Page 1 of 64 Contract No : CHO/2012/DFHD/193 Work Order No: DFHD/2015/042A/001 June 2, 2015 SECTION WORKPACK ITEM DESCRIPTION (TURNAROUND) BOOK 1.0 Introduction Book 1 of 3 1.1 Project Summary & Overall Scope of Work Book 1 of 3 1.2 Organizational Charts Book 1 of 3 1.3 Emergency Response Plan Book 1 of 3 2.0 Turnaround Scope of Work (SOW) Book 1 of 3 2.1 Detailed Turnaround Scope of Work Book 1 of 3 TKP-A Book 1 of 3 WLDP-C Book 1 of 3 2.2 Inspection Test Plan (Inspection Methodology) Book 1 of 3 2.3 Pre-commissioning & Commissioning Procedure Book 1 of 3 3.0 Job Method Statement (Jobcards) with Manhours Book 1 of 3 3.1 Individual Activity Job Method Statement (Jobcards) Book 1 of 3 with Manhours - TKP-A Book 1 of 3 3.2 Individual Activity Job Method Statement (Jobcards) Book 1 of 3 with Manhours - WLDP-C Book 1 of 3 3.3 Manhours Summary List - TKP-A Book 1 of 3 3.4 Manhours Summary List - WLDP-C Book 1 of 3 4.0 Manpower Mobilization Plan (Turnaround) Book 1 of 3 4.1 Manpower Loading & List (Turnaround) - TKP-A Book 1 of 3 4.2 Manpower Loading & List (Turnaround) - WLDP-C Book 1 of 3 5.0 Blind/Spading List Book 1 of 3 5.1 TA Physical Isolation List & Spading Plan (P&ID Mark-up) - TK Book 1 of 3 5.2 TA Physical Isolation List & Spading Plan (P&ID Mark-up) - WL Book 1 of 3 6.0 Material & Consumable List Book 1 of 3 6.1 Overall Material Take-off (TKP-A) Book 1 of 3 6.2 Overall Material Take-off (WLDP-C) Book 1 of 3 6.3 Material Take-off (TA) and Consumable List - TKP-A Book 1 of 3 6.4 Material Take-off (TA) and Consumable List - WLDP-C Book 1 of 3 7.0 Equipment & Tools Loading (Turnaround) Book 1 of 3 7.1 Equipment & Tools Loading Detail List (TKP-A) Book 1 of 3 7.2 Equipment & Tools Loading Detail List (WLDP-C) Book 1 of 3 7.3 Equipment Loading Plan with Layout (TKP-A) Book 1 of 3 7.4 Equipment Loading Plan with Layout (WLDP-C) Book 1 of 3 8.0 Project Schedule Book 2 of 3 8.1 Overall Offshore HUC Schedule (TKP-A & WLDP-C) Book 2 of 3 8.2 Turnaround Schedule (TKP-A & WLDP-C) Book 2 of 3 9.0 Site Specific Procedures (Turnaround) Book 2 of 3 9.1 Project Quality Plan Book 2 of 3 9.2 Lifting & Rigging Procedure Book 2 of 3 9.3 Scaffolding Procedure Book 2 of 3 9.4 Cold Cutting Procedure Book 2 of 3 9.5 Oxy-Acetylene Cutting Procedure Book 2 of 3 9.6 Bolt Tightening Procedure Book 2 of 3 9.7 Piping Fabrication & Installation Procedure Book 2 of 3 9.8 Guideline for Installation of Final Tie-in Golden Joint Book 2 of 3 9.9 Equipment, Instrument and Electrical Installation Procedure Book 2 of 3 PROVISION OF HOOK-UP, COMMISSIONING AND TOPSIDE MAJOR MAINTENANCE SERVICES FOR YEAR 2013 - 2018 PROVISION OF HUC WORK FOR TOPSIDE MODIFICATION FOR SKO PIPELINE REJUVENATION PROJECT - PL381/210

TOC-TA Wpack Rev.1

Embed Size (px)

DESCRIPTION

table of contents for ta wpack

Citation preview

TOC

PROVISION OF HOOK-UP, COMMISSIONING AND TOPSIDE MAJOR MAINTENANCE SERVICES FOR YEAR 2013 - 2018

PROVISION OF HUC WORK FOR TOPSIDE MODIFICATION FOR SKO PIPELINE REJUVENATION PROJECT - PL381/210

Contract No :CHO/2012/DFHD/193Work Order No:DFHD/2015/042A/001June 2, 2015SECTIONWORKPACK ITEM DESCRIPTION (TURNAROUND)BOOK

1.0IntroductionBook 1 of 31.1Project Summary & Overall Scope of WorkBook 1 of 31.2Organizational ChartsBook 1 of 31.3Emergency Response PlanBook 1 of 3

2.0Turnaround Scope of Work (SOW)Book 1 of 32.1Detailed Turnaround Scope of WorkBook 1 of 3TKP-ABook 1 of 3WLDP-CBook 1 of 32.2Inspection Test Plan (Inspection Methodology)Book 1 of 32.3Pre-commissioning & Commissioning ProcedureBook 1 of 3

3.0Job Method Statement (Jobcards) with ManhoursBook 1 of 33.1Individual Activity Job Method Statement (Jobcards) Book 1 of 3with Manhours - TKP-ABook 1 of 33.2Individual Activity Job Method Statement (Jobcards) Book 1 of 3with Manhours - WLDP-CBook 1 of 33.3Manhours Summary List - TKP-ABook 1 of 33.4Manhours Summary List - WLDP-CBook 1 of 3

