2016 Engin. Office J. Gnädinger - All rights reserved
JG Ingenieurbüro
1
COCO Scope & Cost Management System the proven way to improve your returns
Scope Mgmt 1 (March 2016): Methodology to apply EVM
Scope Mgmt 2 (February 2017): Why and how it works
Early Warning System in the age of digital transformation
Key performance indicators to take corrective actions in advance
10. Oracle Primavera Community Day 15. February 2017 Munich
Presentation: Hännes Gnädinger
2016 Engin. Office J. Gnädinger - All rights reserved
JG Ingenieurbüro
2
Scope Mgmt 1 (March 2016): Methodology to apply EVM
Primavera P6
Make use of the potential of Scope & Cost Management with P6
Forecast
Scope & Cost Management
The PwC survey
In companies where EVM tools are used, projects meet their scope criteria
82% of the time, quality criteria 84% of the time and benefits targets 80% of
the time.
2016 Engin. Office J. Gnädinger - All rights reserved
JG Ingenieurbüro
3
COCO - Elevator Speech
The COCO Scope & Cost Management System supports the project
team in order to make the right decisions in time and thereby keep
or even improve the project returns.
The intelligent scope management determines the scope in the
acquisition phase and links it to responsibility, costs, scheduling and
documents. It reduces the complexity through the interface-optimized
cutting of a complex plant into manageable areas and by generating the
purchasing packages for planning and control.
The paradigm shift “plan in tendering to proactively control in
execution" significantly improves the cost and time performance
measurement. The causes of deviations from the baseline are recognized
at an early stage, the time and costs effects are transparent and the
project team is in a position to initiate course corrections in time.
2016 Engin. Office J. Gnädinger - All rights reserved
JG Ingenieurbüro
4
Different data structures
Different tools
Challenge: Eliminate the breaks
Today Execution Offering Project-Acquisition Negotiation
Tools Tools Tools
Bid decision
Contract
Start
Handover
Acceptance
Acquisition Team Tendering Team Execution Team
Bid out
Go / No Go
How do we eliminate breaks?
Industry 4.0
Collaboration Platform
Common Tools
Execution Offering Negotiation Project-Acquisition Operation
COCO Scope & Cost
Management
Optimized Project Controls
2016 Engin. Office J. Gnädinger - All rights reserved
JG Ingenieurbüro
5
COCO Methodology: Ensure the flow of information
Knowledge
library
Standardized
proven
solutions
Digital Plant
Collaboration
Platform
Project Controls
Scope & Cost
Structures to
consolidate cost,
plan baselines,
control progress
and manage
changes
The early warning
system
Cost & Time
Performance
Indicators
Visualized performance,
trend and forecast Engineering Portal
Execution Acquisition
Common Tools
Project controls is based on the collaboration platform, which includes the data structures
and the design rules, supported by common tools in the age of digital transformation.
2016 Engin. Office J. Gnädinger - All rights reserved
JG Ingenieurbüro
6
Project Completeness & Progress
The international coding standards
such as KKS or IEC ensure reuse of
proven solutions and worldwide
interdisciplinary collaboration.
Structuring: Achieve your goals
COCO provides the project structures
to optimize the Division of Work, plan
baseline, control progress, and manage
changes.
