Topic3_CapitalBudgeting

Embed Size (px)

Citation preview

  • 8/10/2019 Topic3_CapitalBudgeting

    1/52

    FINS1613: Business FinanceSemester 2, 2014

    Topic: Capital Budgeting I

  • 8/10/2019 Topic3_CapitalBudgeting

    2/52

    Contact Details

    Emma Jincheng Zhang (Weeks 5-7) [email protected] Rm 302Consultation hours: Monday 9-11am

    mailto:[email protected]:[email protected]
  • 8/10/2019 Topic3_CapitalBudgeting

    3/52

    Outline

    1. Introduction to capital budgetinga. Independent and mutually exclusive projects

    2. Investment decision rulesa. Net present value (NPV)

    b. Payback rulec. Average accounting return (AAR)d. Internal rate of return (IRR)e. Modified internal rate of return (MIRR)f. Profitability index (PI)

    3

  • 8/10/2019 Topic3_CapitalBudgeting

    4/52

    1. Introduction to capitalbudgeting

    4

  • 8/10/2019 Topic3_CapitalBudgeting

    5/52

    Role of the financial manager

    5

    It is the role of the financial manager to make someimportant decisionsCapital budgeting (investment decision)

    What long-term investments should the firm take on?

    Capital structure (financing decision)Where will we get the long-term financing to pay for the investment?Working capital management

    How will we manage the everyday financial activities of the firm?

  • 8/10/2019 Topic3_CapitalBudgeting

    6/52

    Capital budgeting decision criteria

    6

    We need to ask ourselves the following questions whenevaluating decision criteria:Does the decision rule adjust for the time value of money?Does the decision rule adjust for risk?

    Does the decision rule provide information on whether we arecreating value for the firm?

  • 8/10/2019 Topic3_CapitalBudgeting

    7/52

    Independent projects

    7

    What are independent projects?Independent Projects are investments that have no impact oneach others cash flows. This means that the company decides to accept or reject eachproject and that decision will have no impact on whether

    another project is accepted or rejected.The firm could accept one or more projects or it could rejectthem all.

  • 8/10/2019 Topic3_CapitalBudgeting

    8/52

    Mutually exclusive projects

    8

    What are mutually exclusive projects?Mutually exclusive projects are investments in which acceptingone project requires reject of all other options.This may be due to financial constraints or limitations toavailable assets.Projects need to be ranked in order to determine which toundertake.

  • 8/10/2019 Topic3_CapitalBudgeting

    9/52

    Mutually exclusive projects

    9

    An example of two mutually exclusive projects is:A company has a piece of land and it is debating either buildingan office block on the land or building a warehouse.It cannot use the same piece of land for two different things atthe same time.These are mutually exclusive projects.

  • 8/10/2019 Topic3_CapitalBudgeting

    10/52

    Mutually exclusive projects

    10

    A second example of two mutually exclusive projects is:A company has a fixed budget of $20,000 for investment thisyear. The firm is considering two projects. The first will take$15,000 to establish and the second project will require$18,000.

    Clearly, only one project can be carried out this year so theyare mutually exclusive.

  • 8/10/2019 Topic3_CapitalBudgeting

    11/52

    2. Investment Decision Rules

    11

  • 8/10/2019 Topic3_CapitalBudgeting

    12/52

    Net Present Value

    12

    Net present value (NPV): The difference between aninvestments market value and its initial investment.Steps in calculating the NPV:

    Step 1: Estimate the expected future cash

    flows.Step 2: Estimate the required return for projectsof this risk level.

    Step 3: Find the present value of the cash flows

    and subtract the initial investment toarrive at the net present value.NPV Rule: An investment should be accepted if the netpresent value is positive and rejected if it is negative

  • 8/10/2019 Topic3_CapitalBudgeting

    13/52

    Net Present Value

    13

    1 =

    C t: Cash flows from the project. These cash flows areusually inflows (positive).C0: Initial cost of the project. This is usually an outflow

    (negative)r: the discount rate for the project

  • 8/10/2019 Topic3_CapitalBudgeting

    14/52

    Net Present Value

    14

    Cash inflows:Receipts from sale of goods and servicesReceipts from sale of physical assets

    Cash outflows:

    Expenditure on materials, labour, and indirect expenses formanufacturingSelling and administrativeInventory and taxes

  • 8/10/2019 Topic3_CapitalBudgeting

    15/52

    Net Present Value Decision Rule

    15

    If NPV is positive, accept the project NPV > 0 means:

    project is expected to add value to the firmproject will increase the wealth of the owners

    NPV is a direct measure of how well this project willachieve the goal of increasing shareholder wealth.

