Copyright©ArizonaWholesalePoolContractors,2010|
TheSwimmingPoolConstructionChecklistisdesignedtogiveyousomeguidelinesandhintsofitemstolookforwhileyou’rebuildingyourownpool.It’soutlinefollowsthescheduledorderofthephasesofpoolconstruction.It’sonlyaguide–useitassuch.Ifyouhavequestionsorifyouwouldliketoaddsomethingtothischecklistthatyouthinkwouldhelpothersinbuildingtheirownpool–pleaseletusknow.
TableofContents
1. Layout–ConstructionPre‐check2. Excavation3. Plumbing4. Steel/Rebar5. Electrical6. Shotcrete7. Masonry/WaterFeatures8. Decking9. Access,Barriers&Tile10. ConstructionCleanup11. InteriorFinish12. PoolStart‐up
www.ArizonaWholesalePoolContractors.com
RecordBondBeamElevation‐heightsetat:_______
Verifyyourpropertylinesetback,windowandstructuredistancearemaintained Paintoutpoolequipmentlocation–mustbe5’minimumfromwater’sedge. Verifyandestablishpoolbondbeamelevation–confirmdecktypewithlayout. Confirmelectrical,gasandwaterrequirementswithlayoutsub.
Electrical–panellocation,adequatepowerforequipment/futurerequirements Gas–meterlocation–propanetanklocation‐accesstodig21”deeptrench– Propanetanklocationmustbeaccessibletostreetview. Water–selectahosebibforusewiththeautomatedwaterleveler. Allhosebibsrequireavacuumbreakerbeaddedtothehosebib. Finally,doanoverallreviewofthepooldesign. Willthedeckworkwiththeremainingspaceasplanned? Isthepoolwhereyouintendedittobe? Re‐layoutscostmoney,sobesureyoulikewhatyousee. Doestheyardgraderiseorfallnearthepool?Mayrequireretainingcomponent.
Layout: DateScheduled:________________DateCompleted:________________
(+/‐finishedtopatioheightorfinishedhousefloorelevation.)
SwimmingPoolConstructionChecklist:
Copyright©ArizonaWholesalePoolContractors,2010|
SwimmingPoolConstructionChecklist:
Finally,doanoverallreviewofthepooldesign. Willthedeckworkwiththeremainingspaceasplanned? Isthepoolwhereyouintendedittobe? Doestheyardgraderiseorfallnearthepool? Measurewaterfallpad(ifapplicable)–confirmsquarefootage(ie.8’x5’=40sqft.)OrderBlueStake–comparebluestakenotestopoollayoutanddesignfeatures.
Note:Thelayoutwillbe6”largeroneachsideor12”overallmeasuredfortheexcavator.thepoolmustbeoverdugandthenreplacedwithshotcretethenitwillfinishperdesign.
Didyouorderyourpoolequipmentyet?Useyourpoolequipmentspecsheet. Goto:ArizonaWholesalePoolEquipment.comGetyourequipmentdeliveredforFree(Arizonaresidentsonly) haveiton‐sitepriortotheplumbingphase.
Layout(cont.)
Copyright©ArizonaWholesalePoolContractors,2010|
SwimmingPoolConstructionChecklist:
Verifythewidthoftheaccess Makeanoteofwhatisrequiredforthereplacementoftheaccess MasonryWall#of:sections______pilasers________stucco______paintcolor______ Removeandreplaceanexistinggate___________addaselfclosinggatespring Note:Allgatesmustopenoutandawayfromthebackyardnotintotheyard. Confirmpoolbondbeamelevationandverifydecktypewithexcavator. Verifyyardgradechanges. Doesthechangeingradesrequirearetainingwall? Raisedbondbeamoradditionalfilltoremain? Padoutdeckareawithpoolfill3'beyondfinisheddeck. Asktheexcavatoriftheywilldiga“trunkline”forthepoolequipment. Asktheexcavatorwhattheirpolicyisonremovingexcessfill. Note:Harddigsarealwaysapossibility–asktheexcavator’sexperienceinyourarea.
Excavation:DateScheduled:______________DateCompleted:______________
Copyright©ArizonaWholesalePoolContractors,2010|
Confirmexcavatorcompletedpre‐siteandhasbidproperequipmentfortheaccess.
SwimmingPoolConstructionChecklist:
Plumbershouldprovideallpoolequipmentslabs–plasticorconcrete. Poolequipmentshouldbesetonafirmlevelgrade. Poolequipmentsetwithin(+/‐)6”topoolwaterlevel.Checktomakesureallplumbinglinesaresetbelowpoolbondbeam.Verifyplumbingschematic–thenumberofreturns,skimmerlocation, poolvacline,autowaterlevelerandallotherplumbinglinesareinplace.VerifythatallexposedPVCpipesgetpaintedatthepoolequipmentlocation.Didyourplumberinstallyoursaltwatercall?
