Upload
others
View
4
Download
0
Embed Size (px)
Citation preview
RT-GCG Cost Recovery Framework
Technical Panel update
Pre-Approved Values and
Planned Maintenance Framework
May 31, 2016
IESOTP 297-4b
1. Stakeholder engagement update
i. IESO responses to stakeholder feedback from March 31 meeting
ii. Update from May 26 stakeholder meeting
2. Overview of proposed Market rule and Market Manual changes
i. Market Manual - Cost Information
ii. Market Manual – Supporting Processes
3. Proposed changes to Market Rules
4. Next steps
Agenda
2
3
IESO responses to stakeholder feedback
• Program should allow for recovery of actual cost or if pre-approved, there should be a ‘true-up’
• Requests for further data/details on costs
• Regular review of program
• Cap and Trade
• Process for resource-specific costs
• Other costs should be included
• Some costs currently in the framework should be removed
Stakeholder Feedback
4
• RT-GCG is not a full cost-recovery program
• Proposed framework will allow recovery of certain incremental costs eligible under program through pre-approved values informed by principles and methodology discussed at last meeting
• IESO will provide further information underpinning values
• Pre-approved values will be finalized after market rules are approved
• Proposed full program review every 3 years
• Resource-specific discussions to begin in coming weeks
Response to Feedback
5
6
Overview of changes to Market Rules and Market Manuals
In order to implement the proposed changes to the RT-GCG program, market rules and market manuals will be revised:
• Market rules specify market participant and IESO obligations – Higher level obligations
– Specifies “what” market participants/the IESO are obligated to do
• Market manuals outline the specifics of how to meet those obligations – Specifies the “how” or the details of how MPs/the IESO must
meet their obligations
7
Market Rule and Market Manual Changes
Section Market Rule Content Market Manual Content
Chapter 7
2.2B.1.4 Data submission requirements: registration data, cost data and other data
Process/timelines for data submission; Identify specific data to be submitted; Describe screening processes
2.2B.2
IESO right to audit data submissions and recover over-payments
N/A
2.2B.3 Retention requirements for documentation and data
Identify supporting documentation and data that must be retained
2.2B.4 Definition of costs that are eligible under the program
Describe cost categories
2.2B.5 IESO determination and revision of pre-approved cost values and methodologies
Process for revision of pre-approved cost values and methodologies
2.2B.6 Cost submission where pre-approved cost values and methodologies are not established
Submission process (not currently required)
Chapter 9 4.7B.5 Formula for calculating pre-approved eligible costs
Identify pre-approved values and methodology for calculating submitted values
Chapter 11 Definitions
Definition of combined guaranteed costs
Describe point of initiation for different resource types
8
Market Manual References and Content
Market Manual Content – Cost Information
• Market rule amendments in Ch. 7 section 2.2B.4; Ch. 9 section 4.7B.5; Ch. 11 will be supported by following information in the market manuals: – Cost recovery methodologies, including pre-approved universal
values, proposed description of start volume & point of initiation
– Proposed process for determining pre-approved planned maintenance values - additional detail provided in the Appendix to this presentation
Further description of cost categories in stakeholder engagement materials http://www.ieso.ca/Documents/consult/RTGCG/RTGCG-20160526-Presentation.pdf.
9
Component Measure Source/Value Potential Costs
Fuel Price $ NGX Union Dawn Day-Ahead Index price
for the gas day converted to CAD based
upon the noon hour foreign exchange rate
on the day of synchronization
~97% of the total
eligible fuel costs
Start
Volume
GJ Participant to provide based on metered
volume; IESO may audit
Included above
Compressor
Fuel
Volume
Adder
% Universal pre-approved value of 1% added
to the fuel volume for the incremental
percentage of fuel consumed by the
compressor associated with each GCG
eligible start, including volumes for injecting
or removing gas from storage
~1% of the total eligible
fuel costs
Services
Price Adder
$ Universal pre-approved value of $0.043
added to the fuel price for the additional
services costs related to the marketer risk
premium, commodity charge for
transportation and balancing and storage
~2% of the total eligible
fuel costs
Fuel Cost Recovery Methodology
10
Eligible fuel costs = (Fuel Price + Services Price Adder) * (Start Volume + (Start Volume * Compressor Fuel Volume Adder))
Example for a gas turbine submission:
($3.00 CDN + $0.043) * (3000 GJ + (3000*1%))
= $3.043 * 3030 GJ
= $9220.29
Note: this example uses a fictional price and start volume for illustrative purposes.
