Upload
jewel-wilson
View
217
Download
0
Tags:
Embed Size (px)
Citation preview
The Status of the SNS3rd SPL Collaboration Meeting
CERNNov. 11-13, 2009
Sang-ho KimSCL Area Manager
SNS/ORNL
2 Managed by UT-Battellefor the U.S. Department of Energy
Outlines
• SNS operational status• Technical Issues and status
– RFQ– Foil– HVCM– Beam loss & Activation– SCL
• Power Upgrade; Impact on SCL• Summary
3 Managed by UT-Battellefor the U.S. Department of Energy
SNS Accelerator Complex
945 ns
1 ms macropulse
Cur
rent
mini-pulse
Cur
rent
1ms
Front-End:Produce a 1-msec
long, chopped, H- beam
1 GeV LINAC
Accumulator Ring: Compress 1 msec
long pulse to 700 nsec
Chopper system makes gaps
Ion Source2.5 MeV 1000 MeV87 MeV
CCLCCL SRF, =0.61SRF, =0.61 SRF, =0.81SRF, =0.81
186 MeV 387 MeV
DTLDTLRFQRFQ
Accumulator Ring
RTBT
Target
Injection Extraction
RF
Collimators
Liquid Hg Target
PUP
1300 MeV
4 Managed by UT-Battellefor the U.S. Department of Energy
Parameters DesignIndividually
achieved
Highest production
beam
Beam Energy (GeV) 1.0 1.01 0.93
Peak Beam current (mA) 38 40 36
Average Beam Current (mA) 26 26 24
Beam Pulse Length (s) 1000 1000 825
Repetition Rate (Hz) 60 60 60
Beam Power on Target (kW) 1440 1030 1030
Linac Beam Duty Factor (%) 6.0 5.0 5.0
Beam intensity on Target (protons per pulse) 1.5 x 1014 1.55x 1014 1.1 x 1014
SCL Cavities in Service 81 80 80
Major Parameters achieved vs. designed
5 Managed by UT-Battellefor the U.S. Department of Energy
SNS Beam Power Performance History1 MW beam power on target achieved in routine operation
Ion Source,LEBT
Stripperfoil
TargetCMS leak
HVCM
6 Managed by UT-Battellefor the U.S. Department of Energy
Smooth Running…
7 Managed by UT-Battellefor the U.S. Department of Energy
Sometimes not…
8 Managed by UT-Battellefor the U.S. Department of Energy
Power delivery goals for FY09
0100200300400500600700800900
1000110012001300140015001600170018001900200021002200230024002500
1 3 5 7 9 11 13 15 17 19 21 23 25 27 29 31 33 35 37 39 41 43 45 47 49 51 53
Weeks Since October 1, 2008
Inte
gra
ted
Be
am
Po
we
r (M
W-h
rs)
ActualInternal Goal
Commitment
Internal Goal 2471.3Commitment 1977.0Actual 2161.4
Difference 184.4(actual-commitment)
9 Managed by UT-Battellefor the U.S. Department of Energy
FY09 Neutron Production hours goalsFY09 NP Hours Goals
0
200
400
600
800
1000
1200
1400
1600
1800
2000
2200
2400
2600
2800
3000
3200
3400
3600
3800
4000
4200
1 3 5 7 9 11 13 15 17 19 21 23 25 27 29 31 33 35 37 39 41 43 45 47 49 51 53Weeks
Hrs
. NP Scheduled Hours
NP Commitment Hours
NP Delivered Hours
Internal Goal 4125.6Commitment 3506.8Delivered 3541.2
Difference 34.4(delivered-commitment)
10 Managed by UT-Battellefor the U.S. Department of Energy
High Intensity Beam Studies – 7/11/20091 Hz beam
• The linac delivered the full pulse length• For the first time we verified the Ring can stably store
and extract the design intensity of 1.5 x1014 ppp
Cur
rent
(m
A)
Time relative to Ring Extraction (turns)
Linac Beam waveform: • ~ 1 msec long• produces the design intensity
Beam Pulse Extracted from the Ring:• Full baseline design intensity stored and extracted• No gross instability observed
11 Managed by UT-Battellefor the U.S. Department of Energy
Technical Issues and Status
12 Managed by UT-Battellefor the U.S. Department of Energy
Resonance error
Loosing closed-loop
RFQ instability• It was difficult to get stable operation at 60 Hz, >700us
– >30 min. down time in a day– Resonance error goes down loosing closed loop
Resonance error
Vane water temperature
10 min.
