LMC Ltd Pekini Str 28, 0160 Tbilisi T: +995322243505 F: +995322243501 Mail: [email protected] Web: www.lmc.ge Facebook: facebook.com/lmc.llc Twitter: twitter.com/lmc_ge Tax ID: 40487513 Third Party Inspection 9-10th inspections on site Report #7 CONSTRUCTION OF THE GEFPOR NEW CENTER IN TBILISI PROJECT #: 2013002SOR DOCUMENT #: 36-7191173511-2013002SOR-032 REVISION #: 1.0 DOCUMENT STATUS: RELEASED 28/08/2014

Third Party Inspection Report #7 › wp-content › uploads › 2019 › 01 › Third-Party-Inspe… · Construction Of The GEFPOR New Center in Tbilisi 9-10thInspections on Site,

  • Upload
    others

  • View
    3

  • Download
    0

Embed Size (px)

Citation preview

  • LMC Ltd Pekini Str 28, 0160 Tbilisi T: +995322243505 F: +995322243501 Mail: [email protected] Web: www.lmc.ge Facebook: facebook.com/lmc.llc Twitter: twitter.com/lmc_ge Tax ID: 40487513

    Third Party Inspection 9-10th inspections on site Report #7

    CONSTRUCTION OF THE GEFPOR NEW CENTER IN TBILISI PROJECT #: 2013002SOR DOCUMENT #: 36-7191173511-2013002SOR-032 REVISION #: 1.0 DOCUMENT STATUS: RELEASED 28/08/2014

    mailto:[email protected]://www.lmc.ge/http://www.facebook.com/lmc.llchttp://twitter.com/lmc_ge

  • Construction Of The GEFPOR New Center in Tbilisi

    9-10thInspections on Site, Report #7

    TOC DocID: 36-7191173511-2013002SOR-032 Date: 28/08/2014 Rev: 1.0 page 1 of 21

    Approvals

    The signatures below certify that this procedure has been reviewed and accepted, and demonstrates that the signatories are aware of all the requirements contained herein and are committed to ensuring their provision.

    Prepared by: Reviewed by: Approved by:

    Joni Samkharadze Giorgi Merebashvili Giorgi Merebashvili Expert Director Director

    Revision History

    This procedure is reviewed to ensure its continuing relevance to the systems and process that it describes. A record of contextual additions or omissions is given below:

    Purpose/Status Comments Revision Date Draft Document has been created. 0.01 26/08/2014

    Released Document has been reviewed and released 1.0 28/08/2014

  • Construction Of The GEFPOR New Center in Tbilisi

    9-10thInspections on Site, Report #7

    TOC DocID: 36-7191173511-2013002SOR-032 Date: 28/08/2014 Rev: 1.0 page 2 of 21

    TABLE OF CONTENTS

    1 INTRODUCTION & PURPOSE 3

    2 REFERENCES 3

    3 TERMS & DEFINITIONS 3

    4 DOCUMENTS 3

    5 PICTURES OF THE ACTUAL SITUATION: 4

    6 FINDINGS 6

    6.1 Status of Construction Works 6

    6.1 List of defects (D) 17

    6.2 Recommendations (R) 17

    6.3 Review of the removal of detected findings and recommendations 18

    7 SUMMARY 21

    8 OTHERS 21

  • Construction Of The GEFPOR New Center in Tbilisi

    9-10thInspections on Site, Report #7

    TOC DocID: 36-7191173511-2013002SOR-032 Date: 28/08/2014 Rev: 1.0 page 3 of 21

    1 INTRODUCTION & PURPOSE GEFPOR is the client for the Construction of the GEFPOR New Center in Tbilisi. GEFPOR assigned LMC Ltd with the building accompanying Third Party Inspection of the interior and engineering systems works with the contract dated July 14th, 2014. Third party inspection implies only the visual Inspection; it does not include the construction supervising, statistical calculations, testing of the construction materials. On the basis of this contract, the 9-10th inspections took place on August 25th and 26nd, 2014.