4.0Manpower Mobilization Plan (Turnaround)Book 1 of 34.1Manpower Loading & List (Turnaround) - TKP-ABook 1 of 34.2Manpower Loading & List (Turnaround) - WLDP-CBook 1 of 3

5.0Blind/Spading ListBook 1 of 35.1TA Physical Isolation List & Spading Plan (P&ID Mark-up) - TKP-ABook 1 of 35.2TA Physical Isolation List & Spading Plan (P&ID Mark-up) - WLDP-CBook 1 of 3

6.0Material & Consumable ListBook 1 of 36.1Overall Material Take-off (TKP-A)Book 1 of 36.2Overall Material Take-off (WLDP-C)Book 1 of 36.3Material Take-off (TA) and Consumable List - TKP-ABook 1 of 36.4Material Take-off (TA) and Consumable List - WLDP-CBook 1 of 3

7.0Equipment & Tools Loading (Turnaround)Book 1 of 37.1Equipment & Tools Loading Detail List (TKP-A)Book 1 of 37.2Equipment & Tools Loading Detail List (WLDP-C)Book 1 of 37.3Equipment Loading Plan with Layout (TKP-A)Book 1 of 37.4Equipment Loading Plan with Layout (WLDP-C)Book 1 of 3

8.0Project Schedule Book 2 of 38.1Overall Offshore HUC Schedule (TKP-A & WLDP-C)Book 2 of 38.2Turnaround Schedule (TKP-A & WLDP-C)Book 2 of 3

9.0Site Specific Procedures (Turnaround) Book 2 of 39.1Project Quality PlanBook 2 of 39.2Lifting & Rigging ProcedureBook 2 of 39.3Scaffolding ProcedureBook 2 of 39.4Cold Cutting ProcedureBook 2 of 39.5Oxy-Acetylene Cutting ProcedureBook 2 of 39.6Bolt Tightening Procedure Book 2 of 39.7Piping Fabrication & Installation ProcedureBook 2 of 39.8Guideline for Installation of Final Tie-in Golden JointBook 2 of 39.9Equipment, Instrument and Electrical Installation ProcedureBook 2 of 39.10Radiography Testing ProcedureBook 2 of 39.11Magnetic Particle Inspection ProcedureBook 2 of 39.12Ultrasonic Testing ProcedureBook 2 of 39.13Piping Flushing & Hydrotesting ProcedureBook 2 of 39.14System Reinstatement Testing & Nitrogen Purging ProcedureBook 2 of 39.15Repair & Touch-up Painting ProcedureBook 2 of 3

10.0Job Hazard Analysis (JHA)Book 2 of 3

11.0Drawing (Turnaround)Book 2 of 311.1TKP-ABook 2 of 3Process & Instrumentation DiagramBook 2 of 3PipingBook 2 of 3InstrumentBook 2 of 3ElectricalBook 2 of 3

11.2WLDP-CBook 3 of 3Process & Instrumentation DiagramBook 3 of 3PipingBook 3 of 3InstrumentBook 3 of 3ElectricalBook 3 of 3

12.0Site Visit ReportsBook 3 of 312.1StructuralBook 3 of 312.2MechanicalBook 3 of 312.3PipingBook 3 of 312.4Electrical & InstrumentBook 3 of 3

13.0Bolt Torqueing & Flange Management (Turnaround)Book 3 of 3

1.0

PROVISION OF HOOK-UP, COMMISSIONING AND TOPSIDE MAJOR MAINTENANCE SERVICES FOR YEAR 2013 - 2018

PROVISION OF HUC WORK FOR TOPSIDE MODIFICATION FOR SKO PIPELINE REJUVENATION PROJECT - PL381/210

Contract No :CHO/2012/DFHD/193Work Order No:DFHD/2015/042A/001

1.0Introduction1.1Project Summary & Overall Scope of Work

1.2Organizational Charts1.3Emergency Response Plan

1.1

PROVISION OF HOOK-UP, COMMISSIONING AND TOPSIDE MAJOR MAINTENANCE SERVICES FOR YEAR 2013 - 2018

PROVISION OF HUC WORK FOR TOPSIDE MODIFICATION FOR SKO PIPELINE REJUVENATION PROJECT - PL381/210

Contract No :CHO/2012/DFHD/193Work Order No:DFHD/2015/042A/001

1.0Introduction1.1Project Summary & Overall Scope of Work

1.2

PROVISION OF HOOK-UP, COMMISSIONING AND TOPSIDE MAJOR MAINTENANCE SERVICES FOR YEAR 2013 - 2018

PROVISION OF HUC WORK FOR TOPSIDE MODIFICATION FOR SKO PIPELINE REJUVENATION PROJECT - PL381/210

Contract No :CHO/2012/DFHD/193Work Order No:DFHD/2015/042A/001

1.0Introduction1.2Organizational Charts

1.3

PROVISION OF HOOK-UP, COMMISSIONING AND TOPSIDE MAJOR MAINTENANCE SERVICES FOR YEAR 2013 - 2018

PROVISION OF HUC WORK FOR TOPSIDE MODIFICATION FOR SKO PIPELINE REJUVENATION PROJECT - PL381/210

Contract No :CHO/2012/DFHD/193Work Order No:DFHD/2015/042A/001

1.0Introduction1.3Emergency Response Plan

2.0

PROVISION OF HOOK-UP, COMMISSIONING AND TOPSIDE MAJOR MAINTENANCE SERVICES FOR YEAR 2013 - 2018

PROVISION OF HUC WORK FOR TOPSIDE MODIFICATION FOR SKO PIPELINE REJUVENATION PROJECT - PL381/210

Contract No :CHO/2012/DFHD/193Work Order No:DFHD/2015/042A/001

2.0Turnaround Scope of Work (SOW)2.1Detailed Turnaround Scope of Work2.2Inspection Test Plan (Inspection Methodology)

