Upload
dewintha-kania
View
61
Download
8
Embed Size (px)
Citation preview
Tie-in Analysis GuidelineNomenclature
Abbreviation
TH Termination HeadEF End-fittingROV Remotely Operated Underwater Vehicles
1 Introduction
1.1 Scope
The aim of this report is to provide the guidance to an engineer to:
Identify the input data needed for tie-in analysis in ORCAFLEX Give basic tie-in simulation with ORCAFLEX Familiarize with ORCAFLEX output Present Tie-in Analysis in the Report
1.2 Reference
[1] Orcaflex version 9.7c, Orcina Limited
[2] Det Norske Veritas, “DNV-RP-H103 – Modelling and Analysis Operations”, April 2009
[3] Det Norske Veritas, “DNV-RP-F105 – Free-spanning Pipelines”, February 2006
[4] Det Norske Veritas, “DNV-OS-H101 – Marine Operation, General”, October 2011
1.3 Acknowledgement
Contributions of these following engineers are highly acknowledged (list based on alphabet):
Bjørn Frodesen --Flex RTS Tie-in System, Relocation, Goliat Project Dewintha Kania -Flex ROVCON, UTIS Tie-in System, Relocation, Gullfaks Sør IOR
Project Lars Heimdal - Flex RTS Tie-in System, Goliat Steinar Tveit Trygve Veslum Spool, Flex ROVCON, HCCS
2 Tie-in System
2.1 What is Tie-in?Tie-in is the operation where the tie-in product (such as rigid pipe, flexible pipe, umbilical, cable, etc) will be connected to the fix/movable structures’ part on the seabed (such as hub on the template, riser-base, etc) with some system. The tie-in definition is presented on Figure 2-1 below.
Figure 2-1 Tie-in Definition
Figure 2-2 Principal of Tie-in
Straight Line from Hub
Tie-in Poduct
Tie-in StructureHub
Tie-in System
2.2 Type of Tie-in System
2.2.1 Diver Tie-inDiver tie-in is basically tie-in using hyperbaric welding, done by diver with the special chamber. This diver tie-in doesn’t need the analysis and the scope is not included in this guideline.
2.2.2 Diver-less Tie-in for RigidThis Rigid tie-in can be
2.2.3 Diver-less Tie-in for Umbilical
There are two types of diver-less tie-in, it is separated based on how the operate:1. Diverless on seabed tie-in means the TH will be wet stored on the target box in front of the
hub and the winch from the system docked on the hub is connected to the TH and start to pull-in.
2. Diverless on Vessel tie-in means that the TH will be over-boarded straightly from the vessel to the porch / hub.
2.2.3.1 Diver-less (TH is On Seabed Tie-in)
Figure 2-3 ROVCON / ICARUS Figure 2-4 UTIS
2.2.3.2 Diver-less (TH is On Vessel Tie-in)
Figure 2-5
2.2.4 J-Tube Pull-in
Figure 2-6
2.2.5 Tie-in System Provider
There are many tie-in system used, TNOR’s track record is tabulated below:
Tie-in System Provider TNOR’s Track RecordICARUS GE Åsgard Gas Transfer, 2010
Yme 2006
RTS (Remote Tie-in System) Aker Solutions Oselvar, 2011 Kristin Riser Replacement,
2010 Kristin Replacement, 2008 Vilje, 2006 Fram Øst, 2006 Kristin Marine Operations,
2004
HCS (Horizontal Connection System)
Aker Solutions Brynhild 2013 Åsgard Subsea
Compression 2013 - 2014
UTIS FMC Technology Åsgard Repair, 2007 Åsgard Subsea, 2003 Sigyn, 2002
ROVCON FMC Technology Ekofisk 2009 Gjøa 2009 Rev Øst 2009 Fram øst 2006
STABCON FMC TechnologyVECON Mk2 FMC Technology
Tie-in System Provider TNOR’s Track RecordPSS 16 Ula/Blane, 2010
Gjøa (HCCS), 2009 Snøhvit, 2005
2.3 Limiting Criteria for Diver-less Tie-in System
Tie-in Structure Tie-in Tool Tie-in Product Additional Tie-in Check
Limiting Criteria:
Hub Loads Limitation: Force: Fx, Fy, Fz, Moment; Mx, My,
Mz Visual evaluation
wrt. clearance of TH before entering tool’s funnel.
Limiting Criteria:
Tool’s Capacity includes: Tool’s winch tension
during pull-in (Pull-in winch load)
Tool winch’s declination and azimuth before and during tie-in
Stroking force and moment
Limiting Criteria:
For Flexible lines, Umbilicals and Cables:
Bend Moment MBR Maximum Tension Minimum Tension
(compression) TH’s max bend
moment TH angles before and
during tie-inIn Bending Restrictor:
Bending Moment MBR
For Rigid lines and Spools: Stress Strain
Limiting Criteria:
Free-span Big-bags/ turning
points’ Contact Force
On Bottom Stability?
