Upload
others
View
5
Download
0
Embed Size (px)
Citation preview
The ODPM
Framework
Overview
Version 2.1
Prepared by: Iain Aitken
26th June 2013
2 © Bestoutcome Limited 2012 2
What is a successful project?
Our definition
CRM installed to
budget and schedule!!
Not only..
Sales up thanks
to the CRM system!!
But also..
• A successful project is one that has demonstrably achieved the
desired business outcomes and delivered the promised business
benefits
3 © Bestoutcome Limited 2012
What is successful project management? Our definition
Time Cost
Quality
Scope
Not only delivering to…
Promised
Business
Benefits
But also delivering…
4 © Bestoutcome Limited 2012 4
What is ODPM? • ODPM (Outcome-Driven Project Management) is a ‘lean’ approach
to project management focused on achieving desired business
outcomes and delivering the promised business benefits
• It distils necessary and sufficient practices from established project
management methods (e.g. PRINCE2®, DSDM)
• Key aspects of ODPM are automated in
Project
Outputs
Business
Outcomes Business
Benefits
© Bestoutcome Limited 2012 © Bestoutcome Limited 2008 © Bestoutcome Limited 2008 © Bestoutcome Limited 2008
Where does the ODPM Framework fit in?
5 5 5 5
Thick
Methods
Thin
Methods
Totalitarianism? Anarchism?
• Scope-driven
• Highly theoretical
• Long/complex project focus
• Highly bureaucratic
• Time/cost-driven
• Minimal theory
• Short/simple project focus
• Minimal bureaucracy
e.g.PRINCE2 e.g. DSDM
Lean
Methods
• Value-driven
• Just enough theory
• Typical project focus
• Just enough bureaucracy
Necessary & sufficient control
ODPM
6 © Bestoutcome Limited 2012 6
The 4 Keys to Success
7 © Bestoutcome Limited 2012
• Build the project on the foundations of clearly defined/agreed
‘SMART’ objectives, scope and Business Case
• Don’t make ‘wishful thinking’ planning/estimating assumptions
• Estimate cost, time and likely benefits honestly and realistically
• Assess project benefits delivery risks, not just project delivery risks
• Strangle unacceptably risky projects at birth!
• Perform project approval and prioritisation based on affordability,
resource/budget capacity, Payback Period and ‘objective’ cost-
benefit-risk comparisons (rather than emotion/conviction)
The Right Project
8 © Bestoutcome Limited 2012
• Focus on identifying the key milestones that will deliver the
business benefits of the project (Outcome-Driven Planning)
• Plan backwards from the final benefits delivery milestone
• Get (and sustain) sponsor/stakeholder buy-in to the key
milestones
• Plan programmes of projects based on key promoted milestones,
risks and issues
The Right Planning
9 © Bestoutcome Limited 2012
• Manage risk/issue avoidance/mitigation actions • Manage project stakeholders • Accommodate value-adding change • Ensure Project Board is fully engaged and is proactive in its key
project governance responsibilities • Identify at risk projects as soon as possible and take appropriate
action
• Periodically (at Quality/Control Gates) re-assess the viability and
deliverability of the project (and rescope or terminate if
necessary)
The Right Governance
10 © Bestoutcome Limited 2012 © Bestoutcome Limited 2008
• Plan, manage and measure/report the realisation of business benefits
• Ensure real accountability for project benefits realization • Use business change management techniques to gain full buy-in to
behavioural changes necessary to maximise benefits • Maintain scorecards of project success (e.g. budget, schedule,
benefits success criteria)
The Right Outcomes
What are the Framework components?
