T.O.E.C Since 1960 Technical Office for Engineering and Contracting Engs. ABOUKHATER & AKHRASS

TOEC Profile 2010

Embed Size (px)

Citation preview

Page 1: TOEC Profile 2010

T.O.E.C

Since 1960 Technical Office for Engineering and Contracting

Engs. ABOUKHATER & AKHRASS

Page 2: TOEC Profile 2010

Since 1960

Your Construction Partner

Since 1960

T.O.E.C is one of the leading engineering, contracting, construction, industrial and trading companies in Syria, Algeria and Saudi Arabia. The company has been established in 1960 by Eng. Medhat Aboukhater Eng. Haitham Akhrass, Eng. Sadek Akhrass and Mr. Hikmat Aboukhater. T.O.E.C core activity is the construction of large scale civil, mechanical, electrical and instrumentation project in different aspects of the construction industries from luxury buildings and villas to high ways and rail ways including oil and gas projects, power plants, revamping of industrial projects, harbors and irrigation canals.

Our yearly turnover in this sector is around 100,000,000 U.S $. We adhere to our clients' requirements in terms of quality and time by depending on our highly capable staff who has extensive experience and expertise to handle and execute all aspects of construction . T.O.E.C always care to train its staff to ensure that they are skilled enough to handle their job efficiently and cost effectively . T.O.E.C Staff long term of management guarantees the customer with high quality, low cost, prompt and professional procurement services.

Page 3: TOEC Profile 2010

Since 1960

Your Construction Partner

Page 4: TOEC Profile 2010

Since 1960

Your Construction Partner

Some of T.O.E.C Clients

Page 5: TOEC Profile 2010

Since 1960

Your Construction Partner

Head Office at HOMS: Tel: + 963 31 275 52 52 Fax: + 963 31 275 00 46 P.O. Box: 392, Damascus highway, Behind 8 Azar Forest. Homs – Syria Web: www.toec-int.com E-Mail:[email protected] Persons in Contact: BSC Civil Eng. EMBA Managing Partner Eng. Mamdouh ABOUKHATER [email protected] Mobile:+963 933 223 228

Damascus Office Tel: + 963 11 333 98 76 Fax: + 963 11 333 82 06 P.O. Box: 184, Abou-Romanneh District, Al-Nijmah Square. Damascus - Syria E-Mail Address: [email protected] Person in Contact: Commercial Director: Eng. Aref AKHRASS [email protected] Mobile: +963 944 30 88 44

Algeria Branch: S.P.A T.O.E.C ALGERIE Tel: + 213 21 48 40 15/18 Fax: + 213 21 48 34 00 Address: Nº 04-Appt. Nº 08G-VAL D'Hyrda, Chabani-Lotissement. Algiers - Algeria E-Mail Address: [email protected] Person in Contact: General Manager: Eng. Wael Al Hussan. [email protected] Mobile : +213 550 111115

Saudi Arabia Branch: CEMCCO Civil and Elector Mechanical Construction Co. Tel: +966 2 284 84 41/ 0 Fax: +966 2 284 84 42 P.O.BOX: 122615 Jeddah 21322 Al Tahlia Str., Hasan Al Tijari Center Building. Jeddah – Saudi Arabia E-Mail Address: [email protected] Person in Contact: General Manager: Eng. Salem AKHRASS [email protected] Mobile:+966 505 624 655

Page 6: TOEC Profile 2010

Since 1960

Your Construction Partner

HSE Health, Safety and Environment

Since the 80s T.O.E.C paid attention to the safety of its personnel and applied " Safety First" as major in the detailed daily construction activity. Our clients issued many safety awards which we are appreciate to obtain

T.O.E.C also got the international OHSAS 18001

Page 7: TOEC Profile 2010

Since 1960

Your Construction Partner

QA/ QC Quality Assurance/ Quality Control

T.O.E.C. gives the QA/ QC the first priority in all its projects. T.O.E.C. follows all the international standards and codes in executing each project .

T.O.E.C. has successfully obtained ISO 9001:2008

T.O.E.C. has successfully obtained ISO 14001:2004

Page 8: TOEC Profile 2010

Since 1960

Your Construction Partner

Main Equipments List T.O.E.C. policy is to own the main construction equipment, and ready always to rely on trusted rental companies when it

is needed in the peak time. T.O.E.C equipments are always updated with new ones and are varied to cover most construction needs such as cranes, side booms , bulldozers, concrete pumps and trucks…..etc T.O.E.C also use German PERI form work system the world Leader in this Job, which guarantee the best quality of concrete work to be achieved in our projects.