2.3Pre-commissioning & Commissioning Procedure

2.1.TKP-A

PROVISION OF HOOK-UP, COMMISSIONING AND TOPSIDE MAJOR MAINTENANCE SERVICES FOR YEAR 2013 - 2018

PROVISION OF HUC WORK FOR TOPSIDE MODIFICATION FOR SKO PIPELINE REJUVENATION PROJECT - PL381/210

Contract No :CHO/2012/DFHD/193Work Order No:DFHD/2015/042A/001

2.0Turnaround Scope of Work (SOW)2.1Detailed Turnaround Scope of WorkTKP-A

2.1.WLDP-C

PROVISION OF HOOK-UP, COMMISSIONING AND TOPSIDE MAJOR MAINTENANCE SERVICES FOR YEAR 2013 - 2018

PROVISION OF HUC WORK FOR TOPSIDE MODIFICATION FOR SKO PIPELINE REJUVENATION PROJECT - PL381/210

Contract No :CHO/2012/DFHD/193Work Order No:DFHD/2015/042A/001

2.0Turnaround Scope of Work (SOW)2.1Detailed Turnaround Scope of WorkWLDP-C

2.2

PROVISION OF HOOK-UP, COMMISSIONING AND TOPSIDE MAJOR MAINTENANCE SERVICES FOR YEAR 2013 - 2018

PROVISION OF HUC WORK FOR TOPSIDE MODIFICATION FOR SKO PIPELINE REJUVENATION PROJECT - PL381/210

Contract No :CHO/2012/DFHD/193Work Order No:DFHD/2015/042A/001

2.0Turnaround Scope of Work (SOW)2.2Inspection Test Plan (Inspection Methodology)