Fuel Cost Calculation Example
11
• Start Volume for a combined cycle facility: The volume of fuel used from the point of initiation to when MLP is reached (only for eligible RT-GCG submissions):
– Gas turbine submitting resource: only at the submitting resource gas turbine combustion burners
– Steam turbine submitting resource: duct burner fuel
– Based on 5-minute revenue data
• Point of initiation for a gas turbine resource occurs when the gas turbine rotor reaches self-sustaining speed
• Point of initiation for a steam turbine resource occurs at first fire of the steam boiler to generate steam to drive the steam turbine
• Point at which a resource reaches MLP is the ramp submission based on the actual interval of synchronization and actual interval in which the resource reaches its MLP
Proposed Start Volume & Point of Initiation
12
Component Measure Source Potential Costs
Electricity
Consumption
Price
$ Universal pre-approved value of $124.41/MWh for
the cost of electricity represented by Average
Supply Cost for RPP + Wholesale Market Services
Rate + regulatory charges (RRRP, OESP, DRC)
~2% of the total
eligible O&M costs
Electricity
Consumption
Quantity
MWh Universal pre-approved value of 1.5 MWh for the
incremental quantity of electricity consumed during
GCG eligible start-up (incremental cost of
maintaining vacuum prior to the GCG eligible start
to be added, still under development)
Included above
Operating
Consumables
Cost Adder
$ Universal pre-approved value of $63 for the
incremental cost of materials consumed during the
GCG eligible start
~0.5% of the total
eligible O&M costs
per start
Planned
Maintenance
Cost Adder
$ Resource-specific pre-approved value for the
incremental cost of planned maintenance materials
and services dependent on the GCG eligible starting
state (i.e. cold, warm, hot); IESO may audit to verify
appropriate value is applied
~97.5% of the total
eligible O&M costs
per start
O&M Cost Recovery Methodology
13
Eligible O&M costs = (Electricity Consumption Price * Electricity Consumption Quantity) + Operating Consumables Cost Adder + Planned Maintenance Cost Adder
Example for a combined cycle 1x1 start:
GT submission = ($124.41 * 1.5 MWh) + $63 + planned maintenance
= $249.62 + facility-specific planned maintenance
ST submission = ($124.41 * 1.5 MWh) + planned maintenance
= $186.62 + facility-specific planned maintenance
Note: this example does not include proxy for maintaining vacuum which is under development.
O&M Cost Calculation Example
14
1. IESO will issue request for information on planned maintenance costs for each facility to the registered representative – Form will specify information requirements (see appendix) – Evidence to support information in the form will also be
required (e.g. CSA/LTSA*, invoices, etc.) * Contractual Services Agreement/Long Term Services Agreement
2. The IESO, technical consultants and the facility representative will discuss the information and proposed resource-specific values
3. Once determined, the IESO will provide formal confirmation of the facility’s pre-approved values to the participant
Proposed Process for Determining Planned Maintenance Values
15
Market Manual Content - Supporting Processes
Market rule amendments in sections of Chapter 7 will be supported by the following information in market manuals:
• section 2.2B.1.4 – Method of cost submission
– Spot check/screening process
– Data requirements
• section 2.2B.3: – Retention of data
• section 2.2B.5: – Review/revision of pre-approved values - additional detail
provided in the Appendix to this presentation
16
• Participants will continue to make RT-GCG submission through an on-line form within the timelines specified in the existing IESO Real-Time Generation Cost Guarantee Payment Calendar
• Participants will continue to submit RT-GCG claims on a ‘resource’ basis as defined in Market Manual 1.2 (IESO registration system terminology, section 2.4.1) and GCG form 1552
• IESO will automate the new claim submission form as much as possible
Method of Cost Submission
17
IESO will identify submitted values (non pre-approved) that require further scrutiny:
• If a submitted value is outside of a reasonable tolerance for variations in that amount, the cost submission will not be processed by way of a preliminary settlement statement until it can be verified
• The cost submission will be reviewed by the IESO and evidence to support the amount may be requested
• The IESO may adjust the amount to be paid if its review determines an adjustment is warranted
Spot Check Process
18
• Data, such as operational and revenue meter fuel consumption, will be required to support cost submissions
• Participants are required to retain data for audit purposes for a period of 7 years from when cost is incurred
• IESO may audit values that are not pre-approved, for example for natural gas fueled facilities, including: – Fuel start volumes
– Start condition (e.g. cold, warm, hot) of a facility to confirm appropriate planned maintenance pre-approved value is applied
Data requirements for Audit
19
• IESO will complete a review of the program every 3 years including a review of all universal and resource-specific pre-approved values
• An earlier review of a pre-approved value may be completed at the IESO’s discretion if, for example, there is a material change in the underlying costs or a new cost is proposed for recovery
• To review a universal pre-approved value, the IESO will require historical cost data and supporting evidence similar to the requested data during this engagement
• Participants are required to retain data supporting pre-approved values for 7 years from when the cost is paid
Data requirements for Program Review
20
21
Changes to Proposed Market Rules
Market Rule - 2.2B.2
• The proposed market rules were introduced at the April 26 Technical Panel meeting
• Some Panel members expressed concern that the draft audit provision would allow the IESO to reduce GCG payments even where they are based on pre-approved cost values
• Revised wording clarifies that the IESO will not retroactively revise or audit pre-approved cost values, provided that, in relation to the data submitted, the participant is compliant with Chapter 1, sections 10A.1 and 11.2.1
22
