79
Total Steel Project Performance Construction Process Improvement through Progressive Steel Joist and Metal Decking Design

Total Steel Project Performance - BDC University

  • Upload
    others

  • View
    2

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Total Steel Project Performance - BDC University

Total Steel Project Performance

Construction Process Improvement through Progressive Steel Joist and Metal Decking Design

Page 2: Total Steel Project Performance - BDC University

Continuing Education Commitment

New Millennium Building Systems AND/OR Building Design + Construction is/are Registered Provider[s] of professional development hours (PDHs), GBCI and American Institute of Architects Continuing

Education System (AIA/CES) courses. Credit earned on completion of this program will be reported according to rules set forth by those organization. Certificates of Completion for all attendees are available on request.

This program is registered with [NAME ORGS] and the AIA/CES for continuing professional education. As such, it does not include content that may be deemed or construed to be an approval or endorsement by the AIA of any material of construction or any method or manner of handling, using, distributing, or dealing in any material or product.

Questions related to specific materials, methods, and services will be addressed at the conclusion of this presentation.

Page 3: Total Steel Project Performance - BDC University

Learning Objectives

After viewing and listening to this continuing-education module, you should be able to:

•! Recognize and understand the steel construction process through progressive steel joist and metal decking design and implementation.

•! Describe key elements and challenges of joist related total-project performance including cascading costs, cost assessment and the RFI process.

•! List the fundamentals of engineering for total-project cost accountability including tonnage reduction, deeper analysis of MEP, ESFR and joist-and-decking system

design and implementation practices.

•! Discuss the features and benefits of building-information modeling (BIM) based project collaboration for structural steel projects.

Page 4: Total Steel Project Performance - BDC University

Course Outline

I. Defining Progressive Steel Joist Design

II. Engineering for Total Project Cost Accountability

a. Basic approaches to reduce tonnage

b. Deeper analyses for greater cost accountability

c. Metal decking design considerations

III. Cost-Accountable Architectural Design

IV. Taking the Project Owner’s Point of View

V. Frequently Asked Questions

VI. Your Questions (and Answers)

Page 5: Total Steel Project Performance - BDC University

I. Defining Progressive Steel Joist Design

•! The structural steel package is vital to successful management of the construction process.

•! Steel delivery, design and/or detailing can produce significant costs and broadly impact project success.

•! Process improvements can provide significant advantages to building team, benefiting owners and developers.

Page 6: Total Steel Project Performance - BDC University

Cascading Cost Effect

CLASHES

REWORK

PROJECT DELAY

BACK CHARGES

CONTINGENCY EROSION

OCCUPANCY INCOME LOSS

Page 7: Total Steel Project Performance - BDC University

Cost Reduction – Value-Added Engineering

Manufacturing Warehousing Material Trucking Staging Erection

VA

LU

E-A

DD

ED

E

NG

INE

ER

ING

Page 8: Total Steel Project Performance - BDC University

Total Cost Assessment

COST AREAS POTENTIAL SAVINGS CASE STUDY

Materials 3% - 10% and up $1.3 million (9.7%)

Transportation 5% - 10% $ 6,726 (8.3%)

Project Handling $10 per ton $ 1,700 (0.1% total)

Design Errors $ 6,360 per error $ 6,360 (0.5% total)

Lost Occupancy Varies $ 3,000 / week

Logistics Varies

Storage Varies

Erection 10% and up $ 60,000

Addendums Varies

TOTAL SAVINGS $ 1,377,786.00

Page 9: Total Steel Project Performance - BDC University

The Broken RFI Process

•! Current process is dysfunctional.

•! Need for tighter collaboration between subs / suppliers.

•! Structural drawings up to 40% incomplete

•! Dimensions not shown

•! RFIs used for documenting and defending

•! Clashes with MEP and project delays

•! Costly contingency fees

The RFI process should be …

… a tool for fostering communication,

aiding in prevention of extra costs.

Page 10: Total Steel Project Performance - BDC University

Top Fabricator Complaint: The Indecision Loop

?

?

? ?

?

?

? ?

?

?

?

?

?

?

?

?

?

?

? ?

SUPPLIER

Page 11: Total Steel Project Performance - BDC University

II. Engineering for Total Project Cost Accountability

a.! Basic approaches to reduce tonnage

b.! Deeper analyses for greater cost accountability

c.! Metal decking design considerations

Page 12: Total Steel Project Performance - BDC University

a. Basic Approaches to Reduce Tonnage

Rule of Thumb for Material Efficiency

•! Average $1,000 savings per ton removed from steel package

•! Ways to save tonnage include:

1. Reorient the framing

Can save 0.25 lbs./ft. or $0.50 per sq. ft.

