141
Project Title: PROPOSED TWO (2) STOREY LTO BUILDING Project Location: BRGY. POBLACION, URDANETA CITY, PANGASINAN Owner: LAND TRANSPORTATION OFFICE (Urdaneta Branch) 14 GENERAL REQUIREMENTS Qty 1.00 lot 1.0 Mobilization/Demobilization Php 2.0 Temporary Facilities a.) Bunkhouse/Office/Warehouse Php b.) Temporary Lightings Php c.) Temporary Water Php Php II. EARTHWORKS 1.0 Excavation Works/Backfill and Compaction Qty 34.10 cu.m A. LABOR COST 1 Project Engineer @ Php 600.00 /day Php 1 Construction Foreman Php 450.00 /day Php 1 H.E. Operator Php 400.00 /day Php 6 Laborer Php 250.00 /day Php Php Php 2,950.00 x 1.5 day Php B. EQUIPMENT EXPENSES (RENTAL) 1 unit Backhoe/Loader Php 7,000.00 /day Php Fuel, oil, lub.,etc Php 1,750.00 /day Php Php Php 8,750.00 x 1.5 days Php S U M M A R Y A. LABOR COST Php B. EQUIPMENT EXPENSES (RENTAL) Php Php plus: 7% OCM Php 8% CP Php 12% VAT Php Php Unit Cost = Php 20,182.50 / 34.10 cu.m Php Total Item Cost = Php 591.92 x 34.10 cu.m Php III. CONCRETE WORKS Qty 25.12 cu.m A. MATERIAL COST 303.0 bags Portland Cement @ Php 225.00 /bag Php 32.0 cu.m Screened Gravel Php 400.00 /cu.m Php 16.0 cu.m Washed Sand Php 450.00 /cu.m Php Php B. LABOR COST 1.0 Project Engineer @ Php 600.00 /day Php 1.0 Construction Foreman Php 450.00 /day Php 2.0 Mason Php 375.00 /day Php 8.0 Laborer Php 250.00 /day Php Php Php 3,800.00 x 8.0 days Php C. EQUIPMENT EXPENSES (RENTAL) 1 unit One Bagger Concrete Mixer Php 400.00 /day Php Fuel, oil, lub.,etc Php 100.00 /day Php Php Php 500.00 x 8.0 days Php

Tiao Him - Lab

Embed Size (px)

DESCRIPTION

DUPA

Citation preview

Page 1: Tiao Him - Lab

Project Title: PROPOSED TWO (2) STOREY LTO BUILDING

Project Location: BRGY. POBLACION, URDANETA CITY, PANGASINAN

Owner: LAND TRANSPORTATION OFFICE (Urdaneta Branch)

14 GENERAL REQUIREMENTS

Qty 1.00 lot

1.0 Mobilization/Demobilization Php 20,000.00

2.0 Temporary Facilities

a.) Bunkhouse/Office/Warehouse Php 50,000.00

b.) Temporary Lightings Php 30,000.00

c.) Temporary Water Php 10,000.00

Php 110,000.00

II. EARTHWORKS

1.0 Excavation Works/Backfill and Compaction

Qty 34.10 cu.m

A. LABOR COST

1 Project Engineer @ Php 600.00 /day Php 600.00

1 Construction Foreman Php 450.00 /day Php 450.00

1 H.E. Operator Php 400.00 /day Php 400.00

6 Laborer Php 250.00 /day Php 1,500.00

Php 2,950.00

Php 2,950.00 x 1.5 day Php 4,425.00

B. EQUIPMENT EXPENSES (RENTAL)

1 unit Backhoe/Loader Php 7,000.00 /day Php 7,000.00

Fuel, oil, lub.,etc Php 1,750.00 /day Php 1,750.00

Php 8,750.00

Php 8,750.00 x 1.5 days Php 13,125.00

S U M M A R Y

A. LABOR COST Php 4,425.00

B. EQUIPMENT EXPENSES (RENTAL) Php 13,125.00

Php 17,550.00

plus: 7% OCM Php 1,228.50

8% CP Php 1,404.00

12% VAT Php 2,106.00

Php 20,182.50

Unit Cost = Php 20,182.50 / 34.10 cu.m Php 591.92

Total Item Cost = Php 591.92 x 34.10 cu.m Php 20,182.50

III. CONCRETE WORKS

Qty 25.12 cu.m

A. MATERIAL COST

303.0 bags Portland Cement @ Php 225.00 /bag Php 68,175.00

32.0 cu.m Screened Gravel Php 400.00 /cu.m Php 12,800.00

16.0 cu.m Washed Sand Php 450.00 /cu.m Php 7,200.00

Php 88,175.00

B. LABOR COST

1.0 Project Engineer @ Php 600.00 /day Php 600.00

1.0 Construction Foreman Php 450.00 /day Php 450.00

2.0 Mason Php 375.00 /day Php 750.00

8.0 Laborer Php 250.00 /day Php 2,000.00

Php 3,800.00

Php 3,800.00 x 8.0 days Php 30,400.00

C. EQUIPMENT EXPENSES (RENTAL)

1 unit One Bagger Concrete Mixer Php 400.00 /day Php 400.00

Fuel, oil, lub.,etc Php 100.00 /day Php 100.00

Php 500.00

Php 500.00 x 8.0 days Php 4,000.00

Page 2: Tiao Him - Lab

S U M M A R Y

A. MATERIAL COST Php 88,175.00

B. LABOR COST Php 30,400.00

C. EQUIPMENT EXPENSES (RENTAL) Php 4,000.00

Php 122,575.00

plus: 7% OCM Php 8,580.25

8% CP Php 9,806.00

12% VAT Php 14,709.00

Php 140,961.25

Unit Cost = Php 140,961.25 / 25.12 cu.m Php 5,611.43

Total Item Cost = Php 5,611.43 x 25.12 cu.m Php 140,961.25

IV. REINFORCE STEEL BARS

Qty 3,687.06 kgs

A. MATERIAL COST

1,799.0 kgs 16mmØ Def. bars Php 40.00 /kg Php 71,958.98

381.9 kgs 12mmØ Def. bars Php 40.00 /kg Php 15,276.32

1,506.2 kgs 10mmØ Def. bars Php 40.00 /kg Php 60,247.20

52.2 kgs # 16 G.I. tie wire Php 60.00 /kg Php 3,131.26

Php 150,613.76

B. LABOR COST

1.0 Project Engineer @ Php 600.00 /day Php 600.00

1.0 Construction Foreman Php 450.00 /day Php 450.00

4.0 Steelman Php 300.00 /day Php 1,200.00

9.0 Laborer Php 250.00 /day Php 2,250.00

Php 4,500.00

Php 4,500.00 x 12.0 days Php 54,000.00

C. EQUIPMENT EXPENSES (RENTAL)

1 unit Bar cutter Php 200.00 /day Php 200.00

Php 200.00

Php 200.00 x 12.0 days Php 2,400.00

S U M M A R Y

A. MATERIAL COST Php 150,613.76

B. LABOR COST Php 54,000.00

C. EQUIPMENT EXPENSES (RENTAL) Php 2,400.00

Php 207,013.76

plus: 7% OCM Php 14,490.96

8% CP Php 16,561.10

12% VAT Php 24,841.65

Php 238,065.82

Unit Cost = Php 238,065.82 / 3,687.06 kgs Php 64.57

Total Item Cost = Php 64.57 x 3,687.06 kgs Php 238,065.82

V. FORMS AND SCAFFOLDINGS

Qty 1.00 lot

A. MATERIAL COST

25.0 pcs 1/2"x4'x8' Form Plywood @ Php 560.00 /pc Php 14,000.00

4,000.0 bd.ft Asst. Form lumber @ Php 24.00 /bd.ft Php 96,000.00

80.0 kgs Asst. CWNail @ Php 75.00 /kg Php 6,000.00

20.0 bd.ft # 16 G.I. tie wire @ Php 60.00 /kg Php 1,200.00

Php 117,200.00

B. LABOR COST

1 Project Engineer @ Php 600.00 /day Php 600.00

1 Construction Foreman @ Php 450.00 /day Php 450.00

Page 3: Tiao Him - Lab

4 Carpenter @ Php 375.00 /day Php 1,500.00

3 Laborer @ Php 250.00 /day Php 750.00

Php 3,300.00

Php 3,300.00 x 12.0 days Php 39,600.00

S U M M A R Y

A. MATERIAL COST Php 117,200.00

B. LABOR COST Php 39,600.00

Php 156,800.00

plus: 7% OCM Php 10,976.00

8% CP Php 12,544.00

12% VAT Php 18,816.00

Php 180,320.00

Unit Cost = Php 180,320.00 / 1.00 lot Php 180,320.00

Total Item Cost = Php 180,320.00 x 1.00 lot Php 180,320.00

VI. MASONRY WORKS (CHB laying w/ Plastering)

Qty 185.14 sq.m

A. MATERIAL COST

350.0 bags Portland Cement @ Php 225.00 /bag Php 78,750.00

29.0 cu.m Washed sand @ Php 400.00 /cu.m Php 11,600.00

2,450.0 pcs 5" CHB @ Php 10.50 /pc Php 25,725.00

518.0 kgs 10mmØ Def. bars @ Php 40.00 /kg Php 20,720.00

6.0 bd.ft # 16 G.I. tie wire @ Php 60.00 /kg Php 360.00

Php 137,155.00

B. LABOR COST

1 Project Engineer @ Php 600.00 /day Php 600.00

1 Construction Foreman Php 450.00 /day Php 450.00

4 Mason Php 375.00 /day Php 1,500.00

6 Laborer Php 250.00 /day Php 1,500.00

Php 4,050.00

Php 4,050.00 x 12.0 day Php 48,600.00

S U M M A R Y

A. MATERIAL COST Php 137,155.00

B. LABOR COST Php 48,600.00

Php 185,755.00

plus: 7% OCM Php 13,002.85

8% CP Php 14,860.40

12% VAT Php 22,290.60

Php 213,618.25

Unit Cost = Php 213,618.25 / 185.14 sq.m Php 1,153.82

Total Item Cost = Php 1,153.82 x 185.14 sq.m Php 213,618.25

VII. TILE WORKS

Qty 82.40 sq.m

A. MATERIAL COST

15.0 bags Tile Adhessive @ Php 190.00 /bag Php 2,850.00

3.0 cu.m Washed sand @ Php 400.00 /cu.m Php 1,200.00

4.0 pc 4"Ø Diamond cutter @ Php 450.00 /pc Php 1,800.00

428.0 pcs 16"x16" Granite tile @ Php 85.00 /pc Php 36,380.00

Page 4: Tiao Him - Lab

60.0 pcs 16"x16" Outdoor tile @ Php 65.00 /pc Php 3,900.00

20.0 kgs Tile Grout @ Php 25.00 /kg Php 500.00

Php 46,630.00

B. LABOR COST

1 Project Engineer @ Php 600.00 /day Php 600.00

1 Construction Foreman @ Php 450.00 /day Php 450.00

3 Mason @ Php 375.00 /day Php 1,125.00

4 Laborer @ Php 250.00 /day Php 1,000.00

Php 3,175.00

Php 3,175.00 x 5.0 day Php 15,875.00

C. EQUIPMENT EXPENSES (RENTAL)

1 unit Electric Grinder Php 150.00 /day Php 150.00

Php 150.00

Php 150.00 x 5.0 days Php 750.00

S U M M A R Y

A. MATERIAL COST Php 46,630.00

B. LABOR COST Php 15,875.00

C. EQUIPMENT EXPENSES (RENTAL) Php 750.00

Php 63,255.00

plus: 7% OCM Php 4,427.85

8% CP Php 5,060.40

12% VAT Php 7,590.60

Php 72,743.25

Unit Cost = Php 72,743.25 / 82.40 sq.m Php 882.81

Total Item Cost = Php 882.81 x 82.40 sq.m Php 72,743.25

VIII. CARPENTRY AND JOINERY WORKS (2ND Floor Ceiling only)

Qty 82.40 sq.m

A. MATERIAL COST

16.0 pcs Hardiflex ceiling board @ Php 420.00 /pc Php 6,720.00

48.0 pcs 0.40mm 19mm x 50mm x 5m @ Php 115.00 /pc Php 5,520.00

Double furring channel

8.0 pcs 0.80mm 12mm x 38mm x 5m @ Php 140.00 /pc Php 1,120.00

Carrying Channel

15.0 pcs 0.40mm 25mm x 25mm x 3m @ Php 85.00 /pc Php 1,275.00

Wall angle

290.0 pcs W-Clip @ Php 8.00 /pc Php 2,320.00

1.0 kgs 1-1/2" Concrete nail @ Php 90.00 /kg Php 90.00

2.0 pcs 4"Ø Diamond grinding disc @ Php 65.00 /pc Php 130.00

2.0 box Blind rivets @ Php 500.00 /box Php 1,000.00

800.0 bd.ft Asst. Form lumber (Scaffoldings) @ Php 24.00 /bd.ft Php 19,200.00

Php 37,375.00

B. LABOR COST

1 Project Engineer @ Php 600.00 /day Php 600.00

1 Construction Foreman @ Php 450.00 /day Php 450.00

3 Carpenter @ Php 375.00 /day Php 1,125.00

2 Laborer @ Php 250.00 /day Php 500.00

Php 2,675.00

Php 2,675.00 x 5.0 days Php 13,375.00

C. EQUIPMENT EXPENSES (RENTAL)

1 unit Electric Grinder Php 150.00 /day Php 150.00

Php 150.00

Php 150.00 x 5.0 days Php 750.00

Page 5: Tiao Him - Lab

S U M M A R Y

A. MATERIAL COST Php 37,375.00

B. LABOR COST Php 13,375.00

C. EQUIPMENT EXPENSES (RENTAL) Php 750.00

Php 51,500.00

plus: 7% OCM Php 3,605.00

8% CP Php 4,120.00

12% VAT Php 6,180.00

Php 59,225.00

Unit Cost = Php 59,225.00 / 82.40 sq.m Php 718.75

Total Item Cost = Php 718.75 x 82.40 sq.m Php 59,225.00

IX. DOORS AND WINDOWS

Qty 1.00 lot

A. MATERIAL COST

2.0 sets D-1, Panel type door w/ 2"x 6" jamb with @ Php 5,300.00 /set Php 10,600.00

Complete accessories (0.90x2.10mts.)

1.0 sets D-2, Flush type door w/ 2"x 5" jamb with @ Php 4,000.00 /set Php 4,000.00

Complete accessories (0.80x2.10 mts.)

