Upload
itoki229
View
218
Download
0
Embed Size (px)
Citation preview
8/10/2019 Topic3_CapitalBudgeting
1/52
FINS1613: Business FinanceSemester 2, 2014
Topic: Capital Budgeting I
8/10/2019 Topic3_CapitalBudgeting
2/52
Contact Details
Emma Jincheng Zhang (Weeks 5-7) [email protected] Rm 302Consultation hours: Monday 9-11am
mailto:[email protected]:[email protected]8/10/2019 Topic3_CapitalBudgeting
3/52
Outline
1. Introduction to capital budgetinga. Independent and mutually exclusive projects
2. Investment decision rulesa. Net present value (NPV)
b. Payback rulec. Average accounting return (AAR)d. Internal rate of return (IRR)e. Modified internal rate of return (MIRR)f. Profitability index (PI)
3
8/10/2019 Topic3_CapitalBudgeting
4/52
1. Introduction to capitalbudgeting
4
8/10/2019 Topic3_CapitalBudgeting
5/52
Role of the financial manager
5
It is the role of the financial manager to make someimportant decisionsCapital budgeting (investment decision)
What long-term investments should the firm take on?
Capital structure (financing decision)Where will we get the long-term financing to pay for the investment?Working capital management
How will we manage the everyday financial activities of the firm?
8/10/2019 Topic3_CapitalBudgeting
6/52
Capital budgeting decision criteria
6
We need to ask ourselves the following questions whenevaluating decision criteria:Does the decision rule adjust for the time value of money?Does the decision rule adjust for risk?
Does the decision rule provide information on whether we arecreating value for the firm?
8/10/2019 Topic3_CapitalBudgeting
7/52
Independent projects
7
What are independent projects?Independent Projects are investments that have no impact oneach others cash flows. This means that the company decides to accept or reject eachproject and that decision will have no impact on whether
another project is accepted or rejected.The firm could accept one or more projects or it could rejectthem all.
8/10/2019 Topic3_CapitalBudgeting
8/52
Mutually exclusive projects
8
What are mutually exclusive projects?Mutually exclusive projects are investments in which acceptingone project requires reject of all other options.This may be due to financial constraints or limitations toavailable assets.Projects need to be ranked in order to determine which toundertake.
8/10/2019 Topic3_CapitalBudgeting
9/52
Mutually exclusive projects
9
An example of two mutually exclusive projects is:A company has a piece of land and it is debating either buildingan office block on the land or building a warehouse.It cannot use the same piece of land for two different things atthe same time.These are mutually exclusive projects.
8/10/2019 Topic3_CapitalBudgeting
10/52
Mutually exclusive projects
10
A second example of two mutually exclusive projects is:A company has a fixed budget of $20,000 for investment thisyear. The firm is considering two projects. The first will take$15,000 to establish and the second project will require$18,000.
Clearly, only one project can be carried out this year so theyare mutually exclusive.
8/10/2019 Topic3_CapitalBudgeting
11/52
2. Investment Decision Rules
11
8/10/2019 Topic3_CapitalBudgeting
12/52
Net Present Value
12
Net present value (NPV): The difference between aninvestments market value and its initial investment.Steps in calculating the NPV:
Step 1: Estimate the expected future cash
flows.Step 2: Estimate the required return for projectsof this risk level.
Step 3: Find the present value of the cash flows
and subtract the initial investment toarrive at the net present value.NPV Rule: An investment should be accepted if the netpresent value is positive and rejected if it is negative
8/10/2019 Topic3_CapitalBudgeting
13/52
Net Present Value
13
1 =
C t: Cash flows from the project. These cash flows areusually inflows (positive).C0: Initial cost of the project. This is usually an outflow
(negative)r: the discount rate for the project
8/10/2019 Topic3_CapitalBudgeting
14/52
Net Present Value
14
Cash inflows:Receipts from sale of goods and servicesReceipts from sale of physical assets
Cash outflows:
Expenditure on materials, labour, and indirect expenses formanufacturingSelling and administrativeInventory and taxes
8/10/2019 Topic3_CapitalBudgeting
15/52
Net Present Value Decision Rule
15
If NPV is positive, accept the project NPV > 0 means:
project is expected to add value to the firmproject will increase the wealth of the owners
NPV is a direct measure of how well this project willachieve the goal of increasing shareholder wealth.