20 kHz
• One of limitations for 1 MW; − Since March 09; an extensive investigation− Why? What causes this instability? Limiting condition?− How can we improve the stability of operation?
13 Managed by UT-Battellefor the U.S. Department of Energy
All stable except net RF power resonance error fluctuation
• Resonance error; pure passive parameter• Net RF power=forward power – reflected power
+/-2 kHz
+/-10 kWNet RF power
Resonance error
Water temperature
14 Managed by UT-Battellefor the U.S. Department of Energy
RFQ Instability; findings• Direct correlation between Net RF power and res. Error
– When Net power > +40 kW RFQ becomes unstable• Changes in resonance error
– Vanes are getting hotter/colder at a constant field, water temperature• Load changes are clearly observed when
– Hydrogen flow rate is changed; slow response
– (Source off) vs. (source on/beam off); fast response
– (Source on/beam off) vs. (source on/beam on); fast response• Theory
– RFQ (especially vane) absorbs hydrogen from ion source
– Hydrogen are desorbed by ion beam bombardments
– Local vacuum goes up (gauge reading at the wall may not see any changes)
– Local discharge (very mild) starts; discharge conditions changes
– Vane temperature changes resonance error changes
– When discharge reaches a runaway condition instability
15 Managed by UT-Battellefor the U.S. Department of Energy
RFQ operation improvements
• Minimize H2 flow rate in Ion Source (minimize H2 absorption)• Better source alignment (minimum, uniform desorption)• Operate chiller in a good regulation region• Run the gradient at a lower end
– No affection in transmission, beam loss, beam quality
• Run at positive resonance error (around 12 kHz ± 5kHz)– Colder vane
• New auto tuning mechanism (LLRF)– Fine tuning; pulse width adjustment (+/- 30 us)– Coarse tuning; chiller temperature at 0.1 C step
No trip due to instability at 60 Hz, 900 us (limited by HVCM pulse width) during this operation period started on 8/29/09
16 Managed by UT-Battellefor the U.S. Department of Energy
Foil issues• May 09 ~ June 09; foil failures at >700 kW run• June 09~July 09; ~ 400 kW• Causes?
– Best foil failure theory to date is that one of the primary causes is vacuum breakdown (arcing) caused by charge build up on the stripper foils, caused by SEM and maybe thermionic electron emission
– Another primary cause is reflected convoy electrons and possibly also electrons from trailing edge multipacting
– Some of our foil failures also involved convoy electrons hitting the foil bracket
Cathode spot?
17 Managed by UT-Battellefor the U.S. Department of Energy
Foil failures
(Failed May 3)
(Failed May 3)
(Failed June 12)
tear
(Failed June 15)
(Used for high intensity run July 11-13)
18 Managed by UT-Battellefor the U.S. Department of Energy
Foil Fluttering & Glowing Edge/Spot
19 Managed by UT-Battellefor the U.S. Department of Energy
Foil Status
• Our best guess to date is that we have multiple foil failure mechanisms, and the biggest ones are vacuum breakdown, reflected convoy electrons, and trailing edge multipacting
• The Sep – Dec run has new Ti brackets, new foil mounting method, and diamond foils with a longer free length
• Also an HBC foil, and a diamond foil mounted at an angle• The new instrumentation (foil camera, temperature
measurement, clearing electrode, faster vacuum update rates) should help us to understand what is going on
• No foil failure since September and till now in November– But still need more understandings
20 Managed by UT-Battellefor the U.S. Department of Energy
HVCM Improvement
• New capacitors• New IGBTs, physical configuration changes, etc• Running at about 82 % of design duty• This run (since September 1, 09~)
– Much less down time due to smoke alarm related– Still major down time in SNS
21 Managed by UT-Battellefor the U.S. Department of Energy
Activation Buildup Trends3 Month Run Cycle Interval
• Finishing the run at lower power helps reduce the residual activation• SCL is also lower because of reduced loss/C• SNS is not limited by beam loss
22 Managed by UT-Battellefor the U.S. Department of Energy
SNS SCL, Operations and Performance• The first high-energy SC linac for protons, and the first pulsed operational
machine at a relatively high duty • We have learned a lot in the last 5 years about operation of pulsed SC linacs:
– Operating temperature, Heating by electron loadings (cavity, FPC, beam pipes), Multipacting & Turn-on difficulties, HOM coupler issues, RF Control, Tuner issues, Beam loss, interlocks, alarms, monitoring, …
• Current operating parameters are providing very stable and reliable SCL operation – Less than one trip of the SCL per day mainly by errant beam or control noise
• Proactive maintenance strategy (fix annoyances/problems before they limit performance)
• Beam energy (930 MeV) is lower than design (1000 MeV) due to high-beta cavity gradient limitations (mainly limited by field emission)
• No cavity performance degradation has occurred to Oct. 09– Field emission very stable – Recently Nov. 09; One cavity has been showing performance degradation
• Several cryomodules were successfully repaired without disassembly– Multiple beam-line repairs were successfully performed
23 Managed by UT-Battellefor the U.S. Department of Energy
Electron loading usually results in end group heating/beam pipe heating + quenching/gas burst
Electron Loading and Heating (Due to Field Emission and Multipacting)
• Field Emission due to high surface electric field
Multipacting; secondary emission– At resonant condition (geometry, RF field)– At sweeping region; many combinations
are possible for MP Temporally; filling, decay time Spatially; tapered region Non-resonant electrons accelerated
radiation/heating
– Mild contamination easily Processible– But bad surface processing is very
difficult in a cryomodule (operational)Initial VTA or CM HP tests could have a significant conditioning effects for both. But most dangerous moment !