2.0 sets W-1, Steel casement window with 3/16" @ Php 3,780.00 /set Php 7,560.00

thk. Clear glass (1.80x1.40mts)

2.0 sets W-2, Steel casement window with 3/16" @ Php 2,520.00 /set Php 5,040.00

thk. Clear glass (1.20x1.40mts)

Php 27,200.00

B. LABOR COST (Installation only)

1 Project Engineer @ Php 600.00 /day Php 600.00

1 Construction Foreman @ Php 450.00 /day Php 450.00

1 Carpenter @ Php 375.00 /day Php 375.00

1 Welder @ Php 375.00 /day Php 375.00

1 Glass Installer @ Php 300.00 /day Php 300.00

5 Laborer @ Php 250.00 /day Php 1,250.00

Php 3,350.00

Php 3,350.00 x 2.0 days Php 6,700.00

C. EQUIPMENT EXPENSES (RENTAL)

1 unit Electric Grinder Php 150.00 /day Php 150.00

Php 150.00

Php 150.00 x 2.0 days Php 300.00

S U M M A R Y

A. MATERIAL COST Php 27,200.00

B. LABOR COST Php 6,700.00

C. EQUIPMENT EXPENSES (RENTAL) Php 300.00

Php 34,200.00

plus: 7% OCM Php 2,394.00

8% CP Php 2,736.00

12% VAT Php 4,104.00

Php 39,330.00

Unit Cost = Php 39,330.00 / 1.00 lot Php 39,330.00

Total Item Cost = Php 39,330.00 x 1.00 lot Php 39,330.00

X. PAINTING WORKS (Concrete wall & Hardiflex Ceiling board)

Qty 460.08 sq.m

A. MATERIAL COST

5.0 tin Flat Latex paint @ Php 1,810.00 /tin Php 9,050.00

Page 6: Tiao Him - Lab

10.0 tin Semi-gloss Latex paint @ Php 2,370.00 /tin Php 23,700.00

4.0 lits Latex color @ Php 120.00 /lit Php 480.00

4.0 gal. Masonry putty @ Php 15.00 /gal Php 60.00

20.0 kgs Patching compound @ Php 15.00 /lit Php 300.00

8.0 lits Stickwel @ Php 195.00 /lit Php 1,560.00

7.0 pcs Roller brush @ Php 100.00 /pc Php 700.00

17.0 pcs Paint brush @ Php 45.00 /pc Php 765.00

100.0 pcs Sandpaper @ Php 25.00 /pc Php 2,500.00

15.0 pcs Stupa Rag @ Php 20.00 /kg Php 300.00

Php 39,415.00

B. LABOR COST

1 Project Engineer @ Php 600.00 /day Php 600.00

1 Construction Foreman @ Php 450.00 /day Php 450.00

3 Painter @ Php 350.00 /day Php 1,050.00

4 Laborer @ Php 250.00 /day Php 1,000.00

Php 3,100.00

Php 3,100.00 x 5.0 day Php 15,500.00

S U M M A R Y

A. MATERIAL COST Php 39,415.00

B. LABOR COST Php 15,500.00

Php 54,915.00

plus: 7% OCM Php 3,844.05

8% CP Php 4,393.20

12% VAT Php 6,589.80

Php 63,152.25

Unit Cost = Php 63,152.25 / 460.08 sq.m Php 137.26

Total Item Cost = Php 137.26 x 460.08 sq.m Php 63,152.25

XI. TRUSS WORKS

Qty 1.00 lot

A. MATERIAL COST

23.0 pcs 1.5mm x 2"x6" CEE purlins (truss) @ Php 650.00 /pc Php 14,950.00

12.0 pcs 1.0mm x 2"x4" CEE purlins @ Php 397.00 /pc Php 4,764.00

3 5.0 pcs 10mmØ Plain Round bar @ Php 138.00 /pc Php 690.00

9.0 pcs 1/4" x 10"x10" Base plate @ Php 250.00 /pc Php 2,250.00

3.0 box Welding rod @ Php 1,200.00 /box Php 3,600.00

36.0 pcs 12mmØ x 10" Anchor bolts w/

Nut and washer @ Php 120.00 /pc Php 4,320.00

Php 30,574.00

B. LABOR COST

1 Project Engineer @ Php 600.00 /day Php 600.00

1 Construction Foreman @ Php 450.00 /day Php 450.00

2 Welder @ Php 375.00 /day Php 750.00

2 Laborer @ Php 250.00 /day Php 500.00

Php 2,300.00

Php 2,300.00 x 4.0 day Php 9,200.00

1 unit Welding Machine Php 450.00 /day Php 450.00

Php 450.00

Php 450.00 x 4.0 days Php 1,800.00

S U M M A R Y

A. MATERIAL COST Php 30,574.00

Page 7: Tiao Him - Lab

B. LABOR COST Php 9,200.00

C. EQUIPMENT EXPENSES (RENTAL) Php 1,800.00

Php 41,574.00

plus: 7% OCM Php 2,910.18

8% CP Php 3,325.92

12% VAT Php 4,988.88

Php 47,810.10

Unit Cost = Php 47,810.10 / 1.00 lot Php 47,810.10

Total Item Cost = Php 47,810.10 x 1.00 lot Php 47,810.10

XII. ROOFING WORKS

Qty 48.50 l.m

A. MATERIAL COST

48.5 l.m Rib-type Roofing sheet (.5mm thk.) @ Php 420.00 /l.m Php 20,370.00

48.5 l.m One sided Alum. Insulation (9mm thk) @ Php 450.00 /l.m Php 21,825.00

5.0 pcs Wall flashing @ Php 450.00 /pc Php 2,250.00

5.0 pcs 3"Ø PVC pipe @ Php 460.00 /pc Php 2,300.00

6.0 pcs 3"Ø PVC Elbow 1/4 bend @ Php 53.00 /pc Php 318.00

3.0 pcs Gutter @ Php 450.00 /pc Php 1,350.00

300.0 pcs Tekscrew @ Php 1.75 /pc Php 525.00

4.0 tube Silicon Sealant @ Php 150.00 /tube Php 600.00

1.0 box Blind Rivets @ Php 500.00 /box Php 500.00

Php 50,038.00

B. LABOR COST

1 Project Engineer @ Php 600.00 /day Php 600.00

1 Construction Foreman @ Php 450.00 /day Php 450.00

3 Roof Installer @ Php 350.00 /day Php 1,050.00

4 Laborer @ Php 250.00 /day Php 1,000.00

Php 3,100.00

Php 3,100.00 x 4.0 day Php 12,400.00

S U M M A R Y

A. MATERIAL COST Php 50,038.00

B. LABOR COST Php 12,400.00

Php 62,438.00

plus: 7% OCM Php 4,370.66

8% CP Php 4,995.04

12% VAT Php 7,492.56

Php 71,803.70

Unit Cost = Php 71,803.70 / 48.50 l.m Php 1,480.49

Total Item Cost = Php 1,480.49 x 48.50 l.m Php 71,803.70

XIII. TINSMITRY WORKS (Stair Railings)

Qty 1.00 lot

A. MATERIAL COST

4.0 pcs 2"Ø Stainless Steel pipe @ Php 3,250.00 /pc Php 13,000.00

4.0 pcs 3/16"x1" Flat bar @ Php 235.00 /pc Php 940.00

15.0 pcs 3/4"x3/4" Square bar @ Php 245.00 /pc Php 3,675.00

1.0 lot Welding rod/Accessories @ Php 3,000.00 /lot Php 3,000.00

2.0 pc 4"Ø Grinding disk @ Php 65.00 /pc Php 130.00

Php 20,745.00

B. LABOR COST

1 Project Engineer @ Php 600.00 /day Php 600.00

1 Construction Foreman @ Php 450.00 /day Php 450.00

1 Welder @ Php 375.00 /day Php 375.00

Page 8: Tiao Him - Lab

3 Laborer @ Php 250.00 /day Php 750.00

Php 2,175.00

Php 2,175.00 x 3.0 day Php 6,525.00

C. EQUIPMENT EXPENSES (RENTAL)

1 unit Welding Machine Php 450.00 /day Php 450.00

Php 450.00

Php 450.00 x 3.0 days Php 1,350.00

S U M M A R Y

A. MATERIAL COST Php 20,745.00

B. LABOR COST Php 6,525.00

C. EQUIPMENT EXPENSES (RENTAL) Php 1,350.00

Php 28,620.00

plus: 7% OCM Php 2,003.40

8% CP Php 2,289.60

12% VAT Php 3,434.40

Php 32,913.00

Unit Cost = Php 32,913.00 / 1.00 lot Php 32,913.00

Total Item Cost = Php 32,913.00 x 1.00 lot Php 32,913.00

XIV. ELECTRICAL WORKS

Qty 1.00 lot

A. MATERIAL COST

6.0 sets 2x40W FL lamp w/ housing @ Php 1,500.00 /set Php 9,000.00

5.0 sets 25W CFL @ Php 60.00 /set Php 300.00

5.0 sets 4"x4" Pinlight @ Php 250.00 /set Php 1,250.00

6.0 pcs Receptacle 4"Ø @ Php 50.00 /pc Php 300.00

2.0 sets Single pole switch @ Php 120.00 /set Php 240.00

3.0 sets Two pole switch @ Php 165.00 /set Php 495.00

2.0 sets 3-Way switch @ Php 210.00 /set Php 420.00

1.00 sets @ Php 1,850.00 /set Php 1,850.00

11.0 pcs 4"x4" Junction box @ Php 35.00 /pc Php 385.00

15.0 pcs 2"x4" Utility box @ Php 35.00 /pc Php 525.00

34.0 pcs 1/2"Ø PVC pipe x 3.00 mts. @ Php 61.00 /pc Php 2,074.00

2.0 rolls 3.5mm² THHN wire @ Php 3,207.50 /roll Php 6,415.00

20.0 mts 14mm² THHN wire @ Php 85.84 /mt Php 1,716.80

4.0 pcs 1'Ø PVC pipe x 3.00 mts. @ Php 102.00 /pc Php 408.00

2.0 pcs 1"Ø Long sweep elbow @ Php 38.00 /pc Php 76.00

22.0 pcs 1/2"Ø PVC Long sweep elbow @ Php 25.00 /pc Php 550.00

1.0 pc 1"Ø RSC pipe x 3.00 mts. @ Php 420.00 /pc Php 420.00

1.0 sets 1"Ø Entrance cap @ Php 65.00 /set Php 65.00

1.0 set 3-Pole secondary rack @ Php 285.00 /set Php 285.00

1.0 pc 1"Ø Long sweep elbow (RSC) @ Php 85.00 /pc Php 85.00

10.0 rolls Electrical tape @ Php 45.00 /roll Php 450.00

Php 27,309.80

B. LABOR COST

1 Project Engineer @ Php 600.00 /day Php 600.00

1 Construction Foreman @ Php 450.00 /day Php 450.00

1 Electrician @ Php 325.00 /day Php 325.00

3 Laborer @ Php 250.00 /day Php 750.00

Php 2,125.00

Php 2,125.00 x 4.0 day Php 8,500.00

C. EQUIPMENT EXPENSES (RENTAL)

1 unit Electric drill Php 150.00 /day Php 150.00

Php 150.00

Main ACB/ 6-branches, w/ 1-20 AT, 2P, 5-20 AT, 2P

Page 9: Tiao Him - Lab

Php 150.00 x 4.0 days Php 600.00

S U M M A R Y

A. MATERIAL COST Php 27,309.80

B. LABOR COST Php 8,500.00

C. EQUIPMENT EXPENSES (RENTAL) Php 600.00

Php 36,409.80

plus: 7% OCM Php 2,548.69

8% CP Php 2,912.78

12% VAT Php 4,369.18

Php 41,871.27

Unit Cost = Php 41,871.27 / 1.00 sets Php 41,871.27

Total Item Cost = Php 41,871.27 x 1.00 sets Php 41,871.27

TOTAL CONSTRUCTION COST Php 1,331,996.39

Page 10: Tiao Him - Lab

251.20

0.34476892543238

Page 11: Tiao Him - Lab

0.35853297776182

Page 12: Tiao Him - Lab

0.33788395904437

0.3543436258248

ground floor/second floor stairs 12.50 13.00 80 20.00 20.00 260 2.4 14.70 15.00 82.4

Page 13: Tiao Him - Lab

12.50 13.00 195 26.25 5.00 5.00 5.32 6.00 60

0.34044606476517

ground floor/second floor 12.50 13.00 20.00 20.00

14.70 15.00

12.50 13.00 35.42 53.13 5.00 5.00 17.71

5.00 5.00

5.32 6.00

0.35785953177258

Page 14: Tiao Him - Lab

5,300.00

4,000.00

2.52 1500 3,780.00

1.68 1500 2,520.00

0.24632352941176

12.342667

Page 15: Tiao Him - Lab

0.3932513002664

16.579.946.62

3.311

37.44 6.24

0.3009092693138

Page 16: Tiao Him - Lab

0.24781166313602

0.62516.57 8.333333 2713.25 9

9.946.62

46.38 7.73

Page 17: Tiao Him - Lab

0.31453362255965

0.62516.57 8.333333 2713.25 913.25 313.25 1

13.25 0.33333313.25 0.11111113.25 0.037037

96.07 16.011667

0.31124358288966

Page 18: Tiao Him - Lab

Project Title: PROPOSED TWO (2) STOREY LTO BUILDING

Project Location: BRGY. POBLACION, URDANETA CITY, PANGASINAN

Owner: LAND TRANSPORTATION OFFICE (Urdaneta Branch)

BILL OF QUANTITIESItem No. DESCRIPTION UNIT QTY UNIT COST AMOUNT

I GENERAL REQUIREMENTS lot 1.00 110,000.00 110,000.00

II EARTHWORKS cu.m 34.10 591.92 20,182.50

III. CONCRETE WORKS cu.m 25.12 5,611.43 140,961.25

IV REINFORCE STEEL BARS kgs 3,687.06 64.57 238,065.82

V FORMS AND SCAFFOLDINGS lot 1.00 180,320.00 180,320.00

VI MASONRY WORKS sq.m 185.14 1,153.82 213,618.25

VII TILE WORKS sq.m 82.40 882.81 72,743.25

VIII CARPENTRY AND JOINERY WORKS sq.m 82.40 718.75 59,225.00

IX DOORS AND WINDOWS lot 1.00 39,330.00 39,330.00

X PAINTING WORKS sq.m 460.08 137.26 63,152.25

XI TRUSS WORKS lot 1.00 47,810.10 47,810.10

XII ROOFING WORKS l.m 48.50 1,480.49 71,803.70

XIII TINSMITRY WORKS lot 1.00 32,913.00 32,913.00

XIV ELECTRICAL WORKS lot 1.00 41,871.27 41,871.27 TOTAL PROJECT COST 1,331,996.39

Page 19: Tiao Him - Lab

EARTHWORKSEXCAVATION WORKS

MARKFOR ONE (1) STRUCTURE

C1-F1 1.00 1.00 1.00 9.00 9.00WF-1 25.00 0.30 0.55 1.00 4.13Septic Tank 3.05 1.65 2.50 12.58

0.000.00

TOTAL 25.71

BACKFILL/COMPACTION

MARKFOR ONE (1) STRUCTURE

F1 1.00 1.00 0.25 9.00 2.25WF-1 25.00 0.55 0.15 1.00 2.06COLUMN 0.25 0.25 0.75 9.00 0.42

TOTAL 4.73

Excavation = 13.13Backfill/Compaction 8.39 cu.m

GRAVEL BEDDING

MARKFOR ONE (1) STRUCTURE

F-1 1.00 1.00 0.10 9.00 0.90FTB 25.00 0.55 0.10 1.00 1.38

0.25 0.25 0.10 9.00 0.06GB 0.00 0.00 0.10 0.00 0.00

0.00 0.00 0.10 0.00 0.00Area-1 8.00 5.00 0.10 1.00 4.00Area-2 2.00 1.20 0.10 1.00 0.24TOTAL 6.57

ON FILL

MARKFOR ONE (1) STRUCTURE

OPERATOR ROOM 7.00 4.00 0.15 1.00 4.20REST ROOM 2.50 1.50 0.125 1.00 0.47

0.000.000.000.000.00

NO. OF SIMILAR

STRUCTURE

TOTAL VOLUME

(m³)LENGTH

(m.)WIDTH

(m.)HEIGHT

(m.)

NO. OF SIMILAR

STRUCTURE

TOTAL VOLUME

(m³)LENGTH

(m.)WIDTH

(m.)HEIGHT

(m.)

NO. OF SIMILAR

STRUCTURE

TOTAL VOLUME

(m³)LENGTH

(m.)WIDTH

(m.)HEIGHT

(m.)

NO. OF SIMILAR

STRUCTURE

TOTAL VOLUME

(m³)LENGTH

(m.)WIDTH

(m.)HEIGHT

(m.)

Page 20: Tiao Him - Lab

TOTAL 4.67

Page 21: Tiao Him - Lab

3.33 0.75 0.75 0.75 0.4283.33 0.70

0.83

0.00

Page 22: Tiao Him - Lab

V - MASONRY WORKS

GROUND FLOORperimeter wall 26.00 3.50 1.00 91.00

less opening 7.29 7.29

Total area 83.71

185.14

perimeter wall 26.00 3.50 1.00 91.00

4.40 1.00 1.00 4.40

5.00 3.00 1.00 15.00

less opening 8.97 8.97

Total area 101.43

No. of pcs 6” CHB 2,406.82 say 2,450.00 pcs

Cement 187.55 say 190.00 bags

Sand 15.63 say 17.00 m³

Vert. Reinforcement 394.35

Hor. Reinforcement 398.05

792.40 / 5.7m = 139.017403508772

say 140 pcs 10mmØ 518.00

GI Tie Wire 4.44 say 6 kgs

Plastering

perimeter wall 83.71 101.43 1.00 185.14

370.28

370.28

Cement 159.22 say 160 bags

Sand 9.26 say 12 cu.m.

