and then making the decision. This type of material mostly (but not always) occurs in culvert or

embankment foundations and may be recognised at the pre-tender stage.

Where possible, the embankments should be made high enough so that this type of material can be

bridged over. This saves much time and effort. If embankments are too low, the offending

material will have to be removed and replaced, under adverse circumstances and at the unsuitable

rate. The actual volume to be handled will be greater than if the level had been raised and the

cost will be higher by a factor of typically three to five. Any apparent saving in earthworks

volume (measured from the nominal “stripped surface”, pre-tender) is illusory.

Unsuitable by virtue of position. This is the issue that the R44 clause actually deals with e.g. low

CBR material in the floor of cuts. Where there are extensive areas of such materials it is often

possible to recognise them and deal with them using one of the foundation treatments in Clause 3

e.g. extensive low CBR materials in cuts can be dealt with using the C2 or C3 floor treatment.

Material of this type is usually acceptable for incorporation in general earthworks,

“Unsuitably wet”. The major problem with the material is excessive moisture (although it may

also fall into the second category). This is usually encountered following periods of rain or in

cases where the site has been inundated. There are various options: dry, stabilise, spoil, use as is.

The decision will depend on many factors, most of which are specific to the job e.g. earthworks

balance, embankment design, material characteristics, availability of spoil or borrow sites,

availability of sites to dry the materials, climate, implications for long term performance.

Where a treatment can be designated at the pre-tender stage, there will be a significant saving in time

and cost, as the offending material can be removed as part of general earthworks and the need to stop

and wait for testing (which often simply confirms what is already known) can be avoided.

Promptly notify the Principal of any areas of the foundation or any layer within the formation that rut

excessively, yield or show signs of distress or instability.

HOLD POINT

Process Held: Replacement of each Lot of unsuitable material.

Submission Details: Notification that unsuitable material has been removed as directed.

Release of Hold Point: The Principal will inspect the excavation and may direct removal of further

material as unsuitable material prior to authorising the release of the Hold

Point.

Incorporate any material removed as unsuitable in embankments in accordance with Clause 5, unless

directed to spoil in accordance with Clause 2.5.

Page 25: TRANSPORT FOR NSW (TfNSW) SPECIFICATION GUIDE NR44 GUIDE …

(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)

Guide to R44 Earthworks NR44

Ed 2 / Rev 1 17

Remove from the site any contaminated materials that cannot be treated and re-used within the Works,

or stockpiled on the site. Remove such material from the site in accordance with Clause 2.5 of this

specification, and Specification TfNSW G35 or G36 as appropriate.

Replace any material that has been removed in accordance with this Clause with either:

(a) suitable material in accordance with Clause 5.1; or

(b) if directed, with foundation treatments in accordance with Clause 3 or as shown on the

Drawings.

The replacement of unsuitable material is deemed to form part of embankment construction.

If you allow any material to become unsuitable because of your inappropriate construction activities,

all costs associated with reworking or replacing such unsuitable material must be borne by you.

Examples of inappropriate construction activities include poor surface drainage, restricted or

inoperative subsurface drains, contamination, excessive sized construction plant where the imposed

load exceeds the material strength, poorly maintained construction plant allowing leakage of oils and

water onto the formation, and leaving the surface unsealed allowing moisture ingress during wet

weather.

Before and after removal of unsuitable material, carry out a survey in accordance with Specification

TfNSW G71 to determine the surface levels at sufficient locations to later determine the volume of

unsuitable material removed. Where shown in Annexure R44/A1, the survey must be a joint survey in

accordance with Clause 1.6. Alternatively, the Principal may agree to determination of volume by

measurement and calculation.

2.5 SPOIL

2.5.1 Non-contaminated Materials

Except for contaminated materials, dispose of spoil generated from the Works under the Contract in

the manner and at locations authorised or agreed to by the Principal. Use up all available areas within

the site before proposing alternative locations.

Dispose of non-contaminated material by the following means:

(a) flatter batter slopes being provided on embankments; or

(b) uniform widening of embankments; or

(c) stockpiling within the site; or

(d) disposal at an approved off-site location.

Embankment widening or batter flattening work is deemed to form part of the embankment

construction and must be carried out in accordance with Clause 5. Spread and compact the spoil as

specified in Clauses 5 and 7 for material in embankments. Maintain effective drainage for the whole

of the embankment.

For spoil locations outside the limits of the Works, obtain all necessary written approvals, including

environmental approvals, and provide copies to the Principal seven days prior to commencing the

disposal of material offsite. Such spoil material located outside of the Site is deemed to be your

property.

Re-use of spoil

Page 26: TRANSPORT FOR NSW (TfNSW) SPECIFICATION GUIDE NR44 GUIDE …

(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)

NR44 Guide to R44 Earthworks

18 Ed 2 / Rev 1

Excavated public road materials (EPRM) are defined by the Environment Protection Authority (EPA)

as comprising any of the following materials: uncontaminated waste rock, soil, sand, bitumen and

asphalt products, gravel, slag from iron and steel manufacturing, fly and bottom ash and concrete,

excavated during the construction and maintenance of roads and road infrastructure facilities.

EPRM may be applied to land within a road corridor for public road related activities including road

construction and maintenance and installation of road infrastructure facilities provided all conditions

attached to the EPA’s resource recovery exemption “The excavated public road material exemption

2012” are complied with.

Virgin Excavated Natural Material (VENM) and Excavated Natural Material (ENM)

Materials classified as virgin excavated natural material (VENM), as defined in the POEO Act may be

applied to land provided its use is consistent with land use zoning and planning consents.

Materials that meet the definition of excavated natural material (ENM) as defined by the EPA’s

resource recovery exemption “The excavated natural material exemption 2012” may be transported

and applied to land off-site provided all conditions attached to the ENM exemption are complied with

and provided its use is consistent with land use zoning and planning consents.

Section 143 Notices

A completed and signed section 143 notice (POEO Act) must be obtained from the landholder prior to

transporting and applying any materials to a site that is not owned by TfNSW and is not a licensed

landfill in accordance with TfNSW Specifications G35 or G36. The landholder must provide written

evidence that planning consent has been given for the material to be deposited on the site (e.g. local

council development consent or a letter from the council stating that the activity is exempt

development) and you must attach this written evidence to the completed section 143 notice.

Payment for disposal of spoil within the limits of the Works is deemed to be included in the rates

generally. However, where an approved location for spoil disposal is outside the limits of the Works,

payment for disposal of spoil will be made under Pay Item R44P6 or Pay Item R44P1.2.

2.5.2 Contaminated Materials

Contaminated materials must be stockpiled and/or removed from the site in accordance with Clause

2.4 of this Specification and Specification TfNSW G35 or G36, as applicable. If disposal methods and

sites are not specified, it is your responsibility to determine the location(s) and method(s) for the

disposal of the contaminated material.

Notify the Principal at least 24 hours prior to the removal of any contaminated material from the

Works, and provide details of the proposed method and location of disposal.

Payment for excavation and stockpiling of contaminated material on site will be made under Pay Item

R44P1.2 or Pay Item R44P2. Additional payment will be made under Pay Item R44P8 for the

identification, treatment, classification in accordance with EPA Waste Classification Guidelines and

disposal of the contaminated material at sites legally authorised to accept the contaminated material.

Treatment and disposal of contaminated material caused by your operations will be at no cost to the

Principal.

2.6 STOCKPILE SITES

There should be sufficient sites available for the storage of topsoil required for later re-use on site and

these should be located as close as possible to the locations from which the material is removed, with

access available for convenient recovery later in the project.

Page 27: TRANSPORT FOR NSW (TfNSW) SPECIFICATION GUIDE NR44 GUIDE …

(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)

Guide to R44 Earthworks NR44

Ed 2 / Rev 1 19

Locate stockpile sites so that they are outside the drip lines of trees and such that material from the

stockpiles does not enter drainage lines or watercourses. Arrange stockpile sites to minimise damage

to natural vegetation and trees and maintain the existing surface drainage. Locate the stockpile sites

such that the stockpiled material is accessible for carting away at any time.

Carry out any clearing and grubbing required for these sites in accordance with Specification TfNSW

G40. Install and maintain appropriate erosion and sedimentation control measures, in accordance with

Specification TfNSW G38 or G39.

The Principal will only consider requests for new stockpiles sites if all stockpile sites nominated on the

Drawings have already been allocated for full use. You must obtain all the necessary written

approvals, including environmental approvals, and provide copies of such approvals to the Principal

when seeking to use a stockpile site other than those nominated. Such requests must be made at least

ten working days before stockpiling is due to commence, specifying the maximum dimensions of the

proposed stockpile.

Following completion of the Works, carry out restoration of the stockpile sites in accordance with

Specification TfNSW R178.

2.7 BORROW SITES

2.7.1 General

Detail the selection and quality control of materials obtained from borrow sites in the

EARTHWORKS PLAN. Materials to be incorporated in the Works must comply with the

requirements of this Specification.

Where any material is to be obtained from borrow sites, site preparation must be in accordance with

Clause 2.3.1 of this Specification and Specification TfNSW G40. Carry out restoration of borrow sites

in accordance with Specification TfNSW R178.

2.7.2 Specified Borrow Sites

Where borrow sites are specified, the edges of any batter from the resulting excavation must not be

closer than 3 m to any existing or proposed fence line, road reserve boundary or edge of excavation or

embankment. Borrow sites must have adequate drainage outlets.

Cut batter slopes must be as specified in Annexure R44/A2.1, and the borrow sites must be left in a

tidy and safe condition and meet the requirements of Specification TfNSW G35 or G36, as applicable.

Proper planning of the project and consideration of the earthworks balance and materials expected on

site should minimise the likelihood of surprises during the contract. Where it is likely they will be

needed, borrow sites should be identified in the Specification and testing for material qualities should

be carried out as part of the site investigation work.

2.7.3 Contractor Arranged Borrow Sites

For borrow sites arranged by you, take responsibility for obtaining any permits required for entry on to

the land and for payment of any royalty for such borrow material.

Comply with any requirements of the Environmental Planning and Assessment Act, Office of Rural

Affairs, Department of Planning and Infrastructure, Natural Resources Commission, the local

Councils, and landowners as appropriate. Provide copies of all approvals to the Principal ten days

prior to commencing work at these borrow sites.

Page 28: TRANSPORT FOR NSW (TfNSW) SPECIFICATION GUIDE NR44 GUIDE …

(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)

NR44 Guide to R44 Earthworks

20 Ed 2 / Rev 1

You are responsible for all costs involved in opening up, maintaining and restoring any borrow sites

arranged by you.

2.8 MATERIAL IN UPPER ZONE OF FORMATION AND VERGES

The material placed in the Upper Zone of Formation must be selected, placed and controlled to meet

the Contract requirements. The Upper Zone of Formation in embankments consists of 2 main

components as shown in Figure R44.2. The top component of Upper Zone of Formation is the

Selected Material Zone.

2.8.1 Material Source

Unless specified to be imported in Annexure R44/A2.1 (from sources as detailed in

Annexure R44/A2.1), obtain Upper Zone Material of the specified quality from cuttings or borrow

sources from within the Limit of Works.

In the event of a planned or unplanned shortage of site won Upper Zone Material, source the imported

material from those detailed in Annexure R44/A2.1, unless otherwise approved by the Principal.

Where the source of imported material is not specified in Annexure R44/A2.1, source them from

legally operating quarries or recycling facilities or other sources acceptable to the Principal. Provide

the Principal with details of the proposed source locations, quantities and types of material before the

imported material is delivered to site.

Prior to testing, pre-treat any Upper Zone Material which may be susceptible to breakdown or

weathering, by crushing to size, artificial weathering in accordance with Test Method TfNSW T103

and repeated compaction in accordance with Test Method TfNSW T102 (Method A).

Before placement of material from any source, establish the response of that material to pre-treatment

and adopt an appropriate pre-treatment regime for subsequent conformity testing.

This is important as such materials may change their strength characteristics significantly as they are

handled during the earthworks processes. Whilst they may appear to be satisfactory by testing

material in a cutting or borrow pit, we need to be able to predict their quality after compaction when

they are in place in the formation. Pre-treatment by artificial weathering and repeated compaction is

an attempt to simulate the breakdown of material which will occur in the actual construction.

2.8.2 Upper Zone of Formation Material other than Selected Material

2.8.2.1 Site Won Material

Material in the Upper Zone of Formation for the thickness and depth specified in Annexure

R44/A4, must:

(a) have a CBR value as that stated in Annexure R44/A2.2;

(b) have a Plasticity Index (PI) value as that stated in Annexure R44/A2.2;

(c) (i) be free from stone larger than 100 mm maximum dimension; and

(ii) have no less than 50% passing the 19.0 mm AS sieve.

This requirement is an attempt to avoid problems with subsequent installation of barrier rail

posts, guideposts, signposts and subsoil drainage. If material is stabilised to produce these

qualities, difficulties with subsequent operations involving excavation or driving posts through

it, may arise.

Page 29: TRANSPORT FOR NSW (TfNSW) SPECIFICATION GUIDE NR44 GUIDE …

(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)

Guide to R44 Earthworks NR44

Ed 2 / Rev 1 21

2.8.2.2 Imported Material

Sources and quality of imported material must be as detailed in Annexure R44/A2.1 and

R44/A2.2 respectively, or approved by the Principal.

Clause 2.8.2.1 part (c) also applies to the imported material.

2.8.3 Selected Material

2.8.3.1 Site Won Selected Material

Material excavated from within the Site and processed, placed and compacted in the Selected

Material Zone must:

(a) have a characteristic CBR value as stated in Annexure R44/A2.2, for the fraction passing

19.0 mm AS sieve; and

(b) have a PI value as stated in Annexure R44/A2.2;

(c) (i) be free from stone larger than 100 mm maximum dimension; and

(ii) have no less than 50% passing the 19.0 mm AS sieve.

When modification of the material is specified in Annexure R44/A4 or shown in the Drawings

to be required for purposes other than to only meet the specified CBR requirements in Annexure

R44/A2.2 (for example, as part of structural treatment in Clause 6), or directed, the Selected

Material immediately prior to incorporation of the binder must satisfy the requirements stated in

the preceding paragraph.

These properties must be specified for each job and the values specified should only be

determined following proper site investigation, interpretation of results and planning of the

earthworks operation by experienced personnel. We should ensure that realistic values are

specified and that the material can reasonably be available to the contractor at a time during

the contract when it is required.

2.8.3.2 Imported Selected Material

Material imported for the Selected Material Zone must meet the requirements of Specification

TfNSW 3071.

Specification drafters should ensure that the specified materials are available at reasonable

costs. TfNSW 3071 may not be appropriate or cost-effective and the properties of known

economical sources for the area should be specified.

2.8.4 Verge Material

The intention is to supply material which can be compacted in thin layers (hence maximum size is

specified) and which will have reasonable ability to carry errant traffic in service. Knowledge of site

materials and locally available quarried materials should provide and economical solution

2.8.4.1 Site Won Verge Material

Material excavated from within the Site and processed, placed and compacted in the verges

must meet the following requirements:

(a) have a CBR value as stated in Annexure R44/A2.2, for the fraction passing 19.0 mm

AS sieve; and

(b) have a PI value within the range specified in Annexure R44/A2.2;

Page 30: TRANSPORT FOR NSW (TfNSW) SPECIFICATION GUIDE NR44 GUIDE …

(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)

NR44 Guide to R44 Earthworks

22 Ed 2 / Rev 1

(c) be free from stone larger than 50 mm maximum dimension and have no less than 50%

passing the 19.0 mm AS sieve.

2.8.4.2 Imported Verge Material

Material imported to the project site and placed and compacted in the verges must meet the

requirements of TfNSW 3071 for Selected Material Type B and must:

(a) have a CBR value not less than that specified in Annexure R44/A2.2, for the fraction

passing 19.0 mm AS sieve; and

(b) have a PI value within the range specified in Annexure R44/A2.2.

If, prior to tender, TfNSW 3071 is considered too restrictive and uneconomical, it should be

modified to suit the project.

2.8.5 “Spill-Through” Bridge Abutment Fill Material

For both Type ST1 material (at waterway crossings) and Type ST2 material (at overbridges), the fill

material must:

(a) have a CBR value as that stated in Annexure R44/A2.2;

(b) have a PI value as that stated in Annexure R44/A2.2;

(c) have a grading of 100% passing the 53 mm sieve.

3 FOUNDATIONS

3.1 GENERAL

Embankment foundation treatments are applied after removal of unsuitable material, excavating

further in Shallow Embankment areas to provide a minimum embankment height (refer to Clause

3.5.1), and where relevant, terracing of hillside embankment foundations.

Foundation treatments in cuttings are applied after excavation to the Designed Floor Level and

removal of unsuitable material.

Taking into account the site, traffic, access, environmental/climatic conditions and insitu materials,

select your equipment and techniques and use them in such a manner that minimises surface heaving

or other foundation damage during preparation of the foundation and construction of overlying layers.

Construct other measures (such as trench and foundation drains, constructed in accordance with

Specification TfNSW R33) in conjunction with the foundation treatments, as shown on the Drawings,

or as authorised or directed by the Principal.

3.2 FOUNDATIONS FOR EMBANKMENTS

After preparation of the foundation area, present the embankment foundation area for inspection by the

Principal prior to placing embankment materials.

Page 31: TRANSPORT FOR NSW (TfNSW) SPECIFICATION GUIDE NR44 GUIDE …

(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)

Guide to R44 Earthworks NR44

Ed 2 / Rev 1 23

HOLD POINT

Process Held: Treatment of each Lot of embankment foundation.

Submission Details: (a) Survey report;

(b) Notification of completion of: clearing operations;

and,

(c) in the areas other than beneath Shallow Embankments, notification of:

(i) topsoil removal in accordance with Clause 2.3; or

(ii) flattening/mowing of grasses if indicated on the Drawings or

specified;

or,

(d) in the areas beneath Shallow Embankments:

(i) notification that topsoil has been removed and surface excavated in

accordance with Clause 3.5.1; and

(ii) CBR and PI test results, if required in accordance with Clause

3.5.1.

Release of Hold Point: The Principal:

(a) will consider the submitted documents;

(b) may inspect the excavated floor for the embankment foundation; and

(c) may direct further action prior to authorising the release of the Hold

Point. Further action may include removal of unsuitable material in

accordance with Clause 2.4, or treatment in accordance with Clause 3.2.

Maintain the embankment foundation in its conforming condition until embankment construction

commences. You must bear the cost of additional foundation treatments required as a result of

damage to the foundations that is caused, or allowed to occur, by you.

Treat all foundations for embankments in accordance with Type E1, unless otherwise shown on the

Drawings or specified in Annexure R44/A3, or directed or authorised by the Principal, to treat

foundations for embankments in accordance with Type E2 to Type E6, installed individually or in

combination.

These treatments are described below and depicted in Figures R44.3 (a), (b), (c), (d) and (e) or under

Clause 3.2.6

Every effort should be made to anticipate appropriate treatments and indicate on the Drawings where

they are to be applied. Use provisional items where the need for a treatment or its extent will be

determined by factors such as weather.

3.2.1 Type E1 Treatment – Loosen and Compact

Unless otherwise specified or directed by the Principal, and after any unsuitable material has been

treated or replaced, the remaining area of the foundation must be:

(i) prepared for embankment construction by loosening by ripping the material exposed (to a depth

of 300 mm);

(ii) terracing as required by Clause 3.3;

(iii) adjusting the moisture content of the loosened material; and

(iv) compacting to the specified relative compaction specified in Clause 7.

Page 32: TRANSPORT FOR NSW (TfNSW) SPECIFICATION GUIDE NR44 GUIDE …

(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)

NR44 Guide to R44 Earthworks

24 Ed 2 / Rev 1

There will often be difficulties here in compacting material, particularly in relation to moisture

contents when moistures in situ are higher than optimum. The practicality of adjusting moisture needs

to be considered and some relaxation of requirements will usually be necessary. In cases where

moistures are high and wet weather interrupts earthworks, TfNSW geotechnical experts should be

consulted to identify if a relaxation can be achieved.

Where loosening and re-compaction is impractical, consideration should be given to one or more of

the alternatives in the following clauses, depending on the circumstances. The situation regarding

moisture contents will differ from the above in drier areas (ie west of the range).

Figure R44.3(a) – Embankment Foundation Treatment Type E1 – Loosen and Compact

No account will be taken of the volume involved in loosening when measuring the volume of

excavations for payment.

3.2.2 Type E2 Treatment – Bridging Layer

Where specified or where directed by the Principal, or where you demonstrate that it is impracticable

to achieve the degree of compaction specified for the foundation in Clause 7, the Principal may

approve the placement of a bridging layer.

Do not place a bridging layer within the depth below the underside of the pavement stated in Annexure

R44/A3. The thickness of the bridging layer must not exceed the value stated in Annexure R44/A3.

Figure R44.3(b) – Embankment Foundation Treatment Type E2 – Bridging Layer

The bridging layer must be constructed from earth fill or rock fill materials conforming to the

requirements of Clauses 5.2 or 5.3. If earth fill is used, it must consist of granular material with strong

mechanical interlock and low sensitivity to moisture. The bridging layer material must provide a

stable platform upon which a conforming earthworks layer can be constructed.

Topsoil

(removed)

Earth Fill / Rock Fill

Designed Finished Surface Level

Selected Material Zone

MEDIAN (dual carriageways only) BATTER

Pavement Top of Formation

Verge or Pavement (see Drawings)

Upper Zone of Formation

Selected Material Zone

may extend to edge

- see Drawings

Foundation Level

Unsuitable Material

(replaced as required)

Loosened and Compacted

Topsoil

(usually left in place)

Earth Fill / Rock Fill

Geotextile

(if directed) Bridging Layer

Designed Finished Surface Level

Selected Material Zone

MEDIAN (dual carriageways only) BATTER

Pavement Top of Formation

Verge or Pavement (see Drawings)

Upper Zone of Formation

Selected Material Zone

may extend to edge

- see Drawings

Foundation Level

Refer Annex A3 for minimum depth from

underside of pavement to top of bridging layer

Page 33: TRANSPORT FOR NSW (TfNSW) SPECIFICATION GUIDE NR44 GUIDE …

(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)

Guide to R44 Earthworks NR44

Ed 2 / Rev 1 25

The material must be end-dumped and spread in a single layer with a thickness no greater than that

specified in Annexure R44/A3 and of sufficient thickness to allow the passage of earthmoving

equipment over the bridging layer with minimal surface heaving. The compaction requirements of

Clause 7 do not apply to the bridging layer.

Bridging should only be used when the foundation cannot be compacted. The bridging layer is a

construction expedient, to allow the work to proceed, and is not an inherently desirable method of

building an embankment. It must be remembered that bridging is an uncompacted layer which will be

compressed/compacted by the weight of the overlying material etc. Its presence will eventually result

in deformation of the surface. Therefore:

bridging material should normally be coarse, free-draining material which will not break down in

service

Material quality in bridging layers should not be compromised. Particularly avoid the placement

of moisture susceptible materials (e.g. “clay bridging”) and very coarse materials with a high

void content, into which overlying material may infiltrate over time.