24 Managed by UT-Battellefor the U.S. Department of Energy
SNS Cavity Operating RegimeAfter initial commissioning and conditioningsurface conditions are quite stable
re-distribution of gases (slow & fast)processible
Gradient settings in SNS SCL; Not uniform gradients as designedBut as high as individually achievableR
adia
tion
(in lo
g, a
rb. U
nit)
Eacc
FE onsetRadiation onset
MP Surface condition
25 Managed by UT-Battellefor the U.S. Department of Energy
Linac 08, Victoria Canada
Gradient Limitations from “Collective Effects”
a b c d
Beam pipe Temperature
individual limits; 19.5, 15, 17, 14.5 MV/m collective limits; 14.5, 15, 15, 10.5 MV/m
Flange T
Coupler or Outer T
• Electrons from Field Emission and Multipacting– Steady state electron activity and sudden bursts
affects other cavities
• Leads to gas activity and heating with subsequent end-group quench and/or reaches intermediate temperature region (5-20k); H2 evaporation and redistribution of gas which changes cavity and coupler conditions
• Example for CM13:
• Electron impact location depends on relative phase and amplitude of adjacent cavities
26 Managed by UT-Battellefor the U.S. Department of Energy
Performance degradation• First time in 4-years operation + commissioning• Limiting gradient of 5a; 14.5 MV/m due to FE Partial quench at 9 MV/m• Beam between MPS trigger and beam truncation off-energy beam much
bigger beam loss at further down-stream gas burst redistribution of gas/particulate changes in performance/condition
• Random, statistical events; made HOM coupler around FPC worse• As beam power goes higher, things could be worse re-verification of MPS is
ongoing
Partial quench
Cavity fieldForward power
27 Managed by UT-Battellefor the U.S. Department of Energy
• Repaired ~10 cryomodules to regain operation of 80 out of 81 cavities– CM19 removed: had one inoperable cavity (excessive power
through HOM); removed both HOM feedthroughs – CM12 removed: removed 4 HOM feedthroughs on 2 cavities– Tuner repairs performed on ~7 CMs– We have warmed up, individually, ~10 CMs in the past 4 years– Individual cryomodules may be warmed up and accessed due to
cryogenic feed via transfer line.