Summary

Cement 350.00

Sand 29.00

No. of pcs 6” CHB 2,450.00

RSB Reinforcement 518.00

GI Tie Wire 6.00

Page 23: Tiao Him - Lab

kgs

Page 24: Tiao Him - Lab

10MMØ0.616 6.00 3.70

0.616 7.50 4.62

0.616 9.00 5.54

0.616 10.50 6.47

0.616 12.00 7.39

REBAR WORKS

MARK LOCATION

FOR 1 STRUCTURE

F1 top-tranverse 16 1.10 5.00 9.00 45.00

bottom-longitudinal 16 1.10 5.00 45.00

Footing

C1 vertical bar 16 4.55 4.00 9.00 36.00

4.30 outer ties 10 1.20 25.80 232.20

inner ties 10 1.00 25.80 232.20

C2 vertical bar 16 9.00 8.00 0.00 0.00

0.00 outer ties 10 1.20 0.00 0.00

inner ties 10 1.00 0.00 0.00

C3 vertical bar 16 9.00 8.00 0.00 0.00

0.00 outer ties 10 1.20 0.00 0.00

inner ties 10 1.00 0.00 0.00

WF-1 straight bars 12 6.00 10.00 1.00 10.00

25.00 stirrups 10 0.35 125.00 125.00

GB straight bars 16 6.00 4.00 3.00 12.00

5.00 stirrups 10 0.90 36.00 108.00

GB straight bars 16 4.50 4.00 4.00 16.00

4.00 stirrups 10 0.90 27.00 108.00

B-1 straight bars 16 6.00 4.00 2.00 8.00

5.00 top cut bars 16 1.50 2.00 4.00

bott. Cut bars 16 3.00 1.00 2.00

stirrups 10 1.20 36.00 72.00

B-1 straight bars 16 4.50 4.00 4.00 16.00

BAR SIZE

NO. OF SIMILAR STRUCT

URE

TOTAL NO.OF PCS

ONE BAR LENGTH

NUMBER OF PCS

Page 25: Tiao Him - Lab

4.00 top cut bars 16 1.20 2.00 8.00

bott. Cut bars 16 2.50 1.00 4.00

stirrups 10 1.20 27.00 108.00

B-2 straight bars 16 6.00 4.00 1.00 4.00

5.00 top cut bars 16 1.50 4.00 4.00

bott. Cut bars 16 3.00 2.00 2.00

stirrups 10 1.40 36.00 36.00

B-3 straight bars 16 6.00 4.00 1.00 4.00

5.00 top cut bars 16 1.50 2.00 2.00

bott. Cut bars 16 3.00 1.00 1.00

stirrups 10 1.10 36.00 36.00

B-4 straight bars 16 2.50 4.00 1.00 4.00

2.12 top cut bars 16 0.75 2.00 2.00

bott. Cut bars 16 1.50 1.00 1.00

stirrups 10 0.90 15.00 15.00

LB-1 straight bars 12 2.50 4.00 1.00 4.00

2.00 stirrups 10 1.00 15.00 15.00

CB-1 straight bars 12 1.50 4.00 1.00 4.00

1.20 stirrups 10 1.00 9.00 9.00

RB-1 straight bars 12 6.00 4.00 2.00 8.00

5.00 top cut bars 12 1.50 2.00 4.00

bott. Cut bars 12 3.00 1.00 2.00

stirrups 10 0.90 36.00 72.00

straight bars 12 4.50 4.00 4.00 16.00

4.00 top cut bars 12 1.20 2.00 8.00

bott. Cut bars 12 2.50 1.00 4.00

stirrups 10 0.90 27.00 108.00

RB-2 straight bars 16 6.00 4.00 1.00 4.00

5.00 top cut bars 16 1.50 2.00 2.00

bott. Cut bars 16 3.00 1.00 1.00

stirrups 10 1.10 36.00 36.00

RB-3 straight bars 12 6.00 4.00 1.00 4.00

5.00 stirrups 10 0.70 36.00 36.00

straight bars 12 2.50 4.00 1.00 4.00

2.12 stirrups 10 0.70 15.00 15.00

LB-2 straight bars 12 2.50 4.00 1.00 4.00

2.00 stirrups 10 0.80 15.00 15.00

CB-2 straight bars 12 1.50 4.00 2.00 8.00

1.20 stirrups 10 0.80 9.00 18.00

SLAB ON FILL longitudinal 10 7.00 17.50 1.00 17.50

cross section 10 4.00 10.00 10.00

SUSPENDED SLAB top bars(longitudinal) 10 5.00 16.67 1.00 16.67

top bars (cross section) 10 8.00 26.67 26.67

Page 26: Tiao Him - Lab

cut bars(longitudinal) 12 1.25 10.00 10.00

cut bars (cross section) 12 4.00 10.00 10.00

bent up bars(longitudinal) 10 5.00 16.67 16.67

two way bent up bars (cross section) 10 8.00 26.67 26.67

Page 27: Tiao Him - Lab

MB-1 (30.00m) straight bars 16 30.83 4.00 3.00 12.00

@ GL A web bars 12 30.83 2.00 6.00

stirrups 10 1.40 784.00 2,352.00

MB-2(20.00m) straight bars 16 20.83 4.00 3.00 12.00

@ GL 1 web bars 12 20.83 2.00 6.00

stirrups 10 1.40 162.00 486.00

MB (30.00m) straight bars 16 30.83 4.00 1.00 4.00

@ GL A web bars 12 30.83 2.00 2.00

stirrups 10 1.40 184.00 184.00

Midbeam

RB-1 (20.00m) straight bars 16 20.83 4.00 1.00 4.00

@ GL 1 web bars 12 20.83 2.00 2.00

top cut bars-end support 16 0.93 2.00 2.00 4.00

top cut bars-middle support 16 1.65 2.00 2.00 4.00

top cut bars-middle support 16 2.90 2.00 1.00 2.00

top cut bars-middle support 16 2.28 2.00 2.00 4.00

bottom cut bars 16 1.50 2.00 4.00 8.00

bottom cut bars 16 3.00 2.00 2.00 4.00

stirrups 10 1.40 162.00 162.00

RB-1 (30.00m) straight bars 16 30.83 4.00 1.00 4.00

web bars 12 30.83 2.00 2.00

top cut bars-end support 16 1.98 2.00 1.00 2.00

top cut bars-middle support 16 1.78 2.00 1.00 2.00

top cut bars-middle support 16 1.90 2.00 23.00 46.00

top cut bars-middle support 16 1.55 2.00 7.00 14.00

bottom cut bars 16 1.80 2.00 24.00 48.00

bottom cut bars 16 1.50 2.00 8.00 16.00

stirrups 10 1.40 784.00 784.00

RB-2 (20.00m) straight bars 16 20.83 4.00 4.00 16.00

web bars 12 20.83 2.00 8.00

top cut bars-end support 16 0.93 2.00 2.00 16.00

top cut bars-middle support 16 1.65 2.00 2.00 16.00

top cut bars-middle support 16 2.90 2.00 1.00 8.00

top cut bars-middle support 16 2.28 2.00 2.00 16.00

bottom cut bars 16 1.50 2.00 4.00 32.00

bottom cut bars 16 3.00 2.00 2.00 16.00

stirrups 10 1.40 162.00 648.00

S.Angle (20.00m) straight bars 16 20.83 4.00 4.00 16.00

@ GL A web bars 12 20.83 2.00 8.00

top cut bars-end support 16 0.93 2.00 2.00 16.00

top cut bars-middle support 16 1.65 2.00 7.00 56.00

bottom cut bars 16 1.50 2.00 8.00 64.00

stirrups 10 1.40 184.00 736.00

roofbeam

Ground Slab transverse 12 92.00 41.00 1.00 41.00

92 x 20 longitudinal 12 20.00 185.00 185.00

Page 28: Tiao Him - Lab

Ground Slab transverse 12 42.00 41.00 1.00 41.00

42 x 20 longitudinal 12 20.00 85.00 85.00

Ground Slab

Page 29: Tiao Him - Lab

12MMØ 16MMØ0.888 6.00 5.33 1.578 6.00 9.47

0.888 7.50 6.66 1.578 7.50 11.84

0.888 9.00 7.99 1.578 9.00 14.20

0.888 10.50 9.32 1.578 10.50 16.57

0.888 12.00 10.66 1.578 12.00 18.94

49.50 6.00 8.25 8.25 225.00 156.22 1.93

49.50 6.00

156.22 1.93 8616MMØ 156.22

TIE WIRE 2.00

163.80 6.00 27.30 16.00 1,857.60 227.23 10.51

278.64 6.00 46.44 20.00 73.92

232.20 6.00 38.70 17.00 62.83

0.00 9.00 0.00 16.00 0.00 227.23 0.00

0.00 6.00 0.00 21.00 77.62

0.00 6.00 0.00 17.00 62.83

0.00 9.00 0.00 16.00 0.00 227.23 0.00

0.00 6.00 0.00 21.00 77.62

0.00 6.00 0.00 18.00 66.53

1,103.04 10.51

16MMØ 681.70

10MMØ 421.34

TIE WIRE 10.51

60.00 6.00 10.00 1.00 250.00 53.28 2.00

43.75 6.00 8.00 29.57

82.85 2.00

12MMØ 53.28

10MMØ 29.57

TIE WIRE 2.00

72.00 6.00 12.00 12.00 432.00 170.42 2.45

97.20 6.00 16.20 17.00 62.83

72.00 9.00 8.00 8.00 432.00 113.62 2.45

97.20 6.00 16.20 17.00 62.83

409.70 4.89

16MMØ 284.04

10MMØ 125.66

TIE WIRE 4.89

48.00 6.00 8.00 8.00 504.00 75.74 2.85

6.00 6.00 1.00 1.00 9.47

6.00 6.00 1.00 1.00 9.47

86.40 6.00 14.40 15.00 55.44

72.00 9.00 8.00 8.00 756.00 151.49 4.28

TOTAL NO. OF COMML LENGTH

COMML LENGTH

NO. OF VER/LONG

BAR

NO. OF HOR/TRANS

BAR

TOTAL BAR INTERSECTIO

N

Page 30: Tiao Him - Lab

9.60 6.00 1.60 2.00 18.94

10.00 7.50 1.33 2.00 18.94

129.60 6.00 21.60 22.00 81.31

24.00 6.00 4.00 4.00 360.00 37.87 2.04

6.00 6.00 1.00 1.00 9.47

6.00 6.00 1.00 1.00 9.47

50.40 6.00 8.40 9.00 33.26

24.00 6.00 4.00 4.00 252.00 37.87 1.43

3.00 6.00 0.50 1.00 9.47

3.00 6.00 0.50 1.00 9.47

39.60 6.00 6.60 7.00 25.87

10.00 7.50 1.33 1.50 105.00 17.75 0.59

1.50 6.00 0.25 0.50 4.73

1.50 6.00 0.25 0.50 4.73

13.50 6.00 2.25 3.00 11.09

10.00 7.50 1.33 1.50 60.00 6.93 0.34

15.00 6.00 2.50 3.00 11.09

6.00 6.00 1.00 1.00 36.00 5.33 0.20

9.00 6.00 1.50 2.00 7.39

48.00 6.00 8.00 8.00 504.00 42.62 2.85

6.00 6.00 1.00 1.00 5.33

6.00 6.00 1.00 1.00 5.33

64.80 6.00 10.80 11.00 40.66

72.00 9.00 8.00 8.00 756.00 85.25 4.28

9.60 6.00 1.60 2.00 10.66

10.00 6.00 1.67 2.00 10.66

97.20 6.00 16.20 17.00 62.83

24.00 6.00 4.00 4.00 252.00 37.87 1.43

3.00 6.00 0.50 0.50 4.73

3.00 6.00 0.50 0.50 4.73

39.60 6.00 6.60 7.00 25.87

24.00 6.00 4.00 4.00 144.00 21.31 0.82

25.20 6.00 4.20 5.00 18.48

10.00 7.50 1.33 2.00 60.00 13.32 0.34

10.50 6.00 1.75 2.00 7.39

10.00 7.50 1.33 1.50 60.00 9.99 0.34

12.00 6.00 2.00 2.00 7.39

12.00 6.00 2.00 2.00 72.00 10.66 0.41

14.40 6.00 2.40 2.50 9.24

1,096.91 22.19

16MMØ 472.22

12MMØ 227.38

10MMØ 397.32

TIE WIRE 22.19

70.00 5.60 12.50 18.00 175.00 66.53 0.99

70.00 6.00 11.67 17.00 62.83

133.33 6.00 22.22 23.00 988.89 85.01 5.60

133.33 5.60 23.81 24.00 88.70

Page 31: Tiao Him - Lab

40.00 6.00 13.33 14.00 74.59

12.50 6.00 4.17 5.00 26.64

133.33 6.00 22.22 23.00 85.01 0.00

133.33 5.60 23.81 24.00 88.70

578.02 6.59

12MMØ 101.23 18.99 10MMØ 476.78 128.86 TIE WIRE 6.59

16MMØ 151.52

12MMØ 53.30

10MMØ 55.50

TIE WIRE 4.00

Page 32: Tiao Him - Lab

168.00 7.50 6.00 784.00 14,112.00 1,988.70 95.86

84.00 7.50 559.65

588.00 6.00 2,175.60

24.00 12.00 6.00 162.00 2,916.00 454.56 19.81

12.00 12.00 127.92

41.00 6.00 151.70

8.00 12.00 6.00 184.00 1,104.00 151.52 7.50

4.00 12.00 42.64

46.00 6.00 170.20

5,822.49 387.48 698.00 12.00 8.00 162.00 1,296.00 151.52 8.80

4.00 12.00 42.64

1.00 6.00 9.47

1.00 7.50 11.84

1.00 6.00 9.47

1.00 10.50 16.57

2.00 6.00 18.94

2.00 6.00 18.94

41.00 6.00 151.70

56.00 7.50 8.00 784.00 6,272.00 662.90 42.60

28.00 7.50 186.55

1.00 7.50 11.84

0.00

16.00 6.00 151.52

2.00 12.00 37.88

10.00 9.00 142.05

4.00 6.00 37.88

196.00 6.00 725.20

32.00 12.00 8.00 162.00 5,184.00 606.08 35.21

16.00 12.00 170.56

4.00 6.00 37.88

4.00 7.50 47.35

4.00 6.00 37.88

4.00 10.50 66.29

8.00 6.00 75.76

8.00 6.00 75.76

41.00 6.00 151.70

32.00 12.00 8.00 41.00 1,312.00 606.08 8.91

16.00 12.00 170.56

16.00 6.00 151.52

8.00 12.00 151.52

16.00 6.00 151.52

184.00 6.00 680.80

5,568.17 95.53 92328.00 12.00 41.00 185.00 7,585.00 3,496.48 51.52

370.00 10.50 3,451.18

Page 33: Tiao Him - Lab

246.00 7.50 41.00 85.00 3,485.00 1,638.98 23.67

170.00 10.50 1,585.68

10,172.31 75.19 76

Page 34: Tiao Him - Lab

#REF!#REF!

Page 35: Tiao Him - Lab

FINISHING WORKS PLASTERING WORKS

MARK LENGTH HEIGHT FACE

walls

Exterior/Interior Plastering

Total

Computation: Cement 834.98 say 835.00 bags Sand 46.39 say 50.00 m³

TILE WORKS

MARK LENGTH WIDTH say

Ground Floor

24"x24"Homogenous floor tiles

Library 10.00 7.00 16.67 17.00 Moot Court 9.30 7.00 15.50 16.00

SBO/SAS office 4.25 7.00 7.08 8.00 Deans office 6.75 5.00 11.25 12.00

12"x12"Homogenous floor tiles Comport room (floor) 6.75 5.00 22.50 23.00 Comport room (floor) 6.75 5.00 22.50 23.00

Comport room (wall) 14.00 2.20 46.67 47.00 Comport room (wall) 10.00 2.20 33.33 34.00 Comport room (wall) 4.60 2.20 15.33 16.00 Comport room (wall) 5.00 2.20 16.67 17.00

24"x24"Homogenous floor tiles Class room 10.00 7.00 16.67 17.00

4.00 10.00 6.67 7.00 9.30 7.00 15.50 16.00 9.30 7.00 15.50 16.00

hallways 3.00 50.00 5.00 5.00 lobbies 5.15 7.00 8.58 9.00 porch 2.00 6.00 3.33 4.00

platform 10.00 4.20 16.67 17.00 balcony 6.20 6.00 10.33 11.00

Entry along canopy area 6.00 6.00 10.00 10.00 fire scape areas 2.00 5.00 3.33 4.00 stair & landing 7.00 4.50 11.67 12.00

NO. OF SIMILAR

STRUCTURES

(length) no. of pcs.

