Upload
ngokhanh
View
214
Download
0
Embed Size (px)
Citation preview
This week overview
Day Take-homes
Tuesday Theory: Design organizations as we design bridges: predict, measure and manage
and Wednesday
“hidden” work;ICEPractice: apply ICE methods and slowly Practice: apply ICE methods and slowly develop comfort and competence
Product Organization Process
Design for water-free subway box for AWVGood self-assessed coordination between neighbors, DOT, contractor, project manager Engineering designs finished by 12/31/2007
Design for structurally sound subway boxExchange of project documentation and specifications within 24 hours as needed Construction plans finished by 12/31/2007
Project costs Organization cost Tasks to design all systems and componentsTasks to specify all construction packagesTasks to plan and coordinate utility movement
Environmental impact statement Deputy project director Plan and Coordinate utility movement
Traffic management plan UtilitiesDevelop and deliver engineering design documents
Function: Design intent
Form: Design choices
Final Program Confirmation with
Pharmacology
Final Program confirmation with LAR
KPFF
SRG Lab Task 37 Task 44 Project Mgt AEI Core Task 41 Task26 H Block Crew Task 23SRG / AEI Technical
AEI Core andSRG Lab HDCCO Costing
SRGTechnical KPFF
AEI Core and Tech HDCCO Core
Code RevConsultant Solvent Tar ter
H Block Crew& Tech
SRGLandscape
Tele DataDesign Code Rev
Furniture
26. *Finalize B#13 and B#15
Exiting/architecural H occupancy concept
23. *Reprogram B#13 and B#15
Exterior Architecture
Bookend Programming
Accepted by Genentech
SRG Management AEI Management
Genentech PM
SRG Lab Plan
Ken Mouchka
Task 27Task 38
Organization
Task 29
Task 28Task4 Task22
Review 80% documents
Review skin changes w/db team
Lab Planning Program Meetings with Pharmacology
Lab planning Program Meeting with ProteinChemistry
BMS Controls Meetings (Weekly)
Lab Planning Program meeting with Bio Organic 80% Drawing Review
Tele Data Coordination MeetingsSteel Detailing Meetings
Genentech 80% Detailed Design Review
Final Program Confirmation with Officing
Weekly Coordination
MeetingLab Planning Program Meetings with Directors
MEP, Teledata room design
24. *Complete B13,4 H block occupancy
requirements on MEP systems
(8) *Revise MEP loads, MEP
Equipment
(13,15,16) MEP specs, P&ID's, control sequences
Work Process
Meetings
(6) Coord B13 MEP floor section
*Cal OSHA Recommend Determination of LFFH
*Exterior Programming
Accepted by Genentech
23 - 24 June Chalmers Virtual Design Class (c) 2009
1
Traffic management plan Utilities documentsRelocated utilities Engineering Plan land acquisitionEngineering designs Urban design/Architecture Develop work packages
Secant pile tunnel walls Real EstatePlan transportation access in detail throughout construction
Tunnel box - King to Pike Construction Engineering Develop environmental impact studiesNorth section - Pike to BST Transportation PlanningSouth Section - Holdage to King Environmental
Construction plansConstruction staging planConstruction packages
Risks of leaks self-assessed stakeholder coordination quality Predicted schedule performancePredicted structural deformation Predicted actor backlogs Predicted task backlogsPredicted material costs Predicted actor costs Predicted task costs including material, labor
Observed actor response latencyObserved actor decision latency
Behavior: Analysis predictions
*05-07-01
Finish
37. *Reprogram B#15 Shafts
34. *Finalize Pharmacology
Program
33. *Finalize LAR Program
32. *Finalize Bio-Organic Chemistry Program
35. *Finalize Protein Chemistry
Program 20. *Determine Scope of package D including vivar ium
changes
45. *Complete all Basement/LAR Drawings
41. *Reprogram bookends B#13 and
B#15
36. *Analyze structural impacts
12. *Complete UG utiliites
25. *Do Central Plant design changes
19. *Determine ver tical utilities
22. *Complete catwalk drawings
52. Finalize landscape
*Lab and vivarium
Programming Complete
27. *Finalize B#13, 15 Shaft Size &
MEP Room Locations
31.* AEI & SRG
Determine Design $/Time
Impact of
Notice to proceed on structural changes
Architect program/MEP
oncepts Established By Design
Team
29. *Document lab plan
1. *Redesign main MEP distribution systems
5. *Finalize lab & Equipment plans
30. *Approve Change to Design Contract
21. *Prepare Plan Views for Review of Concept w/City
39. *Finalize MEP distr ibution and
section
48. *Develop exiting plan
49. Develop reflected ceiling
plan
Turnover reflected
ceiling plan to AEI
Detailed Design 80 PC Complete
3. Complete Tele Data Design
42. *Develop Execution Strategy
44. *Complete B#14 Officing
Planning
18. *Detailed Lab Program
Documentation
47. *Develop lab DD plan
28. *Determine segregation of lab
and tech space
G accept lab equipment matrix
*Package B structural modifications (CCD3A)
13. *Code Consultants Review Concept for final
city Presentation
14. *HDCCO update Estimate of cost of Program
50. Designate size, location of 13 MEP, teledata rooms
54. KPFF design stairs for 13/1438. *SRG
Reprogram 13/14 interface, exiting,
stairs
43. *Changes in Steel Forwarded to Steel
Detailers
46. *RA Furnture Concept Complete
*Design Budget & Schedule for Changes
Approved
*Notice to proceed with detailed design
17. *Risick reprogram solvent
distribution and waste
Issue 80% MEP CDs
(20) Incorporate 80% MEP review
comments
(19) Genentech review 80% drawings
53. Incorporate comments, complete
Architectural detail
2. Initial redesign MEP branch lateral distribution
G accept 13/14
Interface
*City Accept exiting
*Package C skin
modifications
55. KPFF design stairs for 15/14
40. *SRG Reprogram 15/14 interface, exiting,
stairs
B13 MEP HVAC, conduit, piping mains
completed
MEP 80% Review comments incorporated
Package D and UG addendum issued:
underground utilities, vivar ium catwalk
10. Draft Alternate means
15. Jeff reprogram HMIS
(3) *AEI design MEP HVAC, Conduit & piping mains B13
16. *HDCCO Determine Schedule Impact
City Approval of Alternate Means
for Program
8. Review Alternate Means w/impact on LEL
and LFFH
(21-4) Finalize MEP Details, update specs and p&ID's
Equipment schedules finalized
4. complete all Interior Architcture
51. Designate size, location of 14 MEP, teledata rooms G accept
15/14 Interface
*Accept project scope:budget by Genentech
*City Approval of H Concept
*Turnover lab and vivarium DD plan
to AEI
Notices
• Today (June 23):Today (June 23):– Second reading assessment was due at 10– Org models and ICE theory; ICE sessionOrg models and ICE theory; ICE session– Meet as usual: 10-12; 1-3
• June 24:• June 24: – MACDADI theory; ICE session
M t 10 11 30 1 3 30– Meet 10 – 11:30; 1 – 3:30
23 - 24 June Chalmers Virtual Design Class (c) 2009
2
Q1: Which of the methods below do the papers suggest might help a project team to develop and models in practice today?p p j p p y
23 - 24 June Chalmers Virtual Design Class (c) 2009
3
Q2: Which of the following statements is true about the contents of POP models?true about the contents of POP models?
23 - 24 June Chalmers Virtual Design Class (c) 2009
4
Q3: Which of the following statements is true about “Function – Form – Behavior?about Function Form Behavior?
23 - 24 June Chalmers Virtual Design Class (c) 2009
5
Q4: Which of the following suggestions is appropriate regarding use of POP models?”appropriate regarding use of POP models?
23 - 24 June Chalmers Virtual Design Class (c) 2009
6
Q5: Which of the following statements are true about “breakdown structures?”are true about breakdown structures?