Bulldozer CAT 6

Excavator CAT- Poclain 19

Pay loader CAT 18

Pay loader small size Case- Bobcat 22

Dump truck Mercedes 16

Roller 13 Plate compactor 12

Page 9: TOEC Profile 2010

Since 1960

Your Construction Partner

Side boom (pipe layer) Cat 9

Fork Lift Hyster-Cat 10

Air Compressor Atlas Copco 11

Generating Set CAT-SCANIA 41

Trencher Parson 3

Concrete truck mixer Stetter on Mercedes 19

Concrete pump Schwing on Mercedes 7

Stationary concrete pump Schwing 1

Con. Batching Plant with silos 9

Cement silo truck 7

Page 10: TOEC Profile 2010

Since 1960

Your Construction Partner

Tower cranes Potain 6

Form work Peri

Trailer Flat bed-Loader 10

Truck mounted crane Grove-Libher 11

Piles breaker 1

Pipes bending machine 2

Twin Arc CAT 3

Welding machine 58

Pick-up Toyota-Hyundai 30

Truck Tractor MAN-Mercedes 7

Page 11: TOEC Profile 2010

Since 1960

Your Construction Partner

T.O.E.C Projects In Syria, Saudi Arabia And Algeria

Throughout the50 years of operation T.O.E.C has successfully executed projects in different areas of Syria, Saudi Arabia and Algeria whether it is Power Plants, Oil and Gas projects, Commercial and residential buildings, Water Marin, Irrigation, Infrastructure, Highway and Railway or Industrial projects, all with international specifications and technical requirements. We recognize the need for strong diverse teams offering construction industry specific expertise to each area of operations.

Page 12: TOEC Profile 2010

Since 1960

Your Construction Partner

Oil & Gas Projects Since T.O.E.C was established, many Oil & Gas projects have been executed including Refineries rehabilitation, Gas stations, pipelines, also this kind of works can be found in almost all projects such as power plants, factories, with all related auxiliaries as main contractor in some projects, and sub-contractor for others.

No Project Owner Main Contractor Location Year 1 Uplifting capacity of KARATCHOUK-

TARTOUS P/L (18” ~ 24“) from 8.5 ~ 14.5 million m3/y.

SCOT, Syrian Company for Oil Transportation T.O.E.C. KARATCHOUK-

TARTOUS 1974-1975

2 Survey operation (linalog) of HOMS- BANIAS P/L.

SPC, Syrian Petroleum Company T.O.E.C. HOMS- BANIAS 1986

3 Replacing sections of 30” P/L between PALMYRA and Iraqi Border. (mechanical works)

SPC, Syrian Petroleum Company T.O.E.C. PALMYRA- IRAQI

Border. 1986

4 OMAR field- TESHREEN Power Station P/L Project (260 KM). (mechanical works)

AFPC, Al-Furat Petroleum Company

Military Housing Establishment

OMAR field- TESHREEN Plant 1991-1992

5 Providing Facilities, Maintenance and Repair Services for the Oil Fields (Civil and Electromechanical works).

AFPC, Al-Furat Petroleum Company T.O.E.C. DEIR EZ-ZOR 1991-1993

6 PALMYRA gas gathering and compression station (NAJEEB) including 50 KM 12” P/L and 18 KM 5” Flow-lines.

SPC, Syrian Petroleum Company SPC NAJEEB,

PALMYRA 1998-2000

7 Implementation of Crude Distillation Unit 101. (during shutdown) BANIAS Refinery Co. Technoexport, Czech

Republic BANIAS 2003

8 Repairing of Atmospheric Unit Column 101 in BANIAS Refinery. BANIAS Refinery Co. Technoexport, Czech

Republic BANIAS 2003

9 Revamping of Vacuum Distillation unit 102 BANIAS Refinery During Shut Down.

BANIAS Refinery Co. Technoexport, Czech Republic BANIAS 2007

10 Storage tanks and feeding line for plane fuel ALGIERS Air Plant ALGERIA 2007

Page 13: TOEC Profile 2010

Since 1960

Your Construction Partner

Power Plants Projects

No Project Owner Main Contractor Location Year

1 QATTINE Power Plant. PEE, Public Establishment for

Electricity T.O.E.C. HOMS 1961

2 Conversion of MEHARDEH Power Station from fuel to gas.

PEE, Public Establishment for

Electricity FORNEY Intl. USA HAMA 1992-

1993

3

JANDAR C/C Power Plant (660 MW)