2.3

PROVISION OF HOOK-UP, COMMISSIONING AND TOPSIDE MAJOR MAINTENANCE SERVICES FOR YEAR 2013 - 2018

PROVISION OF HUC WORK FOR TOPSIDE MODIFICATION FOR SKO PIPELINE REJUVENATION PROJECT - PL381/210

Contract No :CHO/2012/DFHD/193Work Order No:DFHD/2015/042A/001

2.0Turnaround Scope of Work (SOW)2.3Pre-commissioning & Commissioning Procedure

3.0

PROVISION OF HOOK-UP, COMMISSIONING AND TOPSIDE MAJOR MAINTENANCE SERVICES FOR YEAR 2013 - 2018

PROVISION OF HUC WORK FOR TOPSIDE MODIFICATION FOR SKO PIPELINE REJUVENATION PROJECT - PL381/210

Contract No :CHO/2012/DFHD/193Work Order No:DFHD/2015/042A/001

3.0Job Method Statement (Jobcards) with Manhours

3.1Individual Activity Job Method Statement (Jobcards) with Manhours - TKP-A

3.2Individual Activity Job Method Statement (Jobcards) with Manhours - WLDP-C

3.3Manhours Summary List - TKP-A3.4Manhours Summary List - WLDP-C

3.1.gen

PROVISION OF HOOK-UP, COMMISSIONING AND TOPSIDE MAJOR MAINTENANCE SERVICES FOR YEAR 2013 - 2018

PROVISION OF HUC WORK FOR TOPSIDE MODIFICATION FOR SKO PIPELINE REJUVENATION PROJECT - PL381/210

Contract No :CHO/2012/DFHD/193Work Order No:DFHD/2015/042A/001

3.0Job Method Statement (Jobcards) with Manhours

3.1Individual Activity Job Method Statement (Jobcards) with Manhours - TKP-A

General

3.1.pip

PROVISION OF HOOK-UP, COMMISSIONING AND TOPSIDE MAJOR MAINTENANCE SERVICES FOR YEAR 2013 - 2018

PROVISION OF HUC WORK FOR TOPSIDE MODIFICATION FOR SKO PIPELINE REJUVENATION PROJECT - PL381/210

Contract No :CHO/2012/DFHD/193Work Order No:DFHD/2015/042A/001

3.0Job Method Statement (Jobcards) with Manhours

3.1Individual Activity Job Method Statement (Jobcards) with Manhours - TKP-A

Piping

3.1.Inst

PROVISION OF HOOK-UP, COMMISSIONING AND TOPSIDE MAJOR MAINTENANCE SERVICES FOR YEAR 2013 - 2018

PROVISION OF HUC WORK FOR TOPSIDE MODIFICATION FOR SKO PIPELINE REJUVENATION PROJECT - PL381/210

Contract No :CHO/2012/DFHD/193Work Order No:DFHD/2015/042A/001

3.0Job Method Statement (Jobcards) with Manhours

3.1Individual Activity Job Method Statement (Jobcards) with Manhours - TKP-A

Instrument

3.1.Ele

PROVISION OF HOOK-UP, COMMISSIONING AND TOPSIDE MAJOR MAINTENANCE SERVICES FOR YEAR 2013 - 2018

PROVISION OF HUC WORK FOR TOPSIDE MODIFICATION FOR SKO PIPELINE REJUVENATION PROJECT - PL381/210

Contract No :CHO/2012/DFHD/193Work Order No:DFHD/2015/042A/001

3.0Job Method Statement (Jobcards) with Manhours

3.1Individual Activity Job Method Statement (Jobcards) with Manhours - TKP-A

Electrical

3.2.gen

PROVISION OF HOOK-UP, COMMISSIONING AND TOPSIDE MAJOR MAINTENANCE SERVICES FOR YEAR 2013 - 2018

PROVISION OF HUC WORK FOR TOPSIDE MODIFICATION FOR SKO PIPELINE REJUVENATION PROJECT - PL381/210

Contract No :CHO/2012/DFHD/193Work Order No:DFHD/2015/042A/001

3.0Job Method Statement (Jobcards) with Manhours

3.2Individual Activity Job Method Statement (Jobcards) with Manhours - WLDP-C

General

3.2.pip

PROVISION OF HOOK-UP, COMMISSIONING AND TOPSIDE MAJOR MAINTENANCE SERVICES FOR YEAR 2013 - 2018

PROVISION OF HUC WORK FOR TOPSIDE MODIFICATION FOR SKO PIPELINE REJUVENATION PROJECT - PL381/210

Contract No :CHO/2012/DFHD/193Work Order No:DFHD/2015/042A/001

3.0Job Method Statement (Jobcards) with Manhours

3.2Individual Activity Job Method Statement (Jobcards) with Manhours - WLDP-C

Piping

3.2.Inst

PROVISION OF HOOK-UP, COMMISSIONING AND TOPSIDE MAJOR MAINTENANCE SERVICES FOR YEAR 2013 - 2018

PROVISION OF HUC WORK FOR TOPSIDE MODIFICATION FOR SKO PIPELINE REJUVENATION PROJECT - PL381/210

Contract No :CHO/2012/DFHD/193Work Order No:DFHD/2015/042A/001

3.0Job Method Statement (Jobcards) with Manhours

3.2Individual Activity Job Method Statement (Jobcards) with Manhours - WLDP-C

Instrument

3.2.ele

PROVISION OF HOOK-UP, COMMISSIONING AND TOPSIDE MAJOR MAINTENANCE SERVICES FOR YEAR 2013 - 2018

PROVISION OF HUC WORK FOR TOPSIDE MODIFICATION FOR SKO PIPELINE REJUVENATION PROJECT - PL381/210

Contract No :CHO/2012/DFHD/193Work Order No:DFHD/2015/042A/001

3.0Job Method Statement (Jobcards) with Manhours

3.2Individual Activity Job Method Statement (Jobcards) with Manhours - WLDP-C

Electrical

3.3

PROVISION OF HOOK-UP, COMMISSIONING AND TOPSIDE MAJOR MAINTENANCE SERVICES FOR YEAR 2013 - 2018

PROVISION OF HUC WORK FOR TOPSIDE MODIFICATION FOR SKO PIPELINE REJUVENATION PROJECT - PL381/210

Contract No :CHO/2012/DFHD/193Work Order No:DFHD/2015/042A/001

3.0Job Method Statement (Jobcards) with Manhours

3.3Manhours Summary List - TKP-A

3.4

PROVISION OF HOOK-UP, COMMISSIONING AND TOPSIDE MAJOR MAINTENANCE SERVICES FOR YEAR 2013 - 2018

PROVISION OF HUC WORK FOR TOPSIDE MODIFICATION FOR SKO PIPELINE REJUVENATION PROJECT - PL381/210

Contract No :CHO/2012/DFHD/193Work Order No:DFHD/2015/042A/001

3.0Job Method Statement (Jobcards) with Manhours

3.4Manhours Summary List - WLDP-C

4.0

PROVISION OF HOOK-UP, COMMISSIONING AND TOPSIDE MAJOR MAINTENANCE SERVICES FOR YEAR 2013 - 2018

PROVISION OF HUC WORK FOR TOPSIDE MODIFICATION FOR SKO PIPELINE REJUVENATION PROJECT - PL381/210

Contract No :CHO/2012/DFHD/193Work Order No:DFHD/2015/042A/001

4.0Manpower Mobilization Plan (TA)4.1Manpower Loading & List (TA) - TKP-A

4.2Manpower Loading & List (TA) - WLDP-C

4.1

PROVISION OF HOOK-UP, COMMISSIONING AND TOPSIDE MAJOR MAINTENANCE SERVICES FOR YEAR 2013 - 2018

PROVISION OF HUC WORK FOR TOPSIDE MODIFICATION FOR SKO PIPELINE REJUVENATION PROJECT - PL381/210

Contract No :CHO/2012/DFHD/193Work Order No:DFHD/2015/042A/001

4.0Manpower Mobilization Plan (TA)4.1Manpower Loading & List (TA)TKP-A

4.2

PROVISION OF HOOK-UP, COMMISSIONING AND TOPSIDE MAJOR MAINTENANCE SERVICES FOR YEAR 2013 - 2018

PROVISION OF HUC WORK FOR TOPSIDE MODIFICATION FOR SKO PIPELINE REJUVENATION PROJECT - PL381/210

Contract No :CHO/2012/DFHD/193Work Order No:DFHD/2015/042A/001

4.0Manpower Mobilization Plan (TA)4.2Manpower Loading & List (TA)WLDP-C

5.0

PROVISION OF HOOK-UP, COMMISSIONING AND TOPSIDE MAJOR MAINTENANCE SERVICES FOR YEAR 2013 - 2018

PROVISION OF HUC WORK FOR TOPSIDE MODIFICATION FOR SKO PIPELINE REJUVENATION PROJECT - PL381/210

Contract No :CHO/2012/DFHD/193Work Order No:DFHD/2015/042A/001

5.0Blind/Spading List5.1TA Physical Isolation List & Spading Plan (P&ID Mark-up) - TKP-A