Project Performance
Object Goal Time & Cost Goals
Procurement plan (home / local)
Area Fuel
Equipment
Pump Units
Cost Drivers
Scope Items
Area Water
Parts
Work Package
Doc Set
€
Project Controls Collaboration Platform
2016 Engin. Office J. Gnädinger - All rights reserved
JG Ingenieurbüro
7
Collaboration platform: Rubber bands
Work Package
Purchase Order
12xRing Type CT
3xOutdoor CT
Key Doc target dates
Import baseline
planning
Cost baseline – Follow up Scope – DOW – Time baseline
Document planning & control
Completeness tracking Progress tracking
Bill of quantity
Engineering
Area
Area
2016 Engin. Office J. Gnädinger - All rights reserved
JG Ingenieurbüro
8
Collaboration: Anybody has access with his view
View: Division of Work
Engineering responsibility
Scope Items
Area responsibility
Scope Items
View: Construction
Areas
Scope Items
Documents
Objects / Parts
Views: Engineering
Function / Product / Location
Scope Items
Cost Drivers
Documents & Target dates
Objects / Parts
Engineer Standards e.g. • KKS Reference designation
• IEC 61355 Document designation
View: Calculation / Procurement
Procurement Plans (home – local)
Work Packages (PSP Elements)
PO-Positions (execution)
Scope Items
Documents & Target dates
Objects / Parts
Knowledge library
Reuse of proven solutions
80%
60%
20%
Reusing factor
Core area
2016 Engin. Office J. Gnädinger - All rights reserved
JG Ingenieurbüro
9
Project Controls: PC is always based on CP
Execution Acquisition Operation
Development
Proven solutions
Deconstruction
PC PC PC Project Controls
Project
Collaboration Platform
Projects Project
Reuse PC CP Lessons
learned
Customer A
Modularization / Standardization
Project cost & time KPIs,
trend and forecast Engineering
Portal
KPIs (CPI / SPI): Key Performance Indicators (Cost / Schedule); CP: Collaboration Platform; PC: Project Controls
2016 Engin. Office J. Gnädinger - All rights reserved
JG Ingenieurbüro
10
Efficiency: Plan in tendering to control in execution
PAC: Preliminary Acceptance Certificate; CPI: Cost Performance Indicator: SPI: Schedule Performance Indicator
Scope
Quality
Time Cost
CPI SPI
Progress
Time Cost
Forecast
Work Package Configure to
calculate for ordering
Scope Item
Seamless handover
Doc Package
Customer
request
800 Scope Items ~100 Work Packages
Design concepts
Configure scope
Allocate responsibility
Control the project
Plan & manage changes
Evaluate performance
Calculate quantity & cost
Plan cost, time, documents
Execution Tendering Project-Acquisition
Bid decision Cost / Risk release Contract PAC Periodic reviews Go / No Go
Operation
2016 Engin. Office J. Gnädinger - All rights reserved
JG Ingenieurbüro
11
Example: Scope – Cost relationship
1 Project management services
2 Engineering services
2.1 Studies & Concepts
2.1.1 Overall Concepts
Fire protection concept A1
2.2 Systems & Layout
2.2.1 Mechanical Systems
Fuel Supply A1
2.3 Equipment Engineering
2.3.1 Mechanical Equipment
Tanks, Pumps, … A1
3 Plant automation
4 Commissioning/Testing/Training
Areas fuel supply
Tank farm
Equipment A2
Bulk Material A2
Civil Works A3
Erection A4
Areas water supply
Fire water supply
…….
Scope configuration
Procurement Plan A1: Services
Mech. engin.: h 10’000 € 300’000
Fire prot. … h 200
Fuel supply h 3000
Tank engin. h 1000
Pump engin. h 2000
…. engin. h …
E&I engin.: h 7’000 € 210’000
…. engin. h ….
Procurement Plan A2: Supplies
Procurement Plan A3: Civil Works
Procurement Plan A4: Erection