PEE, Public

Establishment for Electricity

Mitsubishi Heavy

Industries Co. Ltd., JAPAN

JANDAR,

1993-1996

4 AL-ZARA Thermal Power Plant Project (660MW)

PEEGT,(Public Establishment of

Electricity Generation and Transmission)

Mitsubishi Heavy Industries Co. Ltd.,

JAPAN AL-ZARA, 1997-

2001

5 Rehabilitation and Lining the stacks of3rd&4thUnits. BANIAS Power Plant T.O.E.C. BANIAS 2002

6 Checking the Stacks of 1st & 2nd Units at BANIAS Power Plant. BANIAS Power Plant T.O.E.C. BANIAS 2003

7 Aleppo and Baramkeh Substations PEEGT Areva, France DAMASCUS and ALEPPO

2005-2006

8 Zayzoun Combined Cycle Power Plant PEEGT Koch-Siemens

Germany ZAYZOUN 2005- 2007

9 Banias Gas Turbine Power Plant PEEGT

TOEC &

TurboCare ,Italy BANIAS 2008-

2010

10 YANBU Diesel Power plant MAN DIESEL MAN DIESEL

YANBOU SAUDI

ARABIA 2010

Page 14: TOEC Profile 2010

Since 1960

Your Construction Partner

Commercial And Residential Projects

No Project Owner Main Contractor Location Year

1 Commercial and residential buildings. Miscellaneous Owners T.O.E.C. HOMS Center 1987-

1996 2

154 Units Housing Complex For JANDAR C/C Power Plant

PEE, Public

Establishment for Electricity

Mitsubishi Heavy

Industries Co. Ltd., JAPAN

JANDAR

1993-1996

3 200 Units Housing Complex for AL-ZARA Thermal Power Plant

PEEGT,(Public Establishment of

Electricity Generation and Transmission)

Mitsubishi Heavy Industries Co. Ltd.,

JAPAN AL-ZARA 1997-

2001

4 Al Wadi German Syrian University Al Wadi Company TOEC HOMS 2006- 2009

5 165 Unit Housing Complex with all related facilities in Zayzoun Power plant.

PEEGT Koch-Siemens Germany ZAYZOUN 2005-

2007

6 Homs Fairground Homs Fairground Co. T.O.E.C HOMS 2007-2010

7 Base de vie Project(EPC) Sonatrach T.O.E.C ALGERIA 2007-2010

8 AL Qaser Development Project Residential Complex of Building.

Dar Al Arkan Real Estate Development

Company T.O.E.C RIYADH 2007-

2010

9 MARRIOTT Hotel and complex Trust Real Estate T.O.E.C ALGERIA 2010 -Now

Page 15: TOEC Profile 2010

Since 1960

Your Construction Partner

Industrial Projects

No Project Owner Main Contractor Location Year

1 HOMS Dairy Factory. Ministry of Industry T.O.E.C. HOMS 1960 2 Asbestos Cement Factory. General Establishment

for Chemistry T.O.E.C. DAMASCUS 1965

3 Onion Factory. Ministry of Industry T.O.E.C. HAMA 1969 4 Steel structures for Triple Super

Phosphate Factory (8,500 t). General Establishment

for Chemistry Industrialexport,

Romania HOMS 1976-1978

5 MESKENE Sugar Factory. General Establishment for Sugar T.O.E.C. DEIR EZ-ZOR 1976-

1979 6 ABOUKHATER & AKHRASS

Marble Factory. T.O.E.C. T.O.E.C. HOMS 1978

7 HAMA Tire Plant. Ministry of Industry Technoexport, Czechoslovakia HAMA 1977-

1979 8 Al-Ahliah Vegetable Oil Co. E. S.

