Total Operational Excellence 20/06/22 1 Case Study: Improvement Projects Leila Sarcia- BI Specialist Rio Tinto Group- Energy Resources Aust.

Total Operational Excellence 18/09/2015 1 Case Study: Improvement Projects Leila Sarcia- BI Specialist Rio Tinto Group- Energy Resources Aust

Embed Size (px)

Citation preview

Page 1: Total Operational Excellence 18/09/2015 1 Case Study: Improvement Projects Leila Sarcia- BI Specialist Rio Tinto Group- Energy Resources Aust

Total Operational Excellence 21/04/23

1

Case Study:Improvement Projects

Leila Sarcia- BI Specialist Rio Tinto Group- Energy Resources Aust.

Page 2: Total Operational Excellence 18/09/2015 1 Case Study: Improvement Projects Leila Sarcia- BI Specialist Rio Tinto Group- Energy Resources Aust

Total Operational Excellence 21/04/23 2

Learnings from the Case Study

• Gaining active involvement of C-level – sponsorship and ownership

• How to influence executive decisions and sponsorship with winning business case for continuous funding

• Selling and marketing your improvement projects/ programmes with maximum visibility of outcomes and financial gains

• Establishing and driving executive ownership – knowing how to keep management on board for sustainable change

Page 3: Total Operational Excellence 18/09/2015 1 Case Study: Improvement Projects Leila Sarcia- BI Specialist Rio Tinto Group- Energy Resources Aust

Total Operational Excellence 21/04/23 3

• In 2009 up to present, Improvement projects initiative was rolled out, the metric is for each department to generate cost reduction projects that will impact the annual operating budget expense.

• It is a “cost” reduction initiative intended to reduce the plan operating expense.

• The cost savings will be achieved and recognized as a result of team’s efforts.

Case Study: Improvement Projects

Page 4: Total Operational Excellence 18/09/2015 1 Case Study: Improvement Projects Leila Sarcia- BI Specialist Rio Tinto Group- Energy Resources Aust

Total Operational Excellence 21/04/23

Project Charter

4

• Project charter contains the business case showing the benefits of the project.

• To be approved by the sponsor.

Page 5: Total Operational Excellence 18/09/2015 1 Case Study: Improvement Projects Leila Sarcia- BI Specialist Rio Tinto Group- Energy Resources Aust

Total Operational Excellence 21/04/23 5

• Consolidated tracking and verification through project review.

• Periodic reporting on a monthly basis by each Manager to provide information on the progress.

• Each senior leaders are accountable to achieve the target. Each Manager to measure and report the achievement by the end of the year.

Case Study: Improvement Projects

Page 6: Total Operational Excellence 18/09/2015 1 Case Study: Improvement Projects Leila Sarcia- BI Specialist Rio Tinto Group- Energy Resources Aust

Total Operational Excellence 21/04/23 6

Improvement Projects

Process Flow

Page 7: Total Operational Excellence 18/09/2015 1 Case Study: Improvement Projects Leila Sarcia- BI Specialist Rio Tinto Group- Energy Resources Aust

Total Operational Excellence 21/04/23 7

• Review of each project charter to make sure that the target savings can be verified.

• To assess the quality of project to assure that the results can be measured and are aligned with the intent to reduce plan costs.

• All initial reviews will be completed by the end of Quarter1.

1. Initial Review

Page 8: Total Operational Excellence 18/09/2015 1 Case Study: Improvement Projects Leila Sarcia- BI Specialist Rio Tinto Group- Energy Resources Aust

Total Operational Excellence 21/04/23 8

2. Periodic Reporting

• A periodic reporting on a monthly basis by each Manager to provide information on the progress.

• A project tracker will be maintain at a department level and consolidated at the business level.

• Tracker will be updated by each department every end of the month.

