202
NATIONAL POWER TRANSMISSION CORPORATION SOUTHERN POWER PROJECT MANAGEMENT BOARD TRANSMISSION EFFICIENCY PROJECT DD2-10-001B SUB-PROJECT REHABILITATION AND UPGRADING OF PHU LAM – CAI LAY 2 220KV TRANSMISSION LINE RESETTLEMENT PLAN (FINAL DRAFT) February, 2014 Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized

TRANSMISSION EFFICIENCY PROJECT DD2-10-001B · SOUTHERN POWER PROJECT MANAGEMENT BOARD TRANSMISSION EFFICIENCY PROJECT DD2-10-001B SUB-PROJECT REHABILITATION AND UPGRADING OF PHU

  • Upload
    others

  • View
    10

  • Download
    0

Embed Size (px)

Citation preview

Page 1: TRANSMISSION EFFICIENCY PROJECT DD2-10-001B · SOUTHERN POWER PROJECT MANAGEMENT BOARD TRANSMISSION EFFICIENCY PROJECT DD2-10-001B SUB-PROJECT REHABILITATION AND UPGRADING OF PHU

NATIONAL POWER TRANSMISSION CORPORATION SOUTHERN POWER PROJECT MANAGEMENT BOARD TRANSMISSION EFFICIENCY PROJECT

DD2-10-001B SUB-PROJECT REHABILITATION AND UPGRADING OF PHU LAM – CAI LAY 2 220KV TRANSMISSION LINE RESETTLEMENT PLAN (FINAL DRAFT) February, 2014

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

wb371432
Typewritten Text
RP1560 V7 REV
wb371432
Typewritten Text
wb371432
Typewritten Text
Page 2: TRANSMISSION EFFICIENCY PROJECT DD2-10-001B · SOUTHERN POWER PROJECT MANAGEMENT BOARD TRANSMISSION EFFICIENCY PROJECT DD2-10-001B SUB-PROJECT REHABILITATION AND UPGRADING OF PHU

NATIONAL POWER TRANSMISSION CORPORATION SOUTHERN VIETNAM POWER PROJECT MANAGEMENT BOARD

TRANSMISSION EFFICIENCY PROJECT

DD2-10-001B

SUB-PROJECT REHABILITATION AND UPGRADING OF

PHU LAM – CAI LAY 2 220KV TRANSMISSION LINE

RESETTLEMENT PLAN

POWER ENGINEERING CONSULTING SOUTHERN POWER PROJECT JOINT STOCK COMPANY 2 MANAGEMENT BOARD 32 Ngo Thoi Nhiem, Ward 7 No.610, Vo Van Kiet Ave, Cau Kho Ward District 3, Ho Chi Minh City District 1, Ho Chi Minh City

Page 3: TRANSMISSION EFFICIENCY PROJECT DD2-10-001B · SOUTHERN POWER PROJECT MANAGEMENT BOARD TRANSMISSION EFFICIENCY PROJECT DD2-10-001B SUB-PROJECT REHABILITATION AND UPGRADING OF PHU

Rehabilitation and Upgrading of Phu Lam – Cai Lay 2 220kV Transmission line Resettlement Plan

Owner: Southern Vietnam Power Project Management Board – EVNNPT Page 1 Prepared by: Power Engineering Consulting JS. Company 2

INTRODUCTION AND PROVISIONS OF REPORT

Resettlement Plan (RP) of the subproject Rehabilitation and Upgrading of Phu Lam – Cai Lay 2 220kV transmission line in Investment Project stage shall be provided in a single volume.

Page 4: TRANSMISSION EFFICIENCY PROJECT DD2-10-001B · SOUTHERN POWER PROJECT MANAGEMENT BOARD TRANSMISSION EFFICIENCY PROJECT DD2-10-001B SUB-PROJECT REHABILITATION AND UPGRADING OF PHU

Rehabilitation and Upgrading of Phu Lam – Cai Lay 2 220kV Transmission line Resettlement Plan

Owner: Southern Vietnam Power Project Management Board – EVNNPT Page 2 Prepared by: Power Engineering Consulting JS. Company 2

Abbreviations and Definitions

Abbreviations are applied on the principles:

- Using popular abbreviations

Eg: PC: People’s Committee, CRC: Compensation and Resettlement Council

- Using the shortest form for particular phrases

Eg : RP: Resettlement Plan

APs: Affected People by the sub-project

APs : Affected Persons by the sub-project

AHs : Affected Households

DP : Displaced People

GOV : Government

TL : Transmission Line

TEP : Transmission Efficiency Project

ROW : Right of Way

PC : People’s Committee

VND : Vietnamese Dong

WB : World Bank

DC : The ending point

DD : The starting point

PTC4 : Power Transmission Company 4

EVNNPT : National Power Transmission Corporation

EVN : Vietnam Electricity

HH : Household

SPMB : Southern Vietnam Power Project Management Board

ODA : Official Development Assistance

PMB : Project Management Board

Page 5: TRANSMISSION EFFICIENCY PROJECT DD2-10-001B · SOUTHERN POWER PROJECT MANAGEMENT BOARD TRANSMISSION EFFICIENCY PROJECT DD2-10-001B SUB-PROJECT REHABILITATION AND UPGRADING OF PHU

Rehabilitation and Upgrading of Phu Lam – Cai Lay 2 220kV Transmission line Resettlement Plan

Owner: Southern Vietnam Power Project Management Board – EVNNPT Trang 3 Prepared by: Power Engineering Consulting JS. Company 2

Table of Content

SUMMARY ..................................................................................................................... 6

1. INTRODUCTION ............................................................................................. 8 1.1. Transmission Efficiency Project (TEP) ......................................................................... 8

1.2. Subproject “Rehabilitation and Upgrading of Phu Lam – Cai Lay 2 220kV Transmission Line” .............................................................................................................. 9

1.2.1. Scope of the Subproject .......................................................................................... 9

1.2.2. Impact Scope of Subproject .................................................................................... 9

1.2.3. Technical Specification of Transmission Line ..................................................... 10

1.3. Objectives of Resettlement Plan .................................................................................. 11

2. IMPACTS OF THE SUBPROJECT ............................................................. 13

2.1. Determination of Subproject’s Impacts ....................................................................... 13

2.1.1. Determination of Affected Area/Scope of the Subproject: ................................... 13

2.1.2. Determination of Affected People of the Subproject ............................................ 13

2.2. Impact Types of the Subproject ................................................................................... 17

2.2.1. Permanently Affected Land .................................................................................. 17

2.2.2. Temporarily Affected land.................................................................................... 18

2.2.3. Impacts on Plants, Farm Produce and Domestic Animal .................................... 19

2.2.4. Affected houses and works in the ROW ............................................................... 21

3. LEGAL FRAMEWORK AND COMPENSATION POLICIES....... ......... 23 3.1. Legal Framework ......................................................................................................... 23

3.1.1. Vietnam’s Policies ................................................................................................ 23

3.1.2. World Bank’s Policies .......................................................................................... 25

3.1.3. Compatibility between policies of Government and the World Bank and necessary exemptions ..................................................................................................... 25

3.2. Principle of Compensation Applied for the Subproject ............................................... 27

3.2.1. General Principles ............................................................................................... 27

3.2.2. Policies for compensation, Support and Resettlement Applied to the Subproject 29

4. COMPENSATION, ASSISTANCE AND RESETTLEMENT .................. 30 4.1. Compensation .............................................................................................................. 30

4.1.1. Compensation Unit Prices for Land .................................................................... 31

4.1.2. Compensation Unit Price for Crops, Plant, Domestic Animal ............................ 32

4.2. Assistance .................................................................................................................... 33

4.2.1. Assistance with Occupational Change and Job Creation .................................... 33

Page 6: TRANSMISSION EFFICIENCY PROJECT DD2-10-001B · SOUTHERN POWER PROJECT MANAGEMENT BOARD TRANSMISSION EFFICIENCY PROJECT DD2-10-001B SUB-PROJECT REHABILITATION AND UPGRADING OF PHU

Rehabilitation and Upgrading of Phu Lam – Cai Lay 2 220kV Transmission line Resettlement Plan

Owner: Southern Vietnam Power Project Management Board – EVNNPT Trang 4 Prepared by: Power Engineering Consulting JS. Company 2

4.2.2. For Agricultural Land in Residential Area .......................................................... 34

4.2.3. Assistance with Production Stability .................................................................... 35

4.2.4. Assistance with Renovation of Roof and Roof Earthing of Houses in the ROW .. 35

5. PUBLIC CONSULTATION AND PEOPLE PARTICIPATION.... .......... 35 5.1. Public Consultation and People Participation .............................................................. 35

5.2. Information Disclosure ................................................................................................ 53

5.3. Complaints and Grievances ......................................................................................... 53

6. REPORT, SUPERVISION/MONITORING AND EVALUATION .. ........ 55 6.1. Internal Monitoring and Supervision ........................................................................... 55

6.2. Independent Monitoring .............................................................................................. 57

6.3. Reporting ..................................................................................................................... 57

7. IMPLEMENTATION PLAN ........................................................................ 58

7.1. Implementation responsibility ..................................................................................... 58

7.2. Implementation Schedule ............................................................................................ 60

7.2.1. Proposed Schedule of the Subproject ................................................................... 60

7.2.2. Proposed Schedule of RP ..................................................................................... 61

8. COST AND BUDGET .................................................................................... 63

8.1. Budget .......................................................................................................................... 63

8.2. Costs of RP Implementation ........................................................................................ 63

8.2.1. Cost of RP Preparation ........................................................................................ 63

8.2.2. Cost of Compensation, Assistance ....................................................................... 63

8.2.3. Cost for Compensation Council (Management Cost) .......................................... 68

8.2.4. Cost for Independent Monitoring ......................................................................... 68

8.2.5. Contingency Cost ................................................................................................. 68

8.3. Total Estimated Cost for RP’s Implementation ........................................................... 68

Page 7: TRANSMISSION EFFICIENCY PROJECT DD2-10-001B · SOUTHERN POWER PROJECT MANAGEMENT BOARD TRANSMISSION EFFICIENCY PROJECT DD2-10-001B SUB-PROJECT REHABILITATION AND UPGRADING OF PHU

Rehabilitation and Upgrading of Phu Lam – Cai Lay 2 220kV Transmission line Resettlement Plan

Owner: Southern Vietnam Power Project Management Board – EVNNPT Trang 5 Prepared by: Power Engineering Consulting JS. Company 2

List of tables

Table 1.1: Scope of the acquired land area for tower foundation construction

Table 2.1: Statistics of affected households

Table 2.2: The number of people affected by the subproject – allocating according to locations

Table 2.3: The total of affected people according to affected types

Table 2.4: The area of permanently affected land (for constructing tower foundation)

Table 2.5: The area of temporary affected

Table 2.6: Plants, crops and domestic animal affected on permanent occupied land

Table 2.7: Plants and crops affected in ROW

Table 2.8: Affected houses and works in ROW

Table 3.1: Differences between National Laws and the World Bank Policy and the TEP Policy

Table 4.1: Compensation unit prices and assistance of permanently affected land

Table 4.2: Unit price for plants, crops, domestic animal applied for compensation

Table 4.3: Unit price for occupational change and job creation

Table 4.4: Assistance for agriculture in the residential region, garden land and land with pond without recognizing as a residential land

Table 4.5: Unit price for supporting manufacturing stability

Table 5.1: Summary of People’s Opinion in the Public Consultation Meetings

Table 6.1: Some main activities for internal monitoring and evaluation

Table 7.1: Proposed implementation schedule of the subproject

Table 7.2: Proposed implementation schedule of RP

Table 8.1: Compensation estimated cost for the subproject

Table 8.2: Total estimated cost for RP’s implementation

Appendices

1. Map of site area

2. Entitlement matrix

3. Subproject’s site agreement

4. Minutes and pictures of public consultation meeting

5. Statistics on number of APs by the subproject

Page 8: TRANSMISSION EFFICIENCY PROJECT DD2-10-001B · SOUTHERN POWER PROJECT MANAGEMENT BOARD TRANSMISSION EFFICIENCY PROJECT DD2-10-001B SUB-PROJECT REHABILITATION AND UPGRADING OF PHU

Rehabilitation and Upgrading of Phu Lam – Cai Lay 2 220kV Transmission line Resettlement Plan

Owner: Southern Vietnam Power Project Management Board – EVNNPT Page 6 Prepared by: Power Engineering Consulting JS. Company 2

SSUUMM MM AARRYY

The subproject “Rehabilitation and Upgrading of Phu Lam – Cai Lay 2 220kV Transmission line” is a component of the Transmission Efficiency Project (TEP). The subproject construction will be implemented in the areas of twenty three (23) communes under the management of seven (07) districts of Ho Chi Minh city and provinces of Long An and Tien Giang.

The subproject consists of three main works:

(i) Maintaining the original status from Phu Lam 500kV substation to tower G1 with 2,824 m in length;

(ii) stringing 23,627 m of wire on the towers of the Phu Lam – O Mon 500kV transmission line from tower G1 to G7;

(iii) upgrading the current 45,378 m single-circuit to a double-circuit from tower G7 to Cai Lay 220kV substation.

The route will be upgraded from single-circuit into double-circuit at tower G7 to Cai Lay 220kV substation, which will extend over the area of eighteen communes under the management of four districts of Long An and Tien Giang provinces as follows:

Long An province:

- Nhi Thanh and Binh Thanh communes of Thu Thua district;

- Huong Phu Tho commune, ward 2, 4, 6 and Khanh Hau ward of Tan An city;

Tien Giang province:

- Tan Huong, Tan Ly Tay, Tan Ly Dong, Tan Hiep, Than Cuu Nghia, Tam Hiep, Long Dinh, Nhi Binh and Diem Hy communes of the Chau Thanh district.

- Tan Hoi and Nhi My communes of Cai Lay district.

The proposed construction period of the subproject is twelve months (excluding period of clearance and compensation) as of the commencement date which is tentatively proposed in the second Quarter of 2014.

The subproject will affect 595 households (2,485 persons), five organizations, namely Vocational Training College of Long An province, Ly Tu Trong High school, Long An Teacher Training College, Tan Huong Industrial Zone and Vietnam Institute of Seed Sciences in eighteen communes of the four districts of Long An and Tien Giang provinces. However, due to the nature of this subproject being the upgrading works of the existing Phu Lam – Cai Lay 2 220kV transmission line; so the number of households directly affected by the subproject is only 126 households out of the above 595 households; these directly households will be considered for further compensation in this subproject due to their land being permanently acquired for construction of 126 new tower foundations. The remaining households only locate in the existing ROW and they shall comply with power safety regulations in the existing transmission line; and they will temporarily affect during the process of stringing wire. The area of permanently acquired land of the affected households ranges from 2.06% to 96.60% of the total land area that they possess. Details are as bellows:

- AHs with over 20% (or over 10% for vulnerable households) of cultivated land being permanently acquired: 66 households (290 persons)

- AHs with less than 20% (or less than 10% for vulnerable households) of cultivated land being permanently acquired: 47 households (208 persons)

Page 9: TRANSMISSION EFFICIENCY PROJECT DD2-10-001B · SOUTHERN POWER PROJECT MANAGEMENT BOARD TRANSMISSION EFFICIENCY PROJECT DD2-10-001B SUB-PROJECT REHABILITATION AND UPGRADING OF PHU

Rehabilitation and Upgrading of Phu Lam – Cai Lay 2 220kV Transmission line Resettlement Plan

Owner: Southern Vietnam Power Project Management Board – EVNNPT Page 7 Prepared by: Power Engineering Consulting JS. Company 2

- AHs with crops being permanently affected: 111 households (492 persons)

- AHs with cultivated land being temporarily affected: 595 households (2,485 persons)

- AHs with crops being temporarily affected: 446 households (1,867 persons)

Notes:

In the permanently acquired land for construction of tower foundations, there are five towers located in public land under the ownership of the Government; so there is no compensation for this land area. The data in this report excluded the land of these five towers.

Permanently acquired land area at tower foundation locations of the subproject is 38,828.2 m2, in which, cultivation land constitutes of 89.6% of total permanent acquisition land area and residential land 2.8% only.

Temporarily affected land area in the ROW of the subproject is 847,234 m2, in which, cultivation and residential land account for 82.9% and 17.1% respectively.

This resettlement plan is prepared based on the WB’s OP 4.12 Involuntary Resettlement (OP 4.12) and the Resettlement Policy Framework (RPF) of the Transmission Efficiency Project.

Land acquisition and compensation activities are expected to start in the first Quarter of 2014 with an estimated budget of 56,326,229,934 VND. The budget shall be reviewed and updated at the early stage of subproject implementation to ensure the compensation at replacement cost. Budget for RP’s implementation will be from reciprocal funds of EVNNPT.

Page 10: TRANSMISSION EFFICIENCY PROJECT DD2-10-001B · SOUTHERN POWER PROJECT MANAGEMENT BOARD TRANSMISSION EFFICIENCY PROJECT DD2-10-001B SUB-PROJECT REHABILITATION AND UPGRADING OF PHU

Rehabilitation and Upgrading of Phu Lam – Cai Lay 2 220kV Transmission line Resettlement Plan

Owner: Southern Vietnam Power Project Management Board – EVNNPT Page 8 Prepared by: Power Engineering Consulting JS. Company 2

1. INTRODUCTION

1.1. Transmission Efficiency Project (TEP)

1. The National Power Transmission Cooperation (NPT) is developing Efficient Transmission Project (TEP) with funding from the World Bank (WB). The Project Development Objective (PDO) for TEP is to support the implementation of an investment programs to increase capacity of Vietnam’s electricity transmission grid, improve efficiency and reliability of electricity services and strengthen the institutional capacity of the National Power Transmission Company. The direct beneficiary of the project would be Vietnam’s electricity transmission company NPT. Indirect beneficiaries would include all segments of population. They would benefit from: (i) Improved reliability, which will reduce unserved demand and the number and duration of power outages; and (ii) Increased energy efficiency, which will reduce overall costs and GHG emissions. The project would also bring direct temporary benefits for skilled and unskilled workers that would be employed for the construction of the project. The proposed project is comprised of the following three components:

(a) The Transmission Infrastructure Component will finance transmission lines and substations at voltage levels of 220kV and 500kV. The investments will target three areas that are key to the overall economic development of Vietnam, namely the Greater Hanoi Area, the Greater Ho Chi Minh City Area and the Mekong Delta. Investments at the 500kV level will help increase the transport capacity of the main 500kV trunk system while increasing its reliability. Investments at the 220kV level are aimed at increasing the capacity of the supply points to the distribution utilities and improve the reliability of the network that serves these points.

(b) The Smart Grid Component will support modernization of monitoring, control, and protection equipment in 500kV and 220kV substations to improve the reliability of the interconnected power system as a whole and of some bulk-supply points in the distribution network. Today, 60 percent of the faults in substations are a consequence of faulty operations of monitoring, control, and protection equipment. Aided by monitoring and control gear, protection equipment: (i) detects - among other things - the locations and intensity of faults and, based on such information, determines what equipment should be disconnected to protect the system from damage; and (ii) decides when disconnected equipment should be reconnected to ensure that interruptions in the provision of electricity services are minimized.

(c) The Capacity Building and Institutional Strengthening Component will contribute to the gradual development of NPT to become an independent transmission company with revenues from the application of cost-of-service regulation in the transmission sector. The steps to be supported in this operation include the definition of technical and financial performance indicators, the introduction of enterprise asset management systems and strategies.

Component No.1 and a part of component No.2 will be implemented by three Project Management Boards of EVNNPT; component No.3 and a part of component No.2 will be implemented by EVNNPT and Electricity Regulatory Authority of Vietnam (ERAV). In this project, the land acquisition is mainly in the subprojects of the component No.1. The RP of this subproject is prepared in accordance with the Resettlement Policy Framework for Transmission Efficiency Project.

Page 11: TRANSMISSION EFFICIENCY PROJECT DD2-10-001B · SOUTHERN POWER PROJECT MANAGEMENT BOARD TRANSMISSION EFFICIENCY PROJECT DD2-10-001B SUB-PROJECT REHABILITATION AND UPGRADING OF PHU

Rehabilitation and Upgrading of Phu Lam – Cai Lay 2 220kV Transmission line Resettlement Plan

Owner: Southern Vietnam Power Project Management Board – EVNNPT Page 9 Prepared by: Power Engineering Consulting JS. Company 2

1.2. Subproject “Rehabilitation and Upgrading of Phu Lam – Cai Lay 2 220kV Transmission Line”

1.2.1. Scope of the Subproject

The subproject will be constructed within the boundaries of twenty three communes under the management of the seven districts of Ho Chi Minh city and provinces of Long An and Tien Giang. (Refer to appendix 4: Map of site area).

The subproject will be implemented to achieve the objective of (i) upgrading the existing transmission line that has been in operation for many years and with the technical and safety conditions being degraded; (ii) strengthening the transmission capacity, power network connection capacity and stabilizing the power system in the southern-west region in accordance with the National Power Development Plan for 2011-2020, considering in 2030; and (iii) creating a double-circuit axis line with high capacity to transfer electrical power from Phu Lam 500/220kV substation to Cai Lay 220kV substation in order to replace the Phu Lam – Cai Lay 1 and 2 220kV transmission line.

The scope of subproject consists of three main items:

(i) Maintaining the original status from Phu Lam 500kV substation to tower G1 with 2,824 m in length;

(ii) Stringing 23,627 m of wire on the towers of the Phu Lam – O Mon 500kV transmission line from tower G1 to G7;

(iii) Upgrading the current 45,378 m single-circuit to a double-circuit from tower G7 to Cai Lay 220kV substation.

1.2.2. Impact Scope of Subproject

Impact on land is only found at item (iii) Upgrading the current 45,378 m single-circuit to a double-circuit from tower G7 to Cai Lay 220kV substation; the works of item (iii) consist of (a) rebuilding new tower No.9B at the same position to connect to Phu Lam – O Mon 500kV transmission line; b) stringing 7,270 m of double-circuit wire on trible-circuit tower of Phu Lam – O Mon 500/220kV transmission line, section from G1 to G4; c) stringing 16,360 m of single circuit on trible-circuit tower of Phu Lam – O Mon 500/220kV transmission line, section from G4 to G7; d) upgrading the current 3,220 m single-circuit to a double-circuit from G7 to DC1 to Long An substation; e) upgrading the current 34,770 m single-circuit to a double-circuit from Long An substation to DD2 to My Tho substation; f) upgrading the current 7,400 m single-circuit to a double-circuit from My Tho substation to DC2 to Cai Lay substation; and g) upgrading two 220kV bays of 500/220kV My Tho substation (being connected from Cai Lay 220kV substation) of Long An 220kV substation. This section extends over the territory of eighteen communes.

The subproject construction of 126 tower foundations will permanently acquire 39.088,75 m2 land area; in which 38,828.2 m2 (for construction of 121 tower foundations) and 260,55m2 (for construction of 5 tower foundations) located in the land under the ownership of the local people and the Government, respectively. There is no compensation for the land area owned by the Government and the remaining land areas will be considered as further compensation and support by the owner if these acquired land areas were not compensated in the existing transmission line. Scope of the permanent land acquisition for the tower foundation construction of the subproject is as follows:

Page 12: TRANSMISSION EFFICIENCY PROJECT DD2-10-001B · SOUTHERN POWER PROJECT MANAGEMENT BOARD TRANSMISSION EFFICIENCY PROJECT DD2-10-001B SUB-PROJECT REHABILITATION AND UPGRADING OF PHU

Rehabilitation and Upgrading of Phu Lam – Cai Lay 2 220kV Transmission line Resettlement Plan

Owner: Southern Vietnam Power Project Management Board – EVNNPT Page 10 Prepared by: Power Engineering Consulting JS. Company 2

Table 1.1: Scope of the acquired land area for tower foundation construction

No Location Area (m2) I Long An province 13,341.00

1.1 Thu Thua district 3,874.25

1.1.1 Nhi Thanh commune 1,758.75

1.1.2 Binh Thanh commune 2,115.50

1.2 Tan An city 9,466.75

1.2.1 Huong Tho Phu commune 2,315.60

1.2.2 Ward 6 451.00

1.2.3 Ward 2 1,051.00

1.2.4 Ward 4 2,815.45

1.2.5 Khanh Hau ward 2,833.70

II Tien Giang province 25,487.20 2.1 Chau Thanh district 20,854.60

2.1.1 Tan Huong commune 3,221.20

2.1.2 Tan Ly Tay commune 1,111.30

2.1.3 Tan Ly Dong commune 873.30

2.1.4 Tan Hiep town 305.30

2.1.5 Than Cuu Nghia commune 3,301.50

2.1.6 Tam Hiep commune 2,695.75

2.1.7 Long Dinh commune 5,383.55

2.1.8 Nhi Binh commune 1,491.90

2.1.9 Diem Hy commune 2,470.80

2.2 Cai Lay district 4,632.60

2.2.1 Tan Hoi commune 1,846.90

2.2.2 Nhi My commune 2,785.70

Total 38,828.20

1.2.3. Technical Specification of Transmission Line

Upgrading of Phu Lam – Cai Lay 2 220kV transmission line has the technical specification as follows:

- Voltage level : 220kV.

- The number of circuits

: double-circuit

- The starting point : Gate tower at 220kV switchyard of the existing Phu Lam 500kV substation

- The ending point : Gate tower at 220kV switchyard of the existing Cai Lay 220kV substation

- The length of route : 71.83 km, in which:

+ Maintaining the original status as the existing section: 2.82

Page 13: TRANSMISSION EFFICIENCY PROJECT DD2-10-001B · SOUTHERN POWER PROJECT MANAGEMENT BOARD TRANSMISSION EFFICIENCY PROJECT DD2-10-001B SUB-PROJECT REHABILITATION AND UPGRADING OF PHU

Rehabilitation and Upgrading of Phu Lam – Cai Lay 2 220kV Transmission line Resettlement Plan

Owner: Southern Vietnam Power Project Management Board – EVNNPT Page 11 Prepared by: Power Engineering Consulting JS. Company 2

km.

+ Stringing double-circuit: 7.27 km.

+ Stringing single-circuit: 16.36 km.

+ Upgrading single-circuit into double-circuit: 45.38 km.

- Conductor : ACSR wire, 795MCM, marking Cuckoo (equivalent 400/51 ACSR wire) at sections: stringing wire on combined tower of 500-220kV triple-circuit of the existing Phu Lam – O Mon 500kV transmission line and section from My Tho substation to DC2 and to Cai Lay substation.

: Aluminum conductor steel-reinforced, 2xACSR - bundle conductor, 666.6MCM, marking Flamingo (equivalent 330/43 ACSR wire) for section from tower G7 to DC1 of Long An substation.

: Aluminum conductor steel-reinforced, 3xACSR-bundle conductor 666.6MCM, marking Flamingo for section from section Long An substation to DD2 and to My Tho substation.

- Earth wire : Using the two earth wires, including AWG 7No16AWG and OPGW 90 (12 optical fibers under the standard of ITU – T/G.655) for section from G7 to Long An substation.

: Using the two earth wires, including AACSR 147.1 wire, marking Pastel 147.1 and OPGW 120 (12 optical fibers under the standard of ITU – T/G.652) for section from Long An substation to Cai Lay substation.

- Insulator : 220kV composite for section to string single-circuit and double-circuit on tower of triple-circuit of Phu Lam – O Mon 500kV transmission line.

: Using kind of glass or ceramic for load of 70kN, 120kN, 160kN and 210kN.

- Tower : Steel tower with double-circuit, which is manufactured by hot dip galvanizing of steel tower, attached by bolts.

- Foundation : Plate foundation, made by in-situ reinforced concrete..

- Grounding : Φ12 radial galvanizing round bar.

1.3. Objectives of Resettlement Plan

The resettlement plan is set up in line with the following objectives:

• Involuntary resettlement must be avoided where possible, or be reduced to the lowest possible extent by selecting appropriate design options.

• In the event that involuntary resettlement is unavoidable, resettlement activities shall be prepared and executed in accordance with sustainable development programs; and providing appropriate assistance and investments, and helping AHs to benefit from the sub-project. AHs will be thoroughly advised and allowed to participate in the preparation and execution of the Resettlement Plan;

Page 14: TRANSMISSION EFFICIENCY PROJECT DD2-10-001B · SOUTHERN POWER PROJECT MANAGEMENT BOARD TRANSMISSION EFFICIENCY PROJECT DD2-10-001B SUB-PROJECT REHABILITATION AND UPGRADING OF PHU

Rehabilitation and Upgrading of Phu Lam – Cai Lay 2 220kV Transmission line Resettlement Plan

Owner: Southern Vietnam Power Project Management Board – EVNNPT Page 12 Prepared by: Power Engineering Consulting JS. Company 2

• AHs must be supported in terms of their capacity to improve their living conditions and to rehabilitate their living standards higher than or at least equal to that before constructing the subproject.

Page 15: TRANSMISSION EFFICIENCY PROJECT DD2-10-001B · SOUTHERN POWER PROJECT MANAGEMENT BOARD TRANSMISSION EFFICIENCY PROJECT DD2-10-001B SUB-PROJECT REHABILITATION AND UPGRADING OF PHU

Rehabilitation and Upgrading of Phu Lam – Cai Lay 2 220kV Transmission line Resettlement Plan

Owner: Southern Vietnam Power Project Management Board - EVNNPT Page 13 Prepared by: Power Engineering Consulting JS. Company 2

2. IMPACTS OF THE SUBPROJECT

2.1. Determination of Subproject’s Impacts

2.1.1. Determination of Affected Area/Scope of the Subproject:

As mentioned earlier, the subproject extends over 23 communes/wards of Ho Chi Minh city and in provinces of Long An and Tien Giang. Economic and welfare conditions are diversified through the length of the route; most of the businesses being agricultural production, orchards, small business and other small-scale industrial households. The subproject is not located near or in the environmental sensitive areas such as: cultural heritage; natural reserves and their buffer zone; wetlands; forests and estuary etc. therefore the implementation of the subproject shall not impact the sensitive areas in environment. Other impacts of subproject are recognized and assessed as follows:

a) Impact on crossing infrastructure: The location of the transmission line shall affect some infrastructure works, houses, fields and gardens of residents during upgrading. However, at crossing locations, there are methods to ensure safety, minimize damages for activities of residents under ROW.

b) Impact on land acquisition: The total area of land that is permanently occupied is 39,088.75 m2. On average, a tower foundation requires an area of 312.71 m2. In centralized residential area, foundations will be coincidently constructed with the centerline of existing foundations to minimize land acquisition impact. The area of permanent occupied land at each location of foundation is very low in comparison with the farmland area; therefore, impact on society and economy due to compensation, land acquisition is not muchIn the project area, no physical relocation is required due to the subproject’s impacts. The sub-project only affects the following areas:

- Location of tower foundations of the upgrading transmission line.

- Temporarily impact in surrounding area of the tower foundation during the construction process.

- Temporarily affected area due to stringing wire with an average width of 22 meters, the route is only calculated at area of cultivation land. The land area can be affected from 1 to 2 months.

Temporary land acquisition for the access road in the construction is not necessary because the existing domestic roads, alleys, lanes and ROW shall be used in the construction period.

2.1.2. Determination of Affected People of the Subproject

a) Determination of Affected People and Eligbility Criteria

Subproject Affected People:

The Phu Lam – Cai Lay 2 T/L subproject has only impacts covered in paragraph 3a (items ii, iii) of OP 4.12. People directly affected by this sub-project include:

- Persons whose agricultural land will be affected (permanently or temporarily) by the Project;

- Persons whose residential land/houses will be affected (permanently or temporarily) by the Project;

- Persons whose leased-houses will be affected (permanently or temporarily) by the Project;

Page 16: TRANSMISSION EFFICIENCY PROJECT DD2-10-001B · SOUTHERN POWER PROJECT MANAGEMENT BOARD TRANSMISSION EFFICIENCY PROJECT DD2-10-001B SUB-PROJECT REHABILITATION AND UPGRADING OF PHU

Rehabilitation and Upgrading of Phu Lam – Cai Lay 2 220kV Transmission line Resettlement Plan

Owner: Southern Vietnam Power Project Management Board - EVNNPT Page 14 Prepared by: Power Engineering Consulting JS. Company 2

- Persons whose businesses, occupations. or places of work will be affected (permanently or temporarily) by the Project;

- Persons whose crops (annual and perennial)/ trees will be affected in part or in total by the Project;

- Persons whose other assets or access to those assets, will be affected in part or in total by the Project; and

Identification of vulnerable groups or Households (HHs):

Vulnerable groups include those distinct groups of people who might suffer disproportionately or face the risk of being marginalized by the effects of resettlement, and specifically include:

- Poor and very poor household as identified by regulations of Government of Vietnam.