Work package consolidation
Scope-Items
Procurement
Plan
2016 Engin. Office J. Gnädinger - All rights reserved
JG Ingenieurbüro
12
Reporting: Consolidate performance bottom-up
Project
Work Packages
Scope Items
Parts
Current performance, trend, forecast
Budget, Cost & Schedule KPIs
% complete scheduled vs. performed
Completeness of supplies
Procurement Plans
(home / local)
Progress of services
Number (recommended)
1
<10
~ 100
~ 800
Current performance, trend, forecast
Planned Key Doc’s
supplies services
Project Scope
Cost & Schedule Performance
Cost
Scope
2016 Engin. Office J. Gnädinger - All rights reserved
JG Ingenieurbüro
13
Portal: Navigate down to the causes of deviations I/II
Navigation Multi Projects
Procurement Plan: Region Work Packages
Project: C
Causes of deviations
2016 Engin. Office J. Gnädinger - All rights reserved
JG Ingenieurbüro
14
Performance Reporting DB
%
scheduled
%
performed
SPI
%
performed
CPI
Actual
committed
Cost SPI CPI
Estimate
to complete
Cost
+ Savings
-Overrun
Project 112 250 000 € 66% 59% 62% 62 000 000 € 0.89 1.13 42 250 000 € 8 000 000 €
510 000 € 66% 57% 65% 290 000 € 0.88 1.15 176 100 € 43 900 €
Engineering ME 300 000 € 100% 64% 55% 63% 160 000 € 0.86 1.18 111 000 € 29 000 €
System 90 000 € 30% 26% 22% 22%
Tank 30 000 € 10% 6% 6% 8%
Pump 60 000 € 20% 12% 12% 18%
…. 120 000 € 40% 20% 15% 15%
Engineering EL 210 000 € 100% 68% 61% 69% 130 000 € 0.90 1.11 65 100 € 14 900 €
Weight
Review 4Budget
at
completion
Services Region
Portal: Navigate down to the causes of deviations II/II
Work Package Mech. Engineering
Work Packages Supplies Work Packages Services
Performance Reporting DB
%
scheduled
%
performed
SPI
%
performed
CPI
Actual
committed
Cost SPI CPI
Estimate
to complete
Cost
+ Savings
-Overrun
Project 112 250 000 € 66% 59% 62% 62 000 000 € 0.89 1.13 42 250 000 € 8 000 000 €
Supplies Region 12 200 000 € 59% 50% 54% 6 900 000 € 0.85 0.95 5 612 000 € -312 000 €
BB.1 Tanks 1 300 000 € 100% 92% 61% 69% 980 000 € 0.66 0.92 403 000 € -83 000 €
EG-BB Tanks 1 200 000 € 92% 92% 61% 61%
Volume
SG-BB Tank 100 000 € 8% 0% 8%
Volume
………. … …… …… …….. …… …… …. …. …… ……
Budget at
completion
Weight
Review 4
Weight Scheduled
Performed
SPI
Performed
CPI
PO Date
Scheduled PO PO-Pos. PO Date
BB.1 Tanks 100% 92% 61% 69%
EG-BB Tanks 92% 92% 61% 61%
EG10BB001 Tank 18.10.2016 2016-101 -10 18.10.2016
EG10BB002 Tank 18.10.2016 2016-101 -10 18.10.2016
EG10BB003 Tank 18.10.2016
SG-BB Tank 8% 0% 8%
SGA10BB001 Tank 12.03.2017 2016-101 -20 18.10.2016
% Complete Expediting Data Base
Review 4
Work Package Tanks
Target Received
Date Date Weight Scheduled
Performed
SPI
Performed
CPI
Engineering ME 100% 64% 55% 63%
System 30% 26% 22% 22%
P&ID 1st issue 02.08.16 05.08.16
P&ID 2nd issue 02.11.16
P&ID final 28.02.17
Tank 10% 6% 6% 8%
Enquiry- Spec. 12.09.16 08.09.16
Purchase Order Lot 1 18.10.16 17.10.16
Purchase Order Lot 2 12.03.17 17.10.16
Packing List Lot 1 09.02.17
Packing List Lot 2 06.04.17
Pump 20% 12% 12% 18%
…. 40% 20% 15% 15%
Planning & ControlReview 4
% Complete
2016 Engin. Office J. Gnädinger - All rights reserved
JG Ingenieurbüro
15
Performance Reporting DB
Unit Value
Unit
Cost Rate
%
scheduled
Planned
Value
%
performed
SPI
%
performed
CPI
Earned
Value
SPI
Earned
Value
CPI
Actual
committed
Cost SPI CPI
Estimate
to complete
Cost
+ Savings
-Overrun
Project 112 250 000 € 66% 74 000 000 € 59% 62% 66 000 000 € 70 000 000 € 62 000 000 € 0.89 1.13 42 250 000 € 8 000 000 €
