To: Lincoln High School Building Committee
Lincoln School Committee
From: Charlie Roberts
Date: 10/10/18
Re: Weekly Update – Lincoln High School Project
The purpose of this report is to provide, on a weekly basis, a) a look back to work that was completed during
the previous week, b) report on major project issues and what is being done to correct same, c) a look ahead
to activities that are planned for next week.
Work Activities, Week of 10/01/18:
Please reference the attached Daily Reports for further day-by-day details.
Average daily on-site manpower was roughly 14 workers, primarily working on abatement of the roof
and cmu walls, demolition, debris sorting for recycling and disposal, construction of temporary partitions
where the 1970’s wing met other parts of the building.
As of Friday, October 5th, most of the 1970 connector wing’s roof and exterior walls had been
demolished except for the four classrooms at the bottom of the ramp, several offices where the
connector tied into the former middle school, and the rooms adjacent to the west wall of the
Auditorium. (see photos below).
Back-ordered wall-mounted unit heaters for the temp water service room and entrance vestibule were
received earlier this week and will be installed.
Remaining Offices Near Former Middle School View Towards ‘96 Building; (4) Remaining Classrooms
2
View Towards East Exterior Wall & Auditorium View Towards Ramp Leading Down to Auditorium.
RH Debris Pile is at Former School Store Location.
Work Activities, Week of October 10/08/18:
It is anticipated that most of the mechanical demolition of the roof and walls will be completed by the
end of this week, leaving manual demolition of the walls that tie into the 1996 and former middle school
wings. Next week, demolition work will shift to removal of the concrete slab and foundation walls,
starting near the 1996 wing and working outward towards the parking lot and former front of the
building. Target date for completion of all demolition and removal work is Friday, November 2nd.
Gilbane will be receiving initial bid proposals from subcontractors for the next three bid proposals on
Friday, October 12th. It will then take about 2 weeks to perform detailed scope reviews and obtain best
and final pricing from the lowest three subs for each bid package. Proposals due on Friday include:
o Foundations & concrete. ( 9 bidders)
o Structural steel. (14 bidders)
o Sitework (for balance of project) (10 bidders)
Major Project Issues:
Existing Site Drainage Line, East of Field / Running Track
Lincoln DPW will have the Town’s sewer maintenance vendor, Veolia, inspect the drainage line with a remote
camera system to further determine the exact location and extent of blockage. The camera should be
available after being taken out of service for repairs last week. Once the blockage is cleared, the eroded area
around the manhole will be loamed & seeded. Other grassed areas alongside the connector road have now
fully germinated.
Attachments
Gilbane 3-Week Look Ahead Schedule – 10/09/18
Colliers Daily Field Reports – 10/01/18, thru 10/05/18.
DAILY CONSTRUCTION REPORT
Page 1
Project: Lincoln Public Schools Date: October 1, 2018
Lincoln High School - Enabling Phase
Construction Representative: Daniel M. Daisy Time: 7:00/ 12:00/ 4:00
Cell Phone: 401.500.0117 Weather: Cloudy/ Cloudy/ Cloudy
Temperature Range: 56 / 69/ 68 degrees
Winds: S6/ SW8/ SSW6 mph
Hours on Site: IN: 7:00 a.m. OUT: 4:00 p.m.
# on Job Site
PROJECT ACTIVITIES
SUMMARY:
Lead/
Foreman Other Activities Completed
OPM: Colliers International 1CR
1PM
0 Daniel Daisy and Charlie Roberts onsite all day –
construction monitoring.
Architect: SMMA 0 0
Construction Manager:
Gilbane
(Superintendent: Paul Bertelli)
1S
1PE
1PM
0
Paul Bertelli, Kristin Couto & Mike Marcella onsite all day –
Subcontractor Supervision and coordination.
Demo/ Abatement Contractor:
SiteCon
1FL 1JE
3JL
Continued demolition of the 1970’s building.
ACM Sampling: ATC 1 0 Onsite abatement and demolition monitoring.
Site Work: SiteTech 0 0
General Trades: Excel/ HSI 1FC 1JC
1JL
Start demolition in the old library and layout of temp
weather wall.