The thickness of bridging layers should be kept to the minimum necessary to allow fully compliant

construction of the overlying layers.

The practice of placing multiple bridging layers should be avoided.

Compaction of layers immediately above bridging needs to be conducted with care, particularly

avoiding the use of large vibrating rollers, to prevent the development of compaction-induced pore

pressures and de-stabilisation of the embankment.

If specified or directed by the Principal, place a geotextile complying with the quality requirements of

Specification TfNSW R63. Payment for the geotextile will be made under Pay Item R44P7.3(a).

The purpose of the geotextile is to prevent infiltration of fines from one layer to another at some later

time. A geotextile will normally be used at the boundary of a free-draining layer and could be at the

top, as well as at the bottom of a bridging layer.

3.2.3 Type E3 Treatment – Working Platform

Where specified or where directed by the Principal, strengthen the insitu material to form a Working

Platform on which to construct the formation. The Working Platform is created by the chemical

stabilisation of insitu material in accordance with Specification TfNSW R50.

Alternatively, a Working Platform of imported stabilised material may be specified in Annexure

R44/A2.1 or directed by the Principal.

Figure R44.3(c) – Embankment Foundation Treatment Type E3 – Working Platform

Topsoil

(removed or overlain

by Working Platform)

Earth Fill / Rock Fill

Working Platform

Designed Finished Surface Level

Selected Material Zone

MEDIAN (dual carriageways only) BATTER

Pavement Top of Formation

Verge or Pavement (see Drawings)

Upper Zone of Formation

Selected Material Zone

may extend to edge

- see Drawings

Foundation Level

Page 34: TRANSPORT FOR NSW (TfNSW) SPECIFICATION GUIDE NR44 GUIDE …

(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)

NR44 Guide to R44 Earthworks

26 Ed 2 / Rev 1

When specified or directed, this work will be paid for under the appropriate Pay Items in Specification

TfNSW R50, and this Specification for Imported Material (Pay Item R44P3).

3.2.4 Type E4 Treatment – Geotextile/Geogrid Layer(s)

Where specified or directed by the Principal, construct Type E4 treatment, consisting of a layer or

layers of geotextile and/or geogrid. Supply and place the geotextile and geogrid in accordance with

Specifications TfNSW R63 and TfNSW R67 respectively.

Figure R44.3(d) – Embankment Foundation Treatment Type E4 – Geotextile/Geogrid Layer(s)

3.2.5 Type E5 Treatment – Drainage Layer

Where specified or directed by the Principal, treat embankment foundations with a drainage layer

consisting of a rock layer enclosed by geotextile.

Figure R44.3(e) – Embankment Foundation Treatment Type E5 – Drainage Layer

Shape and trim the embankment foundation to ensure drainage of the embankment. Ensure that post

construction, a clear drainage path through the layer is maintained, particularly at the outer edges of

the embankment.

Construct the drainage layer so that the completed thickness of the layer is that shown in Annexure

R44/A3, and comprising material meeting the properties in Table R44.2.

Topsoil

(removed or

overlain by Geotextile)

Geotextile / Geogrid

(one or more layers)

Earth Fill / Rock Fill

Designed Finished Surface Level

Selected Material Zone

MEDIAN (dual carriageways only) BATTER

Pavement Top of Formation

Verge or Pavement (see Drawings)

Upper Zone of Formation

Selected Material Zone

may extend to edge

- see Drawings

Foundation Level

Topsoil

(removed or overlain

by Drainage Layer)

Earth Fill / Rock Fill

Geotextile

Drainage Layer

Designed Finished Surface Level

Selected Material Zone

MEDIAN (dual carriageways only) BATTER

Pavement Top of Formation

Verge or Pavement (see Drawings)

Upper Zone of Formation

Selected Material Zone

may extend to edge

- see Drawings

Foundation Level

Page 35: TRANSPORT FOR NSW (TfNSW) SPECIFICATION GUIDE NR44 GUIDE …

(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)

Guide to R44 Earthworks NR44

Ed 2 / Rev 1 27

Table R44.2 – Drainage Layer Material Properties

Property Requirement

Maximum dimension 125 mm

Percentage passing:

19.0 mm AS sieve 0 – 15%

1.18 mm AS sieve 0 – 5%

75 m AS sieve < 0.5%

Percentage of + 19.0 mm fraction with

Is(50) < Annexure R44/A2.2

10% (max)

Wet/Dry Strength Variation Annexure R44/A2.2

Adjust the grading of the drainage layer as necessary within the above limits to ensure that it provides

a stable foundation for compaction of the overlying embankment.

Place and spread the drainage layer material in such a way as to avoid segregation and to ensure that it

is not contaminated with foreign materials. Compact the layer using the nominated compaction

routine developed as specified in Clause 7.3.

Place a geotextile of Strength Class C and Filtration Class 5 in accordance with Specification TfNSW

R63, at both the interface between the rock layer and the embankment foundation, and the interface

between the rock layer and the embankment fill.

Provide outlet/drainage treatment at the ends as shown on the Drawings or directed by the Principal.

3.2.6 Type E6 - Other Treatments

Adopt other foundation treatments as shown on the Drawings or as directed or agreed by the Principal.

3.3 FOUNDATION TREATMENT FOR HILLSIDE EMBANKMENTS

Where embankments are to be constructed on or against any slopes or batter of existing embankments

(including batters resulting from the partial construction of embankments under the Contract), and the

existing slope or batter is steeper than 10H:1V in any direction, cut horizontal terraces into such slopes

or batters which will be covered by the embankment to be constructed.

Step the existing slope or batter progressively in successive terraces, each at least 1 metre in width as

shown in Figure R44.4. Cut the terraces to a minimum depth of 300 mm at the steps except where the

existing slope or batter is 4H:1V or steeper, in which case the terraces must be cut to a minimum depth

of 600 mm at the steps.

Page 36: TRANSPORT FOR NSW (TfNSW) SPECIFICATION GUIDE NR44 GUIDE …

(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)

NR44 Guide to R44 Earthworks

28 Ed 2 / Rev 1

Figure R44.4 – Hillside Terracing Requirements

Cut the terraces progressively as the embankment is placed.

Inspect the floor of each terrace in accordance with Clause 2.4 to check for any unsuitable material.

Unless directed otherwise by the Principal, incorporate the material thus excavated in embankments in

accordance with Clause 5, or spoil it off site in accordance with Clause 2.5.

No account will be taken of the material removed in terracing when determining the general

earthworks excavated volume.

The purpose of terracing is to provide a roughened “saw-tooth” surface on the natural slope and to

ensure the freshly-place embankment is “keyed into” the natural slope, so that a potential slip surface

between the old and new material is removed. The cutting into the existing slope should be done just

before a new layer is placed as it can be done conveniently at this time by using the surface of the

previous layer as a working platform. The material cut from the terrace can if suitable, be mixed with

and incorporated into the next layer with minimal disruption to the work.

Consideration also needs to be given to the potential for springs under the embankment and the need

to construct drainage in conjunction with the terraces. This drainage should be incorporated in the

design drawings where possible.

3.4 FOUNDATION TREATMENTS FOR CUTTINGS

Excavate cuttings to the Designed Floor Level. The finished levels of the excavated cutting floor must

comply with the tolerances given in Clause 7.5.

Prior to placing formation materials and carrying out any designed foundation treatments, the cutting

floor must be tested and presented for inspection by the Principal. Determine the CBR and PI values

of the material in the floors of cuttings by the Test Methods stated in Annexure R44/A2.2.

Topsoil (removed)

Natural Surface Level

Material to be removed

Minimum depth of terrace:

for slope > 4H:1V 600 mm

for slope > 10H:1V and < 4H:1V 300 mm

Terraces not required on slopes < 10H:1V

Page 37: TRANSPORT FOR NSW (TfNSW) SPECIFICATION GUIDE NR44 GUIDE …

(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)

Guide to R44 Earthworks NR44

Ed 2 / Rev 1 29

HOLD POINT

Process Held: Treatment of each Lot of floors of cuttings.

Submission Details: (a) Notification that:

(i) excavation to Designed Floor Level; and

(ii) depth specified for Cut/Fill Transition Zone (refer to Clause 3.5),

has been reached;

(b) CBR and PI test results.

(The submission must be concurrent with the submission for any adjoining

Shallow Embankment foundation required by the Hold Point in Clause 3.2.)

Release of Hold Point: The Principal:

(a) will consider the submitted documents;

(b) will inspect the excavated floor; and

(c) may direct further action prior to authorising the release of the Hold

Point.

Further action may include the removal of unsuitable material in accordance

with Clause 2.4; installation of trench drains in accordance with

Specification TfNSW R33, or foundation treatments in accordance with

Clause 3.4, treatment in accordance with Specification TfNSW R50, or other

treatments in accordance with this Clause or changes to the area to be

excavated.

Treat foundations within cuttings in accordance with Type C1, unless otherwise shown on the

Drawings or specified in Annexure R44/A.3 or directed or authorised by the Principal to treat

foundations within cuttings in accordance with Foundation Treatments Type C2 to Type C5.

The treatments are described below and depicted in Figures R44.5 (a), (b), (c) and (d), in Clause 3.4.4

for Type C4 Treatment – Geotextile and Geogrids, and in Clause 3.4.6 for Other Treatments. These

may be applied individually or in combination, as specified in Annexure R44/A3.

Where CBR and PI conform to the requirements of Annexure R44/A2.2, loosen and recompact the

underlying material in accordance with Foundation Treatment Type C1. Where the CBR of the

material in the floor of the cutting is less than, or where the PI is greater than the requirement

nominated in Annexure R44/A2.2, remove the material to the appropriate depth to provide for the

directed foundation treatment (Foundation Treatment Types C2 to C5).

Maintain the cutting floor in its conforming condition until any subsurface drainage is completed and

backfilling and construction of Upper Zone of Formation commence.

You must bear the cost of treatment selected for your convenience or required as a result of damage to

the foundations caused by, or allowed to occur by you.

3.4.1 Type C1 Treatment – Loosen and Compact

Unless shown on the Drawings or otherwise specified or directed by the Principal, treat the floors of

cuttings as described below.

Page 38: TRANSPORT FOR NSW (TfNSW) SPECIFICATION GUIDE NR44 GUIDE …

(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)

NR44 Guide to R44 Earthworks

30 Ed 2 / Rev 1

(a) Following excavation and removal of unsuitable material, loosen all material remaining in the

floor by ripping to a minimum depth of 300 mm below the Designed Floor Level for the width

of the Selected Material Zone as shown on the Drawings, or the width of the pavement layers

plus one metre on each side (whichever width is the greater).

(b) Recompact the loosened material in accordance with Clause 7. The maximum dimension of

particles in the compacted material must not exceed 200 mm.

(c) After recompaction, trim the floors of cuttings parallel with the finished wearing surface so that

their levels do not vary from the Designed Floor Levels by more than the tolerances shown in

Clause 7.5.

Figure R44.5(a) – Cutting Floor Treatment Type C1 – Loosen and Compact

As part of the trimming operation, prepare the surface in accordance with Test Method TfNSW T199,

for deflection monitoring as required in Clause 7.4.

No account will be taken of the volume involved in loosening when measuring the volume of

excavations.

As for embankment foundations, the foundation area must be prepared to assess its ability to carry

subsequent layers. Surveillance of plant working in the area will usually give an indication of this

ability and facilitate decisions to remove unsuitable material. Repetitive loading by heavy

construction plant will cause failures in low CBR and high moisture content materials and

unnecessary plant movements should be avoided if this is the case. Material of CBR value 8 or higher

would normally be satisfactory.

3.4.2 Type C2 Treatment – Excavation and Backfill

Normally this treatment is required when the material in the particular cutting floor is of poor quality

and better quality material is available on the site and is needed to satisfy the pavement design

criteria. It is equivalent in function to removal and replacement of unsuitable material. When

completing Annexure details for the backfill material, the properties specified must be realistic, taking

into account the availability of material from other cuttings on the job. Alternatives to removal and

replacement would be chemical stabilisation of the bottom of the cutting, increasing the thickness of

SMZ, stabilising the selected material or re-designing the pavement). The backfill material quality

would normally be the same as for upper zone of formation

Where specified or directed by the Principal, treat the floors of the cuttings as described below:

(a) The floors of cuttings must be excavated, parallel to the designed grade line, to a foundation

level that will be at a depth below the Designed Floor Level equal to the nominated thickness of

backfill. Trim the floors to the tolerance stated in Clause 7.5. Loosen, compact and trim the

floor of the cutting in accordance with Clause 3.4.1.

MEDIAN (dual carriageways only)

Designed Finished Surface Level

Selected Material Zone

BATTER

Top of Formation Pavement

Refer to Drawings

for drainage details

Verge or Pavement (see Drawings)

Unsuitable Material

(replaced as directed) Upper Zone of Formation

Foundation Level

Selected Material Zone may extend to edge - see Drawings

Foundations (loosened and compacted) Designed Floor Level *

* unless shown otherwise on the Drawings

Page 39: TRANSPORT FOR NSW (TfNSW) SPECIFICATION GUIDE NR44 GUIDE …

(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)

Guide to R44 Earthworks NR44

Ed 2 / Rev 1 31

(b) Place, compact and trim backfill material meeting the requirements of Annexure R44/A2.2 in

accordance with the requirements for earth fill.

Figure R44.5(b) – Cutting Floor Treatment Type C2 – Excavation and Backfill

The material excavated between the underside of the Selected Material Zone and the Foundation Level

is to be included in the excavated volume for general earthworks.

3.4.3 Type C3 Treatment – Working Platform

An appropriate treatment if there is a shortage of good quality material on the project. This is an

alternative to excavation and backfill. It may also be expedient if the quantity of material to be

removed is excessive, on cost grounds, even where removal and replacement is physically possible.

This treatment may also be used where the floor is making water, in conjunction with drainage

measures. This is particularly so if the floor is susceptible to softening and the material extends to

some depth.

Where specified or directed by the Principal, treat the floors of the cuttings as described below:

(a) Increase the strength of the insitu material to form a Working Platform on which to construct the

formation. The Working Platform is created by the chemical stabilisation of insitu material in

accordance with TfNSW R50.

(b) Alternatively, a Working Platform of imported stabilised material may be specified in Annexure

R44/A2.1 or directed.

Figure R44.5(c) – Cutting Floor Treatment Type C3 – Working Platform

Where specified or directed, this work will be paid for under the appropriate Pay Items in

Specification TfNSW R50) and this Specification for imported material (Pay Item R44P3). The

material excavated between the Designed Floor Level and the Foundation Level, at the underside of

MEDIAN (dual carriageways only)

Designed Finished Surface Level

Selected Material Zone

BATTER

Top of Formation Pavement

Refer to Drawings

for drainage details

Verge or Pavement (see Drawings)

Unsuitable Material

(replaced as required)

Upper Zone of Formation

Foundation Level

Selected Material Zone may extend to edge - see Drawings

Backfill (see Drawings) Designed Floor Level *

* unless shown otherwise on the Drawings

MEDIAN (dual carriageways only)

Designed Finished Surface Level

Selected Material Zone

BATTER

Top of Formation Pavement

Refer to Drawings

for drainage details

Verge or Pavement (see Drawings)

Unsuitable Material

(replaced as directed)

Upper Zone of Formation

Foundation Level

Selected Material Zone may extend to edge - see Drawings

Designed Floor Level *

* unless shown otherwise on the Drawings

Working Platform

Page 40: TRANSPORT FOR NSW (TfNSW) SPECIFICATION GUIDE NR44 GUIDE …

(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)

NR44 Guide to R44 Earthworks

32 Ed 2 / Rev 1

the Working Platform, is to be included in the excavated volume for General Earthworks and paid in

accordance with Pay Item R44P2.

3.4.4 Type C4 Treatment – Geotextile/Geogrid Layer(s)

This is a specific treatment which needs to be properly designed to ensure that deflections are reduced

to a level which will allow subsequent earthworks and pavement operations to be carried out and that

strains in the finished pavement do not result in premature failures. Numerous geotextiles and

geogrids are available, with different characteristics. Proper design by a suitably experienced person

is necessary in order to determine the most cost-effective treatment

Where specified or directed by the Principal, construct a Type C4 treatment, consisting of a layer or

layers of geotextile and/or geogrid on the floor of the cutting.

Supply and place the geotextile and geogrid in accordance with TfNSW R63 and/or TfNSW R67

respectively. Payment for the geotextile and geogrid used in the Works will be paid for in accordance

with Pay Item R44P7.3 or Pay Item R67P1.

3.4.5 Type C5 Treatment – Drainage Layer

Where specified or where directed by the Principal, treat the floors of the cuttings as described below:

This is a treatment which should be used where water is entering or can be expected to enter from the

floor of the cutting. Remember that any drainage layer will collect water and clear instructions must

also be given regarding the construction of an outlet drain. In the case of water entering from the side

of the cutting, a longitudinal subsoil drain is more appropriate, although if it is difficult to identify the

exact location of the entry, a small drainage layer in combination with a longitudinal subsoil drain

may be appropriate.

It is desirable that the use of drainage layers and their locations be part of the design, not a decision

made exclusively on site. Be aware that long term groundwater behaviour may be different from what

is observed at the time of excavation, particularly after prolonged dry weather. Outlets of drainage

layers need to be considered inthe design. Care needs to be taken to ensure that this is compatible

with the remainder of the design and that it is constructible in a reasonable manner. Drainage layers

and their outlets are difficult, often impossible, to access and maintain in service and should be

designed with considerable excess capacity. Outlet arrangements should be both robust and as simple

as possible.

Take care to understand how water will flow in three dimensions, rather than simply relying on

longitudinal or cross sections.

(a) Excavate cuttings parallel to the designed grade line, to a foundation level which will be at a

depth below the Designed Floor Level equal to the thickness of the drainage layer. Trim the

excavation to the same crossfall as the pavement above and in such a manner as to ensure

drainage of the cutting occurs. Where the horizontal alignment of the road is in crossfall

transition, ensure that the floor of the cutting has a minimum 1% crossfall.

The requirement for trimming is not appropriate if the floor has been excavated by blasting or ripping

and the floor is essentially broken rock. In such cases, consider the alternative of over excavation by

a small amount (e.g. 0.5 m), followed by compacting the shot rock back into the untrimmed floor and

removal of any protruding “spines” etc of rock. There is only a need to ensure that water will flow to

the outlet. Local ponding is usually not a concern under these circumstances, although there may be

exceptions e.g. if downslope stability is a concern adjacent to a side cut.

(b) Compact the material exposed at the base of the excavation with not less than six passes of a

vibrating roller.

Page 41: TRANSPORT FOR NSW (TfNSW) SPECIFICATION GUIDE NR44 GUIDE …

(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)

Guide to R44 Earthworks NR44

Ed 2 / Rev 1 33

The material at the base of the drainage layer should not be susceptible to marked strength change

with increased moisture. If the material in the floor of the cutting will soften under soaking, it may

then result in loss of stability of the drainage layer once it is placed

(c) Place the drainage layer at the base of the Selected Material Zone with a minimum thickness of

300 mm material meeting the properties in Table R44.2.

Prior to placing the drainage layer, place a geotextile meeting the requirements of Class C and

Filtration Class 5 of TfNSW R63, over the floor of the cutting, except where the cutting is in

rock. Place a geotextile of the same type over the top of the drainage layer.

Adjust the grading of the drainage layer as necessary within the limits in Table R44.2 to ensure

that it provides a stable foundation for compaction of the overlying Selected Material.

Place and spread the drainage layer material in such a way as to avoid segregation and to ensure

that it is not contaminated with foreign materials. Compact the layer using the nominated roller

routine developed as specified in Clause 7.3.

Requirements for drainage layer materials and construction may be modified to suit site conditions,

particularly for site-won materials. Factors to be considered include the excavation method, floor

condition and availability of materials. For instance, in a large cutting with a very irregular floor in

high strength blasted rock:

A thicker blanket may be appropriate, to eliminate the need for extensive trimming of the

irregularities in the floor. The remnants of the shot rock in the irregularities should then be

compacted to form a base for the drainage layer construction.

A higher proportion of non-plastic fines may be allowable, as these will be trapped in the floor

irregularities and will not clog the drainage

Care needs to be taken if placing a drainage layer on a floor which may soften due to the effects of

moisture or compaction. The compaction routine should be developed to minimise these effects e.g. by

using static rather than vibrating rollers.

After compaction, the upper surface of the drainage layer must not vary from the designed

levels by more than shown in Clause 7.5.1.

The above grading is intended for cases where the design calls for substantial drainage provision in

rock cuttings. This can be particularly useful where good quality rock is available in cuttings on the

job. Where not specified but required as a Variation to the contract, small area drainage layers are to

be used to drain particular problem areas, the specified rock grading may not be readily available and

in such cases a clean coarse aggregate, of nominal size ranging from 100mm to 14mm might be more

appropriate. Crushed aggregate rather than river gravel is preferred as the crushed faces will cause

the material to “lock in” better during compaction. The MS (macadam sub-base) gradings in TfNSW

3051 may also be suitable.

(d) Provide end outlet/drainage treatment as shown on the Drawings, or directed by the Principal.

Page 42: TRANSPORT FOR NSW (TfNSW) SPECIFICATION GUIDE NR44 GUIDE …

(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)

NR44 Guide to R44 Earthworks

34 Ed 2 / Rev 1

Figure R44.5(d) – Cutting Floor Treatment Type C5 – Drainage Layer

Payment for the drainage layer will be made in accordance with Pay Item R44P7.4. Material

excavated will be measured and paid in accordance with Pay Item R44P2 or R44P4. The geotextile

will be paid for in accordance with Pay Item R44P7.

3.4.6 Other Treatments

Other foundation treatments may be adopted as shown on the Drawings or as directed or agreed by the

Principal.

3.5 SHALLOW EMBANKMENT AND CUT/FILL TRANSITION

3.5.1 Shallow Embankment

Where the height of the embankment is less than that stated in Annexure R44/A4 for a Shallow

Embankment, excavate the area further to a depth necessary to achieve the minimum height, unless

otherwise shown on the Drawings or directed by the Principal.

You may propose to the Principal a height that is less than the minimum height stated for a Shallow

Embankment to reduce the depth of excavation required. Carry out CBR and PI tests on the

embankment foundation at this proposed higher level and submit them to the Principal. For this lesser

height to be approved by the Principal, the CBR and PI values must comply with those stated in

Annexure R44/A2.2.

This is to confirm design assumptions for the subsequent formation and pavement to be constructed.

Observe the Hold Point in Clause 3.2 and carry out embankment foundation treatments in accordance

with Clause 3.2, before placing the overlying formation.

The thickness of the Upper Zone of Formation will be that corresponding to “shallow embankment” in

Annexure R44/A4, and will generally be the entire formation from Foundation Level to Top of

Formation, unless shown otherwise in Annexure R44/A4. Fill placed within this zone must comply

with that for Upper Zone of Formation material.