- Ethnic Minority Household.

- Household covered by Decree 67/2007/ND-CP of April 13th, 2007 on support policies for social protection beneficiaries and Decree 13/2010/ND-CP of February 27th, 2010 amending and supplementing a number of articles of the Government's Decree No. 67/2007/ND-CP.

Eligbility Criteria:

The eligibility for obtaining entitlements to compensation is generally built upon three concepts relating to asset ownership as follows:

(i) Those who have formal legal rights to land (including customary and traditional rights recognized under the laws of the country) – in the instance, it is also useful to document how long they have been using the land or the assets associated with it;

(ii) Those who do not have formal legal rights to land at the time the census begins but have a claim to such land or assets, provided that such claims are recognized under the laws of the country or become recognized through a process identified in the resettlement plan;

(iii) Those who have no recognizable legal right or claim to the land they are occupying.

Persons covered under (i) and (ii) are provided compensation for the land they lose, and other assistance. Persons covered under (iii) are provided resettlement assistance in lieu of compensation for the land they occupy, and other assistance, as necessary, to achieve the objectives set out in this policy, if they occupy the project area prior to a cut-off date established by the borrower and acceptable to the Bank. Persons who encroach on the area after the cut-off date are not entitled to compensation or any other form of resettlement assistance. All persons included in (i), (ii), or (iii) are provided compensation for loss of owned or used assets other than land.

b) Number of Affected People or Organizations or Households

1. Affected Organization

- Vocational training college of Long An province (305.25 m2 housing land at the dormitory are permanently affected.);

- Ly Tu Trong High School (305.25 m2 permanently affected);

- Long An training teacher college (369 m2 permanently affected);

- Tan Huong Industrial Zone (1,152 m2 of agricultural land permanently affected);

- Vietnam Institute of Seed Sciences (305.25 m2 of agricultural land, fruit – tree land permanently affected).

Page 17: TRANSMISSION EFFICIENCY PROJECT DD2-10-001B · SOUTHERN POWER PROJECT MANAGEMENT BOARD TRANSMISSION EFFICIENCY PROJECT DD2-10-001B SUB-PROJECT REHABILITATION AND UPGRADING OF PHU

Rehabilitation and Upgrading of Phu Lam – Cai Lay 2 220kV Transmission line Resettlement Plan

Owner: Southern Vietnam Power Project Management Board - EVNNPT Page 15 Prepared by: Power Engineering Consulting JS. Company 2

2. Affected Households and People

According to the survey result, 595 households (2,485 people) are affected by the subproject in which 113 households (498 people) have impact on land of . The level of land acquisition impact (at household level) ranges from 2.06% to 96.60% of their total landholding area. Affected people include:

- People whose land is permanently revoked for tower foundation area;

- People whose cultivated land or residential land are affected temporarily in ROW;

- People whose perennial trees and /or crops are temporarily affected in ROW;

- People whose perennial trees and / or crops are temporarily affected in ROW.

None of the affected households fall into the definition of vulnerable groups as defined in the RPF of the TEP. All households losing more than 70% have another source of income from non-agricultural activities. Their residental land is not affected by the subproject. Main activities of this subproject is to rehabilitate the current transmission line. Tower foundations will be constructed in the same place of the existing tower foundation to minimize loss of land. In this subproject, there is no physical relocation required. The result is presented in the following tables (see details in Appendix 5: The inventory of people affected by the subproject):

Table 2.1: Statistics of affected households

No Classification Households People

1 Permanently affected

AHs with more than 20% (or over 10% for vulnerable households) of the total cultivated land being permanently acquired.

66 290

AHs with less than 20% (or less than 10% for vulnerable

households) of the total cultivated land being permanently acquired

47 208

AHs with more than 70% of the total cultivated land being permanently revoked

5 19

AHs with permanently affected crops 111 492

The total permanently affected people 113 498

2 Temporarily affected

AHs with temporarily affected cultivated land 595 2.485

AHs with temporarily affected crops 446 1.867

The total of temporarily affected people 595 2.485

Notes: The household whose land is permanently affected by the transmission lines, they are also temporarily affected.

Table 2.2: The number of people affected by the subproject – allocating according to locations

Page 18: TRANSMISSION EFFICIENCY PROJECT DD2-10-001B · SOUTHERN POWER PROJECT MANAGEMENT BOARD TRANSMISSION EFFICIENCY PROJECT DD2-10-001B SUB-PROJECT REHABILITATION AND UPGRADING OF PHU

Rehabilitation and Upgrading of Phu Lam – Cai Lay 2 220kV Transmission line Resettlement Plan

Owner: Southern Vietnam Power Project Management Board - EVNNPT Page 16 Prepared by: Power Engineering Consulting JS. Company 2

No Location Households with acquired land Households with

affected land in ROW Households People Households People

I Long An province 34 146 227 956 1.1 Thu Thua district 13 55 24 96

1.1.1 Nhi Thanh 8 35 16 64

1.1.2 Binh Thanh 5 20 8 32

1.2 Tan An city 21 91 203 860

1.2.1 Huong Tho Phu 4 20 26 130

1.2.2 Ward 6 1 3 36 108

1.2.3 Ward 2 2 12 29 174

1.2.4 Ward 4 7 26 82 328

1.2.5 Khanh Hau ward 7 30 30 120

II Tien Giang province 79 352 368 1529 2.1 Chau Thanh district 60 257 321 1294

2.1.1 Tan Huong 7 31 51 204

2.1.2 Tan Ly Tay 3 12 49 196

2.1.3 Tan Ly Dong 3 9 29 87

2.1.4 Tan Hiep 1 4 2 8

2.1.5 Than Cuu Nghia 10 41 69 276

2.1.6 Tam Hiep 9 40 44 176

2.1.7 Long Dinh 14 63 43 215

2.1.8 Nhi Binh 5 16 19 57

2.1.9 Diem Hy 8 41 15 75

2.2 Cai Lay district 19 95 47 235

2.2.1 Tan Hoi 9 47 24 120

2.2.2 Nhi My 10 48 23 115

Total 113 498 595 2,485

Notes: The above statistics collected from the survey conducted in May – June of 2013 shall be checked in the stage of measurement and inventory after landmark;

Table 2.3: The total of affected people according to affected types

No Affected types Households People

1 Temporary acquisition of productive land in ROW 446 1.867

2

Temporary impact on residential and garden land. Partial house/building within ROW and the demolished area does not impact to the remaining house/building. Residential land and garden land outside of the ROW is sufficient for re-organizing (not less than 60 m2).

205 868

3 Permanent acquisition of land for tower foundation. 113 498

Page 19: TRANSMISSION EFFICIENCY PROJECT DD2-10-001B · SOUTHERN POWER PROJECT MANAGEMENT BOARD TRANSMISSION EFFICIENCY PROJECT DD2-10-001B SUB-PROJECT REHABILITATION AND UPGRADING OF PHU

Rehabilitation and Upgrading of Phu Lam – Cai Lay 2 220kV Transmission line Resettlement Plan

Owner: Southern Vietnam Power Project Management Board - EVNNPT Page 17 Prepared by: Power Engineering Consulting JS. Company 2

Notes: Details about benefits of APs, compensation policies, terms applied to impact types refer Appendix 2. Entitlement Matrix

2.2. Impact Types of the Subproject

Impact types for AHs in this subproject only include:

- Permanently acquired cultivation land (including areas of rice/crop, annual tree, fruit tree and garden land) due to construction of tower foundation.

- Temporarily acquired cultivation land (including areas of rice/crop, garden land) in construction process of each position of tower foundation.

- Permanently affected crops (including rice, annual plants) and plants in the area of tower foundation construction;

- Temporarily affected crops (rice, farm produce) surrounding tower foundation, plants in the ROW of stringing wire.

- Impact on trees in the ROW, trees with the distance of less than 4 meters from the tree tops to the lowest conducting wire will be cut down (as identified in Article 5, Decree No. 106/2005/ND-CP dated 17/8/2005).

- Impact on houses and buildings in the ROW, it is allowable that houses and buildings be located in the ROW of transmission line, but their roofsand walls must be of nonflammable materials. Metal structure must be grounded, and distance from any part of house, building to the nearest wire at the maximum sag state is not less than 6m (as identified in Article 1, Decree No. 81/2009/ND-CP dated 12/10/2009)

2.2.1. Permanently Affected Land

Table 2.4: The area of permanently affected land (for constructing tower foundation)

No Locations Total

area (m2)

Total permanently affected area (m2)

Rice Other annual tree

Fruit tree

Pond Residential land

Industrial land

Other land

I Long An province 13,341.00 6,538.55 891.00 1,498.60 1,537.00 1,093.55 0.00 1,782.30

1.1 Thu Thua district 3,874.25 3,189.25 280.00 405.00 0.00 0.00 0.00 0.00

1.1.1 Nhi Thanh 1,758.75 1,.353.75 0.00 405.00 0.00 0.00 0.00 0.00

1.1.2 Binh Thanh 2,115.50 1,835.50 280.00 0.00 0.00 0.00 0.00 0.00

1.2 Tan An city 9,466.75 3,349.30 611.00 1,093.60 1,537.00 1,093.55 0.00 1,782.30

1.2.1 Huong Tho Phu 2,315.60 1,271.30 288.00 0.00 0.00 305.30 0,00 451.00

1.2.2 Ward 6 451.00 0.00 0.00 0.00 45.00 0.00 0.00 0.00

1.2.3 Ward 2 1,051.00 0.00 0.00 0.00 280.00 483.00 0.00 288.00

1.2.4 Ward 4 2,815.45 305.30 323.00 1,093.60 483.00 305.25 0.00 305.30

1.2.5 Khanh Hau ward 2,833.70 1,772.70 0.00 0.00 323.00 0.00 0.00 738.00

II Tien Giang province

25,487.20 9,455.85 0.00 14,384.35 495.00 0.00 1,152.00 0.00

2.1 Chau Thanh district 20,854.60 6,948.15 0.00 12,754.45 0.00 0.00 1,152.00 0.00

2.1.1 Tan Huong 3,221.20 1,763.90 0.00 305.30 0.00 0.00 1,152.00 0.00

2.1.2 Tan Ly Tay 1,111.30 788.30 0.00 323.00 0.00 0.00 0.00 0.00

Page 20: TRANSMISSION EFFICIENCY PROJECT DD2-10-001B · SOUTHERN POWER PROJECT MANAGEMENT BOARD TRANSMISSION EFFICIENCY PROJECT DD2-10-001B SUB-PROJECT REHABILITATION AND UPGRADING OF PHU

Rehabilitation and Upgrading of Phu Lam – Cai Lay 2 220kV Transmission line Resettlement Plan

Owner: Southern Vietnam Power Project Management Board - EVNNPT Page 18 Prepared by: Power Engineering Consulting JS. Company 2

No Locations Total area (m2)

Total permanently affected area (m2)

Rice Other annual tree

Fruit tree

Pond Residential land

Industrial land

Other land

2.1.3 Tan Ly Dong 873.30 288.00 0.00 585.30 0.00 0.00 0.00 0.00

2.1.4 Tan Hiep 305.30 0.00 0.00 305.30 0.00 0.00 0.00 0.00

2.1.5 Than Cuu Nghia 3,301.50 628.30 0.00 2,673.20 0.00 0.00 0.00 0.00

2.1.6 Tam Hiep 2,695.75 1,797.15 0.00 898.60 0.00 0.00 0.00 0.00

2.1.7 Long Dinh 5,383.55 0.00 0.00 5,383.55 0.00 0.00 0.00 0.00

2.1.8 Nhi Binh 1,491.90 0.00 0.00 1,491.90 0.00 0.00 0.00 0.00

2.1.9 Diem Hy 2,470.80 1,682.50 0.00 788.30 0.00 0.00 0.00 0.00

2.2 Cai Lay district 4,632.60 2,507.70 0.00 1,629.90 495.00 0.00 0.00 0.00

2.2.1 Tan Hoi 1,846.90 1,644.40 0.00 202.50 0.00 0.00 0.00 0.00

2.2.2 Nhi My 2,785.70 863.30 0.00 1,427.40 495.00 0.00 0.00 0.00

Total 38,828.20 15.994,40 891.00 15,882.95 2,032.0

0 1,093.55 1,152.00 1,782.30

2.2.2. Temporarily Affected land

Temporarily affected land is the one in the boundary of the ROW line except the permanently affected land for constructing tower foundation and public land area (road, river etc.)

Table 2.5: The area of temporary affected

No Locations Total area (m2)

Affected land types in ROW (m2)

Rice Crops Fruit tree

Residential are -

garden Grass

I Long An province 267,612 148,718 1,056 43,020 74,817 0

1.1 Thu Thua district 60,668 47,213 0 13,455 0 0

1.1.1 Nhi Thanh 48,885 37,075 0 11,810 0 0

1.1.2 Binh Thanh 11,783 10,138 0 1,645 0 0

1.2 Tan An city 206,944 101,506 1,056 29,565 74,817 0

1.2.1 Huong Tho Phu 42,516 27,653 0 0 14,863 0

1.2.2 Ward 6 10,709 6,797 0 0 3,912 0

1.2.3 Ward 2 25,357 13,823 0 0 11,533 0

1.2.4 Ward 4 62,009 36,604 0 1,737 23,668 0

1.2.5 Khanh Hau ward 66,354 16,629 1,056 27,828 20,840 0

II Tien Giang province 579,623 159,897 67,672 281,334 69,642 1,078

2.1 Chau Thanh district 476,044 96,134 59,849 257,796 62,266 0

2.1.1 Tan Huong 105,743 20,653 2,309 59,003 23,779 0

2.1.2 Tan Ly Tay 31,870 6,069 706 17,820 7,274 0

2.1.3 Tan Ly Dong 16,794 3,049 994 9,123 3,627 0

Page 21: TRANSMISSION EFFICIENCY PROJECT DD2-10-001B · SOUTHERN POWER PROJECT MANAGEMENT BOARD TRANSMISSION EFFICIENCY PROJECT DD2-10-001B SUB-PROJECT REHABILITATION AND UPGRADING OF PHU

Rehabilitation and Upgrading of Phu Lam – Cai Lay 2 220kV Transmission line Resettlement Plan

Owner: Southern Vietnam Power Project Management Board - EVNNPT Page 19 Prepared by: Power Engineering Consulting JS. Company 2

No Locations Total area (m2)

Affected land types in ROW (m2)

Rice Crops Fruit tree

Residential are -

garden Grass

2.1.4 Tan Hiep 4,288 285 1,328 2,201 474 0

2.1.5 Than Cuu Nghia 44,900 2,358 13,937 23,627 4,977 0

2.1.6 Tam Hiep 46,607 1,258 14,255 26,003 5,091 0

2.1.7 Long Dinh 129,551 6,026 20,244 93,236 10,044 0

2.1.8 Nhi Binh 36,364 15,653 3,319 14,699 2,692 0

2.1.9 Diem Hy 59,930 40,782 2,757 12,083 4,308 0

2.2 Cai Lay district 103,578 63,764 7,823 23,538 7,376 1,078

2.2.1 Tan Hoi 55,106 37,113 2,516 11,545 3,932 0

2.2.2 Nhi My 48,472 26,651 5,306 11,993 3,444 1,078

Total 847,234 308,616 68,728 324,354 144,458 1,078

Affected land in the ROW has been existed in the previous ROW, cultivation activities and other activities on land in the ROW have adapted and matched with the existence of the previous transmission line. When the transmission line is rehabilitated and upgraded, impacts on the ROW will be reduced, because the designed transmission line follows the current electrical standard and relevant Governmental regulations, by which the height of line hanging is elevated, especially in residential areas. Land use in the ROW shall be better after the transmission line is rehabilitated and upgraded.

2.2.3. Impacts on Plants, Farm Produce and Domestic Animal

a) Affected plants, farm produce and domestic animal on permanent occupied land

Table 2.6: Affected plants, crops and domestic animal on permanent occupied land

No Location Permanently affected plants, domestic animals (m2)

Rice (m2) Banana(tree) Grass (m2)

Fruit tree (tree)

Pond (m2)

I Long An province 6,538.55 49 568.00 106 1,537.00

1.1 Thu Thua district 3,189.25 0 280.00 29 0.00

1.1.1 Nhi Thanh 1,353.75 0 0.00 29 0.00

1.1.2 Binh Thanh 1,835.50 0 280.00 0 0.00

1.2 Tan An city 3,349.30 49 288.00 77 1,537.00

1.2.1 Huong Tho Phu 1,271.30 0 288.00 0 0.00

1.2.2 Ward 6 0.00 0 0.00 0 451.00

1.2.3 Ward 2 0.00 0 0.00 0 280.00

1.2.4 Ward 4 305.30 49 0.00 77 483.00

1.2.5 Khanh Hau ward 1,772.70 0 0.00 0 323.00

II Tien Giang province 9,455.85 0 0.00 1,012 495.00

2.1 Chau Thanh district 6,948.15 0 0.00 897 0.00

Page 22: TRANSMISSION EFFICIENCY PROJECT DD2-10-001B · SOUTHERN POWER PROJECT MANAGEMENT BOARD TRANSMISSION EFFICIENCY PROJECT DD2-10-001B SUB-PROJECT REHABILITATION AND UPGRADING OF PHU

Rehabilitation and Upgrading of Phu Lam – Cai Lay 2 220kV Transmission line Resettlement Plan

Owner: Southern Vietnam Power Project Management Board - EVNNPT Page 20 Prepared by: Power Engineering Consulting JS. Company 2

No Location Permanently affected plants, domestic animals (m2)

Rice (m2) Banana(tree) Grass (m2)

Fruit tree (tree)

Pond (m2)

2.1.1 Tan Huong 1,763.90 0 0.00 22 0.00

2.1.2 Tan Ly Tay 788.30 0 0.00 23 0.00

2.1.3 Tan Ly Dong 288.00 0 0.00 41 0.00

2.1.4 Tan Hiep 0.00 0 0.00 22 0.00

2.1.5 Than Cuu Nghia 628.30 0 0.00 188 0.00

2.1.6 Tam Hiep 1,797.15 0 0.00 63 0.00

2.1.7 Long Dinh 0.00 0 0.00 377 0.00

2.1.8 Nhi Binh 0.00 0 0.00 105 0.00

2.1.9 Diem Hy 1,682.50 0 0.00 56 0.00

2.2 Cai Lay district 2,507.70 0 0.00 115 495.00

2.2.1 Tan Hoi 1,644.40 0 0.00 15 0.00

2.2.2 Nhi My 863.30 0 0.00 100 495.00

Total 15,994.40 49 568.00 1,118 2,032.00

b) Affected plants, crops and domestic animals in the ROW

Table 2.7: Affected plants and crops in the ROW

No Location Plants and crops affected in ROW

Rice (m2) Crops Fruit tree Grass

I Long An province 155,257 1,056 3,141 0

1.1 Thu Thua district 50,402 0 972 0

1.1.1 Nhi Thanh 38,429 0 856 0

1.1.2 Binh Thanh 11,973 0 116 0

1.2 Tan An city 104,855 1,056 2,169 0

1.2.1 Huong Tho Phu 28,924 0 0 0

1.2.2 Ward 6 6,797 0 0 0

1.2.3 Ward 2 13,823 0 0 0

1.2.4 Ward 4 36,909 0 221 0

1.2.5 Khanh Hau 18,402 1,056 1,948 0

II Tien Giang province 169,353 67,672 20,707 1,078

2.1 Chau Thanh district 103,082 59,849 18,944 0

2.1.1 Tan Huong 22,417 2,309 4,152 0

2.1.2 Tan Ly Tay 6,858 706 1,271 0

2.1.3 Tan Ly Dong 3,337 994 680 0

2.1.4 Tan Hiep 285 1,328 176 0

2.1.5 Than Cuu Nghia 2,986 13,937 1,842 0

2.1.6 Tam Hiep 3,055 14,255 1,884 0

2.1.7 Long Dinh 6,026 20,244 6,904 0

2.1.8 Nhi Binh 15,653 3,319 1,134 0

Page 23: TRANSMISSION EFFICIENCY PROJECT DD2-10-001B · SOUTHERN POWER PROJECT MANAGEMENT BOARD TRANSMISSION EFFICIENCY PROJECT DD2-10-001B SUB-PROJECT REHABILITATION AND UPGRADING OF PHU

Rehabilitation and Upgrading of Phu Lam – Cai Lay 2 220kV Transmission line Resettlement Plan

Owner: Southern Vietnam Power Project Management Board - EVNNPT Page 21 Prepared by: Power Engineering Consulting JS. Company 2

2.1.9 Diem Hy 42,465 2,757 901 0

2.2 Cai Lay district 66,271 7,823 1,763 1,078

2.2.1 Tan Hoi 38,757 2,516 823 0

2.2.2 Nhi My 27,514 5,306 940 1,078

Total 324,610 68,728 23,848 1,078

2.2.4. Affected houses and works in the ROW

Total area of residential and garden land in the ROW of the upgrade section is 144,458m2 with the ROW limitof 11m from the center line of the route to each side. No house, architectural work is located in the permanently affected land, 510 houses and works in the ROW will limit in development space according to the Item 4, Article 1, Decree No. 81/2009/ND-CP.

Table 2.8: Affected houses and works in ROW

No. Location Quantity Structure of roof

Leaf Sheet-metal Fibro Tile

I Long An province 198 4 22 161 11

1.1 Thu Thua district 14 0 0 13 1

1.1.1 Nhi Thanh 11 0 0 11 0

1.1.2 Binh Thanh 3 0 0 2 1

1.2 Tan An city 184 4 22 148 10

1.2.1 Huong Tho Phu 23 0 4 17 2

1.2.2 Ward 6 35 0 4 31 0

1.2.3 Ward 2 27 0 2 23 2

1.2.4 Ward 4 78 1 10 61 6

1.2.5 Khanh Hau 21 3 2 16 0

II Tien Giang province 312 11 38 225 38

2.1 Chau Thanh district 281 9 28 209 35

2.1.1 Tan Huong 44 2 3 35 4

2.1.2 Tan Ly Tay 47 0 1 39 7

2.1.3 Tan Ly Dong 25 0 0 21 4

2.1.4 Tan Hiep 2 0 0 2 0

2.1.5 Than Cuu Nghia 63 2 1 50 10

2.1.6 Tam Hiep 39 0 4 31 4

2.1.7 Long Dinh 33 5 9 16 3

2.1.8 Nhi Binh 22 0 7 13 2

2.1.9 Điem Hy 6 0 3 2 1

2.2 Cai Lay district 31 2 10 16 3

2.2.1 Tan Hoi 18 0 3 13 2

2.2.2 Nhi My 13 2 7 3 1

Total 510 15 60 386 49

Houses and works existing in the ROW have the height from 2.5 to 11 m, the average height is 4.8 m. The transmission line is designed to cross residential areas with the hanging height that ensure the lowest point of transmission line at maximum sag status to natural ground

Page 24: TRANSMISSION EFFICIENCY PROJECT DD2-10-001B · SOUTHERN POWER PROJECT MANAGEMENT BOARD TRANSMISSION EFFICIENCY PROJECT DD2-10-001B SUB-PROJECT REHABILITATION AND UPGRADING OF PHU

Rehabilitation and Upgrading of Phu Lam – Cai Lay 2 220kV Transmission line Resettlement Plan

Owner: Southern Vietnam Power Project Management Board - EVNNPT Page 22 Prepared by: Power Engineering Consulting JS. Company 2

surface not less than 18 m. When Phu Lam – Cai Lay 2 220kV transmission line is rehabilitated, upgraded; it must be ensured that the distance from any part of houses, works within the ROW to the nearest line at maximum sag situation is not less than 6 m. It should alsobe ensured that houses and works existing in the ROW with their roof and earthing being renovated are permitted to exist under the corridor of 220kV power grid. Therefore, the subproject will not cause relocation, resettlement for the existing houses. Furthermore, when the transmission line is rehabilitated and upgraded, the hanging height is elevated, it ensures more safety for houses in the ROW and increases more space of housing development.

Page 25: TRANSMISSION EFFICIENCY PROJECT DD2-10-001B · SOUTHERN POWER PROJECT MANAGEMENT BOARD TRANSMISSION EFFICIENCY PROJECT DD2-10-001B SUB-PROJECT REHABILITATION AND UPGRADING OF PHU

Rehabilitation and Upgrading of Phu Lam – Cai Lay 2 220kV Transmission line Resettlement Plan

Owner: Southern Vietnam Power Project Management Board - EVNNPT Page 23 Prepared by: Power Engineering Consulting JS. Company 2

3. LEGAL FRAMEWORK AND COMPENSATION POLICIES

Applicable laws and policies for implementing the resettlement and compensation comprise (i) policies of the World Bank, (ii) the current policies of compensation, assistance, resettlement of Government of Vietnam; and (iii) procedures for compensation, assistance and resettlement of local authorities (Long An province).

3.1. Legal Framework

3.1.1. Vietnam’s Policies

(1) Regulations of the Government of Vietnam on compensation, assistance and resettlement will be applied in the RP’s implementation of subproject as follows:

- The Constitution of Vietnam, 2013;

- The Land Law 2003, No.13/2003/QH11, issued on November 26, 2003 (to be replaced by the Land Law 2013 which become effective from July 1st, 2014)

- Decree No.181/2004/ND-CP issued on October 29, 2004 guiding the implementation of the Land Law revised 2003.

- Decree No.188/2004/ND-CP issued on November 16, 2004 providing the method of land price calculation and the tariff for all types of land;

- Decree No.197/2004/ND-CP issued on December 3, 2004 on compensation, support and resettlement when land is recovered by the state.

- Decree No.188/2004/ND-CP issued on November 16, 2004 on methods to determine land prices and assorted land price brackets.

- Decree No.123/2007/ND-CP dated July 27, 2007, on revision and supplementation of some regulations in decree 188/2004/ND-CP of November 16, 2004 on methods to determine land prices and assorted land price brackets.

- Decree No.17/2006/ND-CP dated January 27, 2006 on revision and supplementation of some regulations in decrees guiding the implementation of the Land Law and Decree no. 187/2004/ND-CP on transformation of state companies into joint-stock companies.

- Decree No.84/2007/ND-CP dated May 25, 2007 on revision of issuing LURC, land acquisition, implementation of land use right, procedure for compensation, resettlement when land acquired by State and grievance redress.

- Decree No.69/2009/ND-CP, effective October 01, 2009; an amendment to Decree No. 197/2004/ND-CP; supplementary regulations on land use planning, land prices, land acquisition, compensation, support and resettlement.

- Circular No.116/2004/TT-BTC dated December 17, 2004 providing guidance for the implementation of Decree No.197/2004/ND-CP dated December 3,2004 on compensation, assistance and resettlement upon the State recovery of land;

- Circular No.14/TT-BTNMT dated October 01, 2009 providing detailed regulations on compensation, assistances, relocation and process and procedures for land acquisition, land hand-over and land lease.

- Circular No.57/2010/TT-BTC issued on April 16, 2010 prescribing the estimation, use and settlement of funds for compensation, support and resettlement upon recovery by the State.

- Circular No.02/2010/TTLT-BTNMT-BTC dated January 8, 2010 issued by the Ministry

Page 26: TRANSMISSION EFFICIENCY PROJECT DD2-10-001B · SOUTHERN POWER PROJECT MANAGEMENT BOARD TRANSMISSION EFFICIENCY PROJECT DD2-10-001B SUB-PROJECT REHABILITATION AND UPGRADING OF PHU

Rehabilitation and Upgrading of Phu Lam – Cai Lay 2 220kV Transmission line Resettlement Plan

Owner: Southern Vietnam Power Project Management Board - EVNNPT Page 24 Prepared by: Power Engineering Consulting JS. Company 2

of Natural Resource and Environment and Ministry of Finance guiding the preparation appraisal, and issuance and revision of land prices revision and the competence of the city/province PC under the National Government control.

- Decision No.1956/2009/QD-TTg, dated November 17, 2009, by the Prime Minister approving the Master Plan on vocational training for rural labors by 2020.

- Decision No.52/2012/QD-TTg, dated November 16, 2012, on the support policies on employment and vocational training to farmers whose agricultural land has been recovered by the State.

- The Electricity Law 2004, No.28/2004/QH11, ratified on December 03, 2004.

- Decree No.106/2005/ND-CP (and its associated guiding circulars) dated on August 17, 2005, guiding the implementation of a number of articles under the Electricity Law regarding safety protection of high-voltage power grid.

- Decree No.81/2009/ND-CP (and its associated guiding circulars) dated on October 12, 2009, amending or supplementing a number of articles of the government’s decree No.106/205/ND-CP of August 17, 2005 which details and guide a number of articles of the electricity law regarding the safe protection of high-voltage power grid works.

- Circular No.03/2010/TT-BCT dated on January 22, 2010 of Ministry of Industry and Trade, regulating a number of articles under decrees No.106/2005/ND-CP and decree No.81/2009/ND-CP.

(2) The current stipulations on compensation, assistance and resettlement of local authorities are applied in RP’s implementation of the subproject as follows:

- Decision No.07/2010/QD-UBND dated 01/3/2010 of Long An province on the issuance of regulations of compensation, assistance and resettlement when the State claims land in Long An province;

- Decision No.55/2011/QD0UBND dated 20/12/201 of Long An province People’s Committee issuing the tariff of types of land in 2012 in Long An province;

- Decision No.17/2011/QD-UBND on 24/6/2011 regarding on amendment, supplement some of Articles of Decision on compensation, assistance and resettlement when the State claims land in Long An province, attached with the Decision No.07/2010/QD-UBND dated 01/3/2010 of Long An province

- Decision No.64/2012/QD-UBND on 17/12/2012 regarding issuance of list of land price for land types of Long An province in 2013.

- Decision No.22/2011/QD-UBND on 20/07/2011 of People’s Committee of Long An province on the issuance of unit price of plants and animals, costs of the remaining land, living activities and tombs in regions of Long An province.

- Decision No.15/2013/QD-UBND dated 24/5/2013 of Tien Giang Province People’s Committee issuing regulations on compensation, support and and resettlement when the Government revokes land to use for purposes of national defence, security, national benefits, public benefits and economic development in Tien Giang Province;

- Decision No.28/2012/QD-UBND dated 21/12/2012 of Tien Giang Province People’s Committee issuing regulations in types of land in Tien Giang Province area in 2013;

- Decision No.32/2011/QD-UBND dated 28/10/2011 of Tien Giang Province People’s Committee issuing regulations in unit price of compensation for damage of fruits, crops when

Page 27: TRANSMISSION EFFICIENCY PROJECT DD2-10-001B · SOUTHERN POWER PROJECT MANAGEMENT BOARD TRANSMISSION EFFICIENCY PROJECT DD2-10-001B SUB-PROJECT REHABILITATION AND UPGRADING OF PHU

Rehabilitation and Upgrading of Phu Lam – Cai Lay 2 220kV Transmission line Resettlement Plan

Owner: Southern Vietnam Power Project Management Board - EVNNPT Page 25 Prepared by: Power Engineering Consulting JS. Company 2

the Government revokes land to use for purposes of national defence, national benefits, public benefits, economic development.

3.1.2. World Bank’s Policies

The primary objective of the World Bank’s OP 4.12 is to explore all alternatives to avoid or at least minimize involuntary resettlement. Where resettlement is unavoidable, the living standards of displaced persons should be restored or improved relative to those conditions that prevailed prior to the subproject. The policy applies to the taking of land and other assets when land acquisition results in the loss of shelter, the loss of all or part of productive assets, or access to them, and the loss of income sources or other means of livelihood.

(Main characteristics of OP 4.12 are detailed in Resettlement Policy Framework of Efficiency Transmission Project).

3.1.3. Compatibility between policies of Government and the World Bank and necessary exemptions

Current Laws, Decrees and Regulations bring the Government of Viet Nam resettlement policies and practices to be more consistent with the World Bank’s resettlement policies. The differences between the Government’s Laws and Decrees and World Bank Policy with regard to resettlement and compensation, and how to address these gaps are shown in table 3.1.

Table 3.1. Comparison of Vietnam’s and World Bank’s Policies related to Involuntary Resettlement

Subjects Bank’s OP 4.12 Government of Vietnam Project Measures

Land Property

Policy objectives

DPs should be assisted in their efforts to improve their livelihoods and standards of living or at least to restore them, in real terms, to pre-displacement levels or to levels prevailing prior to the beginning of project implementation, whichever is higher

Resettlement site and its infrastructure should have equal or better development conditions than the existing one.