5.2TA Physical Isolation List & Spading Plan (P&ID Mark-up) - WLDP-C

5.1

PROVISION OF HOOK-UP, COMMISSIONING AND TOPSIDE MAJOR MAINTENANCE SERVICES FOR YEAR 2013 - 2018

PROVISION OF HUC WORK FOR TOPSIDE MODIFICATION FOR SKO PIPELINE REJUVENATION PROJECT - PL381/210

Contract No :CHO/2012/DFHD/193Work Order No:DFHD/2015/042A/001

5.0Blind/Spading List5.1TA Physical Isolation List & Spading Plan (P&ID Mark-up) - TKP-A

5.2

PROVISION OF HOOK-UP, COMMISSIONING AND TOPSIDE MAJOR MAINTENANCE SERVICES FOR YEAR 2013 - 2018

PROVISION OF HUC WORK FOR TOPSIDE MODIFICATION FOR SKO PIPELINE REJUVENATION PROJECT - PL381/210

Contract No :CHO/2012/DFHD/193Work Order No:DFHD/2015/042A/001

5.0Blind/Spading List5.2TA Physical Isolation List & Spading Plan (P&ID Mark-up) - WLDP-C

6.0

PROVISION OF HOOK-UP, COMMISSIONING AND TOPSIDE MAJOR MAINTENANCE SERVICES FOR YEAR 2013 - 2018

PROVISION OF HUC WORK FOR TOPSIDE MODIFICATION FOR SKO PIPELINE REJUVENATION PROJECT - PL381/210

Contract No :CHO/2012/DFHD/193Work Order No:DFHD/2015/042A/001

6.0Material & Consumable List6.1Overall Material Take-off (TKP-A)6.2Overall Material Take-off (WLDP-C)6.3Material Take-off (TA) and Consumable List - TKP-A

6.4Material Take-off (TA) and Consumable List - WLDP-C

6.1

PROVISION OF HOOK-UP, COMMISSIONING AND TOPSIDE MAJOR MAINTENANCE SERVICES FOR YEAR 2013 - 2018

PROVISION OF HUC WORK FOR TOPSIDE MODIFICATION FOR SKO PIPELINE REJUVENATION PROJECT - PL381/210

Contract No :CHO/2012/DFHD/193Work Order No:DFHD/2015/042A/001

6.0Material & Consumable List6.1Overall Material Take-off (TKP-A)

6.2

PROVISION OF HOOK-UP, COMMISSIONING AND TOPSIDE MAJOR MAINTENANCE SERVICES FOR YEAR 2013 - 2018

PROVISION OF HUC WORK FOR TOPSIDE MODIFICATION FOR SKO PIPELINE REJUVENATION PROJECT - PL381/210

Contract No :CHO/2012/DFHD/193Work Order No:DFHD/2015/042A/001

6.0Material & Consumable List6.2Overall Material Take-off (WLDP-C)

6.3

PROVISION OF HOOK-UP, COMMISSIONING AND TOPSIDE MAJOR MAINTENANCE SERVICES FOR YEAR 2013 - 2018

PROVISION OF HUC WORK FOR TOPSIDE MODIFICATION FOR SKO PIPELINE REJUVENATION PROJECT - PL381/210

Contract No :CHO/2012/DFHD/193Work Order No:DFHD/2015/042A/001

6.0Material & Consumable List6.3Material Take-off (TA) and Consumable List - TKP-A

6.4

PROVISION OF HOOK-UP, COMMISSIONING AND TOPSIDE MAJOR MAINTENANCE SERVICES FOR YEAR 2013 - 2018

PROVISION OF HUC WORK FOR TOPSIDE MODIFICATION FOR SKO PIPELINE REJUVENATION PROJECT - PL381/210

Contract No :CHO/2012/DFHD/193Work Order No:DFHD/2015/042A/001

6.0Material & Consumable List6.4Material Take-off (TA) and Consumable List - WLDP-C

7.0

PROVISION OF HOOK-UP, COMMISSIONING AND TOPSIDE MAJOR MAINTENANCE SERVICES FOR YEAR 2013 - 2018

PROVISION OF HUC WORK FOR TOPSIDE MODIFICATION FOR SKO PIPELINE REJUVENATION PROJECT - PL381/210

Contract No :CHO/2012/DFHD/193Work Order No:DFHD/2015/042A/001

7.0Equipment & Tools Loading7.1Equipment & Tools Loading Detail List (TKP-A)

7.2Equipment & Tools Loading Detail List (WLDP-C)

7.3Equipment Loading Plan with Layout (TKP-A)