    2 REFERENCES Reference Title & Description N/A N/A

    3 TERMS & DEFINITIONS Term Definition HVAC Heating, Ventilation and Air Conditioning

    MEP Mechanical, Electrical and Plumbing

    4 DOCUMENTS The following documents had been delivered to LMC Ltd:

    No: Title Contents / date Originator

    U 1 Architectural Design PDF Document, 2013 Year

    GRiFF

    U 2 Interior Design PDF Document 07/03/2014

    Nino Kalandadze Irina Dikhaminjia

    U 3 Engineering Systems Design

    PDF Document 22/03/2014

    Onik Aloiani Giorgi Marshanishvili

    U 4

    U 5

    U 6

    U 7

  • Construction Of The GEFPOR New Center in Tbilisi

    9-10thInspections on Site, Report #7

    TOC DocID: 36-7191173511-2013002SOR-032 Date: 28/08/2014 Rev: 1.0 page 4 of 21

    5 PICTURES OF THE ACTUAL SITUATION:

  • Construction Of The GEFPOR New Center in Tbilisi

    9-10thInspections on Site, Report #7

    TOC DocID: 36-7191173511-2013002SOR-032 Date: 28/08/2014 Rev: 1.0 page 5 of 21

    Data – site inspection

    − Date of inspection 25-26/08/2014 − Weather Sunny/Sunny − Temperature + 31/36°C − Participants Merab Mebuke, LMC Ltd

    Joni Samkharadze, LMC Ltd

  • Construction Of The GEFPOR New Center in Tbilisi

    9-10thInspections on Site, Report #7

    TOC DocID: 36-7191173511-2013002SOR-032 Date: 28/08/2014 Rev: 1.0 page 6 of 21

    6 FINDINGS During the 9-10th inspections it was found that MEP and Interior works are in progress.

    6.1 Status of Construction Works No Findings / construction status Picture

    Interior Works

    7.1 Drywall Partition System, 1st and

    2nd Floors:

    Gypsum boards are being installed on the partition system’s frame.

    Gypsum Boards:

    Manufacturer: Knauf Georgia Board Thickness: 1.25 cm Board Type : Regular and

    Moisture Resistant (in Bathrooms and other wet and damp areas)

    Gypsum Board’s Fixing:

    1st layer is fastened mostly in every 40-50cm with 25mm Knauf screw

    2nd layer mostly in every 20-30cm with 35mm Knauf screws

    Fixing material: Knauf Self Drilling Screws

    UW runner’s Fixing (Perimeter Runner):

    Fixing material: Knauf Plastic and Plug Screws

  • Construction Of The GEFPOR New Center in Tbilisi

    9-10thInspections on Site, Report #7

    TOC DocID: 36-7191173511-2013002SOR-032 Date: 28/08/2014 Rev: 1.0 page 7 of 21

  • Construction Of The GEFPOR New Center in Tbilisi

    9-10thInspections on Site, Report #7

    TOC DocID: 36-7191173511-2013002SOR-032 Date: 28/08/2014 Rev: 1.0 page 8 of 21

    Gypsum Board’s Typess

  • Construction Of The GEFPOR New Center in Tbilisi

    9-10thInspections on Site, Report #7

    TOC DocID: 36-7191173511-2013002SOR-032 Date: 28/08/2014 Rev: 1.0 page 9 of 21

  • Construction Of The GEFPOR New Center in Tbilisi

    9-10thInspections on Site, Report #7

    TOC DocID: 36-7191173511-2013002SOR-032 Date: 28/08/2014 Rev: 1.0 page 10 of 21

    Board Fixing’s Spacing

    Board Fixing

    Knauf Self Drilling Screws

  • Construction Of The GEFPOR New Center in Tbilisi

    9-10thInspections on Site, Report #7

    TOC DocID: 36-7191173511-2013002SOR-032 Date: 28/08/2014 Rev: 1.0 page 11 of 21

    UW Runners Fixing

    Plastic and Plug Screws

  • Construction Of The GEFPOR New Center in Tbilisi

    9-10thInspections on Site, Report #7

    TOC DocID: 36-7191173511-2013002SOR-032 Date: 28/08/2014 Rev: 1.0 page 12 of 21

    7.2 Concrete Floor, Basement Floor:

    Concrete Floor System with Thickness 9-10cm is installed on the basement reinforced concrete slab.

