Time Cost Trade-off

Ahmed Elyamany, PhD

1

Page 2: Time Cost Trade-offdrahmedelyamany.weebly.com/uploads/7/0/1/0/7010103/... · Time Cost Trade-off ... of a project will result in excessive project duration. 2. Time Reduction

Time Reduction / Crashing

The first trial of the scheduling of a project will result in

excessive project duration.

2

Page 3: Time Cost Trade-offdrahmedelyamany.weebly.com/uploads/7/0/1/0/7010103/... · Time Cost Trade-off ... of a project will result in excessive project duration. 2. Time Reduction

Time Reduction / Crashing

Sometimes, there is a need to reduce project time to meet contractual requirements.

3

Page 4: Time Cost Trade-offdrahmedelyamany.weebly.com/uploads/7/0/1/0/7010103/... · Time Cost Trade-off ... of a project will result in excessive project duration. 2. Time Reduction

Time Reduction / Crashing

Critical path shows the activities that must be

examined to reduce the project duration.

4

Page 5: Time Cost Trade-offdrahmedelyamany.weebly.com/uploads/7/0/1/0/7010103/... · Time Cost Trade-off ... of a project will result in excessive project duration. 2. Time Reduction

Time Reduction / Crashing

Reducing activity time is usually called “crashing”

The aim of crashing is to reduce the time with

minimum cost.

5

Page 6: Time Cost Trade-offdrahmedelyamany.weebly.com/uploads/7/0/1/0/7010103/... · Time Cost Trade-off ... of a project will result in excessive project duration. 2. Time Reduction

When Time Reduction / Crashing is needed?

6

Page 7: Time Cost Trade-offdrahmedelyamany.weebly.com/uploads/7/0/1/0/7010103/... · Time Cost Trade-off ... of a project will result in excessive project duration. 2. Time Reduction

When time reduction is needed?

�To meet a contractual project completion date.

�To avoid liquidated damages

�To avoid adverse weather

�To move labor and equipment to another location

�To cover a delay by the end of the project

7

Page 8: Time Cost Trade-offdrahmedelyamany.weebly.com/uploads/7/0/1/0/7010103/... · Time Cost Trade-off ... of a project will result in excessive project duration. 2. Time Reduction

Reduce Project Time with No Cost

•Restudy critical activities

•Accomplish critical activities in parallel

•Subdivision of critical activities

•Subcontracting

8

Page 9: Time Cost Trade-offdrahmedelyamany.weebly.com/uploads/7/0/1/0/7010103/... · Time Cost Trade-off ... of a project will result in excessive project duration. 2. Time Reduction

Reduce Project Time with Cost Increase

If those items did not work, we may have to reduce

project time by increasing project cost

9

Page 10: Time Cost Trade-offdrahmedelyamany.weebly.com/uploads/7/0/1/0/7010103/... · Time Cost Trade-off ... of a project will result in excessive project duration. 2. Time Reduction

Time-Cost relationships

•The direct cost of an activity vary with time

•Normal cost: • is the least direct cost required to complete that activity and it is the cost estimated to finish the work during bidding stage.

•Normal duration: • is the activity duration determined during scheduling stage.

10

Page 11: Time Cost Trade-offdrahmedelyamany.weebly.com/uploads/7/0/1/0/7010103/... · Time Cost Trade-off ... of a project will result in excessive project duration. 2. Time Reduction

Time-Cost relationships

•Crashing time: • is the minimum time to which an activity can be reduced.

•Crashing cost: • is the corresponding direct cost for the crashing time.

•Cost slope: • is the increase in activity direct cost per day.

11

Page 12: Time Cost Trade-offdrahmedelyamany.weebly.com/uploads/7/0/1/0/7010103/... · Time Cost Trade-off ... of a project will result in excessive project duration. 2. Time Reduction

Activity Direct Cost

12

Activity

Duration

Act

ivit

y D

irec

t C

ost Crash

cost

Normal

cost

Crash

time

Normal

time

Crash

point

Normal

point

�������� =(�� ������ − ���� �����)

(���� ���� − �� �����)

Page 13: Time Cost Trade-offdrahmedelyamany.weebly.com/uploads/7/0/1/0/7010103/... · Time Cost Trade-off ... of a project will result in excessive project duration. 2. Time Reduction

Project Indirect Cost

•Indirect cost is the cost incurred in support of the site work but it can not be associated with any particular physical portion of the job.