• Installed an additional modulator and re-worked klystron topology in order to provide higher klystron voltage (for beam loading and faster cavity filling)
• Further increases in beam energy require increasing the installed cavity gradients to design values
Increasing the Beam Energy
28 Managed by UT-Battellefor the U.S. Department of Energy
SCL energy
• Limiting factors; mainly field emission
• 80 out of 81 cavities; 930 MeV +10 MeV
0
2
4
6
8
10
12
14
16
18
1a 1c
2b
3a 3c
4b
5a 5c
6b
7a 7c
8b
9a 9c
10
b
11
a
11
c
12
b
12
d
13
b
13
d
14
b
14
d
15
b
15
d
16
b
16
d
17
b
17
d
18
b
18
d
19
b
19
d
20
b
20
d
21
b
21
d
22
b
22
d
23
b
23
d
Cavity number
Ea
cc
(M
V/m
)
Aug_09 Nov_08
28
HOMB
Additional HVCM; enough RF power for design currentH01 repaired and put in the slot of CM19
0 10 20 30 40 50 60
Electron loading (EG heating, gas
burst, quench)
Coupler Heating
HOM
Quench (cell)
Lorentz forcedetuning
No limits up to 22MV/m
No. of cavities
One does not reach steady state mechanicalvibration
1 cavity is disabledCM19 removed and repaired
CM12 removed and found vacuum leaks at 3 HOM feedthroughs (fixed)
29 Managed by UT-Battellefor the U.S. Department of Energy
• A program is underway to develop and apply plasma cleaning methods to installed accelerator RF components
Plasma Processing Development
29
0.01
0.10
1.00
10.00
100.00
0 2 4 6 8 10 12
Eacc (MV/m)
Do
se
Ra
te (
BL
M7
)
baseline before processing
after processing
– If successful this should significantly reduce field emission, mulitpacting and increase operating stability of RF structures
• First test on SNS cavity allows 2 MV/m increase for same radiation levels
• Experimental Program Includes
– Witness samples from standard processes
– TM020 test cavity – And full RF structures (3-cell
test cavity) for procedure development
30 Managed by UT-Battellefor the U.S. Department of Energy
AP_Talk Feb. 19, 2009
Ionization ChamberInternal Ionization ChamberPhosphor Screen, Camera, Faraday Cup
IC0
IC1
IC2IC3 IC4 IC5 IC6
IC7
IC-int
Phosphor Screen& Faraday Cup
Phosphor Screen& Faraday Cup
Cavity ACavity BCavity CCavity D
Cavity D 12 MV/mCamera exposure; 30 ms
Cavity A 9.3MV/mCamera exposure; 30 ms
Radiation/electron activity diagnostics in the Test Cave
31 Managed by UT-Battellefor the U.S. Department of Energy
Test Cavity
Witness Sample for Chemistry
Demountable witness plate
SRF cavityFPC Flange
Surface analysis
Microwave Plasma processor
150.00
3.3 GHz, TM020 modeEp/Bp=1.12 (MV/m)/mTEx. Ep=50 MV/m, Bp=56 mTPdiss=36 W at 4.2 K
150 mm
-Cold testw/ dual mode (CW or pulse) -Plasma processing
FPC Flange
3–cell cavity For R&D
32 Managed by UT-Battellefor the U.S. Department of Energy
AFF & Beam ramp-up• When beam current is bigger than ~18 mA average
– field regulations go beyond the threshold RF truncation AFF can not learn
– BLM trips AFF can not learn• Klystron power is usually those at saturation
– Non-linear• We use PW (chopping pattern; ratio between midi-pulse and gap)
– Starting around <18 mA Ib,avg after AFF learned increase Ib,avg
At beginning
Cavity Field
forward
reflected
Forward/reflected are in voltage unit
At start
21b
0
100
200
300
400
500
600
0.0E+00 2.0E+08 4.0E+08 6.0E+08 8.0E+08 1.0E+09 1.2E+09
FCM output^2
Kly
stro
n f
orw
ard
po
wer
HP
M r
ead
ing
(kW
)
KlyF 71kV
KlyF 73kV
KlyF 75kV
Overall gain measurement(from FCM digital output to Klystron forward power)
33 Managed by UT-Battellefor the U.S. Department of Energy
• As an urgent matter, we are constructing two spare high-beta cryomodules– These will be 10CRF851-compliant; vacuum vessel envelope was redesigned
for pressure vessel compatibility
– Cavities are currently being qualified at Jefferson Lab (1st string qualified)
– Plan is to construct/integrate these spare CMs in-house
• The SNS Power Upgrade Project (PUP) has CD-1 approval, and includes the following scope:– 9 additional high-beta CMs to increase energy to 1.3 GeV
– Associated RF systems
– Ring modifications to support higher energy
• We expect to involve industry in PUP CM construction (expect CD-2 approval in the next FY)
• We are continuing to build SRF support facilities to provide basic repair and testing capabilities in support of long-term maintenance and the Upgrade
Ongoing and Future Activities
34 Managed by UT-Battellefor the U.S. Department of Energy
34
Bayonets remain in original positions