2. Updated diagram load data

Expedites metal-deck fastening

Page 13: Total Steel Project Performance - BDC University

Economy Table Tool

Page 14: Total Steel Project Performance - BDC University

Maximizing Deck Capacity

Generic intro and illustration needed. Chris to help?

Page 15: Total Steel Project Performance - BDC University

Space Joists to Maximize Deck Capacity

Page 16: Total Steel Project Performance - BDC University

Cost Reduction: Joist Spacing

12.2% WEIGHT REDUCTION

22% ERECTION SAVINGS

17.2% WEIGHT REDUCTION

Load / Foot Joist Standard Joist

Page 17: Total Steel Project Performance - BDC University

Design Collaboration – Delaney Warehouse

Standard Design Building (B22 Deck)

Girders are 47’-6”, 58” Deep, 10 Panels Based on 5’-0” o.c. Joists

500’ x 950’

44LH09 44LH09 30K11 30K11 30K11 30K10 30K10 30K10 30K10

40LH 40LH 30K 30K 30K 30K 30K 30K 30K

300/180 300/180 300/180 300/180 300/180 300/180 300/180 300/180 300/180

Revised Design Building (B22 Deck)

Joists Respaced at 5’-11 1/4” o.c.

Page 18: Total Steel Project Performance - BDC University

Results – Delaney Warehouse

Standard Design Revised Design SAVINGS

Total Tons 926.77 848.23 tons 78.54 tons

8.47%

Total Pieces 1841 1571 Pieces 270 pieces

14.66%

Total Cost $1,282,000 $1,157,117 $124,883

9.74%

Page 19: Total Steel Project Performance - BDC University

Design Out Costs – Cooper Tire Mfg.

12N

30K 192/117

44G 10.6K 12N 32G 9.7K

Assumed Loads vs. Actual Loads Initial Girders vs. Deeper Girders

68G 58G

Page 20: Total Steel Project Performance - BDC University

Design Out Costs – Cooper Tire Mfg.

12N

30K 269/125

44G 14.8K 12N 32G 13.5K

192/117

10.6K 9.7K

Assumed Loads Assumed Loads vs. Actual Loads

Page 21: Total Steel Project Performance - BDC University

Design Out Costs – Cooper Tire Mfg.

RESULTS

1351.25 tons 1251.29 tons

$1,491,632 $1,405,266

SAVINGS 99.96 tons (7.4%)

$86,366 (5.8%)

Page 22: Total Steel Project Performance - BDC University

b. Deeper Analysis = Greater Cost Analysis

In addition to cost analysis related to materials, transportation, handling and other related elements …

Thoroughly analyze all systems.

- MEP

- ESFR sprinkler systems

… for improved cost analysis

and savings.

Page 23: Total Steel Project Performance - BDC University

MEP Systems – Duct Passage

Page 24: Total Steel Project Performance - BDC University

MEP Clash Prevention for Cost Reduction

Benefits of MEP Coordination for Cost Savings

•! 10-20% cost savings using MEP clash prevention methods

•! Up to 20% cost reduction on steel package with early fabricator involvement

•! Cost reduction opportunities include:

1. Reducing rework.

Minor problems: 0.5% of project cost = $6,360

2. Related costs.

Clashes add to Lost Occupancy, Logistics, Storage, Erection, and Contingency Erosion.

Page 25: Total Steel Project Performance - BDC University

Design Impact of ESFR Sprinkler Systems

Page 26: Total Steel Project Performance - BDC University

Information from ESFR Contractor

•! Branch line locations and branch line O.D.

•! Distance from deck bottom to center of branch line

•! Minimum clearance between branch lines and bridging

Page 27: Total Steel Project Performance - BDC University

Information Supplied by ESFR Manufacturer

Page 28: Total Steel Project Performance - BDC University

Interference? No Problem. Flexibility!

Page 29: Total Steel Project Performance - BDC University

Example - Basic Cost Reduction

Benefits of ESFR Coordination for Cost Savings

•! Project cost savings estimated at ___________

•! Cost reduction opportunities include:

1. Reducing rework.

Minor problems: 0.5% of project cost = $6,360

2. Related costs.

Clashes add to Lost Occupancy, Logistics, Storage, Erection, and Contingency Erosion.

Page 30: Total Steel Project Performance - BDC University

Engineering for Even Greater Cost Accountability

Page 31: Total Steel Project Performance - BDC University

Metal Decking Design Issues

•! Use deeper seats

For R-type extensions there may be savings by increasing the extension seat depths.

•! Designate load and locations

Knowing loads and location of loads on joists will decrease costs.

•! Review the building layout

Try alternatives to framing. Avoid transferring moment through girder seats.

Page 32: Total Steel Project Performance - BDC University

Use Deeper Seats

An example: R-type extensions

Bearing angle: 2 @ 2x2x3/16

2 !”