Process Model SU1: Define
Project
Brief
PL1: Develop
Project Plan
11
PBD
Document Templates
Process Definitions
PM3 Screens
3
ODPM Process Model
12 © Bestoutcome Limited 2012 12
Strategy
SU1: Define
Project
Brief
IP1: Define
Project
Scope
IP2: Define
Project
Business Case
IP3: Prioritize
& Schedule
Project
PL1: Develop
Project Plan
PL2: Develop
Work
Schedules
PL4: Launch
Project
PL3: Develop
Risk/Issue
Logs
Project Closure
& Benefits
Realization
Project Start
Up & Initiation
Project
Planning
Project
Delivery
MP1: Manage
Product
Delivery
SB1: Manage
Stage
Boundaries
CS1: Manage Change
& Progress
DP1: Direct Project
CS2: Manage Project
Communications
Organisational
Strategy
Systems
Strategy
Technology
Strategy
Parallel
Activity
Key :
Project
Management
Process
RB1: Manage
Benefits
Realization
CP2: Perform
PCR
RB2: Perform
PIR
CP1: Close
Project
13 © Bestoutcome Limited 2012 13
Process Model with Documents
Strategy
SU1: Define
Project
Brief
IP1: Define
Project
Scope
IP2: Define
Project
Business Case
IP3: Prioritize
& Schedule
Project
PL1: Develop
Project Plan
PL2: Develop
Work
Schedules
PL4: Launch
Project
PL3: Develop
Risk/Issue
Logs
Project Closure
& Benefits
Realization
Project Start
Up & Initiation
Project
Planning
Project
Delivery
MP1: Manage
Product
Delivery
SB1: Manage
Stage
Boundaries
CS1: Manage Change
& Progress
DP1: Direct Project
CS2: Manage Project
Communications
Organisational
Strategy
Systems
Strategy
Technology
Strategy
Key :
RB1: Manage
Benefits
Realization
CP2: Perform
PCR
RB2: Perform
PIR
CP1: Close
Project
PCP CCR
STA
CCR
PBC
PBD
PSD
PBC CBA
PCR
PIR
Parallel
Activity
Project
Management
Process
Document
14 © Bestoutcome Limited 2012 14
Process Model with Control Gates
Strategy
SU1: Define
Project
Brief
IP1: Define
Project
Scope
IP2: Define
Project
Business Case
IP3: Prioritize
& Schedule
Project
PL1: Develop
Project Plan
PL2: Develop
Work
Schedules
PL4: Launch
Project
PL3: Develop
Risk/Issue
Logs
Project Closure
& Benefits
Realization
Project Start
Up & Initiation
Project
Planning
Project
Delivery
MP1: Manage
Product
Delivery
SB1: Manage
Stage
Boundaries
CS1: Manage Change
& Progress
DP1: Direct Project
CS2: Manage Project
Communications
Organisational
Strategy
Systems
Strategy
Technology
Strategy
Key :
RB1: Manage
Benefits
Realization
CP2: Perform
PCR
RB2: Perform
PIR
CP1: Close
Project
PCP CCR
STA
CCR
PBC
PBD
PSD
PBC CBA
PCR
PIR
Parallel
Activity
Project
Management
Process
Document
Control
Gate
1
3
5
6
7
2
4
15 © Bestoutcome Limited 2012
Framework Control Gates
• is acceptably on budget
• is acceptably on schedule
• is likely to deliver the promised benefits
• is acceptably controlling scope
• is acceptably controlling resources
• is acceptably controlling risks
• is acceptably controlling issues
• has satisfactory stakeholder commitment
• is complying with quality standards
A governance review point to
assess if the project
16 © Bestoutcome Limited 2012
e.g. Control Gate 1 CONTROL GATE 1 CRITERIA
COSTS Preliminary costs are defined, reasonable and potentially
affordable
VALUE
If marked non-discretionary, the project is genuinely
non-discretionary
Preliminary financial benefits are defined and
reasonable
The business value of the project is defined and
compelling
The adverse business impact of not performing the
project is defined and compelling
The proposed project is acceptably aligned with the
business, systems and technology strategies
The payback period is defined and reasonable
The payback assumptions are defined and reasonable
RESOURCES Sufficient resources are available to progress the project to
Control Gate 2
STAKEHOLDERS There is an agreed Project Sponsor
Key Stakeholders are defined
QUALITY The Project Brief Document has been completed and
signed-off
PROJECT INITIATION APPROVAL (Control Gate 1 Criteria met?)
ARE WE ABSOLUTELY CLEAR ABOUT WHAT THIS PROJECT IS INTENDED TO
ACHIEVE? Name Signature Date
Head of Projects
Delivery
Project Sponsor
If rejected/deferred, reasons
This authorises project expenditure up to Control Gate 2
17 © Bestoutcome Limited 2012
QG1: Are we all absolutely clear
about what this project is
intended to achieve?
QG2: Is there a truly compelling
business case for performing
this project?
QG3/4: Is there still a truly
compelling business case for
continuing with this project?
QG5: Is everybody ready to go
Live?
QG6: Was the project a success?
What lessons can we learn?
QG7: Have we fully realized the
promised benefits?
Framework Control Gates
18 © Bestoutcome Limited 2012
Framework and PRINCE2
DP
PL MP
SB
CS CP SU IP SU1: Define
Project
Brief
IP1: Define
Project
Scope
IP2: Define
Project
Business Case
IP3: Prioritize
& Schedule
Project
PL1: Develop
Project Plan
PL2: Develop
Work
Schedules
PL4: Launch
Project
PL3: Develop
Risk/Issue
Logs
MP1: Manage
Product
Delivery
CS1: Manage
Change &
Progress
CS2: Manage
Project
Comms
SB1: Manage
Stage
Boundaries
DP1: Direct
Project
CP2: Perform
PCR
CP1: Close
Project
CP RB1: Manage
Benefits
Realisation
RB2: Perform
PIR
19 © Bestoutcome Limited 2012
What are the key benefits of the
Framework?
• Helps increase project delivery predictability (cost/time/quality/value)
• Helps establish/sustain necessary and sufficient project/development
disciplines and controls
• Helps establish the commercially optimal projects portfolio
• Helps sustain and maximize the value of projects during development
• Helps ensure that at risk projects are identified as early as possible, so
minimising non-value-adding project spend
• Helps keep Programme/Project Managers and Senior Management
focused on the Big Picture (achieving desired business outcomes)
20 © Bestoutcome Limited 2012
www.bestoutcome.com