Masonry: Grande Masonry 0 0
Mechanical: Arden 0 0
Plumbing: Arden 0 0
Electrical: Rossi 0 0
Fiber/ Trench: TeleNetworks 0 0
MDF Terminations: American
TeleConnect
0 0
Security System: Sonitrol 0 0
Wood Floors: O’Sullivan Flooring 0 0
TOTAL PEOPLE ON SITE:8 6
DAILY CONSTRUCTION REPORT
Page 2
Problems Encountered: PhotoExisting (unidentified) radiant heat system uncovered
above the old Library ceiling. Gilbane to call Arden to
cut/ cap system.
Discussions:
Name & Title Description:Weekly Demolition Meeting with Principal McNamara
and Staff.
Safety Items / Violations or Notices Issued: None
Equipment & Utilization of EquipmentDescription: Used/Parked/Service
SiteCon: Bobcat skid steer, 2 Komatsu Excavators, Hyundai Loader, Scissor lifts Used
Request for Information Sent (RFI’s) #’s: RFI’s #00021 & 00022 submitted by Gilbane. RFI’s #00020 &
00022 responded to by SMMA.
Observations
Demo/ Abatement Contractor: SiteCon – Continued with major demolition of the 1970’s building.
DAILY CONSTRUCTION REPORT
Page 3
DAILY CONSTRUCTION REPORT
Page 1
Project: Lincoln Public Schools Date: October 2, 2018
Lincoln High School - Enabling Phase
Construction Representative: Daniel M. Daisy Time: 7:00/ 12:00/ 4:00
Cell Phone: 401.500.0117 Weather: Cloudy- light rain/ Cloudy/ Cloudy
Temperature Range: 56 / 59/ 65 degrees
Winds: S6/ NE5/ S3 mph
Hours on Site: IN: 7:00 a.m. OUT: 4:00 p.m.
# on Job Site
PROJECT ACTIVITIES
SUMMARY:
Lead/
Foreman Other Activities Completed
OPM: Colliers International 1CR
1PM
0 Daniel Daisy and Charlie Roberts onsite all day –
construction monitoring.
Architect: SMMA 0 0
Construction Manager:
Gilbane
(Superintendent: Paul Bertelli)
1S
1PE
1PM
0
Paul Bertelli, Kristin Couto & Mike Marcella onsite all day –
Subcontractor Supervision and coordination. Pre-Bid
Meetings held for Site and Structural/ Foundations
Packages.
Demo/ Abatement Contractor:
SiteCon
1FL 1JE
3JL
Continued demolition of the 1970’s building.
ACM Sampling: ATC 1 0 Onsite abatement and demolition monitoring.
Site Work: SiteTech 0 0
General Trades: Excel/ HSI 1FC 1JC
1JL
Demolition of ceilings and walls in the old Library area for
construction of temporary weather wall (now exposed to
outside).
Masonry: Grande Masonry 0 0
Mechanical: Arden 0 0
Plumbing: Arden 0 0
Electrical: Rossi 0 1JE Electrical demolition in the old Library area.
Fiber/ Trench: TeleNetworks 0 0
MDF Terminations: American
TeleConnect
0 0
Security System: Sonitrol 0 0
Wood Floors: O’Sullivan Flooring 0 0
TOTAL PEOPLE ON SITE:8 7
DAILY CONSTRUCTION REPORT
Page 2
Problems Encountered: Photo
Discussions:
Name & Title Description:
Safety Items / Violations or Notices Issued: None
Equipment & Utilization of EquipmentDescription: Used/Parked/Service
SiteCon: Bobcat skid steer, 2 Komatsu Excavators, Hyundai Loader, Boom lift Used
Request for Information Sent (RFI’s) #’s: RFI #00023 submitted by Gilbane.
Observations
Demo/ Abatement Contractor: SiteCon – Continued with major demolition of the 1970’s building.
DAILY CONSTRUCTION REPORT
Page 3
Demo/ Abatement Contractor: SiteCon – Continued with major demolition of the 1970’s building.
DAILY CONSTRUCTION REPORT
Page 4
General Trades: Excel/ HIS - Demolition of ceilings and walls in the old Library area for construction of temp weather
wall (now exposed to outside).