•The indirect cost is directly related to project time

13Project Duration

Act

ivit

y i

ndir

ect

Cost

Page 14: Time Cost Trade-offdrahmedelyamany.weebly.com/uploads/7/0/1/0/7010103/... · Time Cost Trade-off ... of a project will result in excessive project duration. 2. Time Reduction

Project Total Cost

•If the duration of a specific activity is reduced or crashed:

• Direct expenses increases

• Overall project duration decreases

• Indirect cost is reduced

14

Optimum

Duration

Act

ivit

y T

ota

l C

ost

Project Duration

Optimum

Cost

Page 15: Time Cost Trade-offdrahmedelyamany.weebly.com/uploads/7/0/1/0/7010103/... · Time Cost Trade-off ... of a project will result in excessive project duration. 2. Time Reduction

Procedure for Crashing

Least Cost Method

has been developed to reduce project duration with the least

cost

15

Page 16: Time Cost Trade-offdrahmedelyamany.weebly.com/uploads/7/0/1/0/7010103/... · Time Cost Trade-off ... of a project will result in excessive project duration. 2. Time Reduction

Procedure for Crashing

Least Cost Method

It is based on the investigation of the network to indicate which

activities can be reduced at least cost when reducing project

duration.

16

Page 17: Time Cost Trade-offdrahmedelyamany.weebly.com/uploads/7/0/1/0/7010103/... · Time Cost Trade-off ... of a project will result in excessive project duration. 2. Time Reduction

Procedure for Crashing

Least Cost Method

Start crashing with activities that have lowest cost slope.

17

Page 18: Time Cost Trade-offdrahmedelyamany.weebly.com/uploads/7/0/1/0/7010103/... · Time Cost Trade-off ... of a project will result in excessive project duration. 2. Time Reduction

Example 1

18

Given Calculated

Activity Normal

Time

Crash

Time

Crash

Cost

Normal

Cost

Cost Slope

A 6 2 10,000 6,000 1000

B 5 3 20,000 16,000 2000

C 8 5 8,000 3,500 1500

D 6 5 10,000 6000 4000

Page 19: Time Cost Trade-offdrahmedelyamany.weebly.com/uploads/7/0/1/0/7010103/... · Time Cost Trade-off ... of a project will result in excessive project duration. 2. Time Reduction

Example 1

19

0 6

A

6

0 5

B

5

6 14

C

8

6 12

D

6

Start

0Finish

0

0 0 0 0

6 0 6 6 0 0

Page 20: Time Cost Trade-offdrahmedelyamany.weebly.com/uploads/7/0/1/0/7010103/... · Time Cost Trade-off ... of a project will result in excessive project duration. 2. Time Reduction

20

A = 1000

C = 1500

B = 2000

D = 4000

1 2 3 4 5 6 7 8 9 10 11 12 13 14

Original plan

Page 21: Time Cost Trade-offdrahmedelyamany.weebly.com/uploads/7/0/1/0/7010103/... · Time Cost Trade-off ... of a project will result in excessive project duration. 2. Time Reduction

21

A = 1000

C = 1500

B = 2000

D = 4000

1 2 3 4 5 6 7 8 9 10 11 12 13

Reduce 1 day from A = 1000

Page 22: Time Cost Trade-offdrahmedelyamany.weebly.com/uploads/7/0/1/0/7010103/... · Time Cost Trade-off ... of a project will result in excessive project duration. 2. Time Reduction

22

A = 1000

C = 1500

B = 2000

D = 4000

1 2 3 4 5 6 7 8 9 10 11

Reduce 2 days from C = 1500/day

Page 23: Time Cost Trade-offdrahmedelyamany.weebly.com/uploads/7/0/1/0/7010103/... · Time Cost Trade-off ... of a project will result in excessive project duration. 2. Time Reduction