  • Construction Of The GEFPOR New Center in Tbilisi

    9-10thInspections on Site, Report #7

    TOC DocID: 36-7191173511-2013002SOR-032 Date: 28/08/2014 Rev: 1.0 page 13 of 21

  • Construction Of The GEFPOR New Center in Tbilisi

    9-10thInspections on Site, Report #7

    TOC DocID: 36-7191173511-2013002SOR-032 Date: 28/08/2014 Rev: 1.0 page 14 of 21

    MEP Engineering Works

    7.3 Drainage Pipe Installation, Heating and Air Conditioning Systems, 1st Floor:

    Drainage pipe installations are in progress.

  • Construction Of The GEFPOR New Center in Tbilisi

    9-10thInspections on Site, Report #7

    TOC DocID: 36-7191173511-2013002SOR-032 Date: 28/08/2014 Rev: 1.0 page 15 of 21

    7.4 Cable Installation, Electrical works, 1st and 2nd Floors:

    Cable Installation works are in progress.

  • Construction Of The GEFPOR New Center in Tbilisi

    9-10thInspections on Site, Report #7

    TOC DocID: 36-7191173511-2013002SOR-032 Date: 28/08/2014 Rev: 1.0 page 16 of 21

    7.5 Water Supply and Sewage Systems, 1st Floor:

    Hot and Cold Water Supply and Sewerage systems installations are in progress

  • Construction Of The GEFPOR New Center in Tbilisi

    9-10thInspections on Site, Report #7

    TOC DocID: 36-7191173511-2013002SOR-032 Date: 28/08/2014 Rev: 1.0 page 17 of 21

    6.1 List of defects (D) During the 9-10th inspections on site, the following deviations/defects (D) were found.

    No Building unit / location / findings Picture

    D 7.1 Splicing of CW Studs:

    According to actual situations CW studs joint are connected with additional UW profiles with 50-60 cm overlap.

    According to Knauf’s Standard Overlap is recommended to be ≥75cm

    6.2 Recommendations (R) In the following, recommendations (R) are specified.

    No. Building unit / location / findings Picture

    R 7.1 No Recommendations Without Picture

  • Construction Of The GEFPOR New Center in Tbilisi

    9-10thInspections on Site, Report #7

    TOC DocID: 36-7191173511-2013002SOR-032 Date: 28/08/2014 Rev: 1.0 page 18 of 21

    6.3 Review of the removal of detected findings and recommendations No. Building unit / location / finding = done, = open,

    date, comment R 1.1 Air Conditioners Protection:

    All Conditioners have to be protected from dust. Only 1 conditioner is protected on 2nd floor, others are uncovered.

    R 1.2 Air Conditioners Certificate/ Information: Air conditioners certificates, technical data sheets and installation manuals have to be presented to LMC Ltd

    R 1.3 Site Cleanness: Engineering Work Contractor has to guarantee site cleanness

    R 2.1 Door Opening Expansion, Lift Shaft: Cut in Lift Shaft has to be agreed with project constructor. Document has to be presented.

    R 2.2 Construction Safety: Temporary balustrade has to be installed on staircase in order to guarantee construction safety.

    D 3.1 Pipe Insulation, Heating and Air Conditioning Systems:

    According to the MEP Design, Pipe Thermal Insulation Thickness has to be 10 mm According to actual Situation, Pipe Insulation Thickness is 9 mm and 6mm Change in Insulation thickness has to be agreed and approved by MEP Designer and Building Owner.

    According to the official Letter,

    dated and signed on 27/08/2014 by Onik Aloian, The Change has been

    approved by MEP Designer

    D 3.2 Ventilation Ducts Insulation:

    According to the MEP Design, Air Supply System’s Ducts thermal Insulation Thickness has to be 20mm According to actual Situation, Ducts Insulation Thickness is 19 mm Change in Insulation thickness has to be agreed and approved by MEP Designer and Building Owner.

    According to the official Letter,

    dated and signed on 27/08/2014 by Onik Aloian, The Change has been

    approved by MEP Designer

    R 3.1 Air Conditioners Fixing, Heating and Air Conditioning Systems: Air Conditioner Indoor Units has to be fastened with double nuts.