23 - 24 June Chalmers Virtual Design Class (c) 2009
7
Quiz – 1 point distribution
• Mean: 3.5• SD: 1.05
14161820
Frequency
468
101214
Frequency
024
1 2 3 4 5 60 1 2 3 4 5
23 - 24 June Chalmers Virtual Design Class (c) 2009
8
The Ten Most Important Elements Include Physical Elements, Computer Elements and Software, p
Nice use of title as annotation to explain content
6/18/2009 Stanford 11
p
Three Actors; Designer, Manufacturer and Programmer Constitute the OrganizationProgrammer, Constitute the Organization
Nice use of title as annotation to explain content
6/18/2009 Stanford 12
p
Design, Programming and Manufacturing are the Processes Preceeding the Assemblingthe Processes Preceeding the Assembling
Nice use of title as annotation to explain content
6/18/2009 Stanford 13
p
Conformance Objectives Reaching the Highest WeightsHighest Weights
Conformance to ObjectivesObjectives
Notice use of annotation to explain important content
6/18/2009 Stanford 14
Project Time has the Highest Weighted Impact
Project TimeProject Time
Observed Project Time and Backlog
Notice use of annotation to explain important content
6/18/2009 Stanford 15
Peak Predicted Scheduled Risk has the Highest Weighted AssessmentHighest Weighted Assessment
Quality Risk 75%
Project Time
6/18/2009 Stanford 16
Evaluated Goodness Shows a Fairly Low Meeting of ObjectivesMeeting of Objectives
Goal . Evaluated goodness (high is good)
Evaluated Goodness
100
120
s
Evaluated Goodness
60
80
Eval
uate
d go
odne
s
Option 1: POP Option 2: POP V2
Meets all objectives
20
40
E
j
0Evaluated goodness
Design Versions
6/18/2009 Stanford 17
Organization Consists of Three Positions Working on Design, Manufacturing and Assemblingg , g g
Positions
Processes
6/18/2009 18Stanford
Processes
The Project is Performed in Close To a Month With Manufacturing Driving Most TimeWith Manufacturing Driving Most Time
Manufacturing
6/18/2009 19Stanford
Hidden Work Ads 65% Assembling Time Through Mainly CoordinationThrough Mainly Coordination
HiddenWork
6/18/2009 20Stanford
Notice use of annotation to explain important content
Big idea: “Design organizations”
If we design organizations as we design bridges, we can predict measure and manage “hidden” work which makespredict, measure and manage hidden work, which makes projects late if not managed well
Product Organization Process
Function Scope (…)Quality (…)
Design + Construct
Design + ConstructCosty ( )
Cost (…)Backlog (…)
Schedule (…)Schedule risk (…)
Form Deliverables Actors TasksBehavior Scope
QualityWork (direct, hidden) volumes CostBacklog
Work (direct, hidden) volumesCostStart, Finish, DurationS h d l i k
23 - 24 June Chalmers Virtual Design Class (c) 2009
21
Backlog Schedule risk
Organization Models
Models • How is this i ti “ d?”• Organization
• (Design) work
organization “good?”• Simulation
predictions:process predictions:– Gantt chart– Risks
KPFF
SRG Lab Task 37 Task 44 Project Mgt AEI Core Task 41 Task26 H Block Crew Task 23SRG / AEI Technical
AEI Core andSRG Lab HDCCO Costing SRG
Technical KPFFAEI Core and Tech HDCCO Core Code Rev
Consultant Solvent TarterH Block Crew
& TechSRG
LandscapeTele DataDesign Code Rev
Furniture
SRG Management AEI Management
Genentech PM
SRG Lab Plan
Ken Mouchka
Task 27Task 38
Organization
Task 28Task4 Task22
MEP, Teledata room design
Risks, …Final Program
Confirmation with Pharmacology
Final Program confirmation with LAR
35. *Finalize
41. *Reprogram bookends B#13 and
B#15
36. *Analyze structural impacts 22. *Complete catwalk drawings
26. *Finalize B#13 and B#15
Exiting/architecural H occupancy concept
23. *Reprogram B#13 and B#15
Exterior Architecture
Bookend Programming
Accepted by Genentech
Notice to proceed on structural changes
29. *Document lab plan
Task 29
Review 80% documents
*Package B structural modifications (CCD3A)
Review skin changes w/db team
Lab Planning Program Meetings with Pharmacology
Lab planning Program Meeting with ProteinChemistry
BMS Controls Meetings (Weekly)
Lab Planning Program meeting with Bio Organic 80% Drawing Review
Tele Data Coordination MeetingsSteel Detailing Meetings
Genentech 80% Detailed Design Review
Final Program Confirmation with Officing
Weekly Coordination
MeetingLab Planning Program Meetings with Directors
24. *Complete B13,4 H block occupancy
requirements on MEP systems
(8) *Revise MEP loads, MEP
Equipment schedules finalized
(13,15,16) MEP specs, P&ID's, control sequences
Work Process
Meetings
(6) Coord B13 MEP floor section
*Cal OSHA Recommend Determination of LFFH
*Exterior Programming
Accepted by Genentech
*05-07-01
Finish
34. *Finalize Pharmacology
Program
33. *Finalize LAR Program
32. *Finalize Bio-Organic Chemistry Program
Protein Chemistry Program 20. *Determine Scope of
package D including vivarium changes
25. *Do Central Plant design changes
52. Finalize landscape
*Lab and vivarium
Programming Complete
27. *Finalize B#13, 15 Shaft Size &
MEP Room Locations
31.* AEI & SRG
Determine Design $/Time
Impact of
Architect program/MEP
oncepts Established By Design
Team
1. *Redesign main MEP distribution systems
5. *Finalize lab & Equipment plans
30. *Approve Change to Design Contract
21. *Prepare Plan Views for Review of Concept w/City
39. *Finalize MEP distribution and
section
48. *Develop exiting plan
49. Develop reflected ceiling
plan
Turnover reflected
ceiling plan to AEI
Detailed Design 80 PC Complete
3. Complete Tele Data Design
42. *Develop Execution Strategy
44. *Complete B#14 Officing
Planning
18. *Detailed Lab Program
Documentation
47. *Develop lab DD plan
28. *Determine segregation of lab
and tech space
G accept lab equipment matrix
13. *Code Consultants Review Concept for final
city Presentation
14. *HDCCO update Estimate of cost of Program
50 Designate size location of
43. *Changes in Steel Forwarded to Steel
Detailers
46. *RA Furnture Concept Complete
*Design Budget & Schedule for Changes
Approved
*Notice to proceed with detailed design
17. *Risick reprogram solvent
distribution and waste
Issue 80% MEP CDs
(20) Incorporate 80% MEP review
comments
(19) Genentech review 80% drawings
53. Incorporate comments, complete Architectural detail
2. Initial redesign MEP branch lateral distribution
G accept
*City Accept exiting
*Package C skin
modifications MEP 80% Review comments incorporated
Package D and UG addendum issued:
underground utilities, vivarium catwalk
10. Draft Alternate means
15. Jeff reprogram HMIS
16. *HDCCO Determine Schedule Impact
City Approval of Alternate Means
for Program
8. Review Alternate Means w/impact on LEL
and LFFH
(21-4) Finalize MEP Details, update specs and p&ID's
4. complete all Interior Architcture
*Accept project scope:budget by Genentech
*City Approval of H Concept
*Turnover lab and vivarium DD plan
to AEI
23 - 24 June Chalmers Virtual Design Class (c) 2009 22
37. *Reprogram B#15 Shafts
45. *Complete all Basement/LAR Drawings
12. *Complete UG utiliites
19. *Determine vertical utilities
50. Designate size, location of 13 MEP, teledata rooms
54. KPFF design stairs for 13/1438. *SRG
Reprogram 13/14 interface, exiting,
stairs
G accept 13/14
Interface
55. KPFF design stairs for 15/14
40. *SRG Reprogram 15/14 interface, exiting,
stairs
B13 MEP HVAC, conduit, piping mains
completed
(3) *AEI design MEP HVAC, Conduit & piping mains B13
51. Designate size, location of 14 MEP, teledata rooms G accept
15/14 Interface
Conceptual underpinning: Model
Model Executive
Data system coordination
ProgramsProjectsTasks
Architect,Planning
Electrical, security, Netw orks HVAC, Utilities EHS EORM Client
SRG ArchitecturalFi
PM
Redesign FRC II for Open labs
TasksOrganization Start
Identify pathw ays & op w ork zones for
data/telco systems
Firm
Define EMI separationrequirements
Position1
PrecedenceException reportingCoordination Finish
Coordinate MEP design w /datarequirements
Ow ner approvalIdentify pathw ays & op
w ork zones forHVAC/MEP systems
CoordinationReworkMeetings
23 - 24 June Chalmers Virtual Design Class (c) 2009
23
g
The Challenge of Fast-Track Projects:“Concurrent Engineering” Incurs Large Overheadsg g g
CPM view of traditional project work – Sequential ActivitiesCPM View of Fast-Track Project work—Overlapped Activities
Reality of fast-track project work!
Increased Coordination
23 - 24 June Chalmers Virtual Design Class (c) 2009
24
Increased Rework
Conceptual Underpinning:P j t P I f tiProjects Process Information
The organi ation processes e ceptionsThe organization processes exceptions“Actors”:
D di t k
Position1
• Do direct work• Do hidden work
• CoordinateCoordinate• Rework• Wait
T kTasks:• Have direct work
Have hidden work
23 - 24 June Chalmers Virtual Design Class (c) 2009
25
• Have hidden work
Conceptual Underpinning:Simulate Task work, Information processing:Simulate Task work, Information processing:
• Model
Si l tSimulate
Analyze, Intervene,SW P roject
ManagerData
Architect
CustomerHw Spec Available
Analyze, Intervene, reanalyze
S tart1
Finish
UI-Analysis team
Customerrepresentativ e
Integration team
S W Design coordination
Developspecification
Im plem entdata m odel
Implement analysis system
UI stresstest
Info to Hw
Schedule risk
23 - 24 June Chalmers Virtual Design Class (c) 2009
26
Ready forsystem s test
Im plem ent UI
Integratesytem s
S ystem s integration test
analysis stresstest
Fail to Hw Cost Risk
Backlog
How VDT/SimVision worksE x e c u t iv e
S t a r t
Id e n t if y p a t h w a y s & o p w o r k z o n e s f o r
d a t a /t e lc o s y s t e m s
A r c h it e c t ,P la n n in g
E le c t r ic a l , s e c u r i t y , N e t w o r k s H V A C , U t i li t ie s E H S E O R M C lie n t
S R G A r c h i t e c t u r a lF ir m
P M
D e f in e E M I s e p a r a t io nr e q u ir e m e n t s
C d i t M E P d i /d t
D a t a s y s t e m c o o r d in a t io n
O w n e r l
• Basic simulator functions– Entities: tasks + milestones; activities; meetings;
F in is h
C o o r d in a t e M E P d e s ig n w /d a t ar e q u ir e m e n t s
a p p r o v a lId e n t if y p a t h w a y s & o p w o r k z o n e s f o r
H V A C /M E P s y s t e m s
Entities: tasks + milestones; activities; meetings; project
• Attributes: actor skills, task duration, task complexity, … Relationships:– Relationships:
• Responsibility (actor for task)• Reporting (Supervisor to actor)
S ( k k)• Successor (task to task)• Coordination (task to task - bidirectional) • Rework (task to task – directed)
23 - 24 June Chalmers Virtual Design Class (c) 2009
27
• Stochastic Entity “Micro” behaviors
How VDT/SimVision works S t a r t
Id e n t if y p a t h w a y s & o p w o r k z o n e s f o r
d a t a / t e lc o s y s t e m s
A r c h i t e c t ,P la n n in g
E le c t r ic a l , s e c u r i t y , N e t w o r k s H V A C , U t il i t ie s E H S E O R M C lie n t
S R G A r c h i t e c t u r a lF ir m
P M
E x e c u t iv e
D e f in e E M I s e p a r a t io n
D a t a s y s t e m c o o r d in a t io n
• “Discrete event” simulation: Simulator
F in is h
r e q u ir e m e n t s
C o o r d in a t e M E P d e s ig n w /d a t ar e q u ir e m e n t s
O w n e r a p p r o v a lId e n t if y p a t h w a y s & o p
w o r k z o n e s f o rH V A C /M E P s y s t e m s
Discrete event simulation: Simulator 1. Start milestone asks first task(s): please start2. Divide task into (~20) subtasks3. Task asks responsible actor: please start work
on (next) subtask1. Actor says OK; tells simulator to wait for predicted
subtask duration2. When actor “reawakened” later, ask “Am I done?”