Livelihoods and income sources will be restored in real terms, at least, to the pre-displacement levels or to levels prevailing prior to the beginning of project implementation, whichever is higher.

Support for affected households who have no recognizable legal right or claim to the land they are occupying

Financial assistance to all project affected persons to achieve the policy objective (to improve their livelihoods and standards of living or at least to restore them, in real terms, to pre-displacement levels or to levels prevailing prior to the beginning of project implementation, whichever is higher)

Financial assistance provided at different levels depending on the “legal” status of affected persons

Financial assistance of an agreed amount will be given to all DPs, regardless of their legal status, until their livelihoods and standards of living restore in real terms, at least, to pre-displacement levels.

Page 28: TRANSMISSION EFFICIENCY PROJECT DD2-10-001B · SOUTHERN POWER PROJECT MANAGEMENT BOARD TRANSMISSION EFFICIENCY PROJECT DD2-10-001B SUB-PROJECT REHABILITATION AND UPGRADING OF PHU

Rehabilitation and Upgrading of Phu Lam – Cai Lay 2 220kV Transmission line Resettlement Plan

Owner: Southern Vietnam Power Project Management Board - EVNNPT Page 26 Prepared by: Power Engineering Consulting JS. Company 2

Compensation for illegal structures

Compensation at full cost for all structures regardless of legal status of the DP’s land and structure.

Provided to cover the new structure costs. Depending on the “illegality status” attributed , covering between 80% and 0% of the total costs

Compensation at full replacement cost will be given for all structures affected, regardless of legal status of the land and structure.

Compensation

Methods for determining compensation rates

Compensation for lost land and other assets should be paid at full replacement costs,

Compensation for lost assets is calculated at price close to transferring the assets in local markets or the cost of newly-built structures. Provincial governments are granted to annually set up compensation prices for different categories of assets

Independent appraiser identifies replacement costs for all types of assets affected. Provincial government will use this assessment to establish the compensation rates at full replacement.

Compensation for loss of income sources or means of livelihood

Loss of income sources should be compensated (whether or not the affected persons must move to another location)

Assistance in respect of income loss is given only for registered businesses. For affected persons losing agricultural land, additional financial support will be provided.

All income losses are to be compensated and, where necessary to achieve the objectives of the policy, development assistance in addition to compensation will be provided.

Compensation for indirect impact caused by land or structures taking

It is good practice for the borrower to undertake a social assessment and implement measures to minimize and mitigate adverse economic and social impacts, particularly upon poor and vulnerable groups.

Not addressed. Socio-economic assessment has been undertaken and measures identified and being implemented to minimize and mitigate adverse impacts, particularly upon poor and vulnerable groups.

Livelihood restoration and assistance

Provision of livelihood restoration and assistance to achieve the policy objectives.

Livelihood restoration and assistance measures are provided. No follow-up for full livelihood restoration after resettlement completion.

Provision of livelihood restoration and assistance measures to achieve the policy objectives. These will be monitored as detailed in the RP

Consultation and disclosure

Participation in planning and implementation, specially confirming the

Limited mostly to information sharing and disclosure.

Consultation and participation incorporated into RP

Page 29: TRANSMISSION EFFICIENCY PROJECT DD2-10-001B · SOUTHERN POWER PROJECT MANAGEMENT BOARD TRANSMISSION EFFICIENCY PROJECT DD2-10-001B SUB-PROJECT REHABILITATION AND UPGRADING OF PHU

Rehabilitation and Upgrading of Phu Lam – Cai Lay 2 220kV Transmission line Resettlement Plan

Owner: Southern Vietnam Power Project Management Board - EVNNPT Page 27 Prepared by: Power Engineering Consulting JS. Company 2

eligibility criteria for compensation and assistance, and access to Grievances Redress Mechanisms

design, along with information sharing with DPs and stakeholders. Priority will be given to the participation of women in the consultation processes.

Grievance redress mechanism

Grievance redress mechanism should be independent

The same governmental body makes decisions on compensation and resettlement, and also handles grievances at the first step;

Independent Grievance and Redress mechanisms are to be established, built on the existing governmental system, with monitoring by an independent monitor

Monitoring & Evaluation

Internal and independent monitoring are required

There is no explicit requirements on monitoring, including both internal and independent (external) monitoring

Both internal and external (independent) monitoring is to be regularly maintained (on a monthly basis for internal and bi-annual basis for independent monitoring). An end-of-project report will be done to confirm whether the objectives of OP 4.12 were achieved.

Required Waivers

To satisfy WB OP/BP 4.12 policy on Involuntary Resettlement, articles in the laws and regulations of Vietnam that do not guarantee the APs’ right to compensation at replacement costs, or eligibility articles that do not extend the right of being restored and/or assisted to households without valid land papers, or otherwise limit the compensation required by WB OP/BP 4.12, will not apply. The requirements of WB OP/BP 4.12 will fully apply in all cases. This is in accordance with Decree No.38/2013/ND-CP, which states that in case of “discrepancy between any provision in an international treaty on Official Development Assistance, to which the Socialist Republic of Viet Nam is a signatory, and the Vietnamese Law, the provision in the international treaty on ODA shall take precedence” (Article 6, Article 7).

3.2. Principle of Compensation Applied for the Subproject

3.2.1. General Principles

All DPs who have assets within or reside within the area of project land-take before the cut-

Page 30: TRANSMISSION EFFICIENCY PROJECT DD2-10-001B · SOUTHERN POWER PROJECT MANAGEMENT BOARD TRANSMISSION EFFICIENCY PROJECT DD2-10-001B SUB-PROJECT REHABILITATION AND UPGRADING OF PHU

Rehabilitation and Upgrading of Phu Lam – Cai Lay 2 220kV Transmission line Resettlement Plan

Owner: Southern Vietnam Power Project Management Board - EVNNPT Page 28 Prepared by: Power Engineering Consulting JS. Company 2

off date are entitled to compensation or assistance for their losses. Those who have lost their income and/or subsistence will be eligible for livelihood rehabilitation assistance, based on the criteria of eligibility defined by the project and in consultation with the DPs. If, by the end of the project, livelihoods have been shown not to be restored to pre-project levels, additional measures will be provided.

- The compensation rates will be determined based on the results of independent land/assets appraisal in a timely and consultative fashion. All fees and taxes on land and/or house transfers will be waived or otherwise included in a compensation package for land and structures/houses or businesses. The local authorities will ensure that DPs choosing relocation on their own obtain, without additional cost, the necessary property titles and official certificates commensurate with similar packages provided to those who choose to move to the project resettlement sites.

- Land will be compensated “land for land” or in cash according to the DP’s choice whenever possible. The choice of land for land must be offered to those losing 20% or more of their productive land. If land is not available, the borrower must assure itself that this is indeed the case. Those losing 20% or more of their land will have to be assisted to restore their livelihood. The same principles apply for the poor and vulnerable people losing 10% or more of their productive landholding.

- DPs that prefer “land for land” will be provided with land plots with the equivalent productive capacity for lost lands or a combination of land (a standard land plot) in a new residential area nearby for residential land, and cash adjustment for the difference between their lost land and the land plots provided. The resettlement area will be planned properly and implemented in consultation with the DPs. All basic infrastructures, such as paved roads, sidewalks, drainage, water supply, and electricity and telephone lines, will be provided.

- DPs that prefer “cash for land” will be compensated in cash at the full replacement cost. These DPs will be assisted in rehabilitating their livelihoods and making their own arrangements for relocation.

- Compensation for all residential, commercial, or other structures will be offered at the replacement cost, without any depreciation of the structure and without deduction for salvageable materials. Structures shall be evaluated individually. Any rates set by category of structure must use the highest value structure in that group (not the lowest).

- The DPs will be provided full assistance (including a transportation allowance) for transportation of personal belongings and assets, in addition to the compensation at replacement cost of their houses, lands, and other properties.

- Plans for acquisition of land and other assets and provision of rehabilitation measures will be carried out in consultation with the DPs (with particular attention to vulnerable DPs), to minimize the disturbance and shorten the resettlement transition period. The rehabilitation measures will be provided to the DP's prior to the expected start-up date of works in the project sites.

- If, by the end of the project, livelihoods have been shown not to be restored to pre-project levels, additional measures should be considered.

- Financial services (such as loans or credits) will be provided to DPs, if necessary. The installment amounts and the schedule of payments will be within the repayment capacity of DPs.

- Additional efforts, such as economic rehabilitation assistance, training and other forms of assistance, should be provided to DPs losing income sources, especially to vulnerable groups

Page 31: TRANSMISSION EFFICIENCY PROJECT DD2-10-001B · SOUTHERN POWER PROJECT MANAGEMENT BOARD TRANSMISSION EFFICIENCY PROJECT DD2-10-001B SUB-PROJECT REHABILITATION AND UPGRADING OF PHU

Rehabilitation and Upgrading of Phu Lam – Cai Lay 2 220kV Transmission line Resettlement Plan

Owner: Southern Vietnam Power Project Management Board - EVNNPT Page 29 Prepared by: Power Engineering Consulting JS. Company 2

in order to enhance their future prospects toward livelihood restoration and improvement.

- The previous level of community services and resources, encountered prior to displacement, will be maintained or improved for resettlement areas.

- Contractors can only commence civil works after (i) the governmental competent agency has satisfactorily completed compensation payments and rehabilitation assistances in accordance to approved RP for sub-project; (ii) already-compensated DPs have cleared the area in a timely manner; and (iii) the area is free from any encumbrances.

3.2.2. Policies for compensation, Support and Resettlement Applied to the Subproject

In addition to the direct compensation for damages in accordance with the policy framework of World Bank and policy framework of Vietnam mentioned at the above item 3.1.1, APs have the right to receive allowance as stipulated in the Decree No.197/2004/ND-CP, Decree No.69/2009/ND-CP, and Decree No.81/2009/ND-CP. Allowances/ supports include:

- Support in renovation of roof and earthing for houses in ROW

Houses, accessory structure for accommodation, or part thereof located in the ROW, support shall be granted for renovation of roof and earthing to ensure safety conditions for existing in the ROW as stipulated by the Decree No.81/2009/ND-CP.

- Other rehabilitation measures

In addition to aforementioned, any AP exposed to any impact other than those considered to be minor, will have a range of programs to support their full livelihood restoration and assure asset compensation at replacement values; i.e. either at a replacement value for each structure or using the value of the most expensive structures as a bench mark in case those structures are categorized by “types”.

Entitlement matrix: Refer to Appendix 2: the Entitlement Matrix.

Page 32: TRANSMISSION EFFICIENCY PROJECT DD2-10-001B · SOUTHERN POWER PROJECT MANAGEMENT BOARD TRANSMISSION EFFICIENCY PROJECT DD2-10-001B SUB-PROJECT REHABILITATION AND UPGRADING OF PHU

Rehabilitation and Upgrading of Phu Lam – Cai Lay 2 220kV Transmission line Resettlement Plan

Owner: Southern Vietnam Power Project Management Board - EVNNPT Page 30 Prepared by: Power Engineering Consulting JS. Company 2

4. COMPENSATION, ASSISTANCE AND RESETTLEMENT

4.1. Compensation

Cut-off date will be proposed in the Quarter II of 2014; the cut-off date of the subproject will be officially notified to affected people by relevant local authorities. Damages will be inventoried in detail after the cut-off date to implement compensation, resettlement assistance under the stipulations. The impacts listed in this report is totaled up in line with the preliminary survey data in investment phase, its data will be used to prepare plan and cost estimate for compensation. All damages and compensation costs will be made accurate in phase of compensation and land acquisition.

Persons who encroach and move into the area that proposed to be affected area after the cut-off date will not be entitled to compensation and resettlement. They will be requested to dismantle affected structures, cut trees or harvest crops for land clearance of the project; however, they will not have to pay any fine. The cut-off date and terms “no compensation for the encroachers” will be announced clearly to People’s Committee of commune level by the project’s owner.

Replacement cost: In this subproject, the damages are only lands, perennial trees and crops. Survey result has shown that transmission line in the sub-project will be built in rural areas; most of the land is only for agricultural production (rice plants, crops) and gardening with long term stability. There is no trading of land, plants and crops (mostly land is transferred from the owners to their children and relatives) and through consultation with local authorities (Thu Thua, Tan An city of Long An province and Chau Thanh district, Cai Lay of Tien Giang province), compensation prices of land, plants and crops will be applied according to the price regulated by the People’s Committee of province). It is based on the following Decisions:

- Decision No.07/2010/QD-UBND dated 01/3/2010 of Long An province on the issuance of regulations of compensation, assistance and resettlement when the State claims land in Long An province;

- Decision No.17/2011/QD-UBND on 24/6/2011 regarding on amendment, supplement some of Articles of Decision on compensation, assistance and resettlement when the State claims land in Long An province;

- Decision No.64/2012/QD-UBND on 17/12/2012 regarding issuance of list of land price for land types of Long An province in 2013.

- Decision No.22/2011/QD-UBND on 20/07/2011 of People’s Committee of Long An province on the issuance of unit price of plants and animals, costs of the remaining land, living activities and tombs in regions of Long An province;

- Decision No.15/2013/QD-UBND dated 24/5/2013 of Tien Giang Province People’s Committee issuing regulations on compensation, support and and resettlement when the Government revokes land to use for purposes of national defence, security, national benefits, public benefits and economic development in Tien Giang Province;

- Decision No.28/2012/QD-UBND dated 21/12/2012 of Tien Giang Province People’s Committee issuing regulations in types of land in Tien Giang Province area in 2013;

- Decision No.32/2011/QD-UBND dated 28/10/2011 of Tien Giang Province People’s Committee issuing regulations in unit price of compensation for damage of fruits, crops when the Government revokes land to use for purposes of national defence, national benefits, public benefits, economic development.

Page 33: TRANSMISSION EFFICIENCY PROJECT DD2-10-001B · SOUTHERN POWER PROJECT MANAGEMENT BOARD TRANSMISSION EFFICIENCY PROJECT DD2-10-001B SUB-PROJECT REHABILITATION AND UPGRADING OF PHU

Rehabilitation and Upgrading of Phu Lam – Cai Lay 2 220kV Transmission line Resettlement Plan

Owner: Southern Vietnam Power Project Management Board - EVNNPT Page 31 Prepared by: Power Engineering Consulting JS. Company 2

It is worth to note that land and plant unit prices applied in this RP is only for estimation (at the time of compiling this RP). At the time of implementation of RP (expected in 2014), land compensation unit price will be updated to ensure that affected people will be compensated at the level of replacement cost for their losses.

4.1.1. Compensation Unit Prices for Land

Table 4.1: Compensation unit prices and assistance of permanently affected land

No Location

Unit price of lands (VND/m2)

Remark Agricultural

land Aquacul

ture land

Residential land

Industrial land Annua

l tree Perennial tree

I Long An province

Refer appendix of Decision No.64/2012/QD-UBND on 17/12/2012 of People’s Committee of Long An province

1.1 Thu Thua district

1.1.1 Nhi Thanh 70,000 70,000 55,000 500,000 450,000

1.1.2 Binh Thanh 70,000 70,000 55,000 500,000 450,000

1.2 Tan An city

1.2.1 Huong Tho Phu 85,000 85,000

70,000 700,000 630,000

1.2.2 Ward 6 95,000 95,000 75,000 1,100,000 990,000

1.2.3 Ward 2 95,000 95,000 75,000 5,500,000 4,950,000

1.2.4 Ward 4 95,000 95,000 75,000 1,700,000 1,530,000

1.2.5 Khanh Hau 95,000 95,000 75,000 1,000,000 900,000

II Tien Giang province

Stipulations in price of lands in Tien Giang Province (issued with Decision No. 28/2012/QD-UBND dated 21/12/2012 of People’s Committee of Tien Giang Province)

2.1 Chau Thanh district

2.1.1 Tan Huong 70,000 85,000 70,000 280,000 936,000

2.1.2 Tan LyTay 70,000 85,000 70,000 270,000

2.1.3 Tan Ly Dong 70,000 85,000 70,000 230,000

2.1.4 Tan Hiep 90,000 110,000 90,000 700,000

2.1.5 Than Cuu Nghia 70,000 85,000 70,000 270,000

2.1.6 Tam Hiep 70,000 85,000 70,000 480,000

2.1.7 Long Dinh 70,000 85,000 70,000 350,000

2.1.8 Nhi Binh 70,000 85,000 70,000 330,000

2.1.9 Diem Hy 70,000 85,000 70,000 270,000

2.2 Cai Lay district

2.2.1 Tan Hoi 70,000 85,000 70,000 450,000

2.2.2 Nhi My 80,000 100,000 80,000 450,000

Page 34: TRANSMISSION EFFICIENCY PROJECT DD2-10-001B · SOUTHERN POWER PROJECT MANAGEMENT BOARD TRANSMISSION EFFICIENCY PROJECT DD2-10-001B SUB-PROJECT REHABILITATION AND UPGRADING OF PHU

Rehabilitation and Upgrading of Phu Lam – Cai Lay 2 220kV Transmission line Resettlement Plan

Owner: Southern Vietnam Power Project Management Board - EVNNPT Page 32 Prepared by: Power Engineering Consulting JS. Company 2

Notes: The unit price residential land applied is the average unit price in commune/ town/ ward.

In the case that the land use purposes are not changed (e.g: houses and works that are allowable to exist in the ROW) but its usage capacity is limited, compensation will be paid in cash based on the real damage.

However, the transmission line of rehabilitation from 1 circuit to 2 circuit from G7 – Cai Lay 220kV substation mainly enters the ROW of the existing Phu Lam – Cai Lay 1 220kV transmission line and Phu Lam – Cai Lay 2 220kV transmission line. Effects due to limitation of land use posibility has previously existed in ROW of the existing Phu Lam – Cai Lay 1 220kV transmission line and Phu Lam – Cai Lay 2 220kV transmission line. Therefore, effects due to limitation of land use posibility in ROW when improving and upgrading of this transmission line will not be compensated and supported.

4.1.2. Compensation Unit Price for Crops, Plant, Domestic Animal

- Compensation for plants, crops and domestic animals is applicable to permanently occupied land areas for the construction of tower foundation, revoked area of pond land for aquatic production and plants affected in the construction process of the transmission line.

- Compensation unit price refers to Table 4.2:

Table 4.2: Unit price for plants, crops, domestic animals applied for compensation

No Type of land Unit Price Remark

I Long An province

Compensation unit prices for fruits, crops when the Government takes land acquisition (issued with Decision No.32/2011/QD-UBND dated 28/10/2011 People’s Committee’s Tien Giang province

1 Rice m2 1,500

2 Crops m2 3,900

3 Grass m2 1,500

4 Banana Tree 40,000

5 Fruit tree Tree 280,000

6 Pond m2 40,000

II Tien Giang province Compensation unit price for plants and crops, domestic animals, investment costs for remaining land, life means and tombs according to Decision No.22/2011/QD-UBND on 20/7/2011 by Long An People’s Committee.

1 Rice 5,000

2 Crops 14,000

3 Grass 5,000

4 Banana 80,000

5 Fruit tree 780,000

6 Pond 40,000

Notes:

- The unit price of fruit tree applied in Long An and Tien Giang provinces is the average unit price of all types of fruit tree in the province correlatively.

- The unit price of crops applied in Long An and Tien Giang provinces is the average unit price of all crops in the province correlatively.

Page 35: TRANSMISSION EFFICIENCY PROJECT DD2-10-001B · SOUTHERN POWER PROJECT MANAGEMENT BOARD TRANSMISSION EFFICIENCY PROJECT DD2-10-001B SUB-PROJECT REHABILITATION AND UPGRADING OF PHU

Rehabilitation and Upgrading of Phu Lam – Cai Lay 2 220kV Transmission line Resettlement Plan

Owner: Southern Vietnam Power Project Management Board - EVNNPT Page 33 Prepared by: Power Engineering Consulting JS. Company 2

- For aquaculture that at the time of revoking land, but the harvesting time has not come, compensation for actual damage will be implemented due to early harvest. The unit price for compensation of actual damage is temporarily VND 40,000/m2.

4.2. Assistance

In addition to direct compensation for damages, APs are entitled to enjoy assistance as regulated. The assistances are as follows:

4.2.1. Assistance with Occupational Change and Job Creation

- Assistance with occupational change and job creation as stated in Article 39 – Decision No.07/2010/QD-UBND dated 01/3/2010 by People’s Committee of Long An province and Article 27 of Decision No.15/2013/QD-UBND dated 24/5/2013 of Tien Giang province People’s Committee (for permanently acquired land).

Table 4.3: Unit price for occupational change and job creation

No Location

Unit price of types of land (VND/m2)

Remark Agricultural land Aquaculture land Annual

land Perennial

land

I Long An province Compensation price will be 5 times of agricultural price as regulated at Clause 1, Article 39 of Decision 07/2010/QD-UBND dated 01/3/2010 of Long An province People’s Committee.

1.1 Thu Thua District

1.1.1 Nhi Thanh 350,000 350,000 275,000

1.1.2 Binh Thanh 350,000 350,000 275,000

1.2 Tan An City

1.2.1 Huong Tho Phu 425,000 425,000 350,000

1.2.2 Ward 6 475,000 475,000 375,000

1.2.3 Ward 2 475,000 475,000 375,000

1.2.4 Ward 4 475,000 475,000 375,000

1.2.5 Khanh Hau 475,000 475,000 375,000

II Tien Giang province Compensation price will be 2.5 times of agricultural price as stipulated at point a, Clause 1, article 27, Decision No. 15/2013/QD-UBND dated 24/5/2013 of Tien Giang province People’s Committee.

2.1 Chau Thanh district

2.1.1 Tan Huong 175,000 212,500 175,000

2.1.2 Tan Ly Tay 175,000 212,500 175,000

2.1.3 Tan Ly Dong 175,000 212,500 175,000

2.1.4 Tan Hiep 225,000 275,000 225,000

2.1.5 Than Cuu Nghia 175,000 212,500 175,000

2.1.6 Tam Hiep 175,000 212,500 175,000

2.1.7 Long Dinh 175,000 212,500 175,000

2.1.8 Nhi Binh 175,000 212,500 175,000

Page 36: TRANSMISSION EFFICIENCY PROJECT DD2-10-001B · SOUTHERN POWER PROJECT MANAGEMENT BOARD TRANSMISSION EFFICIENCY PROJECT DD2-10-001B SUB-PROJECT REHABILITATION AND UPGRADING OF PHU

Rehabilitation and Upgrading of Phu Lam – Cai Lay 2 220kV Transmission line Resettlement Plan

Owner: Southern Vietnam Power Project Management Board - EVNNPT Page 34 Prepared by: Power Engineering Consulting JS. Company 2

2.1.9 Diem Hy 175,000 212,500 175,000

2.2 Cai Lay district

2.2.1 Tan Hoi 175,000 212,500 175,000

2.2.2 Nhi My 200,000 250,000 200,000

4.2.2. For Agricultural Land in Residential Area

For those households and individuals with revoked garden land and pond land with dwelling therein in a resdential area that are not officially recognized as residential land, compensation will be maded for agricultural land with perennial trees plus a further support equivalent to 70% of land price of such land lot (as stipulated in Clause 3, Article 13 of Decision No.07/2010/QD-UBND on 01/3/2010 of Long An province People’s Committee and Clause 1, Article 28 of Decision No.15/2013/QD-UBND on 24/5/2013 of Tien Giang province People’s Committee).

Table 4.4: Assistance for agricultural land in the residential area, garden land and pond land that are not recognized as residential land

No Location Support unit price

(VND/m2) Remark

I Long An province

Compensation price will be 70% of price unit at the same lot according to stipulation at Clause 3, Article 13 of Decision No.07/2010/QD-UBND on 01/3/2010 People’s Committee of Long An province.

1.1 Thu Thua District

1.1.1 Nhi Thanh 350,000

1.1.2 Binh Thanh 350,000

1.2 Tan An City

1.2.1 Huong Tho Phu 490,000

1.2.2 Ward 6 770,000

1.2.3 Ward 2 3,850,000

1.2.4 Ward 4 1,190,000

1.2.5 Khanh Hau 700,000

II Tien Giang province Compensation price will be 70% of average price in the area where land is revoked according to Clause 1, Article 28, Decision No.15/2013/QD-UBND dated 24/5/2013 of Tien Giang province People’s Committee

2.1 Chau Thanh District

2.1.1 Tan Huong 196,000

2.1.2 Tan LyTay 189,000

2.1.3 Tan Ly Dong 161,000

2.1.4 Tan Hiep 490,000

2.1.5 Than Cuu Nghia 189,000

2.1.6 Tam Hiep 336,000

2.1.7 Long Dinh 245,000

2.1.8 Nhi Binh 231,000

Page 37: TRANSMISSION EFFICIENCY PROJECT DD2-10-001B · SOUTHERN POWER PROJECT MANAGEMENT BOARD TRANSMISSION EFFICIENCY PROJECT DD2-10-001B SUB-PROJECT REHABILITATION AND UPGRADING OF PHU

Rehabilitation and Upgrading of Phu Lam – Cai Lay 2 220kV Transmission line Resettlement Plan

Owner: Southern Vietnam Power Project Management Board - EVNNPT Page 35 Prepared by: Power Engineering Consulting JS. Company 2

No Location Support unit price Remark 2.1.9 Diem Hy 189,000

2.2 Cai Lay District

2.2.1 Tan Hoi 315,000

2.2.2 Nhi My 315,000

4.2.3. Assistance with Production Stability

Households, individuals directly involved in agricultural production at the time the Government revokes agricultural land will be assisted in terms of life stability according to the follows:

For revoking from 20% (or 10% in case of vulnerable households) to 70% of the agricultural land area in the current use in the region of commune, ward, town; people will be assisted with their life stability within 6 months if houses removal is not required, and within 12 months if not;

For revoking more than 70% of agricultural land area in current use in the commune ward, town; people will be assisted with their life stability within 12 months if house removal is not required and 24 months if not;

The assistance for each person according to the above stipulation will be calculated in money, equivalent to 30kg of rice per month according to the average current price at the time of assistance.

Table 4.5: Unit price for supporting manufacturing stability

No Location Support unit price (VND/person.month)

Remark

I Long An Province 285,000 The price will be the average current price in Long An province in June, 2013.

II Tien Giang Province 270,000 The price will be the average current price in Tien Giang province in June 2013.

4.2.4. Assistance with Renovation of Roof and Roof Earthing of Houses in the ROW

Assistance with renovation of wall, roof and earthing by technical method will be implemented for 56 houses with corrugated roof and 15 houses with leaf roof to ensure their continuing habitual condition and no necessary house removal with Article 6 of Decree No.106/2005/ND-CP on 17/8/2005 stipulating in details and guiding, implementing some articles of the Electrical Law in safety protection for high-voltage grid.

The costs for renovation of wall, roof, earthing (by the technical methods) will not be included in the cost estimate of the project because SPMB and Long An province Power Company and Tien Giang province Power Company will implement this work.

5. PUBLIC CONSULTATION AND PEOPLE PARTICIPATION

5.1. Public Consultation and People Participation

Public consultation is carried out in public meeting. In this meeting, the subproject’s owner has presented information on the subproject, compensation policies, site clearance and power

Page 38: TRANSMISSION EFFICIENCY PROJECT DD2-10-001B · SOUTHERN POWER PROJECT MANAGEMENT BOARD TRANSMISSION EFFICIENCY PROJECT DD2-10-001B SUB-PROJECT REHABILITATION AND UPGRADING OF PHU

Rehabilitation and Upgrading of Phu Lam – Cai Lay 2 220kV Transmission line Resettlement Plan

Owner: Southern Vietnam Power Project Management Board - EVNNPT Page 36 Prepared by: Power Engineering Consulting JS. Company 2

safety of the TEP by giving a lecture at the meeting and direct negotiation to affected people. This is a base for community and affected people to be participated in different phases of the subproject.

Based on information provided at the public meeting, survey result on damages and losses, implementation plans for compensation and assistance, entitlement matrix and relevant works of compensation; community and affected people will participate directly and effectively in monitoring activities of this plan. District Compensation Council shall hold meetings with the relevant communes/hamlets to announce all information relating to the subproject. In addition, local authorities shall also announce local people related to the subproject of the potential impacts of the subproject, especially about the Entitlement Matrix.

During the preparation of the RP, Consultant has held public consultation meetings at commune and ward levels with the participation of APs and representatives from People's Committee, Women Union, Veterans’ Organization, Farmer Association, Chief of Hamlet, Officer of land survey, Fatherland Front etc. of communes/wards in region of the subproject in accordance with the below schedule.

- Thu Thua district – Long An province

+ Nhi Thanh commune (at 1:30 p.m on 30/7/2013)

+ Binh Thanh commune (at 3:00 p.m on 30/7/2013)

- Ben Luc district – Long An province

+ Thanh Phu commune (at 8:30 a.m on 30/7/2013)

+ Thanh Duc commune (at 9:00 a.m on 06/8/2013)

- Tan An City – Long An province

+ Huong Tho Phu commune (at 1:00 p.m on 26/7/2013)

+ Ward 6 (at 8:30 a.m on 29/7/2013)

+ Ward 2 (at 1:00 p.m on 29/7/2013)

+ Ward 4 (at 3:00 p.m on 26/7/2013)

+ Khanh Hau ward (at 8:30 a.m on 26/7/2013)

- Chau Thanh district – Tien Giang province

+ Tan Huong commune (at 8:30 a.m on 31/7/2013)

+ Tan Ly Tay commune (at 1:00 p.m on 31/7/2013)

+ Tan Ly Dong commune (at 8:30 a.m on 02/8/2013)

+ Tan Hiep commune (at 8:30 a.m on 06/8/2013)

+ Than Cuu Nghia (at 9:30 a.m on 06/8/2013)

+ Tam Hiep commune (at 1:30 p.m on 02/8/2013)

+ Long Dinh commune (at 8:30 a.m on 01/8/2013)

+ Nhi Binh commune (at 1:30 p.m on 06/8/2013)

+ Diem Hy commune (at 9:30 a.m on 01/8/2013)

- Cai Lay district – Tien Giang province

Page 39: TRANSMISSION EFFICIENCY PROJECT DD2-10-001B · SOUTHERN POWER PROJECT MANAGEMENT BOARD TRANSMISSION EFFICIENCY PROJECT DD2-10-001B SUB-PROJECT REHABILITATION AND UPGRADING OF PHU

Rehabilitation and Upgrading of Phu Lam – Cai Lay 2 220kV Transmission line Resettlement Plan

Owner: Southern Vietnam Power Project Management Board - EVNNPT Page 37 Prepared by: Power Engineering Consulting JS. Company 2

+ Tan Hoi commune (at 1:30 p.m on 07/8/2013)

+ Nhi My commune (at 1:30 p.m on 01/8/2013)

- Binh Chanh district – Ho Chi Minh City

+ Tan Tao ward (at 8:30 a.m on 9/8/2013)

+ Tan Nhut commune, Binh Chanh district (at 2:00 p.m on 9/8/2013)

+ Tan Tuc commune, Binh Chanh district (at 10:30 a.m on 9/8/2013)

(See details in Appendix 4)

Participants in the public consultation meeting include representatives from People’s Committee of commune/ward, Fatherland Front, social organizations at local region, affected people, subproject’s owner and Consultant (PECC2). Representative of commune/ward People’s Committee has presided over and executed the meeting. Representative of PECC2 has briefly presented the main investment items, information on impacts and environmental protection solution, compensation policies, site clearance and power safety of the subproject to relevant authorities of commune/ward level and affected people in region of the subproject. Finally, the representatives of PECC2 and the subproject’s owner answer to all the questions/comment of the participants; and supply relevant information in detail, as well. The opinions of the public consultation meeting are summarized as follows:

Table 5.1: Summary of People’s Opinion in the Public Consultation Meetings

No Location Where

Consultation Took Place,

Date and Time

Participants Summary of Issued or Concerns Discussed/Raised

How Concerns were Taken into Account or Why Not

1 Location: Ward 4, Tan An City, Long An province.

Time: 8:00 a.m on 26/07/2013

Local Authority Representatives and social organizations: 06 persons

Affected Household Representatives: 45 persons

Opinions of local people:

- Mr Tran Minh Tri: House can construct under the ROW, doesn’t it?

- Mr Truong Tan Binh requests that the route should avoid area of city.

- Mr Khoa requests to move this route out of area of the city (ward 4).

- Mr Phan Ban Huan has the same idea as Mr Binh and Khoa.

- Mr Nguyen Tri Thanh: requests to present affects on health to local people under the transmission line.

