JANUARY 2016
Tower A | Tower B | Tower C | Tower D | Tower E | Tower F | Tower G
Tower H | Tower I | Tower J | Tower K | Tower L | Tower M | Tower N
TOWER A : Level 7 Roof Completed. Level 8 Roof Shuttering and Reinforcement works in Progress.
TOWER B : Terrace Works in Progress.
TOWER C : Blockwork and Plastering Works in Progress
TOWER D, E & F : Flooring Works in Progress
TOWER G : Level 14 Roof Completed. Level 15 Roof Shuttering and Reinforcement Works in Progress
TOWER H : Upper Basement Slab Shuttering & Reinforcement Works in Progress
TOWER J : Upper Basement Roof Completed
TOWER K : Level 15 Roof Completed. Level 16 Roof Shuttering & Reinforcement Works in Progress
TOWER L : Lower Basement Slab Shuttering Works in Progress
TOWER M & N : Upper Basement Shuttering Works in Progress
PODIUM:
1. Tower A & G podium slab shuttering in progress.
2. Tower A, F, K & J podium area slab shuttering, reinforcement & concrete in
progress.
3. Tower L,M &N south side podium slab shuttering in progress.
4. Tower C ,D & E podium grade slab concrete in progress .
5. Tower B upper basement blockwork in progress.
6. Tower A upper basement blockwork & plastering in progress.