NPV represents the net gain in shareholder wealth
8/10/2019 Topic3_CapitalBudgeting
16/52
Example: Net Present Value
16
You are looking at a new project and have estimated thefollowing cash flows and net income:
The average book value is $72,000Your required return for assets of this risk is 12%
We will use this project for all investment decision rules.
Year Cash Flow Net Income
0 -165,000
1 63,120 13,6202 70,800 3,300
3 91,080 29,100
8/10/2019 Topic3_CapitalBudgeting
17/52
Example: Net Present Value
17
1
=
63,1201.12 70,8001.12 91,0801.12165,000 = $12,627.41
t = 0 t = 1 t = 2
$63,120
t = 3
$70,800 $91,080-$165,000
8/10/2019 Topic3_CapitalBudgeting
18/52
Analysing the NPV rule
18
Meets all desirable criteriaConsiders all cash flowsConsiders time value of moneyAdjusts for risk
Can rank mutually exclusive projectsNPV method is consistent with the companys objectiveof maximising shareholders wealth. Dominant method; always prevails
8/10/2019 Topic3_CapitalBudgeting
19/52
Payback rule
19
Payback Period: The amount of time required for aninvestment to generate net cash flows sufficient torecover its initial cost (investment).Steps in calculating the payback period:
Step 1: Estimate the expected future cashflows.Step 2: Subtract the future cash flows from the initialcost until initial investment is recovered.
Payback Rule: Accept if the payback period is less thansome predetermined limit.
8/10/2019 Topic3_CapitalBudgeting
20/52
Example: Payback rule
20
2 2,, 2.34
Do we accept or reject the project?Depends on the companys predetermined limit.
Year Cash Flow Cumulative Cash Flow0 -165,000 -165,000
1 63,120 -101,880
2 70,800 -31,080
3 91,080 60,000
8/10/2019 Topic3_CapitalBudgeting
21/52
Example: Payback rule
21
Your companys payback period is 2 years. According tothe payback rule, which of the following projects will youaccept?
Year A B C D E
0 -$100 -$200 -$200 -$200 -$50
1 30 40 40 100 100
2 40 20 20 100 -50,000,000
3 50 10 10 -200
4 60 130 200Payback period 2.6 Never 4 2 or 4 0.5
8/10/2019 Topic3_CapitalBudgeting
22/52
Analysing the payback rule
22
Advantages
Easy to understand Adjusts for uncertainty of
later cash flows Biased towards liquidity
Disadvantages
Ignores the time value ofmoney
Requires an arbitrarycut-off point Ignores cash flows
beyond the cut-off date Biased against long-term
projects, such as researchand development, andnew projects
8/10/2019 Topic3_CapitalBudgeting
23/52
Average Accounting Return
23
Many different definitions for average accountingreturn (AAR).
In your textbook: Average book value depends on how the asset isdepreciated.
Requires a target cut-off rateDecision rule: Accept the project if the AAR is greaterthan target rate.
8/10/2019 Topic3_CapitalBudgeting
24/52
Example: Average Accounting Return
24
Sample project data:
Average book value = $72 000Required average accounting return = 25%
Average net income:($13 620 + 3300 + 29 100) / 3 = $15 340AAR = $15 340 / 72 000 = 0.213 = 21.3%Do we accept or reject the project?
Year Cash Flow Net Income
0 -165,000
1 63,120 13,620
2 70,800 3,300
3 91,080 29,100
8/10/2019 Topic3_CapitalBudgeting
25/52
Analysing AAR
25
Advantages Easy to calculate Needed information
usually available
Disadvantages Not a true rate of
return Time value of money
ignored Uses an arbitrary
benchmark cut-off rate Based on accounting
net income and bookvalues, not cash flowsand market values
8/10/2019 Topic3_CapitalBudgeting
26/52
Internal Rate of Return
26
Most important alternative to NPVWidely used in practiceIntuitively appealingBased entirely on the estimated cash flowsIndependent of interest rates
8/10/2019 Topic3_CapitalBudgeting
27/52
Internal Rate of Return
27
Internal Rate of Return (IRR): the discount rate thatmakes the NPV equal to 0.
0 1=
Decision rule: Accept the project if the IRR is greaterthan the required return. Finding the IRR often involves trial and error.