    NPV represents the net gain in shareholder wealth

  • 8/10/2019 Topic3_CapitalBudgeting

    16/52

    Example: Net Present Value

    16

    You are looking at a new project and have estimated thefollowing cash flows and net income:

    The average book value is $72,000Your required return for assets of this risk is 12%

    We will use this project for all investment decision rules.

    Year Cash Flow Net Income

    0 -165,000

    1 63,120 13,6202 70,800 3,300

    3 91,080 29,100

  • 8/10/2019 Topic3_CapitalBudgeting

    17/52

    Example: Net Present Value

    17

    1

    =

    63,1201.12 70,8001.12 91,0801.12165,000 = $12,627.41

    t = 0 t = 1 t = 2

    $63,120

    t = 3

    $70,800 $91,080-$165,000

  • 8/10/2019 Topic3_CapitalBudgeting

    18/52

    Analysing the NPV rule

    18

    Meets all desirable criteriaConsiders all cash flowsConsiders time value of moneyAdjusts for risk

    Can rank mutually exclusive projectsNPV method is consistent with the companys objectiveof maximising shareholders wealth. Dominant method; always prevails

  • 8/10/2019 Topic3_CapitalBudgeting

    19/52

    Payback rule

    19

    Payback Period: The amount of time required for aninvestment to generate net cash flows sufficient torecover its initial cost (investment).Steps in calculating the payback period:

    Step 1: Estimate the expected future cashflows.Step 2: Subtract the future cash flows from the initialcost until initial investment is recovered.

    Payback Rule: Accept if the payback period is less thansome predetermined limit.

  • 8/10/2019 Topic3_CapitalBudgeting

    20/52

    Example: Payback rule

    20

    2 2,, 2.34

    Do we accept or reject the project?Depends on the companys predetermined limit.

    Year Cash Flow Cumulative Cash Flow0 -165,000 -165,000

    1 63,120 -101,880

    2 70,800 -31,080

    3 91,080 60,000

  • 8/10/2019 Topic3_CapitalBudgeting

    21/52

    Example: Payback rule

    21

    Your companys payback period is 2 years. According tothe payback rule, which of the following projects will youaccept?

    Year A B C D E

    0 -$100 -$200 -$200 -$200 -$50

    1 30 40 40 100 100

    2 40 20 20 100 -50,000,000

    3 50 10 10 -200

    4 60 130 200Payback period 2.6 Never 4 2 or 4 0.5

  • 8/10/2019 Topic3_CapitalBudgeting

    22/52

    Analysing the payback rule

    22

    Advantages

    Easy to understand Adjusts for uncertainty of

    later cash flows Biased towards liquidity

    Disadvantages

    Ignores the time value ofmoney

    Requires an arbitrarycut-off point Ignores cash flows

    beyond the cut-off date Biased against long-term

    projects, such as researchand development, andnew projects

  • 8/10/2019 Topic3_CapitalBudgeting

    23/52

    Average Accounting Return

    23

    Many different definitions for average accountingreturn (AAR).

    In your textbook: Average book value depends on how the asset isdepreciated.

    Requires a target cut-off rateDecision rule: Accept the project if the AAR is greaterthan target rate.

  • 8/10/2019 Topic3_CapitalBudgeting

    24/52

    Example: Average Accounting Return

    24

    Sample project data:

    Average book value = $72 000Required average accounting return = 25%

    Average net income:($13 620 + 3300 + 29 100) / 3 = $15 340AAR = $15 340 / 72 000 = 0.213 = 21.3%Do we accept or reject the project?

    Year Cash Flow Net Income

    0 -165,000

    1 63,120 13,620

    2 70,800 3,300

    3 91,080 29,100

  • 8/10/2019 Topic3_CapitalBudgeting

    25/52

    Analysing AAR

    25

    Advantages Easy to calculate Needed information

    usually available

    Disadvantages Not a true rate of

    return Time value of money

    ignored Uses an arbitrary

    benchmark cut-off rate Based on accounting

    net income and bookvalues, not cash flowsand market values

  • 8/10/2019 Topic3_CapitalBudgeting

    26/52

    Internal Rate of Return

    26

    Most important alternative to NPVWidely used in practiceIntuitively appealingBased entirely on the estimated cash flowsIndependent of interest rates

  • 8/10/2019 Topic3_CapitalBudgeting

    27/52

    Internal Rate of Return

    27

    Internal Rate of Return (IRR): the discount rate thatmakes the NPV equal to 0.

    0 1=

    Decision rule: Accept the project if the IRR is greaterthan the required return. Finding the IRR often involves trial and error.

  • 8/10/2019 Topic3_CapitalBudgeting

    28/52

    Example: IRR

    28

    Sample project data:

    To solve for the IRR:

    0 165,00063,1201

    70,8001

    91,0801

    Using trial and error, IRR = 16.132%

    Year Cash Flow

    0 -165,000

    1 63,120

    2 70,800

    3 91,080

  • 8/10/2019 Topic3_CapitalBudgeting

    29/52

    Example: IRR

    29

    The NPV of the project at various discount rates:

    To calculate the NPV at a discount rate of 4%: 165,00063,1201.04 70,8001.04 91,0801.04 $42,121 We can plot the NPV profile (next slide).