MEDIAN (dual carriageways only)

Designed Finished Surface Level

Selected Material Zone

BATTER

Top of Formation Pavement

Refer to Drawings

for drainage details

Verge or Pavement (see Drawings)

Unsuitable Material

(replaced as directed)

Upper Zone of Formation

Foundation Level

Selected Material Zone may extend to edge - see Drawings

Drainage Layer

Geotextile

Designed Floor Level *

* unless shown otherwise on the Drawings

Page 43: TRANSPORT FOR NSW (TfNSW) SPECIFICATION GUIDE NR44 GUIDE …

(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)

Guide to R44 Earthworks NR44

Ed 2 / Rev 1 35

Notes:

(1) Where the height from Stripped Surface Level to Top of Formation is less than minimum height for Shallow Embankment

(refer to Annexure R44/A4), further excavation to achieve the minimum height for Shallow Embankment is required.

(2) The thickness of the Upper Zone of Formation will be that corresponding to “shallow embankment” in Annexure R44/A4,

and will generally be the entire formation from Foundation Level to Top of Formation, unless shown otherwise in

Annexure R44/A4.

Figure R44.6(a) – Shallow Embankment Nomenclature

The volume of material excavated is to be included in the measured volume for General Earthworks.

This effectively changes the shallow embankment into a cutting. The requirement is intended to deal

with the major problems that occur with poor drainage and unsuitable materials in this situation, in

the same way as the cut/fill transition treatment. It effectively converts the necessary excavation into

the foundations from unsuitable to general earthworks and makes it necessary to take the resultant

quantities into account in the earthworks balance. The temptation to minimise the nominated depth

should be resisted. It may reduce the physical work required, but could mean that it is paid for at a

higher rate and ordered up piecemeal (thus minimising the chances of it being programmed properly).

As a general guide, embankments should be designed for a minimum height of 1.5 m (2 m is

preferable) from the foundation level to the top of the Selected Material Zone to allow for bridging

and minimise the potential need for excavation below the natural surface.

Shallow embankments commonly arise under the following circumstances:

Adjacent to cut/fill transitions (the requirement applies to the full width of the embankment, not

just the area underneath the pavement

Local topographic highs which do not reach the grade line

Urban situations where embankment levels are dictated by the need to match adjoining properties

Extensive low fills on flat, low-lying or gently sloping ground, where the natural slope follows the

gradient of the control line.

Shallow embankments are inevitable under the first three circumstances, but should be avoided, as far

as possible, in the fourth.

3.5.2 Cut/Fill Transition

Following excavation to the Designed Floor Level at the cut/fill transition, within the area classed as

Shallow Embankment in accordance with Clause 3.5.1, carry out further excavation, parallel to the

cutting floor, below the Designed Floor Level, to a depth necessary to achieve the minimum height

specified in Annexure R44/A4 for a Shallow Embankment, as shown in Figure R44.6(b).

Care needs to be taken to ensure that depths of excavation for the cut/fill transition and shallow

embankment are compatible. It is also important to consider the stability of the vertical faces of the

excavation, particularly if the vertical face is at the base of a planned cutting slope. The cutting

stability will likely be reduced by the excavation and backfilling should be carried out as soon as

practicable to eliminate this risk

Stripped Surface Level (after removal

of topsoil)

Selected Material Zone

Pavement

Designed Finished Surface Level

MEDIAN (dual carriageways only) BATTER

Top of Formation

Verge or Pavement (see Drawings) Selected Material Zone

may extend to edge

- see Drawings

Foundation Level after excavation to minimum depth

for Shallow Embankment (1)

Upper Zone of

Formation (2)

Page 44: TRANSPORT FOR NSW (TfNSW) SPECIFICATION GUIDE NR44 GUIDE …

(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)

NR44 Guide to R44 Earthworks

36 Ed 2 / Rev 1

This additional excavation must extend into the cut for a distance of 10 m from the line resulting from

the intersection of the plane of the Designed Floor Level with the plane of the stripped surface, as

shown in Figure R44.6(b). The 10 m is measured perpendicular to the line of intersection between the

two planes.

This cut/fill transition treatment must not however extend into the cutting batter.

Plan View Notes:

(1) Where the height from the Stripped Surface Level to the Top of Formation is greater than the minimum height for a

Shallow Embankment, no further excavation below the Stripped Surface Level, other than terracing, is necessary. The

thickness of the Upper Zone of Formation will be that corresponding to “embankment” in Annexure R44/A4. The fill

below the Upper Zone of Formation may be General Fill.

(2) Where the height from the Stripped Surface Level to the Top of Formation is less than the minimum height for a Shallow

Embankment, further excavation to achieve the minimum height for Shallow Embankment is necessary. This excavation

extends into the cut for a further 10 m as part of the Cut/Fill Transition Zone.

The thickness of the Upper Zone of Formation will be that corresponding to “cut/fill transition” in Annexure R44/A4.

(3) Beyond the Cut/Fill Transition Zone, the thickness of the Upper Zone of Formation will be that corresponding to

“cutting” in Annexure R44/A4.

(4) The 10 m is measured perpendicular to the line resulting from the intersection of the plane of the Designed Floor Level

with the plane of the stripped surface.

Figure R44.6(b) – Cut/Fill Transition Treatment

Within this transition zone, the requirements of Clause 3.5.1 for Shallow Embankment apply.

The volume of material excavated is to be included in the measured volume for General Earthworks.

Ensure that the excavation is free-draining by either sloping toward the nearest exit of the cutting at a

minimum grade of 1%, or installing a subsurface drain at the lower end of the excavation unless

otherwise shown on the Drawings or directed by the Principal. Installation, and payment, of the

subsurface drains must be in accordance with Specification TfNSW R33.

The purpose of the excavation of the cut/fill line is to remove potentially poor quality near surface

material from the upper zone of formation. Note that the requirement applies equally to side cuts.

Upper Zone

of Formation (2)

Foundation Level

after excavation to minimum

height for Shallow Embankment

Top of Formation

Terracing

as required

Designed Floor Level

(base of Selected Material Zone)

Stripped Surface Level

(after removal of topsoil)

Selected Material Zone

10 m (4)

Intersection

line

Transition Zone

Extent of additional excavation

Upper Zone

of Formation (1)

General Fill

Upper Zone of Formation (2)

Upper Zone of Formation (3)

“Shallow

Embankment”

10 m (4)

Cutting batter after excavation

to Designed Floor Level

Intersection

line

Extent of additional

excavation into cut

Page 45: TRANSPORT FOR NSW (TfNSW) SPECIFICATION GUIDE NR44 GUIDE …

(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)

Guide to R44 Earthworks NR44

Ed 2 / Rev 1 37

The thickness of the zone should be chosen and specified in the Annexure to suit each individual

project and its materials.

We need to be aware of very flat existing side slopes which can result in very long skewed transitions

resulting in significant increases in earthworks volumes. It is worthwhile to prepare plan drawings

which show the intersection line after topsoil stripping, together with an additional contour at the

cut/fill transition depth.

The location of the back of the excavation (10 m on the cut side of the intersection line, measured

normal to that line) can also be shown. This will help avoid the problem described above and will

provide a good basis for deriving quantities. It makes the scale of the task explicit to tenderers and

provides tenderers with a breakdown of cut/fill line quantities throughout the job for inclusion in the

earthworks plan).

Material removed from beyond the 10 m line is treated as unsuitable.

4 CUTTINGS

4.1 GENERAL

Construction of cuttings includes all operations associated with the excavation of material within the

limits of the batters including benching, terracing of cut batters, cleaning of batter surfaces, treatment

of cutting floors, foundation treatments in accordance with Clause 3.4, beneath Shallow Embankments

in accordance with Clause 3.5.1, and cut/fill transition in accordance with Clause 3.5.2.

4.2 EXCAVATION

Loosen and process the excavated materials as required to meet the Specification requirements for

incorporation in the Works, in particular Clauses 2, 5.6 and 6 of this Specification.

Good site investigations and interpretation of results will assist greatly in this area. Whilst designers

provide changes of slope at changes in expected materials, it is rare that the actual material changes

will be as uniform and clear as the design may imply. For that reason, where changes to slope are

required by the design, good design will where possible also include a bench at that transition from

soft to hard material.

It is important that the cuttings are inspected regularly as they are excavated to confirm the design

parameters and to enable minor adjustments to bench levels and slopes as required. Upper slopes

should be trimmed (and re-vegetated if required) before lower slopes are excavated as it will become

more difficult and more expensive to repair slopes and make changes when the cutting has been more

fully excavated and large plant and equipment cannot access the upper levels with ease.

Benches will also occur for other reasons than a change of material and will not always coincide with

rock quality transitions. The need to allow for access to the upper parts of a slope for maintenance

should be considered in the design. Persons supervising cut batter construction should be familiar

with the design philosophy of the cut and its implications, to avoid making decisions “on site” which

conflict with design objectives.

The batter slopes in cuttings must be in accordance with those shown on the Drawings, or as

re-determined by the Principal, following a site inspection and investigation during excavation.

Page 46: TRANSPORT FOR NSW (TfNSW) SPECIFICATION GUIDE NR44 GUIDE …

(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)

NR44 Guide to R44 Earthworks

38 Ed 2 / Rev 1

Round off the tops of cuttings to the dimensions shown on the Drawings unless otherwise directed.

Batters will generally require progressive flattening at the ends of cuttings owing to the presence of

less stable material. In all cuttings, undulations in the general plane of the batter are not acceptable.

The cutting must be free of rills running down the face of the batter (except for pre-splitting holes).

Treat the face of the batter if such treatment is shown on the Drawings.

Clear the cut faces of any loose or unstable material progressively as the excavation proceeds.

4.3 CUTTINGS IN ROCK

Clean the cut batters in rock with slopes of 1H:1V or steeper, using compressed air, to allow

inspection of the batter and assessment of its stability immediately following completion of excavation

to the level of each bench. Do not use water jets and air-water jets unless specifically approved by the

Principal for specific areas. Remove any loose or unstable blocks which are too large to be removed

by the above means, by hand or machine, unless otherwise directed by the Principal.

Clean also the surface of the bench at the top of the batter by compressed air, unless otherwise directed

by the Principal.

Continue cleaning until all loose rock and soil material is removed, and all rock and joint surfaces are

sufficiently exposed so that the Principal can assess their condition and likely effect on the stability of

the batter.

HOLD POINT

Process Held: Excavation below bench level for slopes of 1H:1V or steeper.

Submission Details: Presentation of cleaned batter and bench/floor surfaces for geotechnical

inspection.

Release of Hold Point: The Principal will inspect the cleaned surfaces and may direct further action

prior to authorising the release of the Hold Point. Further action may include

additional cleaning (if the condition of the faces cannot, in the opinion of the

Principal, be adequately assessed), and stabilisation works, prior to or

concurrent with any further work within the cutting.

Following inspection, the Principal may direct additional stabilisation works, including changes to the

batter slope.

The scope of stabilisation works should be determined, as far as possible, prior to tender and suitable

treatment quantities allowed. In some cases, special provisions may be needed in R44.

4.4 BATTER TOLERANCES

Excavation of batters must comply with the tolerances given in Table R44.3.

Table R44.3 – Excavation Tolerances for Batters in Cuttings

Location Tolerance (mm)

Slope 1H:1V or flatter Steeper than 1H:1V

Batters at toe of batter +0 / –150 +0 / –200

2 m above toe of batter and higher +300 / –300 +300 / –600

Page 47: TRANSPORT FOR NSW (TfNSW) SPECIFICATION GUIDE NR44 GUIDE …

(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)

Guide to R44 Earthworks NR44

Ed 2 / Rev 1 39

Between level of toe of batter and

2 m above toe of batter pro rata basis pro rata basis

Note: Plus (+) is towards the roadway and minus (–) is away from the roadway. Tolerances are

measured perpendicular to the plane of the slope.

If the batter is over-excavated beyond the tolerance applicable for the batter slope line, or after

cleaning the batter is beyond the tolerance applicable, restore the batter to the specified slope and

stability to the Principal's satisfaction. Proposals for restoration must take into account long term

stability, durability, and consideration of urban design solutions. The cost of restoring or re-forming

the batter must be borne by you.

Restoration of earth batters would normally be carried out using conventional small plant,

remembering to terrace the natural material before compacting fresh material in layers. In rock

cuttings, restoration could be by coloured concrete or by hand placed mortared stone pitching. Urban

design issues and the likelihood of impacting by errant vehicles will influence this decision.

Restoration of rock cuttings could also involve rock bolting of potentially unstable material.

The appropriateness of the standard tolerances should be considered against the expected condition of

the rock mass after excavation. Alternative requirements may be specified if conditions warrant them.

Such requirements could include pre-splitting, closely-spaced line drilling and/or the use of specialist

mining equipment. Economics and urban design aesthetic values will govern the decisions against the

alternative solutions of rock-bolting and shotcreting. Safety considerations for the severity of vehicle

impacts govern the finish requirements for the lower 2 m of the batter.

For batters steeper than 1H:1V, if any section of the batter up to a height of 3 m above the toe of batter

has been over excavated beyond the tolerance limit specified, the Principal may direct that the batter

be re-formed to the average batter slope using randomly mortared stone or other treatments. Where

stone is directed, it must be similar to the sound rock in the cutting and the mortar must be coloured to

match the colour of the rock.

Alternatively, you may request a minor change in the general slope of the batter for your convenience.

If the Principal approves such a change, it will not be regarded as a redetermination of the batter slope

under Clause 4.2 and no additional payment will be made. If your request is denied, restore the batter

to the specified slope and stability to the satisfaction of Principal.

4.5 BENCHING IN CUTTINGS

Cut batters must be benched as shown on the Drawings to provide drainage and erosion control, to

provide geotechnical stability, and to allow access for maintenance purposes. Notwithstanding the

tolerances permitted under Clause 4.4, bench widths must not be less than those shown on the

Drawings.

The floor of the bench must not vary from levels shown on the Drawings by more than the tolerances

shown in Clause 7.5, but the bench must have a crossfall to drain water away from the cut face

immediately below the bench. Provide and maintain longitudinal drainage to prevent ponding of water

on the benches.

Construct bench drains, where shown on the Drawings, progressively as each batter face is completed.

Payment for this work will be made in accordance with TfNSW R33.

Maintain and regularly clean the benches of any loose materials throughout the Contract period. The

cost of such maintenance and cleaning of benches is deemed to be included in the rates generally.

Page 48: TRANSPORT FOR NSW (TfNSW) SPECIFICATION GUIDE NR44 GUIDE …

(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)

NR44 Guide to R44 Earthworks

40 Ed 2 / Rev 1

4.6 PRE-SPLITTING OR LINE DRILLING

Use pre-splitting or line drilling to produce a uniform and neat batter surface after excavation or to

ensure protection of batters prior to burden blasts.

Extensive blasting is not usually required in cuttings with a 1:1 or flatter slope, as the material will

usually be able to be ripped. There are however many exceptions, particularly in igneous rocks such

as granite which weather variably. Batter design may be governed by the more weathered rock (or its

ultimate condition if it is expected to degrade with time) and excavation by the less weathered. We

need to be very careful not to imply that excavation characteristics can be predicted from batter

slopes.

Pre-splitting and line drilling are very difficult to do on such slopes due to the difficulty in controlling

the direction of drilling when angled so far from the vertical plane. Where blasting is required in

these conditions (usually because of variable rock strength), most contractors will propose an

alternative of normal drill and blast and cleaning up/trimming of the batter using rock hammers to

achieve the specified tolerances.

Where flat batters e.g. 2:1 are specified, consideration needs to be given to modifying the specified

tolerances.

The Principal will give consideration to an alternative method of excavation and preparation of the cut

face so as to produce a result equivalent to that produced from pre-splitting or line drilling. Approval

to such alternative methods will be granted at the absolute discretion of the Principal, who may require

a trial section of the proposed method to be carried out to demonstrate its suitability.

Where pre-splitting or line drilling is carried out, the centre-to-centre spacing of drill holes must not

exceed the values in Table R44.4.

Table R44.4 – Hole Diameter and Spacing for Pre-splitting or Line Drilling

Cut Batter Treatment Hole Diameter (mm) Maximum Hole Spacing (mm)

Pre-splitting 38 – 51 450

Pre-splitting 51 – 64 750

Pre-splitting 76 – 89 900

Line Drilling Up to 51 150

Line Drilling 51 – 76 250

4.7 BLASTING

4.7.1 General

The following applies only where blasting is permitted under the Contract, as indicated in Annexure

R44/A6.

Obtain all necessary licences from the appropriate authorities and comply with all Government

regulations relating to transport, storage, handling and the use of explosives and also the rules set out

in AS 2187 Parts 1 and 2. Comply with the requirements of all external agencies including, but not

limited to, the Environment Protection Authority (EPA) and the WorkCover Authority and

demonstrate compliance.

Do not use exposed detonating cord in built-up areas. Demonstrate compliance with Clause 6.8 of

Specification TfNSW G35 or G36, as applicable.

Page 49: TRANSPORT FOR NSW (TfNSW) SPECIFICATION GUIDE NR44 GUIDE …

(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)

Guide to R44 Earthworks NR44

Ed 2 / Rev 1 41

The Vibration and Air Blast Management Plan (refer to Specification TfNSW G35 or G36, as

applicable) must contain details of review and verification of the above requirements and its

operations to ensure that the public, building structures and infrastructure are protected.

HOLD POINT

Process Held: Start of each blasting operation.

Submission Details: Written details of the proposed blasting procedure including the quantity and

type of explosive to be detonated, the blasting pattern to be used and

measures proposed to limit noise and to ensure that vibration from blasting

does not adversely affect nearby structures. This must be contained in the

Vibration and Air Blast Management Plan.

Release of Hold Point: The Principal will consider the submitted documents, prior to authorising the

release of the Hold Point.

Provide certification of the adequacy of the Building Condition Inspection to the Principal at least

three days before the blasting is due to commence. Monitor and report the Building Condition during

the blasting operations. You are responsible for all costs associated with the inspections and reports if

no Pay Item has been provided in Specification TfNSW G36 for this work.

Monitor all blasts for ground vibration and air blast to ensure that the ground vibration and air blast

level caused by blasting does not exceed the respective values of peak particle velocity and air blast

overpressure listed in Annexure R44/A6 and the requirements of Specification TfNSW G35 or G36, as

applicable.

Implement and maintain a community liaison program during blasting activities to keep people in the

vicinity of the Works informed of any activities. Address levels of vibration or air blast.

Advise all residents within a radius of 1 km from the site of the proposed blasting, before blasting

operations commence. Written advice must include the likely times, frequency and duration of

blasting and precautions being taken to ensure that damage to property will not result.

Confine your blasting operations to the weekdays of Mondays to Fridays but excluding public

holidays, between the hours of 9 am and 3 pm, unless otherwise approved by the Principal.

Do not detonate a blast prior to the time that has been announced for that blast, unless otherwise

approved by the Principal.

When blasting operations are being carried out, take precautions relating to the safety of persons and

animals. Close any roads likely to be affected by the blasting to traffic and erect the appropriate signs

in accordance with Specification TfNSW G10. Establish a standard warning procedure such as that

given in the NAASRA Explosives in Roadworks Users Guide 1982 and observe the procedure at all

times.

Clearly outline in the Vibration and Air Blast Management Plan a detailed procedure to be followed in

the event of a misfire.

4.7.2 Pre-splitting or Line Drilling Prior to Blasting

Prior to commencing blasting, batters with gradients 1H:1V or steeper must be pre-split or line drilled

in accordance with Clause 4.6 to the design batter profile at sufficiently close centres to produce a

uniform and neat batter surface after excavation acceptable to the Principal.

Page 50: TRANSPORT FOR NSW (TfNSW) SPECIFICATION GUIDE NR44 GUIDE …

(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)

NR44 Guide to R44 Earthworks

42 Ed 2 / Rev 1

4.7.3 Blasting Records

Maintain accurate records of each blast including the details listed below:

(a) Date, identification number and time of blast;

(b) Location, number and diameter of blast holes loaded;

(c) Depth of each drill hole loaded;

(d) Inclination of drill holes;

(e) Burden(s) and spacing(s);

(f) Types and amounts of explosives used;

(g) Maximum instantaneous charge;

(h) Initiation Plan;

(i) Length and type of stemming in each blast hole;

(j) Ground vibration and noise levels at measuring locations.

The records must be written as the holes are loaded, and must be signed by the shotfirer. Provide a

copy of the records to the Principal on the day of the blast.

Blasting is a hazardous operation and may be an issue with nearby residents. Contractors usually

sub-contract this work to blasting specialists and it needs to be stressed to all involved that the main

contractor must take interest in the details of the blasts so as to minimise damage to properties and

adverse community reactions.

We must ensure that full details of each blast are properly recorded as specified above, as a minimum.

The above items (a) to (i) should be recorded and available for inspection before the blast is carried

out. If difficulties occur with vibration or airblast damage, we will usually require a thorough review

of the blast procedure, specifically dealing with the maximum instantaneous charge, the types and

number of delays and the type of stemming in the holes. We must therefore be able to examine full

details of all blasts and satisfy ourselves that appropriate steps are being taken.

This is a difficult situation as subsequent blasts need to be very conservative in order to ensure no

further damage. Insistence of review of the blasting proposal by an independent experienced and

qualified person is suggested. Re-commencement of blasting should be on a trial basis, be very

conservative and be closely monitored by measuring equipment as well as in person by TfNSW

engineers and inspectors.

5 EMBANKMENTS

5.1 GENERAL

Embankment construction includes:

(a) the preparation of the foundation areas over which fill material is to be placed as described in

Clause 3 and backfilling of excavations undertaken for foundation treatments for both cuttings

and embankments;

(b) the placement and compaction of conforming material within areas from which unsuitable

material has been removed in accordance with Clause 2.4 and within areas where material has

been removed below the pavement zone in cuttings and cut/fill transitions;

Page 51: TRANSPORT FOR NSW (TfNSW) SPECIFICATION GUIDE NR44 GUIDE …

(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)

Guide to R44 Earthworks NR44

Ed 2 / Rev 1 43

(c) the placement and compaction of fill material and of materials of specified quality in nominated

zones throughout the Works, including “spill-through” bridge abutments zones where

subsequent pile foundation works are to be undertaken;

(d) all other activities required to produce embankments as specified, to the alignment, grading and

dimensions shown on the Drawings.

Earth fill embankments are embankments not conforming to rock fill requirements (refer Clause 5.3).

Material for embankment construction must be obtained from excavations within the Works and,

where authorised by the Principal, may be supplemented with borrowed or imported material in

accordance with Clauses 2.7 and 2.8. The material must be free of tree stumps, roots and refuse.

Embankment construction (other than for foundation treatments as specified in Clause 3, Upper Zone

of Formation and verges) must be in accordance with the requirements of either Clause 5.2 or 5.3, as

applicable.

Process those materials which do not meet the requirements of these Clauses to ensure conformity

prior to placement. Select the methods of excavation, transport, depositing and spreading of the fill

material so as to ensure that the placed material in any Lot is homogeneous.

Place fill material for embankment construction in layers parallel to the grade line.

Achieve relative compaction specified in Clause 7 over the full depth of the layer. Describe in the

EARTHWORKS PLAN the method used to verify that the specified compaction has been achieved

over the full layer depth and that the layer depth has not been exceeded.

Compaction must also be achieved over the full width of the formation. At times, this may mean

construction of over-wide embankments and subsequent trimming of loose material from the edges.