  • Construction Of The GEFPOR New Center in Tbilisi

    9-10thInspections on Site, Report #7

    TOC DocID: 36-7191173511-2013002SOR-032 Date: 28/08/2014 Rev: 1.0 page 19 of 21

    R 3.2 Ventilation Ducts Fixing, Ventilation Systems: Ducts have to be fastened on every joint of ventilation ducts. On Air Exhaust Ducts fastening Points, thermal insulation tape has to be used.

    Only on basement and 1st floors, on Air Exhaust Ducts fastening Points, thermal insulation tape is used.

    R 3.3 Ventilation Ducts Screws, Ventilation Systems:

    Screws, inside the ventilation ducts, have to be cut.

    Not surveyable, performer shall present evidence that they took

    into consideration mentioned recommendation

    R 3.4 Heating and Air Conditioning System’s Test:

    Heating and Air Conditioning Systems have to be tested before suspended ceilings installation.

    R 3.5 Ventilation System’s Test: Ventilation System has to be tested before suspended ceilings installation.

    R 3.6 Certificates for Heating, Ventilation and Air Conditioning Systems (HVAC) Materials: For all materials of HVAC Systems, the manufacturer's certificates and a copy of the manufacturer's representative in Georgia have to be presented.

    R 3.7 Documents for HVAC Systems Equipments ( Air Conditioning Indoor and outdoor Units, Air Handling Unit and etc) Following documents have to be presented for HVAC Systems equipments: Equipments technical passport and information

    about manufacturer Installation and maintenance

    manuals/instructions Warranty service document copy of the manufacturers certificates which proves that HVAC Contractor is allowed to sell, install and make service of equipments

    R 3.8 Site Cleanness and Equipment Protection: It is very important to guarantee site cleanness and protect equipments from dust and dirt

    D 4.1 Toilet Entrance:

    Excavated Earth blocked up the toilet entrance and workers can’t use it anymore.

  • Construction Of The GEFPOR New Center in Tbilisi

    9-10thInspections on Site, Report #7

    TOC DocID: 36-7191173511-2013002SOR-032 Date: 28/08/2014 Rev: 1.0 page 20 of 21

    R 4.1 Façade Potential Damage, Excavation works: Because of Excavation works Facade walls are covered up with earth and may cause damage. It is recommended to move off soil from the wall and recover all damages if required.

    R 4.2 Waterproofing Protection: The reinforcement’s wooden board is set on façade wall without protection and it can damage the waterproof membrane. The protection should be applied.

    D 5.1 Façade and Rainwater Pipe Damages:

    Because of excavation works facades and rainwater pipe are damaged on some places.

    D 5.2 Floor and Ceiling Type Air Conditioners Installation, Basement Floor:

    On the basement floor, floor and ceiling type air conditioner’s indoor units are installed on different heights.

    R 5.1 Ponding Water, Lift Shaft, Basement floor:

    On the basement floor, in lift shaft water is gathered.

    Water has to be removed and reason has to be found.

    Water is removed

    D 6.1 UW Runners, Partition Walls:

    UW runners with thickness 0.5mm are used for parturition walls.

    According to Knauf Partition Wall Standard, UW runner thickness has to be Instead of 0.6mm.

  • Construction Of The GEFPOR New Center in Tbilisi

    9-10thInspections on Site, Report #7

    TOC DocID: 36-7191173511-2013002SOR-032 Date: 28/08/2014 Rev: 1.0 page 21 of 21

    7 SUMMARY During the 9-10th inspections it was found that Interior and MEP works were in progress. Deviation has been found, see D 7.1;

    Defects, which will not be visible during the next inspection, have to be repaired professionally and documented by the person in charge or site management. After receiving the documentation LMC Ltd will delete the finding from the control list.

    8 OTHERS As regards of the third party inspection the experts of LMC Ltd do not have power on the companies on site. The responsibilities of the persons and companies in charge are not changed by third party inspection of LMC Ltd. The responsibility for the removal of deficiencies is still with the persons in charge.