Opinions of local authorities:

Owner/Consultant’s answers:

- On the Government’s policy, the subproject does not move the route, it only upgrades the existing 220kV route in order to strengthen load capacity and power network connection; and also stabilize power system in the region in accordance with developmental scheme of power.

- Houses still exist under the ROW of 220kV transmission line. Health also does not affect if local people meet all regulations on safety under the 220kV ROW.

Page 40: TRANSMISSION EFFICIENCY PROJECT DD2-10-001B · SOUTHERN POWER PROJECT MANAGEMENT BOARD TRANSMISSION EFFICIENCY PROJECT DD2-10-001B SUB-PROJECT REHABILITATION AND UPGRADING OF PHU

Rehabilitation and Upgrading of Phu Lam – Cai Lay 2 220kV Transmission line Resettlement Plan

Owner: Southern Vietnam Power Project Management Board - EVNNPT Page 38 Prepared by: Power Engineering Consulting JS. Company 2

No Location Where

Consultation Took Place,

Date and Time

Participants Summary of Issued or Concerns Discussed/Raised

How Concerns were Taken into Account or Why Not

- Mr Nha (Vice President): The 220kV transmission line still exist if without upgrading the transmission line, so People’s Committee of ward and local people agree to upgrade the existing 220kV Phu Lam – O Mon transmission line via region of ward 4.

Conclusion and recommendation of People’s Committee:

- People’s Committee and local people will carry according to the policy.

- The owner is requested to execute the next steps and the People’s Committee wishes that the project will complete soon for serving local people’s life.

2 Loacation: Khanh Hau ward, Tan An City, Long An province

Time: 10:00 a.m on 26/07/2013

Local Authority Representatives and social organizations: 05 persons

Affected Household Representatives: 20 persons

Opinions of local people:

- Mr Phan Huu Nghia asks that the land under the ROW will assist/support or not?

Opinions of local authorities:

- Mr Tam: This is a project for upgrading the existing transmission line; the height of this line will be designed higher the old transmission line, so impacts on health is reduced comparison with the original one.

Conclusion and recommendation:

- All staff of authority and affected people agree to implement the subproject of

Owner/Consultant’s answers:

- The owner will not support/assist land in the ROW because this is the existing transmission line.

Page 41: TRANSMISSION EFFICIENCY PROJECT DD2-10-001B · SOUTHERN POWER PROJECT MANAGEMENT BOARD TRANSMISSION EFFICIENCY PROJECT DD2-10-001B SUB-PROJECT REHABILITATION AND UPGRADING OF PHU

Rehabilitation and Upgrading of Phu Lam – Cai Lay 2 220kV Transmission line Resettlement Plan

Owner: Southern Vietnam Power Project Management Board - EVNNPT Page 39 Prepared by: Power Engineering Consulting JS. Company 2

No Location Where

Consultation Took Place,

Date and Time

Participants Summary of Issued or Concerns Discussed/Raised

How Concerns were Taken into Account or Why Not

upgrading of 220kV Phu Lam – Cai Lay 2 transmission line.

3

Location: Huong Tho Phu commune, Tan An City, Long An province

Time: 2:00 p.m on 26/07/2013

Local Authority Representatives and social organizations: 05 persons

Affected Household Representatives: 22 persons

Opinions of local people:

- Mr Luong Van Loc requests that the compensation price shall apply according to market price.

- Mr Tran Van Thanh requests that a new tower shall avoid out of his house.

Opinions of local authorities:

- Mr Quoc: Construction of a new tower shall loss land of local people.

- Mr Vo Van Hung: The existing transmission line hasn’t been compensated land at location of tower foundation in the past so in this subproject, it is requested that the owner should consider to compensate this location of tower foundation.

Conclusion and recommendation of People’s Committee:

- All staff of authority and local people agree to upgrade the existing 220kV Phu Lam – Cai Lay 2 transmission line.

Owner/Consultant’s answers:

- Compensate price will be based on local price of Long An province.

- The project shall design to avoid moving house of local people on the policy, the contractor will compensate in the specified stipulations if happening any damages during construction period.

4 Location: Ward 2, Tan An City, Long An province

Time: 8:00 a.m on 29/07/2013

Local Authority Representatives and social organizations: 09 persons

Affected Household Representativ

Opinions of local people:

- Mrs Uyen: the status on houses under the ROW will be affected when upgrading the existing transmission line, won’t it?

- Mr Dinh: Can it move tower foundation out of the

Owner/Consultant’s answers:

- Houses and structures shall permit to exist under the ROW according to Article 6 of Decision No.81/2009/ND-CP if meet as stipulation. The height of line for upgrading the transmission line will be 18m, it will be higher than

Page 42: TRANSMISSION EFFICIENCY PROJECT DD2-10-001B · SOUTHERN POWER PROJECT MANAGEMENT BOARD TRANSMISSION EFFICIENCY PROJECT DD2-10-001B SUB-PROJECT REHABILITATION AND UPGRADING OF PHU

Rehabilitation and Upgrading of Phu Lam – Cai Lay 2 220kV Transmission line Resettlement Plan

Owner: Southern Vietnam Power Project Management Board - EVNNPT Page 40 Prepared by: Power Engineering Consulting JS. Company 2

No Location Where

Consultation Took Place,

Date and Time

Participants Summary of Issued or Concerns Discussed/Raised

How Concerns were Taken into Account or Why Not

es: 26 persons

current house?

- Mrs Cuc: People can be affected on their health if their house locates under the ROW, can not they? Does the owner solve according to the policy if local people want to move to another place for living?

Conclusion and recommendation of People’s Committee:

- People’s Committee agrees construction of a subproject in local region.

the existing one so the houses under the line will not be affected.

- This is a project of upgrading of the existing transmission line so all tower foundation will keep at the old location without moving.

5 Location: Ward 6, Tan An City, Long An province

Time: 2:00 p.m on 29/07/2013

Local Authority Representatives and social organizations: 04 persons

Affected Household Representatives: 13 persons

Opinions of local people:

- Mrs Lien: House under the ROW will be affected by electro magnetic field so the power branch is requested to give solutions for repairing all damages.

Opinions of local authorities:

- Dao Thi Tai asks that can the transmission line move to the highway to avoid impact on local people?

- Nguyen Van Dung requests that statistics of damages should execute at each quarter of local people.

- Vo Van Binh requests to describe more details for upgrading the existing and new transmission line.

Conclusion and recommendation of People’s Committee:

- Owner needs to consider alternatives for roof-grounding of affected

Owner/Consultant’s answers:

- Mrs Tai: the subproject will not change the route but only upgrading the existing transmission line in order to strengthen load capacity and meet electricity scheme on the policy.

- Mr Trinh: This is phase of preparation of project investment; the procedures of execution will be carried out in the next phase and will get statistics specifically all impacts of each household.

Page 43: TRANSMISSION EFFICIENCY PROJECT DD2-10-001B · SOUTHERN POWER PROJECT MANAGEMENT BOARD TRANSMISSION EFFICIENCY PROJECT DD2-10-001B SUB-PROJECT REHABILITATION AND UPGRADING OF PHU

Rehabilitation and Upgrading of Phu Lam – Cai Lay 2 220kV Transmission line Resettlement Plan

Owner: Southern Vietnam Power Project Management Board - EVNNPT Page 41 Prepared by: Power Engineering Consulting JS. Company 2

No Location Where

Consultation Took Place,

Date and Time

Participants Summary of Issued or Concerns Discussed/Raised

How Concerns were Taken into Account or Why Not

houses to avoid impacts of electro magnetic field to local people.

- People’s Committee and local people agree according to policy and guideline of Government and Party to upgrade this transmission line at local region.

6 Location: Nhi Thanh commune, Thu Thua district, Long An province

Time: 8:00 a.m on 30/07/2013

Local Authority Representatives and social organizations: 01 person

Affected Household Representatives: 8 persons

Opinions of local people:

- Mrs Dung: Based on the existing transmission line, upgrading of the transmission line has to get more new tower? Has not it? House under the ROW has affected when extending foundation, has not it?

Conclusion and recommendation of People’s Committee:

- Agree alternative for upgrading of transmission line.

Owner/Consultant’s answers:

- Mrs Dung: This is a upgrading project on the basic of the existing transmission line so it shall not construct any new tower but only upgrading at location of the current tower foundation. When upgrading the transmission line, some tower foundation will expand and land is affected by this expansion which will be compensated and assisted according to stipulations.

7 Location: Binh Thanh commune, Thu Thua district, Long An province

Time: 10:00 a.m on 30/07/2013

Local Authority Representatives and social organizations: 03 persons

Affected Household Representatives: 6 persons

Opinions of local people:

- Mr Ai: How many distances to allow for constructing tower foundation away a house.

- Mr Quy: When does the subproject construct?

- Mrs Tien requires that all damages shall be compensated properly and timely.

Opinions of local authorities:

Owner/Consultant’s answers:

- Mr Ai: House will allow constructing far 0.5m from tower foundation.

- Mr Quy: The subproject’s schedule will commence in the third quarter of 2013.

- Mrs Tien: the owner will determine damages in details and give compensation and assistance price reasonably.

Page 44: TRANSMISSION EFFICIENCY PROJECT DD2-10-001B · SOUTHERN POWER PROJECT MANAGEMENT BOARD TRANSMISSION EFFICIENCY PROJECT DD2-10-001B SUB-PROJECT REHABILITATION AND UPGRADING OF PHU

Rehabilitation and Upgrading of Phu Lam – Cai Lay 2 220kV Transmission line Resettlement Plan

Owner: Southern Vietnam Power Project Management Board - EVNNPT Page 42 Prepared by: Power Engineering Consulting JS. Company 2

No Location Where

Consultation Took Place,

Date and Time

Participants Summary of Issued or Concerns Discussed/Raised

How Concerns were Taken into Account or Why Not

- Agree alternative for upgrading of transmission line.

8 Location: Thanh Phu commune, Ben Luc district, Long An province

Time: 2:00 p.m on 30/07/2013

Local Authority Representatives and social organizations: 9 persons

Affected Household Representatives: 37 persons

Opinions of local people:

- Mr Chau: Does a house construct in land affected under the ROW? How policy to compensate and assist for all affected land.

- Mr Trieu: Price compensated at tower foundation between 500kV and 220kV projects is difference; why do they compensate at the same price level? What do they compensate if new impacts coincide with the old one? It has to detail households affected by a new transmission line, 500kV line and upgrading line.

- Mr Cuc: the owner is required to give alternatives of compensation and assistance reasonably all impacts/damages of local people.

Opinions of local authorities:

- The 500kV transmission line has been compensated and assisted the affected land in the ROW; so it also required reasonable compensation and assistance to local people for this subproject.

Conclusion and recommendation of People’s Committee:

- People’s Committee and affected households agree to

Owner/Consultant’s answers:

- Mr Chau: Land under the ROW allows existing house if the house complies with the power safety conditions as specified. Assistance and compensation will apply unit price according to stipulations of Long An province.

- Mr Trieu: This is an upgrading project so compensation and assistance will comply with unit price of local region for all impacts/damages. New impact/damage coincides with the old one, which will be compensate according to unit price as specified.

- When investment project completed and approved; it will detail all damages/losses and apply unit price according to stipulations of Long An province.

Page 45: TRANSMISSION EFFICIENCY PROJECT DD2-10-001B · SOUTHERN POWER PROJECT MANAGEMENT BOARD TRANSMISSION EFFICIENCY PROJECT DD2-10-001B SUB-PROJECT REHABILITATION AND UPGRADING OF PHU

Rehabilitation and Upgrading of Phu Lam – Cai Lay 2 220kV Transmission line Resettlement Plan

Owner: Southern Vietnam Power Project Management Board - EVNNPT Page 43 Prepared by: Power Engineering Consulting JS. Company 2

No Location Where

Consultation Took Place,

Date and Time

Participants Summary of Issued or Concerns Discussed/Raised

How Concerns were Taken into Account or Why Not

construct the subproject at local region.

- The owner is required to reasonably compensate for all affected households.

9 Location: Tan Ly Tay commune, Chau Thanh district, Tien Giang province

Time: 8:00 a.m on 31/7/2013

Local Authority Representatives and social organizations: 04 persons

Affected Household Representatives: 35 persons

Opinions of local people:

- Mr Hiep (Tan Phong hamlet): does the house move if upgrading of transmission line?

- The existing transmission line has not been compensated yet; so does it compensate when upgrading the transmission line in this phase.

- The owner is required to compensate and assist local people at location both the damage/loss tower foundation and ROW.

Conclusion and recommendation of People’s Committee:

- Agree to upgrade the existing 220kV transmission line according to the policy.

Owner/Consultant’s answers:

- House under the ROW does not move when complying with power safety conditions.

- The existing transmission line has been constructed for a long time; so in this phase, it will compensate as stipulations at location of the improved tower foundation.

- This transmission line will be upgraded to meet power supply demand for local people and develop socio-economics as well.

10 Location: Tan Huong commune, Chau Thanh district, Tien Giang province

Time: 2:00 p.m on 31/7/2013

Local Authority Representatives and social organizations: 6 persons

Affected Household Representatives: 25 persons

Opinions of local people:

- It is necessary to get permission of relevant authorities when constructing a new house for son.

- Trees have necessary to cut down or not?

- Do people affect when finding out echo-sound at transmission line in the morning?

Owner/Consultant’s answers:

- Construction of a new house shall be met requirements of the relevant authorities in order to ensure safety for ROW and local people as well.

- Trees comply with safety height of transmission line; its trees will be existed in the ROW.

- Compensation and assistance

Page 46: TRANSMISSION EFFICIENCY PROJECT DD2-10-001B · SOUTHERN POWER PROJECT MANAGEMENT BOARD TRANSMISSION EFFICIENCY PROJECT DD2-10-001B SUB-PROJECT REHABILITATION AND UPGRADING OF PHU

Rehabilitation and Upgrading of Phu Lam – Cai Lay 2 220kV Transmission line Resettlement Plan

Owner: Southern Vietnam Power Project Management Board - EVNNPT Page 44 Prepared by: Power Engineering Consulting JS. Company 2

No Location Where

Consultation Took Place,

Date and Time

Participants Summary of Issued or Concerns Discussed/Raised

How Concerns were Taken into Account or Why Not

Opinions of local authorities:

- Relevant authorities are required to apply a reasonable price for local people.

- Electro magnetic field will affect on psychology of local people; so the owner is required to pay attention this work.

will apply unit price according to stipulations of province and it will be assisted and compensated reasonably for local people.

- Echo-sound is a corona effect of transmission line; it will not affect to local people if ROW meets safety distance according to stipulation.

11 Location: Diem Hy commune, Chau Thanh district, Tien Giang province

Time: 8:00 a.m on 01/8/2013

Local Authority Representatives and social organizations: 02 persons

Affected Household Representatives: 17 persons

Opinions of local people:

- Do impacts/damages assist in the ROW?

- Does it compensate all caused impacts/damages during construction phase?

Opinions of local authorities:

- Veterans will propagandize local affected people to advocate and create an advantage condition for executing the subproject.

- Local people are required to obtain the policy for upgrading of the existing transmission line and advocate power branch for completing their duty.

Conclusion and recommendation of People’s Committee:

- Upgrading of the transmission line will ensure power safety and supply for local region.

- Commune and local people agree the policy for constructing subproject.

- Local people are recommended to support

Owner/Consultant’s answers:

- Direct impacts will be compensated, however this is a upgrading project on the existing transmission line; so damages on crops in the ROW will not compensate and assist according to stipulation.

- Damages/looses due to construction will consider to overcome and compensate.

Page 47: TRANSMISSION EFFICIENCY PROJECT DD2-10-001B · SOUTHERN POWER PROJECT MANAGEMENT BOARD TRANSMISSION EFFICIENCY PROJECT DD2-10-001B SUB-PROJECT REHABILITATION AND UPGRADING OF PHU

Rehabilitation and Upgrading of Phu Lam – Cai Lay 2 220kV Transmission line Resettlement Plan

Owner: Southern Vietnam Power Project Management Board - EVNNPT Page 45 Prepared by: Power Engineering Consulting JS. Company 2

No Location Where

Consultation Took Place,

Date and Time

Participants Summary of Issued or Concerns Discussed/Raised

How Concerns were Taken into Account or Why Not

policy for constructing subproject.

- The owner is required to consider assistances reasonably in accordance with stipulation.

12 Location: Long Dinh commune, Chau Thanh district, Tien Giang province

Time: 2:00 p.m on 01/8/2013

Local Authority Representatives and social organizations: 07 persons

Affected Household Representatives: 16 persons

Opinions of local people:

- Do local people construct a house in the ROW?

- The owner and commune co-operate in determination the affected land area, don’t they?

- Is there any compensation on house in the ROW?

Opinions of local authorities:

- People’s Committee of commune unifies to construct the subproject for power supply in local region.

- The owner is required to assist more on trees and houses in the ROW.

Conclusion and recommendation of People’s Committee:

- Upgrading of the transmission line shall ensure power safety and supply in local region.

- Commune unifies to construct the subproject.

- The owner is required to assist more on trees and houses in the ROW.

Owner/Consultant’s answers:

- House allows existing in the ROW but it shall meet stipulations on power safety of Decree 81 of the Government and agreements of operation unit of the transmission line.

- The subproject upgrades the existing transmission line, which has operated for over 20 years; this route completely runs in the old route.

13 Location: Tam Hiep commune, Chau Thanh

Local Authority Representatives and social

Opinions of local people:

- Local people say no idea; they agree all ideas and

Owner/Consultant’s answers:

Page 48: TRANSMISSION EFFICIENCY PROJECT DD2-10-001B · SOUTHERN POWER PROJECT MANAGEMENT BOARD TRANSMISSION EFFICIENCY PROJECT DD2-10-001B SUB-PROJECT REHABILITATION AND UPGRADING OF PHU

Rehabilitation and Upgrading of Phu Lam – Cai Lay 2 220kV Transmission line Resettlement Plan

Owner: Southern Vietnam Power Project Management Board - EVNNPT Page 46 Prepared by: Power Engineering Consulting JS. Company 2

No Location Where

Consultation Took Place,

Date and Time

Participants Summary of Issued or Concerns Discussed/Raised

How Concerns were Taken into Account or Why Not

district, Tien Giang province

Time: 8:00 a.m on 02/8/2013

organizations: 03 persons

Affected Household Representatives: 39 persons

standpoints of President of Commune.

Opinions of local authorities:

- Project belongs to Government/Nation; if the project has been downgraded and then it will be upgraded, however local people has the same ideas that when the project causes any damages on house and trees; its damage should be compensated and assisted according to regulations of Nation.

- On the People’s Committee will assist power unit during executing and constructing the project.

14 Location: Tay Ly Dong commune, Chau Thanh district, Tien Giang province

Time: 10:00 a.m on 02/8/2013

Local Authority Representatives and social organizations: 04 persons

Affected Household Representatives: 25 persons

Opinions of local people:

- Does it compensate more on damage while upgrading of the transmission?

- The current ROW is 22 meters; does this ROW expand when upgrading the project? And height of transmission line has higher than the old, has not it?

- How distance does it get from tower to house? Trees under the ROW have planted or not? Can house construct under the ROW?

- How many towers which is constructed at Tan Ly Dong commune?

- Affected people require that the project has been not compensated yet in the past; they wish that the owner will consider assisting and

Owner/Consultant’s answers:

- Project will be upgraded on the existing transmission line so it will not affect on house; compensation will be carried out as stipulations.

- Project will be upgraded on the existing 220kV transmission line; so the safety corridor will keep 22m in width; height will be 18m from land surface and the lowest point of the transmission line.

- Distance between tower foundations is 400m. However, distance from house to tower shall not only meet permanently acquired land area, which can construct a house but also get distance at least of 6m. Trees allows planting under the ROW but the height of trees

Page 49: TRANSMISSION EFFICIENCY PROJECT DD2-10-001B · SOUTHERN POWER PROJECT MANAGEMENT BOARD TRANSMISSION EFFICIENCY PROJECT DD2-10-001B SUB-PROJECT REHABILITATION AND UPGRADING OF PHU

Rehabilitation and Upgrading of Phu Lam – Cai Lay 2 220kV Transmission line Resettlement Plan

Owner: Southern Vietnam Power Project Management Board - EVNNPT Page 47 Prepared by: Power Engineering Consulting JS. Company 2

No Location Where

Consultation Took Place,

Date and Time

Participants Summary of Issued or Concerns Discussed/Raised

How Concerns were Taken into Account or Why Not

compensating during executing this project.

Opinions of local authorities:

- Power branch and owner are required that project’s implementation shall ensure regulations of the law in force; and limit at least damages/losses of local people.

- It is required to assist and compensate reasonably for local people.

Conclusion and recommendation of People’s Committee”

- Commune agrees to construct project according to policy of Nation.

shall be far from the lowest point of the transmission line of 4m. – There are three tower foundations at Tan Ly Dong commune.

- Power branch will consider compensating and assisting all affected households according to stipulations.

15 Location: Nhi My commune, Cai Lay district, Tien Giang province

Time: 2:00 p.m on 02/08/2013

Local Authority Representatives and social organizations: 02 persons

Affected Household Representatives: 10 persons

Opinions of local people:

- The project has been not compensated and assisted yet in the past for local people; they wish that the owner will consider assisting and compensating reasonably during upgrading of Phu Lam – Cai Lay 2 220kV (households of Nguyen Van Niem and Huynh Thi Dung).

- Local people unify to construct this transmission line; however it is required to overcome all damages and recover as the original status. It is also required to compensate trees and farm produces in the ROW.

Opinions of local authorities:

- Power branch is required that project’s

Owner/Consultant’s answers:

- Before constructing the upgrading of Phu Lam – Cai Lay 2 220kV transmission line, the owner will cooperate with local authority and affected people to determine affected land or trees and give a reasonable compensation plan according to law and stipulations in force.

- The owner commits that any caused damage will be completed and recovered as the original status after finishing the project. The owner also considers to compensate and assist farm produce (if any) in the ROW before the project’s implementation.

Page 50: TRANSMISSION EFFICIENCY PROJECT DD2-10-001B · SOUTHERN POWER PROJECT MANAGEMENT BOARD TRANSMISSION EFFICIENCY PROJECT DD2-10-001B SUB-PROJECT REHABILITATION AND UPGRADING OF PHU

Rehabilitation and Upgrading of Phu Lam – Cai Lay 2 220kV Transmission line Resettlement Plan

Owner: Southern Vietnam Power Project Management Board - EVNNPT Page 48 Prepared by: Power Engineering Consulting JS. Company 2

No Location Where

Consultation Took Place,

Date and Time

Participants Summary of Issued or Concerns Discussed/Raised

How Concerns were Taken into Account or Why Not

implementation shall ensure regulations as law in force in the purpose of limiting damages as follows:

+ Assisting for compensation;

+ Impacting on environment;

+ Co-operating and detailing information to local people; on the basic of this information, the local people will co-operate and agree highly to construct the project.

16 Location: Tan Hiep town, Tien Giang province

Time: 8:00 a.m on 06/08/2013

Local Authority Representatives and social organizations: 2 persons

Affected Household Representatives: 2 persons

Opinions of local people:

- Local people agree to upgrade the Phu Lam – Cai Lay 2 220kV transmission line.

Opinions of local authorities:

- People’s Committee agree to upgrade the Phu Lam – Cai Lay 2 220kV transmission line.

Owner/Consultant’s answers:

17 Location: Nhi Binh commune, Tien Giang province

Thoi gian: lUc 10g ngay 06/08/2013

Local Authority Representatives and social organizations: 4 persons

Affected Household Representatives: 20 persons

Opinions of local people:

- Does it change the ROW of transmission line?

- Does it compensate the affected land in ROW?

Opinions of local authorities:

- People’s Committee has agreed to construct the upgrading of Phu Lam – Cai Lay 2 220kV transmission line.

Owner/Consultant’s answers:

- This is a upgrading project of the existing 220kV transmission line so it does not change the ROW.

- This is a upgrading project of the existing 220kV transmission line; so the owner will consider compensate and assist according to stipulations if the project’s implementation causes impacts/damage to assets and houses of the local people.

18 Location: Than Cuu

Local Authority

Opinions of local people: Owner/Consultant’s answers:

Page 51: TRANSMISSION EFFICIENCY PROJECT DD2-10-001B · SOUTHERN POWER PROJECT MANAGEMENT BOARD TRANSMISSION EFFICIENCY PROJECT DD2-10-001B SUB-PROJECT REHABILITATION AND UPGRADING OF PHU

Rehabilitation and Upgrading of Phu Lam – Cai Lay 2 220kV Transmission line Resettlement Plan

Owner: Southern Vietnam Power Project Management Board - EVNNPT Page 49 Prepared by: Power Engineering Consulting JS. Company 2

No Location Where

Consultation Took Place,

Date and Time

Participants Summary of Issued or Concerns Discussed/Raised

How Concerns were Taken into Account or Why Not

Nghia commune, Tien Giang province

Time: 06/08/2013

Representatives and social organizations: 06 persons

Affected Household Representatives: 65 persons

- There is a tower located in land of Doan Van Chanh’s household, if the subproject upgrades, his house has lost or not?

- The transmission line crosses over the top of the house-roof, it causes any affection to his/her life, isn’t it?

- Mr Duong Van Rong asks that does it compensate when transmission line crosses over the foundation of his house?

Opinions of local authorities:

- Vice President: Demand for power supply is necessary so it shall upgade the existing 220kV transmission line. The People’s Committee agrees a policy of the Government. Firstly, in the public consultation meeting, the power branch/owner only informs information to construct the project and obtain all local people ideas. Site Clearance Council of district will cooperate with local authority to execute compensation for local people in the clearance phase.

Conclusion and recommendation of People’s Committee:

- People’s Committee unifies the policy to construct the project.

- Dao Van Chanh: This is a upgrading project of the existing Phu Lam – Cai Lay 2 220kV transmission line; so if land located in upgrading section will re-construct new tower foundations at location of old foundation and this foundation will be expanded land area comparison with the old one. The owner will consider and assist the expanded land area according to regulations; house will not loss due to non-impact.

- The transmission line is designed in accordance with power standards and specifications so there are not any impacts to local people’s life.

- Transmission line crosses Duong Van Rong’s household will not compensate because this line is an overhead transmission line with a safety distance. It will be allowed constructing and existing house under the 220kV transmission line as stipulation. This is a upgrading project of the existing transmission line so works of design and implementation will meet in accordance with regulations.

Page 52: TRANSMISSION EFFICIENCY PROJECT DD2-10-001B · SOUTHERN POWER PROJECT MANAGEMENT BOARD TRANSMISSION EFFICIENCY PROJECT DD2-10-001B SUB-PROJECT REHABILITATION AND UPGRADING OF PHU

Rehabilitation and Upgrading of Phu Lam – Cai Lay 2 220kV Transmission line Resettlement Plan

Owner: Southern Vietnam Power Project Management Board - EVNNPT Page 50 Prepared by: Power Engineering Consulting JS. Company 2

No Location Where

Consultation Took Place,

Date and Time

Participants Summary of Issued or Concerns Discussed/Raised

How Concerns were Taken into Account or Why Not

19 Location: Thanh Duc commune, Ben Luc district, Long An province

Time: 8:00 a.m on 07/08/2013

Local Authority Representatives and social organizations: 10 persons

Affected Household Representatives: 29 persons

Opinions of local people:

- Mr Ly: According to design of power branch, the safety corridor of 220kV transmission line is 22m in width. If the transmission line happens risk in broken line or tower; does it affect to local people being lived under the transmission line? and how solution does the power branch solve this case?

- Mr Trinh asks his house is located under the transmission line, he wants to move another place; does he compensate for this movement?

- Mr Son: The owner should inform local people an implementation schedule of the project; this aim is to harvest crops out of construction period and limit impacts/damages for crops of local people.

Conclusion and recommendation of People’s Committee:

- Local authority and people agree to upgrade this project.

- The power unit and relevant authorities should consider reasonable compensation and assistance prices for local people in time.

Owner/Consultant’s answers:

- Mr Ly: the safety corridor of 220kV transmission line is 22m in width, this is a safety width as regulations issued by Vietnam and local people can live under the transmission line. Besides, the owner always periodically check to limit and recover risks.

- Mr Trinh: House can exist under the 220kV transmission line if it is in compliance with power safety standards. If his family wants to move another place, the owner will assist in accordance with stipulations of Long An province.

- Mr Son: the owner will inform and detail implementation schedule of project to local authority and people.

Page 53: TRANSMISSION EFFICIENCY PROJECT DD2-10-001B · SOUTHERN POWER PROJECT MANAGEMENT BOARD TRANSMISSION EFFICIENCY PROJECT DD2-10-001B SUB-PROJECT REHABILITATION AND UPGRADING OF PHU

Rehabilitation and Upgrading of Phu Lam – Cai Lay 2 220kV Transmission line Resettlement Plan

Owner: Southern Vietnam Power Project Management Board - EVNNPT Page 51 Prepared by: Power Engineering Consulting JS. Company 2

No Location Where

Consultation Took Place,

Date and Time

Participants Summary of Issued or Concerns Discussed/Raised

How Concerns were Taken into Account or Why Not

20 Location: Tan Hoi commune, Lai Lay district, Tien Giang province

Time: 2:00 p.m on 07/08/2013

Local Authority Representatives and social organizations: 05 persons

Affected Household Representatives: 20 persons

Opinions of local people:

- Mr Rat asks that the local people can not cultivate/plant crops in the construction phase; Can they re-cultivate/re-plant the crop when completing the project?

- Mr Luong: Do it compensate completely land area located in the ROW?

- Mr Vu: Can the local people live under the ROW?

Opinions of local authorities:

- Mr Thanh: The lowest defection of transmission line is 18m; this deflection can affect to local people’s health, can not it?

- The owner is required to set up a reasonable compensation unit price for affected households and execute compensation plan soon to stabilize their production.

Conclusion and recommendation of People’s Committee:

- People’s Committee unifies to construct project in local region.

- It is requires to reasonably and timely compensate for stabilizing production of local people.

Owner/Consultant’s answers:

- Mr Rat: Crops will be affected during construction phase; the local people can cultivate/plant crops after completing the project.

- Mr Luong: It will be compensated land area at location of tower foundation; and it will be assisted the remaining land area in the ROW.

- Mr Vu: This is a upgrading project so it will not change capacity of transmision line (kilovolt), it still is 220kV transmission line so local people can exist under this transmission line in conditions in compliance with power safety standards.

- Mr Thanh: Safety distance between people’s house and transmission line shall comply with Decree 81 of Government so it will not affect to local people’s life.

21 Location: Tan Nhut commune, Binh Chanh district, Ho

Local Authority Representatives and social organizations

Opinions of local people:

- Mr Kinh: Does it compensate damages/losses on crop of local people

Owner/Consultant’s answers:

- Mr Kinh: This is not a new construction project; it only causes in the stringing phase; and the owner will consider

Page 54: TRANSMISSION EFFICIENCY PROJECT DD2-10-001B · SOUTHERN POWER PROJECT MANAGEMENT BOARD TRANSMISSION EFFICIENCY PROJECT DD2-10-001B SUB-PROJECT REHABILITATION AND UPGRADING OF PHU

Rehabilitation and Upgrading of Phu Lam – Cai Lay 2 220kV Transmission line Resettlement Plan

Owner: Southern Vietnam Power Project Management Board - EVNNPT Page 52 Prepared by: Power Engineering Consulting JS. Company 2

No Location Where

Consultation Took Place,

Date and Time

Participants Summary of Issued or Concerns Discussed/Raised

How Concerns were Taken into Account or Why Not

Chi Minh City

Time: 8:00 a.m on 09/08/2013

: 5 persons

Affected Household Representatives: 11 persons

during stringing wire?

Opinions of local authorities:

- Stringing wire of this project shall inform local people.

- The owner is required to assist timely impacts for local people during stringing wire.

Conclusion and recommendation of People’s Committee

- Local authority agrees the policy for constructing project at local region.

reasonable compensation unit price for local people.

22 Location: Tan Tuc town, Binh Chanh district, Ho Chi Minh City

Time:10:30 a.m on 09/08/2013

Local Authority Representatives and social organizations: 01 person

Affected Household Representatives: 0 person

Opinions of local authorities:

- Phu Lam – O Mon 500kV transmission line has not been existed yet 220kV transmission line in region of town.

- The town has not received yet any policy relating on executing project.

Conclusion of People’s Committee:

- People’s Committee requires that relevant authorities shall supply the above requirements and then they will organize a public consultation meeting.

