Upload
others
View
3
Download
0
Embed Size (px)
Citation preview
Timeline… to date
July 2008
•Kempsey Bypass approved for construction by NSW Minister for Planning
2009 •Stakeholder focus group convened by KSC to prepare Background Issues Paper on bypass
June 2010
•Final Report on Bypass Issues delivered to KSC
July 2010
•KSC internal consultative group convened to develop a comprehensive Bypass Strategy
March 2011
•KSC Bypass Strategy placed on Public Exhibition
May 2011
•KSC Bypass Strategy adopted
July 2011
•Bypass Coordinator appointed and Strategy Implementation Program prepared
Bypass Strategy
Entry Gateways and Signage
Political Engagement
Assets
Future Kempsey
Innovation Strategy
Marketing Strategy
Place Based Promotions
Urban Design - Masterplanning
Community Events
Infrastructure Plans
Consultation Program
Development Control Plans
Economic Strategy
THE ROLE OF THE BYPASS COORDINATOR
Successfully coordinate Council’s strategic response to the implications associated with the Pacific Highway Bypass
Assist in developing positive relationships and partnerships with the Kempsey
community through sound communication and consultation on the implementation of the Bypass Strategy
Provide a responsive and achievable urban design model for Kempsey town
centre and the villages of South Kempsey and Frederickton
KEY FACTORS
1. Public Consultation and Participation
2. Development of the Corridor Master Plan
3. Preparation of detailed precinct designs
Public Consultation
and Feedback
Newsletters
Fact Sheets
Workshops
Bypass Information
Group
Market Stalls
Interviews
Media Releases
Questionnaire and Surveys
THE CORRIDOR MASTER PLAN Looking at the bigger picture : good urban design
• Creating an intersection of landscape architecture, infrastructure engineering, urban business economics and planning
• Preparation of draft master plan covering South Kempsey, Kempsey and Frederickton and adjoining corridor linkages
• Ensures a comprehensive approach to infrastructure planning and execution of works within the Corridor into the future
• Blueprint to further direct the precinct design program
• Foundation document to assist in attracting Commonwealth and State funding to support future construction programs
PRECINCT DESIGN Making it work: getting the detail right
• Informed by the master plan, detail designs prepared for South Kempsey, Kempsey and Frederickton
• Selection of materials, finishes, and planting plans
determined • Preparation of construction documentation.
PUBLIC CONSULTATION AND PARTICIPATION
Stage
Activity Timeframe
1. Understanding the project, community values, aspirations and interests
• Project website • Community surveys • Bypass Information Group [BIG1] • Stakeholder interviews • Community conversations [Oct/Nov] • Newsletter/fact Sheet #1
August – November 2011
2. Master plan development - options and concepts
• BIG2 [early Feb 2012] • Newsletter / Fact Sheet #2 • Website update • Community conversations [present options]
March 2012
December 2011 – March 2012
3. Finalisation of master plan • BIG3 [May] • Additional meeting with key stakeholders • Public exhibition of draft master plan • Website updated
April – June 2012
Draft Consultation Program August 2011 – June 2012
PUBLIC CONSULTATION AND PARTICIPATION
Stage
Activity Timeframe
1. Precinct design development – options and concepts
• BIG4 [July 2012] • Newsletter #3 • Update website
July – Sept 2012
2. Precinct design development - detailed • BIG5 [Dec 2012] • Display final precinct designs • Update website
October – December 2012
3. Finalisation of precinct designs • BIG6 [April 2013] • Newsletter #4 • Update website • BIG7 [June 2013] • Community signoff [June 2013]
January – June 2013
Draft Consultation Program July 2012 – June 2013
THE CORRIDOR MASTER PLAN
Stage
Activity Timeframe
1. Understanding the project; community values, aspirations and interests
• Define scope and working budget • Review existing documentation and identify
gaps • Develop community survey and fact sheet
August – November 2011
2. Master plan development – options and concepts
• Prepare outline plan and analysis • Prepare concept options • Prepare preliminary estimates of total project
cost • Prepare preferred options to present to public
December – March 2012
3. Finalisation of master plan • Prepare firmer estimates of TPC • Prepare final draft master plan based on
preferred option • Place master plan on public exhibition • Adopt master plan
April - June 2012
Draft Master Plan Program August 2011 – June 2012
PRECINCT DESIGN
Stage
Activity Timeframe
1. Precinct design development – options and concepts
• Establish scope of design, resources TPC and budget
• Prepare concept design for each precinct • Select preferred option for each precinct
July – September 2012
2. Precinct Design development - details • Develop schedule of materials and finishes • Prepare detail documentation • Prepare final construction estimates • Prepare final precinct design drawings and
place on display
October – December 2012
3. Finalisation of Precinct designs • Prepare construction documentation of each final precinct design
• Undertake planning for the preparation of plans of management for key public open space within the corridor
January – June 2013
Draft Precinct Design Program July 2012 – June 2013