Page 36: Tiao Him - Lab

3.70 4.50 6.17 7.00 2nd Floor

24"x24"Ceramic floor tiles area-1 8.00 7.00 13.33 14.00

cement fin. w/ h2o proofing area-1 3.00 4.50

3rd Floor 24"x24"Ceramic floor tiles

area-1 8.00 7.00 13.33 14.00

cement fin. w/ h2o proofing area-1 3.00 4.50

roof deck cement fin. w/ h2o proofing 8.00 7.00

area-1 3.00 4.50

CEILING WORKS

MARK LENGTH WIDTH say

2nd floor hardiflex ceiling board

open ceiling 8.50 5.00

1.20 2.00

total

MARK LENGTH WIDTH say

2nd floor double furring channel

open ceiling 8.50 5.00 21.25 22.00

1.20 2.00 1.20 2.00

total

MARK LENGTH comm'l. length say

2nd floor wall angle

open ceiling 42.40 3.00 14.13 15.00

total

MARK LENGTH WIDTH say

2nd floor carrying channel

open ceiling 8.50 5.00 7.08 8.00

total

PAINTING WORKS ceiling area 89.80 mark 1st coating 2nd coating 3rd coating

Flat latex paint 3.59 2.99 2.57

Masonry putty 4.49

latex color 0.45

sand paper 5.99

(length) no. of pcs.

(length) no. of pcs.

(length) no. of pcs.

(length) no. of pcs.

Page 37: Tiao Him - Lab

roller brush paint brush stupa rug

PAINTING WORKS wall area 370.28 mark 1st coating 2nd coating 3rd coating

Flat latex paint 14.81

Semi-gloss Latex 14.81 12.34 12.34

Easytite with hardener latex color 3.70

sand paper 74.06

roller brush paint brush stupa rug

Painting door area 27.00

mark 1st coating 2nd coating 3rd coating

QDE paint 0.90 0.54 Easytite with hardener 0.36

Paint thinner 0.50

tinting color 0.11

sand paper 5.40

roller brush paint brush stupa rug

Painting Metal 336.34 mark 1st coating 2nd coating 3rd coating

QDE paint 11.21 6.73 Easytite with hardener 3.36

Paint thinner 84.09

tinting color sand paper roller brush paint brush stupa rug

Painting Exterior wall 1,640.16 mark 1st coating 2nd coating 3rd coating

Flat latex paint 54.67

Semi-gloss Latex 54.67 41.00 32.80

latex color 8.20

Patching Compound sand paper 164.02

Page 38: Tiao Him - Lab

roller brush paint brush stupa rug

Painting Exposed Conc. 56.89 mark 1st coating 2nd coating 3rd coating

Flat latex paint 1.90

Semi-gloss Latex 1.90 1.42 1.14

latex color 0.28

sand paper 5.69

roller brush paint brush stupa rug

TOILET PARTITIONS

MARK LENGTH WIDTH

Phenolic board female 1.50 1.60 4.00 20.16

0.20 1.60 2.00 1.34 0.40 1.60 3.00 4.03

male 1.50 1.60 2.00 10.08 0.20 1.60 2.00 1.34 0.40 1.60 1.00 1.34

urinal partitions 0.45 0.90 6.00 5.10 total 43.41

DOORS

MARK LENGTH WIDTH

Phenolic board female 0.60 1.60 4.00 8.06 male 0.60 1.60 2.00 4.03

total 12.10

DECORATIVE STONE

MARK LENGTH WIDTH total Area (m²) say

wall angle Area-1 9.00 1.00 36.00 36.00 Area-2 1.75 5.00 17.50 18.00 Area-3 9.50 2.00 38.00 18.00 Area-4 9.50 1.00 19.00 19.00 Area-5 9.00 0.60 10.80 11.00

total 102.00 25.50

ALUM. CLADDING

MARK LENGTH WIDTH total Area (m²) say

wall angle Area-1 5.70 1.50 34.20 18.00

total no. of unit total

Area (m²)

total no. of unit total

Area (m²)

Page 39: Tiao Him - Lab

5.70 0.50 11.40 3.00

Area-2 17.70 1.50 53.10 54.00 total 75.00

FINISHING WORKS(Second floor) PLASTERING WORKS

MARK LENGTH HEIGHT FACE

walls

Exterior/Interior Plastering Err:509 Err:509 Err:509 2.00

Total

Computation: Cement Err:509 say 500.00 bags Sand Err:509 say 35.00 m³

TILE WORKS

MARK LENGTH WIDTH say

Ground Floor concrete pavers

27.50 2.40 24"x24"Granite tiles

gen. merch. 10.00 4.00 16.67 17.00 asessment area 5.00 5.20 8.33 9.00

souvinir area 7.00 4.20 11.67 12.00 photocopy/printing 12.00 8.00 20.00 20.00

300x300mm tile 1.60 1.50 5.33 6.00

Toilet 5.90 1.60 400x400mm tile 1.60 1.50 5.33 6.00

Stairs Peeble washed out 11.00 2.00

mezz. Floor concrete pavers

27.50 2.40 24"x24"Granite tiles open room storage 4.00 3.00

1,2,3,4 16.00 6.00 Corridor

plain cement fin. 29.00 2.25 Stairs

Peeble washed out 11.00 2.00

2nd floor plain cement fin.

corridor-1 27.50 2.25 corridor-2 27.50 2.40

24"x24"Granite tiles dig./audio visual 8.00 8.00

NO. OF SIMILAR

STRUCTURES

(length) no. of pcs.

Page 40: Tiao Him - Lab

photo studio 4.00 8.00 wellness room 4.00 8.00

office 4.00 8.00 300x300mm tile

toilet 1.50 1.45 5.00 5.00 Toilet 5.90 1.60

CEILING WORKS

MARK LENGTH WIDTH say

4th floor

.19mx3mts long

Hall way-1 37.40 2.00

Hall way-2 20.70 2.00

Hall way-3 32.00 2.00

Hall way-4 13.00 2.00

Hall way-5 10.00 4.00

1/4"thk. Hardiflex

hall way 2.00 2.00 6.00

total

MARK LENGTH WIDTH

double furring channel hallway 280.00 2.00 2,800.00 5.00

total

MARK LENGTH say

(length) no. of pcs.

total length (l.m)

comm'l. length(m)

comm'l. length(m)

total length (l.m)

Page 41: Tiao Him - Lab

wall angle

hallway 560.00 3.00 186.67 187.00

total 560.00 187.00

total area(m²) length/sq.m comm'l. length

carrying channel 24.00 1.50 5.00 7.20

double furring clip 5.00 15.00

total area(m²) no. of pcs./sq.m

blind rivets 24.00 20.00 480.00

total lenght(l.m²) kgs./l.m

1" conc. Nail 560.00 0.03 14.00

Painting ceiling area 24.00 mark 1st coating 2nd coating 3rd coating

Flat latex paint 0.80

Semi-gloss Latex 0.80 0.60 0.40

Easytite with hardener 0.24

latex color 0.12

sand paper 2.40

roller brush paint brush stupa rug

Painting door area #REF!

mark 1st coating 2nd coating 3rd coating

QDE paint #REF! #REF! Easytite with hardener #REF!

Paint thinner 0.75

tinting color #REF!

sand paper #REF!

roller brush paint brush stupa rug

Painting Metal 139.20 mark 1st coating 2nd coating 3rd coating

QDE paint 4.64 2.78 Easytite with hardener 1.39

Paint thinner 0.46

tinting color sand paper roller brush paint brush stupa rug

Page 42: Tiao Him - Lab

Painting Interior wall Err:509 mark 1st coating 2nd coating 3rd coating

Flat latex paint Err:509

Semi-gloss Latex Err:509 Err:509 Err:509

latex color Err:509

sand paper Err:509

roller brush paint brush stupa rug

TOILET PARTITIONS

MARK LENGTH WIDTH

Phenolic board female 1.50 1.60 4.00 20.16

0.20 1.60 2.00 1.34 0.40 1.60 3.00 4.03

male 1.50 1.60 2.00 10.08 0.20 1.60 2.00 1.34 0.40 1.60 1.00 1.34

urinal partitions 0.45 0.90 6.00 5.10 total 43.41

DOORS

MARK LENGTH WIDTH

Phenolic board female 0.60 1.60 4.00 8.06 male 0.60 1.60 2.00 4.03

total 12.10

DECORATIVE STONE

MARK LENGTH WIDTH total Area (m²) say

wall angle Area-1 9.00 1.00 36.00 36.00 Area-2 1.75 5.00 17.50 18.00 Area-3 9.50 2.00 38.00 18.00 Area-4 9.50 1.00 19.00 19.00 Area-5 9.00 0.60 10.80 11.00

total 102.00 25.50

ALUM. CLADDING

MARK LENGTH WIDTH total Area (m²) say

wall angle Area-1 1.50 16.00 48.00 48.00 Area-2 1.50 14.00 42.00 42.00 Area-3 7.00 4.00 28.00 28.00

total 118.00

total no. of unit total

Area (m²)

total no. of unit total

Area (m²)

Page 43: Tiao Him - Lab

Quantity of cement and sand for plaster per square meter area

Mixture Cement in bags Thickness of Plaster class 8 mm 12mm

A 0.144 0.216

B 0.096 0.144

C 0.072 0.108

D 0.06 0.09

Sand 0.008 0.012

AREA (m²)

1,855.51

say

- 11.67 12.00 204.00 70.00 11.67 12.00 192.00 65.10 11.67 12.00 96.00 29.75 8.33 9.00 108.00 600.00 33.75

- 16.67 17.00 391.00 391.00 33.75 16.67 17.00 391.00 391.00 33.75

782.00 7.33 8.00 376.00 30.80 58.23 7.33 8.00 272.00 22.00 7.33 8.00 128.00 10.12 7.33 8.00 136.00 912.00 11.00

11.67 12.00 204.00 70.00 16.67 17.00 119.00 40.00 11.67 12.00 192.00 65.10 11.67 12.00 192.00 65.10 83.33 84.00 420.00 150.00 11.67 12.00 108.00 36.05 10.00 10.00 40.00 12.00 7.00 7.00 119.00 42.00 10.00 10.00 110.00 37.20 10.00 10.00 100.00 36.00 8.33 9.00 36.00 10.00 7.50 8.00 96.00 31.50

(width) no. of pcs.

total no. of pcs.

total no. of pcs.

total area (m²)

Page 44: Tiao Him - Lab

7.50 8.00 56.00 1,792.00 16.65

- 11.67 12.00 168.00 56.00

168.00

13.50

- 11.67 12.00 168.00 56.00 182.00

168.00 #REF!

13.50 #REF!

56.00 13.50 69.50

say say

42.50 14.76 15.00

2.40 0.83 1.00

44.90 16.00 pcs

say furring clip say

21.25 22.00 44.00 21.25 12.50 265.63 270.00

1.20 2.00 4.00 3.00 5.00 15.00 20.00

48.00 pcs 290.00 pcs

say say

15.00

- 15.00

say say

42.50 8.00

42.50 8.00

3rd coating gal say unit

9.15 4.00 0.90 1.00 tin

4.00 - 4.00 gal

1.00 lits

20.00 pcs 5,716.80 114.34

(width) no. of pcs.

total no. of pcs.

total area (m²)

no. of pcs.

(width) no. of pcs.

total no. of pcs.

no. of pcs.

(width) no. of pcs.

total no. of pcs.

total area (m²)

no. of pcs.

(width) no. of pcs.

total no. of pcs.

total area (m²)

no. of pcs.

Page 45: Tiao Him - Lab

2.00 pcs

5.00 pcs

5.00 kg

1 Acrylic semi-gloss latext paint finish, boysen white

3rd coating gal say unit

4.00 3.70 4.00 tin

39.50 4.00 9.87 10.00 tin

4.00 lits

80.00 pcs 5,716.80 114.34

5.00 pcs

12.00 pcs

10.00 kg

1 Acrylic semi-gloss latext paint finish, boysen white2 Flat latex paint boysen white3 Flat wall enamel paint

3rd coating gal/tin say unit 4 Q.D.E. Paint Boysen 1.44 2.00 gal 5 Masonry putty

1.00 gal 6 Easytite w/ Hardiner 1.00 gal 7 Perlite (patching compound) 0.50 lits 8 Stikwel 20.00 pcs 9 Sand paper

pcs 10 Paint Rower 4.00 pcs 11 Paint Brush 2.00 kg 12 Paint Thinner

13 Consumable like tinting colors

3rd coating gal/tin say unit

17.94 4.00 4.48 5.00 tin

gal

5.00 gal

2.00 lits

pcs

4.00 pcs

10.00 pcs

5.00 kg

3rd coating gal say unit

4.00 13.67 14.00 tin 15.00

128.48 4.00 32.12 35.00 tin 37.00

9.00 lits

2.00 sacks

200.00 pcs

Page 46: Tiao Him - Lab

8.00 pcs

15.00 pcs

10.00 kg

3rd coating gal say unit

4.00 0.47 1.00 gal

4.46 4.00 1.11 2.00 gal

10.00 lits

10.00 pcs

1.00 pcs

2.00 pcs

3.00 kg

say

say

unit

917.40 811.80 224.40

26.00 6.80 1,953.60 7.00

unit

Page 47: Tiao Him - Lab

AREA (m²)

Err:509Err:509Err:509

say

66.00

6.67 7.00 119.00 40.00 8.67 9.00 81.00 26.00 7.00 7.00 84.00 29.40 13.33 14.00 280.00 96.00

191.40 sq.m 5.00 5.00 30.00 2.40 sq.m

9.44 sq.m 5.00 5.00 30.00 2.40 sq.m

11.84 22.00 sq.m

66.00

12.00 96.00

108.00 65.25

65.25 sq.m 22.00 sq.m

61.88 66.00

127.88 sq.m

64.00

(width) no. of pcs.

total no. of pcs.

total no. of pcs.

total area (m²)

Page 48: Tiao Him - Lab

32.00 32.00 32.00

160.00 sq.m 4.83 5.00 25.00 2.18 sq.m

9.44 sq.m 11.62 sq.m

Quantity of cement and sand for plaster per square meter area

Mixture Cement in bags Thickness of Plaster class 8 mm 12mm

A 0.144 0.216

B 0.096 0.144

C 0.072 0.108

D 0.06 0.09

Sand 0.008 0.012

say say

74.80 131.23 132.00

41.40 72.63 73.00

64.00 112.28 113.00

26.00 45.61 46.00

40.00 70.18 71.00

246.20 435.00

24.00 8.33 9.00

24.00 8.33 9.00 pcs

say unit area (m²)

560.00 560.00 pcs 560.00 3,500.00 907.00 560.00 pcs

unit

(width) no. of pcs.

total no. of pcs.

total area (m²)

no. of pcs.

total no. of pcs.

Page 49: Tiao Him - Lab

pcs

pcs

4.00 pcs

75.00

240.00 pcs 240.00

0.50 kgs

3rd coating gal say unit

4.00 0.20 2.00 gal

1.80 4.00 0.45 4.00 gal

4.00 gal

2.00 lits

30.00 pcs 5,716.80 114.34

2.00 pcs

5.00 pcs

5.00 kg

1 Acrylic semi-gloss latext paint finish, boysen white2 Flat latex paint boysen white3 Flat wall enamel paint

3rd coating gal/tin say unit 4 Q.D.E. Paint Boysen#REF! 4.00 #REF! 3.00 tin 5 Masonry putty

4.00 gal 6 Easytite w/ Hardiner 4.00 gal 7 Perlite (patching compound) 1.00 lits 8 Stikwel 50.00 pcs 9 Sand paper

pcs 10 Paint Rower 8.00 pcs 11 Paint Brush 10.00 kg 12 Paint Thinner

13 Consumable like tinting colors

3rd coating gal/tin say unit

7.42 4.00 1.86 8.00 gal

3.00 gal

5.00 gal

lits

pcs

pcs

5.00 pcs

5.00 kg

Page 50: Tiao Him - Lab

3rd coating gal say unit

4.00 Err:509 10.00 tin

Err:509 4.00 Err:509 22.00 tin

6.00 lits

330.00 pcs

15.00 pcs

20.00 pcs

20.00 kg

say

say

unit

917.40 811.80 224.40

26.00 6.80 1,953.60 7.00

unit

Page 51: Tiao Him - Lab

Quantity of cement and sand for plaster per square meter area

Cement in bags Thickness of Plaster 16mm 20mm 25mm

0.288 0.36 0.45

0.192 0.24 0.3

0.144 0.18 0.225

0.12 0.15 0.188

0.016 0.02 0.025

59.00 3.67 4.00 472.00

Page 52: Tiao Him - Lab

Acrylic semi-gloss latext paint finish, boysen white

Acrylic semi-gloss latext paint finish, boysen white gals 10.00 5.00 50.00

Flat latex paint boysen white gals 6.00 5.00 30.00

Flat wall enamel paint gals 2.00 5.00 10.00

Q.D.E. Paint Boysen gals 1.00 5.00 5.00

Masonry putty gals 1.00 5.00 5.00

Easytite w/ Hardiner ltrs 2.00 5.00 10.00

Perlite (patching compound) ltrs 10.00 5.00 50.00

lits 1.00 5.00 5.00

Sand paper pcs 150.00 5.00 750.00

Paint Rower pcs 2.00 5.00 10.00

Paint Brush pcs 5.00 5.00 25.00

Paint Thinner gals 2.00 5.00 10.00

Consumable like tinting colors lits 2.00 5.00 10.00

Page 53: Tiao Him - Lab

Quantity of cement and sand for plaster per square meter area

Cement in bags Thickness of Plaster 16mm 20mm 25mm

0.288 0.36 0.45

0.192 0.24 0.3

0.144 0.18 0.225

0.12 0.15 0.188

0.016 0.02 0.025

Page 54: Tiao Him - Lab

Acrylic semi-gloss latext paint finish, boysen white gals 10.00 5.00 50.00

Flat latex paint boysen white gals 6.00 5.00 30.00

Flat wall enamel paint gals 2.00 5.00 10.00

Q.D.E. Paint Boysen gals 1.00 5.00 5.00

Masonry putty gals 1.00 5.00 5.00

Easytite w/ Hardiner ltrs 2.00 5.00 10.00

Perlite (patching compound) ltrs 10.00 5.00 50.00

lits 1.00 5.00 5.00

Sand paper pcs 150.00 5.00 750.00

Paint Rower pcs 2.00 5.00 10.00

Paint Brush pcs 5.00 5.00 25.00

Paint Thinner gals 2.00 5.00 10.00

Consumable like tinting colors lits 2.00 5.00 10.00

Page 55: Tiao Him - Lab

CONCRETE WORKS

MARKFOR ONE (1) STRUCTURE

LENGTH (m.)