Market Rule - 2.2B.2
• The reference to Chapter 1, section 11.2.1 notifies participants that if a pre-approved cost value is discovered by the IESO to be based upon untrue, incorrect, incomplete, misleading or deceptive data provided by a participant, then the IESO may review and/or seek recovery of the associated GCG payment made to that participant
23
Market Rule - 2.2B.2
• The reference to Chapter 1, section 10A.1 (General Conduct Rule) notifies participants that if a GCG payment is discovered by the IESO to be part of a scheme that breaches the General Conduct Rule, then the IESO may review and/or seek recovery of all components of that participant’s associated GCG payment including any pre-approved cost values
24
Market Rule - 2.2B.1.4C
• Some Panel members expressed concern that the draft rule language is too broad, particularly with respect to the words “any other data” and “contractual counter-party” – The challenge is that the IESO needs access to sufficient data in
support of the facility’s costs in order to prudently assess and pre-approve eligible costs
– For both internal and external audit purposes, the IESO needs to maintain a thorough and complete record of all the information considered when establishing pre-approved values for eligible costs
25
Market Rule - 2.2B.1.4C • Revised wording clarifies that the IESO’s requests will
be limited to data relevant for the purpose of enabling the IESO to determine eligible costs
• Further, the data requested from the participant is expected to be obtainable through best efforts
• The type of data (e.g. CSA/LTSA) will be further specified in the related market manual to the extent possible, for greater certainty
26
27
Next Steps
• Stakeholder engagement initiative:
– IESO will begin arranging one-on-one meetings to discuss resource-specific values in the coming weeks
– Next stakeholder meeting TBC pending feedback and outcome of one-on-one meetings
• Technical Panel
– Seek vote from TP to post draft market rules for stakeholder comment
Next Steps
28
29
Appendix – Proposed Planned Maintenance Description, Supporting Documentation and Review Process For information only
• The costs assessed should include: – costs that would be avoided if the resource did not start – planned maintenance activities from the time of the review up to
and including the next planned ‘major’ inspection (major inspection following the hot gas path inspection for a gas turbine and after the minor inspection for a steam turbine)
– if the next planned major inspection is less than 3 years from the time of the review, the costs used after the planned major inspection should be the same as before until a review is triggered and a new value provided
– the work scope and period over which the work scope is to be completed will be defined by the facility’s CSA or the original equipment manufacturer’s recommendations for the gas turbine island and steam turbine island
Proposed Pre-approved Planned Maintenance Values
30
• Information required for a Combined Cycle Gas Turbine may include: – Generation facility information including the model, capacity,
start-up times under different start conditions (i.e. cold, warm, hot)
– Inspection intervals and number of inspections per planned maintenance cycle for each type of planned maintenance (i.e. combustion inspection, hot gas path inspection, major inspection)
– Key CSA information such as the anticipated payment structure for CSA/LTSA, variable fees, ratio of fire factored hours to factored starts
– Supporting documentation for above information
Proposed Pre-approved Planned Maintenance Values
31
• Information required for a Combined Cycle Steam Turbine may include: – Generation facility information including the model, capacity,
start-up times under different start conditions (i.e. cold, warm, hot)
– Minor and major inspection intervals (equivalent operating hours)
– Weighting factors and calculated equivalent operating hours per start under different start conditions
– Supporting documentation for above information
Proposed Pre-approved Planned Maintenance Values
32
• Incremental costs during a Combined Cycle Gas Turbine planned maintenance outage may include: – CSA/LTSA milestone payments – replacement in-kind /refurbishment of parts required for the
planned maintenance outage for the gas turbine and gas turbine generator, if applicable
– consumables – technical advisors, incremental labour – crane rentals, temporary infrastructure – cost of permits, cost of utilities – waste disposal costs – additional items with sufficient justification may be considered
Proposed Pre-approved Planned Maintenance Values
33
• Incremental costs for Generation Facility Maintenance Consumables (Balance of Plant Maintenance) may include: – boiler feed water pumps – bypass systems and/or sky vents – Heat Recovery Steam Generator (HRSG) components - limited – condenser cooling water pumps – fuel gas booster compressor, where applicable – auxiliary boilers – miscellaneous maintenance consumables (nuts, bolts, gaskets,
etc.) – additional items with sufficient justification may be considered
Proposed Pre-approved Planned Maintenance Values
34
Examples of information required to assess or review pre-approved values:
• Contracts: fuel contracts or CSA/LTSA effective during the period including any amendments
• Operational data: 5 minute interval fuel operational meter consumption aligned with 5 minute electrical revenue data reconciled to hourly gas provider data in GJ
• OEM documentation, operational data, counter information and narratives detailing the cold, warm and hot start-ups for the steam turbine and various HRSG configurations
Review of Pre-approved Values
35
Examples of information required to assess or review pre-approved values, continued:
• Invoices and supporting data for operating and maintenance costs (e.g. CSA/LTSA invoices, resource specific water consumption, gas consumption, chemical consumption, lubricant consumption, etc.)
• Narratives explaining how costs related to submissions may have changed in quantum and methodology over the review period
• 3rd party outage reports related to the generation facility
• Data needed to calculate station service and consumables costs
Review of Pre-approved Values
36