TDP tension How many
buoyancies needed
Pull-back rigging and winches for contingency
Vessel’s crane deployment needed, weather limitation for AHC and rigging load should be determined
2.3.1 Limiting Criteria for Tie-in Product
2.3.1.1 Rigid SpoolsStandards where appropriate:
Upheaval Buckling - DNV-RP-F110 On Bottom Stability Design of Submarine Pipelines - DNV-RP-F109 Free-spanning - DNV-RP-F105
2.3.1.2 Flexible Pipe, Umbilical, Cable On Bottom Stability Design of Submarine Pipelines -- DNV-RP-F109 Upheaval Buckling - DNV-RP-F110
2.3.2 Limiting Criteria for Tie-in Tool
ROVCON angle relative to pull-in ropes
2.3.3 Limiting Criteria for Tie-in Structure
ROVCON and inboard/outboard hub axis system
2.3.4 Tie-in’s Supports’ Limiting Criteria
2.3.4.1 Free-spanThe after tie-in route will create the free-span, especially when the line is crossing berms. The allowable free-span should be checked (DNV-RP-F109).
2.3.4.2 Big-bags’ Contact Force
3 Tie-in Analysis
3.1 Modelling in Orcaflex
Input Data What to use in
ORCAFLEX?
Settingnecessary
Input Data Specific
Required Output
Comment
Environment DataSeabed profile GeneralCurrent GeneralWaveOn Field LayoutNeighboring Spools
Drawing Coordinate Shape
NoneIf the clash check is needed, set the stuffs in elastic solid, otherwise can be set as drawing just for info.
Existing Sleeper/ rock-berm
Elastic Solid/ drawing
Coordinate Shape
None
Existing Mattresses
Elastic Solid/ drawing
Coordinate Shape
None
GRP Covers Elastic Solid/ drawing
Coordinate Shape
None
Neighboring Flow-line Arrangement
Drawing Coordinate Shape
None
PLET Drawing Coordinate Shape
None
Neighboring Structure’s slope, edges,etc
Drawing Coordinate Shape
None
Tie-in StructureTemplate, Manifold, XT, Riser-base Structure
Drawing None
Hub or
Drawing Coordinate Shape Inclination Hub Height
from seabed
None The hub loads is extracted from the Flowline’s end. The hub here as a
Input Data What to use in
ORCAFLEX?
Settingnecessary
Input Data Specific
Required Output
Comment
visualization to check that the flowline really connect hub’s coordinate
Tie-in ProductFlow-line (Pipe, Umbilical, Cable)
Prescribed Line for umbilical and pipe resting on seabed.
Catenary for umbilical hanging from vessel.
For each Segments of the line (TH, EF, Umbilical, Flex pipe, Cable), have an input data such as:- OD- Submerged weight- EA, EI, GI- MBR- Max, min Tension- BR section length and properties- Seabed’s Friction factors
- Hub Loads- Tie-in angles- MBR on flexible lines
- MBR and bend moment at BRs
- Free-span
Spool OD- Submerged weight- EA, EI, GI- MBR- Max, min Tension- BR section length and properties- Seabed’s Friction factors
- Hub loads- Stresses for rigid spools
Tie-in ToolROVCON Vessel - Loads during
tie-inUTIS
Tie-in SupportTarget Box Drawing
Input Data What to use in
ORCAFLEX?
Settingnecessary
Input Data Specific
Required Output
Comment
Back Tension Winch with history and constant tension at the end.
Buoyancy As an attachment on the line data
Big-bags Elastic solid shape
3.1.1 Field Layout
3.1.1.1 Environment InputData needed for environment input can be found in Met-ocean Report, including sea-water temperature, seabed friction coefficient, soil stiffness, sea-bed contour, survey, etc. There is no current and no wave for analyzing tie-in.
3.1.1.2 Existing Seabed on Tie-in Area
3.1.1.3 Existing Nearby Structures and Constraints
Figure 3-7
Template
Concrete Mattress
GRP Cover PLET
Spools
Spools
Concrete Mattresses
3.1.2 Tie-in Products
3.1.2.1 Rigid Pipe
3.1.2.2 Flexible Pipe /Umbilical
Questions before modelling Line in Orcaflex: Does it installed empty, water-filled, etc? Does the line Mono-bore or Multi-bore Does the line consists of many segments?
For modelling tie-in with TH on seabed, the tie-in route is more important than TH arrangement, this can lead to simplified line’s segment as line type, as described on Figure below:
Figure 3-8
Figure 3-9
Figure 3-10
For modelling tie-in with TH will dock straightly to the porch from the vessel, the TH arrangement should be modelled as 6D buoy to catch the behavior of the head during docking.