7.4Equipment Loading Plan with Layout (WLDP-C)

7.1

PROVISION OF HOOK-UP, COMMISSIONING AND TOPSIDE MAJOR MAINTENANCE SERVICES FOR YEAR 2013 - 2018

PROVISION OF HUC WORK FOR TOPSIDE MODIFICATION FOR SKO PIPELINE REJUVENATION PROJECT - PL381/210

Contract No :CHO/2012/DFHD/193Work Order No:DFHD/2015/042A/001

7.0Equipment & Tools Loading7.1Equipment & Tools Loading Detail List (TKP-A)

7.2

PROVISION OF HOOK-UP, COMMISSIONING AND TOPSIDE MAJOR MAINTENANCE SERVICES FOR YEAR 2013 - 2018

PROVISION OF HUC WORK FOR TOPSIDE MODIFICATION FOR SKO PIPELINE REJUVENATION PROJECT - PL381/210

Contract No :CHO/2012/DFHD/193Work Order No:DFHD/2015/042A/001

7.0Equipment & Tools Loading7.2Equipment & Tools Loading Detail List (WLDP-C)

7.3

PROVISION OF HOOK-UP, COMMISSIONING AND TOPSIDE MAJOR MAINTENANCE SERVICES FOR YEAR 2013 - 2018

PROVISION OF HUC WORK FOR TOPSIDE MODIFICATION FOR SKO PIPELINE REJUVENATION PROJECT - PL381/210

Contract No :CHO/2012/DFHD/193Work Order No:DFHD/2015/042A/001

7.0Equipment & Tools Loading7.3Equipment Loading Plan with Layout (TKP-A)

7.4

PROVISION OF HOOK-UP, COMMISSIONING AND TOPSIDE MAJOR MAINTENANCE SERVICES FOR YEAR 2013 - 2018

PROVISION OF HUC WORK FOR TOPSIDE MODIFICATION FOR SKO PIPELINE REJUVENATION PROJECT - PL381/210

Contract No :CHO/2012/DFHD/193Work Order No:DFHD/2015/042A/001

7.0Equipment & Tools Loading7.4Equipment Loading Plan with Layout (WLDP-C)

8.0

PROVISION OF HOOK-UP, COMMISSIONING AND TOPSIDE MAJOR MAINTENANCE SERVICES FOR YEAR 2013 - 2018

PROVISION OF HUC WORK FOR TOPSIDE MODIFICATION FOR SKO PIPELINE REJUVENATION PROJECT - PL381/210

Contract No :CHO/2012/DFHD/193Work Order No:DFHD/2015/042A/001

8.0Project Schedule8.1Overall Offshore HUC Schedule (TKP-A & WLDP-C)

8.2Turnaround Schedule (TKP-A & WLDP-C)

8.1

PROVISION OF HOOK-UP, COMMISSIONING AND TOPSIDE MAJOR MAINTENANCE SERVICES FOR YEAR 2013 - 2018

PROVISION OF HUC WORK FOR TOPSIDE MODIFICATION FOR SKO PIPELINE REJUVENATION PROJECT - PL381/210

Contract No :CHO/2012/DFHD/193Work Order No:DFHD/2015/042A/001

8.0Project Schedule8.1Overall Offshore HUC Schedule (TKP-A & WLDP-C)

8.2

PROVISION OF HOOK-UP, COMMISSIONING AND TOPSIDE MAJOR MAINTENANCE SERVICES FOR YEAR 2013 - 2018

PROVISION OF HUC WORK FOR TOPSIDE MODIFICATION FOR SKO PIPELINE REJUVENATION PROJECT - PL381/210

Contract No :CHO/2012/DFHD/193Work Order No:DFHD/2015/042A/001

8.0Project Schedule8.2Turnaround Schedule (TKP-A & WLDP-C)

9.0

PROVISION OF HOOK-UP, COMMISSIONING AND TOPSIDE MAJOR MAINTENANCE SERVICES FOR YEAR 2013 - 2018

PROVISION OF HUC WORK FOR TOPSIDE MODIFICATION FOR SKO PIPELINE REJUVENATION PROJECT - PL381/210

Contract No :CHO/2012/DFHD/193Work Order No:DFHD/2015/042A/001

9.0Site Specific Procedures (Turnaround) 9.1Project Quality Plan9.2Lifting & Rigging Procedure9.3Scaffolding Procedure9.4Cold Cutting Procedure9.5Oxy-Acetylene Cutting Procedure9.6Bolt Tightening Procedure 9.7Piping Fabrication & Installation Procedure

9.8Guideline for Installation of Final Tie-in Golden Joint

9.9Equipment, Instrument and Electrical Installation Procedure

9.10Radiography Testing Procedure9.11Magnetic Particle Inspection Procedure9.12Ultrasonic Testing Procedure9.13Piping Flushing & Hydrotesting Procedure9.14System Reinstatement Testing & Nitrogen Purging Procedure

