TIME AND COST CONTROLLING USING CRITICAL PATH METHOD (CASE STUDY AT PALUR FLY-OVER SURAKARTA) A THESIS Submitted as a Partial Fullfilment of the Requirements For the completion of Getting the Postgraduate Degree in Civil Engineering study Program Arranged by: Adel Issa Elsosan S 100130016 POSTGRADUATE PROGRAM DEPARTMENT OF CIVIL ENGINEERING UNIVERSITAS MUHAMMADIYAH SURAKARTA 2015

TIME AND COST CONTROLLING USING CRITICAL PATH A THESISeprints.ums.ac.id/40049/2/00.Depan.pdf · TIME AND COST CONTROLLING USING CRITICAL PATH METHOD (CASE STUDY AT PALUR FLY-OVER

  • Upload
    others

  • View
    6

  • Download
    0

Embed Size (px)

Citation preview

Page 1: TIME AND COST CONTROLLING USING CRITICAL PATH A THESISeprints.ums.ac.id/40049/2/00.Depan.pdf · TIME AND COST CONTROLLING USING CRITICAL PATH METHOD (CASE STUDY AT PALUR FLY-OVER

TIME AND COST CONTROLLING USING CRITICAL PATH

METHOD (CASE STUDY AT PALUR FLY-OVER SURAKARTA)

A THESIS

Submitted as a Partial Fullfilment of the Requirements

For the completion of Getting the Postgraduate Degree in Civil Engineeringstudy Program

Arranged by:

Adel Issa Elsosan

S 100130016

POSTGRADUATE PROGRAM

DEPARTMENT OF CIVIL ENGINEERING

UNIVERSITAS MUHAMMADIYAH SURAKARTA

2015

Page 2: TIME AND COST CONTROLLING USING CRITICAL PATH A THESISeprints.ums.ac.id/40049/2/00.Depan.pdf · TIME AND COST CONTROLLING USING CRITICAL PATH METHOD (CASE STUDY AT PALUR FLY-OVER

ii

TIME AND COST CONTROLLING USING CRITICAL PATH

METHOD (CASE STUDY AT PALUR FLY-OVER SURAKARTA)

A THESIS

Submitted as a Partial Fullfilment of the Requirements

For the completion of Getting the Postgraduate Degree in Civil Engineeringstudy Program

Arranged by:

Adel Issa Elsosan

S 100130016

POSTGRADUATE PROGRAM

DEPARTMENT OF CIVIL ENGINEERING

UNIVERSITAS MUHAMMADIYAH SURAKARTA

2015

Page 3: TIME AND COST CONTROLLING USING CRITICAL PATH A THESISeprints.ums.ac.id/40049/2/00.Depan.pdf · TIME AND COST CONTROLLING USING CRITICAL PATH METHOD (CASE STUDY AT PALUR FLY-OVER
Page 4: TIME AND COST CONTROLLING USING CRITICAL PATH A THESISeprints.ums.ac.id/40049/2/00.Depan.pdf · TIME AND COST CONTROLLING USING CRITICAL PATH METHOD (CASE STUDY AT PALUR FLY-OVER
Page 5: TIME AND COST CONTROLLING USING CRITICAL PATH A THESISeprints.ums.ac.id/40049/2/00.Depan.pdf · TIME AND COST CONTROLLING USING CRITICAL PATH METHOD (CASE STUDY AT PALUR FLY-OVER
Page 6: TIME AND COST CONTROLLING USING CRITICAL PATH A THESISeprints.ums.ac.id/40049/2/00.Depan.pdf · TIME AND COST CONTROLLING USING CRITICAL PATH METHOD (CASE STUDY AT PALUR FLY-OVER
Page 7: TIME AND COST CONTROLLING USING CRITICAL PATH A THESISeprints.ums.ac.id/40049/2/00.Depan.pdf · TIME AND COST CONTROLLING USING CRITICAL PATH METHOD (CASE STUDY AT PALUR FLY-OVER
Page 8: TIME AND COST CONTROLLING USING CRITICAL PATH A THESISeprints.ums.ac.id/40049/2/00.Depan.pdf · TIME AND COST CONTROLLING USING CRITICAL PATH METHOD (CASE STUDY AT PALUR FLY-OVER

vii

ABSTRACT

ABSTRACT-The purpose of this study is to (1.To analyze the remaining work itemsat month of 14th from the project starts, 2). To analyze the remaining cost items at month of14th after the project start. And the last is 3). To reschedule and to optimize the time and costby use Critical Path Method (CPM).