Owner/Consultant’s answers:

23 Location: Tan Tao ward, Ho Chi Minh City

Time: 2:00 p.m on 09/08/2013

Local Authority Representatives and social organizations: 2 persons

Affected Household

Opinions of local authorities:

- Power Engineering Consulting J.S Company 2 has organized a meeting at office of People’s Committee of Tan Tao ward on August 9, 2013; however, Mr Thong (Vice

Page 55: TRANSMISSION EFFICIENCY PROJECT DD2-10-001B · SOUTHERN POWER PROJECT MANAGEMENT BOARD TRANSMISSION EFFICIENCY PROJECT DD2-10-001B SUB-PROJECT REHABILITATION AND UPGRADING OF PHU

Rehabilitation and Upgrading of Phu Lam – Cai Lay 2 220kV Transmission line Resettlement Plan

Owner: Southern Vietnam Power Project Management Board - EVNNPT Page 53 Prepared by: Power Engineering Consulting JS. Company 2

No Location Where

Consultation Took Place,

Date and Time

Participants Summary of Issued or Concerns Discussed/Raised

How Concerns were Taken into Account or Why Not

Representatives: 0 person

President of ward) confirms that the project does not locate in this region so it will not invite households to participate in the public consultation meeting.

5.2. Information Disclosure

Per requirement of Bank’s policy, the Vietnamese version of this draft report was publically disclosed at subproject communes, SPPMB, and VDIC of the World Bank office in Hanoi (Jan. 2014). English version was also disclosed in InfoShop of the World Bank in Washington D.C. Final versions (English and Vietnamese) will also be re-disclosed at project sites, SPPMB, VDIC and InfoShop.

5.3. Complaints and Grievances

DPs are entitled to the complaints regarding their interests and responsibilities in the Project implementation including but not limited to entitlements, compensation policy, unit prices, land acquisition, resettlement and other entitlements related to the recovery support programs. Complaints can also concern issues related to construction safety and nuisances caused by construction. Grievance procedures should be affordable and accessible procedures for third party settlement of disputes arising from resettlement; such grievance mechanisms should take into account the availability of judicial recourse and community and traditional dispute settlement mechanisms.

The mechanism of complaint and grievances resolution steps are as below:

First Stage - At Commune People’s Committee (CPC)

An aggrieved DP may bring his/her complaint to any member of the CPC, in writing or verbally. It is incumbent upon said member of CPC to notify the CPC about the complaint. The CPC will meet personally with the aggrieved DP and will have 15 days following the lodging of the complaint to resolve it. The CPC secretariat is responsible for documenting and keeping file of all complaints that it handles.

Second Stage - At District People’s Committee (DPC)

If after 15 days the aggrieved DP does not hear from the CPC, or if the CPC gives its solutions, but DP is not satisfied with the decision taken on his/her complaint, the DP may bring the case, either in writing or verbally, to any member of DPC or DCB. The DCB in turn will have 30 days to resolve the case. The DPC is responsible for documenting and keeping file of all complaints that it handles.

Third Stage - At Provincial People’s Committee (PPC)

If after 30 days the aggrieved DP does not hear from the DCB, or if the DP is not satisfied with the decision taken on his/her complaint, the DP may bring the case, either in writing or verbally, to any member of the PPC. The PPC has 45 days within which to resolve the

Page 56: TRANSMISSION EFFICIENCY PROJECT DD2-10-001B · SOUTHERN POWER PROJECT MANAGEMENT BOARD TRANSMISSION EFFICIENCY PROJECT DD2-10-001B SUB-PROJECT REHABILITATION AND UPGRADING OF PHU

Rehabilitation and Upgrading of Phu Lam – Cai Lay 2 220kV Transmission line Resettlement Plan

Owner: Southern Vietnam Power Project Management Board - EVNNPT Page 54 Prepared by: Power Engineering Consulting JS. Company 2

complaint to the satisfaction of all concerned. The PPC secretariat is also responsible for documenting and keeping file of all complaints that it handles.

Final Stage - Court of Law Decides

If after 45 days following the lodging of the complaint with the PPC, the aggrieved DP does not hear from the PPC, or if he/she is not satisfied with the decision taken on his/her complaint, the case may be brought to a court of law for adjudication. Under no circumstance, can the DP be evicted from his/her property nor can the Government take over his/her property without the explicit permission of the court.

In order to minimize complaints, SPMB (via their assigned grievance focal point or grievance facilitation unit – GFU) will cooperate with the District Compensation Board/ Center for Land Development Fund to participate in and consult on settling complaints. Names and contact details of Grievance Focal Points and/or the Grievance Facilitation Unit (GFU) will be made publically available in information brochures and at project areas.

Local mass organizations such as Fatherland Front, Farmer’s Union, Women’s Union will be mobilized to participate actively in the process of resolving complaints, questions. The independent monitoring agency will be responsible for checking the procedures for and resolutions of grievances and complaints. The independent monitoring agency may recommend further measures to be taken to redress unresolved grievances.

DPs will be exempted from all administrative and legal fees. Besides that, an escrow accounts for resettlement payments should be used when grievance is resolving to avoid excessive delay of the project while ensuring compensation payment after the grievance has been resolved. SPMB should maintain a system to register queries, suggestions and grievances of the DPs. All queries, suggestions and grievances and their resolution should be recorded and forwarded to the PC and its functioning monitored monthly. SPMB will formulate and maintain a database of the DPs’ grievances related to the Project to ensure that all complaints are recorded, recognized and processed by the functional units at all levels.

Page 57: TRANSMISSION EFFICIENCY PROJECT DD2-10-001B · SOUTHERN POWER PROJECT MANAGEMENT BOARD TRANSMISSION EFFICIENCY PROJECT DD2-10-001B SUB-PROJECT REHABILITATION AND UPGRADING OF PHU

Rehabilitation and Upgrading of Phu Lam – Cai Lay 2 220kV Transmission line Resettlement Plan

Owner: Southern Vietnam Power Project Management Board - EVNNPT Page 55 Prepared by: Power Engineering Consulting JS. Company 2

6. REPORT, SUPERVISION/MONITORING AND EVALUATION

The implementation of RP will be periodically supervised and monitored by the SPMB in a close coordination with Peoples' Committees at different administrative units and independent monitoring agencies. The findings will be recorded in quarterly reports to be furnished to NPT, SPMB, and World Bank.

6.1. Internal Monitoring and Supervision

Internal monitoring and supervision for the RP’s implementation shall be the responsibility of SPMB. The internal monitoring and supervision will:

- Verify that the baseline information of all DPs has been carried out and that the valuation of assets lost or damaged, and the provision of compensation, resettlement and other rehabilitation entitlements have been carried out in accordance with the provisions of this Policy Framework and this RP.

- Oversee that the RPs are implemented as designed and approved.

- Verify that funds for implementing the RP are provided to the SPMB in a timely manner and in sufficient amounts for their purposes, and that such funds are used by SPMB in accordance with the provisions of the RP and policy framework.

- Record all grievances and their resolution and ensure that complaints are dealt with in a timely manner.

Officer in charge of resettlement, site clearance compensation of implementation agencies of the subproject shall take responsibility for updating information on the basis of the following main activities:

Table 6.1: Some main activities for internal monitoring and evaluation

No Activities of RP Implementation

Description/Note Yes No

1. Announcement of all information about the subproject to local authority and people

2. Total lost inventory

3. Investigation of replacement cost

4. RP’s preparation

5. RP’s approval

- EVN/NPT

- Long An Province People’s Committee

- WB

6. RP’s disclosure

Long An province

- Thu Thua district:

+ Nhi Thanh commune;

+ Binh Thanh commune;

Page 58: TRANSMISSION EFFICIENCY PROJECT DD2-10-001B · SOUTHERN POWER PROJECT MANAGEMENT BOARD TRANSMISSION EFFICIENCY PROJECT DD2-10-001B SUB-PROJECT REHABILITATION AND UPGRADING OF PHU

Rehabilitation and Upgrading of Phu Lam – Cai Lay 2 220kV Transmission line Resettlement Plan

Owner: Southern Vietnam Power Project Management Board - EVNNPT Page 56 Prepared by: Power Engineering Consulting JS. Company 2

No Activities of RP Implementation

Description/Note Yes No

- Tan An City:

+ Huong Tho Phu commune;

+ Ward 6;

+ Ward 2;

+ Ward 4;

+ Khanh Hau ward; Tien Giang province

- Chau Thanh district

+ Tan Huong commune;

+ Tan Ly Tay commune;

+ Tan Ly Dong commune;

+ Tan Hiep commune;

+ Than Cuu Nghia commune;

+ Tam Hiep commune;

+ Long Dinh commune;

+ Nhi Binh commune;

+ Diem Hy commune;

- Cai Lay district

+ Tan Hoi commune;

+ Nhi My commune.

- Long An Power Company

- Tien Giang Power Company

- VDIC/Infoshop

7. Counting, measuring lands

8. Applying a compensation price (from RP)

9. Preparation for a specific compensation plan

10. Approval of compensation alternative

11. Disclosure of compensation alternative

12. Adjustment and approval (if any)

13. Compensation payment (including all updates comparison with RP – ex: number of APs, budgets, level of impacts etc.)

14. Internal monitoring

15. Independent monitoring

16. Report of implementation plan

Page 59: TRANSMISSION EFFICIENCY PROJECT DD2-10-001B · SOUTHERN POWER PROJECT MANAGEMENT BOARD TRANSMISSION EFFICIENCY PROJECT DD2-10-001B SUB-PROJECT REHABILITATION AND UPGRADING OF PHU

Rehabilitation and Upgrading of Phu Lam – Cai Lay 2 220kV Transmission line Resettlement Plan

Owner: Southern Vietnam Power Project Management Board - EVNNPT Page 57 Prepared by: Power Engineering Consulting JS. Company 2

No Activities of RP Implementation

Description/Note Yes No

17. Collecting and resolving all grievances

18. Public consultation and participants

- Public consultation

- Providing leaflet

19. Coordinating with other relevant authorities (specially Compensation Council)

20. Mid-term and end-term evaluation (together with project)

6.2. Independent Monitoring

An independent agency or agencies or individual consultant will be retained by SPMB to periodically carry out external monitoring and evaluation of the implementation of RP. The independent agencies would be an academic or research institutions, non-Governmental Organizations (NGO) or independent consulting firms, all with qualified and experienced staff and terms of reference acceptable to the World Bank. Depending on the magnitude of project impact, borrower with consultation from Task’s Team of the World Bank will decide the extent of using independent monitoring consultant. In addition to verifying the information furnished in the internal supervision and monitoring reports of the SPMB, the external monitoring agency will collect information from affected households.

6.3. Reporting

Internal monitoring agency will prepare quarterly report with detail of its implementation schedule, this report shall send to EVN/NPT, WB and external monitoring agency. The terms and condition applicable to the external monitoring agency shall be stipulated in detail in the contract of both parties (the external monitoring agency and SPMB).

A Resettlement Plan cannot be considered as complete until a completion audit or survey confirms that all entitlements have been received by beneficiaries and livelihood restoration is progressing on schedule.

Page 60: TRANSMISSION EFFICIENCY PROJECT DD2-10-001B · SOUTHERN POWER PROJECT MANAGEMENT BOARD TRANSMISSION EFFICIENCY PROJECT DD2-10-001B SUB-PROJECT REHABILITATION AND UPGRADING OF PHU

Rehabilitation and Upgrading of Phu Lam – Cai Lay 2 220kV Transmission line Resettlement Plan

Owner: Southern Vietnam Power Project Management Board - EVNNPT Page 58 Prepared by: Power Engineering Consulting JS. Company 2

7. IMPLEMENTATION PLAN

7.1. Implementation responsibility

Southern Power Projects Management Board (SPMB) representing NPT, have following responsibilities:

- Prepare RPs in accordance with the RPF. Coordinate with the provincial People’s Committees and local authorities to obtain consensus from provincial People’s Committee for the RPs and submit them to the WB for review and clearance.

- Develop and implement a training program for the provincial and district People’s Committee’s, relevant stakeholders involved in RP implementation and Grievance Redress.

- Where relevant, provide technical support (e.g. consultation mobilization) in identifying the replacement cost to inform compensation rate during the RP implementation.

- Secure timely availability of required budget for RP preparation and implementation;

- Conduct internal monitoring of RP implementation as per requirements set out in the project’s RPF and the RPs.

- Prepare bi-annual progress reports and submit to WB

- Designate staff with solid experience in resettlement and familiar with Bank’s safeguard policies as a social focal point for PMB.

- Take part in compensation, support and resettlement council at local level and ensure that the agreed RPs are properly implemented, documented and reported.

- Work closely with competent governmental agencies to address concern, grievances related to resettlement in their managed subprojects.

Provincial People’s Committees have responsibilities as follows:

- To direct, organize, propagate and mobilize all organizations and individuals concerning compensation, support and resettlement policies and ground clearance according to the land recovery decisions of competent State bodies;

- To direct the provincial/municipal services, departments, branches and district-level People's Committees: (i) To draw up resettlement and resettlement area plans in service of the land recovery; (ii) To draw up compensation, support and resettlement plans according to their competence;

- To approve or assign the district-level People's Committees to approve compensation, support and resettlement plans;

- To approve land prices; promulgate the property price tables for compensation calculation; prescribe support levels and supporting measures according to their competence; resettlement arrangement plans, job change training plans according to their assigned competence;

- To direct the concerned agencies to settle citizens' complaints, denunciations related to compensation, support and resettlement according to their law-prescribed competence;

- To guarantee impartiality and equity when considering and deciding on the compensation, support and resettlement when land is recovered by the State according to their competence prescribed in this Decree;

- To decide or assign the district-level People's Committees to apply coercion to cases of deliberately failing to abide by the State's land recovery decisions according to their

Page 61: TRANSMISSION EFFICIENCY PROJECT DD2-10-001B · SOUTHERN POWER PROJECT MANAGEMENT BOARD TRANSMISSION EFFICIENCY PROJECT DD2-10-001B SUB-PROJECT REHABILITATION AND UPGRADING OF PHU

Rehabilitation and Upgrading of Phu Lam – Cai Lay 2 220kV Transmission line Resettlement Plan

Owner: Southern Vietnam Power Project Management Board - EVNNPT Page 59 Prepared by: Power Engineering Consulting JS. Company 2

competence;

- To direct the examination and handling of violations in the compensation, support and resettlement domain.

The District People’s Committees have responsibilities as follows:

- To direct, organize, propagate and mobilize all organizations and individuals concerning compensation, support and resettlement policies and ground clearance according to the land recovery decisions of competent State bodies;

- To direct the compensation, support and resettlement councils of the same level to draw up, and organize the implementation of, the compensation, support and resettlement plans; approve the compensation, support and resettlement plans according to the responsibility assignment by the provincial-level People's Committees;

- To coordinate with the provincial/municipal services, departments and branches, organizations and investors in executing investments projects to build and plans to create resettlement areas in their localities according to the assignment of the provincial-level People's Committees;

- To settle citizens' complaints, denunciations related to compensation, support and resettlement according to their assigned competence; issue coercive decisions and organizing coercion in the cases falling under their competence; coordinate with the functional agencies in organizing coercion according to the decisions of competent bodies.

The compensation, support and resettlement councils shall assist the People's Committees of the same level in making, and organizing the implementation of, compensation, support and resettlement arrangement plans; work on the collective principle and decide by majority; where the numbers of votes for and against are equal, the opinion of the side joined by the council chairman shall be followed. Responsibilities of council members are as follow:

- The council chairman shall direct the council members to make, submit for approval and organize the implementation of, the compensation, support and resettlement plan;

- The investor shall be responsible for assisting the council chairman in making the compensation, support and resettlement plan, ensuring sufficient funds for timely payment of compensation, support and resettlement money;

- Representatives of persons who have land recovered shall be responsible for reflecting the aspirations of persons who have land recovered, persons who must be relocated; mobilizing persons who have land recovered to move and clear the ground according to schedule;

- Other members shall perform the tasks as assigned and directed by the council chairman, suitable to their respective branches.

- The compensation, support and resettlement councils shall be responsible for the accuracy and rationality of inventory statistics, the legality of land and property eligible or ineligible for compensation, supports in the compensation, support and resettlement.

The Center for Land Fund Development has main responsibilities related to resettlement as follows:

- To assume the prime responsibility for, or coordinate the with the compensation and ground clearance council in, organizing compensation and ground clearance;

- To work and coordinate closely with project’s stakeholders to update and implement RP as per project’s RPF.

Page 62: TRANSMISSION EFFICIENCY PROJECT DD2-10-001B · SOUTHERN POWER PROJECT MANAGEMENT BOARD TRANSMISSION EFFICIENCY PROJECT DD2-10-001B SUB-PROJECT REHABILITATION AND UPGRADING OF PHU

Rehabilitation and Upgrading of Phu Lam – Cai Lay 2 220kV Transmission line Resettlement Plan

Owner: Southern Vietnam Power Project Management Board - EVNNPT Page 60 Prepared by: Power Engineering Consulting JS. Company 2

- To provide compensation and ground clearance services;

- To develop resettlement areas;

- To build infrastructure on land funds assigned to it for management in order to organize auction;

- To provide information on land prices and land funds to organizations and individuals upon request;

- To assist the District People’s Committee and Provincial People’s Committee in disseminating information related to Resettlement Plan.

- To assist the District People’s Committee in handling complaints at district level.

- To perform other tasks under decisions of the provincial-level People's Committee.

The Commune People's Committees shall have the responsibilities:

- To organize propaganda on the land recovery purposes, compensation, support and resettlement polices of the projects;

- To coordinate with the compensation, support and resettlement councils in certifying land and property of persons who have land recovered;

- To join in, and create conditions for, the payment of compensation and support money to, and arrange resettlement for, persons who have land recovered, and create conditions for the ground clearance.

7.2. Implementation Schedule

7.2.1. Proposed Schedule of the Subproject

Table 7.1: Proposed implementation schedule of the subproject

Items Schedule

Preparation of document and cost estimate for investment project

March,2011 – May,2011

Preparation and approval for investment project March,2011 – May,2012

Preparation of detail design September,2013

Approval of detail design Junuary,2014

Clearance and compensation Quarter I of 2014 – Quarter II of 2015

Preparation of bidding documents February,2014

Bidding April,2014

Construction drawing (phase 1) Quarter II of 2014

Completion Quarter IV of 2015

Page 63: TRANSMISSION EFFICIENCY PROJECT DD2-10-001B · SOUTHERN POWER PROJECT MANAGEMENT BOARD TRANSMISSION EFFICIENCY PROJECT DD2-10-001B SUB-PROJECT REHABILITATION AND UPGRADING OF PHU

Rehabilitation and Upgrading of Phu Lam – Cai Lay 2 220kV Transmission line Resettlement Plan

Owner: Southern Vietnam Power Project Management Board - EVNNPT Page 61 Prepared by: Power Engineering Consulting JS. Company 2

7.2.2. Proposed Schedule of RP

Fifteen months are necessary to implement RP.

Table 7.2: Proposed implementation schedule of RP

No. Activities of RP First month

Second month

Third month

Forth month

Fifth month

Sixth month

Seventh month

Eighth month

Ninth month

Tenth month

Eleventh month

Twentieth month

Thirteenth month

Fourteenth month

Fifteenth month

1 Inform people and local authorities about the subproject.

x

2 Total loss inventory x x x 3 Replacement cost

survey x x

4 RP preparation x x x 5 RP approval x x 6 RP announcement x 7 Land counting and

measuring x x x

8 Applying compensation price (from RP)

x x

9 Preparing detail compensation plan

x x

10 Approval of compensation plan

x

11 Announcement of compensation plan

x

12 Adjustment and approval (if necessary)

x

13 Compensation payment (including update comparing to RP – ex: number of APs, finance, impacts…)

x x x x x x

Page 64: TRANSMISSION EFFICIENCY PROJECT DD2-10-001B · SOUTHERN POWER PROJECT MANAGEMENT BOARD TRANSMISSION EFFICIENCY PROJECT DD2-10-001B SUB-PROJECT REHABILITATION AND UPGRADING OF PHU

Rehabilitation and Upgrading of Phu Lam – Cai Lay 2 220kV Transmission line Resettlement Plan

Owner: Southern Vietnam Power Project Management Board - EVNNPT Page 62 Prepared by: Power Engineering Consulting JS. Company 2

No. Activities of RP First month

Second month

Third month

Forth month

Fifth month

Sixth month

Seventh month

Eighth month

Ninth month

Tenth month

Eleventh month

Twentieth month

Thirteenth month

Fourteenth month

Fifteenth month

14 Internal monitoring x x x x x x x x x x x x x x x 15 Independent

monitoring x x x

16 Plan implementing report

x x

17 Collecting and solving complaints

x x x x x x

18 Consulting and people’s participating

x x x x x x x x x

- Community meeting

x x

- Leaflet delivery x x 19 Collaborating with

other organization (especially Compensation Council)

x x x x x x x x x x x x

20 Mid-term and final-term assessment (with sub-project)

x x

Note: The first month is the commencement date of surveys for the establishment of RP.

Page 65: TRANSMISSION EFFICIENCY PROJECT DD2-10-001B · SOUTHERN POWER PROJECT MANAGEMENT BOARD TRANSMISSION EFFICIENCY PROJECT DD2-10-001B SUB-PROJECT REHABILITATION AND UPGRADING OF PHU

Rehabilitation and Upgrading of Phu Lam – Cai Lay 2 220kV Transmission line Resettlement Plan

Owner: Southern Vietnam Power Project Management Board – EVNNPT Page 63 Prepared by: Power Engineering Consulting JS. Company 2

8. COST AND BUDGET 8.1. Budget

The budget for RP’s implementation is from EVNNPT’s reciprocal funds.The funds will be channeled to SPMB who will work with local competent agencies (in provinces of Long An and Tien Giang) to implement the RP as approval.

8.2. Costs of RP Implementation

Costs of the RP implementation include:

8.2.1. Cost of RP Preparation

At the beginning of the RP implementation, a survey team shall be established to (a) study design and survey the subproject site, (b) prepare forms of survey and statistics (preliminary measurement of real estates and property statistics), (c) organize community consultation meetings etc. … (d) analyze data and (e) prepare RP for approval.

SPMB has signed contract with consultant to carry out the above tasks:

Consultant contract value: 95,000,000 VND

8.2.2. Cost of Compensation, Assistance

- Compensation for permanently and temporarily acquired land.

- Compensation for permanently and temporarily affected trees and crops.

- Assistances according to national stipulations and the bank’s policy.

Table 8.1: Compensation estimated cost for the subproject

No Items for compensation Unit Quantity Unit price

(VND) Amount (VND)

A LONG AN province 17,399,936,923

I Compensation for permanent effects 4,343,914,825

I.1 Compensation for land 4,240,135,000 I.1.1 Agricultural land m2 851,000,000

- Annual tree m2 603,483,000

+ Thu Thua district m2 242,847,500

Nhi Thanh commune m2 1,353.75 70,000 94,762,500

Binh Thanh commune m2 2,115.50 70,000 148,085,000

+ Tan An City m2 360,635,500

Huong Tho Phu commune m2 1,559.30 85,000 132,540,500

Ward 4 m2 628.30 95,000 59,688,500

Khanh Hau ward m2 1,772.70 95,000 168,406,500

- Perennial tree m2 132,242,000

+ Thu Thua district m2 28,350,000

Nhi Thanh commune m2 405.00 70,000 28,350,000

+ Tan An city m2 103,892,000

Ward 4 m2 1,093.60 95,000 103,892,000

Page 66: TRANSMISSION EFFICIENCY PROJECT DD2-10-001B · SOUTHERN POWER PROJECT MANAGEMENT BOARD TRANSMISSION EFFICIENCY PROJECT DD2-10-001B SUB-PROJECT REHABILITATION AND UPGRADING OF PHU

Rehabilitation and Upgrading of Phu Lam – Cai Lay 2 220kV Transmission line Resettlement Plan

Owner: Southern Vietnam Power Project Management Board – EVNNPT Page 64 Prepared by: Power Engineering Consulting JS. Company 2

No Items for compensation Unit Quantity Unit price

(VND) Amount (VND)

- Land for aquaculture m2 115,275,000

+ Tan An city m2 115,275,000

Ward 6 m2 451.00 75,000 33,825,000

Ward 2 m2 280.00 75,000 21,000,000

Ward 4 m2 483.00 75,000 36,225,000

Khanh Hau ward m2 323.00 75,000 24,225,000

I.1.2 Residential land 3,389,135,000

+ Tan An city m2 3,389,135,000

Huong Tho Phu commune m2 305.30 700,000 213,710,000

Ward 2 m2 483.00 5,500,000 2,656,500,000

Ward 4 m2 305.25 1,700,000 518,925,000

I.2 Plants, crops, domestic animal 103,779,825 Rice m2 6,538.55 1,500 9,807,825

Grass m2 568.00 1,500 852,000

Banana tree 49 40,000 1,960,000

Fruit tree tree 106 280,000 29,680,000

Pond m2 1,537.00 40,000 61,480,000

II Compensation for plants, crops and domestic animals affected in ROW 1,070,836,598

Rice m2 148,718 1,500 223,077,694

Crops m2 1,056 3,900 4,118,903

Fruit tree tree 3,013 280,000 843,640,000

III Assistance 12,070,685,500

III.1 Assistance on occupational change (by money according the price of revoked agricultural land) 4,255,000,000

- Annual tree m2 3,017,415,000

+ Thu Thua district m2 1,214,237,500

Nhi Thanh commune m2 1,353.75 350,000 473,812,500

Binh Thanh commune m2 2,115.50 350,000 740,425,000

+ Tan An city m2 1,803,177,500

Huong Tho Phu commune m2 1,559.30 425,000 662,702,500

Ward 6 m2 0.00 475,000 0

Ward 4 m2 628.30 475,000 298,442,500

Khanh Hau ward m2 1,772.70 475,000 842,032,500

- Perennial tree m2 661,210,000

+ Thu Thua district m2 141,750,000

Nhi Thanh commune m2 405.00 350,000 141,750,000

+ Tan An city m2 519,460,000

Ward 4 m2 1,093.60 475,000 519,460,000

Page 67: TRANSMISSION EFFICIENCY PROJECT DD2-10-001B · SOUTHERN POWER PROJECT MANAGEMENT BOARD TRANSMISSION EFFICIENCY PROJECT DD2-10-001B SUB-PROJECT REHABILITATION AND UPGRADING OF PHU

Rehabilitation and Upgrading of Phu Lam – Cai Lay 2 220kV Transmission line Resettlement Plan

Owner: Southern Vietnam Power Project Management Board – EVNNPT Page 65 Prepared by: Power Engineering Consulting JS. Company 2

No Items for compensation Unit Quantity Unit price

(VND) Amount (VND)

- Land for aquaculture m2 576,375,000

+ Tan An city m2 576,375,000

Ward 6 m2 451.00 375,000 169,125,000

Ward 2 m2 280.00 375,000 105,000,000

Ward 4 m2 483.00 375,000 181,125,000

Khanh Hau ward m2 323.00 375,000 121,125,000

III.2 Assistance for agricultural land in residential area 7,636,135,500

+ Thu Thua district m2 1,355,987,500

Nhi Thanh commune m2 1,758.75 350,000 615,562,500

Binh Thanh commune m2 2,115.50 350,000 740,425,000

+ Tan An city m2 6,280,148,000

Huong Tho Phu commune m2 1,559.30 490,000 764,057,000

Ward 6 m2 451.00 770,000 347,270,000

Ward 2 m2 280.00 3,850,000 1,078,000,000

Ward 4 m2 2,204,90 1,190,000 2,623,831,000

Khanh Hau ward m2 2,095.70 700,000 1,466,990,000

III.3 Support in manufacturing stability 179,550,000

Household having 20% (or 10% in case of vulnerable households) to 70% of agricultural land under use revoked (18 households, 85 people, support 6 month)

Person 85 1,710,000 145,350,000

Household having more than 70% of agricultural land under use revoked (3 households, 10 people, support 12 months)

Person 10 3,420,000 34,200,000

B TIEN GIANG province 32,274,589,804

I Compensation for permanent effects

3,896,567,000

I.1 Compensation for land 3,040,127,750 I.1.1 Agricultural land m2 1,961,855,750

- Annual tree m2 670,542,500

+ Chau Thanh district m2 486,370,500

Tan Huong commune m2 1,763.90 70,000 123,473,000

Tan Ly Tay commune m2 788.30 70,000 55,181,000

Tan Ly Dong commune m2 288.00 70,000 20,160,000

Than Cuu Nghia commune m2 628.30 70,000 43,981,000

Tam Hiep commune m2 1,797.15 70,000 125,800,500

Page 68: TRANSMISSION EFFICIENCY PROJECT DD2-10-001B · SOUTHERN POWER PROJECT MANAGEMENT BOARD TRANSMISSION EFFICIENCY PROJECT DD2-10-001B SUB-PROJECT REHABILITATION AND UPGRADING OF PHU

Rehabilitation and Upgrading of Phu Lam – Cai Lay 2 220kV Transmission line Resettlement Plan

Owner: Southern Vietnam Power Project Management Board – EVNNPT Page 66 Prepared by: Power Engineering Consulting JS. Company 2

No Items for compensation Unit Quantity Unit price

(VND) Amount (VND)

Diem Hy commune m2 1,682.50 70,000 117,775,000

+ Cai Lay district m2 184,172,000

Tan Hoi commune m2 1,644.40 70,000 115,108,000

Nhi My commune m2 863.30 80,000 69,064,000

- Perennial tree m2 1,251,713,250

+ Chau Thanh district m2 1,091,760,750

Tan Huong commune m2 305.30 85,000 25,950,500

Tan Ly Tay commune m2 323.00 85,000 27,455,000

Tan Ly Dong commune m2 585.30 85,000 49,750,500

Tan Hiep commune m2 305.30 110,000 33,583,000

Than Cuu Nghia commune m2 2,673.20 85,000 227,222,000

Tam Hiep commune m2 898.60 85,000 76,381,000

Long Dinh commune m2 5,383.55 85,000 457,601,750

Nhi Binh commune m2 1,491.90 85,000 126,811,500

Diem Hy commune m2 788.30 85,000 67,005,500

+ Cai Lay district m2 159,952,500

Tan Hoi commune m2 202.50 85,000 17,212,500

Nhi My commune m2 1,427.40 100,000 142,740,000

- Land for aquaculture m2 39,600,000

+ Cai Lay district m2 39,600,000

Nhi My commune m2 495.00 80,000 39,600,000

I.1.2 Industrial land 1,078,272,000

+ Chau Thanh district m2 1,078,272,000

Tan Huong commune m2 1,152.00 936,000 1,078,272,000

I.2 Plants, crops, domestic animals 856,439,250 Rice m2 9,455.85 5,000 47,279,250

Fruit tree tree 1,012 780,000 789,360,000

Pond m2 495.00 40,000 19,800,000

II Compensation for plants, crops and domestic animals affected in ROW 17,117,501,879

Rice m2 159,897 5,000 799,485,685

Crops m2 67,672 14,000 947,406,194

Grass m2 1,078.00 5,000 5,390,000

Fruit tree tree 19,699 780,000 15,365,220,000

III Assistance 11,205,440,925

III.1 Assistance on occupational change (by money according to the price of revoked agricultural land) 4,904,639,375

- Annual tree m2 1,676,356,250

+ Chau Thanh district m2 1,215,926,250

Page 69: TRANSMISSION EFFICIENCY PROJECT DD2-10-001B · SOUTHERN POWER PROJECT MANAGEMENT BOARD TRANSMISSION EFFICIENCY PROJECT DD2-10-001B SUB-PROJECT REHABILITATION AND UPGRADING OF PHU

Rehabilitation and Upgrading of Phu Lam – Cai Lay 2 220kV Transmission line Resettlement Plan

Owner: Southern Vietnam Power Project Management Board – EVNNPT Page 67 Prepared by: Power Engineering Consulting JS. Company 2

No Items for compensation Unit Quantity Unit price

(VND) Amount (VND)

Tan Huong commune m2 1,763.90 175,000 308,682,500

Tan Ly Tay commune m2 788.30 175,000 137,952,500

Tan Ly Dong commune m2 288.00 175,000 50,400,000

Than Cuu Nghia commune m2 628.30 175,000 109,952,500

Tam Hiep commune m2 1,797.15 175,000 314,501,250

Diem Hy commune m2 1,682.50 175,000 294,437,500

+ Cai Lay district m2 460,430,000

Tan Hoi commune m2 1,644.40 175,000 287,770,000

Nhi My commune m2 863.30 200,000 172,660,000

- Perennial tree m2 3,129,283,125

+ Chau Thanh district m2 2,729,401,875

Tan Huong commune m2 305.30 212,500 64,876,250

Tan Ly Tay commune m2 323.00 212,500 68,637,500

Tan Ly Dong commune m2 585.30 212,500 124,376,250

Tan Hiep commune m2 305.30 275,000 83,957,500

Than Cuu Nghia commune m2 2,673.20 212,500 568,055,000

Tam Hiep commune m2 898.60 212,500 190,952,500

Long Dinh commune m2 5,383.55 212,500 1,144,004,375

Nhi Binh commune m2 1,491.90 212,500 317,028,750

Diem Hy commune m2 788.30 212,500 167,513,750

+ Cai Lay district m2 399,881,250

Tan Hoi commune m2 202.50 212,500 43,031,250

Nhi My commune m2 1,427.40 250,000 356,850,000

- Land for aquaculture m2 99,000,000

+ Cai Lay district m2 99,000,000

Nhi My commune m2 495.00 200,000 99,000000

III.2 Assistance for agricultural land in residential area 6,025,401,550

+ Chau Thanh district m2 4,566,132,550

Tan Huong commune m2 2,069.20 196,000 405,563,200

Tan Ly Tay commune m2 1,111.30 189,000 210,035,700

Tan Ly Dong commune m2 873.30 161,000 140,601,300

Tan Hiep commune m2 305.30 490,000 149,597,000

Than Cuu Nghia commune m2 3,301.50 189,000 623,983,500

Tam Hiep commune m2 2,695.75 336,000 905,772,000

Long Dinh commune m2 5,383.55 245,000 1,318,969,750

Nhi Binh commune m2 1,491.90 231,000 344,628,900

Diem Hy commune m2 2,470.80 189,000 466,981,200

Page 70: TRANSMISSION EFFICIENCY PROJECT DD2-10-001B · SOUTHERN POWER PROJECT MANAGEMENT BOARD TRANSMISSION EFFICIENCY PROJECT DD2-10-001B SUB-PROJECT REHABILITATION AND UPGRADING OF PHU

Rehabilitation and Upgrading of Phu Lam – Cai Lay 2 220kV Transmission line Resettlement Plan

Owner: Southern Vietnam Power Project Management Board – EVNNPT Page 68 Prepared by: Power Engineering Consulting JS. Company 2

No Items for compensation Unit Quantity Unit price

(VND) Amount (VND)

+ Cai Lay district m2 1,459,269,000

Tan Hoi commune m2 1,846.90 315,000 581,773,500

Nhi My commune m2 2,785.70 315,000 877,495,500

III.3 Support in manufacturing stability 330,480,000

Household having 20% (or 10% in case of vulnerable housholds) to 70% of agricultural land under use revoked (43 households, 186 people, support 6 month)

Person

186 1,620,000 301,230,000

Household having more than 70% of agricultural land under use revoked (2 households, 9 people, support 12 months)

Person

9 3,240,000 29,160,000

TOTAL (A + B) 49,760,026,727

8.2.3. Cost for Compensation Council (Management Cost)

Preparation of the RP implementation, the support groups of the District Compensation Council shall be mobilized to implement (a) preparation of detailed mapping and statistical table, documents and information on resettlement, (b) organizations community meetings, (c) detailed mapping and inventory, (d) negotiate with APs and (e) complete compensation for APs and submitted for approval to District People’s Committee.