DAILY CONSTRUCTION REPORT
Page 1
Project: Lincoln Public Schools Date: October 3, 2018
Lincoln High School - Enabling Phase
Construction Representative: Daniel M. Daisy Time: 7:00/ 12:00/ 4:00
Cell Phone: 401.500.0117 Weather: Cloudy- light rain / Cloudy/ Mostly cloudy
Temperature Range: 64 / 62/ 66 degrees
Winds: N6/ NE7/ NE8 mph
Hours on Site: IN: 7:00 a.m. OUT: 4:00 p.m.
# on Job Site
PROJECT ACTIVITIES
SUMMARY:
Lead/
Foreman Other Activities Completed
OPM: Colliers International 1CR
1PM
0 Daniel Daisy onsite all day – construction monitoring.
Charlie Roberts onsite in the a.m.
Architect: SMMA 0 0
Construction Manager:
Gilbane
(Superintendent: Paul Bertelli)
1S
0
Paul Bertelli onsite all day – Subcontractor Supervision and
coordination.
Demo/ Abatement Contractor:
SiteCon
1FL 1JE
3JL
Continued demolition of the 1970’s building.
ACM Sampling: ATC 1 0 Onsite abatement and demolition monitoring.
Site Work: SiteTech 0 0
General Trades: Excel/ HSI 1FC 1JL
1JC
Continued construction of temp weather wall in the old
library. Metal stud framing and DensGlass sheathing
being installed.
Masonry: Grande Masonry 0 0
Mechanical: Arden 0 0
Plumbing: Arden 0 0
Electrical: Rossi 0 0
Fiber/ Trench: TeleNetworks 0 0
MDF Terminations: American
TeleConnect
0 0
Security System: Sonitrol 0 0
Wood Floors: O’Sullivan Flooring 0 0
TOTAL PEOPLE ON SITE:6 6
Problems Encountered: Photo
DAILY CONSTRUCTION REPORT
Page 2
Discussions:
Name & Title Description:
Safety Items / Violations or Notices Issued: None
Equipment & Utilization of EquipmentDescription: Used/Parked/Service
SiteCon: Bobcat skid steer, 2 Komatsu Excavators, Hyundai Loader, Boom lift Used
Request for Information Sent (RFI’s) #’s: None
Observations
Demo/ Abatement Contractor: SiteCon – Continued with major demolition of the 1970’s building.
DAILY CONSTRUCTION REPORT
Page 3
Demo/ Abatement Contractor: SiteCon – Continued with major demolition of the 1970’s building.
DAILY CONSTRUCTION REPORT
Page 4
General Trades: Excel/ HIS – Continued construction of temp weather wall in the old library. Metal stud framing and
Densglass sheathing being installed.
DAILY CONSTRUCTION REPORT
Page 1
Project: Lincoln Public Schools Date: October 4, 2018
Lincoln High School - Enabling Phase
Construction Representative: Daniel M. Daisy Time: 7:00/ 12:00/ 4:00
Cell Phone: 401.500.0117 Weather: Cloudy / Cloudy/ Cloudy
Temperature Range: 60 / 70/ 69 degrees
Winds: SSW2/ SSW12/ S10 mph
Hours on Site: IN: 7:00 a.m. OUT: 4:00 p.m.
# on Job Site
PROJECT ACTIVITIES
SUMMARY:
Lead/
Foreman Other Activities Completed
OPM: Colliers International 1CR 0 Daniel Daisy onsite all day – construction monitoring.
Architect: SMMA 0 0
Construction Manager:
Gilbane
(Superintendent: Paul Bertelli)
1S
1PE
0
Paul Bertelli, Kristin Couto onsite all day – Subcontractor
Supervision and coordination. Tent (#4) installed in the N.
Gym.
Demo/ Abatement Contractor:
SiteCon
1FL 2JA
1JE
3JL
Continued demolition of the 1970’s building including
abatement of ACM roofing material at 1970’s connector.
ACM Sampling: ATC 1 0 Onsite abatement and demolition monitoring.
Site Work: SiteTech 0 0
General Trades: Excel/ HSI 1FC 1JC
1JL
Continued construction of temp weather wall in the old
library.
Masonry: Grande Masonry 0 1JM Cleaning up masonry debris from the low gym roof and
concession stand. Repointed small section of brick joint
above NE Gym exterior door.