A. (AVOCO) Project AVOCO N.V. DE SMET S.A.

Engineers & Contractors BELGIUM

HAMA 1998-2000

9 Supply and Delivery of Ready Mixed Concrete for HAMA New Cement Plant Project.

G.O.C. General Organization for Cement

IDR Construction Co. IRAN HAMA 2003-

2006

10 Construction of an integrated Oil Seeds Crushing Plant. Oil Seeds Crushing Co.

De Smet Engineers&

Contractors S.A YANBU 2008

11 Arab Tank Project. Emirates National Oil Co.LTD

Belleli Energy S.P.A Italy YANBU 2006-

2009

12 JOTUN Tank Farm JOTUN T.O.E.C YANBU 2007-2009

13 Air Craft hangars. Ministry of Defense T.O.E.C. DIFFERENT LOCATIONS

1969-1970

14 Revamping of Hama steel factory Hama steel factory Apollo HOMS 2010-Now

Page 16: TOEC Profile 2010

Since 1960

Your Construction Partner

Highway And Railway Projects

No Project Owner Main Contractor Location Year

1 LATTAKIA- KAMISHLY railway (46 KM).

The General Company of The Railway

Construction T.O.E.C. LATTAKIA-

KAMISHLY 1965-1967

2 ALEPPO- SARAKEB highway (54 KM) under the supervision of SAUTI Overseas Anstalt

Ministry of Transportation T.O.E.C. ALEPPO-

SARAKEB 1964-1967

3 ALEPPO- JISR EL SHOUGHOUR Highway (30 KM) under the supervision of SAUTI Overseas Anstalt

Ministry of Transportation T.O.E.C.

ALEPPO- JISR EL

SHOUGHOUR

1964-1967

4 HOMS- Phosphate Mines (121 KM) Highway under the supervision of SAUTI Overseas Anstalt

Ministry of Transportation T.O.E.C. HOMS-

PALMYRA 1964-1967

5 SARAKEB- ARIHA Highway (20 KM) under the supervision of SAUTI Overseas Anstalt.

Ministry of Transportation T.O.E.C. SARAKEB-

ARIHA 1964-1967

6 BAB ALHAWA- IDLIB Highway (15 KM) under the supervision of SAUTI Overseas Anstalt

Ministry of Transportation T.O.E.C.

BAB ALHAWA-

IDLIB

1964-1967

7 SARAKEB- IDLIB Highway (26 KM) under the supervision of SAUTI Overseas Anstalt

Ministry of Transportation T.O.E.C. SARAKEB-

IDLIB 1964-1967

8 KANTARI- TAL TAMR Highway (112 KM).

Ministry of Transportation T.O.E.C. RAQQA-

HASSAKEH 1980

Page 17: TOEC Profile 2010

Since 1960

Your Construction Partner

Infrastructure Projects

No Project Owner Main Contractor Location Year

1 Project of Renovation and Extension of Sewerage Network.

Water and Sewage Department of

MAKKAH AL-MUKKARAMAH

Region

CEPCO Heavy

Construction, Daughter of

T.O.E.C

MINA,MAKKAH AL-

MUKKARAMAH,KSA

2003-2009

3 King ABDULLAH Economic city Industrial Area 1 A Infrastructure Emmar CEMCCO

(TOEC) RABEGH 2008-Now

4 King ABDULLAH Economic City Resort Cove Package A Infrastructure. Emmar CEMCCO

(TOEC) RABEGH 2008-Now

Water Marine And Irrigation Projects

No Project Owner Main Contractor Location Year

1 Water supply for BANIAS Refinery. BRC.Banias Refinery Company T.O.E.C. BANIAS 1975-

1977 2 Extension of LATTAKIA Harbor. The General

Establishment for The Grand Projects

T.O.E.C. LATTAKIA 1980-1985

3 TISHREEN Dam on Euphrates river /Hydro Power Plant Ministry of Irrigation

General Company for Land

Reclamation MANBEJ 1994-

1997

5 Pumping Station of Orontes River Water to the Irrigation Canal.

Directorate of Orontes Basin T.O.E.C. HOMS 1960

Page 18: TOEC Profile 2010

Since 1960

Your Construction Partner

Special Projects Executed by TOEC

Client: Mitsubishi Heavy Industries LTD.

AL-ZARA Thermal Power Plant Project

(660MW) : Consists Of

3 Steam Turbines 3 Boilers'. 3 Stacks 150M conical shape 3 Cooling Towers 125M height In addition to the other buildings tanks and structure needed for the Plant.