The cost for compensation council will be about 2% of the total compensation cost.

8.2.4. Cost for Independent Monitoring

Temporarily estimated cost for independent monitoring: 500,000,000 VND.

8.2.5. Contingency Cost

Pursuant to the proposed period for RP’s implementation (proposed in the first quarter of 2014) and experiences of other subprojects with similar natures/scope, which have been implemented and being implementing, the contingency cost is estimated about 10% total cost of compensation and the RP preparation.

8.3. Total Estimated Cost for RP’s Implementation

Table 8.2: Total estimated cost for the RP’s implementation

Unit: VND

No Items Amount

1 RP’s preparation 95,000,000

2 Cost for compensation and assistance 49,760,026,727

3 Cost for Compensation Council (2% of 2) 995,200,535

4 Cost for independent monitoring (temporarily estimated) 500,000,000

5 Contigency cost (10% of 2) 4,976,002,673

Total (1+2+3+4+5) 56,326,229,934

Page 71: TRANSMISSION EFFICIENCY PROJECT DD2-10-001B · SOUTHERN POWER PROJECT MANAGEMENT BOARD TRANSMISSION EFFICIENCY PROJECT DD2-10-001B SUB-PROJECT REHABILITATION AND UPGRADING OF PHU

Rehabilitation and Upgrading of Phu Lam – Cai Lay 2 220kV Transmission line Resettlement Plan

Owner: Southern Vietnam Power Project Management Board – EVNNPT Page 69 Prepared by: Power Engineering Consulting JS. Company 2

Appendices

App

endi

ces

1. Map of site area

2. Entitlement Matrix

3. Site/location Agreement

4. Minutes and pictures on public consultation meetings

5. Statistics on the number of APs by the subproject

Page 72: TRANSMISSION EFFICIENCY PROJECT DD2-10-001B · SOUTHERN POWER PROJECT MANAGEMENT BOARD TRANSMISSION EFFICIENCY PROJECT DD2-10-001B SUB-PROJECT REHABILITATION AND UPGRADING OF PHU

Upgrading of Phu Lam – Cai Lay 2 220kV Transmission line Resettlement Plan

Owner: Southern Vietnam Power Project Management Board- EVNNPT Page 70 Prepared by: Power Engineering Consulting JS. Company 2

Appendix 1: Map of the subproject

Page 73: TRANSMISSION EFFICIENCY PROJECT DD2-10-001B · SOUTHERN POWER PROJECT MANAGEMENT BOARD TRANSMISSION EFFICIENCY PROJECT DD2-10-001B SUB-PROJECT REHABILITATION AND UPGRADING OF PHU

Upgrading of Phu Lam – Cai Lay 2 220kV Transmission line Resettlement Plan

Owner: Southern Vietnam Power Project Management Board- EVNNPT Page 71 Prepared by: Power Engineering Consulting JS. Company 2

Appendix 2: Entitlement Matrix

Type of Loss/ Impacts

Application Entitlements Implementation Arrangements

1. Productive land (Agricultural, garden, pond land, etc.) either in or out of the residential area.

Legal land users

1.1. Marginal loss (<20% of land holding or <10% for vulnerable group) The remaining area of affected plot is still economically viable for use or meets the expected personal yield.

Cash compensation at replacement cost (free from taxes and transaction costs) at 100% replacement cost for the lost area.

- Affected households to be notified at least ninety days before land recovery by the Project.

- The owner of land will hand over the land within 20 days from the date District Compensation Board fully pays compensation for land.

- For vulnerable and severely affected households, affected farmers, including landless, allocation of arable land equal per capita arable land in commune. If there no land available for allocation or, on the DPs’ request through informed choice, training/ rehabilitation programs will be provided to at least restore, if not improve, their income and living standards.

1.2. Loss >20% or >10% for vulnerable groups

Land for land compensation should be as the preferred option. If land is not available, or at the DP’s choice, cash compensation can be provided for the lost area at 100% of land replacement cost. The DP will be provided with the additional rehabilitation measures to restore the lost income sources

- Other assistance options which each province could decide based on the locality conditions.

- Affected households to be notified at least ninety days before land recovery by the Project (Land law-2003; Article 39- Item 2).

- The owner of land will hand over the land within 20 days from the date District Compensation Board/ Land Fund Development Center has paid compensation and other allowances in full.

- For poor, vulnerable and severely affected farmers, including landless, allocation of arable land equal to per capita arable land in commune, or if there no land available for allocation or, on the DPs request through informed choice, training/ rehabilitation programs will be provided to at least restore, if not improve, their income and living standards.

Land Users with temporary or leased rights to use land.

Cash compensation at the amount corresponding to the remaining investment on the land or corresponding to the remaining value of the land rental contract.

Land Users who do not have formal or customary rights to the

DPs will receive assistance corresponding up to 100% of the land value in cash. In addition to above, rehabilitation/training assistance will be provided.

Page 74: TRANSMISSION EFFICIENCY PROJECT DD2-10-001B · SOUTHERN POWER PROJECT MANAGEMENT BOARD TRANSMISSION EFFICIENCY PROJECT DD2-10-001B SUB-PROJECT REHABILITATION AND UPGRADING OF PHU

Upgrading of Phu Lam – Cai Lay 2 220kV Transmission line Resettlement Plan

Owner: Southern Vietnam Power Project Management Board- EVNNPT Page 72 Prepared by: Power Engineering Consulting JS. Company 2

Type of Loss/ Impacts

Application Entitlements Implementation Arrangements

affected land In case the DP uses public land where there was previous agreement to return the land to the Government when so requested, they will not be compensated for the acquired public land but will be compensated for structures, crops, trees and other assets on the land at 100% of the replacement cost.

2. Residential land

2.1. Marginal loss (i.e., land is still viable for use and not requiring relocation).

Compensation for loss of land in cash at (i) replacement cost to the legal and legalizable land users; (ii) An financial assistance of an agreed amount to the land users not having recognizable land use right.

If DPs have to rebuild their houses, they will receive a house rental allowance for 3 months in recognition of the time needed to rebuild their houses.

- Affected household to be notified at least 180 days before land recovery by the Project.

- The owner of land will hand over the land within 20 days from the date District Compensation Board/ Land Fund Development Center has paid compensation in full.

2.2. Relocated DPs

(i) Legal or legalizable land users:

It land is not available, a land plot in a resettlement site or apartment will be provided to the DP, in consultation with them. They will have full land title or apartment ownership title without any cost to them.

Or, on request of the DPs through informed choice, cash compensation at full replacement cost plus the amount equivalent to the value of the infrastructure investments calculated averagely for each household in a resettlement site. In this case, they will be expected to relocate themselves.

If the compensation amounts to less than the cost of a land plot in the project’s resettlement site, DPs will be provided additional supported to enable them to acquire the land plot (or cash assistance will be provided equivalent to this difference for self-relocated

- Affected household to be notified at least 180 days before land recovery by the Project.

- The owner of land will hand over the land within 20 days from the date District Compensation Board/ Land Fund Development Center has paid compensation in full.

The process of compensation for a plot at the resettlement site will be as follows:

- If the selling cost of plot(s) at the new site is more than the value of the affected residential land, DPs receive new plot at no additional cost.

- If the plot(s) at the new site is equal the value of affected residential land, DPs receive new plot at the new site without any balance.

- If the plot(s) at the new site is less than the value of affected residential land, DPs will receive plot and the difference in cash.

The planning and detailed design for the relocation sites will be done

Page 75: TRANSMISSION EFFICIENCY PROJECT DD2-10-001B · SOUTHERN POWER PROJECT MANAGEMENT BOARD TRANSMISSION EFFICIENCY PROJECT DD2-10-001B SUB-PROJECT REHABILITATION AND UPGRADING OF PHU

Upgrading of Phu Lam – Cai Lay 2 220kV Transmission line Resettlement Plan

Owner: Southern Vietnam Power Project Management Board- EVNNPT Page 73 Prepared by: Power Engineering Consulting JS. Company 2

Type of Loss/ Impacts

Application Entitlements Implementation Arrangements

DPs).

(ii) DPs who do not have formal, or customary rights to the affected land:

An identified assistance amount will be provided based on the level of legality of the land and on a case by case basis.

If the DP has no place to move, a land plot or an apartment satisfactory to them will be provided in the resettlement site.

In case the relocated DP belong to vulnerable groups, the project will consider providing them with additional assistance (in cash and kind) to ensure that they can afford to relocated to a new site.

by consultant of DCB/ CLDF in consultation with stakeholders and then approved by the PPC.

Detailed regulation on plot allocation will be developed by DCB/CLDF through consultation with commune and DPs, followed by approval of PPC.

For relocating households, assistance is in form of land-for-land of similar characteristics with title at no cost. The replacement land is no less than 40m2, or compensation in cash with equal value if DP opts for self-relocation.

Area and number of resettlement sites will be decided in consultation with DPs.

For poor or vulnerable DPs who have no other residential land in the same as their affected commune, the project will provide either a residential plot of minimum size at a common resettlement site, or an individual resettlement site, with title to the land (plot of 40 m2 in urban area and 100m2 in rural area); or on request of the DP, through informed choice, an assistance amount corresponding 60% of the land replacement cost for them to rearrange relocation by themselves.

3. Houses

3.1. Partial impact: Unaffected portion of the house is still viable for use and could be remained from the technical viewpoints, therefore, require no relocation.

- If house/structure is partially affected and the remaining structure is viable for continued use, the project will provide a house/structure repair cost, in addition to the compensation for affected portion at replacement cost, to enable DPs to restore it to former or better conditions.

- Compensation for other structures/fixed assets will be at full replacement cost and will be in cash.

The calculation of rates will be based on the actual affected area and not the useable area.

Page 76: TRANSMISSION EFFICIENCY PROJECT DD2-10-001B · SOUTHERN POWER PROJECT MANAGEMENT BOARD TRANSMISSION EFFICIENCY PROJECT DD2-10-001B SUB-PROJECT REHABILITATION AND UPGRADING OF PHU

Upgrading of Phu Lam – Cai Lay 2 220kV Transmission line Resettlement Plan

Owner: Southern Vietnam Power Project Management Board- EVNNPT Page 74 Prepared by: Power Engineering Consulting JS. Company 2

Type of Loss/ Impacts

Application Entitlements Implementation Arrangements

3.2. Full impact (i.e., house is partially acquired by the project but no longer viable for continued use or the entire structure is acquired).

- Compensation in cash for entire affected structures will be provided at 100% of the full replacement cost for materials and labor, regardless of whether or not they have title to the affected land or permit to build the affected structure. The amount will be sufficient to rebuild a structure the same as the former one at current market prices. No deductions will be made for depreciation or salvageable materials.

- Compensation for other structures/fixed assets will be at full replacement cost and will be in cash. Tenants of state or organization’s houses will be: (i) entitled to rent or buy a new apartment of the area at least equal to their affected ones; or (ii) provided an assistance equal 60% of replacement cost of the affected land and houses. Any investments such as structures, trees, crops etc. made on the land by the DPs will be compensated at their full replacement cost.

The tenants who are leasing a private house for living purposes will be provided with transportation allowance for moving their assets. They will also be assisted in identifying alternative accommodation.

The calculation of rates will be based on the actual affected area and not the useable area.

4. Crops and Trees, aquaculture products

Owners regardless of tenure status

For annual and perennial standing crops or trees, aquaculture products regardless of the legal status of the land, compensation in cash will be paid to the affected persons, who cultivate the land, at full replacement cost in local markets to ensure the compensation is sufficient to replace the lost standing crops, trees or aquaculture products.

DPs will be given notice several months in advance regarding evacuation. Crops grown after issuance of the deadline will not be compensated.

6. Public structures

Loss of, or damage to assets

Either in (i) cash compensation to cover the cost of restoring the facilities or (ii) in kind compensation based on the negotiation between District Compensation Board/ Land Fund Development Center

For public structures, the displacement will be carried out by the owners prior to the start of works.

Page 77: TRANSMISSION EFFICIENCY PROJECT DD2-10-001B · SOUTHERN POWER PROJECT MANAGEMENT BOARD TRANSMISSION EFFICIENCY PROJECT DD2-10-001B SUB-PROJECT REHABILITATION AND UPGRADING OF PHU

Upgrading of Phu Lam – Cai Lay 2 220kV Transmission line Resettlement Plan

Owner: Southern Vietnam Power Project Management Board- EVNNPT Page 75 Prepared by: Power Engineering Consulting JS. Company 2

Type of Loss/ Impacts

Application Entitlements Implementation Arrangements

and owners of assets.

7. Communal-owned assets, collective assets

Loss of,, or damage to assets of village, ward, commune, district, provincial government unit.

Either (i) cash compensation to cover the cost of restoring the facilities or (ii) in kind compensation based on the negotiation between DCB/ CLDF and owners of assets.

For the communal owned assets directly affecting lives and production activities of the community, restoration must be done prior to the start of works.

8. Graves

Have to move the graves or tombs

- All costs of excavation, relocation and reburial will be reimbursed in cash to the affected family.

- Graves to be exhumed and relocated in culturally sensitive and appropriate ways.

9. Loss of Income/ Livelihood due to loss of productive land

Impacts due to permanent loss of 20% or more of their total productive land or where <20% land affected but the remaining land is rendered unviable.

(Legal, legalizable land users and DPs with lease agreement over the affected land)

- Allowance for Loss of Livelihood: Affected person will be compensated with one-time payment at cash equivalent to 30 kg of rice/person/month at local market price , including:

(a) DPs losing 20 - 70% of their agricultural landholding (or 10 - 70% for the poor and vulnerable groups) will be provided with the amount equivalent to 30 kg of rice/person/month for 6 months if they do not have to relocate and 12 months in case of relocation. In some special cases, in extremely difficult areas, the compensation may be provided for a maximum of 24 months;

(b) DPs losing more than 70% of their agricultural landholding will be assisted for 12 months if they do not have to relocate and 24 months in case of relocation. In some special cases, in extremely difficult areas, the compensation may be provided upto a maximum of 36 months; .(c) Households affected by loss of less than 20% of land, where the remaining land is rendered unviable for continued use, will be assisted with the above support plus any additional support as

The amount will be given in tranches every 6 months to coincide with the cropping season while affected households are taking part in the income restoration program in order to restore their pre-project income/livelihood.

Page 78: TRANSMISSION EFFICIENCY PROJECT DD2-10-001B · SOUTHERN POWER PROJECT MANAGEMENT BOARD TRANSMISSION EFFICIENCY PROJECT DD2-10-001B SUB-PROJECT REHABILITATION AND UPGRADING OF PHU

Upgrading of Phu Lam – Cai Lay 2 220kV Transmission line Resettlement Plan

Owner: Southern Vietnam Power Project Management Board- EVNNPT Page 76 Prepared by: Power Engineering Consulting JS. Company 2

Type of Loss/ Impacts

Application Entitlements Implementation Arrangements

determined, for a period of 12 months. In case of land-for-land compensation, DPs will be assisted with seedlings, agricultural-forestry extension programs, husbandry etc.

Support for job changing: Every DP affected by loss of productive land, irrespective of the degree of impact, will be provided with additional assistance equivalent to 2 - 5 times the compensation amount.

Support for vocational training and job creation: DPs will be exempted from exemption from tuition fees for the training courses for those of working age (not applicable for those who enroll for a vocational training outside the province). After finishing training courses, they will be given priorities to be recruited in local manufacturers/businesses.

10. Loss of Income/ Livelihood due to relocation of business

Marginal impacts

Owner of the affected business and employees

For DPs losing income and/or business/productive assets as a result of land acquisition, the mechanism for compensating will be:

• The registered non-farm producer/business DPs, who have income-generating and/or business/productive assets affected, will be given cash business assistance for the loss of business income, equivalent to 50% of the annual average for the last 3 years net income. (This amount is equivalent to 100% of monthly net income for 6 months).

• The non-registered business or non-farm producer DPs, whose operations are recognized by local authority and who have income and/or

Page 79: TRANSMISSION EFFICIENCY PROJECT DD2-10-001B · SOUTHERN POWER PROJECT MANAGEMENT BOARD TRANSMISSION EFFICIENCY PROJECT DD2-10-001B SUB-PROJECT REHABILITATION AND UPGRADING OF PHU

Upgrading of Phu Lam – Cai Lay 2 220kV Transmission line Resettlement Plan

Owner: Southern Vietnam Power Project Management Board- EVNNPT Page 77 Prepared by: Power Engineering Consulting JS. Company 2

Type of Loss/ Impacts

Application Entitlements Implementation Arrangements

business/productive assets affected, will be given assistance in cash for the income losses for three months at the minimum

• If the business has to be relocated, then, a priority to provide a replacement business site accessible to customers, or, compensation in cash for the affected area at a replacement cost, plus transportation allowance to remove movable attached assets. If there is no land available, then the business/non-farm producer DPs will be entitled for rehabilitation measures such as job training, credit access to help restore the income sources

Relocating shop owners regardless of tenure status.

If the business has to be relocated, the project will provide alternative site with local advantage and physical attributes similar to the land lost with easy access to customers base, satisfactory to the DP, OR compensation in cash for the affected land at replacement cost, plus transportation allowance for movable attached assets.

DPs will be given priority for business relocation along highway, communal roads and along canals near the bridges or footbridges in order to maximize their benefit from business opportunities. At the time of compensation, allowances will be adjusted to account for inflation.

11. Allowances /Assistance Targeted to Vulnerable Households

Loss of land and non-land assets Affected vulnerable groups regardless of severity of impacts. The vulnerable groups were defined as in Terms of Terminology

Specific assistance to vulnerable groups would be as follows:

-Social Policy: (i) Relocating Households that include heroic mothers, war veterans, wounded or dead soldiers families will be provided with support as regulated by the PPCs but not less than VND 10 mil per household: (ii) Poor Relocated Households or Poor Households where 20% or more of their productive land is affected or where <20% land is affected but the remaining land is rendered unviable: 3-5 mil/HH (to be certified by local authority).

- Other vulnerable groups affected by the Project, whether they have to relocate or not, (female headed households, households with disabled persons, elderly

- Allowance for households as per Government regulation (social policy households, heroic mothers, wounded, dead soldiers). If the household eligible to more than one additional support allowance for the vulnerable people, only one package with the highest value will be applied.

Page 80: TRANSMISSION EFFICIENCY PROJECT DD2-10-001B · SOUTHERN POWER PROJECT MANAGEMENT BOARD TRANSMISSION EFFICIENCY PROJECT DD2-10-001B SUB-PROJECT REHABILITATION AND UPGRADING OF PHU

Upgrading of Phu Lam – Cai Lay 2 220kV Transmission line Resettlement Plan

Owner: Southern Vietnam Power Project Management Board- EVNNPT Page 78 Prepared by: Power Engineering Consulting JS. Company 2

Type of Loss/ Impacts

Application Entitlements Implementation Arrangements

without any source of support, ethnic minority households) will get the same support given to poor households in accordance with the provincial policy but not less than VND 3 mil per household.

- These households are entitled to take part in Income Restoration Program

12. Other Allowances/ Assistances

Loss of land and non-land assets

Incentive Bonus: A bonus of maximum 5 million VND will be awarded to DPs who dismantle their houses and vacate their premises in accordance with the resettlement schedule.

Repair Allowance: If house/structure is partially affected and the remaining structure is viable for continued use, the project will ensure that these will be restored or repaired at no cost for the community and to the community’s satisfaction.

The relocating households with children who are going to schools will be supported with 1-year tuition as regulated by the Ministry of Education

Based on the actual situation of the locality, the PPC Chairman issues other allowances to ensure accommodation and livelihood restoration for DPs. Special cases have to be submitted to the Prime Minister for approval.

13. Temporary impacts

Temporary loss of land

and assets.

Compensation for all affected assets/investments made on the land, including trees, crops etc., at full replacement cost;

Cash compensation for land temporarily acquired in the form of rent which is at least equivalent to the net income that would have been derived from the affected

If the quality of land is radically changed when returned to DPs, requiring DPs to change in the types of land use; then DPs should be compensated for all envisaged cost of losses.

Page 81: TRANSMISSION EFFICIENCY PROJECT DD2-10-001B · SOUTHERN POWER PROJECT MANAGEMENT BOARD TRANSMISSION EFFICIENCY PROJECT DD2-10-001B SUB-PROJECT REHABILITATION AND UPGRADING OF PHU

Upgrading of Phu Lam – Cai Lay 2 220kV Transmission line Resettlement Plan

Owner: Southern Vietnam Power Project Management Board- EVNNPT Page 79 Prepared by: Power Engineering Consulting JS. Company 2

Type of Loss/ Impacts

Application Entitlements Implementation Arrangements

property during the period of disruption;

Restoration of the land within 3 months after use: The contractor is expected to return the land in its original condition within 3 months of the termination of the civil works.

14. Any other impacts that may be identified during implementation

Individuals, organizations in the project area

Entitlements to compensation and other assistance would be provided in accordance with the compensation policy.

Secondary impacts on production and business or DPs isolated from access to resources temporarily have to be compensated and supported in accordance with RP.

In case of impacts on livelihoods of DPs, the contractors, construction units have to agree with the households on payment for disruption of business.

Page 82: TRANSMISSION EFFICIENCY PROJECT DD2-10-001B · SOUTHERN POWER PROJECT MANAGEMENT BOARD TRANSMISSION EFFICIENCY PROJECT DD2-10-001B SUB-PROJECT REHABILITATION AND UPGRADING OF PHU

Upgrading of Phu Lam – Cai Lay 2 220kV Transmission line Resettlement Plan

Page 1

Appendix 3: Subproject’s site agreement

Page 83: TRANSMISSION EFFICIENCY PROJECT DD2-10-001B · SOUTHERN POWER PROJECT MANAGEMENT BOARD TRANSMISSION EFFICIENCY PROJECT DD2-10-001B SUB-PROJECT REHABILITATION AND UPGRADING OF PHU

Upgrading of Phu Lam – Cai Lay 2 220kV Transmission line Resettlement Plan

Page 2

Page 84: TRANSMISSION EFFICIENCY PROJECT DD2-10-001B · SOUTHERN POWER PROJECT MANAGEMENT BOARD TRANSMISSION EFFICIENCY PROJECT DD2-10-001B SUB-PROJECT REHABILITATION AND UPGRADING OF PHU

Upgrading of Phu Lam – Cai Lay 2 220kV Transmission line Resettlement Plan

Page 3

Page 85: TRANSMISSION EFFICIENCY PROJECT DD2-10-001B · SOUTHERN POWER PROJECT MANAGEMENT BOARD TRANSMISSION EFFICIENCY PROJECT DD2-10-001B SUB-PROJECT REHABILITATION AND UPGRADING OF PHU

Upgrading of Phu Lam – Cai Lay 2 220kV Transmission line Resettlement Plan

Page 4

Page 86: TRANSMISSION EFFICIENCY PROJECT DD2-10-001B · SOUTHERN POWER PROJECT MANAGEMENT BOARD TRANSMISSION EFFICIENCY PROJECT DD2-10-001B SUB-PROJECT REHABILITATION AND UPGRADING OF PHU

Upgrading of Phu Lam – Cai Lay 2 220kV Transmission line Resettlement Plan

Page 5

Page 87: TRANSMISSION EFFICIENCY PROJECT DD2-10-001B · SOUTHERN POWER PROJECT MANAGEMENT BOARD TRANSMISSION EFFICIENCY PROJECT DD2-10-001B SUB-PROJECT REHABILITATION AND UPGRADING OF PHU

Upgrading of Phu Lam – Cai Lay 2 220kV Transmission line Resettlement Plan

Page 6

Page 88: TRANSMISSION EFFICIENCY PROJECT DD2-10-001B · SOUTHERN POWER PROJECT MANAGEMENT BOARD TRANSMISSION EFFICIENCY PROJECT DD2-10-001B SUB-PROJECT REHABILITATION AND UPGRADING OF PHU

Upgrading of Phu Lam – Cai Lay 2 220kV Transmission line Resettlement Plan

Page 7

Page 89: TRANSMISSION EFFICIENCY PROJECT DD2-10-001B · SOUTHERN POWER PROJECT MANAGEMENT BOARD TRANSMISSION EFFICIENCY PROJECT DD2-10-001B SUB-PROJECT REHABILITATION AND UPGRADING OF PHU

Upgrading of Phu Lam – Cai Lay 2 220kV Transmission line Resettlement Plan

Page 8

Page 90: TRANSMISSION EFFICIENCY PROJECT DD2-10-001B · SOUTHERN POWER PROJECT MANAGEMENT BOARD TRANSMISSION EFFICIENCY PROJECT DD2-10-001B SUB-PROJECT REHABILITATION AND UPGRADING OF PHU

Upgrading of Phu Lam – Cai Lay 2 220kV Transmission line Resettlement Plan

Page 9

Appendix 4: Minutes and pictures of public consultation meeting

1) Tan Nhut Commune, Binh Chanh District, HCM City

Page 91: TRANSMISSION EFFICIENCY PROJECT DD2-10-001B · SOUTHERN POWER PROJECT MANAGEMENT BOARD TRANSMISSION EFFICIENCY PROJECT DD2-10-001B SUB-PROJECT REHABILITATION AND UPGRADING OF PHU

Upgrading of Phu Lam – Cai Lay 2 220kV Transmission line Resettlement Plan

Page 10

Page 92: TRANSMISSION EFFICIENCY PROJECT DD2-10-001B · SOUTHERN POWER PROJECT MANAGEMENT BOARD TRANSMISSION EFFICIENCY PROJECT DD2-10-001B SUB-PROJECT REHABILITATION AND UPGRADING OF PHU

Upgrading of Phu Lam – Cai Lay 2 220kV Transmission line Resettlement Plan

Page 11

Page 93: TRANSMISSION EFFICIENCY PROJECT DD2-10-001B · SOUTHERN POWER PROJECT MANAGEMENT BOARD TRANSMISSION EFFICIENCY PROJECT DD2-10-001B SUB-PROJECT REHABILITATION AND UPGRADING OF PHU

Upgrading of Phu Lam – Cai Lay 2 220kV Transmission line Resettlement Plan

Page 12

Page 94: TRANSMISSION EFFICIENCY PROJECT DD2-10-001B · SOUTHERN POWER PROJECT MANAGEMENT BOARD TRANSMISSION EFFICIENCY PROJECT DD2-10-001B SUB-PROJECT REHABILITATION AND UPGRADING OF PHU

Upgrading of Phu Lam – Cai Lay 2 220kV Transmission line Resettlement Plan

Page 13

Page 95: TRANSMISSION EFFICIENCY PROJECT DD2-10-001B · SOUTHERN POWER PROJECT MANAGEMENT BOARD TRANSMISSION EFFICIENCY PROJECT DD2-10-001B SUB-PROJECT REHABILITATION AND UPGRADING OF PHU

Upgrading of Phu Lam – Cai Lay 2 220kV Transmission line Resettlement Plan

Page 14

2) Tan Tuc Commune, Binh Chanh District, Tp.HCM

Page 96: TRANSMISSION EFFICIENCY PROJECT DD2-10-001B · SOUTHERN POWER PROJECT MANAGEMENT BOARD TRANSMISSION EFFICIENCY PROJECT DD2-10-001B SUB-PROJECT REHABILITATION AND UPGRADING OF PHU

Upgrading of Phu Lam – Cai Lay 2 220kV Transmission line Resettlement Plan

Page 15

Page 97: TRANSMISSION EFFICIENCY PROJECT DD2-10-001B · SOUTHERN POWER PROJECT MANAGEMENT BOARD TRANSMISSION EFFICIENCY PROJECT DD2-10-001B SUB-PROJECT REHABILITATION AND UPGRADING OF PHU

Upgrading of Phu Lam – Cai Lay 2 220kV Transmission line Resettlement Plan

Page 16

3) Thanh Phu Commune, Ben Luc District, Long An Province

Page 98: TRANSMISSION EFFICIENCY PROJECT DD2-10-001B · SOUTHERN POWER PROJECT MANAGEMENT BOARD TRANSMISSION EFFICIENCY PROJECT DD2-10-001B SUB-PROJECT REHABILITATION AND UPGRADING OF PHU

Upgrading of Phu Lam – Cai Lay 2 220kV Transmission line Resettlement Plan

Page 17

Page 99: TRANSMISSION EFFICIENCY PROJECT DD2-10-001B · SOUTHERN POWER PROJECT MANAGEMENT BOARD TRANSMISSION EFFICIENCY PROJECT DD2-10-001B SUB-PROJECT REHABILITATION AND UPGRADING OF PHU

Upgrading of Phu Lam – Cai Lay 2 220kV Transmission line Resettlement Plan

Page 18

Page 100: TRANSMISSION EFFICIENCY PROJECT DD2-10-001B · SOUTHERN POWER PROJECT MANAGEMENT BOARD TRANSMISSION EFFICIENCY PROJECT DD2-10-001B SUB-PROJECT REHABILITATION AND UPGRADING OF PHU

Upgrading of Phu Lam – Cai Lay 2 220kV Transmission line Resettlement Plan

Page 19

Page 101: TRANSMISSION EFFICIENCY PROJECT DD2-10-001B · SOUTHERN POWER PROJECT MANAGEMENT BOARD TRANSMISSION EFFICIENCY PROJECT DD2-10-001B SUB-PROJECT REHABILITATION AND UPGRADING OF PHU

