2
Lowering CAPEX over 40% Lowering OPEX over 20% Increasing energy yield Reducing LCOE with PEG Light substructure saves over 65% of the material supply and delivery costs Simple and fast installation process saves over 50% labor and machine costs Area utilization of 1.4MWp per hectare with a patented, ground-guided power plant system design Preserving resources: Over 50% lower raw material usage (steel, cabling) Ready-to-install package with pre-assembled components delivered in 40ft container units Higher installation safety and ergonomics through much simpler assembly at 0.8 meter height and no overhead working Application of latest PV module, inverter and 1500V cabling technologies; upgradeable with battery storage unit BELECTRIC EBU IMPROVED DAYTIME ENERGY YIELD The East-West system orientation allows better generation results over the day with less generation at noon time and more during early morning and later afternoon. WIDE FIELD OF PEG APPLICATION Utility-scale multi-megawatt solar PV projects with main demand to reach lowest LCOE at best area utilization Commercial, ground-mounted PV power plants starting from 10kWp Suitable for remote locations, where labor and freight costs are high Adaptable to limited site dimensions, insufficient space or narrow available land, due to the system’s unique area utilization ENERGY HARVESTING AT LOWEST LEVELIZED COST OF ENERGY (LCOE) The PEG solar power plant Clean and affordable energy with BELECTRIC’s revolutionary solar PV power plant www.belectric.com For many years solar PV has been defined by its typical Engineering- Procurement-Construction (EPC) process. Today BELECTRIC is challenging this old-fashioned principle with Engineering-Procurement-Installation (EPI) - a new PV power realization process focused on quick and resource- saving installation. The PEG unit is based on EPI and sets new standards in solar power generation. The system was formed with a simple goal in mind: create a power unit to deliver electricity at lowest possible levelized costs of energy (LCOE), with best in class technologies, long-term reliability and large volume scalability. The PEG unit significantly reduces both substructure supply and delivery, as well as installation costs. PEG BENEFITS VS. OTHER SOLAR PV SYSTEMS EPI = Engineering, Procurement and Installation: Quick Line-by-Line installation instead of complicated and costly construction process with heavy equipment PV module installation and wiring Plates installer PEG nailing robot » The revolution in utility-scale PV power: Best-in-class area utilization of 1.4MWp per hectare TECHNICAL CONTACT PARTNER: Nir Dekel, [email protected], +49 9385 9804-5117 PEG reference sites in Haidt, Germany (top photo), and in Goondiwindi, Australia (bottom)

The PEG solar power plant - Ground-mounted Solar Power ... · PDF filein solar power generation. The system was formed with a simple goal in mind: create a power unit to deliver electricity

  • Upload
    dotram

  • View
    213

  • Download
    1

Embed Size (px)

Citation preview

Lowering CAPEX

over 40%

Lowering OPEX

over 20%

Increasing energy yield

Reducing LCOE with PEG

• Light substructure saves over 65% of the material supply and delivery costs

• Simple and fast installation process saves over 50% labor and machine costs

• Area utilization of 1.4MWp per hectare with a patented, ground-guided

power plant system design

• Preserving resources: Over 50% lower raw material usage (steel, cabling)

• Ready-to-install package with pre-assembled components delivered in

40ft container units

• Higher installation safety and ergonomics through much simpler assembly

at 0.8 meter height and no overhead working

• Application of latest PV module, inverter and 1500V cabling technologies;

upgradeable with battery storage unit BELECTRIC EBU

IMPROVED DAYTIME ENERGY YIELDThe East-West system orientation allows better generation results over the

day with less generation at noon time and more during early morning and

later afternoon.

WIDE FIELD OF PEG APPLICATION • Utility-scale multi-megawatt solar PV projects with main demand to

reach lowest LCOE at best area utilization

• Commercial, ground-mounted PV power plants starting from 10kWp

• Suitable for remote locations, where labor and freight costs are high

• Adaptable to limited site dimensions, insufficient space or narrow available

land, due to the system’s unique area utilization

ENERGY HARVESTING AT LOWEST LEVELIZED COST OF ENERGY (LCOE)

The PEG solar power plant Clean and affordable energy with BELECTRIC’s revolutionary solar PV power plant

www.belectric.com

For many years solar PV has been defined by its typical Engineering-

Procurement-Construction (EPC) process. Today BELECTRIC is challenging

this old-fashioned principle with Engineering-Procurement-Installation

(EPI) - a new PV power realization process focused on quick and resource-

saving installation. The PEG unit is based on EPI and sets new standards

in solar power generation. The system was formed with a simple goal in

mind: create a power unit to deliver electricity at lowest possible levelized

costs of energy (LCOE), with best in class technologies, long-term reliability

and large volume scalability. The PEG unit significantly reduces both

substructure supply and delivery, as well as installation costs.