Programme and manage the Works as detailed in EARTHWORKS PLAN (Clauses 1.5 and 2.2) so

that material of the quality specified in Clause 2.8 for the Upper Zone of Formation and verges is

available when required.

Generally, material for selected material zone and verge material will need to be stockpiled (and often

processed by crushing or screening) before placement in an embankment.

Embankment material zones are as illustrated in Figure R44.2.

5.2 EARTH FILL EMBANKMENTS

Construct the embankment so as to derive its stability from compaction of the fine material around the

coarser particles. Rock material must be broken down and evenly distributed throughout the layer to

prevent the formation of voids and to produce a dense compact embankment. To meet this

requirement, additional fine material may need to be obtained from other places within the Works or

by a change in the method of winning and processing the material.

Maximum layer thicknesses and particle size limitations are given in Table R44.5.

Page 52: TRANSPORT FOR NSW (TfNSW) SPECIFICATION GUIDE NR44 GUIDE …

(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)

NR44 Guide to R44 Earthworks

44 Ed 2 / Rev 1

Table R44.5 – Maximum Layer Thickness and Material Properties of Rock in Earth Fill

Embankments

Maximum Layer

Thickness (mm)

Minimum Quantity

Rock (by volume)

Maximum Rock

Size

(any dimension, mm)

% Passing 37.5 mm

AS Sieve (by mass)

300 Not specified 200 > 60%

500 25% > 200 mm 300 > 60%

Maximum layer thicknesses are specified to help ensure that the specified compaction can be obtained

throughout the full depth of each layer. The ability to achieve compaction in a layer is limited by the

thickness, material type and condition and the available plant. In general, compaction within a layer

will never be uniform and as the thickness increases will be much lower towards the base of the layer.

The requirement means that even the least compacted parts of the layer must reach the specified

relative density. The Contractor is required to have an acceptable method which will demonstrate

that this has been achieved.

In order to demonstrate compaction over the full layer thickness that thickness must be known.

Therefore a method of demonstrating layer thickness must be available. Possible methods include

direct measurement (by extending sampling holes for T111/T112 to the base of he layer), survey or

differential GPS measurements from compaction plant or graders.

Density testing by T173 cannot demonstrate full depth compaction of 500 mm layers as the test is

limited to 300 mm by the maximum extension of the probe of the nuclear gauge. Such a layer will

also, by definition, contain too much oversized rock to allow use of the method T119 (the sand

replacement method) can by used with thicker layers.

Demonstrating conforming average density over the layer depth is not sufficient to meet the specified

requirement, due to the depth effects described above. This is not normally an issue with layers

conforming to thickness requirements but is a major concern where 500 mm layers are being used or

the 300 mm limit is not being observed. Geotechnical advice should be sought if here is a need to

investigate this issue.

The conformance requirements (Clause 7) are intended to ensure that the smaller particles and fines

between cobbles and boulders in the layer are properly compacted. Obviously, density testing of

boulders themselves is not relevant to compaction testing. The 60% by mass passing a 37.5mm sieve,

quoted in the table above, is assessed from the samples recovered for compaction testing. It should be

understood that the requirement refers to the material forming the layer, not the individual samples.

Sampling effects mean that if the oversize content for the layer as a whole is near the specified limit,

some samples will exceed that limit.

The maximum size of rock is specified in any direction. This is to ensure that each rock particle is

wholly contained within the layer being placed and compacted. Rocks which break into large flat

plates are undesirable as they will tend to leave gaps underneath the edges and be unstable in a thin

layer.

Where more than 20% by mass of fill material is retained on the 37.5 mm AS sieve, or the compacted

layer thickness exceeds 300 mm, do not use nuclear density gauges for insitu density tests.

The T173 test (nuclear density gauge test) measures the average density of the material between two

points (the source at the end of the probe, at or near the bottom of the layer, and the detector at the

top of the layer, with a horizontal offset of about 300 mm between them), including any boulders that

may be present. The 20% limit applies because the relationship used to calculate the field density

within the nuclear gauge breaks down if there is too much large rock of much greater density than the

finer matrix.

Sand replacement densities (T119) can be conducted up to a rock content of 40%, which is the overall

limit in the specification for rock content of an earth fill. The reference density (T162 or T111)

Page 53: TRANSPORT FOR NSW (TfNSW) SPECIFICATION GUIDE NR44 GUIDE …

(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)

Guide to R44 Earthworks NR44

Ed 2 / Rev 1 45

excludes the larger rock (> 37.5 mm) simply because the test can’t be done if it is included. There is a

correction applied for the proportion of larger rock and its density, to allow comparison with the field

density.

The layer thickness (after compaction) must not be less than 100 mm.

The maximum size of rock pieces should not exceed 2/3 the layer thickness. For a thin 100mm layer,

the maximum particle size would be approximately 60mm.

In placing embankment layers, use equipment and techniques to avoid surface heaving or other

damage to the foundations and underlying embankment layers.

If heavy haulage equipment is required to pass over the completed work, the paths of the haulage

vehicles need to be varied to avoid failures caused by repeated loading in the same location.

5.2.1 Earth Fill at “Spill-Through” Bridge Abutments

For the earth fill at “spill-through” bridge abutments, the geometry is as shown in Figure R44.7.

At one end, it forms the exposed sloping part of the “spill-through” embankment. At the other end, at

the top, it extends a distance of 2h from the rear face of the bridge abutment headstock; at the bottom

at embankment foundation level, it extends a distance of h/2 from this rear face.

(For the purpose of this Clause, the height “h” is the distance between the soffit of the headstock and

the embankment foundation level. Where excavation is required for foundation improvement, the

height “h” is measured to the base of the excavation.)

Figure R44.7 – Dimensions of Fill at “Spill-Through” Bridge Abutments

The fill material must comply with the requirements of Clause 2.8.5.

Prior to placement, the material must be stockpiled, sampled and tested for conformity in accordance

with the requirements of Clause 6.1.2.

Each layer must not exceed 300 mm in thickness when compacted and must be compacted to the

requirements stated in Table R44.11.

h

h/

2

2h

Soffit of Headstock

Embankment

Foundation Level

h/2

Note: Dashed line above indicates location of

batter behind abutment, and extent of earth fill

complying with Clause 5.2.1, if abutment fill is

placed prior to adjoining embankment.

Earth fill

complying with

Clause 5.2.1

UZF other than SMZ

Selected Material Zone

Slope terraced

in accordance

with Clause 3.3

Page 54: TRANSPORT FOR NSW (TfNSW) SPECIFICATION GUIDE NR44 GUIDE …

(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)

NR44 Guide to R44 Earthworks

46 Ed 2 / Rev 1

Rocks must not be dumped against the columns or retaining walls but must be built up evenly by hand

placing around or against such structures.

Scour protection of the embankment is not considered in this Clause and, where necessary, must be

considered separately.

5.3 ROCK FILL EMBANKMENTS

5.3.1 Introduction

For the purpose of this Clause, a rock fill embankment is an embankment constructed of hard, sound

rock, containing only a small amount of fine particles, which derives its stability from the mechanical

interlock of the coarser particles, rather than from the compaction of the finer material.

Except where shown on the Drawings, do not place rock fill in areas where earth fill has previously

been constructed. If you elect to construct a rock fill embankment, adjust the working methods

employed in the excavation of cuttings so as to produce rock fill material of the grading and rock

strength specified in Clause 5.3.2. Such working methods must include screening and, if necessary,

secondary processing.

Place and spread the rock fill material in such a way as to avoid segregation and to ensure that it is not

contaminated with foreign material. The compacted rock fill layer thickness must not exceed 550 mm.

Compact the rock fill using the nominated compaction routine, developed as specified in Clause 7.3.

Material that does not meet the requirements for rock fill specified in this Clause must be broken down

further into finer particles, or have additional fines incorporated, and used in earth fill embankments in

accordance with Clause 5.2.

Nominate to the Principal the proposed areas of rock fill. If you elect to construct earth fill in part or

all of the nominated rock fill locations, and a surplus of rock, capable of being processed for rock fill,

is later found to exist, then treat the surplus by:

(a) processing the material for use as earth fill; or

(b) removal of earth fill and placement of the surplus rock as rock fill at your cost.

Shape and treat the foundations under rock fills to maintain drainage and to ensure that erosion of the

foundation will not occur.

Protection from future erosion of the foundation area below the rock fill should be carried out by

construction of suitable diversion drains and the placement of geo-textile material at the foundation

level of the rock fill.

Special measures may also be needed to protect culvert backfill material from erosion by water

flowing through a rockfill when the culvert is operating under afflux. This may involve the use of a

non-erodable and free draining select bedding and backfill material around the pipe, such as a 14mm

or 20mm crushed aggregate.

5.3.2 Rock Fill Material

Rock fill material must comply with Table R44.6. The constituent particles must be of uniform

strength and soundness.

The values specified in the Annexure should be chosen following discussions with experienced

geotechnical experts and extensive site investigation and testing of expected materials. The limit

should be specified to make distinction between acceptable and unacceptable materials as easy as

Page 55: TRANSPORT FOR NSW (TfNSW) SPECIFICATION GUIDE NR44 GUIDE …

(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)

Guide to R44 Earthworks NR44

Ed 2 / Rev 1 47

possible. This will require good knowledge of the expected strength characteristics of the rock and

their distribution. It is not desirable to set the limit so as to require extensive testing of “marginal”

materials to determine their suitability.

The properties in the table below are specified to limit the fines in the fill and to ensure that stability of

the fill is achieved by point contact of rock particles and to ensure that fines do not prevent that point

contact.

Table R44.6 – Rock Fill Material Properties

Property Requirement

Maximum particle dimension 300 mm

Percentage passing:

100 mm AS sieve 0 – 20%

19.0 mm AS sieve 0 – 10%

1.18 mm AS sieve 0 – 5%

Percentage of +100 mm fraction with

Is(50) < Annexure R44/A2.2

10% (max)

Wet/Dry Strength Variation Annexure A2.2

5.3.3 Overlying Layers

Do not place rock fill within 600 mm of the underside of the Selected Material Zone. The minimum

depth to rock fill below the underside of the Selected Material Zone is increased to 1.0 m where safety

barrier, posts, subsurface drainage or services are to be installed.

This requirement is to ensure deflections at the surface are reasonably consistent and that, in service,

the material from the Selected Material Zone does not migrate downwards into the voids of the rock

fill. The remaining requirement is so that large rocks are not near the surface where they would

impede the driving of guardrail posts or the future construction of other trenches.

Place a capping layer of 300 mm (+100 mm / –0 mm) thickness after compaction, composed of graded

rock fill immediately above the completed rock fill embankments. The material in the capping layer

must comply with the properties shown in Table R44.7.

Table R44.7 – Capping Layer Material Properties

Property Requirement

Maximum particle dimension 150 mm

Percentage passing:

19.0 mm AS sieve 0 – 10%

1.18 mm AS sieve 0 – 5%

Percentage of +19.0 mm fraction with

Is(50) < Annexure R44/A2.2 10% (max)

Wet/Dry Strength Variation Annexure A2.2

The grading of the capping layer has been chosen so that it behaves as a “graded filter” to minimise

the material from subsequent layers of fine material migrating down to the voids of the rock fill. In

addition to this capping layer, geo-textile separation layers specified below are also required.

Page 56: TRANSPORT FOR NSW (TfNSW) SPECIFICATION GUIDE NR44 GUIDE …

(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)

NR44 Guide to R44 Earthworks

48 Ed 2 / Rev 1

Place and spread the material for the capping layer in such a way as to avoid segregation and to ensure

that it is not contaminated with foreign material. Compact the capping layer using the nominated

compaction routine, developed as specified in Clause 7.3.

5.3.4 Rock Fill Around Structures

Notwithstanding requirements elsewhere in this Specification, the thickness of backfill around

structures specified in Clause 5.6.3 within rock fill embankments must be at least:

horizontally: 2.0 m (measured normal to the axis of the structure)

vertically: 1.0 m (where rock fill is to be placed over the structure).

The requirement is to avoid damage to structures by impact during construction or point loads in

service.

5.3.5 Geotextiles

Place geotextile separation layers conforming to the requirements of TfNSW R63 as follows:

Class D: beneath the first layer of rock fill.

Class D: between backfill to structures and the adjacent rock fill.

Class C: between the capping layer defined in Clause 5.3.3 and the overlying layer of earth fill.

Payment for geotextiles will be made under Pay Item R44P7.3 for Treatment Type E4.

5.4 EMBANKMENT BATTERS

The batter slopes shown on the Drawings may be subject to re-determination by the Principal

depending upon the materials encountered.

When completed, the batters of embankments must conform to those shown on the Drawings unless

otherwise authorised or re-determined by the Principal.

The tolerances for construction of embankment batters are detailed in Table R44.8.

Table R44.8 – Tolerances for Embankment Batters

Location Tolerance (mm)

Slope 1H:1V or flatter Steeper than 1H:1V

At level of Top of Formation/underside of

pavement +0 / –150 +0 / –150

1 m below Top of Formation and higher +150 / –150 +150 / –150

1 m below Top of Formation and lower +300 / –300 +300 / –300

Note: Plus (+) is towards the roadway and minus (–) is away from the roadway. Tolerances are measured

perpendicular to the plane of the slope.

Near the surface of the completed pavement, the shape of the batter is particularly important to ensure

safety for motorists in an out of control run-off.

Notwithstanding the above, the edge of the formation at the level of the underside of the pavement

must not be nearer to the roadway than that shown on the Drawings.

This is required so that the pavement can be constructed to its full width as designed.

Page 57: TRANSPORT FOR NSW (TfNSW) SPECIFICATION GUIDE NR44 GUIDE …

(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)

Guide to R44 Earthworks NR44

Ed 2 / Rev 1 49

Undulations in the general plane of the batter are not acceptable. The completed batter must be free of

rills running down the face of the batter.

Rills should be repaired as soon as practicable, as they are areas where water flow concentrates and

they generally develop into larger gullies through repeated scouring, eventually compromising the

stability of the formation. This matter is closely related to the batter slope angle and the face length

provided. Excessive face lengths or over-steep slopes will make rill formation inevitable in most

earthfill materials. The provision of berms to break up long slopes should be considered. Good

design, together with early revegetation, are essential in order to avoid these problems.

Promptly remove any loose material on the batters as the work progresses.

Placement of additional material on the existing embankment batters must be carried out in the same

manner as that specified for placement of hillside embankments in Clause 3.3.

This is so the new material is keyed in to the original material. Without the key, slope failure will be

more likely.) It also allows the new fill to be compacted against the interface. Consideration needs to

be given to drainage arrangements at the interface when widening on the downslope side of side fills.

5.5 ROCK FACING OF EMBANKMENTS

Where shown on the Drawings, provide a rock facing of clean, hard, durable rock over embankment

batters (including embankments at bridge structures) separated from the earth fill material with a

geotextile complying with TfNSW R63. Place the rock facing outside of the general embankment

dimensions.

Rock facing serves two purposes. It is a way of preventing scour of steep embankments and also an

economical way of dealing with large rock pieces. It is often specified under spill through bridge

abutments where lack of sunlight and water make revegetation difficult. The geotextile is placed

under the rock facing to prevent water running below the rock facing, causing erosion of the

underlying material.

Rock used for rock facing must have a Point Load Strength Index (Is(50)), as determined by Test

Method TfNSW T223, and a Wet/Dry Strength Variation, meeting the respective requirements stated

in Annexure R44/A2.2, and have a minimum dimension of 500 mm.

It is important that the rock is subjected to artificial weathering tests to ensure that it will not break

down prematurely in service. Some shales and siltstones particularly are very hard in situ but

deteriorate rapidly when exposed to cycles of wetting and drying. The test requirements need to be set

appropriately for the materials being considered. This must be job-specific.

You may elect, with the approval of the Principal, to place surplus rock conforming to the above as

rock facing.

The rock facing must be built up in layers ahead of each layer of filling. Place rock in such a manner

that its least dimension is vertical and that mechanical interlock between the larger stones occurs.

Remove any excess of fine material surrounding any rock placed within the rock facing by removing

the rock, removing the excess fine material and re-placing the rock.

Adjust the working methods and program of work to obtain sufficient hard and durable rock of the

specified dimensions to complete the facing as is required. Fill the space between larger batter rocks

and adjacent fill material with progressively smaller rocks to form a graded filter which prevents the

leaching out of fines from the fill material but which does not overfill the voids between larger rocks,

or cause the larger rocks to lose contact with one another.

Page 58: TRANSPORT FOR NSW (TfNSW) SPECIFICATION GUIDE NR44 GUIDE …

(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)

NR44 Guide to R44 Earthworks

50 Ed 2 / Rev 1

Exercise extreme caution whilst placing the rock facing. Where embankment material is placed in the

formation above other roads in use, place the outer rock layer in such a manner as to prevent spillage

down the batter. Implement measures to prevent any rock being dislodged and allowed to roll down

on to any adjacent roadway or track in use.

Payment for the rock facing and drainage layer will be in accordance with Pay Item R44P2. Payment

for the geotextile will be in accordance with Pay Item R44P7.3(a).

5.6 FILL PLACED ADJACENT TO STRUCTURES

5.6.1 General

Supply and placement of fill adjacent to structures is considered to be part of general earthworks. For

the purpose of this Clause, structures include bridges, box and pipe culverts, headwalls and

concrete/masonry retaining walls.

This Clause does not apply to reinforced soil walls (refer to Specifications TfNSW R58 and TfNSW

R59 for their requirements).

Select Fill placed adjacent to culverts and drainage structures, except that adjacent to weep holes, must

be provided in accordance with Specifications TfNSW R11 or TfNSW R22, as applicable. Select Fill

placed against other structures must conform to the requirements of Specification TfNSW B30. Fill

material within the Upper Zone of Formation must also comply with the relevant requirements of

Clause 2.8.

5.6.2 Treatment at Weepholes

Provide drainage adjacent to weepholes using broken stone or river gravel comprising clean, hard,

durable particles, with the following grading:

(i) the maximum particle dimension does not exceed 50 mm; and

(ii) no more than 5% by mass passes the 9.5 mm AS sieve.

The layer of broken stone or river gravel must be continuous in the line of the weep holes, extend at

least 300 mm horizontally into the fill and extend at least 450 mm vertically above the level of the

weepholes.

Alternatively, you may provide a synthetic membrane of equivalent drainage capacity at no extra cost

to the Principal. Store and install it in accordance with manufacturer's instructions. The use of

synthetic membrane as a substitute is subject to the Principal's concurrence.

Many synthetic materials deteriorate when exposed to sunlight. Covering and storing on site should

generally be arranged to avoid exposure to the sun.

5.6.3 Placing Fill Adjacent to Drainage and Bridge Structures

After completion of any backfilling required by Specifications TfNSW B30, TfNSW R11 and TfNSW

R22, place fill complying with Clause 5.6.1 adjacent to structures in accordance with Table R44.9.

Place the fill in accordance with Clauses 3.3 and 5.2 except that layers must have a compacted

thickness between 100 mm and 150 mm. Place layers simultaneously on both sides of box culverts to

avoid differential loading. Compaction must start at the wall and proceed away from it, and must meet

the requirements of Clause 7.

Page 59: TRANSPORT FOR NSW (TfNSW) SPECIFICATION GUIDE NR44 GUIDE …

(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)

Guide to R44 Earthworks NR44

Ed 2 / Rev 1 51

Cut the existing slope behind the structures listed in Table R44.9 in the form of successive horizontal

terraces, each terrace being at least 1 metre in width, 600 mm in height, and place the fill in

accordance with Clause 5.2.

Do not place fill against structures within twenty-one days after placing concrete in these structures,

unless the concrete strength is verified to have reached the specified 28-day strength.

Where a bridge deck is being concreted adjacent to an abutment, do not place fill against the abutment

within twenty-one days after placing concrete in the bridge deck, unless the concrete strength in the

bridge deck is verified to have reached the specified 28-day strength.

In the case of framed structures, bring up embankments at both ends of the structure simultaneously

and the difference between the levels of the embankments at the respective abutments must not exceed

500 mm unless otherwise shown on the Drawings or within the Specification.

Table R44.9 – Placing of Select Fill

Structure Select Fill

Width Height

Bridge Abutments 2 m H

Box Culverts H/3 H + 300 mm

Retaining Walls H/3 H

(where H = height of structure)

6 STRUCTURAL TREATMENTS

6.1 UPPER ZONE OF FORMATION

6.1.1 General

An Upper Zone of Formation, including a Selected Material Zone (see Figures R44.2(a), R44.2(b),

R44.6(a) and R44.6(b)), must be provided to the thickness specified in Annexure R44/A3 and must

meet the quality requirements specified in Clause 2.8.

Unless otherwise specified, do not place imported material in the Works until all material of suitable

quality available from the cuttings in the Works has been placed or has been assigned to be placed in

the formation.

For economy, projects are usually designed for balanced earthworks with a small excess of spoil or

small amount of borrow material. Imported material if not needed may not only be costly, it may also

result in an unwanted large excess of material towards the end of the job.

Experience suggests that it is prudent to allow for a 7 to 10% surplus in the design and have sufficient

space to spoil any that is not used. There is always wastage for various reasons, accompanied by a

tendency to overbuild embankments, the latter in part to ensure that compaction can be safely

achieved out to the design line.

Where it is apparent that special care will be needed to ensure that the required quantities of

materials for specialised uses can be obtained it may be necessary to impose more restrictive

requirements on working materials management. The TfNSW Contract Manager should then ensure

Page 60: TRANSPORT FOR NSW (TfNSW) SPECIFICATION GUIDE NR44 GUIDE …

(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)

NR44 Guide to R44 Earthworks

52 Ed 2 / Rev 1

that any measures needed, whether specified or not, are reflected in the Earthworks Plan.

Note: This comment applies equally to any issue involving materials management.

HOLD POINT

Process Held: Delivery of imported and site won material for the Upper Zone of

Formation.

Submission Details: Proposed location, quantities and type of material, and verification of

conformity. Verification that all possible sources of the material within the

site have been exhausted.

Release of Hold Point: The Principal will examine details and may inspect the source and stockpiles

of material prior to authorising the release of the Hold Point.

Before placing imported Upper Zone Material in any formation, carry out a survey in accordance with

TfNSW G71 to determine the surface levels at sufficient locations to later determine the volume of

compacted imported material placed in the Works. When shown in Annexure R44/A1, the survey

must be a Joint Survey in accordance with Clause 1.6.

This survey is done to establish the need for imported material and is necessary for payment purposes.

Compaction must be in accordance with Clause 7.

6.1.2 Selected Material Zone

Provide a Selected Material Zone (see Figures R44.2(a), R44.2(b), R44.6(a) and R44.6(b)) where

specified or shown on the Drawings. The Selected Material Zone must be placed and compacted in

layers with the compacted thickness of each layer not exceeding 150 mm unless otherwise specified in

Annexure R44/A4.

The properties specified in the Annexure must be to suit site conditions and must be chosen with

economy in mind. The Selected Material Zone is intended to ensure that the better materials available

from cuttings on the job are used at the surface of the formation, immediately below the pavement.