8/10/2019 Topic3_CapitalBudgeting
28/52
Example: IRR
28
Sample project data:
To solve for the IRR:
0 165,00063,1201
70,8001
91,0801
Using trial and error, IRR = 16.132%
Year Cash Flow
0 -165,000
1 63,120
2 70,800
3 91,080
8/10/2019 Topic3_CapitalBudgeting
29/52
Example: IRR
29
The NPV of the project at various discount rates:
To calculate the NPV at a discount rate of 4%: 165,00063,1201.04 70,8001.04 91,0801.04 $42,121 We can plot the NPV profile (next slide).
Discount rate NPV
0% $60,000
4% $42,121
8% $26,446
12% $12,627
16% $380.83
20% -$10,525
8/10/2019 Topic3_CapitalBudgeting
30/52
Example: IRR
30
-20,000-10,000
0
10,000
20,000
30,000
40,000
50,000
60,000
70,000
0 0.02 0.04 0.06 0.08 0.1 0.12 0.14 0.16 0.18 0.2 0.22
Discount Rate
N P V
8/10/2019 Topic3_CapitalBudgeting
31/52
NPV and IRR
31
The NPV and IRR rules always lead to identical decisionsif:1. Cash flows are conventional
Conventional cash flows: First cash flow (the initial investment) isnegative and all the rest are positive
2. The project is independentThe decision to accept or reject this project does not affect thedecision to accept or reject any other.
Whenever there is a conflict between NPV and anotherdecision rule, you should always use NPV.
8/10/2019 Topic3_CapitalBudgeting
32/52
Non-conventional cash flows: Multiple IRRs
32
It is possible for a project to have more than one IRRvalue.This happens in situations when there is a large cashoutflow at the beginning of the project and then
another large outflow at some later time.This makes it difficult to use the IRR methodology as itis not possible to know which IRR result should beused.
8/10/2019 Topic3_CapitalBudgeting
33/52
Example: Multiple IRRs
33
0 1 2 IRR (%)Project X -$100 $230 -$132 ??
General equation:
0 100+ + At 10%:
1002301.10
1321.10 0
At 20%:
1002301.201321.20 0
8/10/2019 Topic3_CapitalBudgeting
34/52
Example: Multiple IRRs
34
-2500
-1500
-500
500
0 5 10 15 20 25 30 35
Discount rate (%)
N e
t P r e s e n
t V
a l u e
( $ )
8/10/2019 Topic3_CapitalBudgeting
35/52
Example: Mutually Exclusive Investments
35
Consider a Projects A and B with the following cash flows:
Year Project A Project B
0 -1,000 -1,500
1 400 599
2 500 400
3 150 600
4 200 350
5 400 400
8/10/2019 Topic3_CapitalBudgeting
36/52
Example: Mutually Exclusive Investments
36
The NPV of the project at various discount rates:
Discount rate Project A NPV Project B NPV
0% $650.00 $849.00
4% $479.97 $607.13
8% $337.35 $403.3612% $216.58 $230.17
16% $113.41 $81.79
20% $24.56 -$46.29
24% -$52.53 -$157.61
8/10/2019 Topic3_CapitalBudgeting
37/52
Mutually Exclusive Investments
37
-400
-200
0
200
400
600
800
1000
0% 5% 10% 15% 20% 25%
N P V
( $ )
Discount rate
Project A Project B
IRR Project B(18.49%)
Cross-over pointNPVA = NPV B
(13.14%)
IRR Project A(21.22%)
8/10/2019 Topic3_CapitalBudgeting
38/52
Analysing the IRR
38
Advantages Knowing a return is
intuitively appealing It is a simple way to
communicate the value of aproject to someone whodoesnt know all theestimation details
If the IRR is high enough,
you may not need toestimate a required return,which is often a difficulttask
Disadvantages Can produce multiple
answers Cannot rank mutually
exclusive projects
8/10/2019 Topic3_CapitalBudgeting
39/52
Modified IRR
39
Controls for some problems with IRRThree methods:1.Discounting approach = Discount future outflows to present
and add to CF 02. Reinvestment approach = Compound all CFs except the
first one forward to end3. Combination approach = Discount outflows to present;
compound inflows to endMIRR will be unique number for each method
Discount (finance) /compound (reinvestment) rateexternally supplied
8/10/2019 Topic3_CapitalBudgeting
40/52
Example: Discounting approach
40
Discounting approach: Discount all negative cash flows to
the present and add to the initial cost.Solving for the MIRR:
Time 0: -$60 + (-$100/1.20 2) = -129.44Time 1: +$155Time 2: $0
MIRR is 19.75%
0 1 2Project X -$60 $155 -$100
Adjusted cash flows -$129.44 $155 0
8/10/2019 Topic3_CapitalBudgeting
41/52
Example: Reinvestment approach
41
Reinvestment approach: Compound all CFs except the
first one to the end of the projects life and calculate IRR.Solving for the MIRR:
Time 0: -$60Time 1: $0Time 2: -$100 + ($155 1.20) = $86
MIRR is 19.72%
0 1 2Project X -$60 $155 -$100
Adjusted cash flows -$60 0 $86
8/10/2019 Topic3_CapitalBudgeting
42/52
Example: Combination approach
42
Combination approach: Negative cash flows discounted
back to the present, positive cash flows compounded tothe end of the project.Solving for the MIRR:
Time 0: -$60 + (-$100/1.20 2) = -$129.44Time 1: $0Time 2: $155 1.20 = $186
MIRR is 19.87%
0 1 2Project X -$60 $155 -$100
Adjusted cash flows -$129.44 0 $186
8/10/2019 Topic3_CapitalBudgeting
43/52
MIRR vs. IRR
43
Different opinions about MIRR and IRR.MIRR avoids the multiple IRR problem.Managers like rate of return comparisons, and MIRR isbetter for this than IRR.