Upgrading of Phu Lam – Cai Lay 2 220kV Transmission line Resettlement Plan

Page 20

Page 102: TRANSMISSION EFFICIENCY PROJECT DD2-10-001B · SOUTHERN POWER PROJECT MANAGEMENT BOARD TRANSMISSION EFFICIENCY PROJECT DD2-10-001B SUB-PROJECT REHABILITATION AND UPGRADING OF PHU

Upgrading of Phu Lam – Cai Lay 2 220kV Transmission line Resettlement Plan

Page 21

4) Thanh Duc Commune, Ben Luc District, Long An Province

Page 103: TRANSMISSION EFFICIENCY PROJECT DD2-10-001B · SOUTHERN POWER PROJECT MANAGEMENT BOARD TRANSMISSION EFFICIENCY PROJECT DD2-10-001B SUB-PROJECT REHABILITATION AND UPGRADING OF PHU

Upgrading of Phu Lam – Cai Lay 2 220kV Transmission line Resettlement Plan

Page 22

Page 104: TRANSMISSION EFFICIENCY PROJECT DD2-10-001B · SOUTHERN POWER PROJECT MANAGEMENT BOARD TRANSMISSION EFFICIENCY PROJECT DD2-10-001B SUB-PROJECT REHABILITATION AND UPGRADING OF PHU

Upgrading of Phu Lam – Cai Lay 2 220kV Transmission line Resettlement Plan

Page 23

Page 105: TRANSMISSION EFFICIENCY PROJECT DD2-10-001B · SOUTHERN POWER PROJECT MANAGEMENT BOARD TRANSMISSION EFFICIENCY PROJECT DD2-10-001B SUB-PROJECT REHABILITATION AND UPGRADING OF PHU

Upgrading of Phu Lam – Cai Lay 2 220kV Transmission line Resettlement Plan

Page 24

Page 106: TRANSMISSION EFFICIENCY PROJECT DD2-10-001B · SOUTHERN POWER PROJECT MANAGEMENT BOARD TRANSMISSION EFFICIENCY PROJECT DD2-10-001B SUB-PROJECT REHABILITATION AND UPGRADING OF PHU

Upgrading of Phu Lam – Cai Lay 2 220kV Transmission line Resettlement Plan

Page 25

Page 107: TRANSMISSION EFFICIENCY PROJECT DD2-10-001B · SOUTHERN POWER PROJECT MANAGEMENT BOARD TRANSMISSION EFFICIENCY PROJECT DD2-10-001B SUB-PROJECT REHABILITATION AND UPGRADING OF PHU

Upgrading of Phu Lam – Cai Lay 2 220kV Transmission line Resettlement Plan

Page 26

Page 108: TRANSMISSION EFFICIENCY PROJECT DD2-10-001B · SOUTHERN POWER PROJECT MANAGEMENT BOARD TRANSMISSION EFFICIENCY PROJECT DD2-10-001B SUB-PROJECT REHABILITATION AND UPGRADING OF PHU

Upgrading of Phu Lam – Cai Lay 2 220kV Transmission line Resettlement Plan

Page 27

5) Nhi Thanh Commune, Thu Thua District, Long An Province

Page 109: TRANSMISSION EFFICIENCY PROJECT DD2-10-001B · SOUTHERN POWER PROJECT MANAGEMENT BOARD TRANSMISSION EFFICIENCY PROJECT DD2-10-001B SUB-PROJECT REHABILITATION AND UPGRADING OF PHU

Upgrading of Phu Lam – Cai Lay 2 220kV Transmission line Resettlement Plan

Page 28

Page 110: TRANSMISSION EFFICIENCY PROJECT DD2-10-001B · SOUTHERN POWER PROJECT MANAGEMENT BOARD TRANSMISSION EFFICIENCY PROJECT DD2-10-001B SUB-PROJECT REHABILITATION AND UPGRADING OF PHU

Upgrading of Phu Lam – Cai Lay 2 220kV Transmission line Resettlement Plan

Page 29

Page 111: TRANSMISSION EFFICIENCY PROJECT DD2-10-001B · SOUTHERN POWER PROJECT MANAGEMENT BOARD TRANSMISSION EFFICIENCY PROJECT DD2-10-001B SUB-PROJECT REHABILITATION AND UPGRADING OF PHU

Upgrading of Phu Lam – Cai Lay 2 220kV Transmission line Resettlement Plan

Page 30

Page 112: TRANSMISSION EFFICIENCY PROJECT DD2-10-001B · SOUTHERN POWER PROJECT MANAGEMENT BOARD TRANSMISSION EFFICIENCY PROJECT DD2-10-001B SUB-PROJECT REHABILITATION AND UPGRADING OF PHU

Upgrading of Phu Lam – Cai Lay 2 220kV Transmission line Resettlement Plan

Page 31

6) Binh Thanh Commune, Thu Thua District, Long An Province

Page 113: TRANSMISSION EFFICIENCY PROJECT DD2-10-001B · SOUTHERN POWER PROJECT MANAGEMENT BOARD TRANSMISSION EFFICIENCY PROJECT DD2-10-001B SUB-PROJECT REHABILITATION AND UPGRADING OF PHU

Upgrading of Phu Lam – Cai Lay 2 220kV Transmission line Resettlement Plan

Page 32

Page 114: TRANSMISSION EFFICIENCY PROJECT DD2-10-001B · SOUTHERN POWER PROJECT MANAGEMENT BOARD TRANSMISSION EFFICIENCY PROJECT DD2-10-001B SUB-PROJECT REHABILITATION AND UPGRADING OF PHU

Upgrading of Phu Lam – Cai Lay 2 220kV Transmission line Resettlement Plan

Page 33

Page 115: TRANSMISSION EFFICIENCY PROJECT DD2-10-001B · SOUTHERN POWER PROJECT MANAGEMENT BOARD TRANSMISSION EFFICIENCY PROJECT DD2-10-001B SUB-PROJECT REHABILITATION AND UPGRADING OF PHU

Upgrading of Phu Lam – Cai Lay 2 220kV Transmission line Resettlement Plan

Page 34

Page 116: TRANSMISSION EFFICIENCY PROJECT DD2-10-001B · SOUTHERN POWER PROJECT MANAGEMENT BOARD TRANSMISSION EFFICIENCY PROJECT DD2-10-001B SUB-PROJECT REHABILITATION AND UPGRADING OF PHU

Upgrading of Phu Lam – Cai Lay 2 220kV Transmission line Resettlement Plan

Page 35

7) Huong Tho Phu Commune, Tan An City, Long An Province

Page 117: TRANSMISSION EFFICIENCY PROJECT DD2-10-001B · SOUTHERN POWER PROJECT MANAGEMENT BOARD TRANSMISSION EFFICIENCY PROJECT DD2-10-001B SUB-PROJECT REHABILITATION AND UPGRADING OF PHU

Upgrading of Phu Lam – Cai Lay 2 220kV Transmission line Resettlement Plan

Page 36

Page 118: TRANSMISSION EFFICIENCY PROJECT DD2-10-001B · SOUTHERN POWER PROJECT MANAGEMENT BOARD TRANSMISSION EFFICIENCY PROJECT DD2-10-001B SUB-PROJECT REHABILITATION AND UPGRADING OF PHU

Upgrading of Phu Lam – Cai Lay 2 220kV Transmission line Resettlement Plan

Page 37

Page 119: TRANSMISSION EFFICIENCY PROJECT DD2-10-001B · SOUTHERN POWER PROJECT MANAGEMENT BOARD TRANSMISSION EFFICIENCY PROJECT DD2-10-001B SUB-PROJECT REHABILITATION AND UPGRADING OF PHU

Upgrading of Phu Lam – Cai Lay 2 220kV Transmission line Resettlement Plan

Page 38

Page 120: TRANSMISSION EFFICIENCY PROJECT DD2-10-001B · SOUTHERN POWER PROJECT MANAGEMENT BOARD TRANSMISSION EFFICIENCY PROJECT DD2-10-001B SUB-PROJECT REHABILITATION AND UPGRADING OF PHU

Upgrading of Phu Lam – Cai Lay 2 220kV Transmission line Resettlement Plan

Page 39

8) Ward 6, Tan An City, Long An Province

Page 121: TRANSMISSION EFFICIENCY PROJECT DD2-10-001B · SOUTHERN POWER PROJECT MANAGEMENT BOARD TRANSMISSION EFFICIENCY PROJECT DD2-10-001B SUB-PROJECT REHABILITATION AND UPGRADING OF PHU

Upgrading of Phu Lam – Cai Lay 2 220kV Transmission line Resettlement Plan

Page 40

Page 122: TRANSMISSION EFFICIENCY PROJECT DD2-10-001B · SOUTHERN POWER PROJECT MANAGEMENT BOARD TRANSMISSION EFFICIENCY PROJECT DD2-10-001B SUB-PROJECT REHABILITATION AND UPGRADING OF PHU

Upgrading of Phu Lam – Cai Lay 2 220kV Transmission line Resettlement Plan

Page 41

Page 123: TRANSMISSION EFFICIENCY PROJECT DD2-10-001B · SOUTHERN POWER PROJECT MANAGEMENT BOARD TRANSMISSION EFFICIENCY PROJECT DD2-10-001B SUB-PROJECT REHABILITATION AND UPGRADING OF PHU

Upgrading of Phu Lam – Cai Lay 2 220kV Transmission line Resettlement Plan

Page 42

Page 124: TRANSMISSION EFFICIENCY PROJECT DD2-10-001B · SOUTHERN POWER PROJECT MANAGEMENT BOARD TRANSMISSION EFFICIENCY PROJECT DD2-10-001B SUB-PROJECT REHABILITATION AND UPGRADING OF PHU

Upgrading of Phu Lam – Cai Lay 2 220kV Transmission line Resettlement Plan

Page 43

Page 125: TRANSMISSION EFFICIENCY PROJECT DD2-10-001B · SOUTHERN POWER PROJECT MANAGEMENT BOARD TRANSMISSION EFFICIENCY PROJECT DD2-10-001B SUB-PROJECT REHABILITATION AND UPGRADING OF PHU

Upgrading of Phu Lam – Cai Lay 2 220kV Transmission line Resettlement Plan

Page 44

9) Ward 2, Tan An City, Long An Province

Page 126: TRANSMISSION EFFICIENCY PROJECT DD2-10-001B · SOUTHERN POWER PROJECT MANAGEMENT BOARD TRANSMISSION EFFICIENCY PROJECT DD2-10-001B SUB-PROJECT REHABILITATION AND UPGRADING OF PHU

Upgrading of Phu Lam – Cai Lay 2 220kV Transmission line Resettlement Plan

Page 45

Page 127: TRANSMISSION EFFICIENCY PROJECT DD2-10-001B · SOUTHERN POWER PROJECT MANAGEMENT BOARD TRANSMISSION EFFICIENCY PROJECT DD2-10-001B SUB-PROJECT REHABILITATION AND UPGRADING OF PHU

Upgrading of Phu Lam – Cai Lay 2 220kV Transmission line Resettlement Plan

Page 46

Page 128: TRANSMISSION EFFICIENCY PROJECT DD2-10-001B · SOUTHERN POWER PROJECT MANAGEMENT BOARD TRANSMISSION EFFICIENCY PROJECT DD2-10-001B SUB-PROJECT REHABILITATION AND UPGRADING OF PHU

Upgrading of Phu Lam – Cai Lay 2 220kV Transmission line Resettlement Plan

Page 47

Page 129: TRANSMISSION EFFICIENCY PROJECT DD2-10-001B · SOUTHERN POWER PROJECT MANAGEMENT BOARD TRANSMISSION EFFICIENCY PROJECT DD2-10-001B SUB-PROJECT REHABILITATION AND UPGRADING OF PHU

Upgrading of Phu Lam – Cai Lay 2 220kV Transmission line Resettlement Plan

Page 48

10) Ward 4, Tan An City, Long An Province

Page 130: TRANSMISSION EFFICIENCY PROJECT DD2-10-001B · SOUTHERN POWER PROJECT MANAGEMENT BOARD TRANSMISSION EFFICIENCY PROJECT DD2-10-001B SUB-PROJECT REHABILITATION AND UPGRADING OF PHU

Upgrading of Phu Lam – Cai Lay 2 220kV Transmission line Resettlement Plan

Page 49

Page 131: TRANSMISSION EFFICIENCY PROJECT DD2-10-001B · SOUTHERN POWER PROJECT MANAGEMENT BOARD TRANSMISSION EFFICIENCY PROJECT DD2-10-001B SUB-PROJECT REHABILITATION AND UPGRADING OF PHU

Upgrading of Phu Lam – Cai Lay 2 220kV Transmission line Resettlement Plan

Page 50

Page 132: TRANSMISSION EFFICIENCY PROJECT DD2-10-001B · SOUTHERN POWER PROJECT MANAGEMENT BOARD TRANSMISSION EFFICIENCY PROJECT DD2-10-001B SUB-PROJECT REHABILITATION AND UPGRADING OF PHU

Upgrading of Phu Lam – Cai Lay 2 220kV Transmission line Resettlement Plan

Page 51

Page 133: TRANSMISSION EFFICIENCY PROJECT DD2-10-001B · SOUTHERN POWER PROJECT MANAGEMENT BOARD TRANSMISSION EFFICIENCY PROJECT DD2-10-001B SUB-PROJECT REHABILITATION AND UPGRADING OF PHU

Upgrading of Phu Lam – Cai Lay 2 220kV Transmission line Resettlement Plan

Page 52

Page 134: TRANSMISSION EFFICIENCY PROJECT DD2-10-001B · SOUTHERN POWER PROJECT MANAGEMENT BOARD TRANSMISSION EFFICIENCY PROJECT DD2-10-001B SUB-PROJECT REHABILITATION AND UPGRADING OF PHU

Upgrading of Phu Lam – Cai Lay 2 220kV Transmission line Resettlement Plan

Page 53

11) Khanh Hau Ward, Tan An City, Long An Province

Page 135: TRANSMISSION EFFICIENCY PROJECT DD2-10-001B · SOUTHERN POWER PROJECT MANAGEMENT BOARD TRANSMISSION EFFICIENCY PROJECT DD2-10-001B SUB-PROJECT REHABILITATION AND UPGRADING OF PHU

Upgrading of Phu Lam – Cai Lay 2 220kV Transmission line Resettlement Plan

Page 54

Page 136: TRANSMISSION EFFICIENCY PROJECT DD2-10-001B · SOUTHERN POWER PROJECT MANAGEMENT BOARD TRANSMISSION EFFICIENCY PROJECT DD2-10-001B SUB-PROJECT REHABILITATION AND UPGRADING OF PHU

Upgrading of Phu Lam – Cai Lay 2 220kV Transmission line Resettlement Plan

Page 55

Page 137: TRANSMISSION EFFICIENCY PROJECT DD2-10-001B · SOUTHERN POWER PROJECT MANAGEMENT BOARD TRANSMISSION EFFICIENCY PROJECT DD2-10-001B SUB-PROJECT REHABILITATION AND UPGRADING OF PHU

Upgrading of Phu Lam – Cai Lay 2 220kV Transmission line Resettlement Plan

Page 56

Page 138: TRANSMISSION EFFICIENCY PROJECT DD2-10-001B · SOUTHERN POWER PROJECT MANAGEMENT BOARD TRANSMISSION EFFICIENCY PROJECT DD2-10-001B SUB-PROJECT REHABILITATION AND UPGRADING OF PHU

Upgrading of Phu Lam – Cai Lay 2 220kV Transmission line Resettlement Plan

Page 57

12) Tan Huong Commune, Chau Thanh District, Tien Giang Province

Page 139: TRANSMISSION EFFICIENCY PROJECT DD2-10-001B · SOUTHERN POWER PROJECT MANAGEMENT BOARD TRANSMISSION EFFICIENCY PROJECT DD2-10-001B SUB-PROJECT REHABILITATION AND UPGRADING OF PHU

Upgrading of Phu Lam – Cai Lay 2 220kV Transmission line Resettlement Plan

Page 58

Page 140: TRANSMISSION EFFICIENCY PROJECT DD2-10-001B · SOUTHERN POWER PROJECT MANAGEMENT BOARD TRANSMISSION EFFICIENCY PROJECT DD2-10-001B SUB-PROJECT REHABILITATION AND UPGRADING OF PHU

Upgrading of Phu Lam – Cai Lay 2 220kV Transmission line Resettlement Plan

Page 59

Page 141: TRANSMISSION EFFICIENCY PROJECT DD2-10-001B · SOUTHERN POWER PROJECT MANAGEMENT BOARD TRANSMISSION EFFICIENCY PROJECT DD2-10-001B SUB-PROJECT REHABILITATION AND UPGRADING OF PHU

Upgrading of Phu Lam – Cai Lay 2 220kV Transmission line Resettlement Plan

Page 60

Page 142: TRANSMISSION EFFICIENCY PROJECT DD2-10-001B · SOUTHERN POWER PROJECT MANAGEMENT BOARD TRANSMISSION EFFICIENCY PROJECT DD2-10-001B SUB-PROJECT REHABILITATION AND UPGRADING OF PHU

Upgrading of Phu Lam – Cai Lay 2 220kV Transmission line Resettlement Plan

Page 61

Page 143: TRANSMISSION EFFICIENCY PROJECT DD2-10-001B · SOUTHERN POWER PROJECT MANAGEMENT BOARD TRANSMISSION EFFICIENCY PROJECT DD2-10-001B SUB-PROJECT REHABILITATION AND UPGRADING OF PHU

Upgrading of Phu Lam – Cai Lay 2 220kV Transmission line Resettlement Plan

Page 62

13) Tan Ly Tay Commune, Chau Thanh District, Tien Giang Province

Page 144: TRANSMISSION EFFICIENCY PROJECT DD2-10-001B · SOUTHERN POWER PROJECT MANAGEMENT BOARD TRANSMISSION EFFICIENCY PROJECT DD2-10-001B SUB-PROJECT REHABILITATION AND UPGRADING OF PHU

Upgrading of Phu Lam – Cai Lay 2 220kV Transmission line Resettlement Plan

Page 63

Page 145: TRANSMISSION EFFICIENCY PROJECT DD2-10-001B · SOUTHERN POWER PROJECT MANAGEMENT BOARD TRANSMISSION EFFICIENCY PROJECT DD2-10-001B SUB-PROJECT REHABILITATION AND UPGRADING OF PHU

Upgrading of Phu Lam – Cai Lay 2 220kV Transmission line Resettlement Plan

Page 64

Page 146: TRANSMISSION EFFICIENCY PROJECT DD2-10-001B · SOUTHERN POWER PROJECT MANAGEMENT BOARD TRANSMISSION EFFICIENCY PROJECT DD2-10-001B SUB-PROJECT REHABILITATION AND UPGRADING OF PHU

Upgrading of Phu Lam – Cai Lay 2 220kV Transmission line Resettlement Plan

Page 65

Page 147: TRANSMISSION EFFICIENCY PROJECT DD2-10-001B · SOUTHERN POWER PROJECT MANAGEMENT BOARD TRANSMISSION EFFICIENCY PROJECT DD2-10-001B SUB-PROJECT REHABILITATION AND UPGRADING OF PHU

Upgrading of Phu Lam – Cai Lay 2 220kV Transmission line Resettlement Plan

Page 66

Page 148: TRANSMISSION EFFICIENCY PROJECT DD2-10-001B · SOUTHERN POWER PROJECT MANAGEMENT BOARD TRANSMISSION EFFICIENCY PROJECT DD2-10-001B SUB-PROJECT REHABILITATION AND UPGRADING OF PHU

Upgrading of Phu Lam – Cai Lay 2 220kV Transmission line Resettlement Plan

Page 67

14) Tan Ly Dong Commune, Chau Thanh District, Tien Giang Province

Page 149: TRANSMISSION EFFICIENCY PROJECT DD2-10-001B · SOUTHERN POWER PROJECT MANAGEMENT BOARD TRANSMISSION EFFICIENCY PROJECT DD2-10-001B SUB-PROJECT REHABILITATION AND UPGRADING OF PHU

Upgrading of Phu Lam – Cai Lay 2 220kV Transmission line Resettlement Plan

Page 68

Page 150: TRANSMISSION EFFICIENCY PROJECT DD2-10-001B · SOUTHERN POWER PROJECT MANAGEMENT BOARD TRANSMISSION EFFICIENCY PROJECT DD2-10-001B SUB-PROJECT REHABILITATION AND UPGRADING OF PHU

Upgrading of Phu Lam – Cai Lay 2 220kV Transmission line Resettlement Plan

Page 69

Page 151: TRANSMISSION EFFICIENCY PROJECT DD2-10-001B · SOUTHERN POWER PROJECT MANAGEMENT BOARD TRANSMISSION EFFICIENCY PROJECT DD2-10-001B SUB-PROJECT REHABILITATION AND UPGRADING OF PHU

Upgrading of Phu Lam – Cai Lay 2 220kV Transmission line Resettlement Plan

Page 70

Page 152: TRANSMISSION EFFICIENCY PROJECT DD2-10-001B · SOUTHERN POWER PROJECT MANAGEMENT BOARD TRANSMISSION EFFICIENCY PROJECT DD2-10-001B SUB-PROJECT REHABILITATION AND UPGRADING OF PHU

Upgrading of Phu Lam – Cai Lay 2 220kV Transmission line Resettlement Plan

Page 71

15) Tan Hiep Commune, Chau Thanh District, Tien Giang Province

Page 153: TRANSMISSION EFFICIENCY PROJECT DD2-10-001B · SOUTHERN POWER PROJECT MANAGEMENT BOARD TRANSMISSION EFFICIENCY PROJECT DD2-10-001B SUB-PROJECT REHABILITATION AND UPGRADING OF PHU

Upgrading of Phu Lam – Cai Lay 2 220kV Transmission line Resettlement Plan

Page 72

Page 154: TRANSMISSION EFFICIENCY PROJECT DD2-10-001B · SOUTHERN POWER PROJECT MANAGEMENT BOARD TRANSMISSION EFFICIENCY PROJECT DD2-10-001B SUB-PROJECT REHABILITATION AND UPGRADING OF PHU

Upgrading of Phu Lam – Cai Lay 2 220kV Transmission line Resettlement Plan

Page 73

Page 155: TRANSMISSION EFFICIENCY PROJECT DD2-10-001B · SOUTHERN POWER PROJECT MANAGEMENT BOARD TRANSMISSION EFFICIENCY PROJECT DD2-10-001B SUB-PROJECT REHABILITATION AND UPGRADING OF PHU

Upgrading of Phu Lam – Cai Lay 2 220kV Transmission line Resettlement Plan

Page 74

Page 156: TRANSMISSION EFFICIENCY PROJECT DD2-10-001B · SOUTHERN POWER PROJECT MANAGEMENT BOARD TRANSMISSION EFFICIENCY PROJECT DD2-10-001B SUB-PROJECT REHABILITATION AND UPGRADING OF PHU

Upgrading of Phu Lam – Cai Lay 2 220kV Transmission line Resettlement Plan

Page 75

Page 157: TRANSMISSION EFFICIENCY PROJECT DD2-10-001B · SOUTHERN POWER PROJECT MANAGEMENT BOARD TRANSMISSION EFFICIENCY PROJECT DD2-10-001B SUB-PROJECT REHABILITATION AND UPGRADING OF PHU

Upgrading of Phu Lam – Cai Lay 2 220kV Transmission line Resettlement Plan

Page 76

16) Than Cuu Nghia Commune, Chau Thanh District, Tien Giang Province

Page 158: TRANSMISSION EFFICIENCY PROJECT DD2-10-001B · SOUTHERN POWER PROJECT MANAGEMENT BOARD TRANSMISSION EFFICIENCY PROJECT DD2-10-001B SUB-PROJECT REHABILITATION AND UPGRADING OF PHU

Upgrading of Phu Lam – Cai Lay 2 220kV Transmission line Resettlement Plan

Page 77

Page 159: TRANSMISSION EFFICIENCY PROJECT DD2-10-001B · SOUTHERN POWER PROJECT MANAGEMENT BOARD TRANSMISSION EFFICIENCY PROJECT DD2-10-001B SUB-PROJECT REHABILITATION AND UPGRADING OF PHU

Upgrading of Phu Lam – Cai Lay 2 220kV Transmission line Resettlement Plan

Page 78

Page 160: TRANSMISSION EFFICIENCY PROJECT DD2-10-001B · SOUTHERN POWER PROJECT MANAGEMENT BOARD TRANSMISSION EFFICIENCY PROJECT DD2-10-001B SUB-PROJECT REHABILITATION AND UPGRADING OF PHU

Upgrading of Phu Lam – Cai Lay 2 220kV Transmission line Resettlement Plan

Page 79

Page 161: TRANSMISSION EFFICIENCY PROJECT DD2-10-001B · SOUTHERN POWER PROJECT MANAGEMENT BOARD TRANSMISSION EFFICIENCY PROJECT DD2-10-001B SUB-PROJECT REHABILITATION AND UPGRADING OF PHU

Upgrading of Phu Lam – Cai Lay 2 220kV Transmission line Resettlement Plan

Page 80

Page 162: TRANSMISSION EFFICIENCY PROJECT DD2-10-001B · SOUTHERN POWER PROJECT MANAGEMENT BOARD TRANSMISSION EFFICIENCY PROJECT DD2-10-001B SUB-PROJECT REHABILITATION AND UPGRADING OF PHU

Upgrading of Phu Lam – Cai Lay 2 220kV Transmission line Resettlement Plan

Page 81

Page 163: TRANSMISSION EFFICIENCY PROJECT DD2-10-001B · SOUTHERN POWER PROJECT MANAGEMENT BOARD TRANSMISSION EFFICIENCY PROJECT DD2-10-001B SUB-PROJECT REHABILITATION AND UPGRADING OF PHU

Upgrading of Phu Lam – Cai Lay 2 220kV Transmission line Resettlement Plan

Page 82

Page 164: TRANSMISSION EFFICIENCY PROJECT DD2-10-001B · SOUTHERN POWER PROJECT MANAGEMENT BOARD TRANSMISSION EFFICIENCY PROJECT DD2-10-001B SUB-PROJECT REHABILITATION AND UPGRADING OF PHU

Upgrading of Phu Lam – Cai Lay 2 220kV Transmission line Resettlement Plan

Page 83

17) Tam Hiep Commune, Chau Thanh District, Tien Giang Province

Page 165: TRANSMISSION EFFICIENCY PROJECT DD2-10-001B · SOUTHERN POWER PROJECT MANAGEMENT BOARD TRANSMISSION EFFICIENCY PROJECT DD2-10-001B SUB-PROJECT REHABILITATION AND UPGRADING OF PHU

Upgrading of Phu Lam – Cai Lay 2 220kV Transmission line Resettlement Plan

Page 84

Page 166: TRANSMISSION EFFICIENCY PROJECT DD2-10-001B · SOUTHERN POWER PROJECT MANAGEMENT BOARD TRANSMISSION EFFICIENCY PROJECT DD2-10-001B SUB-PROJECT REHABILITATION AND UPGRADING OF PHU

Upgrading of Phu Lam – Cai Lay 2 220kV Transmission line Resettlement Plan

Page 85

Page 167: TRANSMISSION EFFICIENCY PROJECT DD2-10-001B · SOUTHERN POWER PROJECT MANAGEMENT BOARD TRANSMISSION EFFICIENCY PROJECT DD2-10-001B SUB-PROJECT REHABILITATION AND UPGRADING OF PHU

Upgrading of Phu Lam – Cai Lay 2 220kV Transmission line Resettlement Plan

Page 86

Page 168: TRANSMISSION EFFICIENCY PROJECT DD2-10-001B · SOUTHERN POWER PROJECT MANAGEMENT BOARD TRANSMISSION EFFICIENCY PROJECT DD2-10-001B SUB-PROJECT REHABILITATION AND UPGRADING OF PHU

Upgrading of Phu Lam – Cai Lay 2 220kV Transmission line Resettlement Plan

Page 87

Page 169: TRANSMISSION EFFICIENCY PROJECT DD2-10-001B · SOUTHERN POWER PROJECT MANAGEMENT BOARD TRANSMISSION EFFICIENCY PROJECT DD2-10-001B SUB-PROJECT REHABILITATION AND UPGRADING OF PHU

Upgrading of Phu Lam – Cai Lay 2 220kV Transmission line Resettlement Plan

Page 88

18) Long Dinh Commune, Chau Thanh District, Tien Giang Province

Page 170: TRANSMISSION EFFICIENCY PROJECT DD2-10-001B · SOUTHERN POWER PROJECT MANAGEMENT BOARD TRANSMISSION EFFICIENCY PROJECT DD2-10-001B SUB-PROJECT REHABILITATION AND UPGRADING OF PHU

Upgrading of Phu Lam – Cai Lay 2 220kV Transmission line Resettlement Plan

Page 89

Page 171: TRANSMISSION EFFICIENCY PROJECT DD2-10-001B · SOUTHERN POWER PROJECT MANAGEMENT BOARD TRANSMISSION EFFICIENCY PROJECT DD2-10-001B SUB-PROJECT REHABILITATION AND UPGRADING OF PHU

Upgrading of Phu Lam – Cai Lay 2 220kV Transmission line Resettlement Plan

Page 90

Page 172: TRANSMISSION EFFICIENCY PROJECT DD2-10-001B · SOUTHERN POWER PROJECT MANAGEMENT BOARD TRANSMISSION EFFICIENCY PROJECT DD2-10-001B SUB-PROJECT REHABILITATION AND UPGRADING OF PHU

Upgrading of Phu Lam – Cai Lay 2 220kV Transmission line Resettlement Plan

Page 91

Page 173: TRANSMISSION EFFICIENCY PROJECT DD2-10-001B · SOUTHERN POWER PROJECT MANAGEMENT BOARD TRANSMISSION EFFICIENCY PROJECT DD2-10-001B SUB-PROJECT REHABILITATION AND UPGRADING OF PHU

Upgrading of Phu Lam – Cai Lay 2 220kV Transmission line Resettlement Plan

Page 92

Page 174: TRANSMISSION EFFICIENCY PROJECT DD2-10-001B · SOUTHERN POWER PROJECT MANAGEMENT BOARD TRANSMISSION EFFICIENCY PROJECT DD2-10-001B SUB-PROJECT REHABILITATION AND UPGRADING OF PHU

Upgrading of Phu Lam – Cai Lay 2 220kV Transmission line Resettlement Plan

Page 93

19) Nhi Binh Commune, Cai Lay District, Tien Giang Province

Page 175: TRANSMISSION EFFICIENCY PROJECT DD2-10-001B · SOUTHERN POWER PROJECT MANAGEMENT BOARD TRANSMISSION EFFICIENCY PROJECT DD2-10-001B SUB-PROJECT REHABILITATION AND UPGRADING OF PHU

Upgrading of Phu Lam – Cai Lay 2 220kV Transmission line Resettlement Plan

Page 94

Page 176: TRANSMISSION EFFICIENCY PROJECT DD2-10-001B · SOUTHERN POWER PROJECT MANAGEMENT BOARD TRANSMISSION EFFICIENCY PROJECT DD2-10-001B SUB-PROJECT REHABILITATION AND UPGRADING OF PHU

Upgrading of Phu Lam – Cai Lay 2 220kV Transmission line Resettlement Plan

Page 95

Page 177: TRANSMISSION EFFICIENCY PROJECT DD2-10-001B · SOUTHERN POWER PROJECT MANAGEMENT BOARD TRANSMISSION EFFICIENCY PROJECT DD2-10-001B SUB-PROJECT REHABILITATION AND UPGRADING OF PHU

Upgrading of Phu Lam – Cai Lay 2 220kV Transmission line Resettlement Plan

Page 96

Page 178: TRANSMISSION EFFICIENCY PROJECT DD2-10-001B · SOUTHERN POWER PROJECT MANAGEMENT BOARD TRANSMISSION EFFICIENCY PROJECT DD2-10-001B SUB-PROJECT REHABILITATION AND UPGRADING OF PHU

Upgrading of Phu Lam – Cai Lay 2 220kV Transmission line Resettlement Plan

Page 97

Page 179: TRANSMISSION EFFICIENCY PROJECT DD2-10-001B · SOUTHERN POWER PROJECT MANAGEMENT BOARD TRANSMISSION EFFICIENCY PROJECT DD2-10-001B SUB-PROJECT REHABILITATION AND UPGRADING OF PHU