– Yes: go to (4)– No; I failed: initiate rework; return to (3)– No; I got interrupted: initiate coordination; return to (3)
4. If last subtask competed, ask successor(s) to
23 - 24 June Chalmers Virtual Design Class (c) 2009
28
start; else return to (3)
How VDT/SimVision WorksE x e c u t iv e
S t a r t
Id e n t if y p a t h w a y s & o p w o r k z o n e s f o r
d a t a /t e lc o s y s t e m s
A r c h it e c t ,P la n n in g
E le c t r ic a l , s e c u r i t y , N e t w o r k s H V A C , U t i li t ie s E H S E O R M C lie n t
S R G A r c h i t e c t u r a lF ir m
P M
D e f in e E M I s e p a r a t io nr e q u ir e m e n t s
C d i t M E P d i /d t
D a t a s y s t e m c o o r d in a t io n
O w n e r l
• Stochastic Entity “Micro” behaviors– Task duration up (down) with actor skill(high low)
F in is h
C o o r d in a t e M E P d e s ig n w /d a t ar e q u ir e m e n t s
a p p r o v a lId e n t if y p a t h w a y s & o p w o r k z o n e s f o r
H V A C /M E P s y s t e m s
Task duration up (down) with actor skill(high, low)– Task coordination and rework probabilities up
(down) with actor skill (high, low)– Task coordination and rework probability up
(down) with task complexity (high, low)– …
• Simulator has precedence to sequence application of multiple µ-behaviors
23 - 24 June Chalmers Virtual Design Class (c) 2009
29
application of multiple µ-behaviors
Predicted project Cost Breakdown
P di t dPredictedDirect work
A d OK• Assumed OK….
Hidden workRework
• Maybe “light”Coordination• May be large
23 - 24 June Chalmers Virtual Design Class (c) 2009
30
Wait: no value add
Predicted Schedule Risks
Risks assuming staffRisks assuming staff, task definition interventionsinterventions
Predicted SchedulePredicted Schedule risk = Simulated –CPM (Optimistic) ( p )Durations
23 - 24 June Chalmers Virtual Design Class (c) 2009
31
Predicted actor backlog
• Backlog = work• Backlog = work left to do at the end of the dayRisks
– Schedule– CoordinationCoordination – Product, process
quality control
Principals need to• Principals need to manage workload
23 - 24 June Chalmers Virtual Design Class (c) 2009
32
Tuesday June 23
Plus Delta• 3 screens• POP introduction
• Computer broken• Use all 6 screensPOP introduction
• Switch screens while talking
Use all 6 screens• Hard to see right
screeng• Stories (Swedish)• Influence – cost
• Hard to hear in backInfluence cost curve
• Plus delta processp
Chalmers Virtual Design Class (c) 2009 3423 - 24 June
Big IdeaType-of
• Design and analyze organizations as we d i d l b iddesign and analyze bridges
• Organization analysis allows predicting the volume and distribution of total, direct and hidden work ⇒– Project and task durations– Actor backlogs & task risks
Final Program Confirmation with
Pharmacology
Final Program confirmation with LAR
KPFF
SRG Lab Task 37 Task 44 Project Mgt AEI Core Task 41 Task26 H Block Crew Task 23SRG / AEI Technical
AEI Core andSRG Lab HDCCO Costing SRG
Technical KPFFAEI Core and Tech HDCCO Core Code Rev
Consultant Solvent TarterH Block Crew
& TechSRG
LandscapeTele DataDesign Code Rev
Furniture
23. *Reprogram B#13 and B#15
Exterior Architecture
SRG Management AEI Management
Genentech PM
SRG Lab Plan
Ken Mouchka
Task 27Task 38
Organization
Task 29
Task 28Task4 Task22
Review 80% documents
Review skin changes w/db team
Lab Planning Program Meetings with Pharmacology
Lab planning Program Meeting with ProteinChemistry
BMS Controls Meetings (Weekly)
Lab Planning Program meeting with Bio Organic 80% Drawing Review
Tele Data Coordination MeetingsSteel Detailing Meetings
Genentech 80% Detailed Design Review
Final Program Confirmation with Officing
Weekly Coordination
MeetingLab Planning Program Meetings with Directors
MEP, Teledata room design
24. *Complete B13,4 H block occupancy
requirements on MEP
Work Process
Meetings
(6) Coord B13 MEP
*Cal OSHA Recommend Determination of LFFH
*Exterior Programming
Accepted by Genentech– Actor backlogs & task risks– Coordination, rework wait time that
make projects late and participants k d d f t t d
*05-07-01
Finish
37
34. *Finalize Pharmacology
Program
33. *Finalize LAR Program
32. *Finalize Bio-Organic Chemistry Program
35. *Finalize Protein Chemistry
Program 20. *Determine Scope of package D including vivarium
changes
41. *Reprogram bookends B#13 and
B#15
36. *Analyze structural impacts
25. *Do Central Plant design changes
22. *Complete catwalk drawings
52. Finalize landscape
26. *Finalize B#13 and B#15
Exiting/architecural H occupancy concept
*Lab and vivarium
Programming Complete
27. *Finalize B#13, 15 Shaft Size &
MEP Room Locations
31.* AEI & SRG
Determine Design $/Time
Impact of
Bookend Programming
Accepted by Genentech
Notice to proceed on structural changes
Architect program/MEP
oncepts Established By Design
Team
29. *Document lab plan
1. *Redesign main MEP distribution systems
5. *Finalize lab & Equipment plans
30. *Approve Change to Design Contract
21. *Prepare Plan Views for Review of Concept w/City
39. *Finalize MEP distribution and
section
48. *Develop exiting plan
49. Develop reflected ceiling
plan
Turnover reflected
ceiling plan to AEI
Detailed Design 80 PC Complete
3. Complete Tele Data Design
42. *Develop Execution Strategy
44. *Complete B#14 Officing
Planning
18. *Detailed Lab Program
Documentation
47. *Develop lab DD plan
28. *Determine segregation of lab
and tech space
G accept lab equipment matrix
*Package B structural modifications (CCD3A)
13. *Code Consultants Review Concept for final
city Presentation
14. *HDCCO update Estimate of cost of Program
50. Designate size, location of 13 MEP, teledata rooms
54. KPFF design stairs for 13/1438. *SRG
Reprogram 13/14 interface, exiting,
stairs
43. *Changes in Steel Forwarded to Steel
Detailers
46. *RA Furnture Concept Complete
*Design Budget & Schedule for Changes
Approved
*Notice to proceed with detailed design
systems
17. *Risick reprogram solvent
distribution and waste
Issue 80% MEP CDs
(20) Incorporate 80% MEP review
comments
(19) Genentech review 80% drawings
53. Incorporate comments, complete
Architectural detail
2. Initial redesign MEP branch lateral distribution
G accept 13/14
Interface
*City Accept exiting
*Package C skin
modifications
55. KPFF design stairs for 15/14
40. *SRG Reprogram 15/14 interface, exiting,
stairs
B13 MEP HVAC, conduit, piping mains
completed
MEP 80% Review comments incorporated
Package D and UG addendum issued:
underground utilities, vivarium catwalk
10. Draft Alternate means
15. Jeff reprogram HMIS
16. *HDCCO Determine Schedule Impact
City Approval of Alternate Means
for Program
8. Review Alternate Means w/impact on LEL
and LFFH
(21-4) Finalize MEP Details, update specs and p&ID's
(8) *Revise MEP loads, MEP
Equipment schedules finalized
(13,15,16) MEP specs, P&ID's, control sequences
(6) Coord B13 MEP floor section
4. complete all Interior Architcture
51. Designate size, location of 14 MEP, teledata rooms G accept
15/14 Interface
*Accept project scope:budget by Genentech
*City Approval of H Concept
*Turnover lab and vivarium DD plan
to AEI
overworked and frustrated 37. *Reprogram B#15 Shafts
45. *Complete all Basement/LAR Drawings
12. *Complete UG utiliites
19. *Determine vertical utilities
(3) *AEI design MEP HVAC, Conduit & piping mains B13
35Chalmers Virtual Design Class (c) 200923 - 24 June
Method
• Design the organization g gmodel using the OBS and Organization segment of the g gPOP model
Final Program Confirmation with
Pharmacology
Final Program confirmation with LAR
KPFF
SRG Lab Task 37 Task 44 Project Mgt AEI Core Task 41 Task26 H Block Crew Task 23SRG / AEI Technical
AEI Core andSRG Lab HDCCO Costing SRG
Technical KPFFAEI Core and Tech HDCCO Core Code Rev
Consultant Solvent TarterH Block Crew
& TechSRG
LandscapeTele DataDesign Code Rev
Furniture
23. *Reprogram B#13 and B#15
Exterior Architecture
SRG Management AEI Management
Genentech PM
SRG Lab Plan
Ken Mouchka
Task 27Task 38
Organization
Task 29
Task 28Task4 Task22
Review 80% documents
Review skin changes w/db team
Lab Planning Program Meetings with Pharmacology
Lab planning Program Meeting with ProteinChemistry
BMS Controls Meetings (Weekly)
Lab Planning Program meeting with Bio Organic 80% Drawing Review
Tele Data Coordination MeetingsSteel Detailing Meetings
Genentech 80% Detailed Design Review
Final Program Confirmation with Officing
Weekly Coordination
MeetingLab Planning Program Meetings with Directors
MEP, Teledata room design
24. *Complete B13,4 H block occupancy
requirements on MEP
Work Process
Meetings
(6) Coord B13 MEP
*Cal OSHA Recommend Determination of LFFH
*Exterior Programming
Accepted by Genentech
*05-07-01
Finish
37
34. *Finalize Pharmacology
Program
33. *Finalize LAR Program
32. *Finalize Bio-Organic Chemistry Program
35. *Finalize Protein Chemistry
Program 20. *Determine Scope of package D including vivarium
changes
41. *Reprogram bookends B#13 and
B#15
36. *Analyze structural impacts
25. *Do Central Plant design changes
22. *Complete catwalk drawings
52. Finalize landscape
26. *Finalize B#13 and B#15
Exiting/architecural H occupancy concept
*Lab and vivarium
Programming Complete
27. *Finalize B#13, 15 Shaft Size &
MEP Room Locations
31.* AEI & SRG
Determine Design $/Time
Impact of
Bookend Programming
Accepted by Genentech
Notice to proceed on structural changes
Architect program/MEP
oncepts Established By Design
Team
29. *Document lab plan
1. *Redesign main MEP distribution systems
5. *Finalize lab & Equipment plans
30. *Approve Change to Design Contract
21. *Prepare Plan Views for Review of Concept w/City