This study will analyze time and cost controlling by using CPM approach on theproject. Based on the background of the study, the statements of the problems can beformulated as follows: (1) How is rescheduling in optimization of time on Palur Fly over ofSurakarta by using Critical Path Method (CPM)? and (2) How is the implement of the normaland the crash of the cost on Palur flyover in Surakarta by using Critical Path Method (CPM)?.The writer analyzed the fly-over project implementation fly over Palur in Surakarta whetheraccording to the time plan. By rescheduling the plan and make optimization of time andminimizing cost with CPM (Critical Path Method).

Based on the result and discussion, the conclusion of this research as follows: Theimplementation of the project is not in accordance with the plan, it is too late because of theweather and can be solved by increasing the valve of workers. Based on the reschedulingalternatives can be implemented as the alternative I with 160 days shorter and the rest of costRp 32.556.381.150

Keywords: Critical Path Method (CPM), Project Management, Time Control, and Costcontrol.

Page 9: TIME AND COST CONTROLLING USING CRITICAL PATH A THESISeprints.ums.ac.id/40049/2/00.Depan.pdf · TIME AND COST CONTROLLING USING CRITICAL PATH METHOD (CASE STUDY AT PALUR FLY-OVER

viii

ACKNOWLEDGEMENT

Bismillahirrahmaanirrahiim

Assalaamu’alaikum wr.wb.

Alhamdulillahirrahmaanirrahiim, praise and gratitude to the most Merciful Allah

Ta’ala, for blessing the writer in finishing this Thesis entitled TIME AND COST

CONTROLLING USING CRITICAL PATH METHOD (CASE STUDY

AT PALUR FLY-OVER SURAKARTA) as one of the requirement for getting the

Postgraduate Degree in Civil Engineering Program. The researchers do not forget to praise to

the messenger, our prophet Muhammad S A W, and his followers.

The writer really realizes that he cannot finish this research because of great attention,

motivation, material, and support given by his parents, relatives, beloved ones, friends, and

others. In addition, the writer also thanks much to the people who helped him to complete this

research paper. Therefore, the writer wants to dedicatee his sincerest gratitude for all them.

The writer would like to express his appreciation to those ones. They are: Nurul

Hidayati, ST, MT., Ph.D, as the Head of Magister of Civil Engineering Study. The next is

Mohamad Solikin, PhD, as the first consultant for his kindness in guiding, helping, teaching

to the writer and also Ir. M. Muh Nursahid, M.M., M.T as the second consultant for his

patience in guiding the writer to complete this thesis. With the third examiner Sri Sunarjono,

Ph.D from the buttonm of his hearth, the writer would like to devote his everlasting mercy

and thanks so much for your time besides precautio.

NO workcan be done perfectly , nor can this research paper. The witer expects that

this research paper will become useful for the development of academic study and following

research.

Wassalaamu’alaikum wr.wb. Surakarta...................................................

Page 10: TIME AND COST CONTROLLING USING CRITICAL PATH A THESISeprints.ums.ac.id/40049/2/00.Depan.pdf · TIME AND COST CONTROLLING USING CRITICAL PATH METHOD (CASE STUDY AT PALUR FLY-OVER

ix

TABLE OF CONTENT

THE TITTLE OF THE RESEARCH ................................................................... i

APPROVAL.......................................................................................................... iii

NOTE OF ADVISOR I ......................................................................................... iv

NOTE OF ADVISOR II ........................................................................................ v

THESIS STATEMENT OF AUTHENTICITY .................................................... vi

ABSTRACT .......................................................................................................... vii

ACKNOWLEDGEMENT..................................................................................... viii

TABLE OF CONTENT ........................................................................................ x

LIST OF TABLES ................................................................................................ xii

LIST OF FIGURES .............................................................................................. xiii