Top chord: 2 @ 2x2x3/16 Joist weight:

228 lbs

Seat depth

5”

Top chord: 2 @ 1 ! x 1 ! x 1/8 Joist weight:

139 lbs Seat depth

Weight savings:

40%

Bearing angle: 2 @ 1 ! x 1 ! x 1/8

Page 33: Total Steel Project Performance - BDC University

Confirm Loads and Load Locations

An example

40’ span with 250plf total load and two 2000-lb. max loads

Requires 24KSC4 joists …

250 plf

2000 lbs 2000 lbs

Designates 24KSP joists…

250 plf

2000 lbs 2000 lbs

10’0” 10’0”

660 lbs per joist

420 lbs per joist

Weight savings:

36%

Page 34: Total Steel Project Performance - BDC University

Confirm Loads and Load Locations

Top chord extension design

Page 35: Total Steel Project Performance - BDC University

Joist Spacing for Maximum Deck Capacity

Page 36: Total Steel Project Performance - BDC University

Use of “Load Zone” Conditions

Load-zone joist vs. KCS joist: An example

Example: KCS selection is 26KCS4, vs. load-zone joist 26KZ200/100 (A, B)

KCS joist:

Load-zone joist:

660 lbs per joist

420 lbs per joist

Weight savings:

21%

Page 37: Total Steel Project Performance - BDC University

End Moment Connections

•! Increase design efficiency

•! Allow for highly efficient steel allocation

•! Traditional approaches are cost-inefficient!

Page 38: Total Steel Project Performance - BDC University

End Moment Connections

Page 39: Total Steel Project Performance - BDC University

End Moment Connections

Bolted type

Page 40: Total Steel Project Performance - BDC University

Incorporate Girders & Joists into Bracing Schemes

Page 41: Total Steel Project Performance - BDC University

Deeper Analyses: A Case Study

•! Costs reduced in all phases:

Design, delivery, assembly and erection

•! Steel tonnage reduced by 50% plus

•! 20% less manufacturing time

•! 67% less transportation costs – no wide-load

•! Reduced on-site storage

•! 66% reduction in erection labor / crane costs

S.C. Governor’s School for Science & Math

Challenge: Athletic wing over school’s gym area features

three-piece Fink-Truss design.

Page 42: Total Steel Project Performance - BDC University

Deeper Analyses: A Case Study

Cost Preventative Design

Page 43: Total Steel Project Performance - BDC University

Source: Structural Engineering & Design, July 2010.

Deeper Analyses: A Case Study

Joist design: A chain reaction of cost reductions

Page 44: Total Steel Project Performance - BDC University

c. Metal Decking Design Considerations

Page 45: Total Steel Project Performance - BDC University

Deck Gauge and Cost Calculation

Page 46: Total Steel Project Performance - BDC University

Specify special thickness!

Example: For a 5,000 ft2 deck…

20ga standard

490 tons required

21ga special

450 tons required

Saves 40 tons, or $25,000!

Deck Specifications … and Costs

Page 47: Total Steel Project Performance - BDC University

Decking Gauge & Cost Calculations

Example: Roof project in Shepherdsville, KY 6,056 squares of deck, specified painted 22ga Total weight: 488 tons

Potential cost and ton savings of 23ga Gravity load capacity: 25 psf total 23ga allowable for 3-span @ 5’-6 5/8”

Diaphragm strength required Pattern: Interior: 325 p/f 36/5 - 5 sidelaps Edges: 464 p/f 36/7 - 7 sidelaps

23ga Interior: 330 p/f 36/5 - 8 sidelaps Edges: 465 p/f 36/7 - 10 sidelaps

Total weight and cost savings for 23ga:

Deck: 8%

Joist/deck package: 2%

Page 48: Total Steel Project Performance - BDC University

Decking Span Restrictions

… Watch framing layouts!

Page 49: Total Steel Project Performance - BDC University

Temporary Shoring of Deck

Temporary Deck Shoring

Page 50: Total Steel Project Performance - BDC University

Per ANSI:

1.! Galvanizing must conform to ASTM A653 (A653M) 2.! Uncoated or phosphatized with painted underside

must be applied to steel conforming to A1008 (A1008M) 3.! Finish on steel composite deck must be suitable for

environment of structure.

Decking Finish Considerations

Page 51: Total Steel Project Performance - BDC University

Deck Accessories

Page 52: Total Steel Project Performance - BDC University

Unsupported Accessory Proper Composite Accessory

Decking Accessories Specification

Page 53: Total Steel Project Performance - BDC University

Shear Stud Strong Positioning

Page 54: Total Steel Project Performance - BDC University

3. Cost-Accountable Architectural Design

Page 55: Total Steel Project Performance - BDC University

Expanded Specifications for Special-Profile Steel Joists

Page 56: Total Steel Project Performance - BDC University

Architectural Vision: Detroit Airport

Cost-Accountable Architectural Design: Case Studies

Page 57: Total Steel Project Performance - BDC University

Architectural Vision: Pittsburgh Mills

Cost-Accountable Architectural Design: Case Study

Page 58: Total Steel Project Performance - BDC University

Castellated Beams for Eglin Air Force Base

•! Castellated beam design can achieve

appearance objectives plus functionality.