39. *Finalize MEP distribution and
section
48. *Develop exiting plan
49. Develop reflected ceiling
plan
Turnover reflected
ceiling plan to AEI
Detailed Design 80 PC Complete
3. Complete Tele Data Design
42. *Develop Execution Strategy
44. *Complete B#14 Officing
Planning
18. *Detailed Lab Program
Documentation
47. *Develop lab DD plan
28. *Determine segregation of lab
and tech space
G accept lab equipment matrix
*Package B structural modifications (CCD3A)
13. *Code Consultants Review Concept for final
city Presentation
14. *HDCCO update Estimate of cost of Program
50. Designate size, location of 13 MEP, teledata rooms
54. KPFF design stairs for 13/1438. *SRG
Reprogram 13/14 interface, exiting,
stairs
43. *Changes in Steel Forwarded to Steel
Detailers
46. *RA Furnture Concept Complete
*Design Budget & Schedule for Changes
Approved
*Notice to proceed with detailed design
systems
17. *Risick reprogram solvent
distribution and waste
Issue 80% MEP CDs
(20) Incorporate 80% MEP review
comments
(19) Genentech review 80% drawings
53. Incorporate comments, complete
Architectural detail
2. Initial redesign MEP branch lateral distribution
G accept 13/14
Interface
*City Accept exiting
*Package C skin
modifications
55. KPFF design stairs for 15/14
40. *SRG Reprogram 15/14 interface, exiting,
stairs
B13 MEP HVAC, conduit, piping mains
completed
MEP 80% Review comments incorporated
Package D and UG addendum issued:
underground utilities, vivarium catwalk
10. Draft Alternate means
15. Jeff reprogram HMIS
16. *HDCCO Determine Schedule Impact
City Approval of Alternate Means
for Program
8. Review Alternate Means w/impact on LEL
and LFFH
(21-4) Finalize MEP Details, update specs and p&ID's
(8) *Revise MEP loads, MEP
Equipment schedules finalized
(13,15,16) MEP specs, P&ID's, control sequences
(6) Coord B13 MEP floor section
4. complete all Interior Architcture
51. Designate size, location of 14 MEP, teledata rooms G accept
15/14 Interface
*Accept project scope:budget by Genentech
*City Approval of H Concept
*Turnover lab and vivarium DD plan
to AEIType-of
37. *Reprogram B#15 Shafts
45. *Complete all Basement/LAR Drawings
12. *Complete UG utiliites
19. *Determine vertical utilities
(3) *AEI design MEP HVAC, Conduit & piping mains B13
Chalmers Virtual Design Class (c) 200923 - 24 June
Breakdown structures in VDC
ProductBreakdown
Product Component types DescribeBreakdown
Structure (PBS)Major types of
Describe Physical elementsSystemsScomponents Spaces
Relate (implicitly) to OBS, WBS
Breakdown structuresType-of
Breakdown structuresHierarchicalRelate to each otherTypes, not instances
23 - 24 June Chalmers Virtual Design Class (c) 2009 37
Breakdown structures in VDC
OrganizationBreakdown
Organization component Breakdown Structure (OBS)
Major types of
types Describe Actors
Designorganization components
gConstructionOther stakeholders
Relate (implicitly) to PBS, WBS
Breakdown structuresType-of
Breakdown structuresHierarchicalRelate to each otherTypes, not instances
23 - 24 June Chalmers Virtual Design Class (c) 2009 38
Breakdown structures in VDC
Process (Work) Breakdown
Process (Work) component types D ib t kBreakdown
Structure (WBS)Major types of
Describe tasksDesignConstruction
tasks OtherRelate (explicitly) to OBS, WBS
Breakdown structuresType-of
Breakdown structuresHierarchicalRelate to each otherTypes, not instances
23 - 24 June Chalmers Virtual Design Class (c) 2009 39
Implicit in BSs, POP
• BSs (and hence POP models) do not (but models do) represent:models do) represent:– Attributes
• Product: dimensions, cost, materials, …• Actor: size, experience, skills available, …• Task: size, complexity, skills needed, …
– Relationships amongp g• Product elements: supports, enclosed-by, adjacency• Actors: reports-to, responsibility• Tasks: precedence, coordination, reworkp , ,• Product Elements ⇔ Organization actors ⇔ Process tasks
23 - 24 June Chalmers Virtual Design Class (c) 2009 40
Implicit in BSs, POP
• BSs (and hence POP models) do not (but i li d d l d ) tspecialized models do) represent:
– Discipline applications• Product model• Organization – Process model
P l h d l• Process plan or schedule
Type-of
23 - 24 June Chalmers Virtual Design Class (c) 2009 41
Big Ideas
• Design the organization model using the OBS and Organization segment of theOBS and Organization segment of the POP model
• Organization analysis allows predicting the volume and distribution of hidden work: thevolume and distribution of hidden work: the coordination and rework that make projects late and cause staff frustration and burnout
• Organization analysis allows predicting theFinal Program
Confirmation with Pharmacology
Final Program confirmation with LAR
KPFF
SRG Lab Task 37 Task 44 Project Mgt AEI Core Task 41 Task26 H Block Crew Task 23SRG / AEI Technical
AEI Core andSRG Lab HDCCO Costing SRG
Technical KPFFAEI Core and Tech HDCCO Core Code Rev
Consultant Solvent TarterH Block Crew
& TechSRG
LandscapeTele DataDesign Code Rev
Furniture
23. *Reprogram B#13 and B#15
Exterior Architecture
SRG Management AEI Management
Genentech PM
SRG Lab Plan
Ken Mouchka
Task 27Task 38
Organization
Task 29
Task 28Task4 Task22
Review 80% documents
Review skin changes w/db team
Lab Planning Program Meetings with Pharmacology
Lab planning Program Meeting with ProteinChemistry
BMS Controls Meetings (Weekly)
Lab Planning Program meeting with Bio Organic 80% Drawing Review
Tele Data Coordination MeetingsSteel Detailing Meetings
Genentech 80% Detailed Design Review
Final Program Confirmation with Officing
Weekly Coordination
MeetingLab Planning Program Meetings with Directors
MEP, Teledata room design
24. *Complete B13,4 H block occupancy
requirements on MEP
Work Process
Meetings
(6) Coord B13 MEP
*Cal OSHA Recommend Determination of LFFH
*Exterior Programming
Accepted by Genentech• Organization analysis allows predicting the volume and distribution of total, direct and hidden work ⇒– Project and task durations
*05-07-01
Finish
37
34. *Finalize Pharmacology
Program
33. *Finalize LAR Program
32. *Finalize Bio-Organic Chemistry Program
35. *Finalize Protein Chemistry
Program 20. *Determine Scope of package D including vivarium
changes
41. *Reprogram bookends B#13 and
B#15
36. *Analyze structural impacts
25. *Do Central Plant design changes
22. *Complete catwalk drawings
52. Finalize landscape
26. *Finalize B#13 and B#15
Exiting/architecural H occupancy concept
*Lab and vivarium
Programming Complete
27. *Finalize B#13, 15 Shaft Size &
MEP Room Locations
31.* AEI & SRG
Determine Design $/Time
Impact of
Bookend Programming
Accepted by Genentech
Notice to proceed on structural changes
Architect program/MEP
oncepts Established By Design
Team
29. *Document lab plan
1. *Redesign main MEP distribution systems
5. *Finalize lab & Equipment plans
30. *Approve Change to Design Contract
21. *Prepare Plan Views for Review of Concept w/City
39. *Finalize MEP distribution and
section
48. *Develop exiting plan
49. Develop reflected ceiling
plan
Turnover reflected
ceiling plan to AEI
Detailed Design 80 PC Complete
3. Complete Tele Data Design
42. *Develop Execution Strategy
44. *Complete B#14 Officing
Planning
18. *Detailed Lab Program
Documentation
47. *Develop lab DD plan
28. *Determine segregation of lab
and tech space
G accept lab equipment matrix
*Package B structural modifications (CCD3A)
13. *Code Consultants Review Concept for final
city Presentation
14. *HDCCO update Estimate of cost of Program
50. Designate size, location of 13 MEP, teledata rooms
54. KPFF design stairs for 13/1438. *SRG
Reprogram 13/14 interface, exiting,
stairs
43. *Changes in Steel Forwarded to Steel
Detailers
46. *RA Furnture Concept Complete
*Design Budget & Schedule for Changes
Approved
*Notice to proceed with detailed design
systems
17. *Risick reprogram solvent
distribution and waste
Issue 80% MEP CDs
(20) Incorporate 80% MEP review
comments
(19) Genentech review 80% drawings
53. Incorporate comments, complete
Architectural detail
2. Initial redesign MEP branch lateral distribution
G accept 13/14
Interface
*City Accept exiting
*Package C skin
modifications
55. KPFF design stairs for 15/14
40. *SRG Reprogram 15/14 interface, exiting,
stairs
B13 MEP HVAC, conduit, piping mains
completed
MEP 80% Review comments incorporated
Package D and UG addendum issued:
underground utilities, vivarium catwalk
10. Draft Alternate means
15. Jeff reprogram HMIS
16. *HDCCO Determine Schedule Impact
City Approval of Alternate Means
for Program
8. Review Alternate Means w/impact on LEL
and LFFH
(21-4) Finalize MEP Details, update specs and p&ID's
(8) *Revise MEP loads, MEP
Equipment schedules finalized
(13,15,16) MEP specs, P&ID's, control sequences
(6) Coord B13 MEP floor section
4. complete all Interior Architcture
51. Designate size, location of 14 MEP, teledata rooms G accept
15/14 Interface
*Accept project scope:budget by Genentech
*City Approval of H Concept
*Turnover lab and vivarium DD plan
to AEI
– Project and task durations– Actor backlogs & task risks– Coordination and rework effort that
make projects late and participants
37. *Reprogram B#15 Shafts
45. *Complete all Basement/LAR Drawings
12. *Complete UG utiliites
19. *Determine vertical utilities
(3) *AEI design MEP HVAC, Conduit & piping mains B13
make projects late and participants overworked and frustrated
23 - 24 June Chalmers Virtual Design Class (c) 2009 42
Organization Models
• ModelO i ti
• How “good” is this Organization – Process• Organization
• (Design) work process
Organization – Process design?