C-1F-1 1.00 1.00 0.25 9.00 2.25 2.25 22.5037.00

WF-1 25.00 0.30 0.15 1.00 1.13 1.13 11.2521.00

GB 5.00 0.20 0.25 3.00 0.754.00 0.20 0.25 4.00 0.80 1.55 13.95

14.00C-1 0.25 0.25 4.30 9.00 2.42C-2 0.00C-1 0.00 2.42 25.00

42.00B-1 5.00 0.25 0.35 2.00 0.88

4.00 0.25 0.35 4.00 1.40B-2 5.00 0.30 0.40 1.00 0.60B-3 5.00 0.25 0.30 1.00 0.38B-4 2.12 0.20 0.25 1.00 0.11 3.36 30.20

31.00LB-1 2.00 0.20 0.30 1.00 0.12 0.12 1.08

2.00CB-1 1.20 0.20 0.30 2.00 0.14 0.14 1.30

2.00RB-1 5.00 0.20 0.25 2.00 0.50

4.00 0.20 0.25 4.00 0.80RB-2 5.00 0.25 0.30 1.00 0.38RB-3 5.00 0.15 0.25 1.00 0.19RB-4 2.12 0.15 0.20 1.00 0.06 1.93 17.33

18.00LB-2 2.00 0.15 0.25 1.00 0.08 0.08 0.67

1.00CB-2 1.20 0.15 0.25 2.00 0.09 0.09 0.81

1.00SLAB ON FILL 7.00 4.00 0.15 1.00 4.20

1.50 2.50 0.125 1.00 0.47 4.67 47.0039.00

SUSPENDED SLAB 5.00 4.00 0.10 1.00 2.005.00 1.88 0.10 1.00 0.942.12 2.00 0.10 1.00 0.421.20 2.00 0.10 1.00 0.24 3.60 32.44

STAIRS 3.20 2.13 0.13 1.00 0.851.20 9.00 0.10 1.00 1.08 1.93 17.39

39.00Total 23.26 25.12 251.20

say 303.00

NO. OF SIMILAR

STRUCTURE

TOTAL VOLUME

(m³)WIDTH

(m.)HEIGHT

(m.)

Page 56: Tiao Him - Lab

1.13 2.252.50 5.000.56 1.131.50 3.00

0.78 1.551.00 2.00

1.50 2.502.50 5.00

1.68 3.362.00 4.000.06 0.120.10 0.200.07 0.140.10 0.20

0.96 1.931.00 2.000.04 0.080.05 0.100.05 0.090.05 0.10

2.50 5.002.50 5.00

1.80 3.60

0.97 1.932.50 5.00

12.56 25.1216.00 32.00 351.00

Page 57: Tiao Him - Lab

Rate/day Rate/hourProj. Engineer 600.00 75.00 Construction Foreman 450.00 56.25 Mason 375.00 46.88 Carpenter 375.00 46.88 H.E. Operator 400.00 50.00 L.E. Operator 325.00 40.63 Driver 300.00 37.50 Steelman 300.00 37.50 Labor 250.00 31.25 Painter 350.00 43.75 Roof Installer 350.00 43.75 Welder 375.00 46.88 Glass Installer 300.00 37.50 Plumber 325.00 40.63 Electrician 325.00 40.63

Page 58: Tiao Him - Lab

Rate/day Rate/hourRoad Grader 7,500.00 Payloader 7,000.00 Road Roller 6,500.00 Water Truck 4,500.00 Transit Mixer 1,500.00 One Bagger Mixer 400.00 Concrete Cutter 400.00 Concrete Vibrator 250.00 Welding Machine 450.00 Electric grinder 150.00 Bar cutter 200.00

Page 59: Tiao Him - Lab

Description Amount unitPortland Cement 225.00 /bagsScreened Gravel 450.00 /cu.mWashed Sand 400.00 /cu.mAsphalt Sealant 110.00 /litAssorted Nails 75.00 /kg16mmØ Def. bars 40.00 /kgForm Lumber 2"x5"x12' Coco lumber 24.00 /bd.ftAggregate Sub-Basecoarse 400.00 /cu.m#16 G.I. tie wire 60.00 /kg1/2"x4'x8' Form Plywood 560.00 /pcAsst. Form lumber 24.00 /bd.ft6" CHB 10.50 /pcTile Adhessive 190.00 /bags16"x16" Ceramic tile 85.00 /pc16"x16" Outdoor tile 65.00 /pcTile Grout 25.00 /kgFlat Latex paint 1,810.00 /tinSemi-gloss Latex paint 2,370.00 /tinLatex color 120.00 /litPatching compound 15.00 /kgStickwel 195.00 /litRoller brush 100.00 /pcPaint brush 45.00 /pcSandpaper 25.00 /pcStupa Rag 20.00 /kgTile Roof Roofing sheet (.5mm thk.) 420.00 /sq.m

Ridge roll 450.00 /pc

Gutter 450.00 /pc

Tekscrew 1.75 /pc

Silicon Sealant 150.00 /tube

Blind Rivets 500.00 /box

Touch-up paint 150.00 /lit

1.5mm x 2"x6" CEE purlins 650.00 /pc

1.2mm x 2"x4" CEE purlins 397.00 /pc

1.0mm x 2"x3" CEE purlins 400.00 /pc

10mmØ Plain Round bar 138.00 /pc

1/4" x 10"x10" Base plate 250.00 /pc

Welding rod 1,200.00 /box

12mmØ x 10" Anchor bolts w/ 120.00 /pc

8"x8" Glazed tile 32.00 /pc

8"x8" Unglazed tile 32.00 /pc

Tile trim 78.00 /pc

Tile Grout 25.00 /kg

4"Ø Diamond cutter 450.00 /pc

3"Ø PVC pipe 460.00 /pc

Page 60: Tiao Him - Lab

3"Ø PVC Elbow 1/4 bend 53.00 /pc

2"Ø Stainless Steel pipe 3,250.00 /pc

3/16"x1" Flat bar 235.00 /pc

3/4"x3/4" Square bar 245.00 /pc

Welding rod/Accessories 2,500.00 /lot

4"Ø Grinding disk 65.00 /pc

Water closets w/ Accessories 2,800.00

Wall hang lavatory w/ Accessories 1,800.00

Soap holder 250.00

Tissue holder 250.00

Towel holder 450.00

4"x4" Floor drain 350.00

Ordinary faucet 65.00

Clean water line pipes and accessories 2,000.00

Sewer pipe line and accessories 3,500.00

2x40W FL lamp w/ housing 1,500.00

25W CFL 60.00

4"x4" Pinlight 250.00

Receptacle 4"Ø 50.00

Single pole switch 120.00

Two pole switch 165.00

3-Way switch 210.00

Main ACB 6-holes 1,850.00

4"x4" Junction box 35.00

2"x4" Utility box 35.00

1/2"Ø PVC pipe x 3.00 mts. 61.00

3.5mm² THHN wire 3,207.50

14mm² THHN wire 85.84

1'Ø PVC pipe x 3.00 mts. 102.00

1"Ø Long sweep elbow 38.00

1/2"Ø PVC Long sweep elbow 25.00

1"Ø RSC pipe x 3.00 mts. 420.00

1"Ø Entrance cap 65.00

3-Pole secondary rack 285.00

1"Ø Long sweep elbow (RSC) 85.00

Electrical tape 45.00

Hardiflex ceiling board 420.00

0.40mm 19mm x 50mm x 5m

Double furring channel 115.00

0.80mm 12mm x 38mm x 5m

Carrying Channel 140.00

0.40mm 25mm x 25mm x 3m

Wall angle 85.00

W-Clip 8.00

1-1/2" Concrete nail 90.00

Mesh tape 150.00

Blind rivets 500.00

Page 61: Tiao Him - Lab

DETAILED UNIT PRICE ANALYSIS

PROJECT NAME:

Item No./Description: 103 Layout and Excavation Works

Unit of Measurement: cu.m.

Output per day: 18.96 cu.m. /day

Quantity: 26.19 cu.m.

Designation No. Person No. of Days Daily Rate Amount

A. Labor

a. Construction Foreman/Eng'g Assist. 1 1.40 524.00 733.60

b. Skilled Laborer 2 1.40 366.00 1,024.80

b. Laborer 8 1.40 317.00 3,550.40

Sub-Total for A P 5,308.80

Name and Capacity No. of Units No. of Days Daily Rate Amount

B. Equipment

N/A

Sub-Total for B P -

C. Total (A+B) 5,308.80 D. Output per day = 18.96 cu.m. /day

Name and Specifications Quantity Unit Unit Cost Amount

E. Materials

a. 10pcs. - 2" x 4" x 10' Coco Lumber 0.1573 cu.m. 8,899.44 1,399.88

b. 12pcs. - 2" x 3" x 10' Coco Lumber 0.1180 cu.m. 8,899.44 1,050.13

c. 4" C.W. Nail 2 kgs. 85.00 170.00

d. Nylon Chord 1 roll 35.00 35.00

Sub-Total for E P 2,655.02

F. Direct Cost (C+E) 7,963.82

G. Overhead, Contingencies & Miscellaneous 7% per D.O. 22 s 2015 557.47

H. Contractor's Profit (CP) 8% per D.O. 22 s 2015 637.11

I. Value Added Tax (VAT) 5% per D.O. 22 s 2015 457.92

J. Total Cost 9,616.31

k. Total Unit Cost 367.16

Upgrading of Existing PVC Pipelines, Redevelopment of Water and

Sanitation System for ZC Conflict Area (Tiao Him) - Laboratory Building

Page 62: Tiao Him - Lab

DETAILED UNIT PRICE ANALYSIS

PROJECT NAME:

Item No./Description: 104 Embankment

Unit of Measurement: cu.m.

Output per day: 40.00 cu.m. /day

Quantity: 21.00 cu.m.

Designation No. Person No. of Days Daily Rate Amount

A. Labor

a. Construction Foreman/Eng'g Assist. 1 0.50 524.00 262.00

b. Skilled Laborer 2 0.50 366.00 366.00

b. Laborer 8 0.50 317.00 1,268.00

Sub-Total for A P 1,896.00

Name and Capacity No. of Units No. of Days Daily Rate Amount

B. Equipment

a. Plate Compactor 1 0.50 984.00 492.00

Sub-Total for B P 492.00

C. Total (A+B) 2,388.00 D. Output per day = 40.00 cu.m. /day

Name and Specifications Quantity Unit Unit Cost Amount

E.

a. Filling Materials (loose volume) 21 cu.m. 328.00 6,888.00

Note: Use Filling Materials for Backfill and Fill

Sub-Total for E P 6,888.00

F. Direct Cost (C+E) 9,276.00

G. Overhead, Contingencies & Miscellaneous 7% per D.O. 22 s 2015 649.32

H. Contractor's Profit (CP) 8% per D.O. 22 s 2015 742.08

I. Value Added Tax (VAT) 5% per D.O. 22 s 2015 533.37

J. Total Cost 11,200.77

k. Total Unit Cost 533.37

Upgrading of Existing PVC Pipelines, Redevelopment of Water and

Sanitation System for ZC Conflict Area (Tiao Him) - Laboratory Building

Materials (25% Shrinkage Factor)

Page 63: Tiao Him - Lab

DETAILED UNIT PRICE ANALYSIS

PROJECT NAME:

Item No./Description: SPL - 1 Soil Poisoning/ Termite Control

Unit of Measurement: sq.m.

Output per day:

Quantity: 54.00 sq.m.

Designation No. Person No. of Days Daily Rate Amount

A. Labor

a. Construction Foreman/Eng'g Assist. 1 1 524.00 524.00

Sub-Total for A P 524.00

Name and Capacity No. of Units No. of Days Daily Rate Amount

B. Equipment

N/A

Sub-Total for B P -

C. Total (A+B) 524.00 D. Output per day =

Name and Specifications Quantity Unit Unit Cost Amount

E. Materialsa.

Soil Poisoning/ Termite Control 54.00 sq.m. 58.00 3,132.00

Sub-Total for E P 3,132.00

F. Direct Cost (C+E) 3,656.00

G. Overhead, Contingencies & Miscellaneous 7% per D.O. 22 s 2015 255.92

H. Contractor's Profit (CP) 8% per D.O. 22 s 2015 292.48

I. Value Added Tax (VAT) 5% per D.O. 22 s 2015 210.22

J. Total Cost 4,414.62

k. Total Unit Cost 81.75

Upgrading of Existing PVC Pipelines, Redevelopment of Water and

Sanitation System for ZC Conflict Area (Tiao Him) - Laboratory Building

Job Order: Supply and Application of Chemicals

Page 64: Tiao Him - Lab

Page 64 of 91

DETAILED UNIT PRICE ANALYSIS

PROJECT NAME:

Item No./Description: 404 Reinforcing Steel

Unit of Measurement: kgs.

Output per day: 609.84 kgs. /day

Quantity: 873.83 kgs.

Designation No. Person No. of Days Daily Rate Amount

A. Labor

a. Construction Foreman/Eng'g Assist. 1 1.40 524.00 733.60

b. Skilled Laborer 10 1.40 366.00 5,124.00

b. Laborer 10 1.40 317.00 4,438.00

Sub-Total for A P 10,295.60

Name and Capacity No. of Units No. of Days Daily Rate Amount

B. Equipment

a. Bar Cutter 1 1.40 1,758.00 2,461.20

b. Bar Bender 1 1.40 2,812.00 3,936.80

c. Cargo Truck (10T, 270Hp) 1 0.10 8,816.00 881.60

Sub-Total for B P 7,279.60

C. Total (A+B) 17,575.20 D. Output per day = 609.84 kgs. /day

Name and Specifications Quantity Unit Unit Cost Amount

E. Materials

1. Column Footing

100.99 kgs. 34.77 3,511.49

#16 G.I. Tie-wire 1 kg. 63.00 63.00

2. Wall Footings

69.26 kgs. 40.21 2,784.94

33.00 kgs. 34.90 1,151.70

#16 G.I. Tie-wire 3 kgs. 63.00 189.00

3. Columns

229.76 kgs. 34.77 7,988.76

147.45 kgs. 34.90 5,145.86

#16 G.I. Tie-wire 9 kgs. 63.00 567.00

4. Lintel Beams

120.77 kgs. 40.21 4,856.16

60.74 kgs. 34.90 2,119.83

#16 G.I. Tie-wire 6 kgs. 63.00 378.00

Upgrading of Existing PVC Pipelines, Redevelopment of Water and

Sanitation System for ZC Conflict Area (Tiao Him) - Laboratory Building

16mm.Ø x 6.00m. Def. Reinforcing Steel

12mm.Ø x 6.00m. Def. Reinforcing Steel

10mm.Ø x 6.00m. Def. Reinforcing Steel

16mm.Ø x 6.00m. Def. Reinforcing Steel

10mm.Ø x 6.00m. Def. Reinforcing Steel

12mm.Ø x 6.00m. Def. Reinforcing Steel

10mm.Ø x 6.00m. Def. Reinforcing Steel

Page 65: Tiao Him - Lab

Page 65 of 91

5. Floor Slabs

110.36 kgs. 34.90 3,851.56

#16 G.I. Tie-wire 1.50 kgs. 63.00 94.50

Sub-Total for E P 32,701.80

F. Direct Cost (C+E) 50,277.00

G. Overhead, Contingencies & Miscellaneous 7% per D.O. 22 s 2015 3,519.39

H. Contractor's Profit (CP) 8% per D.O. 22 s 2015 4,022.16

I. Value Added Tax (VAT) 5% per D.O. 22 s 2015 2,890.93

J. Total Cost 60,709.48

k. Total Unit Cost 69.48

10mm.Ø x 6.00m. Def. Reinforcing Steel

Page 66: Tiao Him - Lab

Page 66 of 91

DETAILED UNIT PRICE ANALYSIS

PROJECT NAME:

Item No./Description: 405 Structural Concrete

Unit of Measurement: cu.m.