CHAPTER I INTRODUCTION.................................................................. 1

1.1 Background ..................................................................... 1

1.2 Problem Statement .......................................................... 5

1.3 Research Question ........................................................... 5

1.4 Purpose of the Study ........................................................ 5

1.5 Scope of the research ....................................................... 6

CHAPTER II LITERATURE REVIEW....................................................... 7

2.1 Project Management .................................................. 7

2.2 Critical Path Method (CPM) ...................................... 9

2.3 Advantages of using the Critical Path Method........... 21

2.4 Disadvantages of using the Critical Path Method ...... 23

2.5 The Human Element Project Teams

and Decision Making ................................................ 25

2.6 Minimizing Project Completion Time ...................... 28

2.7 Minimizing Costs ...................................................... 30

CHAPTER III METHODOLOGY ................................................................ 32

3.1 Type and Research Approach ......................................... 32

3.2 Data Collection Technique ............................................. 32

Page 11: TIME AND COST CONTROLLING USING CRITICAL PATH A THESISeprints.ums.ac.id/40049/2/00.Depan.pdf · TIME AND COST CONTROLLING USING CRITICAL PATH METHOD (CASE STUDY AT PALUR FLY-OVER

x

3.2.1 Observation ........................................................ 33

3.2.2 Interview ............................................................ 33

3.3 Location of the Research .............................................. 34

3.4 Method for Data Collection ........................................... 34

3.5 Data Analysis Technique ............................................... 34

3.6 Research Framework ..................................................... 36

CHAPTER IV RESULT AND DISCUSSION .............................................. 37

4.1 General ............................................................................ 37

4.2 Contact Project ............................................................... 38

4.3 Budget of Project ............................................................ 39

4.4 Analyse the Remaining Works Items ............................ 44

4.5 Analyse of the Remaining Cost ..................................... 48

4.5.1 Minimizing Cost of Division (6) ...................... 48

4.5.2 Minimizing Cost of Division (8) ...................... 49

4.5.3 Minimizing Cost of Division (2) ...................... 50

4.6 Rescheduling ................................................................. 50

4.6.1 Alternative I ..................................................... 52

4.6.2 Alternative II .................................................... 53

4.6.3 Alternative III ................................................... 54

4.6.4 Alternative IV .................................................. 54

4.6.5 Alternative V .................................................... 56

4.7 Discussion ..................................................................... 56

CHAPTER V CONCLUSION AND RECOMMENDATION ..................... 60

5.1 General............................................................................ 60

5.2 Contact Project ............................................................... 60

APPENDICES

BIBLIOGRAPHY

Page 12: TIME AND COST CONTROLLING USING CRITICAL PATH A THESISeprints.ums.ac.id/40049/2/00.Depan.pdf · TIME AND COST CONTROLLING USING CRITICAL PATH METHOD (CASE STUDY AT PALUR FLY-OVER

xi

LIST OF TABLES

Table 4.1 List of the budget project 39

Table 4.2 The Remaining of Works preparatory on Month14th 44

Table 4.3 The Total of Remaining Works n Cost After 13 Month 50

Table 4.4 Curve S of Reschedulling 51

.

Page 13: TIME AND COST CONTROLLING USING CRITICAL PATH A THESISeprints.ums.ac.id/40049/2/00.Depan.pdf · TIME AND COST CONTROLLING USING CRITICAL PATH METHOD (CASE STUDY AT PALUR FLY-OVER

xii

LIST OF FIGURES

Figure 2.1Conventional Schedule and CCPM Schedule

With Time Buffers Shown Explicitly25

Figure 2.2. The Calculation CPM 31

Figure 2.3. Example of CPM 31

Figure 3.1. Research Framework 36

Figure 4.1 Location of Palur Fly-Over, Karanganyar 37

Figure 4.1a Network CPM Alternative I 52

Figure 4.1bNetwork CPM Alternative I, Normal Day for

Rescheduling52

Figure 4.2 Network CPM Alternative II 53

Figure 4.3 Network CPM Alternative III 54

Figure 4.4 Network CPM Alternative IV 55

Figure 4.5 Network CPM Alternative V 56