Problem with MIRR: different ways to calculate with noevidence of the best method.Interpreting a MIRR is not obvious.
8/10/2019 Topic3_CapitalBudgeting
44/52
Profitability Index
44
Profitability index: The present value of an investmentsfuture cash flows divided by its initial cost.
Measures the value created per dollar invested (bang for thebuck). E.g. A profitability index of 1.1 implies that for every $1 ofinvestment, we create an additional $0.10 in value.
This measure can be very useful in situations where wehave limited capital.
Decision Rule (Independent projects): Accept the projectif PI > 1.0.
8/10/2019 Topic3_CapitalBudgeting
45/52
Example: Profitability index
45
What is the profitability index for the following set of cashflows if the relevant discount rate is 10%? Should we acceptthe project?
13,5001.10 8,5001.105,5001.10$20,000 1.171We should accept the project because PI > 1.0.
Year Cash Flow
0 -$20,000
1 13,5002 8,500
3 5,500
8/10/2019 Topic3_CapitalBudgeting
46/52
Example: Profitability index
46
What if the discount rate is 22%?
13,5001.228,5001.225,5001.22$20,000
0.990
We should reject the project because PI < 1.0.
8/10/2019 Topic3_CapitalBudgeting
47/52
Example: Profitability index
47
Consider two mutually exclusive projects with thefollowing cash flows:
The required return is 11%.
According to the PI rule, which project will you choose?According to the NPV rule, which project will youchoose?
Year Project A Project B
0 -$45,000 -$20,000
1 17,000 6,000
2 20,000 13,000
3 24,000 9,000
8/10/2019 Topic3_CapitalBudgeting
48/52
Example: Profitability index
48
According to the PI rule, which project will you choose?
According to the PI rule, we choose Project B.
( )17,0001.11 20,0001.11 24,0001.1145,000 1.091
( )6,0001.1113,0001.11 9,0001.1120,000 1.127
8/10/2019 Topic3_CapitalBudgeting
49/52
Example: Profitability index
49
According to the NPV rule, which project will you choose?
According to the NPV rule, we choose Project A.
The profitability index does not consider the scale of theproject. Project A is approximately double the size of projectB.
17,0001.1120,0001.11
24,0001.1145,000 $4,096.36
6,0001.1113,0001.11 9,0001.1120,000 $2,537.22
8/10/2019 Topic3_CapitalBudgeting
50/52
Analysing the Profitability index
50
Advantages
Closely related toNPV, generally
leading to identicaldecisions Easy to understand
and communicate
May be useful whenavailable investmentfunds are limited
Disadvantages
May lead to incorrectdecisions in
comparisons ofmutually exclusiveinvestment
8/10/2019 Topic3_CapitalBudgeting
51/52
Project Evaluation Methods
51
Method Percentage Accounting Rate of Return 20.29Profitability Index 11.87Internal Rate of Return 75.61Net Present Value 74.93Payback Period 56.74Source: Graham & Harvey (2001)
8/10/2019 Topic3_CapitalBudgeting
52/52
Tutorial QuestionsTextbook (Chapter 8)
Critical Thinking and Concepts Review8.3 8.4 8.5 8.7
Questions and Problems2 4 10 11 12 13 18 21 24 25