Output per day: 4.41 cu.m./day

Quantity: 14.92 cu.m.

Designation No. Person No. of Days Daily Rate Amount

A. Labor

a. Construction Foreman/Eng'g Assist. 1 3.40 524.00 1,781.60

b. Skilled Laborer 10 3.40 366.00 12,444.00

b. Laborer 10 3.40 317.00 10,778.00

Sub-Total for A P 25,003.60

Name and Capacity No. of Units No. of Days Daily Rate Amount

B. Equipment

N/A

Sub-Total for B P -

C. Total (A+B) 25,003.60 D. Output per day = 4.41 cu.m. /day

Name and Specifications Quantity Unit Unit Cost Amount

E. Materials

1. Column Footing

Volume: 2.00 cu.m.

Portland Cement 20 bags 260.00 5,200.00

Washed Sand 1 cu.m. 1,000.00 1,000.00

Gravel 2 cu.m. 1,000.00 2,000.00

2. Wall Footings

Volume: 1.53 cu.m.

Portland Cement 16 bags 260.00 4,160.00

Washed Sand 1 cu.m. 1,000.00 1,000.00

Gravel 2 cu.m. 1,000.00 2,000.00

3. Columns

Volume: 2.28 cu.m.

Portland Cement 23 bags 260.00 5,980.00

Washed Sand 1.50 cu.m. 1,000.00 1,500.00

Gravel 2.50 cu.m. 1,000.00 2,500.00

4. Lintel Beams

Volume: 1.02 cu.m.

Portland Cement 10 bags 260.00 2,600.00

Washed Sand 0.50 cu.m. 1,000.00 500.00

Upgrading of Existing PVC Pipelines, Redevelopment of Water and

Sanitation System for ZC Conflict Area (Tiao Him) - Laboratory Building

Page 67: Tiao Him - Lab

Page 67 of 91

Gravel 1 cu.m. 1,000.00 1,000.00

5. Floor Slabs

Volume: 8.10 cu.m.

Portland Cement 81 bags 260.00 21,060.00

Washed Sand 4.50 cu.m. 1,000.00 4,500.00

Gravel 8.50 cu.m. 1,000.00 8,500.00

Sub-Total for E P 63,500.00

F. Direct Cost (C+E) 88,503.60

G. Overhead, Contingencies & Miscellaneous 7% per D.O. 22 s 2015 6,195.25

H. Contractor's Profit (CP) 8% per D.O. 22 s 2015 7,080.29

I. Value Added Tax (VAT) 5% per D.O. 22 s 2015 5,088.96

J. Total Cost 106,868.10

k. Total Unit Cost 7,160.34

Page 68: Tiao Him - Lab

Page 68 of 91

DETAILED UNIT PRICE ANALYSIS

PROJECT NAME:

Item No./Description: SPL - 2 Roofing Works

Unit of Measurement: sq.m.

Output per day: 5.37 sq.m./day

Quantity: 109.17 sq.m.

Designation No. Person No. of Days Daily Rate Amount

A. Labor

a. Construction Foreman/Eng'g Assist. 1 20 524.00 10,480.00

b. Skilled Laborer 6 20 366.00 43,920.00

b. Laborer 4 20 317.00 25,360.00

Sub-Total for A P 79,760.00

Name and Capacity No. of Units No. of Days Daily Rate Amount

B. Equipment

a. Welding Machine 1 6 3,128.00 18,768.00

b. Angular Grinder 1 6 300.00 1,800.00

Sub-Total for B P 20,568.00

C. Total (A+B) 100,328.00 D. Output per day = 5.37 sq.m. /day

Name and Specifications Quantity Unit Unit Cost Amount

E. Materials

1. Trusses9 pcs. 1,130.00 10,170.00

5 pcs. 890.00 4,450.00

6011 Welding Rod 3 kgs. 144.00 432.00

2. Channel Purlins

#14 x 50mm. x 100mm. x 6.00m. G.I. C-Purlins 31 pcs. 532.00 16,492.00

1 pc. 1,130.00 1,130.00

4 pcs. 175.00 700.00

6011 Welding Rod 2 kgs. 144.00 288.00

3. Fascia Framing and Backing0.4mm. x 19mm. x 50mm. x 5.0m. Furring Channel 14 pcs. 108.00 1,512.00

1 box 251.00 251.00

4. Roofing Sheets, Gutters and Ridge Rolls9 pcs. 802.00 7,218.00

12 pcs. 528.00 6,336.00

Upgrading of Existing PVC Pipelines, Redevelopment of Water and

Sanitation System for ZC Conflict Area (Tiao Him) - Laboratory Building

4mm. Thk. x 50mm. x 50mm. x 6.00m. M.S. Angle

Bar

4mm. Thk. x 38mm. x 38mm. x 6.00m. M.S. Angle Bar

4mm. Thk. x 75mm. x 75mm. x 6.00m. M.S. Angle

Bar (Cleat Angle)

10mm.Ø x 6.00m. Plain Round Bar (Sag Rod)

4mm.Ø x 10mm. Aluminum Blind Rivets

0.4mm. Thk. x 0.45m x 3.65m. Galvalume Spanish Gutter, Pre-painted0.4mm. Thk. x 0.40m. x 2.40m. Galvalume Ridge Roll, Pre-painted

Page 69: Tiao Him - Lab

Page 69 of 91

5 pcs. 802.00 4,010.00

400 pcs. 4.50 1,800.00

1 sht. 272.00 272.00

40 shts. 3,268.00 130,720.00

1,040 pcs. 2.00 2,080.00

5. Others4 pcs. 175.00 700.00

10mm.Ø Standard Turnbuckle 8 pcs. 115.00 920.00

4 pcs. 148.00 592.00

Sub-Total for E P 190,073.00

F. Direct Cost (C+E) 290,401.00

G. Overhead, Contingencies & Miscellaneous 7% per D.O. 22 s 2015 20,328.07

H. Contractor's Profit (CP) 8% per D.O. 22 s 2015 23,232.08

I. Value Added Tax (VAT) 5% per D.O. 22 s 2015 16,698.06

J. Total Cost 350,659.21

k. Total Unit Cost 3,212.05

0.4mm. Thk. x 0.45m. x 3.65m. Galvalume Spanish Flashing, Pre-painted

3mm.Ø x 10mm. Alum. Blind Rivet

Ga. 26 x 1.20m. x 2.40m. G.I. Plain Sheet (Gutter Strap)0.4mm. Thk. x 800mm. x 3.80m. Ordinary Corrugated (915) Galvalume Roofing Sheet, Pre-painted4mm x 38mm Tekscrew (for metal) w/ neoprene washer

10mm.Ø x 6.00m. Plain Round Bar (Crossing

Bracing)

100mm.Ø Grinding Wheel

Page 70: Tiao Him - Lab

DETAILED UNIT PRICE ANALYSIS

PROJECT NAME:

Item No./Description: SPL - 3a Setting of 100mm. CHB

Unit of Measurement: sq.m.

Output per day: 20.00 sq.m./day

Quantity: 87.36 sq.m.

Designation No. Person No. of Days Daily Rate Amount

A. Labor

a. Construction Foreman/Eng'g Assist. 1 4 524.00 2,096.00

b. Skilled Laborer 2 4 366.00 2,928.00

b. Laborer 4 4 317.00 5,072.00

Sub-Total for A P 10,096.00

Name and Capacity No. of Units No. of Days Daily Rate Amount

B. Equipment

N/A

Sub-Total for B P -

C. Total (A+B) 10,096.00 D. Output per day = 20.00 sq.m. /day

Name and Specifications Quantity Unit Unit Cost Amount

E. Materials

a. 100mm. x 200mm. x 400mm. CHB (NLB) 1,092 pcs. 14.00 15,288.00

b. Washed Sand 4 cu.m. 1,000.00 4,000.00

c. Portland Cement 46 bags 260.00 11,960.00

d. 66 pcs. 129.00 8,514.00

e. #16 G.I. Tie-wire 3 kgs.. 63.00 189.00

f. Hacksaw Blade 2 pcs. 43.00 86.00

Sub-Total for E P 40,037.00

F. Direct Cost (C+E) 50,133.00

G. Overhead, Contingencies & Miscellaneous 7% per D.O. 22 s 2015 3,509.31

H. Contractor's Profit (CP) 8% per D.O. 22 s 2015 4,010.64

I. Value Added Tax (VAT) 5% per D.O. 22 s 2015 2,882.65

J. Total Cost 60,535.60

k. Total Unit Cost 692.94

Upgrading of Existing PVC Pipelines, Redevelopment of Water and

Sanitation System for ZC Conflict Area (Tiao Him) - Laboratory Building

10mm.Ø x 6.00m. Def. Reinforcing Steel Bar

Page 71: Tiao Him - Lab

DETAILED UNIT PRICE ANALYSIS

PROJECT NAME:

Item No./Description: SPL - 3b Setting of 150mm. CHB

Unit of Measurement: sq.m.

Output per day: 16.00 sq.m./day

Quantity: 13.60 sq.m.

Designation No. Person No. of Days Daily Rate Amount

A. Labor

a. Construction Foreman/Eng'g Assist. 1 0.85 524.00 445.40

b. Skilled Laborer 2 0.85 366.00 622.20

b. Laborer 4 0.85 317.00 1,077.80

Sub-Total for A P 2,145.40

Name and Capacity No. of Units No. of Days Daily Rate Amount

B. Equipment

N/A

Sub-Total for B P -

C. Total (A+B) 2,145.40 D. Output per day = 16.00 sq.m. /day

Name and Specifications Quantity Unit Unit Cost Amount

E. Materials

a. 150mm. x 200mm. x 400mm. CHB (NLB) 170 pcs. 18.50 3,145.00

b. Washed Sand 1.50 cu.m. 1,000.00 1,500.00

c. Portland Cement 14 bags 260.00 3,640.00

d. 28 pcs. 214.00 5,992.00

e. #16 G.I. Tie-wire 0.50 pcs. 63.00 31.50

f. Hacksaw Blade 1 pc. 43.00 43.00

Sub-Total for E P 14,351.50

F. Direct Cost (C+E) 16,496.90

G. Overhead, Contingencies & Miscellaneous 7% per D.O. 22 s 2015 1,154.78

H. Contractor's Profit (CP) 8% per D.O. 22 s 2015 1,319.75

I. Value Added Tax (VAT) 5% per D.O. 22 s 2015 948.57

J. Total Cost 19,920.01

k. Total Unit Cost 1,464.71

Upgrading of Existing PVC Pipelines, Redevelopment of Water and

Sanitation System for ZC Conflict Area (Tiao Him) - Laboratory Building

12mm.Ø x 6.00m. Def. Reinforcing Steel Bar

Page 72: Tiao Him - Lab

DETAILED UNIT PRICE ANALYSIS

PROJECT NAME:

Item No./Description: SPL - 4a Ceiling Joist and Hangers

Unit of Measurement: sq.m.

Output per day: 32.00 sq.m./day

Quantity: 105.20 sq.m.

Designation No. Person No. of Days Daily Rate Amount

A. Labor

a. Construction Foreman/Eng'g Assist. 1 3 524.00 1,572.00

b. Skilled Laborer 2 3 366.00 2,196.00

b. Laborer 2 3 317.00 1,902.00

Sub-Total for A P 5,670.00

Name and Capacity No. of Units No. of Days Daily Rate Amount

B. Equipment

a. Electric Handrill 2 3 300.00 1,800.00 Minor Tools (10% of Labor Cost) 567.00

Sub-Total for B P 2,367.00

C. Total (A+B) 8,037.00 D. Output per day = 32.00 sq.m. /day

Name and Specifications Quantity Unit Unit Cost Amount

E. Materialsa. 40 pcs. 108.00 4,320.00

b. 4mm.Ø x 10mm. Alum. Blind Rivets 1,052 pcs. 0.50 526.00

c. 1-1/2" Concrete Nail 2 kgs. 148.00 296.00

d. Hacksaw Blade 2 pcs. 43.00 86.00

e. 32 pcs. 115.00 3,680.00

f. W Clip 175 pcs. 3.00 525.00

g. 0.40mm. x 25mm. x 25mm. x 3.00m. Wall Angle 27 pcs. 26.00 702.00

Sub-Total for E P 10,135.00

F. Direct Cost (C+E) 18,172.00

G. Overhead, Contingencies & Miscellaneous 7% per D.O. 22 s 2015 1,272.04

H. Contractor's Profit (CP) 8% per D.O. 22 s 2015 1,453.76

I. Value Added Tax (VAT) 5% per D.O. 22 s 2015 1,044.89

J. Total Cost 21,942.69

k. Total Unit Cost 208.58

Upgrading of Existing PVC Pipelines, Redevelopment of Water and

Sanitation System for ZC Conflict Area (Tiao Him) - Laboratory Building

0.40mm. x 19mm. x 50mm. x 5.00m. Furring Channel

0.80mm. x 12mm. x 38mm. x 5m. Carrying Channel

Page 73: Tiao Him - Lab

DETAILED UNIT PRICE ANALYSIS

PROJECT NAME:

Item No./Description: SPL - 4b Installation of Ceiling Board

Unit of Measurement: sq.m.

Output per day: 30.00 sq.m./day

Quantity: 105.20 sq.m.

Designation No. Person No. of Days Daily Rate Amount

A. Labor

a. Construction Foreman/Eng'g Assist. 1 3.50 524.00 1,834.00

b. Skilled Laborer 1 3.50 366.00 1,281.00

b. Laborer 1 3.50 317.00 1,109.50

Sub-Total for A P 4,224.50

Name and Capacity No. of Units No. of Days Daily Rate Amount

B. Equipment

a. Electric Handrill 1 3.50 300.00 1,050.00

Minor Tools (10% of Labor Cost) 422.00

Sub-Total for B P 1,472.00

C. Total (A+B) 5,696.50 D. Output per day = 30.00 sq.m. /day

Name and Specifications Quantity Unit Unit Cost Amount

E. Materialsa. 4mm. Thk. x 1.20m. x 2.40m. Fiber Cement Board 38 shts. 462.00 17,556.00

b. 2,679 pcs. 1.95 5,224.05

Sub-Total for E P 22,780.05

F. Direct Cost (C+E) 28,476.55

G. Overhead, Contingencies & Miscellaneous 7% per D.O. 22 s 2015 1,993.36

H. Contractor's Profit (CP) 8% per D.O. 22 s 2015 2,278.12

I. Value Added Tax (VAT) 5% per D.O. 22 s 2015 1,637.40

J. Total Cost 34,385.43

k. Total Unit Cost 326.86

Upgrading of Existing PVC Pipelines, Redevelopment of Water and

Sanitation System for ZC Conflict Area (Tiao Him) - Laboratory Building

20mm. Long Galvanized/Zinc-coated Fiber Cement Screw

Page 74: Tiao Him - Lab

DETAILED UNIT PRICE ANALYSIS

PROJECT NAME:

Item No./Description: SPL - 4c Installation of Fascia Board

Unit of Measurement: sq.m.

Output per day: 30.00 sq.m./day

Quantity: 15.87 sq.m.