Recordtheplumbingsystem(pipes,equipment)pressureatplumbingcompletion:____________psi
Plumbing:DateScheduled________________DateCompleted:_____________
Copyright©ArizonaWholesalePoolContractors,2010|
Notes: *Didyouselectyourdeckmaterialyet?Ihopeso–ifnot–getbusy. *Didyouorderyourpoolfence?Needasub?GotoAZWPC.comandrequestaquote. *Didyousubmitforagaslinepermit/inspection(ifnecessary)
SwimmingPoolConstructionChecklist:
Copyright©ArizonaWholesalePoolContractors,2010|
Verifysteelcompanyhasspecialengineeringdetail(ifapplicable)Verifysteelstandardengineeringwiththerebar/steelsub–priortoscheduling thesteelinstalldate.Checkthatallsteelisblockedoffthedirtby3”concretespacers.Visuallyreviewalltiewrapsatcrosssectionarecut,bentdownandawayfromthepoolinteriorfinish.Checksteelisbelowthetopoftheformboardssetbytheexcavators.Confirmadditionalfeaturessuchas:In‐pooltableorbarstool(s)havesteelcaissonsprovided Spas&spill‐ways,waterfeaturesareaccountedfor.
Note:Confirmwithshotcretesub‐contractorthattheywillprovideSonotubesfortableorbar stoolsatthetimeofshotcrete(ifapplicable)
Steel/Rebar:DateScheduled:_______________DateCompleted:_____________
SwimmingPoolConstructionChecklist:
Copyright©ArizonaWholesalePoolContractors,2010|
Allelectricalconduit(wrappedorgreyPVC)andlightbrassisbelowfinishedgrade perUBCandcityrequirements.Verifyalldeck,anchorandfencebondingiscomplete. *DivingPoolsneedabondwireforthemetaljiginthedeck *Wroughtironfencesormetalobjectwithin5’ofwaterneedabondwire *Equalpotentialbond(deckbond)wireinstalled–applicableinsomecitiesProperpoolpanelisinplaceforcurrentandfutureneeds.3’clearanceinfrontofpoolpanelismaintained.
Electrical:ScheduledDate:_________________CompletionDate:_______________
Yourcity:___________________________InspectionRequestLine:__________________ Onlinewebaddress:__________________________________________ YourPermitNumber:________________________ Pre‐shotcrete/rough‐electricalinspectioncode(seecitychart):________|___________ ConfirmationNumber:________________________
CallforyourPre‐shotcreteandinsomecitiesaroughelectricinspection
Note:Oncetheelectricaliscompletedittimetocallforyourfirstinspection.
SwimmingPoolConstructionChecklist:
Copyright©ArizonaWholesalePoolContractors,2010|
Verifypre‐shotcreteinspectionfromyourcity/countyis“green”andapproved.Recordplumbingisstillatorunderpressure:__________________psi.Waterisavailableon‐siteforshotcretecompanytouseduringinstallation.Cleanoutareaisspecifiedoracleantubavailable?Verifysteelblockinginplacenocave‐ins,mudorotherdebrisonorcoveringrebar.
PaverorFlagstonedeck: Havethecrew“notchedthebeam”fortheaerator. In‐pooltablesorseats–Sonotubeon‐siteorshotcretecompanyprovided(verify) Watercureschedule.Seeshotcretecompanyinstructionsheet–4times/day–4days.
Shotcrete:ScheduledDate:_________________CompletionDate:_______________
*Note:Takepicturesand/orvideooftheshotcreteprocess.Sendthemtowww.ArizonaWholesalePoolContractors.com andshowoffyourpoolwithresttherestofthebuild yourpoolbuildershereinArizona.
SwimmingPoolConstructionChecklist:
Copyright©ArizonaWholesalePoolContractors,2010|
Completeallmasonrystructuresinandaroundpoolanddeckarea. Waterfallcomplete Masonrystructuresonthebeamaresettoextendoverthebeamorflushwiththebeam. Seetileandstonefacingdetailonpoolprint. Deckrocks,masonrytransitions/columnscomplete. BBQ,seatwallsandallmasonryfeaturesareinplacetoatleast 18”abovedeckheightorcompleted. Electrical,gaslinesandallfuturesleevingiscompleted,inspected(ifnecessary)andburied. Accesswallscompleted–verifywithdeckcrewforaccessrequirementsprior.