Sometimes, very hard materials will be available but processing costs may be high. In such cases, a

lesser material which still has an adequate CBR may be preferable due to its lower processing and

handling costs. The limitations on size of particles, layer thickness and compaction requirements are

to provide the best support possible for the pavement with these materials. Often, if good quality

material is not available from within the job, the material is specified to be imported. The choice of

imported material is usually based on economy as whilst this material is of better earthworks quality,

it is usually not as high a quality as pavement material.

Where specified in Annexure R44/A2.1, the material placed in the upper layer of the Selected Material

Zone at any particular location must be from the same source, produced using the same process and

exhibit similar properties prior to any chemical modification which may be required, as that placed in

the lower layer at that same location.

Prior to placement, all material intended for use in the Selected Material Zone must be stockpiled and

tested for conformity with the requirements of Clause 2.8.3 and Annexure R44/A2.2. The total mass

of each Lot of stockpiled material must not exceed 4000 tonnes.

Sampling must be in accordance with Table R44.10 and the characteristic value (Q) of the CBR for

each Lot calculated in accordance with Specification TfNSW Q. For the purpose of this calculation,

report the individual CBR values to the nearest 1% and the characteristic value (Q) to the nearest 0.1%

Page 61: TRANSPORT FOR NSW (TfNSW) SPECIFICATION GUIDE NR44 GUIDE …

(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)

Guide to R44 Earthworks NR44

Ed 2 / Rev 1 53

Table R44.10 – Sampling Frequency for Selected Material Zone Lots Before Placement

Total Mass of Lot Represented (tonnes) 1 – 500 501 – 1000 1001 – 2000 2001 – 4000

Minimum Number of Samples per Lot 2 3 4 5

HOLD POINT

Process Held: Placement of each Lot of Selected Material Zone.

Submission Details: Submit test reports verifying conformity of each Lot of stockpiled material

for use in Selected Material Zone.

Release of Hold Point: The Principal will consider the submitted documents, prior to authorising the

release of the Hold Point.

After placement, the Selected Material must be homogeneous and free from patches containing

segregated stone or excess fines. The placement methods used must ensure conformity with the

requirements of Clause 2.8.3 and Annexure R44/A2.2.

Trim the Selected Material Zone to meet the tolerances shown in Clause 7.5.1. As part of the

trimming operation, prepare the surface in accordance with Test Method TfNSW T199, for deflection

monitoring as required in Clause 7.4.

HOLD POINT

Process Held: Covering of each Lot of Selected Material Zone.

Submission Details: Verification of conformity of each Lot of Selected Material Zone with

relevant test and survey reports.

Release of Hold Point: The Principal will consider the submitted documents, prior to authorising the

release of the Hold Point.

6.2 VERGES

Provide verges as shown on the Drawings to meet the quality requirements specified in Clause 2.8.

Unless otherwise specified, do not place imported material in the Works until all material of suitable

quality available from the cuttings in the Works has been placed or has been assigned to be placed in

the formation.

HOLD POINT

Process Held: Delivery of imported material for the verges.

Submission Details: Proposed location, quantities and type of material, and verification of

conformity. Verification that all possible sources of the material within the

site have been exhausted.

Release of Hold Point: The Principal will examine details and may inspect the source and stockpiles

of material prior to authorising the release of the Hold Point.

Page 62: TRANSPORT FOR NSW (TfNSW) SPECIFICATION GUIDE NR44 GUIDE …

(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)

NR44 Guide to R44 Earthworks

54 Ed 2 / Rev 1

Carry out a survey in accordance with Specification TfNSW G71:

(a) before placing material in any verge to determine the surface levels at sufficient locations to

later determine the volume of compacted verge material placed in the Works; and

(b) before placing imported material to determine the surface levels at sufficient locations to later

determine the volume of compacted imported material placed in the Works.

When shown in Annexure R44/A1, the surveys must be a Joint Survey in accordance with Clause 1.6.

Place and compact the verge material in layers with the compacted thickness of each layer between

100 mm and 200 mm unless otherwise specified in Annexure R44/A4.

After placement, the material must be homogeneous and free from patches containing segregated stone

or excess fines.

Compaction must be as specified in Clause 7. You may compact adjacent to a concrete pavement only

after at least 10 days after the placement of concrete, or after joint sealing is completed, whichever is

the later.

Damage to freshly placed concrete must be avoided and placement of verge material before sealing of

joints in concrete pavement will result in fine material being deposited in the joints and prevent them

from achieving their designed movement.

Trim the verge to meet the tolerances shown in Clause 7.5.

6.3 OTHER TREATMENTS

Provide other Structural Treatments where shown on the Drawings, to comply with geotechnical or

other design requirements.

7 ADDITIONAL CONFORMITY REQUIREMENTS

7.1 GENERAL

Compact all layers of material placed in the Works uniformly over the full area and depth of the layer

to achieve the relative compaction specified before the next layer is commenced. Trim each layer of

material prior to and during compaction. Complete the compaction promptly to ensure that moisture

content remains conforming and uniform and to minimise the possibility of rain damage.

Unless the treatment of each layer is consistent throughout the layer, the analysis of testing of a layer

using statistical methods becomes irrelevant. This uniformity of treatment is essential to the definition

of a “Lot”.

7.2 EARTH FILL

For all areas and materials listed in Table R44.11, uniformly compact each layer over the full area and

depth of the layer to achieve the relative compaction specified in Clause 7.2.1 before the next layer is

commenced.

Page 63: TRANSPORT FOR NSW (TfNSW) SPECIFICATION GUIDE NR44 GUIDE …

(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)

Guide to R44 Earthworks NR44

Ed 2 / Rev 1 55

At the time of compaction, maintain the moisture content within the range specified in Annexure

R44/A5 at all locations within the Lot. Adjust the moisture content within that range to enable the

specified compaction to be achieved. Address monitoring and adjusting of moisture content in the

EARTHWORKS PLAN.

Do not compact material that has been placed with a moisture content greater than that specified in

Annexure R44/A5, or has become wetted-up after placement, until it has dried out so that the moisture

content is within the specified range. The drying process may be assisted by aeration or, where

approved by the Principal, by the use of hydrated lime or quick lime, complying with Specification

3211, at your cost.

Alternatively, you may remove the wet material to a stockpile site for drying out and later use as fill

material. Any cost of removal to stockpile, for drying out and later use is deemed to be included in the

rates generally.

The drying out of over-wet material can become very difficult, particularly in very wet seasons and in

winter when drying days and sunlight are short. We ought to be trying to let our contracts in such a

timeframe that these situations are avoided, particularly at the start of a project when large areas for

drying material are simply not available. If we are aware of very wet heavy clays in cuttings and we

know it will be difficult to dry, we should consider specifying and paying for stabilisation to improve

the material properties. Such decisions often result in better pricing by contractors, better site

management as well as an early finish and an overall reduced cost to the project. There may be other

solutions (e.g. spoiling, if the circumstances allow it). The solution should be thought out beforehand

and as far as possible, the work timed to minimise the need for drying or other treatments.

If over optimum material is excavated from cuttings and it is placed deep down in high fills, it may be

possible, with Geotechnical Branch concurrence, to build a stable fill which does not compromise

pavement support or embankment stability. With these materials it is usually easy to achieve

compaction but it is difficult to achieve the specified moisture content. In these cases, there will be

excess pore-water pressures from the compaction and the completed work will tend to “heave” under

heavy plant and machinery.

By waiting a period of time (usually the next day) the pore-water pressures reduce and provided the

material does not heave badly, the next layer can be placed. The best practical method of testing for

heaving is to proof roll in accordance with Clause 7.4.1 with a fully-loaded item of plant and to watch

the surface for movement. There will usually be some movement, however minor movement at depth

will not normally be detrimental to the finished pavement higher up in the fill.).

An alternative location which would usually be suitable for the placement of over optimum moisture

content material is in a wide median area or in very flat, wide batters, sufficiently clear of the

carriageway to not be an influence on the pavement deflections.

Care needs to be taken in placing over-wet material in large embankments. Zoned construction may

be appropriate (placing the wet material in the core of the fill, where large future moisture changes

are unlikely). Placing over-wet clay material full width can lead to stability problems, particularly if

it is highly expansive. Problems with instability under rolling tend to become worse if multiple layers

are placed in quick succession, before compaction-induced pore-pressures can dissipate. Depending

on the nature of the material (including matters such as permeability) it is also possible for apparently

stable layers to become unstable following rain or after wet material is placed on them.

If there is insufficient moisture in the material for it to be compacted as specified, add water. The

added water must be applied uniformly and thoroughly mixed with the material until a homogeneous

mixture is obtained. The cost of such wetting of the material must be borne by you.

Page 64: TRANSPORT FOR NSW (TfNSW) SPECIFICATION GUIDE NR44 GUIDE …

(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)

NR44 Guide to R44 Earthworks

56 Ed 2 / Rev 1

7.2.1 Relative Compaction Conformity Criteria

Carry out compaction control using Standard compaction on Lots using statistical techniques in

accordance with Specification TfNSW Q. Conformity of a Lot will be achieved if the characteristic

value of relative compaction of that Lot is not less than the lower limit specified in Table R44.11.

Table R44.11 – Lower Limit for Characteristic Values of Relative Compaction

Location Lower Limit of Characteristic

Value of Relative Compaction

Earth mounds

Spoil 90.0%

Foundation for Embankments (except where a bridging layer is used, as provided for in Clause 3.2.2).

Each layer of material replacing unsuitable material as detailed in Clause 2.4 (except within 300 mm of design level of floor of cuttings).

Foundation Treatment Types E1 and E3, and Working Platforms in embankments specified in Clause 3.2.3.

95.0%

Each layer of material placed in formations up to the underside of the Selected Material Zone, including that in Shallow Embankments and Cut/Fill Transition Zone.

The entire area on the floors of cuttings.

Material in verges or within medians up to the level at which topsoil is placed.

Select Fill placed adjacent to structures, as specified in Clause 5.4.

Other areas not specifically mentioned herein.

98.0%

Materials placed in the “spill-through” bridge embankment zone, as specified in Clause 5.2.1.

100.0%

Each layer of the Selected Material Zone. 102.0%

A Lot must contain only areas of work that are essentially homogeneous. This occurs when material

origin and properties, general appearance, moisture condition during compaction, compaction

technique, response to compactors, and state of underlying materials are substantially alike.

Areas that fail to meet these conditions must be excluded from the Lot and must be tested separately as

one or more additional Lots.

Failure to ensure compliance with these requirements in Lot definition invalidates the compaction

acceptance scheme. Also ensure that changes to Lot boundaries are accounted for in future testing.

7.2.2 Sampling and Testing

Engineers and Surveillance Officers engaged on contract work should be thoroughly familiar with the

requirements and shortcomings of the sampling and testing specified. They should spend some time

with an experienced laboratory technician and a geotechnical scientist in a soils laboratory to fully

understand test results presented. There are many opportunities for errors in sampling and testing

techniques which can result in erroneous results.

Particular care is needed to ensure that samples are taken to the full depth of the layer. Materials

may not be uniform through the layer depth, particularly in general earthworks. While strictly this is

in breach of the specification requirements, some variation in material properties is inevitable and can

be tolerated provided it is not too extreme. Sampling and testing of the full depth is necessary to

ensure that compaction requirements are being met.

Ensure that the laboratory independently carries out its responsibilities, as detailed in TfNSW Q, for

locating and carrying out sampling and testing.

Page 65: TRANSPORT FOR NSW (TfNSW) SPECIFICATION GUIDE NR44 GUIDE …

(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)

Guide to R44 Earthworks NR44

Ed 2 / Rev 1 57

Provide a smooth surface at each sampling location for the purpose of obtaining samples.

The PROJECT QUALITY PLAN must ensure that Lots are inspected for homogeneity as defined in

TfNSW Q Annexure Q/L Clause L1.

At each sample location selected for determination of compaction, carry out a field density test and a

field moisture test and obtain a sample for a laboratory maximum dry density test.

Carry out field (insitu) density tests in accordance with either Test Methods TfNSW T119 or

TfNSW T173.

Conduct all tests within a particular Lot using only one of the above Test Methods. Do not combine

results obtained from more than one Test Method for a statistical assessment of a particular Lot.

Where Test Method TfNSW T173 is used for the insitu density determination, extend the probe to be

located within the layer and close to the bottom of the nominated layer. Once the test is completed,

take a sample from below the test site, within the circle of area between the probe and the detector and

for the full depth of the nominated layer. The size of this sample must be sufficient for the laboratory

determination of maximum density.

Repair test holes using freshly mixed material of the same type as used in the surrounding earthworks

layer. Compact repair material to a degree equal to that of the surrounding earthworks layer. Detail in

the PROJECT QUALITY PLAN the method of repairing the test holes.

Irrespective of the Test Method used to determine the insitu density, the proportion and density of

oversize material retained on the 37.5 mm AS sieve in the sample for the laboratory maximum dry

density test must also be determined, in accordance with the procedure described in Test Method

TfNSW T119.

Determine field moisture content in accordance with Test Methods TfNSW T120, TfNSW T121, or

TfNSW T180. Only use TfNSW T121 and TfNSW T180 where results have previously been

calibrated against those of TfNSW T120 for the range of materials being compacted.

Determine maximum density using Test Methods TfNSW T111 or TfNSW T162.

7.2.3 Relative Compaction

Calculate relative compaction using Test Method TfNSW T166.

Round off the relative compaction value and the characteristic relative compaction value to the nearest

0.1%.

7.3 ROCK FILL

Conformity of a Lot of rock fill is based on compliance with the nominated compaction routine

verified in accordance with this Clause, and proof rolling in accordance with Clause 7.4.1.

Develop a materials grading, mixing, watering and rolling routine after construction and testing of trial

sections, and nominate the verified routine to the Principal. If the routine includes insitu modification

(e.g. with a grid roller or similar), then verify the after-compaction grading of the material.

The length of a trial section must not exceed 50 m, and the width must be greater than or equal to 2

times the maximum roller drum width. Do not construct trial sections within 1.5 m of the bottom of

the Selected Material Zone.

Page 66: TRANSPORT FOR NSW (TfNSW) SPECIFICATION GUIDE NR44 GUIDE …

(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)

NR44 Guide to R44 Earthworks

58 Ed 2 / Rev 1

Verification of a compaction routine will be based on results from two (2) successive trial sections.

Two contiguous trial sections, constructed over the same time period in a continuous operation, will

not be deemed to be two successive trial sections.

The compaction routine must include at least one vibrating roller.

WITNESS POINT

Process Witnessed: Construction of each trial section of rock fill

Submission Details: Notification of the place, date and time of construction of the trial section, at

least 3 working days prior to commencement with details of:

(i) Test results of all previous trial sections;

(ii) Material type(s) and specifications, including moisture conditioning

prior to and during rolling;

(iii) Plant types and specifications;

(iv) Number of roller passes;

(v) Maximum and minimum roller speed and frequency of vibration;

(vi) In-process testing regime and proof that there is no remaining internal

settlement and proof that embankment stability exists.

HOLD POINT

Process Held: Compaction of rock fill.

Submission Details: Verification, including test results, of conformity of each trial section

including details of the proposed compaction routine, any test results and

survey reports.

Release of Hold Point: The Principal will consider the submitted documents, prior to authorising the

release of the Hold Point.

Where in-process testing of the compaction routine reveals nonconforming results, cease placing and

compacting, and redevelop the routine using trial sections in accordance with the above or break down

and/or sort rock material to achieve an earth fill in accordance with Clause 5.2. The above Hold Point

applies to the redeveloped routine prior to recommencement of placement and compaction operations.

All costs associated with the development and nomination and verification of the compaction routine,

and the utilisation of the nominated compaction routine on rock fill layers is deemed to be included in

the rate for General Earthworks.

7.4 DEFLECTION TESTING

7.4.1 Proof Rolling

All embankment Lots, and all other surfaces within 1.5 metres of the underside of the Selected

Material Zone must be capable of withstanding proof rolling to verify their stability.

Unless otherwise approved by the Principal, undertake proof rolling in accordance with Test Method

TfNSW T198 in the presence of the Principal.

Page 67: TRANSPORT FOR NSW (TfNSW) SPECIFICATION GUIDE NR44 GUIDE …

(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)

Guide to R44 Earthworks NR44

Ed 2 / Rev 1 59

This clause is not intended to require proof rolling of every lift. It specifies the method by which proof

rolling should be done and when it is required. This should only be where there is a need to confirm

the stability of the formation as a platform for further construction. The procedure is T198. This

specifies the plant to be used. Alternative plant can be used providing it applies a loading at least

equivalent to that specified. Whilst the requirement is that each layer “must be capable…”, the

testing is not mandatory and is usually only required if instability and “heaving” are suspected.

The moisture content of the compacted material being proof rolled must be within the range specified

in Annexure R44/A5. Proof roll each layer immediately following compaction. For the purpose of

deflection testing by proof rolling, take the testing paths along the full width and length of each Lot.

WITNESS POINT

Process to be Witnessed: Proof rolling of any embankment fill layer, or any other surface within 1.5

metres of the underside of the Selected Material Zone.

Submission Details: At least 1 working day’s notice of intention to proof roll any surface with the

proof rolling plan and verification of the layer or surface conforms (except

proof rolling).

The tests must not exhibit visible deformation, rutting, or yielding and/or show signs of distress or

instability.

If further proof rolling is required at a later date, the layer must be re-conditioned such that the

moisture content is within the range specified in Annexure R44/A5, re-verified as conforming for

density and survey requirements of this Specification, and given not less than eight (8) passes with the

roller to be subsequently used for the proof rolling operation.

7.4.2 Benkelman Beam

Where shown in Annexure R44/A4, carry out deflection testing following completion of the formation

to the underside and top of the Selected Material Zone (or underside of pavement where no Selected

Material Zone is specified) using the Benkelman Beam in accordance with Test Method TfNSW T199.

Where the required characteristic deflection does not exceed 1.2 mm, the standard deviation of the Lot

must not exceed 0.2 mm. If the required characteristic deflection exceeds 1.2 mm, the coefficient of

variation of the Lot must not exceed 25%.

Limiting the deflection of the formation under the pavement limits the amount of deflection which must

be withstood by the pavement in service. If deflections are too high for a particular pavement design,

premature failure will occur.

The CV requirement will need to be reconsidered where deflections are very low, e.g. a Lot with a

mean deflection of 0.5 mm and SD of 0.2 mm will fail, with a CV of 40%, even though there may not

be a single deflection greater than 1.0 mm. A Lot with a mean of 0.8 mm and the same SD would pass

the CV requirement.

For the purpose of deflection testing with the Benkelman Beam, a Lot must consist of a continuous

length of formation of at least 300 m and of at least a single carriageway width that is generally

homogeneous with respect to material and appearance. In urban areas or area with severe restrictions,

the Principal may reduce the length of the Lot. Mark the boundaries of each Lot such that they are

clearly identifiable in the field.

Page 68: TRANSPORT FOR NSW (TfNSW) SPECIFICATION GUIDE NR44 GUIDE …

(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)

NR44 Guide to R44 Earthworks

60 Ed 2 / Rev 1

Take deflection testing by Benkelman Beam within 3 days of compaction of the material. Undertake

testing over the plan area of the Selected Material Zone within each Lot and any other area within the

Lot as directed by the Principal.

Obtain the Characteristic Deflection for each Lot from the equation:

CD = u + f.σ

where CD = Characteristic Deflection

u = average maximum deflection

f = value as shown in Annexure R44/A4

σ = standard deviation

Where the characteristic deflection exceeds the value in Annexure R44/A4, re-examine the Lot

boundaries, re-check the Lot for homogeneity, and subsequently re-nominate the Lot (or parts thereof)

for further testing.

WITNESS POINT (when Benkelman Beam Testing is specified)

Process to be Witnessed: Benkelman Beam testing of the surface under the first layer of pavement.

Submission Details: Notification of time, date and location of Benkelman Beam testing and

results of proof rolling at least 1 working day prior to the proposed date of

Benkelman Beam testing.

HOLD POINT

Process Held: Placing each Lot of Selected Material Zone or pavement (where there is no

Selected Material Zone).

Submission Details: Deflection test results, Survey Report of the finished surface and verification

of conformity of each Lot of formation at least 3 working days before the

work is programmed to be covered up.

Release of Hold Point: The Principal will consider the submitted documents, and may direct further

action prior to authorising the release of the Hold Point.

7.5 LEVEL CONTROL

7.5.1 Tolerances

Finish the surface levels of the floors of cuttings, transitions, earthworks layers and zones, and verges

to the design surface levels less the nominated thicknesses of the relevant overlying courses and zones

to within the tolerances detailed in Table R44.12.

Page 69: TRANSPORT FOR NSW (TfNSW) SPECIFICATION GUIDE NR44 GUIDE …

(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)

Guide to R44 Earthworks NR44

Ed 2 / Rev 1 61

Table R44.12 – Level Control - Tolerances

Position Tolerance

(a) Top of Selected Material Zone or top of formation where there is no Selected Material Zone:

(i) where overlying layer is part of the Contract, and quantity for payment for overlying layer is in units of square meters

(ii) where overlying layer is part of the Contract, and quantity for payment for overlying layer is in units of cubic meters

(iii) where overlying layer is not part of the Contract

+0 mm / –20 mm

+0 mm / –20 mm

+0 mm / –20 mm

(b) Formation at level of underside of Selected Material Zone:

(i) where underlying layer is a drainage layer in a cutting

(ii) all other cases

+0 mm / –20 mm

+0 mm / –20 mm

(c) Surface of verges +0 mm / –20 mm

(d) Floor of cutting before carrying out foundation treatment:

(i) Type C1 - Loosen and compact

(ii) Type C2 - Excavate and backfill

(iii) Type C3 - Working platform

(iv) Type C4 - Geotextile and geogrids

(v) Type C5 - Drainage layer

+0 mm / –20 mm

+0 mm / –100 mm

+0 mm / –100 mm

+0 mm / –20 mm

+0 mm / –100 mm

(e) Top of foundation treatment under embankment

(i) Type E3 - Working platform

(ii) Type E5 - Drainage layer

+20 mm / –20 mm

+20 mm / –20 mm

(f) Floor of terrace at Cut/Fill Transition +0 mm / –100 mm

(g) Floor of benching in cuttings +0 mm / –100 mm

(h) Top of rock fill +0 mm / –100 mm

7.5.2 Areas Below Level Tolerances

Where the overlying layer is not part of the Contract, and the finished surface level of the top of the

Selected Material Zone is not higher than the upper limit of the tolerance shown in Table R44.12

(+0 mm), but is lower than the lower limit of the tolerance (-20 mm), the work may be accepted by the

Principal, under the following conditions:

(a) Deductions are made at the rate shown in Annexure R44/A6;

(b) Your methods for carrying out the survey and calculation, and the calculated values, are agreed

to by the Principal.

7.5.3 Median Areas

The batter slopes for median areas must comply with those shown on the Drawings and undulations in

the general plane of the batter slope will not be permitted outside of the following tolerances.