Designation No. Person No. of Days Daily Rate Amount

A. Labor

a. Construction Foreman/Eng'g Assist. 1 0.50 524.00 262.00

b. Skilled Laborer 1 0.50 366.00 183.00

b. Laborer 1 0.50 317.00 158.50

Sub-Total for A P 603.50

Name and Capacity No. of Units No. of Days Daily Rate Amount

B. Equipment

a. Electric Handrill 1 0.50 300.00 150.00

Minor Tools (10% of Labor Cost) 60.00

Sub-Total for B P 210.00

C. Total (A+B) 813.50 D. Output per day = 30.00 sq.m. /day

Name and Specifications Quantity Unit Unit Cost Amount

E. Materialsa. 20mm. Thk. x 1.20m. x 2.40m. Marine Plywood 6 shts. 2,154.00 12,924.00

b. 634 pcs. 2.00 1,269.00

Sub-Total for E P 14,193.00

F. Direct Cost (C+E) 15,006.50

G. Overhead, Contingencies & Miscellaneous 7% per D.O. 22 s 2015 1,050.46

H. Contractor's Profit (CP) 8% per D.O. 22 s 2015 1,200.52

I. Value Added Tax (VAT) 5% per D.O. 22 s 2015 862.87

J. Total Cost 18,120.35

k. Total Unit Cost 1,141.80

Upgrading of Existing PVC Pipelines, Redevelopment of Water and

Sanitation System for ZC Conflict Area (Tiao Him) - Laboratory Building

32mm. Long Galvanized/Zinc-coated Fiber Cement Screw

Page 75: Tiao Him - Lab

DETAILED UNIT PRICE ANALYSIS

PROJECT NAME:

Item No./Description: SPL - 5a Tile Works (wall tiles)

Unit of Measurement: sq.m.

Output per day: 1.52 sq.m./day

Quantity: 10.55 sq.m.

Designation No. Person No. of Days Daily Rate Amount

A. Labor

a. Construction Foreman/Eng'g Assist. 1 7 524.00 3,668.00

b. Skilled Laborer 1 7 366.00 2,562.00

b. Laborer 1 7 317.00 2,219.00

Sub-Total for A P 8,449.00

Name and Capacity No. of Units No. of Days Daily Rate Amount

B. Equipment

a. Angular Grinder 1 7 300.00 2,100.00

Sub-Total for B P 2,100.00

C. Total (A+B) 10,549.00 D. Output per day = 1.52 sq.m. /day

Name and Specifications Quantity Unit Unit Cost Amount

E. Materialsa. 200mm. x 200mm. Glazed Ceramic Wall Tiles 290 pcs. 15.00 4,350.00

b. Portland Cement 1 bag 260.00 260.00

c. Tile Adhesive (25kg./bag) 1 bag 253.00 253.00

d. Tile Grout (2kg./pack) 5 1 56.00 280.00

e. 6mm. x 2.40m. Tile Trim Plain 4 pcs. 40.00 160.00

f. 2 pcs. 94.00 188.00

Sub-Total for E P 5,491.00

F. Direct Cost (C+E) 16,040.00

G. Overhead, Contingencies & Miscellaneous 7% per D.O. 22 s 2015 1,122.80

H. Contractor's Profit (CP) 8% per D.O. 22 s 2015 1,283.20

I. Value Added Tax (VAT) 5% per D.O. 22 s 2015 922.30

J. Total Cost 19,368.30

k. Total Unit Cost 1,836.73

Upgrading of Existing PVC Pipelines, Redevelopment of Water and

Sanitation System for ZC Conflict Area (Tiao Him) - Laboratory Building

100mm.Ø Grinding Dics

Page 76: Tiao Him - Lab

DETAILED UNIT PRICE ANALYSIS

PROJECT NAME:

Item No./Description: SPL - 5b Tile Works (floor tiles)

Unit of Measurement: sq.m.

Output per day: 3.68 sq.m./day

Quantity: 51.30 sq.m.

Designation No. Person No. of Days Daily Rate Amount

A. Labor

a. Construction Foreman/Eng'g Assist. 1 14 524.00 7,336.00

b. Skilled Laborer 2 14 366.00 10,248.00

b. Laborer 2 14 317.00 8,876.00

Sub-Total for A P 26,460.00

Name and Capacity No. of Units No. of Days Daily Rate Amount

B. Equipment

a. Angular Grinder 1 14 300.00 4,200.00

2,646.00

Sub-Total for B P 6,846.00

C. Total (A+B) 33,306.00 D. Output per day = 3.68 sq.m. /day

Name and Specifications Quantity Unit Unit Cost Amount

E. Materialsa. 400mm. x 400mm. Granite Floor Tiles 330 pcs. 195.00 64,350.00

b. 200mm. x 200mm. Unglazed Ceramic Floor Tiles 91 pcs. 15.00 1,365.00

c. Portland Cement 5 bags 260.00 1,300.00

d. Tile Adhesive (25kg./bag) 7 bags 253.00 1,771.00

e. Tile Grout (2kg./pack) 14 packs 56.00 784.00

f. 2 pcs. 94.00 188.00

Sub-Total for E P 69,758.00

F. Direct Cost (C+E) 103,064.00

G. Overhead, Contingencies & Miscellaneous 7% per D.O. 22 s 2015 7,214.48

H. Contractor's Profit (CP) 8% per D.O. 22 s 2015 8,245.12

I. Value Added Tax (VAT) 5% per D.O. 22 s 2015 5,926.18

J. Total Cost 124,449.78

k. Total Unit Cost 2,425.92

Upgrading of Existing PVC Pipelines, Redevelopment of Water and

Sanitation System for ZC Conflict Area (Tiao Him) - Laboratory Building

100mm.Ø Grinding Dics

Page 77: Tiao Him - Lab

DETAILED UNIT PRICE ANALYSIS

PROJECT NAME:

Item No./Description: SPL - 6 Plastering of CHB Wall

Unit of Measurement: sq.m.

Output per day: 12.00 sq.m./day

Quantity: 174.72 sq.m.

Designation No. Person No. of Days Daily Rate Amount

A. Labor

a. Construction Foreman/Eng'g Assist. 1 15 524.00 7,860.00

b. Skilled Laborer 2 15 366.00 10,980.00

b. Laborer 2 15 317.00 9,510.00

Sub-Total for A P 28,350.00

Name and Capacity No. of Units No. of Days Daily Rate Amount

B. Equipment

N/A

Sub-Total for B P -

C. Total (A+B) 28,350.00 D. Output per day = 12.00 sq.m. /day

Name and Specifications Quantity Unit Unit Cost Amount

E. Materialsa. Portland Cement 34 bags 260.00 8,840.00 b. Fine Sand (for plastering) 3 cu.m. 1,300.00 3,900.00

Sub-Total for E P 12,740.00

F. Direct Cost (C+E) 41,090.00

G. Overhead, Contingencies & Miscellaneous 7% per D.O. 22 s 2015 2,876.30

H. Contractor's Profit (CP) 8% per D.O. 22 s 2015 3,287.20

I. Value Added Tax (VAT) 5% per D.O. 22 s 2015 2,362.68

J. Total Cost 49,616.18

k. Total Unit Cost 283.98

Upgrading of Existing PVC Pipelines, Redevelopment of Water and

Sanitation System for ZC Conflict Area (Tiao Him) - Laboratory Building

Page 78: Tiao Him - Lab

DETAILED UNIT PRICE ANALYSIS

PROJECT NAME:

Item No./Description: SPL - 7 Painting Works

Unit of Measurement: sq.m.

Output per day: 54.40 sq.m./day

Quantity: 288.25 sq.m.

Designation No. Person No. of Days Daily Rate Amount

A. Labor

a. Construction Foreman/Eng'g Assist. 1 5 524.00 2,620.00

b. Skilled Laborer 2 5 366.00 3,660.00

b. Laborer 2 5 317.00 3,170.00

Sub-Total for A P 9,450.00

Name and Capacity No. of Units No. of Days Daily Rate Amount

B. Equipment

N/A

Sub-Total for B P -

C. Total (A+B) 9,450.00 D. Output per day = 54.40 sq.m./day

Name and Specifications Quantity Unit Unit Cost Amount

E. Materialsa. Concrete Neutralizer 4 gals. 297.00 1,188.00 b. Solvent Based Acrylic Cast 6 gals. 546.00 3,276.00

c. Solvent Based Acrylic Primer 14 gals. 817.00 11,438.00

d. Solvent Based Acrylic Top Coat White 19 gals. 783.00 14,877.00

Solvent Based Thermoplastic Acrylic Rasin:

e. Raw Sienna (1L/can) 5 can 110.00 550.00

f. Hansa Yellow (1L/can) 5 can 110.00 550.00

g. Black (1L/can) 5 can 110.00 550.00

h. Venetian Red (1L/can) 5 can 110.00 550.00

i. Thalo Blue (1L/can) 5 can 110.00 550.00

j. Body Filler w/ Hardener 4 gals. 554.00 2,216.00

k. Solvent Based Acrylic Reducer 9 gals. 385.00 3,465.00

l. #120 Sand Paper 31 pcs. 16.00 496.00

m. #150 Sand Paper 31 pcs. 16.00 496.00

n. 7" Roller Brush w/ Handle 3 pcs. 35.00 105.00

o. 4" Paint Brush 5 pcs. 85.00 425.00

p. 2" Paint Brush 5 pcs. 30.00 150.00

Sub-Total for E P 40,882.00

F. Direct Cost (C+E) 50,332.00

G. Overhead, Contingencies & Miscellaneous 7% per D.O. 22 s 2015 3,523.24

H. Contractor's Profit (CP) 8% per D.O. 22 s 2015 4,026.56

I. Value Added Tax (VAT) 5% per D.O. 22 s 2015 2,894.09

Upgrading of Existing PVC Pipelines, Redevelopment of Water and

Sanitation System for ZC Conflict Area (Tiao Him) - Laboratory Building

Page 79: Tiao Him - Lab

J. Total Cost 60,775.89

k. Total Unit Cost 210.84

Page 80: Tiao Him - Lab

DETAILED UNIT PRICE ANALYSIS

PROJECT NAME:

Item No./Description: SPL - 8 PVC Wall Paneling Installation

Unit of Measurement: sq.m.

Output per day: 1.123 sq.m./day

Quantity: 4.29 sq.m.

Designation No. Person No. of Days Daily Rate Amount

A. Labor

a. Construction Foreman/Eng'g Assist. 1 4 524.00 2,096.00

b. Skilled Laborer 1 4 366.00 1,464.00

b. Laborer 1 4 317.00 1,268.00

Sub-Total for A P 4,828.00

Name and Capacity No. of Units No. of Days Daily Rate Amount

B. Equipment

a. Electric Handrill 1 4 300.00 1,200.00

Sub-Total for B P 1,200.00

C. Total (A+B) 6,028.00 D. Output per day = 1.12 sq.m./day

Name and Specifications Quantity Unit Unit Cost Amount

E. Materialsa. 150mm. X 2400mm. PVC Wall Panel 19 pcs. 126.00 2,394.00 b. 0.40mm. x 19mm. 50mm. x 5m. Furring Channel 13 pcs. 108.00 1,404.00

c. 1 box 251.00 251.00

d. 16mm. Flat Head Metal Screw 164 pcs. 1.95 319.80

e. Hacksaw Blade 1 pc. 43.00 43.00

Sub-Total for E P 4,411.80

F. Direct Cost (C+E) 10,439.80

G. Overhead, Contingencies & Miscellaneous 7% per D.O. 22 s 2015 730.79

H. Contractor's Profit (CP) 8% per D.O. 22 s 2015 835.18

I. Value Added Tax (VAT) 5% per D.O. 22 s 2015 600.29

J. Total Cost 12,606.06

k. Total Unit Cost 2,938.48

Upgrading of Existing PVC Pipelines, Redevelopment of Water and

Sanitation System for ZC Conflict Area (Tiao Him) - Laboratory Building

4mm.Ø x 10mm. Alum. Blind Rivets

Page 81: Tiao Him - Lab

Page 81 of 91

DETAILED UNIT PRICE ANALYSIS

PROJECT NAME:

Item No./Description: SPL - 9 Construction of Septic Vault

Unit of Measurement: cu.m.

Output per day: 0.90 cu.m./day

Quantity: 9.00 cu.m.

Designation No. Person No. of Days Daily Rate Amount

A. Labor

a. Construction Foreman/Eng'g Assist. 1 10 524.00 5,240.00

b. Skilled Laborer 3 10 366.00 10,980.00

b. Laborer 2 10 317.00 6,340.00

Sub-Total for A P 22,560.00

Name and Capacity No. of Units No. of Days Daily Rate Amount

B. Equipment

a. Concrete Bagger Mixer 1 4 1,376.00 5,504.00

b. Concrete Vibrator 1 4 972.00 3,888.00

Sub-Total for B P 9,392.00

C. Total (A+B) 31,952.00 D. Output per day = 0.90 cu.m. /day

Name and Specifications Quantity Unit Unit Cost Amount

E. Materials1. Concreting

Quantity: 4.45 cu.m.

Portland Cement 45 bags 260.00 11,700.00

Washed Sand 2.50 cu.m. 1,000.00 2,500.00

Gravel 5 cu.m. 1,000.00 5,000.00

1 cu.m. 1,000.00 1,000.00

Waterproofing Chemical 45 packs 35.00 1,575.00

2. Rebars

143.12 kgs. 40.21 5,754.86

116.80 kgs. 34.90 4,076.32

#16 G.I. Tie-wire 7 kgs. 63.00 441.00

3. Forms

12mm. Thk. x 1.20m. x 2.40m. Ordinary Plywood 12 shts. 685.00 8,220.00

60pcs. 2" x 3" x 8' Coco Lumber 240 bd.ft. 21.00 5,040.00

2" C.W. Nail 9 kgs. 45.00 405.00

4" C.W. Nail 4 kgs. 42.30 169.20

Upgrading of Existing PVC Pipelines, Redevelopment of Water and

Sanitation System for ZC Conflict Area (Tiao Him) - Laboratory Building

100mm.Ø Boulders (bedding)

12mm.Ø x 6.00m. Def. Reinforcing Steel Bar

10mm.Ø x 6.00m. Def. Reinforcing Steel Bar

Page 82: Tiao Him - Lab

Page 82 of 91

4. Plastering

Fine Sand (for plastering) 9 cu.m. 1,300.00 11,700.00

Portland Cement 6 bags 260.00 1,560.00

5. Pipes & Fittings3 pcs. 54.00 162.00

100mmØ x 100mmØ PVC Sanitary Tee, S-1,000 3 pcs. 124.00 372.00

100mmØ x 3.00m PVC Sanitary Pipe, S-1,000 2 pcs. 1,095.00 2,190.00

PVC Solvent Cement (100ml/can) 2 cans 103.00 206.00

Sub-Total for E P 62,071.38

F. Direct Cost (C+E) 94,023.38

G. Overhead, Contingencies & Miscellaneous 7% per D.O. 22 s 2015 6,581.64

H. Contractor's Profit (CP) 8% per D.O. 22 s 2015 7,521.87

I. Value Added Tax (VAT) 5% per D.O. 22 s 2015 5,406.34

J. Total Cost 113,533.23

k. Total Unit Cost 12,614.80

100mm.Ø PVC Sanitary Clean Out Adaptor & Plug, S-1,000

Page 83: Tiao Him - Lab

DETAILED UNIT PRICE ANALYSIS

PROJECT NAME:

Item No./Description: SPL - 10 Construction of Catch Basin

Unit of Measurement: cu.m.

Output per day: 0.055 cu.m. /day

Quantity: 0.22 cu.m.

Designation No. Person No. of Days Daily Rate Amount

A. Labor

a. Construction Foreman/Eng'g Assist. 1 4 524.00 2,096.00

b. Skilled Laborer 2 4 366.00 2,928.00

b. Laborer 2 4 317.00 2,536.00

Sub-Total for A P 7,560.00

Name and Capacity No. of Units No. of Days Daily Rate Amount

B. Equipment

N/A

Sub-Total for B P -

C. Total (A+B) 7,560.00 D. Output per day = 0.055 cu.m. /day

Name and Specifications Quantity Unit Unit Cost Amount

E. Materialsa. 100mm. x 200mm. x 400mm. CHB (NLB) 28 pcs. 14.00 392.00

b. Portland Cement 2 bags 260.00 520.00

c. Washed Sand 0.15 cu.m. 1,000.00 150.00

d. Gravel 0.10 cu.m. 1,000.00 100.00

e. 10mm.Ø x 6.00m. Def. Reinforcing Steel Bar 22.20 kgs. 34.90 774.78

f. #16 G.I. Tie-wire 1 kg. 63.00 63.00

Sub-Total for E P 1,999.78

F. Direct Cost (C+E) 9,559.78

G. Overhead, Contingencies & Miscellaneous 7% per D.O. 22 s 2015 669.18

H. Contractor's Profit (CP) 8% per D.O. 22 s 2015 764.78

I. Value Added Tax (VAT) 5% per D.O. 22 s 2015 549.69

J. Total Cost 11,543.43

k. Total Unit Cost 52,470.16

Upgrading of Existing PVC Pipelines, Redevelopment of Water and

Sanitation System for ZC Conflict Area (Tiao Him) - Laboratory Building

Page 84: Tiao Him - Lab

DETAILED UNIT PRICE ANALYSIS

PROJECT NAME:

Item No./Description: SPL - 11 Storm Drainage System

Unit of Measurement: ln.m.