Upgrading of Phu Lam – Cai Lay 2 220kV Transmission line Resettlement Plan

Page 98

20) Diem Hy Commune, Chau Thanh District, Tien Giang Province

Page 180: TRANSMISSION EFFICIENCY PROJECT DD2-10-001B · SOUTHERN POWER PROJECT MANAGEMENT BOARD TRANSMISSION EFFICIENCY PROJECT DD2-10-001B SUB-PROJECT REHABILITATION AND UPGRADING OF PHU

Upgrading of Phu Lam – Cai Lay 2 220kV Transmission line Resettlement Plan

Page 99

Page 181: TRANSMISSION EFFICIENCY PROJECT DD2-10-001B · SOUTHERN POWER PROJECT MANAGEMENT BOARD TRANSMISSION EFFICIENCY PROJECT DD2-10-001B SUB-PROJECT REHABILITATION AND UPGRADING OF PHU

Upgrading of Phu Lam – Cai Lay 2 220kV Transmission line Resettlement Plan

Page 100

Page 182: TRANSMISSION EFFICIENCY PROJECT DD2-10-001B · SOUTHERN POWER PROJECT MANAGEMENT BOARD TRANSMISSION EFFICIENCY PROJECT DD2-10-001B SUB-PROJECT REHABILITATION AND UPGRADING OF PHU

Upgrading of Phu Lam – Cai Lay 2 220kV Transmission line Resettlement Plan

Page 101

Page 183: TRANSMISSION EFFICIENCY PROJECT DD2-10-001B · SOUTHERN POWER PROJECT MANAGEMENT BOARD TRANSMISSION EFFICIENCY PROJECT DD2-10-001B SUB-PROJECT REHABILITATION AND UPGRADING OF PHU

Upgrading of Phu Lam – Cai Lay 2 220kV Transmission line Resettlement Plan

Page 102

Page 184: TRANSMISSION EFFICIENCY PROJECT DD2-10-001B · SOUTHERN POWER PROJECT MANAGEMENT BOARD TRANSMISSION EFFICIENCY PROJECT DD2-10-001B SUB-PROJECT REHABILITATION AND UPGRADING OF PHU

Upgrading of Phu Lam – Cai Lay 2 220kV Transmission line Resettlement Plan

Page 103

21) Tan Hoi Commune, Cai Lay District, Tien Giang Province

Page 185: TRANSMISSION EFFICIENCY PROJECT DD2-10-001B · SOUTHERN POWER PROJECT MANAGEMENT BOARD TRANSMISSION EFFICIENCY PROJECT DD2-10-001B SUB-PROJECT REHABILITATION AND UPGRADING OF PHU

Upgrading of Phu Lam – Cai Lay 2 220kV Transmission line Resettlement Plan

Page 104

Page 186: TRANSMISSION EFFICIENCY PROJECT DD2-10-001B · SOUTHERN POWER PROJECT MANAGEMENT BOARD TRANSMISSION EFFICIENCY PROJECT DD2-10-001B SUB-PROJECT REHABILITATION AND UPGRADING OF PHU

Upgrading of Phu Lam – Cai Lay 2 220kV Transmission line Resettlement Plan

Page 105

Page 187: TRANSMISSION EFFICIENCY PROJECT DD2-10-001B · SOUTHERN POWER PROJECT MANAGEMENT BOARD TRANSMISSION EFFICIENCY PROJECT DD2-10-001B SUB-PROJECT REHABILITATION AND UPGRADING OF PHU

Upgrading of Phu Lam – Cai Lay 2 220kV Transmission line Resettlement Plan

Page 106

Page 188: TRANSMISSION EFFICIENCY PROJECT DD2-10-001B · SOUTHERN POWER PROJECT MANAGEMENT BOARD TRANSMISSION EFFICIENCY PROJECT DD2-10-001B SUB-PROJECT REHABILITATION AND UPGRADING OF PHU

Upgrading of Phu Lam – Cai Lay 2 220kV Transmission line Resettlement Plan

Page 107

Page 189: TRANSMISSION EFFICIENCY PROJECT DD2-10-001B · SOUTHERN POWER PROJECT MANAGEMENT BOARD TRANSMISSION EFFICIENCY PROJECT DD2-10-001B SUB-PROJECT REHABILITATION AND UPGRADING OF PHU

Upgrading of Phu Lam – Cai Lay 2 220kV Transmission line Resettlement Plan

Page 108

22) Nhi My Commune, Cai Lay District, Tien Giang Province

Page 190: TRANSMISSION EFFICIENCY PROJECT DD2-10-001B · SOUTHERN POWER PROJECT MANAGEMENT BOARD TRANSMISSION EFFICIENCY PROJECT DD2-10-001B SUB-PROJECT REHABILITATION AND UPGRADING OF PHU

Upgrading of Phu Lam – Cai Lay 2 220kV Transmission line Resettlement Plan

Page 109

Page 191: TRANSMISSION EFFICIENCY PROJECT DD2-10-001B · SOUTHERN POWER PROJECT MANAGEMENT BOARD TRANSMISSION EFFICIENCY PROJECT DD2-10-001B SUB-PROJECT REHABILITATION AND UPGRADING OF PHU

Upgrading of Phu Lam – Cai Lay 2 220kV Transmission line Resettlement Plan

Page 110

Page 192: TRANSMISSION EFFICIENCY PROJECT DD2-10-001B · SOUTHERN POWER PROJECT MANAGEMENT BOARD TRANSMISSION EFFICIENCY PROJECT DD2-10-001B SUB-PROJECT REHABILITATION AND UPGRADING OF PHU

Upgrading of Phu Lam – Cai Lay 2 220kV Transmission line Resettlement Plan

Page 111

Page 193: TRANSMISSION EFFICIENCY PROJECT DD2-10-001B · SOUTHERN POWER PROJECT MANAGEMENT BOARD TRANSMISSION EFFICIENCY PROJECT DD2-10-001B SUB-PROJECT REHABILITATION AND UPGRADING OF PHU

Upgrading of Phu Lam – Cai Lay 2 220kV Transmission line Resettlement Plan

Page 112

Page 194: TRANSMISSION EFFICIENCY PROJECT DD2-10-001B · SOUTHERN POWER PROJECT MANAGEMENT BOARD TRANSMISSION EFFICIENCY PROJECT DD2-10-001B SUB-PROJECT REHABILITATION AND UPGRADING OF PHU

Upgrading of Phu Lam – Cai Lay 2 220kV Transmission line Resettlement Plan

Page 113

Page 195: TRANSMISSION EFFICIENCY PROJECT DD2-10-001B · SOUTHERN POWER PROJECT MANAGEMENT BOARD TRANSMISSION EFFICIENCY PROJECT DD2-10-001B SUB-PROJECT REHABILITATION AND UPGRADING OF PHU

Rehabilitatin and Upgrading of Phu Lam – Cai Lay 2 220kV Transmission line Resettlement Plan

Owner: Southern Vietnam Power Project Management Board- EVNNPT Page 82 Prepared by: Power Engineering Consulting JS. Company 2

Appendix 5: Statistics on number of APs by the subproject

Name of

tower Name of households Address

The numbe

r of person

s in HH

Total land holding of HH (m2)

Land to be

acquired (m2)

Percentage of

acquired land

(m2)

The number of affected land in ROW (m2)

Percentage of

affected land

Loss of Assets Loss of farm produce

Number and type of lost

structures

Structures

permanent (m2)

Structures

temporary (m2)

Area of

residential land lost (m2)

Fruit trees lost

Type and

Number

Rice area (m2)

Other lands

66 4 2,000 341.3 17.06 341.3

67 Nguyen Thi Go Hamlet 7, Nhi Thanh commune, Thu Thua district, Long An province

3 1,000 202.5 20.25 202.5

68 Le Quang Tu Hamlet 5, Nhi Thanh commune, Thu Thua district, Long An province

5 1,500 202.5 13.50 202.5

69 Tran Phuoc Duyen Hamlet 5, Nhi Thanh commune, Thu Thua district, Long An province

10 1,000 202.5 20.25 202.5

70 Vo Van Chot Hamlet 5, Nhi Thanh commune, Thu Thua district, Long An province

2 5,000 202.5 4.05 202.5

71 Pham Van Kheo Team 11, hamlet 5, Nhi Thanh commune, Thu Thua district, Long An province

4 500 202.5 40.50 202.5

72 Le Van Dong Binh Can 1 hamlet, Binh Thanh commune, Thu Thua district, Long An province

4 1,000 202.5 20.25 202.5

73 Nguyen Van Tuong Team 11, Hamlet 5, Nhi Thanh commune, Thu Thua district, Long An province

3 1,500 202.5 13.50 202.5

74 Nguyen Thi Tuyen Binh Cang hamlet, Binh Thanh commune, Thu Thua district, Long An

4 3,000 341.3 11.38 341.25

75 Nguyen Van Hoai Binh Can 2 hamlet, Binh Thanh commune, Thu Thua district, Long An province

2 2,000 341.3 17.06 341.25

76 Chau Huu Ai Binh Can 1 hamlet, Binh Thanh commune, Thu Thua district, Long An province

6 3,000 528.0 17.60 528

77 Do Minh Hieu Binh Can 1 hamlet, Binh Thanh commune, Thu Thua district, Long An province

4 2,000 625.0 31.25 625

78 Tran Van Sang Binh Can 1 hamlet, Binh Thanh commune, Thu Thua district, Long An province

4 2,000 280.0 14.00 Grass

79 Vo Quang Thieu Hamlet 3, Huong Tho A commune, Tan An city, Long An province

4 3,000 305.3 10.18 305.3

80 Domitory of Vocational Training College

Huong Tho Phu commune, Tan An city, Long An province 10,000 305.3 3.05 305.

3

Page 196: TRANSMISSION EFFICIENCY PROJECT DD2-10-001B · SOUTHERN POWER PROJECT MANAGEMENT BOARD TRANSMISSION EFFICIENCY PROJECT DD2-10-001B SUB-PROJECT REHABILITATION AND UPGRADING OF PHU

Rehabilitatin and Upgrading of Phu Lam – Cai Lay 2 220kV Transmission line Resettlement Plan

Owner: Southern Vietnam Power Project Management Board- EVNNPT Page 83 Prepared by: Power Engineering Consulting JS. Company 2

Name of

tower Name of households Address

The numbe

r of person

s in HH

Total land holding of HH (m2)

Land to be

acquired (m2)

Percentage of

acquired land

(m2)

The number of affected land in ROW (m2)

Percentage of

affected land

Loss of Assets Loss of farm produce

Number and type of lost

structures

Structures

permanent (m2)

Structures

temporary (m2)

Area of

residential land lost (m2)

Fruit trees lost

Type and

Number

Rice area (m2)

Other lands

81 Le Thi Ngoc Lan Huong Tho Phu commune, Tan An city, Long An province 6 1,000 288.0 28.80 Grass

82 Muoi Khe Hamlet 4, Huong Tho Phu commune, Tan An city, Long An province

5 2,000 483.0 24.15 483

83 Vo Van Ranh Hamlet 4, Huong Tho Phu commune, Tan An city, Long An province 5 2,000 483.0 24.15 483

84 Public land 5,000 451.0 9.02 451

85 Tran Quoc Vinh Team 1A, Binh Cu 2 quarter, ward 6, Tan An city, Long An province

3 1,000 451.0 45.10 pond

86 Vo Thanh Liem Parking of quarter 6, ward 2, Tan An city, Long An province 3 5,000 483.0 9.66 483

87 Le Thanh Tam 57/16 Huynh Van Gam street, Tan An city, Long An province 9 1,000 280.0 28.00 pond

88 Public land Tower 130 of Long An - Cai Lay 2 220kV Transmission line 1,000 288.0 28.80

89 Huynh Trong Hiep Binh Cu 1 quarter, ward 4, Tan An city, Long An province 4 700 323.0 46.14 Banan

a

90 Nguyen Van Tai Nguyen Van Tao street, Binh Cu 1 quarter, Tan An city, Long An province

3 700 305.3 43.61

91 Cao Thi Thien Han 17/9C Luu Van Te street, ward 4, Tan An city, Long An province

2 400 305.3 76.33 Grass

92 Ly Tu Trong Highschool

Ward 4, Tan An city, Long An province 700 305.3 43.61

93 Vo Duc Minh Ward 1, Tan An city, Long An province 5 500 305.3 61.06 305.3

94 Nguyen Van Nguyen Ward 3, Tan An city, Long An province 5 600 483.0 80.50 483

95 Tran Thi Muoi 676/2 ward 4, Tan An city, Long An province 3 500 483.0 96.60 pond

96 Nguyen Van My 2B, Binh Quan 2 quarter, Ward 4, Tan An city, Long An province

4 1,500 305.3 20.35 305.3

97 Chi Huu Truong Khanh quarter, Khanh Hau ward, Tan An city, Long An province

5 2,000 323.0 16.15 pond

98 Nguyen Van Trung Khanh Hau ward, Tan An city, Long An province 3 800 263.5 32.94 263.5

99 Phan Van Truyen Khanh Hau ward, Tan An city, Long An province 5 1,800 305.3 16.96 305.3

100 Long An Teacher Training College

369.0

101 Public land Quyet Thang 1 quarter, Khanh Hau ward, Tan An city, Long 369.0

Page 197: TRANSMISSION EFFICIENCY PROJECT DD2-10-001B · SOUTHERN POWER PROJECT MANAGEMENT BOARD TRANSMISSION EFFICIENCY PROJECT DD2-10-001B SUB-PROJECT REHABILITATION AND UPGRADING OF PHU

Rehabilitatin and Upgrading of Phu Lam – Cai Lay 2 220kV Transmission line Resettlement Plan

Owner: Southern Vietnam Power Project Management Board- EVNNPT Page 84 Prepared by: Power Engineering Consulting JS. Company 2

Name of

tower Name of households Address

The numbe

r of person

s in HH

Total land holding of HH (m2)

Land to be

acquired (m2)

Percentage of

acquired land

(m2)

The number of affected land in ROW (m2)

Percentage of

affected land

Loss of Assets Loss of farm produce

Number and type of lost

structures

Structures

permanent (m2)

Structures

temporary (m2)

Area of

residential land lost (m2)

Fruit trees lost

Type and

Number

Rice area (m2)

Other lands

An province

102 Trinh Van Sang 203 Luong Van Chien street, Quyet Thang 2 quarter, Khanh Hau ward, Tan An city, Long An province

4 700 288.0 41.14 288

103 Duong Ngoc Tan Hao

Quyet Thang 2 quarter, Khanh Hau ward, Tan An city, Long An province

5 700 305.3 43.61 305.3

104 Ho Van Tinh Quyet Thang 1 quarter, Khanh Hau ward, Tan An city, Long An province

4 1,200 305.3 25.44 305.3

105 Nguyen Thi Thu Quyet Thang quarter, Khanh Hau ward, Tan An city, Long An province

4 4,000 305.3 7.63 305.3

106 Nguyen Van Hu Tan Phu hamlet, Tan Huong commune, Chau Thanh district, Tien Giang province

7 1,750 305.3 17.45 305.3

107 Tran Anh Thu Tan Huong commune, Chau Thanh district, Tien Giang province

2 1,625 305.3

18.79

305.3

108 Tan Huong industrial zone

Tan Huong commune, Chau Thanh district, Tien Giang province

288.0

288

109 Tan Huong industrial zone

Tan Huong commune, Chau Thanh district, Tien Giang province

288.0

288

110 Tan Huong industrial zone

Tan Huong commune, Chau Thanh district, Tien Giang province

288.0

288

111 Tan Huong industrial zone

Tan Huong commune, Chau Thanh district, Tien Giang province

288.0

288

112 Do Thanh Son 277/3- Tan Thanh hamlet-Tan Huong commune, Chau Thanh district, Tien Giang province

7 4,800 305.3

6.36

305.3

113 Nguyen Tan Hoai Tan Thuan hamlet-Tan Huong commune, Chau Thanh district, Tien Giang province

3 480 305.3

63.60

305.3

114 Pham Van Tai Tan Thanh hamlet-Tan Huong commune, Chau Thanh district, Tien Giang province

4 300 288.0

96.00

288

115 Huynh Thi Nu Tan Thuan hamlet-Tan Huong commune, Chau Thanh district, Tien Giang province

4 600 280.0

46.67

280

116 Nguyen Van Nam Tan Thuan hamlet-Tan Huong commune, Chau Thanh district, Tien Giang province

4 5,000 280.0

5.60

280

117 Tran Trung Thanh Tan Thanh hamlet-Tan Ly Tay commune, Chau Thanh district, Tien Giang province

3 1,800 483.0

26.83

483

Page 198: TRANSMISSION EFFICIENCY PROJECT DD2-10-001B · SOUTHERN POWER PROJECT MANAGEMENT BOARD TRANSMISSION EFFICIENCY PROJECT DD2-10-001B SUB-PROJECT REHABILITATION AND UPGRADING OF PHU

Rehabilitatin and Upgrading of Phu Lam – Cai Lay 2 220kV Transmission line Resettlement Plan

Owner: Southern Vietnam Power Project Management Board- EVNNPT Page 85 Prepared by: Power Engineering Consulting JS. Company 2

Name of

tower Name of households Address

The numbe

r of person

s in HH

Total land holding of HH (m2)

Land to be

acquired (m2)

Percentage of

acquired land

(m2)

The number of affected land in ROW (m2)

Percentage of

affected land

Loss of Assets Loss of farm produce

Number and type of lost

structures

Structures

permanent (m2)

Structures

temporary (m2)

Area of

residential land lost (m2)

Fruit trees lost

Type and

Number

Rice area (m2)

Other lands

118 Vo Thi Ut Tan Thanh hamlet-Tan Ly Tay commune, Chau Thanh district, Tien Giang province

3 800 305.3

38.16

305.3

119 Nguyen Van Chinh 192/2 Tan Phong hamlet-Tan Ly Tay commune, Chau Thanh district, Tien Giang province

6 4,750 323.0

6.80 323

120 Nguyen Trung Truc 228 Team 6, Tan Luoc hamlet-Tan Ly Dong commune, Chau Thanh district, Tien Giang province

3 750 305.3 40.71 305.3

121 Nguyen Thi Kim Loan

58 Team 6, Tan Luoc 1 hamlet-Tan Ly Dong commune, Chau Thanh district, Tien Giang province

2 780 288.0 36.92 288

122 Ho Van Tam 174 Team 5, Tan Luoc 1 hamlet-Tan Ly Dong commune, Chau Thanh district, Tien Giang province

4 450 280.0 62.22 280

123 Ba Hong Ho Chi Minh city 4 2,000 305.3 15.27 305.3

124 Dang Thi Thuy Than Duc hamlet-Than Cuu Nghia commune, Chau Thanh district, Tien Giang province

3 2,000 305.3

15.27

305.3

125 Vo Thi Bay Than Duc hamlet-Than Cuu Nghia commune, Chau Thanh district, Tien Giang province

10 5,000 323.0 6.46 323

126 Tran Van Loi Thon Dao hamlet-Than Cuu Nghia commune, Chau Thanh district, Tien Giang province

1 3,050.3 305.3

10.01

323.0

127 Nguyen Van Thien 237/3 Thon Dao hamlet-Than Cuu Nghia commune, Chau Thanh district, Tien Giang province

6 800 323.0

40.38

323

128 Tran Thi Tam 448/2 Tan Phong hamlet-Tan Ly Tay commune, Chau Thanh district, Tien Giang province

2 2,000 305.3

15.27

305.3

129 Ngo Van Phong Thon Dao hamlet-Than Cuu Nghia commune, Chau Thanh district, Tien Giang province

3 2,500 483.0

19.32

483

130 Doan Van Chanh Thon Dao hamlet-Than Cuu Nghia commune, Chau Thanh district, Tien Giang province

5 1,000 305.3

30.53

305.3

131 Dinh Quoc Chien Long An commune, Chau Thanh district, Tien Giang province 4 2,950 305.3 10.35 305.3

132 Nguyen Thi Luong Thon Dao hamlet-Than Cuu Nghia commune, Chau Thanh district, Tien Giang province

4 1,000 323.0

32.30

323

133 Nguyen Van Em Thon Dao hamlet-Than Cuu Nghia commune, Chau Thanh district, Tien Giang province

3 2,900 323.0

11.14

323

134 Nguyen Van Cu Hamlet I-Tam Hiep commune, Chau Thanh district, Tien Giang province

1 450 305.3

67.84

305.3

Page 199: TRANSMISSION EFFICIENCY PROJECT DD2-10-001B · SOUTHERN POWER PROJECT MANAGEMENT BOARD TRANSMISSION EFFICIENCY PROJECT DD2-10-001B SUB-PROJECT REHABILITATION AND UPGRADING OF PHU

Rehabilitatin and Upgrading of Phu Lam – Cai Lay 2 220kV Transmission line Resettlement Plan

Owner: Southern Vietnam Power Project Management Board- EVNNPT Page 86 Prepared by: Power Engineering Consulting JS. Company 2

Name of

tower Name of households Address

The numbe

r of person

s in HH

Total land holding of HH (m2)

Land to be

acquired (m2)

Percentage of

acquired land

(m2)

The number of affected land in ROW (m2)

Percentage of

affected land

Loss of Assets Loss of farm produce

Number and type of lost

structures

Structures

permanent (m2)

Structures

temporary (m2)

Area of

residential land lost (m2)

Fruit trees lost

Type and

Number

Rice area (m2)

Other lands

135 Le Van Son Hamlet I-Tam Hiep commune, Chau Thanh district, Tien Giang province

4 14,000 288.0

2.06

288

136 Ngo Van Bac Hamlet I-Tam Hiep commune, Chau Thanh district, Tien Giang province

6 3,500 305.3

8.72

305.25

137 Nguyen Van Vu Trong Tranh hamlet-Tam Hiep commune, Chau Thanh district, Tien Giang province

5 450 288.0

64.00

288

138 Ho Van Phung Hamlet 2, Team 13-Tam Hiep commune, Chau Thanh district, Tien Giang province

4 500 288.0

57.60

288

139 Nguyen van Tri Hamlet 4-Tam Hiep commune, Chau Thanh district, Tien Giang province

4 600 305.3

50.88

305.3

140 Do Tien Duc Hamlet 4-Tam Hiep commune, Chau Thanh district, Tien Giang province

7 1,000 305.3

30.53

305.3

141 Huynh Thi Be Tu Hamlet 4-Tam Hiep commune, Chau Thanh district, Tien Giang province

4 872 305.3 35.01 305.3

142 Nguyen Van Hoang Hamlet 4-Tam Hiep commune, Chau Thanh district, Tien Giang province

5 798 305.3 38.26 305.3

143 Tran Thi My Dong hamlet-Long Dinh commune, Cai Lay district, Tien Giang province

6 1,800 263.5 14.64 263.5

144 Bui Van Tan Dong hamlet-Long Dinh commune, Cai Lay district, Tien Giang province

5 3,400 625.0 18.38 625

145 Nguyen PhU Minh Dong hamlet-Long Dinh commune, Cai Lay district, Tien Giang province

5 1,000 288.0 28.80 288

146 Vo Van Be Dong hamlet-Long Dinh commune, Cai Lay district, Tien Giang province

5 1,800 305.3

16.96

305.3

147 Vietnam Institute of Seed Sciences Long Dinh commune, Cai Lay district, Tien Giang province

14,000 305.3

2.18

305.3

148 Phan Van Tan Long Dinh commune, Cai Lay district, Tien Giang province 4 628 305.3 48.61 305.3

149 Huynh Van Muoi Trung hamlet , Long Dinh commune, Chau Thanh district, Tien Giang province

4 1,500 305.3

20.35

305.3

150 Huynh Kim Quang Trung hamlet , Long Dinh commune, Chau Thanh district, Tien Giang province

4 810 305.3

37.69

305.3

151 Tran Van Thong Tay 2 hamlet , Long Dinh commune, Chau Thanh district, 1 800 288.0 36.00 288

Page 200: TRANSMISSION EFFICIENCY PROJECT DD2-10-001B · SOUTHERN POWER PROJECT MANAGEMENT BOARD TRANSMISSION EFFICIENCY PROJECT DD2-10-001B SUB-PROJECT REHABILITATION AND UPGRADING OF PHU

Rehabilitatin and Upgrading of Phu Lam – Cai Lay 2 220kV Transmission line Resettlement Plan

Owner: Southern Vietnam Power Project Management Board- EVNNPT Page 87 Prepared by: Power Engineering Consulting JS. Company 2

Name of

tower Name of households Address

The numbe

r of person

s in HH

Total land holding of HH (m2)

Land to be

acquired (m2)

Percentage of

acquired land

(m2)

The number of affected land in ROW (m2)

Percentage of

affected land

Loss of Assets Loss of farm produce

Number and type of lost

structures

Structures

permanent (m2)

Structures

temporary (m2)

Area of

residential land lost (m2)

Fruit trees lost

Type and

Number

Rice area (m2)

Other lands

Tien Giang province

152 Tran Van Van Tay 2 hamlet , Long Dinh commune, Chau Thanh district, Tien Giang province

4 890 305.3

34.30

305.3

153 Nguyen Van Thu Tay 1 hamlet, Long Dinh commune, Chau Thanh district, Tien Giang province

3 2,000 483.0

24.15

483

154 Ngo Minh Duc Tay hamlet, Nhi Binh commune, Chau Thanh district, Tien Giang province

6 500 323.0

64.60

323

155 Nguyen Van Tu Moi hamlet, Long Dinh commune, Chau Thanh district, Tien Giang province

7 1,400 451.0 32.21 451

156 Nguyen Van Tung Tan Trang hamlet, Dong Hoa commune, Chau Thanh district, Tien Giang province

5 1,400 451.0

32.21

451

157 Ngo Thi Thao Moi hamlet, Long Dinh commune, Cai Lay district, Tien Giang province

4 2,000 379.3

18.96

379.25

158 Nguyen Van Toan Hoa hamlet, Nhi Binh commune, Cai Lay district, Tien Giang province

3 879 305.3

34.73

305.3

159 Tran Van Tam Hung hamlet, Nhi Binh commune, Cai Lay district, Tien Giang province

5 752 305.3

40.60

305.3

160 Nguyen Van Khanh Tay 1 hamlet, Long Dinh commune, Chau Thanh district, Tien Giang province

2 1,820 288.0

15.82

288

161 Tran Van Hai Tay hamlet, Nhi Binh commune, Cai Lay district, Tien Giang province

4 4,800 305.3

6.36

305.3

162 Le Thi Liem Tay hamlet, Nhi Binh commune, Cai Lay district, Tien Giang province

2 1,000 288.0

28.80

288

163 Nguyen Van Cu Hung hamlet, Diem Hy commune, Cai Lay district, Tien Giang province

5 3,850 483.0

12.55

483

164 Nguyen Van Duc Hung hamlet, Diem Hy commune, Cai Lay district, Tien Giang province

4 5,000 305.3 6.11 305.3

165 Vo Van Nghe Hung hamlet, Diem Hy commune, Cai Lay district, Tien Giang province

5 950 305.3 32.14 305.3

166 Tran Van SAu Bac B hamlet, Diem Hy commune, Cai Lay district, Tien Giang province

5 1,000 305.3 30.53 305.3

167 Tran Van Nam Bac B hamlet, Diem Hy commune, Cai Lay district, Tien Giang province

7 1800 305.3

16.96

305.3

Page 201: TRANSMISSION EFFICIENCY PROJECT DD2-10-001B · SOUTHERN POWER PROJECT MANAGEMENT BOARD TRANSMISSION EFFICIENCY PROJECT DD2-10-001B SUB-PROJECT REHABILITATION AND UPGRADING OF PHU

Rehabilitatin and Upgrading of Phu Lam – Cai Lay 2 220kV Transmission line Resettlement Plan

Owner: Southern Vietnam Power Project Management Board- EVNNPT Page 88 Prepared by: Power Engineering Consulting JS. Company 2

Name of

tower Name of households Address

The numbe

r of person

s in HH

Total land holding of HH (m2)

Land to be

acquired (m2)

Percentage of

acquired land

(m2)

The number of affected land in ROW (m2)

Percentage of

affected land

Loss of Assets Loss of farm produce

Number and type of lost

structures

Structures

permanent (m2)

Structures

temporary (m2)

Area of

residential land lost (m2)

Fruit trees lost

Type and

Number

Rice area (m2)

Other lands

168 Nguyen Van Bay Bac B hamlet, Diem Hy commune, Cai Lay district, Tien Giang province

6 580 305.3 52.64 305.3

169 Nguyen Thi Mai Bac B hamlet, Diem Hy commune, Cai Lay district, Tien Giang province

5 2,000 280.0 14.00 280

170 Nguyen Van Man Thoi hamlet, Diem Hy commune, Cai Lay district, Tien Giang province

4 5,000 181.3 3.63

181.3

171 Nguyen Thi Be Quy Thanh hamlet, Tan Hoi commune, Cai Lay district, Tien Giang province

4 500 217.0 43.40

217

172 Nguyen Van Nhat Quy Thanh hamlet, Tan Hoi commune, Cai Lay district, Tien Giang province

7 500 202.0 40.40

202

173 Nguyen Van Lam Quy Thanh hamlet, Tan Hoi commune, Cai Lay district, Tien Giang province

6 800 217.0 27.13

217

174 Nguyen Van Loc Quy Thanh hamlet, Tan Hoi commune, Cai Lay district, Tien Giang province

3 1,674 202.5 12.10 202.5

175 Huynh Van Trong Quy Thanh hamlet, Tan Hoi commune, Cai Lay district, Tien Giang province

4 3,000 217.0 7.23 217

176 Doan Van Luot

Quy Thanh hamlet, Tan Hoi commune, Cai Lay district, Tien Giang province

5 345 247.5

71.74

247.5

177 Nguyen Van Hung

My Can hamlet, Nhi My commune, Cai Lay district, Tien Giang province

5 4,000 181.3

4.53

181.3

178 Nguyen Van Thoi Quy Thanh hamlet, An Hoi commune, Cai Lay district, Tien Giang province

5 474 181.3 38.25 181.3

179 Tran Hai Bao Tan Phong hamlet, Quy Thanh commune, Cai Lay district, Tien Giang province

8 720 181.3 25.18 181.3

180 Vu Van Dan Tan Phong hamlet, Quy Thanh commune, Cai Lay district, Tien Giang province

4 1,300 247.5 19.04 pond

181 Huynh Thi Dong My Thuan hamlet, Nhi My commune, Cai Lay district, Tien Giang province

4 500 247.5 49.50 pond

182 Nguyen Bay Hung My An hamlet, Nhi My commune, Cai Lay district, Tien Giang province

2 400 202.5 50.63 202.5

183 Nguyen Van Viet Tan Phong hamlet, Tan Hoi commune, Cai Lay district, Tien Giang province

6 320 217.0 67.81 217

Page 202: TRANSMISSION EFFICIENCY PROJECT DD2-10-001B · SOUTHERN POWER PROJECT MANAGEMENT BOARD TRANSMISSION EFFICIENCY PROJECT DD2-10-001B SUB-PROJECT REHABILITATION AND UPGRADING OF PHU

Rehabilitatin and Upgrading of Phu Lam – Cai Lay 2 220kV Transmission line Resettlement Plan

Owner: Southern Vietnam Power Project Management Board- EVNNPT Page 89 Prepared by: Power Engineering Consulting JS. Company 2

Name of

tower Name of households Address

The numbe

r of person

s in HH

Total land holding of HH (m2)

Land to be

acquired (m2)

Percentage of

acquired land

(m2)

The number of affected land in ROW (m2)

Percentage of

affected land

Loss of Assets Loss of farm produce

Number and type of lost

structures

Structures

permanent (m2)

Structures

temporary (m2)

Area of

residential land lost (m2)

Fruit trees lost

Type and

Number

Rice area (m2)

Other lands

184 Nguyen Van Don Bo Ke hamlet, Nhi My commune, Cai Lay district, Tien Giang province

6 2,000 262.5 13.13 262.5

185 Nguyen Van A Nhi My hamlet, Nhi My commune, Cai Lay district, Tien Giang province

7 3,000 181.3 6.04 181.3

186 Nguyen Van Mãnh My Can hamlet, Nhi My commune, Cai Lay district, Tien Giang province

6 8,000 419.3 5.24 419.3

187 Nguyen Van Hoi My Loi hamlet, Nhi My commune, Cai Lay district, Tien Giang province

5 2,000 419.3 20.97 419.3

188 Tran Van Hung My Can hamlet, Nhi My commune, Cai Lay district, Tien Giang province

5 4,000 247.5 6.19 247.5

189 Nguyen Van Dao Team 5, Cai Lay district, Tien Giang province 3 700 341.3 48.76 341.3