PEG BENEFITS VS. OTHER SOLAR PV SYSTEMS

EPI = Engineering, Procurement and Installation: Quick Line-by-Line installation instead of complicated and costly construction process with heavy equipment

PV module installation and wiring

Plates installer

PEG nailing robot

» The revolution in utility-scale PV power: Best-in-class area utilization of 1.4MWp per hectare

TECHNICAL CONTACT PARTNER:Nir Dekel, [email protected], +49 9385 9804-5117

PEG reference sites in Haidt, Germany (top photo), and in Goondiwindi, Australia (bottom)

Rev. BEL-PEG

_Factsheet_2017-09

-13_EN

TECHNICAL DETAILS AND REQUIREMENTS

REVOLUTIONARY NEW SYSTEM DESIGN:• No foundations required for PEG substructure

• No heavy machines required

• Line-by-line installation with PEG nailing machine achieving a record-

breaking milestone for solar PV of less than 1,000 man-hours per MWp

• Residue-free dismantling after project life

• Overground installed DC wiring

TECHNICAL DATA:BELECTRIC PEG is a highly customizable solar power plant system. Due to its overground-mounted structure it can be adapted to

many landscape surfaces. Indicative figures for an exemplary 1 MWp PEG® unit below:

module module modulemodulemodule

E W

Total power DC: 1000kWp, individual scalability from 10kWp to multi-megawatt systems

Orientation PV array 8° East-West, fixed tilt, aerodynamic designed and proofed (patent-registered design)

BOM (Bill of material)** Dependent on PV module type: 72-cells-module: ~3,850 rods* (incl. base-/head plates); ~7,400 clips60-cells-module: ~4,500 rods* (incl. base-/head plates); ~8,600 clips

eBOP 1,500VDC system components incl. SKID-based inverter-transformer station; built-in PID Protection and Active Lightning Shield

Large volume scalability Any power plant capacity starting at 10kWp can be realized.

Durability Hot-dip galvanized steel; module clips based on corrosion-free stainless steel or aluminum. All components are weatherproof and UV resistant.

System load rating PEG system is designed for typical wind- and snow loads based on 2,400Pa module load rating. Additionally, local site compliance with wind and snow codes has to be defined by engineering company

Valid air temperature Up to 50°C (up to 55°C with Hot Climate Option)

Packing units** PEG system (excl. PV modules and SKID): 1x 40ft container per MWp

System weight PEG system (excl. PV modules and SKID): approx. 19 tons per MWp

Certifications** Clamping approval from module manufacturers. Wind-/snow load certificate by local engineering firm in accordance with local codes.

Warranties Warranty time has to be defined per project based on the site and soil conditions. Functional warranty, excluding cosmetic issues. Standard warranty and geotechnical tests guidance documents available upon request.

Operation and maintenance Optional: BELECTRIC RealTime Management System with SCADA; Operating service life 25+ years

As we follow a principle of continuous improvement, we reserve the right to modify technical specifications. * With the exception of the inverter SKID station placement** The exact figures TBD per project based on the mechanical design, e.g. the size of each mechanical structure.*** Module manufacturer approval required for clamping the module at its edges, or it’s clearly stated in the installation manual. Other modules can be evaluated if required.

REQUIREMENTS FOR PEG:

Land soil condition Cohesive (e.g. sandy-clay, clayey silt) and non-cohesive soil (e.g. sand or sand-gravel)

Upper soil layer No rocks or underground infrastructure up to 1m below ground; rammed depth approx 0.8m

Required land area 0.7 hectare (7,000 sqm) per MWp

Topography Slope North-South and East-West max. ±2° ≈ 3%

Approved PV modules*** BYD: 60-cell and 72-cellCanadian Solar: CS6K-xxxP, CS6KxxxM, CS6A-xxxP, CS6A-xxxM, CS6V-xxxP, CS6V-xxxM, CS6P-xxxP, CS6P-xxxM.Hanwha: SF, HSL 60 and HSL 60 series.JA Solar: JAP6 60/245 and JAM6 72/320.Jinko Solar: JKMXXXPP-60 and JKMXXXPP-72 series.REC: Peak Energy seriesSolar Frontier: SFxx-EX-B MP2, SFxxx-L and SFxxx-S MP3 series. Suntech: W, V and Vdx seriesTrina: TSM-PC05, TSM-PC05.05, TSM-PC05.08 and TSM-PC14Yingli: YLXXX P-29b and YLXXX C-30bOthers brands TBD in case edge mounting is allowed.

Head plate

Steel rod

BELECTRIC Solar & Battery GmbH, Wadenbrunner Straße 10, 97509 Kolitzheim, Germany

www.belectric.com