Figure 3-11
3.1.2.3 Spool
3.1.3 Tie-in Structures
3.1.3.1 Hub’s Declination
Figure 3-12
3.1.3.2 Determining Hub Height
3.2 Tie-in Simulation
3.2.1 Tie-in System Methodology
3.2.1.1 UTIS
3.2.1.2 ROVCON/ ICARUS
3.2.1.3 RTS
3.2.1.4 HCS
3.2.2 Simulation of Base Case
ROVCON / ICARUS HCS UTISStep 1 – Connect the winch from the hub to the TH, start to pull-in
Step 1 – Overboard TH from the vessel
Step 1 – Connect the winch from the hub to the TH, start to pull-in
Step 2 –stop pull-in 500mm away from the hub, Attach the head with vessel, ready for stroking by adjusting the heading, declination and gamma in the time history.
Step 2 – Lowering TH, ready for upending around the porch.
Step 2 - Pull-in TH until it fully enters the funnel. Rotate the funnel to 90 degree.
Step 3 – Stroking done Step 3 – Docking to the porch Step 3 - Hydraulic stroking to the hub. Tie-in completed. UTIS tool recovered.
3.2.3 Sensitivity Study = Load Cases
3.2.3.1 TH position on Target Box
Figure 3-13
3.2.3.2 Seabed’s Soil Friction Coefficient (min, nom, max)
3.2.3.3 Route Over-length (short, nom, far)
3.2.3.4 Hub angle vertical plane (Fy –Fx plane) (min, nom, max)
3.2.3.5 Rock berm height (min, nom, max)
3.2.3.6 Neighbouring Spool’s length (min, nom, max)
Figure 3-14
3.3 Analysis Results
3.3.1 Fulfilling Limiting Criteria
Check Tie-in Structure
Existing Model Arrangement
RUN
Check Tie-in Tool
Check Tie-in Product
OK
Not OK
OK OKExisting/ New Model Arrangement Accepted
Additional Structure:
Support Mattress Needed
Additional Aids: BuoyancyBack TensionBig-bagsWinch from Vessel
Additional Aids: BuoyancyNew Route for Flexible
New Tie-in Arrangement
Created.
Not OK Not OK
Not OK
OK
After Tie-in Route will be input for GRP
cover Design
Arrangement will be an input for making procedure, rigging design, procurement,
etc
OK
3.3.1.1 Tie-in Product and Tie-in Tool Check
Load Case
ROVCON ISU
Pull-in Tension
TH Heading Offset
TH End Declination
Offset
Stroke Force F_L
Max alignment
force horizontal
M_V,
Alignment force
vertical M_T
Max Combined alignment
(M_V, M_T) *)
ISU's MBR
BR’s MBR
Free-Span 1
**)
Free-Span 2
**)
[kN] [deg] [deg] [kN.m] [kN.m] [kN.m] [kN.m] [kN] [m] [m] [m]Limiting Criteria 210 +/-20 +/- 15 660 512 732 475 13 13 39.59 39.59
End-OLC 02 98.34 5.28 4.92 7.54 5.72 246.43 246.50
19.4613.06 21.4 12,4
End PLC 02 96.90 -0.62 10.57 16.78 10.55 204.36 204.63 13.08 18,3 8,8
Utilisation 0,48 0,4 0,6 0,02 0,02 0,3 0,48 - - 0,5 0,3OK / not
OK OK OK OK OK OK OK OK OK OK OK OK
3.3.1.2 Tie-in Tool Check
3.3.1.3 Tie-in Structure Check (Hub Loads)
CasesP-End
F_V F_T F_L M_V M_T M_LLimiting Criteria 60 ±20 50 ±40 200 ±20
Case1 (TH at N, BE soil friction) 43.72 -0.88 11.88 9.67 197.80 0.00Case2 (TH at N, HE soil friction) 44.01 -0.82 13.74 8.73 199.50 0.00
Case3 (TH at NEC, BE soil friction) 43.60 -0.92 11.01 10.32 197.13 0.00Case4 (TH at FEC, BE soil friction) 43.75 -0.84 12.00 9.16 197.95 0.00
Max Value 43.60 -0.82 13.74 10.32 199.50 0.00Utilisation 0.73 0.04 0.27 0.26 1.00 0.00
OK/Not OK OK OK OK OK OK OK
3.3.1.4 Before and After Tie-in Route
Figure 3-15
3.3.1.5 Allowable Free-span
3.3.2 The New arrangement with Additional Installation Aids
Figure 3-16
3.3.2.1 Back Tension
3.3.2.2 Big-bags
3.3.2.3 Buoyancy
3.3.2.4 Mattresses
3.3.2.5 Sliding Skid
3.3.2.6 Winch from Vessel
3.3.3 Present the Findings
3.3.3.1 Quick Tie-in Introduction
3.3.3.2 Summary Modelled in Orcaflex
3.3.3.3 Recommendation / Assessment
3.3.3.4 Sensitivity Analysis Tables
3.3.3.5 Screenshots Drawings
3.3.3.6 Appendixes
4 Worked Examples
4.1 Flexible/ Umbilical Tie-in
4.1.1 ROVCON
4.1.2 UTIS
4.1.3 RTS
4.2 Rigid Pipe/ Spool Tie-in
4.3 Tie-in with Relocation (HCS)
4.4 Worked Tie-in Analysis Report on IPC+