For a horizontal distance of up to 2 m from the edge of the shoulder (except areas where verges are

required), no point on the completed batter may vary from the specified slope line by more than

35 mm when measured at right angles to the slope line. At distances greater than 2 m horizontally

from the edge of the shoulder, no point on the completed batter may vary from the specified slope line

by more than 75 mm when measured at right angles to the slope line.

Notwithstanding the tolerance of construction above, grade medians so as not to pond water.

Page 70: TRANSPORT FOR NSW (TfNSW) SPECIFICATION GUIDE NR44 GUIDE …

(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)

NR44 Guide to R44 Earthworks

62 Ed 2 / Rev 1

ANNEXURE R44/A – PROJECT SPECIFIC INFORMATION

NOTES TO TENDER DOCUMENTER: (Delete this boxed text after completing Annexure A)

Review the default values shown in Annexure A and amend if appropriate, fill in the missing details as

required, and delete as applicable where “Yes/No” options are provided in Annexure A, taking into

account the geotechnical information and the pavement design for the project.

For Annexure A1, consult TfNSW Survey Section on the practicality of the surveys.

These requirements must be complied with when compiling tender documents. They should be project

specific requirements and be based on a thorough knowledge of the site, the expected materials and

the makeup and availability of the site team and available personnel, i.e. it is a plan which is

considered practical and which TfNSW’s site team, as well as the Contractor, will be expected to

follow during the course of the contract. Engineers should consult with survey staff on the practicality

of these surveys.

A1 SURVEYS (Clause 1.6)

Carry out surveys and joint surveys (in accordance with TfNSW G71) where required in the following

table:

Clause Location Survey Joint

Survey

Model File (1)

2.3.2 Topsoil stockpile site before stockpiling Yes Yes Yes/No

2.3.3 Surfaces of each cutting and embankment after

stripping of topsoil

Yes Yes Yes/No

2.4 Before removal of unsuitable material Yes No Yes/No

2.4 After removal of unsuitable material Yes No Yes/No

4.4, 5.4 Completed cut and fill batters prior to

topsoiling, vegetation or other treatments

Yes No Yes/No

5.1, 6.1.1 Surfaces prior to placing imported material Yes Yes Yes/No

6.1.2 Surfaces prior to placing Selected Material Yes No Yes/No

6.2 Before placing verge material Yes No Yes/No

7.5.1 Floor of cutting before placing foundation

treatment materials or formation

Yes No Yes/No

7.5.1 Top of finished Formation Yes Yes Yes/No

7.5.3 Finished surface of median Yes No Yes/No

Note:

(1) If this requirement is “Yes”, the survey report must include a computer file containing data in a format that

is suitable for creating accurate models using the current standard TfNSW CADD software.

Page 71: TRANSPORT FOR NSW (TfNSW) SPECIFICATION GUIDE NR44 GUIDE …

(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)

Guide to R44 Earthworks NR44

Ed 2 / Rev 1 63

A2 MATERIALS

A2.1 Sources

Clause Description Requirement

2.3.1 Topsoil

2.3.1(i) - Stockpile within the Site Yes/No

2.3.1(ii) - Stockpile as a windrow Yes/No

2.3.1(iii) - Spoil outside the Site Yes/No

2.3.1(iv) - Spoil as contaminated material Yes/No

2.7.2 Borrow sites

- Specified location ………………….

- Maximum batter slope of borrow site excavation ……..

2.8.1 The following materials must only be from imported sources:

- Upper Zone of Formation material other than Selected

Material

Yes/No

- Selected Material Yes/No

- Verge material Yes/No

3.2.3, 3.4.3 - Working Platform stabilized material Yes/No

Sources of imported material:

2.8.2.2 - Upper Zone of Formation material other than Selected

Material

………………….

2.8.3.2 - Selected Material Zone material ………………….

2.8.4.2 - Verge material ………………….

5.1 - Imported fill ………………

3.2.3, 3.4.3 - Imported stabilized material ………………

6.1.2 Material in the Selected Material Zone at any location must be

from the same source (1)

Yes/No

Note:

(1) If this requirement is “Yes”, the material placed in the upper layer of the Selected Material Zone at any

particular location must be from the same source, produced using the same process and exhibit similar

properties prior to any chemical modification which may be required, as that placed in the lower layer at

that same location.

A2.2 Properties

All material properties to be entered below are site specific. The properties, Test Nos and values

entered should be chosen so that the best use is made of available materials.

The choice of 4 or 10 day soaks for CBR values should only be made after gaining knowledge of site

materials. Some very fine materials will have a high CBR value at 4 days soak but will deteriorate

after further soaking and the CBR at 10 days can be significantly less than at 4. Whilst a test done

after 4 days soak may give a quick answer, the four day soak result may not properly represent the

material properties in service. As a guide, 4 day soak will be specified for granular materials and 10

day soaks will be specified for lower permeability silts and clays.

Page 72: TRANSPORT FOR NSW (TfNSW) SPECIFICATION GUIDE NR44 GUIDE …

(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)

NR44 Guide to R44 Earthworks

64 Ed 2 / Rev 1

In a practical sense, the specified tests are meant to provide an indication of the suitability or

otherwise of materials before placement in each zone. They are an indication only. Most materials

break down to a degree during excavation, haulage, spreading, mixing with water or other material,

drying, compacting and trimming and many will provide a significantly different test result after these

operations have taken place and the material is in place in its specified zone. Pre-treatment and

accelerated weathering tests should be carried out prior to placement in a zone, in order to best

predict its behaviour in place. (See Note 1 below table.

Clause Location Value Test Pre-treatment

(1)

2.8.2, 3.5

Material for Upper Zone of Formation other than Selected Material, including at Shallow Embankment and Cut/Fill Transition:

a) CBR10 day (2) 8 min T117 T102/T103 (3)

b) Plasticity Index 25 max T109 T102/T103

2.8.3.1 Site won Selected Material:

a) Selected Material Zone top 150 mm layer CBR4 day (2), characteristic value (Q) (3) Refer Note 4

30 min (4) T117 T102/T103 (5)

b) rest of Selected Material Zone CBR4 day (2), characteristic value (Q) (3) Refer Note 4

15 min (4) T117 T102/T103 (5)

c) Plasticity Index 15 max T109 T102/T103 (5)

2.8.4 Verge material:

a) CBR4 day (2) 15 min T117 T102/T103 (5)

b) Plasticity Index 6 and 12 T109 T102/T103 (5)

3.5 Foundation of Shallow Embankment and Cut/Fill Transition where depth of excavation less than specified:

a) CBR10 day (2) 8 min T117 T102/T103 (5)

b) Plasticity Index 25 max T109 T102/T103 (5)

3.4 Floor of Cutting:

a) CBR10 day (2) 8 min T117 T102/T103 (5)

b) Plasticity Index 25 max T109 T102/T103 (5)

3.2.5, 3.4.5

Drainage Layer (Foundation Treatment Type E5 and C5):

a) Point Load Strength Index Is(50) 1 MPa min T223 NA

b) Wet/Dry Strength Variation 35% max T215 T102

3.4.2 Backfill material for Type C2 Foundation Treatment:

a) CBR10 day (2) 8 min T117 T102/T103 (5)

b) Plasticity Index 25 max T109 T102/T103 (5)

5.2.1 Earth fill at “spill-through” bridge abutment zone:

Material Type ST1, for waterway crossings

a) CBR10 day (2), characteristic value (Q) (3) 8 min T117 T102/T103 (5)

b) Plasticity Index 15 max T109 T102/T103 (5)

Material Type ST2, for overbridges

a) CBR10 day (2), characteristic value (Q) (3) 8 min T117 T102/T103 (5)

b) Plasticity Index 25 max T109 T102/T103 (5)

5.3.2 Rock fill:

a) Point Load Strength Index Is(50) 1 MPa min T223 NA

b) Wet/Dry Strength Variation 35% max T215 T102

Page 73: TRANSPORT FOR NSW (TfNSW) SPECIFICATION GUIDE NR44 GUIDE …

(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)

Guide to R44 Earthworks NR44

Ed 2 / Rev 1 65

Clause Location Value Test Pre-treatment

(1)

5.5 Rock facing:

a) Point Load Strength Index Is(50) 1 MPa min T223 NA

b) Wet/Dry Strength Variation 35% max T215 T102

Legend: NA = not applicable max = maximum min = minimum

Notes:

(1) Pre-treatment is not required where samples are taken from the compacted formation.

(2) Compaction for CBR test must be at 100% of MDD under standard compaction.

(3) When calculating CBR characteristic value, report values calculated to the nearest 1%.

(4) (Refer Clause 2.8.3.1.) If any Lot of Selected Material in the top 150mm layer has a CBR less than the value specified above, the material must be modified with hydrated lime at an application rate of 2% by mass. The modified material must have a UCS of less than 1.5MPa, when tested in accordance with TfNSW T131 using 7 days accelerated curing. Other suitable binders may be used where approved by the Principal. However, do not use binders which are prone to give rise to rapid or uneven strength gain or excessive shrinkage.

(5) Where pre-treatment is shown as “T102/T103”, determine the appropriate pre-treatment regime for the material in accordance with Clause 2.8.1.

The intention of Note (4) is that CBR values are selected to make best use of available materials and

that the Contractor should be able to achieve the result using the naturally occurring materials by

taking reasonable care. The option of stabilising in this specification is one which recognises that the

Contractor may actually not finish up with the required material quality. Stabilisation is usually an

option available which would improve the quality and reduce the moisture-susceptibility of the

particular material.

Whilst 2% lime is specified here together with a minimum UCS, other stabilising agents and

properties may be specified. In each case, the treatments and material properties need to be tailored

to suit the material available and the pavement design for the project. The pavement is generally

designed on the CBR of the material prior to modification on the assumption that in the long term the

lime may be leached from the SMZ.

Where the CBR in the SMZ is less than CBR = 30%, the 2% lime will reduce moisture susceptibility

during construction, will reduce the risk of pavers getting bogged and is consistent with achieving an

increase in strength upwards through the Upper Zones of Formation.

Care should be exercised, and Pavements Branch help sought, if a contractor proposes to use Steel

Furnace Slag (SFS) or other waste product materials as a pavement, SMZ or Upper Zone material.

SFS is prone to expansion when exposed to moisture in a pavement layer if not properly weathered for

at least three to four months beforehand. This comment does not apply to Blast Furnace Slag which

has successfully been used as a pavement material in a number of regions.

A3 FOUNDATION TREATMENT

Clause Description Requirement

3.2.2 Type E2 Foundation Treatment - Bridging Layer

- Minimum depth from underside of pavement to top of bridging

layer 600 mm

- Maximum thickness of bridging layer 800 mm

3.2.5 Type E5 Foundation Treatment - Drainage Layer

- Completed thickness of drainage layer 300 mm

(+100 mm, –0 mm)

Page 74: TRANSPORT FOR NSW (TfNSW) SPECIFICATION GUIDE NR44 GUIDE …

(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)

NR44 Guide to R44 Earthworks

66 Ed 2 / Rev 1

3.2, 3.4 Specified Foundation Treatments

- Location ‘A’ Type: …………..

- Location ‘B’ Type: …………..

A4 SHALLOW EMBANKMENT, CUT/FILL TRANSITION, UPPER ZONE OF

FORMATION AND VERGES

Job specific dimensions should be entered here.

Clause Description Requirement

3.2, 3.5.1 A Shallow Embankment exists where the height from the Stripped

Surface Level to the Top of Formation is less than: 1,200 mm

6.1 Thickness of Upper Zone of Formation (incorporating Selected

Material Zone) for:

- Cutting 300 mm

- Cut/Fill Transition Zone 1,200 mm

- Embankment 600 mm

- Shallow embankment 1,200 mm

6.1.2 Selected Material Zone:

- Thickness 300 mm

2.8.3.1 - Depth for modification of material, other than to only meet

specified CBR requirements

6.1.2 Maximum compacted thickness of each layer in the Selected

Material Zone:

150 mm

6.2 Compacted layer thickness of each layer of verge material 100 mm – 200 mm

7.4.2 Monitor deflection at underside and top of Selected Material Zone

with Benkelman Beam.

Yes/No

7.4.2 Maximum Characteristic Deflection (CD) recorded for any Lot

must not exceed:

- Top of Selected Material Zone 1.0 mm

- Underside of Selected Material Zone 1.2 mm

- Factor “f” to be used in determining CD 1.65

7.5.2 Deduction to be applied for out of tolerance surface level where

the overlying layer is not part of the Contract

……..

3.5.1 The removal of material from the transition zone is designed to address the often poor quality of

the natural material occurring in that zone. It is, by its nature, naturally occurring material near the

surface of the earth and is often weathered and of poor or variable quality. There are cases where the

cut/fill transition can extend over a great length and careful consideration should be given to the need

to specify its special treatment as a location needs to be found for the material excavated. The depth

of 900mm has been chosen as this is the depth from finished pavement level (approx 1500mm) which

would normally be affected by heavy vehicles travelling on a granular pavement. In order to be cost

effective, the pavement and earthworks need to be considered together.

Page 75: TRANSPORT FOR NSW (TfNSW) SPECIFICATION GUIDE NR44 GUIDE …

(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)

Guide to R44 Earthworks NR44

Ed 2 / Rev 1 67

6.1 The depths of materials in the upper zone of formation, including the select material zone needs to

be chosen to suit the best usage of available materials and the pavement design for the work. These

depths are site specific and should be chosen after careful consultation with geotechnical staff and

with due consideration of practicality and cost. The specifying of a select material zone is done to

ensure the most appropriate cost effective material is reserved for the surface immediately beneath the

pavement layers. The specifying of a deeper upper zone of formation in fills is done to try and ensure

the better materials available during earthworks excavation from cuttings (usually from towards the

bottom of cuttings), are utilised towards the tops of fills where they will experience the highest traffic

loading.

As explained above, deflections will change with time and moisture content. It will be in the

Contractor’s interests to measure some time after compaction, after no site traffic and after a dry

period of weather. Constraints are placed on the timing of deflection testing in both Clause 7.4.2 and

T199. If it is expected that this issue will be critical, further constraints should be specified.

There may be circumstances where requiring Benkelman Beam readings to be taken at the top of the

SMZ in addition to the underside of the SMZ can be waived but not without seeking prior Pavement

Branch advice.

The shape of the deflection bowl, measured during Benkelman beam readings, will provide a better

indication of quality and will indicate whether any “soft” layer is near the surface or some depth

below it.

A5 COMPACTION MOISTURE REQUIREMENTS (Clause 7.2)

Material Description (1) Source / Location Moisture Range (2)

Earthworks Material 60 – 90%

Notes:

(1) Material types above are project specific.

(2) The Moisture Range is expressed as the ratio of Field Moisture Content to Optimum Moisture Content at

standard compactive effort and is reported as a percentage.

Project specific requirements should be entered here. Whilst 60-90% will generally provide a

satisfactory result, it is conservative from TfNSW’s viewpoint.

In general, there will be difficulties compacting materials at moisture contents below 60% of optimum

and in any case, water will probably need to be added for dust control. It may not be practicable for

many materials to be compacted below 90% of optimum moisture content, particularly with heavy

clays in high rainfall or low-lying areas which are often at or above this moisture content in situ.

Consideration needs to be given to allowing higher moisture contents where this occurs and

permitting its placement at some depth in the fill, where it would not adversely affect the finished

pavement (usually 1500mm minimum below finished surface).

Compaction above optimum moisture content is likely to lead to a degree of “heaving” of the fill

immediately following placement due to the build-up of pore-water pressure. This results in difficulty

in compaction of the next overlying layer. If left overnight, the pore pressures built up during

compaction can often partly dissipate and with the heaving reduced, the next layer can be

satisfactorily placed and compacted.

See also comments in 7.2, regarding placement of high moisture materials in the core area of fills at

or near their equilibrium contents.

Page 76: TRANSPORT FOR NSW (TfNSW) SPECIFICATION GUIDE NR44 GUIDE …

(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)

NR44 Guide to R44 Earthworks

68 Ed 2 / Rev 1

A6 BLASTING (Clause 4.7)

A decision needs to be made. Excavation of hard rock can be achieved by a number of alternative

means, such as ripping, rock breakers or self-expanding chemicals incorporated into closely-spaced

drill holes. Whilst blasting can be a sensitive process in or near residential areas, often the

alternatives involve protracted durations of very noisy work with rock hammers and drills. These

issues should be resolved in the planning phase of the project.

Blasting permitted under Contract? Yes/No

Limiting Peak Particle Velocity and Blast Overpressure:

Blast overpressure is commonly known as “airblast” and is best described as a measure of the level of

noise experienced. The energy in the pressure wave, which is often in the low frequencies, can cause

significant damage to walled structures facing the blast and may cause window breakage. This

airblast is often responsible for the rattling of windows and glassware in houses.

Its effects are harshest on cloudy days and can be accentuated by atmospheric conditions. The effects

can be minimised by appropriate blast design that minimises rapid venting of the expanding gasses,

avoiding blasting on cloudy days, in humid conditions, choosing a suitable time of day (usually around

midday) for blasting and minimising the amount of exposed detonating cord lying on the surface of the

cutting being excavated.

Peak Particle Velocity is a measure of the blast vibration exerted on a structure. It is usually

transmitted through the hardest bands of rock below the surface and can be affected by the level of the

water table. With properly designed blast patterns, damage to buildings caused by blasting is

extremely rare but if any damage to buildings is caused, it is usually because of an excessive Peak

Particle Velocity.

In order to properly manage claims for damage to buildings, it is important to carry out thorough

building inspections before any blasting takes place and then again at the end of a blasting program.

It is advisable to have housing inspections carried out by an independent, reputable architect or

builder, with copies of all reports being provided to residents and owners before and after the blasting

has taken place.

There are many things other than blasting which can cause a building to exhibit cracking. Most

common is the effect of seasonal moisture changes near foundations of buildings, causing movement of

the foundations and cracking of walls.

It is also notable that most newly constructed houses will exhibit minor cracking near cornices of

plaster ceilings and walls within a few years of completion as a result of normal shrinkage of the

construction materials. Blasting can be a sensitive issue in residential areas and for this reason, any

blasting needs to be extremely well managed and must address community concerns.

Point of Potential Damage (within 1 km from the proposed blast site)

Blast Overpressure Level

(dB[linear])

Peak Particle Velocity (1)

(mm/s)

Completed and cured bridge structures or

sub-structures (e.g. completed abutment) – 10 mm/s

Bridgeworks and structural retaining walls

under construction – 10 mm/s

Residential premises, schools, hospitals

and other buildings 115 dB (2) 5 mm/s (2)

Building or monument of historical

significance 115 dB 2 mm/s

Page 77: TRANSPORT FOR NSW (TfNSW) SPECIFICATION GUIDE NR44 GUIDE …

(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)

Guide to R44 Earthworks NR44

Ed 2 / Rev 1 69

Notes:

(1) Peak Particle Velocity is the vector peak particle velocity, defined as the maximum of the resultant vector

particle velocity vp and is the amplitude of the vector sum of three time-synchronised velocity components

directly measured by an instrument.

vp is determined by the equation vp = √(vx2 + vy

2 + vz2),

where vx, vy and vz are the synchronized instantaneous velocity components in the x, y and z axes

respectively.

(2) 5% of readings may exceed 115 dB and 5 mm/s but must not exceed 120 dB and 10 mm/s.

Page 78: TRANSPORT FOR NSW (TfNSW) SPECIFICATION GUIDE NR44 GUIDE …

(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)

NR44 Guide to R44 Earthworks

70 Ed 2 / Rev 1

ANNEXURE R44/B – MEASUREMENT AND PAYMENT

Payment will be made for all activities associated with completing the work detailed in TfNSW R44 in

accordance with Pay Items below.

Unless otherwise specified, a lump sum price for any of these items will not be accepted.

If any item for which a quantity of work is listed in the Schedule of Rates has not been priced by you,

it will be deemed that due allowance has been made in the prices of other items for the cost of the

activity which has not been priced.

Pay Item R44P1 - Topsoil

Pay Item R44P1.1 - Removal and Stockpiling of Non-contaminated Topsoil

The schedule rate for Pay Item R44P1.1 is an average rate to cover the removal, loading,

handling, transporting and stockpiling of all non-contaminated topsoil within the limits of

Works.

The unit of measurement is the cubic metre measured in the stockpile of topsoil removed in

accordance with Clause 2.3.

The volume must be determined by measurement or survey, and calculation.

Note-measured loose in stockpile, although we can estimate the bank volume from depth times

area.

Pay Item R44P1.2 - Removal and Disposal Off-Site of Topsoil

The schedule rate for Pay Item R44P1.2 is an average rate to cover the removal, loading,

handling, transporting and disposal of topsoil off-site, including tipping fees and any other

disposal costs.

Topsoil removed as contaminated material in accordance with Clause 2.5.2 will be measured

and paid in accordance with Pay Item R44P8 and Pay Item R44P1.2.

The unit of measurement of topsoil directed to be removed and disposed of off-site in

accordance with Clause 2.3.1 items (iii) and (iv) is the cubic metre measured as bank volume of

excavation.

The volume must be determined by measurement or survey, and calculation.

Pay Item R44P2 - General Earthworks (Cut/Fill)

The schedule rate for Pay Item R44P2 is an average rate to cover all types of material encountered

during excavation and placed in embankments, including both earth and rock, and disposed of

otherwise than in embankments.

When a contractor encounters harder rock or more rock than anticipated, under the contract, this is

the contractor’s risk as there is no distinction between earth and rock in TfNSW contracts. Resident

Engineers should ensure that they get a survey of each cutting when the method of excavation changes

from rip & load by conventional diggers to a drill and blast operation, so that accurate records are

kept of the actual excavation method adopted by the contractor.

There has been at least one project where a separate rate has been introduced at pre-tender

(successfully) for part of a project, due to expected excavation and geotechnical conditions being very

Page 79: TRANSPORT FOR NSW (TfNSW) SPECIFICATION GUIDE NR44 GUIDE …

(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)

Guide to R44 Earthworks NR44

Ed 2 / Rev 1 71

different from the remainder of the work. This is a possible alternative approach, but requires very

good knowledge of the conditions.

The unit of measurement is the cubic metre measured as bank volume of excavation. Payment for

General Earthworks includes all activities associated with the excavation of material from cuttings

(including table drains and gutters), the excavation of material in/under Shallow Embankments,

excavation of material in Foundation Treatment Types C2, C3 and C5 and the construction of

embankments, including:

(a) preparation of the foundation areas, other than work paid under Pay Item R44P7;

(b) placing and compacting conforming material to replace unsuitable material, contaminated

material, and that required in Foundation Treatment Types C2 and C3, that has been removed;

(c) placing and compacting formation material and materials of specified quality in the Upper Zone

of Formation, other than work paid under Pay Item R44P5;

(d) placing and compacting earth fills and rock fills;

(e) rock facing of embankments;

(f) rounding of the tops of batters;

(g) haulage of material and any pre-treatment such as breaking down or blending material for

purposes such as rock fill;

(h) restoring, stabilising or re-forming any over-excavation;

(i) working General Fill and Upper Zone materials to bring moisture content of the Lot to within

the specified range including drying out material containing excess moisture;

(j) deflection testing and proof rolling;

(k) addressing any deficiency in sites for stockpiling, including disposal of unsuitable materials and

supplying their replacement;

(l) double handling of materials excavated from the site that are stored temporarily in stockpiles

before being returned for incorporation into the Works due to any staging of the Works;

The above list of inclusions and the following list of exceptions must be fully understood by people

administering this document. The document reviewer should check to ensure these exceptions are

relevant to this project.