Output per day: 26.00 ln.m. /day

Quantity: 26.00 ln.m.

Designation No. Person No. of Days Daily Rate Amount

A. Labor

a. Construction Foreman/Eng'g Assist. 1 1 524.00 524.00

b. Skilled Laborer 1 1 366.00 366.00

b. Laborer 2 1 317.00 634.00

Sub-Total for A P 1,524.00

Name and Capacity No. of Units No. of Days Daily Rate Amount

B. Equipment

N/A

Sub-Total for B P -

C. Total (A+B) 1,524.00 D. Output per day = 26.00 ln.m. /day

Name and Specifications Quantity Unit Unit Cost Amount

E. Materialsa. 75mm.Ø x 3.00m. Sanitary PVC Pipe, S-1000 10 pcs. 520.00 5,200.00

b. 1 pc. 59.00 59.00

c. 3 pcs. 48.00 144.00

d. 75mm.Ø x 75mm.Ø Sanitary PVC Tee, S-1000 3 pcs. 104.00 312.00

e. 1 pc. 46.00 46.00

f. PVC Pipe Cement Solvent (200cc/can) 2 cans 166.00 332.00

g. 75mm.Ø Sanitary PVC Coupling, S-1000 3 pcs. 35.00 105.00

Sub-Total for E P 6,198.00

F. Direct Cost (C+E) 7,722.00

G. Overhead, Contingencies & Miscellaneous 7% per D.O. 22 s 2015 540.54

H. Contractor's Profit (CP) 8% per D.O. 22 s 2015 617.76

I. Value Added Tax (VAT) 5% per D.O. 22 s 2015 444.02

J. Total Cost 9,324.32

k. Total Unit Cost 358.63

Upgrading of Existing PVC Pipelines, Redevelopment of Water and

Sanitation System for ZC Conflict Area (Tiao Him) - Laboratory Building

75mm.Ø x 90o Sanitary PVC Elbow, S-1000

75mm.Ø x 45o Sanitary PVC Elbow, S-1000

75mm.Ø Sanitary Clean Out Adaptor & Plug, S-1000

Page 85: Tiao Him - Lab

DETAILED UNIT PRICE ANALYSIS

PROJECT NAME:

Item No./Description: SPL - 12 Installation of Downspout

Unit of Measurement: ln.m.

Output per day: 26.00 ln.m. /day

Quantity: 21.00 ln.m.

Designation No. Person No. of Days Daily Rate Amount

A. Labor

a. Construction Foreman/Eng'g Assist. 1 0.81 524.00 423.23

b. Skilled Laborer 1 0.81 366.00 295.62

b. Laborer 2 0.81 317.00 512.08

Sub-Total for A P 1,230.92

Name and Capacity No. of Units No. of Days Daily Rate Amount

B. Equipment

N/A

Sub-Total for B P -

C. Total (A+B) 1,230.92 D. Output per day = 26.00 ln.m. /day

Name and Specifications Quantity Unit Unit Cost Amount

E. Materialsa. 75mm.Ø x 3.00m. Sanitary PVC Pipe, S-1000 7 pcs. 520.00 3,640.00

b. 15 pc. 59.00 885.00

c. PVC Pipe Cement Solvent (200cc/can) 2 cans 166.00 332.00

d. 75mm.Ø Sanitary PVC Coupling, S-1000 5 pcs. 35.00 175.00

Sub-Total for E P 5,032.00

F. Direct Cost (C+E) 6,262.92

G. Overhead, Contingencies & Miscellaneous 7% per D.O. 22 s 2015 438.40

H. Contractor's Profit (CP) 8% per D.O. 22 s 2015 501.03

I. Value Added Tax (VAT) 5% per D.O. 22 s 2015 360.12

J. Total Cost 7,562.48

k. Total Unit Cost 360.12

Upgrading of Existing PVC Pipelines, Redevelopment of Water and

Sanitation System for ZC Conflict Area (Tiao Him) - Laboratory Building

75mm.Ø x 90o Sanitary PVC Elbow, S-1000

Page 86: Tiao Him - Lab

Page 86 of 91

DETAILED UNIT PRICE ANALYSIS

PROJECT NAME:

Item No./Description: SPL - 13 Plumbing Works

Unit of Measurement: fixtures

Output per day: 1.00 fixture/day

Quantity: 3.00 fixtures

Designation No. Person No. of Days Daily Rate Amount

A. Labor

a. Construction Foreman/Eng'g Assist. 1 3 524.00 1,572.00

b. Skilled Laborer 1 3 366.00 1,098.00

b. Laborer 2 3 317.00 1,902.00

Sub-Total for A P 4,572.00

Name and Capacity No. of Units No. of Days Daily Rate Amount

B. Equipment

a. Portable Electric Handrill 1 3 300.00 900.00

b. Portable Pipe Threader 1 3 500.00 1,500.00

Minor Tools (10% of labor cost) 457.20

Sub-Total for B P 2,857.20

C. Total (A+B) 7,429.20 D. Output per day = 1.00 fixtures/day

Name and Specifications Quantity Unit Unit Cost Amount

E. Materials1. Fixtures and Accessories

1 unit 3,550.00 3,550.00

1 unit 2,848.00 2,848.00

1 unit 269.00 269.00

Ceramic Tissue Holder 1 set 300.00 300.00

Ceramic Soap Holder 1 set 280.00 280.00

2. Sanitary Pipes

100mm.Ø x 100mm.Ø Sanitary PVC Tee, S-10 1 pc. 178.00 178.00

100mm.Ø x 3.00m. Sanitary PVC Pipe, S-1000 1 pc. 693.00 693.00

50mm.Ø x 3.00m. Sanitary PVC Pipe, S-1000 2 pcs. 260.00 520.00

50mm.Ø Sanitary PVC Coupling, S-1000 1 pc. 17.00 17.00

75mm.Ø Sanitary PVC P-Trap, S-1000 1 pc. 135.00 135.00

75mm.Ø x 50mm.Ø Sanitary PVC Tee, S-1000 1 pc. 52.00 52.00

1 pc. 33.00 33.00

PVC Pipe Cement Solvent (200cc/can) 2 cans 166.00 332.00

3. Cold Pipe9 pcs. 23.00 207.00

Upgrading of Existing PVC Pipelines, Redevelopment of Water and

Sanitation System for ZC Conflict Area (Tiao Him) - Laboratory Building

Flush Type Water Closet w/ Complete Fittings and AccessoriesWall Mounted Type Lavatory w/ Complete Fittings and Accessories100mm. x 100mm. Stainless Floor Drain w/ Double Strainer

50mm.Ø x 90o Sanitary PVC Elbow, S-1000

12mm.Ø x 90o G.I. Elbow, ANSI B16.3 Class 150-

Standard

Page 87: Tiao Him - Lab

Page 87 of 91

3 pcs. 30.00 90.00

1 pc. 97.00 97.00

1 pc. 18.00 18.00

1 pc. 226.00 226.00

12mm.Ø Water Meter Stan Set 1 pc. 1,675.00 1,675.00

2 pcs. 678.00 1,356.00

4 pcs. 18.00 72.00

19mm. Teflon Tape 4 rolls 31.00 124.00

19mm.Ø x 150m. P.E. Tubing, SDR-11 1 roll 2,664.00 2,664.00

Sub-Total for E P 15,736.00

F. Direct Cost (C+E) 23,165.20

G. Overhead, Contingencies & Miscellaneous 7% per D.O. 22 s 2015 1,621.56

H. Contractor's Profit (CP) 8% per D.O. 22 s 2015 1,853.22

I. Value Added Tax (VAT) 5% per D.O. 22 s 2015 1,332.00

J. Total Cost 27,971.98

k. Total Unit Cost 9,323.99

12mm.Ø x 12mm.Ø G.I. Tee, ANSI B16.3 Class 150-Standrad12mm.Ø G.I. Union Patent, ANSI B16.3 Class 150-Standard19mm.Ø x 12mm.Ø G.I. Bell Reducer, ANSI B16.3 Class 150-Standard19mm.Ø Brass Single Adaptor, Pack Joint/Clamp Type

12mm.Ø x 6.00m. G.I. Pipe ASTM A53-90A Heavy Gauge Standard12mm.Ø G.I. Coupling, ANSI B16.3 Class 150-Standard

Page 88: Tiao Him - Lab

DETAILED UNIT PRICE ANALYSIS

PROJECT NAME:

Item No./Description: SPL - 14 Lighting Installation

Unit of Measurement: outlet

Output per day: 8.00 outlet /day

Quantity: 7.00 outlet

Designation No. Person No. of Days Daily Rate Amount

A. Labor

a. Construction Foreman/Eng'g Assist. 1 0.88 524.00 458.50

b. Master Electrician 1 0.88 366.00 320.25

b. Laborer 3 0.88 317.00 832.13

Sub-Total for A P 1,610.88

Name and Capacity No. of Units No. of Days Daily Rate Amount

B. Equipment

a. Portable Electric Handrill 1 0.88 300.00 262.50

Sub-Total for B P 262.50

C. Total (A+B) 1,873.38 D. Output per day = 8.00 outlet /day

Name and Specifications Quantity Unit Unit Cost Amount

E. Materialsa. Down Light w/ 12 Watts Led Bulb 6 units 575.00 3,450.00

b. 4 sets 1,250.00 5,000.00

c. 12 Watts Led Bulb 1 pc. 390.00 390.00

d. Ceiling Socket with screw 1 pc. 32.00 32.00

e. 3.5mm2 THW Stranded Wire 1 roll 5,800.00 5,800.00

f. 1 Hp Window Type Air Condition Unit 1 unit 16,500.00 16,500.00

g. Toggle Switch 3-Gang Switch w/ plate 1 pc. 250.00 250.00

h. Toggle Switch 2-Gang Switch w/ plate 1 pc. 190.00 190.00

i. Toggle Switch 1-Gang Switch w/ plate 1 pc. 130.00 130.00

j. 2" x 4" x 2" PVC Utility box (H.D) 5 pcs. 20.00 100.00

k. 4" x 4" PVC Junction Box ( H.D.) w/ Cover 5 pcs. 25.00 125.00

l. 20mmØ x 3.00m PVC Electrical Conduit 30 pcs. 70.00 2,100.00

m. 20mmØ PVC Flexible Electrical Conduit 0.5 roll 715.00 357.50

n. 10 pcs. 35.00 350.00

o. 20mmØ Female Pipe & Flex Adaptor w/ Bushi 10 pcs. 20.00 200.00

p. 0.8mm x 19mm x 8m Polytype Electrical Tape 2 rolls 25.00 50.00

Sub-Total for E P 35,024.50

F. Direct Cost (C+E) 36,897.88

G. Overhead, Contingencies & Miscellaneous 7% per D.O. 22 s 2015 2,582.85

H. Contractor's Profit (CP) 8% per D.O. 22 s 2015 2,951.83

I. Value Added Tax (VAT) 5% per D.O. 22 s 2015 2,121.63

Upgrading of Existing PVC Pipelines, Redevelopment of Water and

Sanitation System for ZC Conflict Area (Tiao Him) - Laboratory Building

Recessed Type Reflectorized Fluorescent Luminaire 1-40W

20mmØ x 90° PVC Electrical Conduit Elbow Long Sweep

Page 89: Tiao Him - Lab

J. Total Cost 44,554.18

k. Total Unit Cost 6,364.88

Page 90: Tiao Him - Lab

DETAILED UNIT PRICE ANALYSIS

PROJECT NAME:

Item No./Description: SPL - 15 Convenience Outlet Installation

Unit of Measurement: outlet

Output per day: 8.00 outlet /day

Quantity: 10.00 outlet

Designation No. Person No. of Days Daily Rate Amount

A. Labor

a. Construction Foreman/Eng'g Assist. 1 1.25 524.00 655.00

b. Master Electrician 1 1.25 366.00 457.50

b. Laborer 3 1.25 317.00 1,188.75

Sub-Total for A P 2,301.25

Name and Capacity No. of Units No. of Days Daily Rate Amount

B. Equipment

a. Portable Electric Handrill 1 1.25 300.00 375.00

Sub-Total for B P 375.00

C. Total (A+B) 2,676.25 D. Output per day = 8.00 outlet /day

Name and Specifications Quantity Unit Unit Cost Amount

E. Materialsa. Duplex Conveniece Outlet w/ plate 10 sets 240.00 2,400.00

b. 3.5mm2 THW Stranded Wire 120 mtrs. 32.00 3,840.00

c. 2" x 4" x 2" PVC Utility box (H.D) 10 pcs. 20.00 200.00

d. 4" x 4" PVC Junction Box ( H.D.) w/ Cover 10 pcs. 25.00 250.00

e. 20mmØ x 3.00m PVC Electrical Conduit 35 pcs. 70.00 2,450.00

f. 20mmØ PVC Flexible Electrical Conduit 0.5 rolls 715.00 357.50

g. 15 pcs. 35.00 525.00

h. 20mmØ Female Pipe & Flex Adaptor w/ Bushi 15 pcs. 20.00 300.00

i. 0.8mm x 19mm x 8m Polytype Electrical Tape 2 rolls 25.00 50.00

j. #16 G.I. Tie Wire 1 kgs. 63.00 63.00

Sub-Total for E P 10,435.50

F. Direct Cost (C+E) 13,111.75

G. Overhead, Contingencies & Miscellaneous 7% per D.O. 29 s 2015 917.82

H. Contractor's Profit (CP) 8% per D.O. 29 s 2015 1,048.94

I. Value Added Tax (VAT) 5% per D.O. 29 s 2015 753.93

J. Total Cost 15,832.44

k. Total Unit Cost 1,583.24

Upgrading of Existing PVC Pipelines, Redevelopment of Water and

Sanitation System for ZC Conflict Area (Tiao Him) - Laboratory Building

20mmØ x 90° PVC Electrical Conduit Elbow Long Sweep

Page 91: Tiao Him - Lab

DETAILED UNIT PRICE ANALYSIS

PROJECT NAME:

Item No./Description: SPL - 16 Main Disconnection Swicthes

Unit of Measurement: outlet

Output per day: 1.00 outlet /day

Quantity: 1.00 outlet

Designation No. Person No. of Days Daily Rate Amount

A. Labor

a. Construction Foreman/Eng'g Assist. 1 1.00 524.00 524.00

b. Master Electrician 1 1.00 366.00 366.00

b. Laborer 3 1.00 317.00 951.00

Sub-Total for A P 1,841.00

Name and Capacity No. of Units No. of Days Daily Rate Amount

B. Equipment

a. Portable Electric Handrill 1 1.00 300.00 300.00

Sub-Total for B P 300.00

C. Total (A+B) 2,141.00 D. Output per day = 1.00 outlet /day

Name and Specifications Quantity Unit Unit Cost Amount

E. Materials

60 Amperes TQD Molded Case Main Circuit Breaker, 3 Phase Main,

240 volts enclosed in Powder Coated Finished

Panel Board with 4 Single Phase Branches of:

2-15 Amps, 250 Volt, 2P, Branch Circuit Breaker

1-20 Amps, 250 Volt, 2P, Branch Circuit Breaker 1 set 10,200.00 10,200.00

Sub-Total for E P 10,200.00

F. Direct Cost (C+E) 12,341.00

G. Overhead, Contingencies & Miscellaneous 7% per D.O. 22 s 2015 863.87

H. Contractor's Profit (CP) 8% per D.O. 22 s 2015 987.28

I. Value Added Tax (VAT) 5% per D.O. 22 s 2015 709.61

J. Total Cost 14,901.76

k. Total Unit Cost 14,901.76

Upgrading of Existing PVC Pipelines, Redevelopment of Water and

Sanitation System for ZC Conflict Area (Tiao Him) - Laboratory Building