9.15Repair & Touch-up Painting Procedure

10.0

PROVISION OF HOOK-UP, COMMISSIONING AND TOPSIDE MAJOR MAINTENANCE SERVICES FOR YEAR 2013 - 2018

PROVISION OF HUC WORK FOR TOPSIDE MODIFICATION FOR SKO PIPELINE REJUVENATION PROJECT - PL381/210

Contract No :CHO/2012/DFHD/193Work Order No:DFHD/2015/042A/001

10.0Job Hazard Analysis

11.1

PROVISION OF HOOK-UP, COMMISSIONING AND TOPSIDE MAJOR MAINTENANCE SERVICES FOR YEAR 2013 - 2018

PROVISION OF HUC WORK FOR TOPSIDE MODIFICATION FOR SKO PIPELINE REJUVENATION PROJECT - PL381/210

Contract No :CHO/2012/DFHD/193Work Order No:DFHD/2015/042A/001

11.0Drawing (Turnaround)11.1TKP-AProcess & Instrumentation DiagramPipingInstrumentElectrical

11.1.P&ID

PROVISION OF HOOK-UP, COMMISSIONING AND TOPSIDE MAJOR MAINTENANCE SERVICES FOR YEAR 2013 - 2018

PROVISION OF HUC WORK FOR TOPSIDE MODIFICATION FOR SKO PIPELINE REJUVENATION PROJECT - PL381/210

Contract No :CHO/2012/DFHD/193Work Order No:DFHD/2015/042A/001

11.0Drawing (Turnaround)11.1TKP-AProcess & Instrumentation Diagram

11.1.Pipe

PROVISION OF HOOK-UP, COMMISSIONING AND TOPSIDE MAJOR MAINTENANCE SERVICES FOR YEAR 2013 - 2018

PROVISION OF HUC WORK FOR TOPSIDE MODIFICATION FOR SKO PIPELINE REJUVENATION PROJECT - PL381/210

Contract No :CHO/2012/DFHD/193Work Order No:DFHD/2015/042A/001

11.0Drawing (Turnaround)11.1TKP-APiping

11.1.Instr

PROVISION OF HOOK-UP, COMMISSIONING AND TOPSIDE MAJOR MAINTENANCE SERVICES FOR YEAR 2013 - 2018

PROVISION OF HUC WORK FOR TOPSIDE MODIFICATION FOR SKO PIPELINE REJUVENATION PROJECT - PL381/210

Contract No :CHO/2012/DFHD/193Work Order No:DFHD/2015/042A/001

11.0Drawing (Turnaround)11.1TKP-AInstrument

11.1.Elect

PROVISION OF HOOK-UP, COMMISSIONING AND TOPSIDE MAJOR MAINTENANCE SERVICES FOR YEAR 2013 - 2018

PROVISION OF HUC WORK FOR TOPSIDE MODIFICATION FOR SKO PIPELINE REJUVENATION PROJECT - PL381/210

Contract No :CHO/2012/DFHD/193Work Order No:DFHD/2015/042A/001

11.0Drawing (Turnaround)11.1TKP-AElectrical

11.2

PROVISION OF HOOK-UP, COMMISSIONING AND TOPSIDE MAJOR MAINTENANCE SERVICES FOR YEAR 2013 - 2018

PROVISION OF HUC WORK FOR TOPSIDE MODIFICATION FOR SKO PIPELINE REJUVENATION PROJECT - PL381/210

Contract No :CHO/2012/DFHD/193Work Order No:DFHD/2015/042A/001

11.0Drawing (Turnaround)11.2WLDP-CProcess & Instrumentation DiagramPipingInstrumentElectrical

11.2.P&ID

PROVISION OF HOOK-UP, COMMISSIONING AND TOPSIDE MAJOR MAINTENANCE SERVICES FOR YEAR 2013 - 2018

PROVISION OF HUC WORK FOR TOPSIDE MODIFICATION FOR SKO PIPELINE REJUVENATION PROJECT - PL381/210

Contract No :CHO/2012/DFHD/193Work Order No:DFHD/2015/042A/001

11.0Drawing (Turnaround)11.2WLDP-CProcess & Instrumentation Diagram

11.2.Pip

PROVISION OF HOOK-UP, COMMISSIONING AND TOPSIDE MAJOR MAINTENANCE SERVICES FOR YEAR 2013 - 2018

PROVISION OF HUC WORK FOR TOPSIDE MODIFICATION FOR SKO PIPELINE REJUVENATION PROJECT - PL381/210

Contract No :CHO/2012/DFHD/193Work Order No:DFHD/2015/042A/001

11.0Drawing (Turnaround)11.2WLDP-CPiping

11.2.Inst

PROVISION OF HOOK-UP, COMMISSIONING AND TOPSIDE MAJOR MAINTENANCE SERVICES FOR YEAR 2013 - 2018

PROVISION OF HUC WORK FOR TOPSIDE MODIFICATION FOR SKO PIPELINE REJUVENATION PROJECT - PL381/210

Contract No :CHO/2012/DFHD/193Work Order No:DFHD/2015/042A/001

11.0Drawing (Turnaround)11.2WLDP-CInstrument

11.2.Ele

PROVISION OF HOOK-UP, COMMISSIONING AND TOPSIDE MAJOR MAINTENANCE SERVICES FOR YEAR 2013 - 2018

PROVISION OF HUC WORK FOR TOPSIDE MODIFICATION FOR SKO PIPELINE REJUVENATION PROJECT - PL381/210

Contract No :CHO/2012/DFHD/193Work Order No:DFHD/2015/042A/001

11.0Drawing (Turnaround)11.2WLDP-CElectrical

12.0

PROVISION OF HOOK-UP, COMMISSIONING AND TOPSIDE MAJOR MAINTENANCE SERVICES FOR YEAR 2013 - 2018

PROVISION OF HUC WORK FOR TOPSIDE MODIFICATION FOR SKO PIPELINE REJUVENATION PROJECT - PL381/210

Contract No :CHO/2012/DFHD/193Work Order No:DFHD/2015/042A/001

12.0Site Visit Reports12.1Structural12.2Mechanical12.3Piping12.4Electrical & Instrument