    Discount rate NPV

    0% $60,000

    4% $42,121

    8% $26,446

    12% $12,627

    16% $380.83

    20% -$10,525

  • 8/10/2019 Topic3_CapitalBudgeting

    30/52

    Example: IRR

    30

    -20,000-10,000

    0

    10,000

    20,000

    30,000

    40,000

    50,000

    60,000

    70,000

    0 0.02 0.04 0.06 0.08 0.1 0.12 0.14 0.16 0.18 0.2 0.22

    Discount Rate

    N P V

  • 8/10/2019 Topic3_CapitalBudgeting

    31/52

    NPV and IRR

    31

    The NPV and IRR rules always lead to identical decisionsif:1. Cash flows are conventional

    Conventional cash flows: First cash flow (the initial investment) isnegative and all the rest are positive

    2. The project is independentThe decision to accept or reject this project does not affect thedecision to accept or reject any other.

    Whenever there is a conflict between NPV and anotherdecision rule, you should always use NPV.

  • 8/10/2019 Topic3_CapitalBudgeting

    32/52

    Non-conventional cash flows: Multiple IRRs

    32

    It is possible for a project to have more than one IRRvalue.This happens in situations when there is a large cashoutflow at the beginning of the project and then

    another large outflow at some later time.This makes it difficult to use the IRR methodology as itis not possible to know which IRR result should beused.

  • 8/10/2019 Topic3_CapitalBudgeting

    33/52

    Example: Multiple IRRs

    33

    0 1 2 IRR (%)Project X -$100 $230 -$132 ??

    General equation:

    0 100+ + At 10%:

    1002301.10

    1321.10 0

    At 20%:

    1002301.201321.20 0

  • 8/10/2019 Topic3_CapitalBudgeting

    34/52

    Example: Multiple IRRs

    34

    -2500

    -1500

    -500

    500

    0 5 10 15 20 25 30 35

    Discount rate (%)

    N e

    t P r e s e n

    t V

    a l u e

    ( $ )

  • 8/10/2019 Topic3_CapitalBudgeting

    35/52

    Example: Mutually Exclusive Investments

    35

    Consider a Projects A and B with the following cash flows:

    Year Project A Project B

    0 -1,000 -1,500

    1 400 599

    2 500 400

    3 150 600

    4 200 350

    5 400 400

  • 8/10/2019 Topic3_CapitalBudgeting

    36/52

    Example: Mutually Exclusive Investments

    36

    The NPV of the project at various discount rates:

    Discount rate Project A NPV Project B NPV

    0% $650.00 $849.00

    4% $479.97 $607.13

    8% $337.35 $403.3612% $216.58 $230.17

    16% $113.41 $81.79

    20% $24.56 -$46.29

    24% -$52.53 -$157.61

  • 8/10/2019 Topic3_CapitalBudgeting

    37/52

    Mutually Exclusive Investments

    37

    -400

    -200

    0

    200

    400

    600

    800

    1000

    0% 5% 10% 15% 20% 25%

    N P V

    ( $ )

    Discount rate

    Project A Project B

    IRR Project B(18.49%)

    Cross-over pointNPVA = NPV B

    (13.14%)

    IRR Project A(21.22%)

  • 8/10/2019 Topic3_CapitalBudgeting

    38/52

    Analysing the IRR

    38

    Advantages Knowing a return is

    intuitively appealing It is a simple way to

    communicate the value of aproject to someone whodoesnt know all theestimation details

    If the IRR is high enough,

    you may not need toestimate a required return,which is often a difficulttask

    Disadvantages Can produce multiple

    answers Cannot rank mutually

    exclusive projects

  • 8/10/2019 Topic3_CapitalBudgeting

    39/52

    Modified IRR

    39

    Controls for some problems with IRRThree methods:1.Discounting approach = Discount future outflows to present

    and add to CF 02. Reinvestment approach = Compound all CFs except the

    first one forward to end3. Combination approach = Discount outflows to present;

    compound inflows to endMIRR will be unique number for each method

    Discount (finance) /compound (reinvestment) rateexternally supplied

  • 8/10/2019 Topic3_CapitalBudgeting

    40/52

    Example: Discounting approach

    40

    Discounting approach: Discount all negative cash flows to

    the present and add to the initial cost.Solving for the MIRR:

    Time 0: -$60 + (-$100/1.20 2) = -129.44Time 1: +$155Time 2: $0

    MIRR is 19.75%

    0 1 2Project X -$60 $155 -$100

    Adjusted cash flows -$129.44 $155 0

  • 8/10/2019 Topic3_CapitalBudgeting

    41/52

    Example: Reinvestment approach

    41

    Reinvestment approach: Compound all CFs except the

    first one to the end of the projects life and calculate IRR.Solving for the MIRR:

    Time 0: -$60Time 1: $0Time 2: -$100 + ($155 1.20) = $86

    MIRR is 19.72%

    0 1 2Project X -$60 $155 -$100

    Adjusted cash flows -$60 0 $86

  • 8/10/2019 Topic3_CapitalBudgeting

    42/52

    Example: Combination approach

    42

    Combination approach: Negative cash flows discounted

    back to the present, positive cash flows compounded tothe end of the project.Solving for the MIRR:

    Time 0: -$60 + (-$100/1.20 2) = -$129.44Time 1: $0Time 2: $155 1.20 = $186

    MIRR is 19.87%

    0 1 2Project X -$60 $155 -$100

    Adjusted cash flows -$129.44 0 $186

  • 8/10/2019 Topic3_CapitalBudgeting

    43/52

    MIRR vs. IRR

    43

    Different opinions about MIRR and IRR.MIRR avoids the multiple IRR problem.Managers like rate of return comparisons, and MIRR isbetter for this than IRR.

    Problem with MIRR: different ways to calculate with noevidence of the best method.Interpreting a MIRR is not obvious.

  • 8/10/2019 Topic3_CapitalBudgeting

    44/52

    Profitability Index

    44

    Profitability index: The present value of an investmentsfuture cash flows divided by its initial cost.

    Measures the value created per dollar invested (bang for thebuck). E.g. A profitability index of 1.1 implies that for every $1 ofinvestment, we create an additional $0.10 in value.

    This measure can be very useful in situations where wehave limited capital.

    Decision Rule (Independent projects): Accept the projectif PI > 1.0.

  • 8/10/2019 Topic3_CapitalBudgeting

    45/52

    Example: Profitability index

    45

    What is the profitability index for the following set of cashflows if the relevant discount rate is 10%? Should we acceptthe project?

    13,5001.10 8,5001.105,5001.10$20,000 1.171We should accept the project because PI > 1.0.

    Year Cash Flow

    0 -$20,000

    1 13,5002 8,500

    3 5,500

  • 8/10/2019 Topic3_CapitalBudgeting

    46/52

    Example: Profitability index

    46

    What if the discount rate is 22%?

    13,5001.228,5001.225,5001.22$20,000

    0.990

    We should reject the project because PI < 1.0.

  • 8/10/2019 Topic3_CapitalBudgeting

    47/52

    Example: Profitability index

    47

    Consider two mutually exclusive projects with thefollowing cash flows:

    The required return is 11%.

    According to the PI rule, which project will you choose?According to the NPV rule, which project will youchoose?

    Year Project A Project B

    0 -$45,000 -$20,000

    1 17,000 6,000

    2 20,000 13,000

    3 24,000 9,000

  • 8/10/2019 Topic3_CapitalBudgeting

    48/52

    Example: Profitability index

    48

    According to the PI rule, which project will you choose?

    According to the PI rule, we choose Project B.

    ( )17,0001.11 20,0001.11 24,0001.1145,000 1.091

    ( )6,0001.1113,0001.11 9,0001.1120,000 1.127

  • 8/10/2019 Topic3_CapitalBudgeting

    49/52

    Example: Profitability index

    49

    According to the NPV rule, which project will you choose?

    According to the NPV rule, we choose Project A.

    The profitability index does not consider the scale of theproject. Project A is approximately double the size of projectB.

    17,0001.1120,0001.11

    24,0001.1145,000 $4,096.36

    6,0001.1113,0001.11 9,0001.1120,000 $2,537.22

  • 8/10/2019 Topic3_CapitalBudgeting

    50/52

    Analysing the Profitability index

    50

    Advantages

    Closely related toNPV, generally

    leading to identicaldecisions Easy to understand

    and communicate

    May be useful whenavailable investmentfunds are limited

    Disadvantages

    May lead to incorrectdecisions in

    comparisons ofmutually exclusiveinvestment

  • 8/10/2019 Topic3_CapitalBudgeting

    51/52

    Project Evaluation Methods

    51

    Method Percentage Accounting Rate of Return 20.29Profitability Index 11.87Internal Rate of Return 75.61Net Present Value 74.93Payback Period 56.74Source: Graham & Harvey (2001)

  • 8/10/2019 Topic3_CapitalBudgeting

    52/52

    Tutorial QuestionsTextbook (Chapter 8)

    Critical Thinking and Concepts Review8.3 8.4 8.5 8.7

    Questions and Problems2 4 10 11 12 13 18 21 24 25