• Simulation predictions:– Gantt chart– Risks, …
KPFF
SRG Lab Task 37 Task 44 Project Mgt AEI Core Task 41 Task26 H Block Crew Task 23SRG / AEI Technical
AEI Core andSRG Lab HDCCO Costing SRG
Technical KPFFAEI Core and Tech HDCCO Core Code Rev
Consultant Solvent TarterH Block Crew
& TechSRG
LandscapeTele DataDesign Code Rev
Furniture
SRG Management AEI Management
Genentech PM
SRG Lab Plan
Ken Mouchka
Task 27Task 38
Organization
Task 28Task4 Task22
MEP, Teledata room design
Final Program Confirmation with
Pharmacology
Final Program confirmation with LAR
35. *Finalize
41. *Reprogram bookends B#13 and
B#15
36. *Analyze structural impacts 22. *Complete catwalk drawings
26. *Finalize B#13 and B#15
Exiting/architecural H occupancy concept
23. *Reprogram B#13 and B#15
Exterior Architecture
Bookend Programming
Accepted by Genentech
Notice to proceed on structural changes
29. *Document lab plan
Task 29
Review 80% documents
*Package B structural modifications (CCD3A)
Review skin changes w/db team
Lab Planning Program Meetings with Pharmacology
Lab planning Program Meeting with ProteinChemistry
BMS Controls Meetings (Weekly)
Lab Planning Program meeting with Bio Organic 80% Drawing Review
Tele Data Coordination MeetingsSteel Detailing Meetings
Genentech 80% Detailed Design Review
Final Program Confirmation with Officing
Weekly Coordination
MeetingLab Planning Program Meetings with Directors
24. *Complete B13,4 H block occupancy
requirements on MEP systems
(8) *Revise MEP loads, MEP
Equipment schedules finalized
(13,15,16) MEP specs, P&ID's, control sequences
Work Process
Meetings
(6) Coord B13 MEP floor section
*Cal OSHA Recommend Determination of LFFH
*Exterior Programming
Accepted by Genentech
*05-07-01
Finish
34. *Finalize Pharmacology
Program
33. *Finalize LAR Program
32. *Finalize Bio-Organic Chemistry Program
Protein Chemistry Program 20. *Determine Scope of
package D including vivarium changes
25. *Do Central Plant design changes
52. Finalize landscape
*Lab and vivarium
Programming Complete
27. *Finalize B#13, 15 Shaft Size &
MEP Room Locations
31.* AEI & SRG
Determine Design $/Time
Impact of
Architect program/MEP
oncepts Established By Design
Team
1. *Redesign main MEP distribution systems
5. *Finalize lab & Equipment plans
30. *Approve Change to Design Contract
21. *Prepare Plan Views for Review of Concept w/City
39. *Finalize MEP distribution and
section
48. *Develop exiting plan
49. Develop reflected ceiling
plan
Turnover reflected
ceiling plan to AEI
Detailed Design 80 PC Complete
3. Complete Tele Data Design
42. *Develop Execution Strategy
44. *Complete B#14 Officing
Planning
18. *Detailed Lab Program
Documentation
47. *Develop lab DD plan
28. *Determine segregation of lab
and tech space
G accept lab equipment matrix
13. *Code Consultants Review Concept for final
city Presentation
14. *HDCCO update Estimate of cost of Program
50 Designate size location of
43. *Changes in Steel Forwarded to Steel
Detailers
46. *RA Furnture Concept Complete
*Design Budget & Schedule for Changes
Approved
*Notice to proceed with detailed design
17. *Risick reprogram solvent
distribution and waste
Issue 80% MEP CDs
(20) Incorporate 80% MEP review
comments
(19) Genentech review 80% drawings
53. Incorporate comments, complete Architectural detail
2. Initial redesign MEP branch lateral distribution
G accept
*City Accept exiting
*Package C skin
modifications MEP 80% Review comments incorporated
Package D and UG addendum issued:
underground utilities, vivarium catwalk
10. Draft Alternate means
15. Jeff reprogram HMIS
16. *HDCCO Determine Schedule Impact
City Approval of Alternate Means
for Program
8. Review Alternate Means w/impact on LEL
and LFFH
(21-4) Finalize MEP Details, update specs and p&ID's
4. complete all Interior Architcture
*Accept project scope:budget by Genentech
*City Approval of H Concept
*Turnover lab and vivarium DD plan
to AEI
37. *Reprogram B#15 Shafts
45. *Complete all Basement/LAR Drawings
12. *Complete UG utiliites
19. *Determine vertical utilities
50. Designate size, location of 13 MEP, teledata rooms
54. KPFF design stairs for 13/1438. *SRG
Reprogram 13/14 interface, exiting,
stairs
G accept 13/14
Interface
55. KPFF design stairs for 15/14
40. *SRG Reprogram 15/14 interface, exiting,
stairs
B13 MEP HVAC, conduit, piping mains
completed
(3) *AEI design MEP HVAC, Conduit & piping mains B13
51. Designate size, location of 14 MEP, teledata rooms G accept
15/14 Interface
23 - 24 June Chalmers Virtual Design Class (c) 2009 43
Conceptual framework: ModelSimulator simulates actors doing tasksSimulator simulates actors doing tasks
Model Executive
Data system coordination
ProgramsProjectsTasks
Architect,Planning
Electrical, security, Netw orks HVAC, Utilities EHS EORM Client
SRG ArchitecturalFi
PM
Redesign FRC II for Open labs
TasksOrganization Start
Identify pathw ays & op w ork zones for
data/telco systems
Firm
Define EMI separationrequirements
Position1
PrecedenceException reportingCoordination Finish
Coordinate MEP design w /datarequirements
Ow ner approvalIdentify pathw ays & op
w ork zones forHVAC/MEP systems
CoordinationReworkMeetingsg
Chalmers Virtual Design Class (c) 200923 - 24 June
Organization Optionsg p
• Any two goals look attainable – Duration; Cost (staff); Organization process quality
Legend Meets Goal Almost meets Unmet goal Goalg
Case Sim Finish Time Sim Cost (K$) Risk Comment*Contractor increase staff 3/21/01 244 0.515 Not feasibleAll staff FT 4/16/01 252 0.56 Very difficult for other projects50% Design review/meetings 5/7/01 353 0.48 Force quick owner decisionsShorten 50% review tasks 5/21/01 384 0.42 Encourage quick owner decisionsJohn Q. Full Time 6/6/01 311 0.525 John Q. plus Gary FTJohn H. Part Time 6/21/01 324 0.545 John H. plus Gary FTDon S. Full Time 8/5/01 321 0.56 Don S. plus Gary FTGary S. Full Time 10/4/01 335 0.485 Split Contractor Tasks 10/19/01 257 0.5 Add contractor resourcesGary, Amy 50% 10/22/01 251 0.395y, y / /Baseline 12/11/01 350 0.515
23 - 24 June Chalmers Virtual Design Class (c) 2009 45
Evaluation of Schedule goalg
To achieve feasible schedule• Most staff available Full time• Do 50% design review by meetings, vs. tasks
Sim Finish Time
/ /12/25/01
2/13/02
2/28/014/19/01
6/8/017/28/019/16/0111/5/01
Fini
sh D
ate
10/1/0011/20/00
1/9/01
rease
staff
All staf
f FT
w/mee
tings
view ta
sks
QFull
Time
Part Ti
meS
Full Tim
eS
Full Tim
ecto
r Tas
ksAmy 5
0%Bas
eline
46*Con
tracto
r incre Al
50% D
esign
revie
w/
Shorte
n 50%
rev
John
Q. F
John
H. P
Don S
. FGary
S. F
Split C
ontra
ctGary
, A B
Chalmers Virtual Design Class (c) 200923 - 24 June Chalmers Virtual Design Class (c) 2009 46
Evaluation of Budget goalg g
To achieve feasible budgetCases with acceptable schedule
P di t d St ff C t (K$)Predicted Staff Cost (K$)
300350400450
050
100150200250300
0
tracto
r incre
ase s
taff
Gary, A
my 50%
All staf
f FT
plit C
ontra
ctor T
asks
John
Q. F
ull Ti
me
Don S
. Full
Time
John
H. P
art Ti
me
Gary S
. Full
Time
Baseli
ne
sign r
eview
/mee
tings
en 50
% revie
w task
s
47
*Con
tra Spli
50% D
esig
Shorte
n
Chalmers Virtual Design Class (c) 200923 - 24 June
Evaluation of risk goal
To achieve feasible organization process qualityCases with acceptable scheduleC ith t bl
Risk
Cases with acceptable budget
0 3
0.4
0.5
0.6
0
0.1
0.2
0.3
% s s e s ff e e e T e
Gary, A
my 50%
Shorte
n 50%
revie
w task
s
% Des
ign re
view/m
eetin
gs
Gary S
. Full
Time
Split C
ontra
ctor T
asks
*Con
tracto
r incre
ase s
taff
Baseli
ne
John
Q. F
ull Ti
me
John
H. P
art Ti
meAll s
taff F
T
Don S
. Full
Time
Sh50
% *C
23 - 24 June Chalmers Virtual Design Class (c) 2009 48
Comparing Project Schedule Risksp g j
Risks assuming staffRisks assuming staff, task definition interventionsinterventions
Predicted Schedule risk = Simulated –CPM (Optimistic) Durations
23 - 24 June Chalmers Virtual Design Class (c) 2009 49
Tabular results
• Program Stats• Program Stats• Project Stats• Task Stats• Organization
Stats• Milestone Stats• Position Stats
Copy and paste to Excelto Excel
23 - 24 June Chalmers Virtual Design Class (c) 2009 50
Executive Dashboard
• Shows evaluation of predicted behaviorShows evaluation of predicted behavior (finish date, revenue, cost, quality, backlog) | Goalsbacklog) | Goals
23 - 24 June Chalmers Virtual Design Class (c) 2009 51
SimVision
• DescribeF F d B f O i ti d l– F,F and B of Organization and process plus relationships within and between each
• Explain (“why”): n/ap ( y )• Evaluate: which organization – process
design version(s) satisfies stated i t (E ti D hb d)requirements (Executive Dashboard);
• Predict:Actor Backlogs task schedule dates actor and– Actor Backlogs, task schedule dates, actor and task effort, actor and task risks (charts)
23 - 24 June Chalmers Virtual Design Class (c) 2009 52
Representation of Organization and ProcessProduct Form Weight
Requirement
Relationshi(sum
=
Function Qualitative Threshhold values Behaviors
– Functions:• POP SimVision
Object AttributeRelationshi
p Requirement Choice Predicted Observed Assessed -2 -1 0 1 2 100)Product
Product Scope
Requirement
Relationship
Functional Requirement
Product Form (Space, System)
Product Scope . Systems includes Systems Systems ?o ?a ?wProduct Scope . Building Spaces includes Spaces Spaces ?o ?a ?wProject GoalsProject Goal . Capacity (people) >= - ?p ?o ?a ?a ?a ?a ?a ?a ?wProject Goal . Evaluated goodness ?o ?a
Organization Scope
Requirement
Relationship
Functional Requirement
Organization Form (Actor)
Organization Scope . Actors includes ActorsOrganization GoalsOrganization Goal . Predicted . Cost (K$) <= ?r ?p ?o ?a ?a ?a ?a ?a ?a ?wProcess
Process Scope (Task Action: Object) Responsible Actor Process Form (Task
Action: Object)Process Task . Design: Building Actor Actor that designs Task . Design: Building
ProcessTask . Predict: Predictable Behaviors Actor Actor that predicts
Task . Predict: Predictable Behaviors
Process Task . Assess: Behaviors Actor Actor that assessesTask . Assess:
BehaviorsProcess Task . Build: Building Actor Actor that builds Task . Build: BuildingProcess GoalsProcess Goal Peak Quality Risk < ?r ?p ?o ?a ?a ?a ?a ?a ?a ?w
Organization
POP SimVision• Represent threshold values and result of evaluating
predicted results in MACDADI– Forms/Scope
S tart1
Finish
S W ProjectManager
DataArchitect
UI-Analysis team
Custom errepresentativ e
Integration team
SW Design coordination
Dev elopspecification
Im plem entdata m odel
Im plem ent analys is system
UI s tresstest
Hw Spec Available
Info to Hw
Process Goal . Peak Quality Risk < ?r ?p ?o ?a ?a ?a ?a ?a ?a ?w0 0Sum (weights):Sum (Assessed goodness):
S tart1
S W ProjectManager
DataArchitect
UI-Analysis team
Custom errepresentativ e
Integration team
SW Design coordination
Dev elop
Hw Spec Available
Info to HwForms/Scope• POP SimVision
– BehaviorsSi Vi i di t i th ti ll f d d
Ready forsystem s test
Im plem ent U I
Integratesytem s
S ystem s integration test
analys is stresstest
Fail to Hw
Ready forsystem s test
Finish
specification
Im plem entdata m odel
Im plem ent U I
Integratesytem s
S ystem s integration test
Im plem ent analys is system
UI s tresstest
analys is stresstest
Fail to Hw
• SimVision predicts using theoretically-founded, model-based methods POP
• EvaluationSimVision evaluates design performance | Functional– SimVision evaluates design performance | Functional goals MACDADI
– You can use MACDADI to define a broader goal set
23 - 24 June Chalmers Virtual Design Class (c) 2009 53
SimVision methods
• Design options: – Create new Case for each option– Suggestion: Make one intervention per case
Compare case results in Executive Dashboard– Compare case results in Executive Dashboardand charts of result comparisons
23 - 24 June Chalmers Virtual Design Class (c) 2009 54
SimVision methods
• Possible Interventions – Change:– Task definition– Task precedence
T k St t t t t l– Task Start-to-start lag– Actor size
Actor task assignment– Actor – task assignment– Actor skills
Goals– Goals
CasesCases
23 - 24 June Chalmers Virtual Design Class (c) 2009 55
Virtual Design and Constructiong
• Use of multi-disciplinary • Organization modelsp yperformance models of design–construction projects
Organization models in VDC– Each discipline has p j
– Product (building)– Organization – Work Process
pan organization, work processAll disciplines mustWork Process
• To– Visualize and describe
project
– All disciplines must coordinate!
– Assuming:project– Analyze project
performance– Predict effects of choices
g– Simulate model:
Predict effects of choices– Evaluate choices
23 - 24 June Chalmers Virtual Design Class (c) 2009 56
(Multiple) Predictable performance objectives• Safety: 0 lost hours
l l dy
Schedule, Cost, Scope: 100% client satisfaction • Sustainability: 10-20% better than previous recent jobs Outcomes
Schedule: 95% on-time start, finish of all scheduled activitiesC t 95% f b d t d it ithi 2% f b d t d t
Directly related to Organization Model
• Cost: >= 95% of budgeted items within 2% of budgeted costField material delivery: 95% within 24 hours of useDecision latency (Decision-making promptness): mean working days <= 1; 95% within 2 daysyResponse latency (Decision-making no earlier than necessary): mean working days <= 1; 95% within 2 daysField-generated Requests for Information: 0 (for questions related to issues that could have been identified at the award of the construction contract)could have been identified at the award of the construction contract) Rework volume: 0 (for field construction work); Goal = 10-20% (virtual work)Meeting effectiveness: > 90% participationMeeting efficiency: > 70% prediction, evaluation Drivers – Measurable processScope: POP designs; objectives to manageModeled and managed Scope: 100% of POP items with > 10 (2)% of time, cost, effort or energyCoordination activity: planned, explicit, public, informed > 90%Coordination activity: planned, explicit, public, informed 90%Prediction basis: > 80% of predictions foundedDesign versions: 2 or more >= 80% Controllable
23 - 24 June Chalmers Virtual Design Class (c) 2009 57
Big IdeaType-of
• Design and analyze organizations as we d i d l b iddesign and analyze bridges
• Organization analysis allows predicting the volume and distribution of total, direct and hidden work ⇒– Project and task durations– Actor backlogs & task risks
Final Program Confirmation with
Pharmacology
Final Program confirmation with LAR
KPFF
SRG Lab Task 37 Task 44 Project Mgt AEI Core Task 41 Task26 H Block Crew Task 23SRG / AEI Technical
AEI Core andSRG Lab HDCCO Costing SRG
Technical KPFFAEI Core and Tech HDCCO Core Code Rev
Consultant Solvent TarterH Block Crew
& TechSRG
LandscapeTele DataDesign Code Rev
Furniture
23. *Reprogram B#13 and B#15
Exterior Architecture
SRG Management AEI Management
Genentech PM
SRG Lab Plan
Ken Mouchka
Task 27Task 38
Organization
Task 29
Task 28Task4 Task22
Review 80% documents
Review skin changes w/db team
Lab Planning Program Meetings with Pharmacology
Lab planning Program Meeting with ProteinChemistry
BMS Controls Meetings (Weekly)
Lab Planning Program meeting with Bio Organic 80% Drawing Review
Tele Data Coordination MeetingsSteel Detailing Meetings
Genentech 80% Detailed Design Review
Final Program Confirmation with Officing
Weekly Coordination
MeetingLab Planning Program Meetings with Directors
MEP, Teledata room design
24. *Complete B13,4 H block occupancy
requirements on MEP
Work Process
Meetings
(6) Coord B13 MEP
*Cal OSHA Recommend Determination of LFFH
*Exterior Programming
Accepted by Genentech– Actor backlogs & task risks– Coordination, rework wait time that
make projects late and participants k d d f t t d
*05-07-01
Finish
37
34. *Finalize Pharmacology
Program
33. *Finalize LAR Program
32. *Finalize Bio-Organic Chemistry Program
35. *Finalize Protein Chemistry
Program 20. *Determine Scope of package D including vivarium
changes
41. *Reprogram bookends B#13 and
B#15
36. *Analyze structural impacts
25. *Do Central Plant design changes
22. *Complete catwalk drawings
52. Finalize landscape
26. *Finalize B#13 and B#15
Exiting/architecural H occupancy concept
*Lab and vivarium
Programming Complete
27. *Finalize B#13, 15 Shaft Size &
MEP Room Locations
31.* AEI & SRG
Determine Design $/Time
Impact of
Bookend Programming
Accepted by Genentech
Notice to proceed on structural changes
Architect program/MEP
oncepts Established By Design
Team
29. *Document lab plan
1. *Redesign main MEP distribution systems
5. *Finalize lab & Equipment plans
30. *Approve Change to Design Contract
21. *Prepare Plan Views for Review of Concept w/City
39. *Finalize MEP distribution and
section
48. *Develop exiting plan
49. Develop reflected ceiling
plan
Turnover reflected
ceiling plan to AEI
Detailed Design 80 PC Complete
3. Complete Tele Data Design
42. *Develop Execution Strategy
44. *Complete B#14 Officing
Planning
18. *Detailed Lab Program
Documentation
47. *Develop lab DD plan
28. *Determine segregation of lab
and tech space
G accept lab equipment matrix
*Package B structural modifications (CCD3A)
13. *Code Consultants Review Concept for final
city Presentation
14. *HDCCO update Estimate of cost of Program
50. Designate size, location of 13 MEP, teledata rooms
54. KPFF design stairs for 13/1438. *SRG
Reprogram 13/14 interface, exiting,
stairs
43. *Changes in Steel Forwarded to Steel
Detailers
46. *RA Furnture Concept Complete
*Design Budget & Schedule for Changes
Approved
*Notice to proceed with detailed design
systems
17. *Risick reprogram solvent
distribution and waste
Issue 80% MEP CDs
(20) Incorporate 80% MEP review
comments
(19) Genentech review 80% drawings
53. Incorporate comments, complete
Architectural detail
2. Initial redesign MEP branch lateral distribution
G accept 13/14
Interface
*City Accept exiting
*Package C skin
modifications
55. KPFF design stairs for 15/14
40. *SRG Reprogram 15/14 interface, exiting,
stairs
B13 MEP HVAC, conduit, piping mains
completed
MEP 80% Review comments incorporated
Package D and UG addendum issued:
underground utilities, vivarium catwalk
10. Draft Alternate means
15. Jeff reprogram HMIS
16. *HDCCO Determine Schedule Impact
City Approval of Alternate Means
for Program
8. Review Alternate Means w/impact on LEL
and LFFH
(21-4) Finalize MEP Details, update specs and p&ID's
(8) *Revise MEP loads, MEP
Equipment schedules finalized
(13,15,16) MEP specs, P&ID's, control sequences
(6) Coord B13 MEP floor section
4. complete all Interior Architcture
51. Designate size, location of 14 MEP, teledata rooms G accept
15/14 Interface
*Accept project scope:budget by Genentech
*City Approval of H Concept
*Turnover lab and vivarium DD plan
to AEI
overworked and frustrated 37. *Reprogram B#15 Shafts
45. *Complete all Basement/LAR Drawings
12. *Complete UG utiliites
19. *Determine vertical utilities
(3) *AEI design MEP HVAC, Conduit & piping mains B13
23 - 24 June Chalmers Virtual Design Class (c) 2009 58
SimVision mechanics
• Tree view• Tree view• Object view• Project modelProject model• Simulate!• Control buttons
23 - 24 June Chalmers Virtual Design Class (c) 2009 59
SimVision object hierarchy
1 File1.File2.Case (version)3 Program3.Program
Projects1.Tasks2 Positions2.Positions3.Meetings4.Milestones5 Connections5.Connections
4.Milestones5.Organizations
23 - 24 June Chalmers Virtual Design Class (c) 2009
60
g
Big idea: “Design organizations”
If we design organizations as we design bridges, we can predict measure and manage “hidden” work which makespredict, measure and manage hidden work, which makes projects late if not managed well
Product Organization Process
Function Scope (…)Quality (…)
Design + Construct
Design + ConstructCosty ( )
Cost (…)Backlog (…)
Schedule (…)Schedule risk (…)
Form Deliverables Actors TasksBehavior Scope
QualityWork (direct, hidden) volumes CostBacklog
Work (direct, hidden) volumesCostStart, Finish, DurationS h d l i k
23 - 24 June Chalmers Virtual Design Class (c) 2009
61