Masonry&WaterFeaturesDateScheduled:__________DateCompleted:__________
*Note:Haveyouselectedyourtileandmadeyourinternalfinishselection?Hurry,it’scomingupsoon…
SwimmingPoolConstructionChecklist:
Copyright©ArizonaWholesalePoolContractors,2010|
Recordplumbingisstillunderpressure_______________psi. Alldrainlines,sleevingandsprinklerrepairsunderthedeckareaarecomplete. Allmasonryandrockaresetandinplace. Colorselectionhasbeenmadeandconfirmedbydecksub‐contractor. Handrailanchors,divingboardjigs,fence/metalbondingwiresareinplaceandon‐site. Allbasketball,volleyballandumbrellasleevesareon‐siteandmarkedonthepoolplan. Inpooltableformedandpouredwithdeck.Paverorstonedeckrequiresseparatesub. Allskimmerandautomatedwaterlevelerringsandlidsareon‐sitefordeckcrew. ConcretePaverandNaturalStoneDecks: Deckcrewtoprovideroundpaverlidsorplasticlids? Aeratoriscutand90over(rememberthe“notch”inthebeamatshotcrete) tothefinishbelowthecopingedgeofthedeck. Pavercrewmustsetandsecureallanchorsandjigsinconcretepriortopaverset. Seemanufacturerspecificationforsecuringanchorsandjigs.
Decking:DateScheduled:__________________DateCompleted:________________
SwimmingPoolConstructionChecklist:
Copyright©ArizonaWholesalePoolContractors,2010|
Internalbarrierssuchaswroughtiron,meshsafetyfenceisscheduledforinstallation.Accessgatesandexistingfencesarecompleteandin‐placepercityrequirements.Selfclosinggatespringsarein‐placeandworking.Gatesopenout&awayfrombackyard.Interiordoorsandwindowsarereadyforfinalinspection.Seecity/countyrequirements.
Access&Barriers:DateScheduled:_____________DateCompleted:_______________
*Note:NeedaSwimmingPoolFence&BarrierSub‐Contractor?
Goto:ArizonaWholesalePoolContractors.com/SafetyandrequestabidfromourqualifiedlistofValleyfenceandbarriercontractors.
Tile:DateScheduled:_________________DateCompleted:______________
Tileandgroutcolorselectioniscompleteandverifiedwithsub‐contractor.Mosaics,step/benchbanding,tileinserts(whiteplasterfinishes)cutandplacedon‐site.
SwimmingPoolConstructionChecklist:
Copyright©ArizonaWholesalePoolContractors,2010|
ConstructionCleanup:DateScheduled:___________DateCompleted:__________
Alltrenchesarebackfilledandexcessfillisremovedfromthesite.Poolinteriorisscrapped,extendedplumbinglines(returns,drains)cutandleveled.AllexcesswateranddebrisremovedfromthepoolinteriorYardisroughgradedandallconstructionwasteandexcessconcreteisremovedfromthesite.
Yourcity:___________________________InspectionRequestLine:__________________ Onlinewebaddress:__________________________________________ YourPermitNumber:________________________ Pre‐shotcrete/rough‐electricalinspectioncode(seecitychart):________|___________ ConfirmationNumber:________________________
CallforYourPre‐plasterinspection
*Note:Someonemustbehometoallowthecity/countyinspectorintothehouse.
SwimmingPoolConstructionChecklist:
Copyright©ArizonaWholesalePoolContractors,2010|
Poolinterioriscleanandreadyforfinish–nostandingwaterorconstructiondebris.Tileinsertsareon‐siteandavailableforfinishcrew.Slurrypitlocationprovidedandarrangedforbyinteriorfinishcompany.Wateravailableon‐site.Ifyourhomeisonawellsystemforwater,requesta Watertruckproviderservice.
*Note:Pebblefinishrequiresaseconddaytocomplete–acidwash.Plasterfinishisinstalledandwaterfillingthepoolthesameday.
InteriorFinish:DateScheduled:______________DateCompleted:______________
Copyright©ArizonaWholesalePoolContractors,2010|
SwimmingPoolConstructionChecklist:
Pullskimmerplugfrombottomofskimmer–requireslonghandlet‐barwith2”squaresocket.Allchemicalsandstartupmaterialson‐site.Saltwaterpoolsrequirelargeamountofsalt(200–400lbs.)usequickdissolvesalt.Poolequipmentorientationavailablefrompoolstartupcompany. Startupdate:______________________________ Startupwaterchemistry Watercalciumnumber:_________________________ Totalhardnessnumber:_________________________ RecommendedPHlevel:_________________________
PoolStartup:DateScheduled:_____________DateCompleted:_______________
Record:Allpoolequipmentmanufacturemodelandserialnumbers.
____________________________________________________________________________________________________________________________________________________________________________________