23

A = 1000

C = 1500

B = 2000

D = 4000

1 2 3 4 5 6 7 8 9

Reduce 2 days from A&B = 3000/day

Page 24: Time Cost Trade-offdrahmedelyamany.weebly.com/uploads/7/0/1/0/7010103/... · Time Cost Trade-off ... of a project will result in excessive project duration. 2. Time Reduction

24

Reduce 1 days from C&D = 5500/day

A = 1000

C = 1500

B = 2000

D = 4000

1 2 3 4 5 6 7 8

Page 25: Time Cost Trade-offdrahmedelyamany.weebly.com/uploads/7/0/1/0/7010103/... · Time Cost Trade-off ... of a project will result in excessive project duration. 2. Time Reduction

25

Step Activity Cost/day Days Cost

1 A 1000 1 1000

2 C 1500 2 3000

3 A&B 3000 2 6000

4 C&D 5500 1 5500

Total cost to crash project duration to 8 days 15,500

Page 26: Time Cost Trade-offdrahmedelyamany.weebly.com/uploads/7/0/1/0/7010103/... · Time Cost Trade-off ... of a project will result in excessive project duration. 2. Time Reduction

Example 2

26

Given

ActivityNormal Time

(weeks)

Crash Time

(weeks)

Normal

Cost (L.E.)Crash Cost

A 5 3 1000 1200

B 4 1 2000 2600

C 6 4 1500 2500

D 5 2 1200 1650

E 6 4 1600 2400

F 5 5 1600 1600

G 7 4 2500 3250

� The indirect cost is L.E. 500 per week.

� Project total cost is L.E. 45,000

� Calculate the optimal cost for this work and the corresponding

duration.

Page 27: Time Cost Trade-offdrahmedelyamany.weebly.com/uploads/7/0/1/0/7010103/... · Time Cost Trade-off ... of a project will result in excessive project duration. 2. Time Reduction

Example 2

27

Given Calculated

ActivityNormal Time

(weeks)

Crash Time

(weeks)

Normal

Cost (L.E.)Crash Cost Cost Slope

A 5 3 1000 1200 100

B 4 1 2000 2600 200

C 6 4 1500 2500 500

D 5 2 1200 1650 150

E 6 4 1600 2400 400

F 5 5 1600 1600 -

G 7 4 2500 3250 250

Page 28: Time Cost Trade-offdrahmedelyamany.weebly.com/uploads/7/0/1/0/7010103/... · Time Cost Trade-off ... of a project will result in excessive project duration. 2. Time Reduction

Example 2

28

0 5

A

5

5 9

B

4

9 15

C

6

15 20

D

5

0 0

Start

0

20 20

Finish

0

0 6

E

6

6 11

F

5

11 18

G

7

Page 29: Time Cost Trade-offdrahmedelyamany.weebly.com/uploads/7/0/1/0/7010103/... · Time Cost Trade-off ... of a project will result in excessive project duration. 2. Time Reduction

29

A

100 100 B

200 200 200 C

500 500 D

E 150 150 150

400 400 FG

250 250 250

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20

Original Network

Page 30: Time Cost Trade-offdrahmedelyamany.weebly.com/uploads/7/0/1/0/7010103/... · Time Cost Trade-off ... of a project will result in excessive project duration. 2. Time Reduction

30

Activity Crashed

weeks

Increased

Direct cost

Project

duration

Decreased

indirect cost

Variance in

project cost

Project

cost

A 1 100 19 500 -400 44,600

A 1 100 18 500 -400 44,200

D&G 1 400 17 500 -100 44,100

D&G 1 400 16 500 -100 44,000

D&G 1 400 15 500 -100 43,900

B&E 1 600 14 500 +100 44,000

B&E 1 600 13 500 +100 44,100

Page 31: Time Cost Trade-offdrahmedelyamany.weebly.com/uploads/7/0/1/0/7010103/... · Time Cost Trade-off ... of a project will result in excessive project duration. 2. Time Reduction

QuestionsQuestionsQuestionsQuestions