Surveyors in particular, working on the project, need to be briefed and any issues clarified before the

work commences.

except that:

(i) supply and placing of imported or borrowed General Fill material and Upper Zone Material will

be paid under Pay Item R44P3;

(ii) removal of unsuitable material will be paid under Pay Item R44P4;

(iii) additional costs of disposal of non-contaminated spoil off site will be paid under Pay Item

R44P6;

(iv) materials from excavations for drainage and drainage structures (other than materials from

excavation for table drains and gutters) must not be included in the measurement for this Pay

Item as this is paid for under TfNSW R11;

(v) additional costs for identification, treatment and disposal of contaminated material will be paid

under Pay Item R44P8;

(vi) additional costs for foundation treatments will be paid under Pay Items R44P7.1 to R44P7.4;

Page 80: TRANSPORT FOR NSW (TfNSW) SPECIFICATION GUIDE NR44 GUIDE …

(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)

NR44 Guide to R44 Earthworks

72 Ed 2 / Rev 1

(vii) additional costs for stabilisation and imported material required in Foundation Treatment Types

E3 and C3 will be paid under TfNSW R50 and Pay Item R44P3;

(viii) additional costs for placing materials from excavations as Selected Material will be paid under

Pay Item R44P5.1;

(ix) additional costs for placing materials from excavation as verge material will be paid under Pay

Item R44P5.3;

(x) payment for incorporation into embankments of surplus material from other works under the

Contract will be included in the relevant pay items for excavation in the specifications for those

other works.

For the purposes of measurement and payment, the base of the excavation is the Foundation Level in

accordance with Clause 3.4 or as specified on the Drawings, before the removal of unsuitable material.

The sides of the excavation are the design cut batters as shown on the Drawings or as determined by

the Principal. No account will be taken of level or batter tolerances.

The volume is determined by calculation of the difference between the base of the excavation defined

in the above paragraph and the stripped surface surveyed under Clause 2.3.3. When measuring the

volume of excavations for payment, no account will be taken of the volume involved in:

(a) ripping and loosening the floor of the cutting (Foundation Treatment Type C1)

(b) loosening embankment floor (Foundation Treatment Type E1)

(c) material removed in terracing (Clause 3.3)

(d) insitu stabilising material in Foundation Treatment Type C3.

Pay Item R44P3 - Imported or Borrowed Material

This Pay Item covers all activities associated with supply and placing of imported or borrowed

material in the formation except for Selected Material, verge material and imported or borrowed

material for fill above and behind reinforced soil block (refer Specifications TfNSW R58 and TfNSW

R59).

The unit of measurement is the compacted volume of imported fill in cubic metres measured in place.

The volume is determined by calculation from the Drawings and survey. The calculation must

exclude the volumes in the Selected Material Zone, verges and zone of imported or borrowed material

for fill above and behind reinforced soil block.

Payment will include all activities associated with the opening up of the borrow site, excavation of

material from the borrow site and the construction of embankments, the supply, haulage and

placement of imported or borrowed material and any pre-treatment such as breaking down or blending

material or drying out material containing excess moisture, maintenance of the borrow site, and

restoration of the borrow site.

Payment will not be made for excess widening of embankments or wastage by you.

Pay Item R44P4 - Unsuitable Material

This Pay Item refers only to unsuitable material as defined in Clause 1.4 and described in Clause 2.4.

The unit of measurement is the cubic metre measured as bank volume of excavation. If the material is

such that the bank volume of excavation cannot be measured, the Principal will determine the

conversion factors to be applied to the loose volumes measured in haulage units or to the measured

stockpile volumes.

Page 81: TRANSPORT FOR NSW (TfNSW) SPECIFICATION GUIDE NR44 GUIDE …

(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)

Guide to R44 Earthworks NR44

Ed 2 / Rev 1 73

The schedule rate(s) under Pay Item R44P4 will include all operations involved in the excavation,

temporary stockpiling, drying out, haulage, compaction or other activity required under Clause 2.4 for

the incorporation of unsuitable material in embankments or all activities required for disposal within

the Site in accordance with clause 2.5.1.

The practicality of re-incorporation depends on why the material was removed in the first place and

on what can actually be done with it subsequently. It is unwise to insist on reincorporation under

adverse circumstances, unless there is no choice. However, low CBR material removed from cut

foundations (for instance) can readily be incorporated into general fill if it is not too wet and there is

still space for it. This is not generally suitable if it is anticipated that the material will be over wet and

drying out will be difficult. Unless it is known that the material can be easily compacted, it would be

best to spoil it.

Where the Principal directs that non-contaminated unsuitable material be disposed of off-site,

additional payment will be made for disposal under Pay Item R44P6.

Additional payment will be made under Pay Item R44P8 for identification, treatment and disposal of

contaminated unsuitable material.

When the schedule of quantities under Pay Item R44P4 provides for ranges of provisional quantities,

the rates must be applied successively, but not cumulatively, as the volume of unsuitable material

increases from one provisional quantity range to the next higher range.

Each rate must be applied for all unsuitable material removed within each quantity range, irrespective

of the nature of the material removed.

Pay Item R44P5 - Selected Material in the Selected Material Zone and Verge

Material

This pay item covers all activities associated with the identification, winning/purchasing, processing

(including blending), stockpiling (including double handling to suit you), testing, haulage, placement,

compaction and trimming of material in the Selected Material Zone and material in the verges.

This pay item covers the costs of modification of materials necessary to meet the CBR requirements of

TfNSW 3071. Should stabilisation/modification of the material be specified, other than only to meet

specified CBR requirements of imported Selected Material, payment for stabilisation will be made

under TfNSW R50.

The unit of measurement is the cubic metre measured in place in the Selected Material Zone and

verges. The width, depth and length must be taken as shown on the Drawings, and no account is taken

of the allowable placement tolerances. Where additional areas or volumes are directed by the

Principal, the volume must be determined by measurement or survey, and calculation.

Pay Item R44P5.1 - Selected Material from cuttings within the Limits of Works area

Where the material is obtained from cuttings within the Limits of Works area, the rate is an

“extra over” rate to cover any extra costs over and above those costs allowed for under Pay Item

R44P2.

Pay Item R44P5.2 - Selected Material Imported from beyond the Limits of Works area

Where the material is imported from beyond the Limits of Works area, the rate must cover all

costs (including any stabilisation required to conform to TfNSW 3071).

Page 82: TRANSPORT FOR NSW (TfNSW) SPECIFICATION GUIDE NR44 GUIDE …

(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)

NR44 Guide to R44 Earthworks

74 Ed 2 / Rev 1

Pay Item R44P5.3 - Verge Material from cuttings within the Limits of Works area

Where the material is obtained from cuttings within the Limits of Works area, the rate is an

“extra over” rate to cover any extra costs over and above those costs allowed for under Pay Item

R44P2.

Pay Item R44P5.4 - Verge Material Imported from beyond the Limits of Works area

Where the material is imported from beyond the Limits of Works area, the rate must cover all

costs.

Pay Item R44P6 - Disposal of Non-Contaminated Spoil Off Site

The schedule rate is an average rate to cover all additional costs associated with the disposal of all

types of non-contaminated material off site, except for topsoil encountered during excavation in

accordance with Clause 2.5.1.

Payment under Pay Item R44P6 is additional to payment under R44P2 or R44P4.

Payment for disposal of non-contaminated topsoil off-site will be made under Pay Item R44P1.2.

The unit of measurement is the bank cubic metre. The volume must be determined by measurement or

survey and calculation using a bulking factor proposed by you and agreed by the Principal or

otherwise determined by the Principal.

Pay Item R44P7 - Foundation Treatments

Pay Item R44P7.1 - Treatment Type E1 and Type C1 - Loosen and Recompact

The schedule rate for this Pay Item is an average rate to cover loosening the floor, terracing,

adjusting the moisture content, processing the material to achieve the specified quality

requirements, and compacting as specified. The Pay Item covers over and above those costs

allowed for under Pay Item R44P2.

The unit of measurement is the square metre.

The area must be determined by measurement, or survey, and calculation. The area must

exclude changes in designed quantities resulting from over-clearing or over-excavation, and

changes to suit you.

Pay Item R44P7.2 – Treatment Type E2 – Bridging Layer

The measured quantity of bridging layer material must exclude changes in designed quantities

resulting from excess widening of the bridging layer, and wastage or changes to suit you.

Geotextile is measured and paid in accordance with the Pay Item for Treatment Type E4

R44P7.3(a).

Pay Item R44P7.2(a) – Material obtained from excavations within the Works.

The unit of measurement must be the cubic metre in place. The quantity must be

determined by measurement, or survey, and calculation.

Page 83: TRANSPORT FOR NSW (TfNSW) SPECIFICATION GUIDE NR44 GUIDE …

(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)

Guide to R44 Earthworks NR44

Ed 2 / Rev 1 75

This Pay Item covers all activities associated with the identification, selection, winning,

processing (including breaking down), stockpiling (including double-handling to suit

you), haulage and placing of site won material in the bridging layer, over and above those

costs allowed for under Pay Item R44P2.

Pay Item R44P7.2(b) – Imported Material

The unit of measurement is the tonnes of material placed.

This Pay Item covers all activities associated with the identification, winning/purchasing,

processing (including breaking down), stockpiling (including double-handling to suit

you), testing, haulage and placing of imported material in the bridging layer.

Pay Item R44P7.3 – Treatment Type E4 and Type C4 – Geotextile and Geogrid

This Pay Item covers payment for all works associated with the use of geotextile and geogrids in

earthworks operations, including use in rock fills, and foundation treatments.

Pay Item R44P7.3(a) Geotextile

Pay Item R44P7.3(b) Geogrid

The unit of measurement is the plan square metre of each type of geotextile or geogrid

installed.

The area of geotextile or geogrid must be based on the theoretical cross-section shown on

the Drawings and the length measured in place to provide a continuous length or width of

geotextile or geogrid.

Measurement must not include the areas of laps required to provide a continuous length

or width of geotextile or geogrid.

The rate will include all specific activities required to procure and place geotextile or

geogrid.

Pay Item R44P7.4 – Treatment Type E5 and Type C5 – Drainage Layer

The costs of excavation will be included in Pay Item R44P2.

Geotextile is measured and paid in accordance with the Pay Item for Type E4 Embankment

R44P7.3(a).

The volume of drainage layer material will be included in the following rates.

Pay Item R44P7.4(a) Drainage Layer Material obtained from excavations within the

Works

This Pay Item covers all activities associated with the identification, selection, winning,

haulage, processing (including breaking down), stockpiling (including double-handling to

suit you), haulage and placing of won-on-site material in the drainage layer, over and

above those costs allowed for under Pay Item R44P2.

The unit of measurement is the cubic metre of drainage layer material placed. The

volume must be determined by specified thickness, measured area, and calculation. The

volume must exclude changes in designed quantities resulting from excess widening of

the layer, wastage, local depressions, settlement, or changes to suit you.

Page 84: TRANSPORT FOR NSW (TfNSW) SPECIFICATION GUIDE NR44 GUIDE …

(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)

NR44 Guide to R44 Earthworks

76 Ed 2 / Rev 1

Pay Item R44P7.4(b) Imported Drainage Layer Material

This Pay Item covers all activities associated with the identification, winning/purchasing,

processing (including breaking down), stockpiling (including double-handling to suit

you), testing, transportation and placing of imported material in the drainage layer.

The unit of measurement is the cubic metre of drainage layer material placed. The

volume must be determined by specified thickness, measured area, and calculation. The

volume must exclude changes in designed quantities resulting from excess widening of

the layer, wastage, local depressions, settlement, or changes to suit you.

Pay Item R44P8 - Identification, Treatment and Disposal Off Site of Contaminated

Material

NOTES TO TENDER DOCUMENTER: (Delete this boxed text after customising Pay Item R44P8)

Use Pay Item R44P8.1 where the presence of specific types of contaminated materials has been

identified during site investigation. Provide separate sub-pay items R44P8.1(a), R44P8.1(b), etc for

each type of identified contaminated material, with descriptions of the contaminated material.

Use Pay Item R44P8.2 for any potential contaminated material which have not been identified at time

of tender.

This Pay Item covers additional costs of all activities associated with the identification, classification

in accordance with OEH Waste Classification Guidelines, treatment, loading, haulage and disposal of

contaminated material at sites legally authorised to accept the contaminated material, whether the

contaminated material is topsoil, general fill or unsuitable material.

Payment under Pay Item R44P8 is additional to payment made under Pay Items R44P1.2, R44P2 or

R44P4 as applicable.

Pay Item R44P8.1 – Identified Contaminated Material

The unit of measurement is the tonne of disposed material. The quantity must be determined

using weighbridge dockets or invoices issued by the disposal facility.

Pay Item R44P8.2 – Other Contaminated Material

The Pay Item is a Provisional Sum.

Payment will be made for the costs of the activities required by Clause 2.5.2 for any

contaminated material other than those provided in Pay Item R44P8.1 plus the provisional sum

margin added in accordance with Clause 55.4 of the General Conditions of Contract.

Page 85: TRANSPORT FOR NSW (TfNSW) SPECIFICATION GUIDE NR44 GUIDE …

(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)

Guide to R44 Earthworks NR44

Ed 2 / Rev 1 77

ANNEXURE R44/C – SCHEDULES OF HOLD POINTS, WITNESS

POINTS AND IDENTIFIED RECORDS

C1 SCHEDULE OF HOLD POINTS

Clause Description

TfNSW G71

Cl 3.2

Notification of Joint Survey.

2.3.3 &

TfNSW G71

Cl 3.2

Submission of Joint Survey results.

2.4 Inspection after removal of unsuitable material and prior to backfilling.

3.2 Presentation of embankment foundation after removal of topsoil.

3.2 Presentation of CBR and PI of materials in the foundation of Shallow Embankments.

3.4 Presentation of each Lot of floor of cuttings.

4.3 Presentation of cleaned batter and bench/floor surfaces for Geotechnical inspection.

4.7.1 Submission of blasting procedure details.

Submission of altered blasting procedure details.

6.1.1 Details of material for Upper Zone of Formation (including Selected Material)

arranged by you. Submission of details of location, quantities, type and verification of

conformity. Verification that all possible onsite sources of material have been

exhausted.

6.1.2 Verification of conformity of Selected Material.

6.1.2 Verification of conformity of each Lot of Selected Material Zone with test and survey

reports.

6.2 Details of imported verge material arranged by you.

7.3 Compaction of rock fills – verification of conformity of each trial section including

submission of Compaction Routine, test results and survey reports.

7.4.2 Placing Selected Material Zone (or pavement where no Selected Material Zone is

specified) – deflection testing results, finished surface levels and verification of

conformity of the formation.

C2 SCHEDULE OF WITNESS POINTS

Clause Description

7.3 Construction of each trial section of rock fill.

7.4.1 Proof rolling of embankment layers and other surfaces within 1.5 m of the underside of

the Selected Material Zone.

7.4.2 Benkelman Beam testing of Selected Material Zone.

Page 86: TRANSPORT FOR NSW (TfNSW) SPECIFICATION GUIDE NR44 GUIDE …

(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)

NR44 Guide to R44 Earthworks

78 Ed 2 / Rev 1

C3 SCHEDULE OF IDENTIFIED RECORDS

The records listed below are Identified Records for the purposes of TfNSW Q Annexure Q/E.

Clause Description of Identified Record

2.4 Notification that unsuitable material has been removed as directed

2.3.2 Survey report of surface levels after removal of topsoil

2.3.3 Submission or survey report and notification that topsoil has been removed from

foundation for embankment

2.8.1 Details of source, location, quantities and type of Selected Material. Verification, with

test results, of conformity of material

3.2 CBR and PI test results and notification that topsoil has been removed from each

Shallow Embankment foundation

3.4.1 CBR and PI test results and notification that floor of cutting has been ripped or

loosened

4.7.1 Report of Buildings Conditions Inspection of all structures likely to be affected by any

blast

4.7.1 Blasting procedure, including quantity and type of explosives and pattern and

certification of the proposed structural survey

4.7.3 Blasting records

6.1 Proposed location, quantities and type of imported Upper Zone of Formation materials

6.1.2 Test reports of each Lot of stockpiled material for use in Selected Material Zone.

Verification of conformity of each Lot of Selected Material Zone with relevant test and

survey reports

7.4 Deflection testing results of each Lot of formation

ANNEXURES R44/D TO R44/K – (NOT USED)

Page 87: TRANSPORT FOR NSW (TfNSW) SPECIFICATION GUIDE NR44 GUIDE …

(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)

Guide to R44 Earthworks NR44

Ed 2 / Rev 1 79

ANNEXURE R44/L – TEST METHODS, MINIMUM FREQUENCY OF

TESTING AND ACCEPTANCE CRITERIA

A summary of the appropriate test methods, minimum frequencies of testing and acceptance criteria in

the earthworks construction process is given in Table R44/L.1.

Table R44/L.1 – Control of Earthworks Process

Work Sequence Reference

Clause Test Method

Minimum Frequency

Acceptance Criteria

1. Project Planning 1.5

PROJECT QUALITY PLAN TfNSW Q TfNSW Q TfNSW Q

EARTHWORKS PLAN 1.5 & 2.2 1.5 1.5

2. Clearing and Grubbing 2.3.1

Completion of clearing and grubbing TfNSW G40 Each section Complete

3. Erosion and Sedimentation Control 1.7

Installing and maintaining effective erosion and sedimentation control measures.

TfNSW G38 or G39

Inspection Each section Approved E&SC Plan

4. Setting Out of Earthworks 1.6

Establish and maintain batter profiles and Transition Zones.

1.6 TfNSW G71 Each section In place

Remove pegs at the completion of work Inspection Each section All removed

5. Stockpile Sites 2.6

Stockpile sites not shown on the Drawings - Obtain the Principal’s approval at least 10 working days in advance

2.6 Each stockpile Approval

Install erosion and sedimentation measures 2.6, TfNSW G38 or G39

Inspection Each stockpile Complete

Restoration of stockpile sites 2.6 Inspection Each stockpile TfNSW R178

6. Topsoil 2.3

6.1 Removal of Topsoil 2.3.1

Survey of stripped surfaces Hold Point

2.3.3, 1.6 TfNSW G71

6.2 Stockpiling Topsoil

Survey of stockpile sites 2.3.2, 1.6 TfNSW G71 Each stockpile TfNSW G71

Stockpile height and shape 2.3.2 Measure Each stockpile Height < 2.5m Slope < 2:1

Contents of stockpile 2.3.2 Inspection Each stockpile 2.3.2

Seeding of stockpile 2.3.2, TfNSW R178

Inspection TfNSW R178 TfNSW R178

7. Embankment Foundations 3

7.1 Preparation of Embankment Foundations 3.2

Removal of topsoil 2.3.1 Inspection Each section Complete

Stripped surface survey 1.6.3 Survey TfNSW G71 Complete

Excavate foundation to ensure a minimum height of formation

3.5.1 Survey TfNSW G71 Report

Excavated surface survey 1.6.3 Survey TfNSW G71 Report

Test Shallow Embankment for 3.5.1

- CBR R44/A2.2 1000 m2 Report

- PI R44/A2.2 1000 m2 Report

Preparation of each Lot of embankment foundation Hold Point

3.2 Each section Complete

7.2 Unsuitable Material 2.4

Page 88: TRANSPORT FOR NSW (TfNSW) SPECIFICATION GUIDE NR44 GUIDE …

(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)

NR44 Guide to R44 Earthworks

80 Ed 2 / Rev 1

Work Sequence Reference

Clause Test Method

Minimum Frequency

Acceptance Criteria

Removal of unsuitable material Hold Point

2.4 Inspection Each Lot Complete

Replacement of unsuitable material 2.4 Inspection Each Lot Complete

- Compaction 5.1 TfNSW T111, T119, T162, T166, T173

TfNSW Q Table R44.11

- Moisture content 5.1 TfNSW T120, T121, T180

TfNSW Q R44/A5

7.3 Loosen and Compact (E1) 3.2.1

Authorisation given 3.2.1 Each section Authorised

Ripping depth & extent 3.2.1 Inspection Each section 3.2.1

- Compaction 7.2 TfNSW T111, T119, T162, T166, T173

TfNSW Q Table R44.11

- Moisture content 7.2 TfNSW T120, T121, T180

TfNSW Q R44/A5

7.4 Use of Bridging Layer (Treatment Type E2) 3.2.2

Authorisation given 3.2.2 Each section Authorised

Material suitability 3.2.2 Inspection Each section 3.2.2

Bridging layer placed 3.2.2 Inspection Each section 3.2.2

7.5 Use of Chemical Stabilisation (Treatment Type E3) 3.2.3

Authorisation given 3.2.3 Each section Authorised

Foundation stabilised 3.2.3 TfNSW R50 TfNSW R50 TfNSW R50

7.6 Use of Geotextile or Geogrid (Treatment Type E4) 3.2.4

Authorisation given 3.2.4 Each section Authorised

Material suitability 3.2.4 TfNSW R63, R67

TfNSW R63, R67

TfNSW R63, R67

Geotextile or geogrid installation 3.2.4 TfNSW R63, R67

TfNSW R63, R67

TfNSW R63, R67

7.7 Use of Drainage Layer (Treatment Type E5) 3.2.5

Authorisation given 3.2.5 Each section Authorised

Material Suitability:

- Grading 3.2.5 AS Sieve 200 m3 3.2.5

- Point Load Strength of rock 3.2.5 TfNSW T223 200 m3 R44/A2.2

- Wet/Dry Strength Variation 3.2.5 TfNSW T215 Each source R44/A2.2

Drainage layer placed 3.2.5 Inspection Each section Complete

7.8 Use of Foundation Treatment Type E6 3.2.6

8. Cuttings 3.4, 4

8.1 Preparation of Cutting Area

Removal of topsoil 2.3.1 Inspection Each section Complete

Stripped surface survey 1.6.3 TfNSW G71 Each section Report

8.2 Excavation 4.2

Material loosened and broken down such that it can be incorporated into the Works, meeting the requirements for:

2.1, 2.2, 4.2 Inspection & Audit

Materials available and conform

- Rock facing of batters 5.5

- Placing adjacent to weepholes 5.6.2

- Select Fill adjacent to structures 5.6.3

- Upper Zone of Formation 6.1.1

Page 89: TRANSPORT FOR NSW (TfNSW) SPECIFICATION GUIDE NR44 GUIDE …

(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)