•! Array of solar panels will generate electricity.

•! Additional engineering steps removed costs and prevent downstream erection costs.

Cost-Accountable Architectural Design: Case Study

Page 59: Total Steel Project Performance - BDC University

4. Taking the Project Owner’s Point of View

Page 60: Total Steel Project Performance - BDC University

Improving the RFI Process

Architect

Fabricator

Contractor

Engineer

Supplier

Page 61: Total Steel Project Performance - BDC University

Digital Steel Joist Design

•! Develop / exchange digital, 3-D

steel joist plans with a (BIM) steel joist design component.

•! Addresses three stages of design:

1. Generic joist object for preliminary design. 2. Use of generic info for detailing- design process. 3. As-built joist BIM object with end conditions, member sizes

•! Joist object imported into BIM model

Page 62: Total Steel Project Performance - BDC University

BIM-Based Project Collaboration

•! Earlier decision-making

•! Works best with sound engineering

•! Complete data transfer & processing

•! Work with suppliers who are BIM-ready

•! Case studies demonstrate the value

Page 63: Total Steel Project Performance - BDC University

!""#$%

&$$"$'"()%

*+(,"-)./0%

1"$23(%

1")/20"#%

1"$23(%

*+($)4.,5+(% 6-"4/5+(%

7"0/58"%*+$)%

+9%%1"$23(%*:/(3"%

•! BIM forces early decision-making

•! Front-load all questions and details

•! Faster approval process

•! Fewer problems lead to more profitable job

BIM-Based Project Collaboration

Page 64: Total Steel Project Performance - BDC University

BIM Capabilities

•! Garbage in = Garbage out

•! BIM = lots of data

•! Users spend time checking

•! But BIG mistakes can happen

•! BIM still demands qualified manual detailing

•! Good detailers > BIM

BIM-Based Project Collaboration

Page 65: Total Steel Project Performance - BDC University

Inputs BIM

Modeling

Detail

Clarification

BOM Created

Steel

Fabrication

BIM allows for complete data transfer and processing

BIM-Based Project Collaboration

Page 66: Total Steel Project Performance - BDC University

BIM-Based Project Collaboration

Page 67: Total Steel Project Performance - BDC University

BIM-Based Project Collaboration

Page 68: Total Steel Project Performance - BDC University

BIM-Based Project Collaboration

Page 69: Total Steel Project Performance - BDC University

The Owner’s Point of View: BIM

Page 70: Total Steel Project Performance - BDC University

BIM-Based Project Collaboration

Page 71: Total Steel Project Performance - BDC University

BIM-Based Project Collaboration

Page 72: Total Steel Project Performance - BDC University

BIM-Based Project Collaboration

Page 73: Total Steel Project Performance - BDC University

BIM-Based Project Collaboration

Page 74: Total Steel Project Performance - BDC University

Project: Target Store, San Clemente, CA

•! Structural package, joists, modeled in 3-D BIM

•! Timeline for shop drawings:

Originally10 weeks …

… to 3.5 weeks

•! BIM goal: Better utilize space around steel for HVAC, electrical

Photo: Ocean County Register

BIM-Based Project Collaboration: A Case Study

Page 75: Total Steel Project Performance - BDC University

Project:

Target Stores

SOURCE: BUILDING DESIGN & CONSTRUCTION, JAN. 2011.

BIM-Based Project Collaboration: A Case Study

Page 76: Total Steel Project Performance - BDC University

“With BIM analysis tools we knew we could reduce conflicts and increase utilization of the space within our box. We

wanted to move beyond that. We wanted to use BIM as a

way to figure out what was in there and then establish that and

build in protocols for how we could start to utilize that space to

reduce the height of our buildings, or maximize the amount of space we have, or minimize the amount of structure put up.”

-!Brad Koland

Group Manager

Structural Engineering, Target

Target on the Effectiveness of BIM

BIM-Based Project Collaboration: A Case Study

Page 77: Total Steel Project Performance - BDC University

Questions and Answers

Total Steel Project Performance

Page 78: Total Steel Project Performance - BDC University

This concludes this registered PDH OR American Institute of Architects Continuing Education Systems Program OR GBCI-registered program

Total Steel Project Performance

Page 79: Total Steel Project Performance - BDC University

Total Steel Project Performance

Construction Process Improvement through Progressive Steel Joist and Metal Decking Design