Mechanical: Arden 0 0
Plumbing: Arden 0 0
Electrical: Rossi 0 0
Fiber/ Trench: TeleNetworks 0 0
MDF Terminations: American
TeleConnect
0 0
Security System: Sonitrol 0 0
Wood Floors: O’Sullivan Flooring 0 0
TOTAL PEOPLE ON SITE:6 9
Problems Encountered: Photo
DAILY CONSTRUCTION REPORT
Page 2
Discussions:
Name & Title Description:
Safety Items / Violations or Notices Issued: None
Equipment & Utilization of EquipmentDescription: Used/Parked/Service
SiteCon: Bobcat skid steer, 2 Komatsu Excavators, Hyundai Loader, Boom lift Used
Request for Information Sent (RFI’s) #’s: None
Observations
Demo/ Abatement Contractor: SiteCon – Continued with major demolition of the 1970’s building.
DAILY CONSTRUCTION REPORT
Page 3
Demo/ Abatement Contractor: SiteCon – Continued with major demolition of the 1970’s building.
DAILY CONSTRUCTION REPORT
Page 4
General Trades: Excel/ HIS – Continued construction of
temp weather wall in the old library. Metal stud framing
and DensGlass sheathing being installed on exterior and
batt insulation and GWB on the interior side.
DAILY CONSTRUCTION REPORT
Page 5
Masonry: Grande Masonry - Cleaning up masonry debris
from the low gym roof and concession stand.
DAILY CONSTRUCTION REPORT
Page 1
Project: Lincoln Public Schools Date: October 5, 2018
Lincoln High School - Enabling Phase
Construction Representative: Daniel M. Daisy Time: 7:00/ 12:00/ 4:00
Cell Phone: 401.500.0117 Weather: Fair / Fair/ Fair
Temperature Range: 54/ 62/ 61 degrees
Winds: N9/ NE14/ ENE10 mph
Hours on Site: IN: 7:00 a.m. OUT: 4:00 p.m.
# on Job Site
PROJECT ACTIVITIES
SUMMARY:
Lead/
Foreman Other Activities Completed
OPM: Colliers International 1CR 0 Daniel Daisy onsite all day – construction monitoring.
Charlie Roberts onsite in the a.m.
Architect: SMMA 0 0
Construction Manager:
Gilbane
(Superintendent: Paul Bertelli)
1S
1PE
0
Paul Bertelli, Kristin Couto onsite all day – Subcontractor
Supervision and coordination.
Demo/ Abatement Contractor:
SiteCon
1FL 2JA
1JE
3JL
Continued demolition of the 1970’s building.
ACM Sampling: ATC 1 0 Onsite abatement and demolition monitoring.
Site Work: SiteTech 0 0
General Trades: Excel/ HSI 1FC 1JC
1JL
Continued construction of temp weather wall in the old
library. Rolling primer DensGlass sheathing for BlueSkin
AVB installation on the weather side.
Masonry: Grande Masonry 0 0
Mechanical: Arden 0 0
Plumbing: Arden 0 0
Electrical: Rossi 0 0
Fiber/ Trench: TeleNetworks 0 0
MDF Terminations: American
TeleConnect
0 0
Security System: Sonitrol 0 0
Wood Floors: O’Sullivan Flooring 0 0
TOTAL PEOPLE ON SITE:6 8
Problems Encountered: Photo
DAILY CONSTRUCTION REPORT
Page 2
Discussions:
Name & Title Description:
Safety Items / Violations or Notices Issued: None
Equipment & Utilization of EquipmentDescription: Used/Parked/Service
SiteCon: Bobcat skid steer, 2 Komatsu Excavators, Hyundai Loader, Boom lift Used
Request for Information Sent (RFI’s) #’s: RFI #00024 submitted by Gilbane and responded to by SMMA.
Observations
Demo/ Abatement Contractor: SiteCon – Continued with major demolition of the 1970’s building.
DAILY CONSTRUCTION REPORT
Page 3
Demo/ Abatement Contractor: SiteCon – Continued with major demolition of the 1970’s building.
DAILY CONSTRUCTION REPORT
Page 4
General Trades: Excel/ HIS – Continued construction of temp weather wall in the old library. Rolling primer DensGlass
sheathing for BlueSkin AVB installation on the weather side.