“Code” Bolted FlangesJ-T’s repositioned
Power Upgrade Cryomodule Design
35 Managed by UT-Battellefor the U.S. Department of Energy
• In place– Cryomodule test-
cave tied-in to CHL
– High-power RF test-stand
– Cleanroom facility
– Ultrapure Water• High pressure rinse
system in fabrication• Vertical Test Area
design complete; construction starting
• Dedicated Cryogenic Support refrigerator in design
SRF Maintenance and Test Facility
Class 100Class 10,000
CryomoduleAssembly
RF/Couplerprocessing
Test Cave
ChemistryVTA
Class 10
CryomoduleAssembly
Mezzanine(lab space)
HPR
36 Managed by UT-Battellefor the U.S. Department of Energy
Power Upgrade Project (PUP)+ Accelerator Improvement Project (AIP)
Parameter SNS Baseline Power upgrade
Kinetic energy [MeV] 1000 1300
Beam power [MW] 1.4 3.0
Chopper beam-on duty factor [%] 68 70
Linac beam macropulse duty factor [%] 6.0 6.0
Average macropulse H- current, [mA] 26 42
Peak macropulse H- current, [mA] 38 59
Linac average beam current [mA] 1.6 2.5
SRF cryo-module number (medium-beta) 11 11
SRF cryo-module number (high-beta) 12 12+8 (+1 reserve)
SRF cavity number 33+48 33+80 (+4 reserve)
Peak surface gradient (b=0.61 cavity) [MV/m] 27.5 (+/- 2.5) 27.5 (+/- 2.5)
Peak surface gradient (b=0.81 cavity) [MV/m] 35 (+2.5/-7.5) 31
Ring injection time [ms] / turns 1.0 / 1060 1.0 / 1100
Ring rf frequency [MHz] 1.058 1.098
Ring bunch intensity [1014] 1.6 2.5
Ring space-charge tune spread, DQsc0.15 0.15
Pulse length on target [ns] 695 691
37 Managed by UT-Battellefor the U.S. Department of Energy
Concerns• Balancing (rf power, gradient, coupler average power)
– 42 mA average current (59 mA peak)
– Existing RF system; 550 kW (at saturation) per cavity
– Existing HVCM; 75 kV, 10 pack configuration
– Existing FPC; ~50 kW average power• No active cooling for inner conductor at vacuum side• Thermal radiation load to end group ~3W
• Optimization works are in progress– Based on what we learned from operational experiences
– Minimize reworks of existing cryomodules
– Multiple approaches for margin (remove the weakest links)
• Changes– Vacuum vessel, FPC (Qex, Higher average power), HOMless, Coupler
cooling configuration, etc.
38 Managed by UT-Battellefor the U.S. Department of Energy
PUP impact on SCL
• Baseline number; 10.1 MV/m (MB), 14.1 MV/m (HB)• Need reworks for the most of existing HB cryomodules;
power coupler (average power) + HP RF + Modulator
0
2
4
6
8
10
12
14
16
0
100
200
300
400
500
600
700
800
0 20 40 60 80 100 120
Eacc
(MV/
m)
RF P
ower
in st
eady
stat
e (k
W)
Cavity Number
Eacc
RF power at the coupler in steady state
Klystron powerAt saturation
Control marginError budget
PUP cavities
39 Managed by UT-Battellefor the U.S. Department of Energy
Option I (based on existing cavity performances)• No reworks for the existing cryomodules + HPRF system +HVCM• New PUP cryomodules
– Cavity radiation threshold >15 MV/m, Coupler>70kW average power (end group heating issues due to thermal radiation)
– 750 kW klystrons + 82 kV HVCM
0
2
4
6
8
10
12
14
16
18
0
100
200
300
400
500
600
700
800
0 20 40 60 80 100 120
Eacc
(MV/
m)
RF P
ower
in st
eady
stat
e (k
W)
Cavity Number
Eacc
RF power at the coupler in steady state
Klystron powerAt saturation
Control marginError budget
PUP cavities
40 Managed by UT-Battellefor the U.S. Department of Energy
Option II • Some reworks for existing system (no rework for the couplers)
– A few kV higher for HVCM For last several CMs
– Some performance improvement; plasma processing
• About same loading on PUP cavities (14.3 MV/m, 700kW RF at saturation)
0
2
4
6
8
10
12
14
16
18
0
100
200
300
400
500
600
700
800
0 20 40 60 80 100 120
Ea
cc
(MV
/m)
RF
Po
we
r in
ste
ad
y s
tate
(k
W)
Cavity Number
Eacc
RF power at the coupler in steady state
Klystron powerAt saturation
Control marginError budget
PUP cavities
41 Managed by UT-Battellefor the U.S. Department of Energy
Summary• 3-yrs operation
– Reached 1 MW operation– Availability is improving– Beam loss seems not a show stopper in SNS
• Technical issues and status– RFQ; Better understanding, very stable operation– HVCM; better in this op. period.
Operational stability needs to be improved– Foil; New batch of foils/brackets, so far no failure
Need more understanding of failure mechanism
– SCL; Tight control, very stable operationPlasma processing R&D to get 1 GeV
• PUP; technical design in this FY.