Guide to R44 Earthworks NR44

Ed 2 / Rev 1 81

Work Sequence Reference

Clause Test Method

Minimum Frequency

Acceptance Criteria

- Transition Zone 3.5.2

- Selected Material Zone 6.1.2

- Verge 6.2

- Backfill in cuttings 3.4.2

- Other treatments 6.3

- Earth fill 5.2

- Rock fill 5.3

- Bridging layers 3.2.2

- Drainage layers 3.2.5, 3.4.5

- Working platforms 3.2.3, 3.4.3

Protection of earthworks 1.7 Inspection Daily 1.7

8.3 Batters 4.4

Batters conform to specification tolerances 4.4 Survey Each batter Table R44.3

Tops and ends of cuttings treated 4.2 Inspection Each batter 4.2

Rock cuttings cleaned down Hold Point

4.3 Inspection Each batter 4.3

Batter stabilisation works 4.3 As directed As directed As directed

Treatment of batters 4.2 As directed As directed 4.2

8.4 Benching in Cuttings 4.5

Benches must conform to tolerances and drain 4.5 Survey Each bench 7.5

8.5 Blasting 4.7

Obtaining of licences and meeting regulatory requirements

4.7.1 Before blasting starts

AS 2187 Parts I & II

Conducting Building Condition Inspection 4.7.1 Inspection TfNSW G35 or G36 Clause 6.8

TfNSW G35 or G36 Clause 6.8

Implement and maintain a community liaison program 4.7.1 Monitor Each blast TfNSW G35 or G36 Clause 6.8

Presplitting of batters with slopes 1:1 Drill hole spacing

4.6

Measure

Each blast

4.6

Start of each blasting operation – submit details Hold Point

4.7.1 Each blast Details OK

Control airblast 4.7.4 AS2187.2 Each blast Annex R44/A6

Control ground vibration 4.7.5 AS2187.2 Each blast Annex R44/A6

Blasting records 4.7.3 Inspection Each blast Submitted on day of blast

8.6 Cut/Fill Transition 3.5.2

Survey and mark the position of the intersection line between cutting and embankment occurring at the underside of the Selected Material Zone

1.6.1 Survey Each transition Report

Excavate a Transition Zone 3.5.2 Survey Each transition 3.5.2 & R44/A4

Excavated terrace should be made free-draining 3.5.2 Inspection Each transition Drainage achieved

9. Foundation Treatments for Cuttings 3.4

9.1 Preparation of Cutting Foundations 3.4

Removal of topsoil 2.3.1 Inspection Each section Complete

Excavate cutting to Designed Floor Level 3.4 Survey TfNSW G71 7.5

Test cutting floor for: 3.4

- CBR R44/A2.2 1000 m2 R44/A2.2

Page 90: TRANSPORT FOR NSW (TfNSW) SPECIFICATION GUIDE NR44 GUIDE …

(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)

NR44 Guide to R44 Earthworks

82 Ed 2 / Rev 1

Work Sequence Reference

Clause Test Method

Minimum Frequency

Acceptance Criteria

- PI R44/A2.2 1000 m2 R44/A2.2

Preparation of each Lot of cutting foundation Hold Point

3.4 Each section Complete

9.2 Unsuitable Material 2.4

Removal of unsuitable material Hold Point

2.4 Inspection Each Lot Complete

Replacement of unsuitable material 2.4 Inspection Each Lot Complete

- Compaction 7.2 TfNSW T111, T119, T162, T166, T173

TfNSW Q Table R44.11

- Moisture content 7.2 TfNSW T120, T121, T180

TfNSW Q R44/A5

9.3 Loosen and Compact (Treatment Type C1) 3.4.1

Authorisation given 3.4.1 Each section Authorised

Ripping depth and extent and particle size 3.4.1 Inspection 1000 m2 3.4.1

- Compaction 7.2 TfNSW T111, T119, T162, T166, T173

TfNSW Q Table R44.11

- Moisture content 7.2 TfNSW T120, T121, T180

TfNSW Q R44/A5

9.4 Excavation and Backfill (Treatment Type C2) 3.4.2

Authorisation given 3.4.2 Each section Authorised

Excavate cutting to Foundation Level 3.4.2 Survey TfNSW G71 7.5

Loosen and compact as above 3.4.2, 3.4.1

Backfill material suitability: 3.4.2

- CBR R44/A2.2 500 m3 R44/A2.2

- PI R44/A2.2 500 m3 R44/A2.2

Compaction of backfill 7.2 TfNSW T111, T119, T162, T166, T173

TfNSW Q Table R44.11

Moisture content of backfill 7.2 TfNSW T120, T121, T180

TfNSW Q R44/A5

Trimming of backfill 3.4.2 Survey TfNSW G71 7.5

9.5 Use of Working Platform (Treatment Type C3) 3.4.3

Authorisation given 3.4.3 Each section Authorised

Foundation stabilised 3.4.3 TfNSW R50 TfNSW R50 TfNSW R50

Trimming of working platform 3.4.3 Survey TfNSW G71 7.5

9.6 Use of Geotextile or Geogrid (Treatment Type C4) 3.4.4

Authorisation given 3.4.4 Each section Authorised

Material suitability 3.4.4 TfNSW R63, R67

TfNSW R63, R67

TfNSW R63, R67

Geotextile or geogrid installation 3.4.4 TfNSW R63, R67

TfNSW R63, R67

TfNSW R63, R67

9.7 Use of Drainage Layer (Treatment Type C5) 3.4.5

Authorisation given Each section Authorised

Excavate cutting to Foundation Level 3.4.5 Survey TfNSW G71 7.5

Material Suitability:

- Grading 3.4.5 AS Sieve 200 m3 3.4.5

- Point Load Strength of Rock 3.4.5 TfNSW T223 200 m3 R44/A2.2

- Wet/Dry strength variation 3.4.5 TfNSW T215 Each source R44/A2.2

Page 91: TRANSPORT FOR NSW (TfNSW) SPECIFICATION GUIDE NR44 GUIDE …

(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)

Guide to R44 Earthworks NR44

Ed 2 / Rev 1 83

Work Sequence Reference

Clause Test Method

Minimum Frequency

Acceptance Criteria

Drainage layer placed 3.4.5 Inspection Each section 3.4.5, 7.3

Trimming of drainage layer 3.4.5 Survey TfNSW G71 7.5

9.8 Use of Other Foundation Treatment Types 3.4.6

10. Embankments 5

10.1 Embankment Materials 2.2, 5

Site won earth fill material: 5.2

- Deleterious materials and homogeneity 5.2 Inspection Each Lot 5.2

- Particle dimensions 5.2 AS Sieve 1000 m3 5.2

Rock fill material: 5.3

- Maximum particle dimension 5.3.2 AS Sieve 5.3.2

- Point load strength 5.3.2 TfNSW T223 500 m3 R44/A2.2

- Wet/Dry strength variation 5.3.2 TfNSW T215 Each source R44/A2.2

Rock fill capping layer material: 5.3.3

- Maximum particle dimension 5.3.3 AS Sieve 5.3.3

- Point load strength 5.3.3 TfNSW T223 500 m3 R44/A2.2

- Wet/Dry strength variation 5.3.3 TfNSW T215 Each source R44/A2.2

10.2 Borrow Sites and Imported Materials 2.7, 2.8, 6

Source of imported fill 2.7 Identify source(s)

10 days prior to commencing work at each source

Approvals for source

Delivery of imported materials Hold Point

6.1.1, 6.2 6.1.1, 6.2 Each source R44/A2

Survey to determine quantity of imported materials placed in the Works

1.6.3, 6.1.1, 6.2

Survey Each site for imported materials

TfNSW G71

Site preparation of borrow sites 2.7.1 Inspection Each borrow site

2.7.1, TfNSW G40

Location and shape of borrow sites 2.7.2 Inspection Each borrow site

2.7.2, R44/A2.1

Restoration of borrow sites 2.7.1 Inspection Each borrow site

TfNSW R178

10.3 Earth Fill Construction 5.2

Placing earth fill for embankment construction:

- Layer thickness 5.2 Measure Each Lot 5.2

- Lot homogeneity 5.1 Inspection Each Lot 5.2

- Compaction TfNSW T111, T119, T162, T166, T173

TfNSW Q Table R44.11

- Moisture TfNSW T120, T121, T180

TfNSW Q R44/A5

Hillside embankment foundations 3.3 Inspection Each earthworks Lot

Terraced as per 3.3

Protection of earthworks 1.7 Inspection Daily 1.7

Placing earth fill at “spill-through” bridge abutment zone: 5.2.1 5.2.1

- Width and height of zone 5.2.1 Measure Each Lot 5.2.1

- Earth fill material:

▪ Grading 5.2.1 AS sieve 400 m3 5.2.1

▪ CBR 5.2.1 R44/A2.2 400 m3 5.2.1

▪ PI 5.2.1 R44/A2.2 400 m3 5.2.1

Page 92: TRANSPORT FOR NSW (TfNSW) SPECIFICATION GUIDE NR44 GUIDE …

(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)

NR44 Guide to R44 Earthworks

84 Ed 2 / Rev 1

Work Sequence Reference

Clause Test Method

Minimum Frequency

Acceptance Criteria

- Layer thickness 5.2.1 Measure Each Lot 5.2.1

- Lot homogeneity 5.1 Inspection Each Lot 5.2.1

- Compaction 5.2.1 TfNSW T111, T119, T162, T166, T173

TfNSW Q Table R44.11

- Moisture TfNSW T120, T121, T180

TfNSW Q R44/A5

10.4 Rock Fill Construction

Placing rock fill for embankment construction

- Trial sections Witness Point / Hold Point

7.3 7.3 Each trial section

7.3

- Layer thickness 5.3 Measure Each Lot 5.3

- Lot homogeneity 5.1 Inspection Each Lot 5.3.1

- Compaction Witness Point

7.3 Inspection & Proof Roll

Each Lot 7.3, 7.4.1

Hillside embankment foundations 3.3 Inspection Each earth-works Lot

Terraced as per 3.3

Placing rock fill capping layer for embankment construction

- Trial sections Witness Point / Hold Point

7.3 7.3 Each trial section

7.3

- Layer thickness 5.3.3 Measure Each Lot 5.3.3

- Lot homogeneity 5.1 Inspection Each Lot 5.3.3

- Compaction Witness Point

7.3 Inspection & Proof Roll

Each Lot 7.3, 7.4.1

Geotextiles:

- Material suitability 5.3.5 TfNSW R63 TfNSW R63 TfNSW R63

- Geotextile or geogrid installation 5.3.5 TfNSW R63 TfNSW R63 TfNSW R63

Protection of earthworks 1.7 Inspection Daily 1.7

10.5 Embankment Batters 5.4

Batters conform to specification tolerances 5.4 Survey Each batter 5.4

Batters free of loose material 5.4 Inspection Each batter 5.4

Treatment of batters 5.4 As directed As directed 5.4

10.6 Rock Facing 5.5

Rock facing material: 5.5

- Maximum particle dimension 5.5 AS Sieve 5.5

- Point load strength 5.5 TfNSW T223 500 m3 R44/A2.2

- Wet/Dry strength variation 5.5 TfNSW T215 Each source R44/A2.2

Placing Rock Facing for embankment construction 5.5 Inspection Each section 5.5

10.7 Fill adjacent to Structures 5.6

Materials 5.6.1 TfNSW R11, R22, B30

TfNSW R11, R22, B30

TfNSW R11, R22, B30

Placing fill adjacent to structures:

- Width & height 5.6.3 Measure Each Lot Table R44.9

- Layer thickness 5.6.3 Measure Each Lot 5.6.3

- Lot homogeneity 5.6.3 Inspection Each Lot 5.6.3

- Compaction 5.6.3 TfNSW T111, T119, T162, T166, T173

TfNSW Q Table R44.11

Page 93: TRANSPORT FOR NSW (TfNSW) SPECIFICATION GUIDE NR44 GUIDE …

(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)

Guide to R44 Earthworks NR44

Ed 2 / Rev 1 85

Work Sequence Reference

Clause Test Method

Minimum Frequency

Acceptance Criteria

- Moisture 5.6.3 TfNSW T120, T121, T180

TfNSW Q R44/A5

Treatment at weepholes:

- Materials 5.6.2 AS Sieve 10 m3 5.6.2

- Placement 5.6.2 Measure Each Lot 5.6.2

- Synthetic membrane 5.6.2 Inspection Each Lot Manufacturer’s Spec

11. Structural Treatments

11.1 Material in the Upper Zones of Formation other than Selected Material Zone

2.8.2

Site won 2.8.2.1

- Maximum particle dimension (where applicable) 2.8.2.1 AS Sieve 1000 m3 2.8.2.1

- Minimum CBR value 2.8.2.1 R44/A2.2 1000 m3 R44/A2.2

- Maximum PI value 2.8.2.1 R44/A2.2 1000 m3 R44/A2.2

Imported 2.8.2.2

- Maximum particle dimension (where applicable) 2.8.2.1 AS Sieve 1000 m3 2.8.2.1

- Minimum CBR value 2.8.2.2 R44/A2.2 1000 m3 R44/A2.2

- Maximum PI value 2.8.2.2 R44/A2.2 1000 m3 R44/A2.2

11.2 Material in the Selected Material Zone 2.8.3

Site won 2.8.3.1

- Maximum particle dimension (where applicable) 2.8.3.1 AS Sieve 1000 m3 2.8.3.1

- Minimum CBR value 2.8.3.1 R44/A2.2 1000 m3 R44/A2.2

- Maximum PI value 2.8.3.1 R44/A2.2 1000 m3 R44/A2.2

Imported 2.8.3.2 TfNSW 3071 TfNSW 3071 TfNSW 3071

11.3 Material in Verges 2.8.4

Site won 2.8.4.1

- Maximum particle dimension and grading 2.8.4.1 AS Sieve 1000 m3 2.8.4.1

- Minimum CBR value 2.8.4.1 R44/A2.2 1000 m3 R44/A2.2

- Maximum PI value 2.8.4.1 R44/A2.2 1000 m3 R44/A2.2

Imported 2.8.4.2 TfNSW 3071 TfNSW 3071 TfNSW 3071 (Type B) & R44/A2.2

11.4 Placing Material for Upper Zone of Formation Hold Point

6.1.1

- Layer thickness 6.1.1 Measure Each Lot R44/A4

- Compaction 6.1.1 TfNSW T111, T119, T162, T166, T173

TfNSW Q Table R44.11

- Moisture 6.1.1 TfNSW T120, T121, T180

TfNSW Q R44/A5

11.5 Placing Material in the Selected Material Zone 6.1.2

- Layer thickness 6.1.2 Measure Each Lot R44/A4

- Compaction 6.1.2 TfNSW T111, T119, T162, T166, T173

TfNSW Q Table R44.11

- Moisture 6.1.2 TfNSW T120, T121, T180

TfNSW Q R44/A5

Verification of conformity for covering Hold Point

6.1.2 Reports Each Lot, Table R44.10

6.1.2

11.6 Placing Fill for Verges 6.2

- Layer thickness 6.2 Measure Each Lot R44/A4

Page 94: TRANSPORT FOR NSW (TfNSW) SPECIFICATION GUIDE NR44 GUIDE …

(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)

NR44 Guide to R44 Earthworks

86 Ed 2 / Rev 1

Work Sequence Reference

Clause Test Method

Minimum Frequency

Acceptance Criteria

- Compaction 6.2 TfNSW T111, T119, T162, T166, T173

TfNSW Q Table R44.11

- Moisture 6.2 TfNSW T120, T121, T180

TfNSW Q R44/A5

11.7 Other Treatments 6.3

12. Deflection Testing 7.4

Proof rolling Witness Point

7.4.1 TfNSW T198 7.4.1 7.4.1

Benkelman Beam testing at underside of the Selected Material Zone. Hold Point

7.4.2 TfNSW T199 R44/A4 7.4.2, R44/A4

Benkelman Beam testing at top of the Selected Material Zone. Witness Point / Hold Point

7.4.2 TfNSW T199 R44/A4 7.4.2, R44/A4

13. Level Control 7.5

Surface levels of Selected Material Zone, formation, floor of cutting, drainage layer, working platform, cut/fill transitions, benches in cuttings, rock fill and verges

7.5.1 Survey TfNSW G71 7.5.1

Median areas 7.5.3 Survey TfNSW G71 7.5.3

14. Spoil 2.5

14.1 Non-contaminated Materials 2.5.1

Authorisation given within the site 2.5.1 Each location Authorised

Authorisation given for off site 2.5.1

10 days prior to commencing work at each location

Approvals provided & authorised

Compaction 2.5.1 TfNSW T111, T119, T162, T166, T173

TfNSW Q Table R44.11

14.2 Contaminated Materials 2.5.2

Method & location of disposal 2.5.2 Submission Each source/ location

TfNSW G35 or G36

Page 95: TRANSPORT FOR NSW (TfNSW) SPECIFICATION GUIDE NR44 GUIDE …

(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)

Guide to R44 Earthworks NR44

Ed 2 / Rev 1 87

ANNEXURE R44/M – REFERENCED DOCUMENTS

TfNSW Specifications

TfNSW G1 Site Specific Requirements

TfNSW G10 Traffic Management

TfNSW G35 or G36 Environmental Protection

TfNSW G38 or G39 Soil and Water Management

TfNSW G40 Clearing and Grubbing

TfNSW G71 Construction Surveys

TfNSW Q Quality Management System

TfNSW B30 Excavation and Backfill for Bridgeworks

TfNSW R11 Stormwater Drainage

TfNSW R22 Corrugated Metal Structures

TfNSW R33 Trench Drains

TfNSW R50 Stabilisation of Earthworks

TfNSW R58 or R59 Construction of Reinforced Soil Walls

TfNSW R63 Geotextiles (Separation and Filtration)

TfNSW R67 High Strength Geosynthetic Reinforcement

TfNSW R178 Vegetation

TfNSW 3071 Selected Material for Formation

TfNSW Test Methods

TfNSW T102 Pretreatment of Samples of Road Materials by Compaction

TfNSW T103 Pretreatment of Road Materials by Artificial Weathering

TfNSW T105 Preparation and Division of Samples for Testing

TfNSW T108 Liquid Limit of Road Materials

TfNSW T109 Plastic Limit and Plasticity Index of Road Materials

TfNSW T111 Dry Density/Moisture Relations of Road Materials (Standard Compaction)

TfNSW T117 California Bearing Ratio of Remoulded Specimens of Road Materials

TfNSW T119 Determination of Density of Road Materials insitu using the Sand Replacement

Method

TfNSW T120 Determination of Moisture Content of Road Materials (Standard Method)

TfNSW T121 Determination of Moisture Content of Road Materials (Sand Bath or Hot Plate

Method)

TfNSW T131 Determination of Unconfined Compressive Strength of Road Materials

Stabilised or modified with Proportions of Cement Lime or Other Cementitious

Materials

TfNSW T160 Benkelman Beam Deflection Test

Page 96: TRANSPORT FOR NSW (TfNSW) SPECIFICATION GUIDE NR44 GUIDE …

(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)

NR44 Guide to R44 Earthworks

88 Ed 2 / Rev 1

TfNSW T162 Compaction Control Test (Rapid Method)

TfNSW T166 Determination of Relative Compaction

TfNSW T173 Determination of Field Wet Density of Pavement Materials using a Nuclear

Gauge in Direct Transmission Mode

TfNSW T180 Determination of Moisture Content of Road Materials (Microwave Oven

Method)

TfNSW T198 Proof Rolling Test

TfNSW T199 Deflection Monitoring Test

TfNSW T215 Wet/Dry Strength Variation

TfNSW T223 Point Load Strength of Rock Specimens, Field Method

Australian Standards

AS 1289.3.8.1 Methods of testing soils for engineering purposes – soil classification tests –

Dispersion – Determination of Emerson class number of a soil

AS 2187 Parts 1 and 2. Explosives – Storage, transport and use

AS 3725 Loads on buried concrete pipes

Other References

NAASRA Explosives in Roadworks Users Guide 1982

ANZECC Technical Basis for Guidelines to Minimise Annoyance due to

Blasting Overpressure and Ground Vibration

Page 97: TRANSPORT FOR NSW (TfNSW) SPECIFICATION GUIDE NR44 GUIDE …

(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)

Guide to R44 Earthworks NR44

Ed 2 / Rev 1 89

(Note: Next 2 clauses to be added as an amendment to this Specification only in appropriate

situations)

4.7.4 Control of Airblast

This Clause will apply only where a noise sensitive location exists within 1 km of the blasting site.

Comply with the criteria recommended in the “ANZECC Technical Basis for Guidelines to Minimise

Annoyance Due to Blasting Overpressure and Ground Vibration (ANZECC)”. The Measurement

process for determining verification of compliance with the ANZECC criteria is to be in accordance

with "AS 2187.2 Explosives - Storage, Transport and Use, Appendix J - Ground Vibration and

Airblast (Informative)".

The noise emanating from blasting operations must not exceed the limits in Annexure R44/A6 at any

noise sensitive location, measured at the noise monitoring location nearest to the noise sensitive

location.

Provide and operate equipment for the monitoring of airblast to ensure compliance with the specified

limits. All monitoring must be carried out by personnel possessing current NATA accreditation for

such monitoring unless approved otherwise by the Principal. Equipment used for monitoring must be

calibrated annually by a recognised testing facility. All test results must be reported on test certificates

which must include a clear statement as to compliance or non-compliance with the requirements of

this Specification. In general, a monitoring location will be near the perimeter of the noise sensitive

location at the point closest to the maximum charge. Provide a copy of the monitoring record to the

Principal.

In the event that the measured airblast exceeds the specified limits, suspend further blasting work and

take additional steps and precautions to ensure that, for any future blast, the limiting airblast must not

be exceeded. Do not resume any blasting until details of the additional steps and precautions have

been provided to the Principal.

4.7.5 Control of Ground Vibration

Provide and operate equipment for the monitoring of ground vibrations to ensure compliance with

Annexure R44/A6. All monitoring must be carried out by personnel possessing current NATA

accreditation for such monitoring unless approved otherwise by the Principal. The measurement

process for determining verification of compliance with the ANZECC criteria is to be in accordance

with AS 2187.2.

Equipment used for monitoring must be calibrated annually by a NATA accredited testing facility or

manufacturer’s facility approved by the Principal. All test results must be reported on test certificates,

which must include a clear statement as to compliance or non-compliance with the requirements of

this Specification. In general, a monitoring location will be near the perimeter of the structure or

building at the point closest to the maximum charge. Provide a copy of the monitoring record to the

Principal.

To minimise the risk of peak particle velocity limits being exceeded, develop a blasting site

relationship between peak particle velocity, distance and blasting charge.

For the first blast, monitors must be set up at not less than five points at varying distances away from

the blasting site. The Maximum Instantaneous Charge for the first blast must not exceed that

calculated from the following formula:

Page 98: TRANSPORT FOR NSW (TfNSW) SPECIFICATION GUIDE NR44 GUIDE …

(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)

NR44 Guide to R44 Earthworks

90 Ed 2 / Rev 1

where MIC = Maximum Instantaneous Charge in kilograms

D = Distance in metres from charge to the point of potential damage

p.p.v = limiting peak particle velocity from Annexure R44/A6

For subsequent blasts, the charge weight and other aspects of blast design may be adjusted provided

that further ground vibration monitoring is undertaken and the blasting site relationship re-determined

to demonstrate that charge weight limits are not exceeded. Make the graphs available to the Principal,

if so requested.

MIC 0.5

D

p p v. . ..

1140

0 625

2