510 000 € 66% 334 800 € 57% 65% 293 100 € 333 900 € 290 000 € 0.88 1.15 176 100 € 43 900 €
Engineering ME h 10 000 30 € 1.00 300 000 € 100% 64% 192 000 € 55% 63% 165 000 € 189 000 € 160 000 € 0.86 1.18 111 000 € 29 000 €
System h 3 000 30 € 1.00 90 000 € 30% 26% 22% 22%
Tank h 1 000 30 € 1.00 30 000 € 10% 6% 6% 8%
Pump h 2 000 30 € 1.00 60 000 € 20% 12% 12% 18%
…. h 4 000 30 € 1.00 120 000 € 40% 20% 15% 15%
Engineering EL h 7 000 30 € 1.00 210 000 € 100% 68% 142 800 € 61% 69% 128 100 € 144 900 € 130 000 € 0.90 1.11 65 100 € 14 900 €
System h 2 000 30 € 1.00 60 000 € 29% 22% 22% 22%
Transformer h 1 000 30 € 1.00 30 000 € 14% 8% 8% 8%
Switchgear h 1 500 30 € 1.00 45 000 € 21% 12% 12% 16%
…. h 2 500 30 € 1.00 75 000 € 36% 26% 20% 20%
Weight
Review 4Review 4Budget
at
completion
Services Region
Example: WP’s Engineering / Construction Services
Work Packages
•ERP (home)
Scope Items % complete
•Primavera P6
Quantity monitoring construction services
•Progress reports
Work Packages
•ERP’s (home/local)
2016 Engin. Office J. Gnädinger - All rights reserved
JG Ingenieurbüro
16
Performance Reporting DB
Unit Value
Unit
Cost Rate
%
scheduled
Planned
Value
%
performed
SPI
%
performed
CPI
Earned
Value
SPI
Earned
Value
CPI
Actual
committed
Cost SPI CPI
Estimate
to complete
Cost
+ Savings
-Overrun
Project 112 250 000 € 66% 74 000 000 € 59% 62% 66 000 000 € 70 000 000 € 62 000 000 € 0.89 1.13 42 250 000 € 8 000 000 €
Supplies Region 12 200 000 € 59% 7 200 000 € 50% 54% 6 100 000 € 6 588 000 € 6 900 000 € 0.85 0.95 5 612 000 € -312 000 €
AA.1 Valves Set 2 25 000 € 1.00 50 000 € 100% 100% 50 000 € 100% 100% 50 000 € 50 000 € 45 000 € 1.00 1.11 0 € 5 000 €
EG-AA Valves Set 1 30 000 € 1.00 30 000 € 60% 60% 60% 60%
SG-AA Valves Set 1 20 000 € 1.00 20 000 € 40% 40% 40% 40%
BB.1 Tanks Pcs 4 325 000 € 1.00 1 300 000 € 100% 92% 1 196 000 € 61% 69% 793 000 € 897 000 € 980 000 € 0.66 0.92 403 000 € -83 000 €
EG-BB Tanks Pcs 3 400 000 € 1.00 1 200 000 € 92% 92% 61% 61%
Volume m3 800
SG-BB Tank Pcs 1 100 000 € 1.00 100 000 € 8% 0% 8%
Volume m3 100
………. Pcs .. … .. … …… …… …….. …….. …… …….. …….. …… …. …. …… ……
….. ….. … …. … … …. …. …. …. …. …. ….
Budget at
completion
Weight
Review 4Review 4
Example: Work Packages Supplies
Scope Items % complete
•Procurement DB
Work Packages
•ERP (home)
Work Packages
•ERP’s (home/local)
2016 Engin. Office J. Gnädinger - All rights reserved
JG Ingenieurbüro
17
Why COCO gets the buy-in from the stakeholders
Project Management is able to navigate "top-down" to the causes of deviations.
Scheduling is able to plan the baseline and to control changes proactively.
Controlling is able to manage the work packages (PSP elements) in relation to
the physical progress and changes.
Document & Quality Management is able to track progress and ensure data
consistency.
Engineering Management is able to collaborate globally and interdisciplinary
and to consolidate physical progress across the work packages.
Procurement Management is able to optimize sourcing and to track
completeness.
Construction Management will get material and documents in time to the
scheduled site areas.
COCO improves returns sustainably in the age of digital transformation.
2016 Engin. Office J. Gnädinger - All rights reserved
JG Ingenieurbüro
18
Ingenieurbüro Johannes Gnädinger
Lindenhof 22 CH-5430 Wettingen
Mobile CH: +41 (0)79 252 23 48
Mobile DE: +49 (0)151 40 258 786
Büro- und Managementservice Brigitte Jahn [email protected]