12.1.tkp-a

PROVISION OF HOOK-UP, COMMISSIONING AND TOPSIDE MAJOR MAINTENANCE SERVICES FOR YEAR 2013 - 2018

PROVISION OF HUC WORK FOR TOPSIDE MODIFICATION FOR SKO PIPELINE REJUVENATION PROJECT - PL381/210

Contract No :CHO/2012/DFHD/193Work Order No:DFHD/2015/042A/001

12.0Site Visit Reports12.1Structural - TKP-A

12.1.wldp-c

PROVISION OF HOOK-UP, COMMISSIONING AND TOPSIDE MAJOR MAINTENANCE SERVICES FOR YEAR 2013 - 2018

PROVISION OF HUC WORK FOR TOPSIDE MODIFICATION FOR SKO PIPELINE REJUVENATION PROJECT - PL381/210

Contract No :CHO/2012/DFHD/193Work Order No:DFHD/2015/042A/001

12.0Site Visit Reports12.1Structural - WLDP-C

12.2.tkp-a

PROVISION OF HOOK-UP, COMMISSIONING AND TOPSIDE MAJOR MAINTENANCE SERVICES FOR YEAR 2013 - 2018

PROVISION OF HUC WORK FOR TOPSIDE MODIFICATION FOR SKO PIPELINE REJUVENATION PROJECT - PL381/210

Contract No :CHO/2012/DFHD/193Work Order No:DFHD/2015/042A/001

12.0Site Visit Reports12.2Mechanical - TKP-A

12.2.wldp-c

PROVISION OF HOOK-UP, COMMISSIONING AND TOPSIDE MAJOR MAINTENANCE SERVICES FOR YEAR 2013 - 2018

PROVISION OF HUC WORK FOR TOPSIDE MODIFICATION FOR SKO PIPELINE REJUVENATION PROJECT - PL381/210

Contract No :CHO/2012/DFHD/193Work Order No:DFHD/2015/042A/001

12.0Site Visit Reports12.2Mechanical - WLDP-C

12.3.tkp-a

PROVISION OF HOOK-UP, COMMISSIONING AND TOPSIDE MAJOR MAINTENANCE SERVICES FOR YEAR 2013 - 2018

PROVISION OF HUC WORK FOR TOPSIDE MODIFICATION FOR SKO PIPELINE REJUVENATION PROJECT - PL381/210

Contract No :CHO/2012/DFHD/193Work Order No:DFHD/2015/042A/001

12.0Site Visit Reports12.3Piping - TKP-A

12.3.wldp-c

PROVISION OF HOOK-UP, COMMISSIONING AND TOPSIDE MAJOR MAINTENANCE SERVICES FOR YEAR 2013 - 2018

PROVISION OF HUC WORK FOR TOPSIDE MODIFICATION FOR SKO PIPELINE REJUVENATION PROJECT - PL381/210

Contract No :CHO/2012/DFHD/193Work Order No:DFHD/2015/042A/001

12.0Site Visit Reports12.3Piping - WLDP-C

12.4.tkp-a

PROVISION OF HOOK-UP, COMMISSIONING AND TOPSIDE MAJOR MAINTENANCE SERVICES FOR YEAR 2013 - 2018

PROVISION OF HUC WORK FOR TOPSIDE MODIFICATION FOR SKO PIPELINE REJUVENATION PROJECT - PL381/210

Contract No :CHO/2012/DFHD/193Work Order No:DFHD/2015/042A/001

12.0Site Visit Reports12.4Electrical & Instrument - TKP-A

12.4.wldp-c

PROVISION OF HOOK-UP, COMMISSIONING AND TOPSIDE MAJOR MAINTENANCE SERVICES FOR YEAR 2013 - 2018

PROVISION OF HUC WORK FOR TOPSIDE MODIFICATION FOR SKO PIPELINE REJUVENATION PROJECT - PL381/210

Contract No :CHO/2012/DFHD/193Work Order No:DFHD/2015/042A/001

12.0Site Visit Reports12.4Electrical & Instrument - WLDP-C

13.0.tkp-a

PROVISION OF HOOK-UP, COMMISSIONING AND TOPSIDE MAJOR MAINTENANCE SERVICES FOR YEAR 2013 - 2018

PROVISION OF HUC WORK FOR TOPSIDE MODIFICATION FOR SKO PIPELINE REJUVENATION PROJECT - PL381/210

Contract No :CHO/2012/DFHD/193Work Order No:DFHD/2015/042A/001

13.0Bolt Torqueing & Flange Management (Turnaround)

TKP-A

13.0.wldp-c

PROVISION OF HOOK-UP, COMMISSIONING AND TOPSIDE MAJOR MAINTENANCE SERVICES FOR YEAR 2013 - 2018

PROVISION OF HUC WORK FOR TOPSIDE MODIFICATION FOR SKO PIPELINE REJUVENATION PROJECT - PL381/210

Contract No :CHO/2012/DFHD/193Work Order No:DFHD/2015/042A/001

13.0Bolt Torqueing & Flange Management (Turnaround)

WLDP-C