Backlog Schedule risk
The Big Idea
• Integrated Concurrent Engineering is aIntegrated Concurrent Engineering is a technology-assisted social process that allows very rapid creation of multi-allows very rapid creation of multidisciplinary performance models of project products, organizations and p oject p oducts, o ga at o s a dprocesses
23 - 24 June Chalmers Virtual Design Class (c) 2009
62
Integrated Concurrent Engineering BackgroundBackground
Given Performance change• Goal = “extreme collaboration”
(1 week)Excellent POP software
Latency (secs)
• Excellent POP software• Collocated team• iRoom X
C
od onal
Latency(secs)
0200004000060000
iRoom • Good generic POP model• SD (DD) phase
Goo
tradi
tio
Duration( ) p
Good traditional100150200250300
23 - 24 June Chalmers Virtual Design Class (c) 2009 63Duration (days)
XC
Good traditional
050
100
The big idea of ICE
• ICE obviously works (e.g., NASA)(T t ti l ) fi d C t ll bl f t• (Tentatively) we find Controllable factors
• Excellent modeling and simulation• Shared project model• Closed K-net• …
⇒ Observed process performance:⇒ Observed process performance:• Very Short latency (~<= 2 minutes)
⇒ Predicted and observed outcomes:Coordination among actors (aggregate + b position)• Coordination among actors (aggregate + by position)
• Rework (aggregate + by position) • Short schedule
23 - 24 June Chalmers Virtual Design Class (c) 2009
64
ICE enabling factorsAll required at a high level of performanceAll required at a high level of performance
• Design staff focus: 100% available• Modeling & Visualization Tools: Specific & Strategic• Modeling & Visualization Tools: Specific & Strategic• Information Network of designers: Closed• Communication Media Richness and Fidelity: Richy• Structure Independence: High• Organizational Hierarchy: Flat
G l C Hi h• Goal Congruence: High• Process equivocality: Low• Integrated Conceptual Models: Semantically richteg ated Co ceptua ode s Se a t ca y c• Social Network Topology: Pooled• Computer Applications Network Topology: Scaled
23 - 24 June Chalmers Virtual Design Class (c) 2009
65
• Design subtask duration: Less than 10 minutes
ICE exercise
• Things to note:Things to note:• Discipline specialty: how does it work
for novices?for novices?• POP deliverable: how helpful is it?
?• Next steps: clear? More or less clear with same effort and traditional
h d ?methods?
23 - 24 June Chalmers Virtual Design Class (c) 2009
66
The big idea of ICE
The Big Ideas:The Big Ideas:• Team-X obviously works (e.g., NASA)• It works because it achieves exceptionally short
information latency and short task durations, reliably.
• Multiple factors enable ICE to work• Multiple factors enable ICE to work.
Chalmers Virtual Design Class (c) 2009
6723 - 24 June
Integrated Concurrent Engineering at JPL
• Integrated Collaborative Engineering (ICE)– Collocated Organization
Photo thanks to JPL
– Excellent Technical Infrastructure– Formal Goal Metrics– Informal Process and CultureInformal Process and Culture– Closed Knowledge Network
23 - 24 June Chalmers Virtual Design Class (c) 2009 68
Integrated Concurrent Engineering at StanfordStanford
• Integrated Collaborative Engineering (ICE)g g g ( )– Collocated Organization– Advanced Technical Infrastructure– Formal Goal Metrics– Informal Process and Culture
Cl d K l d N t k– Closed Knowledge Network
6923 - 24 June Chalmers Virtual Design Class (c) 2009
Observations
Team-X characteristics• Organization: Multiple stations (~18)• Process: careful design
T h l• Technology: – Multiple shared display screens– Shared database (Icemaker)
23 - 24 June Chalmers Virtual Design Class (c) 2009 70
Agenda
Fundamental mechanismsFundamental mechanisms– Short Latency, task durations– Enabling factorsEnabling factors
23 - 24 June Chalmers Virtual Design Class (c) 2009 71
Coordination Latency
• Response latency = Time from a designer posing a question to receipt of a useful answer
• Decision latency = Time from receiving useful information to making a decision with itinformation to making a decision with it
• Good engineering practice for both: 2 daysGood e g ee g p ac ce o bo days– weeks typical
• Measurable ICE Goal for latency: minutes, reliably– For and as assessed by all intended stakeholders
23 - 24 June Chalmers Virtual Design Class (c) 2009 72
Simple analysis of Latency
Traditional ICE (Team-X)• Project requires
100 “queries” per engineer @ Latency = 2 days (good!)
• Project requires 100 “queries” per engineer @ Latency = 1 minute 100 d li l i id b
@ y y (g )100 modeling, analysis, meeting “tasks” @ task durations < 2 days
100 modeling, analysis, sidebar “tasks” @ task durations ~8 minutes
Project duration ~ 2 calendar Project duration ~ 200 calendar days (typical)Latency paces schedule
jdays (Team-X)Direct work (modeling + analysis + documentation)
h d l (T X)(typical)Not direct work
paces schedule (Team-X), Not coordination latency
23 - 24 June Chalmers Virtual Design Class (c) 2009 73
ICE requires latency management
• Latency extends schedulesI t d d t t k h i t i f ti t– Interdependent tasks have incessant information requests
– Requests have response delays (latency)– Latency adds no value, measures collaborative waste
• Integrated Concurrent Engineering dramatically cuts time and• Integrated Concurrent Engineering dramatically cuts time and latency– Reduces latency from days to minutes– Direct work tasks must run in minutes– Enables radically decreased project duration– Researchers, practitioners report improved cost, quality– Requires high reliability (> 99%) latency: one major latency source
jeopardizes project success – New organizational form
23 - 24 June Chalmers Virtual Design Class (c) 2009 74
How ICE (Team-X) works
• ManageManage – Time to do direct work
• Model, analyze, decide, explain• Requires highly skilled engineers with excellent tools that
they know well
– Coordination LatencyCoordination Latency• Time for a designer to obtain usable information• Requires many enabling factors
M bl bj i f f l ICE• Measurable objectives for successful ICE: 1. Time to model, analyze < 10 minutes (> 99% reliability) 2. Latency < = 1 minute (> 99% reliability)2. Latency < 1 minute (> 99% reliability)
23 - 24 June Chalmers Virtual Design Class (c) 2009 75
ICE Enabling Factors(Committed)Organization
(Dynamic) Process
(Visual)Technologyg gy
Closed knowledge network
Low process equivocality
Excellent discipline-Specific Modeling, Visualization ToolsVisualization Tools
Focused design staff High structure independence
Rich communications media
Flat organization structure
Pooledcommunications
Integrated database
Egalitarian cultureg
High goal congruence
23 - 24 June Chalmers Virtual Design Class (c) 2009 76
Organization Enabling factor: Closed Knowledge networkOrganization Process Technology
Closed knowledge network
Low process equivocality
Excellent discipline-Specific Modeling
g
• Objective: Closed
network equivocality Specific Modeling, Visualization Tools
Focused design staff High structure independence
Rich communications media
Flat organization structure
Pooledcommunications
Integrated database
Egalitarian culture
High goal congruence
• Objective: Closed• Meaning: Requisite knowledge, procedures,
options, and authority are immediatelyoptions, and authority are immediately available in the room (almost always)
• Risk factors: call outs; unanswered callouts• Team-X Methods:
– Heavy reliance on collaborative design sessionsD i ll ti d i i– Designer collocation during sessions
– Careful participants selection and training – Pre-plan to identify needed participantsPre plan to identify needed participants
23 - 24 June Chalmers Virtual Design Class (c) 2009 77
Organization Enabling factor: Design staff focusOrganization Process Technology
Closed knowledge network
Low process equivocality
Excellent discipline-Specific Modeling
g
• Objective: 100% available during meetings
network equivocality Specific Modeling, Visualization Tools
Focused design staff High structure independence
Rich communications media
Flat organization structure
Pooledcommunications
Integrated database
Egalitarian culture
High goal congruence
• Objective: 100% available during meetings• Meaning: Design session participants focus
exclusively on project work during designexclusively on project work during design sessions
• Risk factors: Designers have other responsibilities during design sessions, so team waits for expertise
• Team X Methods:• Team-X Methods:– Management support of focus – Short sessions make enable managers to free g
valued staff23 - 24 June Chalmers Virtual Design Class (c) 2009 78
Organization Enabling factor: Hierarchy structureOrganization Process Technology
Closed knowledge network
Low process equivocality
Excellent discipline-Specific Modeling
y
Objecti e Flat
network equivocality Specific Modeling, Visualization Tools
Focused design staff High structure independence
Rich communications media
Flat organization structure
Pooledcommunications
Integrated database
Egalitarian culture
High goal congruence
• Objective: Flat• Meaning: Minimal required decision-making
structure and overheadstructure and overhead• Risk factors: Soliciting management approval
challenges short latencychallenges short latency• Team-X Methods:
– No managers– No managers– Culture of autonomy and respect– One facilitator
23 - 24 June Chalmers Virtual Design Class (c) 2009 79
Organization Enabling factor: Egalitarian cultureOrganization Process Technology
Closed knowledge network
Low process equivocality
Excellent discipline-Specific Modeling
g
• Objective: Egalitarian
network equivocality Specific Modeling, Visualization Tools
Focused design staff High structure independence
Rich communications media
Flat organization structure
Pooledcommunications
Integrated database
Egalitarian culture
High goal congruence
• Objective: Egalitarian• Meaning: Positions assume empowered
decision-making and low managementdecision making and low management overhead