The 3 conical concrete chimney; each of them is 150 m Height, Bottom diameter 12 m , Upper diameter 10 m, TOEC used especial slip form for construct these chimney. TOEC has achieved pouring 2200 m³concrete for each chimney foundation, since the total quantity of the concrete for the project was 110,000 m³ poured within 16 months. More over TOEC completed Steel Structure Erection of 3 Cooling Towers , each of them is 125 m height, Bottom diameter 120m, Weight 3,500 ton. TOEC was full responsible for the complete erection including supervision, drawings revision, Quality Control…etc.

Page 19: TOEC Profile 2010

Since 1960

Your Construction Partner

Client: Siemens-Koch.

Zayzoun Combined Cycle Power Plant extension: T.O.E.C did the civil and electro mechanical works for Zayzoun Combined Cycle.

T.O.E.C has erected steel structure for one cooling tower with 135 m height and 106 m Bottom Diameter. �

Consist of: 3 boilers 1 gas turbine 1 Cooling Tower Other structures and tanks

Page 20: TOEC Profile 2010

Since 1960

Your Construction Partner

Client: Banias Refinery Company

Banias Refinery:

repairing of atmospheric column 101 (during

shutdown) with height of 60M; including replacing all the internals and welding of upper roof with very special welding procedure for MONEL steel material.

TOEC stand working twenty four hours during

shutdown to keep the time schedule.

Page 21: TOEC Profile 2010

Since 1960

Your Construction Partner

Client: Banias Refinery Company

Banias Refinery Rehabilitation: Unit 102 in 2007

revamping of Vacuum distillation During Shutdown including Heaters Revamping with P5 and P9 pipes welding.

T.O.E.C stand working twenty four hours during

shutdown.

Page 22: TOEC Profile 2010

Since 1960

Your Construction Partner

Uplifting capacity of KARATCHOUK- TARTOUS P/L

(Turnkey job)

OMAR- TESHREEN P/L Project

Page 23: TOEC Profile 2010

Since 1960

Your Construction Partner

PALMYRA Gas Gathering Station, NAJEEB

Page 24: TOEC Profile 2010

Since 1960

Your Construction Partner

JANDAR C/C Power Plant (660 MW)

Conversion of MEHARDEH Power Station from Fuel to Gas

Page 25: TOEC Profile 2010

Since 1960

Your Construction Partner

Chimney Slip form Works at AL-ZARA Thermal Power Plant (660 MW)

Power Plants

Page 26: TOEC Profile 2010

Since 1960

Your Construction Partner

Industrial Factories Construction Projects

Steel structures for Triple Super Phosphate Factory

MESKENE Sugar Factory

Page 27: TOEC Profile 2010

Since 1960

Your Construction Partner

Irrigation Projects

Water Supply for BANIAS Refinery

Page 28: TOEC Profile 2010

Since 1960

Your Construction Partner

Page 29: TOEC Profile 2010

Since 1960

Your Construction Partner

TESHREEN Dam/ Hydro Power Plant

The Second Largest Dam On Euphrates River

Page 30: TOEC Profile 2010

Since 1960

Your Construction Partner

Miscellaneous scaffolding system

Page 31: TOEC Profile 2010

Since 1960

Your Construction Partner

Project of Renovation and Extension of Sewerage Network, MINA, MAKKAH AL-MUKKARAMAH, KINGDOM OF SAUDI ARABIA 4.5 Km Tunnel

Page 32: TOEC Profile 2010

Since 1960

Your Construction Partner

Marine Projects

Extension of LATTAKIA Harbor

Page 33: TOEC Profile 2010

Since 1960

Your Construction Partner

ALWADI UNIVERSITY

Page 34: TOEC Profile 2010

Since 1960

Your Construction Partner

Housing complex of JANDAR Housing complex of AL-ZARA

Al Khayam Building - Homs

Zayzoun, complex Housing

Page 35: TOEC Profile 2010

Since 1960

Your Construction Partner

Base de Vie Houd El Hamra – Algeria

Page 36: TOEC Profile 2010

Since 1960

Your Construction Partner

Highways and Roads

Parts II & IV of LATTAKIA- KAMESHLIEH Railway

KANTARI- TAL TAMR Highway (112 KM)

ALEPPO- JISR EL SHOUGHOUR highway

Page 37: TOEC Profile 2010

Since 1960

Your Construction Partner

Page 38: TOEC Profile 2010

Since 1960

Your Construction Partner