Page 9: Total Operational Excellence 18/09/2015 1 Case Study: Improvement Projects Leila Sarcia- BI Specialist Rio Tinto Group- Energy Resources Aust

Total Operational Excellence 21/04/23 9

Tracking ToolsProject

No.Project Title Accountability

Planned Savings $000

Forecast Savings

$000

Actual Savings $000

LOC-001 Neutralisation Lime Usage Reduction 1000 4400 2670LOC-002 R&D Projects Tax Return to the Business 1530 1530 1530LOC-003 Leach Tank Repairs 350 350 0LOC-004 High Cr Grinding Media Trial on BM1 300 150 40LOC-005 Pond water usage reduction - using Brine 500 150 148LOC-006 Rod Mill Liner Wear Monitoring and Reline Strategy 130 130 110LOC-007 Calciner Fuel Reductions 100 30 10LOC-008 L.E.D lighting changes 30 30 8LOC-009 Leach Chemistry Optimisation TBD TBD TBDLOC-010 Fine pH control in Leach Tanks TBD TBD TBDLOC-011 Primary Screen Bottom Deck TBD TBD TBDLOC-012 Alternative to Water Truck Hire 47 70 70LOC-013 Mineralogy Assay Reprogramming 60 30 28LOC-014 Rationalisation of Plant Ops Roles 200 200 200LOC-015 Solar Array 3 3 2LOC-016 Cooling Tower Treatment 15 25 0

Planned Forecast ActualTOTAL $4,265 $7,098 $4,816

(millions) $4.27 $7.10 $4.82

Page 10: Total Operational Excellence 18/09/2015 1 Case Study: Improvement Projects Leila Sarcia- BI Specialist Rio Tinto Group- Energy Resources Aust

Total Operational Excellence 21/04/23

  Planned Forecast Actual

TOTAL (millions)

$5.23 $8.28 $5.25

2012 Cost Savings Metric• Updated and reported monthly

Page 11: Total Operational Excellence 18/09/2015 1 Case Study: Improvement Projects Leila Sarcia- BI Specialist Rio Tinto Group- Energy Resources Aust

Total Operational Excellence 21/04/23 11

3. Closeout Review

• A final review will take place to determine whether your targeted savings were realized based upon the agreed measurement established in the initial meeting.

• All reviews will be scheduled by the end of November of every year.

• All closure reviews will be completed by the end of January of the following year.

Page 12: Total Operational Excellence 18/09/2015 1 Case Study: Improvement Projects Leila Sarcia- BI Specialist Rio Tinto Group- Energy Resources Aust

Total Operational Excellence 21/04/23 12

Cost Savings (2009-2012)

$5M

$3.5M

$13M

$8.3M

0

2

4

6

8

10

12

14

2009 Actual 2010 Actual 2011 Actual 2012 Forecast

(mil

lio

ns

)

2009 2010 2011 2012

$5M $3.5M $13M

$8.3M

Page 13: Total Operational Excellence 18/09/2015 1 Case Study: Improvement Projects Leila Sarcia- BI Specialist Rio Tinto Group- Energy Resources Aust

Total Operational Excellence 21/04/23 13

Page 14: Total Operational Excellence 18/09/2015 1 Case Study: Improvement Projects Leila Sarcia- BI Specialist Rio Tinto Group- Energy Resources Aust

Total Operational Excellence 21/04/23 14

Page 15: Total Operational Excellence 18/09/2015 1 Case Study: Improvement Projects Leila Sarcia- BI Specialist Rio Tinto Group- Energy Resources Aust

Total Operational Excellence 21/04/23 15

Page 16: Total Operational Excellence 18/09/2015 1 Case Study: Improvement Projects Leila Sarcia- BI Specialist Rio Tinto Group- Energy Resources Aust

Total Operational Excellence 21/04/23 16

Page 17: Total Operational Excellence 18/09/2015 1 Case Study: Improvement Projects Leila Sarcia- BI Specialist Rio Tinto Group- Energy Resources Aust

Total Operational Excellence 21/04/23

Page 18: Total Operational Excellence 18/09/2015 1 Case Study: Improvement Projects Leila Sarcia- BI Specialist Rio Tinto Group- Energy Resources Aust

Total Operational Excellence 21/04/23 18

Page 19: Total Operational Excellence 18/09/2015 1 Case Study: Improvement Projects Leila Sarcia- BI Specialist Rio Tinto Group- Energy Resources Aust

Total Operational Excellence 21/04/23 19

Page 20: Total Operational Excellence 18/09/2015 1 Case Study: Improvement Projects Leila Sarcia- BI Specialist Rio Tinto Group- Energy Resources Aust

Total Operational Excellence 21/04/23 20

Page 21: Total Operational Excellence 18/09/2015 1 Case Study: Improvement Projects Leila Sarcia- BI Specialist Rio Tinto Group- Energy Resources Aust

Total Operational Excellence 21/04/23 21

Thank You!

The success of Improvement projects?................................................. Striving for Operational excellence.