• Risk factors: Soliciting management approval challenges short latency
• Team-X Methods:C lt f t d t– Culture of autonomy and respect
– Careful recruitment – Decisions and decision processes highly visible toDecisions and decision processes highly visible to
all23 - 24 June Chalmers Virtual Design Class (c) 2009 80
Organization Enabling factor: Goal CongruenceOrganization Process Technology
Closed knowledge network
Low process equivocality
Excellent discipline-Specific Modeling
g
• Objective: Highly congruent
network equivocality Specific Modeling, Visualization Tools
Focused design staff High structure independence
Rich communications media
Flat organization structure
Pooledcommunications
Integrated database
Egalitarian culture
High goal congruence
• Objective: Highly congruent• Meaning: participants know and aspire to
same goals and methodssame goals and methods• Risk factors: positions debate priorities or
methods• Team-X Methods:
– Discuss goals and methods at session start F ilit t tt ti– Facilitator attention
– Culture of congruence – Analysis and decisions very visible to allAnalysis and decisions very visible to all
23 - 24 June Chalmers Virtual Design Class (c) 2009 81
Process Enabling factor: Process equivocalityOrganization Process Technology
Closed knowledge network
Low process equivocality
Excellent discipline-Specific Modeling
q y
• Objective: Low
network equivocality Specific Modeling, Visualization Tools
Focused design staff High structure independence
Rich communications media
Flat organization structure
Pooledcommunications
Integrated database
Egalitarian culture
High goal congruence
• Objective: Low• Meaning: all participants understand and accept procedures and
goals Implies that method applies only to well understood processes– Implies that method applies only to well-understood processes
• Risk factors: positions ask for and wait for facilitator decisions• Team-X Methods:• Use only for well-understood processes
– Pre-plan for process clarity– Culture of autonomy – Analysis and decisions very visible to all– Excellent process facilitator
23 - 24 June Chalmers Virtual Design Class (c) 2009 82
Process Enabling factor: Structure independenceOrganization Process Technology
Closed knowledge network
Low process equivocality
Excellent discipline-Specific Modeling
p
• Objective: High
network equivocality Specific Modeling, Visualization Tools
Focused design staff High structure independence
Rich communications media
Flat organization structure
Pooledcommunications
Integrated database
Egalitarian culture
High goal congruence
• Objective: High• Meaning: Design tasks are distinct, positions all
understand their responsibilities and can proceed ith i i l t i htwith minimal management oversight
• Risk factors: positions solicit or wait for facilitator decisions
• Team-X Methods:– Use only for projects that allow independence– Pre-plan for independencePre plan for independence – Staff selection and training– Culture of autonomy – Analysis and decisions very visible to all– Analysis and decisions very visible to all
23 - 24 June Chalmers Virtual Design Class (c) 2009 83
Process Enabling factor: Coordination TopologyOrganization Process Technology
Closed knowledge network
Low process equivocality
Excellent discipline-Specific Modeling
p gy
Objecti e Pooled
network equivocality Specific Modeling, Visualization Tools
Focused design staff High structure independence
Rich communications media
Flat organization structure
Pooledcommunications
Integrated database
Egalitarian culture
High goal congruence
• Objective: Pooled• Meaning: Participants resolve problems in
small self formed groupssmall self-formed groups • Risk factors: Formal or inflexible coordination
requirementsrequirements• Team-X Methods:
– Collocation– Collocation – Shared projection screens – Sidebar culture
23 - 24 June Chalmers Virtual Design Class (c) 2009 84
Technology Enabling factor: Modeling, Visualization ToolsOrganization Process Technology
Closed knowledge network
Low process equivocality
Excellent discipline-Specific Modeling
g,
• Objective: Excellent
network equivocality Specific Modeling, Visualization Tools
Focused design staff High structure independence
Rich communications media
Flat organization structure
Pooledcommunications
Integrated database
Egalitarian culture
High goal congruence
• Objective: Excellent• Meaning: Discipline-specific tools allow all
positions to do direct work very fastpositions to do direct work very fast• Risk factors: Manual design activities or poor
tools bottleneck schedule; Other designers fail to understand a model
• Team-X Methods:M d li i li ti l i d d i i– Modeling, visualization, analysis and decision support tools enable all critical path tasks
– High team experience
23 - 24 June Chalmers Virtual Design Class (c) 2009 85
Technology Enabling factor: Communications MediaOrganization Process Technology
Closed knowledge network
Low process equivocality
Excellent discipline-Specific Modeling
• Objective: Rich
network equivocality Specific Modeling, Visualization Tools
Focused design staff High structure independence
Rich communications media
Flat organization structure
Pooledcommunications
Integrated database
Egalitarian culture
High goal congruence
• Objective: Rich• Meaning: Shared and personal, visual, multi-
disciplinary, showing functional requirements, design p y, g q , gchoices and predicted behaviors
• Risk factors: Slow process to describe models, explain rationale evaluate choices make predictionsexplain rationale, evaluate choices, make predictions, create alternatives
• Team-X Methods:– Mature modeling and analysis tools– Personal workstations
Shared “iRoom” displays– Shared iRoom displays
23 - 24 June Chalmers Virtual Design Class (c) 2009 86
Technology Enabling factor: DatabaseOrganization Process Technology
Closed knowledge network
Low process equivocality
Excellent discipline-Specific Modeling
• Objective: Integrated
network equivocality Specific Modeling, Visualization Tools
Focused design staff High structure independence
Rich communications media
Flat organization structure
Pooledcommunications
Integrated database
Egalitarian culture
High goal congruence
• Objective: Integrated• Meaning: Discipline-specific models all access
and store shared data easilyand store shared data easily• Risk factors: data reentry, missing shared data• Team-X Methods:
– Develop good shared generic (POP) model ontology – Applications have developed uniform semantics for
shared datashared data– Data visualization in Excel– Designated position assures consistencyg p y
23 - 24 June Chalmers Virtual Design Class (c) 2009 87
ICE Enabling factors: so what?Organization Process Technology
Cl d k l d L E ll t di i li
• Necessity: excellent ICE performance requires all
Closed knowledge network
Low process equivocality
Excellent discipline-Specific Modeling, Visualization Tools
Focused design staff High structure independence
Rich communications media
Flat organization structure
Pooledcommunications
Integrated database
Egalitarian culture
High goal congruence
Necessity: excellent ICE performance requires allfactors to work well
• Sufficiency: No one factor sufficesE l id (CEE 111/211) f it• Early evidence (CEE 111/211) of necessity, sufficiency of these factors (from observations or theoretically-founded simulation)
• Process and team experience are crucial, so understanding factors may help understand how to change Team-X tog– Make specific improvements– Replicate Team-X (in less than 10 years it to create it)
23 - 24 June Chalmers Virtual Design Class (c) 2009 88
Big idea: so what?Organization Process Technology
Cl d k l d L E ll t di i liClosed knowledge network
Low process equivocality
Excellent discipline-Specific Modeling, Visualization Tools
Focused design staff High structure independence
Rich communications media
Flat organization structure
Pooledcommunications
Integrated database
Egalitarian culture
High goal congruence
• Understanding ICE may help Team-X to– Make specific improvementsMake specific improvements– Replicate Team-X (in less than the 10
years it to create it)y )• Understanding ICE may help CEE to
– Implement ICE appropriate– Implement ICE appropriate– Replicate Team-X (in less than the 10
years it to create it)years it to create it)
23 - 24 June Chalmers Virtual Design Class (c) 2009 89
Why is it hard to determine fundamental enablers of ICE?Organization Process Technology
Cl d k l d L E ll t di i li
• Very hard to understand culture from
Closed knowledge network
Low process equivocality
Excellent discipline-Specific Modeling, Visualization Tools
Focused design staff High structure independence
Rich communications media
Flat organization structure
Pooledcommunications
Integrated database
Egalitarian culture
High goal congruence
Very hard to understand culture from within
• Many factors appear to characterize• Many factors appear to characterize ICE, so no single view or theory appliesTeam X is like a company not a lab:• Team-X is like a company, not a lab: – It needs to do work project-by-project
I i i k f– Instrumenting poses risk to performance
23 - 24 June23 - 24 June Chalmers Virtual Design Class (c) 2009 90
ICE charrette (class on 23 June)
• Task: Design your project • Deliverables
Session Roles• Owner: Presents1. Owner specification: functions
2. Product design 3D sketch(s), PBS + assembly instructions
3 Organization model and org
• Owner: Presents project model
• Product designer + 3. Organization model and org
chart; OBS4. Process model, WBS, Gantt
chart for development
gassembly instructions
• Organization & Process modeler5. POP model and P, O, P detail
6. Presentation of your model• Budget
Process modeler • POP modeler• Cost estimation
– 90 minutes for ICE charrette– 30 minutes for presentations
• Groups of ~7T d 2 l i
Cost estimation• Facilitator
23 - 24 June Chalmers Virtual Design Class (c) 2009 91
• Try to do 2 alternatives